Final Report on Capacity Review of Organization for Rehabilitation and
Development in Amhara (ORDA)
By: Abidan Development Consulting Group Plc
abidan
November 2016
i | P a g e
i. Acknowledgement This capacity review has been initiated by FHE and conducted by Abidan Development
Consulting Group Team under the guidance of FHE. Several individuals (ORDA’s senior staffs
and experts, FHE Management staffs and experts, and Government Stakeholders) have been
contacted and made significant contributions for the realization of this study. We would like to
thank all Institutions and Individuals whom we contacted and provided us with all the pertinent
information for the review.
We are grateful to ORDA’s management for the invaluable support, facilitation and coordination
at their office which helped us accomplish the planned activities as per the schedule.
Undertaking this assessment would have been very difficult without their cooperation and
supports.
We would also like to express our heartfelt gratitude to FHE team for their feedbacks and
technical advices in reviewing the data collection tools and methodologies and in facilitating
communication between ORDA and FHE Bihar Dar office. FHE Bahir Dar staffs have also
helped the assessment team in supplying necessary logistics and coordination and the assessment
team would also like to express its thanks for their kind and valuable supports.
Finally our gratitude goes to FHE for giving us the opportunity to conduct this assignment and
establish enduring partnership with it.
Abidan Development Consulting Group Plc
ii | P a g e
ii. Table of Contents i. Acknowledgement .................................................................................................................... ii
ii. Table of Contents ..................................................................................................................... iii
iii. List of Acronyms ...................................................................................................................... 1
iv. Executive Summary .................................................................................................................. 2
I. Introduction ............................................................................................................................. 11
II. Background ............................................................................................................................. 11
III. Description of the assessment target groups ........................................................................... 12
IV. Objective and Scope of the Review ........................................................................................ 13
V. Methodology ........................................................................................................................... 14
5.1. Desk Review .................................................................................................................. 14
5.2. Quantitative/questionnaire based staff survey ................................................................ 16
5.3. Limitations of the Review ............................................................................................. 16
VI. FHE’s Overall Capacity Building Interventions ..................................................................... 17
VII. Assessment Findings Narration ............................................................................................. 18
7.1 Human Resource Management ........................................................................................... 18
7.2. Financial and Grant Management ...................................................................................... 22
7.3. Property and Resources Management ................................................................................ 30
7.4. Procurement Management.................................................................................................. 35
7.5. Program Management ........................................................................................................ 36
7.6. ORDA’s leadership engagement in capacity building support ........................................ 43
VIII. Relevance, Effectiveness, Efficiency, Sustainability and Impact of the capacity building efforts .. 46
8.1. Relevance of the capacity building support ....................................................................... 46
IX. Strength, Weakness, Opportunity and Threats of the capacity Building efforts .................... 49
X. Challenges ............................................................................................................................... 51
XI. Lessons learnt ......................................................................................................................... 51
XII. Conclusions and recommendations ....................................................................................... 52
12.1. Conclusion ........................................................................................................................ 52
12.2. Recommendation .............................................................................................................. 53
XII. Annex .................................................................................................................................... 57
iii | P a g e
iii. List of Acronyms
BDARP Business Development Action Research Program
BoD Board of Director
BSC Business Score Card
CCTS Country Commodity Trucking System
CGA Capacity Gap Assessment
ChSA Charities and Societies Agency
CRS Catholic Relief Services
DFAP Development Food Assistance Program
DFID Department for International Development
ESMF Environmental and Social Monitoring Framework
EU European Union
FGD Focused Group Discussion
FHE Food for Hungry
FHEE Food for Hungry Ethiopia
GPS Global Positioning System
GTP Growth and Transformation Plan
HR Human Resources
HRM Human Resource Management
INGO International Non Governmental Organization
JD Job Description
KII Key Informant Interview
M and E Monitoring and Evaluation
NGO Nongovernmental Organization
ORDA Organization for Rehabilitation and Development in Amhara Region
PSNP Productive safety Net Programme
SP Strategic Plan
TOR Terms of Reference
USAID United State Agency for International Development
VAT Value Added Tax
1 | P a g e
iv. Executive Summary Introduction: As part of the Development Food Assistance Program (DFAP), FHE has provided multifaceted capacity building supports which focuses on system development to ORDA. The objective of the support was to build ORDA’s capacity so that it can directly access USIAD grant. This capacity review is conducted with the aim of determining the contribution of these supports in enhancing ORDA’s capacity in the area of program management, financial management, human resource management, monitoring and evaluation, commodity management and leadership engagement in capacity building.
Methodology: The study employed both qualitative and quantitative methods to collect and analyze data. Secondary documents were reviewed to understand FHE capacity supports and generate the required secondary information. Focus group discussion (FGD) and key informant interview (KII) and observation were undertaken in participatory manner using checklist as a guide to collect qualitative information. The FGD was conducted with ORDA’s and FHE management staffs and experts. KII was made with senior government officials such as Head of the of Bureau of Agriculture and Head of NGO Desk in Finance and Economic Cooperation and Development Bureau of Amhara Regional State. Observation was made to see the availability and accessibility of manuals, procedures, and policies, to ORDA’s staffs. Questionnaire based staff survey has been used to generate quantitative information and then the information was fed to computer so as to be refined and analyzed (weighed) and used to substantiate the findings of the qualitative study and desk review.
Assessment Findings Narration Human Resource Management: Personnel policy: ORDA has put in place a system of revising its Human Resource (HR)
policy every two years and this enabled it to regularly update its policy documents by considering the dynamism of working environment and donor requirements.
Recruitments: Written recruitment guideline is in place and competency based recruitment process has been implemented. Significant improvement is made by furnishing a written Job Description (JD) for each staff of ORDA confirmed by the quantitative result which changed to (5/5) from (2/5) during the baseline time. The discussion with ORDA staffs confirmed that the contribution of the seconded capacity expat is enormous in bringing about this change.
Volunteers and internship management: To effectively manage the internship and get the best out of it, ORDA has drafted internship management guideline, which is in the process of approval by the management.
Staff Salary and benefits: Though some improvements were made, the salary and benefit package of ORDA remains low and this continues to be an obstacle and causes high staff turnover.
2 | P a g e
Performance Appraisal: Balanced Score Card (BSC) is implemented to review employee’s performance and the process is participatory. Although some improvements have been registered by applying BSC, the scoring system is not as such strict and is largely undertaken for formality purpose.
FHE support for HR Department: valuable supports have been provided by FHE as a result staff familiarity with USAID partnership compliance is enhanced. Quantitative result (4/5) confirmed that HR team has the required knowledge about USAID grant management requirement.
In general, HR Department of ORDA has clearly worked on the capacity gap improvement plan developed by FHE. As a result significant improvements have been made on the major gaps identified during the capacity assessment in 2012 and 2014.
Financial and Grant Management Financial Policy, Systems and Procedures: financial policy of ORDA is strict and fully in
tune with all of ORDA’s Donors policies and requirement. The Finance team at ORDA’s headquarters has good knowledge of USAID’s financial regulation requirements and the quantitative result indicated that finance department is familiar with USAID financial/grant management procedure with the average point of (4.5/5) compared to the baseline result (2.8/5). However, the finance staffs at project offices level lack the requisite knowledge in this regard.
Internal control and Audits: ORDA’s internal audit and inspection department is responsible for supervising the proper utilization of resources. Audit policy and systems are in place and being implemented. ORDA is transforming from purely cash audit to performance audit following the recommendations of the capacity advisor of FHE. This is in fact one of the key contribution of FHE support in enabling ORDA to efficiently utilize the available resources.
Budget Planning: Donor and organizational based budget planning systems are in place and Organizational based budget planning is done on annual bases. Financial documents from the field office have to be reviewed by the internal audit and budget holder (program staff) before a record in the finance section is made. The system guarantees that the budget is controlled by three sections to ensure its effective utilization. A regular meeting is held with senior management and relevant program staffs to review budget status, i.e overseeing both the approved, expenditure, and revenue. Budget variances have been fully explained as per the required standards by the program department.
Financial Reporting: ORDA has improved its capacity to comply with the financial reporting standards of the donors. The quantitative baseline data (3.2/5) showed growth to (4.5/5) and indicated that finance staffs prepare quality reports using the standard procedures of donors and submit within the timeframe. FHE financial manager also confirmed that improvement has been observed in the timely delivery of financial reports and utilization of financial reporting formats of USAID. However, finance staffs at the field office did not get necessary support to deliver financial reports using the USAID reporting formats. ORDA staffs have reflected that improvement is made on the feedback mechanisms of financial reporting and the quantitative result (4.17/5) complements the qualitative findings.
3 | P a g e
Financial sustainability and cost sharing: Resource mobilization strategies are developed. ORDA has been mobilizing the community and local government to contribute for the development projects it has been implementing. However, ORDA has no system as to how cost – sharing is tracked, monitored and reported to donors.
Grant Management: The exposure of working on USAID funded projects and programs as sub-grantee helped ORDA’s staffs to be familiar with the USAID grant management. But, roles and responsibilities of the grant management section are limited to facilitating project agreements and reminding project staff as the project agreement is approaching phase out stage to timely complete project activities. Though the grant management officers of ORDA are familiar with the USIAD grant management guideline they have not fully internalized it to regularly apply in their work.
Overall: Comparing with the baseline time in 2012 and 2014, ORDA has made remarkable improvements in most competency areas of financial management, which enabled ORDA to comply with donor requirements of grant management. Different capacity building supports were provided by FHE to enhance ORDA’s financial management capacity to comply with contract procedure of USAID. As a result, ORDA has in place a system that will help it fulfill USAID grant requirements. But, ORDA needs to work on cascading information to the project office so as to enable the finance staffs of the project at grassroots level to fully understand donor’s requirement in financial management.
Property and Resources Management Operational policy and systems: Written operational procedures are put in place for property
and resource management. The organization’s operational policy and systems are well understood by staffs and more specifically the staffs are aware of USAID funding requirements of vehicle utilization and maintenance etc.
Commodity Management: ORDA’s commodity management manual fully incorporates USAID commodity management requirements. The Country Commodity Tracking System is already instituted. Training offered by FHE on commodity management enabled ORDA to improve its store and commodity management. An experience-sharing program was organized to acquaint ORDA with the practice of international bid systems. However, ORDA has no experience handling commodity management from seaport, as this was not part of terms and condition of partnership agreement with FHE. But, lack of experience in managing commodities from seaport to distribution center is one key capacity gaps of ORDA.
Fixed asset management: A Written manual for property and transport management is under revision. The quantitative result (4.2/5) shows that ORDA has been implementing fixed asset registrar and this procedure is helps ORDA to effectively control its asset. However, there is gap in the fixed asset registration since it lacks documentation of depreciation rate calculation.
Logistic Management: Systems are established for field travel where each department develops Terms of Reference (TOR) indicating the purpose of travel, number of staff traveling, where to travel, duration, estimated budget etc and submit to finance and logistic
4 | P a g e
sections at least two weeks before the travel day and this ensures effective resources utilization.
Procurement Management ORDA has procurement policy that adequately addresses the needs of the organization.
ORDA has decentralized the purchase system and the program offices are mandated to effect purchase of up to Birr 200,000.00. In addition, ORDA delegate program offices to make purchase beyond the limit depending on compelling conditions. It has also adopted a code of conduct applied to staffs engaging in the procurement of goods and services. FHE has provided an adequate and relevant capacity building support to ORDA on USAID commodity management. The quantitative result (3.5/5) confirmed that all purchase managers, senior management, project staffs and purchasers have full awareness about the items prohibited from purchase using the USAID fund. Moreover, ORDA has developed the capacity to manage international purchase.
Program Management
Donor compliance: The program section is well aware of the USAID requirements applicable; these include submission of work plan, marking and branding plan, environmental compliance plans, semi-annual, annual reports, inventory and VAT report etc. An average quantitative result (3.8/5) is fair enough in supporting the qualitative statements. So far, there is no practice of undertaking internal and external audit related to non-compliance with donors’ regulation. But recently due to the provision of training by FHE, they understand the importance of compliance audit.
Technical Reporting: ORDA has made improvements in timely delivery of reports even though the quality of reports in terms of presenting success or case stories and documenting lessons needs further improvements. ORDA’s staffs have clear understanding of the reporting formats and accordingly prepare and submit quarter and semi-annual narrative and financial reports using USAID reporting format.
Community involvement: the community to some extent participates in the project cycle and annual performance meeting and also influence decision in some instances. However, beneficiaries do not influence decision, especially once the project/programs are designed and approved by donors.
Knowledge Management and Diffusion of Technology: ORDA has only recently prepared knowledge management guideline that is not yet familiarized for staffs. There is no practice of regularly organizing learning and knowledge sharing event and the quantitative result is also complement with an average point of (2.4/5).
Proposal development and resources mobilization: ORDA mainly develops proposal based on call for proposal. Quality proposal development, networking and linkage, quality delivery of program at ground level are among some of the fund raising practice of the organization. However, there are not clearly defined structures and Terms of References for program designing team. Despite unclear structure, the success rate of proposal for funding has shown
5 | P a g e
radical growth from the baseline (20%) in year 2014 to a success rate of 92% June 2016. The training on proposal writing has contributed in increasing the success rate of writing winning proposals and quantitative result (3.6/5) also supports the qualitative findings. The practice to internally appraise developed proposals is very limited and the proposal appraising committee does not also use the appraisal checklists of donors. ORDA is not strong in developing innovative proposal and need to work hard in this regard.
Culture and Gender: ORDA has clearly adopted guidelines for culturally relevant and/or gender-based approaches and programming. ORDA conduct gender analysis before intervention of any program so as to inform the program on the gender dynamics of the intervention areas. Despite several improvements, the gender section of ORDA has only one employee. Furthermore, gender integration work of ORDA is only at programming level. It is found that organizational performance in promoting gender is poor and women’s representation at both decision-making and overall staffing is low.
Monitoring and Evaluation: ORDA has in place monitoring and evaluation framework. There is a documented monitoring and evaluation plan, output and outcome indicators, data collection tools schedule, quality review and methods for sharing and using data. ORDA has been providing training on monitoring and evaluation, but as per the findings of quantitative result (3.2/5), ORDA need to do more work in this area. ORDA has been using monitoring and evaluation findings so as to improve the delivery of programs and projects and the quantitative data supports this result (4/5).
ORDA’s Leadership Engagement in Capacity Building Support
Networking and strategic Partnership: ORDA’s leadership perceived strategic partnership with stakeholders as a key tools to mobilize resources and extract new skills and knowledge. To enhance effective partnership, ORDA has developed Communication and Networking Strategy. This document defines ORDA’s audience and the management of ORDA believes that the communication and networking strategy helps to increase ORDA’s visibility.
Capacity building in Strategic Planning: ORDA’s recent strategic plan focused on building the capacity of ORDA to access big donors’ fund directly. Accordingly, ORDA’s Board and Management has made a decision to develop the fourth strategic plan in view of globally changing funding priorities, increasing competition in resource mobilization coupled with the unmet development needs of communities it has been serving. This strategic plan is envisaged to be used as a management tools to guide program management and implementation, resource mobilization, ensure community participation and empowerment, enhance stakeholder collaboration, efficient utilization of resource and ultimately change the livelihood of the end uses/people.
Contribution of ORDA’s Board of Directors to improve ORDA’s Capacity: the contribution of BoD in building the capacity of ORDA is very insignificant. Contrary to expectations,
6 | P a g e
BoD has not been engaging in lobbying to strengthen ORDA’s partnership and networking with donors and enhances resource mobilization.
Relevance, Effectiveness, Efficiency, Sustainability and Impact Relevance: the capacity building plan is relevant to ORDA’s capacity need in system
development and establishing strong networking and partnership as well as in fully complying with USAID grand management procedures. It is found out during discussion that ORDA had been working with USAID supported projects as sub-grantee for many years. However, it had not created the requisite capacity that helped it fully comply USAID grant management procedures and directly access funds from USAID. Therefore, the capacity building supports of FHE was the right and the most relevant support for ORDA.
Effectiveness: The capacity building support started with a comprehensive capacity assessment which used as baseline capacity gap. The startup capacity assessment report has been indispensible to measure the changes brought by the capacity building support of FHE through the DFAP. Different activities were accomplished as per the plan, but except the failure of FHE to re-fill the seconded staff position in time. The implementation of capacity support initiatives has helped ORDA to improve its capacity meaningfully.
Efficiency: The enthusiasm and interest of ORDA’s management and staff to sap knowledge and skills from FHE has helped to ensure system development and transform the organization within a short period of time. Though deployed late, ORDA has utilized the skill and knowledge of the seconded staff efficiently to enhance its system development and meaningful changes have been made on the overall capacity of ORDA as a result. However, ORDA would have been benefited a lot from the skill and knowledge of the expat had the expat used the allocated time fully.
Impacts: the capacity building support enabled ORDA to have all the necessary policy documents that incorporate USAID grant requirements. Staff understanding of the USAID grant requirements improved through different capacity building trainings provided through this capacity building initiative. Though ORDA has not yet directly accessed fund from USAID, promising practices has been indicated and ORDA has tried one proposal for USAID but unfortunately it did not get the fund.
Sustainability: The capacity building supports is founded on fertile ground in terms of addressing ORDA’s felt need, fitting to existing institutional arrangement and a long year experience of ORDA in working with USAID funded projects as sub grantee that entails a positive outlook of its sustainability. The leadership commitments in institutionalizing the capacity building efforts are encouraging as the capacity building is one area of the strategic plan of ORDA. But, staff turnover due to low salary rate may be a threat for sustainability.
7 | P a g e
Strength, Weakness, Opportunity and Threats of the capacity Building efforts
Strength: Leadership and staff commitment to implement the capacity building supports of FHE, the dedication of all the staffs to internalize the recommendations provided by the expat and commitment to act as per the recommendations and ability to create conducive work environment and Organized staffing structure.
Weakness: Unavailability of organized and clear structure that help develop proposals satisfying donor compliance and limited knowledge and information cascading structures and practices, inability to develop innovative proposals.
Opportunities: Familiarity of ORDA to USAID policies and procedures, availability of competent staff to respond to capacity gap recommendations, acceptance of ORDA by the government and target communities’, adoptions of well-defined policies, procedures, and strategic plan and availability of supportive government policies and programs.
Threaten: High staff turnover due to lack of competitive salary and benefit package.
Lessons Learnt Stepwise transformation from sub grantee to consortium and direct partnership; the strategic
move to partnership that the management of ORDA believed is prompting visibility through working in consortium and compete to directly accessing big grants. Accordingly the enhanced capacity building support enabled ORDA to be a consortium member in DFAP II program and this creates opportunity for ORDA to be more visible in USAID funding as ORDA is the lead in one of the component of the project. ORDA’s management believed that being a consortium member would transform ORDA to directly access USAID fund within the next five years.
The capacity building strategy and approach followed (i.e. assignment of the expat and starting the capacity building process from within) is found to be a good lesson. This approach has brought significant transformation.
Immense desire of the organization for change at all level can bring fast and meaningful changes, ORDA in this regards can be typical witness. All the departments of ORDA were very much aware of the gap identified by the capacity builder i.e. FHE and acted on the recommendations with dedication and commitment of both the staffs and management of ORDA.
Conclusion FHE capacity supports to ORDA found to be relevant specially in enabling ORDA to comply with USAID grant management requirements. The supports are found to be multi-dimensional and follow right and logical process. The contribution of the multifaceted supports of FHE is found to be positive and visible in every department of ORDA and the result is progressive and very strong in most departments. The supports are especially very successful in terms of enabling 8 | P a g e
each department to have their own policies and manuals as well as guidelines that harmonize donors’ policies and requirements. Moreover, the support succeeded in enhancing the knowledge and skill of ORDA’s staffs towards donors’ working environments and procedures and on how to comply with donors’ requirement. It is also noted that, the commitment, interest and dedication of ORDA’s management, technical and support staffs as well as the commitment of FHE was a fertile ground for the implementation of the capacity building supports and the achievement of the set objectives.
Recommendations
Recommendation for FHE:
The multi faceted support of FHE to ORDA has enormously contributed to enhance ORDA’s Capacity. However, the support was mainly confined to ORDA’s Headquarter. The knowledge of the project staffs and offices at Woreda level on USAID grant management is somewhat limited indicating the knowledge in not adequately cascaded to the ground. It is recommended therefore that, while undertaking such types of capacity support, FHE should consider staffs and offices of partners at ground level and should develop a system, together with the partners, to address them with adequate budget and follow-up mechanism.
FHE capacity support had two main phases: phase one: undertaking gap assessment and
ensuring availability of working policies and manuals and procedures; and second phase: familiarizing the developed policies and procedures to staffs and start working with the new policies and procedures. The first phase of the support found to be more successful than the second one. There had not been adequate time to implement the second phase and early departure of the seconded staff was also a problem. We therefore recommend FHE to assign sufficient time for each activity while doing such types of capacity building. We also suggest midterm review or other kinds of progress assessment that can help to check whether the support is on track and made timely corrections.
The major objective of the capacity support of FHE to ORDA is to help it develop a
capacity to independently access to USAID grant. In this regard FHE has enormously supported ORDA to bolster its capacity. But, the partnership agreement limits ORDA not to directly participate in some important activities, for instance participate to independently manage commodities from the seaport to the distribution centre, which was very important capacity for ORDA to access USAID grant. We therefore, recommend FHE that while carrying out such types of support, prepare a partnership agreement that have a room which enables partners like ORDA to engage in such important activities after making a thorough assessments of capacities
9 | P a g e
Recommendations for ORDA:
Though ORDA has been implementing many of projects and addressed marginalized communities, it is poor in documenting best practices and lessons that can be used as learning. We strongly recommend ORDA to effectively documenting lessons learned; best practices in a manner that can be easily accessed and used. Using technologies that can simplify accessing the best practice and lesson learnt is strongly recommended.
ORDA has different staff retaining mechanism including provision of education opportunity and providing hardship allowance. However, ORDA’s staff salary is still low comparing with the current market leading to high staff turnover. We therefore recommend ORDA to consider of improvement of staff salary and benefit package, otherwise, the staff turnover will continue to be grave danger to the organization;
Since ORDA has a plan to independently apply for USAID grant. One of the competency areas that USAID requires from ORDA is a good practical experience in effectively managing commodity from the seaport to beneficiaries. As ORDA does not have practical experience in this regard we recommend ORDA to acquire such experience using all available opportunities.
With the support of FHE, ORDA has established fixed asset management systems with trained staffs. However, the fixed asset registration lacks documentation of depreciation rate and calculation. We therefore, recommend ORDA to effectively document depreciation rate and calculation for the fixed asset.
Over the last thirty years ORDA has ensured progressive achievements that helped millions of marginalized people to be survived and improve their livelihood. However, ORDA has no practice of regularly organizing learning and knowledge sharing event. In order to be more visible at national and international level, ORDA need to organize such events regularly and invite donors’ communities and stakeholders to these events. This event will help ORDA to be on board with donor communities and other important stakeholders.
As per the assessment, ORDA is successful in preparing wining proposals. However, it is found out that ORDA is not strong in developing innovative proposals that have taken in to account the current climate change and the changing needs of the donors. We therefore, recommend, ORDA to work hard in this regards to develop innovative projects (that use renewable energy sources like solar and wind power) and win the attention of the donors’ communities.
Integrating Gender at organizational level is overlooked. This is clearly manifested at the leadership position of ORDA where no woman is represented. Therefore, in order to maximize the impact of gender work in programming and results at community level, ORDA should strongly work on organizational transformation from gender perspective.
10 | P a g e
I. Introduction Abidan Development Consulting Group has been commissioned by Food for Hungry Ethiopia
(FHE) to undertake capacity review of Organization for Rehabilitation and Development in
Amhara (ORDA) to assess the progress made in response to the multi-faceted capacity building
support made by FHE. This report is the outcome of a thorough and comprehensive review and
analysis of relevant documents and reflection and thoughts of different experts of ORDA, FHE
and relevant government institutions at regional level.
For conveniences and readability, the report is divided in to ten sections. The first six sections
deal with the introduction, background, and objective of the study, description of the assessment
target groups, methodology and overall capacity building support of FHE. The major findings of
the study are presented in the seventh section of this report. Under this section the findings are
presented in six major sub-sections. Relevance, effectiveness, efficiency, impacts and
sustainability of the capacity supports are treated under section eight. SWOT analysis,
challenges, lesson learnt, conclusion and recommendations are provided in the last four sections
of this report.
II. Background
ORDA was founded in 1984 in response to the prevailing and deep-rooted poverty, which was
aggravated by drought, civil war, and economic mismanagement (SP of ORDA, 2015). Since its
establishment ORDA has executed a number of development and relief programs and projects
and reached the most marginalized areas and people of the region in partnership with
Government and International Non Government Organizations and other development actors.
FHE is one of the development partners of ORDA and they have been in a partnership journey
through implementing different development and relief programs/project in Amhara Regional
State. The presence of ORDA in the region and its government affiliation (good knowledge of
the region and government structure) are the two key factors contributed for FHE to establish
development partnership with ORDA as reported by FHE staffs.
FHE in partnership with ORDA have been supporting Productive Safety Net Program (PSNP) of
the government of Ethiopia in Amhara Region since 2005 by accessing fund from USAID.
11 | P a g e
In 2011 FHE has signed a cooperative agreement with USAID for Development Food Assistant
Program (DFAP) with the main objective of supporting PSNP. Accordingly, FHE facilitated the
implementation of the Development Food Assistance Program (DFAP) in Amhara Region with
ORDA as sub-grantee. The program was implemented in nine Woredas located in three Zones of
the Region namely Lay-Gayint, Simada and Tach Gayint (South Gondar zone), Bugna, Lasta and
Wadla (North Wello Zone), and Dahna, Gazgibla and Sekota (Waghimra zone). Moreover, FHE
and ORDA have been providing food transfers in three additional expansion Woredas. FHE
implemented DFAP directly in three traditional and one expansion Woredas while ORDA as sub
grantee implemented the same program in six traditional and two expansion Woredas.
As a strategic partner of ORDA, FHE has been committed to empower ORDA to independently
partner with and access resources from donor communities without any assistance from external
NGOs. FHE believes that direct engagement with donors will help ORDA to improve project
efficiency, effectiveness and draw crucial lessons from the donor communities. Accordingly
FHE has supported ORDA to bolster its capacity by conducting capacity assessment, which
identifies ORDA’s organizational strengths, weaknesses and map out available opportunities for
further improvements. The assessment enabled ORDA to clearly articulate capacity gaps in the
areas of structures, policies, systems, and processes that help the organization to develop
capacity improvement plan.
Therefore, organizational capacity building support is part of the DFAP program, where FHE has
planned to enhance ORDA’s capacity with a view of enabling ORDA to directly access funding
from USAID. This assessment is conducted to examine ORDA’s current capacity brought about
by the capacity building supports offered by FHE during the implementation period of DFAP
program.
III. Description of the assessment target groups The following target groups have participated in the assessment by furnishing primary and
secondary data for the review:
ORDA staffs representing different departments: These include, Human Resource,
Financial Management, Property and Resources Management, Procurement Management,
12 | P a g e
Business Development Management, and Grant Management departments. The Head of
each department and staffs working in the department who have organizational memory
(at least working in ORDA for the last 3 year) have participated in the Focused Group
discussion organized by the consultant.
ORDA Senior Management team: The senior Management team members of ORDA
are those who are at the top leadership position including the Executive Director, Deputy
and Program Managing Director and Deputy and Resource Managing Director. These
Officials have willingly participated in group interview and have provided valuable
information related to the capacity supports of FHE and its contribution for ORDA’s
capacity enhancement and the gaps observed during the capacity support process.
Government Stakeholders: Representatives of Regional Bureaus that work with ORDA
have also taken part in the capacity review by offering their thoughts regarding the
capacity of ORDA. These participants represent the Bureau of Finance and Development
cooperation and Bureau of Agriculture of the Region.
FHE Head Quarter Staffs: Deputy Chief of party, Program Manager and other staffs
from Commodity Management, and, Finance Department have participated in the process
of capacity review by providing necessary information that ultimately enriches the
findings of the review. .
IV. Objective and Scope of the Review
4.1. Objective of the Review The capacity review is undertaken to measure the status of current ORDA’s capacity and
compare with the set target at the initial stage of the intervention. The main objective of the
assignment is thus to evaluate the progresses made by ORDA as a result of FHE’s multifaceted
supports in the areas of program, finance, human resource and commodity managements, and
monitoring and evaluation. More specifically, the study aimed:
1. To review the progress made in the areas program planning and implementation capacity
of ORDA
13 | P a g e
2. To assess the progresses of ORDA related to commodity and warehouse management in
terms of institutional capacity, logistics, and staff
3. To assess the financial management capacity of ORDA in utilizing USAID grants in its
own.’
4. To investigate improvements made in Monitoring and evaluation of ORDA
5. To review improvements registered on the Human Resource Management (HRM) aspect
of ORDA;
6. To evaluate the capacity level of ORDA in directly accessing USAID grant
7. To review the contributions of FHE capacity building endeavors in bolstering ORDA’s
capacity.
8. To evaluate the capacity building strategy of FHE in terms of relevance, effectiveness,
efficiency, impact and sustainability, and
9. To recommend how ORDA will further strengthen its capacity in the areas of program
design, implementation, monitoring and evaluation, financial management, commodity
management, human resources and accessing USAID grants;
V. Methodology The study adopted a mixed method (both qualitative and quantitative) so as to collect and
analyse data and produce the report. Comparison of the results of this capacity review is made
against the findings of capacity assessment conducted in 2014 to reveal the progress made by
ORDA in building its capacity.
In general, three steps were followed to collect and analyze the quantitative and qualitative
information. These include: desk review (collection of secondary data from documents),
qualitative data collection techniques (i.e. focused group discussion, key informant and direct
observation) and quantitative data collection (i.e. staff survey). Next a brief s presentation of the
techniques employed in the study is in order.
5.1. Desk Review In this very step, the consultant exhaustively reviewed both published and unpublished
documents of FHE, ORDA and government stakeholders in order to generate the required
information. Some of the major sources of secondary data which reviewed before, during and
after the primary data collection include the 2012 and 2014 ORDA capacity assessment report, 14 | P a g e
USAID cost and audit principle documents, ORDA Human Resource Manual, ORDA Financial
Resource Management Manual, ORDA Monitoring and evaluation manuals etc. The data
obtained from secondary sources helped the consultant learn more about the details of the project
and contexts of proposed indicators. These information have also been indispensible inputs in the
design of primary data collection instruments, such as checklists, structured questionnaire and
different data collection formats. Furthermore, the findings of the desk review helped to
substantiate the primary data and produce the report
Qualitative Survey
In the second step, participatory approaches were employed to collect qualitative information
using the most common tools and techniques, including focus group discussions, key informant
interviews, observations/ on the spot checking,
1. Focus Group Discussions: were mainly applied to collect information from ORDA and
FHE’s Staffs. A total of six FGD were undertaken with representatives of Human
Resource Management, Financial and Grant Management, Administrative and logistics
management, procurement management, Program Designing and Action Research
Management and Senior Management staffs of ORDA. One FGD with FHE staff was also
conducted. A total of 44 (8 Female) discussants took part in the participatory FGD.
The FGD was very participatory and most of the discussants were given the chance to
reflect on the capacity support processes, outcomes of the support as well as drawbacks.
For the purpose of guiding the discussion, the consultant has employed pre-designed
checklists prepared for this purpose (the number and position of FGD discussants is
attached in Annex of this report).
2. Key Informant Interview was made with government stakeholders who are working
with ORDA including Amhara Region Agriculture Bureau, Food Security Office and
Finance and Economic Cooperation Bureau. The interview helped the consultant to
analyze and see the trust that government stakeholders have on the capacity of ORDA in
discharging its responsibilities and managing donors’ fund.
3. Observation and on Spot Checking was also a technique utilized by the consultant to
check the availability of manuals, procedures, policies, how they are accessible to the
15 | P a g e
staffs, how they are documented, and how the cheques and cash at hand are being
handled and whether caisson techniques are employed in the warehouse management.
5.2. Quantitative/questionnaire based staff survey
In the third stage, purposive sampling methods were employed to include all departments who
received the supports in the staff survey. Six respondents from each target department were
selected purposively; since the selected staffs have sufficient knowledge of FHE’s support and
its role to ORDA’s capacity development, to fill self- administer structured questionnaire. In
general 27 (5 female) respondents have participated in staff survey. Prior to filling the
questionnaire, a brief orientation as to how to fill the questionnaire, on the purpose of the staff
survey and how they should administer it was given.
The consultant then fed the responses into computer, refined and analysed (weighed) the
response using Excel and utilized the result to substantiate the findings of the qualitative study
and desk review. More specifically, the quantitative result is used to compare with the findings
of the capacity assessment undertaken in the year 2014.
5.3. Limitations of the Review In order to adequately address the required level of quality of the assessment and achieve the
intended objectives, various core competency areas of the organization were touched up on.
Moreover different approaches and data collection tools were applied. However, the consultants
were unable to secure the views of ORDA field level staffs due to inability to travel there as
there were great security concerns in the project area. ORDA could not also be able to mobilize
project staffs to head office at Bahir Dar to fill this gap. However, there were staffs in the FGD
who had been working in the field office and recently transferred to head office and efforts were
made during FGD to fill this gaps by raising questions that address issues at field offices level.
The consultants believed that FGD participates who had been working at project office level
have still the real feelings of their former positions and have the required information to fill this
gaps.
The target groups of ORDA (the communities) are the right holders who deserve to receive
quality program delivery. As the end users of the services provided by ORDA, their views on
16 | P a g e
ORDA’s capacity to timely and quality delivery of services is very crucial. However, this
assessment has not been able to document their views in the due process of the study.
VI. FHE’s Overall Capacity Building Interventions Despite more than 15 years of experiences in implementing different USAID funded projects as
sub grantee recipients; ORDA has been unable to directly access funds from USAID. Although
ORDA has elapsed many years partnering with international Non Governmental Organizations,
these partners have mainly focused capacity building efforts on program implementation rather
than building support systems.
In order to buttress up ORDA with strong and effective support system, FHE in consultation with
USAID, revised DFAP budget and covered the cost of expatriate staff seconded to ORDA head
office, with experience and expertise in systems management and deep acquaintance with
USAID rules and regulations. The expatriate closely worked with ORDA senior management to
bolster ORDA’s support systems. The expatriate was purported mainly to focus on
strengthening the support systems of ORDA to work on compliance issues and enable ORDA to
directly access to USAID funding.
Furthermore, the expatriate focused in assisting ORDA’s team in proposal writing, relationship
building with USAID, and other activities directly related to winning a sole award with USAID.
As part of the capacity building endeavors, a comprehensive capacity assessment of ORDA that
focused on analysis of key departments, management and leadership has been made. Based on
the findings of the capacity assessment, improvement plan was developed and assisted ORDA to
implement the improvement plan.
In general, during the current program period FHE has conducted the following major activities,
among others, to build the capacity of ORDA.
Commissioned a consultant to conduct an initial Capacity Gap Assessment (CGA)
Employed an expatriate who was seconded to ORDA and based at Bahir Dar where the
Headquarter is located. The expatriate has rich experience and expertise in systems
management and familiar with USAID rules and regulations. He was working with
ORDA senior management to strengthen ORDA’s support systems;
17 | P a g e
Facilitated trainings in Ethiopia and abroad on USAID rules and regulations, leadership,
project management, financial management, proposal writing, project closeout, project
cycle management, climate change, Environmental and Social Monitoring Framework
(ESMF), improved agricultural practices, health and nutrition, commodity and warehouse
management, etc.;
Built the capacity of the sub-grantee in managing food resources from the source through
arranging exposure visit to Djibouti port and organize various trainings;
Supported the execution of organizational level climate survey to enable ORDA to
identify its technical and managerial gaps as well as strengths and set its future strategic
direction based on the findings;
Facilitated a forum for ORDA leadership to be introduced with USAID Ethiopian
mission office key staffs and officials;
Arrange different exposure visits to head office and project staff within the country.
VII. Assessment Findings Narration
7.1 Human Resource Management Personnel policy: ORDA has recently (year 2015) revised Human Resource Management
Policy, which ensures fair and transparent recruitment system and procedures. According to the
explanation of the staffs of HR department, all staffs in the department have well internalized the
new manual and the revised HR policy. ORDA has instituted a system revising its HR policy
manual every two year and this enabled it to regularly update its policy documents taking into
account the dynamism of working environment conditions and donor requirements. The
quantitative result (3.6/5) also indicated that donor specific (e.g. USAID) human resource
regulations are well incorporated in to ORDA’s HR policy.
Recruitments: FHE support in enabling ORDA to have written recruitment guidelines is found
to be successful. Now, in ORDA, written recruitment guideline where recruitment procedures are
clearly articulated is properly in place. Competency based recruitment process which includes
experience and academic qualification has been used by advertising on public media to allow
free and faire competition of candidates. As per the discussion with HR section a phone call
reminder for each short listed applicant is made to further ensure the transparency of
18 | P a g e
recruitments. The quantitative result (5/5) implied that the recruitment is undertaken as per the
set policies and rules. Moreover, the written guideline of human resource on recruitment is well
understood by all the staffs. Radical improvement is made by giving a written Job Description
(JD) to each staff of ORDA confirmed by the quantitative result, which is (5/5). This was one
area of capacity gaps observed during the baseline with the quantitative result of (2/5). This is a
further indication that ORDA has properly implemented the capacity building improvement plan
during the last five years.
Volunteers and internship management: According to the discussion held with ORDA HR
manager, the organization has been hosting around 300 internships annually that last three to
four months from different Universities and Vocational Skill Training Colleges. In order to
effectively manage the internship and get the best out of it ORDA has drafted internship
management guideline, which is in the process for approval by the management. This is indeed,
one area of improvement from the baseline as a result of the capacity building support provided
by FHE. The performance of ORDA in this area used to be very poor as indicated by the baseline
result which was 2/5 but now it is improved to (3/5) which is above average.
Staff Salary and benefits: Although recent improvements have been made, both the management
and FGD participants indicated that the salary and benefit package of ORDA is remains low
compared to other similar organizations. The key informant interview with government
stakeholders also mentioned that the meager salary and benefit package of ORDA is cause for
high staff turnover. Thus, the management should consider revision of the salary and benefit
package in line with the financial capacity of ORDA. The comment of FHE staffs is also
consistent with the government stakeholders and they stated that ORDA cannot sustain keeping
its current strengthen of delivering the services unless it revise staff salary and benefit package.
Moreover, FHE’s staffs complained that the quality of ORDA’s services has been compromised
due to high staff turnover because of to low benefit package.
Staffing Level: It is found out that ORDA has well documented the positions needed and staffing
status. The Organization also regularly keeps data on the vacancy available and the extent of
staff turnover. It requires from 15 to 20 days filling in the open vacant place. Though the low
19 | P a g e
salary scale is still a threat for high staff turnover, ORDA has tried to put in place a mechanism
to retain staffs and this include provision of educational opportunities, hardship allowance for
those working in remote areas.
Performance Appraisal: ORDA has been using Balanced Score Card (BSC) to evaluate
employee’s performance of the assigned duties, achievement of goals and fulfillment of
responsibilities every six months. The performance appraisal process is participatory in that it is
held in joint discussion between the staff to be reviewed and the reviewer. This is one of the
areas that ORDA has shown improvement during the capacity building support period. On spot
review of sample employee personal file disclosed that performance appraisal has been
conducted for all employees every six months. FGD participants also affirmed that the
understanding of staffs on Balanced Score Card (BSC) plan development and evaluation is
enhanced through different capacity building trainings. However, the FGD participants voiced
that the scoring system is rendered a mere formality, as it is not strictly applied to really evaluate
the performance of the staffs. As reflected by the FGD discussants, in general HR department is
not using BSC to measure staff performance but, the quantitative result indicated that slight
improvement has been made in performance improvement plan (3.4/5) which was (3.00 /5) in the
baseline.
ORDA has developed employee rewarding guideline to motivate best performing employees
through recognition, incentives and opportunities for career development. The quantitative
survey result which is given (3.6/5) also complements the qualitative results.
Both the primary and secondary data review indicated that useful supports provided by the FHE
related to human resource development enhances ORDA’s capacity to comply with donor
specific (USAID) human resource regulations. The quantitative result (3.8/5) also confirms this
result. Hence, staff familiarity with the USAID funding and partnership compliance is enhanced
and the quantitative result which is (4/5) confirms that the human resource management team has
the required knowledge and familiarity with USAID grant management requirement.
The overall indication of the focused group discussion and quantitative results of the assessment
with human resource management implied that the section has clearly worked on the capacity
20 | P a g e
gap improvement plan and as a result positive changes have been made on the major gaps
identified in 2012 and 2014.
In general, pursuant to the discussion with the HR section and review of documents, during the
last five years the Human Resources Management of ORDA has shown major improvement in
the areas of:
Organizational structure which, is compatible with ORDA’s current development and
capacity has been developed and job descriptions are prepared for all positions.
Important policy documents that harmonize USAID requirements such as anti-corruption
policy, child protection policy etc. are developed and in the process internalization by all
the staffs at all level;
Employee induction manual developed;
Staff familiarity with the USAID funding and partnership compliance enhanced;
Most of the essential codes of conduct that were included in the HR manual to address
employee’s behavioral and professional conduct are separately developed as policy
documents. This included anti-harassments work place policy, anti-bullying procedures;
conflict of interest in resources and procurement; Whistleblowing policy, child protection
policy etc. These inter alia are some of the policy documents that USAID requires from
Organizations that apply for funding.
Guideline for internship management drafted and in the process to be approved
Staff exit interview analysis made regularly and present to the management for decisions.
The analysis of the exit interviews indicated that less salary is the primary factor for
employees’ resignation. Based on this analysis and recommendation of capacity
assessment reports at different time, ORDA management has made salary and benefit
package assessment and revised some salary and benefit package for the positions that
high staff turnover was experienced. However, the FGD participant and the senior
management of ORDA indicated that the salary and benefit package of ORDA is still not
competitive compared to organizations in similar position and current market.
21 | P a g e
Based on the overall discussion on Human Resource Management competency areas, the average
rating continuum given by FGD participants for the overall capacity of HR management is 3.8/4
which is close to the higher continuum that is 4 indicating that ORDA has strong and effective
human resource management in tune with donor requirements.
7.2. Financial and Grant Management
Financial Policy, Systems and Procedures: ORDA has adopted a financial resource policy
manual that ensures ORDA’s accountability and transparency in resource management to donors,
the communities it serves, the government and its internal governance. The manual is a clear
guide and procedure that ensures key financial management procedures including segregation of
duties, authorization limits among key management of the organization, payment administration,
budget control, financial transactions recording, financial documentation, etc. Since the financial
policy of ORDA is stricter than any of ORDA’s Donor corresponding policy, it is safe to say that
the policy accommodates the donors’ policies and regulations including USAID policies and
procedures.
The Focused Group discussion with the Finance Management Team indicated that employees in
the finance section have good grasp of the financial manual of ORDA and the quantitative result
(5/5) confirms the qualitative statement. The baseline quantitative result was (2/5) and this shows
major improvements in the area of staff knowledge and skills on complying donor specific terms
and condition of agreements and grant management requirements.
Furthermore, the participatory discussion with the finance team pointed out that the same has
good knowledge of the USAID financial regulation requirements i.e. definitions of reasonable,
allocable and allowable/ unallowable expenses, VAT tracking and reimbursement procedures
etc. This recent progress of the finance section in complying with the USAID VAT requirement
is practically proven. The FGD participants in finance team disclosed that ORDA has tracked
VAT and got reimbursed around 900 thousand birr from VAT. One of the recommendations that
the Capacity advisor has provided to finance department of ORDA was related to the gap in
VAT clearance. It is in response to this recommendation that the department has shown a lot of
22 | P a g e
progress. This is one area of indication that ORDA has internalized the USAID financial
management requirements as the VAT clearing issues had been a challenge for a long time.
The quantitative result substantiates the findings of the qualitative statement that the finance
department is familiar with USAID financial/grants management procedure with the average
point of (4.5/5) and the baseline result was (2.8/5). Trainings given at different times for finance
staffs and management have enabled ORDA to internalize the USAID financial regulations and
comply with the requirements. However, discussion with the finance team disclosed that despite
many efforts to aware projects staffs on USAID financial procedures and requirements during
project area visit, the finance staffs in project offices still have little understanding and
sporadically apply the financial procedures of USAID in particular and donor agencies in
general. Though training has been provided by FHE on USAID financial reporting compliance
system, ORDA has not worked effectively in cascading the knowledge and skill to the project
level. There is no formal knowledge cascading procedures, but the department has been using
other option like orienting the finance staffs of the project when they come to ORDA HQ for
delivery of financial report. Comparison of quantitative result against the baseline indicated a
slight change or improvements, which were only (2.0/5) and grow to an average result of (2.5/5).
One of the responsibilities of Senior Management of ORDA is to regularly meet with relevant
program and finance staff to review budget status (oversee both the approved and expended
budget). The FGD discussants have confirmed that the senior management regularly reviews the
budget status. The quantitative result supports this with the average point of (4.5/5) this is
significant improvement from the baseline of (3.2/5).
In order to sustain staffs understanding on ORDA’s financial policy, systems and procedures and
donor specific requirements, it is pointed out that the department regularly conduct review
meeting to assess the progress and compliance of financial rules and regulations. The section
also provides orientation for new staffs on the financial policy, systems and procedures and
USAID financial procedures regularly. This is one area of betterment compared to the baseline
capacity gap which ensures that ORDA has implemented systems for the transfer skills from
trained staffs, yet the gaps in transferring skills at project office level remains unchanged.
23 | P a g e
Financial Documentations: ORDA has a well-established financial documentation management
system where responsibilities are assigned for specific staffs with restricted access. The
documentation is organized in a way that can easily be used and trace progress (revenues and
investment by sector). This is further supported by the quantitative result, which is (4.83/5).
The financial document is collected every quarter from program office and centrally controlled at
Head Office.
Internal control and Audits: ORDA has internal audit and inspection department responsible for
auditing the proper utilization of resources of the organization. There is an audit policy and
system instituted to ensure financial, commodity resources and fixed assets are properly utilized
and managed/maintained. The written policies set out internal controlling system and procedures
for internal audit that clearly stipulates the cash handling and carrying systems, monitoring and
controlling of financial income and investment systems. The quantitative result strongly supports
the qualitative statement with the average result of (5/5) and the baseline result was (2/5). The
department regularly conduct cash utilization audit both at head office and program office level
and submit report for the management for informed decision. The department also undertakes
surprising visits mainly to see how resources more specifically financial resources are being
managed, and undertake counting.
Cash audit is traditionally used by businesses to determine if established administrative and
financial rules and regulations are being followed correctly. However organizations have began
using “quality audits” to measure how well internal and external demands were being met. This
type of audit establish whether internal arrangements are appropriate and attuned to each other,
whether the arrangements and their related rules are being followed, and how to improve and
innovate in this area.
Quality audits evaluate the organization’s written policies, documents and handbooks and
determine if the organization is actually applying these – and if so how well and with what
results. They reveal not only whether the job is being done in the right way, but opportunities to
improve and innovate. For this reason the audit collects and analyzes the organization’s capacity
to comply with funding requirements and quality delivery and hence the audit report contains
recommendations related to potential improvement areas and how to implement them. Relevant
and responsible actors could then use the report to produce an action plan. 24 | P a g e
In connection to quality audit, the role of the Audit and inspection section of ORDA is
transforming from purely cash audit to performance audit in response to the recommendations of
the capacity advisor, to ensure that the allocated budget is properly utilized for the intended
objectives and reached the right beneficiaries. Accordingly, the section reviewed its performance
and developed proposal to expand its service to performance audit. However, the Audit and
Inspection section of ORDA has missed opportunity to internally audit ORDA’s compliance with
the USAID grant management requirements in particular and donor agencies in general. The
FGD result also indicated that the audit and inspection section has not yet planned to audit
ORDA’s compliance to donor’s requirements and the section itself is not well aware of the
USAID grant management compliance issues.
ORDA has been audited by external auditors for all USAID projects that it has been
implementing as a sub grantee. The audit findings indicated that ORDA has complied with the
USAID grand management requirements.
Budget Planning: A separate section responsible for budget planning under the finance section
is established. The section carries out participatory budget planning where both the finance and
program staffs participate. Radical improvements achieved in collaboration between program
and finance staffs in budget planning and oversee of budget utilizations. The baseline
quantitative result (3.6/5) improved to (4.67/5) indicating that the program and finance staffs
working together to ensure policies and procedures are followed and expenditures are coded and
reported accurately, setting and controlling the project budget to ensure all costs are included and
money are spent as per the plan. This is one area of competency to ensure that proper budget
control and reduce discrepancy between budget planning and utilization.
Donor based, project based and organizational based budget planning system are in place and
Organizational based budget planning is undertaken on annual basis. A budget holder in charge
of managing each budget is instituted. The budget holder (program staff) received budget
transfer request from program officer and review the request against the budget plan and submit
to the finance section to get the budget released to program officers.
25 | P a g e
The finance section along with the internal audit and budget holder control the budget utilization
through disbursement process. Financial documents from the field office are reviewed by the
internal audit and budget holder before a record in the finance section is made. In this way the
system ensures that budgets are controlled by three sections to ensure its effectiveness.
Furthermore, the quantitative result confirmed that the involvement of the senior managers
administering and monitor the budgets for their respective departments or projects changed
positively from a score of (3/5) to (4.67).
A regular meeting with senior management and relevant program staff is held to review budget
status; oversee both the approved, expenditure, revenue. Budget variance between the approved
and expended is fully explained pursuant to the required standards by the program department.
According to reflection of the FGD discussant, for ORDA up to 10% budget variance is
tolerable. The project officer uses the finance report to cross-check activities to track timely
correction on the budget utilization. As per the quantitative result, there is also improvement in
the involvement of the Executive Director of ORDA in ensuring that the program activities are in
line with the budget and deliverables, which increase from (2.6/5) to (4.5/5).
Financial Reporting: Timely and quality delivery of financial report which, ensures relevance,
accuracy and consistency are some of the competency areas of organizations. With the aid of
different capacity building plan and intervention, ORDA has improved its capacity complying
with the reporting standards of the donors. The quantitative baseline data (3.2/5) showed growth
to (4.5/5) and indicated that the finance staffs prepare quality reports using the standard
procedures of donors and submit within the timeframe. The discussion with ORDA finance team
also pointed out that ORDA has improved its capacity of timely delivering quality report and
donor complains on financial reports are reduced. Delay in financial due date was one major
capacity problem of ORDA and the result indicates that ORDA has made strong efforts to
improve the situation. Since quality reporting and meeting the deadline or timely submission is
the requirements of most funding partners, improvement in this area will enable ORDA to
comply with the funding requirements of donor organizations. Despite the figures indicated that
ORDA has improved its capacity in developing standard financial report, the field office finance
staffs are well equipped to produce financial reports using the USAID reporting formats at
project level. The system requires project finance staffs only to deliver financial invoices and
ledger to Head Office to be recorded in the finance software. In this regard, the department has 26 | P a g e
not shown any improvement since the baseline report even though the improvement plan
developed recommends that ORDA should take action aimed at scaling up the capacity of field
office staffs to develop financial reports.
As per the comment of FHE Operations Director, there is significant improvement in preparation
of quality financial report and its timely delivery. However, further improvement needs to be
made both on the quality and timely delivery of reports. High staff turnover, especially those
who have got training, identified to be the critical challenge in delivering the quality and timely
financial report. The financial report is done using Peachtree and submitted to HQ level for
compilation as the financial report consolidates at HQ level. The financial report submitted is to
the HQ both electronically and in hard copy, yet there is some delays in submitting the financial
report in hard copies and this caused a problem for FHE staff to crosscheck the electronic copy
of the financial report with that of Hard Copy.
Regarding accounting software that support the financial systems, ORDA has been using
Peachtree and in order to adequately support the system ORDA management has planned to
replace the existing accounting software with the latest recommended accounting software that
accommodate the systems. Accordingly this assessment team was informed by ORDA’s
management that it has requested FHE cover the cost for the purchase of upgraded accounting
software. However, the request was denied albeit ORDA management thought that the requested
amount was small. The discussion with FHE Operation Management indicated that though FHE
was positive to support ORDA with latest financial accounting software since ORDA has several
donors and the accounting software works for all donors, FHE insists that other ORDA’s donor
should share the costs.
Improvement is made on the feedback mechanisms of financial reporting and these mechanisms
are properly utilized and quantitative result given (4.17/5) complements the qualitative
statements. Major changes have been scored against the baseline, which was (2.7/5) indicated it
was less often project officers use the finance report to crosscheck with activities and to take
timely corrections on the implementation or budget utilization rate.
27 | P a g e
Financial sustainability and cost sharing: ORDA has diversified funding basis and the funding
base expand over the past five years and new funding partners are included in the funding list of
ORDA like Catholic Relief Services, The Development Fund Norway etc. The quantitative result
(4.67/5) strongly supports the qualitative statement. In order to enhance the financial resource
capacity of ORDA, resource mobilization strategies are developed and communicated with
staffs. Despite the existence of opportunities which enables ORDA to generate its own income
through selling of different services like garage with the exception of recently made efforts to get
license for income generating activities from the Charities and Societies Agency has not tapped
this potential areas. The quantitative result in this regard is (2.17/5) which is below average also
indicates that ORDA has not strongly worked on this area.
As one of the USAID requirements, organizations are encouraged to provide details on cost
sharing or matching contributions to meeting the objectives of proposed program activities.
ORDA was not made responsible in showing cost shared to the program in the DFAP where the
cost sharing part is covered by FHE. However, the participatory discussion with ORDA team
discovered that ORDA has been mobilizing the community and local government to contribute
for the development projects has been implementing. Thus, in the development intervention of
ORDA, the community has been contributing labor, local material, etc. while the government has
been contributing or matching development fund up to 25% of the budget for water and
irrigation related programs. ORDA has also been using its resources (both human and physical),
for the implementation of different project which is not actually allocated for that particular
projects which can be considered as ORDA’s cost sharing. However, this assessment team
discovered that ORDA has no system that shows how cost – sharing procedure is documented.
That is to say there is no system in place that guides how cost share is tracked, monitored and
reported to donors. The cost sharing is not also recorded in the accounting systems and no
system is set out to ensure compliance with cost share. Neither internal nor external audit were
done with regard to cost share especially on community contributions. There is also no staff
training on cost-sharing procedures.
Grant Management: The new organizational restructuring of ORDA put the grant management
unit under the finance section which used to be under the control of program designing and
business development unit. Following this, the finance department has recently been named
Finance and Grant Management Department. The grant management unit is staffed with two 28 | P a g e
experts for the overall responsibilities of ORDA’s compliance with donor terms and conditions
of agreement. For the last 15 years, ORDA has been managing different USAID funded projects
as a sub grantee with various international partner organizations. The exposure of working on
USAID funded projects and programs as sub-grantee helped ORDA’s staffs at different level to
be familiar with the USAID grant management and procedures as confirmed by ORDA’s staff
and senior management. However; despite long years of experience and exposure with the grant
management requirements of USAID, still gaps being observed in the grant management
responsibility of ORDA. The role and responsibilities of the grant management section sis
limited to facilitating project agreements and reminding project staffs as the project agreement is
approaching phase out stage to timely complete project activities.
As one area of their responsibilities the grant management officers needs to internalize the
USAID grants management guideline but it is confirmed that they have hardly internalized it. It
is also observed that the grant officers have limited understanding of the cost principles and the
USAID grant management procedures. They have no copies of Cost principles (A-122) with the
revised circular CFR 230 audit principles (A-133), etc.
The Focused Group Discussion with the Internal Audit and Grant management section indicated
that there is no practice that both sections coordinated to assess or audit ORDA’s compliance to
USAID and other funding agencies grant management requirements.
The role and responsibilities among the two grant management officer is not also clear and both
staff assumed the same position that is entitled “Grant Management Officer”. This is one of the
areas that no improvements made since last capacity improvement plan. Therefore, ORDA needs
to further strengthening its grant management section and revise the role and responsibilities of
the section to ensure that the section effectively work on ensuring donor’s grant management
compliances are adequately addressed.
The qualitative and quantitative data pointed out that ORDA has made remarkable improvements
in most competency areas of financial management which enabled it to comply with donor
compliances of grant management. A range of capacity building support provided by FHE and
other funding partners to enhance ORDA’s financial management capacity to comply with 29 | P a g e
contract procedure of USAID and FGD discussants indicated that the training is indispensible to
carry out their work and this is further complemented by the quantitative results (4.33/5).
As a result of different capacity building supports, the participatory discussion with the finance
team ascertained that ORDA has in place a full-flagged system that will help it to comply with
USAID grant and access USAID grant in the coming years. The quantitative result (4.5/5) is also
complement the qualitative statement in this regard.
Observation and on the spot checking during the capacity assessment further discovered that
ORDA has made efforts in filling the capacity gap identified at different times. All the required
policy documents are prepared and internalized by staffs. Employees of finance department’s
understanding on the financial systems of the organization and donor specific requirements have
shown improvements. The overall average quantitative score of financial management
competency areas was (3.1/5) but now increased to (4.65/5) also confirms improvement in
financial system and employees’ understanding. Furthermore, the qualitative rating continuum
given by finance management team focused group participants for the overall financial
management competency areas of ORDA is (3.6/4) which indicates that all the required
financial policies, systems and procedures are in place and internalized by employees, regularly
deliver accurate and complete financial reports to stakeholder (donors, senior management,
board members), appropriate financial documentation systems are consistently compiled with its
statutory and donor audit requirements in a timely manner.
7.3. Property and Resources Management
Operational policy and systems: Written operational procedures are set out for property and
resource management including logistic, fixed assets and commodity. The quantitative result
(4.4/5) strongly supports the reflection of FGD discussants that there are different written
operational procedures and they are being used for effective commodity and logistics
management. These policies/procedures address donor’s specific rules and regulations (e.g.
USAID) and the quantitative result also supports this (3.6/5). The participatory discussion with
the property and resource management team indicated that operational policies and procedures
are presented in a way that is easy for non- financial staff to understand and comply with. The
section holds an orientation session during the recruitment of new staffs. The quantitative result
(4.2/5) also supports the qualitative statement. 30 | P a g e
The organizational operational policy and systems are well understood by staffs.Moreover, the
staffs familiar with USAID funding requirements of vehicle utilization and maintenance;
marketing and branding, prior approvals for international travel, compliance with Fly America
Act etc. The quantitative result (4.4/5) is consistent with the qualitative statement.
Commodity Management: The assessment team could not be able to physically visit the
commodity store of ORDA but the participatory discussion with property and resource
management team disclosed that ORDA has undertaken commodity management from
Distribution Center to beneficiaries. The management of commodity from port (Djibouti seaport)
to warehouse (distribution center) is, however, managed by the international partner
organization. ORDA has its own commodity management manual developed by hired consultant
and this manual fully incorporates the USAID commodity management requirements.
The country commodity tracking system is already in place. As reported by the discussants 39
Woreda have instituted commodity management system. ORDA has a total of 200 distribution
centers and they have strong capacity in commodity management.
ORDA staffs have got TOT training on commodity management and the trained staffs are
responsible to providing training for new staffs’ and refreshment training for existing ones. As
indicated by the focused group discussion participants, the training provided at different time by
FHE on commodity management helped ORDA improve its store and commodity management.
It is confirmed that maintenance for some warehouse made and adequately staffed to ensure
segregation of duties and check and balance systems. It is also shown that the commodity
distribution was made by the kebele administration but as per the comment of ORDA recruited
commodity distribution officer.
As per the reflection of ORDA’s staffs and also confirmed by FHE staffs, ORDA is strong in
managing the commodity at local level (i.e. from the distribution center to the beneficiaries) due
to the continuous supports provided by FHE and ORDA’s long term experience in the area. But
ORDA do not yet participated in managing commodities from the port to the distribution center.
An experience sharing program was organized to acquaint ORDA with the experience of
international bid systems. Accordingly staffs visited Djibouti seaport to learn the system of
commodity management from seaport to the main warehouses. However despite the importance
31 | P a g e
of the experience sharing visit ORDA has not been given opportunities during the project period
to manage the community directly from the seaport to the warehouse as this is a missed
opportunity in the project agreement signed between ORDA and FHE. The discussants clearly
pointed that this is indeed a missed opportunity for ORDA. FHE staffs have also discussed
these issues which are referred by the ORDA’s staff as missed opportunities. Pursuant to this
FHE staffs argued that, the program had been managed and implemented as per the agreement
made between FHE and ORDA.The agreement didn’t oblige FHE to enable ORDA to
independently handle commodity management from the seaport to the distribution centers.
However, though it was not in the agreement, FHE has organized two experience sharing visits
for its commodity management staffs to Djibouti to draw lessons as to how to manage
commodity from the seaport to the distribution center. In addition, FHE has facilitated
experience sharing for ORDA with REST to lean the factors that enabled REST to directly
access fund from USAID, how they are handling DFAP including managing commodities from
the seaport to distribution center, though the outcome of the experience sharing was not came up
with the expected areas of experience.
Considering the bulk of the commodities and to fully comply with USAID and other donor
requirements, the management of ORDA has decided to re-structure the commodity management
separately from the property and resource management departments. The re-structure is already
approved by the board and ORDA is empowering the department to fully and properly function.
A new system for commodity management that is Country Commodity Tracking System (CCTS)
has also been introduced and is being functional. This further enhances ORDA’s capacity to
comply with donor requirements.
The quantitative results in all competency area of commodity management indicated
improvements. The major areas which have shown improvements in light of the USAID
requirements are the commodity staffs that know and properly use the warehouse inspection and
commodity accountability checklists. This statement is supported by the quantitative result (5/5)
which was (3.6/5) during the baseline. Furthermore the quantitative result (4.7/5) which was
(2.66/5) indicated that the warehouse system has proper filing and documentation to trace/track
records and inform the management for decision making. Records that include (monthly
32 | P a g e
commodity receipt, monthly dispatching, other warehouse records, monthly distribution records,
etc) are maintained.
Fixed asset management: Written manual for property and transport management is under
revision and according the explanation of the Department Head the revision may take SIX
months to be finalized and approved by the management. It is highlighted that the revision of the
manual is an opportunity to incorporate donor specific requirements.
The Fixed Asset Policy of the organization adequately met the need of the organization
including fixed asset registration, inventory marking, depreciation rates, transfer/borrowing of
equipments etc. The quantitative result (4/5) also supports the qualitative statement in this
regard. The quantitative result (4.2/5) showed that ORDA is using fixed asset registrar and this
procedures is helping ORDA to effectively control assets. As per the explanation put forward by
FGD discussants, ORDA has managed to organize inventory committee and asset inventory is
being done on annual basis and the process is being supervised at deputy director level implying
the strong emphasis that ORDA has given for asset management and control. However, there
exist practical lacunae related to documentation of depreciation rate and calculation.
Staff has been oriented on the revised USAID requirement and in order to comply with different
donor requirements ORDA applies the principle of more restricted procedures and accordingly
for fixed asset ORDA applies items that worth more than 1000 birr are registered and treated as
fixed assets where as the USAID requirements is above $ 5000 highlighting that ORDA’s asset
management procedures fully accommodate USAID procedures. The quantitative result (3.8/5)
confirmed this as donor specific fixed asset regulation procedures incorporated into ORDA’s
fixed asset management policy.
Improvements against the baseline in this regard is that the asset disposal procedures of Charities
and Societies Agency (ChSA) and the donor are internalized by staff and hence a committee for
disposal is formed and list of items for disposal are identified and application is submitted to the
ChSA agency. The quantitative result complements the qualitative statement with the average
point of (4.2/5). Improvement is also made on the awareness of management staff on USAID
grants policy which prohibits staffs/leaders from accepting any gift that influences the policy and
33 | P a g e
specific code of conduct to guide purchasers. The quantitative result (4.5/5) against the baseline
(1.6/5), support the improvements in this area.
The participatory discussion with property and resource management team pin pointed that the
section has filled several gaps in the last five years in response to the capacity assessment gap
improvement plan made at different time. Accordingly, areas that have improved are:
Store management was poor and a “Kazan” training was given for store management staffs and improvements made in store management.
Inventory report was not comprehensive and strict. Training for staff provided and
accordingly the system improved. Following this, inventory of phased out projects
planned and conducted at least two month before close out. This improvement is realized
since the implementation of improvement plan prepared following capacity assessment in
year 2014. The quantitative result (4.8/5) indicated that ORDA manages the close out of
projects financially, complete all required deliverables and clarify plans for any
equipment or other inventory purchased. The baseline quantitative result was (1.66/5).
As part of computerizing fixed asset management system, GPS is installed on 40 vehicles
so as to properly monitor their movements. Inventory of fixed assets is also carried out by
the computer using Excel. But, the department is planning to hire consultant to adopt
highly systematized software for effective inventory of fixed asset.
Logistic Management: Written manual for travel policy and procedures are in place. For
instance, systems are established for field travel where each department develop Terms of
Reference (TOR) indicating the purpose of travel, number of staff traveling, where to travel,
duration, estimated budget etc and submit to finance and logistic section at least two weeks
before the date of travel. Extension TOR should be prepared and submitted if there is need to
extend duration of the field work beyond the requested number of days. This ensures effective
and efficient resources utilization of the organization. Advance settlement reconciled within two
days of return back from field.
Log sheet is applied for all vehicles of the organization and fuel standardization limit is also set.
The logistic section makes analysis of the log sheet every three months and presents the findings
for management. The logistic and administration department uses the result of the analysis as
34 | P a g e
criteria to measure the performance of drivers, this in turn enhance the efficiency of resource
utilization.
Consistent with USAID requirements prior approval is need along with travel plan within 45
days before the travel date in order to get prior approval from USAID. However; with regard to
international travel the participatory discussion with ORDA staffs confided that only few staffs
(senior management team and Property and transport manager) understood how to comply with
requirements of planning for the international travels and accept notification.
The quantitative result (4.6/5) indicated that ORDA has currently capacity to comply with
USAID logistic and commodity management and the qualitative rating continuum which is
(3.4/4) also confirms that the organization has put in place policies and procedures for property
and resource management and internalized by employees how to apply the procedures.
7.4. Procurement Management
Transparent and accountable procurement system is one areas of compentcy for strong and
effective organization. With regard to this ORDA has procurement policy that adequately
supports the needs of the organization (procurement responsibilities, procurement planning,
competition, exceptions, award, delivery and inspection, documentation, inventory, etc). The
average quantitative result (4.83/5) confirmed that procurement policy exists and internalized by
employee who applies the policy manual.
The purchase system indicates that annual purchase plan is developed based on the purchase
request from each department and approved by supervisors. The purchase process used to be
centrally managed at head office level. However, considering the delay in the implementation of
project activities which need material purchase, the management has decentralized the purchase
system and accordingly, program offices are mandated to effect purchase of up to Birr
200,000.00. In addition to this, ORDA delegate program offices to effect purchase depending on
compelling conditions. The centralized procurement process was one area of reported challenge
in different capacity assessment report of ORDA. However, the participatory discussion with the
procurement management team indicated that the decentralization procurement system has
35 | P a g e
improved the timely delivery of the organization though it requires close follow up and technical
support for program officers.
To ensure the transparency and accountability of procurement systems, ORDA has issued a Code
of Conduct to be applied to the staff engaged in the procurement of goods and services. This
Code of Conduct is indispensible to effectively manage the procurement process. This is one
area of improvement compared to the baseline qualitative statement charging ORDA for lacking
code of conduct for procurement process that ensures accountable system of procurement.
An average result of (4.2/5) quantitative assessment supported the qualitative statement implying
that FHE has provided capacity building supports to ORDA on USAID commodity management
and the support is adequate and relevant. Furthermore, it is indicated that staffs got training on
USAID procurement compliance procedure and the training helped them to be familiar with
USAID procurement compliance procedures. The quantitative result (3.5/5) confirmed that all
the purchase manager, senior management, project staffs and purchasers have full understanding
about the prohibited items to purchase using the USAID fund. But still the quantitative result
suggests that ORDA need to exert more efforts in the procurement management in order to
enhance staff knowledge and fully comply with the USAID requirements.
A review of the procurement manual of ORDA shows that the manual takes into consideration
the procurement policy and procedures of USAID. This statement is supported by an average
quantitative result of (3.33/5). With regard to international purchase, the participatory discussion
with the procurement management team disclosed that ORDA has developed the capacity to
manage international purchases and this is further confirmed from the fact that ORDA has start
opened bank account for LC and already started the practice as it is currently on international bid
process to purchase solar house from the international market.
7.5. Program Management Donor compliance: It is confirmed that all donor agreements and the modifications made thereto
are readily available. The grant management section which used to be under the program section
was responsible to follow and document donor agreements and any modification made to donor
agreements. The program section was also well aware of the applicable USAID requirements;
these inter alia include submission of work plan, marketing and branding plan, environmental
36 | P a g e
compliance plans, semi-annual and annual reports, inventory and VAT report etc. An average
quantitative result (3.8/5) is fair enough to support the qualitative statements. However, with
regard to program staffs understanding and aligning with the USAID grant standards and cost
principles/ allowable and non allowable/ costs and properly documenting them, the quantitative
results indicated that there is slight decline from the baseline. The baseline result (3.07/5) and the
assessment result is (3/5). As per the voice of the FGD discussants of the program unit, there is
some problems to fully comply with the donor requirement due to the bulkiness of the activities
and programs and high staff turnover.
The external audit related to non- compliances with donor regulation indicated that ORDA has
fulfilled the major requirements. However, the internal audit and inspection section though
mandated to audit the non- compliance with funding partner’s issues there is so far no internal
audit related to non – compliance. Hitherto, neither the practices nor the understanding of the
importance of undertaking compliance audit exists. But recently due to the provision of training,
they seem to realize the paramount importance of compliance audit.
Technical Reporting: One of the communication mechanisms between funding partners and
implementing organization is delivery of good quality reports. USAID and many institutional
donors also require an accurate and complete program deliverables and success stories in their
reporting agreements. ORDA basically prepares two kinds of report i.e. contractual for the
government and donor based report for the donors. The assessment indicated that different
sections or departments in ORDA are responsible for the preparation of reports; these include;
community promoters at kebele level, project officers, program coordinators, managers, and
M&E officers. All these actors have been involving in the report preparation to ensure data
quality and consistency of the report. The participatory discussion with FHE management also
confirmed that ORDA has made improvements in timely delivery of reports even though the
quality of reports in terms of presenting success or case stories and documenting lessons needs
further improvements. ORDA team also confirmed that, the program department is not strong in
presenting success stories and lessons while developing progress report. The baseline
quantitative result (3.3/5) showed slight increase to (3.8/5) implied that though there is some
improvements ORDA needs to strive more in effectively documenting lessons learned, best
37 | P a g e
practices and gaps. Moreover, the documentations must to be well organized and readily
available for learning.
It is also reported during the participatory discussion with ORDA staffs that reports are collected
from the project offices and compiled centrally at HQ level based on the donors’ format and sent
to the donors, program office and to the HQ management. The findings also disclosed that due to
the bulkiness of the activities, activity reports are not checked with financial reports.
The participatory discussion with BDARP section indicated that ORDA staffs have a clear
understanding the reporting formats and accordingly prepares and submits quarter and semi-
annual narrative and financial reports using USAID reporting format. Considering the timing of
the reporting the project offices have been submitting the report within the specified time period
and have no problems in this regards.
Community involvement: Community participation is a core concern of humanitarian and
development organization as it has been set as one commitments in Core Humanitarian (CHS)
Standards. ORDA as a humanitarian and development organization must implement clear
systems that ensure target groups are participated fully in the project cycle management
including utilization of project budgets. The target beneficiaries are the right holders of the
projects’ resources and they are entitled to hold ORDA accountable in the process of project
implementation and utilization of resources. Therefore, ORDA as duty bearers should create
opportunities to engage communities at large.
With regards to community involvement in project cycle management, the FGD discussants have
confirmed that the community participates in project cycle and annual performance meeting and
also influenced decision in few instances, if not always. The quantitative result (3.6/5) which is
slightly above the average support this qualitative statement in this regard. However, in some
instances the target beneficiaries do not influence decision, like forcing donor to change
activities as per their priority after the project/programs are designed and approved. But the
communities are consulted on beneficiary selection and establishment of committees during the
implementation of such projects. However, once the project proposal is developed and approved
ORDA implements it with the full and active participation of the community at large. But, the
target communities have no chance of knowing how much budget is allocated and oversee the
utilization of resources.
38 | P a g e
Knowledge Management and Diffusion of Technology: ORDA has recently prepared
knowledge management guideline by hiring consultant. However the quantitative result (2.4/5)
which is below average indicated that the manual is not familiarized with the staff. Indeed the
majority of the staffs have no idea about the manual. As part of knowledge management and
transfer of skill, learning and knowledge sharing events are one area of competency but ORDA
has no practice of regularly organizing learning and knowledge sharing event and the
quantitative result is also complemented by a little less than average point of (2.4/5). The
quantitative result (2/5) has verified that capacity building training on the principles and
applications of knowledge management is not adequate. The key learning practices and
experiences are not systematically organized and scatterly documented here and there. In
general, ORDA’s knowledge management system can be judged weak and needs further
improvement with the full utilization of the newly developed knowledge management guideline.
Proposal development and resources mobilization: Capacity for quality proposal development
is one area of competency that helps to adequately solicit funds. ORDA develops proposal based
mainly on call for proposal. Searching call for proposal has been undertaken both at HQ and
liaison office (Addis Ababa) level. In addition to this mechanism, some partner’s organizations
of ORDA inform them some calls which is not officially announced.
As indicated in the participatory discussion with ORDA management, quality proposal
development, networking and linkage, quality delivery of program at ground level are among
some of the fund raising practice of the organization. Discussion with ORDA’s Business
Development Action Research (BDAR) team indicated that ORDA use participatory proposal
designing systems. Three program design officers are responsible for writing proposals in
collaboration with food security, natural resource management, and water/irrigation development
departments in line with the thematic focus of the proposal. However, ORDA asserted that it has
been using participatory program designing, there is no clearly defined structures and Terms of
References for the program designing team.
Despite the absence of clearly set structure for the proposal designing team, the success rate of
proposal for funding has shown radical improvement compared to the baseline (20%) in year
2014 to success rate of (92%) June 2016. The bi-annual report of ORDA (January to June 2016) 39 | P a g e
indicated that the organization has developed a total of 17 projects of 11 are funded, one
proposal rejected and 5 are waiting for responses. The statement of the management discussion
also indicated that ORDA has developed its proposal writing skills through different capacity
building trainings provided. It is raised by the FGD discussants that ORDA has provide training
on proposal writing skills and techniques for program staffs on average once in every year.
In this regard, the reflection of BDAR team is consistent with FHE management discussion
which pointed out that capacity building training on proposal writing has been provided for
ORDA program staff so as to enhance their capacity to design competent proposals for funding.
The quantitative result (3.0/5) slightly above average somehow complements the qualitative
statement i.e. regular capacity building supports for program staffs on proposal writing are
provided. BDAR team also confirmed that the training on proposal writing for program staff has
contributed in increasing the success rate of the proposals and quantitative result (3.6/5) also
supports the qualitative findings. Though, ORDA is working hard to improve its capacity to
prepare proposals that meet the technical and accountability requirements of donors , the practice
to internally appraise developed proposals is very limited and the proposal appraising committee
does not use the appraisal checklists of donors which are commonly found in the websites of the
donor agencies.
The quantitative score (3.8/5) showed that ORDA has made some improvement in designing
innovative proposals that contribute to the empowerment of target groups against the baseline.
The senior management of ORDA has emphasized that ORDA is not strong in developing
innovative proposal and need to work hard in this regards so as to win the attention of the
donors. The qualitative statement also depicted that “ORDA’s projects have great contribution to
empower communities and to sustain the program outcomes”. Reviewed bi annual (January to
June 2016) report of ORDA indicated that during the reporting period, job has been created for
10,568 (5930 females) youths and enabled to create Birr 13.5 million via temporary and
permanent employment opportunities which is consistent with statement that developed
programs are contributing for sustainable empowerment of the community.
With regard to designing quality proposals that sufficiently fulfill USAID interest, though the
quantitative result (3.6/5) is above the average, the discussion with BDAR team emphasized the 40 | P a g e
need to hire external consultants to develop proposals and the discussion with ORDA senior
management also confirms the same. However, FHE management argued that hiring consultants
for proposal development is costly, lengthy and hectic process and suggest that ORDA should
bolster its grasp of USAID grant proposal development procedures and requirements. They
suggest ORDA to do this by hiring experienced seconded consultant on permanent basis for
some times to give on job training on quality proposal development that fulfill USAID’s
requirement.
Culture and Gender: Reviewed organizational documents, quantitative results and qualitative
statements indicated that ORDA has clearly out in place guidelines for culturally relevant and/or
gender-based approaches and programming. Gender analysis is conducted before intervention of
any program so as to inform the program on the gender dynamics of the intervention areas.
Accordingly both the program team and the gender section conduct gender analysis regularly and
the quantitative result (3.6/5) indicated that the gender experts of ORDA together with program
staff conduct gender analysis and use the recommendation for improvement of programs.
Biannual (January to June 2016) report of ORDA stated that during the said period a total of 22
gender analyses were conducted.
ORDA design projects in a way to address both strategic and practical gender needs of women.
Regarding empowering women, from January to June 2016 a total of 2,339 women got training
on leadership. Aawareness on gender issues and women’s provisions of the PIM during Public
Works’s (PW) provided for 51,577 (26,876 females) PSNP clients. To enhance the awareness of
the whole community on gender issues, messages on gender equality were transmitted through
radio spots to 10,652 (4073 females) PSNP clients.
Despite several improvements in gender integration there remains strategic issues that need to be
addressed . One of the key issues that need consideration is that the gender section of ORDA is
only staffed with one employee. Though the gender work should be the responsibilities of all
staffs, until ORDA reaches such stage where each and every employee hold responsibility for
gender integration work, the gender section should be adequately staffed and strengthened
considering the number of interventions that ORDA has been engaged.
41 | P a g e
Furthermore, gender integration work of ORDA is only at programming level. Whereas gender
work at organizational level to ensure that policies and procedures adequately integrate gender
issues are overlooked. This is clearly manifested at the leadership position of ORDA where there
is no woman in the leadership position. Therefore, in order to maximize the impact of gender
work at programming and results at community level, ORDA should strongly work on
organizational transformation from gender perspective.
Standards and Quality Assurance: ORDA has operational guidelines that stipulate service
delivery standards. In addition, ORDA has been using the government quality service standard
for infrastructures constructed like water schema, small scale irrigation, road and bridge. The
quantitative score (3.75/5) indicated that there is slight improvement against the baseline (2.76)
in using service quality standard for activities as means of quality assurance. Though the
qualitative score (3/5) is slightly above the average indicate that ORDA has provided regular
training on adherence to this standard. However, the participatory discussion with staff indicated
that awareness on those standards is limited among ORDA’s program staffs. Structurally the
section that is responsible for standards and quality assurance is not clearly defined. Moreover,
there is confusion whether the role of quality assurance belongs to BDARP section or M and E
section.
Supervision: ORDA has a supervision approach and plan in place and utilizing this approach and
plan while supervising the activities at field level. It is also discovered that the findings of
supervisions has been documented and shared and discussed with the management and staffs.
Monitoring and Evaluation: Performance Management Plan (PMP) -a tool designed to help
partners set up and manage the process of monitoring, analyzing, evaluating and reporting
progress toward achieving objectives is one of the competency areas that the USAID grant
management procedures demanded. ORDA has compatible vibrant designing, monitoring and
evaluation framework in place pertaining to performance management system as pointed out by
FGD discussants and also substantiated by quantitative score (3.8/5). The baseline quantitative
indicator (3.3/5) confirmed that ORDA has shown slight improvements in this area.
It is also found out that there is a documented monitoring and evaluation plan (output) and
outcome indicators, data collection tools schedule, quality review and methods for sharing and
42 | P a g e
using data. The quantitative result somewhat confirmed this findings (3.8/5). In order to enhance
the monitoring and evaluation skills of staffs and undertake quality data ORDA has been
providing training, but as per the findings of quantitative result (3.2/5), ORDA need to do more
work in this area.
It is confirmed that ORDA has been using Monitoring and evaluation findings with a view to
improving the delivery of programs and projects, and the quantitative data supports this result
(4/5). The program staffs have well internalized the designing, monitoring and evaluation
guideline and the quantitative result also shows this (3.6/5).
ORDA has also made slight improvement in designing program documents that include essential
Designing, Monitoring and Evaluation elements (baseline, targets, result chains, implementation
modalities & work plan, monitoring milestones, evaluation, accountability and learning
mechanisms which as a result changed to (3.4/5) from 3.15/5 quantitatively.
The qualitative rating continuum given by the program team of ORDA is (2.75/4) indicating that
as compared to other capacity competency area ORDA has need to work more in quality
program designing and management of program delivery.
7.6. ORDA’s leadership engagement in capacity building support
The leadership of ORDA is one of the key aspects that we have looked into while conducting
this capacity reviews. We have observed that to very crucial endeavors have been made by the
leadership of ORDA. These endeavors have contributed for the capacity improvement of ORDA.
The participation of the leadership in building the capacity of ORDA have manifested in such
ways as establishing networking and partnership with various national and international
stakeholders, developing inclusive strategic plan that guide the overall development activities of
ORDA, initiating and leading important studies that can change ORDA’s ways of delivering
services and their close follow-up and supports to the technical and supports staffs and units of
ORDA.
Networking and strategic Partnership: ORDA’s leadership perceived networking and strategic
partnership with stakeholders as a key tools to mobilize resources, extract new skills and
knowledge, deliver effective and efficient services at all level and make the outcomes of project
43 | P a g e
implementation as sustainable. In this regard, ORDA has been working in networking and
partnership with several national and international organizations. To enhance effective
partnership and networking and get the best out of it ORDA has developed Communication and
Networking Strategy document. This document defines its audience which includes Community,
Local and International partners etc.The management of ORDA firmly believes that the
communication and networking strategy helps to increase ORDA’s visibility both at local
national and international level.
So far, ORDA has established a promising strategic partnership with different international
organizations like CRS, EU, DFID, The Development Fund Norway etc to enhancing resource
mobilization and skill and knowledge development. The senior management of ORDA aired that
FHE has helped them establish linkage with USIAD for direct talk with its management team.
Consequently, USAID people have advised ORDA on how to establish direct strategic
partnership with USIAD. As per the reflection of both FHE and ORDA, the established
networking with USAID shows that direct partnership with USAID can be formed by applying
for small grants and in the process ORDA will become familiarized with the compliance
procedures and policies of USAID grant and thereby become more visible to USAID. However
the management of ORDA preferred to compete for consortium approach rather than trying with
small funding. Though a missed opportunity, ORDA can go for and entertain both approaches at
the same time i.e. application for small grant and direct application in consortium.
Though the funding trend of ORDA showed tremendous improvement, the participation of
Board of Directors in soliciting fund is reported to be very weak.
Capacity building in Strategic Planning: ORDA has a strategic plan developed for the period
covering 2016 – 2020. ORDA’s Board and Management has made the decision to develop this
fourth strategic plan in view of the globally ever changing funding priorities, increasing
competition in resource mobilization coupled with the unmet development needs of
communities. The rationale behind the revision of the strategic plan include inter alia, making
the strategic plan consistent with the framework of GTP 2, embrace post 2015 sustainable
development goals and include donors’ interest and willingness to finance the development
interventions. As per the reflections of senior management of ORDA, accessing big donors at
least one in a year is one focus of the strategic plan. The management indicated that they have
44 | P a g e
been working to achieve the set objective and accordingly ORDA has accessed funds directly
from some donors like DFID- Civil Society Fund for three consecutive years. However, the
strategic plan does not set out system to look and track opportunities of small but strategic grants
that link ORDA with big donors. This is very important for ORDA as a small grant of $100K-
200K is issued from time to time by USAID for NGOs that have not received funding from the
USIAD directly in the past.
This strategic plan envisions serving as a management tools to guide program management and
implementation, resource mobilization, ensuring community participation and empowerment,
enhancing stakeholder collaboration, efficient utilization of recourse and ultimately changing the
livelihood of the end uses/people.
Efforts of the leadership of ORDA to get direct access to Donors: The participatory discussion
with the senior management of ORDA indicated that the management envisions to directly
assessing funds from big donors like USIAD in five years. It has also indicated that ORDA is
thinking a strategic move of scaling up its status from sub-grantee to consortium and then to
capacities that enable ORDA to access Donors directly.
Persistence and continuous support of the leadership/senior management to technical and
support staffs/unit of ORDA: It was strongly confirmed by the FGD discussants of different
departments of ORDA that the continuous and persistence supports of the senior management of
to each department highly contributed for the efficiency and effectiveness of the pertinent
department in the discharge of their responsibilities. Member of the senior management
including the Executive Director regularly visit departments and ensure that work is smoothly
going as planned and if the need arise provide supports.
Contribution of ORDA’s Board of Directors to improve ORDA’s Capacity: it is voiced by all
FGD discussants of each department that the contribution of BoD in building the capacity of
ORDA is very insignificant. Contrary to expectations, BoD has so far failed to engage in lobbing
to bolster ORDA’s partnership and networking with donors and enhance resource mobilization.
The BoD is also not active in offering constructive inputs on different reports that need its
feedback.
45 | P a g e
VIII. Relevance, Effectiveness, Efficiency, Sustainability and Impact of the capacity building efforts
8.1. Relevance of the capacity building support
The relevance of the capacity building supports to ORDA’s priorities, pertaining to system
development was assessed. ORDA has been implementing programs with different International
Funding Partners and accumulate more than 15 years of experiences in implementing different
USAID funded projects as sub grantee recipients. However, ORDA has not been able to directly
access funds from USAID. Although ORDA has numerous years of partnering with international
Non-Governmental Organizations, international partners have focused capacity building efforts
on programmatic implementation rather than building support systems.
The findings of the assessment revealed that the capacity building support provided by FHE is
focused on system development of ORDA with a view to strengthening institutional capacity.
The discussion with the staff and reviewed documents indicated the capacity building plan found
to be relevant to ORDA’s capacity need in system development and establishing strong
networking and partnership. ORDA has been working in USAID funded projects for more than
15 years as sub grantee and this long year experience with USAID project implementation has
enabled ORDA to be familiar with the USAID grant management procedures, yet compliance
with the grant management process was proven to be arduous. Despite the long year experience,
ORDA had not yet reached the capacity level of directly accessing funds from USAID.
Employees’ understanding on the basic grant management procedures was low, and the existing
policies, procedures and systems were not reviewed to incorporate donor specific requirements.
In decades of engagement with USAID, ORDA had not got opportunities to establish networking
and relationship with the USAID managements. Technical capacity such as VAT reimbursement
issues, gaps in regularly delivering accurate and complete financial report were the major
capacity gaps in complying with the USAID grant management The findings of document review
and qualitative study showed that the capacity building support provided is relevant and were
priority areas of ORDA. Moreover, it was exhaustive, participatory and passed through
comprehensive planning process. The quantitative result (4.67/5) undoubtedly confirmed that the
46 | P a g e
capacity building support provided by FHE is highly relevant to ORDA’s priorities and needs to
fill the capacity gap in system development.
8.2. Effectiveness of the capacity building support
ORDA has implemented the capacity building initiatives in partnership with FHE Ethiopia. The
partnership is found out to be supportive and based on mutual trust. The decision made by FHE
in revising the DFAP program to incorporate staff salary that seconded to ORDA to support the
capacity building process is appreciable. The capacity building support started with a
comprehensive capacity assessment which used as baseline capacity gap. The startup capacity
assessment report is indispensible to measure the changes brought out by the capacity building
support of FHE through DFAP.
With the supports of the seconded capacity expert, various capacity building activities have been
undertaken. One of the most important outputs of these capacity supports is the capacity
assessment with various recommendations which helped ORDA to prepare different policies and
manuals that facilitate effective human resource, financial, commodity and knowledge
management. In addition to this, various capacity building trainings have been provided by FHE
in different areas including financial management, human resource management, procurement
administration, commodity management, grant management and others. This capacity building
supports provided by FHE helped ORDA to strengthen its capacity to comply with USAID grand
management.
FHE also facilitated various experience sharing visits within the country and aboard. The
commodity management department visited Djibouti two times to get experience in the area of
commodity management from the sea port to distribution center. Experience sharing was also
arranged to Uganda which helped ORDA to acquaint itself with watershed management.
However, ORDA felt that the experience sharing program organized by FHE is not sufficient and
more could have been made, especially in the area of international experience sharing.
ORDA also give credit for the on job training and advices provided by the seconded capacity
builder/staff and the recommendations provided by this expat. However, ORDA felt that the late
assignment and early departure of the capacity builder has put ORDA to the disadvantage
47 | P a g e
position and ORDA would have got more support from this expat had FHE assigned him/her
early as reported by the senior staffs of ORDA.
Different departments of ORDA participated in the capacity assessment and implementation of
the capacity improvement plan. However, the participation of program officer in the
implementation of the capacity gap improvement plan was not noticeable as there is still gap in
complying with USAID grant management procedures at field office level.
Strong leadership commitments for the implementation the capacity building plan was displayed
at Head Office level which enabled ORDA to score improvements in all competency areas of
capacity. In general, the planned activities of the capacity building support has been
implemented during the capacity building support period indicating that the support was
effective in addressing the capacity gap needs of ORDA.
8.3. Efficiency of the capacity building support
Even though it is very difficult to ascertain the efficiency or performance of the project in terms
of fund utilization, the efficiency of the capacity building support is assessed in terms of the
experienced staff seconded to ORDA and time used to build the capacity building support.
Though deployed late, ORDA has utilized the skill and knowledge of the seconded staff
efficiently to enhance its system development and meaningful changes have been made on the
overall capacity of ORDA as a result. However, ORDA would have been benefited a lot from the
skill and knowledge of the expat had the expat used the allocated time fully.
The phase- based capacity building plan enabled ORDA and FHE to prioritize capacity building
plan and strategically intervene which contributed to bring significant change in the key
competency areas in the specified time period, and this indicate efficient utilization of time and
human resources. The enthusiasm and interest of ORDA’s management and staff to sap
knowledge and skills from FHE has helped to ensure system development and transform the
organization within the time frame of this capacity support.
8.4. Impacts of the capacity building support
48 | P a g e
The performance of the capacity building in meeting stated objectives (enhancing ORDA’s
capacity to directly access USAID fund) was assessed. The result confirmed that the capacity
building support has achieved most of the planned objectives as witnessed by self-administered
survey participatory consultation and observation carried out by the assessment team.
Both the qualitative and quantitative data ascertained that the capacity building support enabled
ORDA to obtain all the necessary policy documents that incorporate USAID grant requirements.
Staff understanding of the USAID grant requirements improved through different capacity
building trainings offered via this capacity building initiatives. Discussion with ORDA and FHE
management evidenced that the compliance issues/problems with reporting qualities have been
reduced. Though ORDA has not yet directly accessed fund from USAID, promising practices
has been indicated and ORDA has tried one proposal for USAID but unfortunately was not
funded.
8.5. Sustainability of the capacity building support
The capacity building supports is deeply inculcated in terms of addressing ORDA’s felt need,
fitting to existing institutional arrangement coupled with a long year experience of ORDA in
working with USAID funded projects as sub grantee undoubtedly entails a positive outlook of its
sustainability. The leadership commitments in institutionalizing the capacity building efforts are
encouraging as the capacity building is one area of the strategic plan of ORDA.
IX. Strength, Weakness, Opportunity and Threats of the capacity Building efforts
The consultants have tried to identify strength, weakness, opportunities and threats of the
capacity building efforts. Here in a brief presentation of the findings are in order.
Strengthen 1. The commitment of the senior management to lead the capacity support and creating the
favorable environment for the supports to bring the required result is found to be one of
the strengths of ORDA.
49 | P a g e
2. The existence of professional freedom, job satisfaction and good working environment
contributed to ORDA’s ability to fully exploit the expertise and skill of its staffs at every
level. One of the manifestations of this is the existence of dedicated and highly
professional staffs who have been taking the organization for ward in every aspect.
3. The dedication of all the staffs to internalize the recommendations provided by the expat
and commitment to act as per the recommendation is another noticeable strength of
ORDA.
4. ORDA has produced organizational settings, policies and procedures that incorporate
donors’ interest.
Weakness 1. Unavailability of organized and clear structure aimed at developing proposals that fulfill
donor compliance.
2. Limited knowledge and information cascading structures and practices (ORDA has
limitation in cascading information and skill to the level project office )
3. ORDA has not been benefiting from the privileges that the government has provided to
Non-governmental Organization (70/30 budget utilization). Though this definitely benefit
the target communities, ORDA need to use this opportunity to retain staff by increasing
their salary and reduce the turnover of experienced professional.
Opportunities 1. Familiarities of ORDA to USAID policies and procedures
2. Availabilities of competent staff that responds capacity gap recommendations
3. Acceptance of ORDA by the government and target communities
4. Availabilities of well defined policies, procedures, and strategic plan
5. Availability of supportive government policies and programs
Threat • Less competitive benefit and salary package that endangered staff turnover which in turn
leads to the failure of investment on professionals with serious repercussions to ORDA.
50 | P a g e
• Internet disconnection may create difficulties in report exchange, if ORDA is going to
install the technology which predominantly depend on availability of internet network
X. Challenges The following are the challenges that ORDA has been facing by not fully responding the
recommendations suggested in the capacity assessment of the 2012 and 2014
1. The inability of ORDA to install the financial software that is believed to ease the
financial reporting from the field to the HQ and then to the donor is found to be one of
the perceived challenges. ORDA was not able to get funding to install the software .
2. The monitoring and evaluation and documentation system of ORDA is not fully
organized and comprehensive. Though some efforts being made, ORDA is not fully
computerized and not able to create monitoring and evaluation information pool. As a
result, it is difficult to get the required information from program department for learning
and the information is highly disorganized.
XI. Lessons learnt Stepwise transformative approach to partnership-from sub grantee to consortium and direct
partnership
ORDA has moved a long year journey as sub grantee of USAID fund through implementing
different projects in partnership with different International Non- Governmental Organizations
(INGO). More than 15 years engagement in implementation of USAID funded projects created
an opportunity for ORDA to be familiar with USAID grant management procedures and
requirements. However, no comprehensive capacity assessment conducted in assessing
ORDA’s capacity in complying with USAID funding requirements. The capacity building
support of FHE enabled ORDA to move one step from sub grantee to thinking of consortium
member in USAID funded projects. During the capacity support program, ORDA has got a
chance to meet and discuss with the USAID management and learnt that it is a best strategy to
follow a stepwise approach to access direct funding from USAID. This is an indication to start
with small grant to directly access USAID’s fund.
51 | P a g e
However; the strategic move to partnership that the management of ORDA believed is
enhancing visibility through working in consortium and compute to directly accessing big
grants. Accordingly, the enhanced capacity building support enabled ORDA to be a consortium
member in DFAP II program and this created opportunity for ORDA to be more visible in
USAID funding as ORDA is the lead in one of the component of the project. ORDA’s
management believe this as one areas of lesson acquired and being a consortium member will
transform ORDA to directly access USAID big fund in the next five years time.
The capacity building strategy and approach followed (i.e. assignment of the expat and starting
the capacity building process from within) is found to be a good lesson. This approach has
brought significant transformation.
Immense desire of the Organization for change at all levels can indeed bring fast changes.
ORDA in this regards can be typical model. All the department of ORDA was very much
aware of the gap identified by the capacity builder and acted on the recommendations showing
the dedication and commitment of both the staffs and management of ORDA.
XII. Conclusions and recommendations
12.1. Conclusion FHE capacity supports to ORDA found to be relevant specially in making ORDA comply with
USAID grant management requirements. The supports are seen to be multi-dimensional and
follow right and logical process (i.e. from capacity assessment to determine the status, identify
what is lacking, and prepare the action plan and act accordingly and finally to capacity review to
measure the change). The approach followed, that is the assignment of expat to ORDA was
discovered to noble and helpful to start the change from within and bring fast and full-fledged
transformation.
The contribution of the multifaceted support is confirmed to be positives and visible in every
department of ORDA and the result is progressive and very strong in most departments such as
HR, administration and logistic, procurement and finance. Moreover, the supports are especially
very successful in terms of enabling each department to have their own policies and manuals as
well as guidelines that harmonize donors’ policies and requirements. The support also succeeded
52 | P a g e
in enhancing the knowledge and skill of ORDA’s staffs towards donors’ working environments
and procedures and on how to comply with donors’ requirement.
It is also conclude that, the commitment, interest and dedication of ORDA’s management,
technical and support staffs as well as the commitment of FHE was a fertile ground for the
implementation of the capacity building supports and the achievement of the set objectives.
It is concluded that there are some missed opportunities that both ORDA and FHE has lost.
ORDA and FHE have moved a very long journey in implementing development projects in
Amhara Region and they understood each other. However, due to lack of discussion they could
not continue working together. It would have been good if ORDA had explained its interest on
how and in what future ORDA want to work with FHE in the second DFAP. As discussed by
FHE, there was an opportunity to work with FHE as consortium and this would have been very
helpful as both FHE and ORDA know each other specially in implementing DFAP 1.
12.2. Recommendation Recommendations
Recommendation for FHE:
The multi faceted support of FHE to ORDA has enormously contributed to enhance ORDA’s Capacity. However, the support was mainly confined to ORDA’s Headquarter. The knowledge of the project staffs and offices at Woreda level on USAID grant management is somewhat limited indicating the knowledge in not adequately cascaded to the ground. It is recommended therefore that, while undertaking such types of capacity support, FHE should consider staffs and offices of partners at ground level and should develop a system, together with the partners, to address them with adequate budget and follow-up mechanism.
FHE capacity support had two main phases: phase one: undertaking gap assessment and
ensuring availability of working policies and manuals and procedures; and second phase: familiarizing the developed policies and procedures to staffs and start working with the new policies and procedures. The first phase of the support found to be more successful than the second one. There had not been adequate time to implement the second phase and early departure of the seconded staff was also a problem. We therefore recommend FHE to assign sufficient time for each activity while doing such types of capacity building. We also suggest midterm review or other kinds of progress assessment that can help to check whether the support is on track and made timely corrections.
53 | P a g e
The major objective of the capacity support of FHE to ORDA is to help it develop a capacity to independently access to USAID grant. In this regard FHE has enormously supported ORDA to bolster its capacity. But, the partnership agreement limits ORDA not to directly participate in some important activities, for instance participate to independently manage commodities from the seaport to the distribution centre, which was very important capacity for ORDA to access USAID grant. We therefore, recommend FHE that while carrying out such types of support, prepare a partnership agreement that have a room which enables partners like ORDA to engage in such important activities after making a thorough assessments of capacities.
Recommendations for ORDA:
Though ORDA has been implementing many of projects and addressed marginalized communities, it is poor in documenting best practices and lessons that can be used as learning. We strongly recommend ORDA to effectively documenting lessons learned; best practices in a manner that can be easily accessed and used. Using technologies that can simplify accessing the best practice and lesson learnt is strongly recommended.
ORDA has different staff retaining mechanism including provision of education opportunity and providing hardship allowance. However, ORDA’s staff salary is still low comparing with the current market leading to high staff turnover. We therefore recommend ORDA to consider of improvement of staff salary and benefit package, otherwise, the staff turnover will continue to be grave danger to the organization;
Since ORDA has a plan to independently apply for USAID grant. One of the competency areas that USAID requires from ORDA is a good practical experience in effectively managing commodity from the seaport to beneficiaries. As ORDA does not have practical experience in this regard we recommend ORDA to acquire such experience using all available opportunities.
With the support of FHE, ORDA has established fixed asset management systems with trained staffs. It has shown improvement in undertaking asset inventory to effectively manage fixed assets. However, the fixed asset registration lacks documentation of depreciation rate and calculation. We therefore, recommend ORDA to effectively document depreciation rate and calculation for the fixed asset.
Over the last thirty years ORDA has ensured progressive achievements that helped millions of marginalized people to be survived and improve their livelihood. However, ORDA has no practice of regularly organizing learning and knowledge sharing event. In order to be more visible at national and international level, ORDA need to organize such events regularly and invite donors’ communities and stakeholders to these events. This event will help ORDA to be on board with donor communities and other important stakeholders.
As per the assessment, ORDA is successful in preparing wining proposals. However, it is found out that ORDA is not strong in developing innovative proposals that have taken in to account the current climate change and the changing needs of the donors. We therefore,
54 | P a g e
recommend, ORDA to work hard in this regards to develop innovative projects (that use renewable energy sources like solar and wind power) and win the attention of the donors’ communities.
Integrating Gender at organizational level is overlooked. This is clearly manifested at the leadership position of ORDA where no woman is represented. Therefore, in order to maximize the impact of gender work in programming and results at community level, ORDA should strongly work on organizational transformation from gender perspective.
Audit and inspection section of ORDA has missed opportunity to internally audit ORDA’s compliance with the USAID grant management requirements in particular and donor agencies in general. As ORDA has a plan to independently apply for USAID fund in the future, it is recommended that the audit and inspection unit to undertake audit on ORDA’s compliance with Donors’ grant management requirement.
Despite improvement in developing standard financial report, the field office finance staffs are not fully equipped to produce financial reports using the USAID reporting formats. The consultant would like to recommend ORDA to provide full-fledged assistance and put in place the required system to enable the project office independently produce financial report that complies Donor’s requirement. This will help ease ORDA’s financial reporting process and reduce the time taken to produce the expected report within the deadline.
Currently, due to high competition over resources internationally, the probability getting sufficient financial resources is becoming tough. ORDA need to focus on income generating activities internally so as to diversity its financial sources. It is found out during the assessment that ORDA has opportunities to engage in income generating activities and have been working on it yet there is a need to pace up things.
The consultant has observed gaps in the grant management responsibility of the Grant Management Unit. The role and responsibilities of the grant management section is not clear and limited to facilitating project agreements and reminding project staffs as the project agreement is approaching phase out stage to timely complete project activities. Officers in the section also have limited knowledge of Donor’s Grant management requirements including USAID grant management. We therefore recommend the staff to be well armed with the required knowledge in this regards and contribute what ORDA expect from the section. There is a need to revise the role and responsibilities of the section to make the section effectively work on ensuring donor’s grant management compliances are adequately addressed.
ORDA has made great strides in timely delivery of progress reports even though the quality of reports in terms of presenting success or case stories and documenting lessons needs further improvements. We recommend ORDA to prepare a report to contain success stories and lessons so that it can sell its achievement to donor’s communities. We also strongly recommend ORDA to effectively documenting lessons learned; best practices and documentations need to be well organized and readily available for learning.
55 | P a g e
The key learning practices and experiences are not systematically organized and sporadically documented. ORDA’s knowledge management system is found out to be weak and needs further improvement aiming at full utilization of the newly developed knowledge management guideline.
ORDA management team suggested hiring external consultant to develop proposals to be submitted for USAID for funding. but, FHE management indicated that hiring of consultants for proposal development is costly, lengthy and has hectic process and they instead suggest hiring experienced seconded consultant on permanent basis for some times to develop proposal and in the meantime deliver on job training on quality proposal development that fulfill USAID’s requirement. The consultant therefore would like to suggest ORDA to re-think again, assess the experience of other similar development actors and decide on the best option.
The current ORDA’s, have not been delivering what the organization has been expecting from then, especially in enabling ORDA’s to win the attention of big donors. We, therefore, strongly recommend ORDA’s BoD to be constituted by personalities who have strong commitments and passion to move ORDA forward.
56 | P a g e
XII. Annex 1. Assessment questionnaire
Keys: 1. strongly disagree; 2. Disagree; 3. somewhat agree; 4. Agree; 5. strongly agree.
A. Human Resource Management
No. Description Response by Coode Average
Rank Baseline Average Result
Code 1
Code 2 Code 3 Code 4 Code 5
1 HR policy is put in place to ensure recruitment, deployment, performance appraisal, promotion, remuneration, etc
5 5 5 5 5 5 2 Standards of conduct are set to address the
behavior and professional conduct that affect the employee’s ability to perform his/her job and represent the organization
5
4 4 4 5 4.4 3 3 There is a written Job Description (JD) for
each staffs 5
5 5 5 5 5 3 4 Policy defining the role of volunteers is put
in place 1
4 2 4 4 3 2 5 Employee handbook shared with all staff s
exists
4 4 4 3.75 3 6 HIV/AIDS Policy which defines an
organization’s stance on the employment of persons living with HIV or AIDS and the expected treatment in the workplace is put in place
4 4 4 5 4.2 4 7 There is diligence in Hiring Decisions; HR
takes a summary of a candidate’s academic and work history (a Curriculum Vitae or CV) for every employee hired
4 3 5 5 4.2 5 8 A policy demanding drug free workplace
is instituted
5 2 5 4 2 9 Managers conduct supportive supervision
to create healthy work environment and improve and sustain the performance and satisfaction of their staffs
4
4 4 4 5 4.2 4 10 A vibrant staffs performance management
system including performance appraisal, performance improvement plan, etc is put in place
4
4 5 4 4 4.2 4 11 Regular feedback is given to staffs to
improve performance 3
4 2 4 4 3.4 3
57 | P a g e
B. Financial Management
Respondents code Average Rank
Baseline Average Result
No Description Code 1
Code 2
Code 3
Code 4
Code 5
Code 6
1 The finance/grants management team understand and properly apply the USG cost principles (A-122)
5 4 4 5 4
5 4.20
2.8 2 The staffs clearly understand how to take advantage of
the approved work plan and budget to manage the financial disbursement and settlement process
5 4 4 5 4
5 4.50
3.8 3 Financial resource management policy and operation
guideline that ensure accountability of the partner to donors, communities, etc is put in place. 5 4 5 5 4
5 4.67
3.4 4 There is audit policy and system to ensure financial,
commodity resources and fixed assets are properly utilized and maintained 5 5 5 5 5
5 5.00
2.8 5 Finance staffs clearly understand and apply the
accounting and financial administrative systems of donors as a component of financial management 5 5 5 5 5
5 5.00
2 6 Finance team understands and applies the USAIDs key
pillars of financial management( planning, organizing, controlling, etc) 4 5 4 5 4
5 4.50
2.8 7 The Executive Director (ED) Ensure accurate and
timely preparation and submission of financial reports 5 5 4 5 4 4 4.50
3.4 8 The ED ensure program activities are in line with
budget and deliverables 5 5 4 5 4 4 4.50
2.6 9 The ED monitor financial needs of the organization
and business planning 5 5 4 5 4 4 4.50
3.2 10 The senior managers administer and monitor the
budgets for their departments or projects 5 5 5 5 4 4 4.67
3 11 The senior program managers review financial reports,
give feedback and prepare Future financial needs. 5 5 3 5 5 4 4.50
3.2 12 Program staffs control budgets to ensure money is
spent as agreed and work with finance staff to ensure policies and procedures are followed, expenditures are coded and reported accurately 4 5 5 5 5
4 4.67
3.6 13 Finance staffs complete the books of accounts and
reconcile them every month 5 5 5 5 4 5 4.83
3.8 14 Finance staffs prepare quality reports using the
standard procedures of donors and Submit within the timeframe. 4 5 5 5 4
4 4.50
3.2
58 | P a g e
C. Logistic /Property and Resource management
Average Rank
Baseline Average Result
No. Description Code 1
Code 2
Code 3
Code 4
Code 5
1 The logistics team Understands the USG procurement policy and procedures (what? where? How to buy? Applicable taxes? Documentations required? This includes purchase, rental services, contract administration, fixed asset management
4
4 4 5 5 4.4 3 2 Written standards of conducts are developed for employees and
officers involved in selecting and overseeing procurement which include (conflict of interest, gratuities,) disciplinary dictions
4
4 5 5 5 4.6 1.6 3 Procurement policy includes free and open competition, general
procurement procedures, instruments, contractor evaluation, documentation procedure
4
4 5 4 5 4.4 3.3 4 The organization understands what is allowed and what is not
allowed. Lists of allowable and non-allowable items are recorded in the orgs docs
4
4 4 4 5 4.2 3 5 There is understanding about the restricted and prohibited
purchases, transactions, sources 4
5 4 5 5 4.6 3.6 6 Restricted commodities that need prior approval from USG
(agricultural commodities, motor vehicles, pharmaceuticals, Pesticides, used equipment, U.S.) are well known
4
5 4 4 5 4.4 2 7 The logistics team knows well the Prohibited items: military
equipment, surveillance equipment, commodities and services for support of police or other law enforcement organs; abortion equipment and services; luxury goods and gambling equipment, including alcoholic beverages, jewelry or expensive textiles; and weather modification equipment.
4
4 5 4 5 4.4 3 8 The purchasing team understands the issues related to taxations
when processing purchase using the USG funds 4
4 5 5 5 4.6 3.3 9 There is policy which prohibits staffs/leaders from accepting any
gift that may influences policy and decisions 4
4 5 5 4.5 2 10 ORDA understands what is allowed and what is not allowed. The
lists of allowable and non- allowable items are recorded in the orgs docs
4
5 4 5 5 4.6 2.6 11 Whenever the partner buys goods or services or hires consultants
using USG funds, it must take steps to ensure that the procurement process is objective and encourages fair and open competition
4
4 4 5 5 4.4 2.66 12 ORDA manages the close out financially, complete all required
deliverables and clarify plans for any equipment or other inventory purchased with USG funds
4
5 5 5 5 4.8 1.66
59 | P a g e
C. Program Management
Respondents' Code and response
Average Rank
Baseline Average Rank
No. Description Code 1
Code 2 Code 3
Code 4
Code 5
1 The technical and management capacity of the NGO has improved and it is ready to engage directly with donors, to enhance its capacity to deliver development results.
4
4 4 3 4 3.8 3.69 2 ORDA operates in partnership with local community
organizations, NGOs and private sectors. 5 5 4 4 4 4.4 4.38
3 Capacity building policy and guideline are put in place to enhance the technical and management capacity of staffs 4
4 4 4 4 4 2.69 4 Capacity building assessments are used as baseline to
identify capacity gaps and to develop the CB plan 4 4 4 3 3 3.6 2.69
5 The capacity assessment tools are used to rigorously track CB progress and compare the outcomes against indicators 4 5 3 2 3 3.4 2.79
6 The organization has vibrant DME framework in place as a system critical to carrying out a project effectively and efficiently and boosting accountability to beneficiaries, donors and other stakeholders.
4
4 4 3 4 3.8 3.07 7 The organization uses DME tools to measure project
performance(project is on the right track, on time and on target)
5 4 4 3 3 3.8 3.3
8 Service quality standard is instituted for activities as means of quality assurance. 5
4 4 2 3.75 2.76 9 The program staffs follow up and monitor that funds were
used as intended, and the project/program was implemented as planned and learns whether the program made a difference.
4
3 5 3 4 3.8 3.46 10 The program documents are constructed by including
essential DME elements(baseline, targets, result chains, implementation modalities & work plan , monitoring milestones, evaluation, accountability and learning mechanisms
4
3 4 3 3 3.4 3.38 11 The DME staffs regularly monitor and follow up projects,
provide technical support to staffs and assist the team to solve problems on spot.
4 4 4 3 3 3.6 3.15
12 ORDA is mapping and updating the potential donors with their profiles, contact 3.0 address, interest areas, etc
5
3 3 3 3.5 3 13 Program staffs understand and align with the USG
standards and cost principles, allowable costs and are properly documenting them.
4
2 4 2 3 3 3.07 14 Program managers support technical staffs to prepare work
plan and assign to each Program staff with specific duties and timeframe and monitor the work performance accordingly
5
3 4 3 4 3.8 3.53
60 | P a g e
15 The program team holds regular meetings to review the progress, challenge and take timely correction in the implementation process
5 3 4 3 4 3.8 3.2
16 ORDA makes realistic promises and delivers on them: it doesn’t compromise the quality of the work for the sake of speed.
-
3 4 3 3 3.25 3.46 17 ORDA uses donor funds and implements the program as
described in the proposal; notifies the donor of any needed alterations (for example, changes in scope, location of work, target audience) to its work right away to get guidance on how the donor would like it to proceed.
4
4 4 3 4 3.8 3.84 18 Sharing achievements, recognize and give credit to donors:
ORDA can acknowledge the contribution of donors and disseminates using different media sources to publicize program results broadly and through a variety of media: newspapers, radio, websites, social media, conferences, meetings, special events
4
3 4 3 3 3.4 3.61 19 ORDA has the experience of hosting visitors and taking
opportunities to showcase of programs in order to build its reputation and image
5
3 3 3 4 3.6 3.38 20 ORDA complies with the USAID environmental requirements
and environmental impact assessment, 5 3 4 3 3 3.6 3.46 21 ORDA has the capacity and experience to conduct
environmental impact assessment 5 5 4 3 3 4 3.2 22 ORDA has clear policy/ strategy for engaging the
communities in its programs 5 4 4 3 3 3.8 3.23 23 ORDA’s programming approaches are participatory, right
based, conflict sensitive, gender sensitive, environmentally friendly, etc.
4
5 4 3 3 3.8 3.61 24 The semiannual/annual activity and financial reports are
complete, consistent, accurately describes program deliverables with success stories and submitted within due dates.
5
4 4 3 3 3.8 3.3 25 Reports are prepared by comparing the plan with
accomplishments; budget and the work plan are taken as baseline for comparison.
4 3 5 4 4 4 3.76
26 Changes made on activities and budgets are known before the report is issued 4 4 4 3 4 3.8 3.69
27 The performance report provides a balanced look at the program, both in terms of progress as well as setbacks.
4 4 4 3 4 3.8 3.69
28 Organizational learning and reflections are conducted to enhance program and organizational effectiveness 4 4 3 2 3 3.2 2.92
61 | P a g e
D. Procurement Team
Area of focus
No. Questions/descriptions Code 1
Code 2
Code 3
Code 4
Code 5
Code 6
Average Rank
Operational Policies, procedures and systems
1 Different written operational procedures are put in place and fully used for effective procurement management
4
5 4 4 5 4 4.33 2 The operational policies and procedures are
prepared in a manner that is easy for non-procurement staff to understand and apply
4
4 3 4 4 4 3.83 3 The operational policies and procedures are very
accessible to all staff members of the department 4
5 4 5 4 4 4.33 4 ORDA has procurement policy and the policy is
adequately supporting the needs of the Organization (procurement responsibilities, procurement planning, competition, exceptions, award, delivery and inspection, documentation, inventory, etc.)
5
5 4 5 5 5 4.83 5 The procurement policies address donor specific
procurement regulation (For USAID-funded projects, these include: code of ethics; listing of restricted and ineligible goods; source and origin restrictions; verification of supplier eligibility through the Excluded Parties List System [EPLS] and State Department terrorist watch list, approval requirements
4
4 3 2 3 4 3.33 6 ORDA has prepared procurement plan which is
consistent with Organizational Plan and it is regularly updated?
4
5 2 4 4 4 3.83 7 The procurement manual of ORDA entertain the
procurement policy and procedures of USAID 4
3 5 4 4 3.33 8 The purchase department at ORDA Head Quarter
monitors and provides technical support to help the project adhere to the procedures
4
5 4 3 3 3 3.67 9 ORDA manage to record list of allowable and
non-allowable items in the procurement policy document
4
4 3 3 3 4 3.50 Staff
knowledge with
USAID
10 All staff are trained on USAID procurement compliance procedure and this helped them to become familiar with USAID procurement compliance procedures
3
3 2 3 2 3 2.67
62 | P a g e
compliance to logistic
and commodity manageme
nt
11 All purchase manager, senior management and project staffs and purchasers have full understanding of the prohibited items to purchase using the USAID fund
4
4 4 3 3 3 3.50 Baseline
Information
12 ORDA management is trying to solve problems of purchases associated with the difference in the budget years of Donors which leads to fragmentation of purchase request and disruption of the plan
4
5 4 5 3 5 4.33 13 ORDA adopt code of conduct to be applied to the
staff engaged in the procurement of goods and services and this code of conduct is very helpful in effectively managing the procurement process
4
5 4 5 4 4 4.33
2. Focused Group Discussion (FDG) Participant list
FGD – O1 Human Resource Management Team Name Sex Position
Mengisit Gashaw M Personnel and Insurance Admin officer
Asmarech Frede F Archive Head
Degarge Gashaw M General Service Head
Agegnehu Bezie M Personnel Data Encoder
Abeba Mekonnen F Human Resource Admin Officer
Mekonnen Tilahun M Human Resources Development Management Head
Dejen Tarke M Capacity Building and HR Officer
Siradink Fetene F Personnel and Pension Admin Officer
63 | P a g e
FGD -02 Financial Management Team
Name Sex Position
Tezeru Getie F Program Accountant
Tedla Tefera M Audit Manager
Kiber Tigabu M Finance Manager
Habtamu Yilak M Program Accountant
Mekonnen Defar M Program Accountant
Likinu Alemnehe M Program Accountant
Kasahun Yimer M Finance Manager
Goshu Kesi M Finance Director
FGD- 03 Properties and Resource Management Team
Wederyelesh Degene F Property Admin officer
Habtamu Ashagre M Commodity Accountant
Demewa Tadesse M Transport Officer
Kassa Tilahun M Property and Transport Manager
Mengistu Mehertie M Property Administration officer
FGD-04 Business Development Action Research Program (BDARP) Team
Name Sex Position
Hileleul Admasie M BDARP Manager
Sitotaw Zewdie M BDARP – MLE officer
Dires Admas M MEL Officer
Abebe Beyene M Grant Management Officer
Meaza Tigabie F Grant Management Officer
Shimelis Mohammed M BDARP –Director
Ayana Molla M M and E and Data Base Officer
64 | P a g e
FGD- 05 Senior Management Team
Name Sex Position
Dr. Amlaku M Executive Director
Dejene M
Eshete Gelagaye M
FGD- 06 Procurement Management Team
Name Sex Position
Yalelete Admas M Procurement Officer
Melkamu Zena M Procurement Officer
Sewalem Kassahun M Procurement Officer
Simachew Bizuayehu M Procurement Officer
Bayih Berie M Procurement Officer
Mikir Tesfahun M Procurement Manager
FGD- 07 FHE Head Quarter Staff
Name Sex Position
Gossa Turfassa M Commodity Manager
Getahun Shebeshi M Deputy Chief of Party
Fassil Setargie M Program Manager
Azeb Debebe F Compliance Manager
Tesfaye Legesse M Title II Program Manager
Yohannes Belihu M Design, Monitoring and Evaluation Manager
Hiwot Getachew F Operations Director
65 | P a g e