Upload
kidshieh
View
218
Download
1
Embed Size (px)
Citation preview
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
1/43
Contractual Procedures B
CN3036 Tutorial 1
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
2/43
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
3/43
Assignment
Briefing
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
4/43
Assignment
Weighting : 50% ; Examination : 50%
Maximum of 3,000 words
Write a professional report to yourcontractdirector
Correct format and well structure
(with use of numbered heading)
Font size 12 and 1.5 spacing
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
5/43
Assignment
Latest date for submission: 19 Dec 2010
Reference : relevant clauses from contracts
But do not re-write the clause (use your
own words to express)
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
6/43
Assignment Report FormatCover page Subject of report, author, date
Contents page Heading numbers
Abstract Brief summary of report e.g.
purpose of report
Introduction Background information e.g.
contract used
Main body of report Findings: Difference between 2
contracts
Conclusion Summary of results
Recommendation If any e.g. when appropriate to
use that contract
Appendices/ Reference correct format
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
7/43
Assignment
Critically compare the terms, conditions and
procedures contained within the standard FIDIC
conditions of contract for construction first edition
1999 with a standard HK conditions of contract
What Standard HK conditions of contract refer to?
HKIA (which edition? 2005 or 1999) GCC
Others (e.g. JCT)
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
8/43
Assignment Suggested Contents
Under the following headings:
Nature of projects with approximate values
Master programme
Establishing the contract sum
Procedures for sub-letting
Responsibility for health and safety
Procedures for claiming an extension of time
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
9/43
Standard Forms of Contract
B
ackground
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
10/43
Standard Forms of Contract
For the majority of building contracts, it is
common practice to use standard forms of
contract
Reason
It is essential to set out all the details of the
work in a proper form of contract, and state
each partys duties, obligations and rights
Otherwise misunderstanding and dispute
between the parties to a building contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
11/43
Standard Forms of Contract
Using a standard document avoids the waste of
time that would result from having to individually
draft the many terms necessary for each new
contract
In the event of disputes, standard forms of
building contract provide a means of settlement,
without the need to refer the matter to a court oflaw. E.g. an arbitration agreement clause in the
document allow the parties to refer this disputes
to arbitration
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
12/43
Private Sector
HKIA/RICS standard form
Most wisely used private sectorstandard form of building contract
Full title of this form is Agreementand Schedule of Conditions ofBuilding Contract (Standard FormofBuilding Contract) for use in
Hong Kong , Private Edition (WithQuantities and Without Quantities)
SFBC 2005 edition
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
13/43
Private Sector
FIDIC standard form
Most wisely used standard form of
contract for the purpose of
construction work (both building and
civil engineering) where tenders areinvited on an international basis
General Conditions are linked with
the Conditions of Particular
Application (which is the part of the contractspecially drafted to suit the peculiarities of the
individual contract) by corresponding clause numbers)
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
14/43
Private Sector
Certain employers, e.g. MTRC, Housing
Authority, Swire each produce a standard form of
contract for use on their own projects
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
15/43
Public Sector
Government standard form
Building
Government of Hong Kong General Conditions of
Contract for building, 1990 Edition
Civil Engineering
Government of Hong Kong General Conditions of
Contract for Civil Engineering Works, 1990 Edition
E&M Government of Hong Kong General Conditions of
Contract for Electrical and Mechanical Engineering
Works, 1990 Edition
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
16/43
Differences between Private Sector
& Public SectorStandard Forms
A mediation provision in public sector contract provide an
optional alternative to arbitration as a means of resolving
disputes
The public sector standard form, the payment certificate is
to be issued to the employerwith a duplicate copy to main
contractor. Payment required within 14 days of issue
The private sector standard form require paymentcertificates to be issued to main contractor, who will in
turn present them to employer, payment must be made
with X (21/30/45) days of presentation rather than of issue
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
17/43
Standard Forms of Sub-contract
Most standard forms of main contract will
have a sister document to be used when
the main contractor is directed by theemployer to enter into a nominated sub-
contractor agreement with a sub-contractor
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
18/43
Formalization of contract
Tender submitted by a contractor constitutes an
offerand if the tender is accepted without
qualifications or amendment legally binding
contract
But it is usual practice to quality the tender, which
has the effect of not binding either party legally
Until the standard form of contract document has
been signed by parties
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
19/43
Formalization of contract
When using Standard Form of Contract, the
signatures, together with name and address, of
both parties to the contract, the Employerand
the Main Contractor, are recorded in theA
rticleofAgreement
The names of both the architectand the quantity
surveyorappointed by the employer should also
be recorded
Contract Sum that the Employer has agreed to
pay the main contractor
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
20/43
Precedence of Contract Document
A building contract incorporates the following:
Contract drawings
Contract bills
(Bills of quantities/ Schedule of Rate)
Standard form of contract
Articles of agreement (signed)
Terms of contract (contract clauses) Appendix (fill in the details)
Special Conditions of Contract(Amendment to standard form of contract)
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
21/43
Precedence of Contract Document
If one document conflicts with another
document which one take precedence over
the other?
The specially written or amended clause
will take precedence over the standarddocument
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
22/43
Discrepancies & Errors in Contract
Discrepancies between contract
documents may be discovered :
During Pre-contract stage
Tenderer should immediately inform architect (bymean of tender query) and architect should make
necessary amendment and each inform tenderers
During Post-contract stage Contractor should immediately give architect
written notice and architect should issue A.I. to
correct the discrepancy which would be adjusted in
final account
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
23/43
Contracting Parties
ForBuilding Contracts
And their obligation under the contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
24/43
Contractors obligation
under the contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
25/43
Main Contractors obligations
Progress and complete the works in
accordance with the Contract (Clause 2.2)
Give written notice to the Architect immediatelyupon finding a discrepancy in or divergence
between contract documents
Provide programme and amendments whenamended
Comply with statutory obligations
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
26/43
Main Contractors obligations
Provide necessary insurance in respect of:
Damages to works
Damage to property owned by 3rd party
Personal injury to workmen
Damage by fire, storm, flooding etc.
Clause 18 and 19
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
27/43
Main Contractors obligations
Materials and workmanship complied withthe standards as described in Contract and
to reasonable satisfaction of the Architect
[Clause 8.1.3]
Contractor shall be responsible for the
setting out of the works
Submit any claims to architect in
reasonable time
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
28/43
Main Contractors obligations
Keep a competent foreman-in-chargeconstantly upon the works
Allow architect and his representativesaccess to the site/workshops at all
reasonable time
Permit carry out ofinspection [Clause8.2.2]
Rectify defects [Clause 8.4]
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
29/43
Employers obligation
under the contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
30/43
Employers obligations
Payment Employer is obliged to pay the main contractor for
work carried out
QS to value completed works and then certified by
architect, which in turn is paid by the employer
Give possession of site [Clause 23.1.1]
Employer must give main contractor possession ofsite in order that main contractor may carry out the
works
Employer need to specify the possession date and the
finish date (completion)
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
31/43
Employers obligations
Appoint Architect and Surveyor (Article of
Agreement)
Supply instruction employer must give
main contractor instructions concerning the
works
Employermust not interfere with progress
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
32/43
Non-contracting Parties
ForBuilding Contracts
And their obligation under the contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
33/43
Non-contractual parties to main
contract Consultant team involved in the design
and supervision of works are not parties to
the main contract
Each has their own employment contractwith the Employer
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
34/43
Architects Duty
Design exercise great care to give bestpossible advice and to warn employer ofpotential risks
Drawings to supply sufficient drawingsand information, within reasonable time,for the execution of works
Cost to ensure that building can becompleted within stipulated cost, or areasonable increase
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
35/43
Architects Duty
Supervision to supervise and inspect
sufficiently to ensure that materials and
workmanship conform with contractual
requirement
Payments to certify payments
[Architects Certificate] to the maincontractor, without fraud and with completeimpartiality
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
36/43
Quantity Surveyors Duty
Pre-contract Duties Cost advise Employer of project costs
Contractual arrangements advise on
suitability Tender documents prepare and send to
contractors
Bills of quantities prepare from tenderdrawings
Tender report- advise on choice of
contractors
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
37/43
Quantity Surveyors Duty
Post-contract Duties
Prepare certificates of payment involve
measuring and valuing the work properly
Prepare variation accounts measuring,
pricing and agreeing the value with main
contractors QS
Calculate adjustment adjustment to the
contract sum due to fluctuations
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
38/43
Professional Negligence
Architect, QS and consultant engineers areprofessional people
They owe a duty to the Employer to carry out
theirwork with proper care
They are liable for damages for negligence if
employersuffers a loss that is due to a lack of
care or duty
Legal action [Tort] may be taken against them by
employer based on terms in their employment
contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
39/43
Contractual Arrangements
ForBuilding Contracts
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
40/43
Lump sum on Bills ofQuantities
The contract sum is derived from the total
of the items in the BQ (which is prepared
by consultant QS)
The contractor undertakes to carry out the
work in accordance with the drawings and
as described inB
Q
The responsibility forincorrect quantities
rest on the Employer
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
41/43
Lump sum on Drawing & Specification
Tenderers are required to provide
schedule of rates or tender price
breakdown by themselves
The responsibility for incorrect quantities
rest on the tenderers
Therefore, there are more risks imposed
on tenderers when compared with firm BQ
lump sum contract
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
42/43
Difference between the With Quantities &
Without Quantities Editions
Where bills of quantities have not been produced
and it is the intention of the parties to use a
specification and a schedule of rates in its place,
the without quantities edition of the standard formwill be used
Without quantities edition differs from the withquantities edition in the following:
The specification takes the place of the BQ as
a contract document
8/8/2019 Contractual Procedures B 2010 - Tutorial 01 Assignment)
43/43
Common issues covered by
Standard Forms of Contract
Parties to the contract & the Professionals
Quality & Workmanship
Time (commencement/duration)
Practical / Substantial Completion Payment
Dispute Resolution
Instructions / Variations to the contract
Insurance Sub-letting
Damages for breach of contract
Determination