    S.l.No.

    Description Work Program of January 1,2012 Achievement of December 31,2011 Remarks

    300mm (16No) pipe Installation

    Base CC (15rm) Side CC (30 rm)

    CC casting of 2 nos gully hole and 1 no manhole

    Singles Laying 2nd layer(520mm thick) / Ch 78-137 Singles Laying 1st layer(520mm thick)/Ch 78-137

    Rebar fabrication of longitudinal sleepers (Ch 0-78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)in progress

    3 Pre-cast pile driving(Seg-1A) Identify pile for load test All materials of load test reached at site and preparationin progress

    4 Segment 2A Settlement Record Settlement Record in progress for 70th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress

    Back filling at Navy gate Back filling at Navy gate in progress

    Earth excavation (CH 1000-1040) Earth excavation (CH 1000-1040) in progress

    Wall casting at Navy gate (Ch 1100-1125) /3rd lift/yard side Rebar fabrication executed

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-400)

    Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress

    9 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    10 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress

    11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    12 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    13 RCC Drainage Pipe Concrete pouring(500mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)

    14 PDB Relocation Old pole removing Old pole removing in progress

    15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=11,800 Nos)

    6

    Rail Relocation8

    Segment-2

    Open Deep Drain7

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of January 1,2012

    Segment 15

    Yard Drainage(Seg-1A)1

    RMG (Seg-1A)2

  • 8/13/2019 Daily Program April-2012

    2/59

    S.l.No.

    Description Work Program of January 2,2012 Achievement of January 1,2011 Remarks

    CC Casting of Cable trench. Base CC (15rm)CC Casting of 1 no manhole. CC casting of 2 nos gully hole

    Singles Laying 2nd layer(520mm thick) / Ch 78-137

    Singles Laying 2nd layer(520mm thick) / Ch 78-137in progress

    Rebar fabrication of longitudinal sleepers (Ch 0-78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)in progress

    3 Pre-cast pile driving(Seg-1A) Preparation of load test Preparation of load test in progress

    4 Segment 2A Settlement Record Settlement Record in progress for 71th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress

    Back filling at Navy gate Back filling at Navy gate in progress

    CC Casting (CH 1000-1040) Earth excavation finished (CH 1000-1040)

    Earth Excavation (Ch 1125-1140)Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yardside

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600)

    9 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    10 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress

    11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    12 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    13 RCC Drainage Pipe Concrete pouring(800mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)

    14 PDB Relocation Old pole removing Old pole removing in progress

    15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,000 Nos)

    17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 2,2012

    Segment 15

    1

    RMG (Seg-1A)2

    6

    Rail Relocation8

    Segment-2

    Open Deep Drain7

  • 8/13/2019 Daily Program April-2012

    3/59

    S.l.No.

    Description Work Program of January 3,2012 Achievement of January 2,2011 Remarks

    Base CC (15rm) Earth excavation (15rm)Singles Laying 2nd layer(520mm thick) / Ch 78-137

    Singles Laying 2nd layer(520mm thick) / Ch 78-137in progress

    Rebar fabrication of longitudinal sleepers (Ch 0-78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)in progress

    3 Pre-cast pile driving(Seg-1A) Preparation of load test Preparation of load test in progress

    4 Cable Trench (Seg-1A) CC Casting Earth Excavation executed.

    5 Segment 2A Settlement Record Settlement Record in progress for 72th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress

    Back filling at Navy gate Back filling at Navy gate in progress

    Rebar fabrication of Base (CH 1000-1040) CC Casting (CH 1000-1040)

    Earth Excavation (Ch 1125-1140)Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yardside

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    13 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    14 RCC Drainage Pipe Concrete pouring(800mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)

    15 PDB Relocation Old pole removing Old pole removing in progress

    16 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    17 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,200 Nos)

    18 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 3,2012

    Segment 16

    Yard Drainage1

    RMG (Seg-1A)2

  • 8/13/2019 Daily Program April-2012

    4/59

    S.l.No.

    Description Work Program of January 4,2012 Achievement of January 3,2011 Remarks

    Side CC (30rm) Base CC executed (30rm)

    Pipe Installation 30 rm(300mm dia)

    Wall casting of 01 No Manhole Base Casting of 02 Nos Gully hole & 01 No Manhole

    Ballast Laying (300mm thick) / Ch 78-137Singles Laying 2nd layer(520mm thick) / Ch 78-137finished

    Rebar fabrication of longitudinal sleepers (Ch 0-78)

    Rebar fabrication of longitudinal sleepers(Ch 0-78)in progress

    3 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sand bagging for load test in progress

    4 Cable Trench (Seg-1A) CC Casting Earth Excavation executed.5 Segment 2A Settlement Record Settlement Record in progress for 73th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Pre-cast Bracing installation

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress(500 sqm)

    Back filling at Navy gate Back filling at Navy gate in progress Base casting (CH 1000-1040) Rebar fabrication of Base (CH 1000-1040)

    Bracing fixing (6rm)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Electric Sub station Shuttering & Rebar binding of slab (2nd portion)Shuttering & Rebar binding of slab (2nd portion) inprogress

    12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress13 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    14 RCC Drainage Pipe Concrete pouring(800mm=03 Nos,900mm=02 Nos) Concrete Pouring (800mm=03Nos & 900mm=02 Nos)

    15 PDB Relocation Old pole removing Old pole removing in progress

    16 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    17 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=10,500 Nos)

    18 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 4,2012

    Segment 16

    RMG (Seg-1A)2

    Yard Drainage1

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

  • 8/13/2019 Daily Program April-2012

    5/59

    S.l.No.

    Description Work Program of January 7,2012 Achievement of January 6,2011 Remarks

    1 Yard DrainageBase Casting of 02 Nos Gully hole & 01 No Man

    hole.

    Rebar binding of Base (02 Nos Gully hole & 01 No Man

    hole)

    Shingles Laying (180mm thick) / Ch 78-137 Ballast layer compaction (300mm thick) / Ch 78-137 finished

    Longitudinal sleeper casting (Ch 0-10)Rebar fabrication of longitudinal sleepers(Ch 0-10)finished.

    3 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sand bagging for load test in progress

    4 Sheet Pile Driving Preparation of Pile shifting to bank.

    5 Cable Trench (Seg-1A) CC Casting CC Casting executed.

    6 Segment 2A Settlement Record Settlement Record in progress for 77th day

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    300mm sand blanket laying 300mm sand blanket laying in progress(500 sqm)

    CC Casting (Outlet point) Soling executed.

    Wall casting / Port side/1st lift (CH 1015-1040) Rebar fabrication executed (CH 1015-1040)Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    12 Electric Sub station Shuttering & Rebar binding of slab (2nd portion)Shuttering & Rebar binding of slab (2nd portion) inprogress

    13 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    14 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)

    15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=10,500 Nos)

    17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    8

    Rail Relocation10

    Segment-2

    Open Deep Drain9

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 7,2012

    Segment 17

    RMG (Seg-1A)2

  • 8/13/2019 Daily Program April-2012

    6/59

    S.l.No.

    Description Work Program of January 9,2012 Achievement of January 8,2011

    15 m Base CC casting (300mm) 15m Earth Excavation

    Wall Casting of 03 Nos Gully hole . Rebar binding executed (wall of 03 Nos Gully hole)

    Shingles Laying (180mm thick) / Ch 78-137Shingles Laying (180mm thick) / Ch 78-137 inprogress

    Longitudinal sleeper casting (Ch 0-10)Rebar fabrication of longitudinal sleepers(Ch 0-10)in progress.

    3 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    4 Water Supply Line Leak test of 50m pipe (250mm dia) 50 m pipe welding completed (250mm dia)5 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving FDD test executed at 300mm sand blanket

    Wall casting / Navy side/2nd lift (CH 1015-1040) Wall casting / Port side/1st lift (CH 1015-1040)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Electric Sub station Slab casting of 2nd portion executed

    12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,400 Nos)

    15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 9,2012

    Segment 16

    RMG (Seg-1A)2

    Yard Drainage(Seg-1A)1

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

  • 8/13/2019 Daily Program April-2012

    7/59

    Remarks

    Assistant Engineer NCT Back-up/CPA

  • 8/13/2019 Daily Program April-2012

    8/59

    S.l.No.

    Description Work Program of January 10,2012 Achievement of January 9,2011

    300mm Pipe installation(15rm) 15 m Base CC casting executed.

    Wall Casting of 03 Nos Gully hole and base castingof 02 Nos Gully hole.

    Wall Casting of 03 Nos Gully hole executed

    Rolling of Shingles Layer (180mm thick) / Ch 78-137 Shingles Laying (180mm thick) / Ch 78-137 finished

    Rebar fabrication of longitudinal sleepers(Ch 0-10) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 0-10)in progress.

    3 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    4 Water Supply Line Leak test of 50m pipe (250mm dia) 50 m pipe welding completed (250mm dia)5 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)

    Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Earth Excavation (CH 1040-1060)

    Wall casting / Yard side/2nd lift (CH 1015-1040) Wall casting / Navy side/2nd lift (CH 1015-1040)executed.

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=11,300 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    7

    Rail Relocation9

    Segment-2

    Open Deep Drain8

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 10,2012

    Segment 16

    RMG (Seg-1A)2

    Yard Drainage(Seg-1A)1

  • 8/13/2019 Daily Program April-2012

    9/59

    Remarks

    Assistant Engineer NCT Back-up/CPA

  • 8/13/2019 Daily Program April-2012

    10/59

    S.l.No.

    Description Work Program of January 14,2012 Achievement of January 13,2011

    1 Yard Drainage(Seg-1A) Side CC Casting/30rm/300mm dia pipe Shuttering executed

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)in progress.

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mmdia

    Painting of Pipe & wrapping by Polythene/250mm dia inprogress.

    6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (40,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Base Casting (CH 985-1015) Rebar binding executed.

    Wall casting / Yard side/2nd lift (CH 1015-1040) Rebar binding executed.

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (02 Nos) in progress

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,300 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 14,2012

    8

    Rail Relocation10

    Segment-2

    Open Deep Drain9

  • 8/13/2019 Daily Program April-2012

    11/59

    Remarks

    Assistant Engineer NCT Back-up/CPA

  • 8/13/2019 Daily Program April-2012

    12/59

    S.l.No.

    Description Work Program of January 15,2012 Achievement of January 14,2011

    Side CC Casting/30rm/300mm dia pipe Shuttering executed

    Wall casting of 03 Nos Gully hole and 01 No Manhole

    Shuttering executed

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)in progress.

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm

    dia

    Painting of Pipe & wrapping by Polythene/250mm dia in

    progress.6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Base Casting (CH 1000-1015) Base Casting (CH 985-1000)

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (06 Nos) in progress

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Rebar fabrication and Shuttering executed.

    12 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,200 Nos)

    15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 15,2012

    8

    Rail Relocation10

    Segment-2

    Open Deep Drain9

    Yard Drainage(Seg-1A)1

  • 8/13/2019 Daily Program April-2012

    13/59

    Remarks

    Assistant Engineer NCT Back-up/CPA

  • 8/13/2019 Daily Program April-2012

    14/59

    S.l.No. Description Work Program of January 16,2012 Achievement of January 15,2011 Remarks

    Side CC Casting/30rm/300mm dia pipe

    Wall casting of 01 No Gully hole and 01 No Manhole

    Wall casting of 02 Nos Gully hole and 01 No Man hole .

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-30) in progress.

    Rebar fabrication of longitudinal s leepers(Ch 20-30)in progress.

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mmdia

    Painting of Pipe & wrapping by Polythene/250mm dia inprogress.

    6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving PVD Driving in progress

    Wall casting 1st lift(CH 985-1015) Base Casting (CH 1000-1015)

    Pre-cast Bracing Casting (06 Nos)Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rai l bit f ixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    11 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Rebar fabrication and Shuttering executed.

    12 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=13,600 Nos)

    15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    10 Rail Relocation

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 16,2012

    1 Yard Drainage(Seg-1A)

    8 Segment-2

    9 Open Deep Drain

  • 8/13/2019 Daily Program April-2012

    15/59

    S.l.No.

    Description Work Program of January 17,2012 Achievement of January 16,2011 Remarks

    02 Nos 300mm dia pipe,01 No 700mm dia pipefixing.

    Shuttering & Rebar fabrication of 02 Nos Gully hole. Wall casting of 01 No Gully hole and 01 No Man hole

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-30) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 20-30)in progress.

    3 Seg-1A(mosque portion) Sand filling & Soling work Sand filling & Soling work in progress

    4 Sub-station Building Plaster work Plaster work in progress.

    5 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    6 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mmdia

    Painting of Pipe & wrapping by Polythene/250mm dia inprogress.

    7 Cable Trench (Seg-1A) Plastering of wall.

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    9 Segment-2 Clearing & Grubbing Clearing & Grubbing in progress

    Soling & CC work (CH 1015-1030) Earth Excavation executed.

    Wall casting 1st lift(CH 985-1015) Shuttering & Rebar fabrication executed.

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (06 Nos)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rai l bit fixing (Ch 0-600) Sleepers & Rail bi t fixing in progress (Ch 0-600)

    12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting (10 Nos) in progress.

    13 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    15 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,250 Nos)

    16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    11 Rail Relocation

    Open Deep Drain10

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 17,2012

    1 Yard Drainage(Seg-1A)

  • 8/13/2019 Daily Program April-2012

    16/59

    S.l. No. Description Work Program of January 18,2012 Achievement of January 17,2011 Remarks

    Side CC Casting of 10rm 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing.

    Shuttering & Rebar fabrication of 02 Nos Gully hole.Shuttering & Rebar fabrication of 02 Nos Gully hole and02 Nos Manhole.

    2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    3 Seg-1A(mosque portion) Sand filling & Soling work Sand filling & Soling work in progress

    4 Sub-station Building Plaster work Plaster work in progress.

    5 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    6 Water Supply Line/Seg-1A Painting of Pipe & wrapping by Polythene./250mmdia Painting of Pipe & wrapping by Polythene/250mm dia inprogress.7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    150mm local sand laying 150mm local sand laying in progress

    200mm sand blanket laying 200mm sand blanket laying in progress

    Rebar fabrication of Base (CH 1015-1030) Soling & CC work (CH 1015-1030)

    Rebar fabrication of Wall 1st l ift(CH 985-1015)/Navyside. Wall casting 1st lift(CH 985-1015)/Yard Side

    Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (05 Nos)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bi t fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.

    13 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress

    14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    15 Interlocking Block ILB production (Quantity=13000 Nos)16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    11 Rai l Relocation

    Open Deep Drain10

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 18,2012

    1 Yard Drainage(Seg-1A)

    Segment-29

  • 8/13/2019 Daily Program April-2012

    17/59

    S.l. No. Description Work Program of January 20,2012 Achievement of January 19,2011 Remarks

    Rebar fabrication of 03 Nos Gully hole

    Wall Shuttering of 02 Nos Man hole Wall casting of 02 Nos Gully hole

    Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress.

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    Pre-cast sleepers shifting to Seg-1

    3 Seg-1A(mosque portion) Soling work Soling work in progress

    4 Service Area Sub-base material laying Bed preparation finished

    5 Sub-station Building Plaster work & Parapet shuttering Plaster work & Parapet casting in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mmdia

    Painting of Pipe & wrapping by Polythene/250mm dia inprogress.

    8 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    9 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    150mm local sand laying 150mm local sand laying in progress200mm sand blanket laying 200mm sand blanket laying in progress

    Shuttering of wall (CH 1015-1030) Base casting (CH 970-990)

    Back filling(CH 990-1015)/Navy side. Wall casting 1s t li ft(CH 990-1015)/Navy Side

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rai l bit fixing in progress (Ch 0-600)

    13 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.

    14 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=11000 Nos)

    17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    12 Rail Relocation

    Open Deep Drain11

    Segment-210

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 20,2012

    1 Yard Drainage(Seg-1A)

    RMG Track(Seg-1A)2

  • 8/13/2019 Daily Program April-2012

    18/59

    S.l. No. Description Work Program of January 21,2012 Achievement of January 20,2011 Remarks

    Rebar fabrication of 03 Nos Gully hole Rebar fabrication of 03 Nos Gully hole in progress

    Wall Shuttering of 02 Nos Man hole Wall Shuttering of 02 Nos Man hole in progress

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress

    3 Seg-1A(mosque portion) Rebar binding of raft foundation. Soling work finished.

    4 Service Area Sub-base material compaction. Sub-base material laying finished.

    5 Sub-station Building Plaster work & Parapet casting. Plaster work & Parapet shuttering.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    PVD Driving 300mm sand blanket compaction finished.

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 2nd lift (CH 990-1015)/Navy Side Earth excavation (CH 950-970)

    Soling & CC (CH 950-970)/Navy side. Back filling(CH 990-1015)/Navy side.

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rai l bit f ixing (Ch 0-600) Sleepers & Rail bit f ixing in progress (Ch 0-600)

    12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.

    13 Road Type-1 Field density test of sub-base. Sub base material placement (2nd layer) finished.

    14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    15 Interlocking Block ILB production (Quanti ty=13000 Nos) ILB production (Quantity=12000 Nos)

    16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-29

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 21,2012

    1 Yard Drainage(Seg-1A)

    11 Rail Relocation

    Open Deep Drain10

    RMG Track(Seg-1A)2

  • 8/13/2019 Daily Program April-2012

    19/59

  • 8/13/2019 Daily Program April-2012

    20/59

    S.l. No. Description Work Program of January 23,2012 Achievement of January 22,2011 Remarks

    1 Yard Drainage (Seg 1A) Man hole wall casting (01 No) Shuttering executed.

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) in progress.Concrete Pouring (CH 0-10)

    3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    4 Service Area Sub-base material laying Sub-base material laying in progress

    5 Sub-sta tion Building Plaster work . Plaster work in progress

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)

    Clearing & Grubbing Clearing & Grubbing in progress

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 1st lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Navy Side

    Earth Excavation (CH 935-950) Soling & CC (CH 950-970)

    Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)

    Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=10500 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 23,2012

    11 Rail Relocation

    Open Deep Drain10

    RMG Track(Seg-1A)2

    Segment-29

  • 8/13/2019 Daily Program April-2012

    21/59

    S.l. No. Description Work Program of January 24,2012 Achievement of January 23,2011 Remarks

    1 Yard Drainage (Seg 1A) Man hole wall casting (01 No)

    Rebar fabrication of longitudinal sleepers(Ch 30-

    40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)

    in progress.3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    4 Service Area Sub-base material laying & compaction Sub-base material laying & compaction in progress

    5 Sub-station Building Plaster work . Plaster work in progress

    6 Segment-2A Surcharge Removing Surcharge Removing in progress.

    7 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    8 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress

    9 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (40,000cft)

    PVD Driving

    200mm sand blanket laying 200mm sand blanket laying in progress

    Wall casting 2nd lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Yard Side

    Earth Excavation (CH 935-950) Earth Excavation (CH 935-950) In progress

    Bracing fixing (06 Nos)

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quanti ty=13200 Nos)

    14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 24,2012

    RMG Track(Seg-1A)2

    Segment-210

    Open Deep Drain11

    NCT BACK UP PROJECT CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    22/59

    S.l.No.

    Description Work Program of January 25,2012 Achievement of January 24,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    2 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    3 Service Area Sub-base material c ompaction Sub-base material laying finished.

    4 Sub-station Building Plaster work . Plaster work in progress

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    PVD Driving PVD Driving in progress.

    150mm local sand laying. 150mm local sand laying in progress.

    Wall casting 2nd lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Yard Side

    CC ,Soling (CH 935-950) Earth Excavation (CH 935-950)

    Bracing fixing (06 Nos)

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=13000 Nos)

    12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 25,2012

    RMG Track(Seg-1A)1

    Segment-28

    Open Deep Drain9

    NCT BACK UP PROJECT CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    23/59

    S.l.No.

    Description Work Program of January 26,2012 Achievement of January 25,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    2 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.

    3 Service Area Lean concrete casting

    4 Sub-station Building Bricks masonry work

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (42,000cft)8 Segment-2 150mm local sand laying. 150mm local sand laying in progress.

    Wall casting 2nd lift (CH 970-990)/Yard Side

    Rebar binding of Base (CH 935-970) CC ,Soling (CH 935-950)

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=14200 Nos)

    12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of January 26,2012

    RMG Track(Seg-1A)1

    Open Deep Drain9

    NCT BACK-UP PROJECT, CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    24/59

    S.l.No.

    Descrip tion Work Program of January 30,2012 Achievement of January 29,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    2 Yard Drainage Base casting of 03 Nos Gully holes & wallcasting of 01 No Manhole.

    Rebar fabrication and shuttering executed.

    3 Sub-station Building Bricks masonry work Bricks masonry work in progress.

    FDD Test of 150mm local sand layer

    FDD Test of 200mm sand blanket layer

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.

    6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress

    7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (45,000cft)

    Wall casting 1st lift (CH 955-970)/Navy Side Wall casting 1st lift (CH 935-955)/Navy Side

    9 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    10 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=14200 Nos)

    11 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    NCT BACK UP PROJECT, CHITTAGONGWork Program of January 30,2012

    RMG Track(Seg-1A)1

    Open Deep Drain8

    Segment-24

    NCT BACK-UP PROJECT, CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    25/59

    S.l.No.

    Description Work Program of February1,2012 Achievement of January 31,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    2 Yard Drainage Net cement finishing of Gully hole.

    Bricks masonry work Bricks masonry work in progress.

    Bricks masonry work of Safety Tank. Bricks masonry work of Safety Tank in progress.

    Settlement plate fixing (08 Nos)

    300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion inprogress.

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.(70,000 cft)

    6 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    7 Road Type-1 Sub-base work

    Wall casting 1st l if t (CH 935-955)/Yard Side Wall casting 1st l if t (CH 955-970)/Yard Side

    9 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    10 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=14,500 Nos)

    11 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Sub-station Building3

    Work Program of February 1,2012

    RMG Track(Seg-1A)1

    Open Deep Drain8

    Segment-24

    NCT BACK-UP PROJECT, CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    26/59

    S.l.No.

    Description Work Program of February 2,2012 Achievement of February 1,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    2 Yard Drainage Net cement finishing of Gully hole. Net cement finishing of Gully hole in progress.

    Bricks masonry work Bricks masonry work in progress.

    Bricks masonry work of Safety Tank. Bricks masonry work of Safety Tank in progress.

    Settlement plate fixing (08 Nos)

    300 mm sand blanket laying at remaining portion. 300 mm sand blanket laying at remaining portion inprogress.

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.(70,000 cft)

    6 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)

    7 Rail Relocation Sub-base work at Navy area (CH 620-820)

    8 Road Type-1 Sub-base work Sub-base work in progress

    Wall casting 2nd lift (CH 950-970)/Navy Side Wall casting 1st lift (CH 935-955)/Yard Side

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=12,500 Nos)

    12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-24

    Sub-station Building3

    Work Program of February 2,2012

    RMG Track(Seg-1A)1

    Open Deep Drain9

  • 8/13/2019 Daily Program April-2012

    27/59

    NCT BACK-UP PROJECT, CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    28/59

    S.l.No.

    Description Work Program of February 6,2012 Achievement of February 5,2011 Remarks

    Rebar fabrication of longitudinal sleepers(Ch 30-40) .

    Rebar fabrication of longitudinal sleepers(Ch 30-40)in progress.

    Net cement finishing of Gully hole.

    Base CC Casting of 300 mm dia pipe (40rm) Earth excavation & Levelling.

    Bricks masonry work & Plastering of Wall.Bricks masonry work & Plastering of Wall inprogress.

    Rebar fabrication & Shuttering of slab of septictank. Bricks masonry work & Plastering completed.

    Base casting of Fuel tank.

    Sunshade Casting Sunshade Casting in progress.

    300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion inprogress.

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)

    6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (60,000cft)

    Commissioning of Relocated Line. Rail fixing at Navy area (CH 620-820) finished.

    8 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.

    Wall casting 3rd lift (CH 950-970)/Navy Side Wall casting 3rd lift (CH 925-950)/Navy Side.

    Bracing fixing (near sub-station)

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=13,500 Nos)

    12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Work Program of February 6,2012

    RMG Track(Seg-1A)1

    Segment-24

    Yard Drainage2

    Rail Relocation7

    Sub-station Building3

    Open Deep Drain9

    NCT BACK-UP PROJECT, CHITTAGONG

  • 8/13/2019 Daily Program April-2012

    29/59

    S.l.No.

    Description Work Program of February 8,2012 Achievement of February 7,2011 Remarks

    Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting (10 Nos)

    Side CC ,40rm(300mm dia pipe) Base CC,40rm

    Bricks masonry work & Plastering of Wall.Bricks masonry work & Plastering of Wall inprogress.

    Slab Casting of Septic tank

    Base casting of Fuel tank

    Sunshade Casting Sunshade Casting in progress.

    300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion in

    progress.5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)

    6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (60,000cft)

    Old line removal

    8 Boundar Wall Bricks masonry work near sub-station

    9 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.

    Wall casting 3rd lift (CH 970-990)/Navy Side Wall casting 3rd lift (CH 950-970)/Navy Side

    Bracing fixing (near sub-station)

    11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    12 Interlocking Block ILB production ILB production in progress.

    13 Dismantling work Navy gate.

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Open Deep Drain10

    Rail Relocation7

    Sub-station Building3

    Segment-24

    Yard Drainage2

    Work Program of February 8,2012

    RMG Track(Seg-1A)1

    NCT BACK-UP PROJECT, CHITTAGONGW k P f F b 9 2012

  • 8/13/2019 Daily Program April-2012

    30/59

    S.l.No.

    Description Work Program of February 9,2012 Achievement of February 8,2011 Remarks

    Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting in progress (10 Nos)

    Side CC ,40rm(300mm dia pipe) Pipe fixing executed.

    Bricks masonry work & Plastering of Wall. Bricks masonry work & Plastering of Wall inprogress.

    Sunshade Casting Sunshade Casting in progress.

    300 mm sand blanket laying. 300 mm sand blanket laying in progress.

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)

    6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (70,000cft)

    Old line removal Old line removal in progress.

    8 Boundar Wall Bricks masonry work near sub-station Bricks masonry work near sub-station in progress.

    9 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.

    Wall casting 3rd lift (CH 970-990)/Navy Side

    Bracing fixing (near sub-station)

    11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    12 Interlocking Block ILB production ILB production in progress.(10,000 Nos)13 Dismantling work Dismantling work at Navy gate. Dismantling work at Navy gate in progress.

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Work Program of February 9,2012

    RMG Track(Seg-1A)1

    Segment-24

    Yard Drainage2

    Rail Relocation7

    Sub-station Building3

    Open Deep Drain10

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 11 2012

  • 8/13/2019 Daily Program April-2012

    31/59

    S.l.No.

    Description Work Program of February 11,2012 Achievement of February 10,2011 Remarks

    Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting in progress (10 Nos)

    Side CC ,40rm(300mm dia pipe) Pipe fixing executed.

    CC Castng of 2 Nos Gullyhole & 01 No Manhole.

    Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    Sunshade Casting Sunshade Casting in progress.

    4 Sub-base work (Seg-1A) Water spraying & Rolling Shingles laying (200mm)

    5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)

    6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (70,000cft)

    Old line removal Old line removal in progress.

    8 Boundar Wall Plastering of wall near sub-station Bricks masonry work finished near sub-station .

    9 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.

    Wall casting 3rd lift (CH 990-1010)/Navy Side Wall casting 3rd lift (CH 990-1010)/Navy Side

    Bracing fixing (near sub-station)

    11 Laboratory / Field Test FDD test of 300 mm sand blanket at Seg-2 Regular Test (ILB/Cylinder)12 Interlocking Block ILB production ILB production in progress.(10,000 Nos)

    13 Dismantling work Dismantling work at Navy gate. Dismantling work at Navy gate in progress.

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Yard Drainage2

    Work Program of February 11,2012

    RMG Track(Seg-1A)1

    Sub-station Building3

    Open Deep Drain10

    Rail Relocation7

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 12 2012

  • 8/13/2019 Daily Program April-2012

    32/59

    S.l.No.

    Description Work Program of February 12,2012 Achievement of February 11,2011 Remarks

    Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting in progress (10 Nos)

    Wall casting of 01 No Manhole Side CC ,40rm(300mm dia pipe)

    CC Castng of 2 Nos Gullyhole

    Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    Sunshade Casting Sunshade Casting in progress.

    4 Sub-base work (Seg-1A) Water spraying & Rolling Shingles laying (200mm)

    5 Service Area Lean concrete casting(18 Mpa)

    6 Segment-2 PVD Driving 300mm sand blanket completed.

    7 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)

    8 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (70,000cft)

    Old line removal Old line removal in progress.

    10 Boundar Wall Plastering of wall near sub-station Bricks masonry work finished near sub-station .

    11 Road Type-2 Improved Sub-grade Improved Sub-grade work in progress.

    Shuttering work (CH 1010-1030)/Navy Side Wall casting 3rd lift (CH 990-1010)/Navy Side

    Bracing fixing (near sub-station)

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production ILB production in progress.(11,000 Nos)

    15 Dismantling work Dismantling work at Navy gate. Dismantling work at Navy gate in progress.

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Sub-station Building3

    Open Deep Drain12

    Rail Relocation9

    Work Program of February 12,2012

    RMG Track(Seg-1A)1

    Yard Drainage2

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 12,2012

  • 8/13/2019 Daily Program April-2012

    33/59

    S.l.No.

    Description Work Program of February 16,2012 Achievement of February 15,2011 Remarks

    Wall casting of 01 No Gully hole.

    CC Castng of 4 Nos Gullyhole

    2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    3 Segment-1 Surcharge material placement (70,000 cft) Surcharge material placement in progress(60,000cft)

    Surcharge material placement Surcharge material placement in progress.

    PVD Driving PVD Driving in progress.

    5 Sub-base work (Seg-1A) RTG Track area

    6 Service Area Lean concrete casting(18 Mpa) Lean concrete casting(18 Mpa) in progress.

    7 Seg-2A Soil boring

    8 Road Type-1 Sub-base work. Sub-base work in progress

    9 Open Drain Work Soling,CC work (CH 1040-1050) Earth excavation executed.

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production ILB production in progress.(13,000 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-24

    g y ,

    Yard Drainage1

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 18,2012

  • 8/13/2019 Daily Program April-2012

    34/59

    S.l.No.

    Description Work Program of February 18,2012 Achievement of February 17,2011 Remarks

    1 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    2 RMG Track(Seg-1A) Concrete pouring (16 cum) Rebar binding and shuttering executed.

    3 Segment-1 Surcharge material placement (70,000 cft)Surcharge material placement in progress(60,000cft)

    4 Pile Load Test(up lift) Up lift test for driven pre-cast pile (Seg-1A)

    Surcharge material placement Surcharge material placement in progress.

    PVD Driving PVD Driving in progress.

    6 Sub-base work (Seg-1A) Sub-base work for RTG Track Sub-base work for RTG Track in progress.

    7 Service Area Lean concrete casting(18 Mpa) Lean concrete casting(18 Mpa) in progress.

    8 Seg-2A Soil boring for sample collection Soil boring for sample collection in progress.

    9 Road Type-1 Sub-base work. Sub-base work in progress

    10 Open Drain Work Bracing welding (near Navy gate.) Earth excavation executed.

    Wall casting CH 920-940/3rd lift/Yard side

    Wall casting CH 940-950/1st lift/Navy side

    11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    12 Interlocking Block ILB production ILB production in progress.(12,540 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-25

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 19,2012

  • 8/13/2019 Daily Program April-2012

    35/59

    S.l.No.

    Description Work Program of February 19,2012 Achievement of February 18,2011 Remarks

    Wall casting of 01 No Gully hole.

    CC Castng of 4 Nos Gullyhole

    Side CC (8rm)

    2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    3 RMG Track(Seg-1A) Rebar binding & Shuttering. Concrete pouring (16 cum)

    4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress

    5 Segment-1 Settlement Record Settlement Record in progress.

    Surcharge material placement Surcharge material placement in progress.PVD Driving PVD Driving in progress.

    7 Seg-2A Soil boring for sample collection Soil boring for sample collection in progress.

    8 Road Type-1 Existing Road excavation

    9 Open Drain Work Bracing Fixing (near Navy gate.) Earth excavation executed.

    Wall casting CH 920-940/3rd lift/Yard side

    Wall casting CH 940-950/1st lift /Yard side Wall casting CH 940-950/1st l if t/Navy side

    10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    11 Interlocking Block ILB production ILB production in progress.(12,400 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-26

    Yard Drainage1

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 22,2012

  • 8/13/2019 Daily Program April-2012

    36/59

    S.l.No.

    Description Work Program of February 22,2012 Achievement of February 21,2011 Remarks

    Rebar binding of Base (04 Nos Single Gully hole)

    2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    3 RMG Track(Seg-1A) Rebar binding & Shuttering. Rebar binding & Shuttering in progress.

    4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress

    5 Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting.

    6 Segment-1 Settlement Record Settlement Record in progress.

    Surcharge material placement Surcharge material placement in progress.

    8 Road Type-1 Sub-base work Sub-base work in progress

    9 Open Drain Work Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress

    Wall casting CH 900-920/2nd lift/Yard side Rebar fabrication & Shuttering executed.

    10 Truck Parking Area Sub-grade Preparation

    11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    12 Interlocking Block ILB production ILB production in progress.(11,800 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer

    NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-27

    Yard Drainage1

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of February 23,2012

  • 8/13/2019 Daily Program April-2012

    37/59

    S.l.No.

    Description Work Program of February 23,2012 Achievement of February 22,2011 Remarks

    Base casting (04 Nos Single Gully hole) Rebar binding of Base (04 Nos Single Gul ly hole)

    2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    3 RMG Track(Seg-1A) Rebar binding & Shuttering. Rebar binding & Shuttering in progress.

    4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress

    5 Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. 200mm thick lean concrete casting in progress.

    6 Segment-1 Settlement Record Settlement Record in progress.

    Surcharge material placement Surcharge material placement in progress.8 Segment-4 150mm local sand compaction 150mm local sand compaction in progress.

    9 Segment-3 Dismantling work Dismantling work in progress.

    10 Road Type-1 Sub-base work Sub-base work in progress

    11 Open Drain Work Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress

    Wall casting CH 900-920/2nd lift/Yard side Rebar fabrication & Shuttering executed.

    12 Truck Parking Area Sub-grade Preparation Sub-grade Preparation in progress.

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14 Interlocking Block ILB production ILB production in progress.(9,500 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-27

    Yard Drainage1

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of March 1,2012

  • 8/13/2019 Daily Program April-2012

    38/59

    S.l.No.

    Description Work Program of March 1,2012 Achievement of February 29,2012 Remarks

    Side CC (02 Nos 800mm dia)

    2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    3 RMG Track(Seg-1A) Concrete Pouring (16cum) Rebar binding & Shuttering in progress.

    4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress

    5 Segment-1 Settlement Record Settlement Record in progress.

    Surcharge material placement Surcharge material placement in progress.

    7 Segment-4 150mm local sand compaction 150mm local sand compaction in progress.

    8 Segment-3 Dismantling work Dismantling work in progress.

    9 Road Type-1 300mm Base course laying.

    10 Open Drain Work Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress

    Wall casting CH 920-930/2nd lift/Yard side Rebar fabrication & Shuttering executed.

    11 Truck Parking Area Sub-grade Preparation Sub-grade Preparation in progress.

    12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    13Interlocking Block (02 Nos

    Plant)ILB production ILB production in progress.(18,400 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Segment-26

    Yard Drainage1

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of March 3,2012

  • 8/13/2019 Daily Program April-2012

    39/59

    S.l.No.

    Description Work Program of March 3,2012 Achievement of March 2,2012 Remarks

    Base CC 30rm ( 300mm dia)

    Wall casting of 02 Nos Manhole & 02 Nos Gully hole.

    2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.

    3 RMG Track(Seg-1A) Pre-cast transverse sleepers fixing Pre-cast transverse sleepers fixing in progress.

    4 Service Area Lean concrete casting(18 Mpa) Lean concrete casting(18 Mpa) in progress.

    5 Cable trench Base Casting Rebar fabrication & Shuttering executed.

    6 RTG Track (Seg-1A) Sub-base work Sub-base work in progress

    7 Segment-1 Settlement Record Settlement Record in progress.

    Surcharge material placement Surcharge material placement in progress.

    9 Segment-3 Dismantling work Dismantling work in progress.

    10 Road Type-1 300mm Base course laying. 300mm Base course laying.in progress

    Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress

    Shuttering of wall CH 920-930/3rd lift/Yard side

    12 Truck Parking Area Sub-grade Preparation Sub-grade Preparation in progress.

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14Interlocking Block (02 NosPlant)

    ILB production ILB production in progress.(18,400 Nos)

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Open Drain Work11

    Yard Drainage1

    Segment-28

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of March 25,2012

  • 8/13/2019 Daily Program April-2012

    40/59

    S.l.No.

    Description Work Program of March 25,2012 Achievement of March 24,2012 Remarks

    Rebar binding & Shuttering of wall of Gully hole. Rebar binding & Shuttering of wall of Gully hole.

    Concrete Pouring of wall of Gully hole

    2 Yard Drainage (Seg 2A) Yard Drainage,Pipe laying & Side cc casting Yard Drainage,Pipe laying & Side cc casting in progress

    Rod binding of base of Manhole.

    3 Sub-station Building Platering work Platering work in progress.

    Lime Tracing work of slab Lime Tracing work of slab in progress.

    4 RMG Track(Seg-1A) Rebar binding & Shuttering of Longitudinal sleepers.Rebar binding & Shuttering of Longitudinal sleepers in

    progress.5 Service Area Sub-base work Sub-base work in progress.

    6 Segment-1 Surcharge material removing Surcharge material removing in progress.

    Surcharge material placement Surcharge material placement in progress.

    8 Segment-3 Dismantling work Dismantling work in progress.

    9 Navy Area Surface drain work

    10 Road Type-1 300mm Base course laying. 300mm Base course laying.in progressBase casting near road way box culvert. Rebar binding & Shuttering.

    12 Boundary Wall Column shuttering & Casting

    13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)

    14Interlocking Block (02 NosPlant)

    ILB production

    Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Open Drain Work11

    Yard Drainage (Seg 1A)1

    Segment-27

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of March 27,2012

  • 8/13/2019 Daily Program April-2012

    41/59

    S.l.No.

    Description Work Program of March 27,2012 Achievement of March 26,2012 Remarks

    Rebar binding & Shuttering of wall of Gully hole. Rebar binding & Shuttering of wall of Gully hole.

    Concrete Pouring of wall of Gully hole (02 Nos)

    2 RMG Track Concrete Pouring (02 Nos span) Rebar binding & Shuttering executed.

    3 Sub-station Building Platering work Platering work in progress.

    Lime Tracing work of slab Lime Tracing work of slab in progress.

    4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.

    1 Yard Drainage Pipe laying & Side cc casting Pipe laying & Side cc casting in progress

    Base of Manhole(02 Nos). Rebar binding & Shuttering executed.CC casting of Gullyhole(02 Nos)

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Surcharge material placement Surcharge material placement in progress.

    Existing pavement dismantling Existing pavement dismantling in progress.

    1 PVD PVD Driving

    1 Surface drain work Brick masonry work Brick masonry work in progress

    2 Cable Laying Earth excavation

    3 Main gate Layout fixing & Earth excavation for column

    1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.

    1 Chainage (920-930) Base casting Rebar binding & Shuttering.

    1 Chainage (1-50) Column shuttering & Casting Column shuttering & Casting in progress

    1 Interlocking Block Compressive strength test

    1 Hammer Installation Hammer Installation at bank site

    2 Site Clearance Bank site clearing.

    1 ILB production ILB production in progress(12400 Nos)

    Navy Area

    Segment-2

    Interlocking Block Production

    Segment-2A

    Open Deep Drain Work

    Boundary Wall

    Laboratory / Field Test

    Sheet Pile Driving

    Dismantling1

    Segment-4

    Road Type-1

    Segment-1A

    Segment-1

    Segment-3

    Yard Drainage1

    l

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of March 28,2012

  • 8/13/2019 Daily Program April-2012

    42/59

    S.l.No.

    Description Work Program of March 28,2012 Achievement of March 27,2012 Remarks

    1 Yard Drainage Concrete Pouring of wall of Gully hole (02 Nos) executed.2 RMG Track Rebar binding & Shuttering . Concrete Pouring (02 Nos span) executed.3 Sub-station Building Platering work Platering work in progress.

    Lime Tracing work of slab Lime Tracing work of slab in progress.4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.

    1 Yard Drainage Pipe laying & Side cc casting Pipe laying & Side cc casting in progressBase of Manhole(02 Nos). Rebar binding & Shuttering executed.CC casting of Gullyhole(02 Nos)

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Surcharge mater ial placement Surcharge material placement in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 PVD PVD Driving PVD Driving in progress.

    1 Surface drain work Brick masonry work Brick masonry work in progress2 Cable Laying Earth excavation Earth excavation in progress.

    3 Main gate Layout fixing & Earth excavation for column

    1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.

    1 Chainage (720-730) Earth excavation

    1 Chainage (1-50) Column shuttering & Casting Column shuttering & Casting in progress

    1 Interlocking Block Compressive strength test

    1 Hammer Installation Hammer Instal lation at bank site Hammer Installation at bank si te in progress.2 Site Clearance Bank site clearing. Bank site clearing in progress

    1 ILB production No production due to mechanical fault.

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPANCT Back-up/PBL

    Road Type-1

    Segment-1A

    Segment-1

    Segment-3

    Segment-2

    Interlocking Block Production

    Sheet Pile Driving

    Segment-4

    Segment-2A

    Project Manager

    Open Deep Drain Work

    Boundary Wall

    Laboratory / Field Test

    Navy Area

    S l

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of March 29,2012

  • 8/13/2019 Daily Program April-2012

    43/59

    S.l.No.

    Description Work Program of March 29,2012 Achievement of March 28,2012 Remarks

    1 Yard Drainage2 RMG Track Rebar binding & Shuttering . Rebar binding & Shuttering in progress.

    3 Sub-station Building Platering work Platering work in progress.Lime Tracing work of slab Lime Tracing work of slab in progress.

    4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.5 Cable Trench work Soling & Rebar binding. Soling & Rebar binding in progress.

    1 Yard Drainage Pipe laying & Side CC casting Pipe laying & Side CC casting in progressBase Casting of Gullyhole(02 Nos). Rebar binding & Shuttering executed.

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Surcharge material placement Surcharge material placement in progress .

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 PVD PVD Driving PVD Driving in progress.

    1 Surface drain work Brick masonry work Brick masonry work in progress2 Cable Laying Earth excavation Earth excavation in progress.

    3 Main gate Layout fixing & Earth excavation for column

    1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.

    1 Chainage (720-730) Base casting. Rebar binding & Shuttering executed.

    1 Chainage (1-50) Column shuttering & Casting

    1 Interlocking Block Compressive strength test Compressive strength test

    1 Hammer Installation Hammer Installation at bank site Hammer Installation at bank site in progress.2 Site Cleaning Bank site cleaning. Bank site cleaning in progress

    1 ILB production No production due to mechanical fault.

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Sheet Pile Driving

    Segment-4

    Navy Area

    Segment-2A

    Open Deep Drain Work

    Boundary Wall

    Laboratory / Field Test

    Project Manager NCT Back-up/PBL

    Road Type-1

    Segment-1A

    Segment-1

    Segment-3

    Segment-2

    Interlocking Block Production

    S l

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of April 2,2012

  • 8/13/2019 Daily Program April-2012

    44/59

    S.l.No.

    Description Work Program of April 2,2012 Achievement of April 1,2012 Remarks

    1 Yard Drainage2 RMG Track Rebar binding & Shuttering . Rebar binding & Shuttering in progress.3 Sub-station Building Platering work Platering work in progress.

    Lime Tracing work of slab Lime Tracing work of slab in progress.RTG Track Sub-base work Sub-base work in progress.

    4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.5 Cable Trench work Base Casting of HT Cable Trench Shuttering & Rebar binding executed

    Base Casting of Cable Trench for Refer Shuttering & Rebar binding executed

    1 Yard Drainage Pipe laying & Side CC casting Pipe laying & Side CC casting in progressBase Casting of Manhole(02 Nos). Rebar binding & Shuttering executed.

    Base Casting of Gullyhole (02 Nos). Rebar binding & Shuttering executed.

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Surcharge materia l placement Surcharge materia l p lacement in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 200mm sand blanket Sand blanket laying Sand blanket laying in progress.

    1 Surface drain work2 Cable Laying Pipe laying Pipe laying in progress

    3 Main gate

    1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.

    1 Chainage (730-750) Base Casting Base Casting in progress.

    1 Chainage (1-50) Column shuttering & Casting Column shuttering & Casting in progress.

    1 Interlocking Block Compressive strength test Compressive strength test

    1 Pile Driving Sheet Pile Driving.2 Site Cleaning Bank site cleaning. Bank site cleaning in progress

    1 ILB production ILB production (12,860 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Interlocking Block Production

    Segment-1

    Segment-2

    Segment-1A

    Segment-2A

    Project Manager NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Road Type-1

    Open Deep Drain Work

    Boundary Wall

    Laboratory / Field Test

    Bank Protection work

    S l

    NCT BACK-UP PROJECT, CHITTAGONG

    Work Program of April 3,2012

  • 8/13/2019 Daily Program April-2012

    45/59

    S.l.No.

    Description Work Program of April 3,2012 Achievement of April 2,2012 Remarks

    1 Yard Drainage Base casting of Manhole(01 No). Rebar b inding & Shuttering executed.2 RMG Track Rebar binding & Shuttering . Rebar binding & Shuttering in progress.3 Sub-station Building Plastering work Plastering work in progress.

    Lime Tracing work of slab Lime Tracing work of slab in progress.RTG Track Sub-base work Sub-base work in progress.

    4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.5 Cable Trench work Base Casting of HT Cable Trench Shuttering & Rebar binding executed

    Base Casting of Cable Trench for Refer Shuttering & Rebar binding executed

    1 Yard Drainage Pipe laying & Side CC casting Pipe laying & Side CC casting in progressBase Casting of Manhole(02 Nos). Rebar binding & Shuttering executed.

    Base Casting of Gullyhole (02 Nos). Rebar binding & Shuttering executed.

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Surcharge material p lacement Surcharge materia l p lacement in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 200mm sand blanket Sand blanket laying Sand blanket laying in progress.

    1 Surface drain work2 Cable Laying Pipe laying Pipe laying in progress

    3 Main gate

    1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.

    1 Chainage (730-750) Wall casting Shuttering & Rebar binding executed

    1 Chainage (1-50) Column shuttering & Casting Column shuttering & Casting in progress.

    1 Interlocking Block Compressive strength test Compressive strength test

    1 Pile Driving Sheet Pile Driving.2 Site Cleaning Bank site cleaning. Bank site cleaning in progress

    1 ILB production ILB production (10,500 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Project Manager NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Road Type-1

    Open Deep Drain Work

    Boundary Wall

    Laboratory / Field Test

    Bank Protection work

    Interlocking Block Production

    Segment-1

    Segment-2

    Segment-1A

    Segment-2A

    S l

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of April 4,2012

  • 8/13/2019 Daily Program April-2012

    46/59

    S.l.No.

    Description Work Program of April 4,2012 Achievement of April 3,2012 Remarks

    1 Yard Drainage2 RMG Track Rebar binding & Shuttering . Rebar binding & Shuttering in progress.3 Sub-station Building Plastering Plastering in progress.

    RTG Track Sub-base work Sub-base work in progress.4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.5 Cable Trench work Rebar binding & Shuttering of Base. Concrete Pouring of Base executed.

    Concrete Pouring of wall.

    1 Yard Drainage Pipe laying & Side CC casting Pipe laying & Side CC casting in progressRebar binding & Shuttering of Manhole Rebar binding & Shuttering in progress.Rebar binding & Shuttering of Gullyhole Rebar binding & Shuttering in progress.

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Surcharge material placement Surcharge material placement in progress.

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 Surface drain work

    2 Cable Laying Pipe laying Pipe laying in progress

    3 Main gate

    1 Chainage (730-760) Base & Wall casting Shuttering & Rebar binding executed

    1 Short Column Concrete Pouring (07 Nos) Shuttering & Rebar binding executed

    1 Interlocking Block Compressive strength test Compressive strength test

    1 Pile Driving Sheet Pile Driving. Sheet Pile Driving in progress.2 Site Cleaning Bank site cleaning. Bank site cleaning in progress

    1 ILB production ILB production (14,120 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Interlocking Block Production

    Segment-1

    Segment-2

    Segment-1A

    Segment-2A

    Project Manager NCT Back-up/PBL

    Segment-3

    Segment-4

    Navy Area

    Road Type-1

    Open Deep Drain Work

    Boundary Wall

    Laboratory / Field Test

    Bank Protection work

    S.l.D i i W k P f A il 5 2012 A hi f A il 4 2012 R k

    NCT BACK-UP PROJECT, CHITTAGONGWork Program of April 5,2012

  • 8/13/2019 Daily Program April-2012

    47/59

    No.Description Work Program of April 5,2012 Achievement of April 4,2012 Remarks

    1 Yard Drainage2 RMG Track Rebar binding & Shuttering . Rebar binding & Shuttering in progress.3 Sub-station Building Window's Grill fi tting.

    RTG Track Sub-base work Sub-base work in progress.4 Service Area Rebar binding & Shuttering . Rebar binding & Shuttering in progress.5 Cable Trench work Concrete Pouring of wall (26m) Rebar binding & Shuttering executed.

    Concrete Pouring of Base (31m) Rebar binding & Shuttering executed.

    1 Yard Drainage Pipe laying & Side CC casting Pipe laying & Side CC casting in progressSand Compaction after Drainage pipe fixing.

    1 Surcharge Surcharge material removing Surcharge material removing in progress.

    1 Surcharge Settlement Record

    1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

    1 Surface drain work

    2 Cable Laying Earth excavation & Pipe laying Earth excavation & Pipe laying in progress.3 Main gate

    1 Chainage (730-760)Wall Casting 1st lift at country side & 2nd liftat Yard side.

    Shuttering & Rebar binding executed

    1 Short Column Shuttering & Rebar fabrication. Concrete Pouring (07 Nos)

    1 Interlocking Block Compressive strength test Compressive strength test

    1 Pile Driving Sheet Pile Driving. Sheet Pile Driving in progress.2 Site Cleaning Bank site cleaning. Bank site cleaning in progress

    1 ILB production ILB production (14,270 Nos)

    Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA

    Project Manager NCT Back-