Contractual Procedures B 2010 - Tutorial 01 Assignment)

Embed Size (px)

Citation preview

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    1/43

    Contractual Procedures B

    CN3036 Tutorial 1

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    2/43

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    3/43

    Assignment

    Briefing

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    4/43

    Assignment

    Weighting : 50% ; Examination : 50%

    Maximum of 3,000 words

    Write a professional report to yourcontractdirector

    Correct format and well structure

    (with use of numbered heading)

    Font size 12 and 1.5 spacing

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    5/43

    Assignment

    Latest date for submission: 19 Dec 2010

    Reference : relevant clauses from contracts

    But do not re-write the clause (use your

    own words to express)

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    6/43

    Assignment Report FormatCover page Subject of report, author, date

    Contents page Heading numbers

    Abstract Brief summary of report e.g.

    purpose of report

    Introduction Background information e.g.

    contract used

    Main body of report Findings: Difference between 2

    contracts

    Conclusion Summary of results

    Recommendation If any e.g. when appropriate to

    use that contract

    Appendices/ Reference correct format

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    7/43

    Assignment

    Critically compare the terms, conditions and

    procedures contained within the standard FIDIC

    conditions of contract for construction first edition

    1999 with a standard HK conditions of contract

    What Standard HK conditions of contract refer to?

    HKIA (which edition? 2005 or 1999) GCC

    Others (e.g. JCT)

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    8/43

    Assignment Suggested Contents

    Under the following headings:

    Nature of projects with approximate values

    Master programme

    Establishing the contract sum

    Procedures for sub-letting

    Responsibility for health and safety

    Procedures for claiming an extension of time

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    9/43

    Standard Forms of Contract

    B

    ackground

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    10/43

    Standard Forms of Contract

    For the majority of building contracts, it is

    common practice to use standard forms of

    contract

    Reason

    It is essential to set out all the details of the

    work in a proper form of contract, and state

    each partys duties, obligations and rights

    Otherwise misunderstanding and dispute

    between the parties to a building contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    11/43

    Standard Forms of Contract

    Using a standard document avoids the waste of

    time that would result from having to individually

    draft the many terms necessary for each new

    contract

    In the event of disputes, standard forms of

    building contract provide a means of settlement,

    without the need to refer the matter to a court oflaw. E.g. an arbitration agreement clause in the

    document allow the parties to refer this disputes

    to arbitration

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    12/43

    Private Sector

    HKIA/RICS standard form

    Most wisely used private sectorstandard form of building contract

    Full title of this form is Agreementand Schedule of Conditions ofBuilding Contract (Standard FormofBuilding Contract) for use in

    Hong Kong , Private Edition (WithQuantities and Without Quantities)

    SFBC 2005 edition

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    13/43

    Private Sector

    FIDIC standard form

    Most wisely used standard form of

    contract for the purpose of

    construction work (both building and

    civil engineering) where tenders areinvited on an international basis

    General Conditions are linked with

    the Conditions of Particular

    Application (which is the part of the contractspecially drafted to suit the peculiarities of the

    individual contract) by corresponding clause numbers)

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    14/43

    Private Sector

    Certain employers, e.g. MTRC, Housing

    Authority, Swire each produce a standard form of

    contract for use on their own projects

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    15/43

    Public Sector

    Government standard form

    Building

    Government of Hong Kong General Conditions of

    Contract for building, 1990 Edition

    Civil Engineering

    Government of Hong Kong General Conditions of

    Contract for Civil Engineering Works, 1990 Edition

    E&M Government of Hong Kong General Conditions of

    Contract for Electrical and Mechanical Engineering

    Works, 1990 Edition

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    16/43

    Differences between Private Sector

    & Public SectorStandard Forms

    A mediation provision in public sector contract provide an

    optional alternative to arbitration as a means of resolving

    disputes

    The public sector standard form, the payment certificate is

    to be issued to the employerwith a duplicate copy to main

    contractor. Payment required within 14 days of issue

    The private sector standard form require paymentcertificates to be issued to main contractor, who will in

    turn present them to employer, payment must be made

    with X (21/30/45) days of presentation rather than of issue

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    17/43

    Standard Forms of Sub-contract

    Most standard forms of main contract will

    have a sister document to be used when

    the main contractor is directed by theemployer to enter into a nominated sub-

    contractor agreement with a sub-contractor

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    18/43

    Formalization of contract

    Tender submitted by a contractor constitutes an

    offerand if the tender is accepted without

    qualifications or amendment legally binding

    contract

    But it is usual practice to quality the tender, which

    has the effect of not binding either party legally

    Until the standard form of contract document has

    been signed by parties

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    19/43

    Formalization of contract

    When using Standard Form of Contract, the

    signatures, together with name and address, of

    both parties to the contract, the Employerand

    the Main Contractor, are recorded in theA

    rticleofAgreement

    The names of both the architectand the quantity

    surveyorappointed by the employer should also

    be recorded

    Contract Sum that the Employer has agreed to

    pay the main contractor

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    20/43

    Precedence of Contract Document

    A building contract incorporates the following:

    Contract drawings

    Contract bills

    (Bills of quantities/ Schedule of Rate)

    Standard form of contract

    Articles of agreement (signed)

    Terms of contract (contract clauses) Appendix (fill in the details)

    Special Conditions of Contract(Amendment to standard form of contract)

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    21/43

    Precedence of Contract Document

    If one document conflicts with another

    document which one take precedence over

    the other?

    The specially written or amended clause

    will take precedence over the standarddocument

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    22/43

    Discrepancies & Errors in Contract

    Discrepancies between contract

    documents may be discovered :

    During Pre-contract stage

    Tenderer should immediately inform architect (bymean of tender query) and architect should make

    necessary amendment and each inform tenderers

    During Post-contract stage Contractor should immediately give architect

    written notice and architect should issue A.I. to

    correct the discrepancy which would be adjusted in

    final account

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    23/43

    Contracting Parties

    ForBuilding Contracts

    And their obligation under the contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    24/43

    Contractors obligation

    under the contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    25/43

    Main Contractors obligations

    Progress and complete the works in

    accordance with the Contract (Clause 2.2)

    Give written notice to the Architect immediatelyupon finding a discrepancy in or divergence

    between contract documents

    Provide programme and amendments whenamended

    Comply with statutory obligations

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    26/43

    Main Contractors obligations

    Provide necessary insurance in respect of:

    Damages to works

    Damage to property owned by 3rd party

    Personal injury to workmen

    Damage by fire, storm, flooding etc.

    Clause 18 and 19

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    27/43

    Main Contractors obligations

    Materials and workmanship complied withthe standards as described in Contract and

    to reasonable satisfaction of the Architect

    [Clause 8.1.3]

    Contractor shall be responsible for the

    setting out of the works

    Submit any claims to architect in

    reasonable time

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    28/43

    Main Contractors obligations

    Keep a competent foreman-in-chargeconstantly upon the works

    Allow architect and his representativesaccess to the site/workshops at all

    reasonable time

    Permit carry out ofinspection [Clause8.2.2]

    Rectify defects [Clause 8.4]

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    29/43

    Employers obligation

    under the contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    30/43

    Employers obligations

    Payment Employer is obliged to pay the main contractor for

    work carried out

    QS to value completed works and then certified by

    architect, which in turn is paid by the employer

    Give possession of site [Clause 23.1.1]

    Employer must give main contractor possession ofsite in order that main contractor may carry out the

    works

    Employer need to specify the possession date and the

    finish date (completion)

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    31/43

    Employers obligations

    Appoint Architect and Surveyor (Article of

    Agreement)

    Supply instruction employer must give

    main contractor instructions concerning the

    works

    Employermust not interfere with progress

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    32/43

    Non-contracting Parties

    ForBuilding Contracts

    And their obligation under the contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    33/43

    Non-contractual parties to main

    contract Consultant team involved in the design

    and supervision of works are not parties to

    the main contract

    Each has their own employment contractwith the Employer

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    34/43

    Architects Duty

    Design exercise great care to give bestpossible advice and to warn employer ofpotential risks

    Drawings to supply sufficient drawingsand information, within reasonable time,for the execution of works

    Cost to ensure that building can becompleted within stipulated cost, or areasonable increase

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    35/43

    Architects Duty

    Supervision to supervise and inspect

    sufficiently to ensure that materials and

    workmanship conform with contractual

    requirement

    Payments to certify payments

    [Architects Certificate] to the maincontractor, without fraud and with completeimpartiality

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    36/43

    Quantity Surveyors Duty

    Pre-contract Duties Cost advise Employer of project costs

    Contractual arrangements advise on

    suitability Tender documents prepare and send to

    contractors

    Bills of quantities prepare from tenderdrawings

    Tender report- advise on choice of

    contractors

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    37/43

    Quantity Surveyors Duty

    Post-contract Duties

    Prepare certificates of payment involve

    measuring and valuing the work properly

    Prepare variation accounts measuring,

    pricing and agreeing the value with main

    contractors QS

    Calculate adjustment adjustment to the

    contract sum due to fluctuations

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    38/43

    Professional Negligence

    Architect, QS and consultant engineers areprofessional people

    They owe a duty to the Employer to carry out

    theirwork with proper care

    They are liable for damages for negligence if

    employersuffers a loss that is due to a lack of

    care or duty

    Legal action [Tort] may be taken against them by

    employer based on terms in their employment

    contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    39/43

    Contractual Arrangements

    ForBuilding Contracts

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    40/43

    Lump sum on Bills ofQuantities

    The contract sum is derived from the total

    of the items in the BQ (which is prepared

    by consultant QS)

    The contractor undertakes to carry out the

    work in accordance with the drawings and

    as described inB

    Q

    The responsibility forincorrect quantities

    rest on the Employer

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    41/43

    Lump sum on Drawing & Specification

    Tenderers are required to provide

    schedule of rates or tender price

    breakdown by themselves

    The responsibility for incorrect quantities

    rest on the tenderers

    Therefore, there are more risks imposed

    on tenderers when compared with firm BQ

    lump sum contract

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    42/43

    Difference between the With Quantities &

    Without Quantities Editions

    Where bills of quantities have not been produced

    and it is the intention of the parties to use a

    specification and a schedule of rates in its place,

    the without quantities edition of the standard formwill be used

    Without quantities edition differs from the withquantities edition in the following:

    The specification takes the place of the BQ as

    a contract document

  • 8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)

    43/43

    Common issues covered by

    Standard Forms of Contract

    Parties to the contract & the Professionals

    Quality & Workmanship

    Time (commencement/duration)

    Practical / Substantial Completion Payment

    Dispute Resolution

    Instructions / Variations to the contract

    Insurance Sub-letting

    Damages for breach of contract

    Determination