Development of a 11.2 MW Multi-Campus Solar Project. Mount Diablo Unified School District. October 26, 2010. Agenda. System Specifications Project Team. Economic Benefits Environmental Achievements Educational Opportunities. System Overview. Corporate Strength O&M Services - PowerPoint PPT Presentation
Citation preview
Development of a 11.2 MW Multi-Campus Solar Project
October 26, 2010
Mount Diablo Unified School District
2
Agenda
System Specifications
Project Team
System
Overview
Economic Benefits
Environmental Achievements
Educational Opportunities
Triple Bottom Line Benefits of Solar
Corporate Strength
O&M Services
Performance Guarantee
SunPower’s
Capabilities
3
PG&E Source of Energy – Expensive and Volatile
Source: PG&E, http://www.pge.com/myhome/edusafety/systemworks/electric/energymix/index.shtml
PG&E is largely dependent upon natural gas, an expensive and volatile source of power.
California nuclear plants are being decommissioned, not replaced
Source: US Nuclear Regulatory Commission, http://www.nrc.gov/info-finder/decommissioning/
Map of the United States Showing Locations of Sites Undergoing Decommissioning:
4
Comparing the Solar Choice and the Non-Solar Choice
5
Neither choice is cost or risk free (i.e., electricity is not free)
– Not doing solar means continuing to purchase ~ 21 million kWh ($3.68 million) per year of electricity at unknown but likely increasing rates over the life of the system.
– Doing solar would reduce PG&E usage by ~17 million kWh per year and would enable the District to capture ~$16 million in CSI incentive payments during the first 5 years.
6
SunPower will offset 91% of the District’s PG&E bills by generating 81% of the District’s energy usage
RENEWABLE ENERGY TARGET = 81%
Electric Energy Usage – All 51 Schools* 21,305,397 kWh
SunPower Solar Generation 17,171,710 kWh
Percentage of Energy from Solar 81%
UTILITY COST OFFSET = 91%
Annual PG&E Energy Bill – All 51 Schools * (Before Solar) $ 3,681,410
Annual PG&E Energy Bill – All 51 Schools * (After Solar) $334,991
Estimated Bill Savings from Solar Generation $3,346,418
Percentage of PG&E Energy Bill Reduced 91%
*Annual Current Energy Bill is based on PG&E rate tariff as of June 1st, 2010(Historical Energy Bill $3,365,134)
Energy Bill Savings
7
Vanir-Line Item Roebbelen SolarCity SunPower ParsonsBaseline - without project
1 District Utility Costs w/o Solar 295,606,721$ 295,606,721$ 295,606,721$ 295,606,721$ Expenses
2 District Utility Costs w/ Solar 129,007,657$ 130,756,838$ 119,225,831$ 124,664,240$ 3 Capital Costs (Solar Contract) 59,377,330$ 56,259,883$ 67,404,796$ 79,779,728$ 4 Sub-total Expenses 188,384,987$ 187,016,720$ 186,630,627$ 204,443,967$
Savings and Revenues5 Utility Bill Savings 166,599,065$ 164,849,884$ 176,380,890$ 170,942,482$ 6 CSI Revenues 15,545,955$ 15,236,243$ 16,150,815$ 17,433,635$ 7 Sub-total Savings and Revenues 182,145,020$ 180,086,126$ 192,531,705$ 188,376,117$
Net Benefits8 Net Savings w/o Capital Costs 182,145,020$ 180,086,126$ 192,531,705$ 188,376,117$ 9 Net Savings w/ Capital Costs 122,767,690$ 123,826,244$ 125,126,909$ 108,596,389$
Notes1. Costs expressed as 30-year nominal totals except line 3, capital costs2. Line 3 includes Maintenance contract and Performance Guarantee expenses3. Key assumptions: annual utility escalation rate = 4.47%, annual District load growth = 2%, CSI incentive = $0.19/kWh
Comparison of Proposal Costs and Benefits30-Year Project Analysis Period
8
Environmental Achievements
Equivalent savings (based solely on offset CO2 emissions)
Annual Lifetime
Planting trees (acres) 1,858 55,740
Not driving (miles) 17,709,484 531,284,533
Removing cars (cars) 1,494 44,811
Homes Powered (homes) 1,435 43,055
Offset Home Energy Use (homes) 722 21646
Mt. Diablo USD environmental achievements sets the bar high for other Districts in carbon footprint reduction
9
Program Elements
•Lesson Plans (“How Does Solar Work?” and more)
•Multimedia and Social Networking Tools
•Teaching Videos
•Real-Time Data Monitoring Activities connected with your District’s solar power systems
•Classroom & Assembly Guest Speakers
Program Elements
•Lesson Plans (“How Does Solar Work?” and more)
•Multimedia and Social Networking Tools
•Teaching Videos
•Real-Time Data Monitoring Activities connected with your District’s solar power systems
•Classroom & Assembly Guest Speakers
Educational Opportunities
Mt. Diablo USD’s students will have access to educational opportunities on renewable energy
10
System Overview
TECHNICAL OVERVIEW PROJECT ECONOMICS
Systems 11.191 MWp of parking canopy and shade structures System Price $60,166,112
Total Footprint 666,109 sq ft Energy Cost ($/25-year kWh) $0.1487 per kWh
Energy Density 16.8 watts/sq ft Schools "zero out bill“ or 80% load offset 46
Shade Structure only (%) 19% Constrained Sites 5
Parking Canopies only (%) 42%
Mix of Shade and Parking (%) 39% MAINTENANCE
Module Type SunPower 318 –20-year maintenance, including cleaning and upkeep
Average Performance (Yield) 1,525 kWh/kWp–20-year Performance Guarantee at 95%, valued at full value of lost power (PG&E + CSI incentives)
Energy Output (Year 1) 17,171,710 kWh –Systems built over 3 increments from Q3, 2011 – Q1, 2012
Energy Output (over 25 years) 404,495,967 kWh –Warranties: modules for 25 years; inverters for 20 years
Northgate High School
11
SYSTEM SPECIFICATIONSMounting
TypeModule
TypeSystem size
kWDC
System sizekWAC
Energy Yield (kWh/kWp)
1st Year Energy Production
(kWh)
Total Footprint(sq ft)
PC (array 1-8) SS (array 9)
SunPower 318 SunPower 318
1037 917 1,549 1,606,602 61,718
PROJECT DETAILSBusiness As Usual After SunPower Solution
Rate Tariff E19S A6Annual Current Energy Usage (kWh) 1,914,387 1,606,602Annual Current Energy Bill ($)* 300,030 0Average Energy Value ($/kWh) 0.1567 0.1867
ECONOMIC BENEFITS ENVIRONMENTAL BENEFITS% Energy Usage Offset 84% CO2 Emissions Savings (lb) 1,686,187
% Energy Bill Offset 100% Annual Equivalent Planting Trees (acres) 174Annual Savings ($) 300,030 Annual Equivalent Removing cars (units) 140
12
Northgate High School
13
Northgate High School
14
Northgate High School
15
Northgate High School
Glenbrook Middle School
16
PROJECT DETAILSBusiness As Usual After SunPower Solution
PG&E Rate Tariff A6W A6Annual Current Energy Usage (kWh) 370,200 312,052Annual Current Energy Bill ($)* 68,035 0Energy Value ($/kWh) 0.1838 0.2180
SYSTEM SPECIFICATIONSMounting
TypeModule
TypeSystem size
kWDC
System sizekWAC
Energy Yield (kWh/kWp)
1st Year Energy Production
(kWh)
Total Footprint(sq ft)
SS (array 1-3) SunPower 318 201 178 1,549 312,052 11,988
ECONOMIC BENEFITS ENVIRONMENTAL BENEFITS% Energy Usage Offset 84% CO2 Emissions Savings (lb) 353,076
% Energy Bill Offset 100% Equivalent Annual Planting Trees (acres) 37Annual Savings ($) 68,035 Equivalent Annual Removing cars (units) 29
Glenbrook Rendering
17
Glenbrook Rendering
18
19
Project Team’s experience and knowledge ensure project success
Project Team
Experience working with the MDUSD SunPower’s commercial division (300 employees) based in Contra Costa County Member of the Contra Costa Council
SunPower Overview
Over 550 systems, and 450 MWp installed
5,000 Employees Highest efficiency in the world
Established and Proven. Technology Leaders.
$1.5B in Annual Revenue Tracker Technology
Over 25 years experience
20
Extensive Educational Experience
DSA Approval on Ground, Parking and Rooftop Systems
21
SunPower’s O&M Experience and Capabilities
Experience
Currently managing over 450 MW of solar system in 4 continents
Over 550 systems monitored
New capacity commissioned:
Over 120MW in 2008
Over 100 MW in 2009
40 in house O&M team members
Capabilities
Full service O&M including operations, maintenance, meter reading, and warranty administration
Most experience PV Technicians in the Business
More operational systems under management
Comprehensive monitoring and reporting capabilities
22
SunPower’s technology combined with best-in-class O&M services ensures the greatest return
AvailabilitySystemUptime
PerformanceOperation at
Peak Production
ReliabilitySystem
Longevity
Scope of Services Performance Plus(w/ Module Cleaning)
Customer Technical Support Hotline
Performance Monitoring Website
Performance Reports Monthly
Daily Performance Monitoring and Notification
Preventive Maintenance & Inspections Annual
System Testing Annual
Performance Review Annual
Corrective Maintenance
Module Cleaning Annual
O&M Approach
SunPower’sO&M
Approach
Scope of Services
23
Performance Monitoring Website
http://www.sunpowermonitor.com/commercial
SunPower’s Performance Guarantee
Experience– SunPower has over 50 Performance Guarantees in place.
– Backed by SunPower’s Operations Center based in Richmond, CA
MDUSD Performance Guarantee Contract:– 95% of expected output
– 20-year Term
– Upside Sharing by SunPower: none
– Accounts for value of PG&E energy rates + CSI incentives Average reimbursement rate: ~21 cents
24