ELECTRICITY OF VIETNAM NORTHERN POWER CORPORATION ----------------------------- DISTRIBUTION EFFICIENCY PROJECT SUB - PROJECTS LINE 110KV HAI DUONG PHO NOI (SUB - LINE ON HUNG YEN PROVINCE) AND EXPANSION OF 110KV LINE AT 220KV PHO NOI SUBSTATION ENVIRONMENTAL MANAGEMENT PLAN Prepared by PHU MINH JOINT STOCK COMPANY Ha noi, 18 April 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

ELECTRICITY OF VIETNAM NORTHERN POWER CORPORATION · NORTHERN POWER CORPORATION ----- DISTRIBUTION EFFICIENCY PROJECT SUB - PROJECTS LINE 110KV HAI DUONG – PHO NOI (SUB - LINE ON

  • Upload
    others

  • View
    25

  • Download
    0

Embed Size (px)

Citation preview

ELECTRICITY OF VIETNAM

NORTHERN POWER CORPORATION

-----------------------------

DISTRIBUTION EFFICIENCY PROJECT

SUB - PROJECTS

LINE 110KV HAI DUONG – PHO NOI

(SUB - LINE ON HUNG YEN PROVINCE)

AND EXPANSION OF 110KV LINE AT 220KV PHO NOI SUBSTATION

ENVIRONMENTAL MANAGEMENT PLAN

Prepared by

PHU MINH JOINT STOCK COMPANY

Ha noi, 18 April 2012

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb406484
Typewritten Text
E3035 v19

1

ABBREVIATIONS

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EMF Electromagnetic field

EVN Electricity of Vietnam

HW Hazardous waste

PAHs Project Affected Households

PMU Project Management Unit

PC Power Company

ROW Right of Ways

SIMC Safeguards Independent Monitoring Consultant

NPC Northern Power Corporation

WB The World Bank

CPC Commune People's Committee

2

TABLE OF CONTENTS

I. introduction ........................................................................................................................4

II. POLICY FRAMEWORKS, REGULATIONS ...............................................................4

2.1. Vietnam Government Regulations: .........................................................................4

2.2. World Bank safety Policies: .....................................................................................5

III. PROJECT DESCRIPTION AND WORK SCALE ........................................................5

3.1. Project Description: ..................................................................................................5

3.1.1. Line 110kV Hai Duong – Pho Noi (subline in Hung Yen Province) ...................5

3.1.2. Sub expansion 110kV at 220kV Pho Noi substation ............................................6

Table 3.1. Equipment expansion feeder ...............................................................................6

3.1.3. Amount main workload of project ........................................................................6

Table 3.2. Amount construction 110kV line Hai Duong – Pho Noi ....................................6

3.2. Work transportation .................................................................................................7

3.2.1. Materials and equipment supply: ..........................................................................7

3.2.2. Long distance transportation .................................................................................8

3.2.3. Intermediate transportation ...................................................................................8

3.2.4. Manual handling ...................................................................................................8

3.3. Arranging construction worker force and constructing site.................................8

3.4. Progress and total investment of project: ...............................................................9

3.4.1. Project progress:....................................................................................................9

3.4.2. Project total investment: .......................................................................................9

Table 3.3. Total investment of project .................................................................................9

IV. SUMMARY OF NATURAL AND ENVIRONMENTAL CONDITIONS

PROJECT’S AREA .........................................................................................................10

4.1. Geographical geological conditions .......................................................................10

4.1.1. Geographical location: ........................................................................................10

4.1.2. Topography and geomorphology ........................................................................10

4.1.3. Geological ...........................................................................................................10

4.2. Meteorological conditions ......................................................................................10

4.3. Traffic.......................................................................................................................10

4.4. Describe router: ......................................................................................................12

Table 4.1. Table describes line passing thought territory of administrative ĐDK-

110kV Hai Duong – Pho Noi ............................................................................12

V. IDENTIFICATION OF POTENTIAL IMPACTS OF THE PROJECT ...................16

Table 5.1. Rapid assessment of environmental impacts of the Project ..............................16

3

VI. ENVIRONMENTAL MANAGEMENT PLAN ............................................................20

6.1. Mitigation measures................................................................................................20

Table 6.1. Mitigation measures applied for the Project .....................................................20

6.2. Measures to minimize the specific impact of this project ...................................30

Table 6.2. Measures to minimize the specific impact of this project ................................30

6.3. Environmental monitoring plan ............................................................................30

Table 6.3. Environmental monitoring plan ........................................................................30

VII......... EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING 32

7.1. Responsibilities for Implementing the Environmental Management

Plan ...................................................................................................................32

To ensure effective implementation of the EMP, the following actions will be

carried out during the implementation of the subproject ..................................32

7.1.1 During Detailed Design and Preparation of Bidding Contract

Documents ........................................................................................................32

7.1.1. Construction phase: .............................................................................................33

Role and responsibilities of parties in implementing EMP are summarized in the

below table ........................................................................................................33

Table 7.1. Responsibility for EMP Implementation ..........................................................33

7.2. Building the EMP implementation capacity.........................................................35

Table 7.2.Estimates of capacity building for implementing EMP .....................................35

7.2 Reporting procedure .........................................................................................36

7.3. Estimated cost for implementing the EMP ...........................................................36

VIII. CONSULTATION AND DISCLOSURE OF INFORMATION ........................37

Table8.1 Summery consult public .....................................................................................37

ANNEX 1 ................................................................................................................................40

ANNEX 4 ................................................................................................................................45

ENVIRONMENTAL LICENCEANNEX 5 .........................................................................46

ANNEX 6 ................................................................................................................................47

ANNEX 7 ................................................................................................................................58

4

I. INTRODUCTION

The sub-project 110kV line Hai Duong – Pho Noi and expansion 110KV feeder at

220KV Pho Noi substation (hereinafter referred to as 110KV Hai Duong – Pho Noi Sub-

project) would be invested to ensure safe and reliable power supply for Hung Yen Province,

creating infrastructure for economic development and improving system stability in the

operating modes.

It is one of the sub-projects that will be implemented in Phase I of the Distribution

efficiency project (DEP) of the Electricity of Vietnam which will be financed by the World

Bank. The sub-project will be implemented in My Hao district, Hung Yen province.

The sub-project activities include: i) New construction of 9.427 km double circuit lines

110 kV, ii) Expansion of the 110kV at 220kV Pho Noi substation. These activities can cause

negative impacts on the environment and local communities in during the preconstruction,

construction, and operation phases of the subproject.

To ensure the potential negative impacts are identified and mitigated during the sub-

project implementation and in compliance with the policy on environmental assessment of

the World Bank (OP/BP 4.01), an environmental Management Plan (EMP) of the sub-project

has been prepared in accordance with the guidelines of the Environmental Management

Framework (EMF) of the DEP project. The EMP includes the following contents: sub-project

description, the main framework of policies, rules and technical regulations applicable

environment, the potential negative impacts, the mitigation measures proposed will be

conducted in the previous period building, construction and commissioning, implementation

arrangements. The EMP also includes Environmental Codes of Practice (ECOP) to apply for

the subproject, and to be incorporated into the bidding documents and construction contracts,

as well as a scope for environment quality monitoring.

According to the government EIA regulation the subproject need to prepare and

Environmental Impact Assessment report. An EIA has been prepared and approved by Hung

Yen People Committee on ……...

II. POLICY FRAMEWORKS, REGULATIONS

2.1. Vietnam Government Regulations:

The following laws and regulations are applied for subproject:

Law on Protection of the Environment No. 52/2005/QH11 passed by the National

Assembly on November, 29th

, 2005 regulates the obligations of individuals,

organizations in protecting environment.

Law on forest protection and forest development No. 29/2001/QH11.

Law on cultural heritage No. 28/2001/QH10.

Law on Water Resource No. 08/1998/QH10 dated 20 May, 1998

Decree of Government No. 80/2006/ND-CP dated 9 August, 2006 on guidance for

implementation of Law on Protection of the Environment.

Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating strategic

environmental assessment, environmental impact assessment and environment

protection commitment.

5

Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree

No.29/2011/ND-CP dated 18 April, 2011.

Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on guidance for

Law on electricity relating to the protection of high-voltage networks.

Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending some

Article of Decree No.106/2005/ND-CP dated 17 August, 2005.

Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to hazardous waste

management.

Vietnam National Standard: QCVN01: 2009/BYT- national technical regulation on

drinking water quality; QCVN02: 2009/BYT- national technical regulation on

domestic water quality; QCVN08: 2008/BTNMT - national technical regulation on

surface water quality; QCVN09: 2008/BTNMT - national technical regulation on

ground water quality; QCVN05: 2009/BTNMT – air quality – Standard for ambient

air quality; QCVN06: 2009/BTNMT – air quality –specified maximum allowable

concentrations of certain hazardous substances in ambient air.

Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on

management and pollution prevention and exposure to PCBs.

2.2. World Bank safety Policies:

An environmental screening was undertaken in line with the guidelines provided in the

Environmental Management Framework (EMF) of the DEP project and it showed that the

World Bank’s policies on Environmental Assessment (OP 4.01) and Involuntary

Resettlement (OP 4.12) will be triggered for the subproject. In addition, the Bank’s

requirements on public consultation and information disclosure will need to be followed.

The implementation of policy on involuntary resettlement (OP 4.12) will be addressed in

a separate report

III. PROJECT DESCRIPTION AND WORK SCALE

3.1. Project Description:

3.1.1. Line 110kV Hai Duong – Pho Noi (subline in Hung Yen Province)

Sub line: “110kV line Hai Duong – Pho Noi (subline in Hung Yen province)” has below

main characteristics:

- First point: Pole No 55, 110kV line Hai Duong – Pho Noi

- End point: 110kV Pooctic 220kV Pho Noi Substation.

- Level Voltage: 110kV.

- Line No: 2 lines.

- Length: 9,427km.

- Conductor: ACSR-300/39.

- Insulator: Insulator hanging by ceramic or glass, kind U70BS van U120B.

- Pole: Galvanized steel pole double circuit assembled by bolts.

- Foundation: Concrete pole foundation cast in situ

6

3.1.2. Sub expansion 110kV at 220kV Pho Noi substation

Project investment local:

To supply power for 110 kV two circuit lines Hai Duong – Pho Noi is distribution 110kV

station at 220kV Pho Noi substation must expansion an outgoing feeder for supply power to

the line.

Project investment scale:

- To fit full equipment for a 110kV outgoing feeder is expansion at 220kV Pho Noi

substation, as follows:

Table 3.1. Equipment expansion feeder

No Device’s name and characteristics Unit Quantity Note

1 Cut machine SF6 110kV 3 phase: 123kV-1250A-

25kA/1s

Set 1

2 Power line converter 110kV 1 phase: 123kV-(200-

400-600-800)/1/1/1/1A

Set 3

3 Voltage converter 110kV 1 phase: 123kV-

12000pF - 110:√3/ 0,1:√3/ 0,1:√3kV

Set 3

4 Disconnector 3 phase 110kV 2 earthing blades:

123kV-1250A-25kA/1s

Set 1

5 Disconnector 3 phase 110kV none earthing blade:

123kV-1250A-25kA/1s

Set 2

6 Disconnector 1 phase 110kV 1 earthing blade :

123kV-1250A-25kA/1s

Set 3

- To fit control, protect, information SCADA systems for device is new installed: to

fit a cabinet protect control 110kV line in house, an outdoor cabinet wiring to feeder

of 110kV, an outdoor cabinet wiring to variable voltage 110kV.

3.1.3. Amount main workload of project

Table 3.2. Amount construction 110kV line Hai Duong – Pho Noi

No Work content Unit Quantity Note

1 Pouring concrete rock 2x4, level

durability B15 m

3 1,492.79

Handmade +

Mechanical

2 Pouring concrete rock 4x6, level

durability B3,5 - 370.79 -

3 Processing steel foundation, steel plates Ton 147.96 -

4 Anchor bolts Ton 11.83 -

7

5 Processing to installation Earthing

systems Position 41 -

6 Processing, erection steel pole Ton 270.34 -

7 Pull the wire tension spread ACSR-

300/39 km 58.751 -

8 Pull the tension spread lightning TK-50 - 0.933 -

9 Pull the cable tension spread OPGW68 - 9.797 -

Pull the cable tension spread ADSS - 0.187

10 To fit the wire anchor serial types Serial 216 Handmade

11 To fit the wire serial types - 204 -

12 To fit the support chain, anchor rope

CS, CQ wire - 59 -

13 Amount digging foundation land +

Earthing systems m

3 11,394.82

Handmade +

Mechanical

14 Amount filling foundation land +

Earthing systems - 9,055.9 -

15 Crossing lower voltage information line Time 08 Handmade

16 Crossing medium voltage line - 11 -

17 Crossing lines 220kV - 03 -

18 Crossing roads ≤ 10m - 06 -

19 Number of steering angle Conner 12

20 Pile driving bamboo 2.5m Pile 332 Handmade

21 Wattle bamboo 1x2m Plate 112 -

22 Dikes m3 235 -

3.2. Work transportation

3.2.1. Materials and equipment supply:

Material and equipment supply will be determined in detail in later phase, depending on

the state budget disbursement and the subproject bidding method. Two sources are expected:

- Cement, steel, sand, stone, gravel, shuttering to get local through routes.

- Tubular steel, fiber, wireless accessories, ceramic take in Hanoi.

8

3.2.2. Long distance transportation

For material and equipment supplied by the project owner:

+ Long distance transportation of such material and equipment will be undertaken

using specialized trucks. Such trucks will be selected in accordance with the requirements

provided in the contract.

+ Long distance transportation from the subproject owner warehouse to the site

will be undertaken using 5-7.5 ton trucks and loading and unloading will be done using 5-

ton cranes.

For materials and equipment supplied by the contractor:

+ Electric poles will be transported using Kawaz trucks, using 5-ton cranes for

loading and unloading.

+ Supporting frames and accessories will be transported using 5-ton trucks with

manual loading and unloading.

+ Cement and steel will be transported using 5-ton trucks with manual loading and

unloading.

+ Stone and sand will be transported using 5-ton dump trucks.

3.2.3. Intermediate transportation

Materials are supplied by A as: steel poles, wires insulation, accessories …have hub

transports from Commander Board to rout (before handmade transport into the work).

Transport distance for average the entire route is 3km roads type third. Including some ways

(by local management) have to pay cost, local’s template into, following based on the actual

acceptance of payment.

3.2.4. Manual handling

All materials and equipment will be transported to the construction site manually. The

distance will be determined case by case.

3.3. Arranging construction worker force and constructing site

- Location of construction site in project’s communes: the specific locations are

selected by construction contractors and these must be approved by the local authorities.

- To ensure the maintenance of equipments, materials and housing for workers, the

temporary buildings include:

+ Indoor warehouse for preserving cement, equipments, electricity materials and

accessories: 1 warehouse/30m2 /per commune

+ Opening warehouse with protecting fence for transformer, medium voltage wires,

constructing tools, beams and anchor wires: 1 warehouse/40m2

/per commune.

+ Temporary house for workers: 1 house/20m2

/per commune

+ Indoor warehouse and temporary house are made of bamboo frame and surrounded

by bamboo mats, their roofs are covered by bamboo mats and oil papers. During constructing

process, domestic water, rain water and leftover water are gathered and released into local

drainage network through temporary drain system. All wastes are collected and disposed in

the right places to ensure the hygiene and the beauty of construction site.

9

- To streamline local construction apparatus, local workers will be hired to do manual

works that are not required technical.

- Construction labor force includes 1 construction team/commune. The construction

time: 4 months

One construction team includes:

- Instruction direct : 80 persons.

- Instruction indirect : 05 persons.

- Work Commander Board : 03 persons.

The other auxiliary units coordinate :

- Factory processing steel pole.

- Motor transportation workshop.

- Brand house processing galvanized steel, reinforcing steel and formwork.

3.4. Progress and total investment of project:

3.4.1. Project progress:

Base on demands power supply and ability of Investor force construction progress and

time for work into operation follows:

Preparing the investment : 3 months

Tendering equipment : 2 months

Preparing as-built drawing design : 4 months

Time for test and finish : 1 month

Time execution of the stages the above are arranged alternately with a total time of

project implementation and completion of construction and commissioning of 9 months.

Then 72 hours of commissioning new safety works are put into official operation.

3.4.2. Project total investment:

Table 3.3. Total investment of project

No. Capital Investment Capital

01 Construction cost 28,406,481,000

02 Equipment cost 3,052,574,000

03 Arrangement Site Clearance Cost 10,450,442,000

04 Project management cost 625,274,000

05 Project construction investment Consulting

cost 2,226,315,000

06 Other cost 3,151,377,000

07 Contingently cost 9,324,492,000

Total 157,478,000,000

10

IV. SUMMARY OF NATURAL AND ENVIRONMENTAL CONDITIONS

PROJECT’S AREA

4.1. Geographical geological conditions

4.1.1. Geographical location:

Hung Yen is located in the central the northern plain, in the northern key economic

sectors. The Northern is near Bac Ninh Province. The East side is near Hai Duong province.

The Southern is near Thai Binh Province. The West is near Hanoi city. The South west is

near Ha Nam Province. Have 10 districts with 161 communes, wards and townships.

My Hao district is a northern plain, the northern is near Venal district, the west is near

Yen Mỹ district, the southern is near An Thi district, all of Hung yen Province. East is near

districts of HaiDuong: Cam Giang (northern east) Binh Giang district (southern east). Natural

area of My Hao district is 79.1 km ². The district has 12 communes and 1 town. Ke Sat River

located on the border with Binh Giang district of Hai Duong province. Also in the district

also have Ban River, Bac Hung Hai River, and Cam Xa River through dowsing. 110 KV lines

Hai Duong – Pho Noi (sub line on Hung Yen province) mainly go on paddy land of 4

communes of Hoa Phong, Duong Quang, Cam Xa and Nhan Hoa commune, My Hao District.

4.1.2. Topography and geomorphology

Line 110kV Hai Duong - Pho (subline on Hung Yen province) to the low-lying terrain

plain belonging My Hao district, Hung Yen province. Land of the terrain types are mainly:

Lightning, Asian sand, clay ... derived accumulation Waterfront (amQ).

4.1.3. Geological

Hydro geological conditions

Based on the survey documents along geological sections. During the 2010 survey 04

months of stability of underground water at a depth of 0.6 ~ 1.5 m. Predicts the highest water

level stabilized at depths from 0.0 0.6 m. According to experimental data with calculated

groundwater intrusion weak (Ia) according to TCVN 3994-85.

Dynamic geological conditions – earthquakes

According to the earthquake zone map on the territory of Vietnam, by the Center for

Natural Science and the National Technology established in 1995, the area of control sections

located in the earthquake may occur at level 7 8 .

4.2. Meteorological conditions

110kV Hai Duong – Pho Noi line, sub line VT55 - DC pass through the flat plains of My

Hao district, Hung Yen province

Lines lie completely within the influence of climate, hydrology northern plain. Basically

tropical monsoon, winter cold, summer is hot and humid and rainy.

Through the Hydro meteorological monitoring data with frequency 2% years showed:

Average air temperature in a year, about 23.50 C. Maximum temperature can reach up to

41.50 C, the lowest possible temperature drops below 30C. The average humidity in about

84%.

4.3. Traffic

The district has very favorable position, on many important traffic hub of the area:

Highway No. 5 from Hanoi, pass Ban Yen Nhan town, passes through district to Hai

Duong province. Highway No 39 from junction with Highway No 5 at Ban Yen Nhan town

11

of Hung Yen town, then to ThaiBinh province. The East has highway No 38, cut with

Highway No 5 with the province of Hai Duong Cam Giang district.

The project area is traffic conditions relatively favorable position of the road 5 to about 0.2

km; it is very convenient for the transportation of materials and equipment.

12

4.4. Describe router:

Table 4.1. Table describes line passing thought territory of administrative ĐDK-110kV Hai

Duong – Pho Noi

Sub line/

length Describe router Present use land Location

Position 55 - G1

length 953.8 m

Beginning from No. 55 has value left

steering angle 06015’ take the field

lines cut through some paddy ditches,

cutting through the plastic inter-

district, Garden wall built Mr Nguyễn

Văn Tranh, Phuc Mieu village, Hoa

Phong commune is 7.5m and passing

through rice fields Mr Dang Dinh Khu

next the plastic inter - district. Route

cut through a 0.4-kV power line, a 35

kV power line and a cable

communication lines. G1 is placed on

the rice fields, at the G1 line drive left

at = 090 16 '20"

Rural land, land

transport,

agricultural land

Phuc Mieu

village, Hoa

Phong

commune, My

Hao district,

Hung Yen

province.

G1 – G2

lenght 1,237.3m

Mainly router passing rice fields,

ditches cut through some thin, cut

through a power line was 10 kV. G2 is

placed on the rice fields of the

outermost lines Pha Lai-Pho Noi 220

kV is 15.2m, in line G2 drivers must

tiles = 450 52 '25 "

Rural land, land

transport,

agricultural land

Phuc Mieu

village, Hoa

Phong

commune, My

Hao district,

Hung Yen

province.

G2 – G3

length 52.6m

Route to the rice fields, pass through

220 kV power lines Pha Lai – Pho Noi

existing, G3 is placed on the rice

fields of the outermost 220 kV power

line-Pha Lai – Pho Noi is a 11m , in

the G3 line left drive = 420 48 '15 "

farm soil, paddy

land

Hoa Phong

commune, My

Hao district,

Hung Yen

province.

G3 – G4

length 1,428.4m

Mainly router passing rice fields,

parallel and the outermost of the 220

kV power line-Pho Noi - Pha Lai is

11m, cut through the banana growing

garden land and ponds Mr Trần Văn

Tranh Duong Xa village, Duong

Quang Commune distance houses

abandoned is 0.5m. Cutting through

the plastic inter-district, An

underground cable, a cable

communication lines, a power line 0.4

kV. G4 is located on the rice fields of

the outermost 220 kV power lines Pho

Noi- Pha Lai is 11m, at the G4 line

Rural land, land

transport,

agricultural land

Hoa Phong

commune, My

Hao district,

Hung Yen

province.

13

Sub line/

length Describe router Present use land Location

right drive is OP = 050 34 '20 "

G4 – G5

length 259.0m

Route to the rice fields, avoid the

pagoda Duong Xa village, Duong

Quang commune, should not go in

parallel with now power lines 220 kV

Pha Lai-Phố Nối, cut through a line 30

meters wide ditch and a small ditch,

cut through a 35 kV power line. G5 is

placed on the rice fields, At the G5

line left drive is = 080 15 '20”

Rural land, land

transport,

agricultural land

Duong Quang

commune, My

Hao district,

Hung Yen

province.

G5 – G6

length 611.3m

Line passing rice fields cut through

some smaller canals, ditches G6 is

placed inside the outermost of the 220

kV power line-Pho Noi - Pha Lai is >

11m, G6 line right drive at OP = 090

30' 15 "

Rural land, land

transport, canals

and paddy land.

Duong Quang

commune, My

Hao district,

Hung Yen

province.

G6 – G7

length 250m

Cross section through the drain line

20m cross cut about 150 m, go left to

the kitchen wall Mr Đặng Văn Hiệu

7.2m, go right to the kitchen wall Mr g

Phan Minh Công, Hieu Duong village,

Duong Quang commune 7.2m, cut

thought plastic inter-district, cut

thought 2 times power line 0.4 kV, cut

thought 2 eucalyptus tree sides of

ditches height 15m, G7 is placed

inside the trench. At G7 left drive

=330 03’ 42”

Rural land, land

transport,

agricultural land,

canals and paddy

land.

Duong Quang

commune, My

Hao district,

Hung Yen

province.

G7 – G8

length 165.6m

Route to the rice fields, G8 is placed

on the rice fields of the outermost 220

kV now power lines Pha Lai-Pho

Noiis 11m, At G8 right drive opr =180

52’ 30”

Rural land, land

transport,

agricultural land,

canals and paddy

land.

Duong Quang

commune, My

Hao district,

Hung Yen

province.

G8 – G9

length 1,084.2m

Rout go parallel and the outermost of

the 220 kV power line-Pho Noi - Pha

Lai is 11m, cutting through some

small ditches, cut thought a power line

0.4 kV. G9 is placed on the rice fields

outside of the phase 220 kV now

power lines Pha Lai-Pho Noiis 11m,

At G9 left drive ỏt =230 22’ 35”

Rural land, land

transport,

agricultural land,

canals and paddy

land.

Duong Quang

commune, My

Hao district,

Hung Yen

province.

G9 – G10 length

86.0m

Routes pass through 220 kV now

power lines Pha Lai-Phố Nối, cut

Rural land, land

transport,

Cam Xa

commune, My

14

Sub line/

length Describe router Present use land Location

through the graveyard, G10 is placed

on the rice fields, at G10 right drive

opr =230 35’ 55”

agricultural land,

canals and paddy

land.

Hao district,

Hung Yen

province.

G10 – G11

length 2,464.5m

Route cuts through paddy fields, go

left and outermost of the 220 kV now

power lines Pha Lai-Pho Noi is 11m,

cut thought 3 times power line 10kV,

an information line cable , a time

plastic inter - district. G11 is placed on

the rice fields outside of the phase 220

kV now power lines Pha Lai-Pho Noi

is 11m, at G11 right drive opr =300

39’ 55”

Rural land, land

transport,

agricultural land,

canals and paddy

land.

Cam Xa

commune, My

Hao district,

Hung Yen

province.

G11–G12

length 46.56m

Routes pass through 220 kV now

power lines Pho Noi – Pha Lai, G12 is

placed on the rice fields, at G12 left

drive ỏt =300 42’ 40”

Paddy land Nhan Hoa

commune, My

Hao district,

Hung Yen

province.

G12 – G13

length 350.3m

Go to the right line, parallel and

outermost of the 220 kV now power

lines Pha Lai-Pho Noi is 11m, cut

across a number of small ditches,

cutting through gardens and ponds

raising chickens, ducks of Ms Nguyễn

Thị Xuân, cut thought 2 power line 35

kV. G13 is placed on the rice fields

outside of the phase 220 kV now

power lines Pha Lai-Pho Noi is 11m,

at G13 right drive opr =200 36’ 40”

Rural land, land

transport,

agricultural land.

Nhan Hoa

commune, My

Hao district,

Hung Yen

province.

G13 – G14

length 159.7m

Rout cut thought 3 power line 35 kV,

Cutting through the overpass Pho Noi

to lạc Đạo, and connected to pole No 3

of now power line 110 kV Kim

Dong(It is G14). At G14 right drive

opr =650 18’ 30”

Rural land, land

transport,

agricultural land.

Nhan Hoa

commune, My

Hao district,

Hung Yen

province.

G14 – G15

lenght 74m

Routes to coincide with 110 kV power

lines Kim Dong and connected to pole

No 2 of now power line 110 kV Kim

Dong(it is G15). At G15 left drive ỏt

=90000’ 00”

Rural land, land

transport,

agricultural land.

Nhan Hoa

commune, My

Hao district,

Hung Yen

province.

G15 –G16-PT

length 70.3m

From G15 to G16 line break angle,

from the G16 line is connected to

110kV the bus bar of 220kV

Rural land, land

transport,

agricultural land,

Nhan Hoa

commune, My

Hao district,

15

Sub line/

length Describe router Present use land Location

substation Pho Noi currently operates.

Vegetation cover and which lines are

mainly rice, the rest is the fruit of

people in the region.

canals and paddy

land, fruit tree

Hung Yen

province.

16

V. IDENTIFICATION OF POTENTIAL IMPACTS OF THE PROJECT

The potential impacts of the project is paid model in the table below:

Table 5.1. Rapid assessment of environmental impacts of the Project

Screening questions Yes No Describe the impact

1.Location of Project:

Project location is near or within

the areas of environmental

sensitivity as well?

Cultural Heritage X The transmission line and substation

will not pass through areas with

cultural and historic value.

The conservation area X

Wetlands X

Forests X

Estuaries X

Buffer zones of protected

areas

X

The nature: bird sanctuary,

mangroves, etc.

X

Rivers and reservoirs X

Canal and Irrigation System X

2. Potential environmental

impacts

Is the project would cause:

- Invasive areas historic / cultural X

- Damaging the ecosystem (eg

sensitive areas or conservation,

national parks, nature reserves, etc.)

X

- Morph landscape waste and

increase

X - Due to clearing a corridor should

be small changes in the landscape

and increase waste but is rated at

low levels and will take the

appropriate measures to limit

- Cutting up trees and vegetation, or

to clean surfaces and stations along

X - Corridor routes only felling the

trees also affect the vegetation line

17

Screening questions Yes No Describe the impact

the corridor? and low trees retained (vegetation

only affected at position to the

foundations, but the area affected is

negligible).

- Change of surface water quality or

flow

X

* Increased water turbidity due to

surface runoff or erosion

X - In the course of construction if the

rainy season without safeguards for

the pole to the foundations, the

erosion can occur and affect the

local flow.

* Waste water from area camps

dumped onto the surface water or

not?

X - Units constructed primarily to lease

houses in so wastewater will be

collected into the general sewage

system.

* Waste water is poured into the

construction of surface water or

not?

X

- It increases the level of dust or

not?

X - Due to the transport of sand, rocks

using transport vehicles should have

caused dust. But is considered

negligible.

- It increases the noise and / or

vibration or not?

X - Due to the transportation of sand

stone materials using transport

vehicles should be making noise. But

is considered negligible.

- Permanent Land Acquisition X -Nhan Hoa Conmmune: 1,046.4m2

Including agricultural land and

wasteland.

-Duong Quang Commune: 1,269.

4m2 Including agricultural land and

wasteland.

- Cam Xa Commune: 433.9m2

Including agricultural land and

wasteland...

- Hoa Phong Commune: 444.7m2

Including agricultural land and

wasteland.

- Temporary Land Acquisition X The area of land occupied

temporarily: 69,525m2. Land used

for the corridor is agricultural land,

wasteland and plantation production

18

Screening questions Yes No Describe the impact

is not land acquisition.

- Are families moving or not? If

yes, how many households?

X

- Resettlement Area Is the area of

environmental sensitivity and / or

culture?

X

- Is there any risk to the spread of

disease from construction workers

to the local population (and vice

versa) does not?

X - All the work will be divided into 02

crews in 04 communes, each team

about 40 people. The total number of

workers on site at the highest point is

about 80 people scattered on the

route but not focused in one place.

Therefore, the spread of disease will

also be limited.

- There are potential conflicts

between construction workers and

local people do not?

X - Construction workers and local

people have different incomes,

lifestyles, and customs, so minor

inconsistencies may have occurred

but will be limited.

- There explosives or chemicals

used in the project?

X

- Previously, there were no

accidents caused by mines or

explosive remnants of war?

X

- Construction projects for

disrupting traffic in the area?

X Because rural roads sparse capital,

time and materials handling

equipment is short (about 1 hour), in

addition to construction materials

(sand, earth, stone ...) used dump

truck should cause the level of the

yoke traffic is not large.

- Construction projects can cause

damage to existing road system

does not?

X - All materials and equipment are

classified for transportation in

accordance with the load of the road,

traffic here is an asphalt road

(Highway 5, provincial roads and

village roads, other inter-communal)

should no effect

- Training of land during

construction does not cause

erosion?

X - Pot round-foundation at each

position normally does not last long

(up to about 1 week), construction

finish each item, but there are two

19

Screening questions Yes No Describe the impact

pole foundation position near the

water canals and the construction

plan will take part in the rainy

season so the erosion is likely to

occur if no preventive measures for

good.

- The project should pave the way

public service is new?

X - The lines along roads so the

existing roads are used.

- The project has caused the fault of

the habitat of flora and fauna not?

X

- The project affects air quality? X - The environmental impact level will

be insignificant because the

transportation will be cover by

canvas

- The project has caused the

accident risks for workers and

communities in the construction

phase do not?

X - Minor impact

- The project has generated

hazardous wastes including PCBs

due to replace the transformer?

X

- The project has caused any risk to

safety and health

(electromagnetism, electric shock,

etc.)?

X - The line and transformer station

are designed and built basing on

current regulation of the electricity

sector, in which the calculations on

the harmful effects of

electromagnetic fields and standards

to ensure electrical safety, operation

safety are done to avoid harm to

human health.

- Sub-projects not related to work

off, oil change equipment, so there is

no risk of intrusion of big oil

environment;

- Electric shock and other electrical

accidents can occur if safety

measures are not sufficient attention.

- The negative impact on other

(specify, if any) X

20

VI. ENVIRONMENTAL MANAGEMENT PLAN

6.1. Mitigation measures

Table 6.1. Mitigation measures applied for the Project

Environmental-

social issues Mitigation measures applied

Responsible

bodies

A. Preparation phase

1. Permanent and

temporary land

acquisition will

impact affected

households and

agriculture

production

- To plan for construction activities after harvesting

season and try to shorten the progress.

- Inform the affected HHs about permanent and

temporary land acquisition.

- Properly compensate for land acquisition and tree

compensation in accordance with the Resettlement

Policy Framework of the DEP project and

Resettlement Plan of the Subproject.

- PMU

- Contractor

2. Impacts on

vegetation cover

as a result of site

clearance (ROW)

- Minimize land clearing by planning for

installation of transmission/distribution lines

above existing vegetation.

- Utilize hand clearing of vegetation if possible.

Save as much vegetation as possible. Careful

manage cutting trees. Cut only tree above 4m

within the ROW.

- Do not burn cleared trees and branches;

- Carry out the safety procedures to prevent hazard

of downing trees.

- Dispose at established dump site.

- During clearing, contact with the affected HHs in

order to mitigate impacts and carry out

compensation.

- PMU

- Contractor

3. Explosive

materials left

from war

- Contract with related army unit to clear the site

from unexploded ordnances left from war.

- Return the ground after the clearance.

- PMU

- Army

- Local

authorities

B. Construction

phase

21

Environmental-

social issues Mitigation measures applied

Responsible

bodies

1. Dust pollution - The contractor is responsible for implementing

the state applicable regulations related to air

quality.

- The contractor will ensure minum dust generation

and no impact on local residents and take proper

measures to control dust generation (for example,

praying water, covering the trucks when carrying

material).

- Material will be covered up during. transportation

to prevent scattering of material along the way.

- Material dump site and storage yards will be

covered up and isolated from winds and located

away from schools and residential areas.

- Workers will be provided with masks when

working in high risk areas.

- Contractor

- CSC

2. Air pollution - All transportation vehicles must comply with

applicable regulations of Vietnam with regards to

exhaust gases.

- Transportation vehicles in must be tested

frequently on the waste gases and have to show

certificate of quality, technical safety and

environmental friendliness according to Decision

No.35/2005/QD-BGTVT.

- Do not burn waste or construction materials at the

site.

- Contractor

- CSC

3. Noise and

vibration level

- The contractor will be responsible for complying

with applicable regulations related to permitted

noise and vibration levels.

- All transportation vehicles need to show

certificate of quality, technical safety and

environmental friendliness according to the

Decision No.35/2005/QD-BGTVT; to prevent

excessive noise level from machinery that is not

properly maintained, proper noise reduction

measures are taken, including noise reducers or

arrangement of noisy machinery in a specific

noise proof area.

- To prevent or reduce traffic in residential area as

well as processing of material in residential areas

(concrete mixing)

- Contractor

- CSC

22

Environmental-

social issues Mitigation measures applied

Responsible

bodies

4. Waste water

pollution

- The contractor will be responsible for complying

with applicable regulations related to waste water

treatment and discharge.

- To provide mobile toilets or construct proper

toilets for workers at the site. Toilet waste water

and restaurants will be treated before discharging

into the outside environment.

- When construction is completed, toilets have to

be properly destroyed and/or removed.

- Contractor

- CSC

5. Water drainage

and

sedimentation

control

- The contractor will comply with the water

drainage system design to prevent rain drop from

causing local inundation, soil erosion in high risk

areas.

- To ensure proper operation of the drainage

system.

- To sustain those areas not impacted by

construction activities.

- The excavation work needs to be done in

compliance with applicable technical construction

regulations.

- To prevent the spreading of mud into surrounding

environment, take proper measures to control

sedimentation in high risk areas.

- When there is a need to dry construction site

(foundation concrete pouring), the pumped water

containing sand will be controlled with regards to

sedimentation before discharging it into outside

water bodies.

- Use diversion techniques at construction to

prevent deposit from being stirred up in water

bodies.

- Contractor

- CSC

6. Material

warehouse and

material quarry

management

- Material storage yards will be predetermined in

the approved engineering design.

- Material supplied by local suppliers need to have

operation licenses for particular material type.

- To rehabilitate material storage yard after

construction is completed.

- Contractor

- CSC

7. Waste and

hazardous waste

- Prior to construction, the contractor needs to

prepare a procedure for controlling waste

(storage, use of recycle bins, site

- Contractor

- CSC

23

Environmental-

social issues Mitigation measures applied

Responsible

bodies

decommissioning, etc.) and strictly complying

during construction phase.

- Prior to construction, all necessary licenses have

to be obtained related to waste management.

- Proper measures are taken to ensure good

practices in waste management and treatment.

The contractor will provide recycle bins,

containers and other means to collect waste from

necessary areas.

- Waste can be stored temporarily at the site when

it is approved by the Construction Monitoring

Consultant, local authorities before collection and

treatment. If in the absence of such authorities,

normal domestic waste can be land filled.

- Recycle bins or containers storing waste have to

be covered up from weather impacts and intrusion

by scavengers. Do not burn waste.

- Recyclable waste such as wood form, waste steel

and packing material will be collected and

separated at the site from other waste sources for

reuse, refilling or sale to an external company.

- If it is impossible to carry away from the site,

solid waste can be land filled at a certain place

approved by the construction supervising

consultant provide in the waste management plan.

Under any circumstance, the contractor has to

treat all construction waste within the site.

- Waste lubricants will be taken out from the site

by an authorized recycling company.

- Waste lubricants and cleaning solutions will be

collected into covered containers and carried

away by a contracted external company that is

permitted to treat hazardous waste

8. Site clearance - The contractor will prepare a plan on site

clearance and vegetation recovery according to

applicable regulations for the construction

supervising consultant to approve. The contractor

will strictly comply with this plan.

- Do not use chemicals in clearing vegetation.

- Do not cut down any trees when it is not provided

in the vegetation clearance plan.

- Contractor

- CSC

24

Environmental-

social issues Mitigation measures applied

Responsible

bodies

- If necessary, set up temporary fence to protect

valuable trees prior to starting any construction

activities.

9. Traffic

management

- Prior to construction, conduct consultation with

local authorities and traffic police.

- Impacts on traffic flow needs to be considered in

the construction plan before approval. Traffic

routes, particularly those with heavy duty vehicles

need to consider high risk area such as schools,

hospitals or markets.

- It is necessary to provide sufficient lighting

system for night time to ensure proper traffic

conditions.

- Arrange indication signs at the construction site to

inform public people, provide instructions to

different components and instructions and safety

directions.

- Take proper traffic safety measures including sign

posts and flags to indicate danger

- Do not transport material during peak house.

- Space spared for walkers and vehicles at the site

need to be separate from the site and can be easily

accessible. Provide proper sing posts where

necessary.

- Contractor

- CSC

10. Interruption of

utility and

business services

- Planned or unplanned interruptions to services

such as water, gas power supply and internet

access: The contractor will be prepared for

emergency scenarios and any potential failures.

- Cooperate with services suppliers (water,

telecommunications, etc.) to work out a proper

construction schedule.

- During the laying out of cables crossing over

telecommunications cable, mitigation measures

have to be taken (What are the measures?)

- Notify affected households of construction

schedule as well as expected interruptions (at

least 5 days in advance)

- Interruptions to water supply for agriculture

production need to be avoided.

- The contractor will ensure alternative water

supply for affected residents in case it is more

- Contractor

- CSC

- PMU

25

Environmental-

social issues Mitigation measures applied

Responsible

bodies

than one day.

- Any damage to the existing service cables will be

notified to the local authorities for timely repair.

11. Rehabilitation of

affected areas

- Clearance areas such as soil or rock quarries,

waste treatment areas, worker houses, warehouse

and wood forms and any other temporary areas

during construction phase will be rehabilitated

with regards to the landscape and vegetation

cover.

- Compensate the vegetation cover at the soonest.

Use proper vegetation for such rehabilitation.

- Do not use exotic or banned vegetation for such

rehabilitation

- Excavated hillsides and waste yard need to be

planted with grass to prevent soil erosion and

landslide;

- All the affected areas will be compensated with

proper landscape and there should be no delay in

doing so, including any necessary repair or

construction of green space and other affected

areas.

- Soil contaminated with chemicals or hazardous

waste will be carried away and land filled in a

proper hazardous dump site

- Rehabilitate all affected roads and bridges due to

the project construction

- Contractor

- CSC

12. Labor and public

safety

- The contractor will comply with all applicable

regulations related to labor safety.

- Prepare and implement action plan in response to

risk and emergency cases.

- Prepare emergency services right at the site.

- Provide training for workers on labor safety

requirements.

- Ensure to provide protective devices for workers,

including noise protection at high risk places

- In destroying existing structures, workers and

community need to be protected from falling

objects by taking proper protection measures

- Provide protective fences and warnings of danger

at the construction site to indicate danger to local

- Contractor

- CSC

26

Environmental-

social issues Mitigation measures applied

Responsible

bodies

resident.

- The contractor will provide safety measures such

as installation of fences, provision of warning

signs at high risk areas, including pole foundation

under construction to prevent traffic accidents as

well as other risk to local residents.

- Only allow trained workers to install, maintain or

repair electrical equipment.

- Cut off and do correct earthling for the existing

power line prior to construction work.

- Comply with labor safety procedures when

working at height and with electrical equipment

13. Communications

to local

community

- Sustain communications to local authorities and

community; the contractor will work with local

authorities to agree on construction schedule for

sites near sensitive areas or at sensitive time

(regional festivals).

- Enhance relationship with local community in

order to obtain necessary information about the

project activities in the region, progress and

performance;

- Keep track of the community concerns and

information required such as project progress;

- Respond to community concerns via telephones

and documents in a timely manner;

- Notify local residents of construction schedule,

work schedule, potential interruptions to services

and detour roads and temporary buses, any

destruction or mine explosion schedule;

- Provide technical data and drawings for

community, particularly a scheme on construction

sites and EMP;

- Provide notice boards at all sites to provide

information about the site manager,

environmental officer, medical and safety officer,

with concrete contact details and other

information so that affected people will be able to

raise their voice and concerns.

- Contractor

- CSC

- PMU

14. Chance find

procedures

During construction phase if the contractor finds any

cultural and historical sites, including commentary or

tombs, the contractor will:

- Contractor

- CSC

27

Environmental-

social issues Mitigation measures applied

Responsible

bodies

- Stop construction activities in the particular area;

- Protect the area from any damage or loss to the

sites. In case the historical objects can be

removed or sensitive objects assign a person to

protect it until local authorities come to confirm

and take over the issue;

- Notify the construction supervising consultant,

who will be responsible for informing local

authorities or the state agencies of such cultural or

historical sites (within 24 hours or less);

- Local authorities or state agencies will be

responsible for protecting and isolating such area

before any further processing.

- Decide how to process such issues is the

responsibility of the local authorities, including

change, (in case a cultural or historical site is

found and cannot be removed), reservation,

isolation, rehabilitation and rescue;

- If the cultural or historical site are of high value

and the reservation is recommended by relevant

agencies the project owner will have to change

project design accordingly for the component in

that particular area;

- Decisions related to the management of found

sites will be notified in writing to relevant

authorities;

- Construction work will continue only after

relevant authorities come and take responsibility

of potential sites.

- PMU

C.Operation phase

1. Health and safety

for workers and local

residents

- Disseminate the information on electricity safety

regulations to the users.

- Comply Decree No. 106/2005/ND-CP dated 17

August 2005 of Goverment on protecting grid;

Decree No. 81/2009/ND-CP dated 12 October

2009 of Goverment on protecting hight voltage

grid

- Regular training for local technicians and people

on safety issues.

- Use warning signs, barriers (locks, gates, iron

barriers...) around substation or tower to prevent

- NPC

28

Environmental-

social issues Mitigation measures applied

Responsible

bodies

people reach danger equipment;

- Putting warning signs, barriers on the ground

close to electricity wire to prevent electric shock

- 2. Fire and

explosion

- Periodically inspect fire prevention and fighting

facilities.

- Organize training on fire prevention and fighting

for operation workers.

- NPC

3.Transmisison line -

Mitigation measures

related to

transmission lines

- Only allow workers who have been trained and

obtained certificates on installation, maintenance

and repair of electrical equipment

- Cut off power and provide safe earthling before

construction on the power line or where it is near

power line

- Ensure operations related to power line will be

undertaken by trained workers with strict

compliance with safety regulations. Qualified or

trained workers to operate power lines need to able

to:

- Distinguish between online and offline power lines

from other parts of the distribution system

- Determine voltage of online power lines

- Understand safety distance for each cable types

- Ensure correct and sufficient use of safety devices

and other safety procedures or other online parts of

the distribution system

- Even when being trained, workers will not contact

any online parts unless:

- Workers have been safely isolated from online

parts via gloves or other insulation devices

- Online parts have been safely isolated from

workers and other parts or

- Workers have been isolated and safely insulated

from online objects

- When operations and maintenance request

minimum distance, provide trainings on safety

measures and safety devices for individuals and

other preventive measures identified in the health

and safety compliance plan. (Below is the

recommended safety distance for workers:

- NPC

29

Environmental-

social issues Mitigation measures applied

Responsible

bodies

o 2-15 kV: 0.6 m

o 15.1-35kV: 0.71 m

o 72.6-121 kV: 1.01 m

4.Safety measures

when working at

height

Preventive and control measures include:

- Check the firmness of structures before starting

work

- Take anti-fall measures including climbing skills,

use of supporting devices and first aid toolkit

- Install supporting and anti-fall devices

- Safety bands will not be smaller than 16 mm, two

layers, and durable strength. Safety bands will be

replaced before any defect or crack is detected or if

is too old

- When working with tools at height, workers will

need an additional safely band (backup).

- Sign posts and other obstacles need to be removed

before starting work

- Use standard tool bag to carry tools and materials

to the height when working on pillars

- NPC

5. EMF impacts - Prevent or minimize exposure to EMF in the

working environment by developing and

implementing a EMF safety program with the

following components:

- Determination of potential exposure level

- Trainings for workers on how to identify their

exposure to EMF and its impacts

- Determination of safe areas in order to

differentiate those areas with higher EMF impacts

than the others where EMF impacts are small

enough not to be provided with mitigations and

minimize exposure to high EMF impact areas

- The exposure detector for individuals will be

installed to give warning when exposure is below

the safety limit (for example, 50%). Action plans

for mitigating impacts includes taking turn to work

in high risk areas, and if necessary being provided

with protective devices.

- NPC

30

6.2. Measures to minimize the specific impact of this project

Table 6.2. Measures to minimize the site specific impact of this project

Environmental-social issues Mitigation measures applied

- Location of transformer and medium-

voltage lines passing through rice

fields, forested hills and some canals

will affect the public drainage,

irrigation system if no any mitigation

measures are provided during

construction

- Before construction, workers will

be reminded not to leave rock and

soil fill up the canals drainage

systems, and field irrigation system.

- Safety construction measures shall

be carefully studied in order to not

impact to the existing irrigation

system.

- Materials and refuses must be

removed to reinstate the landscape

and environment after completion

of construction.

6.3. Environmental monitoring plan

Table 6.3. Environmental monitoring plan

Impact Monitored

parameter

Monitored

point

Monitoring

equipment

/method

Timing/

frequency of

monitoring

Responsibility

Construction phase

I.

Vegetation

cover

clearance or

cutting

down trees

-Clearance

technique

- Disposal of

cut-down trees.

- Along the

transmission

line

- In a

centralized

place for

processing.

Observation -From

beginning to

the last

moment.

-Contractor

-Construction

supervising

consultant

I I. Rural

roads in the

project

region

- All heavy

tonnage

vehicles on the

local roads

- Along the

roads

Observation

and

consultation

with local

residents.

-Weekly basis

when material

is transported

to the region.

- Four months.

- Contractor,

-Construction

supervising

consultant

III. Surface

water

quality,

- Not excavate

while it is

raining

- Surface

water near

the site.

Observation -During and

after heavy

rain

-Contractor,

-Construction

supervising

31

Impact Monitored

parameter

Monitored

point

Monitoring

equipment

/method

Timing/

frequency of

monitoring

Responsibility

sedimentati

on and

erosion

- Not clear

plants

completely

consultant

IV. Dust

and air

pollution

- Dust

concentration

in material

storage area

- Cover for

material during

transportation

process

- Areas with

excavation

foils and

material

storage

Observation -In presence of

strong winds

-Contractor,

-Construction

supervising

consultant

V. Noise

level

- Noise by

machinery

- Local

resident

response to

noise from the

construction

process

- The line

section

running over

residental

area

Consultatio

n with local

residents

-During

activities that

may result in

high noise

level;

Complaints by

local residents

-Contractor,

-Construction

supervising

consultant

VI. The

culture and

history

monuments

- The effects of

noise

-At the

construction

places close

to culture and

history

monuments

Observing

the local

residents

-During

construction,

the activities

emanate noise

-Contractors

-Construction

monitoring

consultant

VII.

Sanitation

situation at

the

construction

site,

including

the hygiene

of workers’

camps

-Garbage,

waste water at

the

construction

site and

workers’ tents

- If he tents

have been

supplied clean

water and had

sanitary

latrines

-At the tents Observing -Every week,

when official

acceptance of

work

-Contractors

-Construction

monitoring

consultant

VII. Safety

of workers

and local

- Accidents

happen

- At the sites,

local areas

- Consult,

Record the

constructio

-Contractors

-Construction

32

Impact Monitored

parameter

Monitored

point

Monitoring

equipment

/method

Timing/

frequency of

monitoring

Responsibility

presidents n log of the

contractor

monitoring

consultant

Operation phase

I. Maintain

and protect

the ROW

The height of

plants along

the ROW

Along the

ROW, houses

and trees

Prune trees

and ensure a

safe

distance for

the ROW

One month/

time

North High

Voltage grid

Company

II. Danger

due to

danger

-The intact

situation of

poles,

insulators,

protecting

devices of the

station

- At the pole

of the line

route, the

position of

the station

- Observing

and

assessing

3months/

time

-North high

voltage grid

Company

VII. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING

7.1. Responsibilities for Implementing the Environmental Management Plan

Non-compliance by the contractor could result in suspension of works, financial

penalties, or other penalties, as must be clearly spelled out in the EMP and in the contract.

Contractors are responsible for implementation of EMP. The responsibilities for

monitoring EMP implementation are typically shared between the contractor, the PMU, and

the Construction Supervision Consultant (CSC). The Contractor’s Work Plan should

incorporate the guidelines provided in the EMP created for the subproject. The designated

Technical Officer(s) and Safeguards Officer(s) of the PMU are responsible for supervising

the adherence to the agreed EMP by the selected contractor(s). The World Bank may

periodically supervise implementation activities of the subproject.

At a minimum, the contractor should prepare a monthly report on adherence to EMP

which should be submitted to the CSC and to the PMU. Subproject-specific or contract-

specific reporting requirements are described in the EMP. CSC is responsible for monitoring

overall environmental performance of the project and submit to PMUs quarterly monitoring

reports.

To ensure effective implementation of the EMP, the following actions will be carried out

during the implementation of the subproject

7.1.1 During Detailed Design and Preparation of Bidding Contract Documents

During the detailed design and bidding invitation preparation, the project management

unit will be responsible for incorporate the EMP (mitigation measures, responsibilities of the

contractor) into the attached annexes in the bidding invitation and contract signed with the

33

contractor. Engineers taking charge of the detailed design will also refer to findings in the

EIA and EMP to ensure environmental issues will be looked at in the final design.

During the bidding invitation preparation and the contract, it is necessary to ensure the

contractor is fully informed of its responsibilities in implementing environmental mitigation

measures and its commitment to compliance.

7.1.1. Construction phase:

PMU will assign the Construction Supervising Consultant (CSC) and/or field engineer

to be responsible for supervision of safeguard performance of contractor on a daily basis. A

generic Terms of Reference (TOR) is provided in Annex 1. CSC and/or field engineers will

carry out, but not limited to, the following tasks:

- Before the commencement of the construction, confirm that all compensation for land

and facilities are provided and relocation and/or land acquisition/donation has been

completed.

- Closely supervise the implementation of safeguard measures throughout the

construction period.

- Confirm the compliance with the EMP and inspect for any damages caused by the

contractor. If necessary, prepare a minutes to ask the contractor to compensate or

rehabilitate as provisions of the contract. Contractor safeguard performance will be

included in the subproject progress report.

Role and responsibilities of parties in implementing EMP are summarized in the below table

Table 7.1. Responsibility for EMP Implementation

Role Responsibility Organization

- Project

owner

- Take final responsibility with regards to the

management and implementation of project including

environmental compliance environmental

performance.

-North

Electricity

Corporation

- Environme

ntal officer

- Indicate specific responsibility and provide contact

details.

Environmental

officer of

project

34

Role Responsibility Organization

- Project

manageme

nt and

implement

ation entity

Responsible for cooperating and managing the

implementation of project including providing guidance

and implementing the EMP:

- Develop plan and implement EMP activities during

construction.

- Cooperate with relevant stakeholders with regards to

environmental performance.

- Conduct internal supervision and independent audit.

- Supervise and provide budget for monitoring

activities.

- Report environmental information to relevant

stakeholders.

PMU

- Project

operation

entity

- Operating the project including environmental

management and supervision during operation phase.

North High

Voltage Grid

Company

- Contractor

supervisor

- Support the PMU in supervising project operations

with regards to environmental impacts mitigation

according to measures described in the EMP and keep

in touch with local residents.

Construction

supervising

consultant

hired by the

PMU

- Contractor Constructing and complying with technical requirements of

the EMP, including:

- Taking mitigation measures to minimize negative

impacts as described in the EMP.

- Communicating with local residents and taking action

to prevent environmental and social interruptions in

the project region during construction.

- Ensuring at least one officer supervises compliance to

EMP during construction.

- Ensuring all construction activities are given

necessary approvals from relevant authorities.

- Ensuring workers and officers understand their

responsibilities and procedures in environmental

management.

- Reporting to the construction supervising consultant

on difficulties and solutions.

- Reporting to local authorities and PMU and

cooperating with relevant agencies to address any

issues.

Construction

supervising

consultant

hired by the

PMU

35

7.2. Building the EMP implementation capacity

Training plan in the coming time includes:

EVN’s training program: Internal training courses on the implementation of

environmental management work at site, the preparation of reports on the Project

environmental issues as a part of half-yearly and annual reports. The program will

also provide training on environmental impact mitigation measures which

unexpectedly occur and differ with forecasts stated in the EMP report.

Northern Power Corporation’s training program: NPC’s training program

provided to the local power company’s staff and some local people is about:

Training on safety work: Periodically training on the safety work and power

network maintenance;

Supervision method and report EMP implementation to stakeholders in the

province and the districts where the Project is located. The training work will also

provide guidance’s on the coordination with the people in the environmental

management work;

Table 7.2.Estimates of capacity building for implementing EMP

No. Training contents Participants Unit Amount

1 Annual training of EVN

for all of its subsidiaries

3 persons from the PMU of

NPC, participating in 2days

5,000,000 đ 30,000,000 đ

2 Training and exchanging

experience in

implementing

environment

management plan and the

Environmental

Management Plan

2 persons from the PMU of

NPC, participating in 2days

5,000,000 đ 20,000,000 đ

3 Training on the EMP

implementation

2 persons from NHPNC,

participating in 2 days

5,000,000 đ 20,000,000 đ

4 Training on the EMP

enforcement for local

officers

1 person/commune x 4

communes

1 person/district x 1 districts,

participating in a day

500,000 đ 2,500,000 đ

5 Training for site

commanders

80 persons participating in a

day

300,000 đ 24,000,000 đ

Total 96,500,000 đ

36

7.2 Reporting procedure

Responsibility and frequency of reporting on EMP implementation are shown

the below table.

N

o.

Report by Submitted to Frequency of reporting

1 By contractor to project owner PMU Once prior to starting

construction afterwards

every one month.

2 Construction supervisor (cum

environmental monitor)

PMU Monthly

3 Community supervisor (if any) MPU If any complaint

4 PMU EVN Quarterly

5 EVN WB Biannually

7.3. Estimated cost for implementing the EMP

Estimated cost for (i) implementing main mitigation measures (ii) and trainings:

No. Description Construction phase Operation phase

01 Mitigation measures. Under the contract with the

contractor

Under the production

cost of province

electricity

02 Environmental monitoring during

construction phase (incorporated

into the cost of construction

supervising consultant).

Under the cost for PMU

operation (Supervising

consultant will exercise

independent monitoring)

Under the cost of the

project owner operation

03 Training on environmental

management by project investor

for local officers, contractor and

supervising consultant.

96,000,000 VND Capacity building need

assessment (trainings,

workshops and study

tours)

TOTAL COST: 96,000,000 VND

* The cost for mitigation measures during the construction phase and

environmental monitoring by the supervising consultant will be included in the

construction supervising contract.

37

VIII. CONSULTATION AND DISCLOSURE OF INFORMATION

In the subproject preparation phase (the year of 2011), the following five activities

were carried out:

Activity 1: Surveying the site, working with the local authorities to discuss the route

and the substation locations.

Activity 2: Surveying the site and preparing the EPC and the EMP reports.

Activity 3: Conducting public consultation on the subproject.

From May 16th

, 2011 to May 19th

, 2011, a meeting with local residents in 04

communes was organized in order to consult with the public on the EMP, the representatives

of the Subproject Owner were also involved the following contents:

- Describing the subproject, the route, thesubstation locations, and the necessity for

the subproject;

- The potential impacts on the environment and communities;

-The measures to mitigate environmental impacts.

Participants: Participants of the Commune People Committee, Farmer Association, Women

Association , and other public organizations, hamlet chiefs, representatives of project’s

affected households, and consulting agency.

Table8.1 Summery consult public

No District/ Commune Time People

I My Hao District

1 Hoa Phong Commune 16/05/2011 18

2 Cam Xa Commune 17/05/2011 18

3 Nhan Hoa Commune 18/05/2011 18

4 Duong Quang Commune 19/05/2011 18

Summary of comments from the participants:

- All local people agreed to implement the Project. However, they required quick

construction, limited delay, prolong extension and cleaniness for environment and

work quality.

- The ROW which has been chosen suitable is proper and convenient for construction

work. The line route was chosen to minimize the negative impacts;

- The land occupation and pruning of trees are considered and reduced to a

minimum. Therefore, the long term adverse effects on the environment will not occur;

- Local people have three main concerns to the project’s environment issue. The first

one is that the damages which are due to tree felling, land acquisition are

compensated or not. The second one is that who will be responsible for monitoring

the implementation of mitigation measures, in some previous projects, the Contractor

had promised to implement mitigation measures, but in fact they did not do. The last

38

one is the role of local communities in the implementation of mitigation measures,

especially in monitoring the implementation of mitigation measures. About the

potential impact of sub-project on the environment, local people emphasized the

impact which involves felling trees, occupied land and village roads.

- The Consultant and the Contractor must select the appropriate time for construction

phase to minimize the crop affect, to avoid damage or degradation on the roads, to

avoid traffic jams. The construction space should be allocated appropriately to

minimize the impact on daily life impact of local people;

- Once the construction is completed, the contractor shall rehabilitate the site and return

the original landscape.

- The local government always volunteers to cooperation with the Project owner and

the Contractor in environmental supervision and management activities;

- The citizens and local governments expect that sub-project is constructed and

operated as soon as possible.

The summary of meeting with local residents, minute of stakeholder consultation

meeting and some photos about the meeting attached in Annex 6.

All relevant issues as well as comments by the local residents have been taken into

account by the supervising consultant and the project owner and shall include them in the

design of the project and EMP implementation.

Activity 4: Review and correct the EMP in accordance with the

comments. Continuing to receive feedback from the affected households. To collect opinions

of the people to complete the environmental impact mitigation measures in the EPC and

EMP.

Activity 5:Disclosure of the EMP

The EMP will be translated into Vietnamese and disclosed in the country at PMU, as

well as in Hung Yen province, and the subproject areas.

The EMP copies in Vietnamese and English will be sent to the Vietnam Development

Information Center at 63 Ly Thai To street, Hanoi City for disclosure of information.The

EMP copies in English will also be disclosed in the Infoshop of the World Bank.

39

REFERIENCES

1 Compensation Plan of the Project

2 World Bank Environmental Assessment Source Book

3 Statistical Yearbook 2010 - Statistical Publisher

4 Project investment report

5 Framework for Applying Environment Safeguards to RD Project- WB.

40

ANNEX 1

TERMS OF REFERENCES FOR MONITORING OF EMP IMPLEMENTATION

FOR CONSTRUCTION SUPERVISING CONSULTANT

Background

The construction supervising consultant will deliver technical services (“Services”) to ensure

efficient implementation of the EMP for the project.

Scope of services:

Services provided by the supervising consultant will include reviewing and monitoring of

construction activities to ensure mitigation measures described in the EMP for the project are

correctly complied with and negative environmental impacts are minimized.

On behalf of the PMU, supervising consultant undertakes the following duties:

- Conduct frequent field inspection;

- Review the implementation of environmental protection measures described in the EMP

and contract documentation;

- Review the effectiveness of the mitigation measures and environmental performance of

the project;

- If necessary, validate the acceptability of construction methods with regards to

environmental compliance (for temporary and permanent items), relevant design plans

and other submitted documents. If necessary, the supervising consultant will seek for and

recommend methods with less environmental impacts with consultation with the design

consultant and the PMU;

- Validate inspection results with regards to any non-conformance to environmental

performance and effectiveness of any countermeasures;

- Provide audit results for the leading engineer of the contractor in accordance with non-

conformance handling procedure described in the EMP;

- Direct the contractor to take corrective actions within a specific time period and exercise

additional monitoring if necessary, as per the requirements of the contract in case of non-

conformance and complaints;

- Direct the contractor to take actions to mitigate impacts and comply with the EMP in case

non-conformance is found;

- Direct the contractor to stop any activity resulting negative impacts and/or in case the

contractor does not fulfill requirements of the EMP, to take corrective actions.

- For contracts that need Site Environmental Management Plan (SEMP), the

supervising consultant will conduct a final review and approve all environmental plans at

the site that may affect environment. This work includes but not limited to: dredging

areas, material quarries and dumping areas and worker houses. The supervising

consultant will review and approve such SEMP submitted by the contractor. If such plans

are found non-compliant to the EMP, EPC or RAP, the supervising consultant will work

with the PMU and contractor for a proper solution.

- Complaint handling: Complaints from local residents will be collected by site officer of

the contractor, which may include violations to noise level, dust concentration and traffic

41

safety requirements. The lead consultant of the contractor and the supervising consultant

will address and work out a final solution organizes all such complaints. The supervising

consultant will provide a list of these complaints and confirm they have been properly

handled by the contractor in the same way with issued identified during site inspection.

- Confirmation of monthly payment: The supervising consultant will confirm monthly

payment for environment related activities undertaken by the contractor.

- Report: The supervising consultant will make the following reports in English:

o Report twice a week on non-conformances

o Monthly summary report will include issues and findings from the reviewing

and monitoring of construction activities

o At the end of project, the supervising consultant will make a final summary

report on findings from their work, number of violations, and solutions, etc. as

well as provide consultancy and guidance on how to implement such duties in

future.

42

ANNEX 2

------------

Report template for monitoring of EMP implementation

(Used for report by supervising consultant to PMU)

Project name:

Project location: Province: District:

Commune/Town:

Supervising consultant:......Full name Date of report:……………………

No. Parameter

Assessment of

comments by

supervising

consultant and

community

Comment/

Recommenda

tion

Construction phase

1 Water turbidity and soil erosion

2 Noise level at the site and nearby

residential area

3 Dust concentration

4 Solid waste and site cleaning after

construction

5 Conflict between workers and local

residents

6 Disease spreading

7 Hygiene condition and safety for workers

8 Local traffic interruption

9 Road damage

10 Safety measure application

11 Material management

12 Remained soil and rock management

13 Evidences about loss to biodiversity (if

any)

14 Evidences about loss to cultural and

43

No. Parameter

Assessment of

comments by

supervising

consultant and

community

Comment/

Recommenda

tion

historical sites

15 Other environmental issues (if any)

….

Operation phase

16 Transmission line lobby maintenance

17 1. Health and safety for operation

workers and local residents

44

ANNEX 3: Report template for monitoring of EMP implementation

(Used for reports by contractor)

Project name:

Project location:

Contractor name:

Initial or monthly report:

Date of report:

No. Impact Mitigation

measure taken Comment

Construction phase

1 Surface water pollution

2 Noise and vibration level

3 Soil erosion

4 Air pollution

5 Impacts on agriculture land due to

temporary land acquisition

6 Local traffic interruptions

7 Existing road damage

8 Solid waste from excavation

9 Remained soil management

10 Environmental impacts by workers

11 Conflict between workers and local

residents

12 Disease spreading between workers

and local residents

13 Health and safety

14 …..

Reported by :

Title :

Address :

Telephone

45

ANNEX 4 ENVIRONMENTAL LICENCE

------------

46

ANNEX 5

-------------

MINUTES OF THE COMMUNITY CONSULTATION

47

ANNEX 6

--------------------

SUMMERY OF MEETING PEOPLE

No Location Time Women/

People

Summery of idea’s

people

Summery of idea’s

contractor

1 Venue of Hoa

Phongcommune

people’s

committee, My

Hao district

16/05/2011 3/18 - Supporting the

construction of

common purpose of

social

- Concerned about

the time of

construction and

method of

compensation for

crops to farmers.

- There wants to be

construction

contractors and

investors

employers at the

local school to

create additional

income for people

in the construction

process.

- Thanks for the

support of the local

population relative

to the project.

- The compensation

of crops affected

people will be

calculated with

love and

rationality.

- Will encourage

construction

contractors use

unskilled workers

locally.

2 Venue of Cam

Xa commune

people’s

committee, My

Hao district My

Hao

17/05/2011 5/18 - Agree with the

construction of 110

kV lines.

- Have a little doubt to

the influence of

electromagnetic

field lines to

people's health.

- Construction

contractors,

regardless of local

practices in the

construction process

to avoid conflicts

between workers

with local people

easy to lead to

unfortunate

- Thanks for the

support of the local

population relative

to the project.

- Design of 110 kV

transmission line

route followed the

standards of the

state power grid

safety standards

including, but

allows the

magnetic field.

Thus the effects of

electromagnetic

fields to citizens is

very small, no

harm to health.

48

No Location Time Women/

People

Summery of idea’s

people

Summery of idea’s

contractor

consequences. - It will be noted

contractor

relationship in

communicating

with local people.

Respect the

customs and

practices of local

people as well as

compliance with

law.

3 Venue of Nhan

Hoa commune

people’s

committee, My

Hao district

18/05/2011 2/18 - Supporting the

construction.

- After the work is

completed and put

into use, the rice

and subsidiary

crops in the area

near the poles are

dangerous to the life

of the people do

not?

- In each village

commune has a

garbage collection

site, the proposal is

waste arising from

the need put to

work right where it

was prescribed.

- During construction,

if damaged roads,

ditches, culverts

must refund to the

original local

- Thanks for the

support of the local

population relative

to the project.

- Apart from the land

for planting

permanent

recovery pole,

people can still

pick normally

implanted in the

soil around the

pole, there is no

danger threatening

the lives of the

people.

- It prompted the

construction units

to the correct

collection places of

local regulations.

In the course of

construction if

damage to the

transportation

works as well as

irrigation repairs

will commit

according to the

original state.

4 Venue of

Duong Quang

commune

19/05/2011 3/18 Supporting the

construction.

- Thanks for the

support of the local

population relative

49

No Location Time Women/

People

Summery of idea’s

people

Summery of idea’s

contractor

people’s

committee, My

Hao district My

Hao

- Very welcome

design unit was

designed to avoid

lines of the village

temple.

- Need to perform

design and

construction lines in

accordance with

safety standard grid.

Ensure network for

people.

- Need a plan to

minimize

construction impact

crop most of her

children primarily

because lines go on

the field?

to the project.

- The design lines are

the investors in

accordance with

approved technical

standards and

safety standards of

the grid.

Construction

process the

investor will be

closely monitored

to ensure

construction

according to the

approved design.

- Time of

construction as

well as

construction

methods will be

calculated to

minimize the

impact on people's

crops. If you have

calculated the

impact will be

compensated for

reasonable people.

50

51

LIST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS

(Cam Xa Commune)

Full name Address Signature

1. Pham Thi The– Vice Chairman Ward

2. Dinh Van Phuong – Personnel land

3. Le Thi Thai – Vice Chairman women

4. Ngo Duy Hoang – Chairman of the elderly

5. Dang Thanh Nghe- Chairman of the Veterans

6. Nguyen Thanh Tam– Fatherland Front Chairman

7. Dao Manh Hung– Chairman of the People’s Council

8. Le Thi Minh Khanh– Youth Secretary

9. Dinh Xuan Thuy – Chairman of the farmers...

10. Nguyen Hong Quan– Personnel land

11. Hoang Van Thuy– Vice Youth Secretary

12. Chu Sy Binh– Deputy director of consulting unit

13. Le Thanh Son– Chairman of the project design.

14. Nguyen Xuan Huan– Household is affected

15. Tran Thi Ngung – Household is affected

16. Do Thi Tan – Household is affected

17. Dang Van Quy – Household is affected

18. Nguyen Van Luong – Household is affected

52

53

LIST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS

(Hoa Phong Commune)

Full name Address Signature

1. Vu Van Hoa- Vice Chairman of the CPC

2. Tran Quy Huyen – Personnel land

3. Pham Thi Dung– Chairman of the commune Women

4. Hoang Van An – Chairman of the elderly

5. Bui Van Nghiep - Chairman of the Veterans

6. Nguyen Xuan Huan – Fatherland Front Chairman

7. Do Thi Tan– Chairman of the People’s Council

8. Tran Thi Nhung– Youth Secretary

9. Vu Van Thuan– Chairman of the farmers..

10. Nguyen Hong Quang– Personnel land

11. Nguyen Van Thuy– Vice Youth Secretary

12. Chu Sy Binh– Deputy director of consulting unit

13. Le Thanh Son– Chairman of the project design.

14. Dang Dinh Khu– Household is affected

15. Dinh Van Phuong – Household is affected

16. Dang Dinh Vinh – Household is affected

17. Nguyen Hong Vi– Household is affected

18. Trần Văn Nhan– Household is affected

54

55

LIST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS

(Nhan Hoa Commune)

Full name Address Signature

1. Nguyen Ba Nam- Chairman of the CPC

2. Nguyen Thanh Trung – Personnel land

3. Le Xuan Thuy – Vice Chairman women

4. Ngo Duy Hoang – Chairman of the elderly

5. Bui Xuan Trung - Chairman of the Veterans

6. Trinh Van Bao – Fatherland Front Chairman

7. Nguyen Trung Kien – Chairman of the People's Council

8. Le Thi Anh – Youth Secretary

9. Dinh Xuan Chung – Chairman of the farmers...

10. Nguyen Ba Hung – Personnel land

11. Hoang Trung Kien – Vice Youth Secretary

12. Chu Sy Binh– Deputy director of consulting unit

13. Le Thanh Son– Chairman of the project design.

14. Vu Van Thuan – Household is affected

15. Bui Van Nghiep – Household is affected

16. Cao Van Khoi – Household is affected

17. Dinh Van Toi – Household is affected

18. Hoàng Văn Ân– Household is affected

56

LI

57

ST OF PARTICIPATING COMMUNITY CONSULTATION SESSIONS

(Duong Quang Commune)

Full name Address Signature

1. Vu Dinh Huan - Chairman of the CPC

2. Nguyen Huu Phuoc – Personnel land

3. Le Thi Nhien – Vice Chairman women

4. Ngo Van Dinh – Chairman of the elderly

5. Bui Cong Son - Chairman of the Veterans

6. Nguyen Van Than – Fatherland Front Chairman

7. Dao Manh Thang – Chairman of the People's Council

8. Le Thi Thuong – Youth Secretary

9. Dao Le Ngoc – Chairman of the farmers...

10. Nguyen Ba Quang – Personnel land.

11. Hoang Xuan Thuy – Vice Youth Secretary

12. Chu Sy Binh– Deputy director of consulting unit

13. Le Thanh Son– Chairman of the project design.

14. Trieu Van Uy – Household is affected

15. Bui Thi Lai – Household is affected

16. Tran Quy Huyen – Household is affected

17. Nguyen Huu Huynh – Household is affected

18. Nguyen Dang Phuc – Household is affected

58

ANNEX 7

--------------------

MAP OF THE PROJECT AREA

59

60