Upload
kqed-news
View
215
Download
0
Embed Size (px)
Citation preview
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
1/53
From: Clanon, Paul
Sent: 1/10/2011 5:59:46 PM
To:
Cherry, Brian
K (/0=PG&E/0U=C0RP0RATE/CN=RECIPIENTS/CN=BKC7)
Cc: Johnson,
Kirk
(/0=PG&E/0U=C0RP0RATE/CN=RECIPIENTS/CN=MKJ2)
Bee:
Subject: Re:
CPUC
Newsclips for Monday,
January 10
Here's what I
get
from
my
people. You agree?
Follows:
PG E raises
the pressure in transmission lines to MAOP once every five years based
on its conservative interpretation of 192.917(e)(4). That code section is not clear on
whether the maximum pressure experienced in the preceding five years
means
the
preceding
five
years prior
to designating
the pipeline as HCA fixed)
or
just
the
preceding
five
years
(moving). PG E uses
the
moving
five-year
interpretation. As of
today,
PHMSA
has not given a
clear
interpretation
on this.
Many utilities
in
the
country
use
the moving
five-year
interpretation to be on the safe side.
On
Jan 10, 2011, at 5:19 PM,
Cherry,
Brian K
wrote:
No, I
still think that is
true
- at least that is what
I heard
before.
I
think the subtlety
that
we weren't
told by
our
operating people
is
that it isn't
required -
it is industry practice.
Therefore, if operators
want
to maintain MAOP at those levels, they have the right to
run
them
at
those
pressures to maintain
the rating
-
but
aren't
required
to do so by law
if
they
are ok with a lower rating. Kirk - is
that
right ?
From: Clanon, Paul
[mailto:[email protected]]
Sent: Monday,
January
10, 2011 5:15
PM
To: Cherry, Brian
K
Subject:
Re: CPUC Newsclips for
Monday, January
10
So it
isn't true that
operators
have to operate a line
at MAO P
every
five
years
or
the
MAOP
ratchets down
to
the
highest pressure experienced during
that
time?
I
think
I've heard
that from both
your
guys
and
mine.
On Jan 10, 2011, at 5:05
PM,
Cherry, Brian K wrote:
SB
GT S 025
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
2/53
From: Clanon, Paul
Sent: 1/10/2011 10:48:13 AM
Cherry, Brian K (/0=PG&E/0U=C0RP0RATE/CN=RECIPIENTS/CN=BKC7)To:
Cc:
Bee:
Subject: Re: CPUC Newsclips for Monday, January 10
Thx. Our guys are doing the same thing, and you and I can triangulate.
From: Cherry, Brian K [mailto:[email protected]]
Sent: Monday, January 10, 2011 10:40 AM
To: Clanon, Paul; Clanon, Paul
Subject: Fw: CPUC Newsclips for Monday, January 10
Will get you the answers.
From: Loduca, Janet C.
Sent: Monday, January 10, 2011 10:38 AMTo: Cherry, Brian K
Cc: Garber, Stephen (Law)
Subject: RE: CPUC Newsclips for Monday, January 10
Brian
- the team is working on some follow-up Q&A,
From: Cherry, Brian K
Sent: Monday, January 10, 2011 10:05 AM
To: '[email protected]'; Loduca, Janet C.; Pruett, Greg S.
Cc: Bottorff, Thomas E
Subject: Re: CPUC Newsclips for Monday, January 10
Not sure. Let me follow up, I was under the same understanding, Jane or Greg - can you help
?
From: Clanon, Paul [mailto:[email protected]] Sent: Monday, January 10, 2011 10:03 AM
To:
Cherry,
Brian
KSubject: FW: CPUC Newsclips for Monday, January 10
What
are your guys saying about the facts in the Chron story
yesterday? Contradicted my understanding of the rules, anyway.
SB GT&S 001
mailto:[email protected]:[email protected]:[email protected]:[email protected]
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
3/53
From: Clanon, Paul
Sent: Monday, January 10, 2011 9:35 AMTo:
Clark, Richard W.; Halligan, Julie; Stepanian, Raffy; Lindh, Frank; Fitch, Julie A.; Berdge, Patricks.; Lewis, Kenneth E.
Subject: Re: CPUC Newsclips for Monday, January 10
The
Chronicle's
story
on
the
2008
temporary
rise
in
pressure
on
Line
132
to
400
psi
doesn't match what i've heard. What are the facts? Is it standard practice or not to raise pressure up to
MAOP to preserve the maximum? Is 2008 really the only time PG&E has raised pressure on
that line above 375 until the explosion?
On
Jan
10, 2011, at 9:01 AM, "Hall, Thomas A." wrote:
Good morning. We have clips on the PUC’s work to ensure pipeline safety, high-speed rail and more.
CPUC NEWSCLIPS
For
Monday, January 10, 2011
For newsclips help, contact Tom Hall (tbh) at 916-928-2274
Newsclips also available on Intranet in .doc format
To follow a link, hold CTRL, then click with left mouse button
To return to the top, hold CTRL, then press the “Home” key or click a Back to Table of
Contents
link
TABLE OF
CONTENTS
ENERGY - California
SJ Mercury News - Establishing safe pressures for PG&E gas lines could
prove huge, costly task
U :ords
’ugly,’
California
says
SF Chronicl
CGsT
urge may have stressed San Bruno line in '08
Tahoe Daily Tribune Power through the storm?
Santa Rosa Press Democrat - PG&E, state PUC should heed plea from
U.S. regulal DITORIAU
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
4/53
From: Cherry, Brian K
Sent: 1/10/2011 5:00:39 PM
To: 'Clanon, Paul' ( [email protected])
Cc:
Bcc:
Subject: Re: CPUC Newsclips for Monday, January 10
We live in parallel universes....
From:
Clanon,
Paul [mailto:[email protected] ]
Sent: Monday, January 10, 2011 5:00 PM To: Cherry, Brian K
Subject: Re:
CPUC Newsclips for Monday, January 10
My guys are having trouble with this one too for some reason.
On Jan 10, 2011, at 4:53 PM, "Cherry, Brian K" wrote:
Nothing yet. Soon I hope. I heard the response they received from Law was unintelligible.
From: Clanon, Paul [mailto:[email protected] ]
Sent: Monday, January 10, 2011 4:53 PM To: Cherry, Brian K
Subject: Re:
CPUC Newsclips for Monday, January 10
Nothing back on this yet?
On Jan 10, 2011, at 10:39 AM, "Cherry, Brian K" wrote:
Will
get
you
the
answers.
From:
Loduca, Janet C.
Sent: Monday, January 10, 2011 10:38 AMTo: Cherry,
Brian KCc: Garber, Stephen (Law)Subject: RE: CPUC Newsclips for Monday, January 10
Brian - the team is working on some follow-up Q&A.
SB GT&S 001
mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
5/53
From:
Cherry,
Brian
K
Sent: Monday, January 10, 2011 10:05 AM
To: '[email protected]': Loduca, Janet C.; Pruett, Greg S.
Cc:
Bottorff,
Thomas
E
Subject: Re: CPUC Newsclips for Monday, January 10
Not sure. Let me follow up. I was under the same understanding,
Jane or Greg - can you help ?
From:
Cianon, Paul [mailto:[email protected]]
Sent: Monday, January 10, 2011 10:03 AM To: Cherry, Brian KSubject: FW: CPUC Newsclips for Monday, January 10
What are your guys s out the facts in the
Chron
story
yesterday?
Contradicted
my understanding of the rules, anyway.
From: Cianon, Paul
Sent: Monday, January 10, 2011 9:35 AMTo: Clark, Richard W.; Halligan, Julie; Stepanian, Raffy; Lindh, Frank;
Fitch, Julie A.; Berdge, Patrick S.; Lewis, Kenneth E.
Subject: Re: CPUC Newsclips for Monday, January 10
The Chronicle's story on the 2008 temporary rise in pressure on
Line
132
to
400
psi
doesn't match
what
i've
heard.
What
are
the facts?
Is it standard practice
or not to raise pressure up to MAOP to preserve the maximum? Is 2008 really the only time PG&E has raised pressure on
that line above 375 until the explosion?
On Jan 10, 2011, at 9:01 AM, "Hall, Thomas A." wrote:
Good morning. We have
dips
on the PUC’s work to
ensure
pipeline
safety,
high-speed
rail
and
more.
CPUC NEWSCLIPS
For Monday, January 10, 2011
For newsclips help, contact Tom Hail (tbh) at 916-9282274
SB GT&S 001
mailto:[email protected]:[email protected]:[email protected]:[email protected]
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
6/53
Newsclips also available on Intranet in .doc format
To follow a link, hold CTRL, then click with left mouse button
To
return
to
the
top,
hold
CTRL,
then
press
the
“Home” key or click a Back to Table of Contents link
TABLE OF CONTENTS
ENERGY - California
SJ Mercury News - Establishing safe pressures for PG&E
gas lines could prove
huge,
costly
task
UPI ■ PG&E records ’ugly,’ California says
SF Chronicle - PG&E surge may have stressedSan
Bruno l ine in ’08
Tahoe Daily Tribune Power through the
storm?
Santa Rosa Press Democrat - PG&E, state
PUC should heed plea from U.S. regulators
(EDITORIAL)
Marin Independent Journal - PG&E should
give customers a choice on SmartMeters(EDITORIAL)
TELECOM - California
LA Wh.-*t’v tu hiatus for Alls')outages? (COLUMN)
TRANSPORTATION
-
California
San Mateo Daily Journal - High-speed railhead ditches Caltrain
Fresno Bee - Path of high-speed rail worriesValley farmers
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
7/53
LA Time' F *po Line bidders under new scrutiny in fraud and construction problems
WATER -
California
Monterey
Hera
ttle
brews
over
water
fee
Fresno Bee - Dams release excess water asrain fills Valley reservoirs
ENERGY -
National
Treehugger - A Black Market for 100-WattBulbs?
U.S. Ban Looms
TELECOM - National
Connected
Planet
-
Broadband
payback
not just
about subscriber revenues
Politics/General/Miscellaneous
Bakersfield Californian - Brown should give
Dean Florez
seat
on PUC (EDITORIAL)
Oakland Tribune - Nation's first transgender
trial judge overcame discrimination
SF
Chronicle
-
Brown
gets
hearing
on
sale
of buildings postponed
LA Times - Gov. Jerry Brown wants to tamebudget with tax extensions, deep cuts
LA Times - Selling stat» ts would be folly(COLUMN)
ENERGY - California
SJ Mercury News - Establishing safe pressures
for PG&E gas lines could prove huge, costly task
By Steve Johnson and Pete Carey, Jan 9
As
state
regulators start
the process of making PG&E
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
8/53
verify that the pressure limits for its natural gas pipelines are safe, they have been dismayed by the disorganized state
of the utility's records, complicating a project that is now predicted to take years, cost millions and inconvenience customers along the way.
Based
on
what
the
California
Public
Utilities
Commission
has determined
so far,
it appears at least 450 miles - or one fourth - of the 1,800 miles of gas transmission
pipes that PG&E operates in urban areas
may need
to undergo pressure tests - typically
done with liquid or gas - to establish the safe level. That's because the company may not have paperwork justifying
the limits it has set for those pipes.
Just locating all the records that describe the condition of PG&E's vast pipeline network could prove onerous, commission officials
told
the Mercury News last week. They
said the documents appear to be scattered hither
and
yon,
with
some
in
dusty
file
cabinets,
remote
field
offices
and
other
places
the
company
isn't even
sure
about. Even if all the records can be found, it's unclear
how much stock can be put in their accuracy, given the recent revelation that PG&E's paperwork mischaracterized the portion of San Bruno pipe that exploded Sept. 9, killing eight people and destroying 38 homes.
"We've been putting them under the microscope, and when you do that, you find things that are ugly,” said Julie Halligan, deputy director of the utility commission's consumer protection and safety division.
"That
doesn't
increase
your
confidence.”
After a recommendation from the National Transportation Safety Board, the CPUC last week ordered PG&E to identify all manufacturing, maintenance and other documents for its gas pipes so the utility can determine the lines' maximum allowable operating
pressure, based on each pipe's weakest part. If the utility can't do that, the CPUC board recommended, the
utility should
conduct pressure tests to establish the safe level - a procedure that involves
shutting off the gas to customers.
What
the
CPUC
didn't
reveal -
until
the
interview
with
the
Mercury
News
-
is just how
involved
it expects
the
task of finding records and testing pipes to be.
Although the cause of the San Bruno blast is still under investigation, the NTSB issued a rare "urgent" advisory last week, in part after discovering the pressure in the San Bruno transmission pipe spiked right before the blast but never reached its maximum allowable operating
pressure. The pipe had been pressure tested
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
9/53
at that
maximum level two years before the explosion.
In addition, although PG&E's records described the burst pipe section as seamless, the federal agency found that the segment actually had been welded along its length, making it potentially more susceptible
to
rupture.
PG&E officials declined to comment to the Mercury News late last week about the CPUC's latest concerns. But the company wrote the CPUC on Friday that it hoped to deliver the records the agency is seeking by March 15, adding, "This is a substantial undertaking."
Paul Clanon, the commission's executive director, agreed. "The records search we ordered PG&E to undertake is unprecedented,"
he said. "The pure
logistics of getting to all those records is daunting."
Many
of the
more
than
6,000
miles
of
PG&E's
gas
transmission lines were installed decades ago when
the utility wasn't required to keep extensive paperwork on the pipe's method of construction, inspection history and other factors. Consequently, in some cases PG&E has only limited or incomplete records, Halligan said, and in other instances, "they have no records whatsoever."
State officials hope to find multiple documents that provide matching descriptions about each pipe segment, giving them some assurance the records accurately reflect what is underground.
But in cases where the records are contradictory, fuzzy or nonexistent,
line segments will have to be pressure tested, they said. Although that process will shut off gas to customers in the affected area, the utility could deliver gas via trucks or alternate distribution lines to areas where pipes are being tested. How all that might work, and how many customers will be affected, has yet to be determined. PG&E has 2.9 million natural gas customers in the Bay Area.
"It potentially could be really big in terms of the disruption" for the public, said Frank Lindh, legal
counsel
to
the
CPUC.
Gas pressure already has been reduced by 20 percent in five Bay Area transmission lines because of concerns that the ruptured San Bruno segment may not be the only weak spot in PG&E's pipe network. Depending
on what other problems may surface from PG&E's record search, the utilities commission may have to reduce the pressure in additional lines, which
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
10/53
could result in other customers not getting as much gas as they need.
Similarly
unknown is the price tag for all this work.
Lindh estimated the pressure testing alone might cost
"multiple
tens
of
millions"
of
dollars.
And
if the
pressure tests reveal weaknesses that require pipe segments to
be replaced, the bill could increase much more. State officials said it typically costs $6 million to replace one mile of transmission pipe. Who will pick up the bill is yet to be decided.
None of this will happen overnight.
"It's going to take years," Clanon said, though he stressed
that "doesn't mean the system is unsafe in the meantime.
We're
taking
the
steps
to insure the safety of the system by reducing pressure and taking
other
steps."
He added that his agency is committed to improving PG&E's pipeline operations.
"It will get done," Clanon said. "The sense of urgency we feel at the CPUC is huge. People died at San Bruno."
Back to Table of Contents
UPI - PG&E records 'ugly,' California says
By Staff . Jan 10
SACRAMENTO - Records related to natural gas transmission
pipelines in California
operated by Pacific Gas and Electric Co, are "ugly,” a state utility director said.
The California Public Utilities Commission ordered PG&E
to find documents related to its California gas
transmission
network so it can examine the operating
pressure in
the pipes to find weak spots.
The
company,
the
San
Jose
Mercury
News
reports,
might not have all of the paperwork. The CPUC, meanwhile, notes that about 25 percent of the companies 1,800 miles of pipeline might need pressure testing.
"We've been putting them under the microscope, and when you do that, you find
things
that are ugly," said
Julie Halligan, a deputy director of consumer protection
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
11/53
and safety division at CPUC. "That doesn't increase your confidence."
Most of the gas transmission lines were installed before extensive record-keeping was required, the newspaper
report
adds. Hailigan said in some
circumstances
there
are
no
records
about
California's
natural
gas
pipelines.
A natural gas pipeline owned by PG&E burst Sept. 9, sparking a massive fireball that ripped through a San Bruno neighborhood. The explosion killed eight people and
destroyed 37 homes.
The National Transportation Safety Board said it found
weld issues along the San Bruno pipeline that may have led to the rupture.
Back to Table of Contents
SF Chronicle - PG&E surge may have stressed
San Bruno line in '08
By Jaxon Van Derbeken, Jan 9
Pacific Gas and Electric Co. briefly raised the pressure on its San Bruno natural gas line to the brink less than two years before the explosion that killed eight people - an action experts call a "huge gamble" that they fear made the pipe more susceptible to failure.
A
Chronicle
investigation
into
events
before
the explosion
led PG&E officials to reveal that for two hours on Dec. 9, 2008, the company intentionally boosted gas pressure to the maximum legal limit of 400
pounds per square inch. That was more pressure than PG&E has ever acknowledged using on the line, which it normally ran at 375 pounds per square inch.
The utility initially explained that it had boosted the
pressure because federal regulations required it to do so, but later conceded
that its interpretation was inaccurate. It then explained that the spike was "part of our
operating practice."
This is
the first time the company has ever
acknowledged running the San Bruno line at its legal
maximum - a level now under scrutiny by federal investigators in light of revelations that PG&E had erroneous records about the pipeline's characteristics.
The next time the pressure exceeded 375 pounds per square inch on the line was on Sept. 9, when a
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
12/53
malfunction caused a
surge to 386 pounds - a spike
that coincided with the deadly explosion and fireball in
San Bruno
that destroyed 38 homes.
Early strain in line
PG&E's
intentional
surge
in
2008
could
have
strained the San Bruno line and made it more vulnerable to
failure at lower pressure levels, according to experts interviewed by The Chronicle. Strain caused by one surge, they said, can weaken a pipe to the point where it can fail at a lower point when pressure surges again.
"If there was a defect very close to failure, it could cause that defect to enlarge," said Robert Eiber, a nationally recognized pipeline expert. "I'm frankly amazed they were willing
to take
the risk. I don't know
if they were aware of the risk they were taking or not. But in a case like this, it was a huge gamble."
When queried by The Chronicle, PG&E initially said federal regulators require
that
a pipe be run at full strength at least once every five years in order for the utility to "preserve" its legal capacity.
If the pressure ever exceeds that limit, the utility is obligated to
conduct a costly, high-priority inspection of the line.
Had PG&E not spiked the pressure on the 30-inch transmission
line running from Milpitas to San Francisco, utility spokesman Denny Boyles first said,
the
pipe's
capacity
would
have
been
permanently
reduced to 375 pounds per square inch under federallaw.
Changing stories
But the spokesman later backtracked when asked to cite the specific federal regulation, saying PG&E's earlier
response was "too general and as a result inaccurate.” He maintained that PG&E still believed that 400 pounds per square inch was a "very safe level" for the San Bruno line.
In
a
subsequent
statement,
the
company
no
longer
said
federal law had prompted its action.
"Putting the pressure up to 400 was part of our operating
practice," Paul Moreno, a PG&E spokesman, said Friday. He said the utility operates its lines at their maximum once every five years. He declined to elaborate.
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
13/53
The U.S. Pipeline and Hazardous Materials Safety Administration said in a statement that the agency "does
not require a pipeline
operator to do anything" to preserve the legal pressure capacity of gas transmission
lines.
When
asked
about
the
surge, a spokeswoman
for
the
California
Public
Utilities
Commission,
which
regulates PG&E, said only that "we do not have rules about spiking artificially."
The National Transportation Safety Board's investigation
into the cause of the San Bruno blast is looking at any previous incidents of pressure surges. "That's
going to be part of our investigation, and we will be looking at the pipeline's
operating history," said
Peter
Knudson, a safety board spokesman.
Experts shocked
Although the San Bruno line did not fail during the 2008 pressure
spike, experts interviewed by The Chronicle said the utility had been taking a terrible chance.
Richard
Kuprewicz, a pipeline safety consultant in
Redmond, Wash., said that in spiking the pressure, PG&E's action
created the likelihood
that "stable operations may
be stressed and
become unstable.”
"You just don't go out there and do real-time pressure tests
of this magnitude on lines without doing careful
thought
and
evaluation,"
Kuprewicz
said.
"This
is
a
gas
transmission pipeline. This is in the middle of a city.
You
don't just go raise the pressure on pipelines and hope they stay together."
Eiber, a pipeline integrity consultant and researcher in Columbus,
Ohio, with 50 years of experience in the business, said
the
natural gas industry all but
abandoned
artificial
spikes after a 1960 incident in
New Mexico in
which a pipe split along its seam for 8 miles during such a
test. No one was hurt.
The September disaster in San Bruno, Eiber said, "demonstrated
what
could
have
happened
in
their spike
test. It's not a good practice.”
Boyles, the PG&E spokesman, declined to respond to the
criticisms, citing the federal investigation into what
caused the explosion.
Records problems
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
14/53
The intentional pressure
spike was also
problematic because questions have
emerged since the explosion about
whether PG&E knew the real strength of the San Bruno line when it set the maximum gas pressure at 400 pounds per square inch in
1970.
The
utility
has
conceded
that
its
records
erroneously
showed
that the
San
Bruno
section
of the
pipeline, installed in 1956, had no seams. In fact, federal investigators found, the ruptured portion of the line not only had seams, but was pieced together in several 4- foot-long
sections that were constructed to unknown, potentially
inferior, specifications.
The National Transportation Safety Board says its investigators
are examining the quality of seam welds that held the pipeline together - welds that PG&E did not
know
existed when it
set the pipeline's maximum pressure. The
federal agency has not reached a
conclusion
about
what
caused
the
explosion.
The board said last week that "it is critical to know all the
characteristics of a pipeline in order to establish a valid MAOP (maximum allowable operating pressure) below which the pipeline
can be safely operated. The NTSB is concerned that these inaccurate records may lead to incorrect" maximum pressure levels.
James Hall, a former chairman of the safety board and now an independent pipeline safety advocate, said PG&E's
erroneous records about the line could have
led the utility to set the maximum pressure level too
high.
"If you don't have the records on the pipe, how are you setting the pressure?" Hall said.
Inspection issues
In fact, federal pipeline officials say, the intentional 2008
surge
might have had some bearing on the
validity of PG&E's subsequent inspection of the line in November 2009,
which found no problems in the pipe.
The
only pressure
figure the government considers
relevant,
according
to
the
federal
pipeline
safety
agency, is the highest level at which the line was run
from
about 1997 to 2002, when Congress passed a law requiring
regular inspections of pipelines in urban or"high consequence" areas.
That peak becomes a benchmark that could, if
exceeded, activate a new inspection.
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
15/53
PG&E officials said Friday
that the utility did not run the line above 375 pounds per square inch from 2000 to 2002,
but
that older
records were unavailable.
PG&E has said it kept the San Bruno line's pressure at 375 pounds per square inch because it was connected
to
three
other, weaker
lines
with that
capacity.
PG&E
pinched
off those
lines
for the
2008 surge,
the
utility said.
Putting stress on welds
Any surge above the benchmark level - intentional or otherwise
- is exactly the type of incident that, under the 2002 law, should have
forced PG&E to conduct a high-priority inspection using a technique that could detect weakness in a pipe's welds, federal
officials said.
That's
because
pressure
surges
can
put
stress
on
a
line's welds, meaning the line is no longer considered "stable," the federal pipeline safety agency said.
PG&E went forward with the November 2009 inspection using a method suitable mainly for detecting pipe corrosion, not weakness in welds.
That method, called direct assessment, involves
researching records on a pipeline, electronically mapping it using ski-pole-like devices, and digging spot- check
holes
to
examine
the
pipe.
The
method
considered
more
reliable
for
finding
weak
welds involves
shutting down a pipe,
pumping high- pressure water into it, and then repairing any damage that
materializes.
PG&E has avoided using it on most of its gas transmission pipes, citing the inconvenience to customers and cost of shutting down lines.
Nevertheless,
PG&E's intentional
spike of the line's
pressure might have prevented it from using direct
assessment in its 2009 inspection, federal officials indicated.
"Direct
assessment
is not
considered
a
viable
assessment
method
when
manufacturing
and
construction defects are 'unstable,' and
therefore would not be permitted under federal regulations," the pipeline safety agency said.
PG&E did not respond to queries about the legality of the
2009 inspection. The
utility has consistently
defended
direct assessment tests
as being reliable.
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
16/53
'Reckless
enterprise'
Hall, the former National Transportation Safety Board chairman, called the 2008 spike "a reckless enterprise" that was "obviously an exercise for their financial situation, not safety."
"You are dealing with pipe that has been in the ground more than 50 years, it has never had an internal inspection tool in it, has incomplete records, and they now artificially spike the line?” Hall said. "Why would you take such a high-risk action in a high-consequence area?"
Every spike above normal operating pressure presents a risk of disaster in such an old pipeline, Hall said.
"You can roll the dice many times," he said, "before you come up with snake eyes."
Back to Table of Contents
Tahoe
Daily Tribune - Power through the
storm?
Outages raise concerns as a new company takes over
By Adam Jensen. Jan 10
SOUTH LAKE TAHEO, Calif. — Concerns about how a new, smaller electric company will be able to
respond
to
widespread
power
outages
persist
following
a change in energy providers in the Lake Tahoe Basin.
Liberty
Energy — California Pacific Electric Company completed its purchase of Sierra Pacific Power Company's electrical distribution and generation assets Jan. 1.
The power company was previously referred to as CalPeco
in California Public Utilities Commission documents. Sierra Pacific Power Company is a subsidiary
of NV Energy and included the Nevada corporation's California operations.
Two South Lake Tahoe City Council members, Tom Davis and Bruce Grego, said they are concerned with how
the new company will be able to respond to power outages like those experienced last week.
NV Energy serves about 1.2 million customers in Nevada, while Liberty Energy's coverage includes 46,000
customers in Nevada, Placer, Sierra, Plumas,
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
17/53
Mono,
Alpine
and El Dorado counties.
“They're a small company; do they have the resources to deal with a power outage?” Davis asked Thursday.
Wet, heavy snow knocked
out
power to almost 10,000
customers
at
the
South
Shore
Dec.
29.
Although
most customers' electricity was restored Dec. 30, some
were without power for more than 48 hours.
Several NV Energy crews from Reno and the Carson Valley were used to help restore power at the lake.
Bob
Dodds, president and general manager of Liberty
Energy, said the new company will have two crews at the North Shore and two crews at the South Shore, just like Sierra Pacific did.
He also said the new power company will also be able
to
use
resources
from
NV
Energy
when
necessary.
“We have agreements with NV Energy that we can pull in crews
as we need,” Dodds said.
The agreements are formal, but are not available for public
review because they are proprietary, Dodds said.
Dodds
said the goal is to make the transition between
Sierra Pacific and Liberty Energy as seamless as
possible.
The South Lake Tahoe City Council approved transfer of the city's franchise agreement from Sierra Pacific to Liberty
Energy in October. The 25-year agreement ends
in 2018.
Councilman Bruce Grego was the lone dissenting vote against the transfer. He asked for a delay so the transfer could receive further scrutiny. On Thursday, he
said
the City
Council should have been more
critical of transferring the franchise agreement, possibly placing conditions on the new company to ensure service
standards.
At the time, then-Councilman Bill Crawford said it
would be “frivolous” to delay a vote on the item because the council cannot prevent NV Energy from selling
its property.
The lack of a vested interest in the area covered by Liberty Energy by NV Energy could delay help to the South
Shore in the case of widespread power outages,
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
18/53
Davis said. Using another company's resources could
also pass along? costs to consumers, Davis added.
Customers' monthly bills should remain at the same level, but will be itemized differently because of the switch,
Dodds said. He said a rate increase in 2012
should
be
similar
to
what
Sierra
Pacific
would
have
proposed.
NV Energy spokeswoman Faye Anderson did not return a request for comment Thursday.
Davis called the potential for long-lasting, widespread
power outages in winter “very disturbing,” especially for seniors
or others who have trouble leaving a residence in an emergency.
Both Davis and Grego said they've asked City Manager Tony O'Rourke to discuss emergency
response
preparations
at
an
upcoming
council
meeting, especially when it comes
to keeping the lights on in the city.
Neither councilman had any doubt that the city will see a storm similar to last week's in the future.
Grego said he hoped Liberty Energy would be a part of the discussions with the city. But what the city can do beyond that may be limited, Grego said.
“I think the only thing we can do is wait and see how they
perform,” Grego said.
Back to Table of Contents
Santa Rosa Press Democrat - PG&E, state
PUC should heed plea from U.S. regulators
(EDITORIAL)
By Editorial Board. Jan 8
When a natural gas pipeline exploded in San Bruno on Sept. 9, we, along with many others, suspected it was further
evidence
of our
nation's
aging
infrastructure.
However, we withheld final judgment until the investigation of the cause of the explosion, which killed eight people and demolished 37 homes, could be completed.
Four months later, the verdict is in, and it's
worse than suspected.
Not only was
the
gas line rupture the result of
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
19/53
infrastructure failure, PG&E didn't even have accurate
records about the type of pipes it was using underground.
PG&E's own engineering reports said that the San Bruno pipeline was seamless and had been built by
one
company.
Further
investigation
showed
that
the
steel
segment had
weak
longitudinal seams
and
that the
pipe had ruptured in a segment that had been seam-weided. Pius, not ail of the segments were made by the same company, according to federal officials.
Because of that, federal regulators this week sent an urgent message asking PG&E to make sure it is operating natural gas pipelines at safe pressures and, if uncertain, to consider scaling back on the pressure to 80 percent until the lines can be tested.
Given that most houses and business within Sonoma
County
receive
their
gas
and
electric
service
from PG&E,
locals should take notice.
The warnings came in two waves. On Monday, the National Transportation Safety Board called on PG&E to complete an “intensive record search” including possibly doing pipeline testing.
A day later, the federal Pipeline and Hazardous Materials Safety Administration issued a directive to all of the nation's gas line operators calling for “detailed threat and risk analyses” on the pipeline systems.
The
NTSB
lacks
the
authority
to
force
PG&E
to
take
action. But the California Public Utilities Commission does have such authority — and should use it. In fact, these urgent recommendations by federal regulators should be as embarrassing to the CPUC as it is to PG&E. It raises the question, why wasn't the CPUC ensuring that PG&E maintains proper records while at the same ensuring pressure is at safe levels?
Maintaining infrastructure — let alone maintaining records of infrastructure — is not sexy business. Few citizens
are likely to step up at a CPUC meeting or a PG&E shareholder meeting demanding proper
attention
to
and
funding
for
maintaining
infrastructure,
particularly in a time of austerity.
Nevertheless, the dangers of backing off on such upkeep are now clear and quantifiable: Eight lives lost. Thirty-seven homes demolished.
If PG&E hopes to show its customers it's committed to safety and not taking shortcuts, it will follow the
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
20/53
recommendations of
federal regulators quickly. The
state PUC should do the same.
Back to Table of Contents
Marin Independent Journal - PG&E should
give
customers
a
choice
on
SmartMeters
(EDITORIAL)
By Editorial Board. Jan 9
IF PACIFIC GAS and Electric Co. really cared about good public relations, it would give its customers the option of having SmartMeters installed.
Right now, PG&E is trying to bully its way through a P.R. disaster in Marin — when it needs to repair a few old ones.
On Tuesday, the Marin Board of Supervisors voted for a one-year emergency ban on the installation of the electronic meters that replace mechanical devices that had to be manually checked by meter readers. The wireless meters allow PG&E and its customers to monitor power consumption far more closely, which has many
advantages. The new meters also mean PG&E doesn't have to pay meter readers to visit every house and business that has a meter.
SmartMeters were launched, with the state Public Utilities Commission's blessing, as a "green" measure,
an
easy
way
for
ratepayers
to
keep
track
of their
own power usage as a way to reduce consumption — and
potentially their power costs.
What PG&E and the PUC didn't expect was opposition
to the meters over worries that the wireless devices could pose health risks. That opposition has been especially strong in pockets
of Marin.
A number of Inverness residents made news when they created a blockade in an effort to stop workers from
getting into town to install the meters. Some even were arrested.
That display of civil disobedience was not the right approach. Protesters, while preventing PG&E from having meters installed at their homes, also were preventing the utility from changing meters on other residents' homes, some of whom might want the new devices.
PG&E maintains that SmartMeters create less
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
21/53
exposure to electromagnetic frequencies than regular use of a cellphone or a microwave oven. It could be right.
But the utility giant has a major public-trust problem, much of which is its own doing, including arrogantly
spending
tens
of
millions
in
last
year's
failed
effort
to
get state voters
to
approve
Proposition
16.
And
it
will be dealing with fallout from the pipeline explosion in San Bruno that killed eight people for years.
Assemblyman Jared Huffman has introduced legislation to halt SmartMeter installation until the California Council of Science and Technology can collect
information, analyze it and issue findings about the devices.
Local jurisdictions may not be able to ban the installation
of SmartMeters. PG&E gets its marching
orders
from
the
PUC.
But
there
is
enough
concern
that PG&E,
rather than forcing SmartMeters onto its customers, should give its ratepayers a choice.
That choice may come with a price if PG&E needs to
pay meter readers to go to homes where customers want to keep their mechanical meters. That's a choice each customers would have to make, but it's a choice PG&E would be wise to offer. PG&E would be wise to remember these are customers who are unhappy.
The reality is that most likely will be OK with their
SmartMeters.
Part
of PG&E's job is responding to storms and fixing
damage. The company didn't see this storm coming. Giving ratepayers a
choice is — at this stage — an overdue repair.
Back to Table of Contents
TELECOM - California
LA
Times
-
What's
to
blame
for
AT&T
outages? (COLUMN)
Recent storms caused many AT&T customers in California to lose phone, TV and Internet service, with about 70,000 still affected.
By David Lazarus. Jan 6
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
22/53
Steve Robin works out of his La Crescenta home as a real estate investor and property manager. He relies on
AT&T for his phone line, fax line, broadband Internet
connection and TV service.
So it wasn't a very ho-ho-ho moment when Robin, 50,
became
one
of
thousands
of
AT&T
customers
statewide who
lost service
Christmas
Day
as
a
series of powerful storms clobbered California.
His frustration grew as the days passed and the only thing AT&T service reps could tell him was that technicians were on the case. It wasn't until Monday night — 10 days after the outage began — that Robin's service
was finally restored.
And he can consider himself lucky. As of this week, AT&T said it still had about 70,000 "trouble tickets" to address throughout the state and particularly in
Southern
California.
That's
about
10
times
the
usual number
of customers reporting that their service is on the fritz.
Verizon also experienced extensive
outages, although the company declined to specify how many customers were
affected. Time
Warner
Cable said its service was
disrupted in many SoCal neighborhoods.
The problems highlight the vulnerability of the telecom network — and what technicians say is a shortage of available manpower when
service
goes
down. Recent cutbacks by telecom companies have thinned the
ranks
of skilled
workers
capable
of responding
to
an emergency.
It's unreasonable
to
expect phone and cable
companies to keep work crews around on a just-in
case basis. The trick is finding the correct staffing balance that allows the greatest flexibility.
The storm-related loss of phone, TV and Internet service illustrates how
reliant we've come to be
on
these
technologies, and how isolated (not to mention unproductive) we become when they're
taken away.
"I
was
dead
in
the
water,"
Robin
said.
"To
keep
working, I
had to take my laptop to Starbucks, make business
calls on my cellphone, go to other people's homes. I had to do whatever I could to stay connected."
I know the feeling. Our home also lost Internet access for a week and it was like having the umbilical cord severed.
Suddenly all that life-sustaining data was
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
23/53
gone.
On the plus side, it was a holiday week and neither my wife nor I needed to be online. And our family was able to play some cutthroat games of Clue (isn't it always Col.
Mustard committing the foul deed?).
But it's a drag being without a service that we pay handsomely for and that we expect to be provided with a modicum of stability. Isn't that what ail those rate increases are about — keeping the network up to snuff?
You never realize how much you've come to depend on having ail
of cyberspace piped into your home until the
line suddenly goes dark.
John
Britton, an AT&T spokesman, said he was as
surprised as anyone by the scope of the recent
outages.
"We've seen the most water damage to the network in more
than 10 years," he said.
Britton said hundreds of extra technicians have been
rushed to the Southland from Northern California and other states to
help get the
system up
and running again. He said AT&T hopes to have everything fixed by early February.
"We're putting maximum resources into dealing with this," Britton said.
A pair of AT&T technicians, who asked that their names
be withheld out of concern that it could cost them their
jobs, told me in separate interviews that this is indeed the
case — the company is putting on a full- court press
to
deal with the situation. They said they
and their cohorts are working mandatory seven-day weeks
and 12-hour days.
But
the technicians said the outages didn't need to be
this bad.
"The
company
hasn't
kept
up
with
maintenance
and upgrades for the
network," one
said.
"That's why
the problems are so widespread."
The technicians said cables and phone lines wouldn't have been so
waterlogged
if their casing and insulation had been
inspected and repaired at more regular intervals. Both cited hungry squirrels chewing on lines as
a key reason water gets in.
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
24/53
They also said flooding of underground vaults and
pipes wouldn't have caused so much damage if the facilities had been regularly maintained.
The technicians said the network would be better
maintained,
and
repairs
would
be
faster,
if
AT&T
hadn't lost so many workers in cutbacks. About 525 California
technicians left the company or were reassigned last March.
Britton disputed that AT&T was unprepared for the storm damage.
"This is an emergency situation," he said. "We're not the only ones affected. They even had to close down the freeway because of the weather."
He said the number of technicians has declined in
tandem
with
declines
in
the
number
of
wire-line
phone
customers (as opposed to wireless customers). "We staff for the amount of work we have,” Britton said.
"This network operates virtually flawlessly 99.999% of the time,” he added. "When it doesn't, we're out there maintaining it."
Be that as it may, it's clear that our telecom
infrastructure is more fragile than most people realize.
In this age of multimedia, digital, high-speed, hold-on- to-your-hat content consumption,
any outage can be disastrous for people and businesses.
It's great to get off the grid now and then and chase down mean old Col. Mustard. But that should be at your own choosing, not because you've been knocked offline for weeks.
I'm not telling
AT&T how to run its business. But for a
company that pocketed $12.3 billion in profit in the third quarter of 2010 aione, maybe it wouldn't hurt to have a few more techs on hand.
Just in case.
Back to Table of Contents
TRANSPORTATION
- California
San
Mateo
Daily Journal - High-speed rail
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
25/53
head ditches Caltrain
By Bill Silverfarb, Jan 7
Bob
Doty, a man brought in to help save Caltrain from
financial ruin by partnering with the California High
Speed
Rail
Authority,
is
moving
to
the
private
sector
after heading the Peninsula Rail Program for two years.
Doty will take a senior executive position with HNTB, an engineering firm contracted to design the Peninsula segment of the high-speed rail project. He will first work on a high-speed rail program in Florida, however. Doty worked for and answered to both Caltrain and the rail authority and by agreement will do no work on the Peninsula section of the rail corridor for the next year.
The move forces Caltrain to reconsider how it will
move
forward
with
high-speed
rail
because
Doty
was
hired to “save” Caltrain, Executive Director Mike Scanlon wrote in a statement.
“His departure means we will rethink the structure and the personnel to go forward with high-speed rail,” Scanlon wrote in the statement. “We entered into the agreement with
High-Speed Rail to help save Caltrain. We still have to save Caltrain.”
Doty headed the working groups for city staff and officials
related to the alternatives analysis document released in August and presented designs that showed
mostly
an
aerial
viaduct
solution
for
the
tracks
on
the
Peninsula,
not the most popular choice for many cities.
He also rolled out Context Sensitive Solutions, a tool that was meant to bridge the gap between members of rival communities who may have different opinions on how the tracks should be configured.
Not everyone was impressed with his work, however.
Belmont
Mayor
Coralin Feierbach said she is glad he
is leaving.
“It might help that he’s leaving,” Feierbach said. “He was inflexible.”
Belmont opposes an aerial solution for a high-speed rail and would prefer to have the tracks buried through town as
does Burlingame.
Although
Doty presented solutions for high-speed rail
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
26/53
that were not favored by many cities,
Burlingame Mayor Terry Nagei did appreciate his straightforward approach.
“He will be hard to replace,” Nagel said. “He gave direct
answers early on.”
High-speed rail problems start with an inadequate business plan and faulty ridership projections, Nagel said.
Nagei
hopes the environmental review process will
slow down or restart to include some of the alternatives
the
cities
preferred, such as tunneling or cut-and- covered trenches.
Doty’s last day as director of the Peninsula Rail Program
will be Jan. 21. His new position at HNTB will be vice president and director of high-speed rail
programs.
By agreement with Caltrain and the rail authority, Doty will do no work on the Peninsula section for a year.
“We
created
the PRP to take
full advantage
of
Bob Doty and his unique experience and expertise across the globe in designing and delivering large-scale rail projects. It is no surprise that a man of Bob’s talents and expertise is being snatched up by one of the firms that wants to be a player in the domestic high-speed rail competition,” Scanlon wrote in a statement.
Scanlon
said
Caltrain
entered
into
the
agreement
with
the rail authority to help save the commuter rail
service, which has no dedicated stream of funding.
The transit agency’s overall fiscal year 2010-11 budget, approved in July, is about $100.9 million but is projected to drop by $30 million in the next budget cycle as
contributions from SamTrans, Santa Clara County’s Valley Transportation Agency and the San Francisco Municipal Transportation Agency are expected
to be slashed by half next year.
Doty
would
not
discuss
the
details
of
the
compensation
associated
with
his
new
position
in
the
private
sector,
except to say it is expected to be “substantially more” than the $178,000 per year he was paid as director of the Peninsula Rail Program, according to Caltrain.
HNTB is an engineering and design firm that is under contract to provide
consulting expertise to high-speed rail projects
throughout the United States.
In California, it is designing the Peninsula segment of the California
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
27/53
High-Speed Rail project.
Back to Table of Contents
Fresno
Bee - Path of high-speed rail worries
Valley farmers
By Tim Sheehan. Jan 9
California's ambitious plan for high-speed trains is drawing sharp criticism from San Joaquin Valley farmers who fear the project
would carve
their
property into
useless pieces, disrupt their work
and
drive
down land values.
Others accuse the California High-Speed Rail Authority - the agency tasked with building the 800-mile system over the next decade - of ignoring their concerns and steering the proposed
rail line into the countryside as the
path
of
least
resistance.
"I have been able to deal with immigration officials, the United
Farm Workers union and Congress," said Manuel Cunha, president of the Fresno-based Nisei Farmers League. "But these guys [at the rail authority] don't want to talk with us. Their attitude is, 'We are going
to put this
through and we don't really care about these
farmers. I I!
Not so, said Jeff Barker, the authority's deputy
executive director.
"Agriculture is absolutely being listened to, and it will factor into the decisions we're making," Barker said. "You can't build a piece of infrastructure like this without affecting agricultural land, and we want to work with agriculture to mitigate those effects."
If the project is built as planned, about 170 miles of
dedicated high-speed tracks would carry passengers
between Merced and Bakersfield at speeds of up to 220 mph
across
some of the world's most fertile farmland.
That
worries
not
only
farmers
whose
land
is
likely
in
the path of the
tracks,
but
also growers
who have property on either side of the route.
"I'm a family farmer, and I want to stay a family farmer," said Brad Johns, a tomato farmer north of Hanford
who fears the rail line would slice through his
farmland "and right through the front door of my house.”
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
28/53
"But I am
acquiescing to reality,"
Johns said. "This [train] is coming ... and I just have to learn to live with a new neighbor."
Beyond lost acreage
Between Fresno and Bakersfield - where the first $5.5 billion section of tracks is supposed to be built starting in 2012 - one primary route is being considered by the rail authority. It generally runs alongside the Burlington Northern Santa Fe railroad tracks. Exceptions include a
sweeping arc to take the tracks east of Hanford and
several
options
to bypass
Corcoran,
Allensworth, Wasco
and Shatter.
Two route options are being evaluated between Fresno and Merced. One parallels the Union Pacific railroad tracks and through the cities of Chowchilla and
Madera
along
Highway
99,
while
the
other
tends
to
run
alongside
the Burlington Northern Santa Fe
tracks
a
few miles to the east.
Depending on the route that's ultimately set between Merced and Bakersfield, the rail line may displace about 1,900 acres of property, according to the rail authority. Of that acreage, about 1,460 acres is farmland
-
about 2 one-hundredths of a percent of the more than 7.5 million acres of agricultural land in Merced,
Madera, Fresno, Kings, Tulare and Kern counties.
But
farmers
say
the
effects
would
be
out
of
proportion
to the acreage affected.
Johns owns
320 acres, some
of which has been in his
family for more than 60 years. He estimates he would lose about three acres if the tracks go where he believes they will. He's not happy about it.
"This was never part of my game plan," he said. "But I'm not going to take these lemons and make lemonade. I'm going to make margaritas."
Johns
said
he'll
negotiate
with
the
authority
for
the
best
possible
deal
to
compensate
for
lost
land
and
possible
loss of his home.
Johns
said coming through farmland naturally makes
more sense for rail planners than disrupting businesses and industries in cities.
Back to Table of Contents
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
29/53
LA Times - Expo Line bidders under new
scrutiny in
fraud and construction problems
Probe comes after an initial review disclosed federal
investigations, alleged evasion of hiring requirements
and
other
problems.
By Dan Weikel, Jan 8
Builders of the Expo light-rail line in Los Angeles on
Thursday sought to reevaluate two bidders on the project
after an initial review uncovered a trail of federal investigations, allegations of fraud, past construction problems and payouts of millions of dollars in damages.
The Exposition Metro Line Construction Authority ordered a more in-depth performance analysis of the Skanska/Rados
and
the
URS/Shimmick joint
ventures
— two prospective finalists competing for a contract to build
the $1.5-billion second phase of the light-rail system from Culver City to Santa Monica.
"This is important and indicative of a new level of awareness by the board that we should be proactive," said Los Angeles County Supervisor Mark Ridley- Thomas,
who is a member of the Expo board and requested
the initial review of the two
bidders.
The inspector general's office of the Los Angeles
County
Metropolitan
Transportation
Authority
will
handle
the
more
detailed
analysis,
which
includes contacting
previous clients to assess each company's performance and responsibility on other construction projects.
Ridley-Thomas requested the first evaluation by the inspector
general in early December after reading a news account of a federal investigation in New York that targeted Skanska USA Civil Northwest, a subsidiary
of Skanska USA.
Authorities are looking into whether the subsidiary
used
front
companies
to
evade
requirements
that
it hire
a
certain
number
of subcontractors owned
by women,
minorities or businesses that have been officially
designated as disadvantaged.
Skanska USA, a major construction company, also is the parent company of Skanska USA Civil West, which is interested in participating in the Expo project. Its partner in the joint venture is Steve P. Rados Inc.,
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
30/53
based in Santa
Ana.
The inspector general's initial review did not find anything questionable about Rados' past performance on contracts, but it discovered four other matters related to Skanska operations, including the New York
investigation.
The others involve the construction of a water filtration plant that more than doubled in price from $1.3 billion to
$2.8 billion, the death of a worker for a subcontractor that resulted in occupational health and safety charges, and news accounts indicating that Skanska contributed to a secret blacklist that targeted union officials in the United Kingdom.
Skanska
executives could not
be reached for comment,
but Steve S. Rados, co-president of Rados Inc., defended Skanska USA Civil West as a "first-rate
outfit"
that
he
had
no
reason
to
doubt.
He
added
that he has no problem with the new performance review.
Among other things, the inspector general found that URS
Corp. agreed to
pay $5 million in
damages to the state of Minnesota and $52 million to the victims of the Interstate
35 bridge collapse in Minneapolis three year ago. The report stated that the company was hired to analyze
the integrity of the bridge and failed to discover structural defects.
In addition,
URS has been sued by the Massachusetts attorney general's office, which alleges that the
company
defrauded
the
Massachusetts
Port
Authority. The report also stated that a URS-owned company
caused
uncontrolled radiation contamination at a nuclear
facility and that a URS subsidiary agreed to pay
the U.S. Air Force $1.7 million to resolve allegations of overbilling.
Jamie Tully, a spokesman for URS, said company
representatives could not comment because they have not seen the inspector general's findings. Tully defended the
firm, saying it is "one of the country's leading providers of engineering design and construction services for iight-rail projects."
According to the inspector general, URS' partner in the joint venture, Shimmick Construction, based in Oakland, was involved in a dispute with Bay Area Rapid Transit over whether a pedestrian bridge was improperly welded. A Shimmick spokesman said the issue has been resolved without a finding of fault on the part of the company.
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
31/53
Back to Table of Contents
WATER
- California
Monterey Herald -
Battle
brews
over
water
fee
District contends the money vital to budget and without
it
layoffs likely
By Jim Johnson. Jan 10
Local water officials
are scrambling after a long-
running fee that pays for a wide range of Carmel River mitigation and
water
management efforts was rejected by a state Public Utilities Commission judge last month.
They're contacting state water officials and urging the public
to back the fee, which is collected by California American Water
on its water bills
for the Monterey Peninsula Water Management District's
Carmel River mitigation program. The 8.325-percent fee collects millions
of dollars per year
for the program, which
is
designed to offset the impacts of public use of the river water source. Local officials are arguing that it is essential to continue the legally required river mitigation work in its current form.
A water district official said the fee, which had been
collected
for
the
district
since
the
1990s
until
it
was halted in mid-2009, also represents a significant
portion of the district's budget and the loss of revenue could
result in nearly a dozen layoffs.
On Dec. 21, Administrative Law Judge Maribeth Bushey issued a proposed decision finding the fee was not justified, largely because of concerns about the potential size of the fee and the scope of work it pays for,
and should be discontinued.
The commission must decide whether to adopt
Bushey's proposed decision, and could consider it as
early
as
its
Jan.
27
meeting,
but
is
more
likely
to
wait
until its Feb. 24 meeting.
State and local water officials have until today to respond to the proposed decision, and reply comments are due within a week.
The public can also submit comments through the CPUC.
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
32/53
Water
Management District general manager
Darby Fuerst said officials from the district, Cai Am and the CPUC's Division of Ratepayer Advocates, which signed
an agreement backing the fee, have already met with an advisor to commission President Michael
Peevey.
Fuerst
said
the
advisor
indicated
Peevey
would
consider developing
an
alternate
proposed decision,
and discuss with Bushey the possibility of a revised proposed
decision.
"We think the proposed decision is flawed, both legally and factually," Fuerst said. "We're asking that the (fee) be approved again."
District wants to continue
Cal Am spokeswoman Catherine Bowie said the water district has met its responsibilities under the program
and
the
company
wants
it
to
continue
to
do
so.
Bowie
noted
that the proposed
decision comes on the heels
of commission approval of a regional water project designed to offset the effects of pumping from the river source.
"We
support the district and feel
the fee
should continue to
be paid to them," Bowie said. "With all their years
of experience, we think they're the best to continue this important
work. We also believe that
when
we're
so close
to a water solution
it doesn't make sense to
change course.”
Bowie
pointed
out
that
the
river
mitigation
work
is
required and Cal Am would simply have to find another way to make sure it's done, perhaps by finding another agency to do the work, and customers would still ultimately pay for
it.
"This is part of running the water system," Bowie said.
"The expense will still be there.”
Supervisor Dave Potter, a member of the water district board, said the question is who else could undertake the
mitigation work and how much of it is actually
mandated.
Fuerst said Cal Am
has indicated it wants to continue working with the water district on the mitigation program and is obligated to continue funding it until a final
decision by the commission. But he said Cal Am
officials have already indicated they will send the district an intent to terminate its agreement with the district,
which would take effect within 90 days. And the district board has directed staff to suspend all major
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
33/53
spending for the next
three months.
If Cal Am terminates and renegotiates with the district, Fuerst said he
believes
the company will seek to re evaluate the original intent of the river mitigation measures
required by
the state, and some district
projects
could
be
eliminated or
cut
back.
At the CPUC, the proposed fee was split off by the commission from a larger Cal Am general rate increase bid for 2008-10 after Bushey raised a number of issues with the method and purpose of the monthly charge, including the potential increase in the fee as overall bills rise, the apparent absence of a link between rising fee revenue and required mitigation work, and possible duplication of accounting and effort.
Monitoring the usage
In
addition
to
mitigation
work
on
the
river's
steelhead
and habitat, riparian vegetation and
wildlife, and lagoon vegetation and
wildlife, the district's program
includes water supply and usage monitoring, water production and demand management, and water supply
augmentation. The district also spent nearly $1
million
to help pay for its headquarters.
Following the commission's decision in the summer of 2009,
Cal
Am
stopped
collecting the fees but began an
account to keep
a
record of how much the fees would
equal, and
continued paying that amount — about $4.1 million — to the water district for the mitigation
work.
State
water
officials
require
Cal
Am
to
continue paying for the mitigation work if the water district can't
or won't.
Cal
Am
submitted an application for the fee last January, and submitted a joint motion in May to approve a settlement agreement with the water district and the DRA.
In its application, Cal Am argued the fee was justified because its expenditure by the district occurs only after a "transparent public process," the district is prohibited by state law from collecting more than it spends, and
the
district's
own
rules
allow
it
to
fund
any
endeavor that confers "benefit and/or service" to Cal Am's customers. It also argued that the commission lacked the authority to scrutinize the proposed charge in detail because of its status as a local government fee.
But
in her
proposed
decision, Bushey criticized the
fee proposal because it was not based on the costs of the district's programs, and included "no ratemaking or
SB GT&S 001
8/21/2019 CPUC and PG&E Emails: "You and I can triangulate"
34/53
programmatic
limitations,"
and provided no justification for a potentially large increase in the size of the fee. She
also
expressed
concern about the lack of
incentive for Cai Am to control costs if the commission
"blindly" allows
the
bill
for
mitigation
work to be passed
along to customers.
In
addition,
Bushey
recommended the
memorandum account be dissolved and not recovered from ratepayers "in any way."
Bushey suggested that Cal Am could justify a "forwardlooking
rate mechanism" and the needed funding f