Upload
buibao
View
246
Download
0
Embed Size (px)
Citation preview
DRAFT Environmental and Social Impact Assessment Report
Project Number: 50182-001 May 2018
INO: Riau Natural Gas Power Project
ESIA Vol.5A_Technical Appendices
Prepared by ESC for the Asian Development Bank The environmental and social impact assessment is a document of the project sponsor. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of or any territory or area.
Riau 275 MW Gas Combined Cycle Power Plant IPP -
ESIA
Medco Ratch Power Riau
ESIA Volume 5: Technical Appendices
AM039100-400-GN-RPT-1014 | V2
May 2018
Document Ti tle
Volume 5: Technical Appendices
i
AM039100-400-GN-RPT-1014
Project Name
Project No: AM039100
Document Title: Volume 5: Technical Appendices
Document No.: AM039100-400-GN-RPT-1014
Revision: V2
Date: May 2018
Client Name: Medco Ratch Power Riau
Project Manager: Eamonn Morrissey
Author: Alex Gifford
File Name: \\jacobs.com\NZProjects\AENVW\Projects\AM039100 Riau\Deliverables\ESIA\Volume 5 -
Technical Appendices
Jacobs New Zealand Limited
Level 3, 86 Customhouse Quay,
PO Box 10-283
Wellington, New Zealand
T +64 4 473 4265
F +64 4 473 3369
www.jacobs.com
© Copyright 2018 Jacobs New Zealand Limited. The concepts and information contained in this document are the property of Jacobs. Use or
copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This document has been prepared on behalf of, and for the exclusive use of Jacobs� ✁✂✄☎✆✝✞ ✟✆✠ ✄✡ ✡☛☞✌☎✁✝ ✝✍✞ ✟✆d issued in accordance with, the
provisions of the contract between Jacobs and the client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this document by any third party.
Document history and status
Revision Date Description By Review Approved
0 29/03/2018 Initial Draft Alex Gifford B Clarke B Clarke
V1 20/04/2018 Final Draft for Issue A Kubale B Clarke B Clarke
V2 18/05/2018 Final Draft for Disclosure A Kubale B Clarke B Clarke
Document history and status
Revision Issue Approved Date Issued Issued to Comments
0 29/03/2018 29/03/2018 Medco Ratch Power Riau Draft for client review
V1 20/04/2018 20/04/2018 Medco Ratch Power Riau Final Draft for Issue
V2 18/05/2018 18/05/2018 Medco Ratch Power Riau Final Draft for Disclosure
Volume 5: Technical Appendices
ii
AM039100-400-GN-RPT-1014
Contents
1. Introduction ............................................................................................................................................... 1
Appendix A. Scoping Report ............................................................................................................................... 2
Appendix B. Detailed Process Description ........................................................................................................ 3
Appendix C. ESIA Baseline Survey Terms of Reference (Dry) ......................................................................... 4
Appendix D. ESIA Baseline Survey Terms of Reference (Wet) ........................................................................ 5
Appendix E. Technical Report � Air Quality Impact Assessment .................................................................... 6
Appendix F. Technical Report � Noise Impact Assessment ............................................................................ 7
Appendix G. Technical Report � Water Quality and Freshwater Ecology Assessment ................................ 8
Appendix H. OHS and Working Conditions ........................................................................................................ 9
Appendix I. Stakeholder Engagement Plan Including Community Grievance Mechanism ........................ 10
Appendix J. Chance Find Procedure ................................................................................................................ 11
Volume 5: Technical Appendices
1
AM039100-400-GN-RPT-1014
1. Introduction
ESIA Volume 5 provides Technical Appendices relevant to this ESIA and as referenced within ESIA Volume 1:
Introduction, ESIA Volume 2: EIA, ESIA Volume 3: SIA and ESIA Volume 4: ESMP and Framework ESMS.
Table 1.1 below provides an overview of the Technical Appendices provided in this Volume and indicates which
Volume they are associated with. It should be noted that Appendices may be associated with other more than
one Volume of the ESIA and this will be noted within the respective Volume text.
Table 1.1 : ESIA Technical Appendices
ESIA Volume Technical Appendix Document Title
ESIA Volume 1: Introduction Appendix A Technical Report � Scoping Report
Appendix B Technical Report � Detailed Process Description
Appendix C ESIA Baseline Survey Terms of Reference (Dry)
Appendix D ESIA Baseline Survey Terms of Reference (Wet)
ESIA Volume 2: EIA Appendix E Technical Report � Air Quality Impact Assessment
Appendix F Technical Report � Noise Impact Assessment
Appendix G Technical Report � Water Quality and Freshwater Ecology Assessment
Appendix H Technical Report - Occupational Health and Safety & Working Conditions
ESIA Volume 3: SIA Appendix I Stakeholder Engagement Plan Including Community Grievance Mechanism
Appendix J Chance Find Procedure
Volume 5: Technical Appendices
2
AM039100-400-GN-RPT-1014
Appendix A. Scoping Report
Riau 275 MW Gas Combine Cycle Power Plant IPP
Project - ESIA
Medco Ratch Power Riau
Technical Report � Scoping Report
AM039100-400-GN-RPT-1004 | V3
October 2017
Scoping R eport
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 i
Riau 275 MW Gas Combine Cycle Power Plant IPP Project - ESIA
Project no: AM039100
Document title: Environmental and Social Impact Assessment ✁ Scoping Report
Document No.: AM039100-400-GN-RPT-1004
Revision: V3
Date: October 2017
Client name: Medco Ratch Power Riau
Project manager: Ardi Hartanto
Author: Pete Gabriel / Anthony Kubale
File name: \\jacobs.com\NZProjects\AENVW\Projects\AM039100 Riau\Deliverables\Scoping Report
Jacobs
Talavera Office Park, 15th floor
Jl. T.B. Simatupang Kav. 22 - 26
Jakarta Selatan 12430
INDONESIA
+62 (21) 2758 8200
+62 (21) 2758 8201
www.jacobs.com
© Copyright 2017 Jacobs. The concepts and information contained in this document are the property of Jacobs. Use or copying of this document
in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This document has been prepared on behalf of, and for the exclusive use of Jacobs✂ ✄☎✆✝✞✟✠ ✡✞☛ ✆☞ ☞✌✍✎✝✄✟ ✟✏✠ ✡✞☛ ✆☞☞✌✝☛ ✆✞ ✡✄✄✏✑☛✡✞✄✝ ✒✆✟✓✠ ✟✓✝
provisions of the contract between Jacobs and the client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this document by any third party.
Document history and status
Revision Date Description By Review Approved
V0 24/07/2017 Draft P Gabriel / A
Kubale
B Clarke A Hartanto
V1 04/09/2017 Addressing Client Comments A Kubale B Clarke B Clarke
V2 14/09/2017 Addressing Further Client Comments A Kubale B Clarke B Clarke
V3 12/10/2017 Addressing ADB Comments A Kubale B Clarke B Clarke
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 ii
Contents
Glossary ................................................................................................................................................................. 4
1. Introduction ................................................................................................................................................ 5
1.1 Background ................................................................................................................................................. 5
1.2 Project Location ........................................................................................................................................... 5
1.3 Purpose ....................................................................................................................................................... 7
1.4 Structure of Report ...................................................................................................................................... 7
2. Project Overview and Progress ............................................................................................................... 8
2.1 Project Description ...................................................................................................................................... 8
2.2 Project Land Requirements ......................................................................................................................... 8
2.3 Initial Site Visit ............................................................................................................................................. 9
2.4 Project Stages ........................................................................................................................................... 11
2.5 Project Timescales .................................................................................................................................... 12
3. Existing Environment.............................................................................................................................. 13
3.1 Introduction ................................................................................................................................................ 13
4. Stakeholder Engagement and Grievance Mechanism ......................................................................... 18
4.1 Progress to Date ........................................................................................................................................ 18
4.2 Ongoing Work ............................................................................................................................................ 18
5. Key Environmental and Social Risks .................................................................................................... 19
5.1 Introduction ................................................................................................................................................ 19
5.2 Summary of Key Environmental and Social Risks .................................................................................... 20
6. Terms of Reference for ESIA .................................................................................................................. 21
6.1 Introduction ................................................................................................................................................ 21
6.2 General Approach to ESIA ........................................................................................................................ 21
6.3 Outline of ESIA .......................................................................................................................................... 22
Appendix A. Environmental and Social Impact Scoping Matrix ..................................................................... 29
Appendix B. Baseline Environmental and Social Data Collection Terms of Reference .............................. 30
Appendix C. Applicable Legislation, Standards and Guidelines .................................................................... 31
Appendix D. ESIA and AMDAL Schedule .......................................................................................................... 36
Appendix E. Water Balance Diagram ................................................................................................................. 37
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 3
Important note about your report
The sole purpose of this report and the associated services performed by Jacobs New Zealand Limited
(Jacobs) is to provide a Scoping Report which identifies the key issues that need to be addressed in the
preparation of the Environmental and Social Impact Assessment (ESIA) in respect to the Riau IPP Project, in
accordance with the scope of services set out in the contract between Jacobs and the Client. That scope of
services, as described in this report, was developed with the Client.
In preparing this report, Jacobs has relied upon, and presumed accurate, any information (or confirmation of the
absence thereof) provided by the Client and/or from other sources. Except as otherwise stated in the report,
Jacobs has not attempted to verify the accuracy or completeness of any such information. If the information is
subsequently determined to be false, inaccurate or incomplete then it is possible that our observations and
conclusions as expressed in this report may change.
Jacobs derived the data in this report from information sourced from the Client (if any) and/or available in the
public domain at the time or times outlined in this report. The passage of time, manifestation of latent conditions
or impacts of future events may require further examination of the project and subsequent data analysis, and re-
evaluation of the data, findings, observations and conclusions expressed in this report. Jacobs has prepared
this report in accordance with the usual care and thoroughness of the consulting profession, for the sole
purpose described above and by reference to applicable standards, guidelines, procedures and practices at the
date of issue of this report. For the reasons outlined above, however, no other warranty or guarantee, whether
expressed or implied, is made as to the data, observations and findings expressed in this report, to the extent
permitted by law.
This report should be read in full and no excerpts are to be taken as representative of the findings. No
responsibility is accepted by Jacobs for use of any part of this report in any other context.
This report has been prepared on behalf of, and for the exclusive use of, Jacobs✁✂ ✄☎✆✝✞✟✠ ✡✞☛ ✆✂ ✂☞✌✍✝✎✟ ✟✏✠ ✡✞☛
issued in accordance with, the provisions of the contract between Jacobs and the Client. Jacobs accepts no
liability or responsibility whatsoever for, or in respect of, any use of, or reliance upon, this report by any third
party.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 4
Glossary
AMDAL Analisis Mengenai Dampak Lingkungan
ADB Asian Development Bank
CEMP Construction Environmental Management Plan
CEMS Continuous Environmental Monitoring Station
CCGT Combined cycle gas turbine
CFPS Coal fired power station
CPI Corrugated plate interceptor
EHS Environmental, Health and Safety
EPFI Equator Principle Financial Institution
ESIA Environmental and Social Impact Assessment
ESMP Environmental and Social Management Plan
ESMS Environmental and Social Management System
GFPP Gas fired power plant
GT Gas turbine
H&SP Health and Safety Plant
ha Hectare
HHV High Heating Value
HP High pressure
HRSG Heat recovery steam generator
IP Intermediate pressure
km Kilometres
m Metres
aMSL Above mean sea level
MRPR Medco Ratch Power Riau
MW Megawatt
NOx Oxides of Nitrogen
OHL Overhead Line
OPGW Optical Ground Wire
PPA Power Purchase Agreement
RoW Right of way
SAP Survey Action Plan
SEP Stakeholder Engagement Plan
ST Steam turbine
T Tonnes
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 5
1. Introduction
1.1 Background
This Scoping Report supports an Environmental and Social Impact Assessment (ESIA) for the construction and
operation of the Riau 275 MW Combined Cycle Gas Fired Power Plant IPP Project (Riau 275 MW GFPP). The
Project consists of a 275 MW combined cycle power plant and ancillary facilities, a 40 km long 12-inch gas
pipeline, and a switchyard and a 750 m 150 kV transmission line - collectively referred to hereafter as the
✁✂✄☎✆✝✞✟✠✡ ☛☞✝ ✂✄☎✆✝✞✟ ✌✍☎✎✏☎rs being PT Medco Power Indonesia (MEDCO) and Ratchaburi Electricity
Generating Holding PCL (RATCH), have formed PT Medco Ratch Power Riau (MRPR) to build, own and
operate the plant under the terms of the Power Purchase Agreement (PPA) which has been agreed with PT
Perusahaan Listrik Negara (Persero) (✑PLN✒).
1.2 Project Location
The power plant and ancillary features, switchyard and transmission line is located in the Tenayan Industrial
Village (previously known as Sail Village), Tenayan Sub District, Pekanbaru City, Province of Riau.
The power plant is located approximately;
✓ 10km due east of the city of Pekanbaru in central Sumatra, Indonesia;
✓ 5km south of the Siak River; and
✓ 3✔✕ ✏☎✖✟☞ ☎✗ ✂✘✙✠✏ ✝✚✛✏✟✛✎✜ ✢ ✚ ✣✣✤ MW RIAU Coal Fired Power Station (CFPS).
The power plant and switchyard will be located within the 9 ha of privately owned land currently being used as a
palm oil plantation. The site is bounded by palm oil plantations to the west, south and east and Road 45 on the
North.
MRPR also proposes to seek gas supply from TGI Perawang Station located north of the power plant in the
Siak Regency. The gas will be delivered to the power plant by approximately 40 km of pipeline which will be
located within the reserve of existing road.
An outline of the Project area is detailed in Figure 1.1 and an overview of the general area and proposed
connections to services is outlined in Figure 1.2.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 6
Figure 1.1: Outline of the Project Area
Figure 1.2: Power Plant General Area and Service Connections
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 7
1.3 Purpose
This Scoping Report will review existing environmental and social-related studies and information available for
the site development and identify key risks to be considered in the ESIA including identifying information gaps
for baseline environmental and social studies. The ESIA Scoping Study includes the following:
✁ Relevant International and National requirements relevant to the proposed development including:
✁ Asian Development Bank (ADB) Safeguard Policy Statement 20091;
✁ Equator Principles
✁ International Finance Corporation (IFC) Performance Standards;
✁ World Bank Group (WBG) Environmental, Health and Social (EHS) General and Industry Specific
Guidelines and
✁ Indonesian Regulatory Framework.
✁ key risks to be addressed by the ESIA investigations;
✁ information and data gaps to be addressed through the ESIA baseline studies;
✁ extent and level of further survey required;
✁ Environmental and Social Impact Scoping Matrix
✁ a draft Terms of Reference (ToR) for the ESIA baseline studies, including confirming the scale, timing and
number of specialist ESIA surveys to be conducted (Appendix B);
✁ the outcomes of the initial site visit undertaken for the ESIA in June 2017; and
✁ proposed ESIA assessment methods (and comment on if any changes are proposed to the outline
methodology in the SoW).
It should be noted that this Scoping Report has been written with limited information regarding the design of the
Project.
1.4 Structure of Report
This Scoping Report is structured as follows:
✁ Section 2 ✂ Project Overview and Progress
✁ Section 3 ✂ General Approach to ESIA
✁ Section 4 ✂ Existing Environment
✁ Section 5 ✂ Key Environmental and Social Risks
1 ADB Safeguard Policy Statement 2009 accessed in October 2017 at [https://www.adb.org/site/safeguards/policy-statement]
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 8
2. Project Overview and Progress
2.1 Project Description
The Project comprises a 275 MW combined cycle power plant (CCPP), a 40 km long gas supply pipeline which
will bring fuel to the site, a 150 kV switchyard and 750 m long transmission line to connect the power plant to
the PLN grid. Once constructed, ownership of the switchyard and transmission line will be transferred to PLN.
(The switchyard and transmission line connection are collectively known as the Special Facilities.) At the end of
the 20 year term of the PPA, PLN will take ownership of the power plant and gas supply pipeline.
The power plant will use gas fuel only and is a 2 x 1 combined cycle plant, designed to deliver up to 275 MW
over the 20 year term of the PPA.
Key components of the project will comprise the following:
✁ Power generated by 2 x 1 combined cycle plant, delivering up to 275 MW;
✁ River water intake and outlet;
✁ 2 x 45 m tall, 3.8 m diameter chimneys;
✁ Wet mechanical draft cooling tower;
✁ Earthworks to level and raise the power plant platform from approximately 25m above mean sea level
(MSL) to 28 m;
✁ 500 m access road;
✁ Gas supplied from TGI Gas Station 40 km from the power plant via a 12 inch gas pipeline; and
✁ a 150 kV switchyard at the plant, with a 750 m double-phi connection to intercept the existing Tenayan ✂
Pasir Putih 150 kV transmission line.
The gas pipeline will be mostly trenched and buried within existing road reserve. Horizontal directional drilling
(HDD) will be used to cross the Siak River, with the pipeline anticipated to pass approximately 2 m beneath the
river bed. For other small watercourses and crossing of roads, industry standard methodology determined
during detailed design will be used.
2.1.1 Water Requirements
The water balance diagram detailed in Appendix E provides an overview of water requirements for the Project
including: raw water, treated water and waste water. Raw water is anticipated to be abstracted from the Siak
River and treated water discharged back into the river, estimated daily flow rates are as follows:
✁ Raw Water Abstraction ✂ 368.5 m3 per hour.
✁ Treated Water Discharge ✂ 82.5 m3 per hour.
Following treatment, the combined water discharge from the power plant site is anticipated to have an elevated
temperature of between 3-5°C above background. When it reaches the Siak river via the 3 km buried discharge
pipeline, the discharged water temperature is likely to be much closer to ambient.
2.2 Project Land Requirements
MRPR plan to construct the power plant and switchyard on a 9 ha plot of land owned by up to eight owners and
is currently in procurement process. A✄✄☎✆✝✞✟✠ ✡☎ ☛☞✌✍✟✎✍✆✏ ✑✞✡✒✓✔ ✕✖✍✡✞✍✗ ☛✗✍✟✘ ✡✙☞ land is in a zone allocated
for industrial and warehousing use. There are no dwellings located at the power plant site or along the
transmission line so no physical relocation or resettlement of inhabitants will be necessary.
At the time of writing MRPR is still in the process of identifying proposed lands for acquisition, required in
relation to the gas pipeline route however no physical relocation or resettlement of inhabitants is anticipated as
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 9
the gas and water pipelines will run along the road reserve or within easements which will be agreed with the
affected landowners.
The total land requirements for the power plant and switchyard (including temporary laydown areas and offices
for the construction workforce) are estimated at approximately 9.1 ha as outlined Table 2.1. Preliminary Site
layout plans are provided in the Appendices.
Table 2.1: Riau 275MW GFPP land requirements
Riau 275MW GFPP power plant land area requirements Approximate Area, ha
Power plant and main plant buildings 1.2
Cooling tower 0.2
Balance of plant area 2.5
Switchyard (150 kV) (part of the Special Facilities to be owned by PLN) 1.5
Total 5.4
During construction, there will be further land requirements for the construction workforce including temporary
laydown areas and offices. The additional area, estimated at a further 3.7 hectares will be within the site area
(total of 9.1 ha).
There will also likely be a need for a temporary jetty to be built on the Siak River, expected to be located close
✁✂ ✄☎✆✝✞ 2 x 110 MW CFPS. This will be used for transportation of materials and equipment during the
construction phase of the power plant.
In addition, the Project will also have land requirements for a water abstraction point at the Siak River, water
supply pipelines to and from the power plant site, the gas supply pipeline, and the 150 kV transmission line, as
outlined in Table 2.2 below.
Table 2.2 : Riau 275MW GFPP Land Requirements
Riau 275MW GFPP power plant ✟ Other
infrastructure land requirements
Approximate dimensions, m x m Approximate Area,
ha
Water abstraction point 20 x 20 0.006
Water supply and discharge pipeline corridor 2 x 3,000 0.6
Gas supply pipeline 2 x 40,000 8
Transmission Line (including 4 towers) 20 x 750 3
Access road 10 x 500 0.32
Total 11.926
2.3 Initial Site Visit
An initial site visit of the Project area was undertaken in June 2017. The Figures outlined below provide an
overview of the project area and the current conditions of the power plant site and along the gas pipeline route.
The initial site visit identified that the majority of the area within and surrounding the power plant is made up of
plantation area and open scrub land. The road network comprises unmade dirt road and tarmac.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 10
Figure 2.1 : Road and Surrounding Area Across Power Plant Site Area
Figure 2.2 : South of the Siak River, gas pipeline to be installed on left side of the road
Figure 2.3 : North of Siak River, overlooking gas pipeline crossing point
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 11
Figure 2.4 : Road entering power plant area
Figure 2.5 : Road along gas pipeline route. Pipeline to be located on right side of the road
Figure 2.6 : Road along gas pipeline route. Pipeline to be located on left side of the road
Figure 2.7 : Perawang TGI Station, fuel supply for Riau power plant
2.4 Project Stages
The Project will span three primary stages, being pre-construction, construction and operation, generally as
follows:
✁ Pre-construction: The pre-construction stage involves project development activities, including selection
of contractors, field surveys and permitting, and land acquisition works.
✁ Construction: The construction stage will involve land preparation (including site clearance, backfilling and
land drainage) followed by construction and commissioning of the power plant, gas pipeline and grid
connection.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 12
✁ Operation: The operation stage will involve the full operation of the power plant ✂ first of all over the 20
year term of the PPA and then, as determined by PLN after ownership transfers to PLN.
2.5 Project Timescales
The proposed project timescales for major construction activities are provided in Table 2.3.
Table 2.3: Estimated duration (in months) of activities required for Project construction
Activity Estimated Duration (months)
Site clearance and levelling 6 months
Gas pipeline construction 12 months
Power plant and switchyard engineering, procurement and construction 24 months
Construction of water pipelines (to and from site) 8 months
Transmission line construction 8 months
Commissioning 8 months
Based on current schedule (see Appendix D) the ESIA and Analisis Mengenai Dampak Lingkungan (AMDAL)
will take approximately 10 months. The dates for key for commencement and completion of the ESIA and
AMDAL are outlined below:
ESIA
✁ Scoping ✂ In progress
✁ Baseline Sampling ✂ In progress ✂ 14th November 2017
✁ Draft ESIA and Technical Studies ✂ 2nd November 2017 ✂ 5th January 2018
✁ Framework ESMS and ESMP ✂ 30th November 2017 ✂ 2nd February 2018
✁ ESIA Exhibit / Approval ✂ 8th January ✂ 27th April 2018
AMDAL & UKL-UPL
✁ UKL-UPL (gas pipeline and transmission line) ✂ 11th September ✂ 16th January 2018
✁ KA-ANDAL (power plant) ✂ 4th September ✂ 1st November 2017
✁ AMDAL Sampling ✂ 12th October ✂ 6th December 2017
✁ AMDAL and Technical Studies ✂ 2nd November 2017 ✂ 5th January 2018
✁ ANDAL and RKL-RPL for Power Plant ✂ 30th November 2017 ✂ 2nd April 2018
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 13
3. Existing Environment
3.1 Introduction
This section provides an overview of the environmental and social conditions at the proposed site of the Project, using existing information sources and key findings from the
initial site visit in June 2017. The findings are listed in Table 3.1 below. A number of information gaps currently exist which will be addressed through the ESIA process.
Table 3.1 : Riau 275MW GFPP Existing Environment
Receptor Baseline
Power Plant and Transmission Line Gas Pipeline
Climate Pekanbaru has a tropical climate. The general site climate conditions are provided below.
✁ Ambient air temperature range ✂ 20 °C-37 °C
✁ Design ambient air temperature ✂ 28 °C
✁ Relative humidity range ✂ 40 %-100 %
✁ Design Relative humidity ✂ 80 %
✁ Average annual rainfall - Approximately 3,000 mm - rainy season between November and April
✁ Maximum rainfall - Approximately [136 mm/h]
✁ Average wind speed - Less than 3 m/s, from the north and south
✁ Site elevation - Approximately 25 m aMSL
Air Quality The proposed power plant is located 10 km east of Pekanbaru City in a rural area with a number of nearby landowners, the nearest from the power plant site being approximately
450 m to the South. A screening level modelling assessment has been undertaken for the proposed CCGT power station using the AERMOD dispersion model. The intent of the
modelling is to predict likely locations of maximum impacts resulting from the discharges in order to select locations for baseline ambient air monitoring of oxides of nitrogen for the
project. Figure 3.1 and 3.2 provides results of the screening level modelling assessment.
The meteorological data set was developed using the prognostic model TAPM (Version 4.0.4), CSIRO, Australia. This model predicts meteorological parameters for the region
based on large-scale synoptic information provided by the Australian Bureau of Meteorology. Meteorological data for the project location was extracted from the model simulation
for use with AERMOD. A windrose of the data is detailed in the Figure 3.3 below.
Discharge parameters for the power station, including contaminant emission rates, were obtained from the Jacobs Riau 275 MW GFPP Project - Process Description (June 2017).
Building downwash effects were not considered under the assumption that the stack heights relative to nearby buildings are such that downwash is not an issue.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 14
Receptor Baseline
Power Plant and Transmission Line Gas Pipeline
Figure 3.1 : Maximum Predicted NOX Concentrations (1-hour average, 99.9th percentile)
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 15
Receptor Baseline
Power Plant and Transmission Line Gas Pipeline
Figure 3.2 : Maximum Predicted NOX Concentrations (24-hour average)
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 16
Receptor Baseline
Power Plant and Transmission Line Gas Pipeline
Figure 3.3 : Windrose for AERMOD meteorological dataset
Noise The proposed power plant is located 10 km east of Pekanbaru City in a rural area with a number of nearby landowners, the nearest from the power plant site being approximately
450m to the South. At the time of writing there was no data available for the existing environment for noise in the region for the power plant / transmission line and the gas pipeline.
Ambient noise monitoring will be conducted as part of the ESIA baseline data collection process in accordance with the WBG EHS General Guidelines.
WRPLOT View - Lakes Environmental Software
WIND ROSE PLOT:
Windrose for AERMOD Meteorological datsetRiau 2015-2016
COMMENTS: COMPANY NAME:
MODELER:
DATE:
19/07/2017
PROJECT NO.:
NORTH
SOUTH
WEST EAST
4%
8%
12%
16%
20%
WIND SPEED
(m/s)
>= 11.1
8.8 - 11.1
5.7 - 8.8
3.6 - 5.7
2.1 - 3.6
0.5 - 2.1
Calms: 0.00%
TOTAL COUNT:
17520 hrs.
CALM WINDS:
0.00%
DATA PERIOD:
Start Date: 1/01/2010 - 00:00End Date: 31/12/2011 - 23:00
AVG. WIND SPEED:
3.15 m/s
DISPLAY:
Wind SpeedDirection (blowing from)
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 17
Receptor Baseline
Power Plant and Transmission Line Gas Pipeline
Cultural Heritage There are no sites of cultural significance in the vicinity of the power plant or
transmission line.
The gas pipeline will follow existing road that pass approximately four mosques, one school
and one community graveyard.
Freshwater Quality and
Aquatic Ecology
The Siak River is located an estimated 5k m north of the power plant site and there
is another unnamed creek 500 m south of the site. The Siak River to the north is
estimated to be 150 m wide and is relatively deep given it is used for the barge
transportation of goods for communities and industries.
The gas pipeline route crosses an estimated four minor watercourses and the Siak River.
Landscape and Visual The topography of the region is fairly uniform at the power plant site and along the gas pipeline route.
Soils and Geology The power plant area is situated on minas formation with soils comprising gravel, pebble spreads, sands and clays. The geology on the border of the project area towards the Siak
River is made up of young alluvium formation comprising gravels, sands and clays. The gas pipeline route is predominately situated on minas formation with soils comprising
gravel, pebble spreads, sands and clays.
Terrestrial Ecology There are no protected areas of conservation concern within a 5 km radius of the
project area. The majority of the land surrounding the power plant and transmission
line comprises palm oil plantations and scrub land.
The majority of the land around the proposed gas pipeline route comprises palm oil
plantations and scrub land.
Natural Hazards and
Vulnerability to Climate
Change
At the time of writing there was no data available for the existing environment for natural hazards and vulnerability to climate change in the region for the power plant / transmission
line and the gas pipeline. Ground adjacent to the Siak River is at 10 m aMSL and at the power plant location 20 m aMSL therefore the power plant is not subject to flooding from the
river.
Land Ownership The power plant is privately owned land and by up to eight owners. As the gas pipeline is located within the road reserve the land is likely to be state owned
however this will be confirmed through the ESIA process.
Land Use The power plant Project area is currently being used as a palm oil plantation and is
privately owned.
The majority of the gas pipeline route will be located within the reserve of existing road.
Social Environment The nearest community to the power plant is Rejosari and Sail Sub-District, located
approximately 2 km south-west from the power plant site. There is no direct
route/road from the village to site.
The pipeline route passes through / adjacent to a number of communities. Communities that
have been identified within the Stakeholder Engagement Plan (SEP) as likely to be affected
by the gas pipeline include;
Pinang Sebatang Barat Village (Tualang District), Perawang Barat Villages (Tualang District);
Sail Sub-District (Tenayan Raya District) and Tebing Tinggi Okura Sub-District (Rumbai
Pesisir District).
Ecosystem Services At the time of writing data there was no data available for the existing environment for ecosystems services in the region for the power plant / transmission line and the gas pipeline.
Traffic Existing traffic is limited due to the rural nature of the surrounding land and limited
road connectivity.
Traffic use along the pipeline route is likely to be moderate due to the route running within the
reserve of an existing road network that connects nearby rural communities.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 18
4. Stakeholder Engagement and Grievance Mechanism
4.1 Progress to Date
Jacobs have prepared a Stakeholder Engagement Plan (SEP) for the project. The SEP has the following key
objectives:
✁ describes the proposed methods and processes by which local communities, stakeholders and interested
parties will be consulted in relation to the Project;
✁ outlines the means and locations of information disclosure; and
✁ outlines the grievance mechanism by which stakeholders and/or interested parties can raise their concerns
and observations.
4.2 Ongoing Work
As part of the stakeholder process, consultation will be undertaken with members of communities located near
to the proposed development area to gather information on existing socio-economic conditions and community
and cultural values. This will assist in the development of a socio-economic baseline for communities near to
the Project describing key social and economic characteristics, including:
✁ population and demography, such as age and gender, households and families;
✁ existing livelihoods, including crops being grown, number of people involved in farming activities;
✁ existing economic activities undertaken by communities near the project, such as agriculture and palm oil
plantation;
✁ existing land use and tenure arrangements;
✁ local community values and views on such things as visual and amenity values, cultural/ spiritual values,
health, use of existing natural resources; and
✁ community facilities and features, including historic and cultural sites and existing community facilities.
The Project Sponsor✂✄ Senior Manager and/or Community Liaison Officer will both advise the community and
key stakeholders that the surveys are to undertaken ahead of time and participate in their oversight with the
Jacobs representative that will be on site during all community consultation activities.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 19
5. Key Environmental and Social Risks
5.1 Introduction
An Environmental and Social Impact Scoping Matrix has been developed by Jacobs, which identifies items and
activities in the construction and operation of the power plant, transmission line and gas pipeline that could have
environmental and social impacts or pose environmental and social risks.
The Environmental and Social Impact Scoping Matrix should be revised following completion of the preparation
of the ESIA to take into account any changes to the proposed development site layout or the design as a result
of additional mitigating measures identified in the assessment of environmental and social impacts and risks.
Any improved level of knowledge on the sensitivity of key elements of the receiving environment based on the
baseline surveys should also be incorporated into the revised Environmental and Social Impact Scoping Matrix.
✁✂✄ ☎✄✆✄☎ ✝✞ ✟✠✡☛☞✡✞✡✌✍☞✌✄✎ ✞✝✏ ✄✍✌✂ ✝✞ ✑✂✄ ✄☞✆✡✏✝☞✒✄☞✑✍☎ ✡✒✓✍✌✑✔ ✡✕✄☞✑✡✞✡✄✕ ✡☞ ✑✂✄ ✖☞✆✡✏✝☞✒✄☞✑✍☎ ✍☞d Social
✠✌✝✓✡☞☛ ✗✍✑✏✡✘ ✙✍✔ ✕✄✑✄✏✒✡☞✄✕ ✚✛ ✜✍✌✝✚✔✎ ✓✄✏✔✝☞☞✄☎ ✄✘✓✄✏✡✄☞✌✄✕ ✡☞ ✄☞✆✡✏✝☞✒✄☞✑✍☎ ✍☞✕ ✔✝✌✡✍☎ ✡✒✓✍✌✑
assessments of industrial developments using a qualitative approach. The following issues were considered for
each discharge or activity (hazard) whe☞ ✕✄✑✄✏✒✡☞✡☞☛ ✑✂✄ ☎✄✆✄☎ ✝✞ ✟✔✡☛☞✡✞✡✌✍☞✌✄✎ of the impact.
Environmental and social concerns:
✢ the scale of the resulting impact;
✢ the severity of the impact;
✢ the frequency of occurrence of the impact;
✢ duration of the impact;
✢ offensiveness of the impact; and
✢ cumulative impact.
Business concerns included:
✢ regulatory/legal exposure;
✢ cost of changing the impact;
✢ difficulty in changing the impact;
✢ effect of damage on other processes and activities; and
✢ effect on public image of the organisation/reputational risk.
The impacts were ranked from low to high significance in terms of their potential for environmental and social
impact using the criteria set out below.
Table 5.1: Impact Significance Criteria
Significance Category Impact Criteria
High ✣ Significant off-site impact;
✣ Occurs on a relatively frequent basis;
✣ Breaches environmental permits, licences or national standards;
✣ Results in public complaint; and
✣ Is expensive to mitigate.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 20
Significance Category Impact Criteria
Medium
✁ has off-site effects minor in nature;
✁ could result in public complaint;
✁ at times may slightly exceed legal consents or standards; and
✁ is regarded as not a good practice.
Low ✁ may have an off-site effect;
✁ occurs very infrequently;
✁ is within legal requirements, but could still be improved; and
✁ is cheap/relatively easy to mitigate.
5.2 Summary of Key Environmental and Social Risks
✂✄☎ ✆✝✞✟✠✡☛ ✆☞✌✍✎ ✄✏✆ ✠✍☎✡☞✠✑✠☎✍ ☞✒✞ ✟✞☞☎✡☞✠✏✓✓✎ ✔✕✠☛✄✖ ☎✡✗✠✘✞✡✙☎✡☞✏✓ ✏✡✍ ✆✞✝✠✏✓ ✠✙✟✏✝☞✆ ☞✄✏☞ ✙✏✎ ✞✝✝✌✘ ✚✏✘☎
detailed below in Table 5.2) and these will be assessed in more detail in the ESIA. The ESIA will also consider
environmental and social topics that are of medium and low risk. It should be noted that these potential impacts
are based on limited information available at the time of writing and do not consider mitigation/controls that will
developed through ongoing detailed design and the ESIA process, see Section 6.2.4.1.
Table 5.2: Summary of Key Potential Environment and Social Risks
Environmental/Social Topic Key Impacts
Land Ownership and Land Use Land ownership investigations for the Project are ongoing at the time of writing for the power
plant and along the gas pipeline route
Community Health and Safety Potential adverse impacts to local communities through miss-use / illegal siphoning of gas from
the pipeline. Miss-use / illegal siphoning could lead to uncontrolled releases of gas from the
pipeline that may combust and therefore harm any individuals/settlements within the nearby area.
This is unlikely to occur given the pipeline will be buried for the majority of the route but is a risk
that should be considered further during the ESIA and be factored in to community engagement
and education programs including emergency response planning.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 21
6. Terms of Reference for ESIA
6.1 Introduction
This section describes the Terms of Reference (TOR) for the general approach to the ESIA. The baseline
environmental surveys that are required for the ESIA, and are additional to what is required under the AMDAL
process is provided in Appendix B.
6.2 General Approach to ESIA
6.2.1 Introduction
This section provides an overview of the impact assessment methodology applied to the assessment of
potential environmental and social impacts arising from the Project. The impact assessment methodology has
been developed in accordance with good industry practice, and the potential impacts will be identified in the
✁✂✄☎✆✝☎ ✂✞ ☎✟✆ ✠✡✂☛✆✁☎☞✌ ✍✡✆✍ ✂✞ ✎✄✞✏✑✆✄✁✆✒ ✎✄ ✍✁✁✂✡✓✍✄✁✆ ✔✎☎✟ Asian Development Bank (ADB) Safeguards and
IFC Performance Standard 1 (Assessment and Management of Environmental and Social Risks and Impacts).
6.2.2 Scoping
The Project kick-off meeting was held on 4th May 2017 between representatives of Jacobs and MRPR. Jacobs
completed a site visit in June 2017, the results of which will be used in producing a scoping matrix outlining key
environmental and social hazards that have High significance.
6.2.3 Establishment of Baseline Conditions
In general, baseline information will be collected from secondary desk-based studies and literature reviews and
supplemented with primary data identified in the scoping phase and obtained from site surveys and monitoring,
along with consultation with affected communities and correspondence with local stakeholders. For more details
reference should be made to Appendix B ✕ Baseline Environmental and Social Data Collection Terms of
Reference. At this stage only baseline sampling will be undertaken during the dry season as the proposed
power plant site and gas pipeline route is highly modified habitat with low ecological value. If wet season data is
deemed necessary this will be discussed and agreed with MRPR and ADB.
6.2.4 Impact Assessment
The prediction of the scale and significance of environmental impacts will be assessed against the established
baseline conditions. The assessment criteria will be based on international requirements and good practice
involving quantitative analysis and qualitative analysis with professional judgement supported by an impact
ranking system to classify the magnitude and significance of the impacts. All activities for the Project will
assessed in terms of the significance of the impact on the receiving environment, for example, air quality, noise,
ecology, and the significance of the impact of local society, including livelihoods, health, culture and
employment. For more details reference should be made to Table 6.1.
Due to the elevation of the project area in relation to the Siak River and minimal raising of ground level at the
Project area, quantitative flood risk assessments as set out in the proposal are not deemed necessary however
screening of thermal dispersion modelling of water being discharged back into the Siak River will be
undertaken.
6.2.4.1 Mitigation
The impact assessment will consider mitigation that is inherently within the design of the Project in order to
determine the significance of impacts. If the residual impact including the design mitigation is found to be not
acceptable further mitigation measures will then be recommended as necessary to ensure good practices are
implemented and in order to reduce any significant potential impacts to an acceptable level, in accordance with
ADB Safeguards and IFC Performance Standards. The mitigation hierarchy will be used: avoid, minimise,
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 22
restore or remedy, offset, compensate and mitigation measures will be clearly identified and linked to
environmental and social management plans.
6.2.4.2 Monitoring
Monitoring is not linked to the impact evaluation but is an important component of the ESIA. Monitoring follow-
up actions will be outlined in order to:
✁ Continue the collection of baseline data throughout construction, operation and later decommissioning.
✁ Evaluate the success of mitigation measures, or compliance with project standards or requirements.
✁ Assess whether there are impacts occurring that were not previously predicted.
✁ In some cases, it may be appropriate to involve local communities in monitoring efforts through
participatory monitoring. In all cases, the collection of monitoring data and the dissemination of monitoring
results should be transparent and made available to interested project stakeholders.
6.3 Outline of ESIA
The ESIA is anticipated to following the format and layout outlined in Table 6.1 below.
Table 6.1 : Outline Structure of the ESIA
Non-Technical Summary
Vo
lum
e 1
: In
tro
du
cti
on
Introduction A brief description of the Project, the location and the environmental setting
Policy, Legal and
Administrative Framework
✂ ADB Safeguard Policy Statement (2009), Equator Principles IFC Performance
Standards, WBG General and Industry Specific EHS Guidelines
✂ Indonesian Regulatory Framework
✂ Permits/Licences
Project Description
✂ Overview
✂ Site location
✂ Project land requirements
✂ Project schedule
✂ Description of construction, operation and decommissioning activities
Project Justification and
Assessment of Alternatives
✂ Project justification and site / route selection
✂ ✄☎☎✆☎☎✝✆✞✟☎ ✠✡ ☛☞✟✆✌✞☛✟✍✎✆☎ ✍✞✏☞✑✒✍✞✓ ✟✔✆ ✕✒✠-✞✠✟✔✍✞✓✖ ☎✏✆✞☛✌✍✠
Vo
lum
e 2
: E
nvir
on
men
tal Im
pact
Asse
ssm
en
t
Introduction ✂ Overview
Impact Assessment
Methodology
✂ Baseline Environmental Conditions and Previous Studies
✂ Spatial and Temporary Scope
✂ Impact Assessment Methodology
✂ Impact Identification
✂ Cumulative Impacts
Environmental Impact
Assessment
Environmental baseline for the following topics:
✂ Climate
✂ Air Quality
✂ Greenhouse Gas Emissions
✂ Noise
✂ Natural Hazards
✂ Hydrology
✂ Water Quality and Freshwater Ecology
✂ Landscape and Visual
✂ Terrestrial Ecology
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 23
✁ Soils, Geology and Groundwater
✁ Hazardous Substances and Waste
✁ Traffic and Access
Each of the topics will contain the following:
✁ Assessment of Impacts
✁ Mitigation and Monitoring measures
✁ Assessment of Residual Impacts
Occupational Health and Safety & Working Conditions
Cumulative Impacts
Summary of Environmental Impacts
Vo
lum
e 3
: S
oc
ial Im
pact
Asse
ssm
en
t
Introduction Overview
Legal and Regulatory
Framework
✁ National and International Requirements
Impact Assessment
Methodology
✁ Data sources
✁ Spatial and Temporary Scope
✁ Impact Assessment Methodology
Social Impact Assessment
Social baseline for the following topics:
✁ Demographic Overview
✁ Ethnicity and Culture
✁ Religion
✁ Gender
✁ Indigenous People
✁ Ecosystem Services
✁ Economic Profile
✁ Educational Profile
✁ Land Use and Tenure
✁ Poverty, Deprivation and Vulnerable Groups
Stakeholder Engagement
Impact Assessment for the following:
✁ Employment
✁ Land Acquisition
✁ Cultural Heritage
✁ Community Health, Safety and Security Impacts
✁ Cumulative Impacts
Mitigation, Enhancement Measures and Residual Impacts
Assessment of Residual Impacts
Vo
lum
e 4
: E
SM
P,
ES
MS
an
d C
om
plian
ce
Asse
ssm
en
t
Environmental and Social
Management Plan (ESMP)
✁ Construction Mitigation and Monitoring
✁ Operation Mitigation and Monitoring
Framework Environmental
and Social Management
System (ESMS)
✁ Structure of Framework ESMS
✁ Alignment with IFC Performance Standards and ADB Safeguard Policy Statement
(2009)
✁ Policies
✁ Roles and Responsibilities
✁ Legal and Other Requirements
✁ Identification of Risks and Impacts
✁ Management Programmes
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 24
✁ Monitoring and Review
✁ Stakeholder Engagement
✁ Training
✁ Administration
Compliance Assessment ✁ Compliance with ADB Safeguard Policy Statement (2009), Equator Principles and
IFC Performance Standards
Volume 5: Technical Appendices
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 25
Table 6.2: ESIA Terms of Reference
Environmental Topic Impact Assessment Methodology
Air Quality and
Greenhouse Gas
Assessment
The ESIA will assess the direct and indirect impacts to air quality from construction and operation including potential dust generation
during construction. The assessment will also include greenhouse gases generated by the development and operation of the power plant.
The assessment will include:
✁ Evaluation of the current ambient air quality of the area based on baseline sampling results (see Section 8 of Appendix B for details
of baseline sampling to be undertaken);
✁ Development of a meteorological data set based on prognostic meteorological data and site specific data from the meteorological
station. The TAPM model will be used to fully develop the meteorological data set if no specific data is available
✁ Development of an emission inventory data files for air contaminant sources; and
✁ Conducting air dispersion modelling with AERMOD air dispersion models as area is flat terrain
✁ Evaluation of the level or significance of impact based on the predicted contours produced by the modelling for contaminants by
comparison against WHO ambient air guidelines.
Noise The ESIA will assess potential noise impacts during construction and operation. The assessment will be carried out using the following
method:
✁ Noise monitoring will take place as set out in Section 9 of Appendix B. The noise data collected will then be used to establish project
noise criteria.
✁ Development of a meteorological data set based on prognostic meteorological data and historic, site specific data from the
meteorological station. If no specific data is available TAPM modelling will be used to fully develop the meteorological data set
✁ Development of a sound level inventory for key noise sources and activities of the development
✁ Development of a noise model, including terrain, buildings and a consideration of meteorological conditions using SOUNDPLAN
✁ Prediction of noise levels during construction and operation of the development
✁ Comparison of results from the modelling against evaluation criteria
✁ Evaluation of the level or significance of impact based on the predicted noise levels produced by the modelling.
Cultural Heritage The ESIA will assess the direct and indirect impacts on cultural heritage assets.
Biodiversity freshwater
aquatic assessment
The ESIA will assess the direct and indirect impacts on aquatic flora and fauna values identified through the baseline investigations
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 26
Environmental Topic Impact Assessment Methodology
(including water quality
and sediment)
outlined in Section 4 of Appendix B. The following will also be carried out during the ESIA:
✁ Determine whether any critical habitats are impacted;
✁ Assess the potential impact on water quality from soil erosion, transfer of sediment or movement of contaminant;
✁ Conduct screening modelling to determine the dilution rate of contaminants discharged into the river.
Hydrological
Assessment
The ESIA will assess the direct and indirect impacts on the hydrological regime using qualitative assessments. The assessment will also
include screening of thermal dispersion modelling of water being discharged back into the Siak River.
Groundwater The ESIA will assess how groundwater will be impacted both during the construction of the Project and operation. Groundwater data
collected through baseline sampling outlined in Section 6 of Appendix B will be used to assess any impacts to groundwater quality and
the groundwater take on local users.
Landscape and Visual The ESIA will assess changes to the visual conditions and values of the study area as a result of development infrastructure.
Soils and Geology The ESIA will assess the potential impacts of soil contamination from the development, including identification of management measures.
The baseline sampling will be desk based utilising geotechnical data collected.
Terrestrial Ecology The ESIA will assess the impacts on the terrestrial flora and fauna values using data collected in the baseline sampling terrestrial ecology
fieldwork surveys outlined in Section 5 of Appendix B.
The ESIA will compare the proposed footprint of works and associated infrastructure, the duration and nature of construction activities
and the lifecycle of the Project and identify the potential impacts on the sensitive characteristics of the habitats and species identified in
the baseline study of the surrounding area. Sensitive characteristics include representativeness, intactness, rareness, cohesiveness and
other valuable aspects of the habitats (if any), and the rareness or pest status of the species present. The scale of the impact
assessment will be determined by the sensitivity of the habitats and species identified in the baseline assessment.
The ESIA will determine the scale of impact based on the loss or reduction of habitat, changes to the numbers of species present,
changes in community dynamics and the changes to populations of individual species. Impacts may be positive or negative.
Natural Hazards and
Vulnerability to Climate
Change
The ESIA will undertake a natural hazards assessment will be undertaken which will examine and assess the exposure of the site to
natural hazards such as extreme rainfall and drought.
The natural hazards assessment will use existing and publically available data within the region in order to define the natural hazards
affecting the site under present-day and future climate conditions in order to develop design strategies to appropriately manage the
associated risks.
Hazardous Substances
and Waste
The ESIA will aim to assess the potential impacts associated with the use of hazardous materia✂✄ ☎✆✝ ✄✞✟✄✠☎✆✡☛✄ ☞✌✍ ✠✎☛ ✝☛✏☛✂✌✑✒☛✆✠✓✄
lifecycle. The ESIA will also assess impacts of waste generated by the development and waste management measures to be
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 27
Environmental Topic Impact Assessment Methodology
implemented.
The ESIA will utilise data currently held on other similar developments to assist in the preparation of a list of potentially hazardous
substances used for different phases of the development.
Land Ownership and
Land Use
The ESIA will assess changes to and impacts on the use of land (i.e. agricultural uses, community uses) by the development. It will also
assess changes to land access arrangements for local people. Data will be collected through consultation which will be undertaken by the
social impact assessment team.
Population, Social
Environment and
Health, Economy
The ESIA will complete an assessment of social impacts on communities near to the development. Matters to be assessed as part of the
social impact assessment would be confirmed following the socio and economic surveys outlined in Section 10 of Appendix B.
Strategies to avoid, manage or mitigate potential impacts of the development on the existing socio-economic environment and maximise
the identified benefits of the development would also be identified.
Traffic The traffic assessment will be based on traffic survey data collected during baseline investigations of key routes construction vehicles will
use to access the site. The ESIA will review the baseline data and assess the impacts associated with the transport of people, materials
and equipment to the Project area during construction and operation. The ESIA will also assess any river navigation impacts through
construction of temporary jetty and increased river traffic.
Working Conditions
and Occupational
Health and Safety
The assessment will require review of health and safety procedures that are anticipated to be developed by the EPC (Engineering,
✁✂✄☎✆✂✝✞✝✟✠ ✡✟☛ ☞✄✟✌✠✂✆☎✠✍✄✟✎ ☞✄✟✠✂✡☎✠✄✂✏ ✑✒✝✂✝ ✓✍✔✔ ✡✔✌✄ ✕✝ ✂✝✖✍✝✓ ✄✗ ✘✄✔✍☎✍✝✌ ✂✝✔✡✠✍✟✙ ✠✄ ✚✆✞✡✟ ✛✝✌✄✆✂☎✝✌ ✡✟☛ ✜✄✂✢✝✂✣✌ ✛✍✙✒ts. The
ESIA will assess the adequacy of the proposed controls to prevent major accident scenarios and the level of risk posed on the
surrounding development. The proposed health and safety management system will be summarised and the ESIA will outline mitigation,
management, and monitoring actions to be included in the ESMP.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 28
6.3.1 Mitigation Measures and Recommendations
Additional mitigation measures to those already included in the design and construction methodology will be
recommended to reduce residual impacts to acceptable levels, for example, air quality, ecology or land
acquisition. These additional mitigation measures and those included in the design and construction
methodology will be summarised and used to develop various management and monitoring procedures (i.e.
Environmental and Social Management Plan (ESMP) and Environmental and Social Management System
(ESMS)). For clarity, the purpose of each of these key documents is as follows:
✁ an ESIA identifies and assesses risks and the impacts associated with the Project;
✁ an ESMP sets out the mitigation and monitoring required to manage the impacts; and
✁ an ESMS sets out how the mitigation monitoring will be implemented, checked and reviewed.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 29
Appendix A. Environmental and Social Impact Scoping Matrix
Riau 275MW Combined Cycle Gas Fired Power Plant - Environmental and Social Impact Scoping Matrix
Social Impacts Approval
Plant Items and Operations
Fre
sh
Wa
ter
Qu
ality
Fre
sh
Wa
ter
Ec
olo
gy
Te
rre
str
ial E
co
log
y
Gro
un
dw
ate
r
Gro
un
d c
on
tam
Air
Qu
ality
Du
st
Tra
ffic
Na
vig
ati
on
No
ise
& v
ibra
tio
n
Vis
ua
l
Riv
er
us
e
Fis
hin
g (
+v
e)
Fis
hin
g (
-ve
)
Lo
ss
of
ac
ce
ss
to
res
ou
rce
s
Em
plo
ym
en
t
Cu
ltu
ral H
eri
tag
e
Po
pu
lati
on
Mo
ve
me
nt
(-v
e)
Po
pu
lati
on
Mo
ve
me
nt
(+v
e)
Re
se
ttle
me
nt
(ec
on
om
ic o
r
forc
ed
dis
pla
ce
me
nt)
Lo
ss
of
pro
du
cti
on
lan
d
Pu
blic
He
alt
h
Ae
sth
eti
c
Se
ism
ic
Flo
od
ing
Clim
ate
Ch
an
ge
Ty
ph
oo
n
AM
DA
L
ES
IA
Stage 1 Preconstruction Phase
Land aquistion for Power Plant L L L L M
Land Acquisition for Gas Pipeline H H
Design information M M
Stage 2 Construction of Power Plant & Gas
Pipeline
Transportation of fill to site M M M M M M
Earthworks to increase base height to 28m above
MSLL L M L L M M L L L L L L L M M
Access roads L L L L L L L
Transportation of heavy equipment to site via
temporary jettyL L L L L
Transport of people and materials to site on daily
basisL L M L L L
Construction of Power Plant L L L M M M M M L L L M
Construction of gas pipeline L L L M M M M M M
Crossing of watercourses by the gas pipeline L L L L L
Construction Camp incuding waste and wastewater
disposalL L M L M
Construction of Transmission lines M L M L L L L
Stage 3. Operation of Power Plant and gas
pipeline
Discharge of emissions through exhaust and fans
(primary air, ID, FD etc)M
Cooling water system (Closed circuit) M
Extraction of water from freshwater environment M M L M
Sewage treatment system L M L
Discharge of treated wastewater and stormwater to
freshwater environmentM M M
miss-use / illegal siphoning of gas from the pipeline. H
Solid waste disposal L L
Cumulative impacts with existing Riau IPPs (noise,
air)M M L L L M
Natural
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 30
Appendix B. Baseline Environmental and Social Data Collection Terms of Reference
Memorandum
Level 6, 30 Flinders Street
Adelaide SA 5000 Australia
T +61 8 8113 5400
F +61 8 8113 5440
www.jacobs.com
Subject Baseline Environmental Data
Collection Terms of Reference
(TOR)
Project Name Riau 275 MW GFPP Project (Medco
Ratch Power Riau)
Attention NBC, Medco Ratch Power Riau Project No. AM039100
From PT Jacobs Indonesia
Date 05.07.17
1. Introduction
This Baseline Environmental Data Collection Terms of Reference (TOR) has been developed
by PT Jacobs Group Indonesia (PT JGI) to collect sufficient baseline data to quantify the
receiving environmental and social baseline status for both the power plant site (including 700m
of transmission line) and gas supply pipeline route for the Riau 250 MW CCGT Power Plant
Project for the ESIA, and is in addition to the baseline sampling required under Indonesian
legislation for the power plant AMDAL and the UKL/UPLs for the gas pipeline and transmission
line . The project consists of a 275 MW combined cycle power plant and ancillary facilities, a
40 km long 12-inch gas pipeline, and a switchyard and 150 kV transmission line (750m) -
�✁✂✂✄�☎✆✝✄✂✞ ✟✄✠✄✟✟✄✡ ☎✁ ☛✄✟✄☞✠☎✄✟ ☞✌ ☎☛✄ ✍✎✟✁✏✄�☎✑✒
This TOR should be read in conjunction with the Riau Environmental and Social Impact
Assessment (ESIA) ✓ Scoping Report (to be completed), which provides details on the known
existing environmental and social site conditions and explains the approach taken to ESIA.
2. Summary Project Description
The Project will be located approximately 10 km due east of Pekanbaru City, approximately 5
km south of the Siak River. The power plant and switchyard will be comfortably accommodated
inside the 9 ha of land being procured by the Sponsors. The power plant is a 2 x 1 combined
cycle plant, designed to deliver up to 275MW over the 20 year term of the PPA. It will burn gas
fuel only. Key components of the project will comprise the following:
✔ Power generated by 2 x 1 combined cycle plant, delivering up to 275 MW;
✔ River water intake and outlet;
✔ Air emissions will be released to the atmosphere via 2 x 45 m tall, 3.8 m diameter
chimneys;
✔ Wet mechanical draft cooling tower;
✔ Earthworks to level and raise the power plant platform to approximately 28m above mean
sea level;
✔ Gas will be supplied from TGI Gas Station 40 km from the power plant via a 12 inch
diameter pipeline; and
✔ a 150kV switchyard at the plant, with a 750 m double-phi connection to intercept the
Tenayan ✓ Pasir Putih 150 kV transmission line (TL).
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
2.1 Power Plant and Transmission Line
The power plant site is located to the east of Pekanbaru City, in Sail Sub District. The site
bounded by palm oil plantation to the west, south and east and Road 45 on the North. The
Project Sponsors proposes to construct a 750m long 150kV transmission line to tie in to
Tenayan � Pasir Putih 150kV existing transmission line. Four transmission towers will be
erected between the power plant and the existing transmission line. The proposed power plant
and transmission line sites are shown in Appendix A.
2.2 Gas Pipeline Route
The gas supply line is approximately 46 km long from the PGN Gas Terminal Port at Perawang
(Future Line of KP 457 � SV 1401.1 of the Grissik Duri Pipeline � coordinate: 47N 791885
E81526 (UTM Format)) to the gas receiving facility located within the Riau CCGT Power Plant
at Tenayan district, Pekanbaru City, Riau Province. The proposed pipeline route is shown in
Appendix C.
3. Baseline Sampling
3.1 Introduction
This TOR sets out the baseline survey environmental data that is required to be collected by
NBC (✁✂✄✂☎✆✝✂✄ ✄✂✆✂✄✄✂✞ ✝✟ ☎✠ ✡the subconsultant☛). It describes:
☞ The type of data to be collected by the baseline sampling surveys;
☞ The sampling locations, number of samples, sampling methodology to be followed and
frequency of sampling;
☞ Analysis methods for ecological samples collected;
☞ Parameters that samples should be analysed for (water, sediment, soil and groundwater
samples); and
☞ Reporting formats for the data collected.
3.2 Requirements of the Subconsultant
The baseline sampling as set out in this ToR will be conducted for the Environmental and
Social Impact Assessment (ESIA) for the overall Project adhering to international Asian
Development Bank (ADB) International Safeguards and is in additon to the baseline sampling
conducted in accordance with Indonesian environmental regulations for the the power plant
AMDAL and UKL/UPLs for the transmission line and gas pipeline. The ESIA baseline sampling
will be conducted prior to the sampling required for the AMDAL and UKL/UPL.
The subconsultant is required to report on the progress of the baseline data collection surveys
to PT JGI. The subconsultant shall provide informal fortnightly progress reporting (email) to PT
JGI and monthly face to face meeting✠ ✌✍✝✁ ✎✏ ✑✒✓☛✠ ✎✄✟✔✂✕✝ ✖☎✗☎✘✂✄ ✞✙✄✍✗✘ ✝✁✂ ✚☎✠✂✛✍✗✂ ✞☎✝☎
collection phase. The progress meetings between the subconsultant and PT JGI during this
phase will confirm progress in the data collection, discuss outcomes of consultation undertaken
and identify any issues in the collection of the baseline data, thus avoiding schedule/scope
creep. For all surveys the raw data that underpins the statistical analysis undertaken as part of
the survey should be provided.
Any issues encountered by the subconsultant that prevent the subconsultant undertaking the
baseline survey by the method specified in this TOR or where data is not available or cannot be
obtained must be advised to PT JGI as soon as the issue comes to the notice of the
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
subconsultant. PT JGI will then in discussions with the subconsultant and the Project Sponsors
determine whether the data is required or an alternative survey method or modification to the
proposed survey can be used.
The subconsultant will provide PT JGI with sampling and monitoring methodologies prior to
�✁✂✄☎✆✝✞✟✁✠ ✆✡✄ ☛✝☞✄✌✟✁✄ ✂✝✆✝ ✍✎✌✌✄✍✆✟✎✁ ✏✎☎ ☎✄✑✟✄✒ ✆✎ ✄✁☞�☎✄ ✓✔✕✖☞ ✂✝✆✝ ☎✄✗�✟☎✄✘✄✁✆☞ ✏✎☎ ✆✡✄
ESIA will be met.
A maximum of three months has been allowed in the ESIA preparation schedule for the
undertaking of baseline studies, as the baseline surveys need to be completed before end of
September 2017. At this stage we have only aloowed for dry season sampling and based on
the findings limited wet season sampling may be required. The TOR may be changed based on
environmental and social data currently being collected by the Project Sponsors, which will be
made available to PT JGI for this Project.
4. Freshwater Aquatic Survey, including Water Quality
The subconsultant shall conduct a baseline survey to characterise regional freshwater
communities and ecology of the Siak River and other water courses in the vicinity of the Project
power plant, TL and gas pipeline route that includes:
✙ Fish;
✙ Macroinvertebrates;
✙ Algae and macrophytes;
✙ Aquatic habitats; and
✙ Water quality.
Water quality, and ecological (macroinvertebrate and net fishing) sampling of the above water
courses is required at locations shown in Appendix B and Appendix D.
4.1 Water Quality Samples
4.1.1 Methodology
Water samples should be collected from the Siak River, an unnamed creek to the south of the
proposed power plant site and from four watercourses along the gas pipeline route. Samples
will be collected under dry season flow conditions at minimum two sampling locations (one
upstream and one downstream). The proposed water quality sample locations are shown in
Appendix B (power plant / TL) and Appendix D (gas pipeline route).
Samples will be collected and stored in accordance with the requirements specified in
Government Regulation No. 82 Year 2001 regarding Water Quality Management and Pollution
Control Class II (as minimum, unless otherwise regulated by local government regulation) and
ISO 5667.6:2004 Water quality ✚ Sampling Part: 6 Guidance on sampling of rivers and streams
or its equivalent. The sampling will be conducted to determine the physical, chemical and
biological parameters of the rivers prior to the power plant development. The parameters that
the samples are to be analysed for are set in Table 4.1 below.
For metals the samples jars will be acid preserved. One set of metal samples will be for total
metal and the water sample will be placed in the sample container without filtration. Another
sample will be collected for soluble metals and the sample will be filtered to remove suspended
solids in the field prior to it being placed in the container containing acid preservative.
Laboratory analysis of water samples should be carried out in accordance with APHA method.
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
Organic parameters must be collected in glass jars and that only the first set of samples from
each sampling location needs to be analysed for the organic parameters being organochlorine
pesticides, Dioxins, Furans, other toxics such as PAH (Polycyclic Aromatic Hydrocarbons), and
Polychlorinated Biphenyls (PCB). This would be for the first set of samples collected.
Table 4.1: Analysis Parameters for Water Samples
Parameter Siak River Unnamed Creek
Connecting power Plant
to Siak River
Spot sampling on
watercourses crossed by
proposed gas pipeline
pH ✞ ✞ ✞
Total Suspended Solids ✞ ✞ ✞
BOD ✞ ✞ ✞
COD ✞ ✞ ✞
Oil and Grease ✞ ✞ ✞
Arsenic ✞ ✞ ✞
Boron ✞ ✞ ✞
Cadmium ✞ ✞ ✞
Chromium Hexavalent ✞ ✞ ✞
Total ✞ ✞ ✞
Copper ✞ ✞ ✞
Iron ✞ ✞ ✞
Lead ✞ ✞ ✞
Mercury ✞ ✞ ✞
Manganese ✞ ✞ ✞
Nickel ✞ ✞ ✞
Zinc ✞ ✞ ✞
Soluble Heavy Metals (filtered)
as per bulleted list above
✞ ✞ ✞
Ammonia ✞ ✞ ✞
Fluoride ✞ ✞ ✞
Total nitrogen ✞ ✞ ✞
Nitrate ✞ ✞ ✞
Nitrite ✞ ✞ ✞
Phosphorus ✞ ✞ ✞
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
Parameter Siak River Unnamed Creek
Connecting power Plant
to Siak River
Spot sampling on
watercourses crossed by
proposed gas pipeline
Total Coliform Bacteria ✞ ✞ ✞
Organochlorine pesticides ✞ � �
Dioxins, Furans, other toxics
such as PAH
(Polyaromatic Hydrocarbons)
✞ � �
Polychlorinated Biphenyls (PCB) ✞ � �
Temperature ✞ ✞ ✞
Conductivity ✞ ✞ ✞
Turbidity (NTU) ✞ ✞ ✞
4.1.2 Sampling Frequency and Field Data
As a minimum, water samples should be collected from the identified sampling locations on at
least two occasions during the dry season and on one occasion during the wet season (to be
confirmed at the end of dry season sampling). Measurements of pH, temperature, dissolved
oxygen and conductivity should be recorded in the field at the time the samples are collected.
The date and time that the samples were collected and the weather conditions at the time of
sampling and for the previous 24 hours should also be noted.
The flow rate of the river at each of the sampling point should be estimated at each sample
location. At each sampling point the cross section of the river should be determined along with
the velocity of the river at that point. Velocity can be determined by use of flow measuring
device or by timing a device floating in the main current of the river between two points marked
on the opposite bank. Cross sectional areas will need to be determined, depth and width of the
river at the sampling points. Cross sections may be available from the survey of the rivers,
which is to be conducted either as part of the baseline data collection by the subconsultant or
by the power plant designers. If not they will need to be measured as part of the water
sampling programme.
4.2 Freshwater Ecological Sampling
4.2.1 Macro-invertebrate Sampling
Macro-invertebrate sampling will be conducted at one location (unnamed creek near the power
plant) and at one location on Siak River, as identified in Section 4.1 and shown in Appendix B.
Sediment samples will collected at this location by grab or box corer methods. A total of three
samples will collected at this point following a transect across the rivers. The sediment samples
will be composited and a sample taken and sent to the laboratory to determine the chemical
contaminants present in the sediments.
The benthic fauna will be treated in a standard manner - sieved through 1 mm mesh size,
identified to species level and enumerated, weighed and subjected to ABC analyses.
Abundance, species diversity and distribution frequency will be determined for each sampling
location. The sampling should not be carried out within two weeks of a storm event as this has
the potential to flush organisms out of their ecosystems and thereby potentially reducing the
number of organisms present.
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
The sampling should be conducted by a recognised laboratory or university with the facilities to
store and count the species. Sampling should be conducted following the guidance provided in
the ANZECC Water Quality Guidelines for Fresh and Marine Waters, 2000.
A report will be provided setting out the sampling methodology followed, sample locations, raw
data and the analysis of abundance and diversity.
4.2.2 Net Fishing
If appropriate, net fishing will be conducted at the upstream and downstream sampling
locations identified for both the Siak River and other watercourses to determine the abundance
and diversity of fish species in the rivers prior to the power plant development. Any protected
species identified in the survey will need to be clearly identified so that the impact of effluent
discharged to rivers from the power plant development can be assessed. The sampling should
be conducted by a recognised laboratory or university with experience in conducting similar
surveys.
4.3 Reporting
Reports on the baseline data collected by these studies will be prepared by the subconsultant
and submitted to PT JGI within one month of the data collection being undertaken.
5. Terrestrial Ecology
The baseline survey will assist in determining the baseline for terrestrial ecosystems and the
representative flora and fauna in each of the habitats at the power plant/TL site and the gas
pipeline route. As a minimum, flora and fauna samples should be collected from a number of
identified sampling locations along the gas pipeline route on at least one occasion during the
dry season only. Due to the area being predominantly palm oil plantation and therefore low in
biodiversity, it is considered that dry season sampling is only required for terrestrial ecology.
Date and time that the samples were collected and the weather conditions at the time of
sampling and for the previous 24 hours should be noted.
5.1.1 Site Survey Preparation � All Sites
The task includes review of background information on the locality, field work to survey habitats
and species, and reporting of methodologies, results and conclusions. A literature review shall
be conducted before carrying out field surveys. This will also include screening of international
databases to identify international recognised key biodiversity risks such as designated or
protected areas and threatened species. Specific tasks include:
1) Describing and mapping the various terrestrial habitats on the sites. This is to include the
fish ponds if any.
2) Within each habitat, use internationally accepted, standard sampling techniques to identify:
✁ Habitat type (wetland / agriculture / forest; intact / degraded / modified; man-made;
significance of biodiversity ✂ local, national, international). Include information on
hydrology, soils or other habitat characteristics that are relevant.
✁ Species - including introduced, indigenous, noxious pest or weed, economic value,
significance ✂ local, national, international. The significance of species shall be noted
in the report.
✁ Note the ecological uses of the site for significant faunal species (i.e. feeding, nesting,
migrating)
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
3) Sampling techniques shall be adequate to provide a detailed list of species, abundance,
and habitats condition using primarily visual and aural methods. Trapping, handling,
specimen collection of species is not expected as part of this study (except for the fish
survey, as discussed above).
4) Type of survey will include:
a) Vegetation / flora;
b) Avifauna (birds);
c) Herpetofauna (amphibians and reptiles);
d) Mammals
5.1.2 Survey methodologies
Vegetation / flora
A preliminary land-use/habitat classification of the study area shall be prepared in GIS by
interpretation of satellite imaginary and/or aerial photography. This information shall be used to
stratify the vegetation and habitat types for further detailed survey. Stratification is necessary to
ensure that the full range of potential habitats and vegetation types are systematically
sampled. Stratification shall consider land-use, elevation and vegetation type (shrub, cleared
agriculture / plantation / off-stream wetlands).
Power Plant / TL
Habitat classification maps will be ground-truthed through a combination of walked transects
through habitat-types to provide further detailed information on vegetation boundaries, floristic
diversity and the possible presence of rare and threatened plants.
Walked transect surveys shall aim to record all plant species within the vicinity of the Project.
There will be 3-4 transects for the power plant / TL site. Particular attention shall be paid to the
dominant, rare, endemic, threatened, protected, invasive species, and the species that are of
importance to local communities. Locations of rare or threatened plant species shall be
identified using a GPS and data on the size and distribution of the population shall be recorded.
The following general data shall be along each route:
� location using handheld GPS to record coordinates;
� photographs showing habitat structure and any notable plant species;
� habitat types and structure.
Additional habitat conditions data shall be recorded per transect, including the level of
modification or disturbance of habitat found per transect and this shall be assessed according
to the following grading:
� relatively stable or undisturbed communities (e.g. old growth, unlogged forest);
� late successional or lightly disturbance communities (e.g. old growth mangrove swamp that
was selectively logged in recent years);
� mid-successional or moderately to heavily disturbed communities (e.g. young to mature
secondary forest); and
� early successional or severely disturbed communities.
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
Gas Pipeline Route
The gas pipeline route will be driven with all habitats recorded in detail on route. In areas of
notable floristic diversity, the site will be assessed in more detail with 100m transects running
perpendicular to the road. Notable species will be recorded as above for the power plant / TL
site.
Avifauna
Power Plant / TL
�✁✂ ✄☎✆✝✂✞ ✄✁✟✠✠ ✡☛☞☎✄ ☛✌ ✄✟✍✎✠✏✌✑ ✒✏✆✓ ✄✎✂☞✏✂✄✔ ✆✏☞✁✌✂✄✄ ✟✌✓ ✟✒☎✌✓✟✌☞✂ ✠☛☞✟✕✂✓ ✖ithin the
range of different habitat strata present. Line transects surveys will be used with a point count
method. There will be 3-4 for the power plant / TL site.
Transect surveys and point count surveys involving a 20 minute time-based survey and each
transect/point to record all birds seen or heard within a 50 m radius of the census point. Bird
surveys shall be conducted within four hours of sunrise to sample peak activity time and
surveys shall avoid adverse weather (e.g. high wind or rain). Geographic coordinates shall be
recorded at each survey point
Observations on birds shall be done primarily through visual observation and call identification.
Nests and important food source/trees for any protected and rare species shall be recorded
and captured with GPS. Where possible, surveys will also cover the foreshore area for
seabirds.
Gas Pipeline Route
The gas pipeline route will be driven with all habitats recorded in detail on route. In areas of
notable potential for avifauna, the site will be assessed in more detail with 100m transects
running perpendicular to the road, on the same side as that the pipeline will run. Notable
species will be recorded as above for the power plant / TL site.
Herpetofauna
Power Plant / TL
The type and number of reptile and amphibian species shall be recorded during the walked
transect surveys. Areas of high concentrations of individuals shall be captured with GPS. Study
area and observations of significance shall be photographed.
Gas Pipeline Route
The gas pipeline route will be driven with all habitats recorded in detail on route. In areas of
notable potential for herpetofauna, the site will be assessed in more detail with 100m transects
running perpendicular to the road, on the same side as that the pipeline will run. Notable
species will be recorded as above for the power plant / TL site.
Mammals
Power Plant / TL
The type and number of mammal species shall be recorded during the walked transect surveys.
Visual identification of animals, refuges, scat or other signs is expected. It is not deemed
necessary to use camera traps in this study.
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
Gas Pipeline Route
The gas pipeline route will be driven with all habitats recorded in detail on route. In areas of
notable potential for mammals, the site will be assessed in more detail with 100m transects
running perpendicular to the road, on the same side as that the pipeline will run. Notable
species will be recorded as above for the power plant / TL site.
5.1.3 Reporting
Reports delivered by subconsultants shall include the follows:
� Background context, from desk top study.
� Sampling methodology including limitations to methodology (weather, season, timeframe,
sampling biases, etc.). Cite references for standard sampling methodologies.
� Results, including species lists and abundance (including indigenous and introduced),
observations of refuges / nests etc., significant habitats or species (rare, threatened,
noxious etc.), ecosystem uses for key species (nesting, migrating, foraging etc.).
� Conclusions on the significant issues or factors that should be addressed in the
environmental impact assessment study, including recommendations for further study work
if required.
6. Groundwater Resources (Power Plant Only)
6.1 Collect and Review Background Information
Background information needs to be obtained by the subconsultant on the existing groundwater
use and hydrogeological characteristics of the power plant site. Data required to be obtained as
part of this assessment includes:
� Determine the location, depth and groundwater levels (both static and pumping levels if
available) of existing groundwater /bores and wells within two kilometres of the site.
� Obtain available geological and construction information for bores/wells within two
kilometres of the power plant site. Bore construction data may include information on bore
casing, well screens, and pump installation, such as depth, diameter, material types,
screen slot sizes, and pump specifications.
� Determine the locations of existing groundwater users in nearby villages.
� Advise PT JGI what data is available and whether it is sufficient to prepare hydrogeological
maps.
� Prepare hydrogeological maps if there is sufficient data available that show the locations of
existing boreholes in relation to the proposed power station and ash disposal site. These
maps should clearly identify existing groundwater supply bores, surface geology,
groundwater catchment boundary, and hydrogeological features (e.g. springs).
� Determine seasonal fluctuation of the groundwater levels from either existing monitoring
data, or undertake regular water level monitoring of accessible bores.
� Arrange and undertake a water sampling programme of three bores/wells within one
kilometre of the proposed site to determine baseline water quality of the groundwater
system surrounding the project site. Selection of appropriate sampling sites will be
undertaken in discussions with PT JGI based on the results of the above review and will
target wells which have information on geology, bore construction and yield. It will likely
include a borehole drilled on the project site, assuming that this has accessible piezometer
installation. A total of three water samples are to be collected once the well volume has
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
sufficiently purged such that field parameters (pH, total dissolved solids, temperature)
have stabilised. The samples are to be analysed for the same parameters as set out in Table 4.1, excluding dioxins.
6.2 Reporting
The subconsultant shall provide the base datasets identified above to PT JGI in appropriate
electronic format to enable data manipulation and integration. These data will be used by PT
JGI to develop a preliminary conceptual understanding of the hydrogeology of the area
surrounding the site. The results of this work will be used to refine the scope and specific
requirements for additional investigations and ongoing base data collection to be undertaken.
7. Contaminated Land (Power Plant Only)
Surface soil samples to a depth of 300m are to be collect at the power plant area and analysed
for pesticides being organochlorine, organophosphorous and organo nitrous. A total of 10 soil
samples on a grid based system shall be collected and analysed.
8. Air Quality
8.1 Ambient Air Quality
The construction activities for both the power plant/TL and the have the potential to adversely
impact on the ambient air quality therefore baseline monitoring should be undertaken by the
subconsultant at a selection of potentially sensitive sites that could be affected by the
construction activities.
The monitoring sites must be located in suitable areas that comply with the guidelines set out in
Australian Standard AS 2922 Ambient Air � Guide for the Siting of Sampling Units 1987. The
purpose of AS 2922 is to ensure that the location of the sampling site is such that the collected
data is representative of that location. The standard has a number of guidelines to facilitate the
site location conformity. The guidelines also outline sites to avoid including those that:
✁ Restrict airflows in the vicinity of the sampling inlet.
✁ May alter pollutant concentrations by adsorption or absorption.
✁ Chemical interference with the pollutant being measured may occur.
✁ Physical interference may produce atypical results.
Consideration is also given to vandalism, adequate access, services and local activities when
selecting a site. In addition, for the data to be applicable to human health the sampling inlet
should be located near the breathing zone, i.e. around 1 to 2 m above ground level.
Figure 7.1 of AS 2922 documentation and shows the generalised layout and guidelines for a
typical sampling site. It is noted that security is an issue in respect to the sampling equipment
and local schools, mosques or other relatively secure sites should be used. Discussions should
be entered with village chiefs to fine secure sites.
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
Figure 7.1: Generalised Ground Level Sampling Site
At this initial stage it is proposed that the following monitoring is conducted at the two sites:
� PM10/Total suspended particulate using high volume sampler or low volume method.
� Nitrogen dioxide by either active sampling or by passive diffusion tubes
8.1.1 PM10/PM2.5Total Suspended Particulate
PM10 and PM2.5 will be collected at each of the monitoring sites following Method IO-2.1
Sampling of Ambient Air for PM10 and PM2.5 Using High Volume (HV) Sampler. Ambient air is
drawn at a known flow rate through a prepared filter via a PM10 and a PM2.5 inlet, which
effectively acts as a hood to prevent precipitation and debris from falling onto the filter. . The
sample volume is calculated from the average flow rate and sample duration. The material
collected on the filter is determined gravimetrically. Sampling duration is for a 24-hour period.
Sampling would be carried out twice a month for a minimum of three months at each of the
monitoring sites.
Subconsultant is to advise which method will be followed and when sampling can commence.
8.1.2 Passive Sampling
Table 7-1 lists the gaseous pollutants to be measured using integrated passive samplers. It
also lists a brief description of the reaction occurring in each passive sampler, the analytical
method used to measure the reacted product, the sensitivity required, and references for the
method discussed. Weather shields have been installed at all sites to protect the passive
sampler units.
Table 7.1: Passive Sampling Methods
Pollutant Reaction & Analysis Detection
Limit
NO2 Nitrogen (NO2) is chemiadsorbed onto TEA as nitrite. Nitrite is quantified by visible
spectrophotometry. Sampling is selective for gaseous molecules. Any airborne nitrite
will not cross the diffusive membrane.
± 2 ppb for 14
day mean
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
The radiello passive samplers will be exposed for 14 day periods for the three months prior to
site works commencing at each of the four monitoring sites. For AMDAL requirements the
monitoring will be for one 24 hour period per month.
9. Noise
9.1 Methodology
Construction and operational activities have the potential to adversely impact on the noise
environment therefore baseline monitoring should be undertaken by the subconsultant at a
selection of noise sensitive sites affected by the activities. These locations must be situated
away from existing noise sources such as roads or industry and be representative of the
ambient noise environment. Samples will be collected in accordance with the requirements
specified in the WBG EHS General ..
Long-term measured background noise levels over a minimum period of 48 hours of good
weather should be undertaken to provide information on the background noise environment in
the absence of industrial or extraneous noise sources. The subconsultant in their Baseline
Noise Report should comment on any current activities near the pipeline sites that may cause a
background level of noise and ground vibration (e.g. other industry, railway, major roads, etc.).
The daily variation of background noise levels recorded every 15 minutes at nearby noise
sensitive sites should be recorded and reported as mean daily noise levels in the Baseline
Noise Report with particular regard to the different periods of the day and night. The survey
conditions, meteorology, location and results for each location for the baseline monitoring
should also be recorded and included in the Baseline Noise Report. Noise measurements were
performed by integrating sound level meter which have facilities LTMS, namely Leq recorded
every 5 seconds for 60 minutes measurement. Measurements were taken during the 24-hour
activity (LSM). Each measurement should be able to represent a certain time interval with a set
of at least four time measurements during the day and three at night time measurements, such
as the following example:
� L1 measured at 07:00 to 08:00 to represent at 06:00 to 9:00
� L2 measured at 10:00 to 11:00 to represent at 09:00 to 11:00
� L3 measured at 15:00 to 16:00 to represent at 14:00 to 17:00
� L4 measured at 20:00 to 21:00 to represent at 17:00. to 22:00
� L5 measured from 23.00 to 24.00 for representing 22.00 to 24.00
� L6 measured at 1:00 to 2:00 for representing 24.00 - 3:00
� L7 measured at 4:00 to 5:00 to represent at 03:00 to 6:00
Where possible, sufficient noise data should be collected to account for variations in seasonal
and meteorological conditions. This will provide a baseline for comparison of predicted noise
levels as well as information to be used in later studies.
9.2 Sampling locations ✁ Power Plant
The noise sample locations should represent all potentially affected receivers. This will typically
be residential properties and excludes unoccupied buildings and should be continuous over at
least four days. It should also cover seasonal variations (however as the location is equatorial,
this may not be relevant). The sites for noise monitoring are as following (also shown in
Appendix B):
1) Rural property to the north (affected by existing PS noise)
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
2) Rural property to the south (unaffected by existing PS noise)
3) Outskirts of Penkanbaru to the west
4) Outskirts of Penkanbaru to the south
9.3 Sampling locations � Gas Pipeline Route
Noise monitoring along the gas pipeline should be representative of the main noise
environments along the route. This monitoring can be a single 15 minute period at each
location, however if night works are proposed, monitoring should also be done at night. The
sites for noise monitoring are as following (also shown in Appendix D):
1) Outskirts of Penkanbaru close to the proposed pipeline route
2) Rural environment
3) River crossing
4) Outskirts of Jln Koperasi
5) Close to main road (Ji Raya Minas Perawang)
9.4 Reporting
A short Baseline Noise Report will be prepared setting out the above data and provided to PT
JGI along with the raw noise monitoring data to enable a noise impact assessment to be
prepared. The subconsultant will provide technical details (specification) of the proposed sound
level meter to be used, so that PT. JGI can check that it will produce the data required.
10. Social and Economic
10.1 General
The subconsultant will collect data on the current farming activities in the vicinity of the power
plant site, TL and gas pipeline route. This includes:
✁ A breakdown of the crops being grown, number of hectares covered and the annual
tonnages harvested and the number of local people who farm or are supported by these
fields.
✁ Demographic data on the number of people involved in the farming activities, where they
reside, and age profile.
The subconsultant is required to collect information on:
✁ Historical settlement of the area and traditional activities;
✁ Known archaeological sites within two kilometre radius of the gas supply pipeline;
✁ Traditional and present-day social and tribal structures in the proposed sites;
✁ Identify and describe of sites of cultural and heritage importance within two kilometre
radius of the power plant site, TL and gas pipeline route;
✁ Determine the values(importance) placed on these sites in terms of local, regional and
national significance;
✁ Identify and record existing activities of cultural and heritage value within two kilometre
radius of the power plant site, TL and gas pipeline route;
✁ Identify potential effects of the proposed power plant site, TL and gas pipeline route on the
cultural and heritage sites and values;
Memorandum
Baseline Environmental Data
Collection Terms of Reference
(TOR)
� The views of the key local, regional and national groups, as relevant on the heritage and
cultural sites near the site; and
� Provide a report that sets out the methodology used to collect the baseline data and the
data collect in respect to cultural activities and heritage sites in the surrounding area.
10.2 Public Health
The subconsultant is required to collect information on:
� Historical information of public health in the vicinity of the power plant site, TL and gas
pipeline route, to include:
� Identify and describe of type of public disease on the area;
� Determine the values (dominance) of the disease on the area;
� Identify public health facilities to include availability of health worker on the area;
� Identify potential effects of the proposed transmission line on community public health;
and
� Provide a report that sets out the methodology used to collect the baseline data and the
data collect in respect to public health in the surrounding area.
Appendix 1 Proposed Location of Power Plant and Transmission Line
16
Appendix 2 Proposed Sampling Locations � Power Plant
17
Appendix 3 Proposed Location of Gas Pipeline Route
18
Appendix 4 Proposed Sampling Locations � Gas Pipeline
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 31
Appendix C. Applicable Legislation, Standards and Guidelines
This section is to set out the requirements that apply to stakeholder engagement for the Project. These are driven by:
✁ Asian Development Bank (ADB) Safeguard Policy Statement (2009) (Section C.1)
✁ ✂✄☎✆✝☎✞✟✠✡ ☛✆☞ ✞✄✌✝✠☞✍✄✠✡ ✡✞✠✝☎✎☎✠☞ ✏✑ ✒✓✠ ✔✕✍☛✒✌✄ ✂✄☎✆✝☎✞✟✠✡✖ ✗✓☎✝✓ ☎✆✒✠✘✄☛✒✠ ✒✓✠ ✙✚✛✜✡ ✢✌✝☎☛✟ ☛✆☞
Environmental Policy and Performance Standards (Section C.2)
✁ IFC Performance Standards (Section C.3)
✁ World Bank General and Industry Specific Environmental, Health and Safety Guidelines (Section C.4)
✁ The Indonesian Regulatory Framework (Section C.5)
C.1 ADB Safeguard Policy Statement (2009)
The ADB Safeguard Policy Statement covers safeguard policies on the following:
✁ Environmental - To ensure the environmental soundness and sustainability of projects and to support the integration of environmental considerations into the project decision-making process.
✁ Involuntary Resettlement - To avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and to improve the standards of living of the displaced poor and other vulnerable groups.
✁ Indigenous Peoples Safeguards - To design and implement projects in a way that fosters full respect for ✙✆☞☎✘✠✆✌✍✡ ✂✠✌✞✟✠✡✜ ☎☞✠✆✒☎✒✑✖ ☞☎✘✆☎✒✑✖ ✓✍✣☛✆ ✄☎✘✓✒✡✖ ✟☎✤✠✟☎✓✌✌☞ ✡✑✡✒✠✣✡✖ ☛✆☞ ✝✍✟✒✍✄☛✟ ✍✆☎✕✍✠✆✠✡✡ ☛✡ ☞✠✎☎✆✠☞
by the Indigenous Peoples themselves so that they (i) receive culturally appropriate social and economic benefits, (ii) do not suffer adverse impacts as a result of projects, and (iii) can participate actively in projects that affect them.
ADB Safeguard Requirements
All three ADB Safeguards require the following in relation to the ESIA:
✁ Information disclosure ✥ i.e. displaying the ESIA or IEE on the Project Sponsor/ADB website.
✁ Consultation and participation - The Project Sponsor will carry out meaningful consultation with affected people and other concerned stakeholders, including civil society, and facilitate their informed participation.
✁ Grievance redress mechanism - borrower/client will establish a mechanism to receive and facilitate ✄✠✡✌✟✍✒☎✌✆ ✌✎ ☛✎✎✠✝✒✠☞ ✞✠✌✞✟✠✡✜ ✝✌✆✝✠✄✆✡✖ ✝✌✣✞✟☛☎✆✒✡✖ ☛✆☞ ✘✄☎✠✤☛✆✝✠✡ ☛✏✌✍✒ ✒✓✠ ✞✄✌✦✠✝✒✜✡ ✠✆✤☎✄✌✆✣✠✆✒☛✟
performance.
C.2 Equator Principles
The Equator Principles are guidelines for financial institutions on managing environmental and social risk in project financing. The key points of the Principles for the purposes of this Project are presented below. The Principles apply to new project financing globally where the total project capital cost exceeds US$10m, and to project finance advisory activities.
Equator Principle Financial Institutions (EPFI) will only provide loans to projects that conform to Principles 1 to 9 as outlined below.
Principle 1 (Review and Categorisation)
✧★✩✪✫ ✬ ✭✮✯✰✪✱✲ ✳✴ ✭✮✯✭✯✴✪✵ ✶✯✮ ✶✳✫✬✫✱✳✫✷✸ ✲✩✪ ✹✺✻✼ ✽✳✾✾✸ ✬✴ ✭✬✮✲ ✯✶ ✳✲✴ ✳✫✲✪✮✫✬✾ ✴✯✱✳✬✾ ✬✫✵ ✪✫✿✳✮✯✫❀✪✫✲✬✾
review and due diligence, categorise it based on the magnitude of its potential environmental and social
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 32
risks and impacts. Such screening is based on the environmental and social categorisation process of the
✁✂✄☎✆✂✝✄✞✟✂✝✠ ✡✞✂✝✂☛☎ ☞✟✆✌✟✆✝✄✞✟✂ ✍✁✡☞✎✏ ✍✑✒✓✞✔✞✄ ✁✎✕
Principle 2 (Social and Environmental Assessment)
✖✡✟✆ ✝✠✠ ☞✝✄☎✗✟✆✘ ✙ ✝✂✚ ☞✝✄☎✗✟✆✘ ✛ ✜✆✟✢☎☛✄✣✤ ✄✓☎ ✑✜✡✁ ✥✞✠✠ ✆☎✦✧✞✆☎ ✄✓☎ ☛✠✞☎✂✄ ✄✟ ☛✟✂✚✧☛✄ ✝✂ ✙✣✣☎✣✣★☎✂✄
✌✆✟☛☎✣✣ ✄✟ ✝✚✚✆☎✣✣✤ ✄✟ ✄✓☎ ✑✜✡✁✩✣ ✣✝✄✞✣✪✝☛✄✞✟✂✤ ✄✓☎ ✆☎✠☎✫✝✂✄ ☎✂✫✞✆✟✂★☎✂✄✝✠ ✝✂✚ ✣✟☛✞✝✠ ✆✞✣✬✣ ✝✂✚ ✞★✌✝☛✄✣ ✟✪
the proposed Project (which may include the illustrative list of issues found in Exhibit II). The Assessment
Documentation should propose measures to minimise, mitigate, and offset adverse impacts in a manner
relevant and appropriate to the nature and scale of the proposed P✆✟✢☎☛✄✏✕
Principle 3 (Applicable Social and Environmental Standards)
✖For projects located in non-designated countries, the assessment process evaluates compliance with the
then applicable IFC Performance Standards on Environmental and Social Sustainability (Performance
Standards) and the World Bank Group Environmental, Health and Safety Guidelines (EHS Guidelines)
(Exhibit III).
The Assessment process should, in the first instance, address compliance with relevant host country laws,
regulations and permits ✄✓✝✄ ✌☎✆✄✝✞✂ ✄✟ ✣✟☛✞✝✠ ✝✂✚ ☎✂✫✞✆✟✂★☎✂✄✝✠ ✞✣✣✧☎✣✏✕
Principle 4 (Environmental and Social Management System and Equator Principles Action Plan)
✖✡✟✆ ✝✠✠ ☞✝✄☎✗✟✆✘ ✙ ✝✂✚ ☞✝✄☎✗✟✆✘ ✛ ✜✆✟✢☎☛✄✣✤ ✄✓☎ ✑✜✡✁ ✥✞✠✠ ✆☎✦✧✞✆☎ ✄✓☎ ☛✠✞☎✂✄ ✄✟ ✚☎✫☎✠✟✌ ✟✆ ★✝✞✂✄✝✞✂ ✝✂
Environmental and Social Management System (ESMS).
Further, an Environmental and Social Management Plan (ESMP) will be prepared by the client to address
issues raised in the Assessment process and incorporate actions required to comply with the applicable
standards✏ ✭✓☎✆☎ ✄✓☎ ✝✌✌✠✞☛✝✔✠☎ ✣✄✝✂✚✝✆✚✣ ✝✆☎ ✂✟✄ ★☎✄ ✄✟ ✄✓☎ ✑✜✡✁✩✣ ✣✝✄✞✣✪✝☛✄✞✟✂✤ ✄✓☎ ☛✠✞☎✂✄ ✝✂✚ ✄✓☎ ✑✜✡✁
will agree an Equator Principles Action Plan (AP). The Equator Principles AP is intended to outline gaps
and commitments to meet EPFI requirements in line with ✄✓☎ ✝✌✌✠✞☛✝✔✠☎ ✣✄✝✂✚✝✆✚✣✏✕
Principle 5 (Consultation and Disclosure)
✖✡✟✆ ✝✠✠ ☞✝✄☎✗✟✆✘ ✙ ✝✂✚ ☞✝✄☎✗✟✆✘ ✛ ✜✆✟✢☎☛✄✣✤ ✄✓☎ ✑✜✡✁ ✥✞✠✠ ✆☎✦✧✞✆☎ ✄✓☎ ☛✠✞☎✂✄ ✄✟ ✚☎★✟✂✣✄✆✝✄☎ ☎✪✪☎☛✄✞✫☎
Stakeholder Engagement as an ongoing process in a structured and culturally appropriate manner with
Affected Communities and, where relevant, Other Stakeholders. For Projects with potentially significant
adverse impacts on Affected Communities, the client will conduct an Informed Consultation and
Participation process. The client will tailor its consultation process to: the risks and impacts of the Project;
✄✓☎ ✜✆✟✢☎☛✄✩✣ ✌✓✝✣☎ ✟✪ ✚☎✫☎✠✟✌★☎✂✄✮ ✄✓☎ ✠✝✂✗✧✝✗☎ ✌✆☎✪☎✆☎✂☛☎✣ ✟✪ ✄✓☎ ✙✪✪☎☛✄☎✚ ☞✟★★✧✂✞✄✞☎✣✮ ✄✓☎✞✆ ✚☎☛✞✣✞✟✂-
making processes; and the needs of disadvantaged and vulnerable groups. This process should be free
from external manipulation, interference, coercion and intimidation.
✯✟ ✪✝☛✞✠✞✄✝✄☎ ✰✄✝✬☎✓✟✠✚☎✆ ✑✂✗✝✗☎★☎✂✄✤ ✄✓☎ ☛✠✞☎✂✄ ✥✞✠✠✤ ☛✟★★☎✂✣✧✆✝✄☎ ✄✟ ✄✓☎ ✜✆✟✢☎☛✄✩✣ ✆✞✣✬✣ ✝✂✚ ✞★✌✝☛✄✣✤
make the appropriate Assessment Documentation readily available to the Affected Communities, and
where relevant Other Stakeholders, in the local language and in a culturally appropriate manner.
The client will take account of, and document, the results of the Stakeholder Engagement process,
including any actions agreed resulting from such process. For Projects with environmental or social risks
and adverse impacts, disclosure should occur early in the Assessment process, in any event before the
Project construction commences, and on an ongoing basis.
EPFIs recognise that indigenous peoples may represent vulnerable segments of project-affected
communities. Projects affecting indigenous peoples will be subject to a process of Informed Consultation
and Participation, and will need to comply with the rights and protections for indigenous peoples contained
in relevant national law, including those laws implementing host country obligations under international law.
Consistent with the special circumstances described in IFC Performance Standard 7 (when relevant as
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 33
defined in Principle 3), Projects with adverse impacts on indigenous people will require their Free, Prior and
✁✂✄☎✆✝✞✟ ✠☎✂✡✞✂☛ ☞✌✍✁✠✎✏✑
Principle 6 (Grievance Mechanism)
✒✌☎✆ ✓✔✔ ✠✓☛✞✕☎✆✖ ✗ ✓✂✟✘ ✓✡ ✓✙✙✆☎✙✆✚✓☛✞✘ ✠✓☛✞✕☎✆✖ ✛ ✍✆☎✜✞✢☛✡✘ ☛✣✞ ✤✍✌✁ ✥✚✔✔ ✆✞✦✧✚✆✞ ☛✣✞ ✢✔✚✞✂☛✘ as part of the
ESMS, to establish a grievance mechanism designed to receive and facilitate resolution of concerns and
✕✆✚✞★✓✂✢✞✡ ✓✩☎✧☛ ☛✣✞ ✍✆☎✜✞✢☛✪✡ ✞✂★✚✆☎✂✝✞✂☛✓✔ ✓✂✟ ✡☎✢✚✓✔ ✙✞✆✄☎✆✝✓✂✢✞✏
The grievance mechanism is required to be scaled to the risks and impacts of the Project and have
Affected Communities as its primary user. It will seek to resolve concerns promptly, using an
understandable and transparent consultative process that is culturally appropriate, readily accessible, at no
cost, and without retribution to the party that originated the issue or concern. The mechanism should not
impede access to judicial or administrative remedies. The client will inform the Affected Communities about
the mechanism in the course of the Stakeholder Engagement proces✡✏ ✒
Principle 7 (Independent Review)
✒✌☎✆ ✓✔✔ ✠✓☛✞✕☎✆✖ ✗ ✓✂✟✘ ✓✡ ✓✙✙✆☎✙✆✚✓☛✞✘ ✠✓☛✞✕☎✆✖ ✛ ✍✆☎✜✞✢☛✡✘ ✓✂ ✁✂✟✞✙✞✂✟✞✂☛ ✤✂★✚✆☎✂✝✞✂☛✓✔ ✓✂✟ ✫☎✢✚✓✔
Consultant, not directly associated with the client, will carry out an Independent Review of the Assessment
Documentation including the ESMPs, the ESMS, and the Stakeholder Engagement process documentation
✚✂ ☎✆✟✞✆ ☛☎ ✓✡✡✚✡☛ ☛✣✞ ✤✍✌✁✬✡ ✟✧✞ ✟✚✔✚✕✞✂✢✞✘ ✓✂✟ ✓✡✡✞✡✡ ✤✦✧✓☛☎✆ ✍✆✚✂✢✚✙✔✞✡ ✢☎✝✙✔✚✓✂✢✞✏✑
Principle 8 (Covenant)
✒✌☎✆ ✓✔✔ ✍✆☎✜✞✢☛✡✘ ☛✣✞ ✢✔✚✞✂☛ ✥✚✔✔ ✢☎★✞✂✓✂☛ ✚✂ ☛✣✞ ✄inancing documentation to comply with all relevant host
country environmental and social laws, regulations and permits in all material respects.
Furthermore for all Category A and Category B Projects, the client will covenant the financial
documentation:
a) to comply with the ESMPs and Equator Principles AP (where applicable) during the construction and
operation of the Project in all material respects; and
b) to provide periodic reports in a format agreed with the EPFI (with the frequency of these reports
proportionate to the severity of impacts, or as required by law, but not less than annually), prepared by
in-house staff or third party experts, that
i) document compliance with the ESMPs and Equator Principles AP (where applicable), and
ii) provide representation of compliance with relevant local, state and host country environmental and
social laws, regulations and permits; and
c) to decommission the facilities, where applicable and appropriate, in accordance with an agreed
decommissioning plan.
Where a client is not in compliance with its environmental and social covenants, the EPFI will work with the
client on remedial actions to bring the Project back into compliance to the extent feasible. If the client fails
to re-establish compliance within an agreed grace period, the EPFI reserves the right to exercise remedies,
✓✡ ✢☎✂✡✚✟✞✆✞✟ ✓✙✙✆☎✙✆✚✓☛✞✏✑
Principle 9 (Independent Monitoring and Reporting)
✒✭☎ ✓✡✡✞✡✡ ✍✆☎✜✞✢☛ ✢☎✝✙✔✚✓✂✢✞ ✥✚☛✣ ☛✣✞ ✤✦✧✓☛☎✆ ✍✆✚✂✢✚✙✔✞✡ ✓✂✟ ✞✂✡✧✆✞ ☎✂✕☎✚✂✕ ✝☎✂✚☛☎✆✚✂✕ ✓✂✟ ✆✞✙☎✆☛✚✂✕
after Financial Close and over the life of the loan, the EPFI will, for all Category A and, as appropriate,
Category B Projects, require the appointment of an Independent Environmental and Social Consultant, or
require that the client retain qualified and experienced external experts to verify its monitoring information
✥✣✚✢✣ ✥☎✧✔✟ ✩✞ ✡✣✓✆✞✟ ✥✚☛✣ ☛✣✞ ✤✍✌✁✏✑
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 34
Principle 10 (EPFI Reporting)
✁✂✄☎ ✆✝✝ ✞✆✟✠✡✄☎☛ ☞ ✆✌✍✎ ✆✏ ✆✑✑☎✄✑☎✒✆✟✠✎ ✞✆✟✠✡✄☎☛ ✓ ✔☎✄✕✠✖✟✏✗
✘ The client will ensure that, at a minimum, a summary of the ESIA is accessible and available online.
✘ The client will publicly report GHG emission levels (combined Scope 1 and Scope 2 Emissions) during
the operational phase for Projects emitting over 100,000 tonnes of CO2 equivalent annually. Refer to
Annex A for detailed requirements on GHG emissions reporting.
The EPFI will report publicly, at least annually, on transactions that have reached Financial Close and on
✒✟✏ ✙✚✛✆✟✄☎ ✔☎✒✌✖✒✑✝✠✏ ✒✜✑✝✠✜✠✌✟✆✟✒✄✌ ✑☎✄✖✠✏✏✠✏ ✆✌✍ ✠✢✑✠☎✒✠✌✖✠✎ ✟✆✣✒✌✡ ✒✌✟✄ ✆✖✖✄✛✌✟ ✆✑✑☎✄✑☎✒✆✟✠✤✥
C.3 IFC Performance Standards
The International Finance Corporation (IFC) Performance Standards on Environmental and Social ✦✧★✩✪✫✬✪✭✫✮✫✩✯✰ ✪★ ✱✲ ✳✪✬✧✪✴✯ ✵✶✷✵✰ ✸✹✲✫✬✹ ✩✺✹ ✻✮✫✹✬✩✼★ ✴✱✮✹★ ✪✬✸ ✴✹★✽✱✬★✫✭✫✮✫✩✫✹★ ✲✱✴ ✾✪✬✪✿✫✬✿ ✩✺✹✫✴ ✽✴✱❀✹✻✩★ ✪✬✸
the requirements for receiving and retaining IFC support. They are also relevant to other institutions applying the Equator Principles when making project financing decisions.
❁✺✹ ❂✹✴✲✱✴✾✪✬✻✹ ✦✩✪✬✸✪✴✸★ ✴✹✽✴✹★✹✬✩ ✩✺✹ ❃✽✱✮✫✻✯ ✲✴✪✾✹❄✱✴❅❆ ✲✱✴ ✩✺✹ ❇✦❈❉ ✪✬✸ ★✧★✩✪✫✬✪✭✮✹ ★✱✻✫✪✮ ✪✬✸
environmental management for the Project, whereas the IFC EHS Guidelines provide guidance on general and industry good practice as well as recommended numerical limits for emissions to the atmosphere, noise, liquid and solid wastes, hazardous wastes, health and safety, and other aspects of development projects.
Performance Standard 1, Assessment and Management of Environmental and Social Risks and Impacts, establishes the importance of:
✘ integrated assessment to identify the social and environmental impacts, risks, and opportunities of projects;
✘ effective community engagement through disclosure of project-related information and consultation with local communities on matters that directly affect them; and
✘ t✺✹ ✻✮✫✹✬✩✼★ ✾✪✬✪✿✹✾✹✬✩ ✱✲ ★✱✻✫✪✮ ✪✬✸ ✹✬❊✫✴✱✬✾✹✬✩✪✮ ✽✹✴✲✱✴✾✪✬✻✹ ✩✺✴✱✧✿✺✱ut the life of the project.
Performance Standards 2 through 8, listed below, establish requirements to avoid, reduce, mitigate or compensate for impacts on people and the environment, and to improve conditions where appropriate.
✘ Performance Standard 2: Labor and Working Conditions;
✘ Performance Standard 3: Resource Efficiency and Pollution Prevention;
✘ Performance Standard 4: Community Health, Safety, and Security
✘ Performance Standard 5: Land Acquisition and Involuntary Resettlement;
✘ Performance Standard 6: Biodiversity Conservation and Sustainable Management of Living Natural Resources;
✘ Performance Standard 7: Indigenous Peoples; and
✘ Performance Standard 8: Cultural Heritage.
While all relevant social and environmental risks and potential impacts should be considered as part of the assessment, Performance Standards 2 through 8 describe potential social and environmental impacts that require particular attention in emerging markets. Where social or environmental impacts are anticipated, the client is required to manage them through its Social and Environmental Management System consistent with Performance Standard 1.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 35
C.4 General and Industry Specific EHS Guidelines
In addition to the performance standards, the World Bank Group (WBG) has developed Environmental, Health and Safety (EHS) Guidelines covering both general and industry specific issues. The EHS Guidelines contain the performance levels and measures that are normally acceptable to WBG and are generally considered to be achievable in new facilities at reasonable costs by existing technology. The environmental assessment process may recommend alternative (higher or lower) levels or measures, which, if acceptable to the financiers, become project or site-specific requirements.
In general, when host country regulations differ from the levels and measures presented in the EHS Guidelines, projects are expected to achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, a full and detailed justification for any proposed alternatives is needed as part of the site-specific environmental assessment. This justification should demonstrate that the choice for any alternate performance levels is protective of human health and the environment.
C.5 Indonesian Regulatory Framework
The Indonesian legal system is a hierarchal system, where National Regulations (Acts and National Government Regulations) act as the governing regulation, which are translated into implementing regulations and technical standards at lower levels of the government system (as stated on Law No. 12 of 2011 regarding formation of legislation). The requirements and standards in each regulation must be kept consistent at different levels of the government system, but should there be conflicting standards, the higher level regulation takes precedence.
At provincial level, Governor and provincial government can set up local government standards in the form of Governor Decrees and Provincial Local Government Regulations. These regulations apply only within the subject provincial jurisdiction. The Governor and/or provincial local government can set stricter environmental standards than those set at a National level. In such cases, the stricter standards shall be followed.
The various levels of government of Indonesia, including the provincial and local government agencies, that have some jurisdiction or control over the power plant activities, transmission line and gas pipeline include:
✁ National Level: Ministry of Environment and Forestry (MOEFO);
✁ Province Level: The Province of Riau; and
✁ Regency and City Level: Power plant and transmission line - Environmental Agency of Pekanbaru City (DLH ✂ Kota Pekanbaru) and gas pipeline the Siak Regency and Pekanbaru City.
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 36
Appendix D. ESIA and AMDAL Schedule
ID Task
M ode
Task Name Durat ion Start Finish
1 Phase 1 - Scoping Study 67 days M on 12/ 06/ 17Tue 19/ 09/ 17
2 Site Assumed to be Site 2 0 days Mon 12/ 06/ 17 Mon 12/ 06/ 17
3 Site confirmed 0 days Tue 20/ 06/ 17 Tue 20/ 06/ 17
4 Review of background information 2 wks Mon 12/ 06/ 17 Fri 23/ 06/ 17
5 Draft of Project Descript ion - from OE team 2 wks Mon 12/ 06/ 17 Fri 23/ 06/ 17
6 Site visit 1 wk Mon 19/ 06/ 17 Fri 23/ 06/ 17
7 Stakeholder mapping 2 wks Mon 12/ 06/ 17 Fri 23/ 06/ 17
8 Draft Stakeholder Engagement Plan issued 0 days Fri 23/ 06/ 17 Fri 23/ 06/ 17
9 Review stakeholder engagament plan 1 wk M on 3/ 07/ 17 Fri 7/ 07/ 17
10 Initial Community engagement 10 days Mon 28/ 08/ 17 Fri 8/ 09/ 17
11 Land acquisit ion review 1 wk Mon 21/ 08/ 17 Mon 28/ 08/ 17
12 Risk assessment 3 days Mon 11/ 09/ 17 Wed 13/ 09/ 17
13 Scoping Study report issued 5 days Wed 13/ 09/ 17 Tue 19/ 09/ 17
14 Principal Permit in Place 0 days Mon 12/ 06/ 17 Mon 12/ 06/ 17
15 Location Permit in Place 0 days Mon 12/ 06/ 17 Mon 12/ 06/ 17
16 Spatial Plan Compliance confirmed 0 days Mon 12/ 06/ 17 Mon 12/ 06/ 17
17 UKL-UPL for gas supply pipeline 85 days M on 11/ 09/ 17Tue 16/ 01/ 18
18 Preparation of UKL-UPL for gas supply pipeline 2 mons Mon 11/ 09/ 17 Fri 3/ 11/ 17
19 Review and submission of UKL-UPL for gas supply 2 mons M on 6/ 11/ 17 Tue 9/ 01/ 18
20 Pipeline UKL/ UPL approved 0 days Tue 9/ 01/ 18 Tue 9/ 01/ 18
21 Finalise Environmental permit 1 wk Wed 10/ 01/ 18 Tue 16/ 01/ 18
22 Environmnetal permit issued 0 days Tue 16/ 01/ 18 Tue 16/ 01/ 18
23 UKL-UPL for 150 kV Transmission Line 85 days M on 11/ 09/ 17Tue 16/ 01/ 18
24 Preparation of UKL-UPL for 150 kV transmission line 2 mons Mon 11/ 09/ 17 Fri 3/ 11/ 17
25 Review and submission of UKL-UPL for 150 kV 2 mons M on 6/ 11/ 17 Tue 9/ 01/ 18
26 Transmission line UKL/ UPL approved 0 days Tue 9/ 01/ 18 Tue 9/ 01/ 18
27 Finalise Environmental permit 1 wk Wed 10/ 01/ 18 Tue 16/ 01/ 18
28 Environmnetal permit issued 0 days Tue 16/ 01/ 18 Tue 16/ 01/ 18
29 KA ANDAL for Power Plant 43 days M on 4/ 09/ 17 Wed 1/ 11/ 17
30 Public notif icat ion of AMDAL 2 wks M on 4/ 09/ 17 Fri 15/ 09/ 17
31 Public consultat ion meeting 1 day Mon 18/ 09/ 17 Mon 18/ 09/ 17
32 Preparation of KA ANDAL 1 mon Tue 19/ 09/ 17 Mon 16/ 10/ 17
33 Presentation and review of KA ANDAL 12 days Tue 17/ 10/ 17 Wed 1/ 11/ 17
34 KA Andal approved 0 days Wed 1/ 11/ 17 Wed 1/ 11/ 17
35 Community Engagement 6 mons Thu 2/ 11/ 17 Fri 27/ 04/ 18
36 ESIA Sampling 107 days M on 12/ 06/ 17Tue 14/ 11/ 17
37 Screening assessment to identify locat ions to sample 2 wks Mon 19/ 06/ 17 Fri 7/ 07/ 17
38 Dry Season Sampling 92 days M on 10/ 07/ 17Tue 14/ 11/ 17
39 Air qualit y - 1 week / month - two or three t imes 3 mons Mon 10/ 07/ 17 Fri 29/ 09/ 17
40 River Water Sampling 2 mons Wed 20/ 09/ 17 Tue 14/ 11/ 17
41 Other sampling - dry season 2 mons Wed 20/ 09/ 17 Tue 14/ 11/ 17
42 Determine what wet season sampling required 0 days Tue 14/ 11/ 17 Tue 14/ 11/ 17
43 Wet Season Sampling 0 days M on 12/ 06/ 17M on 12/ 06/ 17
44 As required 0 mons Mon 12/ 06/ 17 Mon 12/ 06/ 17
45 As Required 0 mons Mon 12/ 06/ 17 Mon 12/ 06/ 17
46 AM DAL Sampling 40 days Thu 2/ 11/ 17 Fri 5/ 01/ 18
47 Air quality 1 mon Thu 2/ 11/ 17 Wed 29/ 11/ 17
48 River Water Sampling 2 mons Thu 2/ 11/ 17 Fri 5/ 01/ 18
49 Background noise measurements 1 wk Thu 16/ 11/ 17 Wed 22/ 11/ 17
50 Other sampling 2 mons Thu 2/ 11/ 17 Fri 5/ 01/ 18
51 Technical Studies for AM DAL and ESIA 120 days Thu 2/ 11/ 17 Fri 27/ 04/ 18
52 Project Update project descript ion 4 wks Thu 2/ 11/ 17 Wed 29/ 11/ 17
53 Technical specialist assessment 4 wks Thu 2/ 11/ 17 Wed 29/ 11/ 17
54 Dispersion modelling 1 mon Thu 2/ 11/ 17 Wed 29/ 11/ 17
55 Noise Modelling 1 mon Thu 2/ 11/ 17 Wed 29/ 11/ 17
56 Social Impact Assessment 1 mon Thu 2/ 11/ 17 Wed 29/ 11/ 17
57 Community health, safety, and security 20 days Thu 2/ 11/ 17 Wed 29/ 11/ 17
58 Process safety and working condit ions 2 wks Thu 16/ 11/ 17 Wed 29/ 11/ 17
59 Preparation of Draft ESIA 1 mon Thu 30/ 11/ 17 Fri 5/ 01/ 18
60 Develop Framework ESM S 40 days Thu 30/ 11/ 17 Fri 2/ 02/ 18
61 Develop ESMP 40 days Thu 30/ 11/ 17 Fri 2/ 02/ 18
62 ESIA Exhibit 4 mons M on 8/ 01/ 18 Fri 27/ 04/ 18
63 ESIA Approved 0 days Fri 27/ 04/ 18 Fri 27/ 04/ 18
64 ANDAL & RKL-RPL for Power Plant 81 days Thu 30/ 11/ 17 M on 2/ 04/ 18
65 Preparation of ANDAL, RKL, RPL 2 mons Thu 30/ 11/ 17 Fri 2/ 02/ 18
66 Submission of AMDAL 0 days Fri 2/ 02/ 18 Fri 2/ 02/ 18
67 Review by AM DAL Commit tee 20 days M on 5/ 02/ 18 Fri 2/ 03/ 18
68 AM DAL Hearing 1 day M on 5/ 03/ 18 M on 5/ 03/ 18
69 Amdal Approved 0 days M on 5/ 03/ 18 M on 5/ 03/ 18
70 Secure Environmental Permits 1 mon Tue 6/ 03/ 18 M on 2/ 04/ 18
71 Environmental Permit Issued 0 mons M on 2/ 04/ 18 M on 2/ 04/ 18
12/ 06
20/ 06
23/ 06
12/ 06
12/ 06
12/ 06
9/ 01
16/ 01
9/ 01
16/ 01
1/ 11
14/ 11
12/ 06
12/ 06
12/ 06
27/ 04
2/ 02
5/ 03
2/ 04
10/ 04 29/ 05 17/ 07 4/ 09 23/ 10 11/12 29/01 19/ 03 7/05
1 M ay 11 August 21 November 1 M arch 11 June
Task
Split
Environmental and Social Impact Assessment �
Scoping Report
AM039100-400-GN-RPT-1004 37
Appendix E. Water Balance Diagram
�✁✂✄☎✆✂✝✞☎✟ ✠ ✡✆✞☛✝
☞✌✍✎✌ ✏✑✎✒ ✓✔☎✕✖✡☎✕✟✑✗✘✑✒✎✙ ✍✗✒✏✍✎✙ ✚✂✛
✒✒✌✎✍☛✞✆� ☛✞✜✢✝✞✟✜ ✌✗✍✍✣✎✙ ✘✎✏
✍✏✎✙
✤✂✞✥ ✆✞✁�✆✒✑✌✎✏ ✒✑✌✎✏ ✒✑✌✎✏ ✒✑✒✎✙ ✒✣✌✎✦ ✦✎✦ ✦✎✦ ✦✎✣ ✧☎✟✤★✩�✆✤✌✗✌✣✒ ✌✗✌✣✒✎✙ ✌✗✌✣✒✎✙ ✌✗✘✍☞✎✙ ✌✗✒✘✒✎✙ ✍✑✏✎✙ ✍✑✏✎✙ ✍✏✙✎✙
✚✍ ✪ ✍✘✗✘✙✙ ✫✬✛ ✚✍ ✪ ✍✙✙ ✫✒✛ ✚✍ ✪ ✍✗✒✏✙ ✫✬✛ ✚ ✍ ✪ ✏✙✙ ✫✒✛
✏✎✏ ✒✒✦✎✙ ✘✎✏✍✒✍✎✙ ✒✒✦✎✙ ✍✏✎✙
✡✞✤✄☎✤✂✔ ✑✎✏ ✍✎✙ ✚✓✛ ✍✎✏ ✍✎✏ ✍✎✏ ✧☎✟✤★✩�✆✤✚✧✂✥�✛ ✍✒☞✎✙ ✍✎✙ ✍☞✎✙ ✍☞✎✙ ✍☞✎✙
✏✎✑ ✢✆✤✜ ✓✔☎✕✡☎✕✟✑✘✎✙ ✭★�✟✧✢✞✟✜
✍✎✦ ✤�✆✁✞✧� ✕✂✝�✆✍✏✎✙ ✧☎✟✤★✩�✆✤
✑✎✏ ☎✞✔✮ ✡✆✂✞✟✤ ✍✙✎✙ ✡✞✤✄☎✤✂✔✍✒☞ ✚✄✆�✧✞✄✞✝✂✝✞☎✟✛ ✍☞✙✎✙ ✚☎✞✔✛
✚✓✛ ✍✎✙✍✎✙
✓✔☎✕✖✡☎✕✟ ☛✆☎✩ ✧✯✝ ✏✑✎✒ ✍✙✎✙✚✂✛ ✍✗✒✏✍✎✙ ✍☞✙✎✙
✞✟✝�✆✩✞✝✝�✟✝✔✮ ✏✒✎✙ ✏✒✎✙ ✏✒✎✙ ✍✑✣✎✘ ✤✂✞✥ ✆✞✁�✆✍✑✙ ✫✒✯✧✮✧✔� ✍✑✙✎✙ ✑✒✣✎✌ ✑✒✣✎✌ ✑☞✣✎✌ ✍✗✦✘✏✎✌
✚✍ ✪ ✍✘✙ ✫✬✛ ✚✍ ✪ ✑✣✙ ✫✬✛ ✚✍ ✪ ✒✙ ✫✬✛
✍✙✎✙✍✙✎✙
✍✍✎✑✍✒✌✎✌
✢✆✤✜ ✓✔☎✕✡☎✕✟ ✚✭★�✟✧✢�✡✛ ✍✎✏ ✍✎✏✍☞✎✙ ✍☞✎✙
✰ ✱✲✳✴✵✶✳✷✸✱✲ ✹✳✺✳✻✼✽ ✾ ✿✳✺✳❀❁❁
✔❂❃❂❄❅❆❇ ❈❉❊❋ ●❍■❉ ❏❈❉❏❍❈❉● ❈❉❊❑❉▲❉● ❍❏❏❈▼❊❉●
✆◆❖ ✕◆P❂◗ ❘❙❚❯❱❲❳ ❨
✝◗❂◆P❂❅ ✕◆P❂◗
✕◆❆P❂ ✕◆P❂◗ ✚☎❩❬❭✗ ✤◆❄❩P◆◗❭✛
✟❪P❂❆❇✍✎ ✡❂❆❩❃❄ ✧❪❄❅❩P❩❪❄ ❇ ✓✩✧✆ ✍✙✙❫ ✔❪◆❅ ◆P ✆✤✧ ✧❪❄❅❩P❩❪❄❆ ✚☞✌✝✗ ✌✙❫ ✆✢✗ ✍✎✙✍✙ ❴◆◗✛☞✎ ✝❵❂ ❛◆❜◆❛❩P❭ ❪❝ ❅❂✫❩❄❂◗◆❬❩❞◆P❩❪❄ ❩❆ ❂❆P❩✫◆P❂❅ ❴❭ ☞✎✙ ❫ ❪❝ ❆P❂◆✫ ❃❂❄❂◗◆P❩❪❄ ❝❬❪❖ ◆P ❴◆❆❂ ❬❪◆❅✒✎ ✝❵❂ ◗◆❖ ❖◆P❂◗ ◗❂❆❂◗❡❪❩◗ ❩❆ ❆❩❞❂❅ ❴◆❆❂❅ ❪❄ ☞ ❅◆❭❆ ❝❢❬❬ ❬❪◆❅ ❪❜❂◗◆P❩❪❄✎✣✎ ☛❬❪❖ ◗◆P❂ ❣
✏✎ ✝❵❂ ❅❂P◆❩❬❆ ◆◗❂ ❆❢❴❤❂❛P P❪ ❛❵◆❄❃❂ ◆❆ ❜❂◗ ❅❂P◆❩❬ ❅❂❆❩❃❄ ❩❄❝❪◗✫◆P❩❪❄✎
✐❥❦ ❧❥ ♠♥♦♣q rst♦✉ rst♦✉ ❧❥❧✉ ✈✉✇① ②
③④⑤⑥ ⑦⑧⑨⑩⑤❶❷ ⑨❶❸ ❹④❺ ❻❼❶❹❺❶❹⑥ ❹④❺⑧❺ ❼❶ ⑨⑧❺ ❹④❺ ❽⑧❼❽❺⑧❹❾ ❿❼❹❹❺ ➀➁➂➃ ➂❼❽❾⑤❶❷➄ ➅⑥❺➄ ❻❼➆➆➅❶⑤❻⑨❹⑤❼❶ ⑩⑤❹④❼➅❹ ⑨❶❾ ❽⑧⑤❼⑧ ⑩⑧⑤❹❹❺❶ ❽❺⑧➆⑤⑥⑥⑤❼❶ ⑨⑧❺ ➇❼⑧➈⑤❸❸❺❶
➉ ➉
➊ ➊
➋ ➌ ➍ ➎ ➏ ➐ ➑ ➒
➓ ➓
➔ ➔
→ →
➣↔↕➙ ➛➜➝➝➞➟➠➡➢➤➥ ➦➝➝ ➝➧➨➩➫➭➯
✹➲➲✵➳➵ ➸➺➻ ➼➻➺➽➺➲➾➚
➪
●❉➶➹❈❑❏■❑▼➘
➴➷➬ ➮➬➱✃❐❒❐❮❰➬Ï
ÐÑÒ Ó❚ÔÕÖ×ØÙÚÙÛÜÙÝÝÞ
➪
P✯❵ ✚❵❪❢◗❬❭ ✫◆✪✎✛ ❳ßàáâ Û×ãäÕ Ü×å×æçä èÖ×éÕ×ÚêÕ×Û Û×ãäÕ ÕäëäÕìíÖÕ îíæèïP✯❅◆❭ ✚◆❡❂✎✛
Õëç êÞÝÝð éã åñòóï
➒➋ ➌ ➍ ➎ ➏ ➐ ➑
ôõö÷ô øùú÷ô õûúùü÷ ôùø øùú÷ôô÷ý÷ôöþõô ÿ�þû✁✂
ôùø øùú÷ô✄☎ùôõ✆õ÷ô ✝ �þû✁
�ô÷ýý✞ô÷✆õ☎ú÷ôÿ✟ ✠ ✡☛☛☞✂
øùú÷ô úô÷ùú✌÷ûú�☎ùûú
ÿ✟✍✎ú✏✌✍�✂ÿ✟ ✠ ✡☛☛☞✂
�þúù✍☎÷ øù÷ôúô÷ùú✌÷ûú
✁÷✌õû✑ øùú÷ôýúþôù✒÷ úùûü
✓✔✁ôþ✕�û÷✞✌ùúõ✄úùûü
✄þþ☎õû✒ úþø÷ô
ú✓õ✄ü÷û÷ôÿ✡ ✖ ✡☛☛☞✂
✁÷✓✔✁ôùúþôÿ✡ ✖ ✡☛☛☞✂
ûþô✌ù☎øùýú÷øùú÷ô �þû✁
øùýú÷øùú÷ôúô÷ùú✌÷û ý✔ýú÷✌
øùýú÷øùú÷ô✆õûù☎ ✆õ☎ú÷ôÿ✟ ✠ ✡☛☛☞✂
✆õûù☎ ✁õý�þýù☎�þû✁
ù✍ûþô✌ù☎ øùýú÷øùú÷ô �þû✁
þõ☎✔øùýú÷øùú÷ô �þû✁ÿ✡ ✠ ✗☛ ✘✎✂
þõ☎ ✝øùú÷ôý÷�ùôùúþôÿ✡ ✠ ✡☛☛☞✂
ý÷øù✒÷ úô÷ùú✌÷ûúý✔ýú÷✌
ý÷ôöõ✄÷ øùú÷ôúùûü
Volume 5: Technical Appendices
3
AM039100-400-GN-RPT-1014
Appendix B. Detailed Process Description
Riau 275 MW Gas Combined Cycle Pow er Plant IPP -ESIA
Medco Ratch Power Riau
Technical Report – Process Descript ion
AM039100-400-GN-RPT-1002 | 1
DATE – 17 May 2018
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
2
AM039100-400-GN-RPT-1002 Rev 1
Riau 275 MW Gas Combined Cycle Power Plant IPP - ESIA
Project no: AM039100
Document title: Process Description
Document No.: AM039100-400-GN-RPT-1002
Revision: 1
Date: 17 May 2018
Client name: Medco Ratch Power Riau
Project manager: Eamonn Morrissey
Author: Eamonn Morrissey, Candra Gusri, Gandy Iswara, A Andy, others
Jacobs New Zealand Limited
Level 3, 86 Customhouse Quay,PO Box 10-283Wellington, New Zealand
www.jacobs.com
© Copyright 2018 Jacobs New Zealand Limited. The concepts and information contained in this document are the property of Jacobs. Use or
copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This report has been prepared on behalf of, and for the exclusive use of Jacobs’ Client, and is subject to, and issued in accordance with, the
provisions of the contract between Jacobs and the Client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this report by any third party.
Document history and status
Revision Date Description By Review Approved
0 18/04/2018 For ESIA Jacobs Bruce Clarke Eamonn Morrissey
1 17 May 2018 Revised Transmission Line Route Jacobs Eamonn Morrissey Eamonn Morrissey
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
3
AM039100-400-GN-RPT-1002 Rev 1
Contents
Abbreviations ...................................................................................................................................................1
1. Introduction ..........................................................................................................................................3
1.1 Purpose .................................................................................................................................................3
1.2 Background ............................................................................................................................................3
2. Location and Environmental Setting ...................................................................................................4
2.1 Site location ...........................................................................................................................................4
2.2 Environmental Setting ............................................................................................................................4
2.3 Socio-economic Setting ..........................................................................................................................5
2.4 Project Land Requirements ....................................................................................................................5
3. Project Schedule ..................................................................................................................................7
3.1 Project stages ........................................................................................................................................7
3.2 Project Timescales .................................................................................................................................7
4. Power Plant Pre-Construction Works .................................................................................................8
4.1 Introduction ............................................................................................................................................8
4.2 Contractor Selection ...............................................................................................................................8
4.3 Field surveys, permitting and land acquisition .........................................................................................8
5. Power Plant and Transmission Line Construction .............................................................................9
5.1 Introduction ............................................................................................................................................9
5.2 Site clearance, levelling and general preparation ....................................................................................9
5.3 Construction of Access Road ............................................................................................................... 10
5.4 Power plant and switchyard construction, including construction of water pipelines (to and fromsite)...................................................................................................................................................... 10
5.5 Transmission line construction ............................................................................................................. 12
5.6 Commissioning .................................................................................................................................... 12
5.7 Construction Workforce and Equipment................................................................................................ 13
5.8 HSE precautions during construction .................................................................................................... 13
5.9 Construction Phase Noise .................................................................................................................... 14
5.10 Transportation Impacts ......................................................................................................................... 14
6. Plant Operation .................................................................................................................................. 15
6.1 Introduction .......................................................................................................................................... 15
6.2 General plant description...................................................................................................................... 15
6.3 General process description ................................................................................................................. 16
6.4 Gas Turbine Generators ....................................................................................................................... 16
6.5 Heat Recovery Steam Generator (HRSG) ............................................................................................ 17
6.6 Steam Turbine and condenser ............................................................................................................. 17
6.7 Major Balance of Plant Systems ........................................................................................................... 18
6.8 Labour requirements ............................................................................................................................ 23
7. Transmission Line ............................................................................................................................. 24
7.1 Introduction .......................................................................................................................................... 24
7.2 Transmission Line Route ...................................................................................................................... 24
7.3 Pre-Construction and Field Surveys ..................................................................................................... 25
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
4
AM039100-400-GN-RPT-1002 Rev 1
7.4 Construction ......................................................................................................................................... 26
7.5 Operation ............................................................................................................................................. 28
8. Gas Pipeline ....................................................................................................................................... 29
8.1 General ................................................................................................................................................ 29
8.2 Pipeline Route...................................................................................................................................... 29
8.3 Construction ......................................................................................................................................... 30
8.4 Operation ............................................................................................................................................. 32
9. Power Plant Resource Requirements ............................................................................................... 33
9.1 Natural Gas .......................................................................................................................................... 33
9.2 Water ................................................................................................................................................... 33
10. Power Plant Environmental Discharges ........................................................................................... 35
10.1 Exhaust Stack Emissions ..................................................................................................................... 35
10.2 Emissions to air from the cooling tower................................................................................................. 36
10.3 Other Air Emissions ............................................................................................................................. 36
10.4 Liquid Effluents .................................................................................................................................... 37
10.5 Noise emissions ................................................................................................................................... 40
10.6 Solid Waste management .................................................................................................................... 41
10.7 Hazardous and toxic substances .......................................................................................................... 41
Power Plant Site Location and Layout Drawings .................................................................... 43
Water Flow / Balance Diagram and Other Water Related Drawings and Information ............ 44
Site Investigation ...................................................................................................................... 45
Preliminary Labour Mobilisation Schedule ............................................................................. 46
Preliminary Transportation Plan .............................................................................................. 47
Gas Pipeline Sample Construction Execution Plan and other information ............................ 48
Station Staffing and Organisation Chart ................................................................................. 49
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
5
AM039100-400-GN-RPT-1002 Rev 1
Important note about your report
The sole purpose of this report and the associated services performed by Jacobs is to provide the processdescription for the Project in accordance with the scope of services set out in the contract between Jacobs andthe Client. That scope of services, as described in this report, was developed with the Client.
In preparing this report, Jacobs has relied upon, and presumed accurate, any information (or confirmation of theabsence thereof) provided by the Client and/or from other sources. Except as otherwise stated in the report,Jacobs has not attempted to verify the accuracy or completeness of any such information. If the information issubsequently determined to be false, inaccurate or incomplete then it is possible that our observations andconclusions as expressed in this report may change.
Jacobs derived the data in this report from information sourced from the Client (if any) and/or available in thepublic domain at the time or times outlined in this report. The passage of time, manifestation of latent conditionsor impacts of future events may require further examination of the project and subsequent data analysis, and re-evaluation of the data, findings, observations and conclusions expressed in this report. Jacobs has preparedthis report in accordance with the usual care and thoroughness of the consulting profession, for the solepurpose described above and by reference to applicable standards, guidelines, procedures and practices at thedate of issue of this report. For the reasons outlined above, however, no other warranty or guarantee, whetherexpressed or implied, is made as to the data, observations and findings expressed in this report, to the extentpermitted by law.
This report should be read in full and no excerpts are to be taken as representative of the findings. Noresponsibility is accepted by Jacobs for use of any part of this report in any other context.
The report is based on information supplied by Jacobs’ Client and from information held by Jacobs for theProject. This report has been prepared on behalf of, and for the exclusive use of, Jacobs’ Client, and is subjectto, and issued in accordance with, the provisions of the contract between Jacobs and the Client. Jacobs acceptsno liability or responsibility whatsoever for, or in respect of, any use of, or reliance upon, this report by any thirdparty.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
1
AM039100-400-GN-RPT-1002 Rev 1
Abbreviations
AMDAL Analisis Mengenai Dampak Lingkungan
amsl Above Mean Sea Level
CEMP Construction Environmental Management Plan
CEMS Continuous Environmental Monitoring Station
CCGT Combined cycle gas turbine
CFPS Coal fired power station
CPI Corrugated plate interceptor
CRH Cold reheat
dB decibels
EPC Engineering, procurement and construction
ESIA Environmental and Social Impact Assessment
GFPP Gas fired power plant
GT / GTG Gas turbine / Gas turbine generator
H&SP Health and Safety Plant
ha Hectare
HHV High Heating Value
HP High pressure
HRSG Heat recovery steam generator
H&SP Health and Safety Plan
IP Intermediate pressure
km Kilometres
kg/s Kilograms per second
kV Kilovolt
L litre
lp Low pressure
m Metres
mg/L Milligrams per litre
mm millimetre
m/s Metres per second
m3/h Metres cubed per hour
mAMSL Meters above mean sea level
MRPR Medco Ratch Power Riau
MW Megawatt
NFPA National fire protection association (of America)
NOx Oxides of Nitrogen
OHL Overhead Line
OPGW Optical Ground Wire
PLN Perusahaan Listrik Negara
PPA Power Purchase Agreement
ppmvd Part per million by volume, dry
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
2
AM039100-400-GN-RPT-1002 Rev 1
RoW Right of way
SOx Oxides of sulphur, as SO2
ST / STG Steam turbine / Steam turbine generator
T Tonnes
PT TGI PT Transportasi Gas Indonesia
UKL/UPL Upaya Pengelolaan Lingkungan dan Upaya Pemantauan Lingkungan
wt/vol Weight per volume
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
3
AM039100-400-GN-RPT-1002 Rev 1
1. Introduction
1.1 Purpose
This document provides a process description of the construction and operation of the Riau 275MW CombinedCycle Gas Fired Power Plant IPP Project (Riau 275MW GPPP). The project consists of a 275MW combinedcycle power plant and ancillary facilities, a 40 km long 12-inch gas pipeline, and a switchyard and 150kVtransmission line - collectively comprising the “Project”.
This report provides a brief description of the location and environmental setting, followed by key details of theproposed design in respect to construction and operation of the Project. This report is one of several technicalreports prepared for the Environmental and Social Impacts Assessment (ESIA) and other permitting workassociated with the Project. It is based on preliminary engineering work, including the EPC Contractor’s (LotteE&C) preliminary design of the power plant.
1.2 Background
The Riau 275MW GFPP will be a new, greenfield power station.
The Project Sponsors (being PT Medco Power Indonesia (MEDCO) and Ratchaburi Electricity GeneratingHolding PCL (RATCH), have formed PT Medco Ratch Power Riau (MRPR) to build, own and operate the plantunder the terms of the Power Purchase Agreement (PPA) which has been agreed with PLN.
The key components of the Project include a 275MW combined cycle power plant (CCPP), a 40km long gassupply pipeline which will bring fuel to the site, a 150kV switchyard, and an approximately 750m longtransmission line to connect the power plant to the PLN grid. Once constructed, ownership of the switchyardand transmission line collectively known as the Special Facilities will be transferred to PLN. At the end of the20-year term of the PPA, PLN will take ownership of the power plant and gas supply pipeline.
The Project will be located approximately 10 km due east of Pekanbaru city, approximately 5 km south of theSiak River. The power plant and switchyard well be comfortably accommodated inside the 9 ha of land beingprocured by MRPR. The power plant is a 2 x 1 combined cycle plant, designed to deliver up to 275MW over the20-year term of the PPA. It will burn gas fuel only. It will consist of:
• 2 x GE 6F.03 gas turbine (GT) generator sets;
• 2 x supplementary fired heat recovery steam generators (HRSGs);
• 1 x steam turbine (ST) generator set;
• A wet mechanical draft cooling tower;
• Gas reception area; and
• All normal balance of plant systems.
In addition, there will be:
• a 150kV switchyard at the plant, with an approximately 750 m double-phi connection to intercept theTenayan – Pasir Putih 150 kV transmission line;
• A 40km gas pipeline running from the gas connection point at an offtake location known as SV1401 onthe main Grissik-Duri gas pipeline; and
• Water supply and discharge pipelines to and from the Siak River.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
4
AM039100-400-GN-RPT-1002 Rev 1
2. Location and Environmental Setting
2.1 Site location
The power plant site is located in the Sail Sub District, Tenayan Raya District, Pekanbaru City, and Province ofRiau.
The power plant is located approximately
• 10 km due east of the city of Pekanbaru in central Sumatra, Indonesia;
• 3 km south of the Siak River; and
• 2 km south of PLN’s 2 x 110MW RIAU Coal Fired Power Station (CFPS).
At the moment, the power plant site is part of a privately owned palm oil plantation. According to PekanbaruCity’s Spatial Plan, the land is in a zone allocated for Industrial and Warehousing use.
Drawings in Appendix A show:
• Preliminary, conceptual layout for plant and equipment on the site; and
• The setting of the Site relative to Pekanbaru City and PLN’s existing coal fired power station, along withproposed routes for connections to the Grid, existing road, Siak River, and a pipeline corridor betweenthe site and the Siak River.
2.2 Environmental Setting
2.2.1 Climate
Pekanbaru has a tropical climate. The design and general site climate conditions are provided in Table 1.
Table 1: General site ambient climate conditions
Parameter Value
Ambient air temperature range 20°C-37°C
Design ambient air temperature 28°C
Relative humidity range 40%-100%
Design Relative humidity 80%
River water temperature Approximately 30°C
Average annual rainfall Approximately 3,000 mm - rainy season betweenNovember and April
Maximum rainfall Approximately 136mm/h
Average wind speed Less than 3m/s, predominantly from the south or west
Site elevation Approximately 25 mAMSL
2.2.2 Site Investigation
MRPR has conducted a site investigation of the power plant site. The final report is provided in Appendix C andincludes a topographical map and geotechnical characteristics.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
5
AM039100-400-GN-RPT-1002 Rev 1
2.3 Socio-economic Setting
Riau province has a population of approximately 7 million people, of which approximately one million live inPekanbaru City.
The majority of the population living close to the power plant site are likely to be involved in the palm oilplantation business, fishing and farming.
The proposed site is currently part of a privately owned palm oil plantation. The palm trees appear to be around5 – 7 years old.
The closest settlement is around 2 km to the west of the site.
2.4 Project Land Requirements
MRPR plans to build the power plant and switchyard on a 9.1ha plot of land. Land surrounding the site isgenerally used for palm oil plantations.
There are no dwellings located at the power plant site so no physical relocation or resettlement of inhabitantswill be necessary.
The total land requirements for the power plant and switchyard are estimated at approximately 5.4 ha asoutlined in Table 2. Preliminary Site layout plans are provided in the Appendix A.
Table 2: Riau 275MW GFPP power plant land requirements
Riau 275 MW CCPP pow er plant la nd area requirem ents Approximate Are a, ha
Power plant and main plant buildings (GTGs, HRSGs, STG & Control Room) 1.2
Cooling tower 0.2
Balance of plant area 2.5
Switchyard (150kV) (part of the Special Facilities to be owned by PLN) 1.5
Total 5.4
During construction, there will be further land requirements for laydown areas, offices, and the constructionworkforce. The additional area estimated at a further 3.7 ha, will be within the site area, as shown on thedrawings.
There will also likely be a need for a temporary jetty to be built on or on the banks of the Siak River, expected tobe located close to PLN’s existing Tenayan Coal Fried Power Station (CFPS).
In addition, the Project will have land requirements for the water abstraction point at the River, water supplypipelines to and from the power plant site, the gas supply pipeline, and the 150kV transmission line, estimatedas shown in Table 3.
See Appendix A for details of potential off-site land requirements (excluding the gas pipeline.)
Table 3: Estimated land requirements in addition to the power plant Riau 275MW CCPP power plant – off-site arearequirements
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
6
AM039100-400-GN-RPT-1002 Rev 1
Equipme nt item Approximate dime nsions, m x m Approximate Are a, ha
River water pump house plus local building 50 x 40 0.2
Water supply and discharge pipeline corridor 6 x 3,000 1.8
Gas supply pipeline, though very little, if any, ofthis will actually need to be acquired by MRPR.Extent is to be confirmed.
MRPR may also need to acquire or gain access tosome land at the point of connection to the mainpipeline. This would be for a valve and piglaunching station.
2 x 40,000 8
Transmission Line (including 3 towers not on themain power plant site) – normally via aneasement.
25 x 1000 2.5
Transmission line towers (off the main power plantsite, straddled by transmission line)
3 x 40 x 40 3 x 0.16 ha
Access road 8 x 400 0.32
Temporary Jetty 100 x 70 0.7
It is not expected that any physical relocation or resettlement of inhabitants will be necessary as:
• There are no dwellings located at the site or along the transmission line, and
• The gas and water pipelines will run along the road reserve or within easements which will be agreedwith the affected landowners.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
7
AM039100-400-GN-RPT-1002 Rev 1
3. Project Schedule
3.1 Project stages
The Project will span three primary stages, being pre-construction, construction and operation, generally asfollows:
• Pre-construction: The pre-construction stage involves project development activities, includingselection of contractors, field surveys and permitting, and land acquisition works.
• Construction: The construction stage will involve land preparation (including site clearance, backfilling
and land drainage) followed by construction and commissioning of the power plant, gas pipeline andgrid interconnection.
• Operation: The operation stage will involve the full operation of the power plant – first of all over the 20-
year term of the PPA and then, as determined by PLN after ownership transfers to PLN.
3.2 Project Timescales
The proposed project timescales for major construction activities are provided in Table 4.
Table 4: Estimated duration (in months) of activities required for Project construction
Act ivity Est imated Durat ion (months)
Site clearance and levelling (may commence before financial close) 6 months
Gas pipeline construction 12 months
Power plant and switchyard engineering, procurement and construction 24 months
Construction of water pipelines (to and from site) 8 months
Transmission line construction 8 months
Commissioning 6 months
The total construction and commissioning time from financial close is to be 30 months.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
8
AM039100-400-GN-RPT-1002 Rev 1
4. Power Plant Pre-Construction Works
4.1 Introduction
The pre-construction stage involves project development activities, including selection of contractors, fieldsurveys and permitting, and land acquisition works.
4.2 Contractor Selection
MRPR has have already selected the main Contractors, as follows:
Table 5: Estimated duration (in months) of activities required for Project construction
Scope Cont ractor
Power Plant, switchyard, transmission line, watersupply and discharge structures and pipelines
Lotte Engineering & Construction of South Korea
Gas pipeline PT Citra Panji Manunggal (CPM) of Indonesia
These contractors will be responsible for identifying and recruiting workers with the appropriate skills andqualifications required for the construction stage of the Project.
Note: peak labour requirements for the construction of the power plant and Special Facilities will beapproximately 1,000 people, with the expectation that the local community will be able to provide the bulk of thiswork-force.
4.3 Field surveys, permitting and land acquisition
In order to collect the data required to finalise the location and design of the Project, MRPR has beenconducting field surveys of the site, including topographical survey, geological and geotechnical investigationsof the soil.
Additional surveying activities will include those necessary for securing the permits and approvals – AMDAL forthe Power Plant, UKL-UPL for the gas pipeline, UKL-UPL for the Switchyard and transmission line,Environmental and Social Impact Assessment (ESIA) for the Project.
Requirements for land acquisition will be identified as part of the process. Land will be acquired for the PowerPlant, Switchyard and transmission line. Land for the water intake and pumphouse etc. will be leased. Someland may be needed for the gas pipeline (e.g. at the point of connection to the main gas pipeline at SV1401).Otherwise, the gas pipeline will run along the road reserve, or follow easements to be agreed with any affectedlandowners.
Nor is it expected that it will be necessary to acquire land for the water supply or wastewater discharge pipelinesbecause it is anticipated that these will either follow road reserves or easements to be agreed with any affectedlandowners.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
9
AM039100-400-GN-RPT-1002 Rev 1
5. Power Plant and Transmission Line Construction
5.1 Introduction
The construction phase of the Project is scheduled to last from late early 2018 to the end of 2020.
The following stages are envisaged.
• Site clearance, levelling and general preparation;
• Construction of access road;
• Gas pipeline construction (see later section of this report);
• Power plant and switchyard construction, including construction of water pipelines (to and from site)
• Transmission line construction; and
• Commissioning.
5.2 Site clearance, levelling and general preparation
5.2.1 Site Clearance and levelling
The site area for the Power Plant and Switchyard will need to be cleared of vegetation and any debris prior tolevelling. Site clearance works will include felling, trimming, and cutting trees, and disposing of vegetation anddebris off-site. Voids and water ponds will be dried and filled with suitable material.
Vegetation, roots, debris, stones, and other materials will be removed from the areas to be stripped by mowing,grubbing, raking, etc.
Topsoil will be stripped from the surface. Excavated topsoil will be transported to and stockpiled in designatedtopsoil storage areas. Prior to being filled, any sub-grade surfaces will be freed of standing water andunsatisfactory soil materials will be removed. All unnecessary excavated materials will be transported anddeposited off-site at an approved facility.
The site will then be levelled. Ideally, the cut and fill will be balanced, to minimise the need to import or exportmaterial from the site area. Based on the site topography, preliminary estimates show that if the site elevationis set at 28m, then the cut and fill / backfilling volumes will be reasonably well balanced at approximately165,000m3 each.
Notwithstanding this, it is likely that approximately 45,000m3 of soil will need to be disposed of offsite. At 20m3
per truck, this will require 2,250 truck movements over approximately 3 months.
5.2.2 Flood Risk
According to investigations for the site originally proposed for the project, it was determined that a site level of 3mAMSL would be adequate to ensure the site would be above the 100-year return period flood level of the SiakRiver. The lowest point of the current site for the project is more than 20 mAMSL.
Therefore, the site will not be subject to flooding via the Siak River.
During the engineering stage, the site elevation will be set to ensure stormwater from adjacent propertiescannot cause the site to flood and to ensure that stormwater falling on the site does not flood neighbouring land.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
10
AM039100-400-GN-RPT-1002 Rev 1
5.3 Construction of Access Road
The construction stage includes the development of an access road which will be approximately 500 m long andrun from the main road to the north of the Site.
The access road will be a permanently sealed two-lane 8m road.
5.4 Power plant and switchyard construction, including construction of waterpipelines (to and from site)
5.4.1 Excavations
A range of excavations will be carried out at the site, primarily:
• Excavation for structures (footings and foundations);
• Excavation of ditches, gutters, and channels;
• Excavation for drainage structures; and
• Trench excavation.
Where excavated material is suitable to be used for fill and backfill, the material will be segregated andtransported to a stockpile location at the power plant site. Unless specified or directed otherwise, allunnecessary excavated materials will be transported and deposited outside the power plant site. This materialwill be disposed in a location not to disturb the environment and which is permitted by municipal authorities.
Soil on site will be deposited and compacted, and the slopes will be trimmed to ensure that the soil is stable andfree of surface depressions, and that the slopes drain freely and do not interfere with natural drainage to or fromthe surrounding area.
5.4.2 Piling
Piling will be undertaken as part of the construction activities. Piling methods will likely include pile driving andbored cast-in-place piling.
Pile driving will be used to pile the main power station foundations. Driving shall be done with fixed leads to holdthe pile firmly in position and in axial alignment with the hammer. Piles will be driven continuously and withoutinterruption to or below the calculated tip elevation to reach a driving resistance based on load test results.
Pile driving will not be carried out at night.
Bored, cast-in place piles may be used for lighter structures. With this technique, the pile hole is bored out, asteel cast is placed in the hole and the pile is formed using reinforcing steel and concrete.
Sheet piling may be used to protect shallow excavations which are normally backfilled once the equipment isinstalled.
5.4.3 Foundations
Reinforced concrete foundations and base building slabs will be prepared prior to the installation of large itemsof equipment and the erection of buildings. Concrete for the foundations and building slabs will either bebatched at the power plant site or brought on to the site in a ready-mixed form by concrete trucks. If batching onsite is selected, then sand and cement will be brought to the power plant site and stored in bins and bags nextto the batching plant. Water required for concrete batching would be approximately 45m3/day.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
11
AM039100-400-GN-RPT-1002 Rev 1
5.4.4 Equipment Installation
Once the foundations are prepared the plant equipment can be installed.
Some equipment will be installed outdoors – e.g. the gas turbine generator sets, the HRSGs, the step-uptransformers. Other equipment, including the steam turbine generator set and the condenser, will be installed inpurpose built buildings.
The Contractor is likely to pre-fabricate as much of the plant and equipment in factory conditions off-site, inorder to minimise site work. For example, the HRSG modules will likely be shipped to site complete, so that sitewelding requirements are reduced.
Normal construction processes and techniques will be used. In addition to the workers needed or the sitepreparation and civil works, the workforce will include:
• Steel erectors
• Mechanical fitters
• Pipefitters
• Welders
• Electricians
• Instrumentation technicians
• Crane-drivers
• Scaffolders
• Painters
• Labourers, and
• Support staff.
Specialists will also be necessary from time to e.g. for radiography and other non-destructive testing, and forhigh voltage work.
5.4.5 Off-site work
Off-site work associated with this stage of the project will include the following:
• The construction of the water intake at the Siak River, as well as the pipeline to take the water from theRiver to the site. Preliminary details of the proposed structures for this are included in the Appendix A.
• The construction of the water discharge pipeline, which will run alongside the water supply pipeline.
• The construction of a temporary jetty to serve as a berth for ships or barges delivering plant items andconstruction materials and equipment – e.g. the gas and steam turbines, generators, transformers,HRSG modules. The jetty will be located approximately 4km to the north of the power plant site, closeto PLN’s 2 x 110 MW coal fired plant. See Appendix A for further details of the possible location andAppendix E for the preliminary Transportation Plan.
Construction of the jetty will involve sheet piling for the “tunnel”, while rock and sandbagging will be used for thehead area. The tunnel will be dredged where required, the scope of which will depend on the exact location andlocal depth and conditions. The construction period will be approximately four months. After construction of the
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
12
AM039100-400-GN-RPT-1002 Rev 1
Project is complete and assuming there is no reason for the jetty to remain in place, it will be removed. This willtake approximately one month.
The roadway from the temporary Jetty past the CFPS and up to the power plant site is narrow in places andsome widening of or improvements to the route may also be required.
5.4.6 Landscaping
After construction and erection work are completed, the power plant site will be landscaped for visualappearance and to limit erosion from surface water during heavy rains. The upper, organic layer of soiltemporarily removed and stored during construction, will be used to provide fertile soil for landscaping, wherepossible.
5.5 Transmission line construction
The construction of the transmission line will likely be labour-intensive with simple hand tools rather thanthrough the use of cranes and/or helicopters.
The major steps are:
• Survey and tower staking;
• Construction of foundations (typically cast in place);
• Erection of towers (i.e. assembly of tower members);
• Conductor, shieldwire, and OPGW stringing;
• Clean up; and
• Testing and commissioning.
Teams can work on separate towers or line sections simultaneously if necessary to reduce the constructionschedule. However, this is unlikely to be necessary as the connection is so short.
Smaller vehicles will be used to transport materials (e.g. steel members) to and from each tower location inorder to avoid the need for large access tracks or roads.
Inspection, testing, and commissioning will follow PLN’s specification requirements.
Further details are included later in this report and the proposed connection route is shown in Appendix A.
5.6 Commissioning
After construction of the power plant is complete, the plant and equipment will be commissioned and set towork. The commissioning process involves:
• Calibrating and setting control and protection devices to ensure the safety of plant, equipment andpersonnel;
• Energising equipment for the first time;
• Checking individual components work correctly;
• Checking individual systems work correctly;
• Checking that the systems are properly integrated and work together as designed; and
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
13
AM039100-400-GN-RPT-1002 Rev 1
• Testing the plant for compliance with the EPC Contract, including for compliance with the Grid Codeand environmental requirements.
5.7 Construction Workforce and Equipment
As mentioned earlier, the labour force is expected to peak at close to 1,000, providing an estimated 10,000man-months of work. Many of the work force are likely to come from the local community.
See Appendix D for a preliminary labour mobilisation schedule for the construction of the power plant andSpecial Facilities.
A range of equipment will be used in the construction of the plant. The principal type of equipment to be usedincludes the items listed in the following table.
Table 6: Construction equipment details
Equipme nt Est imated No. units
Backhoe 5
Bulldozer 3
Trailer 2
Dump truck / Mixer truck 28
Cranes 12
Crane barge 1
Pile driver 6
Forklift 7
Welding machines 111
Electricity generators 8
Appendix D also contains further details of the proposed equipment mobilisation schedule.
5.8 HSE precautions during construction
All Contractors involved in the Project will be required to comply with all local health and safety requirements, aswell as the requirements of any environmental permits issued for the Project.
Provisions will include developing and then following Construction Environmental Management Plans (CEMPs)and Health and Safety Plans (H&SPs) to reduce the risk of harm to staff, the environment or the localcommunity. This will include drainage and sediment controls.
MRPR will monitor and supervise every contractor to ensure they are fulfilling the rights of workers inaccordance with applicable laws and regulations.
Temporary construction offices and facilities for the labour force will be erected close to the Site. This willinclude areas for
• Food preparation and consumption;
• Ablutions; and
• First aid.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
14
AM039100-400-GN-RPT-1002 Rev 1
There will also be a prayer room.
There is no plan to construct a worker’s camp at or close to the site. Lotte and its subcontractors expect to rentany accommodation necessary to house workers not from the area.
5.9 Construction Phase Noise
The major source of noise emissions will be through heavy machinery such as pile drivers, earthmovingequipment and transport vehicles.
As part of the ESIA and AMDAL process, procedures will be defined to reduce the potential for constructionnoise to impact on the community. Potential mitigation measures are likely to include
• Restricting hours of work to reduce the possibility of nuisance to neighbours;
• The use of modularisation, and encouraging the EPC Contractor to fabricate as much of the plant offsiteas possible – e.g. the HRSG harp sections may be delivered fully assembled, reducing the need forsite-work;
• Use of low noise and low vibration equipment to reduce the potential impact of piling operations; and
• Use of silencers during steam blowing exercises.
5.10 Transportation Impacts
The transportation of power station components to site via road could lead to temporary noise impacts onresidential areas due to the proximity of the roads to the houses.
A mitigation measure for the transport noise is to transport the equipment to site via barges on the Siak River.This will remove the noise impact on residents in two ways. Firstly, the jetty is further from the residents andany noise would have a lower impact. Secondly, the barges are comparatively less noisy than trucks.
General construction traffic and other deliveries will inevitably come by road from the area surrounding thePlant. In addition to traffic associated with the workforce coming to and from the site, there are likely to be inthe order of 10 light trucks and 50 to 60 heavy trucks per day, bringing equipment and material such asconcrete, rebar and construction raw materials.
As part of the CEMP, traffic management plans will be developed to minimise any potential impact on nearbyresidents, including:
• A truck wheel wash facility will be constructed to clean truck wheels prior to exiting the site in order toprevent dust and spoil being transported on to the public road. The wheel wash facility will be usedthrough-out the construction phase of the power plant. The washing facility (pit) will not connect to adrain or watercourse and therefore will not filter the water; it will be manually cleaned out as required.
• Timing of deliveries to avoid peak travel times for residents, and in particular hours when children arescheduled to be going to or returning from school.
See Appendix E for a preliminary Transportation Plan.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
15
AM039100-400-GN-RPT-1002 Rev 1
6. Plant Operation
6.1 Introduction
The section provides
• A general overview of the power plant process;
• More detailed descriptions of the main power plant components
• A general description of resource requirements and environmental impacts; and
• General information about labour requirement.
6.2 General plant description
The power plant is a 2 x 1 combined cycle plant, designed to deliver up to 275MW over the 20-year term of thePPA. It will burn natural gas fuel only. The plant will consist of:
• 2 x GE 6F.03 gas turbine (GT) generator sets
• 2 x supplementary fired heat recovery steam generators (HRSGs).
• 1 x steam turbine (ST) generator set
• A wet mechanical draft cooling tower
• Normal balance of plant systems will also be provided, including:
- Gas compression (if required) and conditioning system
- Demineralised water treatment plant to treat raw water before it is added to the water steam cycle
to make up for water lost from the cycle.
- Closed cycle cooling water system to cool plant and equipment such as lubricating oil coolers,
generator coolers, boiler feed pumps
- Systems to dose and sample the water and steam
- Compressed air system
- Fire protection system, in accordance with local requirements with scope and design generally in
accordance with NFPA 850
- Emissions monitoring system
- Drainage systems
- Overall plant distributed control system
- Metering and protection systems
- Enclosures to house the plant and equipment as required
- Control room and office space for the O&M staff
- Black start diesel generators and system
- HV switchyard.
The Appendix A includes the following conceptual drawings and information, including:
• Conceptual layout
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
16
AM039100-400-GN-RPT-1002 Rev 1
• Water balance
• Single line diagram.
6.3 General process description
In a combined cycle plant, ambient air is filtered and led to the compressor of the gas turbine, where it iscompressed. Fuel is added and combusted in the combustors and the hot gas fed to the turbine which drivesthe generator to generate electricity.
The exhaust gas leaving the turbine may still be in the order of 600°C. In an open cycle (or simple cycle) plant,the exhaust gas flows back to the atmosphere and so a good deal of useful energy is lost. However, in acombined cycle plant, the exhaust gas is fed to a HRSG and is used to generate steam. This is why acombined cycle plant is more efficient than an open cycle plant.
From the HRSG the superheated high pressure (HP) steam is fed to the high pressure section of the steamturbine where it expands before being returned to the HRSG for re-heating. The reheated steam is mixed withintermediate pressure steam also generated in the HRSG and fed to the intermediate pressure section of thesteam turbine. Steam leaving this section is fed to the low pressure section of the turbine where it issupplemented with further low pressure steam from the HRSG. All steam exhausts to the condenser where it iscondensed to water before returning to the HRSG to be converted to steam once again.
A schematic diagram of the process is provided in the figure below.
Figure 1: Schematic of General Process
6.4 Gas Turbine Generators
The gas turbine generators will be a 6F.03 model supplied by GE. This is an “F” Class, heavy duty, single shaft,industrial type of gas turbine, of proven design. Each unit will have a capacity of approximately 81MW.
The gas turbines will be equipped with lean-premix dry low NOx combustion systems. No water or diluentinjection will be necessary to control NOx emissions.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
17
AM039100-400-GN-RPT-1002 Rev 1
The turbine generators will be installed outdoors, though within acoustic, ventilated enclosures incorporating firedetection and protection facilities. They will be provided with all associated ancillary and auxiliary equipmentand systems for safe, efficient, and reliable operation. They will fire natural gas only.
6.5 Heat Recovery Steam Generator (HRSG)
The HRSGs will be triple pressure with reheat design.
In order to generate additional steam to boost power from the steam turbine from time to time, as desired byPLN, the HRSGs will be fitted with low NOx duct burners.
The HRSGs will include economizer, evaporator, and super-heater tube bank sections with finned tubing, asappropriate, to maximize heat transfer. The thermal cycle will be designed to suit the specific requirements ofthis Project.
Pressure parts will be designed, manufactured and tested in accordance with "ASME Boiler and PressureVessel Code, Section 1, Power Boilers" or equivalent. The HRSG stack height and the flue gas exit temperaturewill be sufficient to ensure adequate dispersion of the flue gases in accordance with the relevant environmentalstandards and requirements. At present, a stack height of 45m is anticipated.
The design steam conditions at full load are as follows:
Table 7: HRSG Design Steam Conditions
Parameter Unit HP IP HRH LP
Steam pressure at HRSG outlet Bar 142.0 27.9 22.0 5.3
Steam pressure at steam turbine Bar 136.7 21.3 4.8
Steam temperature at HRSG outlet °C 571 298 576 295
Steam temperature at steam turbine °C 569 314 (CRH) 574 290
Steam flow per HRSG kg/s 37.7 2 39.5 2
The HRSGs will be installed outdoors.
6.6 Steam Turbine and condenser
Steam from the two HRSGs will be combined, and fed to the steam turbine generator set to generate moreelectricity. It will be provided with all associated ancillary and auxiliary equipment and systems for safe,efficient, and reliable operation.
The steam turbine will produce approximately 126MW at the design point.
Steam will be condensed in the condenser which will be cooled using water fed from a wet mechanical draughtcooling tower.
Preliminary condenser design conditions are:
Table 8: Steam Turbine and condenser details
Parameter Unit Value
Steam pressure at inlet bar 0.0949
Steam temperature °C 44.8
Steam flow Kg/s 83.9
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
18
AM039100-400-GN-RPT-1002 Rev 1
Parameter Unit Value
Cooling water temperature increase across condenser °C 10.3
Cooling water flow Kg/s 4,756
The steam turbine generator and condenser will be installed within a building.
6.7 Major Balance of Plant Systems
6.7.1 Cooling Water Systems
The condenser will be cooled by a closed cycle cooling system with a wet (evaporative) mechanical draughtcooling tower.
In a wet tower, the cooling effect is obtained by presenting a large surface of the heated water returning fromthe condenser to the atmosphere, allowing heat loss to occur predominantly by evaporation. On this project,the mechanical draft tower will comprise a number of "cells" arranged in a line above a basin. The large surfacearea for the water will be obtained by the use of "fill", likely to consist of a plastic honeycomb or slats installed ineach cell. The heated water will descend from upper trays through the fill. Some of it (approximately 2%) willbe evaporated, and in the process, the temperature of the remaining water will be reduced. The remainingwater will be collected in a concrete basin below, and then pumped back to the condenser to condense steamonce again.
The water lost to evaporation and blowdown will have to be replaced, with make-up water extracted from theSiak River.
Ventilation through the fill to allow effective evaporation will be obtained by installing large fans at the top ofeach cell.
Preliminary cooling tower design parameters are:
Table 9: Cooling Tower parameter details
Parameter Unit Value
Cold water temperature (to the condenser) °C 31.6
Cold water temperature (from the condenser) °C 41
Water flow kg/s 5,114
A chemical dosing system will be provided to control the water quality in the cooling water system to preventfouling, scaling or corrosion. The cooling water treatment will include at least:
• Addition of an acid to the makeup water to reduce the carbonate concentration in the makeup water inorder to prevent deposition of calcium carbonate scale particularly on the condenser tubes.Alternatively, the addition of a dispersant along with acid dosing may be used, as long as the dispersanthas no adverse impacts on the environment.
• Dosing with organic biocide or NaOCl to control organic growth in the cooling system. A system capableof dosing both continuously and via shock treatment (approximately 20 minutes every 8 hours) will beprovided.
Final details will be confirmed once the river water quality and cooling tower design are confirmed.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
19
AM039100-400-GN-RPT-1002 Rev 1
6.7.2 Gas reception area
The pressure of the gas supplied to the gas turbines must be controlled to be within a set range. On arriving atthe site, the gas may be above, within or below the correct range. Therefore, the following facilities will beinstalled in order to ensure the gas pressure at the gas turbines is correct:
• Gas compressors will be installed, to boost the gas pressure if it is too low. (If it is confirmed that thegas pressure at the supply point (SV1401) will never be so low as require gas compression on site, thenthese may be removed from the scope of the project.)
• Pressure regulators will be installed to reduce the pressure on occasions when it is too high.Depending on the design, this system may need to incorporate a system to heat the gas before thepressure is reduced. Any such temperature control system is likely to use natural gas to heat water toheat the gas flowing to the plant.
Other equipment in the gas reception area will include:
• An emergency shut down valve, to isolate the plant in the event of a problem (perhaps installed as partof the gas pipeline project);
• A pig receiver station (perhaps installed as part of the gas pipeline project) which will be used to helpmaintain the cleanliness of the gas pipeline;
• A gas chromatograph to check the composition of the gas arriving at the site; and
• A system to control the pressure of the gas to be used by the HRSG supplementary firing system.
6.7.3 Water treatment
This section describes the process expected to be used for the handling and treatment of the raw water when itarrives on site. Refer to the water balance diagram in Appendix B for further details as well as the preliminaryP&ID.
Water will be taken from the Siak River for use in the power generation process.
On arrival at site, the water will enter a raw water reservoir / settling pond, be clarified and filtered, and thenstored in a filtered water tank. This initial system shall be sized to store enough water to allow the plant to runat full load for two days without and make-up – approximately 17,700 m3.
The filtration process will involve dosing with caustic soda and alum.
Preliminary details are as follows:
Table 10: Water treatment details
Parameter Descript ion / value / comm ent
Clarification and filtration technologies Clarifier+ Gravity Filter or Sand filter
Number of streams Clarifier 50% x 2
Gravity Filter 100% x 2 or
Sand filter 100% x 2
Rated capacity of each stream 160m3/h
Raw Water storage capacity 17,700m3
Potable Water System 2m3/h, Activated carbon filter + NaOCl dosing
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
20
AM039100-400-GN-RPT-1002 Rev 1
The raw river water may be dosed with chlorine (as a biocide) in order to prevent biological growth while towater is stored in the raw water reservoir – especially during outages.
Filtered water will be used
• As make-up for the cooling tower (see above);
• As make-up to the demineralised water treatment plant;
• To generate potable water; and
• As a fire water supply.
It is expected that the demineralisation plant will be a conventional ion exchange based plant with a mixed bedpolisher.
Preliminary details are as follows:
Table 11: Filtered water details
Parameter Descript ion / value / comm ent
Type Ion Exchanger
Stages of treatment Activated carbon + 2B3T ion exchange + Mixed BedPolisher
Number of Streams 2
Rated Capacity of Each Stream 12 m3/h
Demineralised water storage tank capacity 500 m3
Preliminary details for the potable water system are as follows:
Table 12: Potable water system details
Parameter Descript ion / value / comm ent
Type Ion Exchanger
Stages of treatment Activated carbon filtration plus NaOCl dosing
Capacity 2 m3/h
6.7.4 Water steam cycle chemical treatment
Chemicals will also be used to help control the chemistry of the water and steam in the water/steam cycle.Preliminary details are as follows:
Table 13: Chemical treatment details
Parameter Descript ion / value / comm ent
HRSG chemical treatment programme Ammonia, Phosphate, Carbohydrazide
Ammonia
Injection point CEP discharge & HP/IP feed pump suction (provision
Chemical strength 1% wt/vol
Dosage per litre of product water 3 mL/L
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
21
AM039100-400-GN-RPT-1002 Rev 1
Parameter Descript ion / value / comm ent
Phosphate
Injection location HRSG HP and IP drums
Chemical strength 1% wt/vol
Dosage per litre of product water 3 mL/L
Carbohydrazide or equivalent
Injection location Deaerator outlet & provision for dosing at CEPdischarge
Chemical strength 1~2% wt/vol
Usage per litre of product water 0.1 mL/L
A sampling system will monitor the quality of the water and steam in the system. The station staff will use thesample results to adjust the dosing systems, so that the chemistry is acceptable while minimising chemicalusage.
6.7.5 Wastewater treatment
The plant’s onsite wastewater treatment systems will include systems for non-clean stormwater, normalwastewater, abnormal waste water, oily waste water and sanitary water. A preliminary P&ID for the system isincluded in Appendix B.
The following systems are envisaged:
Table 14: Wastewater treatment details
System / param eter Descript ion / value / comm ent
StormwaterOily or potentially oily stormwater will drain to the oilywater pond where the oil will be separated in a CPItype separator, after which the clean water may bedischarged from Site
The design will avoid or minimise the potential forstormwater to become contaminated with chemicalsother than oil. Where this is not possible, stormwaterfrom those areas will be collected and sent to thenormal waste water pond.
Clean stormwater will be collected and either re-usedin the process – perhaps in the cooling water system,to reduce make-up water requirements – or dischargedfrom Site with the other effluents.
Oily Drains Oily drains will be sent to the oil water separator
Process drains – e.g. from the water steam cycle,the demineralisation water treatment plant,blowdown from the cooling tower
Process drains will be sent to the waste water pond forpH adjustment and further treatment before beingdischarged off site.
Compressor water wash effluents Effluents from the compressor water washing systemswill be collected in a dedicated tank to be emptied viaroad tanker and disposed of separately.
Sanitary wastewater These effluents will be treated in a package sewage
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
22
AM039100-400-GN-RPT-1002 Rev 1
System / param eter Descript ion / value / comm ent
treatment plant
6.7.6 Fire Fighting System
The plant fire detection and protection system will be designed in accordance with the local fire codes and therequirements of NFPA 850.
The following systems are envisaged:
Table 15: Firefighting details
System / param eter Descript ion / value / comm ent
Deluge systems GT-Generator Step Up Transformer
ST- Generator Step Up Transformer
Main oil tank for Black Start Diesel Generator
Unit Aux Transformer
Sprinkler systems Cable room
Workshop
Gaseous systems Electronic room
Control Room
Switchgear Room
Gas turbine enclosures
In addition to these systems, there will be
• A ring main with hydrants; and
• Portable fire extinguishers located strategically around the installation.
6.7.7 Lighting
Outdoor artificial lighting including flood lights will be installed at suitable locations. Pole mounted, high pressuresodium vapour lamp fixtures will be used for the approach and work roads. A combination of high pressuresodium vapour, fluorescent, and incandescent fixtures will be used for the turbine hall, HRSG platforms andgalleries as necessary. The illumination levels at the various locations will be maintained as stipulated ininternationally accepted codes.
A suitable number of lighting panels will be supplied and installed at the convenient locations throughout thePlant. In addition to the normal illumination scheme, an emergency AC and DC lighting scheme will be provided.
Aircraft warning lights will be provided on the chimney stack in accordance with local regulations and/or FAAstandards. The uppermost set of lamp fittings will be located as close as practicable to the top of the chimneyand further sets of twin lamp fittings will be located on the chimney as required by the applicable regulation /standard.
6.7.8 Security
The site will be enclosed by a security fence. Security guards will be employed undertaking regular securitypatrols of the boundary fence. A gatehouse will be provided and this will be located on the access road prior toentering the site.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
23
AM039100-400-GN-RPT-1002 Rev 1
6.8 Labour requirements
The operation of the plant will require approximately 60 full time employees. The expected organisation chart isincluded in the Appendix G.
Staff will receive comprehensive training during the construction phase – and ongoing training over the lifetimeof the Project.
Where possible, labour will be sourced locally.
During scheduled maintenance there will be additional temporary workers on site which can increase the totalup to approximately 200.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
24
AM039100-400-GN-RPT-1002 Rev 1
7. Transmission Line
7.1 Introduction
An approximately 750m long, 150kV overhead line transmission (OHL) will be installed. The line will include 6transmission towers and will intercept the existing transmission line between Tenayan Switchyard and the PasirPutih Switchyard via a double phi connection. See Figure 2 below for the for the proposed line route.
To minimize the use of land use between the connection point and plant switchyard, a four circuit transmissionline concept will be adopted where possible, so that the loop-in and loop-out to and from the Pasir – Putih linecan use the same towers.
The following section provides a description of the route, pre-construction, construction and operation of thetransmission line.
7.2 Transmission Line Route
Due to the short length of the proposed transmission line, no route option study will be necessary. Theproposed route will be straight forward selected based on the following criteria:
• Maximum 500m wind span, 700m weight span, and 350m basic span;
• Maximising span lengths; and
• Land under spans will be cleared as required to meet conductor clearance to ground requirement.
The transmission line will be connected to existing line by a double phi connection method depicted in thefollowing figure.
Figure 2: 150kV Double Phi Connection
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
25
AM039100-400-GN-RPT-1002 Rev 1
The land for five of the towers is currently owned by private landowners.
The estimated co-ordinates of the towers and other preliminary details are provided in the following table.
Table 16: Preliminary Details for the Towers
Tow er Number Co-ordinates Number of c irc uits Ow nership
X.1780,523mE
2 MRPR59,576mN
X.2780,568mE
2 MRPR59,589mN
X.3780,656mE
2 MRPR59,547mN
X.4780,527mE
2 MRPR59,452mN
X.5780,926mE
2Private
59,456mN
X.6780,726mE
2Private
59,222mN
X.7781,034mE
2Private
59,478mN
X.8780,937mE
2Private
59,270mN
X.9781,106mE
2Private
59,312mN
Notes:
• the route/corridor depicted above is almost finalised. The line will run in this general area. It could bethat there may need to be one or two more towers off-site, but they would be in this general area.
• TP.10, TP.11, TP.12, and TP.13 already exist and would be modified as part of the project.
The Right of Way (RoW) for the transmission line will be approximately 25m wide. The towers will requirefootings covering approximately 40m x 40m each. Tall vegetation will be trimmed in the RoW to obtain thenecessary conductor clearance of 8.5m as per SNI 04-6918-2002.
7.3 Pre-Construction and Field Surveys
Prior to construction commencing, field surveys and land acquisition works will be carried out
MRPR will conduct field surveys of the site, including topographical survey, geological and geotechnicalinvestigations of the soil, in order to collect the data required to finalise the location and design of thetransmission line. There will also be baseline survey activities for the preparation of the Environmental andSocial Impact Assessment (ESIA) and UKL-UPL for the Special Facilities.
There are no settlements or residences along the route.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
26
AM039100-400-GN-RPT-1002 Rev 1
7.4 Construction
7.4.1 General
The design and construction of the transmission line will take approximately 8 months.
The construction workforce will be approximately 50 and it is expected the bulk will come from the localcommunity. The workforce will include:
• Civil works
• Steel erectors
• Mechanical fitters
• Welders
• Electricians and linesmen
• Instrumentation technicians
• Crane-drivers
• Scaffolders
• Painters
• Labourers, and
• Support staff
The staffing schedule in Appendix D includes the workforce associated with the construction of the transmissionline.
Materials required for the construction of the transmission line include the conductors (ACSR 450mm2), earthwire, insulators, and steelwork for the tower sections. Other materials such as sand, stone, portland cementand reinforcement will be required for the foundations.
7.4.2 Erection of Towers
Erection of the lattice towers will occur once the foundations are completely hardened.
Erection is undertaken following the steps:
• Installation of the stub (foot tower) gradually section-by-section;
• Installation of a criss-cross (diagonal) tower; and
• Installation of cross arms on the tower.
The towers will be lattice type, with the following preliminary technical specifications:
• Voltage: 150kV (Max = 170kV);
• Path length: approximately 750m;
• Number of circuits: Quadra circuit;
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
27
AM039100-400-GN-RPT-1002 Rev 1
• Tower type: lattice / tower steel frame;
• High of 4-circuit towers: 40 - 49m;
• Conductor / phase: 4 x 450mm2 ACSR;
• Insulator / insulator: Ceramics
• Carrying capacity: 400MVA / circuit.
In general, the transmission towers consist of the following components:
• Stub: the bottom of the foot of the tower, mounted in conjunction with the installation of the foundationand fastened to the foundation.
• Leg: tower foot which is connected between the stub and the tower body.
• Common body: the bottom of the tower body which is connected between the leg and the top of thetower body (super structure).
• Super structure: tower upper body connected to the common body and the cross arm phase wire andlightning wire.
• Cross arm: the part of the tower which supports the insulators and conductors.
Typical 2-circuit and 4-circuit transmission tower designs are presented in the following Figures.
A typical 4-Circuit Lattice Tower Typical 2-circuit dead-end towerinterfaced to the plant gantry
Typical 2 circuit lattice tower forintercepting existing line
Figure 3: Typical 4-circuit and 2-circuit tower designs
7.4.3 Conductor Wire Stringing
Conductor wire drawing activities carried out in the following order:
• Installation of insulators and equipment;
The linked image cannot be displayed. The file may have been moved, renamed, or deleted. Verify that the
link points to the correct file and location.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
28
AM039100-400-GN-RPT-1002 Rev 1
• Stringing of the wire conductors, wire retaining lightning and ground wire; and
• Setting sag and tension.
Stringing the conductor wires between the towers will be carried out using pullies and winches. Stringing isundertaken once the insulators are mounted in place on the towers.
Stringing of conductor wires will be performed per phase, for each bundle there are two (2) wire conductors perphase. The stringing is undertaken for two (2) conductors simultaneously. Because the conductor should nottouch the ground, it is necessary to maintain tension (pull so that the conductor is always tense), therefore inaddition to the winch machine, it is necessary brake machine that maintains the conductor sag at the correctamount. To obtain the desired tension this is done by pulling the conductor slowly while removing the armatureslowly from the conductor drum.
7.4.4 Safety Inspection prior to operation
Once the electrical installation work has been completed, it will be tested before it is operated. The scope oftesting activities is as follows:
a. Visual Examination:
• Check the condition of the tower (e.g. everything is in good condition, no parts are rusty, including itsnuts and bolts);
• Check the condition of the insulators, (e.g. whether everything is in good condition and clean, nothing isbroken or cracked, no deformation); and
• Check the condition of conductors, ground wires and joint sleeves.
b. Construction inspection:
• Examine all components installed and compare them with specifications and regulations.
c. For certain work items that cannot be seen by naked eye, then testing using test equipment ormeasuring devices will need to be undertaken:
• Testing isolation insulators, insulation resistance between phase to phase and phase insulationresistance between the neutral wire. Test equipment includes Mega Ohm Meter / Megger / InsulationResistance Tester.
• Ground earthing, using test equipment or measuring devices such as Earth Resistance Tester.
After the inspection and testing activities have been carried out and the lines are certified safe for operation theymay be energised for operation.
7.5 Operation
Once constructed and operational, the transmission line will be transferred as an asset for PLN to own tooperate. Maintenance activities will be carried out to ensure the line and equipment are functioning properly.Maintenance will also include maintaining the space under the transmission line by trimming any plant growth.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
29
AM039100-400-GN-RPT-1002 Rev 1
8. Gas Pipeline
8.1 General
The fuel for the project will be dry natural gas. It will be supplied via a 40km long pipeline which will connect tothe Grissik-Duri transmission pipeline (operated by PT. TGI) at an offtake location known as SV1401. A custodygas metering facility will be installed by PT. TGI just upstream of the point of interconnection. Downstream of themetering skid, the pipeline size will transfer gas to the plant.
This section of this report addresses the pipeline downstream of the metering point.
Process conditions for the pipeline as follows:
Table 17 : Gas Main Process Parameters
Parameter Unit Value
Tie-in point SV1401
Distance km Approximately 40
Gross Heating Value Btu/SCF 950 - 1250
Diameter inch 12
Flowrate MMSCFD Up to 46
Pipeline design pressure barg 79.3
Supply pressure at tie-in point barg Approximately 50
Delivery Pressure Barg Estimated at between 24 and 50
The pipeline will be buried and will mostly follow the existing road. Refer to Appendix F for the proposed route.
The arrival pressure will depend on the pressure of the main pipeline at the delivery point and the flowrate. Theflow rate will depend on the level of dispatch of the plant, as determined by PLN.
The pipeline design will be equipped with a pigging facility, mainly intended for piping cleaning and integritychecking. A Pig launcher will be installed at the tie-in point to the Grissik–Duri pipeline, and the receiver will beat the power station site. Sectional valves will be installed to allow pipeline isolation for maintenance or duringan emergency.
At the power plant, the gas will enter the gas reception area – described earlier.
8.2 Pipeline Route
The preferred pipeline route is shown in the following figure.1
1 MRPR is currently going through the process of land acquisition / rental, endeavouring to obtain approval fromthe relevant stakeholders. Thus, minor rerouting may be required in order to avoid permanent damage or landsettlement, all in accordance with the prevailing regulations and approvals by MIGAS.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
30
AM039100-400-GN-RPT-1002 Rev 1
Figure 4: Preferred Gas Pipeline Route
The bulk of the route follows roadways approximately 5 km of which pass close to habited areas. Approximately8 km is through palm oil plantation land.
During the design stage, the pipeline classification will be determined in accordance with Mining and EnergyMinisterial Decree no. 300 (KEPMEN 300) and relevant international guidelines and standards. This processwill ensure that there is adequate separation between the pipeline and residents, businesses or other services(e.g. other pipelines for oil, water, gas etc. or power lines) close to the route. Additional safety provisions will beimplemented where deemed necessary for public safety.
The pipeline will cross several roads and streams and may run close to or under other existing services(including oil and gas pipelines and power lines). The design will incorporate safeguards in accordance with theregulations and good industrial practice in order to minimise the risk of harm or damage from constructionworks.
8.3 Construction
8.3.1 Introduction
The pipeline will be installed by CPM, a contractor with substantial experience of this type of work.
The pipeline route extends over a significant area and particular attention will be paid to matters of:
• Maintaining good relations and communication with the communities which could be affected by thework;
• Public safety;
• Traffic control; and
• Environmental protection.
8.3.2 Construction
Construction will involve:
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
31
AM039100-400-GN-RPT-1002 Rev 1
• Preparing the pipeline route by clearing vegetation and grading the immediate area;
• Transporting the pipe sections to the workfront;
• Welding the pipeline sections together, followed by non-destructive testing of the welds to check forflaws. Any flaws will be repaired.
• Digging and preparing the trench for the pipe – with the maximum open trench at any time likely to be500m;
• Lowering the pipe into the trench;
• Backfilling the trench and compaction; and
• General area reinstatement.
A typical Construction Execution Plan has been provided by CPM and in included in Appendix F for reference.
8.3.3 Tie-ins and final testing
The various sections of pipe will be welded together at what are referred to as tie-ins. These tie-in welds willalso undergo non-destructive testing.
Eventually, after the pipeline is complete and has been cleaned, the entire length will undergo a hydro test tocheck the integrity of the pipeline.
Once complete, the pipeline will be dried and then preserved until the power plant is ready to accept gas.
8.3.4 Construction crew and equipment
The construction team will include:
• Pipefitters
• Welders
• Crane operators and riggers, and
• General labourers.
Construction equipment will include:
• Excavators
• Bulldozers
• Dump trucks
• Cranes
• Welding machines
• Water pumps for temporary drainage systems, and
Appendix F contains further details of the estimated labour requirements and equipment mobilisation schedule.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
32
AM039100-400-GN-RPT-1002 Rev 1
8.4 Operation
MRPR will operate the pipeline over the term of the PPA.
In general, the pipeline will be in service at all times. The timing of any shutdowns will have to be co-ordinatedcarefully with the gas supplier and PLN as any shutdown will result in an inability of the power station tooperate.
At the end of the PPA, ownership of the pipeline will pass to PLN.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
33
AM039100-400-GN-RPT-1002 Rev 1
9. Power Plant Resource Requirements
9.1 Natural Gas
The amount of natural gas fuel required from day to day will vary depending on ambient conditions and the levelof generation requested by PLN.
Maximum daily fuel demand is estimated as follows:
Table 18: Fuel demand details
I tem Unit Value
Heat rate at 100% load Btu/kWh, HHV 6,920
Net output at full load kW 275,000
Fuel flow per hour at full load Btu/h 1,903,000,000
CV of fuel, HHV Btu/scf 1,039
Hours per day h 24
Use per day mmscf/d 44
PLN have a nominal target annual net capacity factor (NCF) of 60%. The fuel needed to achieve this annualNCF will depend on the load mix used to deliver the energy. If the 60% AF is achieved using the load mix PLNused during the IPP selection process, then fuel use over the term of the PPA is estimated as follows:
Table 19: Fuel use details
I tem Unit Value
Capacity at base load kW 275,000
Hours per normal year h 8,760
AF % 0.6
Generation required per year kWh 1,445,400,000
Average heat rate at evaluation load mix Btu/kWh, HHV 6,942
Fuel use per year Btu, HHV 10,033,966,800,000
Fuel use per year PJ, HHV 10.5
Fuel use over PPA PJ, HHV 211.7
9.2 Water
9.2.1 General
The plant will extract raw water from the Siak River for use on site. The main water consumption will be for thefollowing:
• Cooling water to cooling towers;
• Demineralised water makeup for the steam cycle;
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
34
AM039100-400-GN-RPT-1002 Rev 1
• Potable water for plant us; and
• Firewater.
The raw water requirements when the plant is at full load are predicted to be approximately 370m3/h with thepredominant usage being for the cooling system. Maximum demand will be in the order of 400m3/h. Most ofthe losses from the cooling system will be due to evaporation from the cooling tower. Evaporation losses willvary with steam turbine load and ambient conditions. With the evaporation of water from the cooling watersystem, the concentration of the salts and impurities in the circulating water increases. In order to control these,additional water is drained from the cooling water system. Such drained water is called blowdown. Theblowdown rate depends on the quality of the water and the design of the cooling tower fill. All requirements willbe finalised during detailed design.
The following table presents expected demands:
Table 20: Raw water demand details
User Nominal demand at full load, m 3/h
Cooling tower evaporation and blowdown 340
Water steam cycle 10
Other users and losses 20
Total 370
To minimise make-up requirements, where possible, water will be recycled – for example clean stormwater andsome process wastes can go to the cooling tower basin to reduce the need for make-up from the River.
A preliminary water balance / flow diagram for the plant is provided in the Appendix B.
9.2.2 Plant demand in context of Siak River water flow
Daily river flow data for the years 2004 to 2013 have been reviewed and the data yields the following results:
Table 21: Plant demand versus Siak River Flows
Year 2004 2005 2006 2007 2008 2009 2010 2011 2012
Minimum flow m3/h 33840 61200 29160 65160 43200 64440 33840 77040 31680
Average flow m3/h 259,200 219,600 224,280 270,000 261,000 279,720 250,920 312,480 265,680
Average takerequired m3/h 370
Take as a % ofminimum flow % 1.09% 0.60% 1.27% 0.57% 0.86% 0.57% 1.09% 0.48% 1.17%
Take as a % ofaverage flow % 0.14% 0.17% 0.16% 0.14% 0.14% 0.13% 0.15% 0.12% 0.14%
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
35
AM039100-400-GN-RPT-1002 Rev 1
10. Power Plant Environmental Discharges
10.1 Exhaust Stack Emissions
10.1.1 General
Emissions estimates are presented for NOx, CO, SOx, PM, and CO2 as these are the emissions of interest froma gas fired power station.
Table 22: Exhaust Stack Emissions – Per Stack
STACK Emissions Basis 100% Load
Stacks in service - 2
NOx 51 mg/Nm3 = 25 ppmvd, guaranteed by GE /Lotte g/s per stack 12.1
CO 30 mg/Nm3 = 23 ppm g/s per stack 6.5
SOx 30 ppm by weight, sulphur in fuel2 g/s per stack 0.47
PM30mg/Nm3, allowed by local regulations andguaranteed by GE/Lotte
g/s per stack 7.4
CO2
Heat Balances, Design Fuel composition, and52.5 TCO2/TJ, HHV g/kWh
383
Temperature Heat Balances °C 82.4
Exhaust Gas Velocity Estimated based on 3.8 m diameter stack m/s 20 m/s
Stack concentrations (mg/Nm3 and ppm) and are based on 15% O2, dry gas. Each stack will have a continuousemissions monitoring system (CEMS) in order to monitor emissions during plant operation.
All emissions will be within the limits outlined in the IFC/World bank guidelines and within the requirements ofthe Indonesian regulations.
The following table shows the maximum possible annual emissions, in tonnes/year, based on a Net CapacityFactor (NCF) of 93%.
Table 23: Estimated Maximum Annual CCGT Exhaust Stack Emissions,
STACK Emissions 100% Load and 93% NCF
NOx t/year 355
CO t/year 191
SOx t/year 499
PM, based on PM content in gas t/year 217
PM, based on PM concentration allowed t/year 355
CO2 t/year 860,000
2 Indonesian regulations permit exhaust concentrations of up to 30mg/Nm3. This would increase the emission rate by a factor of approximately 20.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
36
AM039100-400-GN-RPT-1002 Rev 1
10.1.2 Stack Parameters
The height of the exhaust stack is assumed to be 45m.
The diameter of the exhaust stack is estimated at 3.8m.
The final height and diameter will be determined once the dispersion modelling is completed to make sure thatground level concentrations of the various pollutants do not exceed permitted levels.
10.2 Emissions to air from the cooling tower
There will be emissions to air from the cooling tower, estimated as follows:
Table 24: Emissions to air estimation details
Parameter Value
Hot humid air 3,000 kg/s of air heated by about 9.7C above ambient at 100% relative humidity
Drift Less than 1 kg/s
Expected conditions at the top of the cooling tower are:
Table 25: Cooling tower condition details
Parameter Value
exhaust temperature 35.8°C
exhaust flow 3,800 kg/s
volumetric flow rate 3,500 m3/s
Exhaust velocity 10.4 m/s
Geometry of cooling tower 73 m long x 18 m wide x 10.1 m high (top deck)
Discharge height 13 m
The cooling towers will be fitted with a drift eliminator. As such, the emission of water droplet from the top of thecooling towers (drift) will be minimal.
However, because the drift droplets will contain the same chemical impurities as the water circulating throughthe tower (concentrated salts from the incoming supply plus traces of chemicals added for process control) theparticulate matter constituent of the drift droplets may be classified as an emission. The magnitude of the driftloss will be influenced by the number and size of droplets produced within the tower, which are determined bythe tower fill design, tower design, the air and water patterns, and design of the drift eliminators.
Chemicals used in the cooling tower shall be of a type
• That will have no significant adverse effect on the environment or local community; and
• Which decompose faster than deposited on the surrounding land (and thus do not accumulate)
During the permitting process, these emissions will be modelled.
10.3 Other Air Emissions
The great majority of plant emission to air will be via the exhaust stacks. However, for completeness, thefollowing emissions may also be considered during the permitting process.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
37
AM039100-400-GN-RPT-1002 Rev 1
• Condenser: Very small quantities from the air ejectors - equivalent to the dissolved gases in the steamcycle make-up -of steam and dissolved air from water.
• Heat: from generator, oil and other cooling systems.
• Steam, gas and air from vents and drains;
• Intermittent steam from emergency relief valves, CO2 if released for fire protection, etc. (althoughemergencies are not expected to occur).
• Intermittent combustion gases from the Black Start Diesel Generator and the Fire Water Diesel DrivenPump.
• Minor discharges (e.g. SF6 from electrical equipment) during maintenance.
These emissions occur in trace amounts and are generally non harmful. Therefore, further mitigation measuresbeyond good utility practice are not normally considered necessary.
10.4 Liquid Effluents
10.4.1 General
The power generation process does not produce any hazardous liquid wastes. Preliminary P&IDs for thewastewater treatment system are included in Appendix B.
The primary liquid waste streams will be treated as required before being discharged into the Siak River.
• Clean stormwater will be collected and sent to the cooling tower basin or discharged from site.
• Stormwater which could be contaminated with oil will be collected and sent to a separator, before beingdischarged to the River.
• Stormwater which could be contaminated with chemicals will be collected and sent to the wastewatertreatment plant.
• Effluent from the raw water settling and filtration process will be thickened and dehydrated. The solidswill be disposed of off-site via truck. Liquid effluents will be discharged to the wastewater treatmentplant.
• Effluents from the water treatment plant (the demineralised water plant) will be discharged to thewastewater treatment plant.
• It should be possible to maintain the chemistry of blowdown from the cooling tower to be within theeffluent discharge limits, and so this may not be treated before discharge. In the event any suchtreatment is necessary, it will be carried out in the wastewater treatment plant.
• Areas storing oils and chemicals will be bunded and drained to an operational wastewater pit fortreatment before discharge.
• Compressor water wash water will be collected in a dedicated tank and then trucked off site fordisposal.
• The design and chemical treatment regimes will be finalised once adequate river water samples areavailable.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
38
AM039100-400-GN-RPT-1002 Rev 1
10.4.2 Effluent Volumes
The following table presents expected discharge volumes.
Table 26: Discharge volume details
User Nominal discharge at full load, m3/h
Cooling tower 56
Water steam cycle 2
Other users including losses from water filtration and treatment 22
Total 80
The volume of solids removed in the raw water settling and filtration process will depend on the level suspendedsolids (TSS) in the incoming water. Based on the samples available (analyses are included in Appendix B) themaximum TSS level in the River was 56mg/l. At an average intake flowrate of 370m3/h, approximately 21kg/hof solids will be removed and will have to be disposed of.
10.4.3 Effluent Volumes in context of Siak River water flow
Daily river flow data for the years 2004 to 2013 have been reviewed and the data yields the following results:
Table 27: Estimated Discharge volumes compared with River Water Flow
Year 2004 2005 2006 2007 2008 2009 2010 2011 2012
Minimum flow m3/h 33840 61200 29160 65160 43200 64440 33840 77040 31680
Average flow m3/h 259200 219600 224280 270000 261000 279720 250920 312480 265680
Average discharge m3/h 80
Discharge as a %of minimum flow % 0.24% 0.13% 0.27% 0.12% 0.19% 0.12% 0.24% 0.10% 0.25%
Discharge as a %of average flow % 0.03% 0.04% 0.04% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
10.4.4 Effluent quality
The quality of the main effluent – blowdown from the cooling tower - will depend on the
• Incoming water quality. Salts in the original River water will likely be concentrated approximately 6times.
• Chemicals added to the cooling water system to control biocides, scaling, and (perhaps, if necessaryfrom time to time) deposits.
Water samples have been taken from the river and the results are included in Appendix B. The following tablelists the parameters to which discharge limits apply and the relevant limits, lists the maximum incoming value forthat parameter based on the samples taken, and predicts the discharge concentration for that parameter, basedon the cooling tower operating at 6 cycles of concentration.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
39
AM039100-400-GN-RPT-1002 Rev 1
No allowance is made for chemicals added in the raw water treatment process or cooling water system dosing.These are normally dosed in small quantities (compared with the circulating water flow rate), and are chosen orcontrolled so that they cannot cause discharges to exceed environmental limits.
Table 28 Estimated Cooling Tower Blowdown quality based on incoming water quality
Parameter Unit Local StandardIFC/World Ba nk
GuidelineMax incoming
Discharge
quality,
assuming 6
cycle s of
concentrat ion
pH value - 6 - 9 6 - 9 6.88 controlled
Suspended Solids mg/L 100 5056
Removed in filtration
system
Chromium (Total) mg/L 0.5 0.5 <0.002 < 0.012
Copper (Cu) mg/L 1 0.5 <0.01 < 0.06
Zinc (Zn) mg/L 1 1 0.05 < 0.3
Iron (Fe) mg/L 3 1 1.168 < 1
Free Chlorine (Cl2) mg/L 0.5 0.2 controllable
Oil and grease mg/L 10 102.4
Removed in
separator
Phosphate (PO4-)** mg/L 10 silent 0.862 5.172
Lead (Pb) mg/L silent 0.5 <0.005 < 0.03
Cadmium (Cd) mg/L silent 0.1 <0.002 < 0.012
Mercury (Hg) mg/L silent 0.005 <0.0005 < 0.003
Arsenic (As) mg/L silent 0.5 <0.005 < 0.03
Temperature °C silent
Less than 3°C above
ambient water
temperature at edge
of mixing zone at
discharge. This
Zone shall be
established during
permitting.
Raw blowdown
temperature will be
31.6 at design case,
and temperature will
drop between site
and river
Note, the measured incoming Iron level exceeds the effluent guideline value. The non-soluble content will beremoved by filtration. The soluble content will be removed by aeration, clarifying (coagulation / flocculation /sedimentation) and filtration. It is expected that the iron level entering the cooling tower basin will be between0.05 ~ 0.10 ppm. Even after concentrating 6 times, the iron content in any discharge will be lower than 1.0 mg/Las Fe, and so will comply with the guidelines. The iron level will be monitored and effluent may be routed to thewastewater treatment system if it happens that the discharge limit will not be met. The wastewater treatmentsystem also has aeration, clarifying and filtration facilities and these would reduce the iron content to meet thespecification.
The blowdown will be taken from the cold water stream leaving the cooling tower rather than the hot waterstream flowing to it from the plant. The temperature of the blowdown will depend on several factors, mostnotably:
• The thermal load on the condenser. This which will depend on the steam flow which is a function of the
plant output at the time.
• Ambient wet bulb temperature at the time. The ambient wet bulb temperature sets the absolute lowerlimit for the cold water temperature. The temperature by which the cold water will exceed this is knownas the approach and this is normally in the order of 5 to 8°C. For this project, the preliminary design is
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
40
AM039100-400-GN-RPT-1002 Rev 1
based on an approach of approximately 6.3°C. As ambient conditions vary, the wet bulb varies but the
approach remains almost constant.
At the design conditions (plant operating at full load, at 28°C and 85% RH) the wet bulb temperature is 25.2°Cand it is estimated the blowdown will be 31.5°C. At the hottest ambient conditions (estimated to be 35°C and50% RH), the wet bulb will drop to 26.2°C and it is estimated the blowdown will be 32.2°C if the plant isoperating at full load at the time.
All effluents will be collected and neutralised as required so that the effluent quality will meet the local and IFC /World Bank EHS Guidelines.
10.4.5 Estimated annual water use and discharges
Likely maximum annual water use and discharge volumes are:
Table 29: Annual water use and discharge details
100% Load a nd 93 % AF
Water Use m3/year 2,6000,000
Effluent m3/year 650,000
10.5 Noise emissions
10.5.1 General
The power plant will generate noise when in operation. Noise levels from the Project will not exceed theIndonesia and World Bank / IFC noise limits. The noise level in the control room will not exceed 55dB(a).Warning sites will be provided at all entrances to rooms and operating areas where the noise levels exceed75dB(A). The noise emissions are outlined in the Table below.
Table 30: Noise emissions details
Project locat ion Allow able Noise emissions
At the plant boundary under normal operation 70dB(A)
1 m from major equipment 85dB(A)
Within central control rooms 55dB(A)
10.5.2 Impact on neighbours
The project site boundary is located approximately 2 km from the nearest residential areas. There is littlelikelihood of a significant noise impact on these areas from the power station during the operational stage.
In any case, the plant will follow good design and construction practices and implement the mitigation measuresincluding those described below.
The main sources of noise emissions will be the:
• Gas Turbines;
• Gas Compressors (if required);
• HRSG;
• Cooling tower; and
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
41
AM039100-400-GN-RPT-1002 Rev 1
• Transformers
Noise reduction measures in the design will include:
• Silencing of the gas turbine inlets;
• Locating the steam turbine inside a building;
• Limiting noise emissions from any gas compressors, building ventilation fans, transformers etc.;
• Buildings will be lined and cladded as required;
• Safety valves will have silencers fitted, where necessary; and
• Noise sources will be directed away from the most sensitive receptors.
The EPC Contractor will implement measures to achieve the maximum allowable noise levels of 85dBA at 1mfrom the equipment and 70dBA at the plant boundary.
Noise will be monitored during operation to check that, other than during emergencies, noise emissions arewithin the acceptable limits, identified below.
Table 31: Noise reduction details
Source of Noise Criteria Noise Criteria
Day-t ime Night-t im e
LAeq1 hr LAeq1 hr
World Bank Guidelines Industrial / Commercial 70 dB(A) 70 dB(A)
Residential 55 dB(A) 45 dB(A)
10.6 Solid Waste management
The power plant will not produce any bulk solid wastes such as ash or sludge as are generated in a coal firedpower station or some industrial processing facilities. Solid wastes are minimal and will generally be as theresult of maintenance or housekeeping activities and may include items such as
• Old pipework, steel work, cabling, instrumentation etc., replaced due to upgrades or modifications;
• Consumable items e.g. oil and air filters; and
• Maintenance items, e.g. rags, containers for paints or chemicals etc.
Where possible, items will be recycled. Otherwise, solid wastes will be disposed to a licensed facility nearby.
10.7 Hazardous and toxic substances
According to the Indonesian Government Regulation No. 101 Year 2014 on the Treatment of Hazardous andToxic Waste, a hazardous substance is a substance, energy, and/or other components that is due to itsproperties, concentration and/or quantity, either directly or indirectly, can pollute and/or damage theenvironment, and/or endanger the environment, the health and well-being of human and other living creatures.
The following is a list of typical chemicals and their storage quantities for CCGT plant of this size.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
42
AM039100-400-GN-RPT-1002 Rev 1
Table 32 - Sample list of Chemicals Stored Onsite for a Typical Combined Cycle Plant
Chemical/Product Storage
Quantity
Genera l Use of Chemical
Sulphuric acid 10,000 L Demineralisation system
Hydrochloric acid 10,000 L Demineralisation and cooling watersystems
Scale inhibitor 10,000 L Cooling water systems
Caustic (e.g. NaOH) 10,000 L Demineralisation system
Turbine oils (e.g. Terrestic 32 or 68, Exxon) 5,000 L Turbines, pumps, air compressor,lubrication
SAE 15 W - 40 Oil 600 L Diesel fire pumps
Hydraulic fluid 1,000 L Steam turbine electrohydraulic fluid
Ammonia (NH3) Boiler water treatment
Trisodium Phosphate 100 kg Boiler water treatment
Sodium Hypochlorite 100 L Water treatment biocide for rawwater and possible for cooling water
Insulating Oil (non PCB) 1,000 L Transformers
O2 Scavenger 500 L Deaerator tanks
Misc. Chemical Reagents for WaterLaboratory
50 kg Water testing lab chemicals
Water Wash Liquid 1,000 L GT water wash
CO2 4,000 kg Fire protection
Miscellaneous oils, reagents, chemicals, thinners etc. used for O&M activities
The hazardous substances listed are not waste products but chemicals used in the general maintenance of thestation.
All chemicals and hazardous substances will be stored in secure locations on site and waste materials will betrucked from site for proper disposal where appropriate.
.
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
AM039100-400-GN-RPT-1002 Rev 1
Power Plant Site Location and Layout Drawings
1 2 3 4 5 6
1 2 3 4 5 6
A
B
C
D
A
B
C
D
A3
DRAWING No
DATE
DRAWING CHECK
DESIGN REVIEWDESIGNED
DRAWN
CLIENT
REVIEWED
DATE
APPROVED
SCALE
TITLE
REV
REV DATE REVISIONDRAWN REV'D APP'D
PROJECT
GENERAL AREA, FOOTPRINT,
AND SERVICE CONNECTIONS
AS SHOWN AM039100-300-GN-DRG-0001 E
MEDCO RATCH POWER RIAU
RIAU 275 MW GFPP.
JL .
EM .
.
.
EM
.
A 29/06/17 JL EM EM PRELIMINARY ISSUE
B 06/12/17 JL EM EM REVISED ISSUE
C 08/01/18 JL EM EM REVISED GRID CONNECTION
D 18/01/18 JL EM EM REVISED WATER PIPELINE
E 22.03.18 JL EM EM REVISED WATER PIPELINE
PRELIMINARY FOR INFORMATION ONLY
Suite E-13A-20, Level 13ABlock E, Plaza Mont' Kiara, 2 Jalan KiaraMont' Kiara, KUALA LUMPUR 50480MALAYSIA
Tel: + 60 3 6204 6688Fax: +60 3 6204 6698Web: www.jacobsskm.com
5,000
6,0
00
5,000
6,0
00
6,0
00
20
05
,80
0
50
0
6,0
00
20
04
,80
0
50
0
5,000 5,000
1,0
00
Riau GFPP (275MW) IPP Project
AGENCY OF THE MINISTRY OF MINES AND ENERGYGOVERMENT OF THE REPUBLIC OF INDONESIA
PT Medco Ratch Power Riau 0
Water Intake Pipeline
Water Intake Pipeline 3km x 6m width (2m pipe + 4m workway)
0°33'59.88"N
101°31'7.70"E
=
780357.29 m E
62691.00 m N
Government doesn’t have
coordinate yet, this is
only estimation from Map
given by Government
0°32'34.61"N
101°30'54.60"E
PT Medco Ratch Power Riau 2
Access Road
Access Road (two- lane) 28 m x 200 m
8m is paving road and 10mx2(both side) is slope area
Lokasi Koordinat
Entrance at site boundary(FGL +28m)
780570.00 m E59953.00 m N
Outer Ring Road (using google mapGL +16m)
780570.00 m E60153.00 m N
10m 8m 10m
PT Medco Ratch Power Riau 4
Access Road (two-lane) 28 m x 200 m
8m is paving road and 10mx2(both side) is slope area
Required area remains unchanged.
10m 8m 10m
Location Coordinate
Entrance at site boundary(FGL +28m)
780570.00 m E59953.00 m N
Outer Ring Road (using google mapGL +16m)
780570.00 m E60153.00 m N
Location Coordinate
Entrance at site boundary(FGL +28m)
780488 m E59949.00 m N
Outer Ring Road (using google mapGL +16m)
780488.00 m E60149.00 m N
✌ Previous Coordinate
✌ Revised Coordinate
LEC revise access road location by following water intake
pipeline. Around 82m to shift from previous location.
Revised plot plan will be provided later if Owner need to
receive it.
☛ LEC - Coordinate for Access Road (move to left)
PT Medco Ratch Power Riau 5
82m to left
☛ LEC - Access Road (move to left)
PT Medco Ratch Power Riau 6
Start point at site boundary Finish point nearby siak river
780476.00 m E59945.00 m N
780357.29 m E62691.00 m N
(This coordinate is suggested by Owner. LEC willfollow this location.)
☛ Location for Water intake pipe line (including discharge pipeline)
Coordinate
PT Medco Ratch Power Riau 7
Previous
water line
82m to left
Revised
water line
Revised water intake line (purple)
Previous water intake line (red)
☛ LEC – Revised water intake/discharge pipe line route
PT Medco Ratch Power Riau 8
☛ LEC – Revised water intake facility location
Water intake facility to move around 120m left according to suggestion by Owner. In addition,
facility is needed 30m from the edge of river. Required area (50m x 40m) remains unchanged.
120m to left
Intake/outfall line
30m from the edge of river
☛ Possible Location for temporary jetty / RoW
Inside Tenayan CFPP Area adjacent to labor camp in Tenayan
To use permanent or temporary jetty in Tenayan
CFPP
To build temporary jetty in siak river bank adjacent
to Tenayan CFPP
Coordinate : 781196.00 m E 63803.00 m N( Location is indicated as above “ ” )
Temp. Jetty / 70 m x 100 m
100m
70m
III. Temporary Jetty (option 1)
☛ Temporary Jetty to Site Route / RoW (5.3 km)
☛ Preliminary Temporary Jetty Design
59.5695
30.0167
23.4037
3.2001
3.0226
1.85464.3330
1.3104
<Description>
For tunnel, sheet pile & wire sling for stud will be installed in both wall of tunnel.For head (red area), splitstone and sandbag will be installed in river bank.Dredging will be required subject to siak river condition of river bottom. (green area)To construct temporary jetty, it takes 3~ 4 months. (To remove jetty, 1 month to be required)Temporary jetty`s capacity is upto 270ft barge available.
<Permit>
1. Temporary jetty/ dredging permit from...- Dept. of Transportation- Directorate of River transportation- Directorate of port and dredging facilities- Local port & authorities in Riau
2. Evaluation of safety for environmental impact by localNGO(s) and local leaders
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
AM039100-400-GN-RPT-1002 Rev 1
Water Flow / Balance Diagram and Other WaterRelated Drawings and Information
�✁✂✄☎✆✂✝✞☎✟ ✠ ✡✆✞☛✝
☞✌✍✎✌ ✏✑✎✒ ✓✔☎✕✖✡☎✕✟✑✗✘✑✒✎✙ ✍✗✒✏✍✎✙ ✚✂✛
✒✒✌✎✍☛✞✆� ☛✞✜✢✝✞✟✜ ✌✗✍✍✣✎✙ ✘✎✏
✍✏✎✙
✤✂✞✥ ✆✞✁�✆✒✑✌✎✏ ✒✑✌✎✏ ✒✑✌✎✏ ✒✑✒✎✙ ✒✣✌✎✦ ✦✎✦ ✦✎✦ ✦✎✣ ✧☎✟✤★✩�✆✤✌✗✌✣✒ ✌✗✌✣✒✎✙ ✌✗✌✣✒✎✙ ✌✗✘✍☞✎✙ ✌✗✒✘✒✎✙ ✍✑✏✎✙ ✍✑✏✎✙ ✍✏✙✎✙
✚✍ ✪ ✍✘✗✘✙✙ ✫✬✛ ✚✍ ✪ ✍✙✙ ✫✒✛ ✚✍ ✪ ✍✗✒✏✙ ✫✬✛ ✚ ✍ ✪ ✏✙✙ ✫✒✛
✏✎✏ ✒✒✦✎✙ ✘✎✏✍✒✍✎✙ ✒✒✦✎✙ ✍✏✎✙
✡✞✤✄☎✤✂✔ ✑✎✏ ✍✎✙ ✚✓✛ ✍✎✏ ✍✎✏ ✍✎✏ ✧☎✟✤★✩�✆✤✚✧✂✥�✛ ✍✒☞✎✙ ✍✎✙ ✍☞✎✙ ✍☞✎✙ ✍☞✎✙
✏✎✑ ✢✆✤✜ ✓✔☎✕✡☎✕✟✑✘✎✙ ✭★�✟✧✢✞✟✜
✍✎✦ ✤�✆✁✞✧� ✕✂✝�✆✍✏✎✙ ✧☎✟✤★✩�✆✤
✑✎✏ ☎✞✔✮ ✡✆✂✞✟✤ ✍✙✎✙ ✡✞✤✄☎✤✂✔✍✒☞ ✚✄✆�✧✞✄✞✝✂✝✞☎✟✛ ✍☞✙✎✙ ✚☎✞✔✛
✚✓✛ ✍✎✙✍✎✙
✓✔☎✕✖✡☎✕✟ ☛✆☎✩ ✧✯✝ ✏✑✎✒ ✍✙✎✙✚✂✛ ✍✗✒✏✍✎✙ ✍☞✙✎✙
✞✟✝�✆✩✞✝✝�✟✝✔✮ ✏✒✎✙ ✏✒✎✙ ✏✒✎✙ ✍✑✣✎✘ ✤✂✞✥ ✆✞✁�✆✍✑✙ ✫✒✯✧✮✧✔� ✍✑✙✎✙ ✑✒✣✎✌ ✑✒✣✎✌ ✑☞✣✎✌ ✍✗✦✘✏✎✌
✚✍ ✪ ✍✘✙ ✫✬✛ ✚✍ ✪ ✑✣✙ ✫✬✛ ✚✍ ✪ ✒✙ ✫✬✛
✍✙✎✙✍✙✎✙
✍✍✎✑✍✒✌✎✌
✢✆✤✜ ✓✔☎✕✡☎✕✟ ✚✭★�✟✧✢�✡✛ ✍✎✏ ✍✎✏✍☞✎✙ ✍☞✎✙
✰ ✱✲✳✴✵✶✳✷✸✱✲ ✹✳✺✳✻✼✽ ✾ ✿✳✺✳❀❁❁
✔❂❃❂❄❅❆❇ ❈❉❊❋ ●❍■❉ ❏❈❉❏❍❈❉● ❈❉❊❑❉▲❉● ❍❏❏❈▼❊❉●
✆◆❖ ✕◆P❂◗ ❘❙❚❯❱❲❳ ❨
✝◗❂◆P❂❅ ✕◆P❂◗
✕◆❆P❂ ✕◆P❂◗ ✚☎❩❬❭✗ ✤◆❄❩P◆◗❭✛
✟❪P❂❆❇✍✎ ✡❂❆❩❃❄ ✧❪❄❅❩P❩❪❄ ❇ ✓✩✧✆ ✍✙✙❫ ✔❪◆❅ ◆P ✆✤✧ ✧❪❄❅❩P❩❪❄❆ ✚☞✌✝✗ ✌✙❫ ✆✢✗ ✍✎✙✍✙ ❴◆◗✛☞✎ ✝❵❂ ❛◆❜◆❛❩P❭ ❪❝ ❅❂✫❩❄❂◗◆❬❩❞◆P❩❪❄ ❩❆ ❂❆P❩✫◆P❂❅ ❴❭ ☞✎✙ ❫ ❪❝ ❆P❂◆✫ ❃❂❄❂◗◆P❩❪❄ ❝❬❪❖ ◆P ❴◆❆❂ ❬❪◆❅✒✎ ✝❵❂ ◗◆❖ ❖◆P❂◗ ◗❂❆❂◗❡❪❩◗ ❩❆ ❆❩❞❂❅ ❴◆❆❂❅ ❪❄ ☞ ❅◆❭❆ ❝❢❬❬ ❬❪◆❅ ❪❜❂◗◆P❩❪❄✎✣✎ ☛❬❪❖ ◗◆P❂ ❣
✏✎ ✝❵❂ ❅❂P◆❩❬❆ ◆◗❂ ❆❢❴❤❂❛P P❪ ❛❵◆❄❃❂ ◆❆ ❜❂◗ ❅❂P◆❩❬ ❅❂❆❩❃❄ ❩❄❝❪◗✫◆P❩❪❄✎
✐❥❦ ❧❥ ♠♥♦♣q rst♦✉ rst♦✉ ❧❥❧✉ ✈✉✇① ②
③④⑤⑥ ⑦⑧⑨⑩⑤❶❷ ⑨❶❸ ❹④❺ ❻❼❶❹❺❶❹⑥ ❹④❺⑧❺ ❼❶ ⑨⑧❺ ❹④❺ ❽⑧❼❽❺⑧❹❾ ❿❼❹❹❺ ➀➁➂➃ ➂❼❽❾⑤❶❷➄ ➅⑥❺➄ ❻❼➆➆➅❶⑤❻⑨❹⑤❼❶ ⑩⑤❹④❼➅❹ ⑨❶❾ ❽⑧⑤❼⑧ ⑩⑧⑤❹❹❺❶ ❽❺⑧➆⑤⑥⑥⑤❼❶ ⑨⑧❺ ➇❼⑧➈⑤❸❸❺❶
➉ ➉
➊ ➊
➋ ➌ ➍ ➎ ➏ ➐ ➑ ➒
➓ ➓
➔ ➔
→ →
➣↔↕➙ ➛➜➝➝➞➟➠➡➢➤➥ ➦➝➝ ➝➧➨➩➫➭➯
✹➲➲✵➳➵ ➸➺➻ ➼➻➺➽➺➲➾➚
➪
●❉➶➹❈❑❏■❑▼➘
➴➷➬ ➮➬➱✃❐❒❐❮❰➬Ï
ÐÑÒ Ó❚ÔÕÖ×ØÙÚÙÛÜÙÝÝÞ
➪
P✯❵ ✚❵❪❢◗❬❭ ✫◆✪✎✛ ❳ßàáâ Û×ãäÕ Ü×å×æçä èÖ×éÕ×ÚêÕ×Û Û×ãäÕ ÕäëäÕìíÖÕ îíæèïP✯❅◆❭ ✚◆❡❂✎✛
Õëç êÞÝÝð éã åñòóï
➒➋ ➌ ➍ ➎ ➏ ➐ ➑
ôõö÷ô øùú÷ô õûúùü÷ ôùø øùú÷ôô÷ý÷ôöþõô ÿ�þû✁✂
ôùø øùú÷ô✄☎ùôõ✆õ÷ô ✝ �þû✁
�ô÷ýý✞ô÷✆õ☎ú÷ôÿ✟ ✠ ✡☛☛☞✂
øùú÷ô úô÷ùú✌÷ûú�☎ùûú
ÿ✟✍✎ú✏✌✍�✂ÿ✟ ✠ ✡☛☛☞✂
�þúù✍☎÷ øù÷ôúô÷ùú✌÷ûú
✁÷✌õû✑ øùú÷ôýúþôù✒÷ úùûü
✓✔✁ôþ✕�û÷✞✌ùúõ✄úùûü
✄þþ☎õû✒ úþø÷ô
ú✓õ✄ü÷û÷ôÿ✡ ✖ ✡☛☛☞✂
✁÷✓✔✁ôùúþôÿ✡ ✖ ✡☛☛☞✂
ûþô✌ù☎øùýú÷øùú÷ô �þû✁
øùýú÷øùú÷ôúô÷ùú✌÷û ý✔ýú÷✌
øùýú÷øùú÷ô✆õûù☎ ✆õ☎ú÷ôÿ✟ ✠ ✡☛☛☞✂
✆õûù☎ ✁õý�þýù☎�þû✁
ù✍ûþô✌ù☎ øùýú÷øùú÷ô �þû✁
þõ☎✔øùýú÷øùú÷ô �þû✁ÿ✡ ✠ ✗☛ ✘✎✂
þõ☎ ✝øùú÷ôý÷�ùôùúþôÿ✡ ✠ ✡☛☛☞✂
ý÷øù✒÷ úô÷ùú✌÷ûúý✔ýú÷✌
ý÷ôöõ✄÷ øùú÷ôúùûü
CERTIFICATE OF ANALYSIS COA 5.8 NO : GS.COA.03.2016.031 Terbitan : A
TESTING FACILITY : BANDUNG Revisi : 00
JOB NO. : 16/031 CLIENT : PT. HEXA INTEGRA ELECTRICA DATE RECEIVED : 03 March 2016 SAMPLED BY : Client. TIME OF ANALYSIS : Commenced 04 March 2016 until 17 March 2016. TEST METHOD : Waters analyzed in accordance with the procedures published by the American Public
Health Association (APHA, 2012), PT. Geoservices Environmental Laboratories WILAB 5.0.
Lab. No : B 001 Client ID : AIR SUNGAI
Parameter Unit Result Method
Physical
pH (25�C) 6.0 APHA 4500 H+ B - 2012
Electrical Conductivity ✁✂✄☎✆ 49 APHA 2510 B - 2012
Turbidity NTU 17 APHA 2130 B ✝ 2012
Total Suspended Solids (TSS) mg/L < 10 APHA 2540 D - 2012
Chemical
Total Hardness (as CaCO3) mg/L 10 APHA 2340 B - 2012
Total Alkalinity (as CaCO3) mg/L 9 APHA 2320 B - 2012
Chloride (Cl) mg/L 6 APHA 4500 Cl--C - 2012
Sulfate (SO4) mg/L 9 APHA 4500 SO4 E - 2012
Dissolved Silica (SiO2) mg/L 18 APHA 3111 B - 2012
Dissolved Iron (Fe) mg/L 1.1 APHA 3113 B - 2012
Dissolved Aluminum (Al) mg/L 3.9 APHA 3113 B - 2012
Dissolved Manganese (Mn) mg/L < 0.02 APHA 3111 B - 2012
Dissolved Calcium (Ca) mg/L 2.8 APHA 3111 D - 2012
Dissolved Magnesium (Mg) mg/L 0.8 APHA 3111 B - 2012
Dissolved Sodium (Na) mg/L 3.9 APHA 3111 B - 2012
Dissolved Potassium (K) mg/L 2.2 APHA 3111 B - 2012
Nitrate (NO3) mg/L 1.2 APHA 4500 NO3E - 2012
Nitrite (NO2) mg/L 0.043 APHA 4500 NO2 B - 2012
Bicarbonate (HCO3) mg/L 11 APHA 2320 B - 2012
Carbonate (CO3) mg/L < 1 APHA 2320 B - 2012
Hydroxide (OH) mg/L < 1 APHA 2320 B - 2012
Total Phosphate (PO4) ✝ P mg/L 0.19 APHA 4500 E - 2012
Chemical Oxygen Demand (COD) mg/L 27 APHA 5220 D - 2012
Dissolved Oxygen (DO) mg/L 7 APHA 4500 O - C
page 1 of 2
The results of these tests relate only to the sample(s) submitted. This report shall not be reproduced except in full without the written approval of the testing laboratory [Hasil analisa ini hanya berlaku untuk sampel yang diterima. Laporan ini tidak boleh direproduksi sebagian tanpa ijin tertulis dari laboratorium penguji]
CERTIFICATE OF ANALYSIS COA 5.8 NO : GS.COA.03.2016.031 Terbitan : A
TESTING FACILITY : BANDUNG Revisi : 00
JOB NO. : 16/031 CLIENT : PT. HEXA INTEGRA ELECTRICA DATE RECEIVED : 03 March 2016
SAMPLED BY : Client. TIME OF ANALYSIS : Commenced 04 March 2016 until 17 March 2016. TEST METHOD : Waters analyzed in accordance with the procedures published by the American Public
Health Association (APHA, 2012), PT. Geoservices Environmental Laboratories WILAB 5.0.
Lab. No : B 001
Client ID : AIR SUNGAI
Parameter Unit Result Method
Physical
Biochemical Oxygen Demand (BOD) mg/L < 1 IK 5 � 6.71
Total Dissolved Solids (TDS) mg/L 25 IK 5 � 6.2
Bandung, 17 March 2016 ---------------------------------- ---------------------------------------
Checked Approved Signatory Nengsih Lasmijati Kosasih
Analyst Laboratory Manager
page 2 of 2
The results of these tests relate only to the sample(s) submitted. This report shall not be reproduced except in full without the written approval of the testing laboratory [Hasil analisa ini hanya berlaku untuk sampel yang diterima. Laporan ini tidak boleh direproduksi sebagian tanpa ijin tertulis dari laboratorium penguji]
Addit ional Siak River water quality information
No. Analyzed items Unit Result
1 Turbidity NTU 26.7
2 Total suspended solids mg/l 41.0
2a Total dissolved solids mg/l 48.2
3 pH ---- 6.16
4 Total Hardness Meq/l
5 Total Alkalinity: CaCO3 mg/l
6 Dissolved Silica: SiO2 mg/l
7 Iron (Fe+2 +3
) mg/l 1.168
8 Aluminum (Al+3
) mg/l
9 Manganese (Mn+) mg/l 0.067
10 Calcium (Ca+2
) mg/l
11 Magnesium (Mg+2
) mg/l
12 Sodium & Potassium (Na+ + K+
) mg/l
13 Chloride (Cl-) mg/l
14 Sulfate (SO4-) mg/l 0.022
15 Nitrate (NO3-) mg/l 1.204
16 Nitrite (NO2-) mg/l 0.083
17 Bicarbonate (HCO3-2
) mg/l
18 Carbonate (CO3-2
) mg/l
19 Hydroxide (OH-) mg/l
20 Phosphate (PO4-3
) mg/l 0.862
21 Total Dissolved Solids mg/l 48.2
22 Dissolved Oxygen mg/l 5.1
23 BOD mg/l 20.3
24 COD mg/l 81.1
25 Conductivity ✂S/cm
Source:
Vol. 1: Final Master Plan – Pekanbaru Report of the IndII Wastewater Investment Master Plan - Package III Project 2011 (Data of
sample ST 1: Siak I Bridge (Jl. Satrio – Rejosari):
Riau 275 MW Gas Combined Cycle Pow er Plant IPP
ESIA - Process Descript ion
AM039100-400-GN-RPT-1002 Rev 1
Site Investigation
Project:
Soil Investigation, Soil Improvement, and
Topography Study of
Gas Fired Power Plant Project 275 MW
In Riau, Indonesia ❚�✁❛②❛✁ ❘❛②❛ ❉✂✄☎r✂✆☎✝
P�✞❛✁✟❛r✠ ❘�✡�✁✆②✝
❘✂❛✠ Pr☛☞✂✁✆�
Draft Final Report
Year 2017
DRAFT
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Prepared by : Checked by / Date :
A R Muttaqien
Budi Cahyadi Maryodi
Fadhli / 16 June 2017
Dist r ibut ion : Approved by / Date :
………. …….
………………. / …. June 2017
DRAFT i
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Table of Contents
Table of Contents .................................................................................................................. i
List of Figures ...................................................................................................................... iii
List of Tables ....................................................................................................................... iii
1. Introduction .................................................................................................................. 1
1.1 Background ......................................................................................................... 1
1.2 Project Location ................................................................................................... 1
1.3 Scope of Works .................................................................................................... 2
1.4 Report Organization .............................................................................................. 2
2. Topography .................................................................................................................. 4
2.1 General ............................................................................................................... 4
2.2 Survey Methodology ............................................................................................. 4
2.3 Reference Coordinate ............................................................................................ 6
2.4 Benchmark Installation ......................................................................................... 6
2.5 Horizontal Control (Traverse) Measurement ............................................................. 6
2.6 Vertical Control Measurement ................................................................................ 6
2.7 Measurement of Detailed Situation ......................................................................... 7
2.8 Data Processing and Drawing ................................................................................. 7
2.9 Analysis of Topography Survey............................................................................... 8
2.10 Survey Result ...................................................................................................... 8
2.11 Quantity of Cut/Fill and Recommended Level ........................................................... 9
3. Geotechnical Investigation ............................................................................................ 10
3.1 Geology and Geotechnical Site Investigation Methodology ....................................... 10
3.2 Geological Condition ........................................................................................... 12
3.3 Core Drilling and Insitu Test ................................................................................. 13
3.4 Chemical Properties ............................................................................................ 18
3.5 Geoelectrical Survey ........................................................................................... 19
3.5.1 Implementation of Survey Works ............................................................ 19
3.5.2 Result of Geoelectrical Survey ................................................................. 21
3.6 Geotechnical Investigation and Foundation ............................................................ 22
3.6.1 Recommendation of Design Parameter ..................................................... 22
3.6.2 Shallow Foundation ............................................................................... 25
3.6.3 Deep Foundation ................................................................................... 27
3.6.4 Settlement ........................................................................................... 35
DRAFT 2 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
3.6.5 Slope Stability ....................................................................................... 38
3.6.6 Liquefaction .......................................................................................... 41
4. Comparison to Location Alternative 1 ............................................................................. 42
4.1 Soil Type and Stratification .................................................................................. 42
4.2 Soil Plasticity Behaviour ...................................................................................... 42
4.3 Soil Strength and Stifness ................................................................................... 42
5. Conclusion and Recommendation ................................................................................... 43
LI ST OF APPENDI X
Appendix A: Topogrpahy Map
Appendix B: Description of Benchmark
Appendix C: Borehole Log
Appendix D: Photo of Drilling Activity and Core box
Appendix E: Data and Interprertation of Geoelectric Survey
Appendix F: Result of Soil Mechanc Laboratory
Appendix G: Result of Water Quality and Soil Chemistry
Appendix H: Photo Documentation
DRAFT 3 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
List of Figures
Figure 1 - 1 Project Location ........................................................................................................................... 1
Figure 3 - 1 Typical bedrock encountered at investigation. ................................................................................ 13
Figure 3 - 1 Map layout of soil investigation and geoelectric survey. ................................................................... 14
Figure 3 - 2 Documentation of drilling acitivity at investigation area ................................................................... 18
Figure 3 - 4 Implementation of geoelectrical survey at investigation area ........................................................... 20
Figure 3 - 5 Layout of geoelectrical survey ...................................................................................................... 21
Figure 3 - 6 Geological cross section based on geoelectrical data (section GL-1 to GL-3). ...................................... 22
Figure 3 - 7 Undraned shearing resistance vs adhesion factor. ........................................................................... 28
Figure 3 - 8 Undrained shear strength vs adhesion factor.................................................................................. 31
Figure 3 - 9 Immediate settlement curve. ....................................................................................................... 37
List of Tables
Table 2 - 1 List of topographic surveying standard. ............................................................................................ 4
Table 2 - 2 Analysis of Topography survey ........................................................................................................ 8
Table 2 - 3 Coordinate of installed benchmark. .................................................................................................. 8
Table 2 - 4 List of survey result ....................................................................................................................... 8
Table 3 - 1 Applied standard reference of geotechnical investigation. .................................................................. 10
Table 3 - 2 Permeability level (SNI 2436 : 2008) ............................................................................................. 12
Table 3 - 3 Summary of lithology unit for each borehole location. ...................................................................... 14
Table 3 - 4 SPT field record of BH-01. ............................................................................................................. 15
Table 3 - 5 SPT field record of BH-02. ............................................................................................................. 16
Table 3 - 6 SPT field record of BH-03. ............................................................................................................. 16
Table 3 - 7 Permeability insitu test results. ...................................................................................................... 17
Table 3 - 8 Summary of ground water quality result ......................................................................................... 18
Table 3 - 9 Summary of Soil Chemistry result .................................................................................................. 19
Table 3 - 1 0 Summary of ground water quality result. ...................................................................................... 19
Table 3 - 1 1 Parameter design of BH-01. ........................................................................................................ 23
Table 3 - 1 2 Parameter design of BH-02. ........................................................................................................ 23
Table 3 - 1 3 Parameter design of BH-03. ........................................................................................................ 24
Table 3 - 1 4 Bearing capacity of shallow foundation based on SPT of BH-01. ....................................................... 26
Table 3 - 1 5 Bearing capacity of shallow foundation based on SPT of BH-02. ....................................................... 26
Table 3 - 1 6 Bearing capacity of shallow foundation bsed on SPT of BH-03. ......................................................... 27
Table 3 - 1 7 Bearing capacity of deep foundation at BH-01 using bored pile based on SPT data. ............................ 28
DRAFT 4 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Table 3 - 1 8 Bearing capacity of deep foundation at BH-02 using bored pile based on SPT data. ............................ 29
Table 3 - 1 9 Bearing capacity of deep foundation at BH-03 using bored pile based on SPT data ............................. 30
Table 3 - 2 0 Bearing capacity of deep foundation using driven pile based on SPT data with pre-boring at BH-01. ..... 32
Table 3 - 2 1 Bearing capacity of deep foundation using driven pile based on SPT data with pre-boring at BH-02. ..... 32
Table 3 - 2 2 Bearing capacity of deep foundation using driven pile based on SPT data with pre-boring at BH-03. ..... 33
Table 3 - 2 3 Bearing capacity of deep foundation using driven pile based on SPT without pre-boring at BH-01. ....... 34
Table 3 - 2 3 Bearing capacity of deep foundation using driven pile based on SPT without pre-boring at BH-02. ....... 34
Table 3 - 2 5 Bearing capacity of deep foundation using driven pile based on SPT without pre-boring at BH-03. ....... 35
Table 3 - 2 6 Allowable bearing settlement of BH-01. ........................................................................................ 37
Table 3 - 2 7 Allowable bearing settlement of BH-02. ........................................................................................ 37
Table 3 - 2 8 Allowable bearing settlement of BH-03. ........................................................................................ 38
Table 3 - 2 9 Safety factor for 75 degrees inclination. ........................................................................................ 39
Table 3 - 3 0 Safety factor for 60 degrees inclination. ........................................................................................ 39
Table 3 - 3 1 Safety factor for 45 degrees inclination. ........................................................................................ 40
Table 3 - 3 2 Safety factor for 30 degrees inclination. ........................................................................................ 40
Table 3 - 3 3 Safety factor for 15 degrees inclination. ........................................................................................ 40
DRAFT 1 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
1 . I nt roduct ion
1 .1 Background
Energy has an important role to support regional development, especially in support of other
development sectors. For those reasons, the energy development have targets to provide
adequate energy.
In line with the growth of regional development, the demand for energy, particularly electricity
will continue to rise. Likewise in the next few years with the transition process of rural
communities into urban communities will drive the need for energy.
In order to meet the demand for electricity in accordance with RUPTL 2016-2025 to provide
the load demand of Pekanbaru area, especially the management of primary energy, PLN offers
private party to build a Gas Engine Power Plant (GFPP) with 275 MW capacity, which is MRPR
(Medco Ratch Power Riau).
In preparation of construction the GFPP (275 MW) is necessary to prepare Feasibility Study,
Engineering Design, and Tender Documents. Therefore, before the implementation of the
necessary physical development, is necessary the study based on primary data (based on
survey and investigation) and laboratory test results to determine feasibility of the project.
1 .2 Project Locat ion
The selected site is located at Badak Village, Badak Jaya Sub-District, Tenayan Raya District
Pekanbaru Regency, province of Riau. The site location can be reached by air plane from
Jakarta through Pekanbaru Airport, it takes 1 hour by car or land transportation to reach the
project site.
Figure 1 - 1 Project Locat ion
Project location
DRAFT 2 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
1 .3 Scope of W orks
The Site Investigation was includes Topographic survey, Geoelectrical survey and modeling,
Geotechnical Investigation. A summary of the scope of work for this site investigation typically
include the following:
1. Topographic Survey. Performing topographic survey about 9.5 ha area and establishment
of 2 units of Benchmark.
2. Leveling measurement to reference Benchmark
3. Performing 3 (three) points of core drilling, with 30 meter depth each and total 90 meter.
The investigation includes:
� Standard penetration test (SPT) every 1.5 meter depth of drilling.
� Permeability test every 5 meter depth of drilling.
� Extraction of undisturbed sample (UDS) as much as possible (if required).
� The core shall be store in core box, one box for 5 meter cores.
4. Geoelectrical measurement about 3 (three) points.
5. Laboratory Analysis of Soil Mechanic with following parameters:
a. Index Properties :
� Moisture Content
� Unit Weight
� Specific Gravity
� Grain Size Analysis
� Atterberg Limits
� Compaction standard and modified test
� Amount of material finer than No. 200 Sieve. b. Mechanical Properties :
� Triaxial Compression test
� Consolidation Test
� Direct Shear Test
� Unconfined Compression Test
6. Geotechnical analysis and recommendation shall includes:
� Design parameter of shallow foundation
� Design parameter of deep foundation
Other geotechnical recommendation: Excavation criteria; Recommendation on soil
improvement; Coefficient of permeability and Slopes (steepness) of excavation.
1 .4 Report Organizat ion
Continuing the first chapter was Introduction aspect, this report is organized in to following
section:
� Chapter – 1: Introduction
� Chapter – 2: Topography
� Chapter – 3: Geotechnical Investigation
� Chapter – 4: Comparison of geotechnical analysis with previous study
� Chapter – 5: Conclusion and Recommendation
In an integrated book, this report is complement by following appendices:
� Appendix A: Topography Map
� Appendix B: Description of Benchmark
� Appendix C: Borehole Log
DRAFT 3 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
� Appendix D: Photo of Boring Activities and Core Boxes
� Appendix E: Data and Interpretation Curve of Geoelectrical survey
� Appendix F: Result of Soil Mechanic Laboratory
� Appendix G: Result of Groundwater Quality and soil Chemistry
� Appendix H: Photo Documentation
DRAFT 4 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
2 . Topography
2 .1 General
Location of Topography Measurement are at future GFPP 275 MW area (alternative 2), which
is slightly hilly. The survey located area at coordinates 0°32'23" N, 101° 31' 13.6" E.
2 .2 Survey Methodology
Topographic survey is performed at the study area, cover whole area of future GFPP and
surrounding.
a. Standard and Reference
Standard which applied in execution of this work is Indonesian National Standard (SNI) for
category Topographic Surveying, as show below :
Table 2 - 1 List of topographic surveying standard.
NO
STANDARD
TI TLE Code Year
Standard
I tem s
1. BAKOSURTANAL - Standard Survey Topography Survey and Mapping
2. SNI 19-6724-2002 2002 Standard Survey Horizontal Control Network
3. SNI 19-6988-2004 2004 Standard Survey Vertical Control Network by
Levelling Method
b. Preparat ion and Secondary Data
Before performing the survey work, it’s necessary to prepare and collect secondary data as
follows:
� Prepare National Topographic Map by Bakosurtanal (now named as Badan Informasi
Geospasial), sheet of Pekanbaru with index number 0816-52 and sheet of Perawang with
index number 0816-61. All of the map provided in scale of 1:50.000
� Reference coordinate of existing Benchmarks.
� and other supporting data.
c. Horizontal Control ( Traverse) Measurem ent
Measurement of horizontal control network carried out by closed network traverse. The
horizontal measurements connected to reference Benchmarks. Measurement of traverse shall
performed by following methods :
✁ Point of traverse is strived as near with line alignment connecting the Benchmark Existing
(reference) at site.
DRAFT 5 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
� Apart closeness of between point of traverse is adapted condition of field range from 10
- 50 meter for area relatively leveled off, and about 25 meter for terrain having height
difference enough strike.
� Measurement was carried out by measuring instrument Total Station with reading accu-
racy maximum 5", and measured in one series of reading (forward and backward).
� Measurement of distance every section of traverse done by minimum two times reading
(forward-backward).
� Every execution of measurement of polygon always controlled so that be knowable devi-
ation happened and soon given by correction for returned toward alignment which ought
to.
� Every point of polygon is marking using wooden peg with dimension ¾” or 30 cm (or
other markings) and setup numbering or coding by Surveyor.
d. Vert ical Control ( Elevat ion) Measurem ent
Vertical control measurement aims to give each points of traverse or control points an eleva-
tion value.
Elevation measurements performed by the following:
� Elevation measurement should starts and ends from Benchmark.
� Measurement should through the points (peg) of traverse measurement.
� The elevation measurement conducted using waterpass instrument, a TOPCON ATB4
type.
� Elevation measurement for each section carried by double stand with complete reading
measurement (yarn top, middle and bottom) and double stands.
� Every step of measurement, maximum distance between instrument and measuring staff
is 50 m.
� Before starting and after completion of daily measurement, waterpass instrument should
checked its collimation errors.
e. Measurem ent of Topographic Situat ion
Measurement of topographic situation carried out to get data of land surface, existing building,
house, road, drainage, river and other object that represented situation of intention area.
Measurement of topographic situation shall performed by following methods:
� All detailed measurement should tied to Benchmark or traverse point.
� Measurement of topographic situation carried out to get data of land surface, measure-
ment of situation also done to get data position of natural objects and made in along
with the situations residing in measurement area like, house and other building, road,
river, powerline (HVTL), plantation boundary, forestry, etc, to be presented as infor-
mation at situation vector map (topography map)
� All specific utility such as: existing transmission line, PDAM supply pipe, drainage, etc
shall identified and drawn in Topography map
DRAFT 6 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
� The detailed situation measurement conducted using Total Station
2 .3 Reference Coordinate
The existing BM (benchmarks) owned by Regional Government Owned Company (BUMD) was
utilized as reference BM. Following are data of reference BM which applied :
✄ BM name : BM 0
✄ X value : 783310.000
✄ Y value : 057048.000
✄ Z value : 44.690
The reference BM located at BUMD area, about 7 Km from GFPP site.
2 .4 Benchm ark I nstallat ion
For the purposes of topographic, conducted Benchmark manufacture and installation of as
many as one pair (two units), consisting of BM-03 and CP-03.
2 .5 Horizonta l Control ( Traverse) Measurem ent
The traverse measurement was conducted to determine position of distributed reference point
which will function as tied point (traverse point). The traverse point will be utilized by detailed
situation measurement. Traverse measurement started at BM-03 and finished at CP-03, which
also as initial azimuth.
Implementation of horizontal or traverse measurement are as follows :
✁ Measurement started at reference Benchmark to project site, conducted by geometric
loop (closed loop) and connected to reference points BM-03 and CP-03.
✁ The measurement conducted using Total Station
✁ Measurement of horizontal angle carried out by one double series (one times of normal
and repetition measurement)
✁ Distance measurement also get from Total Station for each traverse range and finally
average distance of each traverse range.
2 .6 Vert ical Control Measurem ent
Measurement of vertical control network conducted using levelling (waterpass) method while
the route follow horizontal control network (traverse) with closed loop. The measurement
connected to BM-0 as starting point of vertical reference (height). The measurement con-
ducted using Waterpass which comply standard and complement by levelling staff. Allowable
tolerance of vertical control measurement is under (20✂D(km)) mm.
DRAFT 7 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
2 .7 Measurem ent of Detailed Situat ion
The detailed situation measurement intended to get position (coordinate) and height
(elevation) of every measured point, which are terrain of ground surface, every object above
ground surface. All detailed situation will presented in the Situation Map. The detailed
situation measurement conducted by following terms :
� Measurement by Total Station
� Measurement carried out by trigonometry method
� The detailed spot measured with scale of 1:1000 standard, which all detail such as river,
road, gully, and 5-10 meter maximum density of ground surface alteration.
� All detailed situation measurement connected to nearest control network point.
2 .8 Data Processing and Draw ing
Data processing / calculation of control network survey result carried out by bowditch for
horizontal control network (traverse), vertical control network and detailed situation
calculated by trigonometry method.
The data processing carried out in two (2) steps as follows:
1. Pre data processing directly on site
This step intended to early make sure the measurement comply with allowable tolerance.
2. Post data processing at office.
This step conducted by computer based after all measurement completed.
Data processing of horizontal control network consist of :
� Calculate arithmetic average angle and arithmetic average distance,
� Checking angle closure error,
� Checking linear closure error.
Data processing of vertical control network consist of :
� Checking calculation of total distance,
� Checking height difference,
� Checking height difference closure error.
Drawing work refers to following terms:
a. Drawing process carried out by computer using AutoCAD Land Development 2009 Soft-
ware.
b. Detail Situation Map made in 1 : 1000 scale with 1 meter contour interval,
c. The Situation map can produced in A1 paper size
d. Long section drawing made in 1 : 1000 scale of horizontal and 1 : 100 scale of vertical.
e. Cross section drawing made in 1 : 100 scale of horizontal and 1 : 100 scale of vertical.
f. All detail situation, natural or man-made shall plotted in Map / drawing and complement
with each symbols, comply with cartography standard as follows :
� Map Title,
� Map Index,
� Legend,
� Grid lines with 10 Cm interval,
� Bar scale
� Sheet guideline and North orientation
Information on date/month/year of measurement implementation and drawing
DRAFT 8 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
2 .9 Analysis of Topography Survey
Analysis of topography survey result intended to evaluate the quantity and quality of survey
implementation compared to terms of reference.
a. Analysis based on Quant ity
Based on proposed work quantity, the survey result shall meet the requirement, as
follows:
1. Quantity of topography survey consist of:
a. Preparatory works
b. Survey / measurement work
c. Data calculation work
d. Analysis of survey result
e. Drawing
f. Reporting
2. Quantity or total area of survey of Riau GFPP 275 MW is 10 Ha,
3. Total distance of levelling measurement is 5830.7 m
b. Analysis based on Quality
Analysis and checking the horizontal control network result shall refer to allowable
tolerance as describes at following table.
Table 2 - 2 Analysis of Topography survey
NO. ROUTE OF
SURVEY
TOTAL
DI STANCE
( m )
REQUI REMEN T SURVEY RESULT REMARK
1 BM 0 – BM-03 5,830.7 20mm �D 3.2 mm �D Passing the
requirement
2 .1 0 Survey Result
After whole field activities and office activities completed and produced description of
Benchmark, Map, Drawing and other related result. Following table describe summary of
survey result while the detail result shows in appendix.
Table 2 - 3 Coordinate of installed benchm ark.
Num ber
of BM X ( m eters) Y ( m eters) Elevat ion
BM 03 780508.180 59944.905 27.072
CP 03 780630.268 59965.075 23.044
Table 2 - 4 List of survey result
No. Survey Result Num ber of Sheet Scale
1 Topography Map 3 1: 2000 & 1: 1000
2 Land Profile of GFPP area 18 1: 2000 & 1: 1000
DRAFT 9 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
2 .1 1 Quant ity of Cut / Fill and Recom m ended Level
On construction projects it is often necessary to modify the existing ground levels to create
platforms to build on. Accurately calculating the volumes of soil that must be removed (cut)
or added (fill) to create the final ground levels is an essential part of the planning process.
For the GFPP 275 MW project, the cut & fill calculation was made to get a ballace quatity
(volume) of cut works and fill works as follows:
✄ Quantity of Cut/Fill : 165778.75/165343.39 M3 (remaining cut material: 435.35 M3)
✄ Recommended Level : 28.05 m
DRAFT 1 0 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
3 . Geotechnical I nvest igat ion
3 .1 Geology and Geotechnical Site I nvest igat ion Methodology
a . Standard and Reference
The Field investigation works was implemented based on common standards and references.
The standards and references are shown in Table 3-1 bellow.
Table 3 - 1 Applied standard reference of geotechnical invest igat ion.
NO.
STANDARD
TI TLE
Code Year Source
1 D 1452 – 80 1980 ASTM Drilling Operation
2 D 1586 - 99 1999 ASTM Standard Penetration Test (SPT)
3 D-1587 - 00. 2000 ASTM Undisturbed Sampling
4 D 2487 – 00 2000 ASTM Classification of Soils for Engineering Purpose
5 D 2488 – 00 2000 ASTM Description and Identification of Soils (Visual-Manual
Procedure)
6 1981 ISRM Basic Geotechnical Description of Rock Masses
7 D6032-02 2000 ASTM Rock Quality Designation ("RQD")
8 13-4691 1998 SNI Preparation of Geological Map
9 13-6185 1999 SNI Preparation of Geomorphological Map
10 D 2216 – 98 1998 ASTM Laboratory Determination of Water (Moisture) Content
of Soil and Rock by Mass
11 D 854 – 00 2000 ASTM Standard Test Method for Specific Gravity of Soil Solids
by Water Pycnometer
12 D 422 – 63 (98) 1998 ASTM Standard Test Method for Particle-Size Analysis of Soils
13 D 2166 – 00 2000 ASTM Standard Test Method for Unconfined Compressive
Strength of Cohesive Soil
14 D 2850 – 95 1995 ASTM Standard Test Method for Unconsolidated-Undrained
Triaxial Compression Test on Cohesive Soils
15 D 4746 – 95 1995 ASTM Standard Test Method for Consolidated-Undrained
Triaxial Compression Test on Cohesive Soils
16 D 2435 – 96 1996 ASTM Standard Test Method for One-Dimensional
Consolidation Properties of Soils
17 D 698 – 00a 2000 ASTM Standard Test Method for Laboratory Compaction
Characteristics of Soil Using Standard Effort (12,400 ft-
lbf/ft3(600 kN/m3))
18 D5878 - 08 1998 ASTM Standard Guides for Using Rock-Mass Classification
Systems for Engineering Purposes
b. Core Drilling
The core drilling carried out using drilling machine at each investigation points based on
general layout of power plant. The core drilling purposes are to identified the geological and
geotechnical condition of sub surface. The Direct Rotary Core Drilling was applied with fresh
water as drilling fluids. (ASTM D.2113 - 99). The work implementation shall carried out based
on following methods :
DRAFT 1 1 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
1. Location or site of bore hole should be clean up and level to make comfortable work
space. The drilling machine are setting up based on its drilling machine operat ion m anual,
2. The application of drilling fluids are very important, to assure the cores un-eroded, and
cores taken fully recovery and keeps identity of soil/rock.
3. When drilling reach overburden layers or un-stable layers, all potential holes collapse
shall be avoid and protect by casing.
4. The ground water table in each bore hole recorded every day during the drilling work
implemented and also after drilling complete. Some special condition arise (artesian or
water loose) have to recorded also.
5. Prepare the Drilling Daily Report, included:
� Date of drilling implementation,
� Location and number of hole,
� Elevation of water table,
� Name and type of drilling machine, type of core barrel applied, diameter of bore hole
and depth of casing installed,
� Description of core,
� Name of Bore Master,
� Any necessary information about the drilling activities.
6. The core placed into transparent plastic in order to protect it and placed into core box
orderly based on drilling depth. On the cover of core box put label or information about:
� Name / Project Location
� Number of Bore hole
� Sequence number of core boxes
� Depth of drilling of each box.
7. Immediately conduct the core description and continue with log bore preparation. The
log bore contains as follows :
� Date of drilling implementation,
� Length of core,
� Rock Quality Designation (RQD),
� Water table,
� Rock symbols and its description,
� Result of on site tests and another necessary/ important description for design needs.
c. Standard Penet rat ion Test ( SPT)
The Standard Penetration Test (SPT) was carried out on each holes during drilling activities,
based on the USBR specification in Earth Manual Book, ASTM D 1586-99 or SNI 03-4148. It
was conduct using Raymond Sampler and Drive Hammer with 140 + 2 lb (63,5+ 1 kg) weight,
every stated depth level.
It was recorded every 15 cm penetration of 75 cm falling of hammer. The SPT report consist
of :
� Depth of test
� Number of hit for 15 cm penetration
The N-value is total number of hit for 30 cm penetration.
d. Perm eability Test and Ground W ater Monitor ing
The Falling Head Test method was applied for non-permeable soil layers (clay and silt) and
Constant Head Test method was applied for permeable soil layers (sand, gravel). The testing
DRAFT 1 2 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
carried out based on BS standard 5930 -1999 and Lugeon Test method based on Earth
Manual. Interpretation of the test result was referred to SNI 2436:2008 as shown in following
table
Table 3 - 2 Perm eability level (SNI 2436 : 2008)
Value of perm eability
( cm / sec) Level of perm eability
> 10-2 Very high
10-2 - 10-3 High
10-4 - 10-5 Medium
10-6 Low
<10-6 Very low
e. Soil and Ground W ater Sam ples
The undisturbed sample of soil extracted using Shelby Tube Sampler in drilling hole at
designed depth and carried out based on ASTM D-1587 - 00. After soil sample trapped in
shelby tube, sealed both side of tube paraffin, and then sending to laboratory to analysis of
its properties.
The soil sample will process in Soil Mechanic laboratory and some of them will process in
chemical soil laboratory. Whereas water sample of bore hole will process in chemical
laboratory. The chemical test will focus in corrosive parameter of soil and ground water.
g. Soil Mechanic Test
The soil mechanic laboratory test consists of 2 major parameter, physical (index) properties
and mechanical (engineering) properties.
Physical Propert ies :
✄ Water content
✄ Specific Gravity
✄ Particle-size analysis
✄ Atterberg Limits
✄ Unit weight
Mechanical Propert ies :
✄ Triaxial ❈�✁✂☎✆✝✝✞�✟ Test
✄ Consolidation Test
✄ Direct Shear
✄ ❯✟❝�✟❢✞✟✆ ❈�✁✂☎✆✝✞�✟ ❚✆✝✠
3 .2 Geological Condit ion
According to the field geological mapping that have been conducted, the lithology type
emerges in the investigation area typically consists of silt and clay. Typically showing massive
DRAFT 1 3 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
to interbeded feature, gently diping of bedding with gently folding area structures commonly
found in the area.
Figure 3 - 1 Typical bedrock encountered at invest igat ion.
According to regional gelogy map of Riau Quadrangle this rock unit is part of Minas formation
of Quarternary age (pleistocene) assocciated with gravel and sand deposits which is
sometimes interpreted as fluvial origin.
No fault structures encountered in the area, according to regional geology map of Riau
Quadrangle (scale 1: 250,000 Clarke. W et al 1982) the nearest large scale fault structure
from the area approximately 12 km.
3 .3 Core Drilling and I nsitu Test
In order to understand the behavior, distribution, geological and geotechnical characteristics
of rocks in investigation site. Three drilling locations had had been undertaken. Namely BH-
01, BH-02, and BH-03.
Following map shows the layout of soil investigation area, where the drillholes and land
boundary situated and the site investigation work is undertaken.
DRAFT 1 4 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Figure 3 - 2 Map layout of soil invest igat ion and geoelect r ic survey.
Lithology of site investigation area, according to drilling result consists of consolidated fine
grained soil material: silty Clay and Clay. Following table describe soil and rock layer
occupying the investigated area.
Table 3 - 3 Summary of lithology unit for each borehole locat ion.
No. BH- I D Depth ( m ) Lithology Hardness
1 BH- 0 1
0 – 0.40 clayey SILT
Top Soil (D) soft, dull, blackish
brown, clayey SILT, moist,
frequent small root encountered.
DRAFT 1 5 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
No. BH- I D Depth ( m ) Lithology Hardness
0.40 – 1.00 silty CLAY
firm - stiff (MW-HW) of light
brown - yellowish brown of
moist silty CLAY, some fine
sand and silt encountered.
1.00 – 27.00 CLAY
very stiff, (MW-HW) of greyish
brown - dark brown CLAY.
27.00 – 30.00 CLAY very stiff, (MW-HW) of
massive greyish brown - dark
brown CLAY.
2 BH- 0 2
0 – 0.60 clayey SILT Top Soil (D) soft, dull, blackish
brown, clayey SILT, moist,
frequent small root encount
0.60 – 3.45 silty CLAY
firm - stiff (MW-HW) of light
brown - yellowish brown of
moist silty CLAY, some fine sand and silt encountered.
3.45 – 30.00 CLAY
very stiff, (MW-HW) of
massive greyish brown - dark brown lean CLAY.
3 BH- 0 3
0 – 1.20 Clayey SILT
top soil (D), soft of blackish
brown clayey SILT, moist, root frequent.
1.20 - 5.60 Clayey SILT
(MW-HW), soft - firm of light
brown - greyish brown silty
CLAY. Medium to high plasticity
5.60 – 30.00 CLAY
(MW), stiff - very stiff of dark
grey to light grey massive lean
clay with silt. Medium to high
plasticity.
In addition to geological description we also undertook the Field Standar Penetration Test
(SPT) were performed by 1.5 m interval of testing in regular basis. following tables show field
record of SPT data from each borehole.
Table 3 - 4 SPT field record of BH-01.
No Depth N1 N2 N3 NSPT ( N2 + N3 )
1 1.50 - 1.95 3 8 10 18
2 3,00 - 3.45 3 10 10 20
3 4.50 - 4.95 5 8 10 18
4 6.00 - 6.45 2 4 2 6
5 7.50 - 7.95 2 6 9 15
6 9.00 - 9.45 5 10 17 27
7 10.50 - 10.95 8 15 18 33
8 12.00 - 12.45 7 20 18 38
9 13.50 - 13.95 5 12 15 27
10 15.00 - 15.45 8 18 18 36
11 16.50 - 16.95 8 18 30 48
DRAFT 1 6 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
No Depth N1 N2 N3 NSPT ( N2 + N3 )
12 18.00 - 18.45 5 16 34 50
13 19.50 - 19.95 10 21 30 >50
14 21.00 - 21.45 11 15 32 47
15 22.50 - 22.95 8 26 33 >50
16 24.00 - 24.45 17 28 26 >50
17 25.50 - 25.95 9 26 34 >50
18 27.00 - 27.45 15 40 43 >50
19 28.50 - 28.95 20 35 36 >50
20 30.00 - 30.45 9 24 34 >50
Table 3 - 5 SPT field record of BH-02.
No Depth N1 N2 N3 NSPT ( N2 + N3 )
1 1.50 - 1.95 1 1 1 2
2 3.00 - 3.45 2 3 4 7
3 4.50 - 4.95 5 10 12 22
4 6.00 - 6.45 6 10 16 26
5 7.50 - 7.95 7 19 30 49
6 9.00 - 9.45 8 15 34 49
7 10.50 - 10.95 9 18 27 45
8 12.00 - 12.45 10 20 30 50
9 13.50 - 13.95 10 20 44 >50
10 15.00 - 15.45 11 18 33 >50
11 16.50 - 16.95 15 32 38 >50
12 18.00 - 18.45 20 28 25 >50
13 19.50 - 19.95 10 19 30 49
14 21.00 - 21.45 14 29 28 >50
15 22.50 - 22.95 9 28 45 >50
16 24.00 - 24.45 7 12 25 37
17 25.50 - 25.95 10 18 20 38
18 27.00 - 27.45 7 18 40 >50
19 28.50 - 28.95 20 23 35 >50
20 30.00 - 30.45 22 24 36 >50
Table 3 - 6 SPT field record of BH-03.
No Depth N1 N2 N3 NSPT ( N2 + N3 )
1 1.50 - 1.95 2 4 6 10
DRAFT 1 7 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
No Depth N1 N2 N3 NSPT ( N2 + N3 )
2 3.00 - 3.45 3 3 5 8
3 4.50 - 4.95 2 2 6 8
4 6.00 - 6.45 2 5 6 11
5 7.50 - 7.95 4 8 10 18
6 9.00 - 9.45 6 12 16 28
7 10.50 - 10.95 8 14 20 34
8 12.00 - 12.45 5 10 25 35
9 13.50 - 13.95 11 15 13 28
10 15.00 - 15.45 6 125 18 30
11 16.50 - 16.95 18 25 21 46
12 18.00 - 18.45 6 12 20 32
13 19.50 - 19.95 6 14 23 37
14 21.00 - 21.45 12 20 40 60
15 22.50 - 22.95 8 20 30 50
16 24.00 - 24.45 29 36 36 >50
17 25.50 - 25.95 14 27 50 >50
18 27.00 - 27.45 15 25 30 >50
19 28.50 - 28.95 15 28 31 >50
20 30.00 - 30.45 16 26 39 >50
Following tables described the permeability result obtained from field permeability test, from
the test results we might conclude that the permeability value of investigated area ranging
from 10-5 to 10-4 cm/s therefore categorized as medium permeability.
Table 3 - 7 Perm eability insitu test results.
No. BH- I D Depth ( m ) Perm eability
( cm / sec) No BH- I D Depth ( m )
Perm eability
( cm / sec)
1 BH- 0 1 0 – 5 2.22E-04 2 BH- 0 2 2.95 – 5 2.10E-05
2.8 – 10 1.24E-04 8.9 – 10 2.31E-05
2.8 – 15 7.40E-06 14.8 – 15 4.13E-05
14.8 – 20 1.17E-06 17.8 – 20 1.35E-05
19.5 – 25 1.85E-06 20.8 – 25 1.82E-06
19.3 – 30 2.21E-06 20.8 – 30 7.50E-07
3 BH- 0 3 2.8 – 5 9.96E-05
8.8 – 10 4.86E-05
DRAFT 1 8 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
14.8 – 15 7.43E-05
17.8 – 20 5.66E-06
23.9 – 25 5.27E-06
20.8 – 30 7.50E-07
Figure 3 - 3 Docum entat ion of dr illing acit ivit y at invest igat ion area
3 .4 Chem ical Propert ies
During implementation of drilling works, ground water of borehole was taken for water quality
laboratory test. Each borehole represented by one groundwater sample obtained after drilling
work, one sample taken at 10 meter hole depth and other at 30 meter hole depth. Following
table is summary of the laboratory result and the detail result attached in Appendix G.
Table 3 - 8 Sum m ary of ground water quality result
No. Parameter Unit BH-01 BH-02 BH-03
Depth 28 m Depth 10 m Depth 20 m
1 Acidity (as CaCO3) mg/L
(CaCO3) 133 �✁ 104
2 Alkalinity (as CaCO3) mg/L
(CaCO3) 95 328 132
3 Hydrogene Sulphide (H2S) mg/L 0.21 28 2
4 Soluble Chloride (Cl) mg/L 21 31 94
5 Soluble Sulphate (SO
4) ppm 36 34 104
Documentation of Drilling acitivity
BH-01
Documentation of Drilling acitivity
BH-02
Documentation of Drilling acitivity BH-03
DRAFT 1 9 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
6 Organic Content mg/L 366 702 304
Table 3 - 9 Sum m ary of Soil Chem ist ry result
No. Parameter Unit BH-01 BH-02 BH-03
Depth 28 m Depth 10 Depth 20
1 pH - 7.3 9.62 9.66
2 Acidity Mg/Kg (CO3)
64.92 66.05 65.51
3 Alkalinity mg/Kg (HCO3)
264.01 266.83 266.59
4 Sulphur Trioxide (SO3) ppm 9.62 9.76 9.48
5 Soluble Chloride (Cl) ppm 67.32 67.19 67.29
6 Soluble Sulphate (SO
4) ppm 24.01 24.44 24.62
7 Organic Content % 9.00 9.11 9.17
3 .5 Geoelect r ical Survey
3 .5 .1 I m plem entat ion of Survey W orks
The geoelectric survey work that has been done in is 3 (three) points V.E.S. (Vertical Electrical
Sounding), where the placement of dots suspect attention to morphological aspects, geology
and aspects of local physical infrastructure located at the location of the investigation. Coor-
dinates of geoelectric points can be seen in Table 3.10, while the layout map of the geoelectric
investigation points can be seen in Figure 3.5
Table 3 - 1 0 Sum m ary of ground water quality result .
Point X ( m ) Y ( m ) Z ( m )
GL-1 780533.750 59873.540 28.62
GL-2 780544.970 59711.440 28.97
GL-3 780566.520 59551.520 31.05
DRAFT 2 0 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
I m plem entat ion of geoelect r ical survey at GL-1
I m plem entat ion of geoelect r ical survey at GL-2
Figure 3 - 4 I m plem entat ion of geoelect r ical survey at invest igat ion area
The Geolistrical survey try to penetrate 100 meter of ground consist of 3 (three) points of
VES, distributed on future power plant area. Following figure describe lay out of the survey.
I m plem entat ion of geoelect r ical survey at GL-3
DRAFT 2 1 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Figure 3 - 5 Layout of geoelect rical survey
3 .5 .2 Result of Geoelect r ical Survey
Based on the results of interpretation of geoelectric data correlated with the drill log data and
regional geology sheet Pekanbaru, then the arrangement of layers of soil / rock contained in
the area of investigation based on the type of resitivity can be grouped as follows:
1. The first layer, interpreted as top soil with a resistivity value of its type ranges from
2100 to 2938 ohm-meters. This unit is found from the local surface to a depth of 1.53
meters with a thickness ranging from 0.64 meters to 1.53 meters.
DRAFT 2 2 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
2. The second layer, interpreted as a unit of silty clay, with a resistivity value of the type
ranges from 504 to 784 ohm-meter. This layer has a thickness ranging from 2.17 meters
to 4.39 meters.
3. The third layer, interpreted as a unit of clay, with the resistivity value of the species
ranged from 8.7 - 13 ohm-meter. This layer has a thickness ranging from 27.63 to 30.00
meters.
4. The fourth layer, interpreted as a unit of clayey sand, with resistivity value of the species
ranges from 53 to 79 ohm-meters. This layer has a thickness This layer has a thickness
of more than 66 meters
Geological Section Based on Geoelectric Interpretation and Drilling Result (Bor Log) can be
seen in Figure 3-6, while Field Data & Interpretation Curve of Geoelectric Survey Results can
be seen in Appendix.
Figure 3 - 6 Geological cross sect ion based on geoelect r ical data (sect ion GL-1 to GL-3) .
3 .6 Geotechnical I nvest igat ion and Foundat ion
3 .6 .1 Recom m endat ion of Design Param eter
Based on field investigation data which includes 3 boreholes with SPT, the general soil
stratification of Gas Fired Power Plant 275 MW Riau area are consist of Clay and Silty Clay soil
DRAFT 2 3 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
type. The strength and consistency of soil layers increased within depth. Ground water level
was found between -4.00 to -9.00 m from ground surface elevation.
Soil properties are interpreted from field data as describes in following tables.
Table 3 - 1 1 Param eter design of BH-01.
�✁✂✁✄☎✆☎✂ ✝☎✞✟✠✡ ☛☞ ✌✍✎✏✑
✝✒✓✔✕ ✡✎✞�✆ ✞✖✗✘ ✙ ✞✚ ✛✜ ✢✜ ☎✚ ☎✜ ✣✤ ✠ ✥✦✧
★✥✩ ★✪✘✖✫✬✭✔✩ ✆✮✓✒ ★✯✡✬✥✰✩ ★✯�✦✩ ★✯�✦✩ ★✱✒✲✩ ★✯�✦✩ ★✯�✦✩ ★✥✬✤✩ ★✯�✦✩
✳✴✳✳ ✵✶✴✳✳ ✷✸✹✺ ✵✻✴✼✶ ✵✳✽✴✳✾ ✽✳✴✳✵ ✾✳✴✼✻ ✾✿❀✵✳✶ ✾✾❀✻✾✼ ✾✳✻✴❁❁ ❂❁❀✼❂❂
✵✴✿✳ ✵✶✴✳✳ ✷✸✹✺ ✵✻✴✼✶ ✵✵✽✴✶✾ ✽✳✴✳✵ ✾✳✴✼✻ ✾❂❀❂❁✳ ✾✿❀✽✾✻ ✾✵✼✴✵✳ ❂✻❀✻✵✿
✽✴✳✳ ✾✳✴✳✳ ✷✸✹✺ ✵✻✴✼✶ ✵✽✽✴❁✶ ✽✽✴✽✿ ✾✳✴✼✻ ✽✾❀✿✽✽ ✾✻❀❂✳✿ ✾✾❂✴✵✻ ✶✻❀✳✼✾
❁✴✿✳ ✵✶✴✳✳ ✷✸✹✺ ✵✶✴✽✵ ✵✵✾✴❁✵ ✽✳✴✳✵ ✾✵✴✻✻ ❁❁❀✿✼✼ ❁✳❀✾✻✶ ✾✾✾✴✽❁ ✶❁❀✻✻✿
✼✴✳✳ ✼✴✳✳ ✷✸✹✺ ✵✶✴✽✵ ✽✶✴✿✾ ✵✵✴✿✳ ✾✵✴✻✻ ✵✿❀✾❂✳ ✵✽❀✶✳❂ ✵✿✶✴✶✽ ❁✵❀✳✾✶
❂✴✿✳ ✵✿✴✳✳ ✷✸✹✺ ✵✶✴✽✵ ✻✶✴❁✽ ✾✿✴✳✳ ✾✵✴✻✻ ✽✻❀✳✾✵ ✽✿❀✾✶❁ ✾✵✽✴✾✿ ❂❂❀✼✿✾
✻✴✳✳ ✾❂✴✳✳ ✷✸✹✺ ✵✶✴✶✽ ✵❂✽✴❁✿ ❁✿✴✳❁ ✾✵✴❁✼ ✼✵❀✾✿✻ ✿✿❀✿✿✵ ✾✿❂✴✻❁ ✵✵❂❀✾❁✻
✵✳✴✿✳ ✽✽✴✳✳ ✷✸✹✺ ✵✶✴✶✽ ✾✵✿✴✽✳ ✿✿✴✳✼ ✾✵✴❁✼ ❂✼❀✳❁✳ ✼✶❀✻✿✿ ✾❂✼✴✳✼ ✵✽✿❀✶✵✽
✵✾✴✳✳ ✽✶✴✳✳ ✷✸✹✺ ✵✶✴✶✽ ✾✿✵✴✾✶ ✼✽✴❁✵ ✾✵✴❁✼ ✶✶❀❂❁✶ ✶✳❀❁❂✻ ✾✶✻✴❂✶ ✵✿✳❀✶✼✾
✵✽✴✿✳ ✾❂✴✳✳ ✷✸✹✺ ✵✶✴✶✽ ✵✶✳✴✼❂ ❁✿✴✳❁ ✾✵✴❁✼ ✼✽❀✶✵✾ ✿❂❀✶✼✼ ✾✼✵✴✾❂ ✵✾✳❀✿❁✻
✵✿✴✳✳ ✽✼✴✳✳ ✷✸✹✺ ✵✶✴✶✽ ✾❁✽✴❁❂ ✼✳✴✳❂ ✾✵✴❁✼ ✶✿❀✻✻✾ ❂❂❀✻✶✳ ✾✶✼✴✻✽ ✵❁❂❀✼✼✳
✵✼✴✿✳ ❁✶✴✳✳ ✷✸✹✺ ✵✶✴❂✼ ✽❁✾✴✳✵ ✶✳✴✵✵ ✾✳✴❂✼ ✻✽❀✶✶✳ ✶✿❀✿❂✾ ✽✵✿✴✳✳ ✵✶✳❀❂❁✽
✵✶✴✳✳ ✿✳✴✳✳ ✷✸✹✺ ✵✶✴❂✼ ✽✿✼✴✾✼ ✶✽✴❁✿ ✾✳✴❂✼ ✻❂❀❂✻✾ ✶✻❀✵✽❂ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✵✻✴✿✳ ✿✳✴✳✳ ✷✸✹✺ ✵✶✴❂✼ ✽✿✼✴✾✼ ✶✽✴❁✿ ✾✳✴❂✼ ✻❂❀❂✻✾ ✶✻❀✵✽❂ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✾✵✴✳✳ ❁❂✴✳✳ ✷✸✹✺ ✵✶✴❂✼ ✽✽❁✴✶✻ ❂✶✴❁❁ ✾✳✴❂✼ ✻✵❀✻✾❁ ✶✽❀❂✶✻ ✽✵✾✴✻✽ ✵❂✶❀✵❂✽
✾✾✴✿✳ ✿✳✴✳✳ ✷✸✹✺ ✵✶✴✻❂ ✽✵✼✴✽✽ ✶✽✴❁✿ ✾✾✴✵✽ ✵✾✶❀✳✶✽ ✵✵✿❀❂✾✶ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✾❁✴✳✳ ✿✳✴✳✳ ✷✸✹✺ ✵✶✴✻❂ ✽✵✼✴✽✽ ✶✽✴❁✿ ✾✾✴✵✽ ✵✾✶❀✳✶✽ ✵✵✿❀❂✾✶ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✾✿✴✿✳ ✿✳✴✳✳ ✷✸✹✺ ✵✶✴✻❂ ✽✵✼✴✽✽ ✶✽✴❁✿ ✾✾✴✵✽ ✵✾✶❀✳✶✽ ✵✵✿❀❂✾✶ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✾❂✴✳✳ ✿✳✴✳✳ ✷✸✹✺ ✵✻✴✳✳ ✽✾✽✴✳✿ ✶✽✴❁✿ ✾✾✴❁✾ ✵✽✻❀✳❂✻ ✵✾✿❀❁✼✻ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✾✶✴✿✳ ✿✳✴✳✳ ✷✸✹✺ ✵✻✴✳✳ ✽✾✽✴✳✿ ✶✽✴❁✿ ✾✾✴❁✾ ✵✽✻❀✳❂✻ ✵✾✿❀❁✼✻ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
✽✳✴✳✳ ✿✳✴✳✳ ✷✸✹✺ ✵✻✴✳✳ ✽✾✽✴✳✿ ✶✽✴❁✿ ✾✾✴❁✾ ✵✽✻❀✳❂✻ ✵✾✿❀❁✼✻ ✽✵✻✴✳❂ ✵✶✿❀✶✽✳
Table 3 - 1 2 Param eter design of BH-02.
�✁✂✁✄☎✆☎✂ ✝☎✞✟✠✡ ☛☞ ✌✍✎✏❃
✝✒✓✔✕ ✡✎✞�✆ ✞✖✗✘ ✙ ✞✚ ✛✜ ✢✜ ☎✚ ☎✜ ✣✤ ✠ ✥✦✧
★✥✩ ★✪✘✖✫✬✭✔✩ ✆✮✓✒ ★✯✡✬✥✰✩ ★✯�✦✩ ★✯�✦✩ ★✱✒✲✩ ★✯�✦✩ ★✯�✦✩ ★✥✬✤✩ ★✯�✦✩
✳✴✳✳ ✾✴✳✳ ✷✸✹✺ ✵✶✴✻✿ ✶✴✼✵ ❁✴✳✳ ✾✶✴✵❁ ✶❀✾❁❂ ❂❀✾✼✾ ✵✳✿✴✳✼ ✵✼❀❂✼✵
✵✴✿✳ ✾✴✳✳ ✷✸✹✺ ✵✶✴✻✿ ✻✴✿✾ ❁✴✳✳ ✾✶✴✵❁ ✻❀✵✵✵ ✶❀✳✾❁ ✵✳✶✴❁✳ ✵❂❀✻✽❂
✽✴✳✳ ❂✴✳✳ ✷✸✹✺ ✵✻✴✳✳ ✽✶✴❁✶ ✵✽✴✳✳ ✾✾✴✵✽ ✵✿❀✻✾❂ ✵❁❀✽✻✵ ✵✼✽✴✽✻ ❁✽❀✼✵❂
❁✴✿✳ ✾✾✴✳✳ ✷✸✹✺ ✵✻✴✳✳ ✵✾✿✴❁❁ ✽✼✴✼✻ ✾✾✴✵✽ ✿✵❀✻✾❁ ❁✼❀✻✵✿ ✾✽✼✴✶✳ ✻❂❀❁✾✾
✼✴✳✳ ✾✼✴✳✳ ✷✸✹✺ ✵✻✴✳✳ ✵✾✳✴❁✾ ❁✽✴✽❂ ✾✼✴✾✵ ✻✿❀✽✶✻ ✶❁❀✿✼✵ ✾✿✵✴❂✵ ✵✵✵❀✾✳✽
❂✴✿✳ ❁✻✴✳✳ ✷✸✹✺ ✵✶✴✽❁ ✾✽✵✴✻✶ ✶✵✴❂✶ ✾✼✴✾✵ ✵✶✽❀❂✿✶ ✵✼✾❀✶✻✻ ✽✳✻✴✾✼ ✵❂✽❀✼❂✶
DRAFT 2 4 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✁✄☎✆☎✂ ✝☎✞✟✠✡ ☛☞ ✌✍✎✏✑
✝✒✓✔✕ ✡✎✞�✆ ✞✖✗✘ ✙ ✞✚ ✛✜ ✢✜ ☎✚ ☎✜ ✣✤ ✠ ✥✦✧
★✥✩ ★✪✘✖✫✬✭✔✩ ✆✮✓✒ ★✯✡✬✥✰✩ ★✯�✦✩ ★✯�✦✩ ★✱✒✲✩ ★✯�✦✩ ★✯�✦✩ ★✥✬✤✩ ★✯�✦✩
✳✴✵✵ ✶✳✴✵✵ ✷✸✹✺ ✻✼✴✽✶ ✾✽✿✴✾✶ ✼✻✴❀✼ ✾✿✴✾✻ ✻✼❀❁✻✾✼ ✻✿❂❁✼✼❀ ✽✻✻✴✵✽ ✻❀❂❁✼✽✼
✻✵✴❂✵ ✶❂✴✵✵ ✷✸✹✺ ✻✼✴✽✶ ✾✽✿✴✾✳ ❀❂✴✻✵ ✾❂✴✶✽ ✻❀✻❁❂✾✶ ✻❂✾❁❂✾✳ ✽✵✶✴✾✳ ✻✿❀❁❀✵✻
✻✾✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✼✾ ✾✿✿✴✻✵ ✼✽✴✶❂ ✾❂✴✶✽ ✻✳✽❁✻✿❂ ✻❀✻❁❀❀✽ ✽✻❂✴✼✿ ✻✼✻❁✼✻✶
✻✽✴❂✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✼✾ ✽✻✻✴✶✼ ✼✽✴✶❂ ✾✾✴✶✾ ✻✽✶❁✿❂✵ ✻✾✻❁✶❀✶ ✽✻❀✴✵✶ ✻✼✽❁✾✼✳
✻❂✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✼✾ ✽✻✶✴✼✻ ✼✽✴✶❂ ✾✾✴✶✾ ✻✽✿❁✵✳✵ ✻✾✾❁❀❀✽ ✽✻✼✴✻✵ ✻✼✶❁✿✾✵
✻✿✴❂✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✼✾ ✽✻❀✴✼❂ ✼✽✴✶❂ ✾✾✴✶✾ ✻✽❀❁✶✵✶ ✻✾✽❁✳❂✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✻✼✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✾✿ ✽❀✶✴✳❂ ✼✽✴✶❂ ✾✵✴✼✵ ✻✵✿❁❀❂✽ ✳❀❁✻✼✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✻✳✴❂✵ ✶✳✴✵✵ ✷✸✹✺ ✻✳✴✾✿ ✽✿❀✴✶❂ ✼✻✴❀✼ ✾✵✴✼✵ ✻✵✶❁✿✻✼ ✳❂❁✾✶✶ ✽✻❀✴✵❂ ✻✼✽❁✾✳❂
✾✻✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✽❀✶✴✳❂ ✼✽✴✶❂ ✾✵✴✼✵ ✻✵✿❁❀❂✽ ✳❀❁✻✼✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✾✾✴❂✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✽❀✶✴✳❂ ✼✽✴✶❂ ✾✵✴✼✵ ✻✵✿❁❀❂✽ ✳❀❁✻✼✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✾✶✴✵✵ ✽❀✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✾✳✻✴✶✻ ✿✻✴❀✶ ✾✵✴❀✽ ❀❀❁❀❂✾ ❀✵❁✳✻✽ ✾✳✵✴✾✼ ✻❂✻❁✶✾✶
✾❂✴❂✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✽✳✽✴✼✵ ✼✽✴✶❂ ✾✵✴❀✽ ✻✵❂❁✵❀✻ ✳❂❁✼✾✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✾❀✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✽✳✽✴✼✵ ✼✽✴✶❂ ✾✵✴❀✽ ✻✵❂❁✵❀✻ ✳❂❁✼✾✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✾✼✴❂✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✽✳✽✴✼✵ ✼✽✴✶❂ ✾✵✴❀✽ ✻✵❂❁✵❀✻ ✳❂❁✼✾✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✽✵✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✼ ✽✳✽✴✼✵ ✼✽✴✶❂ ✾✵✴❀✽ ✻✵❂❁✵❀✻ ✳❂❁✼✾✼ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
Table 3 - 1 3 Param eter design of BH-03.
�✁✂✁✄☎✆☎✂ ✝☎✞✟✠✡ ☛☞ ✌✍✎✏✰
✝✒✓✔✕ ✡✎✞�✆ ✞✖✗✘ ✙ ✞✚ ✛✜ ✢✜ ☎✚ ☎✜ ✣✤ ✠ ✥✦✧
★✥✩ ★✪✘✖✫✬✭✔✩ ✆✮✓✒ ★✯✡✬✥✰✩ ★✯�✦✩ ★✯�✦✩ ★✱✒✲✩ ★✯�✦✩ ★✯�✦✩ ★✥✬✤✩ ★✯�✦✩
✵✴✵✵ ✻✵✴✵✵ ✷✸✹✺ ✻✳✴✵✵ ✶✿✴✼✻ ✻❀✴❂✵ ✾✾✴❂❀ ✾✵❁✳✵✶ ✻✼❁✼✶✽ ✻❀✶✴✻✶ ❂✵❁✵❀✽
✻✴❂✵ ✻✵✴✵✵ ✷✸✹✺ ✻✳✴✵✵ ❂✻✴❀✾ ✻❀✴❂✵ ✾✾✴❂❀ ✾✽❁✵✳❂ ✾✵❁✼✻✳ ✻❀✳✴✿✼ ❂✽❁❂✼❂
✽✴✵✵ ✼✴✵✵ ✷✸✹✺ ✻✳✴✵✵ ✶✽✴✿❀ ✻✶✴❂✵ ✾✾✴❂❀ ✻✳❁❂✵✾ ✻❀❁❂❀✳ ✻❀✵✴✽✼ ✶❀❁❀✿✽
✶✴❂✵ ✼✴✵✵ ✷✸✹✺ ✻✼✴✻✳ ✶❂✴✽✵ ✻✶✴❂✵ ✾✾✴❂❀ ✾✵❁✾✾✳ ✻✼❁✾✽❂ ✻❀✾✴✽❂ ✶✼❁✳✿✼
✿✴✵✵ ✻✻✴✵✵ ✷✸✹✺ ✻✼✴✻✳ ✿✶✴✵✽ ✻✳✴✵✵ ✾✾✴❂❀ ✾✼❁❂✳✻ ✾❂❁❀❀✽ ✻✳✾✴✻✽ ✿✻❁✳❂✿
❀✴❂✵ ✻✼✴✵✵ ✷✸✹✺ ✻❀✴❀✻ ✳✼✴✶✶ ✽✵✴✵✻ ✾✽✴✳✽ ❂✿❁✶✳❂ ❂✵❁❂❀✼ ✾✾❂✴✼✻ ✼❀❁✳✵✾
✳✴✵✵ ✾✼✴✵✵ ✷✸✹✺ ✻❀✴❀✻ ✻❂❂✴✳✶ ✶✿✴❀✻ ✾✽✴✳✽ ✼✳❁✶✳✽ ✼✵❁✻✾✻ ✾✿✵✴✳✵ ✻✾✵❁✻✼✶
✻✵✴❂✵ ✽✶✴✵✵ ✷✸✹✺ ✻✳✴✵✶ ✻✳✽✴✻✿ ❂✿✴❀✽ ✾✶✴❂✽ ✻✾✾❁✳✽✵ ✻✵✳❁❀✶✼ ✾❀✼✴✿✿ ✻✽✼❁❂✳✼
✻✾✴✵✵ ✽❂✴✵✵ ✷✸✹✺ ✻✳✴✵✶ ✾✵✻✴❂✶ ❂✼✴✶✵ ✾✶✴❂✽ ✻✾✼❁✾✿✵ ✻✻✶❁❂✵❀ ✾✼✾✴✶✵ ✻✶✾❁✿❂❀
✻✽✴❂✵ ✾✼✴✵✵ ✷✸✹✺ ✻✳✴✵✶ ✻✿✽✴✻✿ ✶✿✴❀✻ ✾✶✴❂✽ ✻✵✽❁✼✽❂ ✳✾❁❀✵✻ ✾✿✶✴✾❀ ✻✾✽❁❂✿✼
✻❂✴✵✵ ✽✵✴✵✵ ✷✸✹✺ ✻✳✴✵✶ ✻❀✿✴✿✼ ❂✵✴✵❂ ✾✶✴❂✽ ✻✻✾❁✶✶✻ ✻✵✵❁✽✼✶ ✾❀✵✴✳✿ ✻✽✵❁✶✶✽
✻✿✴❂✵ ✶✿✴✵✵ ✷✸✹✺ ✻✳✴✵✶ ✾❀✽✴❂✽ ❀✿✴❀❀ ✾✶✴❂✽ ✻❀✶❁✵❀❂ ✻❂❂❁✶✵✳ ✽✻✵✴✼✾ ✻❀❂❁❂✼❀
✻✼✴✵✵ ✽✾✴✵✵ ✷✸✹✺ ✻✼✴❂✵ ✾✻❂✴✶✽ ❂✽✴✽✳ ✾✵✴✼✼ ✿✼❁✻✵✵ ✿✻❁✼✼✵ ✾❀❀✴✽✶ ✻✽❀❁✻✼✳
✻✳✴❂✵ ✽❀✴✵✵ ✷✸✹✺ ✻✼✴❂✵ ✾✶✳✴✵✳ ✿✻✴❀✶ ✾✵✴✼✼ ❀✼❁❀✶✵ ❀✻❁❂✶✳ ✾✳✵✴✾✼ ✻❂✻❁✶✾✶
✾✻✴✵✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✶ ✾✿✼✴✾✶ ✼✽✴✶❂ ✾✶✴✻✾ ✻✿✻❁✾✾✽ ✻✶✶❁✾✵❀ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
✾✾✴❂✵ ❂✵✴✵✵ ✷✸✹✺ ✻✳✴✻✶ ✾✿✼✴✾✶ ✼✽✴✶❂ ✾✶✴✻✾ ✻✿✻❁✾✾✽ ✻✶✶❁✾✵❀ ✽✻✳✴✵❀ ✻✼❂❁✼✽✵
DRAFT 2 5 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✁✄☎✆☎✂ ✝☎✞✟✠✡ ☛☞ ✌✍✎✏✑
✝✒✓✔✕ ✡✎✞�✆ ✞✖✗✘ ✙ ✞✚ ✛✜ ✢✜ ☎✚ ☎✜ ✣✤ ✠ ✥✦✧
★✥✩ ★✪✘✖✫✬✭✔✩ ✆✮✓✒ ★✯✡✬✥✑✩ ★✯�✦✩ ★✯�✦✩ ★✰✒✱✩ ★✯�✦✩ ★✯�✦✩ ★✥✬✤✩ ★✯�✦✩
✲✳✴✵✵ ✶✵✴✵✵ ✷✸✹✺ ✻✼✴✶✶ ✽✳✾✴✿✾ ✼✽✴✳✶ ✲✵✴✼✼ ✻✵✾❀✿✵✿ ✾✾❀❁✼✿ ✽✻✾✴✵✿ ✻✼✶❀✼✽✵
✲✶✴✶✵ ✶✵✴✵✵ ✷✸✹✺ ✻✼✴✶✶ ✽✳✾✴✿✾ ✼✽✴✳✶ ✲✵✴✼✼ ✻✵✾❀✿✵✿ ✾✾❀❁✼✿ ✽✻✾✴✵✿ ✻✼✶❀✼✽✵
✲✿✴✵✵ ✶✵✴✵✵ ✷✸✹✺ ✻✼✴✶✶ ✽✳✾✴✿✾ ✼✽✴✳✶ ✲✵✴✼✼ ✻✵✾❀✿✵✿ ✾✾❀❁✼✿ ✽✻✾✴✵✿ ✻✼✶❀✼✽✵
✲✼✴✶✵ ✶✵✴✵✵ ✷✸✹✺ ✻✼✴✶✶ ✽✳✾✴✿✾ ✼✽✴✳✶ ✲✵✴✼✼ ✻✵✾❀✿✵✿ ✾✾❀❁✼✿ ✽✻✾✴✵✿ ✻✼✶❀✼✽✵
✽✵✴✵✵ ✶✵✴✵✵ ✷✸✹✺ ✻✼✴✶✶ ✽✳✾✴✿✾ ✼✽✴✳✶ ✲✵✴✼✼ ✻✵✾❀✿✵✿ ✾✾❀❁✼✿ ✽✻✾✴✵✿ ✻✼✶❀✼✽✵
3 .7 .1 .5 Em bankm ent Materials
The Gas Fired Power Plant 275 MW Riau area is consist of Clay and Silty Clay soil type with
LL = 44.00 – 84.79% and PI = 16.41 – 59.91%, which indicate medium to very high plasticity
behaviour. From laboratory data results using Standard Proctor Test at TP-01 and TP-02, we
found that the maximum dry density MDD = 1.351 – 1.354 ton/m3 after compacted. The
maximum dry unit weight values are too low for compacted soil. These results indicate that
the soil absorp water, which also indicate swelling behaviour.
Hence, the soil of TP-01 and TP-02 are not good for embankment materials. Soil with medium
to high plasticity has potential tendency to shrink when the water content decreased, and
swell when the water content increased. These behaviours will cause cracks within
embankment bodies that within time will lead to slopes failure.
3 .6 .2 Shallow Foundat ion
Shallow foundation shall be calculated with various factors :
❂ embedment depth of 0.5 m, 1.0 m, 1.5 m and 2.0 m
❂ squared base footing size (B, L) of 0.5 m, 1.0 m, 1.5 m, and 2.0 m.
❂ stripped base footing size (B) of of 0.5 m, 1.0 m, 1.5 m, and 2.0 m.
3 .6 .2 .1 Shallow Foundat ion Form ula Based on SPT
Shallow foundation formula based on SPT data is adopted from Meyerhoff (1965) such as
follows:
❋❃❄ ❇ ❅ ▲ ❆ ❈❉❊ ♠ ● KdN
Qa SPT
❍■❏❍❑ ▼◆❖P◗ P❖ ❦❘❛❙
❋❃❄ ❇ ❅ ▲ ❚ ❈❉❊ ♠ ● KdB
BNQa SPT
❯❱❲❳
❳❨❲❳❩❬
❭❪❫
❴ ❵❜ ▼◆❖P◗ P❖ ❦❘❛❙
❝❞❡❄❡ ●B
DKd ❢❢❣❤✐ ❥❧ ❆ ❈❉♥♥
DRAFT 2 6 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
This formula especially used for calculate allowable bearing capacity Qa in terms of 1 inch
settlement and not taken the type of foundation (squared or stripped) into account.
Table 3 - 1 4 Bearing capacity of shallow foundat ion based on SPT of BH-01.
�✁✂✄☎
✆✝✞✟✠ ✡☛☞✌✍✝✎ ✏✑✑✒✓✌✔✑✝ �✝✌✍✕✖✗ ✘✌✞✌✙✕✟✚ ✛✜✢✣
✛✤✣ ☎ ✥ ☎ ☎✦✧ ✥ ☎✦✧ ★ ✥ ★ ★✦✧ ✥ ★✦✧ ✩ ✥ ✩
✪✫✪✪ ✬✭✪✫✪✪ ✮✯✰✫✪✪ ✱✱✰✪✫✯✲ ✱✮✭✳✫✪✪ ✯✳✲✪✫✯✲
✪✫✲✪ ✳✱✰✫✳✪ ✴✪✰✫✱✰ ✱✯✴✴✫✳✲ ✱✴✴✪✫✳✯ ✯✲✴✲✫✪✱
✱✫✪✪ ✳✮✴✫✴✪ ✴✴✰✫✬✴ ✱✬✴✭✫✭✳ ✱✰✰✭✫✴✲ ✯✮✱✰✫✮✴
✱✫✲✪ ✳✮✴✫✴✪ ✰✭✰✫✲✮ ✱✳✴✳✫✴✳ ✯✱✱✬✫✯✮ ✯✴✲✳✫✲✳
✯✫✪✪ ✳✮✴✫✴✪ ✰✭✰✫✲✮ ✱✲✴✬✫✪✬ ✯✯✯✰✫✮✪ ✯✰✴✰✫✬✱
✆✝✞✟✠ ✡✟✍✕✞✞✝✎ ✏✑✑✒✓✌✔✑✝ �✝✌✍✕✖✗ ✘✌✞✌✙✕✟✚ ✛✜✢✵✤✣
✛✤✣ ☎ ✤ ☎✦✧ ✤ ★ ✤ ★✦✧ ✤ ✩ ✤
✪✫✪✪ ✬✭✪✫✪✪ ✳✴✭✫✪✪ ✲✰✲✫✱✬ ✮✪✲✫✭✪ ✴✱✭✫✮✲
✪✫✲✪ ✳✱✰✫✳✪ ✲✬✰✫✳✭ ✭✳✳✫✯✯ ✮✲✯✫✱✮ ✴✭✱✫✭✮
✱✫✪✪ ✳✮✴✫✴✪ ✲✰✯✫✰✯ ✭✰✬✫✬✯ ✮✰✴✫✮✳ ✰✪✭✫✲✰
✱✫✲✪ ✳✮✴✫✴✪ ✭✳✭✫✬✴ ✮✳✯✫✳✯ ✴✳✲✫✬✱ ✰✲✱✫✲✱
✯✫✪✪ ✳✮✴✫✴✪ ✭✳✭✫✬✴ ✮✰✱✫✲✯ ✴✰✱✫✴✴ ✰✰✭✫✳✳
Table 3 - 1 5 Bearing capacity of shallow foundat ion based on SPT of BH-02.
�✁✂✄★
✆✝✞✟✠ ✡☛☞✌✍✝✎ ✏✑✑✒✓✌✔✑✝ �✝✌✍✕✖✗ ✘✌✞✌✙✕✟✚ ✛✜✢✣
✛✤✣ ☎ ✥ ☎ ☎✦✧ ✥ ☎✦✧ ★ ✥ ★ ★✦✧ ✥ ★✦✧ ✩ ✥ ✩
✪✫✪✪ ✳✪✫✪✪ ✴✱✫✪✪ ✱✬✯✫✯✲ ✱✰✭✫✪✪ ✯✮✯✫✯✲
✪✫✲✪ ✳✭✫✭✪ ✴✰✫✰✱ ✱✳✬✫✱✭ ✯✪✴✫✰✳ ✯✴✮✫✯✯
✱✫✪✪ ✲✬✫✯✪ ✰✴✫✴✯ ✱✲✳✫✪✮ ✯✯✱✫✴✮ ✬✪✯✫✯✪
✱✫✲✪ ✲✬✫✯✪ ✱✪✮✫✮✬ ✱✭✳✫✰✴ ✯✬✳✫✴✱ ✬✱✮✫✱✮
✯✫✪✪ ✲✬✫✯✪ ✱✪✮✫✮✬ ✱✮✲✫✴✰ ✯✳✮✫✮✳ ✬✬✯✫✱✲
✆✝✞✟✠ ✡✟✍✕✞✞✝✎ ✏✑✑✒✓✌✔✑✝ �✝✌✍✕✖✗ ✘✌✞✌✙✕✟✚ ✛✜✢✵✤✣
✛✤✣ ☎ ✤ ☎✦✧ ✤ ★ ✤ ★✦✧ ✤ ✩ ✤
✪✫✪✪ ✳✪✫✪✪ ✲✳✫✪✪ ✭✭✫✱✬ ✮✴✫✳✪ ✰✪✫✮✲
✪✫✲✪ ✳✭✫✭✪ ✲✰✫✰✳ ✮✱✫✲✴ ✴✬✫✲✮ ✰✲✫✮✳
✱✫✪✪ ✲✬✫✯✪ ✭✲✫✴✴ ✮✮✫✪✳ ✴✴✫✮✲ ✱✪✪✫✮✬
✱✫✲✪ ✲✬✫✯✪ ✮✱✫✴✯ ✴✯✫✳✰ ✰✬✫✰✯ ✱✪✲✫✮✯
✯✫✪✪ ✲✬✫✯✪ ✮✱✫✴✯ ✴✮✫✰✲ ✰✰✫✱✪ ✱✱✪✫✮✯
DRAFT 2 7 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Table 3 - 1 6 Bearing capacity of shallow foundat ion bsed on SPT of BH-03.
�✁✂✄☎
✆✝✞✟✠ ✡☛☞✌✍✝✎ ✏✑✑✒✓✌✔✑✝ �✝✌✍✕✖✗ ✘✌✞✌✙✕✟✚ ✛✜✢✣
✛✤✣ ✥ ✦ ✥ ✥✧★ ✦ ✥✧★ ✩ ✦ ✩ ✩✧★ ✦ ✩✧★ ☎ ✦ ☎
✪✫✪✪ ✬✪✪✫✪✪ ✭✪✮✫✪✪ ✯✯✰✫✬✮ ✱✲✪✫✪✪ ✰✳✯✰✫✬✮
✪✫✮✪ ✬✳✳✫✪✪ ✭✭✱✫✮✮ ✴✰✮✫✲✪ ✰✪✭✭✫✯✲ ✰✭✳✯✫✰✬
✰✫✪✪ ✬✯✯✫✪✪ ✭✱✭✫✰✪ ✴✴✪✫✳✯ ✰✰✪✱✫✳✯ ✰✮✰✪✫✱✱
✰✫✮✪ ✬✯✯✫✪✪ ✮✳✲✫✯✮ ✲✬✭✫✱✰ ✰✰✴✭✫✪✭ ✰✮✲✮✫✲✯
✬✫✪✪ ✬✯✯✫✪✪ ✮✳✲✫✯✮ ✲✴✱✫✭✯ ✰✬✳✲✫✴✬ ✰✯✯✪✫✴✳
✆✝✞✟✠ ✡✟✍✕✞✞✝✎ ✏✑✑✒✓✌✔✑✝ �✝✌✍✕✖✗ ✘✌✞✌✙✕✟✚ ✛✜✢✵✤✣
✛✤✣ ✥ ✤ ✥✧★ ✤ ✩ ✤ ✩✧★ ✤ ☎ ✤
✪✫✪✪ ✬✪✪✫✪✪ ✬✴✪✫✪✪ ✳✳✪✫✯✳ ✳✱✬✫✪✪ ✭✮✳✫✴✮
✪✫✮✪ ✬✳✳✫✪✪ ✬✱✱✫✴✪ ✳✮✴✫✱✪ ✭✰✴✫✲✴ ✭✴✲✫✴✰
✰✫✪✪ ✬✯✯✫✪✪ ✳✬✱✫✭✪ ✳✲✮✫✰✲ ✭✭✳✫✴✭ ✮✪✳✫✯✯
✰✫✮✪ ✬✯✯✫✪✪ ✳✮✱✫✰✪ ✭✰✬✫✭✮ ✭✯✱✫✯✬ ✮✬✲✫✯✬
✬✫✪✪ ✬✯✯✫✪✪ ✳✮✱✫✰✪ ✭✳✱✫✴✳ ✭✱✮✫✭✱ ✮✮✳✫✮✲
3 .6 .3 Deep Foundat ion
Considering there are many lenses of hard soil layers with inadequate thickness, it is not
preferable to use driven piles. Driven piles are prefabricated piles which had limitation of
structural axial capacity, hence, if the bearing capacity of the soil is greater than the structural
capacity, the piles cannot be driven into the soil layer without any structural damages.
Therefore, bored piles is more suitable choice for deep foundation at Gas Fired Power Plant
275 MW Riau area. However, if under any circumstances driven piles should be used,
preboring method must be adopted, to help driven piles reach required depth.
Bored piles and driven piles foundation shall be calculated with various factors :
✶ diameter size (D) of 0.30 m, 0.40 m, 0.50 m, 0.60 m and 0.80 m.
✶ different locations based on soil investigation points
✶ depth limitation due to the termination level of boreholes
3 .6 .3 .1 Bored Piles Based on SPT Data
❇✷✸✹✺ ♣✐✻✹s ❜✼s✹✺ ✷♦ ❙✽❚ ✺✼❞✼ s✾✼✻✻ ❜✹ ❝✼✻❝✿✻✼❞✹✺ ✼s ❢✷✻✻✷✇s ❀
For cohesive soil
End bearing : qp = 9 Su
Sleeves friction : fs = ❁ Su
DRAFT 2 8 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
For granular soil
End bearing : qp = 67 NSPT
Sleeves friction : fs = 3.125 NSPT
❯�t✁♠❛t✂ ❜✂❛✄✁♥❣ ❝❛☎❛❝✁t✆ ✿ ◗✝ ❂ q☎ ❆☎ ✰ ✞ ❢✟ ❆✟
❆��♦✇❛❜�✂ ❜✂❛✄✁♥❣ ❝❛☎❛❝✁t✆ ✿ ◗❛ ❂ ◗✝ ✴ ❙✠
Where :
❙✝ ❂ ✝♥❞✄❛✁♥✂❞ ✟s✂❛✄ ✟t✄✂♥❣ts
❆☎ ❂ ❛✄✂❛ ♦❢ ☎✁�✂ ❜❛✟✂
❆✟ ❂ ❛✄✂❛ ♦❢ ☎✁�✂ ✟�✂✂✡✂✟
☛ ❂ ❛❞s✂✟✁♦♥ ❢❛❝t♦✄ ❜❛✟✂❞ ♦♥ ❣✄❛☎s ❜✂�♦✇
Figure 3 - 7 Undraned shear ing resistance vs adhesion factor.
Table 3 - 1 7 Bearing capacity of deep foundat ion at BH-01 using bored pile
based on SPT data.
☞✌✍✎✏
✑✒✓✔✕
✖✗✗✘✙✚✛✗✌ ✑✌✚✜✢✣✤ ✥✚✍✚✦✢✎✧ ★✩✪✫
★✬✫ ☞ ✭✔ ☞ ✮✔ ☞ ✯✔ ☞ ✱✔ ☞ ✲✔
✳✵✳✳
✶✵✷✳ ✷✸✵✹✺ ✻✺✵✹✺ ✶✼✸✵✻✼ ✶✸✼✵✽✻ ✼✻✶✵✸✳
✹✵✳✳ ✺✹✵✶✾ ✶✹✺✵✼✸ ✶✺✼✵✺✷ ✼✷✾✵✶✻ ✹✺✺✵✼✽
✾✵✷✳ ✶✶✽✵✳✳ ✶✽✸✵✹✸ ✼✼✷✵✶✳ ✼✻✺✵✶✻ ✾✹✽✵✾✳
✽✵✳✳ ✶✶✷✵✸✷ ✶✷✻✵✽✺ ✼✳✹✵✻✳ ✼✷✶✵✳✺ ✹✷✼✵✼✶
✸✵✷✳ ✶✷✸✵✹✽ ✼✼✳✵✺✾ ✼✺✳✵✳✻ ✹✽✾✵✸✻ ✷✹✳✵✻✻
✺✵✳✳ ✼✶✶✵✾✸ ✹✳✶✵✷✽ ✾✳✶✵✾✽ ✷✶✶✵✶✽ ✸✷✺✵✺✻
✶✳✵✷✳ ✼✽✶✵✻✸ ✹✸✹✵✷✳ ✾✺✸✵✹✳ ✽✹✹✵✼✽ ✺✾✶✵✸✳
DRAFT 2 9 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✄☎
✆✝✞✟✠
✡☛☛☞✌✍✎☛✁ ✆✁✍✏✑✒✓ ✔✍✂✍✕✑✄✖ ✗✘✙✚
✗✛✚ � ✜✟ � ✢✟ � ✣✟ � ✤✟ � ✥✟
✦✧★✩✩ ✪✦✫★✫✧ ✬✬✭★✦✩ ✫✭✮★✯✰ ✰✫✯★✯✮ ✦✦✧✫★✬✪
✦✪★✫✩ ✪✪✪★✪✪ ✬✮✬★✯✰ ✮✩✮★✮✧ ✰✫✯★✫✰ ✦✩✭✪★✦✪
✦✫★✩✩ ✪✭✧★✯✪ ✫✫✦★✪✩ ✰✧✪★✫✪ ✭✩✭★✫✦ ✦✪✧✧★✰✰
✦✮★✫✩ ✬✰✦★✯✭ ✮✮✰★✯✬ ✯✯✪★✦✪ ✦✦✦✰★✰✫ ✦✮✬✬★✭✯
✦✯★✩✩ ✫✪✩★✰✩ ✰✬✰★✯✯ ✭✯✫★✦✯ ✦✧✬✧★✮✪ ✦✯✦✰★✭✪
✦✭★✫✩ ✫✯✫★✯✭ ✯✧✦★✬✮ ✦✩✰✰★✦✰ ✦✪✫✪★✩✦ ✦✭✮✫★✦✩
✧✦★✩✩ ✮✪✪★✯✭ ✯✯✪★✩✬ ✦✦✫✦★✦✧ ✦✬✪✯★✦✪ ✧✩✮✯★✭✪
✧✧★✫✩ ✮✯✩★✯✫ ✭✬✪★✫✮ ✦✧✧✬★✦✬ ✦✫✧✧★✮✦ ✧✦✰✪★✦✯
✧✬★✩✩ ✰✪✧★✫✧ ✦✩✦✧★✬✮ ✦✪✦✩★✧✰ ✦✮✧✫★✭✮ ✧✪✦✩★✭✯
✧✫★✫✩ ✰✯✬★✧✩ ✦✩✯✦★✪✮ ✦✪✭✮★✪✭ ✦✰✧✭★✪✦ ✧✬✬✯★✰✯
✧✰★✩✩ ✯✪✯★✧✩ ✦✦✫✬★✦✧ ✦✬✯✯★✧✭ ✦✯✬✩★✰✪ ✧✮✩✩★✪✰
✧✯★✫✩ ✯✭✩★✬✭ ✦✧✧✪★✯✬ ✦✫✰✫★✬✫ ✦✭✬✫★✪✧ ✧✰✪✭★✯✧
✪✩★✩✩ ✭✬✧★✰✭ ✦✧✭✪★✫✰ ✦✮✮✧★✮✦ ✧✩✬✭★✭✦ ✧✯✰✭★✧✯
Table 3 - 1 8 Bearing capacity of deep foundat ion at BH-02 using bored pile
based on SPT data.
�✁✂✄☎
✆✝✞✟✱
✡☛☛☞✌✍✎☛✁ ✆✁✍✏✑✒✓ ✔✍✂✍✕✑✄✖ ✗✘✙✚
✗✛✚ � ✜✟ � ✢✟ � ✣✟ � ✤✟ � ✥✟
✩★✩✩
✦★✫✩ ✰★✯✩ ✦✦★✬✰ ✦✫★✮✭ ✧✩★✬✬ ✪✦★✫✮
✪★✩✩ ✪✪★✰✩ ✬✭★✧✯ ✮✰★✩✪ ✯✮★✭✮ ✦✪✪★✪✫
✬★✫✩ ✯✫★✮✧ ✦✧✯★✪✬ ✦✰✯★✦✫ ✧✪✫★✩✫ ✪✰✩★✦✧
✮★✩✩ ✦✦✪★✫✬ ✦✮✫★✩✩ ✧✧✪★✧✰ ✧✯✯★✪✬ ✬✪✯★✭✦
✰★✫✩ ✦✯✪★✭✯ ✧✰✦★✫✧ ✪✰✧★✦✯ ✬✯✫★✭✮ ✰✫✧★✯✪
✭★✩✩ ✧✧✰★✮✬ ✪✪✩★✧✧ ✬✬✮★✦✮ ✫✰✫★✬✬ ✯✰✬★✩✰
✦✩★✫✩ ✧✰✩★✧✬ ✪✯✰★✩✪ ✫✦✰★✦✰ ✮✮✩★✮✰ ✭✯✰★✰✪
✦✧★✩✩ ✪✧✬★✦✩ ✬✮✧★✧✦ ✮✦✫★✪✮ ✰✯✪★✫✫ ✦✦✮✫★✩✮
✦✪★✫✩ ✪✯✮★✯✫ ✫✫✦★✩✦ ✰✪✧★✰✯ ✭✪✧★✦✫ ✦✪✯✪★✰✦
✦✫★✩✩ ✬✪✭★✧✮ ✮✧✦★✧✮ ✯✧✦★✩✮ ✦✩✪✯★✮✮ ✦✫✧✰★✧✧
✦✮★✫✩ ✬✭✦★✯✭ ✮✭✦★✰✯ ✭✩✭★✮✬ ✦✦✬✫★✬✮ ✦✮✰✦★✩✩
✦✯★✩✩ ✫✮✪★✩✰ ✰✭✪★✦✬ ✦✩✬✬★✬✦ ✦✪✦✮★✯✰ ✦✭✧✫★✪✮
✦✭★✫✩ ✮✦✰★✧✪ ✯✮✬★✫✦ ✦✦✪✧★✫✮ ✦✬✧✦★✪✯ ✧✩✮✦★✪✧
✧✦★✩✩ ✮✰✫★✯✩ ✭✬✪★✬✫ ✦✧✪✧★✪✩ ✦✫✬✧★✪✪ ✧✧✧✫★✭✯
✧✧★✫✩ ✰✪✧★✬✮ ✦✩✦✭★✩✩ ✦✪✧✮★✰✪ ✦✮✫✫★✮✫ ✧✪✰✰★✩✰
✧✬★✩✩ ✰✮✩★✪✮ ✦✩✬✮★✰✫ ✦✪✬✭★✮✦ ✦✮✮✯★✭✫ ✧✪✫✰★✩✪
✧✫★✫✩ ✯✬✬★✪✪ ✦✦✰✩★✧✭ ✦✫✦✯★✫✩ ✦✯✯✯★✭✰ ✧✮✭✮★✮✭
✧✰★✩✩ ✭✩✧★✧✮ ✦✧✬✰★✫✪ ✦✮✦✫★✩✫ ✧✩✩✬★✯✬ ✧✯✫✦★✦✰
DRAFT 3 0 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✄☎✆✝✞✟✠
✡☛☛☞✌✍✎☛✁ ✆✁✍✏✑✒✓ ✔✍✂✍✕✑✄✖ ✗✘✙✚
✗✛✚ � ✜✟ � ✢✟ � ✣✟ � ✤✟ � ✥✟
✦✧★✩✪ ✫✬✪★✭✫ ✭✮✦✯★✰✰ ✭✰✭✭★✬✪ ✦✭✦✪★✰✪ ✮✪✪✩★✬✩
✮✪★✪✪ ✭✪✭✧★✭✦ ✭✯✪✦★✪✭ ✭✧✪✧★✭✩ ✦✦✮✬★✩✬ ✮✭✬✪★✭✯
Table 3 - 1 9 Bearing capacity of deep foundat ion at BH-03 using bored pile
based on SPT data
�✁✂✄☎✆✝✞✟✜
✡☛☛☞✌✍✎☛✁ ✆✁✍✏✑✒✓ ✔✍✂✍✕✑✄✖ ✗✘✙✚
✗✛✚ � ✜✟ � ✢✟ � ✣✟ � ✤✟ � ✥✟
✪★✪✪
✭★✩✪ ✮✮★✮✧ ✩✪★✮✬ ✰✪★✦✬ ✫✮★✪✧ ✭✯✰★✯✫
✮★✪✪ ✩✪★✩✯ ✰✦★✮✮ ✫✬★✩✧ ✭✦✮★✮✪ ✭✧✯★✭✩
✯★✩✪ ✰✪★✭✬ ✫✧★✬✰ ✭✦✫★✰✯ ✭✬✮★✮✰ ✦✮✧★✮✭
✬★✪✪ ✫✬★✯✫ ✭✮✩★✧✫ ✭✰✧★✫✦ ✦✦✩★✩✬ ✮✦✫★✬✫
✰★✩✪ ✭✮✭★✬✦ ✭✧✬★✬✦ ✦✯✰★✭✧ ✮✭✮★✮✭ ✯✬✦★✦✬
✫★✪✪ ✭✰✫★✩✭ ✦✩✬★✫✧ ✮✯✮★✦✬ ✯✮✧★✮✩ ✬✩✯★✫✧
✭✪★✩✪ ✦✦✩★✫✦ ✮✦✮★✪✬ ✯✮✭★✭✦ ✩✩✪★✪✫ ✧✦✪★✧✪
✭✦★✪✪ ✦✬✩★✧✬ ✮✰✰★✦✬ ✩✪✪★✪✬ ✬✮✯★✦✯ ✫✮✬★✰✧
✭✮★✩✪ ✦✫✪★✪✩ ✯✪✩★✭✰ ✩✦✫★✩✦ ✬✬✮★✪✫ ✫✩✰★✫✪
✭✩★✪✪ ✮✦✧★✧✰ ✯✩✧★✯✬ ✩✫✧★✪✯ ✰✯✰★✬✭ ✭✪✰✬★✰✪
✭✬★✩✪ ✯✪✪★✬✬ ✩✬✩★✭✯ ✰✯✩★✪✰ ✫✯✪★✯✰ ✭✮✰✰★✬✮
✭✧★✪✪ ✯✦✩★✬✰ ✩✫✭★✫✭ ✰✰✪★✮✮ ✫✬✪★✫✦ ✭✮✰✧★✬✮
✭✫★✩✪ ✯✰✧★✯✯ ✬✬✬★✪✧ ✧✬✰★✧✪ ✭✪✧✮★✩✫ ✭✩✩✰★✯✭
✦✭★✪✪ ✩✦✫★✧✩ ✰✮✬★✰✫ ✫✩✧★✧✫ ✭✭✫✬★✭✩ ✭✰✭✬★✭✬
✦✦★✩✪ ✩✰✬★✮✫ ✰✫✧★✧✯ ✭✪✮✬★✯✩ ✭✦✧✫★✦✮ ✭✧✯✪★✦✬
✦✯★✪✪ ✬✩✭★✧✮ ✫✪✧★✬✩ ✭✭✧✩★✦✯ ✭✯✧✭★✬✪ ✦✭✮✮★✬✦
✦✩★✩✪ ✰✪✬★✩✯ ✫✧✭★✩✫ ✭✦✰✬★✯✭ ✭✩✫✭★✪✭ ✦✦✰✫★✩✪
✦✰★✪✪ ✰✬✭★✦✯ ✭✪✩✯★✩✮ ✭✮✬✰★✩✫ ✭✰✪✪★✯✦ ✦✯✦✩★✮✧
✦✧★✩✪ ✧✭✩★✫✩ ✭✭✦✰★✯✰ ✭✯✩✧★✰✬ ✭✧✪✫★✧✦ ✦✩✰✭★✦✬
✮✪★✪✪ ✧✰✪★✬✩ ✭✦✪✪★✯✭ ✭✩✯✫★✫✯ ✭✫✭✫★✦✮ ✦✰✭✰★✭✯
3 .6 .3 .2 Driven Piles Based on SPT Data
❉✱✲✳✴✵ ♣✲✶✴s ❜✷s✴❞ ♦✵ ❙✸✹ ❞✷✺✷ s✻✷✶✶ ❜✴ ❝✷✶❝❧✶✷✺✴❞ ✷s ❢♦✶✶♦✼s ✿
For cohesive soil
End bearing : qp = 9 Su
Sleeves friction : fs = ✽ Su
DRAFT 3 1 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
For granular soil
End bearing : qp = 400 NSPT
Sleeves friction : fs = 2 NSPT
❯�t✁♠❛t✂ ❜✂❛✄✁♥❣ ❝❛☎❛❝✁t✆ ✿ ◗✝ ❂ q☎ ❆☎ ✰ ✞ ❢✟ ❆✟
❆��♦✇❛❜�✂ ❜✂❛✄✁♥❣ ❝❛☎❛❝✁t✆ ✿ ◗❛ ❂ ◗✝ ✴ ❙✠
Where :
❙✝ ❂ ✝♥❞✄❛✁♥✂❞ ✟s✂❛✄ ✟t✄✂♥❣ts
❆☎ ❂ ❛✄✂❛ ♦❢ ☎✁�✂ ❜❛✟✂
❆✟ ❂ ❛✄✂❛ ♦❢ ☎✁�✂ ✟�✂✂✡✂✟
☛ ❂ ❛❞s✂✟✁♦♥ ❢❛❝t♦✄ ❜❛✟✂❞ ♦♥ ❣✄❛☎s ❜✂�♦✇
Figure 3 - 8 Undrained shear st rength vs adhesion factor.
With preboring method, we can drive the piles until they reach required depth. The result of
the calculation are presented in the table below.
3 .6 .3 .3 Driven Pile W ith Pre- Boring
Since driven piles should be installed using preboring method, it will eliminate the sleeve
friction capacity. Hence, the resistance will depend only to end bearing capacity.
☞✌✍✎✏✑✌✒✍ ✓✔✒✏✎ ✓✕✎✒✌✖✕✔ ✗✘ ✑✌ ✙✚✏
DRAFT 3 2 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Table 3 - 2 0 Bear ing capacity of deep foundat ion using driven pile based on
SPT data with pre-boring at BH-01.
�✁✂✄☎
✆✝✞✟✠
✡☛☛☞✌✍✎☛✁ ✆✁✍✏✑✒✓ ✔✍✂✍✕✑✄✖ ✗✘✙✚
✗✛✚ � ✜✟ � ✢✟ � ✣✟ � ✤✟ � ✥✟
✦✧✦✦
★✧✩✦ ✪★✧★★ ✫✬✧✭✩ ★✭✬✧✦✮ ★✯✦✧★✮ ✮✫★✧✪✭
✭✧✦✦ ★✦✭✧✯✬ ★✩✭✧✩✬ ✮★✦✧✰✯ ✮✰✩✧✩✰ ✬✮✰✧✰✫
✬✧✩✦ ★✭✦✧✮✩ ★✯✪✧✭✰ ✮✬✯✧✯✩ ✭★✰✧✪✯ ✬✰✬✧✬✦
✪✧✦✦ ★✭✦✧✦✯ ★✰✰✧✰✫ ✮✮✰✧✪✯ ✮✰✫✧✰✩ ✭✫✦✧✬★
✰✧✩✦ ★✰✭✧★✭ ✮✬★✧✫✰ ✭★✪✧✭✰ ✭✫✪✧✭✭ ✩✰✮✧✫✬
✫✧✦✦ ✮✬★✧✮✭ ✭✬★✧✮✬ ✬✩★✧✦✪ ✩✰✦✧✪✯ ✯✭✫✧✭✭
★✦✧✩✦ ✭★✮✧✰★ ✬✬★✧✮✫ ✩✯✮✧✦✭ ✰✭✬✧✫✬ ★✦✰✰✧✮✯
★✮✧✦✦ ✭✫✮✧✯✯ ✩✩✮✧✮✬ ✰✮✩✧✯✦ ✫★✭✧✩✰ ★✭✭★✧✰★
★✭✧✩✦ ✬✮✩✧✫✯ ✩✯✯✧✭✫ ✰✪★✧✦✮ ✫✬✭✧✯✪ ★✭✬✦✧★✰
★✩✧✦✦ ✩★✦✧✰✪ ✰✦✯✧✩✭ ✫✮✦✧✦✰ ★★✬✩✧✭✪ ★✪✭✰✧✮✬
★✪✧✩✦ ✪✭✮✧✬✰ ✯✯★✧✫✪ ★★✩✦✧✰✰ ★✬✭✯✧✫✮ ✮✦✰✭✧✮✦
★✯✧✦✦ ✰✭✪✧✰✯ ★✦✮✮✧✪✬ ★✭✮✯✧✪✬ ★✪✩✬✧✰✯ ✮✭✪✰✧✬✪
★✫✧✩✦ ✯✭✰✧✬✪ ★★✩✪✧✯✯ ★✬✫✪✧✬✬ ★✯✩✪✧★✬ ✮✪✭✩✧✫✬
✮★✧✦✦ ✫✮✪✧✪✪ ★✮✰✭✧✬✦ ★✪✭✫✧✦✰ ✮✦✮✭✧✪✰ ✮✯✬✫✧✪✩
✮✮✧✩✦ ★✦★★✧✭✬ ★✭✯✬✧✮★ ★✰✰✬✧✫✪ ✮★✯✭✧✩✯ ✭✦✩✬✧✬✯
✮✬✧✦✦ ★★✦✦✧✰✭ ★✩✦✭✧✬✦ ★✫✮✭✧✫✩ ✮✭✪✮✧✭✯ ✭✮✫✮✧✯✰
✮✩✧✩✦ ★★✫✦✧★✭ ★✪✮✮✧✪✦ ✮✦✰✮✧✫✬ ✮✩✬★✧★✰ ✭✩✭★✧✮✪
✮✰✧✦✦ ★✮✯✭✧★✭ ★✰✬✰✧✭✩ ✮✮✮✫✧✯✬ ✮✰✭✦✧✩✯ ✭✰✯✪✧✯✬
✮✯✧✩✦ ★✭✰✬✧✬✮ ★✯✪✫✧✦✯ ✮✭✯★✧✫✫ ✮✫★✭✧★✰ ✬✦✭✦✧✮✫
✭✦✧✦✦ ★✬✪✩✧✰★ ★✫✫✦✧✯✦ ✮✩✭✬✧★✩ ✭✦✫✩✧✰✩ ✬✮✰✭✧✰✬
Table 3 - 2 1 Bearing capacity of deep foundat ion using driven pile
based on SPT data with pre-boring at BH-02.
✆✝✞✟✱
✡☛☛☞✌✍✎☛✁ ✆✁✍✏✑✒✓ ✔✍✂✍✕✑✄✖ ✗✘✙✚
� ✜✟ � ✢✟ � ✣✟ � ✤✟ � ✥✟
✰✧✯✦ ★★✧✬✰ ★✩✧✪✫ ✮✦✧✬✬ ✭★✧✩✪
✭✭✧✰✰ ✬✫✧✭✯ ✪✰✧★✪ ✯✰✧★✮ ★✭✭✧✩✪
✫★✧✭✬ ★✭✩✧✫✰ ★✯✰✧✪✫ ✮✬✪✧✩✦ ✭✯✩✧✭✯
★✮✬✧★✦ ★✰✫✧✦✰ ✮✬✦✧✯✪ ✭✦✫✧✬✩ ✬✪✰✧✦✩
✮★✯✧✦✭ ✭★✪✧✫✭ ✬✮✯✧✫✬ ✩✩✬✧✦✪ ✯✬✭✧✪✬
✮✯✩✧✯✰ ✬✦✰✧✯✪ ✩✬✭✧✮★ ✪✫★✧✫★ ★✦✮✫✧✭✪
✭✩✮✧✪✪ ✬✫✪✧✫✮ ✪✩✬✧✩✬ ✯✮✩✧✩★ ★✮✦✰✧✩✮
DRAFT 3 3 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✄☎
✆✝✝✞✟✠✡✝☛ �☛✠☞✌✍✎ ✏✠✑✠✒✌✓✔ ✕✖✗✘
✙ ✚✄ ✙ ✛✄ ✙ ✜✄ ✙ ✢✄ ✙ ✣✄
✤✥✦✧✤✤ ★✩✪✧★★ ✫✪✪✧✬✥ ✩✪✪★✧✭✤ ✩✤★✩✧✬✮
✦✥✦✧✪✩ ✮✤✫✧✦✦ ✬✮✬✧✮✪ ✩✭✭✫✧✤★ ✩✮✮✫✧✮✫
★✭✤✧✫✭ ✫★✫✧★✫ ✩✩✥✪✧✥✥ ✩✤✪✬✧✮✫ ✭✪✭✭✧✪✦
✮✩✦✧✤✭ ✬✫✬✧✫✭ ✩✭✫✭✧✩✬ ✩✦✬✭✧✦✭ ✭✭★✮✧✪✫
✫✥✦✧✬✪ ✩✩✦★✧✬✭ ✩✤✬✬✧✩✥ ✩✫★✭✧✦✥ ✭★✦✭✧✬✪
✬✥✮✧✫✥ ✩✭✬✩✧✬✫ ✩★★★✧✬✪ ✭✪★✭✧✦✫ ✭✬✩★✧✭✦
✩✪✤✦✧✮✪ ✩✤✥★✧★✦ ✩✫✤✫✧✮✬ ✭✭✫✭✧✩✥ ✥✭✩✭✧✥✮
✩✩✦✩✧★★ ✩✦✮✮✧✬✥ ✭✪✭✦✧✥✬ ✭✤✬✤✧✪✦ ✥✤✬✤✧✬✥
✩✭✩✭✧✮✮ ✩★✤✬✧✬★ ✭✩✪✥✧★✥ ✭✦✮✥✧✮✮ ✥✦★✥✧✤✦
✩✥✦✪✧✪✬ ✩✫✤✤✧★✤ ✭✥★✩✧✤✦ ✭✬✪✪✧✦✩ ✤✪✤✦✧✤✪
✩✤★✩✧✥✫ ✩✬✬✥✧✪✭ ✭✦✤★✧✬✭ ✥✩✭✥✧✪✫ ✤✥✤✭✧✩✮
✩✦✮✭✧★✮ ✭✩✤✩✧✤✩ ✭✮✥✭✧✤✪ ✥✥✤✦✧★★ ✤★✥✫✧✬✥
✩★✫✥✧✬★ ✭✭✫✬✧✮✬ ✭✬✩✮✧✫✫ ✥✦★✫✧✭✥ ✤✬✥✦✧✮✪
Table 3 - 2 2 Bear ing capacity of deep foundat ion using driven pile
based on SPT data with pre-boring at BH-03.
�✁✂✄✚
✆✝✝✞✟✠✡✝☛ �☛✠☞✌✍✎ ✏✠✑✠✒✌✓✔ ✕✖✗✘
✙ ✚✄ ✙ ✛✄ ✙ ✜✄ ✙ ✢✄ ✙ ✣✄
✥✥✧✬✤ ✦✩✧✩✪ ✮✩✧✩✬ ✬✤✧✭✪ ✩✤✫✧✬✫
✦✩✧★✤ ✮✥✧✫✪ ✬✫✧✤✩ ✩✭✦✧✦✪ ✩✫✮✧✪✬
✮✩✧✬✮ ✩✪✩✧✪✬ ✩✥✭✧✮★ ✩★★✧✬✬ ✭✤✥✧✩✤
✬✮✧✭✤ ✩✥★✧✬✪ ✩✫✪✧✩✮ ✭✭✮✧✪★ ✥✥✩✧✮✪
✩✥✥✧✫✭ ✩✫✬✧✦✦ ✭✦✪✧✫✤ ✥✩✮✧✮✩ ✤★✫✧✩✭
✩✬✭✧✦✩ ✭✮✤✧✥✪ ✥★✤✧✬✩ ✤★✤✧✥✤ ★✫✬✧★✥
✭✦★✧✦★ ✥★✥✧✬✭ ✤✫✭✧✩✬ ★✩✩✧✥✫ ✬✪✭✧✦✭
✥✩✦✧★✦ ✤✤✥✧★✦ ✦✫✥✧✪✤ ✮✥✥✧✫✭ ✩✪★✬✧✦✦
✥✦✭✧✪✪ ✤✫✮✧✮✮ ★✥✭✧✮✮ ✮✫★✧✬✬ ✩✩✭✥✧✪✬
✤✪✦✧✥✮ ✦★✪✧✤★ ✮✭✦✧✦✤ ✬✪✪✧★✩ ✩✭✫✪✧✮✪
✦✪✮✧✥✪ ✮✪✮✧✥✭ ✬✭✭✧✮✬ ✩✩✦✥✧✮✥ ✩★★✩✧✬✬
✦✦✥✧✤✪ ✮★✭✧✭✭ ✬✫✥✧✭✩ ✩✭✩★✧✥✫ ✩✮✩✬✧✭✦
★✥✭✧✥✦ ✫✮✩✧✭✬ ✩✩✭✤✧✥✩ ✩✥✬✩✧✤✩ ✩✬★✮✧✫✤
✮✩✥✧✪✥ ✬✫✩✧✪✥ ✩✭★✤✧✩✬ ✩✦★✭✧✦✩ ✭✭✪✤✧★✤
✮✫✫✧✫✤ ✩✪✫✭✧✩✪ ✩✥✬✪✧✦✥ ✩✮✩✤✧✩✭ ✭✤✪★✧✮✬
✬✪✫✧✤✥ ✩✭✦✪✧✮✮ ✩★✩✭✧✫✬ ✩✬✬✤✧✮✫ ✭✫✩✮✧✫✮
✩✪✪✮✧✭✫ ✩✥✫✭✧✦✫ ✩✮✮✮✧★✤ ✭✩✬✭✧✤✫ ✥✪✫✩✧✤✮
DRAFT 3 4 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✄☎
✆✝✝✞✟✠✡✝☛ �☛✠☞✌✍✎ ✏✠✑✠✒✌✓✔ ✕✖✗✘
✙ ☎✄ ✙ ✚✄ ✙ ✛✄ ✙ ✜✄ ✙ ✢✄
✣✣✤✥✦✣✧ ✣★✣✩✦✧✪ ✣✫✩✬✦✧✫ ✬✧✫✤✦✣✪ ✧✧✩★✦✤✭
✣✬✤✩✦✫✪ ✣✥✩✥✦✣✪ ✬✣✤✭✦✣✩ ✬★✪✭✦✪✪ ✧✥✤✪✦✥✭
✣✧✤✧✦✪✧ ✣✭✭✭✦✫✪ ✬✬✭✣✦✫✤ ✬✭✪★✦★✪ ✧✪✭✬✦✬✭
3 .6 .3 .4 Driven Pile W ithout Pre- Boring
Without pre-boring method, the piles cannot be driven deep into the soil without being
damaged, considering there is a limit on structural capacity of pile axial load.
Hence to prevent pile damage during installation, driven piling can be applied directly without
pre-boring, with appropriate allowable bearing capacity described as follows:
Table 3 - 2 3 Bearing capacity of deep foundat ion using driven pile based on
SPT without pre-boring at BH-01.
✙☛✑✓✮
�✁✂✄✯
✰✝✓✌✱✠✓☛ �☛✠☞✌✍✎ ✏✠✑✠✒✌✓✔ ✕✖✗✘
✕✱✘ ✙ ☎✄ ✙ ✚✄ ✙ ✛✄ ✙ ✜✄ ✙ ✢✄
✤✦✤✤
✣✦★✤ ✥✣✦✣✣ ✫✩✦✧★ ✣✧✩✦✤✬ ✣✪✤✦✣✬ ✬✫✣✦✥✧
✧✦✤✤ ✣✤✧✦✪✩ ✣★✧✦★✩ ✬✣✤✦✭✪ ✬✭★✦★✭ ✩✬✭✦✭✫
✩✦★✤ ✣✧✤✦✬★ ✣✪✥✦✧✭ ✬✩✪✦✪★ ✧✣✭✦✥✪ ✩✭✩✦✩✤
✥✦✤✤ ✣✧✤✦✤✪ ✣✭✭✦✭✫ ✬✬✭✦✥✪ ✬✭✫✦✭★ ✧✫✤✦✩✣
✭✦★✤ ✣✭✧✦✣✧ ✬✩✣✦✫✭ ✧✣✥✦✧✭ ✧✫✥✦✧✧ ★✭✬✦✫✩
✫✦✤✤ ✬✩✣✦✬✧ ✧✩✣✦✬✩ ✩★✣✦✤✥ ★✭✤✦✥✪ ✪✧✫✦✧✧
✣✤✦★✤ ✧✣✬✦✭✣ ✩✩✣✦✬✫ ★✪✬✦✤✧ ✭✧✩✦✫✩ ✣✤✭✭✦✬✪
✣✬✦✤✤ ★★✬✦✬✩ ✭✬★✦✪✤ ✫✣✧✦★✭ ✣✧✧✣✦✭✣
✣✧✦★✤ ✫✩✧✦✪✥ ✣✧✩✤✦✣✭
✣★✦✤✤ ✣✥✧✭✦✬✩
✣✥✦★✤ ✬✤✭✧✦✬✤
✣✪✦✤✤
Table 3 - 2 4 Bear ing capacity of deep foundat ion using driven pile based
on SPT without pre-boring at BH-02.
�✁✂✄✲
✰✝✓✌✱✠✓☛ �☛✠☞✌✍✎ ✏✠✑✠✒✌✓✔ ✕✖✗✘
✙ ☎✄ ✙ ✚✄ ✙ ✛✄ ✙ ✜✄ ✙ ✢✄
DRAFT 3 5 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
�✁✂✄ ☎☎✁✆� ☎✝✁✞✟ ✠✄✁✆✆ ✡☎✁✝✞
✡✡✁�� ✆✟✁✡✂ ✞�✁☎✞ ✂�✁☎✠ ☎✡✡✁✝✞
✟☎✁✡✆ ☎✡✝✁✟� ☎✂�✁✞✟ ✠✆✞✁✝✄ ✡✂✝✁✡✂
☎✠✆✁☎✄ ☎�✟✁✄� ✠✆✄✁✂✞ ✡✄✟✁✆✝ ✆✞�✁✄✝
✠☎✂✁✄✡ ✡☎✞✁✟✡ ✆✠✂✁✟✆ ✝✝✆✁✄✞ ✂✆✡✁✞✆
✠✂✝✁✂� ✆✄�✁✂✞ ✝✆✡✁✠☎ ✞✟☎✁✟☎ ☎✄✠✟✁✡✞
✞✝✆✁✝✆ ✂✠✝✁✝☎ ☎✠✄�✁✝✠
☎✄✄✞✁✠✆ ☎✆✞☎✁✟�
☎��✂✁�✂
Table 3 - 2 5 Bear ing capacity of deep foundat ion using driven pile
based on SPT without pre-boring at BH-03.
☛☞✌✍✎
✏✑✒✓✔✕✒✖ ☛✖✕✗✓✘✙ ✚✕✛✕✜✓✒✢ ✣✤✥✦
✧ ✎✍ ✧ ★✍ ✧ ✩✍ ✧ ✪✍ ✧ ✫✍
✡✡✁✟✆ ✝☎✁☎✄ �☎✁☎✟ ✟✆✁✠✄ ☎✆✂✁✟✂
✝☎✁✞✆ �✡✁✂✄ ✟✂✁✆☎ ☎✠✝✁✝✄ ☎✂�✁✄✟
�☎✁✟� ☎✄☎✁✄✟ ☎✡✠✁�✞ ☎✞✞✁✟✟ ✠✆✡✁☎✆
✟�✁✠✆ ☎✡✞✁✟✄ ☎✂✄✁☎� ✠✠�✁✄✞ ✡✡☎✁�✄
☎✡✡✁✂✠ ☎✂✟✁✝✝ ✠✝✄✁✂✆ ✡☎�✁�☎ ✆✞✂✁☎✠
☎✟✠✁✝☎ ✠�✆✁✡✄ ✡✞✆✁✟☎ ✆✞✆✁✡✆ ✞✂✟✁✞✡
✠✝✞✁✝✞ ✡✞✡✁✟✠ ✆✂✠✁☎✟ ✞☎☎✁✡✂ ✟✄✠✁✝✠
✡☎✝✁✞✝ ✆✆✡✁✞✝ ✝✂✡✁✄✆ �✡✡✁✂✠ ☎✄✞✟✁✝✝
✆✂�✁�� ✞✡✠✁�� �✂✞✁✟✟ ☎☎✠✡✁✄✟
�✠✝✁✝✆ ✟✄✄✁✞☎ ☎✠✂✄✁�✄
☎☎✝✡✁�✡ ☎✞✞☎✁✟✟
☎�☎✟✁✠✝
3 .6 .4 Set t lem ent
Guidance on tolerable settlements can be found in engineering textbooks, such as Soil
Mechanics in Engineering Pract ice (Terzaghi and Peck), Foundat ion Analysis and Design
(Bowles) and Foundat ion Engineering (Hanson, Peck and Thornburn). As a rule, these
references indicate that a total settlement of 1 inch (25 mm) is acceptable for the majority of
structures, while other structures can tolerate even greater settlements without distress. On
the other hand, a more restrictive settlement criterion can be necessary based on the needs
of a specific structure. Current engineering practice is often based on an allowable total
DRAFT 3 6 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
settlement of 1 inch (25 mm) with the objective of controlling the differential settlements to 3/4 inch (19 mm) or less.
There are two kind of settlements that taken into account : immediate settlement which take
places during 0 – 14 days after the load of structure being applied due to the shear distortion,
and long term settlement, also known as consolidation settlement which take a long time to
occur. The third kind of settlement, secondary settlement, usually considered negligible and
not significant. On this analyses, we are going to calculate the maximum load that make the
foundations settled at 1 inch.
Immediate settlement caused by distorsion of soil due to load and occur immediately after
load being applied till 7 days afterward.
E
IqBISi �✁
✂
Where :
q = P / A = total applied load from upper structure
B = width of foundation base
I0 = influence factor due to the depth of embedment
I1 = influence factor due to the dimension of the base
E = soil modulus elasticity
The results of 1 inch settlement due to maximum load are presented below. Hence, for the
safety of design, we recommend to use the lower value, which is the allowable bearing
settlement.
3 .7 .4 .1 I m m ediate Set t lem ent
Immediate settlement caused by distorsion of soil due to load and occur immediately after
load being applied till 7 days afterward.
Where :
q = P / A = total applied load from upper structure
B = width of foundation base
I0 = influence factor due to the depth of embedment
I1 = influence factor due to the dimension of the base
E
IqBISi ✄☎
✆
DRAFT 3 7 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
E = soil modulus elasticity
Figure 3 - 9 I m m ediate set t lem ent curve.
The results of 1 inch settlement due to maximum load are presented below. Hence, for the
safety of design, we recommend to use the lower value, which is the allowable bearing
settlement.
Table 3 - 2 6 Allowable bearing set t lem ent of BH-01.
�✁✂✄☎
✆✝✞✟✠✡☛ ☞✌✞✍☛✟✎✏✌✍ ✆✎✠✏✑✑✡☛ ☞✌✞✍☛✟✎✏✌✍
☞✌✞✍☛✟✎✏✌✍ ✆✏✒✡ ✓✟✔ ✕✌✟☛ ☞✌✞✍☛✟✎✏✌✍ ✆✏✒✡ ✓✟✔ ✕✌✟☛
� ✖✗✘ ✕ ✖✗✘ ✖✙✚✘ � ✖✗✘ ✖✙✚✘
✛✜✢✢ ✛✜✢✢ ✣✤✢✜✢✢ ✛✜✢✢ ✤✛✥✜✢✢
✛✜✦✢ ✛✜✦✢ ✛✢✣✢✜✢✢ ✛✜✦✢ ✤✦✦✜✢✢
✥✜✢✢ ✥✜✢✢ ✛✧✣✢✜✢✢ ✥✜✢✢ ✤★✢✜✢✢
✥✜✦✢ ✥✜✦✢ ✛✩✧✢✜✢✢ ✥✜✦✢ ✧✛✦✜✢✢
✤✜✢✢ ✤✜✢✢ ✥✥✛✢✜✢✢ ✤✜✢✢ ✧✧✢✜✢✢
Table 3 - 2 7 Allowable bearing set t lem ent of BH-02.
�✁✂✄✪
✆✝✞✟✠✡☛ ☞✌✞✍☛✟✎✏✌✍ ✆✎✠✏✑✑✡☛ ☞✌✞✍☛✟✎✏✌✍
☞✌✞✍☛✟✎✏✌✍ ✆✏✒✡ ✓✟✔ ✕✌✟☛ ☞✌✞✍☛✟✎✏✌✍ ✆✏✒✡ ✓✟✔ ✕✌✟☛
� ✖✗✘ ✕ ✖✗✘ ✖✙✚✘ � ✖✗✘ ✖✙✚✘
✛✜✢✢ ✛✜✢✢ ✥✫✦✜✢✢ ✛✜✢✢ ✛✦✢✜✢✢
✛✜✦✢ ✛✜✦✢ ✧✢✣✜✢✢ ✛✜✦✢ ✛✩✥✜✢✢
✥✜✢✢ ✥✜✢✢ ✦✩✦✜✢✢ ✥✜✢✢ ✥✛✢✜✢✢
✥✜✦✢ ✥✜✦✢ ✣✣✢✜✢✢ ✥✜✦✢ ✥✤✧✜✢✢
✤✜✢✢ ✤✜✢✢ ★✣✢✜✢✢ ✤✜✢✢ ✥✦✦✜✢✢
DRAFT 3 8 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Table 3 - 2 8 Allowable bearing set t lem ent of BH-03.
�✁✂✄☎✆✝✞✟✠✡☛ ☞✌✞✍☛✟✎✏✌✍ ✆✎✠✏✑✑✡☛ ☞✌✞✍☛✟✎✏✌✍
☞✌✞✍☛✟✎✏✌✍ ✆✏✒✡ ✓✟✔ ✕✌✟☛ ☞✌✞✍☛✟✎✏✌✍ ✆✏✒✡ ✓✟✔ ✕✌✟☛� ✖✗✘ ✕ ✖✗✘ ✖✙✚✘ � ✖✗✘ ✖✙✚✘✛✜✢✢ ✛✜✢✢ ✣✢✢✜✢✢ ✛✜✢✢ ✤✣✥✜✢✢✛✜✦✢ ✛✜✦✢ ✥✧✢✜✢✢ ✛✜✦✢ ★✢✧✜✢✢✤✜✢✢ ✤✜✢✢ ✛✛✩✢✜✢✢ ✤✜✢✢ ★★✥✜✢✢✤✜✦✢ ✤✜✦✢ ✛✦✢✢✜✢✢ ✤✜✦✢ ★✣✦✜✢✢★✜✢✢ ★✜✢✢ ✛✥✢✢✜✢✢ ★✜✢✢ ★✥✥✜✢✢
3 .6 .5 Slope Stability
For open cut excavation requirements, we also provide the calculation of slope stability with
various depth and various slope inclination.
The recommendation of minimum safety factor adopted from JM Duncan and AL Buchignani
(UC Berkeley, 1974) are as follows:
❚✪❡ ❝❛❧❝✫❧❛✬✐✭♥ ✭♦ s❧✭✮❡ s✬❛✯✐❧✐✬✰ s❛♦❡✬✰ ♦❛❝✬✭✱ ✐s ❛s ♦✭❧❧✭✲s ✿
✳ ✴✵✶✷
✸✹✺
✻✼✽ ✾❀✾❁✾
❂❂ ❃❄❅❆❇❈❉❊❃❄❅❇
❈❉❊
❆ur
H
cSF
❲✪❡✱❡ ✿
❋ ● s❧✭✮❡ ✐♥❝❧✐♥❛✬✐✭♥ ✭♦ ❡①❝❛✈❛✬✐✭♥
❝❍ ● s✭✐❧ ❝✭✪❡s✐✭♥
■ ● s✭✐❧ ✫♥✐✬ ✲❡✐❏✪✬
❑ ● ❞❡✮✬✪ ✭♦ ❡①❝❛✈❛✬✐✭♥
▲▼◆❖❖ P◆◗❘❙❯ ◆ ❱❳ ❨❩❙ ❬❭❪❨ ❭❳ ◗❙❫◆❴◗▼❙❵❨ ❙❜❢◆❖ ❨❭ ❬❭❵❪❨◗❢❬❨❴❭❵ ❬❭❪❨❣ ❱❳ ❨❩❙◗❙ ◆◗❙ ❵❭ ◗❴❪❤❪ ❭❳ ❪❨◗❢❬❨❢◗❙❪ ◆❵❥ ❩❢▼◆❵ ❖❴❳❙
❦ ◆ ❱❳ ❨❩❙ ❬❭❪❨ ❭❳ ◗❙❫◆❴◗▼❙❵❨ ❖◆◗❘❙◗ ❨❩◆❵ ❬❭❵❪❨◗❢❬❨❴❭❵ ❬❭❪❨❣ ❱❳ ❨❩❙◗❙ ◆◗❙ ◗❴❪❤❪ ❭❳ ❪❨◗❢❬❨❢◗❙❪ ◆❵❥ ❩❢▼◆❵ ❖❴❳❙
❯♠❦♣ ❯♠♣q
❯♠♣q ❦♠qq
rt✉✇②②t③④⑤⑥⑦✇③ ✇⑧ ⑨⑦③⑦②⑩② ❶⑤✉⑥✇❷ ✇⑧ ❸⑤⑧t⑥❹
❺❭ ❻❭❪❨ ◆❵❥ ❬❭❵❪❙❜❢❙❵❬❙❪ ❭❳ ❪❖❭❫❙ ❳◆❴❖❢◗❙❼❵❬❙◗❨◆❴❵❨❴❙❪ ❭❳ ❽◗❙❥❴❬❨❴❵❘
▲❭❴❖ ▲❨◗❙❵❘❨❩
DRAFT 3 9 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
r✉ ❂ ❯ ✴ ❲ s�✁ ✂ ❂ r✄t☎♦ ♦✆ ♣♦r� ✇✄t�r ♣r�ss✝r� ✇☎t✞ ✇�☎❣✞t ♦✆ s♦☎✟
❯ ❂ ✠✡ ❍✡ ❂ ♣♦r� ✇✄t�r ♣r�ss✝r�
✠✡ ❂ ✾☛✽✶ ❦☞✴✌✸ ✇✄t�r ✝✍☎t ✇�☎❣✞t
❍✡ ❂ ✞�☎❣✞t ♦✆ ❣r♦✝✍✎ ✇✄t�r ✟�❧�✟
❲ ❂ ✇�☎❣✞t ♦✆ s♦☎✟
Following tables show the safety factor of each borehole location regarding to the degree of
slope inclination.
Table 3 - 2 9 Safety factor for 75 degrees inclinat ion.
Depth SAFETY FACTOR FOR 7 5 DEGREES I NCLI NATI ON
( m ) BH- 0 1 BH- 0 2 BH- 0 3
1.00 3.43 0.80 2.26
2.00 1.90 0.55 1.34
3.00 1.51 0.76 0.92
4.00 1.22 1.35 0.80
5.00 0.66 1.34 0.82
6.00 0.86 1.16 1.01
7.00 1.08 1.76 1.20
8.00 1.12 1.57 1.20
9.00 1.14 1.33 1.14
10.00 0.87 1.22 0.95
Table 3 - 3 0 Safety factor for 60 degrees inclinat ion.
Depth SAFETY FACTOR FOR 6 0 DEGREES I NCLI NATI ON
( m ) BH- 0 1 BH- 0 2 BH- 0 3
1.00 3.74 0.96 2.37
2.00 1.98 0.75 1.30
3.00 1.52 0.86 0.83
4.00 1.18 1.37 0.68
5.00 0.52 1.41 0.70
6.00 0.76 1.25 0.91
7.00 1.02 1.77 1.13
8.00 1.07 1.61 1.12
9.00 1.09 1.39 1.05
10.00 0.78 1.29 0.83
DRAFT 4 0 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Table 3 - 3 1 Safety factor for 45 degrees inclinat ion.
Depth SAFETY FACTOR FOR 4 5 DEGREES I NCLI NATI ON
( m ) BH- 0 1 BH- 0 2 BH- 0 3
1.00 4.18 0.99 2.85
2.00 2.41 0.57 1.78
3.00 1.96 1.02 1.31
4.00 1.65 2.04 1.16
5.00 0.99 1.96 1.18
6.00 1.23 1.65 1.42
7.00 1.47 2.68 1.64
8.00 1.53 2.36 1.65
9.00 1.55 1.95 1.58
10.00 1.23 1.77 1.36
Table 3 - 3 2 Safety factor for 30 degrees inclinat ion.
Depth SAFETY FACTOR FOR 3 0 DEGREES I NCLI NATI ON
( m ) BH- 0 1 BH- 0 2 BH- 0 3
1.00 6.20 1.41 3.80
2.00 3.15 1.17 1.95
3.00 2.36 1.23 1.13
4.00 1.66 1.82 0.87
5.00 0.59 1.91 0.91
6.00 0.99 1.73 1.25
7.00 1.46 2.32 1.63
8.00 1.56 2.14 1.61
9.00 1.59 1.87 1.49
10.00 1.06 1.77 1.10
Table 3 - 3 3 Safety factor for 15 degrees inclinat ion.
Depth SAFETY FACTOR FOR 1 5 DEGREES I NCLI NATI ON
( m ) BH- 0 1 BH- 0 2 BH- 0 3
1.00 7.51 2.84 5.24
2.00 4.46 2.42 3.39
3.00 3.67 2.43 2.57
4.00 3.15 3.45 2.31
5.00 2.01 3.66 2.35
6.00 2.42 3.36 2.79
7.00 2.83 4.38 3.16
8.00 2.93 4.07 3.19
9.00 2.96 3.59 3.07
10.00 2.42 3.41 2.68
DRAFT 4 1 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
3 .6 .6 Liquefact ion
Liquefaction usually occur at soil layers with these criteria :
� Saturated fine sand layer with no cohesion
� Saturated cohesive layer with LL < 35 % and clay content below 15%.
Since the soil classification at Gas Fired Power Plant 275 MW Riau area is consist of Clay and
Silty Clay soil type with LL = 44.00 – 84.79%, we can conclude that liquefaction will not occur
at GFPP 275 MW Riau area.
DRAFT 4 2 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
4 . Com parison to Locat ion Alternat ive 1 Comparing the soil investigation results recently at Alternative-2 (Alt-2) area to soil
investigation results conducted earlier which located at Alternative-1 (Alt-1) (studied on April
2016), we came into conclusions as follow:
4 .1 Soil Type and Strat ificat ion
At Alt-2 location, the soil types are dominated by Silt (50% average), follow by Clay (25%
average) and Sand (25% average), which can be named as Clayey Silt with Sand. These soil
types are consistent until depth of boring termination (30 meters).
At Alt-1 location, the same types of soil (Clayey Silt with Sand ) also found at the top layer
with thickness of 8 – 14 meter. Below Clayey Silt with Sand layer, we found medium to very
dense sand layer until depth of boring termination (24 - 26 meters). While at Alt-2 location,
no sand layer was found until termination depth.
4 .2 Soil Plast icity Behaviour
Clayey Silt with Sand soil type at Alt-2 location can be categorized as medium to very high
plasticity behaviour, with LL = 47.56 – 84.76% and PI = 29.42 – 59.91%. The Clayey Silt
with Sand soil type at Alt-1 location also showed the same behaviour, with LL = 69.52 –
108.20% and PI = 39.30 – 80.61%, slightly higher than Alt-2 location.
4 .3 Soil St rength and St ifness
At Alt-2 location, we already found firm to stiff soil at surface layer (N-SPT = 7 – 20), and the
strength and stiffness of soil are increasing with depth. The only exception is at BH-02 area,
where soft soil layer (N-SPT = 2) with thickness of 2 meter was found.
At Alt-1 location, the soil showed the same tendency, the strength and stiffness are increasing
with depth. Soft soil layer as at BH-02 area Alt-2 location was found with thickness of 5 – 7
m.
To summarize, both Alt-2 and Alt-1 location has the same type of soil. The differences are
the soil at Alt-1 location has thicker soft layer (5 – 7 meters) and underlaid by medium to
very dense sand layer. While at Alt-2 location, the soft soil is much thinner (2 meters) and no
sand layer was found until the termination of boring depth.
DRAFT 4 3 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
5 . Conclusion and Recom m endat ion
Based on geotechnical drilling had been conducted we might conclude the stratigraphy of the
soil layer in investigation area by as follows:
� Top Soil consists of clayey SILT layer with thickness approximately 0.4 – 1.2 m and locally
up to 5.6 m.
� Silty CLAY, is a soil layer underlying top soil layer with thickness approximately 0.6 – 2.85
m.
� CLAY layer, the lower most layer up to end of drilling depth, approximately 24 – 29 m
thick relative to the end of drilling depth.
From geoelectrical survey, based on the resistivity range, we interpret the discontinuity that
might reflect the soil layer boundary in subsurface by as follows:
� 1st layer with resistivity value ranging from 2100 – 2938 ohm m, with thickness ranging
from 0.64 up to 1.53 m. This layer interpreted as top soil cover.
� 2nd layer with rasistivity value ranging from 504 – 784 ohm m, with thickness ranging
from 2.7 up to 4.39. This 2nd layer interpreted as silty Clay unit.
� 3rd layer with resistivity value ranging from 8.7 up to 13 ohm m, with thickness ranging
from 27.63 m up to 30 m. This layer interpreted as Clay unit.
� 4th layer with resistivity value ranging from 53 up to 79 ohm m, with thickness
approximately more than 66 m. this layer is underlie below drilling depth and interpreted
as clayey SAND unit.
Geotechnical analysis is undertaken to understand the geotechnical aspect of investigation
area in terms of the bearing capacity of subsurface material regarding to shallow and deep
foundation, the settlement analysis, slope stability assesment during construction work, and
liquefaction potential.
Detail design parameters from geotechnical aspect that had been deduced from geotechnical
analysis can be seen in table 3.11 to 3.13.
The bearing capacity of soil for shallow foundat ion at BH- 0 1 location is summarized as
follows (the detailed result can be seen in table 3.14):
� For 1 x 1 m, 1.5 x 1.5 m, 2 x 2 m, 2.5 x 2.5 m, and 3 x 3 m of squarred foundat ion
allowable bearing capacity to support load to the ground of 1 m depth of foundation
respectivley are 478.8 kN (47,8 ton), 889.38 kN (88.9 ton), 1386.64 kN (138.6 ton),
1996.85 kN (199.6 ton), and 2719.78 kN (271.9 ton).
� For 1 x 1 m, 1.5 x 1.5 m, 2 x 2 m, 2.5 x 2.5 m, and 3 x 3 m of squarred foundat ion
allowable bearing capacity to support load to the ground of 2 m depth of foundation
respectivley are 478.80 kN (47.8 ton), 969.57 kN (96.9 ton), 1583.03 kN (158.3 ton),
2229.70 kN (229.9 ton), 2989.31 kN (298.9 ton).
� For 1 m, 1.5 m, 2 m, 2.5 m, and 3 m of stripped foundat ion allowable bearing capacity
to support load to the ground of 1 m depth of foundation respectivley are 478.80 kN
(47.8 ton), 592.92 kN (59.9 ton), 693.32 kN (69.3 ton), 798.74 kN (79.8 ton), 906.59
kN (90.6 ton).
� For 1 m, 1.5 m, 2 m, 2.5 m, and 3 m of stripped foundat ion allowable bearing capacity
to support load to the ground of 2 m depth of foundation respectivley are 478.80 kN
(47.8 ton), 646.38 kN (64.6 ton), 791.52 kN (79.1 ton), 891.88 kN (89.1 ton), 996.44
kN (99.6 ton).
DRAFT 4 4 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
The bearing capacity of soil for shallow foundat ion at BH- 0 2 location is summarized as
follows (the detailed result can be seen in table 3.15):
� For 1 x 1 m, 1.5 x 1.5 m, 2 x 2 m, 2.5 x 2.5 m, and 3 x 3 m of squarred foundat ion
allowable bearing capacity to support load to the ground of 1 m depth of foundation
respectivley are 53.20 kN (5,3 ton), 98.82 kN (9.8 ton), 154.07 kN (15.4 ton), 221.87
kN (22.1 ton), and 302.20 kN (30.2 ton).
� For 1 x 1 m, 1.5 x 1.5 m, 2 x 2 m, 2.5 x 2.5 m, and 3 x 3 m of squarred foundat ion
allowable bearing capacity to support load to the ground of 2 m depth of foundation
respectivley are 53.20 kN (5.3 ton), 107.73 kN (10.7 ton), 175.89 kN (17.5 ton), 247.74
kN (24.7 ton), 332.15 kN (33.2 ton).
� For 1 m, 1.5 m, 2 m, 2.5 m, and 3 m of stripped foundat ion allowable bearing capacity
to support load to the ground of 1 m depth of foundation respectivley are 53.20 kN (5.3
ton), 65.88 kN (6.5 ton), 77.04 kN (7.7 ton), 88.75 kN (8.8 ton), 100.73 kN (10.1 ton).
� For 1 m, 1.5 m, 2 m, 2.5 m, and 3 m of stripped foundat ion allowable bearing capacity
to support load to the ground of 2 m depth of foundation respectivley are 53.20 kN (5.3
ton), 71.82 kN (7.1 ton), 87.95 kN (8.7 ton), 99.10 kN (9.9 ton), 110.72 kN (11.1 ton).
The bearing capacity of soil for shallow foundat ion at BH- 0 3 location is summarized as
follows (the detailed result can be seen in table 3.16):
� For 1 x 1 m, 1.5 x 1.5 m, 2 x 2 m, 2.5 x 2.5 m, and 3 x 3 m of squarred foundat ion
allowable bearing capacity to support load to the ground of 1 m depth of foundation
respectivley are 266.00 kN (26,6 ton), 494.10kN (49.4 ton), 770.36 kN (77 ton), 1109.36
kN (110.9 ton), and 1510.99 kN (30.2 ton).
� For 1 x 1 m, 1.5 x 1.5 m, 2 x 2 m, 2.5 x 2.5 m, and 3 x 3 m of squarred foundat ion
allowable bearing capacity to support load to the ground of 2 m depth of foundation
respectivley are 266.00 kN (26.6 ton), 538.65 kN (53.8 ton), 879.46 kN (87.9 ton),
1238.72 kN (12.3 ton), 1660.73 kN (16.6 ton).
� For 1 m, 1.5 m, 2 m, 2.5 m, and 3 m of stripped foundat ion allowable bearing capacity
to support load to the ground of 1 m depth of foundation respectivley are 266.00 kN
(26.6 ton), 329.40 kN (32.9 ton), 385.18 kN (38.5 ton), 443.74 kN (44.3 ton), 503.66
kN (50.3 ton).
� For 1 m, 1.5 m, 2 m, 2.5 m, and 3 m of stripped foundat ion allowable bearing capacity
to support load to the ground of 2 m depth of foundation respectivley are 266.00 kN
(26.6 ton), 359.10 kN (35.9 ton), 439.73 kN (43.9 ton), 495.49 kN (49.5 ton), 553.58
kN (55.3 ton).
For deep foundation we provided two bearing capacity of soil regarding to the foundation type
both bored pile and driven pile type. In addition to driven pile we also provided the bearing
capacity with pre-boring and without pre-boring. All the bearing capacity had been calculated
with respect to depth and the diameter of pile collumn. The detail bearing capacity of deep
foundation can be seen in section 3.6.3.
One of the purpose of slope stability analysis is to provide the factor of safety of the slope.
We have provided the factor of safety for the slope with respect to the slope angle (inclination)
for artificial slope during construction and excavation. For this stage, every selected slope
angle with factor of safety can be seen in section 3.6.5 with different factor of safety
determination is provided with respect to the depth of excavation during construction work.
In particular the detailed factor of safety for given slope inclination can be seen in table 3.29
to table 3.33.
DRAFT 4 5 of 4 5
Site Investigation of Riau GFPP (275 MW) 15/06/2017
PT Wahana Guna Mandiri for PT Medco-Ratch Power Riau
Since the soil layer and lithology unit predominantly consists of cohesive soil layer of Silt and
Clay, therefore the potential of soil liquefaction relatively very low. As mentioned at the begin-
ing of section 3.6.6, the criteria for soil material that might undergoing liquefaction are for
non-cohessive and cohessive soil with liquid limit (LL) <35%, while based on laboratory data
the liquid limit of soil properties in investigation area is > 35% (47.56 – 84.76%), therefore
we assume the liquefaction will probably not occurred.
To get a ballace quatity/volume of cut/fill works, it’s recommended the design level at 28.05
m. Quantity of Cut/Fill are 165778.75/165343.39 M3, withremaining cut material are 435.35
M3.
APPENDIX A
Topography Map