CXC Manager’s Status Report. Chandra Users’ Committee Meeting Roger J. Brissenden 25 January 2005. Topics. Program Level Status Program Management Spacecraft Mission Planning Science Instruments and Calibration OCC Data Processing CXCDS CDO Education and Outreach Mission Metrics - PowerPoint PPT Presentation
Citation preview
CXC Manager’s Status Report
Chandra Users’ Committee Meeting
Roger J. Brissenden
25 January 2005
25 January 2005 CXC Status Report/CUC Page 2
Topics
• Program Level Status
– Program Management
– Spacecraft
– Mission Planning
– Science Instruments and Calibration
– OCC
– Data Processing
– CXCDS
– CDO
– Education and Outreach
• Mission Metrics
• Chandra Grant Awards
25 January 2005 CXC Status Report/CUC Page 3
• Program Management
– Successfully passed the 5 year milestone on July 23, 2004!
– CXC remained within budget for FY04 and expect FY05 costs to track to POP04 plan. HRC, ACIS & HETG PI subcontracts moved under SAO, 1 Oct 04.
– Staffing: Martin Elvis resigned as Lead for Science Data System Planning, Jonathon McDowell appointed new Lead with Mike Wise (MIT) as Deputy.
– Tom Aldcroft certified as 3rd Chandra Flight Director (replaces Rob Cameron).
– Facilities: Draper Labs moving ahead with new Hill building attachment. ~1500 sf floor space to be lost to 7th floor including the conference room and 5 offices. ACIS room to be sacrificed to allow for new conference room to be built. ACIS Equipment has been relocated to the TST room.
Program Level Status 6/30/04 – 1/25/05
25 January 2005 CXC Status Report/CUC Page 4
25 January 2005 CXC Status Report/CUC Page 5
25 January 2005 CXC Status Report/CUC Page 6
Present 7th Floor Layout
ACIS
25 January 2005 CXC Status Report/CUC Page 7
Proposed7th Floor Modifications
25 January 2005 CXC Status Report/CUC Page 8
• Spacecraft– Continues to operate extremely well overall
– OBC patch for SCS 101 and SCS 31. Modify 101 to contain all CPE patches; modify 31 to call 101 during eclipse ops, 8/23. Improved eclipse safemode transition.
– Helium Channel replacement patch, 9/1, for use of HRC anti-coincidence shield data in place of EPHIN as radiation detector. 6 cases of EPHIN rail voltage anomaly due to high temperatures however no indication of performance degradation; plan to budget ~6 rail voltage drops per year.
– Conducted ACA dark current calibration 9/9 and 12/24 – shows expected trend in warm pixel increase
– Nominal ’04 summer and ’05 winter eclipse seasons, nominal Lunar Eclipse, 11/12
– Radiation events during ’04 eclipse season resulted in contingency commanding and 3 Normal Sun Mode (NSM) recoveries.
– Uneventful Leonids passage 11/19
– Anomalies: Propulsion line cooling, EPHIN rail voltage, unexpected NSM transition
Program Level Status 6/30/04 – 1/25/05
25 January 2005 CXC Status Report/CUC Page 9
• Mission Planning
– Thermal heating and constraints starting to impact mission planning
– 10 SCS 107 runs due to high radiation events (includes major event last week)
– 7 load interrupt TOOs:
Date Target Request
07/05/04 AXP 1048-5937 1 day
08/14/04 GRB 040812 3 days
08/31/04 XRF 040825 3 days
09/13/04 GRB 040912 3 days
10/06/04 GRB 041006 3 days
10/06/04 SGR 1806-20 3 days
12/13/04 BL 0520+675 1 day
Program Level Status 6/30/04 – 1/25/05
25 January 2005 CXC Status Report/CUC Page 10
• Science Instruments and Calibration
– Operating extremely well overall
– ACIS bakeout decision postponed in Sept due to safety concern over use of abort heaters, and simulation questions over contaminant volatility
– HRC anticoincidence shield rates show acceptable correlation with high energy EPHIN channel. Antico rates exceeded proposed threshold for prior radiation safing event during mission, i.e., a safe EPHIN alternative
– 2004 Calibration Review held 10/25-10/26
• OCC
– Linux Migration initial config. 10/4, test started 12/1, to ops 3-4/05
– DSN unexpected commanding, 9/11
Date Version Change
07/23/04 OFLS 11.0 Linux port12/06/04 ONLS 3.10.6 Linux port; test fixes12/06/04 OFLS 11.3 Linux port
Program Level Status 6/30/04 – 1/25/05
25 January 2005 CXC Status Report/CUC Page 11
• Data Processing
– Automatic processing is current; data delivery time averaged <4 days
– Planning underway for Re-processing #3
• CXCDS
Date Version Change
07/07/04 CIAO 3.1 Tools, data model, infrastructure11/29/04 CXCDS 7.4 Automated V&V, MTA DB, AGASC 1.612/14/04 CXCDS 7.5 Cycle 7 support12/15/03 CIAO 3.2 Tool updates (e.g., mkacisrmf), bug fixes
– CalDB 2.28 released 8/11, 2.29 on 11/29, and 3.0 on 12/15
Program Level Status 6/30/04 – 1/25/05
25 January 2005 CXC Status Report/CUC Page 12
• GO and Fellows Program, CDO
– Cycle 6 stage 2 cost review held 10/20, results sent to observers 11/1
– Cycle 6 EPO review held 10/20, results announced 11/16
– Cycle 7 CfP released on schedule 12/15
– Cycle 8 Fellows review held 1/19
– Other: Galaxies workshop 7/7, Fellows Symposium 10/13
• Education and Public Outreach
– 14 Chandra press releases and 7 additional image releases made
Program Level Status 6/30/04 – 1/25/05
25 January 2005 CXC Status Report/CUC Page 13
Mission MetricsMUPS Fuel Usage
25 January 2005 CXC Status Report/CUC Page 14
Mission Metrics (con’t)
25 January 2005 CXC Status Report/CUC Page 15
Mission Metrics (con’t) Scheduled Observing Efficiency
Scheduled Observations
Month Seconds in month (ks)
Scheduled Observing Time (ks)
Scheduled Observing Efficiency
Jan-04 2678.4 1700.3 0.63
Feb-04 2505.6 1807.6 0.72
Mar-04 2678.4 1727.7 0.65
Apr-04 2592.0 1767.3 0.68
May-04 2678.4 1896.3 0.71
Jun-04 2592.0 1769.7 0.68
Jul-04 2678.4 1687.7 0.63
Aug-04 2678.4 1718.9 0.64
Sep-04 2592.0 1640.8 0.63
Oct-04 2678.4 1827.3 0.68
Nov-04 2592.0 1439.6 0.56
Dec-04 2678.4 1796.1 0.67
25 January 2005 CXC Status Report/CUC Page 16
Mission Metrics (con’t)Observing Efficiency
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
Jan-04 Feb-04 Mar-04 Apr-04 May-04 Jun-04 Jul-04 Aug-04 Sep-04 Oct-04 Nov-04 Dec-04
Sch
edu
led
Eff
icie
ncy
25 January 2005 CXC Status Report/CUC Page 17
Data Delivery EffectivenessAs of middle of following month As of 1/13/05
Month Number of Obs
Days to Data Delivery Number Deliv
Number Outstanding
Number Deliv
Number Outstanding
Min Avg Max
Jan-04 65 0 3 19 65 0 65 0
Feb-04 59 0 4 13 59 0 59 0
Mar-04 53 1 6 39 53 0 53 0
Apr-04 36 1 5 18 36 0 36 0
May-04 50 0 5 23 50 0 50 0
Jun-04 66 1 5 27 66 0 66 0
Jul-04 52 1 4 10 52 0 52 0
Aug-04 53 1 3 13 53 0 53 0
Sep-04 50 0 3 12 50 0 50 0
Oct-04 44 0 4 22 44 0 44 0
Nov-04 36 1 5 12 36 0 36 0
Dec-04 73 0 2 7 73 0 73 0
25 January 2005 CXC Status Report/CUC Page 18
Chandra Grant Awards
As of middle of following monthAs of 1/12/05
Month of Data Delivery
No. Grants (1)
No. Grants Awarded
No. Outstand
ing
Avg days to award (2) *
No. Grants
Awarded
No. Outstand
ing
Outstanding AwardsProposal no, Comments
Grants to Non-Federal Institutions
Jan-04 54 35 19 40 54 0
Feb-04 14 12 2 35 14 0
Mar-04 23 15 8 15 22 1 5700535 – PI changed institution, req cancelled. Reissued in Sep. 04.
Apr-04 11 5 6 18 11 0
May-04 4 3 1 10 4 0
Jun-04 15 7 8 16 15 0
Jul-04 13 3 10 19 13 0
Aug-04 12 0 12 n/a 12 0
Sep-04 10 4 6 38 9 1 5300202
Oct-04 10 2 8 22 9 1 5200622
Nov-04 4 0 4 n/a 4 0
Dec-04 31 22 9 25 22 9 6200274, 6200742, 6400243, 6400892, 6500974, 6610143, 6700116, 6700990 (A&B)
* Grant awards delayed due to SAO conversion to new Institute-wide financial software system.
25 January 2005 CXC Status Report/CUC Page 19
Chandra Grant Awards
As of middle of following monthAs of 1/12/05
Month of Data Delivery
No. Grants (1)
No. Grants Awarded
No. Outstan
ding
Avg days to award
(2) *
No. Grants Award
ed
No. Outstan
ding
Outstanding AwardsProposal no, Comments
Grants to Federal Institutions
Jan-04 6 1 5 21 6 0
Feb-04 3 2 1 24 3 0
Mar-04 1 1 0 7 1 0
Apr-04 1 0 1 n/a 1 0
May-04 1 1 0 7 1 0
Jun-04 2 0 2 n/a 2 0
Jul-04 0 0 0 n/a 0 0
Aug-04 3 0 3 n/a 3 0
Sep-04 1 0 1 n/a 1 0
Oct-04 0 0 0 n/a 0 0
Nov-04 0 0 0 n/a 0 0
Dec-04 0 0 0 n/a 0 0
(1)Number of grants eligible for award, for which data were delivered to the observer in the month(2)Average days from data delivery to grant award to observer.
25 January 2005 CXC Status Report/CUC Page 20
Grant Award Efficiency
CXC GO Data Distribution (# Of Days from Data Distribution to Award )July 1, 2004 through October 31, 2004
0255075
100125
7/1
7/16
7/31
8/15
8/30
9/14
9/29
10/14
10/29
# o
f D
ays
SAO Days to Award SAO Outstanding Awards MSFC Outstanding Awards