Upload
charlene-reeves
View
221
Download
0
Embed Size (px)
DESCRIPTION
Slide 31/16/2015 Electricity | Natural Gas | Water | Wastewater Whey is a by-product of cottage cheese production A Dairy approached Colorado Springs Utilities to say they would find a way to dispose of whey to avoid BOD surcharge Utilities analyzed the whey – thought to be a good source of carbon JDPWRRF was limited on carbon for its biological treatment processes Plant effluent pH was too low – had to add sodium hydroxide to raise effluent pH - $100K per year Adding Whey for Denitrification Background
Citation preview
Electricity | Natural Gas | Water | Wastewater
Adding Whey for Denitrification
Dale Adams, P.EManaging Engineer, Colorado Springs Utilities
September 8, 2015
Slide 21/16/2015 Electricity | Natural Gas | Water | Wastewater
BackgroundNitrogen RemovalPhosphorous RemovalBenchtop fermentation of wheyFull scale designProblems with start-up
Adding Whey for Denitrification
Agenda
Slide 31/16/2015 Electricity | Natural Gas | Water | Wastewater
• Whey is a by-product of cottage cheese production• A Dairy approached Colorado Springs Utilities to say they
would find a way to dispose of whey to avoid BOD surcharge
• Utilities analyzed the whey – thought to be a good source of carbon
• JDPWRRF was limited on carbon for its biological treatment processes
• Plant effluent pH was too low – had to add sodium hydroxide to raise effluent pH - $100K per year
Adding Whey for Denitrification
Background
Slide 41/16/2015 Electricity | Natural Gas | Water | Wastewater
• Temporary tanks were installed in 2009 and the dairy trucked cottage cheese whey to fill the tanks
• During the pilot project whey was dosed to the inlet of the primary sedimentation tanks
• As winter approached, the decision was made to move the whey operation into a spare grit tank to keep the whey from freezing and use the grit tank pump to dose the whey
• This allowed a larger inventory to be maintained and some fermentation occurred
Adding Whey for Denitrification
Background
Slide 51/16/2015 Electricity | Natural Gas | Water | Wastewater
• Ammonia conversion to nitrogen gas is a multi-step biologically driven process
• One set of bacteria (nitrifiers) takes ammonia to nitrite then to nitrate under aerobic conditions (lots of air is blown into the basins to give the bacteria oxygen)
• Another set of bacteria (denitrifiers) take nitrate to nitrite under anoxic conditions (very low oxygen) and then to nitrogen gas which goes to the atmosphere; requires CARBON for this step
• The conversion of nitrate to nitrogen gas adds alkalinity back into the wastewater – raising the plant’s effluent pH
Adding Whey for Denitrification
Nitrogen Removal
Slide 61/16/2015 Electricity | Natural Gas | Water | Wastewater
Adding Whey for Denitrification
0
2
4
6
8
10
12
14
16
07/20/2009 08/09/2009 08/29/2009 09/18/2009 10/08/2009 10/28/2009 11/17/2009 12/07/2009 12/27/2009 01/16/2010
ASE
Nitr
ate
(mg/
L)
Date
JDPWRF - Activated Sludge Effleunt (ASE) Nitrate Concentrations (mg/L)
AS Effluent Nitrate (mg/L)
Whey Addition
Aged Whey Ef fect
Slide 71/16/2015 Electricity | Natural Gas | Water | Wastewater
Adding Whey for Denitrification
20
30
40
50
60
70
80
90
100
110
120
07/20/2009 08/09/2009 08/29/2009 09/18/2009 10/08/2009 10/28/2009 11/17/2009 12/07/2009 12/27/2009 01/16/2010
Fina
l Eff
luen
t Alk
alin
ity (m
g/L)
Date
JDPWRF - Final Effluent Alkalinity (mg/L)
Final Effluent Alkalinity (mg/L)
Whey Addition
Slide 81/16/2015 Electricity | Natural Gas | Water | Wastewater
• Was not occurring at JDPWRRF very much prior to whey addition
• Biological P removal requires several things:• First an anaerobic zone is needed (no oxygen)• Second, volatile fatty acids need to be present• Under these conditions bacteria dump phosphorous and store
the VFA as energy• Under subsequent aerobic conditions, bacteria take up twice as
much phosphorous
Adding Whey for Denitrification
Phosphorus Removal
Slide 91/16/2015 Electricity | Natural Gas | Water | Wastewater
Adding Whey for Denitrification
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
07/20/2009 08/09/2009 08/29/2009 09/18/2009 10/08/2009 10/28/2009 11/17/2009 12/07/2009 12/27/2009 01/16/2010
Fina
l Eff
luen
t Ort
ho-p
hosp
hate
(mg/
L)
Date
JDPWRF - Final Effluent Ortho-phosphate Concentrations (mg/L)
Final Effluent Ortho-phosphate (mg/L)
Whey Addition
Aged Whey Ef fect
Slide 101/16/2015 Electricity | Natural Gas | Water | Wastewater
• Set up a reactor• Fed it fresh whey at a rate that controlled the hydraulic
residence time• Temperature was maintained at 94 F – the temp that we
receive cottage cheese whey from the dairy• pH was maintained at 5.7-6.0• VFAs were analyzed to see what was happening with
fermentation
Adding Whey for Denitrification
Benchtop Fermentation Experiments
Slide 111/16/2015 Electricity | Natural Gas | Water | Wastewater
Adding Whey for Denitrification
Slide 121/16/2015 Electricity | Natural Gas | Water | Wastewater
• Adding Whey for Denitrification
Slide 131/16/2015 Electricity | Natural Gas | Water | Wastewater
• Whey is very a very dilute source of carbon
Adding Whey for Denitrification
Design of Full-scale Carbon Facilities
Slide 141/16/2015 Electricity | Natural Gas | Water | Wastewater
• Dairy may not stay in the cottage cheese business • Need to design for flexibility• Tanks were designed to handle whey, primary sludge,
and acetic acid (could not make them compatible for methanol)
Adding Whey for Denitrification
Design of Full-scale Carbon Facilities
Slide 151/16/2015 Electricity | Natural Gas | Water | Wastewater
Design for Handling Whey
• Two tanks, each 35,000 gallons
• Telescoping valves for scum removal
• Mixer in main chamber under fermentation mode
• Connection from tank headspace to odor control ductwork in existing PSTs
• Special coatings systems to withstand a variety of chemical action
• Waterproofing membrane on outside
Slide 161/16/2015
Process Schematic
Mixers
Future Mixers
Future PS Screens
pH Control Pumps
Feed Pumps
Tank Drain/Future PS Recirc. Pumps Pumps
Telescoping Valves
Control Valves and Flow Meters
Slide 171/16/2015 Electricity | Natural Gas | Water | Wastewater
Primary sludge fermentation
• Up to two more tanks, each 35,000 gallons
• Combination submersible tank drain/future PS recirculation pumps to be used
• Additional mixers will be installed
• FRP baffles will be installed
Slide 181/16/2015 Electricity | Natural Gas | Water | Wastewater
Start-up Problems
• Started up the whey tanks with pH control set at 5• Shortly after start-up ground settlement broke the
feed piping – 20 foot deep excavation and repair was completed
• After the repair bio-P and nitrogen removal have not responded like we saw during the pilot project
• The dose location is different than during the pilot project
• We have not had time yet to do a deep dive into why the system is not performing as expected