70
Different Contracts Including EPC Contract System Dr I Satyanarayana Raju, MTech,MBA,MPhil,BL,FIE,PhD., Former Chief Engineer,CDO(AP) Hyderabad & Member, Technical Advisory Council,WRD(AP)& Expert-Dam Safety Inspection Team & Past Chairman,IEI-Telangana State Centre & AP State Centre, Hyderabad-500082(TS). Contact:9676686158;[email protected]

Different Contracts Including EPC Contract System - …APHRDI/A… ·  · 2018-01-22Different Contracts Including EPC Contract System Dr I Satyanarayana Raju, ... force with effect

  • Upload
    votuong

  • View
    233

  • Download
    0

Embed Size (px)

Citation preview

Different Contracts Including EPC Contract System

Dr I Satyanarayana Raju, MTech,MBA,MPhil,BL,FIE,PhD.,

Former Chief Engineer,CDO(AP) Hyderabad &

Member, Technical Advisory Council,WRD(AP)&

Expert-Dam Safety Inspection Team &

Past Chairman,IEI-Telangana State Centre & AP State Centre, Hyderabad-500082(TS).

Contact:9676686158;[email protected]

Contract And Agreement

• Contract is derived from Latin word ‘Contractum’ meansdrawn together. Contract is an agreement enforceable by law.There shall be two parties between agreement, one who offerand the other accepting it.

• Agreement = Offer + Acceptance.

• An Agreement is defined as every promise and every set ofpromises forming consideration for each other sec2 (e) ofIndian Contract Act, 1872.

• All legal contracts are enforceable by Indian Contract Act,1872 (Act IX of 1872). An Amended Act 4 of 2013 was come inforce with effect from 18-01-2013

• Clause 2 of Act says-

• When one person signifies to another his willingness to do or abstain fromdoing anything with a view to obtaining the assent of that other to such actor abstinence, he is said to make a proposal.

• When the person to whom the proposal is made signifies his assent there to,the proposal said to be accepted. A proposal when accepted becomes apromise.

• The person making the proposal is called the ‘proposer’ and the personaccepting the proposal is called the ‘promisee’.

• e) Every promise and every set of promises forming the consideration foreach other is an agreement.

• g) An agreement not enforceable by law is said to be void.

• h) An agreement enforceable by law is contract.

• i) An agreement which is enforceable by law at the option.

• A contract is based on reciprocal promises. Reciprocal promises by theparties are conditions precedent for a valid contract. A contract furthermoremust be for consideration.

• “Consideration means a reasonable equivalent or othervaluable benefit passed by the promisor to promisee.

• Clause 3 of Chapter 1 of Indian Contract Act, 1872 elaboratesCommunication, acceptance, and revocation of proposals:-

• The communication of proposals, the acceptance ofproposals, and the revocation of proposals and acceptances,respectively are deemed to be made by any act or omission ofthe party proposing accepting or revoking by which he intendsto communicate such proposal, acceptance or revocation orwhich has the effect of communicating it.

• Clause 10: what agreements are contracts? All agreements arecontracts if they are by free consent of parties competent tocontract for lawful consideration and with lawful object and arenot here by expressing declared to be void.

• Clause11: Who are competent to Contract? Every person iscompetent to contract who is of the age of majority accordingto the law to which he is the subject ( Indian Majority Act1875(9 of 1875)) and who is of sound mind and is notdisqualified from contracting by any law to which he is subject.

• Clause 13: Two or three persons are said to consent when theyagree upon the same thing in same sense. Consent is said to befree when it is not by coercion, undue influence, fraud,misrepresentation, mistake.

• Clause 20: Agreement is void when both parties are undermistake as to matter of fact.

Void Contracts:

• Clause 24: Agreements are void of considerations and objectsunlawful in part.

• Clause 25: Agreement without consideration void, unless it isin writing and registered, or it is promise to compensate forsomething done or is a promise to pay a debt barred by aLimitation law.

• Clause 29: Agreements void of uncertainty: - Agreements, themeaning of which is not certain, or capable of being madecertain, are void

• Essentials of Contract: According to Section 10 of Indian Contract, 1872-All agreements are contracts if they are made by free consent of parties competent to contract, for a lawful consideration and with a lawful object, and are not here by expressly declared to be void.

• “Nothing here in contained shall affect any law in force in India and not here by expressly repeated by which any contract is required to be made in writing or in the presence of witness or any law relating to the registration of documents”.

• Offer: When one person signifies to another his willingness to do or abstain from doing anything with a view to abstaining the assent of other, by such act of abstinence he said to make a proposal or offer. Acceptance of offer must be absolute unqualified and unconditioned. The Communication of Acceptance be made by letters, it will be complete at the time when and at the place, the letter of acceptance is posted

Contracts in Public Works Departments(State Engineering Depts. for Project Works and maintenance works)

• K2 Contract: The value of contract is very less and meant for piece work of small item of work. Process will be one time and single payment.

• Lump sum Contract(LS): A LS contract is one to complete the work comprised it in for an ascertained and specified sum, or for a specified sum subject to it being increased or diminished by taking into consideration the value of extra done and omission made in accordance with the contract.

• LS contract is also called Item rate Contract paid based on measured quantity with rate quoted of that specific item by Contractor as per agreement.

• The State Engineering departments are following LS Contract since inception even during pre independence Era. and even today 90% contracts are LS Contracts.

• Turn Key Contract: The Turn key Contract term is used in design and builds contracts. It may be that it is intended to indicate that upon completion the Key can be turned and everything will be ready.

Engineering Procurement and Construction Contract (EPC):• In LS contract after doing Hydrology and Soil investigation, surveying, designing

and drawing, estimating cost, bill of quantities, preparing specification for eachitem of work and sub work, and the tenders will be floated.

• The Success full bidder there upon enters in to an agreement with employer.

• He commence work and will be arranged payments as per bill of quantitiesperiodically according to progress.

• Whereas the EPC contract is similar to a Turn Key contract. The Internal BenchMark value of the project or package work will be considered with requiredproject completion in a certain period of contract.

• The total completion of project will be divided in Mile stones assigningpercentage of progress.

• The tenders will be and lowest tender will be awarded EPC contract. It is theresponsibility of EPC contractor to investigate, submit designs for obtainingapproval (Engineering), Procuring materials at his end and commence, construct,and complete the work within Agreement period at quoted total cost of Project.

• But all operation by EPC Contractor shall with in frame work of all approvals fromtime to time by employer. Instead payment by bill of quantities in LS Contract,

• EPC payments will be made according achieving the Mile stones stipulatedin agreement and satisfying technical and general specifications afterparticular percentage completion of work.

• After final and full completion of Project or Package, the full payment willbe arranged safe guarding employer interests of defect liability andmaintenance of work to specified period mentioned in agreement.

• All major project were taken up under EPC contract mode since 2003-2004in WRD (erstwhile I&CAD Dept) and some were completed with balance inprogress.

• The APDSS, Department Code, Accounts Code were basically brought insuiting LS contracts since a long time.

• After EPC contracts introduced necessary amendments to these codes wereissued by Government from time to time along with guidelines andamended rules-regulations of state.

• The original clauses of D Code(LS Contract) are very much applicablesubletting, deleting portion work from main contract to entrust to othercontract(clause:63C) and Termination Clause 61 are very much in force

under EPC too.

EPC CONTRACT SYSTEM

(ENGINEERING PROCUREMENT CONSTRUCTION)

( Dr.ISNRaju, Former CE,CDO, & Member,TAC-WRD,AP)

EVOLUTION OF CONTRACT SYSTEM

CONTRACT SYSTEM• A promise enforceable by law

• Offer acceptance (legally binding)

• To be legally binding as a contract, a promise must be exchanged foradequate consideration. i.e., benefit a party receives.

AGREEMENT• “Every promise and every set of promises forming the consideration for

each other is an agreement ” section 2 (e) of the Indian Contract Act1872 ( as ammended by Act 1 of 1997).

AGREEMENT AND CONTRACT• An agreement which is enforceable by law is considered to be a

contract – section 2 (h) of the Indian Contract Act.

GOVERNMENT CONTRACTS

Government is, by far, the largest contractor in any country, so too inIndia. Supply products (purchases ) and services (consultancy, labouretc.,)

Contracts entered into between private persons and the governmentare governed by article 299 of constitution of India.

Article 299 stipulates “all contracts made in exercise of the executivepower of the union or the state shall be expressed to be made by thepresident or by the governor of the state as the case may be and allsuch contracts and all assurances of property made in the exercise ofthat power shall be executed on behalf of the president or the governorby such person and in such manners as he may direct or authorise”

Neither the president nor the governor shall be personallyliable_______”

CONTRACT SYSTEM IN AP

AP Financial code mentions only 4 forms ofexecution of work, vide chapter VIII, Article 163

1) Department execution

2) K2 Contract – Piece Work

3) Lump Sum Contract

4) Schedule Contract

Only the first 3 forms are in vogue in GovernmentDepartments

1) DEPARTMENTAL EXECUTION OF WORKS :

The Public works are executed departmentally, by

engaging work charged staff.

2) K2 CONTRACTS :

When several developmental works were taken-up, it

became difficult to manage several works with the

available meagre work charged staff. The system of ‘K2

Contracts’, or piece work agreements have come into

force. This is basically a labour and material supply

agreement and the contractor has to execute the work,

strictly as directed by the Engineer-in-Charge and with no

responsibility fixed on him.

3) L.S. Contracts :

As the number of experienced contractors started raising,

with the passage of time, the ‘Lump Sum’ contracts have

come into force. In this form of contracts, the contractor

has to execute the work as per Designs & Specifications

issued by the Department by duly employing technical

persons. The contractor is also responsible for QUALITY

EXECUTION of work.

Estimates, Administrative Approval and Technical Sanction(Article 185 of “F” code, para 99, 101, 102, 154, 390 of A.P.P.W. “D”

Code, G.O.Ms.No.94 dt.1.7.2003)

State Government works are executed following thespecifications, rules and regulations laid down in:

AP Standard Specifications (APSS)

ISI, IRC, MOST, CPWD etc specifications

AP Departmental code

AP Accounts code

G.O’s issued from time to time

In Irrigation department, for every project, estimates are

prepared on 3 different occasions.

First, at the time of preparation of feasibility report; a very

rough estimate is prepared, based on experience in construction

of similar projects.

When once Government accords approval to take up detailed

investigation, a detailed project report (DPR) is prepared based

on preliminary designs.

In the DPR the main canal estimates are prepared on levels

taken at 200 m interval. For the distributor net work and

CM/CD works estimates are drawn from cost curves. There are

bound to be variations when actual construction takes place.

Government first accords Administrative Approval, based on

DPR estimates.

When actual execution is taken up, further detailed investigation

is carried out at closer intervals of 25 m, actual quantities are

worked out and then detailed estimates are prepared adopting

Rates as per:

The common SSR (Standard Scheduled of Rates) of all

Engineering Depts approved by Board of Chief

Engineers every year (which comes into force with effect

from Ist June of every year).

The Estimated Amount thus arrived will be the ECV

(Estimated Contract Value) of the tender put to bid.

The technical sanction is accorded by the competent authority

and after technical sanction, tenders are invited.

It is observed in practice that detailed estimates prepared so

carefully are also revised based on actual at the time of

construction.

Revised Estimates (Article 197, Para 214, Para 215 ).

A revised technical estimate must be submitted when the

expenditure is likely to exceed the amount of sanctioned

estimate plus such excess as can be passed by the appropriate

authority for any case what ever other than tender premium or

when material developments or deviations necessitate revised

administrative approval.

21

Flaws in the existing practices

Abnormal variations in the sanctioned estimates and revised

estimates.

Delays due to non-finalization of alignment, non-approval of

drawings, delays due to approval from competent authority for

change in soil classification, Change in leads and lifts and delays in

land acquisition and R & R.

Prolonged litigation by Arbitration.

Thus there are both time and cost overruns in conventional

tender system.

22

EXAMPLE:

Telugu Ganga Project started in 1983 with an estimated cost of Rs.

640 crores and programmed to be completed in 6 years,

expenditure till 2003 was Rs 1800 crores with stage of completion

@ 60%. Balance works are taken up and nearing completion under

Jalayagnam Programme. The total revised cost of project is about

Rs. 4000 crores with actual completion period of more than 25

years.

23

Prolonged Litigation by ARBITRATION:

Arbitration clause as per act, was introduced in L.S. contracts, with a nobleintention to render quick justice.

The most common factors in the arbitration claims areChange in quarries and increase in leads,Reclassification of soils strata,Delays in processing of Land Acquisition and R & R,Delays in processing of Project Clearances from different departments and

acquisition of forest areas etc,.

All these lapses are often attributed to the Department and the Department inmost of the cases put up a meek defense and leads to exorbitant claims used tobe admitted.

Government, therefore, brought a change in the system in 1986, putting a ceilingof Rs. 50,000/ for resolution of disputes through Arbitration. For claims above Rs.50,000 agency has to seek dispute resolution only through civil suit. This hasresulted in bringing down the amounts due to arbitration claims drastically.

24

CAG in his report ending 31st March, 2004 has reviewed 24

Irrigation projects (10 Major and 14 Medium), out of which

17 were more than 20 years old, taken up in Andhra

Pradesh and has observed that out of 24 projects 13 projects

only giving partial benefits and in respect of 11 projects no

benefits accrued. It was also observed as “Delay in

completion of the projects resulted in huge cost overrun

(583%) and non-achievement of intended benefits (vide

para 1.8.1 of CAG Report for the year ended 31st March ,

2004. )

Observations of CAG

Concept of

EPC Contracts & Salient Features

26

NEED FOR EARLY COMPLETION OF IRRIGATION PROJECTS

Certain areas of Andhra Pradesh have been under the severe influence ofDrought for many years. Agriculture in those areas were fully dependenton monsoon.

The livelihood of farmers in those regions were affected. Many debtstrapped farmers took the extreme step of taking their own lives.

On one hand more than 2000 TMC of water is wasted into sea every yearand on the other hand in about 800 taluks out of a total of 1128 taluks inA.P., people suffer for want of water, both for irrigation and drinkingneeds.

Thus, urgent need was felt by government for early completion ofIrrigation projects to utilise the dependable waters.

To stabilise the agricultural sector, I & CAD Department in 2004 hasintroduced the “Jala Yagnam” program.

27

In these efforts, the State Government has not onlysanctioned projects but is also giving adequate financialresources to complete the projects. From 2004 onwards tilldate, 86 irrigation projects (including major and mediumirrigation, modernization and flood banks) are taken upwith estimated cost of Rs.1,79,891.74 Crores for creatingan additional irrigation potential of 109 lakh acres.

28

CHOICE OF PROCUREMENT

To carryout the programme in a time bound manner, the Government looked

around the world the existing practices of procurement for Irrigation Projects

to obtain the best practices.

Breaking up the works into convenient packages and entrusting them to

major construction companies on EPC Turn Key System.

The EPC system is in vogue in developed countries and in some of the

public sector undertakings in India and successfully adopted in Narmada

Valley project, NTPC, NHPC, NHAI etc.

FIDIC : (French acronym for the International Federation of Consulting

Engineers)

International Federation of Engineering Consultants, Europe – released a

standard tender document.

in 1987 – Red Book (Designs by employer, work by contractor)

in 1995 – Orange Book / Yellow Book (Designs & work by contractor)

in 1999 – Silver Book – EPC Turnkey System (Definite date & definite amount)

As per this document

The Employer

(i) has to obtain all project clearances, land acquisition and R & R.

(ii) make fund arrangements and make payments in time.

The Contractor

(i) has to Investigate & Design (Engineering)

(ii) has to Procure men and materials and

(iii) construct the project

THE SILVER BOOK(EPCT Contract)

• More certain final price and time required

– Balance of risk being changed

– Privately financed BOT type

• Contractor asked to cover extra risks

• Employer will have to pay more

• Completely new book – unbalanced risk

• Full open acceptance of risk picture

• Starting point for BOT type projects

30

(contd….) EPCT Contract

The EPCT Contract is suitable for:

particularly E&M and process plant projects

all types of Employers

civil law jurisdictions

where government employer or private developer wants a fixed price turnkey basis and two-party approach

31

Special Features of theSilver Book

• Responsibility for design lies with Contractor

• Employer’s Requirements usually a ‘performance specification’ (functional basis)

• Contractor carries out all engineering, procurement, construction, ready for operation at the ‘turn of a key’

• No Engineer - instead the Employer

• Lump Sum Contract Price (but adjustments in limited specified cases)

32

(contd…) Special Features

• Testing procedures to demonstrate achievement of specified end result

• Contractor carries majority of risks, so Employer pays more

• Final price and time should be more certain

• Small number of tenders with negotiation

• Contractor given freedom to use own methods and techniques

• Has to prove reliability and performance

33

(contd…) Special Features

• These Conditions are not suitable in the following circumstances:

if time or information is insufficient before Contract signature

if considerable work underground or difficult to inspect

if Employer intends to supervise closely or control or review

if an intermediary certifies interim payments

where part of the works is designed by the Employer

34

Mr. Grove, the Eminent Engineer, who was the chairman of

the Engineers team, which executed the Hong Kong Air Port

(1990-1997) pleaded for all risks to be borne by employer.

The winning tenderer, under EPC system, will either be the

gambler or low guesser.

Mr. Christopher Wade, Chairman, FIDIC commented in 2001

that Silver Book is now a reality.

The Silver Book, has become internationally popular and is

now available on U.N. website.

36

37

E.P.C – TURN KEY SYSTEM

E.P.C (Engineering Procurement Construction) /

Turn Key System is the methodology being

adopted for expeditious completion of the

projects to achieve the targeted goals by

simultaneous Investigation, Exploration, Design,

Estimating, Procurement and Construction and

Completion of Projects in a time-bound manner.

38

ENGINEERING

The Agency (Contractor) shall carry out all the related surveys ie.,

Project site, Head Works, Canals and Distributory system etc.

The Agency shall also conduct the exploration of sub soil for

preparation of detailed designs and drawings of various structures.

The Agency shall prepare Hydraulic Particulars of canals and

designs for all Structures (Head Works and CM & CD Works) and

submit to the Department for approval. The Construction will be

taken up after approval by the Department.

The Agency shall also prepare the Land Plan schedules required

for acquisition of land for construction of the project components

including localisation of area to be irrigated and submit to the

Department for further processing and making available the lands

for construction.

39

PROCUREMENT

The agency shall work out the requirement of machinery,

material, men etc for construction and procure them as per

requirement for completion of various components of the

project as per the time frame stipulated.

The agency shall also evolve the construction programme to

complete the whole work in a stipulated period (PERT and

CPM charts) and the Department shall approve the same.

40

CONSTRUCTION

As per the approved Hydraulic Particulars, designs and drawings

for various components of the project, the construction shall be

taken up and completed by the agency as per the milestones agreed.

The agency shall establish a quality control lab and conduct

various tests to specify the quality requirements and standards

specified for each item of work as per the BIS codes.

The agency shall also maintain all the required records of the

materials, test results, mark out, placement, consolidation, and any

other registers that are required for satisfying the Department as

well as the third party quality assurance teams or any other agency.

41

The agency shall prepare the record of measurements of the work done

and produce to the Department for checking and arranging payment.

The Department shall arrange land to the agency and continuously

monitor and keep a watch on the quality of work, rate of progress,

approval of designs and take necessary actions as per agreement,

payments etc., to ultimately get the whole work completed on turnkey

basis by the agency within the stipulated period.

The agency shall also do the operation and maintenance for a period of

2 years after completion of the project. During the operation and

maintenance period of the system they should ensure water supply to the

whole of the ayacut contemplated under the project.

The contractor will be discharged of his responsibility only after

successful performance of all the above conditions.

42

ADVANTAGES OF EPC SYSTEM

The procurement is for completion of the job in totality, but not

for completion of quantities assigned, as per the existing age old

practice.

The contract covers investigation, soil/foundation exploration,

preparation of designs & drawings, procurement of materials and

execution of the work to complete the job in all aspects.

Minimization of Project cost due to competitive designs and

latest construction techniques.

Advantages. . .

43

Contract value is only one fixed amount. No additional payments

either by way of increased quantities, variation of classification of

soils, increased foundation depths, deviations due to leads, change

of quarries etc. will be given.

This system is followed in Narmada valley project and other

Central Government undertakings and has been completed

successfully.

44

Pre-qualification (RFQ & RFP) In case of specialised nature of works, tenders for pre-qualification

will be called for inviting the firms having required experience inthat specialised category of works.

They will be short listed against some qualification criteria.

Whenever the tenders are called for that specialized category ofwork, only these short listed firms will be eligible to tender.

Tender (bid) documentsTender documents are to be approved by the authority who accordstechnical sanction.

Tender (Bid) documents comprise off

NIT (Notice Inviting Tenders)

Instruction to bidders

Conditions of contract (General/special)

Technical Specifications

Basic Parameters / Project Profiles

Mile Stones (Annexure – I)

Payment Schedule (Annexure – II)

45

AREAS TO BE INVESTIGATED IN

EPC SYSTEM

Mobilisation advance taken for men and materials is

being properly utilised.

Whether 5% Machinery advance taken is being

properly invested for purchasing new or old machinery

and availability of them at the site of work.

Whether insurance coverage is taken. Verification of

Bank Guarantees regarding genuinety.

Whether 5% advance on labour, materials, machinery

and its crew is properly utilised.

46

Whether establishment of Quality Control Laboratory and

Equipment provided is sufficient to conduct various tests

during execution of work.

Deployment of Technical Agents at the site of work.

Whether all the investigations required for the project is

being carried as per agreement conditions.

Like carrying out foundation exploration / bore hole

data / permeability tests / bearing capacity of soil strata

etc., for arriving soil parameters for designing the

project elements.

Whether various tests required for materials as per BIS

Codes and agreement is being conducted.

47

Whether all specifications required as per agreement and

approved drawings are being followed.

Conducting the field test on the day of working

Testing of materials being used on the work like

cement, steel, sand, aggregates etc.

Conducting of Non-destructive tests.

Whether payments made to the contracting agencies are as

per actual execution and drawings and according to the

agreement conditions.

Whether advances paid are being recovered regularly

including interest accrued from the work bills as per

agreement.

48

Whether the work is being executed as per milestones agreed

according to the agreement.

If not, reasons for not achieving the milestones.

Is it due to contracting agency fault or department

delay.

If it is due to agency fault, whether liquidated clause is

imposed and recovered as per agreement.

If it is due to departmental delay, whether revised

milestone programme is approved by the competent

authority.

49

Whether recoveries like Siegnorage fee, IT, VAT and other

statutory taxes are being recovered from the work bills.

Whether defects pointed out by various supervising agencies

being rectified or redone.

Whether labour amenities are provided to the working labour

and their families.

Verification of final measurements for the completed works

and comparing with approved drawings.

INSTITUTIONAL ARRANGEMENTS:

1. IBM : Through a High Level Technical Committee.

(Eng in Chief, CE/CDO and Concerned Project Chief Engineer)

2. State Level Standing Committee: ENC, CE/CDO,. Commissioner of

Tenders, Chief Engineer (Projects), representative of Finance (DOA).

(Evaluation of Tenders, Price Escalation, Addition / Deletion of work,

Extension of time, Sub-Contracts etc.,)

3. ENCs Committee: To examine agreements, deviations in basic project

parameters and other issues, as directed by the Government.

4(a). High Power Committee: Chief Secretary, Spl. Chief Secretary

(Finance), Secretary, Irrigation. For scrutinizing tenders and recommending

category – I packages, each valued above Rs. 150 Crs.

(b). Committee of Secretaries: Prl. Secretary (Finance), Secretary (W&P)

Finance and Secretary, Irrigation. For scrutinizing Medium Size Packages

(below Rs 150 crores).

51

Safe Guards

in EPC System

52

Safe Guards against inflation of estimate

Internal Bench Mark

ECV (Estimated Contract Value as per detailed estimate) inconventional LS contract method is replaced by Internal BenchMark in EPC mode of contracting.

IBM is prepared by field Engineers with provisions made based onthe cost of already approved similar items of work, data from theavailable DPRs, arriving at prorate cost by detailed survey of someportion of ayacut / command and scrutinized and approved by theconcerned Chief Engineer.

53

Safe Guards against inflation of estimate (Contd….)

To further safe guard the sufficiency of the IBM value i.e. fromeliminating any unnecessary provisions / inflation as well as toinclude any missing essential provisions, IBM Committee consistingof the following TechnicalExperts was constituted by the Government1) Engineer in Chief (of the respective region)2) Chief Engineer, CDO.3) Chief Engineer (of the concerned project)

The IBM Committee examines the provisions and finalises the IBMvalue.

54

Designs Safe Guards The EPC Agency is not vested with approval of any Designs.

Approval of all designs is vested only with the Department i.e. Chief Engineer,CDO, concerned Chief Engineer / Superintending Engineer as per delegationensuring compliance of the standards stipulated as per the CWC guidelines,Bureau of Indian Standards (Formerly IS Codes).

Detailed design guidelines were also issued from time to time .

Further guidelines for approval and finalisation of designs of structures wereissued streamlining the whole process vide Government Memo No.3277/Reforms/2008 Dt: 2-4-2008.

Foundations of all Earth Dams and major structures, deep cut reaches tunnelsetc, get inspected by the Geological Survey of India and designs are finalizedas per their suggestions irrespective of proposals of the EPC Agency.

55

Construction Safe Guards

EPC Agency is not allowed to take up any item of work on hisown.

Construction work by the EPC Agency either Earth work orconcrete work etc., is permitted only after due checking of themark out / passing the area by the field Engineers of theDepartment duly ensuring necessary soil explorations, materialtesting, design mix for concrete etc.

Necessary checks are exercised by the respective level of FieldEngineers.

The measurements recorded are check measured (as per thepercentages stipulated) by the Field Engineers up to level ofSuperintending Engineer and certified by the TPQC Agencybefore recommending for payment.

56

Quality Control Safe Guards

The quality control of all works executed by the EPC Agencies ischecked by the Field Engineers and quality control wing of theDepartment / V& E.

No materials i.e. soils, sand, metal, cement, steel is allowed to beused in the works without fully satisfying the characteristics of thematerial by the Field Engineers of the Department.

Other tests on the dams, concrete structures, gates, pumps,Motors, Pressure mains etc., are also carried out regularly by thefield engineers and quality control wing of the department.

57

Quality Control Safe Guards (Contd….)

Apart from the above, 3rd Party Quality Control Agencies arealso engaged to carry out necessary tests to assure the qualityof works executed out by the EPC Agencies.

3rd Party Quality Control independently carry out qualityassurance measures by engaging experts like experiencedengineers and Professors from reputed universities /Engineering Colleges by establishing their own mobile testinglaboratories, central laboratory and all other equipmentrequired.

58

Quality Control Safe Guards

Detailed guide lines for quality control were issuedvide Engineer-in-Chief, Irrigation Circular Memo No.DCE-I/OT MP/AEE/29384/2005-3 Dt: 15.6.2006.

Without the certificate issued by the 3rd party qualitycontrol after fully satisfying quality standards of theworks, no bill is admitted for payment.

Chief engineers for Quality Control also supervisequality aspects.

59

Performance Safe Guards

Price Adjustment

Normal full price adjustment clause was not allowed for EPCcontracts .

As a Safe Guard, Price adjustment of Cement, Steel, Fuels andelectro mechanical components only were allowed for EPCcontract leaving aside other materials and labour whichconstitutes major amount in EPC Agreements.

60

Performance Safe Guards(Contd…)

Mobilization Advance

As per earlier procedure works exceeding more than Rs. 1.00 croreof estimated contract value are permitted to avail mobilizationadvance in two installments equivalent to 10% of the contractamount (5% for labour mobilization and 5% for machinery andequipment).

As a safe guard, mobilization advance of 5% towards Labourmobilization is paid in two installments i.e. 1% after concludingagreement and 4% at the time of commencement of work aftercompletion of investigation, design and survey (clause 49.1 of theAgreement) as per instructions of Government vide Memo No.26135/Reforms/06 Dt: 16.9.2006.

61

Performance Safe Guards (Contd…)

Maintenance Period

As Safe Guard towards performance of the system aftercompletion under EPC contract, Maintenanceresponsibility is vested with the EPC Agencies for a periodof 2 to 15 years as per system need.

After completion of the Project, the agency shall takecare of maintenance for a period of 2 years in respect ofgravity canal systems and 5 to 15 years in respect of LiftIrrigation Schemes.

The agency shall be responsible for the maintenance ofall components of the project including associated worksin accordance with prudent utility practice (Clause – I ofSection – V of the Agreement).

62

Performance Safe Guards (Contd…)

Commensurate Bank Guarantees for both performance guarantee as well as mobilization advance.

Retention amount

The Department retains from each payment due to thecontractor at the rate of 7.5% of bill amount as FSD untilcompletion of the whole of the works.

The retention amount so accumulated will be released to atune of 5% against Bank Guarantee in Spells of Rs. 25.00 /50.00 lakhs. (Clause 47.1 of the Agreement) keeping a balanceof 2.5% (clause 47.2 of the Agreement)

5% (2.5% from EMD and 2.5% from FSD) of the value of workwill be retained till defect liability period of 2 years.

63

Performance Safe Guards (Contd…)

Liquidated Damages

As Safe Guard against delays in exemption of contract, LD are stipulatedin the Agreements.

If the contractor fails to complete whole of the works or any part thereofor section of the works within the stipulated periods of individual milestones (including any bona fide extensions allowed by the competentauthority without levying liquidated damages), the SuperintendingEngineer may without prejudice to any other method of recovery willdeduct one twentieth of one percent (0.05%) of respective mile stonefinancial programme value per calendar day or part of the day for theperiod of delays subject to a maximum of 10% of the contract value asdamages due from the contractor from any amounts in his hands due orwhich may become due to the contractor (Clause – 48.2 of theAgreement).

64

Performance Safe Guards (Contd…)

Insurance

The contractor shall obtain and maintain in forceincluding period of maintenance, contractor all riskinsurance for the project providing full coverage onreplacement value basis. Covered peril shall include fire,flood and allied perils.

Insurance for workers against injury and death as perworkman compensation act shall also be obtained bythe contractor (Clause – 8 of Section – V of theAgreement)

65

Payment Schedules for Civil, Hydro-mechanical and Electro-mechanical works

Payment for Earth Work Excavation and lining of gravity

canals:

A) The unit length of eligibility for arranging payment for earth work

excavation of canals (excluding CM & CD works) shall be taken as 100 M.

for main canal (discharge more than 10000 Cusecs), 250 M. for main

canal (discharge between 1000 cusecs and 10000 cusecs), 1.0 Km. for

branch canal and distibutaries/majors (discharge between 10 cusecs and

1000 cusecs).

B) In case of deep cuts, the payment schedule shall further subdivided into

components berm wise with a bay length of 25 M. and the berm wise

payments shall be followed duly restricting the berm wise payment to a

maximum length of 1 KM. in a reach (Govt.Memo No.3277/ Major. Irri/

2006-5, Dt.24-2-2007).

C) The unit length for eligibility for arranging payment for lining of canals shall

be taken as 100 M.

66

Payment for construction of CM & CD works:A) In respect of CM & CD works, the intermediate payments shall

be in three stages, i.e., at (a) Completion of foundations

including earthwork, (b) Completion of Sub-structure and (c)

Completion of Super structure including miscellaneous items.

The mode of payment shall be 30% after completion of

foundations, 30% after completion of Sub-structure and balance

40% after completion of individual structure.

B) However, 30% of payment against 40% in the 3rd stage shall

be released after completion of deck slab of the structure (CM

& CD works), other than Aqueducts and super passages and

remaining 10% shall be released after completion of structure

in full shape. (Govt. Memo. No. 31960/ Reforms/2007-1, dt.

27.5.2008)

C) In case of big structures where ever the length of structure is

more than 40 M. and above on main canal, the Chief Engineer

may revise the payment schedule subject to ensuring that the

over all payment is limited to the agreement value. (Govt.

Memo. No. 37245/ Reforms/2007-1, dt.11.2.2008)

67

Payment for Hydro-Mechanical works:

A) 85 % of the quoted price of Hydro-Mechanical works component for

supply of goods including fabrication (for price including all taxes

and duties) shall be paid on receipt at the Project Site based on

certificate prepared by Engineer-in-Charge and Supplier’s

Representative, on the basis of various items received in

accordance with the Contract Agreement.

B) 10 % of quoted price of Hydro-Mechanical Works component shall

be paid on erection, testing and commissioning of equipment, on

pro rate contract value of work completed as per the agreed

construction schedule and on certification by the Engineer-in-

Charge and Supplier’s Representative.

C) Balance 5 % of the quoted price of Hydro-Mechanical Works

component shall be paid at the time of final bill.

68

Contingent works

Where work can not be proceededindependently without interfering with thework let out but have necessarily to beexecuted along with the original contract shallbe considered as contingent on the originalwork.

Contingent works may be with in the definedscope or out side.

69

Non Contingent Works

Wherever additional items not contingent onthe main work and outside the scope oforiginal agreement which has to be executedalong with the original work are noncontingent works.

70