CPUC and PG&E Emails: "You and I can triangulate"

Embed Size (px)

Citation preview

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    1/53

    From: Clanon, Paul

    Sent: 1/10/2011 5:59:46 PM

    To:

    Cherry, Brian

    K (/0=PG&E/0U=C0RP0RATE/CN=RECIPIENTS/CN=BKC7)

    Cc: Johnson,

    Kirk

    (/0=PG&E/0U=C0RP0RATE/CN=RECIPIENTS/CN=MKJ2)

    Bee:

    Subject: Re:

    CPUC

    Newsclips for Monday,

    January 10

    Here's what I

    get

    from

    my

    people. You agree?

    Follows:

    PG E raises

    the pressure in transmission lines to MAOP once every five years based

    on its conservative interpretation of 192.917(e)(4). That code section is not clear on

    whether the maximum pressure experienced in the preceding five years

    means

    the

    preceding

    five

    years prior

    to designating

    the pipeline as HCA fixed)

    or

    just

    the

    preceding

    five

    years

    (moving). PG E uses

    the

    moving

    five-year

    interpretation. As of

    today,

    PHMSA

    has not given a

    clear

    interpretation

    on this.

    Many utilities

    in

    the

    country

    use

    the moving

    five-year

    interpretation to be on the safe side.

    On

    Jan 10, 2011, at 5:19 PM,

    Cherry,

    Brian K

    wrote:

    No, I

    still think that is

    true

    - at least that is what

    I heard

    before.

    I

    think the subtlety

    that

    we weren't

    told by

    our

    operating people

    is

    that it isn't

    required -

    it is industry practice.

    Therefore, if operators

    want

    to maintain MAOP at those levels, they have the right to

    run

    them

    at

    those

    pressures to maintain

    the rating

    -

    but

    aren't

    required

    to do so by law

    if

    they

    are ok with a lower rating. Kirk - is

    that

    right ?

    From: Clanon, Paul

    [mailto:[email protected]

    Sent: Monday,

    January

    10, 2011 5:15

    PM

    To: Cherry, Brian

    K

    Subject:

    Re: CPUC Newsclips for

    Monday, January

    10

    So it

    isn't true that

    operators

    have to operate a line

    at MAO P

    every

    five

    years

    or

    the

    MAOP

    ratchets down

    to

    the

    highest pressure experienced during

    that

    time?

    I

    think

    I've heard

    that from both

    your

    guys

    and

    mine.

    On Jan 10, 2011, at 5:05

    PM,

    Cherry, Brian K wrote:

    SB

    GT S 025

    mailto:[email protected]:[email protected]

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    2/53

    From:  Clanon, Paul

    Sent:  1/10/2011 10:48:13 AM

    Cherry, Brian K  (/0=PG&E/0U=C0RP0RATE/CN=RECIPIENTS/CN=BKC7)To:

    Cc:

    Bee:

    Subject: Re: CPUC  Newsclips for  Monday, January 10

    Thx. Our  guys are doing the same thing, and you and I can triangulate.

    From: Cherry, Brian K [mailto:[email protected]]

    Sent: Monday, January 10, 2011 10:40 AM

    To: Clanon, Paul; Clanon, Paul

    Subject: Fw: CPUC Newsclips for  Monday, January 10

    Will get you the answers.

    From: Loduca, Janet C.

    Sent: Monday, January 10, 2011 10:38  AMTo: Cherry, Brian K

    Cc: Garber, Stephen (Law)

    Subject: RE: CPUC Newsclips for  Monday, January 10

    Brian 

    - the team is working on some follow-up Q&A,

    From: Cherry, Brian K

    Sent: Monday, January 10, 2011 10:05 AM

    To: '[email protected]'; Loduca, Janet C.; Pruett, Greg S.

    Cc: Bottorff, Thomas E

    Subject: Re: CPUC Newsclips for  Monday, January 10

    Not sure. Let me follow up, I was under  the same understanding, Jane or  Greg - can you help

    ?

    From: Clanon, Paul [mailto:[email protected]] Sent: Monday, January 10, 2011 10:03  AM 

    To: 

    Cherry, 

    Brian 

    KSubject: FW: CPUC Newsclips for  Monday, January 10

    What 

    are your  guys saying about the facts in the Chron story 

    yesterday? Contradicted my understanding of  the rules, anyway.

    SB GT&S 001

    mailto:[email protected]:[email protected]:[email protected]:[email protected]

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    3/53

    From: Clanon, Paul

    Sent: Monday, January 10, 2011 9:35  AMTo:

     

    Clark, Richard W.; Halligan, Julie; Stepanian, Raffy; Lindh, Frank; Fitch, Julie  A.; Berdge, Patricks.; Lewis, Kenneth E.

    Subject: Re: CPUC Newsclips for  Monday, January 10

    The 

    Chronicle's 

    story 

    on 

    the 

    2008 

    temporary 

    rise 

    in 

     pressure 

    on 

    Line 

    132 

    to 

    400 

     psi 

    doesn't match what i've heard. What are the facts? Is it standard   practice or  not to raise  pressure up to 

    MAOP to  preserve the maximum? Is 2008 really the only time PG&E has raised   pressure on 

    that line above 375 until the explosion?

    On 

    Jan 

    10, 2011, at 9:01 AM, "Hall, Thomas A."  wrote:

    Good morning. We have clips on the PUC’s work to ensure pipeline safety, high-speed rail and more.

    CPUC NEWSCLIPS

    For  

    Monday, January 10, 2011

    For  newsclips help, contact Tom Hall (tbh) at 916-928-2274

    Newsclips also available on Intranet in .doc format

    To follow a link, hold CTRL, then click with left mouse button

    To return to the top, hold CTRL, then press the “Home” key or  click a Back to Table of  

    Contents 

    link

    TABLE OF 

    CONTENTS

    ENERGY - California

    SJ Mercury  News - Establishing safe pressures for  PG&E gas lines could

    prove huge, costly task

    U  :ords 

    ’ugly,’

     

    California 

    says

    SF Chronicl 

    CGsT 

    urge may have stressed San Bruno line in '08

    Tahoe Daily Tribune Power  through the storm?

    Santa Rosa Press Democrat - PG&E, state PUC should heed plea from

    U.S. regulal DITORIAU

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    4/53

    From:  Cherry, Brian K 

    Sent:  1/10/2011 5:00:39 PM

    To:  'Clanon, Paul' ( [email protected])

    Cc:

    Bcc:

    Subject: Re: CPUC  Newsclips for  Monday, January 10

    We live in parallel universes....

    From: 

    Clanon, 

    Paul [mailto:[email protected]

    Sent: Monday, January 10, 2011 5:00 PM To: Cherry, Brian K

    Subject: Re: 

    CPUC Newsclips for  Monday, January 10

    My guys are having trouble with this one too for  some reason.

    On Jan 10, 2011, at 4:53 PM, "Cherry, Brian K"  wrote:

    Nothing yet. Soon I hope. I heard the response they received from Law was unintelligible.

    From: Clanon, Paul [mailto:[email protected]

    Sent: Monday, January 10, 2011 4:53 PM To: Cherry, Brian K

    Subject: Re: 

    CPUC Newsclips for  Monday, January 10

     Nothing  back  on this yet?

    On Jan 10, 2011, at 10:39 AM, "Cherry, Brian K"  wrote:

    Will 

    get 

    you 

    the 

    answers.

    From: 

    Loduca, Janet C.

    Sent: Monday, January 10, 2011 10:38  AMTo: Cherry,

     Brian KCc: Garber, Stephen (Law)Subject: RE: CPUC Newsclips for  Monday, January 10

    Brian - the team is working on some follow-up Q&A.

    SB GT&S 001

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    5/53

    From: 

    Cherry, 

    Brian 

    K

    Sent: Monday, January 10, 2011 10:05 AM

    To: '[email protected]': Loduca, Janet C.; Pruett, Greg S.

    Cc: 

    Bottorff, 

    Thomas 

    E

    Subject: Re: CPUC Newsclips for  Monday, January 10

    Not sure. Let me follow up. I was under  the same understanding, 

    Jane or  Greg - can you help ?

    From: 

    Cianon, Paul [mailto:[email protected]

    Sent: Monday, January 10, 2011 10:03  AM To: Cherry, Brian KSubject: FW: CPUC Newsclips for  Monday, January 10

    What are your  guys s  out the facts in the

    Chron 

    story 

    yesterday? 

    Contradicted  

    my understanding of  the rules, anyway.

    From: Cianon, Paul

    Sent: Monday, January 10, 2011 9:35 AMTo: Clark, Richard W.; Halligan, Julie; Stepanian, Raffy; Lindh, Frank; 

    Fitch, Julie  A.; Berdge, Patrick S.; Lewis, Kenneth E.

    Subject: Re: CPUC Newsclips for  Monday, January 10

    The Chronicle's story on the 2008 temporary rise in  pressure on 

    Line 

    132 

    to 

    400 

     psi 

    doesn't match 

    what 

    i've 

    heard. 

    What 

    are 

    the facts?

     Is it standard   practice 

    or  not to raise  pressure up to MAOP to  preserve the maximum? Is 2008 really the only time PG&E has raised   pressure on

     that line above 375 until the explosion?

    On Jan 10, 2011, at 9:01 AM, "Hall, Thomas A."  wrote:

    Good morning. We have 

    dips 

    on the PUC’s work to 

    ensure 

    pipeline 

    safety, 

    high-speed 

    rail 

    and 

    more.

    CPUC NEWSCLIPS

    For  Monday, January 10, 2011

    For  newsclips help, contact Tom Hail (tbh) at 916-9282274

    SB GT&S 001

    mailto:[email protected]:[email protected]:[email protected]:[email protected]

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    6/53

    Newsclips also available on Intranet in .doc format

    To follow a link, hold CTRL, then click with left mouse button

    To 

    return 

    to 

    the 

    top, 

    hold 

    CTRL, 

    then 

    press 

    the 

    “Home” key or  click a Back to  Table of  Contents link

    TABLE OF CONTENTS

    ENERGY - California

    SJ Mercury News - Establishing  safe pressures for  PG&E

     

    gas lines could prove

    huge, 

    costly 

    task

    UPI ■ PG&E records ’ugly,’ California says

    SF Chronicle - PG&E surge may have stressedSan

     Bruno l ine in ’08

    Tahoe Daily Tribune Power  through the

    storm?

    Santa Rosa Press Democrat - PG&E, state 

    PUC should heed plea from U.S. regulators

    (EDITORIAL)

    Marin Independent Journal - PG&E should

    give customers a choice on  SmartMeters(EDITORIAL)

    TELECOM - California

    LA  Wh.-*t’v tu hiatus for   Alls')outages? (COLUMN)

    TRANSPORTATION 

    California

    San Mateo Daily Journal - High-speed  railhead ditches Caltrain

    Fresno Bee - Path of  high-speed rail worriesValley farmers

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    7/53

    LA Time' F *po Line bidders under  new scrutiny in fraud and construction problems

    WATER - 

    California

    Monterey 

    Hera 

    ttle 

    brews 

    over  

    water  

    fee

    Fresno Bee - Dams release excess water  asrain fills Valley reservoirs

    ENERGY - 

    National

    Treehugger  -  A Black Market for  100-WattBulbs?

     U.S. Ban Looms

    TELECOM - National

    Connected 

    Planet 

    Broadband 

    payback 

    not just

     

    about subscriber  revenues

    Politics/General/Miscellaneous

    Bakersfield Californian - Brown should give

    Dean Florez 

    seat 

    on PUC (EDITORIAL)

    Oakland Tribune - Nation's first transgender 

    trial  judge overcame discrimination

    SF 

    Chronicle 

    Brown 

    gets 

    hearing 

    on 

    sale 

    of buildings postponed

    LA Times - Gov. Jerry Brown wants to tamebudget with tax extensions, deep cuts

    LA Times - Selling stat»   ts would be folly(COLUMN)

    ENERGY - California

    SJ Mercury News - Establishing safe pressures

     for  PG&E gas lines could prove huge, costly task

    By Steve Johnson and Pete Carey, Jan 9

    As 

    state 

    regulators start 

    the process of  making PG&E

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    8/53

    verify that the pressure limits for  its natural gas pipelines are safe, they have been dismayed by the disorganized state

     of  the utility's records, complicating a project that is now predicted to take years, cost millions and inconvenience customers along the way.

    Based 

    on 

    what 

    the 

    California 

    Public 

    Utilities 

    Commission 

    has determined 

    so far, 

    it appears at least 450 miles - or  one fourth - of  the 1,800 miles of  gas transmission

     

    pipes that PG&E operates in urban areas 

    may need 

    to undergo pressure tests - typically 

    done with liquid or  gas - to establish the safe level. That's because the company may not have paperwork  justifying

     

    the limits it has set for  those pipes.

    Just locating all the records that describe the condition of  PG&E's vast pipeline network could prove onerous, commission officials

     

    told 

    the Mercury News last week. They

     

    said the documents appear  to be scattered hither  

    and 

    yon, 

    with 

    some 

    in 

    dusty 

    file 

    cabinets, 

    remote 

    field 

    offices 

    and 

    other  

    places 

    the 

    company 

    isn't even 

    sure 

    about. Even if  all the records can be found, it's unclear  

    how much stock can be put in their  accuracy, given the recent revelation that PG&E's paperwork mischaracterized the portion of  San Bruno pipe that exploded Sept. 9, killing eight people and destroying 38 homes.

    "We've been putting them under  the microscope, and when you do that, you find things that are ugly,” said Julie Halligan, deputy director  of  the utility commission's consumer  protection and safety division. 

    "That 

    doesn't 

    increase 

    your  

    confidence.”

     After  a recommendation from the National Transportation Safety Board, the CPUC last week ordered PG&E to identify all manufacturing, maintenance and other  documents for  its gas pipes so the utility can determine the lines' maximum allowable operating

     pressure, based on each pipe's weakest part. If  the utility can't do that, the CPUC board recommended, the

     

    utility should 

    conduct pressure tests to establish the safe level - a procedure that involves

     

    shutting off  the gas to customers.

    What 

    the 

    CPUC 

    didn't 

    reveal - 

    until 

    the 

    interview 

    with 

    the 

    Mercury 

    News 

    is  just how 

    involved 

    it expects 

    the 

    task of  finding records and testing pipes to be.

     Although the cause of  the San Bruno blast is still under  investigation, the NTSB issued a rare "urgent" advisory last week, in part after  discovering the pressure in the San Bruno transmission pipe spiked right before the blast but never  reached its maximum allowable operating

     pressure. The pipe had been pressure tested

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    9/53

    at that 

    maximum level two years before the explosion.

    In addition, although PG&E's records described the burst pipe section as seamless, the federal agency found that the segment actually had been welded along its length, making it potentially more susceptible 

    to 

    rupture.

    PG&E officials declined to comment to the Mercury News late last week about the CPUC's latest concerns. But the company wrote the CPUC on Friday that it hoped to deliver  the records the agency is seeking by March 15, adding, "This is a substantial undertaking."

    Paul Clanon, the commission's executive director, agreed. "The records search we ordered PG&E to undertake is unprecedented,"

     

    he said. "The pure 

    logistics of  getting to all those records is daunting."

    Many 

    of  the 

    more 

    than 

    6,000 

    miles 

    of  

    PG&E's 

    gas 

    transmission lines were installed decades ago when 

    the utility wasn't required to keep extensive paperwork on the pipe's method of  construction, inspection history and other  factors. Consequently, in some cases PG&E has only limited or  incomplete records, Halligan said, and in other  instances, "they have no records whatsoever."

    State officials hope to find multiple documents that provide matching descriptions about each pipe segment, giving them some assurance the records accurately reflect what is underground.

    But in cases where the records are contradictory, fuzzy or  nonexistent,

     line segments will have to be pressure tested, they said.  Although that process will shut off  gas to customers in the affected area, the utility could deliver  gas via trucks or  alternate distribution lines to areas where pipes are being tested. How all that might work, and how many customers will be affected, has yet to be determined. PG&E has 2.9 million natural gas customers in the Bay  Area.

    "It potentially could be really big in terms of  the disruption" for  the public, said Frank Lindh, legal 

    counsel 

    to 

    the 

    CPUC.

    Gas pressure already has been reduced by 20 percent in five Bay  Area transmission lines because of  concerns that the ruptured San Bruno segment may not be the only weak spot in PG&E's pipe network. Depending

     on what other  problems may surface from PG&E's record search, the utilities commission may have to reduce the pressure in additional lines, which

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    10/53

    could result in other  customers not getting as much gas as they need.

    Similarly 

    unknown is the price tag for  all this work.

    Lindh estimated the pressure testing alone might cost 

    "multiple 

    tens 

    of  

    millions" 

    of  

    dollars. 

     And 

    if  the 

    pressure tests reveal weaknesses that require pipe segments to 

    be replaced, the bill could increase much more. State officials said it typically costs $6 million to replace one mile of  transmission pipe. Who will pick up the bill is yet to be decided.

    None of  this will happen overnight.

    "It's going to take years," Clanon said, though he stressed

     that "doesn't mean the system is unsafe in the meantime.

     

    We're 

    taking 

    the 

    steps 

    to insure the safety of  the system by reducing pressure and taking 

    other  

    steps."

    He added that his agency is committed to improving PG&E's pipeline operations.

    "It will get done," Clanon said. "The sense of  urgency we feel at the CPUC is huge. People died at San Bruno."

    Back to Table of  Contents

    UPI - PG&E records 'ugly,' California says

    By Staff . Jan 10

    SACRAMENTO - Records related to natural gas transmission

     

    pipelines in California 

    operated by Pacific Gas and Electric Co, are "ugly,” a state utility director  said.

    The California Public Utilities Commission ordered PG&E

     

    to find documents related to its California gas 

    transmission 

    network so it can examine the operating 

    pressure in 

    the pipes to find weak spots.

    The 

    company, 

    the 

    San 

    Jose 

    Mercury 

    News 

    reports, 

    might not have all of  the paperwork. The CPUC, meanwhile, notes that about 25 percent of  the companies 1,800 miles of  pipeline might need pressure testing.

    "We've been putting them under  the microscope, and when you do that, you find

     

    things 

    that are ugly," said 

    Julie Halligan, a deputy director  of  consumer  protection

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    11/53

    and safety division at CPUC. "That doesn't increase your  confidence."

    Most of  the gas transmission lines were installed before extensive record-keeping was required, the newspaper 

     

    report 

    adds. Hailigan said in some 

    circumstances 

    there 

    are 

    no 

    records 

    about 

    California's 

    natural 

    gas 

    pipelines.

     A natural gas pipeline owned by PG&E burst Sept. 9, sparking a massive fireball that ripped through a San Bruno neighborhood. The explosion killed eight people and

     destroyed 37 homes.

    The National Transportation Safety Board said it found 

    weld issues along the San Bruno pipeline that may have led to the rupture.

    Back to Table of  Contents

    SF Chronicle - PG&E surge may have stressed 

    San Bruno line in '08

    By Jaxon Van Derbeken, Jan 9

    Pacific Gas and Electric Co. briefly raised the pressure on its San Bruno natural gas line to the brink less than two years before the explosion that killed eight people - an action experts call a "huge gamble" that they fear  made the pipe more susceptible to failure.

     A 

    Chronicle 

    investigation 

    into 

    events 

    before 

    the explosion

     

    led PG&E officials to reveal that for  two hours on Dec. 9, 2008, the company intentionally boosted gas pressure to the maximum legal limit of  400

     pounds per  square inch. That was more pressure than PG&E has ever  acknowledged using on the line, which it normally ran at 375 pounds per  square inch.

    The utility initially explained that it had boosted the 

    pressure because federal regulations required it to do so, but later  conceded

     that its interpretation was inaccurate. It then explained that the spike was "part of  our 

     

    operating practice."

    This is 

    the first time the company has ever  

    acknowledged running the San Bruno line at its legal 

    maximum - a level now under  scrutiny by federal investigators in light of  revelations that PG&E had erroneous records about the pipeline's characteristics.

    The next time the pressure exceeded 375 pounds per  square inch on the line was on Sept. 9, when a

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    12/53

    malfunction caused a 

    surge to 386 pounds - a spike 

    that coincided with the deadly explosion and fireball in 

    San Bruno 

    that destroyed 38 homes.

    Early strain in line

    PG&E's 

    intentional 

    surge 

    in 

    2008 

    could 

    have 

    strained the San Bruno line and made it more vulnerable to 

    failure at lower  pressure levels, according to experts interviewed by The Chronicle. Strain caused by one surge, they said, can weaken a pipe to the point where it can fail at a lower  point when pressure surges again.

    "If  there was a defect very close to failure, it could cause that defect to enlarge," said Robert Eiber, a nationally recognized pipeline expert. "I'm frankly amazed they were willing

     

    to take 

    the risk. I don't know 

    if  they were aware of  the risk they were taking or  not. But in a case like this, it was a huge gamble."

    When queried by The Chronicle, PG&E initially said federal regulators require

     

    that 

    a pipe be run at full strength at least once every five years in order  for  the utility to "preserve" its legal capacity.

    If  the pressure ever  exceeds that limit, the utility is obligated to

     conduct a costly, high-priority inspection of  the line.

    Had PG&E not spiked the pressure on the 30-inch transmission

     

    line running from Milpitas to San Francisco, utility spokesman Denny Boyles first said, 

    the 

    pipe's 

    capacity 

    would 

    have 

    been 

    permanently 

    reduced to 375 pounds per  square inch under  federallaw.

    Changing stories

    But the spokesman later  backtracked when asked to cite the specific federal regulation, saying PG&E's earlier 

     

    response was "too general and as a result inaccurate.” He maintained that PG&E still believed that 400 pounds per  square inch was a "very safe level" for  the San Bruno line.

    In 

    subsequent 

    statement, 

    the 

    company 

    no 

    longer  

    said 

    federal law had prompted its action.

    "Putting the pressure up to 400 was part of  our  operating

     practice," Paul Moreno, a PG&E spokesman, said Friday. He said the utility operates its lines at their  maximum once every five years. He declined to elaborate.

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    13/53

    The U.S. Pipeline and Hazardous Materials Safety  Administration said in a statement that the agency "does

     

    not require a pipeline 

    operator  to do anything" to preserve the legal pressure capacity of  gas transmission

     lines.

    When 

    asked 

    about 

    the 

    surge, a spokeswoman

     

    for  

    the 

    California 

    Public 

    Utilities 

    Commission, 

    which 

    regulates PG&E, said only that "we do not have rules about spiking artificially."

    The National Transportation Safety Board's investigation

     into the cause of  the San Bruno blast is looking at any previous incidents of  pressure surges. "That's

     

    going to be part of  our  investigation, and we will be looking at the pipeline's

     

    operating history," said 

    Peter  

    Knudson, a safety board spokesman.

    Experts shocked

     Although the San Bruno line did not fail during the 2008 pressure

     

    spike, experts interviewed by The Chronicle said the utility had been taking a terrible chance.

    Richard 

    Kuprewicz, a pipeline safety consultant in 

    Redmond, Wash., said that in spiking the pressure, PG&E's action

     

    created the likelihood 

    that "stable operations may

     

    be stressed and 

    become unstable.”

    "You  just don't go out there and do real-time pressure tests

     of  this magnitude on lines without doing careful 

    thought 

    and 

    evaluation," 

    Kuprewicz 

    said. 

    "This 

    is 

    gas 

    transmission pipeline. This is in the middle of  a city. 

    You 

    don't  just go raise the pressure on pipelines and hope they stay together."

    Eiber, a pipeline integrity consultant and researcher  in Columbus,

     Ohio, with 50 years of  experience in the business, said

     

    the 

    natural gas industry all but 

    abandoned 

    artificial 

    spikes after  a 1960 incident in 

    New Mexico in 

    which a pipe split along its seam for  8 miles during such a

     

    test. No one was hurt.

    The September  disaster  in San Bruno, Eiber  said, "demonstrated

     

    what 

    could 

    have 

    happened 

    in 

    their  spike

     

    test. It's not a good practice.”

    Boyles, the PG&E spokesman, declined to respond to the

     

    criticisms, citing the federal investigation into what 

    caused the explosion.

    Records problems

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    14/53

    The intentional pressure 

    spike was also 

    problematic because questions have

     emerged since the explosion about

     

    whether  PG&E knew the real strength of  the San Bruno line when it set the maximum gas pressure at 400 pounds per  square inch in

     

    1970.

    The 

    utility 

    has 

    conceded 

    that 

    its 

    records 

    erroneously 

    showed 

    that the 

    San 

    Bruno 

    section 

    of  the 

    pipeline, installed in 1956, had no seams. In fact, federal investigators found, the ruptured portion of  the line not only had seams, but was pieced together  in several 4- foot-long

     sections that were constructed to unknown, potentially

     inferior, specifications.

    The National Transportation Safety Board says its investigators

     are examining the quality of  seam welds that held the pipeline together  - welds that PG&E did not

     

    know 

    existed when it 

    set the pipeline's maximum pressure. The

     

    federal agency has not reached a 

    conclusion 

    about 

    what 

    caused 

    the 

    explosion.

    The board said last week that "it is critical to know all the

     

    characteristics of  a pipeline in order  to establish a valid MAOP (maximum allowable operating pressure) below which the pipeline

     can be safely operated. The NTSB is concerned that these inaccurate records may lead to incorrect" maximum pressure levels.

    James Hall, a former  chairman of  the safety board and now an independent pipeline safety advocate, said PG&E's

     

    erroneous records about the line could have 

    led the utility to set the maximum pressure level too 

    high.

    "If  you don't have the records on the pipe, how are you setting the pressure?" Hall said.

    Inspection issues

    In fact, federal pipeline officials say, the intentional 2008

     

    surge 

    might have had some bearing on the 

    validity of  PG&E's subsequent inspection of  the line in November  2009,

     

    which found no problems in the pipe.

    The 

    only pressure 

    figure the government considers 

    relevant, 

    according 

    to 

    the 

    federal 

    pipeline 

    safety 

    agency, is the highest level at which the line was run 

    from 

    about 1997 to 2002, when Congress passed a law requiring

     regular  inspections of  pipelines in urban or"high consequence" areas.

    That peak becomes a benchmark that could, if  

    exceeded, activate a new inspection.

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    15/53

    PG&E officials said Friday 

    that the utility did not run the line above 375 pounds per  square inch from 2000 to 2002,

     

    but 

    that older  

    records were unavailable.

    PG&E has said it kept the San Bruno line's pressure at 375 pounds per  square inch because it was connected 

    to 

    three 

    other, weaker  

    lines 

    with that 

    capacity. 

    PG&E 

    pinched 

    off  those 

    lines 

    for  the 

    2008 surge,

     

    the 

    utility said.

    Putting stress on welds

     Any surge above the benchmark level - intentional or  otherwise

     - is exactly the type of  incident that, under  the 2002 law, should have

     

    forced PG&E to conduct a high-priority inspection using a technique that could detect weakness in a pipe's welds, federal

     

    officials said.

    That's 

    because 

    pressure 

    surges 

    can 

    put 

    stress 

    on 

    line's welds, meaning the line is no longer  considered "stable," the federal pipeline safety agency said.

    PG&E went forward with the November  2009 inspection using a method suitable mainly for  detecting pipe corrosion, not weakness in welds.

    That method, called direct assessment, involves 

    researching records on a pipeline, electronically mapping it using ski-pole-like devices, and digging spot- check

     

    holes 

    to 

    examine 

    the 

    pipe.

    The 

    method 

    considered 

    more 

    reliable 

    for  

    finding 

    weak 

    welds involves 

    shutting down a pipe, 

    pumping high- pressure water  into it, and then repairing any damage that

     

    materializes. 

    PG&E has avoided using it on most of  its gas transmission pipes, citing the inconvenience to customers and cost of  shutting down lines.

    Nevertheless, 

    PG&E's intentional 

    spike of  the line's 

    pressure might have prevented it from using direct 

    assessment in its 2009 inspection, federal officials indicated.

    "Direct 

    assessment 

    is not

     

    considered 

    viable 

    assessment 

    method 

    when 

    manufacturing 

    and 

    construction defects are 'unstable,' and 

    therefore would not be permitted under  federal regulations," the pipeline safety agency said.

    PG&E did not respond to queries about the legality of  the

     

    2009 inspection. The 

    utility has consistently 

    defended 

    direct assessment tests 

    as being reliable.

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    16/53

    'Reckless 

    enterprise'

    Hall, the former  National Transportation Safety Board chairman, called the 2008 spike "a reckless enterprise" that was "obviously an exercise for  their  financial situation, not safety."

    "You are dealing with pipe that has been in the ground more than 50 years, it has never  had an internal inspection tool in it, has incomplete records, and they now artificially spike the line?” Hall said. "Why would you take such a high-risk action in a high-consequence area?"

    Every spike above normal operating pressure presents a risk of  disaster  in such an old pipeline, Hall said.

    "You can roll the dice many times," he said, "before you come up with snake eyes."

    Back to Table of  Contents

    Tahoe 

    Daily Tribune - Power  through the 

    storm?

    Outages raise concerns as a new company takes over 

    By  Adam Jensen. Jan 10

    SOUTH LAKE TAHEO, Calif.  —  Concerns about how a new, smaller  electric company will be able to 

    respond 

    to 

    widespread 

    power  

    outages 

    persist 

    following 

    a change in energy providers in the Lake Tahoe Basin.

    Liberty 

    Energy  —  California Pacific Electric Company completed its purchase of  Sierra Pacific Power  Company's electrical distribution and generation assets Jan. 1.

    The power  company was previously referred to as CalPeco

     

    in California Public Utilities Commission documents. Sierra Pacific Power  Company is a subsidiary

     of  NV Energy and included the Nevada corporation's California operations.

    Two South Lake Tahoe City Council members, Tom Davis and Bruce Grego, said they are concerned with how

     the new company will be able to respond to power  outages like those experienced last week.

    NV Energy serves about 1.2 million customers in Nevada, while Liberty Energy's coverage includes 46,000

     

    customers in Nevada, Placer, Sierra, Plumas,

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    17/53

    Mono, 

     Alpine 

    and El Dorado counties.

    “They're a small company; do they have the resources to deal with a power  outage?” Davis asked Thursday.

    Wet, heavy snow knocked 

    out 

    power  to almost 10,000 

    customers 

    at 

    the 

    South 

    Shore 

    Dec. 

    29. 

     Although 

    most customers' electricity was restored Dec. 30, some 

    were without power  for  more than 48 hours.

    Several NV Energy crews from Reno and the Carson Valley were used to help restore power  at the lake.

    Bob 

    Dodds, president and general manager  of  Liberty 

    Energy, said the new company will have two crews at the North Shore and two crews at the South Shore,  just like Sierra Pacific did.

    He also said the new power  company will also be able 

    to 

    use 

    resources 

    from 

    NV 

    Energy 

    when 

    necessary.

    “We have agreements with NV Energy that we can pull in crews

     as we need,” Dodds said.

    The agreements are formal, but are not available for  public

     

    review because they are proprietary, Dodds said.

    Dodds 

    said the goal is to make the transition between 

    Sierra Pacific and Liberty Energy as seamless as 

    possible.

    The South Lake Tahoe City Council approved transfer  of  the city's franchise agreement from Sierra Pacific to Liberty

     Energy in October. The 25-year  agreement ends

     in 2018.

    Councilman Bruce Grego was the lone dissenting vote against the transfer. He asked for  a delay so the transfer  could receive further  scrutiny. On Thursday, he

     

    said 

    the City 

    Council should have been more 

    critical of  transferring the franchise agreement, possibly placing conditions on the new company to ensure service

     standards.

     At the time, then-Councilman Bill Crawford said it 

    would be “frivolous” to delay a vote on the item because the council cannot prevent NV Energy from selling

     

    its property.

    The lack of  a vested interest in the area covered by Liberty Energy by NV Energy could delay help to the South

     

    Shore in the case of  widespread power  outages,

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    18/53

    Davis said. Using another  company's resources could 

    also pass along? costs to consumers, Davis added.

    Customers' monthly bills should remain at the same level, but will be itemized differently because of  the switch,

     

    Dodds said. He said a rate increase in 2012 

    should 

    be 

    similar  

    to 

    what 

    Sierra 

    Pacific 

    would 

    have 

    proposed.

    NV Energy spokeswoman Faye  Anderson did not return a request for  comment Thursday.

    Davis called the potential for  long-lasting, widespread 

    power  outages in winter  “very disturbing,” especially for  seniors

     

    or  others who have trouble leaving a residence in an emergency.

    Both Davis and Grego said they've asked City Manager  Tony O'Rourke to discuss emergency 

    response 

    preparations 

    at 

    an 

    upcoming 

    council 

    meeting, especially when it comes 

    to keeping the lights on in the city.

    Neither  councilman had any doubt that the city will see a storm similar  to last week's in the future.

    Grego said he hoped Liberty Energy would be a part of  the discussions with the city. But what the city can do beyond that may be limited, Grego said.

    “I think the only thing we can do is wait and see how they

     

    perform,” Grego said.

    Back to Table of  Contents

    Santa Rosa Press Democrat - PG&E, state 

    PUC should heed plea from U.S. regulators  

    (EDITORIAL)

    By Editorial Board. Jan 8

    When a natural gas pipeline exploded in San Bruno on Sept. 9, we, along with many others, suspected it was further 

     

    evidence 

    of  our  

    nation's 

    aging 

    infrastructure.

    However, we withheld final  judgment until the investigation of  the cause of  the explosion, which killed eight people and demolished 37 homes, could be completed.

     

    Four  months later, the verdict is in, and it's 

    worse than suspected.

    Not only was 

    the 

    gas line rupture the result of 

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    19/53

    infrastructure failure, PG&E didn't even have accurate 

    records about the type of  pipes it was using underground.

    PG&E's own engineering reports said that the San Bruno pipeline was seamless and had been built by 

    one 

    company. 

    Further  

    investigation 

    showed 

    that 

    the 

    steel 

    segment had 

    weak 

    longitudinal seams 

    and 

    that the

     pipe had ruptured in a segment that had been seam-weided. Pius, not ail of  the segments were made by the same company, according to federal officials.

    Because of  that, federal regulators this week sent an urgent message asking PG&E to make sure it is operating natural gas pipelines at safe pressures and, if  uncertain, to consider  scaling back on the pressure to 80 percent until the lines can be tested.

    Given that most houses and business within Sonoma 

    County 

    receive 

    their  

    gas 

    and 

    electric 

    service 

    from PG&E,

     

    locals should take notice.

    The warnings came in two waves. On Monday, the National Transportation Safety Board called on PG&E to complete an “intensive record search” including possibly doing pipeline testing.

     A day later, the federal Pipeline and Hazardous Materials Safety  Administration issued a directive to all of  the nation's gas line operators calling for  “detailed threat and risk analyses” on the pipeline systems.

    The 

    NTSB 

    lacks 

    the 

    authority 

    to 

    force 

    PG&E 

    to 

    take 

    action. But the California Public Utilities Commission does have such authority  —  and should use it. In fact, these urgent recommendations by federal regulators should be as embarrassing to the CPUC as it is to PG&E. It raises the question, why wasn't the CPUC ensuring that PG&E maintains proper  records while at the same ensuring pressure is at safe levels?

    Maintaining infrastructure  —  let alone maintaining records of  infrastructure  —  is not sexy business. Few citizens

     

    are likely to step up at a CPUC meeting or  a PG&E shareholder  meeting demanding proper  

    attention 

    to 

    and 

    funding 

    for  

    maintaining 

    infrastructure, 

    particularly in a time of  austerity.

    Nevertheless, the dangers of  backing off  on such upkeep are now clear  and quantifiable: Eight lives lost. Thirty-seven homes demolished.

    If  PG&E hopes to show its customers it's committed to safety and not taking shortcuts, it will follow the

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    20/53

    recommendations of  

    federal regulators quickly. The 

    state PUC should do the same.

    Back to Table of  Contents

    Marin Independent Journal - PG&E should 

    give 

    customers 

    choice 

    on 

    SmartMeters 

    (EDITORIAL)

    By Editorial Board. Jan 9

    IF PACIFIC GAS and Electric Co. really cared about good public relations, it would give its customers the option of  having SmartMeters installed.

    Right now, PG&E is trying to bully its way through a P.R. disaster  in Marin  —  when it needs to repair  a few old ones.

    On Tuesday, the Marin Board of  Supervisors voted for  a one-year  emergency ban on the installation of  the electronic meters that replace mechanical devices that had to be manually checked by meter  readers. The wireless meters allow PG&E and its customers to monitor  power  consumption far  more closely, which has many

     

    advantages. The new meters also mean PG&E doesn't have to pay meter  readers to visit every house and business that has a meter.

    SmartMeters were launched, with the state Public Utilities Commission's blessing, as a "green" measure, 

    an 

    easy 

    way 

    for  

    ratepayers 

    to 

    keep 

    track 

    of  their  

    own power  usage as a way to reduce consumption  —  and 

    potentially their  power  costs.

    What PG&E and the PUC didn't expect was opposition 

    to the meters over  worries that the wireless devices could pose health risks. That opposition has been especially strong in pockets

     of  Marin.

     A number  of  Inverness residents made news when they created a blockade in an effort to stop workers from

     getting into town to install the meters. Some even were arrested.

    That display of  civil disobedience was not the right approach. Protesters, while preventing PG&E from having meters installed at their  homes, also were preventing the utility from changing meters on other  residents' homes, some of  whom might want the new devices.

    PG&E maintains that SmartMeters create less

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    21/53

    exposure to electromagnetic frequencies than regular  use of  a cellphone or  a microwave oven. It could be right.

    But the utility giant has a major  public-trust problem, much of  which is its own doing, including arrogantly 

    spending 

    tens 

    of  

    millions 

    in 

    last 

    year's 

    failed 

    effort 

    to 

    get state voters

     

    to 

    approve 

    Proposition 

    16. 

     And 

    it 

    will be dealing with fallout from the pipeline explosion in San Bruno that killed eight people for  years.

     Assemblyman Jared Huffman has introduced legislation to halt SmartMeter  installation until the California Council of  Science and Technology can collect

     information, analyze it and issue findings about the devices.

    Local  jurisdictions may not be able to ban the installation

     of  SmartMeters. PG&E gets its marching 

    orders 

    from 

    the 

    PUC. 

    But 

    there 

    is 

    enough 

    concern 

    that PG&E,

     

    rather  than forcing SmartMeters onto its customers, should give its ratepayers a choice.

    That choice may come with a price if  PG&E needs to 

    pay meter  readers to go to homes where customers want to keep their  mechanical meters. That's a choice each customers would have to make, but it's a choice PG&E would be wise to offer. PG&E would be wise to remember  these are customers who are unhappy.

    The reality is that most likely will be OK with their  

    SmartMeters.

    Part 

    of  PG&E's  job is responding to storms and fixing 

    damage. The company didn't see this storm coming. Giving ratepayers a

     choice is  —  at this stage  —  an overdue repair.

    Back to Table of  Contents

    TELECOM - California

    LA 

    Times 

    What's 

    to 

    blame 

    for  

     AT&T 

    outages? (COLUMN)

    Recent storms caused many  AT&T customers in California to lose phone, TV and Internet service, with about 70,000 still affected.

    By David Lazarus. Jan 6

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    22/53

    Steve Robin works out of  his La Crescenta home as a real estate investor  and property manager. He relies on

     

     AT&T for  his phone line, fax line, broadband Internet

     connection and TV service.

    So it wasn't a very ho-ho-ho moment when Robin, 50, 

    became 

    one 

    of  

    thousands 

    of  

     AT&T 

    customers 

    statewide who

     

    lost service 

    Christmas 

    Day 

    as 

    series of  powerful storms clobbered California.

    His frustration grew as the days passed and the only thing  AT&T service reps could tell him was that technicians were on the case. It wasn't until Monday night  —  10 days after  the outage began  —  that Robin's service

     

    was finally restored.

     And he can consider  himself  lucky.  As of  this week,  AT&T said it still had about 70,000 "trouble tickets" to address throughout the state and particularly in 

    Southern 

    California. 

    That's 

    about 

    10 

    times 

    the 

    usual number 

     of  customers reporting that their  service is on the fritz.

    Verizon also experienced extensive 

    outages, although the company declined to specify how many customers were

     

    affected. Time 

    Warner  

    Cable said its service was 

    disrupted in many SoCal neighborhoods.

    The problems highlight the vulnerability of  the telecom network  —  and what technicians say is a shortage of  available manpower  when

     

    service 

    goes 

    down. Recent cutbacks by telecom companies have thinned the 

    ranks 

    of  skilled 

    workers 

    capable 

    of  responding 

    to 

    an emergency.

    It's unreasonable 

    to 

    expect phone and cable 

    companies to keep work crews around on a  just-in 

    case basis. The trick is finding the correct staffing balance that allows the greatest flexibility.

    The storm-related loss of  phone, TV and Internet service illustrates how

     

    reliant we've come to be 

    on 

    these 

    technologies, and how isolated (not to mention unproductive) we become when they're

     

    taken away.

    "I 

    was 

    dead 

    in 

    the 

    water," 

    Robin 

    said. 

    "To 

    keep 

    working, I 

    had to take my laptop to Starbucks, make business

     

    calls on my cellphone, go to other  people's homes. I had to do whatever  I could to stay connected."

    I know the feeling. Our  home also lost Internet access for  a week and it was like having the umbilical cord severed.

     

    Suddenly all that life-sustaining data was

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    23/53

    gone.

    On the plus side, it was a holiday week and neither  my wife nor  I needed to be online.  And our  family was able to play some cutthroat games of  Clue (isn't it always Col.

     Mustard committing the foul deed?).

    But it's a drag being without a service that we pay handsomely for  and that we expect to be provided with a modicum of  stability. Isn't that what ail those rate increases are about —  keeping the network up to snuff?

    You never  realize how much you've come to depend on having ail

     of  cyberspace piped into your  home until the

     line suddenly goes dark.

    John 

    Britton, an  AT&T spokesman, said he was as 

    surprised as anyone by the scope of  the recent 

    outages.

    "We've seen the most water  damage to the network in more

     

    than 10 years," he said.

    Britton said hundreds of  extra technicians have been 

    rushed to the Southland from Northern California and other  states to

     

    help get the 

    system up 

    and running again. He said  AT&T hopes to have everything fixed by early February.

    "We're putting maximum resources into dealing with this," Britton said.

     A pair  of   AT&T technicians, who asked that their  names

     be withheld out of  concern that it could cost them their 

     

     jobs, told me in separate interviews that this is indeed the

     case  —  the company is putting on a full- court press

     

    to 

    deal with the situation. They said they 

    and their  cohorts are working mandatory seven-day weeks

     

    and 12-hour  days.

    But 

    the technicians said the outages didn't need to be 

    this bad.

    "The 

    company 

    hasn't 

    kept 

    up 

    with 

    maintenance 

    and upgrades for  the

     

    network," one 

    said. 

    "That's why 

    the problems are so widespread."

    The technicians said cables and phone lines wouldn't have been so

     

    waterlogged 

    if  their  casing and insulation had been

     inspected and repaired at more regular  intervals. Both cited hungry squirrels chewing on lines as

     a key reason water  gets in.

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    24/53

    They also said flooding of  underground vaults and 

    pipes wouldn't have caused so much damage if  the facilities had been regularly maintained.

    The technicians said the network would be better  

    maintained, 

    and 

    repairs 

    would 

    be 

    faster, 

    if  

     AT&T 

    hadn't lost so many workers in cutbacks.  About 525 California 

    technicians left the company or  were reassigned last March.

    Britton disputed that  AT&T was unprepared for  the storm damage.

    "This is an emergency situation," he said. "We're not the only ones affected. They even had to close down the freeway because of  the weather."

    He said the number  of  technicians has declined in 

    tandem 

    with 

    declines 

    in 

    the 

    number  

    of  

    wire-line 

    phone 

    customers (as opposed to wireless customers). "We staff  for  the amount of  work we have,” Britton said.

    "This network operates virtually flawlessly 99.999% of  the time,” he added. "When it doesn't, we're out there maintaining it."

    Be that as it may, it's clear  that our  telecom 

    infrastructure is more fragile than most people realize. 

    In this age of  multimedia, digital, high-speed, hold-on- to-your-hat content consumption,

     any outage can be disastrous for  people and businesses.

    It's great to get off  the grid now and then and chase down mean old Col. Mustard. But that should be at your  own choosing, not because you've been knocked offline for  weeks.

    I'm not telling 

     AT&T how to run its business. But for  a 

    company that pocketed $12.3 billion in profit in the third quarter  of  2010 aione, maybe it wouldn't hurt to have a few more techs on hand.

    Just in case.

    Back to Table of  Contents

    TRANSPORTATION 

    - California

    San 

    Mateo 

    Daily Journal - High-speed rail

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    25/53

    head ditches Caltrain

    By Bill Silverfarb, Jan 7

    Bob 

    Doty, a man brought in to help save Caltrain from 

    financial ruin by partnering with the California High 

    Speed 

    Rail 

     Authority, 

    is 

    moving 

    to 

    the 

    private 

    sector  

    after  heading the Peninsula Rail Program for  two years.

    Doty will take a senior  executive position with HNTB, an engineering firm contracted to design the Peninsula segment of  the high-speed rail project. He will first work on a high-speed rail program in Florida, however. Doty worked for  and answered to both Caltrain and the rail authority and by agreement will do no work on the Peninsula section of  the rail corridor  for  the next year.

    The move forces Caltrain to reconsider  how it will 

    move 

    forward 

    with 

    high-speed 

    rail 

    because 

    Doty 

    was 

    hired to “save” Caltrain, Executive Director  Mike Scanlon wrote in a statement.

    “His departure means we will rethink the structure and the personnel to go forward with high-speed rail,” Scanlon wrote in the statement. “We entered into the agreement with

     High-Speed Rail to help save Caltrain. We still have to save Caltrain.”

    Doty headed the working groups for  city staff  and officials

     related to the alternatives analysis document released in  August and presented designs that showed 

    mostly 

    an 

    aerial 

    viaduct 

    solution 

    for  

    the 

    tracks 

    on 

    the 

    Peninsula, 

    not the most popular  choice for  many cities.

    He also rolled out Context Sensitive Solutions, a tool that was meant to bridge the gap between members of  rival communities who may have different opinions on how the tracks should be configured.

    Not everyone was impressed with his work, however.

    Belmont 

    Mayor  

    Coralin Feierbach said she is glad he 

    is leaving.

    “It might help that he’s leaving,” Feierbach said. “He was inflexible.”

    Belmont opposes an aerial solution for  a high-speed rail and would prefer  to have the tracks buried through town as

     does Burlingame.

     Although 

    Doty presented solutions for  high-speed rail

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    26/53

    that were not favored by many cities, 

    Burlingame Mayor  Terry Nagei did appreciate his straightforward approach.

    “He will be hard to replace,” Nagel said. “He gave direct

     

    answers early on.”

    High-speed rail problems start with an inadequate business plan and faulty ridership projections, Nagel said.

    Nagei 

    hopes the environmental review process will 

    slow down or  restart to include some of  the alternatives 

    the 

    cities 

    preferred, such as tunneling or  cut-and- covered trenches.

    Doty’s last day as director  of  the Peninsula Rail Program

     will be Jan. 21. His new position at HNTB will be vice president and director  of  high-speed rail 

    programs.

    By agreement with Caltrain and the rail authority, Doty will do no work on the Peninsula section for  a year.

    “We 

    created 

    the PRP to take 

    full advantage 

    of  

    Bob Doty and his unique experience and expertise across the globe in designing and delivering large-scale rail projects. It is no surprise that a man of  Bob’s talents and expertise is being snatched up by one of  the firms that wants to be a player  in the domestic high-speed rail competition,” Scanlon wrote in a statement.

    Scanlon 

    said 

    Caltrain 

    entered 

    into 

    the 

    agreement 

    with 

    the rail authority to help save the commuter  rail 

    service, which has no dedicated stream of  funding.

    The transit agency’s overall fiscal year  2010-11 budget, approved in July, is about $100.9 million but is projected to drop by $30 million in the next budget cycle as

     contributions from SamTrans, Santa Clara County’s Valley Transportation  Agency and the San Francisco Municipal Transportation  Agency are expected

     

    to be slashed by half  next year.

    Doty 

    would 

    not 

    discuss 

    the 

    details 

    of  

    the 

    compensation 

    associated 

    with 

    his 

    new 

    position 

    in 

    the 

    private 

    sector, 

    except to say it is expected to be “substantially more” than the $178,000 per  year  he was paid as director  of  the Peninsula Rail Program, according to Caltrain.

    HNTB is an engineering and design firm that is under  contract to provide

     

    consulting expertise to high-speed rail projects

     

    throughout the United States. 

    In California, it is designing the Peninsula segment of  the California

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    27/53

    High-Speed Rail project.

    Back to Table of  Contents

    Fresno 

    Bee - Path of  high-speed rail worries 

    Valley farmers

    By Tim Sheehan. Jan 9

    California's ambitious plan for  high-speed trains is drawing sharp criticism from San Joaquin Valley farmers who fear  the project

     

    would carve 

    their  

    property into

     

    useless pieces, disrupt their  work 

    and 

    drive 

    down land values.

    Others accuse the California High-Speed Rail  Authority - the agency tasked with building the 800-mile system over  the next decade - of  ignoring their  concerns and steering the proposed

     

    rail line into the countryside as the

     

    path 

    of  

    least 

    resistance.

    "I have been able to deal with immigration officials, the United

     Farm Workers union and Congress," said Manuel Cunha, president of  the Fresno-based Nisei Farmers League. "But these guys [at the rail authority] don't want to talk with us. Their  attitude is, 'We are going

     to put this 

    through and we don't really care about these

     

    farmers. I I!

    Not so, said Jeff  Barker, the authority's deputy 

    executive director.

    "Agriculture is absolutely being listened to, and it will factor  into the decisions we're making," Barker  said. "You can't build a piece of  infrastructure like this without affecting agricultural land, and we want to work with agriculture to mitigate those effects."

    If  the project is built as planned, about 170 miles of  

    dedicated high-speed tracks would carry passengers 

    between Merced and Bakersfield at speeds of  up to 220 mph

     

    across 

    some of  the world's most fertile farmland.

    That 

    worries 

    not 

    only 

    farmers 

    whose 

    land 

    is 

    likely 

    in 

    the path of  the 

    tracks, 

    but 

    also growers 

    who have property on either  side of  the route.

    "I'm a family farmer, and I want to stay a family farmer," said Brad Johns, a tomato farmer  north of  Hanford

     

    who fears the rail line would slice through his 

    farmland "and right through the front door  of  my house.”

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    28/53

    "But I am 

    acquiescing to reality," 

    Johns said. "This [train] is coming ... and I  just have to learn to live with a new neighbor."

    Beyond lost acreage

    Between Fresno and Bakersfield - where the first $5.5 billion section of  tracks is supposed to be built starting in 2012 - one primary route is being considered by the rail authority. It generally runs alongside the Burlington Northern Santa Fe railroad tracks. Exceptions include a 

    sweeping arc to take the tracks east of  Hanford and 

    several 

    options 

    to bypass 

    Corcoran, 

     Allensworth, Wasco

     and Shatter.

    Two route options are being evaluated between Fresno and Merced. One parallels the Union Pacific railroad tracks and through the cities of  Chowchilla and 

    Madera 

    along 

    Highway 

    99, 

    while 

    the 

    other  

    tends 

    to 

    run 

    alongside 

    the Burlington Northern Santa Fe 

    tracks 

    few miles to the east.

    Depending on the route that's ultimately set between Merced and Bakersfield, the rail line may displace about 1,900 acres of  property, according to the rail authority. Of  that acreage, about 1,460 acres is farmland

     

    about 2 one-hundredths of  a percent of  the more than 7.5 million acres of  agricultural land in Merced,

     

    Madera, Fresno, Kings, Tulare and Kern counties.

    But 

    farmers 

    say 

    the 

    effects 

    would 

    be 

    out 

    of  

    proportion 

    to the acreage affected.

    Johns owns 

    320 acres, some 

    of  which has been in his 

    family for  more than 60 years. He estimates he would lose about three acres if  the tracks go where he believes they will. He's not happy about it.

    "This was never  part of  my game plan," he said. "But I'm not going to take these lemons and make lemonade. I'm going to make margaritas."

    Johns 

    said 

    he'll 

    negotiate 

    with 

    the 

    authority 

    for  

    the 

    best 

    possible 

    deal 

    to 

    compensate 

    for  

    lost 

    land 

    and 

    possible 

    loss of  his home.

    Johns 

    said coming through farmland naturally makes 

    more sense for  rail planners than disrupting businesses and industries in cities.

    Back to Table of  Contents

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    29/53

    LA Times - Expo Line bidders under  new  

    scrutiny in 

    fraud and construction problems

    Probe comes after  an initial review disclosed federal 

    investigations, alleged evasion of  hiring requirements 

    and 

    other  

    problems.

    By Dan Weikel, Jan 8

    Builders of  the Expo light-rail line in Los  Angeles on 

    Thursday sought to reevaluate two bidders on the project

     after  an initial review uncovered a trail of  federal investigations, allegations of  fraud, past construction problems and payouts of  millions of  dollars in damages.

    The Exposition Metro Line Construction  Authority ordered a more in-depth performance analysis of  the Skanska/Rados

     

    and 

    the 

    URS/Shimmick  joint 

    ventures 

     —  two prospective finalists competing for  a contract to build

     the $1.5-billion second phase of  the light-rail system from Culver  City to Santa Monica.

    "This is important and indicative of  a new level of  awareness by the board that we should be proactive," said Los  Angeles County Supervisor  Mark Ridley- Thomas,

     who is a member  of  the Expo board and requested

     

    the initial review of  the two

     

    bidders.

    The inspector  general's office of  the Los  Angeles 

    County 

    Metropolitan 

    Transportation 

     Authority 

    will 

    handle 

    the 

    more 

    detailed 

    analysis, 

    which 

    includes contacting

     

    previous clients to assess each company's performance and responsibility on other  construction projects.

    Ridley-Thomas requested the first evaluation by the inspector 

     general in early December  after  reading a news account of  a federal investigation in New York that targeted Skanska USA Civil Northwest, a subsidiary

     of  Skanska USA.

     Authorities are looking into whether  the subsidiary 

    used 

    front 

    companies 

    to 

    evade 

    requirements 

    that 

    it hire

     

    certain 

    number  

    of  subcontractors owned 

    by women,

     minorities or  businesses that have been officially

     designated as disadvantaged.

    Skanska USA, a major  construction company, also is the parent company of  Skanska USA Civil West, which is interested in participating in the Expo project. Its partner  in the  joint venture is Steve P. Rados Inc.,

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    30/53

    based in Santa 

     Ana.

    The inspector  general's initial review did not find anything questionable about Rados' past performance on contracts, but it discovered four  other  matters related to Skanska operations, including the New York 

    investigation.

    The others involve the construction of  a water  filtration plant that more than doubled in price from $1.3 billion to

     $2.8 billion, the death of  a worker  for  a subcontractor  that resulted in occupational health and safety charges, and news accounts indicating that Skanska contributed to a secret blacklist that targeted union officials in the United Kingdom.

    Skanska 

    executives could not 

    be reached for  comment,

     but Steve S. Rados, co-president of  Rados Inc., defended Skanska USA Civil West as a "first-rate 

    outfit" 

    that 

    he 

    had 

    no 

    reason 

    to 

    doubt. 

    He 

    added 

    that he has no problem with the new performance review.

     Among other  things, the inspector  general found that URS

     

    Corp. agreed to 

    pay $5 million in 

    damages to the state of  Minnesota and $52 million to the victims of  the Interstate

     35 bridge collapse in Minneapolis three year  ago. The report stated that the company was hired to analyze

     the integrity of  the bridge and failed to discover  structural defects.

    In addition, 

    URS has been sued by the Massachusetts attorney general's office, which alleges that the 

    company 

    defrauded 

    the 

    Massachusetts 

    Port 

     Authority. The report also stated that a URS-owned company 

    caused 

    uncontrolled radiation contamination at a nuclear 

     facility and that a URS subsidiary agreed to pay

     the U.S.  Air  Force $1.7 million to resolve allegations of  overbilling.

    Jamie Tully, a spokesman for  URS, said company 

    representatives could not comment because they have not seen the inspector  general's findings. Tully defended the

     

    firm, saying it is "one of  the country's leading providers of  engineering design and construction services for  iight-rail projects."

     According to the inspector  general, URS' partner  in the  joint venture, Shimmick Construction, based in Oakland, was involved in a dispute with Bay  Area Rapid Transit over  whether  a pedestrian bridge was improperly welded.  A Shimmick spokesman said the issue has been resolved without a finding of  fault on the part of  the company.

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    31/53

    Back to Table of  Contents

    WATER 

    - California

    Monterey Herald - 

    Battle 

    brews 

    over  

    water  

    fee

    District contends the money vital to budget and without 

    it 

    layoffs likely

    By Jim Johnson. Jan 10

    Local water  officials 

    are scrambling after  a long- 

    running fee that pays for  a wide range of  Carmel River  mitigation and

     

    water  

    management efforts was rejected by a state Public Utilities Commission  judge last month.

    They're contacting state water  officials and urging the public

     to back the fee, which is collected by California  American Water 

     

    on its water  bills 

    for  the Monterey Peninsula Water  Management District's

     Carmel River  mitigation program. The 8.325-percent fee collects millions

     

    of  dollars per  year  

    for  the program, which 

    is 

    designed to offset the impacts of  public use of  the river  water  source. Local officials are arguing that it is essential to continue the legally required river  mitigation work in its current form.

     A water  district official said the fee, which had been 

    collected 

    for  

    the 

    district 

    since 

    the 

    1990s 

    until 

    it 

    was halted in mid-2009, also represents a significant 

    portion of  the district's budget and the loss of  revenue could

     result in nearly a dozen layoffs.

    On Dec. 21,  Administrative Law Judge Maribeth Bushey issued a proposed decision finding the fee was not  justified, largely because of  concerns about the potential size of  the fee and the scope of  work it pays for,

     and should be discontinued.

    The commission must decide whether  to adopt 

    Bushey's proposed decision, and could consider  it as 

    early 

    as 

    its 

    Jan. 

    27 

    meeting, 

    but 

    is 

    more 

    likely 

    to 

    wait 

    until its Feb. 24 meeting.

    State and local water  officials have until today to respond to the proposed decision, and reply comments are due within a week.

    The public can also submit comments through the CPUC.

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    32/53

    Water  

    Management District general manager  

    Darby Fuerst said officials from the district, Cai  Am and the CPUC's Division of  Ratepayer   Advocates, which signed

     an agreement backing the fee, have already met with an advisor  to commission President Michael 

    Peevey. 

    Fuerst 

    said 

    the 

    advisor  

    indicated 

    Peevey 

    would 

    consider  developing

     

    an 

    alternate 

    proposed decision,

     and discuss with Bushey the possibility of  a revised proposed

     

    decision.

    "We think the proposed decision is flawed, both legally and factually," Fuerst said. "We're asking that the (fee) be approved again."

    District wants to continue

    Cal  Am spokeswoman Catherine Bowie said the water  district has met its responsibilities under  the program 

    and 

    the 

    company 

    wants 

    it 

    to 

    continue 

    to 

    do 

    so. 

    Bowie 

    noted 

    that the proposed 

    decision comes on the heels 

    of  commission approval of  a regional water  project designed to offset the effects of  pumping from the river  source.

    "We 

    support the district and feel 

    the fee 

    should continue to

     

    be paid to them," Bowie said. "With all their  years

     of  experience, we think they're the best to continue this important

     

    work. We also believe that 

    when 

    we're 

    so close 

    to a water  solution 

    it doesn't make sense to

     

    change course.”

    Bowie 

    pointed 

    out 

    that 

    the 

    river  

    mitigation 

    work 

    is 

    required and Cal  Am would simply have to find another  way to make sure it's done, perhaps by finding another  agency to do the work, and customers would still ultimately pay for 

     

    it.

    "This is part of  running the water  system," Bowie said. 

    "The expense will still be there.”

    Supervisor  Dave Potter, a member  of  the water  district board, said the question is who else could undertake the

     

    mitigation work and how much of  it is actually 

    mandated.

    Fuerst said Cal  Am 

    has indicated it wants to continue working with the water  district on the mitigation program and is obligated to continue funding it until a final

     

    decision by the commission. But he said Cal  Am 

    officials have already indicated they will send the district an intent to terminate its agreement with the district,

     which would take effect within 90 days.  And the district board has directed staff  to suspend all major 

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    33/53

    spending for  the next 

    three months.

    If  Cal  Am terminates and renegotiates with the district, Fuerst said he

     

    believes 

    the company will seek to re evaluate the original intent of  the river  mitigation measures

     

    required by 

    the state, and some district 

    projects 

    could 

    be 

    eliminated or  

    cut 

    back.

     At the CPUC, the proposed fee was split off  by the commission from a larger  Cal  Am general rate increase bid for  2008-10 after  Bushey raised a number  of  issues with the method and purpose of  the monthly charge, including the potential increase in the fee as overall bills rise, the apparent absence of  a link between rising fee revenue and required mitigation work, and possible duplication of  accounting and effort.

    Monitoring the usage

    In 

    addition 

    to 

    mitigation 

    work 

    on 

    the 

    river's 

    steelhead 

    and habitat, riparian vegetation and 

    wildlife, and lagoon vegetation and

     

    wildlife, the district's program 

    includes water  supply and usage monitoring, water  production and demand management, and water  supply

     augmentation. The district also spent nearly $1

     

    million 

    to help pay for  its headquarters.

    Following the commission's decision in the summer  of  2009,

     

    Cal 

     Am 

    stopped 

    collecting the fees but began an 

    account to keep 

    record of  how much the fees would 

    equal, and 

    continued paying that amount  —  about $4.1 million  —  to the water  district for  the mitigation 

    work. 

    State 

    water  

    officials 

    require 

    Cal 

     Am 

    to 

    continue paying for  the mitigation work if  the water  district can't 

    or  won't.

    Cal 

     Am 

    submitted an application for  the fee last January, and submitted a  joint motion in May to approve a settlement agreement with the water  district and the DRA.

    In its application, Cal  Am argued the fee was  justified because its expenditure by the district occurs only after  a "transparent public process," the district is prohibited by state law from collecting more than it spends, and 

    the 

    district's 

    own 

    rules 

    allow 

    it 

    to 

    fund 

    any 

    endeavor  that confers "benefit and/or  service" to Cal  Am's customers. It also argued that the commission lacked the authority to scrutinize the proposed charge in detail because of  its status as a local government fee.

    But 

    in her  

    proposed 

    decision, Bushey criticized the 

    fee proposal because it was not based on the costs of  the district's programs, and included "no ratemaking or 

    SB GT&S 001

  • 8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"

    34/53

    programmatic 

    limitations," 

    and provided no  justification for  a potentially large increase in the size of  the fee. She

     

    also 

    expressed 

    concern about the lack of  

    incentive for  Cai  Am to control costs if  the commission 

    "blindly" allows 

    the 

    bill 

    for  

    mitigation 

    work to be passed 

    along to customers.

    In 

    addition, 

    Bushey 

    recommended the 

    memorandum account be dissolved and not recovered from ratepayers "in any way."

    Bushey suggested that Cal  Am could  justify a "forwardlooking

     

    rate mechanism" and the needed funding f