2
Proj : 1460-403- 11-111 PM : Kamaruddin DWP Thickener 1 OVERALL PROJECT STATUS MINIMUM REQUIREMENT SCOPE Completion Date Cost Current Approval 31-Dec-14 (IFR) $ 9,811,000 Current Forecast 31-Dec-14 $ 23,403,095 This Week To Date Planned 2.23% 90.55% (IFR) Earned 2.61% 88.91% Continue progress at DWP Thickener Project Continue sandblast and painting inside Thickener tank Continue pulling cable above pipe rack

Dec 22 2014 CSLL

Embed Size (px)

Citation preview

Page 1: Dec 22 2014 CSLL

Proj : 1460-403-11-111

PM : KamaruddinDWP Thickener

1

OVERALL PROJECT STATUSMINIMUM REQUIREMENT SCOPE

  Completion Date CostCurrent Approval 31-Dec-14 (IFR) $ 9,811,000Current Forecast 31-Dec-14 $ 23,403,095

  This Week To DatePlanned 2.23% 90.55% (IFR)Earned  2.61% 88.91% 

Continue progress at DWP Thickener Project

Continue sandblast and painting inside Thickener tank

Continue pulling cable above pipe rack

Page 2: Dec 22 2014 CSLL

Proj : 80108031

PM : KamaruddinPortsite VPA #2 (Building)

2

OVERALL PROJECT STATUS  Completion Date CostCurrent Approval 31-Jul-2015 $ 32,926,000Current Forecast 7-Aug-2015 $ 32,434,052

   This Week To DatePlanned 1.22% 42.71%Earned 0.00% 39.90%

VPA Building 2nd floor VPA Building E-house preparation before energize

Note: No progress within this week due to batchplant at Portsite breakdown since 18 November 2014 and resources allocation except civil crew are dedicated to DWP Thickener project.