Proj : 1460-403-11-111
PM : KamaruddinDWP Thickener
1
OVERALL PROJECT STATUSMINIMUM REQUIREMENT SCOPE
Completion Date CostCurrent Approval 31-Dec-14 (IFR) $ 9,811,000Current Forecast 31-Dec-14 $ 23,403,095
This Week To DatePlanned 2.23% 90.55% (IFR)Earned 2.61% 88.91%
Continue progress at DWP Thickener Project
Continue sandblast and painting inside Thickener tank
Continue pulling cable above pipe rack
Proj : 80108031
PM : KamaruddinPortsite VPA #2 (Building)
2
OVERALL PROJECT STATUS Completion Date CostCurrent Approval 31-Jul-2015 $ 32,926,000Current Forecast 7-Aug-2015 $ 32,434,052
This Week To DatePlanned 1.22% 42.71%Earned 0.00% 39.90%
VPA Building 2nd floor VPA Building E-house preparation before energize
Note: No progress within this week due to batchplant at Portsite breakdown since 18 November 2014 and resources allocation except civil crew are dedicated to DWP Thickener project.