273
1. Introduction 1.1. Project Background The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project is a new 342 km double track railway line starting from the city of Harbin, running through Bing County, Fangzheng County, Yilan County, and ending at the city of Jiasmusi. The Project is located in Heilongjiang Province, and the south of the Songhua River, in the northeast China (See Figure 1-1). The total investment of the Project is RMB 38.66 Billion Yuan, including a World Bank loan of USD 300 million. The construction period is expected to last 4 years, commencing in July 2010. Commissioning of the line is proposed by June 2014. HaJia Line, as a Dedicated Passenger Line (DPL) for inter-city communications and an important part of the fast passenger transportation network in northeast of China will extend the Harbin- Dalian dedicated passenger Line to the the northeastern area of Heilongjiang Province, and will be the key line for the transportation system in Heilongjiang Province to go beyond. The project will bring together more closely than before Harbin , Jiamusi and Tongjiang, Shuangyashan, Hegang, Yinchun among which there exists a busy mobility of people potentially demanding high on passenger transportation. The completion of the project will make it possible for the passenger line and cargo train line between Harbin and Jiamusi to be separated, and will extend the the line Harbin- Dalian passenger line to the northeast of Heilongjiang Province,It willl also strengthen the skeleton of the railway network of the northeastern part of China and optimize the express passenger transportation network of the northeast. As another express railway to divert the passenger train and cago train, the pjoject will relieve the pressure of the transportation between Harbin and Jiamusi and will play an important role in the smooth execution of E2646 V1

E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

1. Introduction

1.1. Project Background

The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project is a new 342 km double track railway line starting from the city of Harbin, running through Bing County, Fangzheng County, Yilan County, and ending at the city of Jiasmusi. The Project is located in Heilongjiang Province, and the south of the Songhua River, in the northeast China (See Figure 1-1). The total investment of the Project is RMB 38.66 Billion Yuan, including a World Bank loan of USD 300 million. The construction period is expected to last 4 years, commencing in July 2010. Commissioning of the line is proposed by June 2014.

HaJia Line, as a Dedicated Passenger Line (DPL) for inter-city communications and an important part of the fast passenger transportation network in northeast of China will extend the Harbin-Dalian dedicated passenger Line to the the northeastern area of Heilongjiang Province, and will be the key line for the transportation system in Heilongjiang Province to go beyond. The project will bring together more closely than before Harbin , Jiamusi and Tongjiang, Shuangyashan, Hegang, Yinchun among which there exists a busy mobility of people potentially demanding high on passenger transportation. The completion of the project will make it possible for the passenger line and cargo train line between Harbin and Jiamusi to be separated, and will extend the the line Harbin-Dalian passenger line to the northeast of Heilongjiang Province,It willl also strengthen the skeleton of the railway network of the northeastern part of China and optimize the express passenger transportation network of the northeast. As another express railway to divert the passenger train and cago train, the pjoject will relieve the pressure of the transportation between Harbin and Jiamusi and will play an important role in the smooth execution of the snational strategy of “revitalize the old industrial bas of Northeastern Provinces” . In addition, the execution of the project will also play an important role in ensuring the good transportation as a rear-area for the trading ports between China an Russia , in accelerating the development of the relevant trading ports, in developing the economic division and cooperation between China and Russia and the economic win-win and promoting the regional economic development and flourishing the frontiers of the northeast of China.

1.2. Environmental Asessment (EA) Preparation

According to World Bank OP4.01 Environmental Assessment, the proposed project is classified as Category A, dur to the scale of potential environmental and social impacts. As a result, the Bank required a full environmental impact assessment report. Chinese environmental impact assessment laws and regulations also required preparation of a full enviornmental impact assessment report.

E2646V1

Page 2: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

MOR retained China Railway Third Survey and Desing Institute (TSDI) Co., Ltd. for EIA preparation. The TSDI has Class A environmental impact assessment accreditation from Ministry of Environmental Protection (MEP). The EIA report was prepared in accordance with relevant provisions specified in China EIA laws / regulations and technical guidelines, as well as consideration of World Bank

Page 3: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 1-1 Harbin-Jiamusi Dedicated Passenger Line (HaJia Line)

Page 4: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

safeguard policies.

The final English EA documents submitted to the World Bank inlcude:

Enviornmental Impact Assessment Report (EIA) Environmental Management Plan (EMP) EA Executive Summary

This report is the English version of the Environmental Impact Assessment, which includes a sumary of the main text and the following Annexes:

Annex 1 List of Main Applicable Laws and Regulations Annex 2 Screening of Environmental Objects Annex 3 Ecological Baseline Survey Annex 4 Baseline Noise Monitoring Annex 5 Noise Impact Prediction Table Annex 6 Mitigation Measure for Noise Control Annex 7 Baseline Vibration Monitoring Annex 8 Vibration Impact Predication Table Annex 9 Mitigation Measures for Vibration Control

The Chinse EIA report was approved by the Ministry of Environmental Protection on Nov XX, 2010.

Page 5: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

2. Legal and Regulatory Framewok

2.1 Environmental Assessment Purpose and Principles

The purpose of the environmental impact assessment is as follows.

1. Through the survey and supervision of the existing conditions of the environment sensitive items and environment, it is expected to have an understanding of the existing environmental conditions of the region. And with strategy of sustainable development as the guide line to carry out the policy “Prevention as a major concern and protection as the priority” , “Development and protection as equally important aspect” and with environmental evaluation as a guide in designing , construction and environmental protection and to forecast the impact of the project on the environment during its construction and operation. And based on the forecast results, the controlling measures presented in the design document can be proved, which is imperative. n the light of the principle characterized by “letting the new measures to substitute the old, it aimed to forward corresponding measures and proposals in order to reduce and control the emission of pollutants and to reach the target of keeping total amount of emission of pollutants within the controlled limit of the region and to proved a scientific ground for the local environment protection department to control and plan the environment.

2. To carry out the principle of “people oriented” by involving the public in the project and residents in the proving of the project, so that the decision of the project will be more democratic , scientific, to avoid the potential dangers created by the impact of the project on the environment in the future. To guide the public to the management and supervision of the environment protection during the construction and operation of the project. And at the same time to publicize the national laws, statutes and policies on environmental protection.

3. To provide a ground for environmental protection and engineering design and environmental management of the project from the perspective of environmental protection, together with the analysis of the economic benefits and too prove the feasibility of the project.

The principle of the environmental assessment - The assessment is based on the national laws, statutes, and relevant documents and with the environmental evaluation guiding principle and the technological criteria for railway environment as the guiding principle. The assessment is done in the light of the characteristics of the planned railway and with sensitive problems involved in ecological damage, noise ,and vibration as the evaluating principle. During the assessment full use is made of the existing data with the necessary supplementary elements such as survey, monitoring, and analogical monitoring of the existing conditions.The assessment is done in the light of the engineering design and with full consideration of different assessment elements for different section of the planned line. And finally based on the assessment results a control measures and suggestions not only feasible in technology but also rational in economy are put forward.

Page 6: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

2.2 National Laws and Regulations

The preparation of the EIA for the proposed project fully complies wit hthe provision of relevant Chinese natonal laws and regulations for construction projects. A list of relevent laws, regulations, technical guidelines and relvant document is presented in Annex 1.

Table 2-1 summarizes some key provisions of applicable laws and regulations and project compliance relative to the preparation of environmental impact assessment and project design.

Page 7: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 2-1 Key Environmental Laws and Regulations and Project Compliance

Laws and Regulations Key Applicable Provisions Project Compliance

Environmental Protection Law “Construction projects that would cause environmental pollution must follow the provisions of relevant environmental protection rules and regulations. The environmental impact assessment document must assess the pollution the project is likely to produce and its impact on the environment, and stipulate the preventive and mitigation measures. The EA documents shall, after initial examination by the authorities in charge of the construction project, be submitted to the environmental protection administration authorities for approval following specified procedure.”

“Pollution mitigation measures of a construction project must be designed, built and commissioned at the same time with the main part of the project. No permission shall be given for a construction project to be commissioned or used, until its installations for the prevention and control of pollution are examined and considered up to the standard by the relevant environmental protection authority which had originally reviewed and approved the environmental impact assessment documents.

EIA is prepared according to relevant laws/regulations and technical guidelines.

Mitigation measures are developed in an EMP, incorporated into project design, and are to be implemented and supervised during construction.

Final acceptance inspection will be carried out before commissioning.

Environmental Impact Assessment Law

“The State adopts a categorized management approach for environmental impact assessment of construction projects according to the extent of environmental impact of construction projects ……The Project proponent shall prepare Environmental Impact Assessment Report, or Environmental Impact Assessment Form, or Environmental Impact Registration Form according to the follow criteria:

1) An Environmental Impact Assessment Report is required for a construction project that may cause major impact on the environment, giving comprehensive and detailed evaluation of the pollution generated and environmental impact caused by the construction project;

“Catalog for the Categorized Environmental Impact Assessment Management for Construction Projects shall be compiled and published by the environmental protection administration under the State Council.”

“For construction projects that involve water conservation and soil erosion control, a Water and Soil Conservation Plan must be prepared and approved by relevant water resource authorities.”

A full EIA report is prepared, and approved by Ministry of Environmental Protection.

A dedicated Water and Soil Conservation Plan is developed and approved by water resources authorities.

Notice on Strengthening EIA Management for Construction Projects Funded by Loans from International Financial Institutions

“The construction project must abide by environmental protection laws, regulations and standards of China, and subject to EIA policies. With precondition of compliance with China EIA provisions, consideration should be given to technical requirements of the IFI.”

EIA and EMP are prepared in compliance with World Bank OP4.01 and in consideration of World Bank Safeguards.

Environmental Protection Management Regulations for Transport Projects

“All environmental protection facilities in transport projects must be simultaneously designed, constructed and put into operation with the main body project…After project completion, the project proponent shall submit application for acceptance inspection to the environmental protection authority which had originally reviewed and approved the environmental impact

Mitigation measures are developed in the EMP and incorporated into project design, and are to be implemented and supervised during

Page 8: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Laws and Regulations Key Applicable Provisions Project Compliance

assessment documents.” construction. Final acceptance inspection will be

carried out by MEP before commissioning.

Solid Waste Pollution Prevention and Control Law

“It is forbidden for any units or individuals to dump or pile solid waste into rivers, lakes, canals, channels, reservoirs and flood lands and bank slope below the highest water level and other places where laws and regulations stipulate to be forbidden to dump or pile solid waste.”

“The construction units shall timely remove the solid waste produced during the construction of the project and shall utilize or dispose of the solid waste in accordance with the requirement stipulated by the relevant administrative department in charge of environmental sanitation.”

A Water and Soil Conservation Plan is developed, and incorporated into EMP and contracts for implementation

Waste will be recycled or properly disposed of in preselected and approved disposal sites with a re-vegetation plan.

Water Pollution Prevention and Control Law

“It is forbidden to discharge or dump industry waste residues, urban refuse or other wastes into any water body…. It is forbidden to pile or deposit solid wastes and other pollutants on flood land and bank slopes below the highest water level of rivers, lakes, canals, irrigation channels and reservoirs”

“Domestic and drinking surface water sources protection zones shall be divided into Class 1 protection zone and Class 2 protection zone…. It is forbidden to construct or expand any projects that have noting to do with water supply facilities and protection of water sources within the Class 1 zone. It is forbidden to construct or expand projects that would discharge sewage into water bodies within the Class 2 zone.”

Mitigation measures regarding waste management are built into the EMP.

The alignment is carefully chosen to avoid drinking water resource protection areas.

Forestry Law “Construction project, survey and mining operations shall not occupy forest land or occupy as little forest land as possible. If forest land is to be occupied or acquired, project proponent shall submit a land use application to the forestry authority of the people's government of or above the county level, and, after examination and approval, pay forest restoration fees according to the standard stipulated by the state.”

The alignment is designed with tunnel-bridge-tunnel scheme to minimize occupation of forestry land.

Legal procedures will be followed for land acquisition and compensation for restoration.

Wildlife Protection Law “The State protects wildlife and its habitats. It is forbidden for any one to illegally hunt or destruct wildlife habitats.”

“If a construction project produces adverse effects on the environment for the survival of wildlife under special state or local protection, the construction unit shall submit a report on the environmental impact. The department of environmental protection shall, in examining and approving the report, seek the opinion of the department of wildlife administration at the same level.”

Alignment is carefully chosen to avoid protected natural habitats

Tunnel-bridge-tunnel scheme is adopted to minimize fragmentation impacts.

Potential impact is thoroughly addressed in the EIA, and necessary mitigation measures are developed in the EMP.

Wild Plants Protection Regulations

“The State protects wild plants and their habitats. All units and individuals shall be forbidden to illegally collect wild plants or damage the environment for their survival.”

“If a construction project may produce adverse effects on the environment for the survival of the wild plants under special state or local protection, the construction unit shall make an assessment on the effects in its submitted report on the environmental impact; ……”

Alignment is carefully chosen to avoid protected natural reserves.

Protected wild plants are identified and protection measures developed

Page 9: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Laws and Regulations Key Applicable Provisions Project Compliance

Nature Reserve Protection Regulations

“Nature reserves are classified into three zones, known as the Core Zone, Buffer Zone and Experimental Zone ….No unit or individual are allowed to enter the Core Zone, except those who have been approved.….”

“A certain amount of area at the periphery of the Core Zone can be designated as Buffer Zone where only scientific research and observation activities are allowed. The area at the periphery of the Buffer Zone is designated as Experimental Zone where scientific experiments, teaching training, visit and observation, tourism and taming and breeding rare and endangered wild animals and plants and other activities are allowed.”

“Production facilities shall not be constructed in the Core Zone and Buffer Zone of nature reserves….For projects to be constructed in Experimental Zone, the discharge of pollutants of projects shall not exceed the pollutant discharge standards stipulated by the state or the local government.”

Alignment is carefully chosen to avoid protected natural reserves

For un-avoidable reserves, alignment is arranged in Experimental Zone using tunnel scheme to minimize impact

Other necessary measures are developed in EMP

Scenic Area Management Regulations

“All the scenic spots and natural environment in the scenic area shall be protected strictly and shall not be damaged or changed at will. …All the construction inside the scenic area or its peripheral protection area shall be harmonious with the landscape…. Trees inside the scenic area and its peripheral protection area shall be cultivated and managed according to the planning regardless of its tenure rights and shall not be felled. ……It is forbidden to fell ancient and famous trees. ……”

Alignment is carefully chosen to avoid scenic areas as much as possible

For un-avoidable scenic areas, alignment is arranged to avoid main scenic spots

Greening plan and special design of stations are developed to be harmonious with the landscape

Water and Soil Conservation Law

“In the construction of a rai1way, highway or waterway project, the disturbance of vegetation shall be minimized; waste sand, rocks and earth thus created must be disposed of in an area specially designated for the purpose, and shall not be dumped out into any river, lake, reservoir or any ditch or canal other than the specially designated area; slope protection must be built or other land management measures adopted on hill-slopes within the frontage of the railway and highway; after the project is completed, trees must be planted and grass grown on the earth--fetching area, excavated land surface and the exposed land surface for the disposition of waste sand, rock and earth, in order to prevent soil erosion. ”

A Water and Soil Conservation Plan is developed, and incorporated into EMP and contracts for implementation

Urban Old and Famous Trees Management Method

“No units or individuals shall, for any reason or by any means, fell old and famous trees or transplant old and famous trees without approval….If for special need that the Class 2 old and famous trees should be transplanted, it should, after being examined and approved by the urban greening authorities, be submitted to the provincial construction authorities for approval; the transplanting of Class 1 ancient and famous trees should be examined by the provincial construction authorities and be submitted to the provincial government for approval….”

Alternative alignment is studied to avoid old and famous trees to the extent possible

Un-avoidable trees will be relocated following applicable legal procedures

Notice on Strengthening “Green Corridor Construction is a major part of national greening campaign, and its main Extensive greening plan is designed

Page 10: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Laws and Regulations Key Applicable Provisions Project Compliance

National Green Corridor Construction by State Council

objective is to build green belt along roads, railways, rivers/canals and embankment….”

“Green Corridor must be planned together with overall planning of roads, railways and water resources facilities, and be designed, implemented and finally accepted prior to commission at same time with main projects”

“By 2005, all expressways, 60% of existing railway lines….shall be greened. By 2010, all roads, railway lines, rivers/canals and embankment that have the possibility of greening shall be greened”

along the railway line following relevant technical guidelines

Cultural Property Law “For large scale infrastructure projects, project proponent shall submit application to provincial and municipal cultural property management authorities which will organize specialized institutes to conduct archeological survey and investigation within the project scope.”

“During project construction or agricultural activities, if cultural relic is found, one should immediately stop to protect the site, and report to local cultural property authorities. When a cultural authority receives such reporting, it shall, under normal situation, visit the site within 24 hours and provide decision within 7 days. The cultural property authority can report to local government to mobilize police department to protect the site. Chance find of important cultural relics shall be immediately reported to national cultural property administration which shall issue decision within 15 days since receipt of such reporting.”

Cultural property survey along the whole line has been conducted by licensed archeological institutes.

Alignment is fine-tuned to avoid existing cultural relics sites

Chance-find procedure will be strictly followed.

Notice on Strengthening Noise Pollution Control of Railway

“New railway project must be subject to EIA procedure. …In urban areas, interchange shall be adopted and the railway tracks shall be fully-fenced to eliminate horning noise impact during operation. …Mitigation measures shall be adopted to ensure compliance with Railway Border Noise Limit Standard.”

“Urban planning department shall, in accordance with Urban Regional Noise Standard, avoid planning of noise sensitive buildings such as schools, hospitals, residential areas, governmental or research institutes near the railway.”

Noise impact is thoroughly assessed following EIA technical guidelines

Noise mitigation measures (noise barriers, sound-insulation windows, seamless rail, noise damping system etc.) are designed to mitigate noise impact

Page 11: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

2.3 World Bank Safeguard Polices

The preparation of environmental impact assessment documents also follows the requirements of the World Bank’s safeguard policies. Ten World Bank safeguard policies were screened for the project. Of the ten policies, five are triggered: (1) OP4.01 Environmental Assessment; and (2) OP4.12 Involuntary Resettlement. The EIA documents have been prepared according to the requirements of these safeguard policies, which are summarized in Table 3-2.

Table 2-2: Applicable World Bank Safeguard Policies and Project Compliance

Safeguard Policies Actions

Environmental Assessment(OP/BP 4.01) Category A project. Full EIA and EMP are prepared.

Involuntary Resettlement (OP/BP 4.12) RAP is prepared.

2.4 Assessment Scope and Applicable Standards

The overall project scope considers the following:

The entire Harbin-Jiamusi Railway main line, 342 km in length, including new Jiamusi east terminal, 8 intermediate stations and renovation of existing Jiamusi station, and liaison lines affiliated to Harbin and Jiamusi terminal (Figure 3-4-1). Harbin Terminal is not included in the project.

Construction period: construction is expected to commence in July 2010 and complete in June 2014, with a total construction time of 4 years.

Operation period: from commencement of operation until 2020 for the near future, and 2030 for the far future.

2.4.1 Assessment Scope and Grade

The assessment scope of this EIA covers the main railway alignment, stations, auxiliary lines, traction sub-stations (which is for power supply purpose), borrow pits and disposal sites, access roads, construction/camp sites etc. The impacts addressed in the EIA include environmental impacts (e.g. ecology, water, air, noise, etc.) and social impact (e.g. traffic disturbance, restriction of access due to fencing, impact on local drainage/irrigation system, impact on local community life, induced impacts etc.)

The assessment scope and grade of each environmental factor is determined as shown below in Table 3-3, according to the relevant stipulations of Technical Guidelines for Environmental Impact Assessment of Railway Construction Projects (TB10502—93) and regional environmental features.

Page 12: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 2-3: Environmental Factors and Assessment Scope and Grade

Environmental factors

Assessment Grade Assessment Scope

Ecological environment

I

Area within 300m at the both sides of the center lines along the outer rails of the railway line.

Area within 30m at the both sides of the center line of the construction access road.

Area within 100m out of boundaries of temporary sites.

The boundary of Mayi Rive Wetland Nature Reserve is 9 km away from the alignment.

The alignment will cross Class II protection Zone of Yilan County Drinking Water Protection Area

Acoustic environment I

Sensitive objects within 200m at the both sides of the railway line.

Vibration I

Area within 60m from the center lines along the outer rails at the both sides of the railway line.

Electromagnetic frequency

N/A

Assessment scope for impact on televisions shall be within 80m from the center lines along the outer rails of the railway line

Assessment scope for impact on traction substations shall be within 50m from the boundary walls of the traction substations, and focus area for analysis of impact on GSMR base station shall be the area of 50m in radius from the antennas.

Water environment III

Wastewater discharge outlets at stations along the railway line

Discharge of waste water produced in construction of key works during the construction period

Assessment scope for source water production areas along the railway line shall be from bridge locations to downstream intakes

Atmospheric environmental III

Chimney emission outlet of new boiler in railway stations.

Area with 50m from the construction site.

Solid waste N/A Solid waste generated during construction stage.

Solid waste generated from railway operation.

2.4.2 Assessment Standards

Standards for the project environmental assessment are presented below in Table 3-4. The standards were established in response to the official reply from the environmental protection bureaus of Heilongjiang Province, the city of Harbin and Jiamusi to the Letter of Request for Verification of the

Page 13: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Environmental Standards Proposed for the New Harbin-Jiamusi Railway Line. These standards are based on general national standards as well as local regulations and planning.

Table 3-4 Applicable Standards for Environmental Assessment

Type Env. Factor Standard No. Standard Name Function Zone and Criteria Applicable Area/Subject

Envi

ronm

enta

l Qua

lity

Stan

dard

Aco

ustic

GB3096-2008Acoustic

Environment Quality Standard

Zone 2-daytime 60dBA,night time 50dBA

60m and beyond from the center lines of the outer rails.School and hospital within assessment scope

Zone 4-daytime 70dBA,night time 55dBA

30~60m from the center lines of the outer rails

Vib

ratio

n

GB10070-88Environmental

Vibration Standards for Urban Area

Daytime: 80dB;Night time: 80dB

Residential area, schools and hospitals etc. along the railway line.

Wat

er GB3838-2002Surface Water

Environment Quality Standard

Class III~V water body standards

Ashi River, Feiketu River, Mayi River and Mudanjiang River, etc.

Am

bien

t A

ir

GB3095-1996 Ambient Air Quality

Standard and its amendment

Class II Entire alignment

Dis

char

ge S

tand

ard

Noi

se

GB12525-90

Emission Standard and Measurement

Methods of Railway Noise on the

Boundary Alongside Railway Line

Daytime: Leq70 dBANighttime: Leq70 dBA

Place at 30m away from the center line along the outer rails

GB12523-2008GB12524-90

Noise Limits for Construction Site and

Measurement Methodology of

Noise on the Boundary of

Construction Site

Depending on the type of construction activities Construction sites

Was

tew

ater

GB8978-1996 《 Comprehensive Wastewater Discharge Standards》 Class III

Binxi Station, Fangzheng Station, Yilan Station, Jiamusi Station :discharge into urban sewer system

Class I Binzhou Station, Gaolimao Station, Geoleng Station, Dalianhe Station, Hongkeli Station, East Jiamusi Station: discharge into nearby waterbody

Page 14: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Type Env. Factor Standard No. Standard Name Function Zone and Criteria Applicable Area/Subject

Discharge from construction site will comply with receiving water body function.

Elec

trom

agne

tic GB8702-88

Regulations for Electromagnetic Radiation Protection

4kV/m0.1mT Be healthy to human body

/ CCIR Recommended Methodology

Signal-to-noise ratio not less than 35dB

Radio television reception for inhabitants

Ambient air GB13271-2001 Pollutants Emission

Standard for Boiler Zone 2, Time II Railway station

Page 15: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

3. Project Description and Engineering Analysis

3.1 Project description

The HaJia Line is designed to be a Dedicated Passenger Line (DPL) incorporated with inter-city function. It is an important portion of the Northeast China fast-speed railway network, an extension of the HaDa DPL to northeast Heilongjiang Province, and a backbone passenger line of of the province.

The total length is 342 km, with 5 km existing BinJiang line in Harbin city and 337 km new. The total investment of the entire project is RMB 38.66 Billion Yuan, including a World Bank loan of USD 300 million. The construction period is expected to last 4 years, commencing in July 2010. Commissioning of the line is proposed by June 2014.

Key project technical parameters are presented in Table 3-1 below.

Table 3-4: Key technical parameters of the Gui-Guang Line

Parameter Unit

Type Railway dedicated passenger line (DPL)Track DoubleDesign speed 250 km/hLength 342 kmMinimum curve radius 4000m, in difficult locations sharper curves shall be

toleratedMaximum grade 20 in 1000Distance in center line of two tracks 4.6 mTraction Electric Train type Electric Multiple Units Effective length of departure track 650m for freight and 650m for passenger trainsTrain operation control Automatic3.1.1 Project Contents and ScaleA description of key project works and land occupation is summarized in table 3-2

Table 3-5 Project Content and Scale

Works Unit Quantity

Length of line Kilometer of trunk line 342.057

Permanent land occupation hm2 1416.27

Temporary land occupation hm2 534.78

Page 16: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Stat

ion

Renovation station 1

New station 8

Relocation station 1

Subg

rade

Backfill 104m3 1437.24

Excavation 104m3 2674.54

Ancillary

facilities

Mortar rubble 104m3 246626

Civil grill m2 5028924

Brid

ge a

nd v

iadu

ct

Extra-long Bridge Linear meter/bridge 157506.23 /88

Long bridge Linear meter /bridge 15084.71/53

Medium bridge Linear meter /bridge 271.66/3

Box bridge M2/bridge 2391.84/4

Culvert Horizontal linear meter/bridge 10547.68/294

Highway overpass Square meter/bridge 38615.76/62Tunne

l Double-line tunnel Linear meter /bridge 14093/9

Traction substation / 8

House demolition and resettlment m2 906750

Newly built production houese m2 99969

Total investment estimate RMB100 million Yuan 386.64

3.1.2 Railway Alignment

The proposed Harbin-Jiamusi (HaJia hereafter) Railway Project is a new 342 km double track

railway line (including 5 km of existing Binjiang Line and newly built line 337 km)starting from

the city of Harbin, running through Bing County, Fangzheng County, Yilang County, and ending at

the city of Jiasmusi.

The land form of the project area is mainly alluvain plain, low mountains and rolling hills.

Between Harbin and Bin County the land form is mainly the alluvian plain of the Songhua River.

Between Bin County and Jiamus the land form is mainly rolling hills.

3.1.3 Subgrade Embankment

The length of embankment subgrade is 150 km, amounting to 44% of the total main line.

3.1.4 Stations

The HaJia Line will have 10 stations, including Harbin terminal (which is not included in the

project) in the west end, 8 intermediate stations and Jiamusi terminal in the east end. Between two

adjacent stations the average distance is 37.97km, the maximum is 58.507 km (between Shengli

and Fangzheng), and the minimum is 18.02km between Dalianhe and Yilan.

Page 17: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

In Jiamusi, the existing Jiamusi terminal will be upgraded to a dedicated passenger station; the

existing east Jiamusi station will be relocated, and functioned as an freight station.

3.1.5 Bridge Works

A total of 144 bridges/viaducts will be constructed along the whole railway main line, for a total

length of 172862 m, accounting for 51% of the total line length.

A total of 294 culverts/underpasses will be built, which means, not considering bridges/viaducts there will be 1.9 culverts per kilometer of the the rail line.

3.1.6 Tunnel Works

A total of 9 tunnels will be construced along the whole railway line, for a total length of 14km,

accounting for 4.2% of the total line length. The longest tunnel will be Houshishan Tunnel, with a

length of 4,902 meters.

3.1.7 Electrification WorksA new AT power supply system will be providd to the main line between Taiping Bridge (where the newly HaJia line connects existing BinJiang line) and Jiamusi. A total of 8 AT traction stations will be constructed.

Power will be sourced from the local grid under an electricity purchase agreement between HaJia DPL Company and local electrical grid companies. Each company will be responsible for constructing a transmission line to each railway traction substations prior to operations. They will also prepare environmental assessments of their transmission line in accorance with national EIA regulations and technical guilelines, and submitted to local environmental authorities for review and approval.

3.1.8 Aggregate, Spoil and Borrow MaterialsThe project will need to borrow 4.9 million m3earth and stone materials, which will be obtained under commercial agreements with local land resouce bureaus of Bin County, Fangzheng County, Yilan County and Jiamusi City. At preliminary design stage, 12 exisisting borrow pits have been identified.

The project will generate 17.2 million m3 of spoil materials, of which 1.2 million m3 of tops soils will be reused for revegeation. The remain 16 million m3 of spoils will be disposed of at 45 spoil sites that have been identified during design stage.

3.1.9 Temporary Construction WorksTemprorary works include material storage and processing plant, beam fabricating yard, mixing plants, access road, camp etc. Temporary works long the whole alignment are summarized in Table Table 3-3.

Table 3-6 Temporary Construction Works

Name of Tempoary Work Unit Quantity

Material storage and processing plant Nr. 4

Page 18: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Beam fabricating (storage) yard Nr. 10

Long rail storage base Nr. 2

Ballastless track slab prefabricating yard Nr. 3

Concrete mixing plant Nr. 31

Temporary transmission line km 163

Construction sites and camp Nr. 143

Temporary soil storage yard Hm2 71

Construction access road km 202

3.2 Engineering Analysis

The purpose of engineering analysis is to analyze the project environmental settings, and the type, nature, and scale of project activities. Based on the engineering analysis, scoping and screening of project environmental issues are conducted.

3.2.1 Scoping and screening of environmental issuesThe project will result in environmental impacts during construction stage and operation stage as well. During construction, the main environmental issues include disturbance to ecological environment along the alignment, noise, vibration, wastewater, dust, solid wastes; during operation stage, the negative impacts include noise, vibration, and wastes. Social disturbance such as land take and resettlement and community severance are also potentially significant.

Based on the nature of the environental and social issues, environmental settings and the sensitity, an screening matirx of environmental issues is developed, see Table 3-4

Table 3-7 Environmental Screening

Stag

e

Activities

Sign

ifica

nce

Ecological Environment Physic-Chemical Environment Social Economic Environment

land

form

Vege

tatio

n

Soil

cons

erva

tiirr

igat

ion

Sew

er

Surf

ace

wat

er

Aco

ustic

Vib

ratio

n

Elec

trom

agn

etic

Am

bien

t ai

r

Live

lihoo

d

Agr

icul

tur

Fore

stry

Loca

l ec

onom

yG

roun

d tra

ffic

Wat

erw

ay

traff

icTo

uris

m

land

scap

e

Significance Ⅰ Ⅰ Ⅰ Ⅱ Ⅱ Ⅱ Ⅰ Ⅰ Ⅰ Ⅲ Ⅰ Ⅰ Ⅰ Ⅱ Ⅱ Ⅱ

Con

stru

ctio

n St

age

Land take and resettle Ⅱ -S -S -S -M -M -M

Build access road / temp

worksⅡ -L -L -L -M -M -M -M -S -M -M -M -S

Material storage and

haulingⅡ -M -S -M -M +M -S -M

Subgrage earth stone

works

Ⅰ -L -L -L -M -M -M -M -M -M -M -M -S

Page 19: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Bridge / viaduct Ⅱ -M -M -M -M -M -M

Subgrade protection Ⅰ +M +L +S +S +M +M +M

House building Ⅲ +S -S -S

Greening and

reclaimationⅠ +L +L +L +S +S +S +M +M

Spoils disposal Ⅱ -M -M -M -S -S -S -S -S

Camp Ⅲ -S -S -S +S

Ope

ratio

n St

age Train

running Ⅰ -L -L -L -S +M

Station Ⅰ -M -M -M +L +L +LTrain

preparation Ⅲ -S -S -S -S

Domestic waste Ⅲ -S -S -S -S -S

Note: Two types of impacts are indicated in the matrix

1. Incremental impact: + positive impact, - negative impact, L High Impact, M Moderate Impact, S Low Impact, Blank No Impact

2. Combined/Cumulative impact: I Significant Impact, II Moderate Impact, III Low Impact

3.2.2 Ecological environmental impactsLand Occupation

Permanent land occupation of the project is caused by construction of subgrade, station/terminal,

bridge/viaduct, culvert, tunnel portal. The total permanent land occupation of the project amounts

to 1,416.27hm2. Permanent land occupation of the project will change functions of the original

land, of which arable land is 903.20 hm2(63.8% of the total), woodland is 419.85 hm2(29.65% of

the total). On the condition of satisfying technical criteria, bridge and viaduct scheme is

maximized to reduce permanent land occupation as much as possible.

Temporary Land occupation of the project is caused by borrow pit, disposal site, access road, and

other temporary works. The total temporary land occupation of the project amounts to 534.78hm2.

The porject construction activities, such as excavation and filling will cuase land occpation,

vegetation clearance, damages to soils of irrigation facilities, and has the potential to result in

degradation of soil conservation function and negative impacts to agricultural production in the

regions along the line.

Earth and Stone Works

Total earth and stone works of the project amount to 4,111×104m3 , of which filling is

1437×104m3,and excavation is 2,675×104m3. Material balance will be achieved to the extent

Page 20: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

possible. The quantity for reuse is 951×104m3. Total total spoils is 1,723×10 4m3 , of which

119×104m3 of top soils will be reused for revegetation. Eventually, 1,605×104m3 will be disposed

of at spoil sites.

Environmental impacts cuased by earth and stone works include

Land clearance and preparation will result in damages to original natural landscapes and the biological environment, short-time exposure of earth’s surface and soil erosion.

Embankment filling will result in excavation and filling of a large area of surface layer of the earth, soil erosion. In addition, construction and material hauling for embankment will cause dust and pollution to ambient air quality.

Construction of embankment protection works, including drainage system, will cause flushing, damages to irrigation system and soil erosion.

Material borrowing practices will cause loosening of land surface and soil erosion Spoil disposal practices will potentially cause soil erosion if not well managed.

Bridge Works

Bridge may change the natural hydrological conditions in river, valley, and channels, which will in

turn cause flushing to river bed and bank and impede flood discharge. Bridge pier construction

will generate spoils and wastes that may pollute river, farmland and accelerate soil erosion.

Tunnel works

There will be 9 double-line tunnels, with total linear meters of tunnels of 14,093m, accounting to 4.12% of the total length of the line.

The burial depth of the tunnels of the line is rather shallow. The maximum burial depth of Houshishan Tunnel is about 130m and that of the other tunnels is less than 100m. Underground water in most of the tunnels are not developed, and no springs are found during the geological survey. Limited crevice water in the base rock is prevalent, which is mainly supplemented thorough natural precipitation.

The potential impact of tunnel works is cut-off of ground water channel/layer, causing leakage and affecting water supply to people and plants on top of the tunnel. Tunnel wastewater, spoils and wastes, if not well managed, will pollute receiving water bodies. Soil erosion is another concern resulting from poor siting or protection of spoil sites.

3.2.3 Acoustic environmental impacts

Noise sensitive sites such as residential areas and schools are distributed on both sides of the railway of the project. Train noise and construction noise will have impact on those objects.

During construction, filling, compaction, pier building, material hauling, demolition and excavation, and vehicle are the major sources of noises.

3.2.4 Vibration impacts

Vibration comes from bumping and abrasion of wheels against rails while the train is running, and the vibration is transmitted to buildings via sleepers, roadbeds, subgrades (or bridge structures) and the ground, causing the vibration of the buildings and impacts on residential houses.

Page 21: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Apart from these, the project construction activities will have vibration impact on the neighboring buildings and residents passing through in the construction period.

3.2.5 Electromagnetic impacts

When electric locomotive is running, pulse electromagnetic radiation with wide frequency band will be generated from instantaneous off-line in the course of sliding of the pantograph against the overhead line system, and this kind of radiation will have affect TV signal quality nearby. Meanwhile, high speed railway passing through overhead viaducts or high subgrade sections will have shielding and reflective effects TV signal nearby.

Moreover, newly built traction substations will generate a power frequency magnetic field, and the newly built GSMR base station may have impact of electromagnetic radiation.

3.2.6 Water environmental impacts

Domestic wastewater discharged from stations during operation has the potential to pollute receiving water body. As discussed earlier, bridge pier and tunnel construction and oils from machinery will potentially cause water pollution if not well managed.

3.2.7 Ambient air impacts

Electric locomotive is adopted for traction in this line. There’s no emission of air pollutants from locomotives along the line. Fixed air pollution sources are new boilers at all the stations. Boilers use coal as fuel. Main pollutants are smoke dust and SO2. By design, desulphurization and dust-removal system will be installed to boiler to ensure emissions meet the national standards. Alternatively, old boilers will be replaced with environmental friendly ones.

During construction, machinery, transportation vehicles, cooking and heating at construction camps will generate waste gas. Material hauling will cause dust.

3.2.8 Solid waste impacts

The project is a passenger dedicated line. After it is put into operation, solid waste will come mainly from domestic garbage from working personnel, passengers waiting for trains and garbage from passenger trains.

Fuel coal boilers will generate some slag. The slag can be used as building materials for road projects in a planned manner, which will not have great impact on the surrounding environment.

Solid waste during the construction is mainly building solid waste and solid waste generated on the construction site, which, if not disposed of properly, may have an unfavorable impact on the surrounding environment.

3.2.9 Screening of Environmental Protection ObjectsBased on screening and scoping of environmental factors and impacts, ecological environment, acoustic environment, vibration and electromagnetic environmental are considered main environmental receptor or impacts of this project. Several types of environmental protection objects were identified during the environmental assessment process. These include:

Ecological objects: land, basic farmland, vegetation, water resource conservation facilities, and biodiversity resources

Page 22: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Noise protection objects: residential buildings, schools, hospitals, etc. , totaling 139; Vibration protection objects: residential buildings, schools, hospitals, etc. , totaling 88; Electromagnetic protection objects: residential buildings, etc., totally 85; Surface water protection objects: 10 rivers and the Yilan water source protection area; Social environmental protection objects: 4 cultural relics, land take and resettlement, etc.

A complete list of these environmental protection objects is presented in Annex 2 and further analyzed later in the report.

Page 23: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

4 Alternative Analysis

4.1 No project Scenario

At present, there is no direct railway line between Harbin and Jiamusi. Railway transportation between the two cities uses existing Harbin-Bei’an line (BinBei Line, 325 km long) and Suihua-Jiamusi line (SuiJia Line, 382 km long). The time required for travel is about 12 hours. Highway network plays a crucial role in the project regional transportation, including HaJia Expressway, YiHa Expressway (Harbin to Suihua), national highway G221 and G222. The continuous improvement of the above-mentioned major highways during the past years has increased the traffic capacity, running speed and service quality to different extents. The road transport is playing a more and more important role in the HaJia transportation function.

The existing railway lines were originally developed 1920-1940’s. Though the two lines have been renovated, the service level and conditions is rather poor. On the other hand, the road traffic is heavily affected by weather conditions, notably in winter. The proposed project will be a major passage in the regional railway network. It connects the Harbin hub with Jiamusi hub, and links to Harbin-Dalian, Harbin-Qiqihar and Harbin-Mudanjiang DPLs. Hence, it will serve not only regional (northeast China) but also short-distance passenger travelling purposes. The targeted passengers mainly consist of the people with the purpose of tourism, business and visit of families.

Without the proposed HaJia project, the increasing passenger and fright transportation demand would have to be met through widening of the existing highway network and construction of new high-grade highway, which will have large environmental footprint and social impact given its wider right-of-way. Furthermore, vehicles will have higher emission of air pollutants and green house gases, compared the railway for equivalent transportation capacity of passenger and freight, and poses higher risks of traffic safety in Chinese context.

The proposed HaJia railway will substantially shorten the travel distance between Harbin and Jiamusi from 506 km to 342 km, and reduce the travel time from 12 to 2 hours. It is expected that once the HaJia line is open to traffic, the traffic system in this region will be greatly optimized, the restricted traffic demand will be released, and the passenger traffic volume will be increased in a faster manner. The faster and better traffic links will provide convenient conditions for the social and economic exchanges and the industrial cooperation. Through existing railway lines and planned railway lines, this HaJia Line will connect several ports in the eastern and western borders of the Northeast. In return, the development of foreign trade will increase the number of commercial and trade passengers. With the cooperation and exchange between port cities, the number of passengers between port cities and passing borders will be increased accordingly. The HaJia railway will significantly improve mobility and accessibility in the project area. During the construction and operation period, the supporting industries along the railway lines such as, building materials and the power industry will be stimulated, the quality of employment will increased, development of local economy will be accelerated, social resource allocation will be optimized, and sustainable development of regional

Page 24: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

social economy will be promoted.

The proposed HaJia railway project will have adverse environmental and social impacts, while these impacts can be avoided, minimized, mitigated or otherwise adequately compensated through careful alignment selection to avoid environmentally and social sensitive sites and development of a strong environmental management plan.

4.2 General Alignment Selection

During the project proposal and feasibility study, 4 general alignment schemes were studied, namely Songhua River South Scheme, Songhua River North Scheme, Songhua River North Existing Passage Scheme and Songhua River North Sraightening Scheme (Figure 4-1). Comparative analyses of these three corridors were carried out considering the main cities along the corridor, and other major aspects. As HaJia line is an inter-city line of relatively short length. The general alignment selection is the main alternative analysis step.

The four general alignment schemes include:

Songhua River South Scheme: 342 km, including 5 km existing line; 20 stations to be built. Songhua River North Scheme: 354 km, 8 stations to be built Songhua River North Existing Passage Scheme: 377 km, 10 stations to be built Songhua River North Sraightening Scheme: 326 km, including 6.7 km existing line, 7

stations to be built.

Table XXX summarizes the advantages and disadvantages of the four general alternatives considering environment, social, economic, technical, implementation readiness, and comatibility with pronvincial planning. Based on the comparison, the following conclsions are reached.

The Songhua River North Straightening Scheme is shorter and straightest scheme. However, there are few economic hubs along the alignment, and many major construction works which are complicated and costly to build

The Songhua River North Existing Passage Scheme will pass many economic hubs. The passenger lines and freight lines can be separated in this passage to improve the service quality, but in this passage there is already BinBei Line and SuiJia Line which can meet the basic passenger transport need along the lines. Meanwhile, this scheme can’t meet the passenger transport need of both sides of Songhua River, and its line is about 40 km longer than other schemes, which is disadvantageous in terms of travelling time and cost. In addition, the scheme will pass through Heilongjiang Jiajiao Wetland Nature Reserve, an environmentally sensitive area, and will cross Songhua River, so it’s not favorable from the point of view of environment protection.

Songhua River South Scheme and Songhua River North Scheme will open a new transport passage. It is reasonable in terms of the railway network planning. Both schemes have the advantages of shorter length, simpler topography, less major works, more economic hubs along the line, better coordination with the local urban planning.

Songhua River South Scheme has the advantages such as not crossing Songhua River, not crossing environment sensitive area, higher economic development level and passenger transport need along the line, compliance with the local government’s requirement for the alignment of the line, lower investment on project, less difficulty in project implementation. Therefore, the Songhua River South Scheme is the recommended general alignment scheme.

Page 25: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-2 General Alignment Comparison of the HaJia Line

Page 26: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 4-8 Comparison of Four General Alignments

Scheme Advantage Disadvantage

Songhua River South Scheme

1. It has the shortest length and journey time besides the straightening scheme.2. The line is in parallel with Tongsan Highway, in accordance with the requirement of

local government for location of lines.3. The line is located in the coal chemistry industry planning zone which is one of the

four industrial planning zones of Heilongjiang Province, in accordance with the industrial planning requirement of Heilongjiang Province.

4. The line is in coordination with the planning of cities at the south bank of Songhua River, which helps the development of the cities along the railway line.

5. The line will neither cross Songhua River nor pass by important environment sensitive regions, so it has no impact on the river traffic and flood control of Songhua River, satisfying the environment protection requirement.

6. Few major projects along the line, which is easier for construction.

1. The line will cross Tongsan Highway for four times.2. The introduction of Harbin Hub will cause large scale house

demolition project.

Songhua River North Scheme

1. There are two more major economic zones along this line than in Songhua River South Scheme.

2. The line takes HaQi passenger line to connect Harbin Hub, avoiding the separation of the city. The demolition project scale is smaller and the construction is easier. The existing railway infrastructure can be well used.

3. The line will pass by the north of Songhua River, which is helpful for the development of Hulan District of Harbin.

4. The line is in coordination with the planning of cities at the north bank of Songhua River, which helps the development of the cities along the railway line.

1. The new line is 7.24 km longer than that in Songhua River South Scheme requiring an extra investment of 4.42 billion RMB.

2. The line passes by an environment sensible area which is Heilongjiang Jiajiao Wetland Nature Reserve.

3. The line crosses Songhua River.

Songhua River North Existing Passage Scheme

1. The line passes by some important economic areas such as Hulan District and Suihua City, which will help to attract passengers.

2. The line takes Haqi passenger dedicated line to connect Harbin Hub, avoiding the separation of the city. The demolition project scale is smaller and the construction is easier. The existing railway infrastructure can be well used.

3. The line is in coordination with the planning of cities along the line, which helps the development of these cities.

1. This line is the longest, 39.2 km longer than that in Songhua River South Scheme. The journey time is the longest.

2. The orientation of the line is not in accordance with the industrial planning of Heilongjiang Province.

3. The main economic development areas in the service scope of the line are overlapped with those along HaJia Line, which doesn’t help the development of other cities.

4. The line passes by an environment sensitive area which is Heilongjiang Jiajiao Wetland Nature Reserve.

5. The line will cross the forest areas in some sections. There are many major projects such as bridges and tunnels.

6. The line will cross Songhua River, not in accordance with the current environment requirement for construction.

Songhua River North Straighten-ing Scheme

1. The line provides the shortest length and journey time. 1. The line passes by few economic development areas, which is not helpful for attracting passengers and developing local economy.

2. The line passes by an environment sensitive area which is Heilongjiang Jiajiao Wetland Nature Reserve.

3. The line will cross Songhua River twice and most of the line will cross forests and mountains. There are many major projects such as bridges and tunnels.

Page 27: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

4. The line will cross Songhua River twice, not in accordance with the current environment requirement for construction.

5. The introduction of Harbin Hub will cause large scale house demolition project.

6. The route of the line is not in accordance with the industrial planning of Heilongjiang Province.

Page 28: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

4.3 Alternatives for sections and stations

Field surveys were conducted along the Songhua River South scheme to identify environmental sensitive areas that could be potentially affected, including nature reserve, scenic area, forest park, geological park, source water protection area and cultural relics, as well as urban planning. There are 6 environmentally and social sensitive areas identified, including Qinghua Relics, Chang’an Ancient Town, Sino-Japan Friendship Forest, Qiaonan Relics, Mayi River Wetland Nature Reserve and Yilan County Drinking Water Source Protection Area. Various alternatives were studied and the final proposed alignment successfully avoided most of them. However, due to constraint on topography, alignment curve and the necessity to access Yilan county, the Class II zone of Yilan Drinking Water Source Protection Area will be impacted.

Alternative alignments for various sections and terminal/stations have been extensively studied, during which a comprehensive comparison was conducted to choose the optimal scheme in terms of environmental and social impacts, technical feasibility, and financial and economic benefits. Consultation with local governments and relevant authorities of environmentally sensitive areas were conducted and fully incorporated into the alternative selection process. Several key sections alternative comparison processes were summarized below.

4.3.1 Comparisons of access lines to and locations of Jiamusi Terminal

The HaJia Line ends at the city of Jiamusi. Two level of comparison was conducted during the feasibility study stage. Level I studies the access approach to Jiamusi, while Level II aims to study the optimal location of new east Jiamusi station based on the result of Level I comparison.

Level 1 Study

Access to existing Jiamusi station scheme: the HaJia Line will be connected to existing Jiamusi station.

Newly built Jiamusi passenger station scheme: a new Jiamusi Station will be built at the boundary of city planning area.

The access to existing Jiamusi station scheme was selected because due to the economics reason, as the newly built station will require development of a new green area, building a major bridge across the Songhua River (see Figure 4-2).

Level 2 Study (CK325+000 [HaJia Line] ~ AK166 + 200[JiaTong Line])

The introduction of HaJia Railway into Jiamusi Station will cause the outward movement of local freight technical operation. A northern outer loop line for freight train will be constructed as per the general planning. Considering Jiamusi local passenger and freight transport system arrangement, existing equipment of East Jiamusi Station, renovation of JiaTong Line, discharging location of the long-term northern loop line for freight wagon, project of Jiamusi to JiaTong passenger link line, we compared the station location schemes including renovation of East Jiamusi Station, building East Jiamusi Station in new site and building new South Jiamusi technical operation station. The scheme comparison scope is shown in the schematic drawing of location of Jiamusi Local Technical Operation Station. (see Figure 4-3)

Scheme I: Scheme of East Jiamusi Technical Operation Station

New East Jiamusi Station is located in the west of the existing station, the TuJia Line will be renovated with parking yard and planned freight yard at one side of the existing line to

Page 29: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

facilitate the fetch/load operation on the dedicated line. The planned Jiamusi to JiaTong Passenger Line passes between the planned freight yard and tatinium sponge dedicated line through overhead track. The north loop line for freight wagons will cross the existing TuJia Line in the south of passenger car refitting site and at the throat section of the new EMU parking yard, and will get into East Jiamusi Station after discharging. JiaTong Line begins from the south end of East Jiamusi Station, not crossing Tongsan Highway, turns east at the north side of Tongsan Highway. See the schematic drawing of the location of East Jiamusi Technical Operation Station.

Scheme II: Scheme of building East Jiamusi Technical Operation Station in a new site

The new East Jiamusi Station will move southward compared with Scheme I. The south end throat area of the station is adjacent to the highway. The station is close to the existing line. The planned freight yard can use the free yard from Tatinium sponge factory to highway. Jiamusi to Jiatong passenger line passes between the parking yard and the planned freight yard through overhead track. The hump shunting track is located at the south side of the highway. JiaTong Line and TuJia uplink and downlink all use the existing archways in the bridge to cross the highway. Tujia uplink will cross JiaTong Line after discharging to reach East Jiamusi Station. The discharging of Tujia Line and JiaTong Line is located at the south side of the highway.

Scheme III: Scheme of new South Jiamusi Technical Operation Station

The new South Jiamusi Technical Operation Station will be built on the TuJia Line to the south of East Jiamusi. As the vertical section conditions of existing TuJia Line are bad between East Jiamusi Station and Changfatun Station, TuJia Line will be renovated, removing existing Changfutun Station and build a new South Jiamusi Station at the east side of Changfatun Station. The line between Jiamusi Station and South Jiamusi Station will be transformed to double-track. In the station, JiaTong Line will be connected with the JiaTong Main Line in the direction of Jiamusi.

Comparison of the schemes

Comparison of the 3 schemes is summarized in Table 4-2. The scheme of building new East Jiamusi Station in a new site is in accordance with the overall planning of the city and can meet the need of short-term and long-term operations. The railway infrastructure is concentrated, so it will occupy minimum of land. The titanium sponge factory is far away, so there is less noise and pollution interfering the station. The north loop line for freight wagons is in coordination with the planning of the city and easy to realize. There is no interference with the new parking yard. Scheme I requires the minimum of investment, but the long-term north loop line has big difficulties in realization. The discharging of JiaTong Line and TuJia Line will seriously separate the regions to the north of the highway and have big difficulty in realizing the longterm road planning of the city. Considering the water and soil conservation, the scheme of building new East Jiamusi Station will occupy the minimum of land, use the minimum of earthworks and have the minimum impact on the environment and water and soil conservation.

Page 30: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 4-9 Comparison of East Jiamusi Station

Scheme Scheme of East Jiamusi Technical Operation Station Scheme of building East Jiamusi Technical Operation Station in a new site

Scheme of new South Jiamusi Technical Operation Station

Length of line 53.917 55.064 65.671

Length of bridge 26995 38277 37874

Length of tunnel 0 0 3240

Occupied area 214.33hm2 211.79hm2 234.79hm2

Earthwork 5331550 m3 4722790 m3 6682460 m3

Type of occupied land and vegetation Farmland vegetation Farmland vegetation Farmland vegetation

Compliance with planning

1.The north loop line is in accordance with the overall planning of the city and meets the local requirement of operation in short term and long term.2.The station is close to the city. The fetch/load operation on dedicated line is in short distance.3.The north loop line for freight wagons crosses the city and causes a large scale house demolition project and have big impact on the existing enterprises and residents along the line.4.The discharging of JiaTong Line and TuJia Line will seriously separate the regions to the north of the highway and have big difficulty in realizing the longterm road planning of the city.

1.The line is in accordance with the overall planning of the city and meets the local requirement of operation in short term and long term.2.The station is close to the existing line and so can well use the existing railway land. The planned freight yard can use the free space between tatinium sponge factory and the highway. MuJia New Passage crosses the planned yard. Here the concentration of the railway infrastructure helps to reduce the area of occupied land to minimum. The north loop line for freight wagons is in coordination with the planning of city, reduce the scale of house demolition project and avoid the interference with the new parking yard.

1. The line is in accordance with the overall planning of the city and meets the local requirement of operation in short term and long term.2. The north loop line for freight wagons is in coordination with the planning of city, reduce the scale of house demolition project and avoid the interference with the new parking yard.3.The existing tracks and equipment of East Jiamusi Station can be kept and used for the local industrial station.4. The station is far from city, so the planned freight transport will be in long distance.

Evaluation of impact on environment

This scheme requires more occupied land and earthworks, which has bigger impact on environment and water and soil conservation.

This scheme requires minimum occupied land and earthworks, which has minimum impact on environment and water and soil conservation.

This scheme requires maximum occupied land and earthworks, which has maximum impact on environment and water and soil conservation.

Page 31: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-3 Access to existing Jiamusi Station Scheme (Recommended)

Page 32: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-4 Location of East Jiamusi Station

Page 33: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

4.4 Analysis of the project’s compatibility with related planning

4.4.1 Analysis of coordination with railway network planning

As per the Medium-term and long-term railway network planning of China (adjusted in 2008), Heilongjiang Province will build a railway passage between Harbin and Jiamusi to improve the railway network in East and Central regions. It will be an important part of North-East railway rapid passenger transport network and the extension of HaDa passenger dedicated line toward the North-East region of Heilongjiang Province. The project will reduce the time and space distance from Harbin to Jiamusi, even to Tongjiang, Shuangyashan and Hegang. It will become the most convenient passenger transport passage from the North-East region of Heilongjiang to Harbin and Inside Shanhaiguan Pass.

Currently, the construction of HaDa and HaQi passenger dedicated lines has started. HaMu passenger dedicated line and MuJia new passage are under planning. After this project is built up, a rapid passenger transport network will be formed in Heilongjiang region and connect, through HaDa passenger dedicated line, with all the railway passenger dedicated networks. It permits the rapid passenger transport network to reach all the regions in Heilongjiang and extend the coverage radius of the rapid passenger network. This network will make full use of the impacts of passenger dedicated lines and meet the need for rapid intercity passenger transport along the railway lines. The realization of this project will greatly reduce the time and space distance between North-East to Harbin and Inside Shanhaiguan Pass, help to improve the development of Harbin city circle and accelerate the urbanization along the lines. The project is significant for pushing the win-win cooperation of North-East regions and accelerating the regional economic integration.

See Figure 4-4 “Schematic Drawing of Medium-term and long-term railway network planning (adjusted in 2008)”.

Page 34: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project
Page 35: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-5 Schematic Drawing of Medium-term and long-term railway network planning (adjusted in 2008)

Page 36: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

4.4.2 Analysis of coordination with local traffic and economic development planning

At present, HaJia passage is attracting the passengers from the prefecture-level cities of Heilongjiang Province such as Harbin, Jiamusi, Shuangyashan, Hegang and Yichun. There is a frequent people flow and a great potential need for passenger transport. In 2007, the existing HaJia railway line transported 7.29 million people (in single direction), only after HaDa, ShenShan(QinShen) and HaQi lines in North-East regions.

Table 4-10 Passenger flow density (in single direction) of existing HaJia line in different years (Unit: 10,000 people)

Section 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

Harbin-Suihua 506 537 532 511 505 525 558 512 769 628 693 729

Suihua-Nancha 325 361 330 309 298 287 341 298 362 388 427 453

Nancha-Jiamusi

235 265 235 232 228 214 257 215 407 295 331 347

The existing railway transport system are already not able to meet the need of the rapid development of regional economy. It is in urgent need to improve the railway transport capacity and quality.

The realization of HaJia passenger dedicated line will bring breaking progress of the regional traffic infrastructure and it is significant for establishing and improving a modern comprehensive transport system which is unblocked and convenient and effectively combined with various modes of transport in the passage. The realization of this project will strengthen the economic links among the cities along the railways and help the mutual complementation and harmonious development of all the cities in capital, resources, technology and talents. It will have very deep impact on the realization of industry cluster, resources assignment and profound integration within the passage and become an important traffic passage with remarkable connecting impact within the region.

In addition, this line passes by some regions with beautiful natural scenary in northern China style. But when the tourist economy is growing faster and faster, the tourism along the line is waiting for development due to the lack of the important engine of “convenient traffic”. The realization of this project will open a rapid transport passage in HaJia region for the tourists and reach the whole country by connecting with adjacent passenger dedicated networks. It will greatly help to develop the tourist resources along the railway to attract the tourists and make the regional tourism greater and stronger.

The forecast annual passenger flow density on HaJia passenger dedicated line is given in Table 4-4.

Page 37: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 4-11 Forecast of passenger flow on HaJia passenger dedicated line(in single direction) Unit: 10,000 people

Sections

Passenger flow density (10,000 people)

Year 2020 Year 2030

Total IntercityLong distance

Total IntercityLong distance

Harbin-Binxian 1717 837 880 2328 1039 1289

Binxian-Fangzheng 1635 755 880 2237 948 1289

Fangzheng-Yilan 1584 704 880 2172 883 1289

Yilan-Jiamusi 1528 648 880 2097 808 1289

Consequently, this project will greatly push the development of local traffic and economy and is in coordination with the traffic and economic planning of the cities along the line.

4.4.3 Analysis of coordination with the planning of the cities along the line

Coordination with overall planning of Harbin

Harbin is the capital of Heilongjiang Province, a famous historical and cultural city, a modern center city in the north of North-East China in economy, politics, trade, science and technology, information, culture and tourism. The population in city center is 3.47 million and the overall city planning forecasts 4.60 million till 2020 (1.1 million in the north of Songhua River). The spatial layout is an open city spatial structure with multiple centers described as “One river, two cities (south of river and north of river), nine groups, eighteen clusters”. The future city spatial development strategy is “to develop North(north of Songhua River, both banks of Hulan River), to expand West(Qunli and Haxi New Area), to extend South(develop bungalows), to optimize East(maily industry), to improve Center(commerce, trade, finance, information, conferences and exhibitions) and to communicate with outside”.

In the project, the line begins from Harbin Station. The existing Binjiang Line and Jiangnan Line are rebuilt till Taiping Bridge. The new line passes a corner of the planned Thermal Power Plant of Harbin, goes northward and then turns to east. The project uses the existing Binjiang Line to connect Harbin Station so as to reduce the cutting of the urban area. The project is in accordance with the overall planning of Harbin city, harmonious and compatible. The Urban and Rural Planning Bureau of Harbin agreed on the itinerary of this line in Harbin with Haguicheng[2010]No.53 document – Report of opinions about the selection of location of the Harbin urban section of HaJia passenger dedicated line.

Page 38: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-6 Sketch map of the planned HaJia railway project and overall planning of Harbin

Analysis of coordination with overall planning of Bin County

It is planned to build Bin Countyinto a major industrial function area of Harbin. Production and manufacturing, recreational tourism, special agricultural trade and transport are the main town

Page 39: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

functions of Binxian District.

The planned HaJia railway project passes by the north of urban area of Bin County(not introduced into the existing areas). According to the overall planning of Binzhou Town of Bin County(2006-2020) – Land Development Planning, this area is classified as Level-4 and Level-5 control area and planned for the purpose of Level-3 housing land as well as commercial, financial and warehouse purpose. So the existing areas of the city will not be separated, the pollution sources for ecological system and noise will not be expanded. The boilers in the station are in accordance with the emission regulation and the sewage of station is treated by the Sewage Treatment Plant. So the planned project doesn’t have big interference with the overall planning of Binxian District. In addition, the planned project passes by the Level-3 housing land. We propose that the noise and vibration reduction measures shall be taken when this housing land is put into construction in the future.

Figure 4-7 Sketch map of the planned HaJia railway project and overall city planning of Binxian District

Analysis of coordination with overall planning of Fangzheng

As per the Overall city planning of Fangzheng (2004-2020), the nature of Fangzheng Town is the political, economic and cultural center of the district, an ecological garden city specialized in green food, deep manufacturing of forest products and tourism.

The planned HaJia railway project passes by the north of Fangzheng but does not reach the planned

Page 40: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

urban area, about 2.5 km away from the District. Fangzheng city overall planned area is located in the south of the planned railway project. So the planned project has not big interference with the overall city planning of Fangzheng District. See Figure 4-7.

Page 41: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-8 Sketch map of the planned HaJia railway project and Fangzheng city overall planning

Analysis of coordination with overall city planning of Yilan County

According to the overall planning of Yilan County, the urban area of Yilan is concentrated in the north of Songhua River, between Woken River and Mudan River near Songhua River. The south and south-west of Yilan County is planned for industrial and warehouse purpose.

The planned HaJia railway project passes by the south-west corner of Yilan County. According to the overall planning of Yilan, this area is part of the warehouse land. The project will not cause new split of the urban area and will not expand the pollution sources for econology and noise pollution. The boilers in the station are in accordance with the emission regulation and the sewage of station is treated by the Sewage Treatment Plant. Consequently the planned project is in accordance with the overall planning of Yilan County. See Figure 4-8.

Page 42: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 4-9 Sketch map of the planned HaJia railway project and overall planning of Yilan

Analysis on coordination with overall planning of Jiamusi

The planned project will cross Tongsan Highway atill the reserved New Jiamusi Station. Then the line will go along the reserved passage in Jiamusi city till the destination of the existing Jiamusi Station.

The planned HaJia railway project will pass by the south of the planned urban area of Jiamusi by means of Jiamusi Great Bridge, and turn northeastward at Wanfatun and go along the existing railway line. This project will not cause new split of the urban area. The areas along the line is the passage

Page 43: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

reserved to railway, so it will not cause new split of the urban area and will not expand the pollution sources for econology and noise pollution. The boilers in the station are in accordance with the emission regulation and the sewage of station is treated by the Sewage Treatment Plant. Consequently the planned project is not in conflit with the overall planning of Jiamusi.

In the Jiaguicheng[2010]No.12 document – Demand for opinion on the preliminary selection of location for Harbin-Jiamusi railway passenger dedicated line project, Jiamusi Planning Bureau indicates that the HaJia passenger dedicated line project is located within the scope defined by the overall planning of Jiamusi. The nature of project, location of stations, itinerary of the line are in accordance with the related requirements of the overall urban planning.

Figure 4-10 Sketch map of the planned HaJia railway project and overall planning of Jiamusi

4.5 Summary of the alternative analysis

In this design stage, the concept of environment protection is always in our mind during the whole design procedure of the project. When we select the route schemes, we tried to avoid and reduce the impact on the environment sensible areas along the line in order to ensure the environment feasibility of the route. After investigating the environment sensible areas within the route selection scope, the line avoids the important econological and social environment sensible areas along the line such as Mayi River Wetland Nature Reserve (9km away from the border of experimental zone of the Reserve), Qinghua Ancient Ruines, Changan Old City, Sino-Japanese Friendship Garden, Qiaonan Ancient

Page 44: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Ruines. But limited by the conditions such as topography, radius of curve and the need of introducing Yilan County into the scope, the project will still cross the Level-2 Reserve for the source of drinking water of Yilan County.

According to the function of this railway passenger dedicated line, the spatial layout of Jiamusi and the distribution of the economic development areas of Binxian, Fangzheng and Yilan, the itinerary of this line is reasonable from the point of view of economic development areas. The line is in coordination with the planning of the cities along the south bank of Songhua River and helps the development of the cities along the line. The line is in parallel with Tongsan Highway, which is in accordance with the requirement of local government for the location of the line. The line will not cross Songhua River, so it has small impact on the traffic and flood protection of Songhua River. The line will not passes by important econology sensible areas and cultural relic protection units.

In brief, the route is reasonable.

Page 45: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

5 Environmental Baseline

3.

4.

5.

5.1 Natural Environment

5.1.1 Landform

HaJia Railway is located in the northeast of Heilongjiang Province. The topography along the railway line is mainly alluvial plain, low mountains and hills. From Harbin to Binxian is mainly the alluvial plain of Songhua River, from Binxian to Jiamusi mainly hills. Jiamusi is located in the northern edge of Sanjiang Plain at the altitude of 100m ~500m.

Alluvial plain Low mountains and hills

5.1.2 Hydrology and river systemGroundwater

Because of different types of topography and sedimentation along the railway line, there are various types of groundwater. In the river valley flat area near Songhua River, Mayi River, Feiketu River and Mudan River accumulate stratums of Pleistocene series, upper Pleistocene series and Holocene series. As there isn’t stable aquiclude between stratums, a unified quarternary system of water-content rock formation was formed to conserve the pore water. The flood plain of the river has thicker water-content layer with loose granules, good water permeability and strong watery. The water inflow per well is 1000~5000 m3/d and the buried depth of the groundwater level is not deep. The supply and drainage both depend on the river. The groundwater level is normally 2.0~50.3 m underground.

In the hills area are distributed a large area of granite, Metamorphite series and sedimentary rocks where the bedrock fissure water is mainly conserved. The supply is from atmospheric precipitation. The groundwater level is buried very deep at about 11.0~38.5 m underground. The water level in some

Page 46: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

concave section is buried more superficial at 2.3~3.6m underground.

Surface water

The water system along HaJia railway line belongs to Songhua River water system. In Songhua River South Scheme, there are several larger rivers such as Mudan River, Woken River, Mayi River, Big Luomi River, Small Luomi River, Demoli River and Feiketu River. In Songhua River North Scheme, there are several larger rivers such as Hulan River, Piao River, Shaoling River, Mulanda River, Baiyangmu River, Chalin River, Wulahun River, Xibei River, Dagudong River, Xiaogudong River, Balan River and Tangwang River, and many medium and small rivers and irrigation canals criss cross.

Now we describe the main rivers passed by the project as follows:

Ashi River

Ashi River basin is located at the south bank of Songhua River. Ashi River is the first-level tributary of Songhua River, originating from Jianshan Rock of Maoershan Town of Shangzhi, flowing through Shangzhi, Wuchang, Acheng, Harbin, and flowing into Songhua River near Harbin Cement Plant. Main stream of Ashi River is totally 213 km long with a river basin area of 3581 km2. Ashi River develops a good river system and have many tributaries. Its main tributaries include Liushu River, Liangjia Channel, Fanjia Channel, Huaijia Channel, Small Yellow River, Dongfeng Channel, Dashitou River and Haigou River. Ashi River is a mountain river with rich water yield in summer but frozen and almost cutoff in winter. The ice period is from mid-November to the first third of April of the next year.

This project is located at the tidal mouth of downstream of Ashi River. This section of river becomes zigzag from Xiaosanjiazi and is naturally divided into two branches eastward and westward at Huangjiaweizi below the entrance of Dongfeng Channel. They cross four bridges at Hatong Road and Cement Plant Road and flow into Songhua River respectively. The levee of both banks of the tidal mouth section is the backwater dyke. The distance between the dykes of both banks is 2.5~3.0 km.

The discharge rate of this river section when the water rise to the same level as the banks is 551m3/s. For the sections above the backwater dyke of Songhua River, the flood stage at 20-year frequency of the section with dyke is close to the top of dyke, while the flood will be overbank at the section without dyke. The flood stage at 50-year frequency is at the same level as the roads along the banks and the main irrigation canals. The flood protection standard of the banks of backwater dyke section of Songhua River is higher: the Huagong Dyke of left bank can resist a flood of Songhua River at 50-year frequency, while the Dongfeng Dyke of right bank can resist a flood of Songhua River at 20-year frequency.

There are many industrial and mining enterprises along Ashi River, so a lot of industrial waste water flows into the river, which causes serious water pollution. The downstream tributaries of Ashi River, where the vegetation is in bad condition, are mostly intermittent rivers. The sources of some rivers are even the drainage of the factories.

Within the bridge section, the centenary flow rate of the catchment area of Ashi River is 2037 m3/s.

Feiketu River

Feiketu River is the first-level tributary at the right bank of Songhua River, originating from northeast

Page 47: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

of Diaoshui Lake Ridge, its river basin at the north end of Zhangguangcai Mountain Range, its upstream splitting with Ashi River in north-south direction. From the source, it flows northward to Linglong Mountain and turns to northwest, then flows westward slowly at Erlongshan Reservoir, then turns to northwest again after Binxi and flows into Songhua River at Tangfang Laoshantou.

The area of river basin is 1057 km2, of which 887.15 km2 in Binxian. The center line of the river is 78.6 km long, and the straight line is 67.6 km long.

The larger tributaries of Feiketu River include: Dasheli River, Xiaosheli River at left bank, Deyuanheng Channel, Dijuzi Channel, Tangfang Channel, Shuiquan Channel at right bank. In dry season, this river has little runoff, but there are many runoff in spring and summer flood periods.

Figure 5-11 Position of Erlongshan Reservoir, Tongsan Highway and railway bridge

Erlongshan Reservoir is located at upstream of Feiketu River, in south of HaTong Road, 6 km from Binxian. The basin area controlled by the Reservoir is 275.5 km2, reservoir capacity is 94 million m3. The standard of the Reservoir is designed for resisting flood of 50-year frequency, corrected as per the resistance to flood of 500-year frequency. It is a comprehensive and adjustable reservoir mainly for irrigation and flood control and combined with fish-farming and electricity generation.

Binzhou River

Binzhou River is a tributary of Hailihun River, originating from north of Beishan Mountain Rocks. The controlled river basin area at the railway bridge is 37.61 km2. It is 13.8 km long. Its centenary flow rate is 133.77m3/s. The tributary of Binzhou River at CK161+300: upstream basin area at the bridge location is 9.2 km2, and flow rate is 52.07m3/s

Hailihun River

It originates from Hailihun Mountain of Datong Village of Xinli Town. It flows through four counties which are Xinli, Binzhou, Niaohe and Minhe and flows into Songhua River at Bin Village of Minhe

Page 48: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Town. Hailihun River is totally 43.3km long and the river basin area is 326 km2. Its main tributaries include Binzhou River and Jiangshuidian Channel. The controlled basin area within the bridge section is 83.4 km2 and 18.9 km long. Its centenary flow rate is 228.07m3/s.

Mashe River

Mashe River originates from Gaotai Village of Sanbao Town. It flows through four towns which are Sanbao, Binan, Jingjian and Xindian and flows into Datong River at Xinmin Village of Binan Town and then into Songhua River. Mashe River is totally 33.3km long and its river basin area is 344 km2. Its main tributaries include Erdao Channel, Toudao Channel, Kongxin Channel, Yuanbao Channel, Caishen Channel and Xiaosanxing Channel. The controlled river basin area within bridge section is 119.08 km2 and 14.3km long. Its centenary flow rate is 289.54 m3/s.

Jiaban River

Jiaban River is totally 53.5 km and its river basin area is 950 km2. Its main tributaries include Hengdao River, Tangshi River, Chaoyang River and Shidong River. The controlled river basin area within bridge section is 511.73 km2 and 39.5 km long. Its centenary flow rate is 769.03 m3/s.

Taoqi River

Taoqi River originates from Taiping Mountain of Shengli Town of Binxian. It flows through two towns Shengli and Xindian and flows into Songhua River at Yuquan Village of Xindian. Taoqi River is totally 47.7 km long and its river basin area is 311.3km2. Its main tributaries include Heimalu Channel, Chengqianglazi Channel, Luoquan Channel, Hama Channel. The controlled river basin area within bridge section is 169.94 km2 and 24.6 km long. Its centenary flow rate is 367.44 m3/s.

Mayi River

Mayi River originates from the southeast side of Hufeng Ridge of Laoye Mountain in Shangzhi District at the north end of Wandashan Mountains. Its trunk stream gathers several steams from the mountains and flows through Shangzhi District and Yanshou District. It gathers Daliushu River at 49.3 km from the river mouth and goes into Fangzheng District with Yanshou District at right bank. It flows northeastward along the border of Yanfang District and gathers Dongliangzhu River from right hand at 32 km from the river mouth. The two rivers flow into Fangzheng District. Its trunk stream flows toward northeast and gathers Tongzi River from left and Shitou River from right at 25 km from the river mouth, then it gathers Huangni River from right at 20km from the river mouth, cross HaTong Road, finally flows into Songhua River in the east of Xinsheng Village of Tianmen Town and in the west of Laolonggang of Songnan Town. The river is totally 341 km long, in which 49.3km is in Fangzheng District. The total river basin area is 10727 km2. The tributaries include at left bank Shitou River, Huangni River, Weisha River, Niannu River, Liangzi River, Xiliushu River, Dongliushu River, Taipingchuan River, Daliushu River, Tongzi River, and at right bank Dahuangni River, Shitouhezi River, Wujimi River, Dongliangzhu River, Shitou River and Huangni River.

Lianhua Hydrologic Station of Mayi River is located at 20km upstream from the river mouth. The controlled river basin area is 10425km2. At medium and high water level, the maximum width of water surface is 260~1900m, maximum depth of water is 2.6~6.0m, maximum flow speed is 1.3~2.2m/s. At low water level, the maximum width is 145m, maximum depth is 1.3m, maximum flow speed is 1.1m/s. According to the documents collected from Harbin Hydrologic Station, the

Page 49: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

centenary flow rate at Lianhua Hydrologic Station is 6520m3/s. The historic maximum flood flow rate is 4060m3/s and the corresponding flood level is 100.18m. The frequency of flood is every 30 years.

Daluomi River

Daluomi River originates from north side of Zhangguangcai Mountain and flows from south to north. It flows into Songhua River at 1km from west of Daluomi. Its total length is 42km and the river basin area is 491km2. Its main tributaries include Xiangshui River, Dazhujuan River, Yaochuan River (Xiaohuangni River).

Xiaohuangni River, called Yaochuan River too, is a tributary of Daluomi River. Its total length is 19km and its river basin area is 81km2. It flows into Daluomi River at 2km upstream from the river mouth of Songhua River where it gathers Daluomi River.

Xiaoluomi River

Xiaoluomi River originates from north of Zhangguangcai Mountain. The altitude of river source is 560m and the altitude of river mouth is 121m. It flows from south to north and flows into Songhua River at 1km south to Dagaoleng and 3km downstream from the railway bridge. Its total length is 52km and its river basin area is 419km2. Xiaoluomi River crosses mountains and its tributaries are small. Its main tributary is Wugu River. The river basin area upstream from the bridge is 412km2, 49km long and the centenary flow rate is 682.44 m3/s.

Figure 5-12 Layout of Songhua River, Daluomi River, Xiaohuangni River, Xiaoluomi River

Mudan River

Mudan River is a larger tributary at right bank of downstream of Songhua River. It originates from Mudan Ridge of Changbai Mountain and flows from south to north through Dunhua, Ningan, Hailin, Mudanjiang, Linkou, Yilan, and flows into Songhua River at Yilan County of Heilongjiang Province.

Page 50: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

The total length of Mudan River is 725km and the area of river basin is 37600km2. The shape of river basin is like a band in south to north direction and crossing Jilin Province and Heilongjiang Province. The river is located at 127°32′-130°45′E and 43°00′N. There are many high mountains but few flat in the river basin. The mountains represent 89% of the total area and the flat 7.7%. The land is higher in the south and lower in the north, distributed between 300 and 1100m altitude. The average altitude of the river basin is 528m. The river basin is near Muling River in the east, Tumen River in the south, Zhangguangcai Mountain, Lalin River and Mayi River in the west, main stream of Songhua River in the north.

Mudan River is a mountain river flowing through the band of valley between Zhangguangcai Mountain and Laoye Mountain. The topography changes greatly: narrow valley upstream and U valley downstream, width between 400-500m. There are 7 larger tributaries: Sha River, Zhuerduo River, Mayi River, Hailang Rier upper than Mudanjiang city, Wuhulin River, Sandao River and Wusihun River lower than Mudanjiang city. The tributaries are distributed evenly at both sides of the main stream.

This project is located at 1km from where Tongsan Highway crosses Mudanjiang Great Bridge. The span of the river at the location of bridge is about 500m. The section of the river is in U form and there is cobble river bed and scouring phenomenon. The main channel bends at the location of bridge. There is running water but no plant in the main channel. Cobble river bed with a coefficient of roughness of 0.026. The flood plain is about 150~300m wide, normally no water, maximum average depth of water about 4m. There are arable land, sand quarrying pit and flood control forest. The soil is sandy soil with a coefficient of roughness of 0.06. At right bank of the river is a flood dam in soil texture. The top of dam is about 6.5m wide where can pass large-scale sand truck. The centenary flow rate is 14670 m3/s.

The flood control project of Mudan River mainly consist of a reservoir project and a levee project. There are now in Mudan River basin 28 large, medium and small reservoirs, in which 3 large reservoirs, 6 medium ones and 19 small ones. The existing medium and small reservoirs are mostly reservoirs with problems or risks which are useless for the flood control of the main stream. Among the large reservoirs, Huashuchuan Reservoir is in risk and its control area is only 505km2, so it’s useless for controlling the flood of downstream. Jingbohu Reservoir plays certain adjusting role to the medium and small flood, but has little adjusting impact on big flood. Lianhua Reservoir has no flood control capacity, so it discharges all the flood of below 50-year frequency, but has little adjusting impact on the flood of 50-year frequency and above.

The levee of the main river channel crossed by Mudan River Great Bridge is the backwater levee of Mudan River.

Woken River

The area of river basin of Woken River is 11630km2 in which the area of main stream is 6242km2.

Woken River is first-level tributary at right bank in the middle of Songhua River. It is located in the east of Heilongjiang Province and originates from northwest of Wanda Mountains, composed by many small mountain streams and springs. It flows into Songhua River at 1km east to Yilan County. The river is 305km long, the average gradient is 0.59% and the river channel bending coefficient is 1.5. The tributaries of Woken River are densely distributed. The tributaries at right bank are larger,

Page 51: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

including Wajinbie River, Qibahuli River, Songmu River, etc. The tributaries at left bank are smaller, including Qiezi River, Qitai River, Xiaowuzhan River, Nianzi River, Lianzhu River, Jixing River, etc. There are about 16 tributaries with an area of river basin above 100km2. The river bed of the main stream and the tributary are dissected superficially. The river channels are mostly in groove profile and are wide and superficial.

The main river channel is in obvious ladder shape wide of 80m, deep of 0.5m with scouring phenomenon. There is running water but no plant in the main channel at the location of bridge. The river bed consists of stones and mud. The coefficient of roughness is 0.026. At the side of shorter milage, the flood plain is 100m wide, normally no water, maximum depth of water is 3m, there are arable land and sand quarrying pit. The soil is sandy soil with a coefficient of roughness of 0.06. At the side of longer milage, there is dense vegetation which are grassland and forest. At the location of bridge, the river channel bends and the bridge is located at the turning of river channel. The centenary flow rate of the river at the position of bridge is 3660m3/s.

The main stream and the tributary of Woken River Basin will be frozen in winter and become frost-bound before and after January.

The documents collected from Woken Station (1961-2006) show that in drift ice period, maximum water level is 130.02m and minimum water level is 128.19m.

Songhua River

Songhua River is one of the seven large rivers of China. It has two sources in south and north. Its northern source is Nenjiang River originating from Yilehuli Mountain of Daxinganling. Its southern source is the second Songhua River originating from Tianchi of Changbai Mountain of Jilin Province. The two rivers flow together at Sancha River and are called Songhua River. Songhua River flows eastward till the border between China and Russia and into Heilongjiang Province. Nenjiang River is 1370km long while the second Songhua River is 958km long. Songhua River is 939km long.

Songhua River flows through Inner Mongolia, Heilongjiang Province and Jilin Province. It is 920km long from east to west, 1070 km wide from south to north. The area of river basin is 542000km2 representing 44.8% of the total area of North-East region.

Songhua River is wide and superficial river in plain. There are many distributaries, sandbanks and flood plains in the center of river. The river network at both banks of the main stream is very developed with a lot of tributaries. From the mouth of convergence, from above down, the tributaries at right bank include Lalin River, Mayi River, Mudan River and Woken River, and at left bank include Hulan River and Tangwang River.

This railway line is in the territory of Fangzheng, at south bank of Songhua River. Their distance is the shortest at this position. In the territory of Fangzhen, the main stream of Songhua River flows from west to east till 2km north-west to Liuhe Village, Xinan Township of Fangzheng District. It flows through the northern borders of the five townships which are Xinan, Tianmen, Songnan, Yihantong and Daluomi and enters into Yilan County at Shahezi Coal Mine of Daluomi Township. The length of Songhua River within Fangzheng District is 114km. There are Wangjianglou Pier, Fangzheng Port, Gaoleng Pier and Shahezi Port Office at the river banks in Fangzheng. The land at upper end and lower section of the river bank is higher. The middle section is the alluvial plain delta of Mayi River.

Page 52: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

The bank is convex. It forms a concave bank at Daxingtun at the upstream and Demoli of Yihantong River at downstream. Songhua River is open every year in the middle to the late April and closed late of November. It is open to navigation in unimpeded period. The upstream connects Tonghe, Mulan, Bayan and Harbin. The downstream connects Yilan, Jiamusi, Fujin and Tongjiang. There are frequently passenger and merchandise vessels coming and going to transport passengers and woods, coal, etc. It is an important water passage to connect Fangzheng with outside.

Tonghe Hydrologic Station is located at left bank in the middle section of Songhua River within Fangzheng District. According to the record of Songhua River’s hydrology between 1935 and 1985, when the Songhua River is at middle and high level at this station, the maximum width of water surface varies between 1500 and 5500 m, the maximum depth of water 7.3~10.4 m, the maximum flow speed at 1.2~1.7m/s. During dry season, the maximum width of water surface is 500mm and the maximum depth of water is 2.4m.

The characteristics of the main rivers along the railway line are given in Table 5-1.

Table 5-12 Characteristics of main rivers along railway line

Mileage of railway line

River

Centenary flow rate

m3/s

Centenary water level

m

Designed flow rate

m/s

CK3+600-CK5+600 Ashi River 2037.0 116.57 2.57

CK36+520.00 Feiketu River 1400.19 145.007 2.95

CK66+736.50 Hailihun River 228.07 151.725 2.63

CK81+580.00 Mayi River 289.54 136.738 3.10

CK90+743.60 Jiaban River 769.03 140.298 2.86

CK163+770.00 Mayi River 6520 112.710 2.07

CK201+250.00 Daluomi River 526.9 10.381 1.23

CK206+450.00Xiaoluomi River

682.44 104.981 2.26

CK249+550.00 Mudan River 14670 101.802 4.13

CK254+230.00 Woken River 3660 99.992 2.97

Note: The rivers above-mentioned in the table are mainly those whose centenary flow rate is above 200m3. The centenary flow rate of other rivers are all very small, so not described here.

Page 53: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

The photos of the main rivers along the railway line are shown below:

Ashi river Jiaban River

Halihun River Taoqi River

Mayi River Xiaohuangni River

Page 54: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Mudan River Daluomi River

Demoli River Feiketu River

Xiaoluomi River Woken River

5.1.3 Meteorological Characteristics

This region belongs to temperate zone with humid continental climate. The area that the railway line passes by is controlled by artic continental air mass in winter, so it is freezing and dry. In summer it is affected by subtropical maritime air mass, so the climate is hot and rainy. In spring and autumn, due to the alternative winter monsoon and summer monsoon, the climate is variable. In spring, there are a lot of gales, little precipitation evaporating fast and frequent drought. In autumn, cold wave often attacks this area with sudden drop of temperature and frequent frost injury. It is classified as severe cold area according to the classification of climate zone affecting railway projects. As the temperature drops fast in winter, the moisture content forms the zone of accumulation. In spring, the temperature increases

Page 55: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

slowly, so the infiltration of moisture content is not easy, which is unfavorable to the strength and stability of the roadbed. So the depth of fill of the roadbed shall be ensured to avoid ice accumulation and expanding of the ground water in winter and the roadbed shall meet the frost resisting requirement to avoid the disasters such as ice expanding and water seepage.

The principal meteorological factors of the main cities along HaJia Line such as Harbin, Binxian, Fangzheng, Yilan and Jiamusi(1979~2008) are given in Table 5-2.

Page 56: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 5-13 Principal meteorological factors of weather station

City

ItemHarbin Binxian Fangzheng Yilan Jiamusi

Mensal extreme high temperature for years (℃)

39.2 36.6 36.8 37.8 38.1

Mensal extreme low temperature for years(℃)

-37.7 -35.7 -38.6 -36.1 -39.5

Mensal average temperature for years(℃)

4.7 5.3 4.2 4.3 4.3

Average relative humidity for years(%)

64 62 71 68 65

Average precipitation for years(mm)

537.5 504 532 488.2 469.3

Average evaporation capacity for years(mm)

1454 1524 1117.9 1272.3 1106.1

Maximum depth of snow(cm) 24 30 50 42 45

Average wind velocity for years(m/s)

3.1 3 2.9 3.5 2.7

Maximum wind velocity(m/s) and wind direction for years

24.7 21.7 23 33 25.5

SW WNW SW WSW SW

Most frequent wind direction for years

S

W、S、SSW

WN

W、SSWSW、WSW SW、WSW SW、WSW

According to the meteorological documents(1979~2008) and investigation documents, the maximum frozen depths of the soil along the railway line are classified in Table 5-3.

Table 5-14 Table of classification of the maximum frozen depths of the soil along the railway line

Section Maximum frozen depth (m)

Page 57: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

BJCK0+000~CK256+000 2.05

CK256+000~CK338+600 2.20

5.1.4 Formation lithology and geologic structureFormation lithology

The exposed stratums along the railway line include Quaternary Holocene series artificial accumulative formation(Q4ml), Quaternary Holocene series alluvium(Q4al), Quaternary Holocene

series alluvium(Q4al+pl), Quaternary upper Pleistocene alluvial proluvial stratum(Q3al+pl), Quaternary upper Pleistocene talus-pluvial stratum(Q3dl+pl), Quaternary mid Pleistocene alluvial proluvial stratum(Q2al+pl), Quaternary mid Pleistocene talus-pluvial stratum(Q2dl+pl), late Tertiary (E) mudstone, sandstone, Cretaceous upper series(K2) tuff, lower series(K1)mudstone, sandstone, conglomerate, Jurassic mid series(J2) basalt, Proterozoic(Pt) gneiss, griotte and intrusive rock of Yanshannian Period(γ5) and Variscan Period(γ4).

The stratums are described as follows:

Quaternary system(Q)

①Holocene series artificial accumulative formation(Q4ml) is mainly composed by miscellaneous fill

and plain fill.

②Quaternary Holocene series alluvium(Q4al) is mainly composed by silty clay, rough angle gravelly

soil and rough round gravelly soil. It is distributed in the riverbed, flood plain and first-level terrace at both sides of Songhua River and its tributaries. It is the alluvial deposit of the river.

③Holocene series alluvium(Q4al+pl) is mainly composed by silty clay, clay, silt, fine sand, medium

sand, grit and gravel sand.

④Upper Pleistocene talus-pluvial stratum(Q3dl+pl) is mainly composed by silty clay, clay, silt, fine

sand, medium sand, grit, gravel sand, fine round gravelly soil, rough round gravelly soil, fine angle gravelly soil, rough angle gravelly soil, cobbly soil. It is distributed in the second level terrace at both sides of Songhua River and its tributaries.

⑤Quaternary upper Pleistocene talus-pluvial stratum(Q3dl+pl) is mainly composed by silty clay and

clay.

⑥Mid Pleistocene alluvial proluvial stratum(Q2al+pl) is mainly composed by silty clay, clay, silt, fine

sand, medium sand, grit and gravel sand. It is distributed in the third level terrace at both sides of Songhua River and its tributaries.

⑦Quaternary mid Pleistocene talus-pluvial stratum(Q2dl+pl) is mainly composed by silty clay and clay.

Late tertiary system(E)

①Dingshancun Fm (Eds) is mainly composed by mudstone, sandstone, conglomerate. It is distributed in Binxian.

②Tertiary Dalianhe Fm (Edl) is mainly composed by mudstone. It is distributed in Dalianhe Township.

Page 58: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Cretaceous system (K)

①Upper series (K2) is mainly composed by tuff. It is distributed between Yilan and Jiamusi.

②Lower series (K1) is mainly composed by mudstone, sandstone and conglomerate. It is distributed in Binxian at right bank of Songhua River and in the eastern mountains area of Binxian.

Jurrasic mid series (J2)

Basalt: tawny, weakly weathered, cryptocrystalline texture and blocky structure, 0~>3m thick. Scattered distribution.

Proterozoic(Pt)

Gneiss >10.0m thick and mainly distributed in the east of Woken river.

Yanshannian Period(γ5)

Granite: tawny, fleshred, completely weathered ~ highly weathered, granular structure, blocky structure, core in form of sand, fragment, short column, normally 10~20cm long, thickness of layer >10m. It is mainly distributed in the rolling terrain along the railway line from Binxian to Fangzheng. Scattered distribution of diabase.

Variscan Period(γ4)

Granite: tawny, brown yellow, taupe, fleshred, completely weathered ~ weakly weathered, 0~46.7m thick, mainly distributed in the mountains along the railway line from Fangzheng to Yilan.

Geologic structure

The geologic structure movement along the railway line is intense, frequent and complex, affected by multiperiodic structure movement. It is preliminarily divided into eastward and westward structure systems, Cathaysian structure system, Neocathaysian structure system, Cathaysoid structure system, southward and northward structure systems and northward and westward structure systems.

The geologic structure in this area is mainly rift structure. The larger fracture zone are as follows:

Songhua River Fault (F1): It is distributed along the valley of Songhua River and divided into two parts. The first part is mainly the normal fault dipping steeply to the north. The geologic structure characteristics of two sides of the faultage are different. The north side accept a large area of Quaternary coverage, while the south side forms a banding concave in parallel with the river body or abrupt bank. The basement is widely exposed, mainly in Harbin ~ Fangzheng. The second part is mainly the reverse faultage of subtwisted nature constituting rift of the trunk of the east branch of Yishu graben. It is covered by very thick illuvial horizon and has no relationship with and no impact on the railway line.

Beilidong-Zhendong Fault (F3): It begins from Beilidong and extends to north west by 300°. Total length is about 60km. This faultage is a normal fault formed by tension impact and steeply invading north east. It has no relationship with and no impact on the railway line.

Shengli-Huifa Fault (F4): It is distributed in east-west direction through Shengli and Huifa. The strong invasion forms a large area of granite. Triangular section and steep rock of the northern rift appears from time to time. There are normal faults along the rift line such as vein rock, well, etc. It passes by

Page 59: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

CK146+000 and is coverd by Quaternary stratums. It has little impact on the construction of the railway.

Dongliangzhu River Fault (F5): It passes by Jiaxinzi, Zhonghetun, nearly south-north direction, length

>76km, and triangular sections of rift appear along both banks of Dongliangzhu River. It passes by CK161+000 and CSK158+000, covered by very thick illuvial horizon, so has little impact on the construction of the railway.

Demoli Thrust Fault (F6): It is an insidious fault of 17km long. It moves over a long period. The Variscan gabbro body invades along the fault. In late geological time, due to the continuous movement of this fault, the north part descended relatively and accumulated the silty clay and silt of Quaternary upper Pleistocene. It passes by CK194+000, covered by the Quaternary stratums, and has little impact on the construction of the railway.

Daluomi Fault (F7): It is distributed in Daluomi and extends to north east by 20°, 24km long. Daluomi River generates along the fault. It passes by CK198+000, covered by the Quaternary stratums, and has little impact on the construction of the railway.

Chenjialiangzi Oblique Thrust Fault (F8): It is distributed from Gaoleng to Suliantun and extends to north west about 75km. It passes by CK205+000, covered by the Quaternary stratums, and has little impact on the construction of the railway.

Sifengshan Reservoir Fault (F9): It is distributed in Sifengshan Reservoir, 17km long, extends to north west and inclines to north east. No visible relief characteristic. It is a reverse fault. It has no relationship with and no impact on the railway line.

Zhaoyang Village Fault (F10): It is distributed in Paoziyan to Jiangongcun, 40km long in east-west direction. It is a series of discontinuous piedmont faults causing the visible border between mountain and plain. It passes by CK335+000, covered by the Quaternary stratums, and has little impact on the construction of the railway.

Jusheng Fault (F11), Upland Fault (F12): They are distributed in Jusheng and 372 Upland. Jusheng Fault is 11km long, while Upland Fault is 4.5km long. They both incline to north east and are normal fault. They pass by CK320+000 and CK323+000 and cross each other in a big angle. They have little impact on the construction of the railway.

Electrician Bureau Farm Fault(F13): It is distributed in Fruit Tree Farm to Electrician Bureau Farm in north-east direction and inclines to north west, 10km long. It is in relief a modern river valley and a shift fault. It has no relationship with and no impact on the railway line.

5.1.5 Seismic parameters

As per Annex A of Regionalization Map Chinese Earthquake Dynamic Parameters (GB18306~2001) and combined with the field investigation and engineering setup, the acceleration of the dynamic peak value of earthquake along the railway line is classified as follows:

Harbin to Jiamusi: the acceleration of the dynamic peak value of earthquake is 0.05g (basic earthquake intensity is Grade VI).

5.1.6 Unfavorable Geology and special rock and soil

Page 60: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Loose and soft soil

In the project scheme, there exist loose and soft soil including silty clay and clay. Silty clay and clay: grey black, tawny, charcoal grey, grayish yellow, light grey, molliplast~fluidal plastic, containing rusty spot. It is mainly distributed in the surface layer of the earth’s surface, 2.0~23.0m thick. See Table 5-4 for detailed sections.

Table 5-15 Loose and soft soil section table

Scheme Mileage distributing section

Route

scheme

CK11+000~CK12+305.96

CK16+392.54~CK18+396.06

CK23+137.7~CK23+681

CK24+191.06~CK27+502.7

CK28+528.5~CK31+167.7

CK39+906~CK48+500

CK166+674~CK168+654Filling soil

There is generally fill along the line, mainly including plain fill, miscellaneous fill, filled soil, etc. As the different filling years, various filling methods and different material sources, the variation of thickness, content and compactness is important. The filled soil is distributed in the existing roadbed and composed by silty clay with more homogeneous soil texture and better engineering geological conditions. Plain fill, tawny, molliplat~stiff-plastic, mainly composed by silty clay filled with a few of plant roots. It scatters around the towns and villages. Miscellaneous fill, light grey, black grey, mixed color, moist, mainly composed by silty clay and life waste. It is mainly distributed around the towns and villages.

Swelling rock (soil)

The mudstone of lower Neogene series and lower Cretaceous series between Harbin and Dalianhe as well as the completely weathered tuff of upper Cretaceous series between Gaolimao and Jiamusi have weak to medium expansibility. The side slope shall be moderated during excavation section and the fill in cutting foundation bed shall be exchanged. In the new station scheme, existing Jiamusi to East Jiamusi scheme and other scheme, the local silty clay has medium~strong expansibility. The side slope shall be moderated during excavation section and the fill in cutting foundation bed shall be exchanged. The depth of excavation shall be controlled.

Seasonal frozen earth

Along the railway line are severe cold regions. There is a layer of seasonal frozen earth on the surface layer of the ground, thick of 2.2m. It begins freezing every year from the last third of October and reaches the maximum freezing depth in mid-March.

Page 61: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

5.2 Social-economic Environment

5.2.1 Regional economic characteristics

This project is located in Heilongjiang Province, connecting Harbin hub in the west and through Harbin hub linked to HaDa and HaQi passenger dedicated lines under construction and planned HaMu passenger dedicated line and related existing lines. It is connected to Jiamusi in the east. It is an important part of Heilongjiang High Speed Railway Network. It passes by Harbin and Jiamusi of Heilongjiang Province.

Harbin

Harbin is the capital of Heilongjiang Province, a modern center city in the north of North-East of China in terms of economy, politics, trade, science and technology, culture and tourism. Its whole area is 5.3×104km2. Its total population is 9.874 million by the end of 2007. In 2007, it realized a regional GDP of 243.68 billion RMB, an increase of 16.4% compared with the precedent year. The ratio of the three industries is 14.3:37.0:48.7. GDP per capita is 24768 RMB.

Harbin is rich in mineral resources. 63 minerals have been discovered, in which 25 types have been verified for industrial purpose. In which 20 minerals take important position in Heilongjiang Province, including coal, natural gas, copper, zinc, wolfram, molybdenum, iron pyrite, smelting crystal, serpentinite, arsenic, stones for construction, mineral water, etc.

Harbin has particular tourist resources, reputed as “Oriental Paris” and “Oriental Moscow”. There are many historic landmarks and sites such as Dragon Tower, Flood Protection Monument, Confucious Temple, Jile Temple, Saint-Sophia Church, Central Avenue of Russian culture, Former Residence of Xiaohong, Shangjing Huining Mansion of Jin Dynasty and more than 500 human and natural landscapes. They, together with Jingbo Lake, Five Volcano Pools and Zhalong Nature Reserve, constitute a distinct and particular tourist place in the North of China.

The industrial production of Harbin keeps growing fast. In 2007, the total industrial output is 214.88 billion RMB, an increase of 16.7% compared with the precedent year.

The agricultural production grows steadily. In 2007, Harbin realized a total agricultural output of 50.69 billion RMB, an increase of 6.3% compared with the precedent year. Its total grain output is 975×104t, oil output of 1.2×104t, beet output of 2.3×104t, vegetable output of 194.2×104t.

By 2020, after realizing the objective of building a well-off society in all aspects, Harbin will realize the modernization, with a GDP of 850 billion RMB and a GDP per capita of 8300 USD.

Bin County

The total area is 3845km2. The total population by the end of 2008 is 620000 and the natural rate of growth of population is 4.41‰. It has jurisdiction over 17 towns including 10 nations: Han, Manchu, Mongolian, Hui, Miao, Zhuang, Korean, Dong, Yao and Xibe. In 2008, Binxian realized a GDP of 11.12 billion RMB, an increase of 16.9% compared with the precedent year. In which, the primary industry realized an added value of 2.61 billion RMB, an increase of 7.0%. The secondary industry realized an added value of 4.95 billion RMB, an increase of 20.1%. The tertiary industry realized an added value of 3.56 billion RMB, an increase of 20.7%. The ratio of the three industries is

Page 62: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

23.5:44.5:32. The GDP per capita is 17821 RMB, an increase of 16.1% compared with the precedent year. It realized the general budget revenue of local public finance of 260 million RMB, an increase of 21.1% compared with the precedent year. The total industrial output is 16.60 billion RMB, an increase of 17.9%. The total fixed investments are 4.49 billion RMB, an increase of 31.7%. The total social retail goods is 2.85 billion RMB, an increase of 22.3%. The disposable income per capita of urban residents is 8938 RMB, an increase of 14.0% compared with the precedent year. The net income per capita of farmers is 5501 RMB, an increase of 19.8%.

Fangzheng

The total area is 2969km2. By the end of 2008, the total population is 220000. It has jurisdiction over 8 towns. There are 17 national minorities living here, representing 2.5% of the total population. In 2008, it realized a GDP of 2.38 billion RMB, an increase of 20.2% compared with the precedent year. In which, the primary industry realized an added value of 840 million RMB, an increase of 16.7%. The secondary industry realized an added value of 590 million RMB, an increase of 34.0%. The tertiary industry realized an added value of 950 million RMB, an increase of 15.9%. The ratio of the three industries is 35.3:25.0:39.7. It realized the general budget revenue of local public finance of 130 million RMB, the total industrial output of industrial enterprises of 610 million RMB, an increase of 54.2%. The total fixed investments are 1.17 billion RMB, an increase of 50%. The total social retail goods is 1.16 billion RMB, an increase of 23.3%. The disposable income per capita of urban residents is 7573 RMB, an increase of 20.6%. The net income per capita of farmers is 5782 RMB, an increase of 20.0%.

Yilan County

The total area is 4616km2. By the end of 2008, the total population is 400000. It has jurisdiction over 9 towns. There are 17 national minorities living here, representing 5.9% of the total population, most of whom are Manchu, Hui and Korean. In 2008, it realized a GDP of 5.21 billion RMB, an increase of 15.6% compared with the precedent year. In which, the primary industry realized an added value of 1.63 billion RMB, an increase of 9.7%. The secondary industry realized an added value of 11.89 billion RMB, an increase of 18.5%. The tertiary industry realized an added value of 2.00 billion RMB, an increase of 17.8%. The ratio of the three industries is 31.5:30.3:38.2. It realized the general budget revenue of local public finance of 230 million RMB, an increase of 30.9%. The total industrial output of industrial enterprises above designated size is 11.89 billion RMB, an increase of 14.2%. The total fixed investments are 2.87 billion RMB, an increase of 45.2%. The total social retail goods is 1.50 billion RMB, an increase of 24.4%. The disposable income per capita of urban residents is 10031 RMB, an increase of 25.6%. The net income per capita of farmers is 5949 RMB, an increase of 19.8%.

Jiamusi

Jiamusi is located in the heart of Sanjiang Plain where Songhua River, Heilong River and Wusuli River join gather together. It is the center of economy, culture, traffic, science and technology of north east of Heilongjiang Province and the largest comprehensive center city. Its total area is 32700 km2. There are 5 open ports of national first level, two international passenger and merchandise transport passage from Tongjiang and Fuyuan to Russia and a golden water channel joined by river and sea connecting the countries in Asia-Pacific. It’s very convenient for the trade with Russia. Its total population is 2.505 million. There are 7 districts in its jurisdiction. In 2007, it realized a GDP of

Page 63: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

50.754 billion RMB. The ratio of the three industries is 39.4:18.2:42.4.

Jiamusi is rich in mineral resources. There are 50 minerals explored and verified such as iron, manganese, titanium, copper, aluminum, zinc, etc. It has distinct tourist resources including Russian frontier travel, “First sentry in Orient”in Wusu Township of Fuyuan, folk custom of Nanai nationality, Tangyuan Daliangzi River Forest Garden, etc. With the ownership of Heixiazi Island and its future development, Jiamusi will become an important breach for the development of tourism.

The industrial economy of Jiamusi operates at high speed and efficiency. As the old industrial basis of China, its industrial system is complete with solid industrial foundation. There are over 20 sectors such as mechanical and electrical, paper making, medicine and chemical, foods, textile, etc. There are a lot of large and medium size key enterprises known in the whole countries in paper making and motor production field. Its equipment manufacturing industry such as large-size agricultural machines, large-size coal mining equipment and large-size electrical equipment is in a leading position in Chinese and international market. In 2007, the enterprises above designated size have realized a total industrial output of 126.48 billion RMB.

Jiamusi possesses rich resources and products. It is located in the heart of Sanjiang Plain, one of the world’s three largest black soil plains. With 22 million mu of arable land, it’s the main development zone of Sanjiang Plain and an important marketale grain basis of the country, abound in grain crops such as soy bean, rice, corn, wheat, etc. In 2007, its total grain output is 722.3×104t and its total agricultural output is 11.59 billion RMB.

According to the planning of Jiamusi, by 2020, its total GDP is expected to be more than 120 to 140 billion RMB with an average annual increase of more than 11%. The GDP per capita is expected to reach 6000 USD and the people will enjoy higher and more comprehensive well-off life level. The ratio of the three industries will be adjusted to 15:40:45.

The main economic indices of the cities along the railway line are given in Table 5-5.

Table 5-16 Main economic indices of cities along railway line in 2007

Indices Unit Harbin Jiamusi Total

Area of land 10000 km2 5.3 3.27 8.57

Total population 10000 people 987.4 250.5 1237.9

GDP100 million RMB

2436.8 507.5 2944.3

In which

Primary industry100 million RMB

347.7 200.1 547.8

Secondary industry

100 million RMB

902.6 92.5 995.1

Page 64: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Tertiary industry100 million RMB

1186.5 215 1401.5

GDP per capita RMB 24768 20259

Total agricultural output100 million RMB

506.9 115.9 622.8

Total industrial output100 million RMB

2141.8 1264.8 3406.6

Total grain output 104t 975 722 1697

Social retail goods100 million RMB

1035.9 120.4 1156.3

5.2.2 Traffic and transport situation and reality of passenger carrying capacit

HaJia passenger dedicated line is surrounded by convenient traffic system which has formed a solid transport network involving water, road and air as well as a large international sea and river combined transport passage.

Railways

In HaJia passage, the existing railways related to Hajia Railway include BinBei Railway, SuiJia Railway, TuJia Railway, JiaFu Railway, etc. In 2007, on the section of Harbin to Suihua in this passage were running 24 pairs of passenger trains, 16 pairs from Suihua to Nancha, 15 pairs from Nancha to Jiamusi. This railway line, together with Hada passenger line, HaQi intercity line, HaMu passenger line, will constitute a rapid passenger traffic network in north east region to improve the passenger and merchandise transport system capacity of 3-longitudinal-4-horizontal railway network of north east region.

Road

The main modes of transport in HaJia passage include highways like HaJia Highway, YiHa Highway(Harbin to Suihua) and national highways G221 and G222, etc.

Civil aviation

Along HaJia line there are Harbin Airport and Jiamusi Airport. During the last years, with the rapid development of economy and growth of life level, the passenger traffic volume by civil aviation increases fast.

In 2008, Heilongjiang Airport Group Corporation realized a passenger throughput of 5.41million person-time, a merchandise throughput of 60000t. In which, Harbin Airport realized 4.98 million person-time and 58000t of merchandises; Jiamusi Airport realized 110000 person-time and 226t of merchandises. The passenger and merchandise throughput represents 94.09% and 97.04% respectively of the total throughput of Heilongjiang Province.

Water transport

Page 65: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Harbin Port is one of the eight biggest river ports of China and also the largest river port in north east. Its river lines cover Songhua River, Heilong River, Wusuli River and Nenjiang River and connect some ports in Russia and Far-East. Through the river sea combined line, the ships can go out of Dada Strait and go up to Japan, North Korea, South Korea and South East Asia. Now there are one passenger port (Beiqidao Street, Daowai District) and one merchandise port (Sankeshu, Taiping District).

Every summer, there are passenger liners running from Harbin to Jiamusi by Songhua River.

5.2.3 Cultural property

Cultural property survey was conducted for roject alignment by entrusting local archeological institutes, combined with consultation with local cultural property management authorities/general public and field survey during EA preparation.

In total 4 cultural property were identified, and the alignment was shifted to avoid all of them. The location of thse cultural properties is shown in Table 5-6.

Table 5-17 Cultural property along the alignment

Name Location Level Relation with the railway alignment

Qinghua relics Bin County of Harbin Provincial Level

2km out of control boundary

Chang’an ancient twown Bin County of Harbin Provincial

Level3km out of control boundary

Sino-Japan Friendship Forest

Fangcheng County of Harbin

Provincial Level

3km out of control boundary

Qiaonan Relics Yilan County of Harbin Provincial Level

200m out of control boundary

Page 66: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

6 Impact Assessment of Ecological Environment

6.1 Forecast and Evaluation of impact on ecological environment

6.1.1 Impact analysis of land occupation on land use and mitigation measures

Impact analysis of permanent land occupation on land useThe permanent occupation of lands by the project includes subgrades, station yards, bridges and culverts,tunnel inlets and outlets. The permanently expropriated lands by this project line totals an area of 1416.27 hm2, including cultivated lands of 903.20 hm2 (paddy fields of 45.92 hm2 and dry lands of 857.28 hm2), accounting for 63.77%, orchards of 7.59 hm2, accounting for 0.54%, forest lands of 419.85 hm2, accounting for 29.65%, ponds of 8.24 hm2, accounting for 0.58%, lands for construction of 42.63 hm2 (including house site), accounting for 3.01% and other lands of 34.75hm2, accounting for 2.45%. Including stations and relevant facilities, the permanently expropriated lands averagely cover an area of 4.21 hm2 per kilometer.

The classification and quantity of permanent occupation of lands in the project refers to Table 5-3-1.

Table 6-18 Classification and quantity of permanent land occupation Unit: hm2

CityCounty and District

Total

Cultivated AreasGarden Plots

Forest Lands

Pasture Lands

Ponds

Other Lands

Lands for Construction

Unused Lands

Subtotal

Paddy Fields

Dry Lands

Vegetable Plots

Harbin

Daowai 66.79

56.49

0.27

56.22 2.49 1.7

4 6.07

A’cheng

116.94

105.70

105.70 0.30 1.78 4.0

42.41 2.71

Bin 413.64

281.11

1.78

279.33

128.16 0 4.37

Fangzheng

268.18

109.05

43.76

65.29

157.72

0.92 0.49

Yilan 293.45

174.68

0.11

174.57

113.18

0.14 5.44

Total 1159.0

727.03

45.92

681.10 2.79 400.

856.84

2.41 19.07

Jiamusi

Suburbs

257.27

176.17

176.17 4.80 19.0

0 1.4 32.33 23.56

Total 257.27

176.17

176.17 4.80 19.0

0 1.4 32.33 23.56

Total of the Whole line

1416.27

903.20

45.92

857.28 7.59 419.

858.24

34.75 42.63

Percentage % 100 63.77

3.24

60.53 0.54 29.6

50.58

2.45 3.01

The permanent land occupation will change the original use function of land, wherein the cultivated lands cover an area of 903.20 hm2, accounting for 63.77%; and the permanently occupation of lands averagely cover an area of 2.64 hm2 per kilometer. The forest lands cover an area of 419.85 hm2, accounting for 29.65%.

Page 67: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

The occupied basic farmlands along the whole line cover an area of about 767.72 hm2, accounting for 85.0%. It is estimated by the yield per unit area of the cultivated lands from each city along the line (By 5000 kg/hm2) that the local grain yield caused by railway construction is reduced by about 3836.5t/a. The permanently occupation of lands in the project will slightly impact the land utilization pattern of regions along the line; and the expropriated lands will reduce the quantity of agricultural lands per capita and the agricultural output aiming at related towns and villages, thereby having an adverse impact on agricultural production.

Impact analysis of temporary land occupation on land useThe temporary land occupation include borrow pit, Spoil ground, construction roads, large-scale temporary facility sites, Construction buildings and the like which totally cover an area of 534.78 hm2. The respective floor areas are shown as follows: Spoil ground of 217.78 hm2, construction roads of 85.38 hm2, beam construction and storage yards of 123.40 hm2, Prefabrication site of ballastless track slab of 25.20 hm2, concrete mixing plant of 29.00 hm2, temporary power lines of 7.34 hm2, construction sites of 22.68 hm2, Temporary residue piling yards in tunnel of 3.20 hm2 and Construction buildings of 20.80 hm2. Refer to Table 5-3-2.

Table 6-19 Classification and Quantity of temporary land occupation Unit: hm2

City and County Cultivated Lands

Forest Lands

Ponds

Uncultivated Lands Total

Harbin

Spoil ground 0.00 0.00 0.00 0.00 0.00

Construction roads 5.91 2.22 0.00 1.11 9.23

Beam construction yards 12.34 0.00 0.00 0.00 12.34

Prefabrication site of ballastless track slab 0.00 0.00 0.00 0.00 0.00

Concrete mixing plants 3.00 0.00 0.00 0.00 3.00

Temporary power lines 0.32 0.12 0.00 0.06 0.50

Construction sites 0.00 0.00 0.00 1.60 1.60

Temporary residue piling yards in tunnel 0.00 0.00 0.00 0.00 0.00

Construction buildings 0.00 0.00 0.00 0.80 0.80

Subtotal 21.57 2.34 0.00 3.57 27.47

Bin

Spoil ground 65.70 2.40 0.00 9.78 77.88

Construction roads 16.27 6.10 0.00 3.05 25.43

Beam construction yards 37.02 0.00 0.00 0.00 37.02

Prefabrication site of ballastless track slab 8.40 0.00 0.00 0.00 8.40

Concrete mixing plants 7.00 0.00 0.00 0.00 7.00

Temporary power lines 1.30 0.49 0.00 0.24 2.03

Construction sites 0.00 0.00 0.00 5.32 5.32

Temporary residue piling yards in tunnel 0.00 0.00 0.00 0.40 0.40

Construction buildings 0.00 0.00 0.00 4.80 4.80

Page 68: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Subtotal 135.69 8.99 0.00 23.59 168.27

Fang

zheng

Spoil ground 5.48 9.61 0.00 59.21 74.30

Construction roads 15.28 5.73 0.00 2.87 23.88

Beam construction yards 12.34 12.34 0.00 0.00 24.68

Prefabrication site of ballastless track slab 8.40 0.00 0.00 0.00 8.40

Concrete mixing plants 6.00 3.00 0.00 0.00 9.00

Temporary power lines 1.44 0.54 0.00 0.27 2.25

Construction sites 0.00 0.00 0.00 7.60 7.60

Temporary residue piling yards in tunnel 0.00 0.00 0.00 1.60 1.60

Construction buildings 0.00 0.00 0.00 8.00 8.00

Subtotal 48.94 31.22 0.00 79.55 159.71

Yilan

Spoil ground 0.00 0.00 0.00 51.47 51.47

Construction road 12.24 4.59 0.00 2.29 19.12

Beam construction yard 12.34 24.68 0.00 0.00 37.02

Ballastless track slab recasting yard 8.40 0.00 0.00 0.00 8.40

Concrete mixing plant 4.00 2.00 0.00 1.00 7.00

Temporary power line 1.00 0.38 0.00 0.19 1.57

Construction site 0.00 0.00 0.00 5.84 5.84

Temporary tunnel slag piling yard 0.00 0.00 0.00 0.80 0.80

Construction building 0.00 0.00 0.00 5.60 5.60

Subtotal 37.98 31.65 0.00 67.19 136.82

Jiamusi

Spoil ground 0.00 7.18 0.00 6.95 14.13

Construction road 4.95 1.86 0.00 0.93 7.73

Beam construction yard 12.34 0.00 0.00 0.00 12.34

Ballastless track slab recasting yard 0.00 0.00 0.00 0.00 0.00

Concrete mixing plant 3.00 0.00 0.00 0.00 3.00

Temporary power line 0.63 0.24 0.00 0.12 0.99

Construction site 0.00 0.00 0.00 2.32 2.32

Temporary tunnel slag piling yard 0.00 0.00 0.00 0.40 0.40

Construction building 0.00 0.00 0.00 1.60 1.60

Subtotal 20.92 9.27 0.00 12.32 42.51

TotalSpoil ground 71.18 19.19 0.00 127.41 217.78

Construction road 54.65 20.49 0.00 10.25 85.38

Page 69: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Beam construction yard 86.38 37.02 0.00 0.00 123.40

Ballastless track slab recasting yard 25.20 0.00 0.00 0.00 25.20

Concrete mixing plant 23.00 5.00 0.00 1.00 29.00

Temporary power line 4.70 1.76 0.00 0.88 7.34

Construction site 0.00 0.00 0.00 22.68 22.68

Temporary tunnel slag piling yard 0.00 0.00 0.00 3.20 3.20

Construction building 0.00 0.00 0.00 20.80 20.80

Total 265.11 83.46 0.00 186.21 534.78

Percentage 49.57% 15.61% 0.00% 34.82% 100.00

%

(1) According to engineering design, the temporary land occupation cover an area of 534.78 hm2, mainly dry land (265.11 hm2). As a matter of railway construction experience, the foundation of beam storage yards are generally larger in dimension, with serious hardened earth and difficult to recover after construction.

(2) The track laying bases and the material plants which are shallower in operation and are easy to manage may impact local vegetations in case of mishandle, thereby reducing the cultivated lands and reducing the vegetation coverage rate.

(3) Consider arranging the access roads for major projects, borrow earth pits and spoil pits, material storage yards and other construction sites during the construction of the temporary roads in the project design. Totally arrange construction access roads with a length of 202 km in the whole line, including newly-built double lanes with a length of 28.20 km, newly-built single lanes with a length of 149.01 km, rebuilt double lanes with a length of 11.30 km and rebuilt single lanes with a length of 13.49 km, which all cover a total floor area of 85.38 hm2.

(4) The project, which is mainly excavated, is required to respectively excavate and borrow the earth of 485.8×104 m3 and 1604.57×104 m3 except for the use of partial excavations, and the borrow earth pits and spoil pits cover an area of 217.78 hm2. As the water and soil loss are easily produced on borrow earth pits, spoil pits and construction roads, the occupied lands will be largely damaged in absence of protection.

Mitigation measures (1) Increase the proportion of the bridges during the scheme selection providing that technical conditions are satisfied; and ensure that the bridges along the main line have a full length of 172,862.60 m, which accounts for 50.54 % so as to reduce the quantity of the permanent land occupation as much as possible.

Earth and rock engineering should be implemented on principle of reasonable allocation by means of cut to fill as well as full use; and make the best of earthwork from cutting excavation, temporary project and bridge & culvert so as to reduce the earth from borrow pit and spoil pit.

These measures can remit the contradiction between railway construction and land resource protection.

(2) After field investigation and negotiation with county governments along project line and according to railway construction requirements and local actual situation, design company decided that all earth required by this project will be purchased . 12 borrow pits selected for this project are all existing stone pits. Recover low vegetation coverage rate by adopting the measures of reinforcing the protection during the construction and the vegetation recovery after earth excavation and the like after earth excavation to a certain degree as the vegetation is slightly impactd during the earth excavation; and recover or improve the ecological environment within a certain time.

(3) Arrange the borrow pits on the low lands with sparse vegetation so as not to impact the agricultural production and the vegetation in the local. Meanwhile, protect the project and the plants well; and give priority to farmland building and re-cultivation on the earth discarding fields under adequate conditions.

(4) Give priority to permanent and temporary combination in the temporary project and utilize the

Page 70: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

expropriated permanent lands and the used urban lands within the existing sites or the areas as much as possible so as to reduce the newly occupied lands. Ensure that all the arranged temporary material plants use the existing stations along the Binzhou line; and arrange 2 track-laying bases at the Xinxiangfang station in Harbin and the Jiamusi station along the line; and utilize the freight yards in Xinxiangfang and the rebuilt parking lots in Jiamusi so as not to newly increase the temporarily occupation of lands.

(5) Continuously use a small amount of construction access roads taken as the rural roads as the rural road network nearby the project is relatively prefect, and plant trees on two sides so as to green and beautify the environment; recover other construction access roads to be the cultivated lands after the whole lands are tilled and turned or recover the vegetations; recover the original land utilization type and plant undershrubs.

(6) Peel 30-cm-thick surface earth before use in the temporary project for the occupied lands and recover the vegetations after use.

(7) According to the laws and the statutes, etc. regulated in the “Land Administration Law of the Peoples Republic of China”, the “Regulations on the Implementation of the Land Administration Law of the Peoples Republic of China”, the “Measures for the <Land Administration Law of the Peoples Republic of China> implemented by Heilongjiang Province” and the like, let the Employer be responsible for supplementing the cultivated lands in case that the lands are occupied by the project; pay the cultivated land reclamation fee in case that the cultivated lands can not be reclaimed under some conditions and let the unit capable of supplementing the cultivated lands implement the cultivated land supplementing obligation; and let the Provincial Land Administrative Department inspect and accept the supplemented cultivated lands. Pay the land compensation fee, the relocation subsidy, the young crop compensation fee and the like for land requisition for recovering and improving the expropriated farmers’ living standard.

Table 6-20 Regulations on Compensation of expropriated lands

Regulations Land compensation fee Relocation subsidyAttachment and young crop compensation fee

“Measures for the <Land Administration Law of the Peoples Republic of China> implemented by Heilongjiang Province”

Calculate by 4-5 times of average output per mu in the former five years as for the requisition of the basic farmland; and calculate by 3-4 times of average output per mu in the former five years as for the requisition of the general farmland. Additionally regulate by the Autonomous Regional People's Government as for the requisition and the appropriation of grassland and forestland compensation fees

Calculate by 3-5 times of average output per mu in the former five years as for the standard on relocation subsidy of farmers required to be relocated and ensure that the relocation subsidy does not exceed 10 times. Ensure the relocation subsidy of animal husbandry people required to be relocated during the grassland requisition to be higher than the standard on the relocation subsidy of farmers.

Compensate by the value and the practical loss of attachments; and compensate by the output per mu in the current year as for the young crop compensation fee

(8) Basic farmland protection scheme

Modify the overall land utilization planning according to the document approved by the State in case of changing the overall land utilization planning of the lands for the construction of large-scale energy sources, traffic, water resource facilities and other infrastructures approved by the State Council according to the regulations in Article 26 of the “Land Administrative Law”.

Through estimate, the project will cover a basic farmland area of 767.72 hm2 along the line. Because the Employer has no condition to reclaim new cultivated lands, the compensation for the occupied basic farmlands and the occupied cultivated lands will be implemented according to the regulations in the relevant laws and policies from the State and Heilongjiang Province so as to ensure unchanged quantity of the local basic farmlands. Implement the following processes according to the relevant regulations in the “Regulations on the Protection of Basic Farmland” as for the expropriated permanent farmlands:

Transacting the approval process on agricultural land transfer

Page 71: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Implement the basic farmland protection system. According to the regulations in Article 44 of the “Land Administration Law of the Peoples Republic of China” and Article 15 of the “Regulations on the Protection of Basic Farmland”, transact the approval process on agricultural land transfer with the approval of the State Council if the project can not avoid the basic farmland protection area from the view of site selection and must occupy the basic farmlands as well as the agricultural lands are required to be transferred to be the lands for construction.

Paying the cultivated land reclamation fee

According to the regulations in Article 16 of the “Regulations on the Protection of Basic Farmland” that the land occupying unit is responsible for reclaiming the cultivated lands which are equivalent to the occupied farmlands in quantity and quality according to the principle of "Reclaiming the same amount of occupied lands” in case of occupying the basic farmlands approved by the State Council; and if the land occupying unit has no condition to reclaim or the to-be-reclaimed cultivated lands does not comfort to the requirements, he should pay the cultivated land reclamation fee according to the regulations from provinces, autonomous regions and municipalities to reclaim the new cultivated lands, it is preferred that the cultivated land reclamation fee is paid as the Employer is difficult to reclaim the equivalent cultivated lands in quantity and quality due to deficient standby land resources along the line; the quantity of the basic farmlands occupied by the subgrade should be subjected to that affirmed by the local at the next stage; and an equivalent number of cultivated land reclamation fees should be paid.

Disposal for basic farmland cultivated horizon

According to the requirements in Item II, Article 16 of the “Regulations on the Protection of Basic Farmland” that the basic farmland occupying unit should ensure that the earth from the occupied basic farmland cultivated horizon is used for the earth improvement of newly-reclaimed cultivated lands, poor lands or other cultivated lands according to the requirements of the local people's governments at or above the county level, move and transport the 30-cm-thick cultivated horizons on the surfaces of the basic farmlands to the right place during the construction in coordination with the local government; transport the earth from the cultivated horizons to the borrow pits for piling if necessary; and let the Local People's Government use the earth for the earth improvement of newly-reclaimed cultivated lands, poor lands or other cultivated lands.

Basic farmland protection plan

Seriously control and protect the cultivated lands, in particular to the basic farmlands as the land is non-renewable and is taken as the primary resource of national economy and social development and the elementary condition of social and economical development. Seriously implement the cultivated land protection policy, in particular to the basic farmland protection policy and carry out the cultivated land and basic farmland compensation system.

According to the regulations in Article 31 of the “Land Administration Law of the Peoples Republic of China” that the State should carry out the cultivated land compensation system, the Employer should fulfill the occupying-supplementing balance for the occupied basic farmland during the evaluation so as to balance the quantity and the quality of the occupied and the supplemented cultivated lands. Implement the measure that the basic farmlands are evenly occupied and supplemented. Insist on the guideline of increasing income and reducing expenditure and greatly excavate the potential of standby cultivated land resources. Formulate the following basic farmland compensation plan during the evaluation through field investigation:

Agricultural land consolidation: The land consolidation includes both agricultural land① consolidation and non-agricultural land consolidation. The agricultural land consolidation is carried out in combination with low-and medium-yield farmland upgrade and farmland capital construction; and a great deal of low-and medium-yield farmlands are distributed in hilly areas where the project passes through. For example, a great deal of low-and medium-yield farmlands in the hilly areas in Fangzheng and Yilan Counties can be developed and reclaimed.

Non-agricultural land consolidation: The non-agricultural land consolidation refers to the② development and the consolidation of villages in the agricultural land, barren hills, barren ditches, barren hillocks, barren wastes and other odd and waste lands so as to increase the effective utilization area of the cultivated land and other agricultural lands, improve the land output and

Page 72: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

improve the important measures of ecological environment. The agricultural land consolidation can be combined with the comprehensive agricultural development so as to consolidate the lands belonging to one production unit but enclosed in that of another in the agricultural lands, the bad lands, the land barrier factors and other bad conditions according to the sequence of easy first and difficult then step by step, area by area and plot and plot.

Land development and reclaim: It can be realized through developing the easy-to-cultivate③ wild grassland and other lands during the planning according to the practical situations of standby land resources from each city and county along the line. The land reclaim mainly refers to the rectification and the reclamation of waste brick and tile kilns damaged by mining and pressing, industrial and mining wastes and damaged lands.

The balance of occupied and supplemented basic farmlands can be realized in quantity and quality through the above-mentioned plan.

(9) The compensation fee for land requisition is 664,790,770 RMB during the design so as to minimize the impact of the project on the cultivated lands and the basic farmlands.

6.1.2 Impact analysis of project construction on plants and mitigation measures

Impact of fugitive dust during the construction on crops and vegetations and mitigation measuresImpact analysis

The earthwork and the stonework will be excavated and filled during the railway construction; and a great deal of fugitive dust are easily caused in dry season during the construction and covered on neighboring crops, branches and leaves, thereby influencing the photosynthesis and reducing the yield of the crops and the fruit trees. The fugitive dust also will impact the fruit setting during the flowering phase, thereby reducing the yield. The fugitive dust caused during the construction can cause the TSP content in the atmosphere to increase by 0.3-0.8 mg/m3 within 20-50 m away from the construction site due to exposed soil through rough estimate during the construction.

In addition, the fugitive dust caused by transport vehicles, which also can easily impact the crops and the trees on two sides of each construction access road, can be covered on the branches and the leaves, thereby influencing the growth. It is researched and tested that the fugitive dust caused by vehicle bumping can reach 8-10 mg/m3 in short-term concentration on two sides of a traffic lane when the weather is continuously dry and the road conditions are worse. However, the concentration of the fugitive dust can quickly drop along with the increasing distance and can not be impactd beyond down wind of 200 m.

Mitigation measures

1) Adopt relevant measures such as watering or capping for transport vehicles in case of transporting sand, soil, dust and other fugitive dust easy-to-produce building materials so as to prevent the fugitive dust.

2) Manage and maintain the construction roads to keep level road surface; and frequently water the gravels and unsurfaced roads so as to prevent the adverse impact on the vegetations and the crops during the transportation of the fugitive dust.

3) Harden the main roads on the construction site with clay-bound macadam.

4) Cover or harden in case of storing the earth on the construction site in a concentrated manner.

5) Ensure that the construction site is cleaned by specially-assigned persons and provided with corresponding watering devices as well as watered and cleaned so as to reduce the pollution produced by the fugitive dust.

Impact analysis on biomass and mission measuresImpact analysis of project construction on regional biomass

The biomass is used for measuring the function stability of a community, in particular to the function stability of an ecological system and indicating the living organic matter deposited in the unit area of the ecological system during the investigation at a particular moment.

The biomass is lost and reduced due to land occupying and ground vegetation destroying during the project construction, which mainly manifested in two aspects: the project permanently occupies the lands, so that

Page 73: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

the land use nature is changed and the permanent biomass loss is caused, and the project is constructed on the occupied temporary land, so that the ground vegetations are destroyed and the biomass is lost. But, the biomass on the temporarily occupation of lands will be gradually recovered through agriculture reclamation and vegetation recovery after the construction. Refer to Table 5-3-4 for fell trees in the project.

Table 6-21 Summary Table for Fell Trees along Hajia Railway

Project/unit

Mleage

Fell young treesFell trees (Diameter: cm)

Main tree species 6-20 21-40 41-60 61-80

100m2 pc. pc. pc. pc.

CK0+000 CK7+000 90 100 Poplar

CK7+000 CK51+000 290 1390 260 30 Poplar

CK51+000 CK70+400 1500 1100 Poplar

CK70+400 CK178+500 430 640 200 Poplar

CK178+500 CK219+500 5.5 780 150 Poplar

CK219+500 CK259+000 500 260 Poplar

CK259+000 CK325+000 14.45 3030 1840 100 Poplar

CK325+000 CK338+67092.20 Poplar

12410 5290 240 Poplar

Total 112.15 19030 10770 800 30

Totally fall 30,630 trees in the project, including 19,030 trees with the diameter of 6-20 cm, 10,770 trees with the diameter of 21-4 cm, 800 trees with the diameter of 41-60 cm and 30 trees with the diameter of 61-80 cm. In addition, fall 11,215-m2 nurseries with the diameter of below 6 cm. The fell tree species is mainly subjected to poplar and a small quantity of fruit trees. The fell trees are mainly distributed in Fangzheng County, Yilan County and Jiamusi suburbs.

Investigate the community biomass by adopting the biocoenology method and calculate it according to the sample community type. Calculate the community biomass on the arborous layer by adopting the average sample tree method. The biomass of each community during the evaluation is changed along with different site conditions.

Calculation formula: W=S ( W ' / S ' )

Where: S-basal area of total sample trees;

W', S'-weight and basal area of samples

Calculate the weight and the total quantity of trunks, branches and leaves according to the above formula. Determine the biomass on the shrub layers and the herbaceous layers by adopting the full harvest method through weighing the gross dry weight. Refer to Table 5-3-21 (indicated by dry weight) for biomass sample investigation results of main community type in the project. Calculate the lost biomass on the basis of occupied permanent floor area and occupied temporary floor area of vegetations and calculated as well as the unit area of different vegetations.

Refer to Table 5-3-5 for biomass loss of each community caused by permanently occupation of lands and temporarily occupation of lands in the project.

Table 6-22 Computation Table for Biomass Loss of each Community

Community Type Area (hm2) Site

conditions Plant species Biomass (t/hm2) Total biomass (t)

Secondary forest 502.2 Good Poplar, etc. 12.5 6277.5

Page 74: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Wild grassland 74.48 Common Guinea grass and weeds 1.5 111.72

Orchard 8.37 Good Apple, etc. 16 133.92

Crops 1167.82 Good Corn, rice and sorghum, etc. 19.6 22889.27

Total 1752.87 / / / 29412.41

The project will occupy a permanent and temporary vegetation area of 1,752.87 hm2 during the construction and cause 29,412.41-t total biomass loss.

Mitigation measures

1) Tree transplant and compensation

Further determine the species and the quantity of the fell trees at the next stage and transplant if the trees are protected by the State and the Local during the design and construction process. Transplant the young trees which are suitable for being transplanted or the trees which have larger economic value. Carry out mutual compensation (including mutual complementary planting or monetary compensation) to the trees which have small transplanting value or are not suitable for being transplanted on the principle of equivalent compensation under local forest department’s direction in accordance with national and local compensation standard. Contact the Local Forestry Department at the next stage to further detail the mutual complementary planting or monetary compensation scheme. Locally select the unused land and the suitable land for forest to replant on the principle of balanced occupation and compensation. Ensure that the area of newly-planted forests is larger than that of forests occupied by the project as the forest compensation is on the principle of biomass equivalence compensation. Select the suitable land for forest in other places for forestation in case that the unused land and the suitable land for forest are not enough so as to ensure unchanged total forestry land.

2) Subgrade side-slope greening

Protect by planting the Amorpha when the embankment side-slope has a height of below 2 m. Protect by adopting 3×3-m cement mortar coffer stone arch type framework with a water intercepting trench, wherein the framework, in which the Amorpha is planted, has a thickness of 0.6 m.

3) Station and living quarter greening

Protect the newly-built embankment side-slope through planting; plant trees in open places on two sides of the newly-built subgrade for greening and combine the greening trees with local weather and natural environment; and arrange flower beds at the newly-built stations so as to beautify the environment.

In addition, compensate the lost biomass by greening the soil excavating and discarding fields in the project; and let the Land Department to reclaim in other places after the Employer pays the cultivated land reclamation fee in case that the reduced crop biomass is caused by engineering construction so as to ensure unchanged biomass after the completion of the project.

Newly plant 375,510 arbors and 43,729,360 shrubs along the whole line in the project by adopting the measures of planting on the subgrade side-slope, planting the arbors and the shrubs and greening the temporary fields and the soil (slag) discarding fields; and ensure that the seeding, planting and greening area reaches 237.52 hm2.

Through implementing these measures, the ecological environment along the line also can be improved.

4) Selection principle of greening trees

Adopt a series of slope protecting and greening works for existing railways and highways according to geographic and geomorphic conditions, weather, soil, water and soil loss causes and other environmental conditions of the project so as to obtain good impact.

Bring forward the selection principle of tree and grass species at this section in combination with local natural conditions and many years of relevant experience:

Page 75: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Arbor: Poplar, willows, pinus sylvestris and larch, etc.; and the greening seedling can select cedars and① spruces, etc.

Shrub: Shrub willows, Amorpha, Lespedeza, caragana, sallow thorn, poplar willows and Salix② sungkianica, etc.; and the greening seedling can select cloves, privets, green fence and purple leaf barberries, etc.

Grass seed: Ryegrass, annual meadowgrass, alfalfa, chinese wildrye, Astragalus adsurgens and③ daghestan sweetclover.

Observe the growth rhythm of natural vegetations during the greening, adjust measures according to local conditions and match species with the site. Give priority to local plants and then select the plants introduced successfully; give priority to deciduous and broad trees, simultaneously and properly combine evergreen conifer trees and then prepare arbors, shrubs and ground cover plants, etc. for viewing leaves, flowers, fruits, stems, branches and barks so as to form rich seasonal aspect.

Impact analysis on rare plants and old and famous trees

Impact analysis

Three Class-II State protected key wild plants, namely linden, manchurian China ash and amur corktree, are discovered in the process of preliminarily investigating the rare plants and the old and famous trees. In addition, numbered old and famous trees are not discovered within the evaluation area. Refer to the diagram for distribution position relation between newly-built Hajia railway and protected key wild plants in Heilongjiang Province.

Mitigation measures

1) Avoid the State protected wild plants and the old and famous trees, etc. on two sides of the railway within the impact range during the next design phase as much as possible; employ professional personnel to identify the protected plants before surface cleaning; and move, transplant and adopt other relevant protection measures for unavoidable protected plants.

2) Train constructors about environment protection before construction to teach them how to protect the protected wild plants; distribute relevant pictures; and additionally strengthen the propagandizing and teaching works in a manner of issuing brochures and pictures, etc. or organizing constructors’ representatives to learn. Strengthen the propagandizing and teaching works about the protection of the protected wild plants, formulate relevant regulations and supervisory systems, and forbid the constructors to randomly destroy the vegetation activities. Immediately report and cooperate with the Forestry Department to protect or transplant the discovered protected plants.

Page 76: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-13 Diagram for Distribution Position Relation between Newly-built Hajia Railway and Protected Key Wild Plants in Heilongjiang Province

6.1.3 Impact of project construction on animals and mitigation measures

Impact on terrestrial animals and mitigation measuresImpact assessment

Form the barrier impact due to railway construction and operation, improve the habitat fragmentation degree, increase the patch quantity and enhance the heterogeneity, so that the population of the terrestrial wild animals is divided, and their activity range is impactd.

The damage of railway construction to animal habitat is mainly manifested in two aspects, namely railway route selection and construction period. As the railway construction is a trans-regional and trans-basin project, and the animal field has to be divided, the large area required by the animals for living is divided into small areas, so that the natural habitat, the growth, the reproduction and the activity place of the

Page 77: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

animals are damaged, the living environment of the animals is threatened, and the animals can not obtain enough foods and information.

In addition, the railway self as well as the temporary facilities, the temporary houses and the soil excavating and discarding fields during the construction occupies some land; and the natural environment is damaged by the disturbance caused by excavating the cut, filling the embankment and tunneling to ground surface, so that the animal habitat is damaged to a certain degree.

Mitigation measures

Realize the coordinated development of railway construction and ecological behavior of the animals by adopting systematic and all-around protective measures in the railway planning, designing, constructing, operating process to minimize the impact of the railway construction on the ecological behavior of the animals.

Selecting optimal line

Main animal habitat along the line as well as natural reserve and other areas with relatively rich wild animal resources is not related in the project; and bridges or tunnels should be arranged for water bodies, hilly areas and other sensitive sections to ensure smaller barrier impact and satisfy the walking demands of nearby animals.

Strengthening the management

The management adopts a man-made measure and is related to railway construction and ecological behavior of the animals in the project. The railway planning should not only satisfy the economic demand, but also satisfy the social and environmental protection demands; and the railway construction and operation should be explicitly regulated and seriously implemented. Meanwhile, warning signs should be arranged at the nearby road sections where the animals come and go.

The farmlands, the residential areas and hills, etc. are mainly distributed along the line, the human interference factors are larger, the habitat is seriously damaged and the natural ecosystem is slightly conserved. Thereby, there are poor animal resources and unstable habitats of large-scale animals in areas where the line passes through; and national protected key animals (Refer to Fig. 5-3-1) are not seen during the filed investigation. The national protected animals mainly depend on birds, and most of birds with wider habitat are travelers, which are not propagated along the line and confined at a certain place, so that the impact is less.

Page 78: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-14 Diagram for Mutual Distribution Position Relation between Hajia Railway and Protected Key Animals in Heilongjiang Province

Impact evaluation of noise during the railway construction and operation on bird habitation and breedingThe impact of the noise on the birds is mainly manifested as follows: the noise may lead the birds to lose the nesting sites, so that the bird breeding, the food chain and the migration route, etc. are changed.

Impact of noise on birds: the foreign study shows that the sensitive range of the birds to the noise is basically similar to that of people. However, the birds can not hear the low frequency noise like people under the usual conditions, and their optimal hearing threshold is 1-5 kHZ, and the birds can adapt the noise due to great endurance to the noise.

The ambient background noise level (such as leave trembling) beyond the bird habitats is 45 dB averagely, and the background noise level in the bird nests is 56-60 dB generally. According to some data concerned, the birds in the bird nests can not be impactd by the noise when the noise level is 60 dB. According to the results observed by foreign scholars, the birds in the bird nests will be impactd by the

Page 79: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

noise when the maximum sound level L max in the nests is more than 60 dB(A).

Bulldozers, excavators, construction machines and other fixed sources as well as concrete agitator trucks, road rollers, various transport vehicles and other mobile sources will generate strong noise during the project construction. Through taking heavy cranes with higher sound level A for example, the noise source level is 90 dBA, which can weaken to 60 dBA at 315 m without any blockage.

Through field investigation, some birds breeding in the evaluation area such as corvidae, fringillidae and other birds will cause the disappearance and the migration of breeding places in the occupied areas due to construction. As the breeding birds in the evaluation area have less varies and larger interference factor, the impact on the breeding birds is less. The foraging of partial birds in the occupied areas will interfered during the construction, so that the foraging place is slightly transferred.

The weak night light from motor vehicles will have less impact on the habitat of phototactic birds and other animals during the operation.

In conclusion, due to the adaptability of the birds to the noise and the position relation between the project and the habitat and breeding place of the protected birds as well as the social and natural activities nearby the proposed railway, the habitat and breeding of the protected birds can not be impactd for a long time during the construction through investigating relevant similar projects.

Impact evaluation of project construction on rare animals along the lineThrough carrying out filed investigation and consulting relevant data, there are 28 protected species along the line. There are 26 bird species, including 20 Class II state protected birds and 6 Heilongjiang provincial protected birds; and there are 2 provincial protected reptiles.

Refer to Table 5-3-6 for the distribution of protected animals along the line and the impact analysis of the project for details.

Table 6-23 Protected Animals in the Evaluation Area and Impact Analysis of the Project

Ser. No. Species Name Relation between main habitat and proposed project Protection

Class

Birds

1 Accipiter gentilis

They are distributed in the forests and the hilly regions along the line and nested on the tall trees in the forests. Because the areas where the line passes through are mostly parallel to Tongsan Highway and other existing roads or are positioned in a same channel, the hilly areas where the line passes through mostly pass through in a tunnel manner; and their suitable nesting environment is not discovered through field investigation, so that the project will not impact the habitat and the breeding of these birds basically.

Class-II State Protection

2 Accipiter nisus Class-II State Protection

3 Accipiter gularis Class-II State Protection

4 Buteo buteo Class-II State Protection

5 Buteo lagopus Class-II State Protection

6 Strix uralensis Class-II State Protection

7 Asio otus Class-II State Protection

8 Falco amurensis Class-II State Protection

9 Falco tinnunculus

10 Milvus migrans

Page 80: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

11 Circus melanoleucos

They are inhabited on wide low hills, plains at the foots of mountains, grasslands, open fields, river valleys, marshes, bushes in the forest and marsh grasslands and also move in the farmlands and the cultivated lands as well as the grasslands and the forests nearby the villages after breeding sometimes. They are mostly nested on the haystacks on the tower heads of the shrub meadows in the open forests or the ground. They mainly move on the bank of Songhua River through consulting local people.

Class-II State Protection

12 B. hemilasius

They are generally nested on the cliffs or the trees, and its nest is protected by small shrubs. Their activity areas are mainly distributed along the line, where the population quantity is extremely rare. There is no suitable breeding environment along the line.

Class-II State Protection

13 Falco columbarius

They are generally nested on the trees or the cliffs and also nested on the ground sometimes. They particularly like occupying the old nests of crows, magpies and other birds and move in the waste lands and other unused lands along the line sometimes.

Class-II State Protection

14 Bubo bubo

They are nested in the tree holes and at the recessions under the cliffs or directly laid at the recessions on the ground. Their activity areas are distributed along the line, and there is no suitable breeding environment.

Class-II State Protection

15 Asio otus

They, which are nested in the forest and also nested in the tree holes, generally utilize the old nests of crows, magpies and other birds. Their activity areas are distributed along the line, and there is no suitable breeding environment.

Class-II State Protection

16 Asio flammeus

They are nested in the grass nearby the marshes as well as in rotten tree holes in the secondary broad-leaved forest. The grassland habitat along the line is less, most of cultivated lands are distributed on the periphery, and the human interference factors are stronger, so that the project will slightly impact the Asio flammeus.

Class-II State Protection

17 Circus cyaneus

They are mainly inhabited on the ground of dry reeds on the bank of Songhua River, grasslands or bushes. The inhabit suitable for the Circus cyaneus to nest along the line is less, and the populative structure of the Circus cyaneus in this area during the breeding period is not damaged basically, so that the project will slightly impact the Circus cyaneus.

Class-II State Protection

18 Circus spilonotus They are mainly inhabited in low-humidity regions. The inhabit along the line is less, and there is no inhabit suitable for the Circus spilonotus to nest due to frequent human farming activities nearby the farmlands, so that the project will not impact the

Class-II State Protection

Page 81: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Circus spilonotus.

19 Aix galericulataThey are mainly distributed in the water areas of Songhua River and are not distributed at the river sections in the project crossing areas.

Class-II State Protection

20 Bonasa bonasia

They, which are mainly nested at the base of the trees, are also nested on the sunny slopes, at the primary water sections and under the fallen trees and are mainly distributed in the broad-leaf forest in Fangzheng County, are far away from the line, so that the project will not impact the Bonasa bonasia.

Class-II State Protection

21 Dryocopus martius They are nested in the conifer forests and have wider inhabitation range, so that the project will not impact the Dryocopus martius.

Provincial Protection

22 Anser fabalis

They are distributed on the bank of Songhua River sometimes and nested on the ground; and there is no suitable nesting environment in the impact area, so that the project will not impact the Anser fabalis.

Provincial Protection

23 Hirundo rusticaThey basically belong to a natural bird living together with people, so that the project will not impact the Hirundo daurica.

Provincial Protection

24 Hirundo daurica Provincial Protection

25 Lanius sphenocercus

They are inhabited in the forests and the bushes; a certain area of bushes will be fell in the project; the Lanius sphenocercus and the Cyanopica cyana utilize other ecological niches suitable for inhabit to breed; and two species of birds have stronger adaptability, so that the project will not impact the Cyanopica cyana basically.

Provincial Protection

26 Cyanopica cyana Provincial Protection

Reptiles

27 Takydromus wolteriWith smaller activity areas, they are inhabited in the bushes under the mountains and are not distributed in the evaluation area.

Provincial Protection

28 Agkistrodon saxatilis

They are inhabited on the sunny slopes, which are also discovered on the forest edges and are commonly discovered in the stone cracks on the bank of rivers. They are not distributed in the evaluation area.

Provincial Protection

Page 82: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-15 Diagram for Mutual Distribution Position Relation between Hajia Railway and Class-I State Protected Animals in Heilongjiang Province

Page 83: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-16 Diagram for Mutual Distribution Position Relation between Hajia Railway and Class-II State Protected Animals in Heilongjiang Province

According to the investigation on reptile resources along the line and the distribution of rare animal resources in Heilongjiang Province, the areas where the proposed Hajia railway passes through belong to IC3 (Songliao Plain Area) and IC4 (Changbai Mountain and Lesser Khingan Mountain Area) from the view of zoogeographical division. The above analysis results show that the proposed project does not belongs to the distribution area of State protected mammals and Class-I State protected birds and only relates to the distribution area of a small quantity of Class-II State protected birds and partial Heilongjiang Provincial Protected animals.

In order to avoid many ecological interference factors (visual interference and noise interference, etc., in particular to traffic noise and vibration impact) generated by railway construction and operation, the habitats of the animals should be far away from the railway during the selection, i.e. the inhabit selection of the animals will be changed due to the existence of the railway to avoid the inhabits and transfer the nests. Because the linear project only occupies about 30-m-wide long and narrow area, and Tongsan

Page 84: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Highway, national highway G221 and other existing roads are adjacent in the channel, there is no inhabiting and breeding rare and endangered animal basically along the proposed project. In addition, artificial forests, wet lands and other suitable habitats are arranged along the line so as to satisfy the inhabiting, foraging and breeding demands of above birds and other animals. Thereby, the distribution of the protected animals in this area can not be impactd by the habitat avoidance of partial population during the evaluation.

Mitigation measures

Strengthen the management during the construction, reasonably arrange the construction time, avoid the morning-evening peak of the birds during the process of protecting the birds; strengthen the propaganda and the education of constructors, enhance the awareness of protecting the animals and forbid to catch the birds and collect the eggs.

6.1.4 Impact analysis on ecological protection zone The Harbin-Jiamusi rail line to be built will pass through the following areas: the downtown of Harbin and the agricultural ecology area in the suburb( 5-1-1), the Mayi River downstream, the agriculture andⅠ soil maintaining ecology area ( 4-2-5), the ecology area of agriculture and animal husbandry and soilⅠ maintaining of Woken River downstream ( 3-2-4), the ecology area of city and agriculture in Jiamusi ( 3-Ⅰ Ⅰ1-1).

Analysis of the project impact on Harbin and suburb agricultural ecology area The project passes through this ecology area from the designed starting spot (the Harbin station) to the nearby (BJCK0-CK62). Harbin-Jiamusi rail line in this region mainly involves in bridge and roadbed construction. And the length of bridge is approximately 29.02km, composing about 46.8% of the total length in this section. The use of large-proportioned bridge will to a certain extent diminish the destruction to the local agricultural production, coordinating with the agricultural ecology area.

In this section, the volume of living water is little, which will not intensify the excessive picking of ground water of the city. The project will destroy the vegetation for a certain area, but it will compensate to vegetation’s destruction in a large degree with the finished temporary land’s reclamation, afforestation, the afforestation toward the transplanted arbors and shrubs and such grass on both sides or the roadbed side slope. Therefore, it will not be obvious to the urbanized warming impact. In the Binxi station and the Bin County station, sanitary sewage respectively is 10m3/d, 21m3/d, entering sewage treatment plant after the septic tank processing, the sewage water quality satisfying “Sewage Synthesis Emission standard” (GB8978-1996) the third-level standard, which will not affect the water quality of the Songhua River. In this section, the coal boiler is used, with the standardized air pollutant emissions, nearly not influencing Harbin’s winter mist and dust pollution. Based on the above possible environmental problems the railroad may produce and the ecology area faces, there is the assessment that the project will not affect the ecology function area.

Impact analysis of the project toward the Mayi River downstream, the agriculture and soil maintaining ecology area This project passes through this ecology area from Bin County nearby (CK62) to the about spot (CK245), 8km from the south west of Yilan County. Harbin-Jiamusi rail line in this region mainly includes bridge, roadbed and tunneling, with the bridge about 93.9km in length, approximately composing 51.3% of the total length in this section. The designing of large-proportioned bridge will to a certain extent diminish the destruction to the local agricultural production and the backfilling of the bridge waste(dregs) will reduce the soil erosion, both coordinating with the agriculture and soil maintaining ecology area.

The main ecological environment problems are that the slope farming soil are mostly albic soil, with poor water permeability, extremely easy to cause the soil erosion; The quality of the forest is relatively bad and the ecosystem service function is weak. In addition, in the area the Mayi River basin is the extremely important area for the soil maintenance. The construction will inevitably bring about the soil erosion to a certain extent, but with the end of the construction perturbation's conclusion, the soil erosion will be effectively controlled with the implementation of the construction and plant-protecting measures on both sides of the railroad. Besides, it is appraised the soil erosion in this section.

Page 85: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Impact analysis of the project toward the Woken River downstream, the agriculture, animal husbandry and soil maintaining ecology area This project passes through this ecology area from the spot (CK245), about 8km from the southwest of Yilan County southwest to the point (CK297), about 10km from the northeast of Hongkeli Station. Harbin-Jiamusi rail line in this region mainly includes bridge, roadbed and tunneling, with the bridge about 26.8km in length, approximately composing 51.5% of the total length in this section. The designing of large-proportioned bridge will to a certain extent diminish the destruction to the local agricultural production and the backfilling of the bridge waste(dregs) will reduce the soil erosion, both coordinating with the agriculture and soil maintaining ecology area.

The main ecological environment are the following: The multiple-crop index of agriculture is high and so is the agriculturally-used chemical’s investment, and also the surface source of pollution is relatively serious; The vegetation coverage fraction is low and soil erosion is in existence. In the area the Songhua River basin, the Woken River basin and the Mudanjiang basin are the extremely vital areas for soil maintaining. This area is moderately sensitive area for soil erosion.

Collectively connecting with the ecological environment problems in this area, the main impact of the project on this ecology area is soil erosion in the construction period, but which does not involve in the desertification-controlled vital areas of the soil. Therefore there is the assessment thought that the conservation of water and soil should be strengthened for this section in the construction period so as to reduce the quantity of soil erosion.

Impact analysis of the project on the Jiamusi towns and agricultural ecology areaThis project passes through the northwest of the ecology area from the spot (CK297) about 10km from Hongkeli Station to the end point (CK338+670), Jiamusi Station, which does not cover the highly sensitive areas of biodiversity and sensitivities or water polluted moderately sensitive areas along Songhua River basin. It is thought that the main impact of the project on this ecology area is the possible soil erosion to a certain extent. Harbin-Jiamusi rail line in this region mainly includes bridge, roadbed and tunneling, with the bridge about 22.09km in length, approximately composing 53.01% of the total length in this section. The use of large-proportioned bridge will to a certain extent diminish the destruction to the local agricultural production, coordinating with the agricultural ecology area.

6.1.5 Environmental impact analysis and mitigation measures of roadbed project

Impact analysisThis design includes 487 individual roadbed construction sites, with the total length of 150.142km, occupying 44.54% of the newly-built total length. The construction types are mainly the moat slope protection and the deep cuts, sticky earth embankment, the soft ground embankment and so on. For details sees Table 5-3-7.

Table 6-24 special roadbed construction point list

Serial number Type Length(km) Construction number(spots)1 Embankment slope

proofing 18.168 101

2 Low embankment slope 7.652 20

3 Sticky earth embankment 31.772 131

4 Soft ground embankment 15.537 46

5 Moat slope proofing and deep cuts 64.973 168

Page 86: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

6 Inflation cuts 3.964 9

7 Cuts along the level 1.026 3

8 Groundwater cuts 0.854 2

9 Soaking embankment 4.966 7

Sum 150.142 487

Before the slope protection project completes, the roadbed slope face will meet with the following outcomes if not protected properly, especially after the cross section excavated: If in storms, it is easy to wash the slope face, bring about soil erosion, cause the side slope to collapse so as to possibly destroy and even wash away the vegetation and the farmland nearby the roadbed, and also possible to cause that has embankment near the rivers to stop up, to compress the rivers and the drainage ditch.

Mitigation measures

Related protection is done to different side slopes and both sides of the roadbed on the condition that it is safe and stable for the entire roadbed, stations, and the principal part of bridges and ditches. And the perfect dewatering excavation is designed to on both sides of the line and the stations, with high-standard designing and satisfactory water-passing capability.

Protection of the slope face of embankment

The protection of the slope face of embankment should act according to the height and padding nature and the like of the embankment. The identical labor usually uses the identical protection forms and in ordinary circumstance the following protection is used:

1) The qualified padding is filled to the low embankment 2.7m below the roadbed face according to the foundation-bed requirement.

2) The slope face of low embankment uses the planted amorpha fruticosa to protect.

3) The common embankment with the height H≥2.5m, uses 3×3m concrete arch-type skeleton of the C25 belt shutting to protection, with skeleton thickness 0.6m, and amorpha fruticosas planted in the skeleton. When the embankment is higher than 5m, every other 0.6m a bidirectional earthwork grill is laid down from the toe of slope to the foundation-bed surface layer, horizontal width 3.0m.

Water immersing embankment

1) Pit immersion

Protection elevation is equal to pit bank elevation and 0.3m. Protection berms in elevation place are designed together considering the berms with freezing and inflating-proof berms, with the width 2.0-3m. Above the elevation, the side slope of embankment is designed according to the common embankment. Below the elevation, the side slope of embankment can degrade a level. Below the elevation water is pumped, silt is digged and water infiltrating soil is reclaimed.

2)Bridge head immersion

The protection elevation is equal to the many-year meeting design level, the height of attacking waves, backwater height and 0.5m. The protection berms in elevation place are designed with the width 2.0-4m. Above the elevation, the side slope of embankment is designed according to the common embankment. Below the elevation, the side slope of embankment can degrade a level. Below the elevation water infiltrating soil is reclaimed. In the pumping difficult section, slabstone is thrown and filled from below general water level plusing 0.5m. In the protection berms and the slope face below them and M7.5 cement mortar slabstone or dry slabstones of 0.3m in thickness are used to protect the slope. Under the protection slope is crushed stone layer, with the thickness 0.15m and the foundation pattern basis is determined according to washout depth. Generally the bucket foundation is adopted: The bottom extends to 0.6m, with burying depth 1.0m. Above the protection elevation, the protection is carried on according to the principles of the slope face protection of embankment. In the shoal place, when the speed of flow is bigger than 4m/s, it is considered to thicken the layers of the slope with mortar slabstones. In the section, when

Page 87: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

the washout depth is bigger than 0.5m, the foot wall foundation is established.

Deep cut and moat slope protection

1) The slope of cut slope basis is established according to engineering geology and the hydrogeological conditions, the ground category, the side slope altitude, combining with the factors, rock mass structure, structural plane occurrence, decency degree and so on.

2) Moat slope protection: The slope of cut generally uses M7.5 to back the wall and the slope with mortar slabstone and the skeleton. To the moat slope higher than 25m highly or the steep rock moat slope, generally the gravity bulkhead wall is used to reinforce or the pile wooden fence is used to pull the slope.

Inflation earth cuts

In this section, the inflation earth is mainly located along Dalian River~Ilan (CK245+470~CK248+520), geologically belonging to late third system and mudstone under the Cretaceous system and between the spot Korean hat ~ Jiamusi (CK306+600~CK327+200) in the Cretaceous system the series tuff entire regolith, with the weak ~ strong expansibility.

1) The 0.4m graded broken stone is filled to the foundation-bed surface layer and to the bottom 2.3m non-heave padding is filled. In the lower part of the foundation-bed surface layer is established two-pieces-of-cloth and one-membrane airtight water and earth worker cloth(600g/m2), with high and low respectively coarse sand breaker strip, 0.1m and 0.05m in thickness.

2) When the side slope of cut is smaller than 10m in length, at the toe of slope is designed a 2~4m high retaining wall, the retaining wall slope 1:0.25. Behind the wall, is designed crushed stone inverted filter of granulated clamp, 0.5m in thickness. Behind the top wall, a 2m wide platform is designed, above it moat slope 1:1.5~1:2, one level every 6m, between two levels the side slope platform 2~3m wide and 0.4m thick; The slope face uses 3×3m the belt shutting arch-type skeleton, in the skeleton lays down the C25 concretes hexagon hollow slug, in the block amorpha fruticosa planted to protect.

3) When the moat slope of inflation earth cut is higher than 10m, the pre-reinforcement anchor pile is designed at the toe of slope, pile 8m long. The moat slope above top moat is 1:2, one level every 6m, between two levels the side slope platform 3m wide and 0.4m thick; The slope face uses 3×3m the belt shutting arch-type skeleton, in the skeleton lays down the C25 concretes hexagon hollow slug, in the block amorpha fruticosa planted to protect.

Soft ground embankment and sticky earth embankment

1) Qualified padding and attacks roller compaction processing is adopted as loose soft soil and loose, slightly dense granulated substance class earth is located within 2.0m of the surface, at the same time above underground water level. And forced tamping is used when surface element earth fill, mixed filling earth and common sticky earth is located within 2.0~4.0m scope of the surface and at the same time above underground water level. After the tamping, on the top is laid down the 0.5m thick crushed stone breaker strip.

2) When the loose soft soil and sticky earth depth are bigger than 4m, the CFG pile reinforcement is generally used, with the computed length of the pile long basis, and in principle penetrating the weak level to the hard bottom. Regarding the soil texture stratum of the fourth system, it should be inserted into the granulated soil layer or the hard plastic viscosity earth, with the general depth not smaller than 2.0m. The entire regolith not less than 0.5m should be inserted into the underlying bedrock section. Subsidence examination should be carried on to the bedrock entire regolith of loose and low modulus compression. The processing scope is between two toes of slope (not including the lower part of non-heave berms), with CFG pile 0.5m in diameter, the square arrangement, spacing 1.5m, the head of pile having breaker strip, 0.6m in thickness (crushed stone 0.15 +sand mat 0.3 +crushed stone breaker strips 0.15), in the breaker strip laying down 2 earthwork grills (tensile strength 100kN/m). When the pile is longer than 20m, the reinforced concrete pile cap is added to the top of the pile, 1×1m in size, and 0.35 in thickness.

Earth-retaining wall

1) In the embankment section, the weak toe of slope should be filled to pull the embankment to avoid the thin strip roadbed or to avoid the embankment taking up or pressing the existed buildings such as the

Page 88: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

designed road shoulders or embankment earth-retaining wall by constructing road shoulders or the embankment breast wall and so on. In the cut section, the breast walls are designed to reduce the height of the side slope, to guarantee stability of slope and reduce the excavation of cubic meter of earth and stone.

2) The embankment wall or cut wall between the sections is mainly gravity-typed. In the station the breast wall should be of the reinforced concrete cantilever or the buttress type. In the horizontal -longitudinal project of Jiamusi key transportation systems, gravity-typed breast walls are designed on both sides of approach of the intersected bridges. When the supporting capacity of the breast wall basis can not meet the requirement, reinforcement processing should be carried on regarding the ground situation.

Seasonal frozen earth roadbed

This section lies in severely cold area, so the freezing precaution is the key point in the designing of the embankment, for which the following measures are adopted: the limitation of the embankment minimum altitude, improving of roadbed padding or foundation-bed structure, establishment of aquiclude and the elimination of table water and ground water and so on.

1) Limitation of the embankment minimum altitude

The height of the embankment should be in principle bigger than freezing depth +0.5m. The road shoulder in the yearly water-accumulated areas should be above the ordinary water level and not smaller than freezing depth +0.5m.

2) Improving of the embankment padding

Fine-grain content control of the foundation-bed surface layer should be strengthened. Based on “Passenger transportation Special line Foundation-bed Surface layer Graded broken stone Temporary Engineering factor”, the foundation-bed surface layer padding should simultaneously satisfy: The fine-grain (pellet particle size ≤0.075mm), the content is smaller than 5%, smaller than 7% after compaction; the post-compaction soaking coefficient is not smaller than 5×10-5m/s.

Group of A and B of non-heave padding is filled to the foundation embankment including the upper of the culvert and the non-heave padding is the fine-grain (pellet particle size ≤0.075mm); the content is smaller than 5% and smaller than 7% after compaction; the post-compaction soaking coefficient is not smaller than 5×10-5m/s.

3) Establishment of the aquiclude

In the lower part of the foundation-bed surface layer is established two-pieces-of-cloth and one-membrane airtight water and earthworker cloth, with high and low coarse sand breaker strip, respectively 0.1m and 0.05m in thickness.

Subgrade drainage principle of designing

Page 89: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

1) To reduce the investment of strengthening works, the drain should be designed depending on the geographical conditions. It is better to choose good places in geology. The outlet of drainage should be connected to the natural ditch river, avoiding irrigation of the farmland directly. When the ground transversal grade is not obvious, it is necessary to construct outlet on both sides of the embankment. The plane of drainage should use the straight line as far as possible. Its radius is not smaller than 10~20m, if curve is necessary. The length of the drainage is decided according to the actual need, usually suitably in 500m. The lengthwise grade of the drainage is not smaller than 2 ‰. The grade can be reduced to 1 ‰, only in the special difficult situation, as smooth ground or counter-slope draining. The cross section should be carried on the computation according to the capacity of 1/50 flood frequency .The most light-sized of the drainage is 0.6×0.6m, the side slope 1:1, it should be defended with mortar rubble masonry 0.3m M7 in thickness.

2) One-sided or the two-sided gutter is established outside the edge 5m of the cut .The lengthwise grade is not smaller than 2 ‰. In the deep cuts made of different stratum, catch drain is established on the platform of the middle of side slope or in the dividing places of the different stratum. The rectangular side-gutter, 0.6m wide and 0.8m deep, is adopted in the soft crag cuts, the strong decency flinty crag cut and the soil cuts, using the concrete prefabricated component in masonry building or using the slabstone concrete for scene watering construction. On one side of the line, water emitting hole should be reserved and concrete top panel should be added to. In the side-gutters listed above, the drain gutter and the catch drain of the side slope platform, M7.5 mortar slabstone or the C15 concrete prefabricated component is used in masonry building.

Embankment temporary protective measures

Temporary steep slope excavation protective measure

When excavating the roadbed on the steep slope, the iron wire netting should be used to carry on obstruction and excavation the cubic meter of earth and stone under the slope, avoiding the destruction of downstream vegetation, the farmland and the traffic equipment. The netting is 2m in height. It should be fixed in the roadbed downhill to uses the boundary place. Line (1:2000) and the line profile diagram (1:2000). The length of the roadbed for iron netting is 60.47km. Among them, Harbin 4.40km, Bin County 18.50km, Fangzheng County 20.16km, Yilan County 7.40km, and Jiamusi 10.01km.

Temporary draining water measure in roadbed construction

The engineering project locates in the area where the precipitation mainly focuses from June to September. Therefore, the temporary draining water measure is not allowed to be ignored in the roadbed construction.

In fill section, chute should be established every other 50m over the edge of the roadbed’s two sides. In the section of partly digging and partly filling, chute should also be established every other 30m .The two has the loudspeaker shape of the mouth. Chute should be closely connected with the waterproof platform with the trough width 0. 5m, depth 0.5m. Lower part the chute along the roadbed direction should be build with earth drainage. The mouth of the cross section is 0.9m wide and 0.3m deep, the mouth of the bottom extends 0.3m and the side slope 1:1. The chute should be installed with the earth knitting bag, laid down along the side slope. The install should guarantee that the knitting bag joint is close and smooth, and meets with the earth drainage. It makes discharge of the rain water smoothly from the roadbed scope to natural draining system. The earth loading knitting bags should be abandoned to neighbored dregs field. Sedimentation basin should be built every other 100m, its size is: 1.5m×3m×1m. Sand collector silt in the basin should be cleaned up and taken away regularly in the construction period so as to subside the runoff

Page 90: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

silt and reduce the runoff speed of flow.

In order to prevent the rain water of the embankment from flowing off willfully, washing away the side slope, both sides of the filling embankment, (or partly digs partly fills in roadbed flank), a long strip waterproof ridge should be established in the place of the road shoulder. Size for the cross section is: top width0.3m, 0.5m high, pitch 1:0.5. It should be connected with the trumpet of the chute after being strengthened. It can gather rain water to chute and discharge them.

Outside the earth or stone excavation section, roadbed draining water should be considered about the temporary and permanent impact. Firstly draining gutter should be constructed to prevent the external catchment of water from washing the excavated slope in rainy season.

This time altogether 51.52km of water-resisting ridge is established and 34.35km earth knitting bags for current ridge is designed.

Temporary protective measures of regolith

This time the peeled surface soil from the roadbed is used in afforesting along the route and secondary ploughing in abandoned dregs field. Therefore, the stripped regolith should be collectively piled in the roadbed land-levying scope according to different sections of route and terrain, to afforest along the route and secondarily plough in abandoned dregs field. The regolith should not be piled at will in solicits land outside the scope. The disturbing surface area should be expanded. This roadbed altogether strips the surface soil 75.46×104m3. In order to prevent the soil erosion of the surface soil in the temporary stack period, this project is designed to install the earth knitting bag in peripheral stack field to obstruct temporarily, built in trapezoidal cross section, 0.5m top wide, 1.0m high, 1.1, bottom wide, piled 4m high equally. And the dense item of net is used in the surface. After computing, temporary protective measures and the resilience in the roadbed area, sees Table 5-3-8.

Page 91: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-25 Temporary embankment protective measures

Item Unit Harbin Bin county

Fangzheng county

Ilan county Jiamusi Sum

Temporary measures

Water-proof ridge

Length m 7577 12414 15942 13046 2544 51524

Cubic meter of earth

m3 2076.22 3401.52 4368.05 3574.56 697.14 14117

Current groove

Length m 5052 8276 10628 8697 1696 34349

Earth knitting bag

m3 3788.73 6207.15 7970.89 6522.91 1272.15 25762

Temporary drainage ditch

Length m 7654 12540 16103 13178 2570 52044

Cubic meter of earth

m3 1377.72 2257.15 2898.50 2371.97 462.60 9368

Sedimentation basin

Quantity item 77 125 161 132 26 520

Cubic meter of earth

m3 344 564 725 593 116 2342

Iron net fence m2 8800 37000 42120 14800 20020 122740

Knitting cloth coverage m2 17820 9100 135051 115236 184570 461777

Temporary earth piling protection

Earth piling quantity

10,000m3 7.65 22.21 22.92 16.26 6.42 75.46

Earth knitting bag retaining wall

m3 2866.455

8322.087 8588.124 6092.62

22405.574

28274.862

Dense item of net coverage

m2 19507.5 56635.5 58446 41463 16371 192423

6.1.6 Environmental impact analysis and mitigation measures of bridge building

Bridge building survey The total length of the main-line bridge is 172862.60 double linear meter /144, accounting for 51.28% of the line span. Among it, double-line extra-longbridges are 157506.23 double extension meter/88; double-line large bridges are 15084.71 double extension meter/53; double-line moderate bridges are 206.46 double extension meter/2; steel-framed moderate bridges are 65.2/double extension meter one. The number of newly-built culverts is 294 and after deducting the length of the bridges and tunnels, the culvert is 1.90 for each kilometer.

In this project, the designed flood frequency of the bridge and culvert is 1/100, and the Ilan Mudanjiang

Page 92: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

extra-longbridge uses the frequency 1/300 for examination and calculation.

The main river characteristic and watered pillar establishment of the cross river bridge water along the line sees Table 5-3-9.

Table 6-26 Water pillar establishment situation of main river characteristics and cross river bridge along the route

Serial number

Railway central course

Name of bridge

Century flow(m3/s)

Century water level

m

Designing flowing speed

m/s

Rrdinary water level pillar

Pillar number on drying water level

Basic type

1 CK7+699.99Harbin especially large bridge

2037.0 40 / Hole-drilling stake

2 CK35+919.27

Feiketu River especially large bridge

1400.19 145.007 2.95 2 / Hole-drilling stake

3 CK90+084.85Jiaban River especially large bridge

769.03 140.298 2.86 3 / Hole-drilling stake

4 CK161+924.58Mayi River especially large bridge

6520 112.710 2.07 30 / Hole-drilling stake

5 CK201+582.82

Large Luomi River especially large bridge

526.9 10.381 1.23 13 / Hole-drilling stake

6 CK206+307.5

Small Luomi River especially large bridge

682.44 104.981 2.26 4 / Hole-drilling stake

7 CK249+860.3

Ilan-Mudan River especially large bridge

14670 101.802 4.13 7 / Hole-drilling stake

8 CK253+845.88

Ilan-Woken River especially large bridge

3660 99.992 2.97 4 / Hole-drilling stake

Key bridge specifications

Feiketu river extra-longbridge

Feiketu river especially large bridge is entirely 1601.15m long, central course CK35+919.27, located at a 6000m-radius circular curve, an easement curve and a straight line. This line spans Feiketu River in the position CK37 + 05, an angle of intersection for 94° with this river. The opening cross model of the entire bridge is: (2-24m) double-line prestressed concrete simple support box bean + (52-32m) double-line prestressed concrete simple support box beam +1 unite (12+16+12m) double-line steel-framed continuous

Page 93: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

beam, spanning 1795.1m; The entire bridge uses the round-tipped entity bridge abutments; The pier is in a form of Chinese character “one”; The foundation uses stakes, with the basis stake’s diameter 1.0m and 1.25m; The preliminary idea is like the following: the scene prefabrication is for simple support box beam to construct while steel-framed continuous beam uses the support for cast-in-place construction.

Mayi River especially large bridge

Mayi River especially large bridge spans for 9097.60km, central course CK161+924.58, located at a 8000m-radius circular curve, an easement curve and a straight line. There is not any special grade intersected path, and in principle the bridge span uses 32-meter simple support box beam to pass. Then opening cross model of the entire bridge is: (278-32m) double-line prestressed concrete simple support box beam.

The bridge spanning scope involves the farmland, the farming, and the soil texture is the granulated clay. The Mayi River bed is the granulated sand, both banks sandy soil. At the shore is the farming. The groundwater in the bridge site is mainly hole groundwater of 4th system, supplied by atmospheric water and river water. The surface water in the bridge site is from Mayi River, a seasonal river, whose bed is steady, and whose course is smoothly straight; In reconnaissance period the principal river bed is approximately 100m wide, water breadth approximately 40m, water depth 0.5~3.0m.

In the bridge site distributes the holocene alluvium (Q4 al) of 4th system, early pleistocene diluvium (Q3 al+pl) and middle pleistocene diluvium (Q2 al+pl). In the bridge site area the biggest freezing depth of soil is 2.05m; The acceleration of seismic peak value is: 0.05g (basic earthquake intensity ). ⅥThe entire bridge uses the round-tipped entity bridge abutments. The pier is in a double-line form of Chinese character “one”. The foundation uses stakes, with the basis stake’s diameter 1.0m and 1.25m; the scene prefabrication is for simple support box beam to construct. In Mayi River the foundation uses the steel-plated stakes for cofferdam construction.

CK164+000 right side of Mayi River CK162+160 right side of Mayi River

Yilan Mudanjiang extra-longbridge

This bridge is designed to span across Yichen highway, the Mudanjiang river course and dam, the central course, CK249+860.3, total length 1834.3m. Surmounts the Mudanjiang main river channel in the scope of CK249+350~CK249+745, surmounts main course of the Mudanjiang and the course span is approximately 400m. The cross section of the river is U-shaped with pebbled riverbed. The line is between the water junctions of two current in the Mudanjiang River and 1km downstream is the old Tong-San freeway bridge. The river course in the bridge site is smoothly straight. In the main channel the current of water is massive, and along the beach is planted 20-30m-wide floodproofing forest. There is neat slabstone to protect the slope on the Mudanjiang floodproof.

The groundwater in the bridge site is mainly hole groundwater of 4th system, supplied by atmospheric water and river water. Mudanjiang is approximately 500m wide, with water running all the year and water

Page 94: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

depth about 10m.

Intersect point of main & inferior river course of Mudanjiang Mudanjiang bridge in Tong-San freeway

Decision ground of bridge opening:

Navigation

The site of the planned Mudanjiang extra-longbridge is located at the Mudanjiang main current, about 1km apart from the downstream Mudanjiang extra-longbridge in Tong-San freeway. Ilan section in Mudanjiang is now V-Level navigating course, with the capability of passing for 500-ton barges. The clear width is not less than 50m according to Heilongjiang river system standard of national V-level navigation course.

Overpass

The line is at the location CK249+260, from above spanning Yichen highway. The requirement of the overpass is clear width times clear height: 8×4m, the overlapping angle 96°07'. 32m simple beam is planned to span in this designing.

Bridge-type plan:

Impactd by the existed bridge and navigation of Mudanjiang, 10-opening 64m simple beam is planned to use in the spanning of Mudanjiang to meet the requirement of navigation and put the bridge to the hole as the existed bridge in Tong-San freeway. The others use 32m simple beams to span. The entire bridge opening cross model is: (36-32m) double-line prestressed concrete simple support box beam + (10-64m) double-line prestressed concrete simple support box beam, spanning 1834.3m.

Preliminary suggestions of construction:

32m simple support box beam uses the prefabrication construct, and 64m simple support box beam uses movable frame to construct. In Mudanjiang the foundation of the abutment uses the steel-plated pile for cofferdam construction.

Ilan Woken River extra-longbridge

This bridge is established for Woken River and its bank passing Yilan County nearby in Harbin-Jiamusi rail line project, central course CK253+845.88, entire bridge 1247.3m long. The surface breadth of Woken is approximately 100 meters, approximately 1-4 meters deep.

There is running water not plant in the main channel at the bridge site. Rubbled stones silt riverbed. The side sandbank in small course is approximately 100m wide, usually anhydrous, mean depth of hydraulic maximum approximately 3m. The river course is curving in the bridge site, the bridge located right at turning point. The century current capacity is 3660 m3/s at the bridge site. The groundwater in the bridge site is mainly hole groundwater of 4th system, supplied by atmospheric water and river water, soaking coefficient: powdered clay k=0.05m/d; gravel sand: k=5.0m/d; thin round gravel soil: k=20.0m/d.

The entire bridge opening cross model: (2-24m) double-line prestressed concrete simple support box mean + (32-32m) double-line prestressed concrete simple support box beam +1 unite (40+64+40m) double-line prestressed concrete continual box beam. It is planned to use 32m double-line span across this

Page 95: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Cofferdam water extractionfrom the cofferdam

mechanical hole drilling

Mechanical earth filling &pile grouting-in

platform-bearing abutment constructionmaintenance

operationBridge floor constructioncofferdam demolition, hoisting precast slab and box beam

reconditioning

river, 40+64+40m prestressed concrete continuous beam used to surmount the bank. Simple support box beam uses the prefabrication for construction, 40+64+40m prestressed concrete continual box beams used for hanged pouring construction.

Woken River landform at the bridge site Woken River dike

Impact analysis and mitigation measures in construction period Impact analysis of the cross-river bridge construction on water environment

The impact of the cross-river bridge construction on water environment includes the following aspects. The mud deposit at the bottom will be stirred because of foundation of the abutment, pillar body

and temporary support and so on in construction and then the suspension in the water is increased and the water quality is polluted, which will brings the adverse impact to the water body. Although this kind of impact will vanish with the end of the construction, but the impact is serious, not allowing for neglecting. Besides, the environmental impact is also possible because of the mechanical oil leak in the construction.

The bridge foundation construction flow sees Figure 6-5. Seen from the actual construction process analysis, the suspension in the construction period are mainly from cofferdam, water extraction from the cofferdam, the mechanical hole drilling and cofferdam demolition. While compared with the above process, the suspension is much less from pile grouting-in, platform-bearing abutment construction, maintenance, bridge floor, reconditioning, which impacts relatively little after taking some protective measures.

Figure 6-17 Bridge construction flow schematic drawing

The concrete analysis of the bridge construction about key pollution links is as follows:

a. The cofferdam and the demolition construction: In the basic construction of the bridge, with the cofferdam or the trestle and their demolition, the bottom silt and sand of rivers will be stirred and the opacity of partial waters is enhanced. The density of the suspension is increased instantly, which will in a certain degree impact the water quality around the construction area. Concerned data show that the amount of the suspension in the course of cofferdam is 0.9-1.75kg/s.

b. Water in cofferdam: Besides that the suspension from the process of cofferdam directly releases and goes into the water body, a great deal of suspension keeps in the water of the steel pipe cofferdam. The water in cofferdam is generally extracted first into the multistage sedimentation ponds outside the dike and then into the water body after precipitation. The production quantity of cofferdam water is concerned

Page 96: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

with such factors as pressing depth of the pipe pile, the pile volume, water extraction and so on. According to the estimate data for suspension production in the construction of the bridge, when the pipe pile with water inside is pressed underneath steadily, the amount of the suspension in the extracted water is 0.1-0.5 kg/s.

c. Mechanical hole-drilling: The dregs (bottom mud) from hole-drilling contain little moisture; if ejected at will, they will also greatly impact the water quality of the construction area. Generally the drilled dregs do not enter the water body but enter the slag pot nearby the drilling pile and are sent into the prepared sedimentation basin on the bank after the pot is full. After precipitation, the base mud is used for farming, afforesting or dealt with by municipal department after drying. The upper clear part can be used in water circulation or dispersed into the water body. In this part, the density of waste-water suspension reduces to below 60mg/l.

Table 6-27 The suspension quantity in bridge foundation construction process

main construction course

releasing speed and density of suspensionnotegeneral cofferdam

protectionsteel cylinder cofferdam protection

cofferdam and demolition course 1.75~1.33(kg/s) 0.90~1.2(kg/s) no suspension release after the

completion of cofferdam

water in cofferdam 0.31~0.5(kg/s) 0.1~.0.5kg/s) steel tube protection, dregs after the instant sending away of drilled holes

dreg sedimentation basin

before precipitation 500~1000 mg/l,

after precipitation<60 mg/lsediment in the dregs field out the dike

Forecast and analysis of suspension proliferation density in construction process

By the above analysis of construction pollution, massive increase of water suspension caused by the construction have negative impact on quality of partial waters, thus affects the living environment of aquatic organism. For an accurate understanding of the influential area and the degree caused by construction process, two-dimensional mix pattern of stable state of river is adopted to evaluate and predict the mixture degree and scope of the spread and mixture of the suspended proliferation in the Mudanjiang extra-longbridge water. The prediction take the single pillar work as the basic operating mode and regards each bridge pier as the continuous drop discharge source of suspended substance. .

Prediction mode

c ( x , y )=ch+c p Q p

2 H ( πMY xu)1/2 {exp (−uy 2

4 M y x)¿¿+exp[−

u (2a+ y )2

4 M Y x]+exp[−

u (2 B−2 a− y )2

4 M y x]} ¿

Where, c is the pollutant density; H is the water depth; a is the distance from emission point to the shore; My is the crosswise mixed coefficient; u is the water speed of flow; B is a river width; Qp is the discharging quantity of wasted water.

Parameter determination

MY =(0 . 058 H +0.0065 B)( gHI )1/2

gHI≤100

where, I is riverbed gradient.

Source intensity determination

According to the analysis of construction pollution, suspended substance is released most during the

Page 97: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

process of coffer dam and weir opening. Take this process as source intensity, dereferencing 1.2kg/s.

The state of prediction

Predict suspension concentration under the normal construction situation in the low water season.

Prediction results and analysis

Input parameter, the proliferation scope of the suspended substance during bridge construction process. Area of enveloping line and concentration value-added of suspended substance and affected distance of the upstream and downstream is as follows. See Table 5-3-11, 5-3-12 respectively.

Table 6-28 Concentration value-added of suspended substance and area of enveloping line during construction period

unit: km2

State of suspended substance

Concentration value-added of suspended substance≥

5mg/l 10 mg/l 15 mg/l 20 mg/l

Diffusion area 0.08 0.010 0.005 0.001

Table 6-29 the biggest affected distance and concentration value-added of suspended substance during construction period.

Unit: m

State of prediction The largest affected distance

Concentration value-added of suspended substance≥

5 mg/l 10 mg/l

Construction of single pier

upstream 346 87

downstream 864 239

Lateral diffusion breath 52 23

The result indicated that during cofferdam and demolition ,when single pillar works, the waters area is 0.01km2 in which concentration value-added of suspended substance ≥10mg/l . The suspension density ≥10mg/l. Affected impact distance of upstream is 87m and downstream 239m.The maximum diffusion breadth is 11.5m (take bridge pier as center). Obviously the suspension area of impactd is only restricted in nearby work and the area of impactd is limited.

When two close pillars work at the same time, density of suspension possibly will double, depending on the water pillar spacing and the lateral divergence width of suspension. Table 5-3-12 shows that affected distance is 11.5m crosswise in the bridge pier one side. Therefore, even if construction is carried out simultaneously between the neighboring two bridge piers, the suspension density created by each pier is independent and proliferation does not superimpose mutually.

According to the standard of national fishery water, the increase of suspension caused by man should not surpass 10mg/l. During this bridge construction, the water area with suspension density over 10mg/l is very limited. Therefore, the construction has little impact on the environment of fish living.

During cofferdam and demolition period, the time of disturbance of river bed bottom mud lasts a short time. Massive suspended concentration gather in the coffer dam of steel pipe. And the increased suspended concentration will not further impact water quality with the completion of cofferdam and demolition.

Impact of mechanical oil leakage

Because machinery is electrically operated primarily, the occurrence of mineral oil leakage can be

Page 98: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

avoided. Even partial machinery operates on machine oil or the lubricating oil with limited quantity. Generally, water will not be polluted with strict management of construction so long as the strict construction management will not have the pollution generally.

Suggestion of water pollution prevention

a. River crossing bridge's foundation construction should be carried out in the dry season, avoiding the impact caused by mud and mechanical oil leakage during rainy season. Simultaneously, the Construction should optimize the plan of construction and adopts the most advanced construction craft, the scientific management as far as possible. Enhance the construction progress under the construction quality. Shorten the submarine operating time as far as possible and strengthens the management and the maintenance of construction equipment. Avoid the leakage of contaminating material as petroleum and the leakage of building material which and reduces the water pollution as far as possible.

b. During the construction period of main bridge, the dregs, wasted material and life garbage are not allowed to discharge in to the construction waters. Temporary restroom and trashcan should be built in the platform of the site. It should be cleaned regularly and delivered to the bank. Measures are as follow:

During the construction of pier, sediment barrel should be built nearby the drilling poles to deposit the① mud dregs. It should be shipped to sedimentation pond when filled.( slush pit and sedimentation pond is built on the bank). The wasted water is cycled for reuse. Desiccated mud should be loaded and shipped to dreg piled field. Do not throw mud dregs and slush into the river course. After the construction, slush pit and sedimentation pond should be filled to restore the plantation of ground surface.

Before the construction, based on the amount of piers, the designing department should put forward a② scheme concerning the dreg piled field, and ways and surfaces. The field should not be built along two sides of bank. Dams should be built surrounding the field before drilling the dregs. Thus, the wasted will not form the mud flow to pollute the farmland. Flowing wastes, like slush, can first be solidated and then piled. Pillar construction in the water is carried out in dry season. After completion, the field should be improved and processed with filling and afforestation and the planting of trees and grasses.

c. Certain buffer distances, generally above 20-30m, should be kept between the construction location and the bank to prevent the pollution of water body. Sanitary sewage of constructors and production wasted water cannot be dispersed into the water body.

d. The location of cement mix should be beyond residential area 300m. Cement must be deposited away from water and rain. Mixer and other materials must be piled in the material field. Wasted water must be cycled for reuse. Wasted water can be discharged when it reach the required standard. When mixer shipped to pier, the material spray can affect the water quality. Station of mixer must have dedusting equipment, avoiding the pollution of air and water.

e. Because of the scattered construction batalior, collective process of the wasted water is difficult. So it is suggested to build dry restroom in the camping area. Dry restroom is suggested to build and cleared promptly and regularly. Avoid the float of sewage during rainy season.

f. Regarding the construction place with oily sewage, a small-sized oil removal, and base sump should be established. Oily sewage can be discharged after oil filter.

g. In the construction machinery maintenance point, hardened ground and desiccation groove should be established at the construction machinery maintenance point to prevent the machinery maintenance and cleaning sewage from polluting the water body and soil. Examination and maintenance should be strengthened about the construction machinery with strict management to defend the machines’ oil against running, braving, dropping and leaking.

h. The awning lid should be established in the material piled field if inside it are some particular materials such as asphalt, cement and so on, so as to avoid the pollution toward environment because of the outflow in rain washing.

i. Relieving measures of the impact on fish

Because the dog-legged steel cofferdam is used in some foundation constructions such as that in Ilan① and Mudanjiang extra-longbridge, in the shallow water part the steel-plated pile is inserted for cofferdam

Page 99: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

construction. The low frequency noise is weakened in the conduction melt with air noise into the water. In construction, it is suggested that the low frequency acoustic source be put at the bottom of the water and then put into the steel cofferdam after the fish is driven for a period. The protective measures should be taken promptly for the fish in the course of mud absorbing, bottom covering and water pumping.

Try to use advanced construction equipment and ships of the low frequency noise and pay attention to② the daily maintenance and reduce the construction noise; close the floor system of the bridge and reduce the acoustic level spreading to the water.

Temporary protective measures of bridge construction

In order to effectively avoid the different kinds of soil erosion in the bridge construction, the following measures are newly increased, measures of waste earth resisting, mud dealing and management.

a. In the bridge levying area, the temporary waste earth field is established to collectively pile the waste earth. The temporary resisting measures are designed to use rack to fill in earth forming a ladder shape, with the top breadth 0.5m, height 1.0m and bottom breadth 1.1m.

b. The sedimentation basin is built to deal with the mud created in hole-drilling foundation construction to reduce the soil erosion in the course of construction.

Table 6-30 Construction quantity of temporary protective measures in bridge area

Admin.district

Temporary measures

Earth knitting bag retaining wall(m3)

Mud sump Sedimentation basinDense network coverage(10,000m2)Number

(item)

Foundation excavation(m3)

Number

(item)

Foundation excavation

(m3)

Harbin 622.73 1 8 2 12 67325.00

Bin county 762.07 2 16 4 24 100825.00

Fangzheng

county800.05 3 24 6 36 111125.00

Ilan county 846.15 5 40 10 60 124300.00

Jiamusi 612.59 2 16 4 24 65150.00

Sum 3643.59 13 104 26 156 468725.00

Impact assessment in operation period In operation time, the cross-river bridge impacts the ecological environment mainly in the following aspects. Because the aperture is not suitably designed for surmounting the drainage ditch and the culvert of the river, which is likely to reduce the water-passing cross section of small scream, or even block and compress the river course, affecting the function of flood discharging or possibly intensifying the washing of the river toward its bank.

The anti-flush ability of the different rivers is good along the construction line and the suspension ratio will be relatively small. So bridge building will not have tremendous impact to the fishery resources.

This building of this bridge will not change the current capacity and temperature of the river, and will not be cut off other fish channels.

The bridge and the dam are two completely different kinds of hydraulic architecture. The building of the river-crossing bridge has shown the ecological impact of the river dam, which is seen from the operation impact of many built bridges across the main and branch river in some rivers, Songhuajiang River, for

Page 100: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

example.

6.1.7 Environmental impact analysis and mitigation measure of tunneling

Tunnel works outlineThe Harbin-Jiamusi rail line involves 9 tunnels, all in double-line, total length 14.093km, which is approximately 4.18% of the total line. Tunnel design is as shown in Table 2-7 and Table 2-8.

The main tunnels see the following virtual appliance photos:

Korea hat tunnel entrance Korea hat tunnel exit

Pingan tunnel entrance Pingan tunnel exit

Changfa tunnel entrance Ilan 2 tunnel exit

Page 101: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Monkey rocky mountain entrance Monkey rocky mountain exit

Key tunnel introduction-monkey rocky mountain tunnel

Outline of tunnel

The tunnel entrance course is CK316+484, the exit course is CK321+386, span 4902m. The greatest burying depth of the tunnel is approximately 110m.

Condition of engineering geology

Lithology character of stradum

The surface of the tunnel is covered with powdered clay of slope diluvium (Q3dl+pl) of the early pleistocene of 4th system, clay, gravel sand, thick-angle gravel soil and thin-angle gravel soil, and tuff of Cretaceous system (K2) beneath and with partial appearance .

Classification of rock construction

Table 6-31 Monkey rocky mountain tunnel ground construction work grading

Lithology Rock-soil construction grading

Powered clay II

Clay II

Gravel sand I

Fine-caped gravel earth Medium density II

Rough-caped gravel earth Medium density III

Tuff (W4) III

Tuff (W3) IV

Tuff (W2) IV

Fault fracture zone III

Rock mass classification

Table 6-32 Adjacent formation hierarchical list of monkey rocky mountain tunnel

lithology starting course ending course length(m) wall rock

grading

powered clay、clay、tuff(W4) CK316+565 CK317+015 450 V

Page 102: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

tuff(W3、W4),fault fracture zone CK317+015 CK318+400 1385 IV

tuff(W2) CK318+400 CK319+195 795 III

fault fracture zone CK319+195 CK319+325 130 IV

tuff(W2) CK319+325 CK320+735 101410 III

tuff(W3) CK320+735 CK320+935 200 IV

rough-caped gravel earth、fine-caped gravel earth、tuff(W4) CK320+935 CK321+300 365 V

3). Hydrogeological conditions

There is a spring mouth at the location 200m of the tunnel access nearby the left side of the line, containing little water and little amount of bedrock crevice water in the inside tunnel body in the exploration depth and scope .

Soaking coefficient: K=0.02m/d. the tuff, the entire decency, strong decency K=10m/d, weak decency K=5m/d, fault crushed zone K=100m/d.

Construction methods

II-rate adjacent formation uses the terrace cultivation or the entire cross-section measures for construction. -rate adjacent formation uses the terrace cultivation for construction. Deep buried section of -rateⅢ Ⅳ

adjacent formation uses three-terrace cultivation for construction, while the shallow-submersion uses the short-terrace cultivation (if necessary temporary inverted arch increased) for construction. The deep buried section of V-rate adjacent formation uses three-stairs-seven-steps excavation, the slanting pressed and shallow-submersion sections use the CRD or the two-sided wall guiding hole for construction.

Analysis on construction period

The monkey rocky mountain tunnel is designed to have double accesses, both the access and exit, without considering of the designing of slant hole, construction period of time altogether 36.24 months (3 months for construction preparation).

Security measures and suggestions for construction

a. Before the tunnel construction, the low-lying place should be backfilled on the surface of the shallow-submersion section at the entrance and exit to prevent the stagnant water.

b. Since the end section of this tunnel are covered with shallow layer in V grade rocks including silty clay, tuff, coarse breccias clay, and fine breccias clay, they must be constructed to a large round pipe shelf at the end of it. (Steel pipe in diameter of 108mm, and thickness of 5mm) The shelf length will be 30m, and interval distance of the round will be 33cm.

Wall rock of grade, reinforced section of it, wall rock of grade, and reinforced section of it areⅣ Ⅴ designed to vessel grouting in advance at arc part. Vessel type is designed to hot-rolled seamless pipe in diameter of Φ42mm, and thickness of 3.5mm.

Advices

Research will be done at the next stage on how to use abandoned dreg according to geological information. As to the abandoned dreg unable to use, careful investigation will be done to determine the position of abandoned dreg site and permanent dreg site protection works will be set up. Cut-off and drainage system will be set up on the top. Measures will be taken on the slope of dreg site by growing plants to prevent soil erosion.

Analysis on environment impact from tunnel project The impact of tunnel engineering on the environment mainly includes:

Tunnel spoil disposal taking up land will lead to soil erosion, thus affecting the ecological environment;

Page 103: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Water leaking from tunnel construction will affect plants on the top and residents’ drinking water.

Tunnel spoil disposal

The project consists of 9 tunnels. For tunnels of less than 500m, dreg will be carried from one exit to reduce the damage to the surrounding environment.

Tunnel spoil disposal will be 204.34×104m3, among which 75.95×104m3 will be used and the other128.39×104m3 will be placed in spoil yard forever. 12 spoil yard will be built along the whole route, taking up 34.72hm2 land and holding abandoned dreg of 338.16×104m3.

Tunnel spoil disposal sites along the route see table 5-3-16.

Table 6-33 Tunnel spoils site

District No Places Locations Amount

Area

(hm2)

Land

Harbin

1 Disposal site at Gaolimao Tunnel CK112+800 left gully 15 2.4 Woodland

steppe

2 Disposal site at entrance of Pinan Tunnel

CK123+750 right 100m gully 28.95 2.90 Woodland

steppe

3 Disposal site at exit of PinganTunnel

CK125+000 right 200m gully 18.61 1.86 Waste

land

4 Disposal site at Lianbin Tunnel CK128+750 left 250m gully 42.02 4.20 Waste

land

5 Disposal site at entrance of Fangzheng Tunnel

CK131+000 left 400m gully 28.7 2.87 Waste

land

6 Disposal site at exit of Fangzheng Tunnel

CK133+500 left 500m gully 27.99 2.80 Woodland

steppe

7 Disposal site at Changfa Tunnel

CK139+500 right 300m gully 15.83 1.58 Woodland

steppe

8 Disposal site at Yilan Tunnel 1 CK247+100 right 800m 19.96 2.00 Waste land

9 Disposal site at entrance of Yilan Tunnel 2 CK254+100 right 1500m 31.5 3.15 Waste

land

10 Disposal site at exit of Yilan Tunnel 2 CK257+880 right 500m 37.8 3.78 Waste

land

Jiamusi 11 Disposal site at entrance of Houshishan Tunnel

CK316+400 right 600m gully 35.9 3.59 Woodland

steppe

12 Disposal site at exit of Houshishan Tunnel

CK321+400 left 500m gully 35.9 3.59 Woodland

steppe

Total 338.16 34.72

Spoil yard of this project will mainly consist of uncultivated land and land with few scattered woods. The large amount of spoil will take up land and bury vegetation. Loosely piling up, the abandoned layer is likely to cause soil erosion and damage the ecological environment.

It is suggested that geological exploration work be strengthened and earth and stone be mixed proportionately in the next stage work of survey and design. Tunnel dreg will be made full use of as roadbed stuff to further reduce the amount of Tunnel spoil disposal, thus reducing land being taken up and

Page 104: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

damage to vegetation caused by this project.

When tunnel dreg can’t be used, the choice of spoil yard will be based on local planning. Little cultivated land will be taken up. Abandoned dreg mustn’t be used to back fill earth drawing site. Safety of buildings and facilities in lower reaches will be taken into account. Spoil yard mustn’t be built in higher reaches of villages to avoid dreg collapsing and threatening the safety of residents. Tunnel spoil disposal mustn’t be placed in river course. According to the rule of “first blocking and later abandoning”, retaining wall of mortar flag stone will be set up under abandoned dreg. Combined with local practical condition, measures such as land-cultivating restoration, land producing, planting grass and trees must be taken. Slopes of spoil yard must be protected. If tunnel construction is done before construction of roadbed and of spoil yard because of construction progress, the dreg dug must be placed in appropriate temporary places. It mustn’t be placed in the ditch mouth or flood land. Temporary protection measures will be taken based on terrain.

2) The impact of water leaking caused by tunnel construction on top vegetation and on residents’ life water

The project tunnels are mainly distributed in the hilly land along the route, where large amount of granite, metamorphic rock series and sedimentary rock group are distributed. Bedrock crevice water is stored here, which is supplied by rainfall. Groundwater level lies relatively in deeper places.

1) The impact of tunnel construction on vegetation on the top

The tops of most tunnels of this project are generally covered with few scattered bushes and weeds. Growth of vegetation usually depends on water contained by top soil and natural rain. Leaking water caused by tunnel construction mainly consists of roadbed crevice water and pore water. Water content in top soil will not be affected, so vegetation on the top will not be affected. Only the vegetation in tunnel mouth will partially be affected.

As to the area with woods of deep roots on the top of tunnel, vegetation root absorbing water will be affected because of the possible negative impact of tunnel construction on groundwater, thus affecting the growth of vegetation. As to large-amount-of-water-pouring tunnels, blocking will be the first choice, which will be done through the method of grout curtain. Effective control will be done by reducing water pouring during construction. In addition, tunnels in these sections are usually buried deep, basically above tens of meters, so project construction will basically not damage vegetation roots on the top. After construction everything will be restored. Vegetation growth will not be affected during the operation. 2)Analysis about the impact on residents’ life water

According to spot survey and Ha-Jia railroad drawing of 1:10000, in this project only the both sides of Gaolimao tunnel (CK111+954- CK112+866, with total length of 912m) entrance within the range of 1000m will involve two villages--Sunjiujingtun Village and Liuchunxitun Village. No residential areas are distributed within the range of other tunnel entrances and exits and on the top of tunnel.

Gaolimao tunnel①

The tunnel will be located in slow, buffer hilly land. Terrain changes much. Ground level is 217~278m.

Gullies develop. Top soil vegetation develops. Tunnel elevation will be about 210m and the maximum burying depth is about 63m.

Surface of the tunnel is silty clay in alluvial layer of Quaternary Pleistocene series (Q3dl+pl )above the granite of invasion rock in Variscan (γ4). The granite is of brown-yellow to yellowish brown in coarse grain and massive structure, fully weathered to weakly weathered, in developed joints and fissures.

Groundwater is not found within the depth of exploration during the period of survey. Little amount of roadbed crevice water is stored in tunnel body, and chances are small that large amount of water will be pouring.

Analysis about the impact on residents’ life water ②

Sunjiujingtun is located on the left side of Gaolimao tunnel entrance. Water used by residents mainly comes from groundwater, which is supplied by Sunhuajia Branch—Taoqi River and rainfall. Because the

Page 105: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

body of tunnel is made of granite with poor water yield property, the little amount of bedrock crevice water leaking will not affect the supply of surrounding groundwater. Besides, the village is about 830m away from the tunnel entrance, so tunnel digging will not affect residents’ life water.

Liuchunxitun is located on the right side of Gaolimao tunnel entrance, and is about 850m away from the tunnel entrance. Water used by residents mainly comes from groundwater, which is supplied by Sunhuajia Branch—Taoqi River, rainfall and little amount of bedrock crevice water. Between this village and the railroad project is Tongsan highway and a valley. Tunnel area has nothing to do with the water system of groundwater in the village, so tunnel digging will not affect residents’ life water.

Protection measures for tunnel project and adviceMeasures for construction management

a. Construction unit must be under strict management. Construction personnel can’t abandon dreg freely, damage vegetation in lower courses of tunnel exit or expand disturbance of earth surface.

b. As to less than 500-meter-long tunnels, construction must be done in one tunnel mouth. Roadbed body must be used as access roadof construction when construction is done between adjacent short tunnels to reduce the range of disturbance.

Figure 6-18 Geological Profile of Gaolimao Tunnel

Page 106: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-19 Distribution of Villages around Gaolimao Tunnel Entrance

Temporary protection measures for tunnel construction

Part of the tunnel dreg will be used as roadbed stuff and station stuff, while part of it will be abandoned forever. Permanently abandoned dreg must be carried to spoil yard in time and corresponding measures be taken. Dreg used as roadbed stuff and station site stuff must be carried to corresponding places for filling. When tunnel sides in the connection between bridge and tunnel and upslope are dug, the bottom of slope will be blocked by wiring netting to catch tunnel dreg, avoiding abandoned dreg damaging vegetation, farmland and traffic facilities in lower courses.

When tunnel dreg can’t be carried away in time, it should pile up in designated temporary dreg sites and should not be abandoned freely to avoid farmland being taken up and vegetation being damaged. Dreg sites must be away from flood course and from the area in higher reaches where large amount of water pours. During the period when tunnel dreg piles up temporarily, retaining wall of moraine must be built at the foot of dreg site slope to avoid dreg falling. Big aggregate in dregs can be used as moraine. The section of retaining wall of moraine will be in the shape of trapezoid section with size of height × top width × base width being 1.5m×0.5m×3.5m.

Temporary protection measures for tunnel area construction see Table 5-3-17, which is based on calculation.

Table 6-34 Temporary protection measures for Tunnel Area

Administrative areaTemporary measure

Guardrail in barbed wire(m2) Retaining wall for stone pile (m3)

Harbin Municipal 0.00 0.00

Binxian County 260 755.60

Fangzheng County 1300 1240.05

Yilan County 520 1543.89

Jiamusi Municipal 260 1544.57

Total 2340 5084.12

Ecological environment and the impact on water and soil conservation and measures taken

a. The principle of “ early in and late out” must be stuck to. Structure of tunnel mouth must be simple. In combination with construction of green lanes, structure of tunnel mouth must be coordinated well with the surrounding landscape.

b. As to tunnels with strict requirement on ecological environment, when drainage of groundwater has negative impact on them, leakage prevention measures such as blocking water inside tunnel, strengthening water carrying section of earth surface and water storage structures on earth surface will be taken to make the impact of construction on groundwater under control.

c. Tunnel dreg mustn’t be abandoned on fertile land if possible. The best choice will be to use it as filling earth and concrete coarse aggregate. To prevent soil erosion, slope foot of the dreg body must be constructed to some flood proof wall or dreg controlling wall. Vegetation will be done according to the

Page 107: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

surrounding environment.

d. For pouring water caused by tunnel digging, if it needs to be drained away, it will be drained away after being treated through sand bath located at tunnel mouth. Waste water caused by construction will be drained away after being treated through sedimentation tank and filtering basin and meeting drainage standard. It will be drained into nearby rivers or reservoir in lower reaches by using water pumps. Then it can be used for irrigating farmland or supply water resources of earth surface. It mustn’t be drained freely to avoid the loss of groundwater resource.

Suggestions

a. It is suggested that further exploration and analysis be strengthened in the next stage and that further investigation on water use condition nearby be made. In combination with practical condition, effective measures for prevention and slowing-down will be worked out. Hydrogeological survey and environmental protection will be strengthened in the design. Construction program will be worked out well. Tunnel construction program affecting the environment must be carried out under strict principle of “first blocking, then control drainage”. Aquifer blocking technology like pre-grouting technology will be employed. Strict measures will be taken to supervise tunnel construction. construction unit must strengthen tunnel construction management work, choose experienced tunnel construction units, assign specialized construction supervisor and avoid water pouring accident caused by violation of rules during construction. During construction and initial stage of operation, water level and water quality of the important wells along tunnel routes will be monitored. Once abnormal condition occurs, remedy must be done in time to ensure the safety of nearby residents’ life water.

b. It is suggested that geological exploration work be strengthened and earth and stone be mixed proportionately in the next stage work of survey and design. Tunnel dreg will be made full use of as roadbed stuff to further reduce the amount of Tunnel spoil disposal, thus reducing land being taken up and damage to vegetation caused by this project.

When tunnel dreg can’t be used, the choice of spoil yard will be based on local planning. Little cultivated land will be taken up. Abandoned dreg mustn’t be used to back fill earth drawing site. Safety of buildings and facilities in lower reaches will be taken into account. Spoil yard mustn’t be built in higher reaches of villages to avoid dreg collapse threatening the safety of residents. Tunnel spoil disposal mustn’t be placed in river course. According to the rule of “first blocking and later abandoning”, retaining wall of mortar flag stone will be set up under abandoned dreg. Combined with local practical condition, measures such as land-cultivating restoration, land producing, planting grass and trees must be taken. Slopes of spoil yard must be protected. If tunnel construction is done before construction of roadbed and of spoil yard because of construction progress, the dreg dug must be placed in appropriate temporary places. It mustn’t be placed in the ditch mouth or flood land. Temporary protection measures will be taken based on terrain.

6.1.8 Impact assessment on borrow pits and disposal sites and mitigation measuresAnalysis about the impact of earth drawing and earth abandoning sites on the environment and measures for harnessing

Total cubic meter of earth and stone along the route will be 4111.78×104m3, among which filling will be 1437.24×104m3 and excavation be 2674.54×104m3.Excavated earth will be made full use of as filling stuff. Earth used will amount to 951.44×104m3. Total abandoned earth will amount to1723.10×104m3, among which top soil of 118.53×104m3 will be reused for greening purpose and 1604.57×104m3 be abandoned at dreg sites forever.

Table 6-35 Amount of stone and earth work Unit: 104m3

Items Excavation Filling Utilization Topsoil utilization

Permanent waste Borrowing

Roadbed 1949.78 635.07 658.58 75.46 1215.74 242.7

Stations 229.96 606.6 21.34 43.07 165.55 243.1

Tunnel 204.34 75.95 128.39

Page 108: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Bridge 290.46 195.57 195.57 94.89

In total 2674.54 1437.24 951.44 118.53 1604.57 485.8

Page 109: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Wasted excavation Excavation earth Non-usable earth Fill earth Borrow earth

Permanent waste1604.57

Roadbed backfill635.07

Site backfill606.60

Slag from bridge290.46

Site229.96

21.87

94.89

128.39

243.1

Borrow earth485.8

Landscaping 118.53 43.07

Roadbed 1949.78

1215

.74

75.46

195.57

21.34

Roadbed utilization392.37

Site utilization363.50

396.09

392.37

Tunnel 204.34

Backfill for bridge195.57

370.50

242.7

165.55

288.08

54.08

Figure 6-20 TPFG of earth and stone work

Page 110: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Treatment Methods and Environment Impact Assessment of borrow pitGeneral condition of the borrow pits

Since the excavation of this engineering is much more than the fill of it, the fill will be done mainly by using the excavation. According to the treatment plan to earth and stone work, borrow earth in the whole line is designed to amount of 485.80×104m3 from 12 pits of the existed quarry plant.

General condition of the borrow pits is listed in Table 5-3-19 supported by some natural photographs of them.

Longsheng Quarry Taipingshan Quarry

Jianzishan Quarry in Fangzheng County Pingan Quarry

Borrowing earth from above pits will destroy the vegetation on them, and cause some living things vanish, and decrease the vegetation covering rate of them. Borrowing earth from them will also disturb the original soil structure, and to cause the soil become loose. This will destroy the balance of soil mass in natural condition, and destroy the soil structure, even to cause soil and water loss become easy.

Page 111: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-36General condition of the borrow pits

No Pit Average depth(m) Deposit

(104) Stone and qualityGround water

depth(m) Pit condition and road condition Use

1 Longsheng quarryWeakly weathered

>25.0100m3

Tuff: gray, weakly weathered, cryptocrystalline massive complete structure

>10.0m

This pit is of lower mountain landform with rare ground vegetation. It locates in Binxi Changqing village of Bingxian County.

Roadbed and station filling

2 Baichao QuarryWeakly weathered

>36.080m3

Tuff: gray, weakly weathered, cryptocrystalline massive complete structure

>10.0mThis pit is of lower mountain landform with rare ground vegetation. It locates in Binzhou of Bingxian County.

Roadbed and station filling

3 Shidonghe Quarry Weakly weathered >20.0 60m3

Granite: gray, weakly weathered, joint fissure in developing, open grained massive structure.

>10.0mThis pit is of lower mountain landform with rare ground vegetation. It locates in Yongzeng village of Bingxian County.

Roadbed and station filling

4Shengli Taipingshan Quarry

Weakly weathered

>20.064m3

Granite: beige, weakly weathered, joint fissure in developing, open grained massive structure.

>10.0m

This pit is of lower mountain landform with rare ground vegetation. It locates in Taiping Mountain, Shengli Town of Bingxian County.

Roadbed and station filling

5 Jianshanzi Quarry Weakly weathered >30.0 100 m3

Basalt: beige, weakly weathered, joint fissure in developing, cryptocrystalline massive structure

>20.0m

This pit is of lower mountain landform with rare ground vegetation. Natural slope of it is 45°~60°. It locates in Jianshan village of Yihantong town, 13km east of Fangzheng County.

Roadbed and station filling

6 Songjiang Quarry Weakly weathered >40.0 128 m3

Gabbro: beige, weakly weathered, joint fissure in developing, massive complete structure.

>20.0m

This pit is of lower mountain landform with rare ground vegetation. Natural slope is 30°~40°. It locates in Demoli village of Yihantong town, Fangzheng County.

Roadbed and station filling

7 Balinban Quarry Weakly weathered >30.0

160 m3 Andesite: gray, weakly weathered, joint fissure in

>10.0m This pit is of lower mountain landform with rare ground vegetation. It locates in

Roadbed and

Page 112: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

developing, cryptocrystalline massive complete structure

Chensuo village, at Gaoleng Forestry Bureau of Fangzheng County. station filling

8 Zhushan Quarry Weakly weathered >30.0 120 m3

Ophite: gray green to brown-yellow, weakly weathered, cryptocrystalline massive structure.

>20.0m

This pit locates at west of Fendou village of Yilan town, and is 1.5km away from the village, and is 6.2km west away from line K262+600. It is of hill area. Road Hong-Tong (cement structure) connects it with outside world in convenient traffic condition.

Roadbed and station filling

9 Pingan Quarry Weakly weathered >20.0 80 m3

Andesite: gray-brown to gray-green, weakly weathered, cryptocrystalline massive structure, joint fissure developed

This pit locates near the Xiaodangui village of Hongkeli town, and is 2km away from the village, and is 5.8km north-east away from line CK282+000. It is of hill area. The old Tong-Sang road (in gravel) connects it with outside world in convenient traffic condition.

Roadbed and station filling

10 Xinghua Quarry Weakly weathered >30.0 150 m3

Tuff: steel gray, weakly weathered, tuffite structure, massive structure, joint fissure developed

This pit locates in Qiongshengtown of Jiamusi city, and is 1.2km away from Xinghua village, and is 3.6km southeast of line CK319+000. It is of hill area. Country road (in cement structure) connects it with outside world in convenient traffic condition.

Roadbed and station filling

11 Tianhengshan Quarry

Weakly weathered>20.0 80 m3

Tuff: steel gray, weakly weathered, tuffite massive structure, joint fissure developed.

This pit locates at Qiongsheng town, and is 500m away from Xinhua village, 2.2km southeast away from line CK320+000. It is of lower hill area. Country road (in cement) connects it with outside world in convenient traffic condition.

Roadbed and station filling

12 Kuangye Quarry Weakly weathered >30.0

120 m3 Tuff: gray-brown to gray-green, weakly weathered, tuffite massive structure, joint fissure developed.

This pit locates at Xinhua village of Jiamusi City, and is 700m southeast away from Xinhua village, 1.2km northeast away from line CK322+300. It is of slope

Roadbed and station filling

Page 113: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

face of hill area. Country road (in cement) connects it with outside world in convenient traffic condition.

Page 114: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Reasonability analysis to borrow pitsSince utilization of borrow pits may cause side impacts to the environment, and in order to protect the farmland and woodland, and to minimize the levy to farmland and woodland, earth source is generally selected by local government, approved by railway construction party, and supported by earth source agreement signed by railway construction party and the local government.

As to this design, after site survey and negotiation with local county level government, also according to the demands of railway construction building and the local real condition, 12 borrow pits of existing quarry was preliminary selected. Moreover, new pits for earth borrowing are not planned in this design. So earth borrowing will be in market way from other earth pits rather than some new borrowing pits are required. Borrowing earth design in this way is suitable.

Treatment Methods and Environment Impact Assessment of disposal siteGeneral condition of the disposal site

Dregs construction of this project mainly includes those from railway line, station, tunnel, and bridge engineering in total amount of 1723.10×104m3. Among them, partly waste earth from roadbed and station construction is of topsoil in total amount of 118.53×104m3, and they may be reused again as the cultivation land. Others dregs in amount of 1604.57×104m3 will be disposed in the dreg field. According to the design, 45 places of dreg field are selected in total area of 217.78hm2 which can accept all dreg from whole line of this engineering. See detail in Table 5-3-20.

Page 115: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-37 General condition of disposal site for Harbin-Jimusi railway line

No. Places District of Location Area (hm2) Land type Amount (104 m3) Depth (m)1 Waste earth yard 1 at Binxi

Develop Zone

Binxian County

CK41+000 left 8.50 Slope dry land 85 10

2 Waste earth yard 2 at Binxi Develop Zone CK41+001 left 4.54 Slope dry land 45.4 10

3 Waste earth yard at Binzhou Town CK62+000 right 3km 5.13 Waste gully 51.25 10

4 Waste earth yard at Shiyangtun CK63 right 8km 6.95 Slope dry land 69.5 10

5 Waste earth yard at Taipingqiao village CK63+500 right 8.5km 3.75 37.5 10

6 Waste earth yard at Baichao of Binxian county CK75 right 8km 5.71 Slope dry land 45.7 8

7 Waste earth yard at Binan Brick plant CK83+500 left 5km 0.90 Wasteland 22.54 25

8 Disposal site at Gaolimao Tunnel CK112+800 left gully 2.40 Woodland steppe 15 10

9 Waste earth yard at Baiduhe CK118 left 1km 40 Dry land 57.15 2

10 Disposal site at entrance of Pinan Tunnel

Fangzheng County CK123+750 right 100m gully 2.90 Woodland steppe 28.95 10

11 Disposal site at exit of PinganTunnel CK125+000 right 200m gully 1.86 Wasteland 18.61 10

12 Disposal site at Lianbin Tunnel CK128+750 left 250m gully 4.20 Wasteland 42.02 10

13 Disposal site at entrance of Fangzheng Tunnel

CK131+000 left 400m gully 2.87 Wasteland 28.7 10

Page 116: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

14 Disposal site at exit of Fangzheng Tunnel CK133+500 left 500m gully 2.80 Woodland steppe 27.99 10

15 Waste earth yard 1 at Changfatun village CK138 left 500m 5.48 Dry land 25 5

16 Disposal site at changfa Tunnel CK139+500 right 300m gully 1.58 Woodland steppe 15.83 10

17 Waste earth yard 2 at Changfatun village CK141 right 200m 2.72 Wasteland 27.23 10

18 Waste earth yard at Shangzhi village CK149+700 right 700m 2.15 Waste gully 27.5 13

19 Waste earth yard at Shangzhi Brick plant CK155 right 200m 1.00 Wasteland 13 15

20 Waste earth yard at Jianshanzi CK180+700 right 1.7km 3.14 Wasteland 31.2 10

21 Waste earth yard at Demoli CK189 left 500m 17.07 Wasteland 30 2

22Waste earth yard at borrow pit for highway construction

CK189+500 right 2km 4.15 Wasteland 82.9 20

23 Waste earth yard of G221 CK190 right 1.7km 0.90 Wasteland 7.2 8

24 Waste earth yard at Shuanggou gully

Fangzheng County CK194 left 300m 1.38 Wasteland 13 10

25 Waste earth yard at Caopigou gully CK197+600 right 200m 2.33 Woodland steppe 30 15

26 Waste earth yard 1 at Gaoleng CK207+300 right 300m 1.88 Wasteland 37.5 20

27 Waste earth yard 2 at Gaoleng CK207+400 right 150m 1.40 Wasteland 20 4

28 Waste earth yard at Yongqi CK210 left 1km 3.29 Wasteland 38.5 12

Page 117: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

River

29 Waste earth yard at Waqi River CK215v1km 4.17 Wasteland 38.4 8

30 Waste earth yard at Shaizihe River CK217 left 100m 3.02 Wasteland 20 8

31 Waste earth yard at Shahezi CK220+500 left 500m 4.01 Wasteland 31.37 10

32 Waste earth yard at Erdaogou

Yilan County

CK226+500 right 500m 4.50 Wasteland 45 10

33 Waste earth yard at Toudaogou CK228+500 right 3km 8.72 Wasteland 84.2 10

34 Waste earth yard of CK230 CK230 left 100m 1.48 Wasteland 7.4 5

35 Waste earth yard ofCK236 CK236v100m 5.54 Wasteland 25.5 5

36 Waste earth yard of CK242 CK242 right 1km 10.00 Wasteland 25 3

37 Disposal site at Yilan Tunnel 1 CK247+100 right 800m 2.00 Wasteland 19.96 10

38 Disposal site at entrance of Yilan Tunnel 2 CK254+100 right 1500m 3.15 Wasteland 31.5 10

39 Disposal site at exit of Yilan Tunnel 2 CK257+880 right 500m 3.78 Wasteland 37.8 10

40 Waste earth yard at Zhushan CK262+600 right 6.2km 6.50 Slope wasteland 65 10

41 Waste earth yard at Xiaowadan CK282+000 left 5.8km 5.80 Wasteland 58 10

42 Waste earth yard at Xinhua Jiamusi city CK319+000southeast 3.6km 4.2 Wasteland 42 10

43 Disposal site at entrance of Houshishan Tunnel CK316+400 right 600m gully 3.59 Woodland steppe 35.9 10

44 Disposal site at exit of CK321+400 left 500m gully 3.59 Woodland steppe 35.9 10

Page 118: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Houshishan Tunnel

45 Waste earth yard at Xinshi village CK322+300northwest 1.2km 2.75 Wasteland 27.5 10

Page 119: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Reasonability analysis to disposal site

As to this design, 45 places for disposal site use were selected. Among them in 4 types, 36 are of gully type yard, 6 are of slow slope yard, 2 are of low-lying land yard, and 1 waste earth yard is of alluvial land yard.

Since the land occupation of this project is dominated by 19.19hm2 of woodland and 71.18 hm2 of cfarmland, and 127.41hm2 of waste land. For those disposal sites occupying the farmland, land in poor operation condition will be emphasized, and their level for cultivation will be raised after the dreg is covered by soil in depth of 40-50mm. In this way, impact from construction to agricultural production activity may be limited to a minimize range. Reasonability analysis to disposal site is listed in Table 5-3-21.

Table 6-38 Reasonability analysis to disposal site

Disposal site type Environment condition Reasonability analysis

Gully type yard

Disposal site of gully type dots in 36 places. They are not located in the stream line of the gully. Land occupation of them is waste land and woodland steppe in pile height of 2-10m.

According to the site survey report and the topographic map along the railway line, all those disposal sites can’t be regarded as the debris flow gully, and does not locates in the sensitive area. Retaining wall will be built before the dreg is being disposed, and side slope will be recovered to vegetation plants after the disposal.

Slow slope type yard

Disposal site of slow-slope type dots in6places. Land occupation of them is farmland in average pile height of 2-8.0m.

According to the site survey report and the topographic map along the railway line, all those disposal sites does not locates in the sensitive area. Retaining wall will be built before the dreg is being disposed, and side slope will be recovered to vegetation plants after the disposal. Moreover, dreg pile platform will be covered with vegetation plants. These yards are acceptable when they are supported by proper protection measures.

low-lying land yard

Disposal site of low-lying land type dots in 2 places of waste earth yard in Binan Brick Plant, and waste earth yard of borrow pits of highway construction engineering. Land occupation of them is waste land. Since water covering area over there is small, drain flow rate is designed to 0.23 and 3.49m3/s.

These 2 yards does not locate in the sensitive area. Since the land there is flat, retaining wall is unnecessary. They will also be covered with vegetation plants after disposal. These yards are acceptable when they are supported by proper protection measures.

alluvial land yard

Disposal site of alluvial land type locates in Demoli. It is the beach land of Songhuajiang River.

This yard is not rationally selected; therefore, it must be designed again in future stage.

Protection consideration for the disposal site

a. Retaining wall first. Retaining wall must be built at the site before the disposal is carried out. Waste earth and dregs must be piled in layer and pressed to compaction. Pile slope must be constructed to masonry grid type.

b.Considering the topography condition of the disposal site, protection to retaining wall must be built near the slope foot. Protection measure and type for them must be designed according to the technical specification in “Technical Specification for water and soil conservation in development to construction project”.

c. For those disposal site whose neighbor are expected to collect large area of water space, drain ditches

Page 120: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

must be constructed to prevent the runoff from sweeping over the yard.

d. Protection measure to disposal site must be done in advance the dreg disposal to secure its protection role may be realized.

e. After the disposal of dreg or waste earth, yard shall be made flat and recovered its vegetation according to actual condition to prevent the water and soil loss.

Protection measure for the disposal site

a. Protection measure for typical disposal site on gully and slope

Before the dreg is being discharged, water draining system like drain ditches must be constructed to prevent the rainfall from flushing the dreg of waste earth. This system must lead the rainfall into the natural ditches smoothly. The slope foot must be constructed to retaining wall; the slope face must be constructed to masonry grid type; and the slope end must be done to flat. The stone dreg shall be discharged in the bottom, and shall be covered by the waste earth, further covered by humus of 40-50cm depth. Finally, they shall be covered by vegetation of trees and shrub.

By considering the topography and terrain feature of the yard area, following typical treatment and protection measure to gully type yard and slope type yard can be designed. See detail in figure 5-3-8 and figure 5-3-9.

Table 6-39 Scheme for protection to gully type disposal site

Figure 6-21 Scheme for protection of gentle slope spoil yard

Page 121: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

b. Engineering measure

Engineering measure in disposal site includes retaining wall, drain ditches, rapid flow slot, and masonry grid slope.

Design to retaining wall①

According to the calculation, height of the retaining wall is designed to 3-5m, type of it is designed to gravity one. Stability of the wall then can be calculated by the computer program. As to its length, site survey to topography may be employed.

An expansion joint of 2cm wide will be designed to the wall in every longitudinal 10~15m length of the wall which will be filled by the asphalt board. Moreover, hole for draining water will be designed in every longitudinal 2~3m length of the wall. If the wall is higher than 1m~1.5m, bottom of it will be designed to a row of hole for graining water. If the wall is higher than 2-3 m, two row of hole for draining water in vertical will be designed in the wall which lowest row of them will be higher than 0.3m from the ground level. Hole for draining water on the retaining wall will be designed to geotextile for filtration.

As to this design, stability calculation is done according to the height of 3-5m. Earth press is calculated according to the Coulomb’s Theory.

According to the calculation, each target can meet the requirements in “Technical Specification for water and earth reservation in development construction project”. The stability factor can meet the demand; the anti-sliding stability factor is more or to 1.3; the anti-inclining stability factor is more or to 1.5. It shall be noted that selection to the disposal site must consider that load ability of the base must be more than the designed maximum base pressure value; otherwise, base strengthening measure or reinforced concrete base board must be employed. Calculation result is listed in Table 5-3-22.

Table 6-40 Calculation to section size of retaining wall and its parameter

Section size(mm) Volume in meter (m3)

Standard soil pressure (kN) Stability factor

Deviation (mm)

Designed base press value (kPa)h h1 h2 b1 b b2 H V Slide-

pIncline-p

2000 / 173 500 865 0 1.32 18.11 4.85 1.66 2.16 194 119.03

3000 / 231 600 1154 0 2.31 40.74 10.91 1.38 1.67 354 252.92

4000 400 317 750 1587 100 3.17 72.42 19.4 1.33 1.74 455 290.49

5000 400 413 950 2067 200 4.13 113.16 30.31 1.35 1.88 531 309.31

Page 122: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-22 Design scheme of spoil retaining wall

Design to flood releasing valley and energy dissipation measure②

At the top platform of the dreg pile, masonry flood ditches will be constructed, and their ends will be supported by rush slots or water-fall to drain the rainfall on the pile or from slope around it. As to this design, the maximum peak flow of rain collection area for this disposal site is used to calculate the section area of the typical flood ditches. Typical section size of flood ditches in all disposal site is selected according to the rain collection area. Length of them is defined according to the site surveyed topography.

a. Flood calculation

Design to the flood frequency: according to regulation on smaller water drain engineering for medium-size slope face in “Technical Specification on water and soil preservation treatment ---- smaller water drain and utilization engineering”, also considering the flood control standards and importance of the downstream area, flood frequency is designed to once in ten years or in twenty years. Since many sensitive areas and national preservation areas locates near this railway line, the precaution standard then is designed to once in twenty years. Rain collection area for flood ditches in disposal site is normally less than 1.0km2. Flow of the peak for slope face then is calculated to according to formula in “Technical Specification on water and soil preservation for development of construction project”:

KIFQB 278.0Where, QB—designed maximum peak flow (m3/s);

I—maximum rainfall intensity in 1h(mm/h), 78mm/h;

F—rain collection area of ditches in upstream(km2); K—runoff factor(for this design 0.65)According to the designed discharge, flow passing cross section is calculated based on the equation below:

Where, QB- the biggest precipitation of slope face (m3/s);

A- cross sectional area of intercepting drain (m2);

C- Chezy coefficient;

QB=AC √Ri

Page 123: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

R- hydraulic radius (m);

i – gradient of intercepting drain

Channel of flood discharge is in trapezoidal cross section. The size is decided by a formula, uniform stream of open channel. The speed of flow should be moderate.

The grade of channel lengthwise is 5/1000~1/100, and the ratio of inslope is 1:0.75, safe altitude 0.2m, h is the water depth of the peak discharge when passing. The channel is built by layers of stones. The stone is 0.3m thick, 0.15m- thick gravel sand cushion laid below.

After computation, the following determined 7 kinds of typical section size see Table 5-3-39. The cross section size of truncation and drain ditch is chosen according to the real controlled area and designed discharging quantity. At the point of big bottom slope in the drain ditch, the size of cross section should be suitably reduced and the side slope ratio should be enlarged.

Table 6-41 typical cross section table

fracture surface type

discharge capacity(m3/s)

side slope

m

roughness

n

Gradient

i(1:n)

Designing water depth(m)

bottom breadth

b(m)

valley height

H(m)

mouth breadth

B(m)

fracture surface(m2)

each linear

meter fluid laying stone(m3)

each linear

meter

foundation excavation ( m3)

each linear meter sand cushion(m3)

I 0.34 0.75 0.014 200 0.30 0.50 0.50 1.25 0.31 0.825 1.781 0.347

II 0.88 0.75 0.014 200 0.50 0.50 0.70 1.45 0.51 0.975 2.285 0.422

III 1.15 0.75 0.014 200 0.50 0.70 0.70 1.75 0.61 1.035 2.519 0.452

Ⅳ 1.79 0.75 0.014 200 0.60 0.80 0.80 2.00 0.80 1.140 2.933 0.504

Ⅴ 3.07 0.75 0.014 200 0.80 0.80 1.00 2.20 1.10 1.290 3.563 0.579

Ⅵ 7.74 0.75 0.014 200 1.00 1.50 1.20 3.45 2.07 1.650 5.375 0.759

Ⅶ 12.32 0.75 0.014 200 1.00 2.50 1.20 4.95 2.97 1.950 6.995 0.909

b. Energy-reducing measures

This project is located at the low hill. The ground at the exit of flood-discharging ditch heaves greatly in some of dregs field, and energy-reducing facility is needed to establish to connect with the original water-discharging system and prevent the water from washing the downstream. Because the exit dropping variance in some dregs field is bigger than 5m, steep trough project and energy-reducing basin is chosen in this report’s water-discharging designing in the dregs field.

The energy-reducing facility is made up of graduation section upstream, steep trough section, energy-reducing basin and entirely flowing section downstream, meeting with flood-discharging ditch above and with the original water-discharging system, the typical cross-section schematic drawing showing in chart 5-3-11.

Page 124: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Figure 6-23Typical schematic drawing of energy-reducing facility

The steep trough uses the rectangular section, and adds alternating rectangular coarse-tank at the bottom to increase the water depth, reduce the speed of flow and improve downstream energy-reducing condition. The size is established according to the open canal uniform-stream formula, the gradient 1:3.0. The height of side wall H is determined after the designed water depth and security height 0.5m.

The force-reducing basin uses brick-laying for mortar walling, trough floor and spandrel wall both 0.5m in thickness, the cross section size determined according to the equation below:

The size of steep trough in typical dregs field and the typical section of energy-reducing basin sees Table 5-3-24.

Table 6-42 steep design parameter list

designing flowing quantity

Q (m3/s)

entrance section

steep tank section  Energy releasing basin section exit section

length

(cm)

bottom breadth

(cm)

groove depth (cm)

breadth (cm)

depth (cm)

ridge height

(cm)

baseboard thickness

(cm)

level length of slope(cm)

total flowing length(cm)

Q≤1.0 150 40 60 150 100 40 45 90 150

1.0<Q<2.0 200 50 70 200 110 50 50 100 200

2.0<Q<5.0 250 60 80 250 120 55 55 110 250

5.0<Q<8.0 300 75 95 300 120 60 55 120 300

8.0<Q<12.0 450 85 100 400 120 70 60 130 450

Platform draining ditch ③

In the dregs field, the platform drainage facility uses brick-laying stone water discharging ditch (vertically and horizontally spacing 200m). Because the platform area is small, the size of drain cross-section selects trapezoidal cross section, the bottom extension 50cm, orifice width 80cm, deep 50cm, the lengthwise slope not smaller than 3/1000. The mortar layers are 0.3m, 0.15m thick sandy gravel breaker strip below.

Land improvement④

After the completion of the construction, the dregs field should be leveled and smooth by backfilling,

Page 125: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

second ploughing and vegetation, according to the actual condition. If conditions permit, clay layers in 20cm thick is compacted to form the aquiclude and covered with surface soil 40-50cm. If used for farming, the fields should be cultivated completely and executed with chemical substances to improve soil structure and nutrients.

Outer slope face of the field needs improvement, when higher than 8m; the 2m platform should be built. Boundary ridges should be built to keep off water at the intersection point of the dregs platform and side slope.

Temporary protective measure

For temporary project, topsoil stripping quantity of farming is 50cm and forest land 30cm, without stripping for wasted land and pond. The peeling regolith should be deposited inside the scope of dregs field land scope. Knitting bags are used to protect the toe of slope as temporary protective measure. Piles sets should not be higher than 4m and ratio of side slope should be controlled in 1:1.5. Height× top wide × bottom wide =1.0m×0.5m×1.1m trapezoidal cross section is adopted as the temporary earth retaining wall. it should be mutual linking and joining when built, the length of joint should not be less than 1/3 of the knitting bag . Surface of piled soil should be compacted and sprayed with water. Due to a long period of piling and loose structure of the soil, it is easy to become the source of wind and water erosion. Soil erosion happens during rainy and windy season, so the exposed surface should be protected by mixing the seeds of bermuda grass and eremochloa ophiuroides, etc. plant the protection, 60kg seeds should be sowed each hectare.

Design of plant protective measure

Dreg abandoning sticks to the principle of resisting before abandoning. The dregs resisting should be built at the beginning. Stone dregs are thrown away before the wasted earth. After the completion of abandonment, the field should be compacted to smooth and leveled. The dregs piling slope should be controlled at about 1:2. Then afforestation and grass sowing is carried on in outside earth from embankment and station topsoil, to restore plantation. The thickness of the covered earth is 40cm for the planting of shrubs and mixed grass sown in different rows.

The plant protection measures should relate to the local soil conservation and forest plan. Based on the principle of ecology restoration, the local wide-spreading fine tree species and grass of shrub should be planted to restore the plantation as soon as possible to make the community stable. Arbors should be primarily locust tree and shrubs should be amorpha fruticosa, lespedeza and so on. The grass seeds will be setaria viridis, purple fescue, awnless brome, etc. The afforestation designing sees Table 5-3-25 afforestation technology skills see Table 5-3-26.

Table 6-43 afforestation designing table

plant type forest species

mixed growth type

row spacing(m) tree specification density

arbor silver chain mixed growth between rows 2×2 2-year strong sprout 1250

item/hm2

Wide-leafed shrub

river locust, bicolor

river locust, bicolor mixed growth between rows , sowing mixed grass seeds within rows

1×1 tree height about 80cm 10000 item/hm2

mixed grassneatness≥90% , germination percentage≥85%

60kg/hm2

Table 6-44 Afforestation technology table

item season means Specifications & requirement

planting spring tree planting Trees straight,root extending,moderate depth,raising and treading

Page 126: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

trees after half earth filling, refilling and treading, loose earth covering; depth of the trees 2-3cm over the original earth marking of the root; sowing method for mixed grass seeds (suitable earth covering based on the moisture of the soil); germination hastening before sowing for good rate of emergency.

nurture Spring & autumn

2-year continual nurturing after planting,soil loosening and weeding, fertilizing, pesticide defending , dead tree wiped away immediately and replanting.

After analysis and computation, the measures of soil conservation and construction quantity in the dregs(waste earth) field 5-3-27.

Page 127: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-45 soil conservation measures and construction quantity in the dregs(waste soil) protection field

No Name

Admin.

district

Construction measures Planting measures Temporary measures

Brick-laying stone dreg-resisting wall

Flood-releasing ditch &energy-reducing measures

Platform water drainage ditch

Field leveling(hm2)

Arbor

Shrub

Mixed grass

seeds

Topsoil

stripping

(10000m3)

Earth knitting bag retaining wall

(m3)

Grass seeds

sowing

Topsoil

backfilling

(10000m3)

L( m)

H(m)

Brick-

laying

stone

(m3)

Foundation

excavation

(m3)

L(m)

Brick-

laying

stone

(m3)

Earth

excavation

(m3)

Sand

cushion (m3)

L

(m)

Brick-

laying

stone

(m3)

Earth

excavation

(m3)

Sand

cushion

(m3)

Field

leveling

Reclaiming

ground

leveling

1000

item

1000

item

Area

(hm2)

Quan.(kg)

Area

(hm2)

Quan.(kg)

1

Binxi development

region

waste earth field 1

Bin County

117 5 481.64 242.57 729 1093

.30 976.68 2223.05

206

158.74 319.54 70.0

9 8.50 8.50 8.50 221.27 0.85 51 3.40

2 Binxi development

region

waste earth field 2

85 5 352.00

177.28 533 695.28

1692.18

303.64

151

116.01

233.53 51.23

4.54 4.54 4.54 161.71

0.45 27.24 1.82

Page 128: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

3

Binzhou town waste

earth field

91 5 373.99 188.35 566 848.

94 758.39 1726.18

160

123.26 248.12 54.4

3 5.13 10.25

30.75

3.59 215.25 5.13 148.8

0 0.38 23.0625 1.54

4

Shichang village waste earth field

105 5 435.51 219.34 659 988.

61 883.16 2010.17

186

143.54 288.94 63.3

8 6.95 6.95 6.95 200.08 0.70 41.7 2.78

5

Taipingqiao village waste earth field

77 5 319.91 161.12 484 726.

18 648.72 1476.57

137

105.44 212.24 46.5

6 3.75 7.50

22.50

2.63 157.50 3.75 127.2

8 0.28 16.875 1.13

6

Waste earth field in Baichao of Bin County

96 4 303.06 198.85 598 896.

28 800.68 1822.44

169

130.13 261.96 57.4

6 5.71 5.71 5.71 181.39 0.57 34.275 2.29

7

Binan brick-field waste earth field

67

51.70 104.07 22.8

3 0.90 1.80 5.41 0.6

3 37.87 0.90 62.41 0.07 4.0572 0.27

8 Korea hat tunnel

62 5 255.93

128.89 387 580.95

518.98 1181.26

110

84.35

169.79 37.25

2.40 4.80

14.40

1.68

100.80 2.40 101.82

0.18 10.8 0.72

Page 129: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

dreg field

9

Baidu River waste earth field

447

344.35 693.18 152.

0540.00 40.00 40.00 480.0

0 4.00 240 16.00

10

Pingan tunnel entrance

dreg field

Fangzheng

County

68 5 281.08 141.56 425 425.

37 680.59 986.85

120

92.64 186.48 40.9

1 2.90 5.79

17.37

2.03 121.59 2.90 111.8

3 0.22 13.0275 0.87

11

Pingan tunnel exit dreg field

55 5 225.36 113.50 341 511.

57 457.00 1040.19

96

74.28 149.52 32.8

0 1.86 3.72

11.17

1.30 78.16 1.86 89.66 0.14 8.3745 0.56

12

Lianbin tunnel dreg field

82 5 338.64 170.55 512 768.

70 768.70 1563.03

145

111.61 224.67 49.2

8 4.20 8.40

25.21

2.94 176.48 4.20 134.7

3 0.32 18.909 1.26

13

Fangzheng tunnel entrance dreg field

68 5 279.87 140.95 424 635.

29 635.29 1291.76

120

92.24 185.68 40.7

3 2.87 5.74

17.22

2.01 120.54 2.87 111.3

5 0.22 12.915 0.86

14

Fangzheng exit dreg field

67 5 276.38

139.20 418 627.38

627.38 1275.68

118

91.09

183.37 40.22

2.80 5.60

16.79

1.96

117.56 2.80 109.96

0.21 12.5955

0.84

Page 130: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

15

Changfa village waste

earth field

94 3 216.30 194.77 585 877.

85 877.85 1784.97

166

127.46 256.57 56.2

8 5.48 5.48 5.48 177.66 0.55 32.88 2.19

16

Changfa tunnel dreg field

50 5 207.85 104.68 315 471.

81 471.81 959.36

89

68.50 137.90 30.2

5 1.58 3.17 9.50 1.1

1 66.49 1.58 82.70 0.12 7.1235 0.47

17

Changfa village

waste earth field 2

170 4 538.90 353.60 446 668.

31 668.31 1358.90

117

89.85 180.86 39.6

7 2.72 5.45

16.34

1.91 114.37 2.72 108.4

6 0.20 12.2535 0.82

18

Shangzhi village

waste earth field

70 6 702.10 145.60 750 1125

.001125.00

2287.50

104

79.84 160.71 35.2

5 2.15 4.30

12.90

1.51 90.30 2.15 96.37 0.16 9.675 0.65

19

Shangzhi brickyard

waste earth field

250 375.00 375.00 762.

5071

54.45 109.60 24.0

4 1.00 2.00 6.00 0.7

0 42.00 1.00 65.73 0.08 4.5 0.30

20

Jianshanzi waste

71 5 292.74

147.43 443 664.50

664.50 1351.15

12

96.48

194.21 42.60

3.14 6.28

18.84

2.20

131.88 3.14 116.47

0.24 14.13 0.94

Page 131: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

earth field 5

21

Demoli waste earth field

292

224.95 452.83 99.3

317.07

34.14

102.42

11.95 716.94 17.07 271.5

6 1.28 76.815 5.12

22

freeway earth in-take pit waste earth field

509 763.47 763.47 1552

.39

144

110.85 223.14 48.9

5 4.15 8.29

24.87

2.90 174.09 4.15 133.8

1 0.31 18.6525 1.24

23

G221waste earth field

66 4 210.51 138.13 237 355.

76 355.76 723.37

67

51.65 103.98 22.8

1 0.90 1.80 5.40 0.6

3 37.80 0.90 62.35 0.07 4.05 0.27

24

Shuanggou waste earth field

94 5 388.13 195.48 294 440.

53 440.53 895.73

83

63.96 128.75 28.2

4 1.38 2.76 8.28 0.9

7 57.96 1.38 77.21 0.10 6.21 0.41

25

Caopigou waste earth field

122 8 2152.88 254.00 382 572.

41 572.41 1163.91

108

83.11 167.30 36.7

0 2.33 4.66

13.98

1.63 97.86 2.33 100.3

3 0.17 10.485 0.70

26

Gaoleng waste earth field

110 8 1931.27 227.85 342 513.

49 513.49 1044.10

97

74.55 150.08 32.9

2 1.88 3.75

11.25

1.31 78.75 1.88 90.00 0.14 8.4375 0.56

27

Gaoleng waste

95 2 124. 196.89 296 295. 473.29 686. 8 64. 129.68 28.4 1.40 2.8 8.40 0.9 58.80 1.40 77.77 0.11 6.3 0.42

Page 132: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

earth field 2 95 80 27 4 42 5 0 8

28

Yongqi River

waste earth field

145 6 1455.42 301.82 453 974.

94 693.79 1786.63

128

98.76 198.80 43.6

1 3.29 6.58

19.74

2.30 138.18 3.29 119.2

2 0.25 14.805 0.99

29

Waqi River waste earth field

Fangzheng

County

82 4 258.93

169.90 511 1097.6

1781.09

2011.43

144 111.18 223.8

149.09 4.17 8.3

425.02

2.92

175.14 4.17 134.

22 0.31 18.765 1.25

30

Shazi River waste earth field

139 4 440.71

289.17 434 934.08 664.7

11711.75

123 94.62 190.4

741.78 3.02 6.0

418.12 2.11 126.

84 3.02 114.22 0.23 13.5

9 0.91

31

Shahezi waste earth field

160 5 661.63

333.22 501 1076.3

4765.96

1972.46

142 109.03 219.4

848.14 4.01 8.0

224.06

2.81

168.42 4.01 131.

62 0.30 18.045 1.20

32

Erdaogou waste earth field

Ilan

170 5 700.88

352.99 530 1140.2

1811.41

2089.50

150 115.50 232.5

051.00 4.50 9.0

027.00

3.15

189.00 4.50 139.

43 0.34 20.25 1.35

33

Toudaogou waste earth field

236 5 975.66

491.37 738 1107.3

6989.24

2251.64

209 160.78 323.6

570.99 8.72 17.

4452.32

6.10

366.24 8.72 194.

09 0.65 39.24 2.62

3 CK230 97 3 224. 202.4 304 851.59 526.1 1462 86 66.24 133.3 29.2 1.48 2.9 8.8 1.0 62.1 1.48 79.9 0.11 6.66 0.44

Page 133: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

4waste earth field

82 3 6 .90 4 5 6 8 4 6 6

35

CK236 waste earth field

188 3 434.97

391.66 588 1647.6

01017.98

2830.35

166 128.15 257.9

756.59 5.54 11.

0833.24

3.88

232.68 5.54 154.

70 0.42 24.93 1.66

36

CK242 waste earth field

253 2 333.94

526.20 791 790.57 1264.

911834.12

224 172.18 346.5

976.03 10.00 20.

0060.00

7.00

420.00 10.00 207.

85 0.75 45 3.00

37

Ilan tunnel 1 dreg field

113 5 466.79

235.09 353 353.20 565.1

2819.42

100 76.92 154.8

433.97 2.00 3.9

911.98

1.40

83.83 2.00 92.8

6 0.15 8.982 0.60

38

Ilan tunne 2 entrance dreg field

142 5 586.40

295.33 444 443.71 709.9

31029.40

125 96.63 194.5

242.67 3.15 6.3

018.90

2.21

132.30 3.15 116.6

5 0.24 14.175 0.95

39

Ilan tunnel 2 exit dreg field

156 5 642.37

323.52 486 486.06 777.6

91127.65

137 105.86 213.0

946.74 3.78 7.5

622.68

2.65

158.76 3.78 127.

79 0.28 17.01 1.13

40

Zhushan waste earth field

204 5 842.36

424.24 637 637.38 1019.

801478.72

180 138.81 279.4

361.29 6.50 13.

0039.00

4.55

273.00 6.50 167.

57 0.49 29.25 1.95

41

Xiaowadan waste earth

193 5 795.71

400.74

602 602.08 963.33

1396.82

170

131.13 263.96

57.90

5.80 11.60

34.80

4.06

243.60

5.80 158.29

0.44 26.1 1.74

Page 134: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

field

42

Xinghua waste earth field

City of

Jiamusi

143 5 592.48

298.39 512 512.35 819.7

61188.65

145 111.58 224.6

249.27 4.20 8.4

025.20

2.94

176.40 4.20 134.

70 0.32 18.9 1.26

43

Monkey rocky mountain entrance

dreg field

133 5 547.77

275.87 474 1743.1

5923.68

2818.41

134 103.16 207.6

745.55 3.59 7.1

821.54

2.51

150.78 3.59 124.

53 0.27 16.155 1.08

44

Monkey rocky mountain exit

dreg field

133 3 306.38

275.87 474 1018.4

2724.73

1866.31

134 103.16 207.6

745.55 3.59 7.1

821.54

2.51

150.78 3.59 124.

53 0.27 16.155 1.08

45

Xinhua village waste earth field

116 5 479.42

241.45 415 891.34 634.3

01633.44

117 90.29 181.7

539.87 2.75 5.5

016.50

1.93

115.50 2.75 109.

00 0.21 12.375 0.83

Page 135: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

6.1.9 Analysis and protective measure of temporary construction During the construction of the main project, the matching facilities include material field, beam field, rail laying site, mixer station, construction site, Construction building and construction detour ,etc. these facilities basically distribute on the both sides of the roadbed along the project route.

Prevention area of construction and production This area mainly includes the beam field, mixer station, construction site and life area, etc. mainly cultivated land and wasted land. During construction, due to frequent activities of machinery and people, the original geomorphology and vegetation are disturbed and destroyed. The hardened construction site and the remained wasted sand stone will result in changes of soil structure, leading to a poor ability of production. In order to improve the region ecological environment and reduce soil erosion, effective measures must be taken during and after the construction. Objects of treatment are as follows:10 beam fields (123.40hm2 ) 3 rail board prefabrication field (25.20h m2 ), 31 mixer station (2900h m2) temporary electricity line163.00km(7.34h m2) and other construction field, Construction building and temporary dregs piling field 46.68h m2 .the whole is 231.62h m2.

Measures for prevention and control

This project involves a great variety of construction fields and disturbs many kinds of earth surface .According to the principle “unified plan, source control, combination of prevention and restoration”, effective prevention protective measures must be taken. The key is source control and the process control. Reduce the damages of the original landform to a minimum degree. The priority is given to the combination of permanence and temporary concerning the location choice of the temporary project .2 rail laying bases need to unify permanent occupying land area of the station yard. Material factory should be built in the existed railway station.

Distribution of measures.

Temporary facility built in the existed field should be cleared after the construction had ended. Before the implementation of temporary facilities occupying the forest land, the open land and the cultivated land. Topsoil stripping quantity of farming is 50cm and forest land 30cm, wasted land 20cm. The peeling regolith should be deposited beyond fields. Knitting bags are used to protect as temporary protective measure. Piles sets should not be higher than 4m and ratio of side slope of piling should be controlled in 1:1. During piling, the exposed surface should be protected by mixing the seeds of bermuda grass and eremochloa ophiuroides, etc. plant the protection, 60kg seeds should be sowed each hectare.

In the large-scale temporary location draining water system has been included in the main body design. Excavation of drain or the cloth lap drain tank. The resilience and the investment has integrated in the principal part.

After the construction, hardened ground and the macadam pavement will be demolished completely and then filled and leveled to be smooth. cultivation and preparation of soil, the backfill regolith, execution of the farm manure, restoration for the farming and the lawn, farm manure 45m3 for each hectare. Selection of the grass plants the white aneurolepidium chinense, the purple sheep fescue, the awnless brome and so on, each hectare broadcast sowing grass seed 60kg.

The flow sees Figure 5-3-12.

The measures of soil conservation and construction quantity in the dregs (waste earth) field

Page 136: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Coverage clearing Topsoil stripping Topsoil conservation

Temporary facility arrangement

Field clearing

Topsoil backfilling

Reclaiming ground leveling/earth and fertilizer adding

earthand fertilizer addin fertilizzertadding

Original land type Other-used land Reclaiming grassland

Farmland

Reclaiming farmland

Figure 6-24 Construction produces the quarters measure arrangement flow chart

After the analysis computation, the construction production life prevention area prevention measure and the resilience see Table 5-3-28.

Page 137: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-46 Bill of quantity for prevention measures in construction site and camp

administrative district City of Harbin

Bin County

Fangzheng County

Ilan county

City of Jiamusi sum

Construction

measures

ground leveling(hm2) 18.24 64.97 61.53 66.23 20.65 231.62

reclaiming ground leveling

green fertilizer adding(hm2)15.66 53.72 28.18 25.74 15.97 139.27

Plantation

measures

grass sowingarea(hm2) 2.58 11.25 33.35 40.49 4.68 92.35

quantity(kg) 154.80 675.00 2001.00 2429.40 280.80 5541.00

shrub 1000 item 15.48 67.50 200.10 242.94 28.08 554.10

Temporary

measures

Topsoil stripping(10,000m3) 8.36 29.16 22.35 23.67 8.95 92.48

earth knitting bag(m3) 346.92 647.99 567.28 583.87 358.90 2504.96

grass seeds sowingarea(hm2) 2.09 7.29 5.59 5.92 2.24 23.12

quantity(kg) 125.37 437.39 335.22 355.11 134.18 1387.26

topsoil backfilling

(10,000m3)(10,000m3) 8.36 29.16 22.35 23.67 8.95 92.48

Temporary access road of construction Newly built and rebuilt construction detour 202km, with a land area of 85.38hm2, are designed to be the village road or the field road. It is suggested that road surface can be the macadam pavement or the putty stone road surface, 20cm thick. When construction detour span ditch and ditch, the culvert or the bridge etc. the building should be constructed ,guaranteeing the draining water channel or the irrigation water channel unimpeded, simultaneously, the road surface should be sprayed with water regularly, Appearance of the floating dust by driving cars should be prevented. After the construction, part of the construction detour is used as the field by-path or the country road with the width 4m~7m. Pavement condition in the project area should be improved and the road system should be perfected. The roadbed the side slope of the roadbed should be protected with planting grass.

Protection of roadbed side slope

The excavation of the construction detour on the slope worsens the degree of soil erosion .The emphasis lies in the protection of side slope. The specific measures are as follows: it must be followed by the Construction that earth should be excavated and transported as needy and promptly and can not be dumped down willingly. Drainage ditches should be built inside the excavated side slope and be built with layers with a thickness 30cm. base sand cushion 15cm, the cross section for the bottom wide × ditch deep× orifice width =0.5×0.5×0.8m, the lengthwise grade 1%, flow capacity is 0.38m3/s. planting grass to protect side slope of filling and excavation..

Measures for later period

Construction detour should be restored to the original land function, if not used as the country road or the field by-path. Farming land should restored with application of farm manure, each hectare with farm manure 45m3; The original wasted land and forest land should be restored by cultivation and preparation of sowing mixed grass, the white aneurolepidium chinense, the purple sheep fescue, the awnless brome etc, each hectare sowing grass seed 60kg.

After the analysis calculation, in the construction detour area, measures of conservation of water and soil and the quantity see Table 5-3-29.

Table 6-47 prevention measure project meter of construction detour area

Page 138: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

administrative

district

construction measuresplantation measures

ground

leveling

(hm2)

draining ditch reclaiming ground leveling and green fertilizer adding (hm2)

length

(m)earth excavation

(m3)

M7.5

mortar-laying

stone

(m3)

sand cushion

(m3)

grass sowing

(hm2)

grass sowing slope(m2)

City of Harbin 9.23 0 0 0 0 3.32 0 5.91

Bin County 25.43 15990 24785 12152 5437 9.15 191880 16.28

Fangzheng County 23.88 14880 23064 11309 5059 8.6 178560 15.28

Ilan County 19.12 11865 18391 9017 4034 6.88 142380 12.24

City of Jiamusi 7.73 3855 5975 2930 1311 2.78 46260 4.95

sum 85.39 46590 72215 35408 15841 30.73 559080 54.66

6.1.10 conservation of water and soil plan

soil erosion In construction process, because of some construction activities, such as earth intake and abandonment, construction of embankment and culvert, remodeled landform with the artificial side slope has come into being. Moreover these activities have contributed heavy damages to the original landform and the natural vegetation, leading to reduction or lose of its original function- conservation of water and soil. The occurrence and development of original landform soil erosion are intensified and new artificial loss has being created.

Analysis of influencing factors concerning soil erosion in railway construction sees Table 5-3-30.

Page 139: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-48 Analytical table for influencing factors concerning soil erosion

Area

Affective factors

type of soil erosion Artificial factor

Natural factor

Type of vegetation Texture type Exogenic force

roadbed section station yard section

Bridge and culvert section tunnel section

earth filling section

strip the floor vegetation, form bare earth roadbed,form earth side slope and roadbed.

Forest land

Farmland

relatively loose precipitation hydraulic erosion

both sides of embankment

Frequent vehicle grinding, artificial activities and stripped topsoil tying up, impacts vegetation growth to reduce the soil conservation function.

relatively loose precipitation hydraulic erosion

Bridge and culvertExcavated earth and mud from bridge foundation ditch not cleared promptly is easy to be washed away by runoff water to form new soil erosion.

relatively loose precipitation hydraulic erosion

Station strip topsoil, form bare earth roadbed,form earth side slope and roadbed.

relatively loose precipitation hydraulic erosion

Tunnel Front slope of tunnel side not protected promptly is easy to form earth side slope and in soil erosion. relatively loose precipitation hydraulic

erosion

Earth intake area Earth take field

Strip topsoil vegetation , form borrow pit , disturb the stability of original body earth and form a great area of bare surface.

Waste land Loose precipitation hydraulic erosion

Dregs area Dregs fieldWaste piled loosely, before the realization of protection, is extremely to create serious soil erosion because of loose structure and lack of floor coverage.

Shrub woodland, farmland, waste land loose precipitation hydraulic

erosion

Construction access area

Construction access road Form bare roadbed surface and suppress vegetation Farmland , forest

land relatively loose precipitation hydraulic erosion

Construction Large and Suppress and destroy original landform, wildwood Farmland ,waste relatively loose precipitation hydraulic

Page 140: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

production and living area temporary facility and weaken original soil conservation function land, forest land erosion

Page 141: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Forecast time interval of soil erosion This project belongs to the construction item. Concerning the details of the beginning and development of soil erosion during the process, prediction period is made up of the construction preparation period, the construction period and the natural recovery period.

Preparation period

The construction preparation period of this project is from July, 2010 to October, 2010, the deadline is 3 months.

Construction period

This project construction period is from July, 2010 to June, 2014. The total time is 4.0 years.

Natural recovery period

According to natural condition of the rail line and the project characteristics, it is predicted that 2 years is needed for nature to recover from the impact of soil erosion.

The period for roadbed project construction is 17 months. The period for arch of bridge construction is 30 months. The period for tunnel construction is 33 months, after certain subsidence time, the roadbed can be paved. Period for roadbed project construction is prolonged to 24 months. Considering the construction period will possibly be adjusted, under the most disadvantageous interval, period for the tunnel area, the arch of bridge area, the abandoned dregs field area, the construction detour area and the area of construction and production should be predicted to be 3 years. Other construction period predicted to be 2.5 year. For details sees Table 5-3-31.

Table 6-49 project various project areas soil erosion forecast time interval table

foreshadowing period

roadbed section

station yard section

bridge and culvert

section

tunnel section

dregs field

construction access

road section

construction production and living area

temporary earth piling section

construction preparing period

0.5 year

0.5year 0.5 year 0.5 / 0.5 year 0.5 year /

Construction period

2.5 year

2.5 year 3.0 year 3.0

year 3.0 year 3.0 year 3.0 year 1.0 year

nature restoring period

2 year 2 year 2 year 2 year 2 year 2 year 2 year /

Quantity forecast of soil erosion (1) The additional quantity of soil erosion is predicted by calculating several aspects. Possible soil erosion area caused by the construction, the soil erosion background value and predicted value of soil erosion intensity. The formula is as follows:

Prognostic formula of soil erosion quantity is:

Where, Ws1-- present soil erosion quantity (t);

Mwi-- soil erosion modulus of original landform (t/ km2. a);

W =∑i=1

5

∑k=1

3

F i×M ik×Talignl ¿ ik ¿¿¿

Page 142: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Fi-- disturbed surface area (km2);

Ti-- forecast time interval (a);

N-- forecast unit.

The new added soil erosion quantity may be calculated according to the equation below:

Where, W—quantity of soil erosion of the surface disturbance, t;

W—additional quantity of soil erosion of the surface disturbance, t; △i-- forecast unit (1,2,3,4,5);

k-- forecast time interval (1,2,3), refers to the construction preparation period, the construction period and the natural recovery period;

Fi-- ith forecast unit area, km2;

M-- additional soil erosion modulus at different time interval and of different unit, t/(km2 . a); △(2) Modulus determination of original landform soil erosion

Based on materials collected by remote research, in combination with material collected through on-the-spot investigation, a detailed analysis of construction area's terrain landform, the climate, the vegetation and present situation of soil erosion is performed. The degree of Soil erosion of project area is and mild primarily, partial land sector suffer from moderate corrosion. The occupying land area of project belongs to forest land and cultivated land. The farming is primarily smooth and the soil erosion is slight. Therefore, depending on the present situation of soil erosion, it can be decided that original landform soil erosion modulus of this area is 200~1500t/km2 .a along the route.

(3)Modulus determination of soil erosion of landform disturbance

This project has almost the same conditions of terrain landform, vegetation and rainfall as the Snow Town highway of China. So, it is beneficial to analyze reasons, kinds and distributions of soil erosion from ChangTing to Liuhe of Snow Town highway of China. Considering the construction characteristics of railway, the result of soil erosion intensity can be analyzed and revised comprehensively

Regional soil erosion modulus of this project See Table 5-3-32.

Table 6-50 modulus of soil erosion of landform disturbance Unit: t/km2.a

Section

Soil erosion modulus(t/km2•a)Construction preparing

period

Construction period

Nature restoring period

First year Second year

Plain area

( starting point ~CK36+477)

Roadbed section 1000 3000 1000 200

Station yard section 1000 3000 1000 200

Bridge and culvert section 1000 3000 1000 200

construction access road section 1000 3000 1000 200

Construction production and living section

1000 3000 1000 200

△W =∑i=1

5

∑k=1

3

Fi×△M ik×Talignl ¿ ik ¿ ¿¿

Page 143: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Temporary earth piling section / 5000

Low hill area ( CK36+477 ~ending point)

Roadbed section 2000 4000 3000 1000

Station yard section 2000 4000 3000 1000

Bridge and culvert section 2000 4000 3000 1000

Tunnel section 2000 4000 3000 1000

Dregs field section / 4000 3000 2000

Construction access road section 2000 4000 3000 1000

Construction production and living section 2000 5000 3000 1000

Temporary earth piling section / 8000

(4) Quantity forecast of soil erosion of original landform

A ccording to possible soil erosion area of different construction stages and the prediction time of project construction and natural recovery, the quantity of soil erosion of original landform during future project construction and natural recovery period can be predicted based on the soil erosion modulus of original landform. The forecast time for roadbed area, the station yard area, the abandoned dregs field area forecast time is 5 years, 5.5 year for the arch of bridge area, the tunnel area, the construction detour area, the construction production and living area. Total quantity for original landform soil erosion total is 13.76×104t. For details, see Table 5-3-33.

Page 144: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-51forecast table for original landform soil erosion

Administrative district Commencement and germination mile Foreshadowing unit

Original landform

Foreshadowing

area(hm2)

Foreshadowing

period(a)Modulus(t/km2·a) Quantity of soil

erosion (t)

City Harbin Plain area

Commencement~CK16+150

Roadbed section 82.75 5 200 827.50

Station yard section 0.84 5 200 8.40

Bridge and culvert section 54.19 5.5 200 596.09

Construction access road section 9.23 5.5 200 101.52

Temporary facility section 18.24 5.5 200 200.64

Temporary earth piling 7.35 1 200 14.70

Subtotal 172.60 1748.85

Bin County

Low hill area

CK16+150~CK103+350 Roadbed section 194.94 5 1500 14620.50

Station yard section 52.99 5 1500 3974.25

Bridge and culvert section 102.25 5.5 1500 8435.63

Tunnel section 0.40 5.5 1500 33.00

Waste earth section 77.88 5 1500 5840.93

Construction access road section 25.43 5.5 1500 2097.56

Temporary facility section

64.97 5.5 1500 5360.03

Page 145: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

temporary earth piling 17.30 1 1500 259.50

Subtotal 536.15 40621.40

Fang Zheng county

Low hill area

CK103+350~CK223+000

Roadbed section 207.43 5 1500 15557.25

station yard section 43.87 5 1500 3290.25

bridge and culvert section 130.78 5.5 1500 10789.35

Tunnel section 2.00 5.5 1500 165.00

Waste earth section 74.30 5 1500 5572.50

Construction access road section 23.88 5.5 1500 1970.10

Temporary facility section 27.95 5.5 1500 2305.88

Temporary earth piling 18.62 1 1500 279.30

Subtotal 528.83 39929.63

Ilan County

low hill section CK16+150~CK103+350

roadbed section 151.79 5 1500 11384.25

station yard section 52.16 5 1500 3912.00

bridge and culvert section 96.59 5.5 1500 7968.68

tunnel section 0.80 5.5 1500 66.00

waste earth section 51.47 5 1500 3860.25

construction access road section 19.12 5.5 1500 1577.19

temporary facility section 66.23 5.5 1500 5463.98

temporary earth piling 18.94 1 1500 284.10

Page 146: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

subtotal 457.10 34516.44

City of Jiamusi

low hill section

CK16+150~CK103+350

roadbed section 80.92 5 1500 6069.00

station yard section 86.74 5 1500 6505.50

bridge and culvert section 56.09 5.5 1500 4627.43

tunnel section 0.40 5.5 1500 33.00

waste earth section 14.13 5 1500 1059.75

construction access road section 7.73 5.5 1500 637.93

temporary facility section 20.65 5.5 1500 1703.63

temporary earth piling 8.76 1 1500 131.40

subtotal 275.42 20767.63

total 1970.10 137583.95

Page 147: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

(5) Quantity foreshadowing of soil erosion of landform disturbance

Based on possible soil erosion area of different project areas as well as the prediction time of project construction period and the natural recovery period , quantity of soil erosion of landform disturbance during project construction and the natural recovery period can be predicted , depending on the modulus of soil erosion of landform disturbance. By prediction, soil erosion quantity for 27.86×104t. For details, see Table 5-3-34.

(6) Additional quantity foreshadowing of soil erosion

After the computation analysis, the addition quantity of soil erosion is 14.10×104t. Among this, 4.12×104t is added in the roadbed area , the station yard area 1.30×104t, the bridge culvert 3.09×104t, the tunnel area 0.02×104t, the dregs field area 2.07×104t, the construction detour area 0.75×104t, the construction production and living area 2.29×104t and temporary earth piling area 0.45×104t. The quantity of soil erosion during project construction period is far bigger than the natural recovery period. So , it is critical time to prevent soil erosion. Practical and feasible measures, including project and plant measure as well as the temporary protective measures, should be manipulated . For possible soil erosion of the land sector, reasonable and special measure should be taken so as to control soil erosion effectively.

Page 148: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-52 quantity forecast table of soil erosion of landform disturbance

Admin. district

Commencement and germination mile

Foreshadowing unit

Construction preparing period Project construction periodNature recovery period

Total of soil erosion

quantity (t)

Quantity

of new soil erosion (t)

First year Second year

Foreshadowing area

(hm2)

Foreshadowing period

(a)

Eosion

modulus

(t/km2·a)

Quantity of soil erosion(t)

Foreshadowing area

(hm2)

Foreshadowing period

(a)

Erosion modulus

(t/km2·a)

Quantity of soil erosion (t)

Foreshadowing area

(hm2)

Erosion modulus (t/km2·a)

Quantity of soil erosion (t)

Foreshadowing area

(hm2)

Erosion modulus (t/km2·a)

Quantity of soil erosion(t)

City of Harbin

plain area

commencement~CK16+150

roadbed section 82.75 0.5 1000 413.

75 82.75 2.5 3000 6206.25 41.38 1000 413.

75 41.38 200 82.75

7116.50

6289.00

station yard section

0.84 0.5 1000 4.20 0.84 2.5 3000 63.00 0.00 1000 0.00 0.00 200 0.00 67.2

058.80

bridge and culvert section

54.19 0.5 1000 270.95 54.19 3 3000 4877

.10 27.10 1000 270.95 27.10 200 54.1

95473.19

4877.10

construction access road section

9.23 0.5 1000 46.15 9.23 3 3000 830.

66 9.23 1000 92.30 9.23 200 18.4

6987.56

886.03

temporary facility section

18.24 0.5 1000 91.20 18.24 3 3000 1641

.60 18.24 1000 182.40 18.24 200 36.4

81951.68

1751.04

temporary earth

7.35 1 5000 367.50

367.50

352.80

Page 149: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

piling section

total 165.25 826.25 172.60 1398

6.11 95.94 959.40 95.94 191.

8815963.63

14214.77

Bin County

low hill area

CK16+150~DK28+950

roadbed section 194.94 0.5 2000 1949

.40 194.94 2.5 4000 19494.00 97.47 3000 2924

.10 97.47 1000 974.70

25342.20

10721.70

station yard section

52.99 0.5 2000 529.90 52.99 2.5 4000 5299

.00 26.50 3000 794.85 26.50 1000 264.

956888.70

2914.45

bridge and culvert section

102.25 0.5 2000 1022.50 102.25 3 4000 1227

0.00 51.13 3000 1533.75 51.13 1000 511.

2515337.50

6901.88

tunnel section 0.40 0.5 2000 4.00 0.40 3 4000 48.0

0 0.20 3000 6.00 0.20 1000 2.00 60.00

27.00

waste earth section

77.88 3 4000 9345.49 77.88 3000 2336

.37 77.88 2000 1557.58

13239.45

7398.51

construction access road section

25.43 0.5 2000 254.25 25.43 3 4000 3051

.00 25.43 3000 762.75 25.43 1000 254.

254322.25

2224.69

temporary facility section

64.97 0.5 2000 649.70 64.97 3 5000 9745

.50 64.97 3000 1949.10 64.97 1000 649.

7012994.00

7633.98

temporary earth piling section

17.30 1 8000 1384.00

1384.00

1124.50

subtotal 440.98 4409 536.15 6063 343.56 1030 343.56 4214 7956 3894

Page 150: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

.75 6.99 6.92 .43 8.10 6.70

Fangzheng

County

low hill area

DK160+1000~CK223+000

roadbed section 207.43 0.5 2000 2074

.30 207.43 2.5 4000 20743.00 103.72 3000 3111.

45 103.72 1000 1037.15

26965.90

11408.65

station yard section

43.87 0.5 2000 438.70 43.87 2.5 4000 4387

.00 21.94 3000 658.05 21.94 1000 219.

355703.10

2412.85

bridge and culvert section

130.78 0.5 2000 1307.80 130.78 3 4000 1569

3.60 65.39 3000 1961.70 65.39 1000 653.

9019617.00

8827.65

tunnel section 2.00 0.5 2000 20.0

0 2.00 3 4000 240.00 1.00 3000 30.0

0 1.00 1000 10.00

300.00

135.00

waste earth section

74.30 3 4000 8916.00 74.30 3000 2229

.00 74.30 2000 1486.00

12631.00

7058.50

construction access road section

23.88 0.5 2000 238.80 23.88 3 4000 2865

.60 23.88 3000 716.40 23.88 1000 238.

804059.60

2089.50

temporary facility section

27.95 0.5 2000 279.50 27.95 3 5000 4192

.50 27.95 3000 838.50 27.95 1000 279.

505590.00

3284.13

temporary earth piling section

18.62 1 8000 1489.60

1489.60

1210.30

subtotal 435.91 4359.10 528.83 5852

7.30 318.17 9545.10 318.17 3924

.7076356.20

36426.58

Ilan Count

low

DK160+1000~CK223+000

roadbed section

151.79 0.5 2000 1517.90

151.79 2.5 4000 15179.00

75.90 3000 2276.85

75.90 1000 758.95

19732.70

8348.45

Page 151: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

y

hill area

station yard section

52.16 0.5 2000 521.60 52.16 2.5 4000 5216

.00 26.08 3000 782.40 26.08 1000 260.

806780.80

2868.80

bridge and culvert section

96.59 0.5 2000 965.90 96.59 3 4000 1159

0.80 48.30 3000 1448.85 48.30 1000 482.

9514488.50

6519.83

tunnel section 0.80 0.5 2000 8.00 0.80 3 4000 96.0

0 0.40 3000 12.00 0.40 1000 4.00 120.

0054.00

waste earth section

51.47 3 4000 6176.40 51.47 3000 1544

.10 51.47 2000 1029.40

8749.90

4889.65

construction access road section

19.12 0.5 2000 191.18 19.12 3 4000 2294

.10 19.12 3000 573.53 19.12 1000 191.

183249.98

1672.78

temporary facility section

66.23 0.5 2000 662.30 66.23 3 5000 9934

.50 66.23 3000 1986.90 66.23 1000 662.

3013246.00

7782.03

temporary earth piling section

18.94 1 8000 1515.20

1515.20

1231.10

subtotal 386.69 3866.88 457.10 5200

2.00 287.49 8624.63 287.49 3389

.5867883.08

33366.63

City of

Low hill

DK160+1000~CK223+000

roadbed section

80.92 0.5

2000

809.20 80.92 2.5

4000

8092.00 40.46 3000

1213.80

40.46 1000

404.60 10519.60

4450.60

Page 152: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Jiamusi

section

station yard section

86.74 0.5

2000 867.40 86.74 2.

54000 8674.00 43.37 300

01301.10 43.37 100

0 433.70 11276.20 4770.70

bridge and culvert section

56.09 0.5

2000 560.90 56.09 3 400

0 6730.80 28.05 3000 841.35 28.05 100

0 280.45 8413.50 3786.08

tunnel section 0.40 0.

52000 4.00 0.40 3 400

0 48.00 0.20 3000 6.00 0.20 100

0 2.00 60.00 27.00

waste earth section

14.13 3 4000 1695.60 14.13 300

0 423.90 14.13 2000 282.60 2402.10 1342.35

construction access road section

7.73 0.5

2000 77.33 7.73 3 400

0 927.90 7.73 3000 231.98 7.73 100

0 77.33 1314.53 676.59

temporary facility section

20.65 0.5

2000 206.50 20.65 3 500

0 3097.50 20.65 3000 619.50 20.65 100

0 206.50 4130.00 2426.38

temporary earth piling section

8.76 1 8000 700.80 700.80 569.40

subtotal 252.53 2525.33 275.42 29966.6

0 154.59 4637.63 154.59 1687.1

838816.73

18049.09

total 1681.35

15987.30

1970.10

215119.00

1199.75

34073.67

1199.75

13407.76

278587.72

141003.77

Page 153: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

(7) Prediction of destruction to the conservation of water and soil facility

According to the regulations of the charge and use of soil erosion prevention in Heilongjiang Province, forests and grassed destroyed by productive construction is included in the destruction of conservation of water and soil facility area.

Based on the above stipulation, the damage of this project to the facilities of conservation of water and soil is mainly the biological ones, including the forest land, the lawn, the orchard, the reed, the weed place. The total area is 697.13hm2, containing permanent expropriation Land 427.44hm2, temporary land 269.69hm2.

Based on the above stipulation, this project damage to facility of conservation of water and soil area is 697.13hm2, for details sees Table 5-3-35.

Table 6-53 damage of facility of the soil conservation caused by construction

DistrictPermanent expropriated land Temporary occupied land

TotalOrchard Forest land Subtotal Forest land Waste land Subtotal

Harbin municipally-governed

District2.79 1.78 4.57 2.34 3.57 5.91 10.48

Bin county 0 128.16 128.16 8.99 23.59 32.58 160.74

Fangzheng county 0 157.72 157.72 31.22 79.55 110.77 268.49

Ilan county 0 113.18 113.18 31.65 67.19 98.84 212.02

Jiamusi municipally-governed

District4.80 19.00 23.8 9.27 12.32 21.59 45.39

sum 7.59 419.85 427.44 83.47 186.22 269.69 697.13

Preventive measures for soil erosion The protective measures include measures taken by the project, plant measure and temporary protective measures. The result indicates problems arise during the project construction period and the natural recovery period to a certain degree - disturbing the surface, destroying the original landform structure, and the acceleration of soil encroachment question. To prevent artificial soil erosion during construction and the process, protective measures of the intake field and dreg field should be supported mainly by project measure, with plant measure and reclamation measure auxiliary ,depending on the intensity and the corroded quantity ,with the combination of environment characteristic and the project characteristic. Plant measure and the reclamation measures for the side slope and the both sides of the roadbed:

(1) To the side slope, according to its height, the slope, the soil condition and geological condition of passing areas, plant measures or project measures or the combination of the two measures are adopted. To strengthens its anti-washout ability. Guarantee its stability and prevent soil erosion.

(2) To river crossing bridge’s water immersion sector, the entire slope face of the head should be build by laying slabstones one layer after another. During the construction process, few abandoned earthwork produced during excavation of pier should be immediately used in the filling of bridge head roadbed , if not, temporary straw bags should be used to protect; For the bridge foundation with hole drilling poles, the drill hole construction process will produce the massive muds and dregs will be produced. So it is requested that the mud pit and the sedimentation pond should be built before the hole-drilling construction. And muds should be reused after recycling and sedimentation.

(3) Drainage should be established to discharge the precipitation from the slope face of the roadbed, avoiding the washout to the surrounding environment.

(4) The excavation of earth should be carried out according to the need, not leaving loose earth surface. After the construction, protective measures second ploughing or forestation should be taken to deal with

Page 154: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

the earth taking and abandoning field. And complete the drainage system.

(5) To construction detour, and big temporary base .when in use, the management and maintenance should be strengthened. After the construction, it should be restores to its original function as far as possible.

Benefit analysis After the completion of conservation of water and soil project, a comprehensive protective system will be established with project control measures primarily, the mechanical control measure, the plant measure, the temporary measure and the plant protection unify conservation of water and soil ecological environment synthesis protection system. The system can prevent soil erosion of the roadbed side slope effectively, and can control soil erosion of the dregs field basically, and can reduce soil erosion of occupied land area of construction detour, construction area on a large scale, and will limit the newly-produced soil erosion in the smallest scope. It will form a positive cycle of ecological environment. It will play a significant in the prevention and the conservation of soil and water, the security of railroad, the protection and the improvement railroad.

6.1.11 landscape vision impact assessment Along the route area many for farmland, lawn, village landscape, in addition has the part of cities landscape. Locate the region landscape environment characteristic according to the region of no relief project characteristic as well as the project, this project's following road section will create the varying degree to the local nature and the humanities landscape the impact.

Impact analysis of embankment sectionThe landform of the project passes through is in plain area and many are filling section. But the filling is not so deep or high. Besides, the construction is designed to afforest all the side slopes of the roadbed, which makes people see a green porch in harmony with the peripheral surroundings but not a high pessimistic obstacle.

Impact analysis of the station yard to landscape vision8 intermediate stations are newly established for this project, respectively farming land and construction land. The landscape type is common and single. However, in the construction designing, forestation and beautification are strengthened to approach to the multiplicity and coordination of the landscape. Therefore, after the completion of the project, the exchanging overpasses, peripheral environment and visual circumstance will all be improved.

Impact analysis of the bridge to landscape vision This project altogether involves in 144 large and medium-sized bridges. The building of the bridge will produce cutting impact toward the landscape environment, forming the visual impact. Because the bridge lies between small towns and the countryside estate, the landscape is ordinary. Therefore, if only paying great attention to the landscape designing, the bridge will not have the significant impact to the peripheral landscape vision. The cross-river bridge is strengthened in the beautification designing, trying to achieve the multiplicity and the coordination of the landscape, which will greatly improve the landscape vision.

Impact analysis of earth intake field and waste (dregs) field on the landscape This project establishes 12 earth-intake field and 45 waste (dregs) field along the route. During the railroad construction, these fields have serious impact on the landscape, and leave scars in the landscape, abrupt in vision; after the construction, because of the reclamation and the restoration of plantation, the vision impact will be eliminated.

Generally speaking, because the local landscape is common along the route, there is not the distribution of sensitive point of landscape, and the sensitivity of the landscape is not unusual, either. The roadbed and bridge section forms the visual impact mainly because the construction itself forms the cutting impact on the landscape environment it passes through. The earth in-take and waste (dregs) field will create landscape scars and adverse towering visual impact, but which can be coordinated with the peripheral environment through the landscape afforest, outside color and appearance designing to be in integrity with the general landscape.

Page 155: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

6.2 Investment estimate and benefit analysis of ecological

protection measure

6.2.1 Investment estimate of ecological protection There are many protection constructions in the railroad project, which are not only for the safety and stability of the project, but also for the protection of ecological environment and defending of soil erosion. The two aspects are quite difficult to separate from each other clearly. Therefore, the constructions listed in this chapter are that of protection against ecological environment, defending against soil erosion, such as protection of side slope of the embankment, the forestation, protection of earth in-take and waste (dregs) field and so on.

The project quantity and investment estimate of ecological protection measures sees Table 5-4-1. The ecology protection invests the total 534,683,500 Yuan.

Page 156: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-54 Master list of project quantity of ecological protection measures

Unit: 10,000 Yuan

Item Unit

Harbin

municipally- governed district

Bin County Fangzheng County Ilan County city of Jiamusi sum

quantity

investment quantity investm

ent quantity investment quantity investm

ent quantity investment

quantity

investment

Project measures

Roadbed section

Slope protection of embankment

M10

brick-laying

slab stones

m3 24662.6 592.89 69055.2

8 1660.09 76454.06 1837.96 54257.7

2 1304.36 22196.34 533.6 246626 5928.89

Earthwork

grillm3 502892

.4 1021.37 1408098.7 2859.85 155896

6.4 3166.26 1106363.3 2247.02 452603.

16 919.24 5028924

10213.74

Slope protection of moat

C25

concretem3 36677 1038.95 201033 5694.66 212444 6017.9 102234 2895.98 6777 191.97 559165 15839.4

7

brick-laying stone draining ditch

Brick-laying

stonem3 18272 517.59 48851 1383.8 66141 1873.58 39602 1121.81 12104 342.87 184970 5239.65

Station section

Draining ditch

Brick-laying

slabs tones

m3 2800 79.32 14820 419.81 16150 457.48 8550 242.2 10980 311.03 53300 1509.83

Waste Dreg- Brick- m3 0 0 2522.03 57.5 10983.6 250.43 6003.89 136.89 1926.04 43.91 21435.6 488.73

Page 157: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

earth (dregs)

field resisting wall

laying

stones6 3

Foundation

excavation

m3 0 0 1316.4 0.81 3758.29 2.31 3643.58 2.24 1091.59 0.67 9809.85 6.02

Flood releasing ditch and energy releasing

measures

Brick-laying

stonem3 0 0 5829.55 135.18 14175.2

2 328.69 8059.75 186.89 4165.26 96.58 32229.77 747.34

Foundation

excavation

m3 0 0 6278.79 5.5 13375.94 11.72 8645.57 7.57 3102.48 2.72 31402.7

8 27.51

Sand cushion m3 0 0 10743.3

1 88.88 28209.92 233.38 16320.5

2 135.02 7506.8 62.1 62780.56 519.38

Platform

draining

ditch

Brick-laying

stonem3 0 0 1257.52 29.16 2065.53 47.9 1192.2 27.64 408.2 9.47 4923.45 114.17

Foundation

excavation

m3 0 0 2531.38 2.22 4157.88 3.64 2399.89 2.1 821.7 0.72 9910.85 8.68

Sand cushion m3 0 0 555.27 4.59 912.05 7.55 526.43 4.36 180.24 1.49 2173.99 17.99

Ground leveling

Ground

levelinghm2 0 0 77.88 84.75 74.29 80.85 51.47 56.01 14.13 15.38 217.77 236.98

Reclaiming

hm2 0 0 65.7 32.43 5.48 2.7 0 0 0 0 71.18 35.13

Page 158: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

ground

leveling

Construction

access

road

section

Water draining

ditch

Cubic meter excavation

m3 0 0 24784.5 21.71 23064 20.2 18390.75 16.11 5975.25 5.23 72214.5 63.26

M7.5

brick-laying

stone

m3 0 0 12152.4 281.79 11308.8 262.23 9017.4 209.1 2929.8 67.94 35408.4 821.05

sand cushion m3 0 0 5436.6 44.98 5059.2 41.85 4034.1 33.37 1310.7 10.84 15840.6 131.05

Field leveling hm2 9.23 10.04 25.43 27.67 23.88 25.99 19.12 20.81 7.73 8.41 85.39 92.92

Agricultural reclaiming hm2 5.91 2.92 16.28 8.04 15.28 7.54 12.24 6.04 4.95 2.44 54.66 26.98

Production and living

area in construction

field leveling hm2 18.24 19.85 64.97 70.7 61.53 66.96 66.23 72.07 20.65 22.47 231.62 252.05

reclaiming

ground leveling and farmyard manure

using

hm2 15.66 7.73 53.72 26.51 28.18 13.91 25.74 12.7 15.97 7.88 139.27 68.74

Planting

measures

Embankment

area

both-side greening

shrub Item 4229575 465.25 1184281

0 1302.71 13111683 1442.29 930506

5 1023.56 3806617.5 418.73 422957

50 4652.53

arbor item 8234 28.74 23055.2 80.49 25525.4 89.11 18114.8 63.24 7410.6 25.87 82340 287.45

Station

arealandscaping hm2 0.04 2.1 2.65 132.48 2.19 109.68 2.61 130.4 4.34 216.85 11.83 591.5

Bridge bridge greening ( grass

m2 3.84 1.19 19.33 6.01 24.73 7.69 10.84 3.37 5.3 1.65 64.04 19.91

Page 159: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

and culvert

area

sowing)ivy item 8960 1.46 22400 3.65 26880 4.38 28000 4.56 5600 0.91 91840 14.97

waste earth(dregs)

field

arbor 1000items 0 0 24.35 28.1 137.63 158.82 102.93 118.78 28.26 32.61 293.17 338.32

1000items 0 0 73.06 68.82 412.88 388.93 308.8 290.89 84.78 79.86 879.51 828.5

mixed grass sowing

area(hm2) 0 0 8.52 0.35 48.17 1.97 36.03 1.47 9.89 0.4 102.61 4.2

quantity ( kg) 0 0 511.42 2.3 2890.15 13.01 2161.57 9.73 593.46 2.67 6156.6 27.7

young wood nurture hm2 0 0 8.52 1.15 48.17 6.5 36.03 4.86 9.89 1.33 102.61 13.84

construction

access road

section

grass sowing hm2 3.32 1.04 9.15 2.87 8.6 2.7 6.88 2.16 2.78 0.87 30.73 9.64

Grass sowing slope protection m2 0 0 191880 149.86 178560 139.46 142380 111.2 46260 36.13 559080 436.64

Page 160: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 6-55 master list of project quantity of ecological protection measures Unit: 10,000 Yuan

item unit

Harbin

municipally- governed district

Bin County Fangzheng County Ilan County City of Jiamusi sum

quantity

investment

quantity

investment

quantity

investment

quantity

investment

quantity

investment quantity investme

nt

planting

measures

production and living

area in construction

shrub1000 item

15.48 14.58 67.5 63.59 200.1 188.49 242.94 228.85 28.08 26.45 554.1 521.96

grass sowing hm2 2.58 0.81 11.25 3.53 33.35 10.47 40.49 12.71 4.68 1.47 92.35 28.98

temporary

measures

embankment

section

waterproof ridge

cubic earth m3 2076.2

2 1.82 3401.52 2.98 4368.0

5 3.83 3574.56 3.13 697.14 0.61 14117.4

8 12.37

torrent groove

earth knitting bag

m3 3788.73 47.35 6207.1

5 77.58 7970.89 99.63 6522.9

1 81.53 1272.15 15.9 25761.8

3 321.99

temporary water draining ditch

cubic earth m3 1377.7

2 1.21 2257.15 1.98 2898.5 2.54 2371.9

7 2.08 462.6 0.41 9367.94 8.21

sand-basin cubic earth m3 344.43 0.3 564.29 0.49 724.63 0.63 592.99 0.52 115.65 0.1 2341.98 2.05

iron wire guardrail m2 8800 44 37000 185 42120 210.6 14800 74 20020 100.1 122740 613.7

knitting cloth coverage m2 17820 1.78 9100 0.91 13505

1 13.51 115236 11.52 18457

0 18.46 461777 46.18

temporarily -piled earth protection

earth knitting bag

m3 2866.46

35.83 8322.09

104.02 8588.12

107.34 6092.62

76.15 2405.57

30.07 28274.86

353.41

Page 161: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

earth-retaining wall

dense network coverage

m2 19507.5 5.85 56635.

5 16.99 58446 17.53 41463 12.44 16371 4.91 192423 57.73

station

area

earth knitting bag

earth-retaining wallm3 225.14 2.81 434 5.42 690.31 8.63 476.54 5.96 292.71 3.66 2118.69 26.48

dense network coverage m2 8800 2.64 32700 9.81 20675 6.2 39425 11.83 14875 4.46 116475 34.94

tunnel

section

guardrail bar ( iron wire) m2 0 0 260 1.3 1300 6.5 520 2.6 260 1.3 2340 11.7

stone-piling dreg-resisting wall m3 0 0 755.6 1.94 1240.0

5 3.18 1543.89 3.96 1544.5

7 3.96 5084.12 13.05

bridge and culvert section

earth knitting bag

earth-retaining wallm3 622.73 7.78 762.07 9.53 800.05 10 846.15 10.58 612.59 7.66 3643.59 45.54

dense network coverage m2 67325 20.2 10082

5 30.25 111125 33.34 124300 37.29 65150 19.55 468725 140.62

mud sump quantity

Item 1 0.03 2 0.07 3 0.1 5 0.17 2 0.07 13 0.45

sedimentation basin

quantity item 2 0.05 4 0.11 6 0.16 10 0.27 4 0.11 26 0.71

production and living

area in constructio

topsoil stripping hm2 18.24 17.15 64.97 61.08 61.53 57.85 66.23 62.27 20.65 19.42 231.62 217.77

earth knitting bag m3 346.92 4.34 647.99 8.1 567.28 7.09 583.87 7.3 358.9 4.49 2504.96 31.31

grass seeds sowing hm2 2.09 0.65 7.29 2.27 5.59 1.74 5.92 1.84 2.24 0.7 23.12 7.19

Page 162: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

ntopsoil backfilling hm2 8.36 54.23 29.16 189.21 22.35 145.01 23.67 153.62 8.95 58.04 92.48 600.11

waste earth (dregs) field

topsoil stripping hm2 0 0 77.88 73.22 74.29 69.85 51.47 48.39 14.13 13.29 217.77 204.75

earth knitting bag m3 0 0 1684.76 21.06 2517.2

3 31.46 1439.19 17.99 492.76 6.16 6133.94 76.67

grass seeds sowing hm2 0 0 7.48 2.33 5.71 1.77 3.86 1.2 1.06 0.33 18.11 5.63

topsoil backfilling hm2 0 0 29.93 194.24 22.84 148.18 15.44 100.19 4.24 27.51 72.45 470.1

Page 163: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

6.2.2 Benefit analysis of ecological protection The construction plane will be in control after the implementation of ecological protection measures. By the end of the construction and the afforestation, the vegetation will be restored for the exposed surface caused by the construction. The soil erosion will be effectively controlled and quality and of the ecological environment will also be improved.

The degree of the soil erosion is weakened for the roadside side slope because there are some effective drainage systems such as mortar-laying slabstone on the roadbed side slope, plant coverage protection, drain gutters, side-gutters, etc. The systems are useful to the stability of side slope to guarantee the safety of railway transportation.

There are altogether 375510 arbors and 43729.36 thousand bushes newly planted, 237.52hm2 for grassing sowing and gardening afforestation. All these play an active role in the soil conservation and ecological environment improving along the route.

6.3 Summary

1. The land utilization patterns are primarily farmland for the railroad construction from Harbin to Jiamusi. Vegetation coverage is relatively ideal in Fangzheng and Ilan County. The soil erosion is mild. Along the route, the ecological environment is comparatively stable and the bearing capacity is strong.

2. According to National vegetation regionalization, the entire line of the construction belongs to the temperate zone prairie region -eastern prairie sub-region - temperate zone north prairie region the temperate zone needle broad-leaf mixed forest region-temperate zone north needle broad-leaf mixed forest region. Along the route the vegetations are mainly wildwood, planted forest, brush, meadow prairie, bog and farmland. The common plants are the populus davidiana, the Korean pine, two-color lespedeza and so on.

3. In the animal geography regionalization, the route belongs to Song-Liao Plain area, Changbai Mountain and Xiao Xing’an range mountain area, because this area sees frequent human activities, along the route mostly farmland, villages. In addition, because of the impact from The Tong-San highway, G211 and railway, the animal resoureces are more deficient along the route and they are primarily common kinds.

There are 28 protection animals along the route. And among them, birds are 26 kinds (national Level-II protection birds 20 kinds, Heilongjiang provincial-level protection birds 6 kinds); there are 2 kinds of provincial-level protection animals for crawling class.

4. The permanent occupying land area in this project includes roadbed occupying land, station yard land, the arch of bridge, access-exit tunnel land, altogether 1416.27hm2. The additional land-levying type involves in farmland 903.20 hm2, 63.77%; forest land 419.85, 29.65%; construction land 42.63 hm2, 3.01%; orchard 7.59 hm2, 0.54%; pond 8.24 hm2, 0.58%.

The permanent occupying land impacts slightly on the local land utilization pattern along the route. The design fully considers reducing of occupying land, and the project is in striation distribution. Therefore it may reduce the impact to the smallest degree through economic compensation measures making and restoring field and so on.

5. This project occupies a land area of 534.78 hm2 temporarily, primarily arid land. The temporary project takes into account the combination of temporary and forever impact, trying to reduce land-occupying through using permanent levying-land and urban land within the scope of existed field or station section. The established temporary store depots completely use the old stations, without new land-occupying. Using old stations without increasing occupying, this line lays 2 rail bases, located separately at Xinxiangfang Station and Jiamusi Station of Harbin.

6. The construction will permanently occupy forest land for 419.85hm hm2. The next design will

Page 164: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

further make clear about the quantity and kinds of felling tree. In the design and construction process, if national or local protective trees found, they should be transplanted. And so are done to those small trees suitable for transplanting and those trees of great value. To those of little value and unsuitable for transplanting, under the local forestry department’s instruction, different replanting or currency compensation is carried on, in line with the isometric compensation principle of national and local compensation standard.

This project takes many measures such as plantation measures on roadbed side slope plant measure, afforestation of arbor and bush planting, forest belt on the sandstorm roadbed, afforestation on the temporary location, earth in-take area, and waste (dregs) fields and so on. The entire line altogether newly plants tree 375510, bush 43729.36 thousand, grass sowing and gardening afforestation 237.52hm2, which may play an active role improving the ecological environment along the route.

7. The total length of the main-line bridge is 172862.60 double linear meter /144, accounting for 51.28% of the line span. Among it, double-line extra-longbridges are 157506.23 double extension meter/88; double-line large bridges are 15084.71 double extension meter/53; double-line moderate bridges are 206.46 double extension meter/2; steel-framed moderate bridges are 65.2/double extension meter one. The number of newly-built culverts is 294 and after deducting the length of the bridges and tunnels, the culvert is 1.90 for each kilometer.

When surmounting the high-grade road, in the design the bridge directly passes through. The bridge pier is not established amidst the road and on the roadbed side slope. Simultaneously it should be considered that the bridge construction may impact the normal use of the road. The measures above can satisfy the need of activities and passing for people and animals.

Some requirements are considered in the construction designing of the bridges and culverts, such as flood expelling, irrigation, the surface runoff, and people’s outgoing, animal channels. Bridges and culverts are all designed with a 1/100 water level ( Ilan-Mudanjiang bridge using 1/300 for examination and calculation). And the draining ditch will be designed on both sides of the railroad to the impact to the least degree toward the rivers, flood expelling, irrigation, surface flow and animal channels.

8. The Harbin-Jiamusi rail line penetration plan includes 9 tunnels, all in double-line, total length 14.093km, taking up 4.18% of the entire new line. It is suggested that the tunnels shorter than 500m use single mouth for construction and dregs outgoing to reduce the destruction toward surroundings.

The impact analysis of the tunneling to crown vegetation indicates the volume of the water upwelling is small and leaking is mainly the micro bedrock crevice water; the water for the tunnel summit vegetation to grow is mostly from the natural precipitation and the construction nearly has no impact to the vegetation. There are only 2 inhabited areas within the scope of 1000m at the entrance and exit. The production and living both use groundwater and the section of the body tunnel has little connection with the resident’s water conservation. The construction has the slight impact to the local people’s drinking water.

9. This design includes 487 individual roadbed points, with the total length labor 150.142km, taking up 44.54% of the newly built total length. The constructions are mainly moat slope protection, deep cut, sticky embankment, soft ground embankment and so on.

10. The additional soil-erosion quantity is 14.10×104t, which is more than that in natural recovery period. This is the important section for soil erosion protection. To effectively control soil erosion, some points must be paid attention to, such as feasible project, plant measure as well as temporary protective measures, having a reasonable government toward the possible section for soil erosion.

In the whole line, the total quantity of earth and stone is 4111.78×104m3, among it is filling 1437.24×104 m3; the earth or stone excavated 2674.54×104 m3. The earth excavated should be used to fill as far as possible. In this construction the used earth is 951.44×104 m3. And the total abandoned earth is 1723.10×104 m3, in which 118.53×104 m3 topsoil is reused in afforestation with the earth, 1604.57×104 m3 taken to the dregs field as permanent waste (dregs).

Page 165: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

This design initially chooses 12 earth in-take areas, all old stone pits. Altogether 45 dregs fields are chosen, the area 217.78hm2 , many enough for the dregs along the route. And in this construction, some measures are taken concerning corresponding project protection and afforestation. These measures are all about the following aspects: mixing of earth and stone, waste (dregs) field, roadbed side slope, foundation waste of arch and bridge. The implementation of these measures will reduce the soil erosion and the impact of earth-stone construction on the ecological environment.

11. The monitoring and inspection of construction unit, supervisor unit and environment protection personnel will enhance the realization of every environment protection measure.

In brief, the impact of railroad on ecological environment is mainly shown in the destruction to the vegetation and land along the route. The destruction is from earth taking and abandoning, roadbed excavation and backfilling, etc. Through the realization of every relieving and compensating measure, the construction will not create serious harm toward the local ecological environment. After the construction, the ecological environment will gradually restore and improve along the route with the carrying out of the protection and greening measures.

Page 166: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

7 Environmental Impact Assessment of Noise

7.1 Investigation and assessment on current status of acoustic

environment

Noise level monitoring along the alignment was conducted at noise-sensitive sites during EIA preparation. Details of the monitoring results and prediction are shown in Annex 4.

7.2 Predication and evaluation on noise impact

7.2.1 Assessment of prediction result

Noise level prediction was conducted based on monitoring results and mathematical models. The details of the prediction results are shown in Annex 5.

Due to the construction of the project, the quantity of freight transportation pairs within Harbin and Jiamusi Hubs would reduce. Increasing CWR would better the noise and vibration impact within the hubs.

1. Harbin Hub

(1)30m to the Outer Rail Central Line

The near term Leq at 30m to the old outer rail central line were 57.7~65.1dBA、54.3~66.2dBA in

the day and night, -4.4~2.5dBA、-6.8~3.9dBA higher than the current status, thus are able to meet

the standards of Day 70dBA and Night 70dBA set in the GB12525-90《Railway Boundry Noise

Limits and Measuring Methods》.

(2)residential area

Grade IV area - The near term value of each survey point in the Grade IV area were 56.0~59.5dBA and 52.5~56.2dBA in the day and night, -4.3~-2.5dBA, -6.3~-3.2dBA higher

than the current status, up to the standards of Day 70dBA set in the GB12525-90《Railway

Boundry Noise Limits and Measuring Methods》. 7 points surpassed 0.2~1.2dBA of the standard of Night 55dBA for the Grade IV area set in GB3096-2008.

Grade II area - The near term value of each survey point in the Grade II area were 53.7~57.6dBA and 49.1~54.5dBA in the day and night, -4.3~-2.5dBA, -6.4~-3.1dBA higher

than the current status. 33 points surpassed 0.1~6.1dBA of the standard of Day 60dBA for

the Area II set in GB3096-2008; 154 points surpassed 0.3~4.5dBA of the standard of Night 50dBA for the Area II set in GB3096-2008.

Grade III area - The near term value of each survey point in the Grade III area along the both

sides of the old railways were 53.5~61.4dBA and 49.3~62.1dBA in the day and night, -3~

Page 167: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

1.6dBA、-4.0~3.6dBA higher than the current status, up to the standards of Day 65dBA set

for the Grade III area in the GB3096-2008. 3 points surpassed 0.2~7.1dBA of the standard of Night 55dBA for the Area III set in GB3096-2008.

(3)Special Sensitive Points at Schools and Hospitals

Day54.8~59.4dBA,-4.4~-2.7dBA higher than the current status, met the according criteria;

Night50.4~56.1dBA, -7.2~-3.2dBA higher than the current status. 8 Points surpassed 1.4~3.4dBA of the criteria.

The specific estimation statistical results at Harbin are as in the table 6-2-5 below.

Table 7-56 Estimated Statistic Results

Measuring Points

Monitoring Point

Numbers

Estimated

Value(dB)Overstandard

Value(dB)Overstandard Measuring

Point Numbers

Difference to the Current

Value(dB)

Day Night Day Night Day Nigh

t Day Night

Within 30m to external rail central

line 内 27 56.6~67.554.1~66.5

/ / / / -4.5~2.4 -7~4

30m to external rail central line

31 57.7~65.154.3~66.2

0~0 0~0 0 0 -4.4~2.5 -6.8~3.9

Class IV 15 56~59.552.5~56.2

0~0 0.2~1.2 0 7 -4.3~-2.5

-6.3~-3.2

Area Class 1 42 53.7~57.649.1~54.5

0~0 0.3~4.5 0 33 -4.3~-2.5

-6.4~-3.1

Class III 10 53.5~61.449.3~62.1

0~0 0.2~7.1 0 3 -3~1.6 -4~3.6

School 20 54.8~59.450.4~56.1

0~0 1.4~3.4 0 8 -4.4~-2.7

-7.2~-3.2

Page 168: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

2. Jiamusi Hub

(1)30m to the Outer Rail Central Line

The near term value at 30m to the old outer rail central line were 59~69.4dBA, 55.8~69.5dBA in the

day and night, -2.5~5.9dBA, -2.4~6.7dBA higher than the current status, up to the standards of Day

70dBA and Night 70dBA set in the GB12525-90《Railway Boundry Noise Limits and Measuring

Methods》.

(2)Residential areas

Grade IV area - The near term value of each survey point in the Grade IV area were 55~68.2dBA and 52.9~68.4dBA in the day and night, -3.5~2.2dBA, -6.8~2.6dBA higher than

the current status, up to the standards of Day 70dBA set in the GB12525-90《Railway

Boundry Noise Limits and Measuring Methods》. 23 points surpassed 0.1~13.4dBA of the standard of Night 55dBA for the Grade IV area set in GB3096-2008.

Grade I area - The near term value of each survey point in the Grade I area were 54.6~59.5dBA and 50.8~58.9dBA in the day and night, -2.4~1.3dBA, -4.4~2 .0dBA, -2.4~1.3dBA, -4.4~2 .0dBA higher than the current status. 11 points surpassed 0.3~4.5dBA of

the standard of Day 55dBA for the Area I set in GB3096-2008; 12 points surpassed 5.8~13.9dBA of the standard of Night 45dBA for the Area I set in GB3096-2008.

The near term value of each survey point in the Grade III area were 56.1~62.8dBA and 53.0

~62.7d dBA in the day and night, -2.4~3.5dBA, -1.8~4.0dBA higher than the current status, up to the standards of Day 65dBA set for the Grade III area in the GB3096-2008. 11

points surpassed 0.3~7.7dBA of the standard of Night 55dBA for the Area III set in GB3096-2008.

(3)Special Sensitive Points at Schools and Hospitals

Day55.8~60.0dBA,-2.2~-0.1dBA higher than the current status, met the according criteria;

Night53.1~59.4dBA, -1.4~0.6dBA higher than the current status. 2 Points surpassed 3.1~9.4dBA of the criteria.

The specific estimation statistical results at Harbin are as in the table 6-2-6 below.

Table 7-57 Estimated Statistic Results

Measuring Points

Monitoring Point

Numbers

Estimated

Value(dB)Overstandard

Value(dB)Overstandard Measuring

Point Numbers

Difference to the Current

Value(dB)Day Night Day Night Day Night Day Night

Page 169: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Within 30m to external rail central

line 内 17 58.2~

73.554.7~73.7

/ / / /-1.3~13.4

-1.9~16.2

30m to external rail central line

27 59~69.455.8~69.5

0~0 0~0 0 0 -2.5~5.9 -2.4~6.7

Class IV 26 55~68.252.9~68.4

0~0 0.1~13.4 0 23 -3.5~2.2 -6.8~2.6

Area Class 1 12 54.6~

59.550.8~58.9

0.3~4.5

5.8~13.9 11 12 -2.4~1.3 -4.4~2

Class III 13 56.1~

62.853~62.7 0~0 0.3~7.7 0 11 -2.4~3.5 -1.8~4

School 2 55.8~6053.1~59.4

0~0 3.1~9.4 0 2 -2.2~-0.1 -1.4~0.6

3. Inter-zone Section

(1)30m to the Outer Rail Central Line

The near term value at 30m to the old outer rail central line were 62.3~69.2dBA, 57.1~63.7dBA in

the day and night, 6.4~18.1dBA, 8.2~19.8dBA higher than the current status, up to the standards of

Day 70dBA and Night 70dBA set in the GB12525-90《Railway Boundary Noise Limits and

Measuring Methods》.

(2)Residential Houses

Grade IV area - The near term value of each survey point in the Grade IV area were 59.6~67.8dBA and 56.3~62.3dBA in the day and night, 5.3~16.3dBA, 7.3~15.2dBA higher than

the current status, up to the standards of Day 70dBA set in the GB12525-90《Railway

Boundry Noise Limits and Measuring Methods》. 9 points surpassed 1.3~7.3dBA of the standard of Night 55dBA for the Grade IV area set in GB3096-2008.

Grade I area - The near term value of each survey point in the Grade I area were 57.1~61.2dBA and 53.1~57.9dBA in the day and night, 4.0~6.3dBA, 4.7~10.7dBA, -2.4~1.3dBA, -4.4~2 .0dBA higher than the current status. 3 points surpassed 2.1~6.2dBA of the

Page 170: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

standard of Day 55dBA for the Area I set in GB3096-2008; 3 points surpassed 8.1~12.9dBA of the standard of Night 45dBA for the Area I set in GB3096-2008.

Grade II area - The near term value of each survey point in the Grade II area were 56.5~66.1dBA and 51.0~60.6dBA in the day and night, 1.6~15dBA, 1.8~17.1dBA. 89 points

surpassed 0.1~6.1dBA of the standard of Day 55dBA for the Area II set in GB3096-2008;

121 points surpassed 1.0~10.6dBA of the standard of Night 50dBA for the Area II set in GB3096-2008.

Grade III area - The near term value of each survey point in the Grade III area were 58.7~65.5dBA and 54.1~60.2dBA in the day and night, 3.4~14.1dBA、4.4~15.4dBA higher than the current status. 1 points surpassed 0.5dBA of the standard of Day 65dBA for the Area

III set in GB3096-2008; 4 points surpassed 0.4~5.2BA of the standard of Night 55dBA for the Area III set in GB3096-2008.

(3) Special Sensitive Points at Schools and Hospitals

Day57.1~67.5dBA,5.1~13.7dBA higher than the current status, met the according criteria;

Night53.1~59.4dBA, 5.1~13dBA higher than the current status. 1 points surpassed 0.5dBA of the

standard of Day 65dBA for the Area III set in GB3096-2008; 5 points surpassed 1.0~7.5dBA in the

day; 7 points surpassed 1.3~12.1dBA of the standard in the evening.

The specific estimation statistical results at inter-zone sections are as in the table 6-2-6 below.

The specific estimation statistical results at Harbin is as in the table 6-2-7 below.

Table 7-58 Estimated Statistic Results

Measuring Points

Monitoring Point

Numbers

Estimated

Value(dB)Overstandard

Value(dB)Overstandard Measuring

Point Numbers

Difference to the Current

Value(dB)Day Night Day Night Day Night Day Night

Within 30m to external rail central

line

20 61.3~7058.0~

64.7/ / / / 6.4~19.1

10.6~20.3

30m to external rail central line

63 62.3~69.2

57.1~63.7

0~0 0~0 0 0 6.4~18.18.2~19.8

Class IV 9 59.6~ 56.3~ 0~0 1.3~7.3 0 9 5.3~16.3 7.3~

Page 171: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

67.8 62.3 15.2

Area Class I 3 57.1~61.2

53.1~57.9

2.1~6.28.1~12.9

3 3 4~6.34.7~10.7

Area Class II

121 56.5~66.1

51~60.6 0.1~6.1 1~10.6 89 121 1.6~151.8~17.1

Area Class III

6 58.7~65.5

54.1~60.2

0.5~0.5 0.4~5.2 1 4 3.4~14.14.4~15.4

School 7 57.1~67.5

51.3~62.1

1~7.51.3~12.1

5 7 5.1~13.7 5.1~13

4. Noise Estimation Value Changes in the Long Run

The project operation train types and opening modes will have no change while the train pair numbers will have an increase in the long run. The noise estimation will be higher than the current value: noise equivalent grade will add 0.1~4.7dBA in the day and 0.1~1.8dBA in the evening.

5. Noise Sensitive Points in the Zone between the Old and New Lines

3 points of this sort were designed in this project. They were N38 Water Source Community Bungalow at Harbin Hub; N113 Glass Factory Family Buildingt N137 Model Village at Jiamusi Hub. 3 functional zones were all over standard. The assessment suggested the resettlement within 30m of the project and adopting the sound barriers and sound isolation windows at N38 and N113. Also, the assessment suggested the sound isolation window for the inhabitants at N137 lived in dispersion ,

7.2.2 Equivalent Sound Grade Estimation Results of Typical Sections

In the light of the actual situations, the sound grade estimation results of the pure railway noise were shown at the different sections and subgrade types and heights in the table 7-4.

Table 7-59 Shield-free Noise Equivalent Sound Level along the Route

Unit: dBA

Section Route Type

Rail Top Height(m

)

Noise Equivalent Sound Level (dBA)

30m 60m 120m 200m

Day Night Day Night Day Night Day Night

Harbin -Taiping Bridge

Subgrade

0 58.7 56.9 55.0 53.2 51.6 50.1 48.9 48.0

Page 172: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Section Route Type

Rail Top Height(m

)

Noise Equivalent Sound Level (dBA)

30m 60m 120m 200m

Day Night Day Night Day Night Day Night

Subgrade

2 60.0 58.2 55.5 53.7 51.8 50.3 49.1 48.1

Subgrade

4 61.0 59.2 56.0 54.3 52.1 50.6 49.2 48.2

Bridge 8 62.1 60.4 59.9 58.2 55.5 54.0 52.5 51.5

Taiping Bridge - Jiamusi

Subgrade

0 60.9 55.6 57.2 51.9 53.8 48.7 50.9 46.2

Subgrade

2 62.2 56.9 57.7 52.5 54.0 48.9 51.0 46.3

Subgrade

4 63.2 57.9 58.2 53.0 54.3 49.2 51.1 46.4

Bridge 8 64.3 59.1 62.2 56.9 57.7 52.6 54.4 49.7

Jiamusi – Eastern Jiamusi

Subgrade

0 63.0 62.0 59.2 58.3 55.9 55.0 53.6 52.8

Subgrade

2 64.3 63.3 59.8 58.8 56.2 55.2 53.7 52.9

Subgrade

4 65.3 64.3 60.3 59.3 56.4 55.5 53.8 53.0

Bridge 8 66.4 65.4 64.2 63.2 59.9 58.9 57.1 56.3

Notes: 1. The noise shielding distance determination condition is the area open and without any

shield;2. The table above considered the noise impact of the project railroad only, without taking any other noise source and environmental background noise into consideration.

7.2.3 City Planning for the Ongoing Zone Noise Protection Distance

The assessment suggested the sound environment distances for the valuable land resource, speedy development and the protection of the newly built buildings in the new developing zones along the

Page 173: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

project as shown in the table 7-5.

Table 7-60 Sound Environment Protection Distance Unit: m

Section Route Type

Rail Top Height(m

)

Distance to the External Rail (m)

30m to the exterial rail central line

(70dB、70dB)

Area Class I

(70d

B、55dB)

Area Class III

(65d

B、55dB)

Area Class II

(60d

B、50dB)

Area Class I

(55dB、45dB)

Day Night Day Night Day Night Day Night Day Night

Harbin -Taiping Bridge

Subgrade

0 <30 <30 <30 39 <30 39 <30 110 64 >200

Subgrade

2 <30 <30 <30 45 <30 45 31 117 69 >200

Subgrade

4 <30 <30 <30 50 <30 50 36 124 75 >200

Bridge 8 <30 <30 <30 93 <30 93 62 >200 138 >200

Taiping Bridge - Jiamusi

Subgrade

0 <30 <30 <30 34 <30 34 36 92 96 >200

Subgrade

2 <30 <30 <30 40 <30 40 42 98 101 >200

Subgrade

4 <30 <30 <30 45 <30 45 47 104 107 >200

Bridge 8 <30 <30 <30 82 <30 82 85 193 185 >200

Jiamusi – Eastern Jiamusi

Subgrade

0 <30 <30 <30 125 <30 125 53 >200 152 >200

Subgrade

2 <30 <30 <30 130 <30 130 59 >200 158 >200

Subgrade

4 <30 <30 <30 135 <30 135 65 >200 164 >200

Bridge 8 <30 <30 <30 >200 55 >200 120 >200 >200 >200

Page 174: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Notes: 1 . The noise shielding distance determination condition is the area open and

without any shield;2. The table above considered the noise impact of the project railroad only, without taking any other noise source and environmental background noise into consideration.

7.3 Noise Mitigation Measures

7.3.1 Noise mitigation schemes

1. Economic Comparison of Noise Pollution Treatment Measures

The railway noise pollution treatment measures are mainly the barrier screen, green-belt, sensitive point function change and building sound-proof protection. The noise pollution treatment measures suitable to the sensitive points of all kinds are outlined according to the experience of the railway noise pollution treatment of many years, the general condition of the project sensitive points, noise over standard situation and other projects and surrounding conditions in the table 6-1-3.

Table 7-61 Economy and Technology Comparison of Noise Pollution Treatment Measures

Treatment Measures

Effect AnalysisInvestment Comparison

Suitable Sensitive Point Classification

Barrier Screen

Noise reduced by 6~10dBA could improve indoor and outdoor environment, not to affect the everyday life of the inhabitants.

Large investment

Applicable to the sensitive points close to the railway, high intensity building, large scale, line mode in embankment and bridge

Green-belt

1~3dBA additional rainfall of

green belt of 10 ~ 30m while beautify the environment; Requiring more land and resettlement

Comparative large

investment

Having the best comprehensive environment effect, but involving more land and resettlement. Harder in realization.

Sensitive point function changes

The railway noise impact avoided basically, but more investment and more difficult performance。

large difference between rural and

urban areas and large

Requiring the new purchase of houses by the inhabitants and comprehensive arrangement of the government. Not easy in performance.

Page 175: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

investment

Building sound-proof(sound-

proof ventilation windows, sound-proof corridors and balconies,

etc)

Noise reducing amoun

>25dBA , affecting visual sense and ventilation and the everyday life of the inhabitants

Comparative less

investment

Good noise reducing effect and less investment, but affecting the everyday life of the inhabitants

Damping steel rail

Effectively degraded the noise grade and vibration, noise

reducing amount 2~3dBA

Comparative large

investment

Several railways parallel, could be supplementary measure to the bad effect of the sound barrier

2. Noise Pollution Treatment Principles

The project is the new construction of the railway. In accordance with the project features, sensitive point scale and position relations, the assessment was determined to employ the noise treatment principles as follows:

1)Based on the principle of “better the old with the new”, the project treated the overstandard sensitive points affected by the old railway.

2)In accordance with the principle of “treatment by the one who polluted”, the bidding due to the project adopted the measures as sound barriers, sound isolation windows and the like to meet the corresponding standard limits or house utilizing function.

3)Considering the sound barrier measures first, then the partial protection of the receiving points.

4)Adopting the installation of the sound isolation ventilation windows at the points at a small scale or inapplicable for the sound barriers. Remeasuring the actual noise level during the trail operation period following the project completion, carrying out the measures in case of the real overstandard results.

5)Ensuring the schools up to the standards, or enough for the indoor function.

6)In combination with the vibration overstandard protection measures, resettle the sensitive objects adjacent to the railways and under a greater impact.

3. The analysis and demonstration on the treatment measures for the rebuilt section in Harbin

There are normally 3 kinds of noise pollution protection measurement: resettlement, sound isolation window and sound barrier.

The reconstruction of Harbin line under the project changed the rail only without the movement of the line position. In the meanwhile, the sensitive points along the route were distributed in high density and mostly the comparatively new high-storey buildings in their construction ages in Harbin Hub,

Page 176: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

which replaced by the bodies and rails in better condition. Therefore, it was forecasted that the noise value in the Harbin Hub in the operation period.

In view of the special circumstances at the Harbin, the assessment adopted the following noise pollution treatment measurements:

1)Only sound proof windows were installed for the deep cutting section unable to set sound barriers and resettlement.

2)Demolishing the houses within 30m at the plane sub-grade or bridge section.

3)The sound barrier and isolation window methods at the sensitive points in high density.

4)The sound isolation measure was used at the scattered sensitive points.

3. Noise Pollution Treatment Measures

In accordance with the noise pollution treatment principles and the economic and technical comparative results, the summary of the noise pollution treatment measures for the sensitive objects along the project was as in the Annex 6.

7.3.2 Noise Mitigation Measure Assessment

1. The current situation of measure assessment sensitive points at N4 Xiehe Hospital, Highway Bureau and State Resource Bureau and N6 Hayi Hospital:

Xiehe hospital has high cutting in 3.1m, 3 floor-storey and 50 beds in in-patient department.

Highway Bureau and State Resource Bureau and Hayi Hospital has high cutting in 1.2m, 12 storey, work in the day, no accommodation. The oral and optical departments of Hayi Hospital were affected, having 11 storey and 300 beds altogether.

The present subgrade has 4 rails, 2 of them near the sensitive points are close to the main line of Bingjing Line, the other are and line 3 and 4. Following the opening, 2 main line will be in use for the straight assess from the project to Harbin Station.

The current condition is that the old lines have trains flow of 12 pairs of freight trains, passenger train of 38.5 pairs, with the seam line.

Page 177: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Current Noise Value, referring to Table 7-7。Table 7-62 Current Noise Values at Xiehe Hospital, State Land Bureau, Highway Bureau and Hayi Hospital

Names of Sensative

Points

Subgrade Type

Directions

Distance from Monitoring Points to External Rail Central

Line(m)

Difference between

Measuring Points to

Rail Top(m)

Current Status ValueLeq(dB)

Project Line

Old Line Day Night

Xiehe Hospital

Cutting Right 24 24 4.3 63.2 61.9

State Land Bureau,

Highway Bureau

Cutting Right

18 18 2.4 63.5 62.3

18 18 17.4 61.1 59.4

18 18 32.4 59 57

Hayi Cutting Right 20 20 2.4 63.8 62.9

协和医院协和医院

公路局公路局

国土资源局国土资源局

哈大医院哈大医院

Page 178: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Names of Sensative

Points

Subgrade Type

Directions

Distance from Monitoring Points to External Rail Central

Line(m)

Difference between

Measuring Points to

Rail Top(m)

Current Status ValueLeq(dB)

Project Line

Old Line Day Night

Hospital

30 30 2.4 62.8 61.2

108 108 14.6 59.8 56.6

108 108 29.6 60.8 57.3

108 108 59.6 59.3 56.3

The current noise values are all above 55db.

The train flow after operation: 6 pairs of passenger trains, 56 pairs of motor trains with 8 in one group, 29 pairs with 16 in one group. Cancelling the freight trains, change the seam rails to seamless, close the entire line. Due to the cancellation of the freight train pairs, improved line conditions and train body, the noise value will better than the current status value.

The noise estimated values in the operation period are as shown in the table 6-3-4.

Table 7-63 Estimated Value of Noise at Xiehe Hospital, State Land Bureau, Highway Bureau ,Hayi Hospital during Operation Period

Names of Sensative

Points

Subgrad

e 形式Direction

s

Distance from Monitoring

Points to External Rail Central Line

(m)

Difference between Measuring Points to Rail Top(m)

Current Status Value

Leq(dB)

Estimated Value in 2020

Leq(dB)

Difference between Current

Value and in 2020 (dB)

Project Line

Old Line

Day Night Day Night Day Night

Xiehe Hospital

Cutting Right 24 24 4.3 63.2 61.9 58.8 55.2 -4.4 -6.7

State Land Bureau,

Highway

Cutting Right 18 18 2.4 63.5 62.3 59.1 55.5 -4.4 -6.8

18 18 17.4 61.1 59.4 56.8 52.2 -4.3 -7.2

Page 179: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Names of Sensative

Points

Subgrad

e 形式Direction

s

Distance from Monitoring

Points to External Rail Central Line

(m)

Difference between Measuring Points to Rail Top(m)

Current Status Value

Leq(dB)

Estimated Value in 2020

Leq(dB)

Difference between Current

Value and in 2020 (dB)

Project Line

Old Line

Day Night Day Night Day Night

Bureau18 18 32.4 59 57 54.8 51.1 -4.2 -5.9

Hayi Hospital

Cutting Right

20 20 2.4 63.8 62.9 59.4 56.1 -4.4 -6.8

30 30 2.4 62.8 61.2 58.5 54.5 -4.3 -6.7

108 108 14.6 59.8 56.6 55.6 51.1 -4.2 -5.5

108 108 29.6 60.8 57.3 56.6 51.5 -4.2 -5.8

108 108 59.6 59.3 56.3 55.1 50.4 -4.2 -5.9

In view of the estimated values, 3 sensitive points will still be 55db higher than the standard in the operation period, but lower than the current status.

The investigation to the old subgrade condition of this section shown that the ballast is 1,5m away from the drainage ditch and embedded the telecommunication cable. Therefore, no condition in this section is enough for the placement of the sound barrier. The assessment adopted the sound proof windows at 3 sensitive points along this section based on the principle of the new improving the old.

2. Sensive Points Noise Pollution Treatment Measures

There were 139 sensitive points along the project line, of which, 21 were the school special sensitive points, 118 inhabitant residences.

Page 180: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

The noise pollution treatment measures for the entire line are as follows:

(1)46 sound barriers of 3.15m in length of 15380m at the bridge section.

(2)43 sound barriers of 3m in length of 12096m at the subgrade section. 1 sound barrier in length of 7m.

(3)132 sound isolation ventilation windows of 107550 m2。The actual surveys will be carried out by the completion of the project for the noise level at the sensitive points, putting in use in case of the real overstandard conditions.

(4)In combination of the vibration estimation and measurement implementation situations, 1194 households sensitive points were resettled within 30m along the project line.

(5)The total noise protection investment is 270.187 million RMB Yuan.

41 points employed the noise reducing method of sound isolation windows to meet the relative standard or the utilizations function requirement along the entire project.

8 points employed the noise reducing method of sound isolation windows together with the resettlement to meet the relative standards or the utilization function requirement along the entire project.

47 points employed the noise reducing method of sound isolation windows and sound barriers to meet the relative standards or the utilization function requirement along the entire project.

36 points employed the noise reducing method of sound isolation windows together with the resettlement to meet the relative standards or the utilization function requirement along the entire project.

1 points employed the noise reducing method of sound barriers together with the resettlement to meet the relative standards or the utilization function requirement along the entire project.

6 points employed the noise reducing method of sound barriers to meet the relative standards or the utilization function requirement along the entire project.

7.3.3 Noise Pollution Protection Proposals

In consideration of the project measures above, the following measures should be used to abate the noise impact to the best extent.

(1)Reinforcement of the train bodied and rail maintenance.

A regular maintenance of the train bodies and polishing the steel rails should be performed to ensure their operation at a good condition and decrease the noise induced from the train moving and vibration.

(2)No horn within the completely closed section at Harbin and Jiamusi Hubs.

(3)Rational Scheme and Controlling the Land Usage on the both sides of the railway

It is suggested that relative city departments combine the land utilization and ciry plan with the project

Page 181: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

construction.

In consideration of an overall thought of the interactive development and improvement, the city planning divisions should put the land utilization function along the project under a strict control in

accordance with the stipulation in “Clause 11 in Chapter 2” of 《Environment Noise Pollution

Protection and Treatment Law of P.R.China》that the city planning divisions should determine the noise proof distance from the buildings to the traffic trunks and put forward the corresponding plans and design requirements while making decision of the building arrangement in accordace with the state environment quality standard and civil building design regulations and rules.

With the reference of the noise estimation results in this report, it is commented that the planning departments along the project make a reasonable scheme for the land function on the both sides of the railway and strengthen the building arrangement and sound proof and noise decreasing design. The ready researches have shown that, in view of the reducing noise impact, the surrounding building groups were better than parallel arrangement, parallel building groups were better than the perpendicular arrangement, and the non-noise sensitive buildings as the industy, storage and logistics were more applicable to the first rows of the buildings for the sake of reducing the railway noise impact to the sound environment in the building groups.

7.4 Acoustic environment asessment for the construction period

7.4.1 Noise Source in the Construction Period

The construction noise impact to the environment is due to not only the sound source and its function period, but the surrounding sensitive points distribution and its distance to the sound source also.

The construction noise of the project included the construction machinery, transportation vehicles and temporary construction facilities, of which, the construction machinery and transportation vehicles had the sound grade of higher level and longer working time. As the main sound sources, the measured values of common construction machinery noise according to a large number of the site survey data are shown in the table 6-4-1 below.

Table 7-64 Noise Source Intensity of Major Construction Machinery & Transportation Vehicles Unit: dBA

Construction Period

Names Distance between Measuring

Point and Noise Source(m)Sound Grade

AValuesAverage

Earth and gravel Works

Bulldozer 10 78~96 88

Excavator 10 76~84 80

Loader 10 81~84 82

Road Breaker 10 80~92 85

Page 182: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Heavy Lorry 10 75~95 85

Constructure

Blader 10 78~86 82

Compactor 10 75~90 83

Riveted Machine 10 82~95 88

Concrete Mixer 10 75~88 82

Electricity Generator

10 75~88 82

Peumatic Presser 10 80~98 88

Vibrator 10 70~82 76

Installation &

Maintenance

Hoister 10 84~86 85

Jumbo Crane 10 85~95 90

The main noise sources in the construction period were bulldozers, heavey trucks and road compactors. Earthworks mixing and material transportation work affected more people due to their high mobility, but this sort of impact most constrained to the day with the non-continuity and generally accepted by the civilians.

7.4.2 Noise Environment Impact Assessment Standard in the Construction Period

The noise limits at different construction stages are as in the table 7-10 below.

Table 7-65 GB12523-90 Noise Limited Value at Construction Area

Unit:Leq(dBA)Construction

PeriodMajor Noise Source

Noise Limited Value

Day Night

Earth and gravel Works

Bulldozer, excavator, loader, etc 75 55

Pile Driving Various pile drivers, etc 85 No Construction

Page 183: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Structure Concrete mixer, vibrator and electric saw, etc 70 55

Decoration Hoister, elevator, etc 65 55

7.4.3 The Controlled Distance of the Construction Machinery to the Site

The machiney at the construction sites should be managed to be at a controlled distance up to the requirement of the equivalent sound grade limits within the sites.

The equivalent and continuous sound grade A at this survey point could be calculated as the fomula below:

Leq ,T =10 lg [ 1T ∑

i=1

n

ni t eq, i 100.1(Lp0 , i+C i)]Noise declining fomula is as follow:

LA=L0−20 lg (r A /r0)

Where: LA-sound grade at rA to the sound source, dBA

L0-sound grade at ro to the sound source, dBA

The controlled distance of the construction machinery to the site should be calculated based on the actual situations. In this job, working period were 8, 10 and 12 hours in the day and 1, 2 and 3 in the evening, machines were 1, 2 and 3 pieces respectively, working out the controlled distrance of the construction machinery by the fomula. The noise impact range of the machinery under various circumstances was as in the table 6-4-3.

Page 184: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Table 7-66 Typical Construction Mechinery Contro Distrance Estimation Unit:m

Construction Machinery

Limit Value at the Site(dBA)

Operation

Time(hours) Using 1 piece Using 2 pieces Using 3 pieces

Day Night Day Night Day Night Day Night Day Night

Bulldozer 75 55

8 1 32 158 45 223 55 274

10 2 35 223 50 316 61 387

12 3 39 274 55 387 67 474

Road Breaker 75 55

8 1 22 112 32 158 39 194

10 2 25 158 35 224 43 274

12 3 27 194 39 274 47 335

loader 75 55

8 1 18 89 25 126 31 154

10 2 20 126 28 178 34 218

12 3 22 154 31 218 38 266

Blader, compactor,

generator and concrete mixer

70 55

8 1 28 79 40 112 49 137

10 2 31 112 45 158 55 194

12 3 34 137 49 194 60 237

7.4.4 Mitigation Measurements and Suggestions

In accordance with the stipulation of Clause No.27, 28, 29 and 30 of 《Environment Protection

Methods of P.R.China》, the project should be in line with the building construction site criteria of the state regulations; 15 days ahead of the construction, the environment protection administrative divisions in charge should submit the project name, working location and period and possibe environment noise values, noise pollution protection and treatment measures; No noise pollution inducing works are allowed in the evening. In case of the special working necessary at night, the identification issued by the government above the level of county or relative department in charge and notify the residents the approved jobs at night.

The assessment suggested the the following measures and suggestions on the sound environment impact during construction period in view of the actual project situation:

Page 185: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

1. The machinery with louder noise like generators, air compactors, etc. should be arrange at a remote area and be away from the sound environment sensitive points such as the residential areas, schools and hospitals and so on; the sites of mixing, stirring and precasting should be in general more than 200m away from the residential areas; for those hard tto choice suitable sites should use close sound insulation measures and carrying out a regular maintenance strictly following the operation regulations and rules.

2. Making a rational working schedule, trying to avoid the construction in the evening or doing jobs

with lower noise. Machinery with the high sound grade should be stopped in the evening (22:00~6:00). The relative approval should be obtained in case of inevitable continuous construction need and keep the residents well-informed. The construction at night should utilize the certain methods to reduce the noise to the maxium extent. The construction produced by the staff should be supported by the management rules and noise reducing measurement and be kept under a strict control. The vehicles delivering the material during the night should ban the horns, be gentle in the loading and unloading, not to disturb the people with the minimum noise.

3. During the construction period, the related vehicle passing time should be well coordinated to avoid the traffic gams by means of a proper communication among the construction party, constructors and traffic departments. The evening transportation should ban the horns, slower, and try not to use the road through the towns and villages to reduce the noise impact to a minimum extent.

4. Optimizing the construction scheme, making a logical working schedule, reducing the construction environment noise hazard to a minimum extent. The noise protection measures shoube be listed in the construction organization design and explicate in the contracts at the stage of biding and tendering stage.

5. In accordance with the 《Notification on the Strengthening Environment Noise Pollution

Supervision and Management during the Senior High School Examination Period 》issued by the State Environment Bureau on Apr. 26, 1998, in the process of the senior high school examination and 2 weeks ahead of the examination, the noise overstandard and disturbing works should be banned besides the environment noise sources of all kinds be severely under control.

6. The contruction site environment supervision should be well done in the construction period. In

accordance with 《Construction Working Range Noise Measuring Methods》, the working site should have a noise survey with the values within the noise discharge standard. This report set out the environment management survey schemes in the environment management and monitoring plan, which should be stricted followed by the relative units at work, keep the working site noise within the allowance by means of survey to reduce the construction impact on the resident living environment to a minimum extent.

7.5 Summary

7.5.1 Assessment Standards and Protection Objects

There were 139 sensitive points, of which, 21 special sensitive points and 118 concentrated residential housings.

Page 186: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

The residential houses at 30m to the exterial rail central line within the assessment scope used the

limit value of 70dBA/70dBA in 《Railway Boundry Noise Limit and Measuring Method》(GB12525-90).

The area having the noise function divisions followed the relative noise function division criteria.

Areas through the project are mostly the villages without noise function divisions, belong the Class 2 area. The urban areas with the functional division should follow the relative functional requirement. As for the special sensitive points as schools and hospitals, the standard is 60dBA in the day and

50dBA at night(with the requirement for the dormitory)7.5.2 The Current Status Assessment

The current status survey results shown that the sound grades of each sensitive object were 52.4~67.8dBA 和 45.3~68.4dBA in the day and evening.

The sound grade at 30m to outer rail central line were up to the standards of Day 70dBA and Night

70dBA set in the GB12525-90《Railway Boundry Noise Limits and Measuring Methods》.

7.5.3 Main Environment Impact and Proposed Environment Protection Measurements

1. The environment protection measures mentioned in the report for the construction period included majorly a rational arrangement of working site, machinery with high noise be far away side for the residential area; a rational working schedule, the job with high noise being done in the day, the beforehand report and approval by the relative administrative departments in charge for the technologically required continuous construction or some special needs; strengthening the environment noise survey in construction period, and so on.

2. On the basis of the environment noise estimation, the recent sound grade of the residential houses at

30m to the outer rail central line were 57.7~69.4dBA and 54.3~69.5dBA in the day and evening;

55.0~68.2dBA and 52.5~68.4dBA within the Class IV area; 54.6~61.2dBA and 50.8~58.9dBA

within the Class I area, 53.7~66.1Db and 49.1~60.6dBA within the Class II area, 53.5~65.5dBA

and 49.3~62.7dBA within the Class III area

The forecasted survey on 21 school special sensitive point shown the noise level of 54.8~67.5dBA

and 50.4~62.1dBA in the day and evening.

3. In accordance with the environment noise estimation survey results and considering the sensitive point scale and surrounding land condition, 46 sound barriers of 3.15m high and 15380 linear meter in total length were placed at the bridge section; 43 sound barriers of 3m high and 12096 linear meter in total length at the subgrade; 1 sound barrier of 7m of 380 linear meter at the subgrade section. 132 sound proof ventilation windows of 107550m2.

4. In combination with the vibration estimation and measurement utilizatioin, 1194 households at the sensitive points were resettled.

5. The noise environment protection investment was 270.187 million RMB¥

Page 187: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

8 Environment Vibration Impact Assessment

8.1 General

Following the project openning, the train wheels and steel rail generated the collision vibration, which transferred from rail sleepers and bedding to the subground, then to the ground surface, vibration disturance produced to the surroundings and the residential houses and schools along the route, having a bad impact on the life, study and rest. That vibration of the train will be the major environmental vibration source.

In addition, a temporary vibration interference will be generated by the subgrade filling, site excavation, bridge foundation, pier and abutment building, tunnel blasting and the like during the construction period.

8.2 The Current Status Assessment on Environment Vibration

8.2.1 The Current Status Investigation on Environment Vibration

The proposed railway will go through Helongjiang Province, Ha’erbing and Jimusi. The areas along the route are mostly residential environment for cities, villages and towns.

The current status investigation and research indicated that there were 88 environment vibration protection objects, of which, 7 schools with the structure of Class II and III; some of sensitive points affected by the old railway with a higher vibration grade; other points’ main vibration sources were social life induced vibration with a lower grade.

8.2.2 Current Status MonitoringI. Monitoring Methods

The environment vibration measuring was carried out according to GB10071-88《Urban Area

Environment Vibration Measuring Methods》In the old railway section, measurement was done by the method of “railway vibration”, that is “read the biggest indicated number of each train passing through, 20 trains should be measured in succession at each point, the arithmetic average of 20 readings would be the assessment value.”

Other pointing(areas without the passing-by train) were measured by “inregular vibration” method for the urban area, that is each continuous measurement should last for no less than 1000s, sampling interval 0.1s, reading accumulation Z percentage vibration grade, using VLz10 as assessment value.

Measuring points were arranged at the flat and firm ground no more than 0.5m away outside the building or at the floor conter of the inside the building.

II. Measuring Unit

The measurement was performed by the Central Laboratory of No.3 Railway Investigation and Design Institute Group, having the measurement qualification certificate No. 2009001162N of P.R.China.

III. Measuring Apparatus

Page 188: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

AWA6256B environment vibration grade analyser was used. To ensure the measurement accuracy, the apparatus had a self-correction before the inspection and check, up to the requirement the measure technology requirement.

IV. Measuring

Measurement was scheduled in April of 2010.

8.2.3 Current Measuring Point Arrangement

The sensitive point distribution method was adopted to place the survey points at each sensitive object, all at 30m to the old railway or proposed railway and at the flat and firm ground no more than 0.5m away outside the first row of the buildings.

33 survey section, 135 point were arranged as shown in the appendix drawings.

8.2.4 The Current Monitoring Results and Assessment

The current monitoring result and assessment are as shown in the Annex 7.

The current status survey results indicated:

The sound grade of part of the sensitive points of 44 along the project were over standard due to the impact of the old railway in the day and evening, the other 44 points were majorly impactd by the social life noise.

The relative parameters of the old railway operation are shown in the table 6-1-

Table 6-2 Current Train Pair Unit: pair/day

Railway SectionOrdidary Goods

Train

Ordidary Passenger

TrainTractive Type

Freight Train Tractive

Mass(t)Ha’erbing Hub 12 38.5 Electrified 5000

Jiamusi Hub 31 43.5 Electrified 5000

I. Sensitive Points Affected by the Old Railways

The sound grades at 30m to the old outer rail central line were 60.9~67.8dBA and 58.4~68.4dBA in the day and night, up to the standards of Day 70dBA and Night 70dBA set in the GB12525-

90《Railway Boundry Noise Limits and Measuring Methods》.

II. Other Sensive Points

No obvious vibration source at the present status, mainly from the human activity impact, the current

vibration grade of VLZ10 value is 49.0~57.0dB and 43.1~52.0dB in the day and evening, up to the

requirement of 70 dB and 67 dB in the day and night set in 《Urban Area Environment Vibration

Standards》(GB10070-88)

Page 189: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

8.3 Environment Vibration Impact Asessment during the

Operation Period

8.3.1 Estimation Methods

The vibration source strength and transmitting rules are affected by quite many factors. Generally, land form, land feature, geological condition and some man-made structures should all place a special impact on the sound generation and spreading. Therefore, the sound generation and spreading could show their own characters under some actual circumstance.

The vibration assessment estimation mode was according to the fomula recommended in Rail

Docu.No.44, 2010《Railway Construction Project Environment Impact Assessment, Noise Vibration

Source Intensity Value-taken and Treatment Priciple Guidance and Proposals 》(revised in 2010).

i. Vibration Estimation Fomula Selection

Railway environment vibrationVLz estimation calculation fomula is as follow:

VLZ=1n∑i=1

n

( VLZ 0, i+C i )

Where:

VLZ0,i—— vibration source intensity, the maximum grade Z vibration at the train passing through, dB

Ci —— vibration correction item of the train of No.i, dB;n —— numbers of the trains passing by

Vibration correction item Ci is calculated by Ci = CV + CW + CL + CR+ CH + CG + CD+CB

In fomular: CV—— velocity, dB;CW——axle weight correction, dB;CL—— line kind correction, dB;

CR—— rail type correction, dB;CH—— Bridge height correction, dB;CG—— Geological correction, dB;CD—— distance correction, dB;CB—— building type correction, dB。

II. Fomula Parameter Determination

Page 190: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

1. Vibration Source IntensityVLzo

The train vibration source strength in the Assessment was determined in accordance with the Rail

Docu.No.44, 2010《Railway Construction Project Environment Impact Assessment, Noise Vibration

Source Intensity Value-taken and Treatment Priciple Guidance and Proposals 》(revised in 2010)as

shown in the tables 7-3-1、7-3-2、7-3-3 below:

Table 8-67 Passenger Train Vibration Intensity at 160km/h or below

Speed(km/h)Source

Intensity(dB)Line Condition

Geological Condition

Axle Weight

Reference Point

Location

Correction Value

50~70 76.5 Railway of Grade , seamless,Ⅰ

rail of 60kg/m, rail surface in

good condition, concrete rail sleeper, road bedding with slug, straight subgrade line

Alluviation Layer

21t

30m to the training

moving line central line

Deducting 3dB from the source strength for the strength value at the bridge line

80~110 77.0

120 77.5

130 78.0

140 78.5

Table 8-68 Ordinary Goods Train Vibration Source Intensity

Speed(km/h)Source Intensity(dB

Line ConditionGeological Condition

Axle Weight

Reference Point

LocationSubgrade Bridge

50 78.5 75.5 Railway Class ,Ⅰ seamless, seamless steel

60kg/m, rail surface condition, concrete rail sleeper, rail bed with

slug,straight line, low sub-grade or bridge of

11min height

Alluviation Layer

21t

On the ground 30m to the outer train line

center

60 79.0 76.0

70 79.5 76.5

80 80.0 77.0

Table 8-69 Motor Train Group Train Vibration Source Intensity

Page 191: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Motor Train Group

Subgrade Route Bridge Route

Railway Class ,Ⅰ seamless, seamless steel 60kg/m, rail surface condition,

concrete rail sleeper, rail bed with

slug,straight line, low sub-grade or bridge of 11min height, on the ground 30m to the

outer train line center, alluviation

Layer,axle weight of 16t

without switch

with switch

without switch

with switch

160 70.0 76.0 66.0 67.5

170 70.5 76.5 66.5 68

180 71.0 77.0 67.0 69.0

190 71.5 77.5 67.5 69.5

200 72.0 78.0 68.0 70.5

210 72.5 78.5 68.5 71.5

220 73.0 79.0 69.0 72.5

230 73.5 79.5 69.5 73.5

240 74.0 80.0 70.0 74.0

250 74.5 80.5 70.5 74.5

III. Estimation Technological Conditions

Rail

The main rail adopted the interval seamless line of 60kg/m. The rail structures were dominated by

the rail with the 砟 at Ha’erbing and Jiamusi and the slab-rail without the 砟 at the interval sections.

Train Travelling Speed

The actual travelling speed at each estimating point was calculated and determined by the train type and train traction.

Locomotive Train Conditions

The electric locomotive traction mass was 5000t, the passenger trains were hauled by the locomotive SS4.

D. Traffic Flow Distribution

The passenger and freight train paires were as in the table 7-3-4 below.

Table 7-3-4 Estimated Annual Train Pair Unit: pair/day

Section 2020 2030

Page 192: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Ordinary Goods Train

Ordinary Passenger Train

Motor Train Group Ordinary Goods

Train

Ordinary Passenger Train

Motor Train Group

8 in a group

16 in a group

8 in a group

16 in a group

Ha’erbing-Taiping Bridge

8 6 56 29 8 6 69 43

Taiping Bridge-Jiamusi

0 0 56 29 0 0 69 43

Jiamusi~Jiamusi东 20 44 0 29 28 50 0 43

III. The Vibration Estimation Results and Assessment at Grade Z

The vibration impact estimation results at Grade Z at each sensitive point during the operation period were as in the Annex 8.

The estimation results indicated:

1.The evaluation values of Grade Z at the survey point 50 within 30m to the outer rail were 70.1-81.9db and 70.1-82.7db in the day and evening. 6 points were over 80dB in the day, 1.0-1.9dB higher; 11 points were over 80dB at night, 0.8-2.7dB higher.

2.The evaluation values of Grade Z at the survey point 85 within 30m to the outer rail were 52.9-77.2db and 53.5-77.9db in the day and evening, all meeting the standard requirement of 80db “on the both sides of the rainway trunk” of GB10070-88

3. In the long run, due the unchanged train types and speed and only increased traffic flow, it was estimated that the vibration estimation should have not much difference from the one in 2020, generally 0.2~0.4 dB higher.

Estimated statistic results were as in the table 7-3-6 below:

Table 8-70 Estimated Statistic Results

Measuring Point

Location

Estimated Measuring

Point Numbers

Monitoring Value(dB) Over

80(dB)ValueOver 80(dB)points

Day Night Day Night Day Night

Page 193: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Within 30m 50 70.1-81.9 70.1-82.7 1-1.9 0.8-2.7 6 11

Beyond 30m 85 52.9-77.2 53.5-77.9 0-0 0-0 0 0

8.3.2 Vibration Distance Estimation up to the Standards

For the sake of the plan and control, the vibration estimation values at the different distances and route types, and the vibration distance up to the standards were given as in the table 7-3-7 below:

Table 8-71 Railway Vibration Criteria Distance

Section

Speed (km/h)Track

Condition

Geological Condition

Line Conditio

n

Estimated

Value(dB) Distance up to

the criteri

a(m)Good

s Train

Motor Train Grou

p

Passenger Train

15m

20m

30m

60m

Ha’erbing-Taiping Bridge

60 120 100 with slugAlluviation Layer

Sub-grad

e(6m)79.5 78.3 76.5 70.5 15

Bridg

e(11m

)72.3 71.1 69.3 63.3 4

Taiping Bridge-Jiamusi

/ 230 /without

slugAlluviation Layer

Sub-grad

e(6m)76.5 75.3 73.5 67.5 7

Bridg

e(11m

)72.5 71.3 69.5 63.5 4

Jiamusi~Jiamusi 东 60 120 100 with slug

Alluviation Layer

Sub-grad

e(6m)80.8 79.5 77.8 71.7 19

Bridg

e(11m

)75.6 74.3 72.6 66.5 7

Page 194: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

Note: The distance up to the criterial is for the outside.

Indicated by the data in the table 7-3-7, the vibration impact range was larger at the sub-grade line than the bridge line.

8.4 Vibration Mitigation Measurements and Proposals

To meet the environmental vibration requirement, the following measures were proposed to decrease the impact of train vibration on the environmental vibration in combination with estimation evaluation results and on the principles of the technological feasibility and the economica reasonableness.

8.4.1 City and Town Schem, Control and Management

In order to mostly alleviate the railway construction impact on the environmental vibration, it was suggested that the government divisions of planning, construction and environmental protection should delimit a certain range of the buffer zone of no new construction of the vibration sensitve buildings as the residential houses, schools and hospitals within 30m along the both sides of the railway, taking into consideration of the fact of a higher vibration level along the both sides of the railway while making a plan for the land management.

8.4.2 Source Strength Control

It was proposed that a regular polishing of the overall rail should be arranged to eliminate the wear and reduce the unevenness between the wheels and rails after the opening of the project, a regular wheel rounding to improve the vibration due the irregular wheel. With the development of our railway transportation, locomotive and vehicle manufacture industry, rail conditions have upgraded, the old trains will be replaced by the new, the nationaliztion and popularity of the large machinery like the rail polishing will benefit the vibration impact.

8.4.3 Vibration Control Measurements

The resettlement was decided to the control the vibration impact at the points with the values over 80db after the construction.

In this assessment, 438 points along the railway were resettled in view of the noise protection measurements. The investment induced was listed in the noise protection cost to reduce the impact of railway vibration on the resident life, referring to the Annex 9.

8.5 Vibration Environment Impact Analysis during the

Construction Period

8.5.1 Construction Period Vibration Pullution Source Anaysis

The vibration pollution source was mainly the construction machinery working vibration largely from pile drilling, hole boring, road(earth)compaction, raming and heavey transportation vehicles moving, such as jumbo excavator(earth digging), air compactor, hole driller, pile driller, vibrating raming machines and so on.

The project is newly built. The construction vibration control is focus on the rural residents

Page 195: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

concentrated area close to the alignment and stations .

The constrution and blasting works in the construction period should also place an vibration impact on the nearby sensitive points.

8.5.2 Construction Machinery Equipment Vibration Strength

The table 7-5-1 is mainly for the construction machinery vibration values. It is shown that the pile driver produced the maximum vibration strength among those listed; the vibration declined with the increase of the machines distance; With the exception of the high vibration machines, other equipment

vibration are arrange within 25~30m, up to the environment standard in “mixed area”.

Table 7-5-1 Construction Mechinery Equipment Vibration Value

(VLz:dB)

Construction Machinery

Distance to Vibration Source(m)5 10 20 30

Dissel Pile Driver 104 ~ 106 98 ~ 99 88 ~ 92 83 ~ 88

Vibrating Pile Hammer

100 93 86 83

Pneumatic Hammer

88 ~ 92 83 ~ 85 78 73 ~ 75

Excavator 82 ~ 94 78 ~ 80 74 ~ 76 69 ~ 71

Compactor 86 82 77 71

Pneumatic Pressor 84 ~ 86 81 74 ~ 78 70 ~ 76

Bulldozer 83 79 74 69

Heavy Goods Train 80 ~ 82 74 ~ 76 69 ~ 71 64 ~ 66

8.5.3 Construction Vibration Control Measurements

In order to reduce the vibration to the minimum extent during the construction of the project, the following effective measurements:

1. Logical Arrangement of the Site

The scientific site arrangement is the critical way to reduce the construction vibration. The relation between the site arrangement and environment should be properly considered while ensuring the construction work.

(1)Choosing the position with less environment requirement as the fixed manufacture work site,

Page 196: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

take the girder making for instance, to avoid to be close to the sensitive areas(points) like the residentia houses;

(2)Keeping the road for the construction vehicles, especially the heavy transportation away the vibration sensitive areas;

(3)Trying to arrange the vibration-generated construction equipment 30m away from the vibration sensitive area to avoid the interruption to the surrounding environment;

(4)No use of the machines with high vibration, such as the pile driver, road compactor of raming type at the sensive construction sections as the residential areas in the evening;

2. Scientific Management, Propoganda and Civilized Construction

Under the circumstance of the construction progress, making a logical construction schedule and the scientific management; The proper propoganda should be carried out for the impact to the surrounding environment even with some correpondent control measurement and stradegies because of the technology conditions and concrete environment limit at the construction sites. To increase the residents’ mental tolerance to the bad impact, reinforce the education on the environment protection awareness of workers, initialize the consciousness of the civilized construction to alleviate the construction vibration due to the man-made reasons.

3. The explosion design staff should decide the allowed safe vibration speed by the controlling standard and calculate the controlled dynamite amount each time according to the actual conditions of the buildings at the explosive areas and the sensitive areas( points). The largest dynamite amount should be under a strict control at the construction blasting, making a rational blasting sequence to ensure the ground equipment safety; the explosive time should be properly selected to minimize the impact on the residents; the efficient propoganda and safety measurement pre-scheme should be done ahead of the explosion each time to each time to lessen or eliminate the residents’ psychological panic and the necessary safety protection measurements.

4.In order to make an effective control of the construction vibration impact on the resident living environment, the environmental management should be emphasized besides the performance of the controlling measures.The construction units should accept willingly the supervision and management of the environment department in accordance with the relative laws, rules and regulations of the state and cities along the project.

8.6 Summary

1.Affected by the old railway, the average values of current vibration grade Vlzmax within 30m

were 73.1 dB~84.1dB and 74.3 dB~84.3dB in the day and evening. 12 points were over 80db in the

day, 0.1~4.1db higher; 12 points were over 80db, 0.4~4.4db higher. Within 30m and beyond were

57.0~78.6dB and 57.3~78.9dB in he day and evening, all points in the day and evening were up to the standard value of 80db at “boths sides of the railway truck” of GB10070-88. No obvious vibration sources at the current stage, mainly the man-made acitivities. The VLZ10 value of the current

Page 197: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

vibration grade were 49.0~57.0dB and 43.1~52.0dB in the day and evening, up to the requirement

of 70 dB and 67 dB in the day and evening set in 《Urban Area Environment Vibration Standards》(GB10070-88)2.The evaluation values of Grade Z at the survey point 50 within 30m to the outer rail were 70.1-81.9db and 70.1-82.7db in the day and evening. 6 points were over 80db in the day, 1.0-1.9db higher; 11 points were over 80db, 0.8-2.7db higher. The evaluation values of Grade Z at the survey point 85 within 30m to the outer rail and beyond were 52.9-77.2db and 53.5-77.9db in the day and evening, all meeting the standard requirement of 80db “on the both sides of the rainway trunk” of GB10070-88.

3.In this assessment, 438 points along the railway were resettled in view of the noise protection measurements. The investment induced was listed in the noise protection cost to reduce the impact of railway vibration on the resident life.

4.It was suggested that the government divisions of planning, construction and environmental protection should delimit a certain range of the buffer zone of no new construction of the vibration sensitve buildings as the residential houses, schools and hospitals within 30m along the both sides of the railway, taking into consideration of the fact of a higher vibration level along the both sides of the railway while making a plan for the land management.

5.The construction sequence should be logical arranged due to the vibration impact from some of the construction machinery on the surrounding environment during the construction period. Also, it is quite necessary and effective to take the protection measures and increase the environmental awareness of the construction staff to decrease the environment vibration impact, which would vanish after the completion of the construction, during the construction period.

Page 198: E2646V1Introduction - All Documents | The World Bank€¦  · Web viewE2646V1Introduction. Project Background. The proposed Harbin-Jiamusi (HaJia Line hereafter) Railway Project

198