10
KEGIATAN : PEMBANGUNAN KANTOR BUPATI PEKERJAAN : PEMBANGUNAN KANTOR DINAS PENGELOLAAN KEUANGAN DAERAH LOKASI : KABUPATEN LIMA PULUH KOTA NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH 1 3 4 5 6 1 Analisa Pembersihan Lapangan/ 10 m2 0.75 Pekerja 45,000.00 Rp 33,750.00 Rp 0.25 Mandor 60,000.00 Rp 15,000.00 Rp 48,750.00 Rp untuk 1 m2 = 1/10x 4,875.00 Rp 4,875.00 Rp 2 Analisa F.37 / M Memasang Papan Bouplank 0.8 Tukang Kayu 60,000.00 Rp 48,000.00 Rp 0.08 Kepala Tukang Kayu 70,000.00 Rp 5,600.00 Rp 0.28 Pekerja 45,000.00 Rp 12,600.00 Rp 0.014 Mandor 60,000.00 Rp 840.00 Rp 0.09 m3 Papan Klas III 1,900,000.00 Rp 171,000.00 Rp 13.5 m Pancang 2,000.00 Rp 27,000.00 Rp 0.1 Kg Paku 14,400.00 Rp 1,440.00 Rp 67,040.00 Rp 199,440.00 Rp 266,480.00 Rp 3 Analisa Pekerjaan Cut & Fill / M3 a. Pekerjaan Galian Tanah Biasa/Pemotongan Tebing 1. Tenaga 0.0480 Mandor 60,000.00 Rp 2,880.00 Rp 0.1450 Pekerja 45,000.00 Rp 6,525.00 Rp 2. Biaya Peralatan 0.0250 Excavator 286,000.00 Rp 7,150.00 Rp 0.0167 Buldozer 260,000.00 Rp 4,342.00 Rp 1.0000 Alat Bantu 50.00 Rp 50.00 Rp 9,405.00 Rp 11,542.00 Rp Over head 10% 940.50 Rp 1,154.20 Rp Untuk Pekerjaan Cut / M3 10,345.50 Rp 12,696.20 Rp 23,041.70 Rp b. Pekerjaan Timbunan bekas galian 1. Tenaga 0.0180 Mandor 60,000.00 Rp 1,080.00 Rp 0.0720 Pekerja 45,000.00 Rp 3,240.00 Rp 2. Biaya Peralatan 0.0250 Motor Greder 263,000.00 Rp 6,575.00 Rp 0.0333 Mesin Gilas 130,000.00 Rp 4,329.00 Rp 0.0167 Water Tanker 135,000.00 Rp 2,254.50 Rp 1.0000 Alat Bantu 50.00 Rp 50.00 Rp 4,320.00 Rp 13,208.50 Rp Over head 10% 432.00 Rp 1,320.85 Rp Untuk Pekerjaan Cut / M3 4,752.00 Rp 14,529.35 Rp 19,281.35 Rp 42,323.05 Rp 4 Analisa A.I Galian Tanah Pondasi / m3 0.75 Pekerja 45,000.00 Rp 33,750.00 Rp 0.025 Mandor 60,000.00 Rp 1,500.00 Rp 35,250.00 Rp 35,250.00 Rp 5 Analisa Pekerjaan Stabilitas Tanah / M3 Upah Pekerjaan Stabilitas 0.022 Mandor 60,000.00 Rp 1,320.00 Rp 1,320.00 Rp 1,320.00 Rp Biaya Peralatan 0.0254 Operator Terampil 60,000.00 Rp 1,524.00 Rp 0.0305 Pembantu Operator 45,000.00 Rp 1,372.50 Rp 2,896.50 Rp 2,896.50 Rp Waktu Kerja Alat 8 jam/hari Sewa Alat 200,000.00 Rp /jam x 8 jam/hari 1,600,000.00 Rp Kapasitas Produksi Alat 200.00 Rp m2/jam 200.00 Rp /m3 x 8 jam/hari 1,600.00 Rp 1,000.00 Rp URAIAN 2 DAFTAR SATUAN ANALISA PEKERJAAN

Daftar Satuan Analisa Pekerjaan

Embed Size (px)

DESCRIPTION

Daftar Satuan Analisa Pekerjaan

Citation preview

Page 1: Daftar Satuan Analisa Pekerjaan

KEGIATAN : PEMBANGUNAN KANTOR BUPATIPEKERJAAN : PEMBANGUNAN KANTOR DINAS PENGELOLAAN KEUANGAN DAERAHLOKASI : KABUPATEN LIMA PULUH KOTA

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

1 Analisa Pembersihan Lapangan/ 10 m20.75 Pekerja 45,000.00Rp 33,750.00Rp 0.25 Mandor 60,000.00Rp 15,000.00Rp

48,750.00Rp untuk 1 m2 = 1/10x 4,875.00Rp 4,875.00Rp

2 Analisa F.37 / M Memasang Papan Bouplank0.8 Tukang Kayu 60,000.00Rp 48,000.00Rp

0.08 Kepala Tukang Kayu 70,000.00Rp 5,600.00Rp 0.28 Pekerja 45,000.00Rp 12,600.00Rp

0.014 Mandor 60,000.00Rp 840.00Rp 0.09 m3 Papan Klas III 1,900,000.00Rp 171,000.00Rp 13.5 m Pancang 2,000.00Rp 27,000.00Rp 0.1 Kg Paku 14,400.00Rp 1,440.00Rp

67,040.00Rp 199,440.00Rp 266,480.00Rp

3 Analisa Pekerjaan Cut & Fill / M3a. Pekerjaan Galian Tanah Biasa/Pemotongan Tebing1. Tenaga

0.0480 Mandor 60,000.00Rp 2,880.00Rp 0.1450 Pekerja 45,000.00Rp 6,525.00Rp

2. Biaya Peralatan0.0250 Excavator 286,000.00Rp 7,150.00Rp 0.0167 Buldozer 260,000.00Rp 4,342.00Rp 1.0000 Alat Bantu 50.00Rp 50.00Rp

9,405.00Rp 11,542.00Rp Over head 10% 940.50Rp 1,154.20Rp Untuk Pekerjaan Cut / M3 10,345.50Rp 12,696.20Rp 23,041.70Rp

b. Pekerjaan Timbunan bekas galian1. Tenaga

0.0180 Mandor 60,000.00Rp 1,080.00Rp 0.0720 Pekerja 45,000.00Rp 3,240.00Rp

2. Biaya Peralatan0.0250 Motor Greder 263,000.00Rp 6,575.00Rp 0.0333 Mesin Gilas 130,000.00Rp 4,329.00Rp 0.0167 Water Tanker 135,000.00Rp 2,254.50Rp 1.0000 Alat Bantu 50.00Rp 50.00Rp

4,320.00Rp 13,208.50Rp Over head 10% 432.00Rp 1,320.85Rp Untuk Pekerjaan Cut / M3 4,752.00Rp 14,529.35Rp 19,281.35Rp

42,323.05Rp

4 Analisa A.I Galian Tanah Pondasi / m30.75 Pekerja 45,000.00Rp 33,750.00Rp

0.025 Mandor 60,000.00Rp 1,500.00Rp 35,250.00Rp 35,250.00Rp

5 Analisa Pekerjaan Stabilitas Tanah / M3Upah Pekerjaan Stabilitas

0.022 Mandor 60,000.00Rp 1,320.00Rp 1,320.00Rp 1,320.00Rp

Biaya Peralatan0.0254 Operator Terampil 60,000.00Rp 1,524.00Rp 0.0305 Pembantu Operator 45,000.00Rp 1,372.50Rp

2,896.50Rp 2,896.50Rp Waktu Kerja Alat 8 jam/hariSewa Alat 200,000.00Rp /jam x 8 jam/hari 1,600,000.00Rp Kapasitas Produksi Alat 200.00Rp m2/jam

200.00Rp /m3 x 8 jam/hari 1,600.00Rp 1,000.00Rp

URAIAN2

DAFTAR SATUAN ANALISA PEKERJAAN

Page 2: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

Kebutuhan Biaya Bahan Bakara. Diesel 0.16 ltr/HP/jamb. Tenaga Alat Berat 115 HPc. Harga Solar 4,500.00Rp /literKebutuhan 4,500.00Rp /liter x 8 jam x 115 HP x 0.16 414.00Rp

1,600.00Rp

Mobilisasi Alat 150.00Rp 5,780.50Rp

6 Analisa G.2 Urugan Pasir di Bawah Pondasi/M30.3000 Pekerja 45,000.00Rp 13,500.00Rp 0.0100 Mandor 60,000.00Rp 600.00Rp 1.2000 m3 Pasir Urug 24,750.00Rp 29,700.00Rp

14,100.00Rp 29,700.00Rp 43,800.00Rp

7 Analisa G.43 Lantai Kerja 1:3:5 /m36.0000 Pekerja 45,000.00Rp 270,000.00Rp 0.3000 Mandor 60,000.00Rp 18,000.00Rp 0.5000 Tukang Batu 60,000.00Rp 30,000.00Rp 0.0500 Kep. Tukang Batu 70,000.00Rp 3,500.00Rp 3.6600 Zak Semen 50,000.00Rp 183,000.00Rp 0.5400 m3 Pasir Beton 53,625.00Rp 28,957.50Rp 0.9100 m3 Kerikil Beton 61,875.00Rp 56,306.25Rp

504,500.00Rp 85,263.75Rp 589,763.75Rp

8 Analisa I.2 Pasang Rangka Besi/100 kg9.0000 Tukang Besi 60,000.00Rp 540,000.00Rp 3.0000 Kep. Tukang Besi 70,000.00Rp 210,000.00Rp 9.0000 Pekerja 45,000.00Rp 405,000.00Rp

110.0000 Kg. Besi Beton 17,325.00Rp 1,905,750.00Rp 2.0000 Kg. Kawat Beton 15,000.00Rp 30,000.00Rp

1,155,000.00Rp 1,935,750.00Rp Upah diambil 3/4 866,250.00Rp Untuk 1 kg 8,662.50Rp 19,357.50Rp 28,020.00Rp

9 Analisa G.41 Stamp Beton Spesi 1:2:3 / M36.0000 Pekerja 45,000.00Rp 270,000.00Rp 0.3000 Mandor 60,000.00Rp 18,000.00Rp 1.0000 Tukang Batu 60,000.00Rp 60,000.00Rp 0.1000 Kep. Tukang Batu 70,000.00Rp 7,000.00Rp 6.8000 Zak Semen 50,000.00Rp 340,000.00Rp 0.5400 m3 Pasir Beton 53,625.00Rp 28,957.50Rp 0.8200 m3 Kerikil Beton 61,875.00Rp 50,737.50Rp

695,000.00Rp 79,695.00Rp 774,695.00Rp

10 Analisa F.8 Cetakan Beton / m32.0000 Pekerja 45,000.00Rp 90,000.00Rp 0.1000 Mandor 60,000.00Rp 6,000.00Rp 5.0000 Tukang Kayu 60,000.00Rp 300,000.00Rp 0.5000 Kep. Tukang Kayu 70,000.00Rp 35,000.00Rp 0.4000 m3 Cetakan Begisting 1,550,000.00Rp 620,000.00Rp 4.0000 Kg Paku 14,400.00Rp 57,600.00Rp

431,000.00Rp 677,600.00Rp untuk 1 m2 43,100.00Rp 67,760.00Rp 110,860.00Rp

11 Analisa Stutwerk / m32.5000 Pekerja 45,000.00Rp 112,500.00Rp 0.0130 Mandor 60,000.00Rp 780.00Rp 7.5000 Tukang Kayu 60,000.00Rp 450,000.00Rp 0.7500 Kep. Tukang Kayu 70,000.00Rp 52,500.00Rp 1.0000 m3 Cetakan Begisting 1,550,000.00Rp 1,550,000.00Rp 4.0000 kg Paku 14,400.00Rp 57,600.00Rp

615,780.00Rp 1,607,600.00Rp 2,223,380.00Rp

12 Analisa Pondasi Plat (Type P1) / M3128.21 kg Besi Beton I.2 17,325.00Rp 2,221,238.25Rp

6.33 m2 Cetakan Beton F.8 110,860.00Rp 701,743.80Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

3,697,677.05Rp 3,697,677.05Rp

13 Analisa Pondasi Plat (Type P2) / M393.52 kg Besi Beton I.2 17,325.00Rp 1,620,234.00Rp 6.33 m2 Cetakan Beton F.8 110,860.00Rp 701,743.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 3,096,672.80Rp 3,096,672.80Rp

Page 3: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

14 Analisa Pondasi Plat (Type P3) / M3115.22 kg Besi Beton I.2 17,325.00Rp 1,996,186.50Rp

6.33 m2 Cetakan Beton F.8 110,860.00Rp 701,743.80Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

3,472,625.30Rp 3,472,625.30Rp

15 Analisa Pondasi Plat (Type P4) / M3162 kg Besi Beton I.2 17,325.00Rp 2,806,650.00Rp 6.33 m2 Cetakan Beton F.8 110,860.00Rp 701,743.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 4,283,088.80Rp 4,283,088.80Rp

16 Analisa Sloof Beton Bertulang (Type S1) / M3131 kg Besi Beton I.2 17,325.00Rp 2,269,575.00Rp 10.5 m2 Cetakan Beton F.8 110,860.00Rp 1,164,030.00Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 4,208,300.00Rp 4,208,300.00Rp

17 Analisa Sloof Beton Bertulang (Type S2) / M384.9 kg Besi Beton I.2 17,325.00Rp 1,470,892.50Rp

16.67 m2 Cetakan Beton F.8 110,860.00Rp 1,848,036.20Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

4,093,623.70Rp 4,093,623.70Rp

18 Analisa Sloof Beton15/30 (Besi 84.39) / M384.9 kg Besi Beton I.2 17,325.00Rp 1,470,892.50Rp 13.3 m2 Cetakan Beton F.8 110,860.00Rp 1,474,438.00Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 3,720,025.50Rp 3,720,025.50Rp

19 Analisa Kolom K1 Ukuran 30/30234.2 kg Besi Beton I.2 17,325.00Rp 4,057,515.00Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

5,940,810.00Rp 5,940,810.00Rp

20 Analisa Kolom K1' Ukuran 30/30312.9 kg Besi Beton I.2 17,325.00Rp 5,420,992.50Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

7,304,287.50Rp 7,304,287.50Rp

21 Analisa Kolom K2 Ukuran 30/30184.03 kg Besi Beton I.2 17,325.00Rp 3,188,319.75Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

5,071,614.75Rp 5,071,614.75Rp

22 Analisa Kolom K2' Ukuran 30/30236.42 kg Besi Beton I.2 17,325.00Rp 4,095,976.50Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

5,979,271.50Rp 5,979,271.50Rp

23 Analisa Kolom K3 Ukuran 30/30199.7 kg Besi Beton I.2 17,325.00Rp 3,459,802.50Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

5,343,097.50Rp 5,343,097.50Rp

24 Analisa Kolom K5 Ukuran 30/30189.05 kg Besi Beton I.2 17,325.00Rp 3,275,291.25Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

5,158,586.25Rp 5,158,586.25Rp

Page 4: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

25 Analisa Kolom K5' Ukuran 30/30252.11 kg Besi Beton I.2 17,325.00Rp 4,367,805.75Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

6,251,100.75Rp 6,251,100.75Rp

26 Analisa Kolom K6 Ukuran 30/30151.8 kg Besi Beton I.2 17,325.00Rp 2,629,935.00Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

4,513,230.00Rp 4,513,230.00Rp

27 Analisa Kolom K6 Ukuran 30/30151.8 kg Besi Beton I.2 17,325.00Rp 2,629,935.00Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

4,513,230.00Rp 4,513,230.00Rp

28 Analisa Kolom K7 Ukuran 30/30212.96 kg Besi Beton I.2 17,325.00Rp 3,689,532.00Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

5,572,827.00Rp 5,572,827.00Rp

29 Analisa Kolom K8 Ukuran 30/30292.3 kg Besi Beton I.2 17,325.00Rp 5,064,097.50Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

6,947,392.50Rp 6,947,392.50Rp

29 Analisa Kolom K9 Ukuran 30/30154.3 kg Besi Beton I.2 17,325.00Rp 2,673,247.50Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

4,556,542.50Rp 4,556,542.50Rp

30 Analisa Kolom Praktis ukuran 12/12209 kg Besi Beton I.2 17,325.00Rp 3,620,925.00Rp 25 m2 Cetakan Beton F.8 110,860.00Rp 2,771,500.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

7,167,120.00Rp 7,167,120.00Rp

31 Analisa Beton 30/30 (Besi 120.65)120.65 kg Besi Beton I.2 17,325.00Rp 2,090,261.25Rp

10 m2 Cetakan Beton F.8 110,860.00Rp 1,108,600.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

3,973,556.25Rp 3,973,556.25Rp

32 Analisa Beton Tangga146.7048 kg Besi Beton I.2 17,325.00Rp 2,541,660.66Rp

1.01 m3 Stutwerk 2,223,380.00Rp 2,245,613.80Rp 8.33 m2 Cetakan Beton F.8 110,860.00Rp 923,463.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 6,485,433.26Rp 6,485,433.26Rp

33 Analisa Balok Lantai Ukuran 15/30115.72 kg Besi Beton I.2 17,325.00Rp 2,004,849.00Rp

0.5 m3 Stutwerk 2,223,380.00Rp 1,111,690.00Rp 16.67 m2 Cetakan Beton F.8 110,860.00Rp 1,848,036.20Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,739,270.20Rp 5,739,270.20Rp

34 Analisa Balok Canopy83.3 kg Besi Beton I.2 17,325.00Rp 1,443,172.50Rp 0.16 m3 Stutwerk 2,223,380.00Rp 355,740.80Rp 8.67 m2 Cetakan Beton F.8 110,860.00Rp 961,156.20Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 3,534,764.50Rp 3,534,764.50Rp

35 Analisa Balok Lantai Ukuran 25/40158.02 kg Besi Beton I.2 17,325.00Rp 2,737,696.50Rp

0.24 m3 Stutwerk 2,223,380.00Rp 533,611.20Rp 10.5 m2 Cetakan Beton F.8 110,860.00Rp 1,164,030.00Rp

Page 5: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,210,032.70Rp 5,210,032.70Rp

36 Analisa Balok Lantai Ukuran 30/40133.21 kg Besi Beton I.2 17,325.00Rp 2,307,863.25Rp

0.2 m3 Stutwerk 2,223,380.00Rp 444,676.00Rp 9.17 m2 Cetakan Beton F.8 110,860.00Rp 1,016,586.20Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 4,543,820.45Rp 4,543,820.45Rp

37 Analisa Plat Lantai tebal 12 cm115 kg Besi Beton I.2 17,325.00Rp 1,992,375.00Rp 1.31 m3 Stutwerk 2,223,380.00Rp 2,912,627.80Rp 10.3 m2 Cetakan Beton F.8 110,860.00Rp 1,141,858.00Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 6,821,555.80Rp 6,821,555.80Rp

38 Analisa Plat Konsul tebal 10 cm110 kg Besi Beton I.2 17,325.00Rp 1,905,750.00Rp 1.01 m3 Stutwerk 2,223,380.00Rp 2,245,613.80Rp 8.33 m2 Cetakan Beton F.8 110,860.00Rp 923,463.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,849,522.60Rp 5,849,522.60Rp

39 Analisa Plat Dag Tebal 10 cm110 kg Besi Beton I.2 17,325.00Rp 1,905,750.00Rp 1.54 m3 Stutwerk 2,223,380.00Rp 3,424,005.20Rp

12 m2 Cetakan Beton F.8 110,860.00Rp 1,330,320.00Rp 1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp

7,434,770.20Rp 7,434,770.20Rp

40 Analisa Ring Balok Ukuran 25/40122.96 kg Besi Beton I.2 17,325.00Rp 2,130,282.00Rp

0.24 m3 Stutwerk 2,223,380.00Rp 533,611.20Rp 10.5 m2 Cetakan Beton F.8 110,860.00Rp 1,164,030.00Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 4,602,618.20Rp 4,602,618.20Rp

41 Analisa Ring Balok Ukuran 15/25300.16 kg Besi Beton I.2 17,325.00Rp 5,200,272.00Rp

0.75 m3 Stutwerk 2,223,380.00Rp 1,667,535.00Rp 18.33 m2 Cetakan Beton F.8 110,860.00Rp 2,032,063.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 9,674,565.80Rp 9,674,565.80Rp

42 Analisa Ring Balok Ukuran 30/50160 kg Besi Beton I.2 17,325.00Rp 2,772,000.00Rp 0.16 m3 Stutwerk 2,223,380.00Rp 355,740.80Rp 10.5 m2 Cetakan Beton F.8 110,860.00Rp 1,164,030.00Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,066,465.80Rp 5,066,465.80Rp

43 Analisa Ring Balok Ukuran 30/40169.02 kg Besi Beton I.2 17,325.00Rp 2,928,271.50Rp

0.2 m3 Stutwerk 2,223,380.00Rp 444,676.00Rp 10.5 m2 Cetakan Beton F.8 110,860.00Rp 1,164,030.00Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,311,672.50Rp 5,311,672.50Rp

43 Analisa Ring Balok Ukuran 15/20171.33 kg Besi Beton I.2 17,325.00Rp 2,968,292.25Rp

0.75 m3 Stutwerk 2,223,380.00Rp 1,667,535.00Rp 18.33 m2 Cetakan Beton F.8 110,860.00Rp 2,032,063.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 7,442,586.05Rp 7,442,586.05Rp

44 Analisa Lesplank beton tebal 10 cm86 kg Besi Beton I.2 17,325.00Rp 1,489,950.00Rp

0.33 m3 Stutwerk 2,223,380.00Rp 733,715.40Rp 21.43 m2 Cetakan Beton F.8 110,860.00Rp 2,375,729.80Rp

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,374,090.20Rp 5,374,090.20Rp

45 Analisa Lesplank beton tebal 10cm86 kg Besi Beton I.2 17,325.00Rp 1,489,950.00Rp

0.33 m3 Stutwerk 2,223,380.00Rp 733,715.40Rp 21.43 m2 Cetakan Beton F.8 110,860.00Rp 2,375,729.80Rp

Page 6: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

1 m3 Stamp Benton G.42 774,695.00Rp 774,695.00Rp 5,374,090.20Rp 5,374,090.20Rp

46 Analisa G.33 Pasangan Dinding Batu Bata 1:2 /m31.5 Tukang Batu 60,000.00Rp 90,000.00Rp

0.15 Kepala Tukang batu 70,000.00Rp 10,500.00Rp 4.5 Pekerja 45,000.00Rp 202,500.00Rp

0.225 Mandor 60,000.00Rp 13,500.00Rp 500 bh Batu Bata 625.00Rp 312,500.00Rp

3.397 zak Semen 50,000.00Rp 169,850.00Rp 0.333 m3 Pasir 53,625.00Rp 17,857.13Rp

316,500.00Rp 500,207.13Rp 816,707.13Rp

47 Analisa G.33 Pasangan Dinding Batu Bata 1:4 /m31.5 Tukang Batu 60,000.00Rp 90,000.00Rp

0.15 Kepala Tukang batu 70,000.00Rp 10,500.00Rp 4.5 Pekerja 45,000.00Rp 202,500.00Rp

0.225 Mandor 60,000.00Rp 13,500.00Rp 500 bh Batu Bata 625.00Rp 312,500.00Rp 2.09 zak Semen 50,000.00Rp 104,500.00Rp

0.406 m3 Pasir 53,625.00Rp 21,771.75Rp 316,500.00Rp 438,771.75Rp 755,271.75Rp

48 Analisa G.50.h Memplester Dinding 1:4 / m20.4 Pekerja 45,000.00Rp 18,000.00Rp

0.02 Mandor 60,000.00Rp 1,200.00Rp 0.15 Tukang Batu 60,000.00Rp 9,000.00Rp

0.015 Kepala Tukang Batu 70,000.00Rp 1,050.00Rp 0.1536 zak Semen 50,000.00Rp 7,680.00Rp 0.021 m3 Pasir 53,625.00Rp 1,126.13Rp

29,250.00Rp 8,806.13Rp 38,056.13Rp

49 Analisa G.50.i Memplester Dinding 1:2 / m20.4 Pekerja 45,000.00Rp 18,000.00Rp

0.02 Mandor 60,000.00Rp 1,200.00Rp 0.2 Tukang Batu 60,000.00Rp 12,000.00Rp

0.02 Kepala Tukang Batu 70,000.00Rp 1,400.00Rp 0.1536 zak Semen 50,000.00Rp 7,680.00Rp 0.021 m3 Pasir 53,625.00Rp 1,126.13Rp

32,600.00Rp 8,806.13Rp 41,406.13Rp

50 Analisa Pasang Rangka Dinding Partisi / m327 Tukang Kayu 60,000.00Rp 1,620,000.00Rp 2.7 Kepala Tukang Kayu 70,000.00Rp 189,000.00Rp

9 Pekerja 45,000.00Rp 405,000.00Rp 0.45 Mandor 60,000.00Rp 27,000.00Rp 1.1 m3 Kayu Kelas III 1,900,000.00Rp 2,090,000.00Rp 0.2 kg Paku 14,400.00Rp 2,880.00Rp

2,241,000.00Rp 2,092,880.00Rp 4,333,880.00Rp

51 Analisa Pasang Dinding Partisi GRC / m20.8 Tukang Kayu 60,000.00Rp 48,000.00Rp

0.08 Kepala Tukang Kayu 70,000.00Rp 5,600.00Rp 0.28 Pekerja 45,000.00Rp 12,600.00Rp

0.014 Mandor 60,000.00Rp 840.00Rp 67,040.00Rp

Partisi GRC Tebal 6 mm / m21 Upah 67,040.00Rp 67,040.00Rp

2.4 GRC tebal 6 mm 25,000.00Rp 60,000.00Rp 0.2 kg Paku 14,400.00Rp 2,880.00Rp

67,040.00Rp 62,880.00Rp 129,920.00Rp

Partisi GRC Tebal 4.5 mm / m21 Upah 67,040.00Rp 67,040.00Rp

2.4 GRC tebal 6 mm 18,000.00Rp 43,200.00Rp 0.2 kg Paku 14,400.00Rp 2,880.00Rp

67,040.00Rp 46,080.00Rp 113,120.00Rp

52 Analisa Afwerking Beton / m20.6 Pekerja 45,000.00Rp 27,000.00Rp

0.03 Mandor 60,000.00Rp 1,800.00Rp 0.225 Tukang Batu 60,000.00Rp 13,500.00Rp 0.022 Kepala Tukang Batu 70,000.00Rp 1,540.00Rp 0.105 zak Semen 50,000.00Rp 5,250.00Rp 0.009 m3 Pasir Pasang 53,625.00Rp 482.63Rp

43,840.00Rp 5,732.63Rp 49,572.63Rp 53 Analisa Kuda-Kuda Baja /kg

Page 7: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

0.03 Tukang Las 60,000.00Rp 1,800.00Rp 0.03 Kepala Tukang Besi 70,000.00Rp 2,100.00Rp 0.09 Pekerja 45,000.00Rp 4,050.00Rp 1.1 kg Besi baja 7,500.00Rp 8,250.00Rp

0.01 Alat Bantu 35,000.00Rp 350.00Rp 7,950.00Rp 8,600.00Rp 16,550.00Rp

54 Analisa Pasang Baut + Plat sambungan / kgUntuk Pasang Baut + Plat Sambungan diperlukan :

= 1/3 x Analisa Baja 5,516.67Rp

55 Analisa Mengerjakan Gording Canal0.0092 Tukang Besi 60,000.00Rp 552.00Rp 0.0009 Kepala Tukang Besi 70,000.00Rp 63.00Rp 0.0031 Pekerja 45,000.00Rp 139.50Rp

1 kg Baja Kait 7,500.00Rp 7,500.00Rp 0.02 kg Kawat Las 22,000.00Rp 440.00Rp

0.001 Peralatan Las 50,000.00Rp 50.00Rp 754.50Rp 7,990.00Rp 8,744.50Rp

56 Analisa Mengerjakan Rangka Atap Genteng/ m20.1 Tukang kayu 60,000.00Rp 6,000.00Rp

0.01 Kepala Tukang Besi 70,000.00Rp 700.00Rp 0.15 Pekerja 45,000.00Rp 6,750.00Rp

0.0075 Mandor 60,000.00Rp 450.00Rp 0.019 m3 Kayu Kelas III 1,900,000.00Rp 36,100.00Rp

0.1 kg Paku 14,400.00Rp 1,440.00Rp 13,900.00Rp 37,540.00Rp 51,440.00Rp

57 Analisa Pasang Reuiter Baja INP / m0.092 Tukang Besi 60,000.00Rp 5,520.00Rp 0.009 Kepala Tukang Besi 70,000.00Rp 630.00Rp

0.0031 Pekerja 45,000.00Rp 139.50Rp 1 kg Baja I 7,500.00Rp 7,500.00Rp

0.02 kg Kawat Las 22,000.00Rp 440.00Rp 0.001 Perlatan Las 50,000.00Rp 50.00Rp

13,789.50Rp 490.00Rp 14,279.50Rp 58 Analisa Residu Kayu Kap Atap / m2

0.01 Pekerja 45,000.00Rp 450.00Rp 0.005 Mandor 60,000.00Rp 300.00Rp 0.35 kg Residu 5,000.00Rp 1,750.00Rp

750.00Rp 1,750.00Rp 2,500.00Rp

59 Analisa Pasang Atap Genteng Metal / m20.3 Tukang Kayu 60,000.00Rp 18,000.00Rp

0.03 Kepala Tukan Kayu 70,000.00Rp 2,100.00Rp 0.15 Pekerja 45,000.00Rp 6,750.00Rp

0.015 Mandor 60,000.00Rp 900.00Rp 0.035 kg Paku 14,400.00Rp 504.00Rp

1 m2 Genteng atap metal 125,000.00Rp 125,000.00Rp 27,750.00Rp 125,504.00Rp 153,254.00Rp

60 Analisa Pasang Perabung Genteng Metal / m0.025 Tukang kayu 60,000.00Rp 1,500.00Rp

0.0025 Kepala Tukang 70,000.00Rp 175.00Rp 0.025 Pekerja 45,000.00Rp 1,125.00Rp 0.02 kg Paku 14,400.00Rp 288.00Rp 1.1 lbr Perabung Genteng 85,000.00Rp 93,500.00Rp

2,800.00Rp 93,788.00Rp 96,588.00Rp 61 Analisa Singok Tembaga Berukir / m2

Pas. Singok tembaga berukir ditaksir 700,000.00Rp

62 Analisa Pasang Pucuak Rabunag Gonjong/ bhPas. Ornamen gonjong ditaksir 900,000.00Rp

63 Analisa Pasang Rangka Plafon / m35 Pekerja 45,000.00Rp 225,000.00Rp

0.25 Mandor 60,000.00Rp 15,000.00Rp 15 Tukang Kayu 60,000.00Rp 900,000.00Rp 1.5 Kepala Tukang Kayu 70,000.00Rp 105,000.00Rp 1.1 m3 Kayu Kelas III 1,900,000.00Rp 2,090,000.00Rp

8 kg Paku 14,400.00Rp 115,200.00Rp 1,245,000.00Rp 2,205,200.00Rp 3,450,200.00Rp

64 Analisa Pasang Plafond Gypsum Tebal 9 mm / m20.2 Tukang kayu 60,000.00Rp 12,000.00Rp

0.02 Kepala Tukang 70,000.00Rp 1,400.00Rp

Page 8: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

0.28 Pekerja 45,000.00Rp 12,600.00Rp 0.4 lbr Gypsum 50,000.00Rp 20,000.00Rp 0.2 kg Paku Gypsum 18,500.00Rp 3,700.00Rp

26,000.00Rp 23,700.00Rp 49,700.00Rp

Analisa Pasang Plafond GRC Tebal 4.5 mm / m20.2 Tukang kayu 45,000.00Rp 9,000.00Rp

0.02 Kepala Tukang 70,000.00Rp 1,400.00Rp 0.28 Pekerja 45,000.00Rp 12,600.00Rp 0.4 lbr Gypsum 18,000.00Rp 7,200.00Rp 0.2 kg paku 14,400.00Rp 2,880.00Rp

23,000.00Rp 10,080.00Rp 33,080.00Rp

65 Analisa Pasang Plafond GRC Tebal 4.5 mm / m20.4 Tukang kayu 60,000.00Rp 24,000.00Rp

0.04 Kepala Tukang 70,000.00Rp 2,800.00Rp 0.04 Mandor 60,000.00Rp 2,400.00Rp

0.019 m3 Kayu 1x8x400 1,900,000.00Rp 36,100.00Rp 0.05 kg paku 14,400.00Rp 720.00Rp

29,200.00Rp 36,820.00Rp 66,020.00Rp

65 Analisa Pasang Urugan Tasirtu /m30.3 Pekerja 60,000.00Rp 18,000.00Rp

0.01 Mandor 60,000.00Rp 600.00Rp 1.2 Tarsitu 42,000.00Rp 50,400.00Rp

18,600.00Rp 50,400.00Rp 69,000.00Rp

66 Analisa Pasangan Keramik 30x30 / m20.5 Pekerja 45,000.00Rp 22,500.00Rp

0.025 Mandor 60,000.00Rp 1,500.00Rp 0.36 Tukang Batu 60,000.00Rp 21,600.00Rp

0.025 Kepala Tukang Batu 70,000.00Rp 1,750.00Rp 0.062 m3 Pasir Pasang 53,625.00Rp 3,324.75Rp 0.32 zak Semen 50,000.00Rp 16,000.00Rp

1 m2 Keramik 47,000.00Rp 47,000.00Rp 47,350.00Rp 66,324.75Rp 113,674.75Rp

67 Analisa Pasangan Keramik KM/WC 20x25 / m20.5 Pekerja 45,000.00Rp 22,500.00Rp

0.025 Mandor 60,000.00Rp 1,500.00Rp 0.36 Tukang Batu 60,000.00Rp 21,600.00Rp

0.025 Kepala Tukang Batu 70,000.00Rp 1,750.00Rp 0.062 m3 Pasir Pasang 53,625.00Rp 3,324.75Rp 0.32 zak Semen 50,000.00Rp 16,000.00Rp

1 m2 Keramik 50,000.00Rp 50,000.00Rp 47,350.00Rp 69,324.75Rp 116,674.75Rp

67 Analisa Pasangan Keramik KM/WC 20x20 / m20.5 Pekerja 45,000.00Rp 22,500.00Rp

0.025 Mandor 60,000.00Rp 1,500.00Rp 0.36 Tukang Batu 60,000.00Rp 21,600.00Rp

0.025 Kepala Tukang Batu 70,000.00Rp 1,750.00Rp 0.062 m3 Pasir Pasang 53,625.00Rp 3,324.75Rp 0.32 zak Semen 50,000.00Rp 16,000.00Rp

1 m2 Keramik 47,000.00Rp 47,000.00Rp 47,350.00Rp 66,324.75Rp 113,674.75Rp

68 Analisa Pasangan Membran Waterproofing / m2Harga Satuan ditaksir 100,000.00Rp

69 Analisa F.27 Mengerjakan Kozen Kayu / m336.6 Tukang kayu 60,000.00Rp 2,196,000.00Rp 3.6 Kepala Tukang Kayu 70,000.00Rp 252,000.00Rp 12 Pekerja 45,000.00Rp 540,000.00Rp 0.6 Mandor 60,000.00Rp 36,000.00Rp 1.1 m3 Kayu Kelas I 3,750,000.00Rp 4,125,000.00Rp

3,024,000.00Rp Upah di ambil 3/4 2,268,000.00Rp 4,125,000.00Rp 6,393,000.00Rp

70 Analisa F.33.A Pasang Pintu Triplek Lapis Sungkai / m24.2188 Tukang Kayu 60,000.00Rp 253,128.00Rp 0.3164 Kepala Tukang Kayu 70,000.00Rp 22,148.00Rp 1.4063 Pekerja 45,000.00Rp 63,283.50Rp 0.0703 Mandor 60,000.00Rp 4,218.00Rp

0.2 kg Paku 14,400.00Rp 2,880.00Rp 0.035 m3 Papan Kls I 3,750,000.00Rp 131,250.00Rp

2.4 Triplek tebal 4 mm 55,000.00Rp 132,000.00Rp 342,777.50Rp 266,130.00Rp 608,907.50Rp

Page 9: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

71 Analisa F.37 Pasang Kaca Mati Setebal 5 mm / m20.025 Tukang Kayu 60,000.00Rp 1,500.00Rp

0.0025 Mandor 60,000.00Rp 150.00Rp 1.1 m2 kaca 5 mm 125,000.00Rp 137,500.00Rp

4 m List Kaca 3,250.00Rp 13,000.00Rp 1,650.00Rp 150,500.00Rp 152,150.00Rp

72 Mencat Dinding dengan Cat Tembok / m2Upah mencat 1 x jalan 100/m2 Analisa K.23

0.75 Tukang Cat 60,000.00Rp 45,000.00Rp 0.075 Kepala Tukang Cat 70,000.00Rp 5,250.00Rp

0.5 Pekerja 45,000.00Rp 22,500.00Rp 0.025 Mandor 60,000.00Rp 1,500.00Rp

74,250.00Rp 74,250.00Rp Mendepul 10/m2 Analisa K.30

1.4 Tukang Cat 60,000.00Rp 84,000.00Rp 0.14 Kepala Tukang Cat 70,000.00Rp 9,800.00Rp 1.26 kg dempul jadi 17,500.00Rp 22,050.00Rp

2 Helai amplas 3,000.00Rp 6,000.00Rp 93,800.00Rp 28,050.00Rp 121,850.00Rp

Membersihkan Dinding Analisa K.330.5 Pekerja 45,000.00Rp 22,500.00Rp

0.025 Mandor 60,000.00Rp 1,500.00Rp 24,000.00Rp 24,000.00Rp

73 Analisa Mencat Minyak kayu yang kelihatan 10/m22 Upah analisa K.23 74,250.00Rp 148,500.00Rp 1 Analisa k.30 121,850.00Rp 121,850.00Rp

1.42 kg Cat Dasar 19,500.00Rp 27,690.00Rp 2.48 kg Cat Warna 57,500.00Rp 142,600.00Rp

270,350.00Rp 170,290.00Rp 440,640.00Rp

74 Analisa Mencat Air dinding Tembok 10 /m2Analisa Cat bagian Luar

2.6 Tukang Cat 60,000.00Rp 156,000.00Rp 0.265 Kepala Tukang Cat 70,000.00Rp 18,550.00Rp

1.5 Pekerja 45,000.00Rp 67,500.00Rp 3.125 kg Cat Tembok Dulux 35,000.00Rp 109,375.00Rp

2 lbr Amplas 3,000.00Rp 6,000.00Rp 242,050.00Rp 115,375.00Rp 357,425.00Rp

Analisa Cat bagian Dalam2.6 Tukang Cat 60,000.00Rp 156,000.00Rp

0.265 Kepala Tukang Cat 70,000.00Rp 18,550.00Rp 1.5 Pekerja 45,000.00Rp 67,500.00Rp

3.125 kg Cat Tembok Catilax 35,000.00Rp 109,375.00Rp 2 lbr Amplas 3,000.00Rp 6,000.00Rp

242,050.00Rp 115,375.00Rp 357,425.00Rp

75 Analisa Mencat Air Plafond 10/ m22.65 Tukang Cat 60,000.00Rp 159,000.00Rp

0.265 Kepala Tukang Cat 70,000.00Rp 18,550.00Rp 1.5 Pekerja 45,000.00Rp 67,500.00Rp

0.068 Mandor 60,000.00Rp 4,080.00Rp 3.125 kg Cat tembok 35,000.00Rp 109,375.00Rp

245,050.00Rp 113,455.00Rp 358,505.00Rp

76 Analisa Mencat Minyak Kayu dengan cat IMPRA / m20.5 Tukang Cat 60,000.00Rp 30,000.00Rp

0.05 Kepala Tukang Cat 70,000.00Rp 3,500.00Rp 1 lbr Amplas 3,000.00Rp 3,000.00Rp

0.426 kg Cat warna impra 57,500.00Rp 24,495.00Rp 0.426 kg Melamin 60,000.00Rp 25,560.00Rp

36,500.00Rp 50,055.00Rp 86,555.00Rp

77 Analisa Pasangan Paving Block / m20.2 Pekerja 45,000.00Rp 9,000.00Rp

0.06 Mandor 60,000.00Rp 3,600.00Rp 35 bh Paving Block 3,500.00Rp 122,500.00Rp

0.0035 m3 Pasir Pasang 53,625.00Rp 187.69Rp 12,600.00Rp 122,687.69Rp 135,287.69Rp

78 Analisa Mencat Zinkromat / 10 m20.75 Tukang Cat 60,000.00Rp 45,000.00Rp

0.075 Kepala Tukang Cat 70,000.00Rp 5,250.00Rp 0.5 Pekerja 45,000.00Rp 22,500.00Rp

0.025 Mandor 60,000.00Rp 1,500.00Rp

Page 10: Daftar Satuan Analisa Pekerjaan

NO HARGA SATUAN JUMLAH UPAH JUMLAH BAHAN JUMLAH1 3 4 5 6

URAIAN2

1.2 kg Zinkromat 25,000.00Rp 30,000.00Rp 74,250.00Rp 30,000.00Rp 104,250.00Rp

79 Pekerjaan Septiktank + Peresapan Kapasitas 50 orang24 m3 Galian tanah 35,250.00Rp 846,000.00Rp

1.25 m3 Stam Beton Tumbuk 1:2:3 774,695.00Rp 968,368.75Rp 4.5 m3 Pasangan Bata 1:2 816,707.13Rp 3,675,182.06Rp

42.5 m3 Memplester 1:2 41,406.13Rp 1,759,760.31Rp 0.35 m3 Plat Beton Bertulang 1:2:3 6,821,555.80Rp 2,387,544.53Rp 2.5 m3 kerekel Saringan 61,875.00Rp 154,687.50Rp

2 m3 Pasir Saringan 53,625.00Rp 107,250.00Rp 5 m Memasang Pipa PVC dia 4" 1,343,700.00Rp 6,718,500.00Rp 3 m memasang pipa besi dia 2" 250,000.00Rp 750,000.00Rp

20 kg Ijuk Saringan 15,000.00Rp 300,000.00Rp 17,667,293.16Rp 17,667,293.16Rp