East Hampton Bridge Replacement

Embed Size (px)

Citation preview

  • 8/16/2019 East Hampton Bridge Replacement

    1/35

    Public Information Meeting 

    State Project No. 41-118Replacement of

    Bridge No. 02018CT Route 66 (East High Street) over

    Pocotopaug Creek

    East Hampton, Connecticut

    Thursday, May 19, 2016 at 7:00 pmMeeting Room of

    the East Hampton Town Hall20 East High Street

    East Hampton, Connecticut

  • 8/16/2019 East Hampton Bridge Replacement

    2/35

    Project Location MapN

  • 8/16/2019 East Hampton Bridge Replacement

    3/35

    Introductions

    •Connecticut Department of Transportation–Theodore Nezames, Manager of Bridges

    –Rabih Barakat, Transportation Principal Engineer

    –Andrew Cardinali, Transportation Supervising Engineer

    –Dobieslawa Kania, Transportation Project Engineer–Michelle Miller, Project Coordinator

    •CME Associates, Inc.–Donald Wurst, Senior Project Manager

    –Thomas Lopata, Project Engineer

  • 8/16/2019 East Hampton Bridge Replacement

    4/35

    Department’s Role 

    • Systematically inspect bridges for deficienciesand schedule the rehabilitation of structures

    • Oversee the development of technical drawingsand bid documents on projects

    • Administration and inspection during construction 

  • 8/16/2019 East Hampton Bridge Replacement

    5/35

    Project Needs and Goals

    • Maintain/provide a safe crossing of PocotopaugCreek for vehicles traveling on CT Route 66

    • Remove deteriorated elements from service byrepair or replacement

    • Minimize disturbance for the traveling public

    during construction

    • Improve roadway ride-ability for traveling public

  • 8/16/2019 East Hampton Bridge Replacement

    6/35

    Project Overview

    • Project is in preliminary design stage

    – We are looking for your input

    • Full replacement of bridge to remove deterioratedelements from service

    • Widening of the bridge to the north by 5.5’ to

    maintain two lanes of traffic across the bridge forthe majority of construction and always at leastone lane. The existing width of lanes and southsidewalk will remain unchanged, both shoulderswill be widened to 4’. 

  • 8/16/2019 East Hampton Bridge Replacement

    7/35

    CT Route 66 Over Pocotopaug Creek

    • Built in 1913 and widened in 1925• Original 1913 section consists of concrete slab with

    embedded steel beams. Newer 1925 section is aconventional reinforced concrete slab.

    • Substructure consists of stone masonry abutments behind

    concrete scour walls flanked by concrete wingwalls

  • 8/16/2019 East Hampton Bridge Replacement

    8/35

    Existing Geometry

    • Single span, total bridge length of 11’  

    • Bridge width = 33.7’ (curb-to-curb), 43.8’ (out-to-out)

    • Carries a 16’ EB lane, 11’ WB lane, 3’ wide north shoulderand a 3’ wide south shoulder 

    Existing Conditions

    • Deck: “5” Fair 

    • Superstructure: “5” Fair • Substructure: “4” Poor 

    • Deck Geometry: “4” Poor 

    • Structure Evaluation: “4” Poor 

    • Average Daily Traffic: 11,300 Vehicles

    Bridge No. 02018

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    9/35

     

    CT Route 66 Over Pocotopaug Creek

     Approach Looking West

  • 8/16/2019 East Hampton Bridge Replacement

    10/35

    CT Route 66 Over Pocotopaug Creek

     Approach Looking East

  • 8/16/2019 East Hampton Bridge Replacement

    11/35

     

    CT Route 66 Over Pocotopaug Creek

    Existing sidewalk at bridge looking west and east

  • 8/16/2019 East Hampton Bridge Replacement

    12/35

     

    CT Route 66 Over Pocotopaug Creek

    Looking upstream and downstream at inlet

  • 8/16/2019 East Hampton Bridge Replacement

    13/35

    CT Route 66 Over Pocotopaug Creek

    Looking upstream and downstream under bridge

  • 8/16/2019 East Hampton Bridge Replacement

    14/35

    CT Route 66 Over Pocotopaug Creek

    Looking upstream and downstream at outlet

  • 8/16/2019 East Hampton Bridge Replacement

    15/35

    CT Route 66 Over Pocotopaug Creek

    Existing drainage outfalls at outlet

  • 8/16/2019 East Hampton Bridge Replacement

    16/35

    Proposed Replacement Measures:

    • Full replacement using 11’ wide x 6’ high precast concrete boxculvert, with cast-in-place concrete wingwalls, cutoff walls, andreturn walls

    • Curb-to-curb width of 40’ -6”, consisting of a 16’ -0” eastbound laneand an 11’ -0” westbound lane, with a 4’ -0” shoulder on the southside, and a 9’ -6” shoulder on the north side. 

    • Out-to-out width of 50’ -6”, with a 7’ -6” sidewalk and brick accentstrip on the south side. The proposed 9’ -6” shoulder on the northside is wide enough to accommodate a sidewalk in the future.

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    17/35

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    18/35

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    19/35

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    20/35

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    21/35

    CT Route 66 Over Pocotopaug Creek

  • 8/16/2019 East Hampton Bridge Replacement

    22/35

  • 8/16/2019 East Hampton Bridge Replacement

    23/35

    Traffic Impacts

    • Traffic on Route 66 will be maintained at alltimes

    • One-way alternating traffic pattern requiredfor 55 hour weekend period (Stage 3)

    • Pedestrian movements allowed throughout allstages of construction

    • Access to abutting driveways to be limited

    • Eastern driveway (to Subway plaza) adjacent

    to bridge, to be closed for majority ofconstruction

  • 8/16/2019 East Hampton Bridge Replacement

    24/35

    Right-of-Way Impacts

    Anticipated Impacts to Private Properties:

    • Construction Easement and possible Right toMaintain MBR for 36, 40, and 31 E High Street

    (American Distilling)• Eastern driveway (to Subway plaza) adjacent

    to bridge, to be closed for majority ofconstruction

  • 8/16/2019 East Hampton Bridge Replacement

    25/35

    Department of TransportationDivision of Rights of Way

    (ROW)

    Michelle MillerProject Coordinator

    2800 Berlin TurnpikeP.O. Box 317546

    Newington, CT 06131-7546

  • 8/16/2019 East Hampton Bridge Replacement

    26/35

    Function

    • Acquire all property/property rights necessary fortransportation projects.

  • 8/16/2019 East Hampton Bridge Replacement

    27/35

    Statutory References

    • State of Connecticut

    C.G.S. Sections 13a-73 & 13a-98e 

    • Federal

    Uniform Relocation Assistance and Real Properties

    Acquisition Act of 1970, as amended.

  • 8/16/2019 East Hampton Bridge Replacement

    28/35

    Property Impacts

    • Total Acquisitions• Partial Acquisitions

    • Easements

    • Construction Easements

    • Rights

    * Note: Specific impacts are subject to change as the design

    progresses.

  • 8/16/2019 East Hampton Bridge Replacement

    29/35

    ROW Acquisition Process

    • Letter of Intent to Acquire

    • Valuation

    • Offer of JustCompensation

    • Negotiation

    • Acquisition• Agreement

    • Eminent Domain/Condemnation» 6 month appeal period

  • 8/16/2019 East Hampton Bridge Replacement

    30/35

    Timing for Acquisitions

    • All property rights must be acquired bythe project advertising date.

    • Current Advertising Date: 8/16/2017

  • 8/16/2019 East Hampton Bridge Replacement

    31/35

    Project Cost

    • Construction cost for this project is currently

    estimated at approximately $1,200,000

    • The replacement of this bridge will be

    undertaken using 20% State and 80% FederalFunds under the “National Highway

    Performance Program”  

  • 8/16/2019 East Hampton Bridge Replacement

    32/35

    Project Schedule

    • Construction Start: Spring of 2018

    • Completion: Fall of 2018

    • The schedule is preliminary and is subject to

    change

  • 8/16/2019 East Hampton Bridge Replacement

    33/35

    Contact Information

    Thank You

    Questions and Comments

    Andrew Cardinali – Supervising EngineerConnecticut DOT

    2800 Berlin Turnpike

    P.O. Box 317546

    Newington, CT 06131

    Email: [email protected]

    Phone: 860-594-3315

  • 8/16/2019 East Hampton Bridge Replacement

    34/35

    Detour Options

  • 8/16/2019 East Hampton Bridge Replacement

    35/35