DEDEAUX ROAD WIDENING – PHASE I (from Three Rivers Road to Dede Drive) $4.5M budget 15 month construction period 6-7-16 May 17 – Office Review of construction plans with MDOT - COMPLETE June 17 – Complete MDOT Revisions and begin preparing P,S & E Assembly of 17 checklist items. June 30 – Submit full P,S & E Assembly to MDOT for final approval. + - August 19 – MDOT completes review of P,S & E Assembly and authorizes advertisement for bid. + - October 7 – Receive Bids for project. + - December 7 - MDOT concurs with award of project.

Dedeaux Rd Status Report 6-7-16

Embed Size (px)

DESCRIPTION

Report from Billy Waits, Waggoner Engineering, on progress of Dedeaux Road Widening Project Phase I.

Citation preview

Page 1: Dedeaux Rd Status Report 6-7-16

DEDEAUX ROAD WIDENING – PHASE I (from Three Rivers Road to Dede Drive)

$4.5M budget

15 month construction period

6-7-16

May 17 – Office Review of construction plans with MDOT - COMPLETE

June 17 – Complete MDOT Revisions and begin preparing P,S & E Assembly of 17 checklist items.

June 30 – Submit full P,S & E Assembly to MDOT for final approval.

+ - August 19 – MDOT completes review of P,S & E Assembly and authorizes advertisement for bid.

+ - October 7 – Receive Bids for project.

+ - December 7 - MDOT concurs with award of project.

+ - December 10 – Contracts are sent to low bidder for bonds and signatures.