DEDEAUX ROAD WIDENING – PHASE I (from Three Rivers Road to Dede Drive)
$4.5M budget
15 month construction period
6-7-16
May 17 – Office Review of construction plans with MDOT - COMPLETE
June 17 – Complete MDOT Revisions and begin preparing P,S & E Assembly of 17 checklist items.
June 30 – Submit full P,S & E Assembly to MDOT for final approval.
+ - August 19 – MDOT completes review of P,S & E Assembly and authorizes advertisement for bid.
+ - October 7 – Receive Bids for project.
+ - December 7 - MDOT concurs with award of project.
+ - December 10 – Contracts are sent to low bidder for bonds and signatures.