Upload
doantuong
View
238
Download
2
Embed Size (px)
Citation preview
Production → Duration → Cost
CSTM 370 -ESTIMATING I
Estimate Durations
• Durations should be estimated based on available resources which include labor, material and equipment.
• These durations should reflect the planned resource productivity and anticipated site conditions.
Resource Availability
The key to estimating durations is the availability of resources. It is imperative that the estimator to realistically address labor resources…
• Labor - the main focus…
• Crew Mix
• Who?
• How Many?
Time Unit Selection
Durations can be expressed in any convenient time unit, however, for estimating purposes the following are commonly used:
• Days
• Hours (used for determining cost)
Calculating Durations
Two elements go into calculating durations...
• Work Quantity
• Production Rate
Activity Duration =
therefore…
OR
= 10 days = 400 hrs
Work Quantity Production Rate
500 cy 50 cy / day
500 cy 1.25 cy / hour
Necessary Information
• Quantity of Work
• Production Rate
• Total Hours
• Based on a Crew
• Productivity
• Crew Mix
• Quantity Takeoff
• Outside Information
• Estimating Guides
• Industry and trade organizations
• Manufacturers, Fabricators and suppliers
• Historical Data
• Past Experience
• Constructive Imagination
Quantity & Productivity Data
?
Crew Mix & Cost
Turn man-hours into Costs…
One crews consisting of:
3 carpenters & 2 laborers per crew
3 Carpenters @ 20.50/hour = $61.50
2 Laborers @ 16.25/hour = $32.50
• $32.50 + $61.50= $94/5 = $18.80 Crew Average Wage Rate
• $18.80 x 300 hours = $5,640.00
Formwork: concrete walls
Formwork: concrete walls shoes/wedges/cleats
Formwork: concrete walls corner details
Formwork: concrete walls bulkheads
Formwork: concrete walls control joints
Work-up Sheet Basics…material A Material for wood forms QUANITITY unit price Material Total
List out parts to panels QUANITITY unit price Material Total
List out parts to panels QUANITITY unit price Material Total
List out parts to panels QUANITITY unit price Material Total
Total Mat. A
Material Total A / SF of panels
SF / uses = SF price of panels
B Material to Erect Forms QUANITITY unit price Material Total
List out parts to erect QUANITITY unit price Material Total
List out parts to erect QUANITITY unit price Material Total
List out parts to erect QUANITITY unit price Material Total
List out parts to erect QUANITITY unit price Material Total
List out parts to erect QUANITITY unit price Material Total
Total Mat. B
Material Total B / SF to erect panels
SF / uses = SF price of erect.of forms
C Material of no re-use Same as above Same as Above
D Material of no re-use Same as above Same as Above
E Material of no re-use Same as above Same as above
Totals of A,B,C,D, etc
Work-up Sheet Basics…labor
A Labor to Build Panels
Crew Composition QUANITITY unit price Total Cost A
and
Production
Labor Cost / SF of panels
(NOTE: sf of panels can = 1 panel or total for project)
Labor cost per SF / uses = A
B Labor to Erect Forms QUANITITY unit price Total Cost B
Labor Cost / SF of forms erected
C Labor to Remove Panels Same as Above
D Labor to Clean & Repair Panels Same as Above
Totals of A,B,C,D, etc
Factors Affecting Durations
You plan it and guess what happens? Poor productivity in relation to:
• Nature of the work
• Labor and Equipment Productivity
• Management skill
• Material and Equipment Availability
• Seasonal Conditions
• Work Restrictions
• Quality of Work
• Concurrent Activities
Variables to Evaluate
• Production Rate
• Quantity or work in place
• Total man-hours
• Crew Size or Mix
Work-up Sheet Basics…material Project : Work-up Sheet Example Estimator: JBP Page 1 of 1
Location: Ply Form - 4'x8' panel system Architect: DCH Architects
Based on 40 LF of form 8'-0" @ high Project Size: 320 SF
Date: 8 / 22 / 20xx Sheet Title: Material Only
Checked By: JBP Extensions Checked by: JBP
Notes Description Quantity unit Labor Extension unit Material Ext.
A Mat'l to Build Panels (4'x8')form plywd - 3/4", 9 ply 3 2 0 sf 1 63 5 2 2
2x4 plates 6 0 bf 0 53 3 2
2x4 studs 2 7 0 bf 0 53 1 4 3
misc. hdwe. 1 0 % 10% 7 0
7 6 7
$767 - ÷ 320 sf = $2 40 /sf$2 40 ÷ 4 uses = $0 60 /sf
Totals of A,B,C,D & E
0 60 + 0 57 + 0 39 + 0 06 + 0 09 = $1 71 /sf
Mat’l to Erect & Material of No Re-Use (no re-use items are separate items)
Work-up Sheet Basics…labor
Labor to Erect, Labor to Remove & Labor to Clean & Repair
Project : Work-up Sheet Example Estimator: JBP Page 1 of 1
Location: Ply Form - 4'x8' panel system Architect: DCH Architects
Based on 40 LF of form 8'-0" @ high Project Size: 320 SF
Date: 8 / 22 / 20xx Sheet Title: Labor Only
Checked By: JBP Extensions Checked by: JBP
Notes Description Quantity unit Labor Extension unit Material Ext.
A Labor to Build Panels (4'x8')1 carpenter @ $25.00 1 0 mhr 25- 2 5 0
2 laborers @ $15.00 1 0 mhr 30- 3 0 0
60 min/panel or 1 hour/panel 5 5 0
$550 - ÷ 320 sf = $1 72 /sf$1 72 ÷ 4 uses = $0 43 /sf
Totals of A,B,C,D, etc
0 43 + 8 98 + 3 28 + 0 70 = $13 39 /sf