Countermeasure Design, Implementation, and Monitoring

Nicole Bartelt| Assistant Waterway Engineer

October 5, 2017

mndot.gov/bridge/hydraulics

Page 2: Countermeasure Design, Implementation, and Monitoring

Brief History of MnDOT Scour program

• MnDOT issued formal screening guidelines in 1990

• Completed screening of all bridges in 1992

• Continued to work on all unknown foundations and scour critical bridges to present day

• No unknown foundations left on the system (either replaced, rated critical, or rated low risk)

• All bridges have been evaluated for scour, have a scour code, and have POAs as needed

• Currently 350 scour critical bridges in MN, 37 are MnDOT owned

10/9/2017 mndot.gov/bridge/hydraulics 2

Page 3: Countermeasure Design, Implementation, and Monitoring

Typical MN Countermeasures

• Riprap

• Guidebanks / Spurdikes

• Bendway weirs

• Articulated Concrete Block (ACB), less common

10/9/2017 mndot.gov/bridge/hydraulics 3

Page 4: Countermeasure Design, Implementation, and Monitoring

Riprap

• Most common form of countermeasure

• All spillthrough abutments have riprap

• Variety of rock material and quality throughout the state

10/9/2017 mndot.gov/bridge/hydraulics 4

Page 5: Countermeasure Design, Implementation, and Monitoring

Guidebank / Spurdike

10/9/2017 mndot.gov/bridge/hydraulics 5

Page 6: Countermeasure Design, Implementation, and Monitoring

Bendway Weir

10/9/2017 mndot.gov/bridge/hydraulics 6

Page 7: Countermeasure Design, Implementation, and Monitoring

Bendway Weir

10/9/2017 mndot.gov/bridge/hydraulics 7

Page 8: Countermeasure Design, Implementation, and Monitoring

ACB

10/9/2017 mndot.gov/bridge/hydraulics 8

Page 9: Countermeasure Design, Implementation, and Monitoring

Why new countermeasures?

• Variable riprap sources

• Quality – angularity and durability

• Quantity

• Trucking (price)

• Filter material

10/9/2017 mndot.gov/bridge/hydraulics 9

Page 10: Countermeasure Design, Implementation, and Monitoring

Matrix Riprap

• AKA: Partially grouted riprap

• Renamed to avoid contractor confusion

• Frequent uses:

• Very high velocity areas

• Limited or poor riprap

• Vandalism areas

10/9/2017 mndot.gov/bridge/hydraulics 10

Page 11: Countermeasure Design, Implementation, and Monitoring

Implementation Research project

• May 2012 – Hired Paul Clopper of Ayres Associates for a demonstration project

• Installed grout on an abutment slope with rounded riprap, only installed on one abutment

http://www.dot.state.mn.us/bridge/hydraulics/resources.html

10/9/2017 mndot.gov/bridge/hydraulics 11

Page 12: Countermeasure Design, Implementation, and Monitoring

10/9/2017 mndot.gov/bridge/hydraulics 12

Page 13: Countermeasure Design, Implementation, and Monitoring

Lessons learned

• Best to use a screw-type pump (got “pulses” of grout with a dual-piston)

• 2-3” hose diameter (2” minimum)

• Need contractor education on this method

• Website with youtube video on installation and grout

• Always need to be onsite during install

Page 14: Countermeasure Design, Implementation, and Monitoring

Use in construction projects

10/9/2017 mndot.gov/bridge/hydraulics 14

Page 15: Countermeasure Design, Implementation, and Monitoring

Not so good

10/9/2017 mndot.gov/bridge/hydraulics 16

Page 16: Countermeasure Design, Implementation, and Monitoring

Not so good

10/9/2017 mndot.gov/bridge/hydraulics 17

Page 17: Countermeasure Design, Implementation, and Monitoring

Lab study - Design impacts

• Most work with PGR was done for pier protection

• We want to use it primarily for abutment protection

• Hired SAFL-MN in April 2015

• Within limits of the flume, could not fail the matrix riprap

• Used both rounded and angular riprap

http://www.cts.umn.edu/Research/Projectdetail.html?id=2012004

10/9/2017 mndot.gov/bridge/hydraulics 18

Page 18: Countermeasure Design, Implementation, and Monitoring

Limitations

• Cannot place underwater – environmental restrictions (not allowed by the MPCA and DNR)

• Aesthetics – although coloring the grout makes a big difference

• Contractor knowledge

• Not sure of long-term survival - monitoring

10/9/2017 mndot.gov/bridge/hydraulics 19

Page 19: Countermeasure Design, Implementation, and Monitoring

Geobags

• Placing filter material in deep or fast moving water is difficult

• Big 4’x4’ geotextile bags partially filled with aggregate

• Used on 2 jobs on the Mississippi River

10/9/2017 mndot.gov/bridge/hydraulics 20

Page 20: Countermeasure Design, Implementation, and Monitoring

Geobag installation

Video LinksBelow are links to videos of a geobag installation.

• Geobag filling: https://youtu.be/SiDBDUntQPU

• Geobag Stitching: https://youtu.be/XQYsCedvYK8

• Geobag Placement: https://youtu.be/4sTrDazhSIM

10/9/2017 mndot.gov/bridge/hydraulics 21

Page 21: Countermeasure Design, Implementation, and Monitoring

Inspection of Countermeasures

• Upgrade scour code to “P” – protected

• Inspect during and after flooding to ensure they performed as inspected

• Visual and 3D sonar inspection after flooding

• Primarily sonar and probing during flooding

Page 22: Countermeasure Design, Implementation, and Monitoring

Monitoring

• Fixed monitoring

• During flooding

• Post flood / routine inspection

10/9/2017 mndot.gov/bridge/hydraulics 24

Page 23: Countermeasure Design, Implementation, and Monitoring

Fixed Monitoring

• Fixed sonar

• Float-outs

• Monitor geobags and riprap placement

• Tilt sensors

10/9/2017 mndot.gov/bridge/hydraulics 25

Page 24: Countermeasure Design, Implementation, and Monitoring

Fixed monitoring issues

• Power

• Solar power in MN at bridge sites

• Unsure if installed correctly

• System bugs/problems in getting the alarms (and false alarms)

10/9/2017 mndot.gov/bridge/hydraulics 26

Page 25: Countermeasure Design, Implementation, and Monitoring

Monitoring during floods

• Side-scan sonar (Humminbird 898c)

• Pole mounted

• Boogey-board

• ADCP

• Mounted on riverboat

• Partner with USGS to measure tough spots

10/9/2017 mndot.gov/bridge/hydraulics 29

Page 26: Countermeasure Design, Implementation, and Monitoring
Page 27: Countermeasure Design, Implementation, and Monitoring

Post flood / routine monitoring

• 3D mechanical scanner

• Blueview 1350

• Side scan

• Visual inspection

• Partner with underwater divers to get a complete picture

10/9/2017 mndot.gov/bridge/hydraulics 31

Page 28: Countermeasure Design, Implementation, and Monitoring

BV5000 3D System

Page 29: Countermeasure Design, Implementation, and Monitoring

Boat Configuration

• There are three basic deployment methods: boat mounted surface, metal plate, and tripod.

Page 30: Countermeasure Design, Implementation, and Monitoring

Boat Mounted Surface Stationary Deployment Method

10/9/2017 mndot.gov/bridge/hydraulics 34

Page 31: Countermeasure Design, Implementation, and Monitoring

Metal Plate Stationary Deployment Method

Plate was manufactured by our Mankato District

bridge maintenance staff. It weighs about 75 lbs

with the pan and tilt unit mounted on it.

Page 32: Countermeasure Design, Implementation, and Monitoring

Plate deployed using cherrypicker

Page 33: Countermeasure Design, Implementation, and Monitoring

Tripod Stationary Deployment Method

Page 34: Countermeasure Design, Implementation, and Monitoring

3D scan Post Flood – Contraction Scour

https://www.youtube.com/watch?v=KKP3qKvPlQA

Page 35: Countermeasure Design, Implementation, and Monitoring

Mobile Scanning

• Data is Geo-Referenced

• Pitch and Roll are accounted for

• Soundings of structures using stationary methods can by “dropped” into this data set

Page 36: Countermeasure Design, Implementation, and Monitoring

Data can be used for 2D modeling

Page 37: Countermeasure Design, Implementation, and Monitoring

Case Studies Br 2440- Third Ave Br.

Page 38: Countermeasure Design, Implementation, and Monitoring

Br 4654- Stillwater Lift Bridge

Page 39: Countermeasure Design, Implementation, and Monitoring

Br 19004- Hastings Br.

Page 40: Countermeasure Design, Implementation, and Monitoring

Br 9040- Red Wing

Page 41: Countermeasure Design, Implementation, and Monitoring

Br 85851- Winona Br.

Page 42: Countermeasure Design, Implementation, and Monitoring

Thank you again!