19
Production → Duration → Cost CSTM 370 -ESTIMATING I

CSTM 370 -ESTIMATING I

Embed Size (px)

Citation preview

Page 1: CSTM 370 -ESTIMATING I

Production → Duration → Cost

CSTM 370 -ESTIMATING I

Page 2: CSTM 370 -ESTIMATING I

Estimate Durations

• Durations should be estimated based on available resources which include labor, material and equipment.

• These durations should reflect the planned resource productivity and anticipated site conditions.

Page 3: CSTM 370 -ESTIMATING I

Resource Availability

The key to estimating durations is the availability of resources. It is imperative that the estimator to realistically address labor resources…

• Labor - the main focus…

• Crew Mix

• Who?

• How Many?

Page 4: CSTM 370 -ESTIMATING I

Time Unit Selection

Durations can be expressed in any convenient time unit, however, for estimating purposes the following are commonly used:

• Days

• Hours (used for determining cost)

Page 5: CSTM 370 -ESTIMATING I

Calculating Durations

Two elements go into calculating durations...

• Work Quantity

• Production Rate

Activity Duration =

therefore…

OR

= 10 days = 400 hrs

Work Quantity Production Rate

500 cy 50 cy / day

500 cy 1.25 cy / hour

Page 6: CSTM 370 -ESTIMATING I

Necessary Information

• Quantity of Work

• Production Rate

• Total Hours

• Based on a Crew

• Productivity

• Crew Mix

Page 7: CSTM 370 -ESTIMATING I

• Quantity Takeoff

• Outside Information

• Estimating Guides

• Industry and trade organizations

• Manufacturers, Fabricators and suppliers

• Historical Data

• Past Experience

• Constructive Imagination

Quantity & Productivity Data

?

Page 8: CSTM 370 -ESTIMATING I

Crew Mix & Cost

Turn man-hours into Costs…

One crews consisting of:

3 carpenters & 2 laborers per crew

3 Carpenters @ 20.50/hour = $61.50

2 Laborers @ 16.25/hour = $32.50

• $32.50 + $61.50= $94/5 = $18.80 Crew Average Wage Rate

• $18.80 x 300 hours = $5,640.00

Page 9: CSTM 370 -ESTIMATING I

Formwork: concrete walls

Page 10: CSTM 370 -ESTIMATING I

Formwork: concrete walls shoes/wedges/cleats

Page 11: CSTM 370 -ESTIMATING I

Formwork: concrete walls corner details

Page 12: CSTM 370 -ESTIMATING I

Formwork: concrete walls bulkheads

Page 13: CSTM 370 -ESTIMATING I

Formwork: concrete walls control joints

Page 14: CSTM 370 -ESTIMATING I

Work-up Sheet Basics…material A Material for wood forms QUANITITY unit price Material Total

List out parts to panels QUANITITY unit price Material Total

List out parts to panels QUANITITY unit price Material Total

List out parts to panels QUANITITY unit price Material Total

Total Mat. A

Material Total A / SF of panels

SF / uses = SF price of panels

B Material to Erect Forms QUANITITY unit price Material Total

List out parts to erect QUANITITY unit price Material Total

List out parts to erect QUANITITY unit price Material Total

List out parts to erect QUANITITY unit price Material Total

List out parts to erect QUANITITY unit price Material Total

List out parts to erect QUANITITY unit price Material Total

Total Mat. B

Material Total B / SF to erect panels

SF / uses = SF price of erect.of forms

C Material of no re-use Same as above Same as Above

D Material of no re-use Same as above Same as Above

E Material of no re-use Same as above Same as above

Totals of A,B,C,D, etc

Page 15: CSTM 370 -ESTIMATING I

Work-up Sheet Basics…labor

A Labor to Build Panels

Crew Composition QUANITITY unit price Total Cost A

and

Production

Labor Cost / SF of panels

(NOTE: sf of panels can = 1 panel or total for project)

Labor cost per SF / uses = A

B Labor to Erect Forms QUANITITY unit price Total Cost B

Labor Cost / SF of forms erected

C Labor to Remove Panels Same as Above

D Labor to Clean & Repair Panels Same as Above

Totals of A,B,C,D, etc

Page 16: CSTM 370 -ESTIMATING I

Factors Affecting Durations

You plan it and guess what happens? Poor productivity in relation to:

• Nature of the work

• Labor and Equipment Productivity

• Management skill

• Material and Equipment Availability

• Seasonal Conditions

• Work Restrictions

• Quality of Work

• Concurrent Activities

Page 17: CSTM 370 -ESTIMATING I

Variables to Evaluate

• Production Rate

• Quantity or work in place

• Total man-hours

• Crew Size or Mix

Page 18: CSTM 370 -ESTIMATING I

Work-up Sheet Basics…material Project : Work-up Sheet Example Estimator: JBP Page 1 of 1

Location: Ply Form - 4'x8' panel system Architect: DCH Architects

Based on 40 LF of form 8'-0" @ high Project Size: 320 SF

Date: 8 / 22 / 20xx Sheet Title: Material Only

Checked By: JBP Extensions Checked by: JBP

Notes Description Quantity unit Labor Extension unit Material Ext.

A Mat'l to Build Panels (4'x8')form plywd - 3/4", 9 ply 3 2 0 sf 1 63 5 2 2

2x4 plates 6 0 bf 0 53 3 2

2x4 studs 2 7 0 bf 0 53 1 4 3

misc. hdwe. 1 0 % 10% 7 0

7 6 7

$767 - ÷ 320 sf = $2 40 /sf$2 40 ÷ 4 uses = $0 60 /sf

Totals of A,B,C,D & E

0 60 + 0 57 + 0 39 + 0 06 + 0 09 = $1 71 /sf

Mat’l to Erect & Material of No Re-Use (no re-use items are separate items)

Page 19: CSTM 370 -ESTIMATING I

Work-up Sheet Basics…labor

Labor to Erect, Labor to Remove & Labor to Clean & Repair

Project : Work-up Sheet Example Estimator: JBP Page 1 of 1

Location: Ply Form - 4'x8' panel system Architect: DCH Architects

Based on 40 LF of form 8'-0" @ high Project Size: 320 SF

Date: 8 / 22 / 20xx Sheet Title: Labor Only

Checked By: JBP Extensions Checked by: JBP

Notes Description Quantity unit Labor Extension unit Material Ext.

A Labor to Build Panels (4'x8')1 carpenter @ $25.00 1 0 mhr 25- 2 5 0

2 laborers @ $15.00 1 0 mhr 30- 3 0 0

60 min/panel or 1 hour/panel 5 5 0

$550 - ÷ 320 sf = $1 72 /sf$1 72 ÷ 4 uses = $0 43 /sf

Totals of A,B,C,D, etc

0 43 + 8 98 + 3 28 + 0 70 = $13 39 /sf