47
1 Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010 Office of Satellite Data Processing and Distribution National Oceanic and Atmospheric Administration NOAA Satellite and Information Service 1 April 7, 2010

Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

  • Upload
    havyn

  • View
    29

  • Download
    0

Embed Size (px)

DESCRIPTION

Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010. Office of Satellite Data Processing and Distribution National Oceanic and Atmospheric Administration NOAA Satellite and Information Service. April 7, 2010. 1. Outline. POES Program - PowerPoint PPT Presentation

Citation preview

Page 1: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

1

Cooperative Operational Processing Center’s Cooperative Support and Back-

Up Meeting Spring 2010

Office of Satellite Data Processing and DistributionNational Oceanic and Atmospheric Administration

NOAA Satellite and Information Service

1

April 7, 2010

Page 2: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

22

Outline

• POES Program– Operational Spacecraft– MetOp-B & MetOp-C– Jason-2

• GOES Program– Operational Spacecraft and GOES -15

• ESPC CIP Fail-over Testing

• ESPC System Freeze

• Products Transitioned to Operations

• DAPE Statistics

– For Official Use Only –

Page 3: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

33

POES ProgramOperational Spacecraft

– For Official Use Only – 3

• Current Status:

– NOAA-19: Primary PM Spacecraft• Advanced Data Collection System (A-DCS) issue

– The A-DCS provided by EUMESAT transmits in a frequency owned by the U.S. Alarm Industry Communications Committee (AICC).

– NOAA turned off the A-DCS transmitter on November 13, 2009. – NESDIS is discussing mitigation options with EUMETSAT and CNES

for future ADCS systems– This affects a new service, not legacy services

• MHS channel 3 noise out of spec, taken out of product processing

– MetOp-A: Primary mid-AM Spacecraft• Operations are nominal

– NOAA-18: Secondary PM Spacecraft

Page 4: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

4

Polar Operational Environmental Satellite (POES) Performance Status

08 March 2010

OperationalSpacecraft Issue but no user impacts S/COperational with limitations YNon-Operational RNot Applicable N/A

Page 5: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

5

POES Constellation Performance Status Details

02 March 2010

5– For Official Use Only –

Page 6: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

6

SVL pass

1st half of orbit N

2nd half of orbit N

2nd half of orbit N

SVL pass

ADA pass

SVL pass

Full orbit N

#3: 9/14 half orbits transferred from ADA

#2: 2 parallel half orbits transferred fromSVL

#1: Complete orbit transferred from SVL

#4: All half orbits transferred from ADA

4 Mb/s

4 Mb/s TBD Mb/s

4 Mb/s

5 Mb/s1st half of orbit N

2nd half of orbit N

SVL pass

ADA pass

4 Mb/s

5 Mb/s1st half of orbit N

Current

4th Quarter 2010

2nd Quarter 2011

2nd Quarter 2014

Eumetsat Processing System Evolution- NOAA Data Transfer

Page 7: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

7

Summary

Data types Coverage EPS System Steps

Best case timeliness

30%timeliness

50%timeliness

worst casetimeliness

Global data

tVCDUstimeliness

@ NOAA GS extension

tVCDUs holding all Metop

instruments’ data

Global

Now 1:19h 1:24h 1:27h 1:36h

2 half orbits from Svalbard

0:45h best possible

1:10h best possible

1:27h 1:36h

ADA demo phase

Depends on the number of dumps supported

1:36h

ADA operational 0:36h 0:43h 0:46h 0:50h

Metop Timeliness Improvements

Page 8: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

8

POES ProgramMetOp-B & MetOp-C

• Current Status: – MetOp-B and MetOp-C developments are on schedule– Both spacecraft have been manufactured and are in storage– MetOp-B is scheduled to launch April 2012 – MetOp-C will be launched 4.5 years after MetOp-B

– For Official Use Only –

U.S. provided instrument status

Instrument MetOp-B (Launch Apr 2012) MetOp-C (Launch Oct 2016)

Advanced Very High Resolution Radiometer -3 (AVHRR-3)

Integrated on spacecraft Integrated on spacecraft

Advanced Microwave Sounding Units A1 & A2 (AMSU-A1 & AMSU-A2)

A1: Integrated on spacecraft

A2: Integrated on spacecraft

A1: In environmental testing

A2: Integrated on spacecraft

High Resolution Infrared Sounder -4 (HIRS-4)

Integrated on spacecraftNot manifested – replaced by Infrared Atmospheric Sounding Interferometer (IASI) (CNES)

Space Environment Monitor (SEM) Integrated on spacecraft Integrated on spacecraft

Page 9: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

99

Ocean Observations

• Jason-2/Ocean Surface Topography Mission (OSTM)– NOAA commenced public distribution of the Jason-2 Geophysical Data

Records (GDR) from CNES on August 5, 2009.– NOAA continues routine operations of Jason-2; includes command and

control through 2 U.S. and 1 European ground stations.– Spacecraft, instruments, and ground system are performing nominally.

• Jason-3– Funds for Jason-3 has been appropriated for the FY 2010 NOAA Budget– EUMETSAT secured all needed funding in Europe and announced formal

start of their Jason-3 activity on February 1.– Authority to negotiate the Memorandum of Agreement (MOA) between

NOAA, NASA, EUMETSAT, and CNES was provided by the Department of State January 29

– Interagency Agreement between NOAA and NASA has been signed and the support agreement to transfer FY2010 funds is pending at DOC/GC.

– Funding for Jason-3 in FY2011 is part of President’s Budget submission to Congress.

– For Official Use Only –

Page 10: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

1111

GOES ProgramOperational Spacecraft

• Current Status:

– GOES-10 was decommissioned December 1, 2009. Spacecraft disposal in full compliance with Outer Space Treaty.

– GOES-11 battery has previously shown degraded performance during the twice yearly solar eclipse periods, but normal performance this past year and should continue as GOES-West until December 2011.

– GOES-12 approved by NOAA to provide support to South American users no later than June 2010.• Noise in short wave channels 13-17 starting in November 2009• Filter Wheel has periodic loss of synchronization resulting in data drop outs

– GOES-13 activated on January 27, 2010 and is being transitioned to become operational as GOES-East on April 14, 2010

– GOES-14 handed over to NOAA on December 14, 2009• NOAA science testing successfully completed on January 4, 2010; imaging operations

suspended on January 18, 2010 (normal storage actions).

– GOES-15 launched from Cape Canaveral at 6:57 PM March 4,

• Undergoing six month check-out with NASA

• First image expected April 6, 2010 at 1730Z

• Key Risks/Issues:– The GOES satellites are experiencing normal extended mission concerns

– For Official Use Only –

Page 11: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

12

Page 12: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

13

Geostationary Operational Environmental Satellite (GOES)

Performance StatusMarch 2010

Payload Instrument GOES-11(West)

Launch: May 00Activation: Jun 06

GOES-12(East)

Launch: Jul 01Activation: Apr 03

GOES-13(Standby)

Launch: May 06

GOES-14(Standby)

Launch: Jun 09

GOES-P/15(On-orbit Check-

out)Launch: Mar 10

Imager G G G G

Sounder G Y (3) G G

Energetic Particle Sensor (EPS) G Y (4) G G

Magnetometers G G G G

High Energy Proton and Alpha Detector (HEPAD) G G G G

X-Ray Sensor (XRS) R (1) R (5) R (7) G

Solar X-Ray Imager (SXI) N/A R (6) Y (8) G

Spacecraft Subsystems

Telemetry, Command & ControlG G G G

Attitude and Orbit Control G G G G

Inclination Control G G G G

Propulsion G G G G

Mechanisms G G G G

Electrical Power Y (2) G G G

Thermal Control G G G G

Communications Payloads G G G G

KeyOperational

Operational with limitations

Non-operational

Not Applicable

G

R

Y

N/A

13– For Official Use Only – 13

Page 13: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

14

Geostationary Operational Environmental Satellite (GOES)

Performance StatusMarch 2, 2010

GOES-11 Action Taken Impacts

1. X-Ray Sensor (XRS) Positioner failed

GOES-11 XRS operational but can’t accurately be pointed at sun

Using GOES-14 spacecraft to receive solar x-ray data

No user impacts

2. Degraded battery capability during eclipse periods

In 2008, SAR, SEM, and DCS payloads were turned off during eclipse periods to preserve battery capability

Temporary interruption of GOES-11 SAR, SEM and DCS payloads during eclipse periods if needed

14– For Official Use Only –

Page 14: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

15

Geostationary Operational Environmental Satellite (GOES)

Performance StatusMarch 2, 2010

GOES-12 Action Taken Impacts

3. Sounder filter wheel currents elevated and shortwave channels noisy

User has been notified Causes are under investigation

Elevated motor currents caused filter wheel out of sync and data dropout Noisy data in shortwave channels

4. Energetic Particles Sensor (EPS) channels noisy

User has adjusted forecasting procedures Degraded space environment data

5. XRS Positioner failed

GOES-12 XRS operational but can’t accurately be pointed at sun

Using GOES-14 spacecraft to receive solar x-ray data

No user impacts

6. Solar X-Ray Imager (SXI) failed

High-voltage power supply failed – No recovery possible

User not able to receive solar x-ray dataGOES-12 SXI flown as demonstration instrument – becomes operational on GOES-13

15– For Official Use Only –

Page 15: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

16

Geostationary Operational Environmental Satellite (GOES)

Performance StatusMarch 2, 2010

GOES-13 Action Taken Impacts

7. XRS capacitor short Performed tests on GOES-O & P sensors to ensure failures will not be repeated

No x-ray space environment measurements possible from GOES-13

8. SXI detector damage due to flare

Modified flight software to implement safing of SXI to prevent permanent damage

Implement additional ground validation of operational sequences prior to loading flight instrument

Degraded solar x-ray dataUser impacts, if any, not known until GOES-13 becomes operational

16– For Official Use Only –

Page 16: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

1717

Page 17: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

1818

Outline

• POES Program– Operational Spacecraft– MetOp-B & MetOp-C– Jason-2

• GOES Program– Operational Spacecraft and GOES -15

• ESPC CIP Fail-over Testing

• ESPC System Freeze

• Products Transitioned to Operations

• DAPE Statistics

– For Official Use Only –

Page 18: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

19

Critical Infrastructure Protection (CIP) Failover Testing

TARGET: Ability to independently execute a controlled failover to the ESPC backup facility (ESPC-CIP), and fail back to NSOF

The following is required to meet target:

– ESPC-CIP proof of concept test March 2010- Completed

– Planned ESPC-CIP failover test May 2010- Delayed due to customer impact on products not included in CIP and technical issues

– CIP designed to provide backup for critical products within 24-48 hours but organization is being requested to conduct testing in a manner that minimizes impact to all products

– Working to ensure user concerns are addressed prior to executing failover

– Identified path forward for the operational implementation of IASI and ACSAT at CIP (end of June 2010)

– Identified viability of AIRS back-up source (GSFC)– Identify alternative data sources for products not supported by CIP

– Technical Issues:– Bandwidth Utilization Study underway (April 12) and plan upgrade as

necessary– Detailed Failover test plans still needs management review

Page 19: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

2020

Outline

• POES Program– Operational Spacecraft– MetOp-B & MetOp-C– Jason-2

• GOES Program– Operational Spacecraft and GOES -15

• ESPC CIP Fail-over Testing

• ESPC System Freeze

• Products Transitioned to Operations

• DAPE Statistics

– For Official Use Only –

Page 20: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

21

ESPC System Status

• Following the FY2009 FISMA audit of ESPC by Commerce Office of the Inspector General (OIG), the ESPC Authorization To Operate (ATO) was downgraded to an Interim Authorization To Operate (IATO)– Findings noted by OIG led to conclusion that ATO was issued with an

insufficient understanding of risks inherent in system operations; a significant portion of security controls are partially or not implemented

– Recommendation is to establish an IT Security Program for ESPC that addresses core security requirements as noted in NIST, Commerce, NOAA, and NESDIS guidance

• Status:– Interim ESPC System Freeze applied February 2, 2010

• Scope:– Modifications to the ESPC System (those components within the

accreditation boundary) be suspended between February 2, 2010 and April 15, 2011

• Mitigation:– Develop ESPC IT Security Program Plan – Refocus PAC (Ground System and PSDI) resources as appropriate to

execute plan

– For Official Use Only –

Page 21: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

22

ESPC System Status (cont)

Authorized Freeze exceptions:

- Corrective and preventive maintenance required to maintain availability and accuracy of operational products

- Modifications required to address security deficiencies in the ESPC POA&M, or to implement NIST recommended security controls

- Modifications required to support launch of new satellites and to accommodate continuity of products from new satellites transitioned into operations

All other modifications will require a waiver from the [Authorizing Official/SO]

Page 22: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

23

ESPC System Status (cont)

Impacts to National Centers for Environmental Prediction (NCEP) – “no show stoppers for NCEP for the proposed satellite development freeze”

- Environmental Modeling Center – significant concern over potential delay in getting AMSR-E retrievals and SST analysis with microwave data – EMC is relying on these for critical deliverables this year

- Tropical Prediction Center – no individual project will significantly impact the center; however, almost half of the projects apply to TPC hurricane and/or marine programs – collectively, they could have a negative impact

- Ocean Prediction Center – with recent failure of QuikSCAT the ASCAT sea ice coverage product would fill a gap

- Storm, Climate, Hydrometeorological, Space Weather Prediction Centers and NCEP Central Operations – no significant impact

- Aviation Weather Center – pace of improvements slowed in areas such as volcanic ash detection and numerical model guidance

No impact to AWIPS program – NESDIS not failing to meet a product delivery associated with a planned AWIPS build – no degradation in service

Page 23: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

24

ESPC System Status (cont)

The benefits of the freeze include:

- Attention - it will focus OSDPD attention on security

• Responds to OIG guidance which states “...immediate management attention is needed to ensure that appropriate security controls are implemented to effectively protect the system.”

- Resources – it will focus OSDPD ORF and other PAC resources on IT security

• OSDPD will work with OSD to reallocated ground and satellite product funding to address IT Security

• Some PSDI funds could be used to continue development activities on STAR systems

• Funds to be used to complete security planning and to develop and implement security controls

- Risk – mitigates risk associated with completing actions and milestones in the ESPC POA&M

Page 24: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

25

ESPC Freeze-Impact

Feb 2, 2010 - April 15, 2011

35 Satellite Products Planned to Transition to Operations from Oct 1, 2009 - Apr 30, 2011

- 5 products complete - transitioned to operations by Jan 31, 2010 -FY-10 AOP milestone to deliver 14 new products to operations

- Remaining 34 products meet user requirements from NOAA Programs in all three Atmosphere, Ocean and Land Areas

- Development to continue on new and replacement products per continuity of satellite criteria (e.g. GOES-13; NPP); None of the 34 products fall in this category

- Anticipate a total 24-month set back on promotion of new products; Includes 15-month freeze, pre-operations, system admin triage and programmer training following lift of freeze for each product

– For Official Use Only –

Page 25: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

2626

Outline

• POES Program– Operational Spacecraft– MetOp-B & MetOp-C– Jason-2

• GOES Program– Operational Spacecraft and GOES -15

• ESPC CIP Fail-over Testing

• ESPC System Freeze

• Products Transitioned to Operations

• DAPE Statistics

– For Official Use Only –

Page 26: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

27

SPSRB Products Transition To Operations

• Five Major Algorithm Enhancements: (1) extension of retrievals in precipitating conditions; (2) extension of retrievals from DMSP F16 SSMIS; (3) addition of the cross-correlations in covariance matrix; (5) Fine tuned bias corrections; Regression-based first guess and (5) more specific QC flags

• Eight New Products: Vertically integrated cloud ice water content (IWP) and vertically integrated rain water content (RWP) from NOAA-18 and MetOp (4 products). Total Precipitable Water (TPW) over ocean, Land Surface Temperature (LST), emissivity spectrum over snow and land and surface type (sea, land, snow, sea-ice) for F16 SSMIS (4 products).

• Two Demo Products: Temperature and moisture profiles over ocean from F16 SSMIS.

• Ten Enhanced Products: Temperature profile (over ocean); Moisture profiles (over ocean and non-costal land); Total Precipitable Water (TPW) (over ocean and non-costal land); Land Surface Temperature (LST); Emissivity Spectrum over land and snow; Emissivity-based Snow Water Equivalent (SWE); Emissivity-based Snow Cover Extent (SCE); Emissivity-based Sea Ice Concentration (SIC); Vertically integrated non-precipitating cloud liquid water content (CLW); Surface Type (sea, land, snow, sea-ice).

Page 27: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

New Products

April, 2009 – April 2010

Page 28: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

29

eTRaP (Ensemble Tropical Rainfall Potential)

• Imagery and data of tropical storm rainfall totals and probabilities of precipitation for 6-hourly and 24-hour total time bins, for 4 accumulated rainfall thresholds. eTRaP is comprised of TRaPs created using microwave McIDAS area rain rates from AMSU-B, MHS, SSMI, TMI, and AMSR-E.

• Significance: eTRaP is used by tropical storm forecasters to determine the forecast rainfall accumulations and rainfall probabilities for numerous rainfall totals. The product is particularly useful for determining rainfall expectations for land-falling tropical storms. The probabilities of precipitation, which are a new eTRaP feature, provide information for decision makers to better anticipate heavy rainfall for land-falling storms. This new ensemble approach is a substantial improvement over the TRaP product, which it replaced.

Page 29: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

Enhanced Products

April, 2009 – April 2010

Page 30: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

31

ADT (Advanced Dvorak Technique) Objective Tropical

Storm Classifier v7.2.3• ADT is used as an independent, objectively

derived data source in the validation of the consensus (best) estimate of tropical storm intensity and location. It utilizes IR GOES imagery and automated tropical cyclone forecast (ATCF) bulletins. The enhancements in v7.2.3 included the addition of a new scheme for determining shear scene characteristics, which has reduced the previous problem of overestimating storm intensity during shear scenes. Another improvement is the addition of ATCF bulletins from basin-local Regional Specialized Meteorological Centres (RSMCs), which provide improved 6-hour ADT timeliness as well as the addition of an ADT product driven by the local RSMC forecasts for use by the local RSMC.

• Significance: ADT provides the tropical forecasting user community with an independent, objectively derived estimate of tropical storm intensity and location. GOES-12 (East) 18E (TS Polo)

Page 31: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

32

Aqua AMSR-E TRaP

• Aqua AMSR-E TRaPs were added to the eTRaP (Ensemble Tropical Rainfall Potential) product. The product output is imagery and data of tropical storm rainfall totals for 6-hourly and 24-hour total time bins. TRaPs are also generated using microwave McIDAS area rain rates from AMSU-B, MHS, SSMI, TMI.

• Significance: TRaP is used by tropical storm forecasters to determine forecast rainfall accumulations. The product is particularly useful for determining rainfall expectations for land-falling tropical storms. This new TRaP adds to the number of microwave sensors being used to generate eTRaPs

Page 32: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

33

METOP AVHRR Polar Winds

Page 33: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

34

MIRS v5

• Adds new Ice Water Path (IWP), Rain Water Path (RWP) and Rain Rate (RR) from DMSP F16 SSMIS– Enhances the current

MIRS v4.0 products

Daily MiRS Precipitation Estimate Composite (N18, MetopA and F16) (mm/day)

0.50 deg grid

Page 34: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

35

Met 8/9 and MTSAT-1R WildFire ABBA Products Upgrades

Page 35: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

3636

Outline

• POES Program– Operational Spacecraft– MetOp-B & MetOp-C– Jason-2

• GOES Program– Operational Spacecraft and GOES -15

• ESPC CIP Fail-over Testing

• ESPC System Freeze

• Products Transitioned to Operations

• DAPE Statistics

– For Official Use Only –

Page 36: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

37

NOAA/NESDIS Operational Statistics

[JAN – FEB 2010]Files Received From: Number of Files Volume [Gigabytes]

AFWA 3,194 61

FNMOC 14,006 347

NAVOCEANO 2,516 3.9

MONTEREY 382 34.8

Files Sent To:

AFWA 178,580 4977

FNMOC 246,261 914.7

NAVOCEANO 37,097 2053.6

– For Official Use Only –

Page 37: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

38

SATELLITE DATA PRODUCT EXCHANGE REQUEST LOG

SDPER NR

ACTION OPC

USER OPC

SDPER DATE

DATA PRODUCT REQUESTED

SUSPENSEDATE

DATEAPPROVED

OPC CCB REF

DATECOMPLETED/

CLOSED

2009-001 NOAA/NESDIS FNMOC 1/29/2009 MLS Ozone & Temp +SBUV/2 Ozone profile data V8

2/15/2009 2/26/093/17/09

CCR00451CCR00492

5/7/09 (MLS Ozone)4/9/09 (SBUV/2)

2009-002 NOAA/NESDIS FNMOC 1/29/2009 N-19 Polar Data: AMSU-A, MHS, HIRS, ATOVS

2/15/2009 4/7/09 CCR00512 3/10/09 (L1b Products)5/21/09 (ATOVS )

2009-003 NOAA/NESDIS AFWA/2 WXG 6/8/2009 Terminate transmission of ATOVS BUFR data products

6/8/2009 6/8/2009 None 6/8/2009

2009-004 NOAA/NESDIS AFWA/2 WXG 6/8/2009 Transmit N-19 AMSU-A data products to AFWA

6/10/09 6/8/2009 CCR00557 6/9/2009

2009-005 NOAA/NESDIS NAVOCEANO 8/10/2009 Transmit N-19 LAC & HRPT 1b data products to NAVOCEANO

8/21/2009 8/11/2009 CCR00747 8/19/2009

2009-006 NAVOCEANO NOAA/NESDIS 8/18/2009 Transmit N-19 GAC SST data products to NOAA/NESDIS

8/20/2009 8/19/2009 CCR00748 9/2/2009

2009-007 NOAA/NESDIS AFWA/2WXG 9/28/2009 Rain Rate EDRs, Level 2 Data—EOS-AQUA AMSR-E

11/19/2009 10/27/2009 CCR00916 12/7/2009

2009-008 NOAA/NESDIS AFWA/2WXG 9/28/2009 Rain Rate EDRs, Level 2 Data—N-15, 16, 17 AMSU-B

11/12/2009 10/27/2009 CCR00913 11/17/2009

2009-009 NOAA/NESDIS AFWA/2WXG 9/28/2009 Rain Rate EDRs, Level 2 Data—METOP MHS

12/4/2009 11/17/2009 WR00145/CCR1029

3/5/2010

2009-010 NOAA/NESDIS AFWA/2WXG 9/28/2009 Rain Rate EDRs, Level 2 Data—N-18 & 19 MHS

12/4/2009 11/17/2009 WR00145CCR1029

3/5/2010

2009-011 NOAA/NESDIS AFWA/2WXG 9/28/2009 Polar-Cloud Drift Winds, L2 Data—EOS Aqua & Terra MODIS

12/4/2009 11/17/2009 CCR-00957 3/18/2010

2010-001 NOAA/NESDIS AFWA/2WXG 3/5/2010 4 KM Snow Cover Files 4/1/2010 TBD TBD ---

– For Official Use Only –

Page 38: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

39

Backup

– For Official Use Only – 39

Page 39: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

40

Eumetsat Processing System Evolution

NOAAExtension

PGF

SVL

NOAAExtension

PGF

SVL

NOAAExtension

PGF

SVL

ADA

NOAAExtension

PGF

SVL

ADA#1 #2#1 #2 #3 #4

9 orbits / day 14 orbits / day

1/2 orbit

2/2 orbit

1/2 orbit

2/2 orbit

1/2 orbit

2/2 orbit

.

2010 2011 2012 2013 2014

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Page 40: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

41

EPS System Evolution: Data Transfer to PGF

SVL pass

1st half of orbit N

2nd half of orbit N

2nd half of orbit N

SVL pass

ADA

pass

SVL pass

Full orbit N

#3: 9/14 half orbits transferred from ADA

#2: 2 parallel half orbits transferred from SVL

#1: Complete orbit transferred from SVL

#4: All half orbits transferred from ADA

4 Mb/s

4 Mb/s

4 Mb/s

4 Mb/s

5 Mb/s1st half of orbit N

2nd half of orbit N

SVL pass

ADA

pass

4 Mb/s

5 Mb/s1st half of orbit N

Eumetsat Processing System Evolution

Page 41: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

42

ESPC Freeze-Product Impact

Loss of Improvement in Forecast Model Skill

- GOES TC Surface Winds - NWS (TPC, HPC) storm surge

- AMSR Global Soil Moisture - NWS (HPC, CPC) drought; floods

- GOME-2 OMI Trace Gases – NWS air quality

- Ocean Heat Content - NWS (TPC, HPC, TPC) TC intensity

- Global TC Formation Probability – NWS, DOD TC location

- AMSU TC Intensity - NWS (TPC, HPC, TPC)

- IASI Collocated FOV’s - NWS sounder product improvements

Loss of Prediction Capability - Interactive Weather Forecasts

- POES/GOES Blended Rain Rate - NWS (HPC) floods

Loss of Analysis Capability - Interpretative Hazard Products

- Automated AVHRR Volcanic Ash Detection & Height - FAA, SAB (VAAC) airline safety

- Automated OMI/AIRS Volcanic SO2 and Ash Cloud Heights - FAA, SAB (VAAC) airline safety

– For Official Use Only –

Page 42: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

43

ESPC Freeze-Product Impact

Loss of Detection Capability for Ocean Applications

- MODIS Ocean Color SWIRS - (NOS, NMFS) ocean productivity

- Chlorophyll Frontal Product - (NMFS) fisheries management

- Global E-Hux Bloom Maps - (NOS, NMFS) ocean acidification

- GOES Sea Surface Temperature - (NOS) SST improvements

- ASCAT Sea Ice Coverage - (NIC) all weather ice product

- Ocean Heat Content – (NOS) coral reef watch

Loss of AWIPS Product Enhancements

- POES/GOES Blended Rain Rate - NWS (HPC, FO’s) floods

- POES/GOES Blended TPW - NWS (HPC, FO’s) floods

- DMSP SSMI/S Rain Rate - NWS (HPC, FO’s) floods

- GOES Sounder 1x1 SFOV Sounder Retrievals in BUFR - NWS

– For Official Use Only –

Page 43: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

44

ESPC IT Security Program Plan

• Project to Create IT Security Program Plan– Address security deficiencies reflected in POAMs, incorporate

recommendations from IBM Assessment, and respond to OIG concerns noted in FY2009 FISMA review

– Kick-off held week of 2/22/10

– Project charter and schedule briefed to OCIO on 3/11/2010

• Project Activities & Milestones:– Complete POAM Restructuring: due 3/31/2010

– Deliver Program Plan, to include task description, schedule, resource allocation, implementation risks: due 5/31/2010

– Develop contract work assignments for ESPDS O&M /Dev contractors: ongoing starting 4/15/2010

– Coordinate plan within OSPO and with NESDIS OCIO with signatures by OSPO & OCIO leadership: due 6/30/2010

– For Official Use Only –

Page 44: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

45

ESPC IT Security Program Plan

• Plan includes key projects to improve ESPC IT security posture:– Develop Situation Awareness capability

• Bring intrusion detection capability into full production status• Implement “Solar Winds – Orion” capability previously approved• Establish initial capability for centralized logging• Establish inventory management/provisioning capability

– Publish Policies & Procedures to integrate security into all ESPC development and operations activities

– Establish automated mechanisms for User Identity & Account Management

– Document system baseline configurations and apply to ESPC components

– Additional projects as indicated by POAMs & IBM Assessment

– For Official Use Only –

Page 45: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

46

ESPC IT Security Program Plan

• Plan includes recurring activities to sustain security improvements

– Tied to controls in NIST 800-53, e.g. annual Contingency Plan training and testing, firewall reviews

– Resource requirements for sustaining controls will be included

• Plan incorporates previously identified ongoing and planned activities

– Complete updates of ESPC System Security Plan and related documents to support FY2011 reaccreditation activities

• STATUS: ONGOING. SSP review and gap analysis completed by SimIS. SSP will be updated as part of reaccreditation project, using SimIS support.

– Complete FY2010-FY2011 reaccreditation efforts

• STATUS: AWAITING START. Reaccreditation project scheduled to begin in April 2010, using SimIS support

– For Official Use Only –

Page 46: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

47

New Products Distributed Via DAPE Gateway

• Ozone Products– MLS Ozone data products – processed in HDF file format and transmitted to

FNMOC since 5/7/2009.– SBUV/2 Ozone data products – processed in BUFR file format and transmitted to

FNMOC since 4/9/2009• NOAA-19

– ATOVS BUFR data products -- transmitted to FNMOC since 5/21/2009– AMSU-A 1b data products -- transmitted to AFWA since 6/9/2009– LAC & HRPT 1b data products -- transmitted to NAVOCEANO since 8/19/2009

• Level 2 Rain Rate Data Products– AMSR-E Level 2 Rain Rate data products (from EOS AQUA) transmitted in HDF

file format to AFWA since 12/7/2009 – AMSU-B Level 2 Rain Rate data products (from N-15, -16, -17) transmitted in

HDF file format to AFWA since 11/17/2009– MHS Level 2 Rain Rate data products (from N-18, -19, MetOp-A) transmitted in

HDF file format to AFWA since 3/5/2010

– For Official Use Only –

Page 47: Cooperative Operational Processing Center’s Cooperative Support and Back-Up Meeting Spring 2010

48

New Products Distributed Via DAPE Gateway

• MODIS EOS TERRA & AQUA Polar Cloud Drift Winds data products based on 1 kilometer MODIS (MOD02 1KM) data products.

– Data received at NOAA/NESDIS from NASA and converted from HDF to BUFR file format for transmission to AFWA (as of 3/18/2010)

– For Official Use Only –