Upload
joanna-terry
View
251
Download
6
Tags:
Embed Size (px)
Costing Systems
EMBA 5403Fall 2010
Fall 2010 Mugan 2/37
Available costing systems
Absorption costing Actual Costing Normal Costing Standard Costing
Variable costing Actual Costing Normal Costing Standard Costing
Fall 2010 Mugan 3/37
Costing systems
Cost component
Actual Normal Standard
material Actual Actual Standard
labor cost Actual Actual Standard
Manufacturing Overhead-Variable
Actual Applied Standard
Manufacturing Overhead-Fixed
Actual Applied Standard Applied
Fall 2010 Mugan 4/37
Variance
Differences between the costs according to the costing system used and actual amounts
Actual amounts are reflected in the financial statements
Fall 2010 Mugan 5/37
Absorption CostingAbsorption costing allocates
variable and fixedoverhead costs to products.
Finished GoodsInventoryValuation
Cost of GoodsSold
Cost of Goods Manufactured
Fall 2010 Mugan 6/37
Product Costing Proceduresin Organizations
ProcessCosting
Job-orderCosting
Distinct jobs or batches of units. • Costs accumulated separately by job. •Typical job order cost applications:
• Special-order printing• Building construction
• Also used in service industry• Hospitals• Law firms
Fall 2010 Mugan 7/37
Product Costing Proceduresin Organizations
ProcessCosting
Job-orderCosting
Typical process cost applications: Petrochemical refinery Paint manufacturer Paper mill
Fall 2010 Mugan 8/37
Job-Order Costing
Traced directly to each job
Traced directly
to each job
TheTheJobJobTheTheJobJob
Direct labor
Direct labor
Direct materials
Direct materials
Manufacturingoverhead (MOVH)
Applied (added) to
eachjob using a
predeterminedrate
Fall 2010 Mugan 9/37
Job-Order Costing
Part of the job cost
MaterialsRequisition and
Time tickets
Direct materials
and labor
Indirect materials and labor
Manufacturing Overhead Control Account
Raw materials could be used as direct or indirect
product cost.
An employee’stime may be eitherdirect or indirect.
Fall 2010 Mugan 10/37
Job-Order Costing
wages
Job-Order Cost
Sheets
Material usage
OtherActual OHCharges
IndirectMaterials
IndirectLabor
AppliedOverhead
Manufacturing Overhead Control Account
Fall 2010 Mugan 11/37
Job-Order Cost Sheet
XYZ Job-Order Cost Sheet
Job Number A - 143 Date Initiated 17 September 2008Date Completed
Department A4 Units Completed 2Item Steel water tank
Direct Materials Direct Labor Manufacturing OverheadReq. No. Amount Ticket Hours Amount Hours Rate AmountMR 1041 TL 1200 20 8 TL 160 8 TL 6 TL 48
Cost Summary Units ShippedDirect Materials TL 1200 Date Number BalanceDirect Labor TL 160Manufacturing Overhead TL 48Total Cost 1408Unit Cost 704 11/17/08 1 1
17-Nov-08
Fall 2010 Mugan 12/37
Job-Order System Cost Flows
Direct Labor
Mfg. Overhead
Salaries and Wages Payable
Work-in-Process(Job Cost Sheet)
Direct
Materials
OverheadApplied to
Work inProcess
IndirectLabor
Direct Labor
Overhead Applied
IndirectLabor
Indirect Materials
Actual Applied If actual and applied manufacturing overheadare not equal, a year-end adjustment is required.
If actual and applied manufacturing overheadare not equal, a year-end adjustment is required.
Fall 2010 Mugan 13/37
Job-Order System Cost Flows
Cost ofGoodsMfd.
Finished Goods
Cost ofGoodsSold
Cost ofGoodsMfd.
Cost of Goods Sold
Cost ofGoodsSold
Work-in-Process(Job Cost Sheet)
Direct
MaterialsDirect Labor
Overhead Applied
Fall 2010 Mugan 14/37
Allocation Process
Define the cost objects.Accumulate indirect costs in cost pools.Choose an allocation base.Estimate an application rate.Allocate indirect costs based on use of
the allocation base
Fall 2010 Mugan 15/37
Over- and Underabsorbed Overhead
Overabsorbed overhead
Underabsorbed overhead
Overabsorbed overhead
Underabsorbed overhead
Fall 2010 Mugan 16/37
Over- and Underabsorbed Overhead
SOLUTIONApplied Overhead = POHR × Actual Direct Labor Hours
Applied Overhead = TL 6.00 per DLH × 100,000 DLH = TL 600,000
SOLUTIONApplied Overhead = POHR × Actual Direct Labor Hours
Applied Overhead = TL 6.00 per DLH × 100,000 DLH = TL 600,000
XYZ’s actual overhead for the year was TL650,000 and a total of 100,000 direct labor hours were
worked.
Using XYZ’s predetermined overhead rate ofTL 6.00 per direct labor hour, how much overhead
was applied to XYZ’s jobs during the year?
Fall 2010 Mugan 17/37
Accounting for Over- andUnderabsorbed Overhead
Three basic approaches Prorate among work-in-process,
finished goods, and cost of goods sold.
Adjust cost of goods sold. Recalculate the application rate and
apply to all the jobs during the period.
Three basic approaches Prorate among work-in-process,
finished goods, and cost of goods sold.
Adjust cost of goods sold. Recalculate the application rate and
apply to all the jobs during the period.
Fall 2010 Mugan 18/37
Accounting for Over- andUnderabsorbed Overhead
Alternative 1 Alternative 2If Manufacturing Close to Cost Overhead is . . . of Goods Sold Allocation
UNDERABSORBED INCREASE INCREASECost of Goods Sold Work-in-Process
(Applied OH is less Finished Goodsthan actual OH) Cost of Goods Sold
OVERABSORBED DECREASE DECREASECost of Goods Sold Work-in-Process
(Applied OH is greater Finished Goodsthan actual OH) Cost of Goods Sold
Fall 2010 Mugan 19/37
Allocation Base
Products
Application Rate
If overhead costs are
accumulated in a single cost
pool and allocated using
a single allocation base.
If overhead costs are
accumulated in a single cost
pool and allocated using
a single allocation base.
Single Overhead Cost Pool
Single Overhead Cost Pool
Fall 2010 Mugan 20/37
Many companies use Activity Based Costing where multiple cost pools and a different allocation base for each cost pool.
Many companies use Activity Based Costing where multiple cost pools and a different allocation base for each cost pool.
Products
Application Rate A
Overhead Cost Pool
A
Overhead Cost Pool
A
Overhead Cost Pool
B
Overhead Cost Pool
B
Overhead Cost Pool
C
Overhead Cost Pool
C
Application Rate B
Application Rate C
Multiple Allocation Bases
Fall 2010 Mugan 21/37
Improves planning and control. Activity Based Costing (ABC) is one
method of using multiple allocation bases.
ABC and Multiple Allocation Bases
Fall 2010 Mugan 22/37
Multistage Allocation Processes
Overhead Cost Pool 1Overhead
Cost Pool 1Overhead
Cost Pool 2Overhead
Cost Pool 2Overhead
Cost Pool 3Overhead
Cost Pool 3Overhead
Cost Pool 4Overhead
Cost Pool 4
Separate Application Rates
Department ADepartment A Department CDepartment CDepartment BDepartment B
Products
Dept. Application Rates
Dept. Application Rates
Fall 2010 Mugan 23/37
Process Costing
Identical units of product are producedin a continuous flow through a series of manufacturing steps or processes.
Costs are assigned to completed units transferred out of the process and to
incomplete units remaining in the process.
Identical units of product are producedin a continuous flow through a series of manufacturing steps or processes.
Costs are assigned to completed units transferred out of the process and to
incomplete units remaining in the process.
Fall 2010 Mugan 24/37
Costs are accumulated for a period of period of timetime for products in work-in-process
inventory.
Equivalent unitsEquivalent units is a concept expressing these partially completed
products as a smaller number of fully completed products.
Costs are accumulated for a period of period of timetime for products in work-in-process
inventory.
Equivalent unitsEquivalent units is a concept expressing these partially completed
products as a smaller number of fully completed products.
Process Costing
Fall 2010 Mugan 25/37
Two one-half completed products are equivalent to one completed product.
Two one-half completed products are equivalent to one completed product.
+ =
So, 8,000 units 70 percent completeare equivalent to 5,600 complete units.
So, 8,000 units 70 percent completeare equivalent to 5,600 complete units.
Equivalent Units
Fall 2010 Mugan 26/37
For the current period, Ames started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Ames have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
For the current period, Ames started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Ames have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
Equivalent Units Question
Fall 2010 Mugan 27/37
For the current period, Ames started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Ames have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
For the current period, Ames started 15,000 units and completed 10,000 units, leaving
5,000 units in process 30 percent complete. How many equivalent units of production did
Ames have for the period?
a. 10,000
b. 11,500
c. 13,500
d. 15,000
10,000 units + (5,000 units × .30) = 11,500 equivalent units
Equivalent Units Question
Fall 2010 Mugan 28/37
Calculating and Using Equivalent Units of Production
To calculate the cost perequivalent unit for the period:
Cost perequivalent
unit
=Costs for the period
Equivalent units for the period
Fall 2010 Mugan 29/37
Now assume that Ames incurred $27,600 in production costs for the 11,500 equivalent units. What was Ames’ average cost per
equivalent unit for the period?
a. $1.84
b. $2.40
c. $2.76
d. $2.90
Now assume that Ames incurred $27,600 in production costs for the 11,500 equivalent units. What was Ames’ average cost per
equivalent unit for the period?
a. $1.84
b. $2.40
c. $2.76
d. $2.90
Equivalent Units Question
Fall 2010 Mugan 30/37
Now assume that Ames incurred $27,600 in production costs for the 11,500 equivalent units. What was Ames’ average cost per
equivalent unit for the period?
a. $1.84
b. $2.40
c. $2.76
d. $2.90
Now assume that Ames incurred $27,600 in production costs for the 11,500 equivalent units. What was Ames’ average cost per
equivalent unit for the period?
a. $1.84
b. $2.40
c. $2.76
d. $2.90
$27,600 ÷ 11,500 equivalent units
= $2.40 per equivalent unit
Equivalent Units Question
Fall 2010 Mugan 31/37
What portion of the $27,600 in production costs was assigned to work-in-process
inventory and what amount was assigned to completed units for the period?
a. $0 and $27,600
b. $7,600 and $20,000
c. $3,600 and $24,000
d. $12,000 and $15,600
What portion of the $27,600 in production costs was assigned to work-in-process
inventory and what amount was assigned to completed units for the period?
a. $0 and $27,600
b. $7,600 and $20,000
c. $3,600 and $24,000
d. $12,000 and $15,600
Equivalent Units Question
Fall 2010 Mugan 32/37
What portion of the $27,600 in production costs was assigned to work-in-process
inventory and what amount was assigned to completed units for the period?
a. $0 and $27,600
b. $7,600 and $20,000
c. $3,600 and $24,000
d. $12,000 and $15,600
What portion of the $27,600 in production costs was assigned to work-in-process
inventory and what amount was assigned to completed units for the period?
a. $0 and $27,600
b. $7,600 and $20,000
c. $3,600 and $24,000
d. $12,000 and $15,600
Work-in-process:1,500 equivalent units @ $2.40 = $3,600
Completed units: 10,000 equivalent units @ $2.40 = $24,000
Equivalent Units Question
Fall 2010 Mugan 33/37
Equivalent Units
When there are partially completed units in beginning inventory, work efforts
during the period can be categorized as follows:
Work to complete beginning work-in-process Work on units started and completed during
the period Work on units in ending work-in-process
When there are partially completed units in beginning inventory, work efforts
during the period can be categorized as follows:
Work to complete beginning work-in-process Work on units started and completed during
the period Work on units in ending work-in-process
Fall 2010 Mugan 34/37
Equivalent Units - ExampleACE started June with 250 partially completed
units in work-in-process (30% complete).
During June, ACE completed the units in work-in-process and started an additional 1,200 units.
There were 300 units in ending work-in-processon June 30. They were 40% complete. How many total equivalent units
did ACE produce during June?
Continue
Fall 2010 Mugan 35/37
Equivalent Units - Example
Since 30% of the work was done on these units in May, the remaining 70% of
the work is done in June.
Since 30% of the work was done on these units in May, the remaining 70% of
the work is done in June.
Fall 2010 Mugan 36/37
Equivalent Units - Example
Since 1,200 units were started during June, and 300 ofthose units are still in work-in-process on June 30,900 units were started and completed during June.
Since 1,200 units were started during June, and 300 ofthose units are still in work-in-process on June 30,900 units were started and completed during June.
Fall 2010 Mugan 37/37
Equivalent Units - Example
40% of the work was done on these units in June.40% of the work was done on these units in June.