52
Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction Audit Services

Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Embed Size (px)

Citation preview

Page 1: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Construction Auditing Risks and Capital Project Recovery

Strategies for 2014 and BeyondPresented by:

Matt R. Gardner, CCA, CICA Practice Leader – Construction Audit Services

Page 2: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Agenda

Outcomes of this presentation

What is a Construction Audit?

Construction statistics

Why is it important to internal auditors?

Variations of Construction Audits

Types of construction contracts and associated risks to your organization

What to look for during an audit

High-risk areas and common issues

Examples and case studies

Page 3: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Outcomes of this Presentation

What a Construction Audit is and the variations of a Construction Audit

Why a Construction Audit is important to your organization

Determination if a construction project at your organization is a candidate for an audit

The various scopes of a construction review

Key high-risk areas to audit during a review

Page 4: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

What is a Construction Audit?

First, we must define what we mean by construction:

– Not just new construction but also renovations, remodels, demolitions, etc.

– Across all industries worldwide – health care, entertainment, higher education, government, etc.

– Includes schools, casinos, buildings, stadiums, highways/bridges, etc.

– Can include construction costs less than $1million but oftentimes $1million or more to accumulate larger cost recoveries

Page 5: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

What is a Construction Audit?

Audit is defined as an all-encompassing scope of the construction process from solicitation of bids to final payment.

– Not just looking for cost recoveries or overbillings, but also provide process improvement recommendations for the project management team

Page 6: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

– Is not just a cost recovery review but cost prevention

– Should involve auditors prior to contract execution

– Should act as intermediary between owner and General Contractor (GC)

– Should assist with disputes and litigation

Therefore, a Construction Audit…

Page 7: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction
Page 8: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction
Page 9: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

During the second quarter of 2013, the U.S. economy has expanded 1.7%

However, non-residential construction has not

1% decline in June 2013

$545 billion in construction costs – June 2013

Down from $551 in May 2013Source: Marcum Commercial Construction Index

Construction Statistics

Page 10: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Construction Statistics

The ups….

o Power segments up 3.6%

o Communication up 2.5%

o Health care up 1%

o Amusement/recreation up .4%

And the downs….

o Conservation and development down 9.4%

o Religious down 6.8%

o Water Supply down 5.5%

o Sewage and Waste down 5.3%

Page 11: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Construction Statistics

The forecast?

o Non-residential and residential construction are moving in opposite directions.

o Over a 12-month period, non-residential slumped down 4% while residential rose 17.6%.

o Pipeline of projects in various stages is very dense

o Time will tell

o Industry is the first the fall and last to recover

Page 12: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Why is it Important to Internal Auditors?

What does it mean to us and why are these audits necessary?

– Billions spent on capital expenditures each year

– Lack of project management resources and sound processes/procedures

– Improve internal controls around project management function

– Project management may not have sufficient independence to aggressively prevent all unreimburseable costs

Page 13: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

What does it mean to us and why are these audits necessary?

–Risks to your organization can be significant

o Loss of capital funds

o Fraud

o Impact to operations

o Impact to strategic objectives

o Lack of management/committee trust for future expenditures

o Litigation

Why is it Important to Internal Auditors?

Page 14: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction
Page 15: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Why is it Important to Internal Auditors?

What does it mean to us and why are these audits necessary?

– “In some organizations, cost recoveries from contract audits exceed the entire annual budget for the internal audit department, . . .”From Construction Contract Auditing as published in INTERNAL AUDITOR, February, 1999, by James D. Cashell, CPA, MBA, PHD; George R. Aldhizer, III, CPA, PHD; and Rick Eichmann, CIA

– Typical recoveries are 1 to 3% of total project cost

Page 16: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction
Page 17: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Common rebuttal:

“We hire a construction management firm to monitor and manage the project.”

Risk still exists even with outsourcing the project management function

May not have the owner’s best interest in mind

Possible collusion between GC and CM

Priorities such as schedule could take precedence over cost

Scope and contract changes between GC and PM could occur without proper oversight

Owner and/or auditors still need to stay involved throughout the process!

Page 18: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Common rebuttal:

“We have worked with the same GC and no issues or cost overruns have occurred in the past.”

Just because a project is on budget or was completed under budget does not mean all costs were appropriate

Was the original budget a sound figure?

Sound bidding and budget policies and procedures are needed

Aggressive GC savings established

Incentive to come in under budget

Scope completed as planned

Scopes of work eliminated to maintain budget

Substitution of materials

Utilize materials of lesser value and quality to limit cost

Page 19: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Common rebuttal:

“GCs that work on our jobs have never been convicted of fraud.”

Generally overcharges or unallowable costs are not due to fraudulent activity

Regardless of contract – “This is how it has always been done.”

Lack of resources by owner and/or GC

Lack of communication between owner and GC/architect

Excessive change orders/scope changes

Mathematical errors

Abundance of paperwork

Page 20: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Why is it Important to Internal Auditors?

However, some of these costs do turn out to be fraudulent

Lend Lease (Bovis)

– Cheated clients out of millions of dollars in overbilling scheme

– Undercut competition to get a job, then padded the books with change orders – often with the client’s knowledge

– Submitted falsified invoices to clients for labor when contractors were on vacation or sick

– Occurred over a decade’s time!

– Agreed to pay $56million to settle charges of over billing clients

Page 21: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Variations of Construction Audit

Contract review

Job walks

Limited scope/full scope

– Only audit select change orders or pay applications

– Audit from bidding to project close out

Based on contract type (GMP, lump sum, etc.)

Cost segregation studies – hidden tax savings

Page 22: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Contract Types

What are the types of contracts and the associated risks:

Lump Sum Time and Material Cost Plus Cost Plus: Guaranteed Maximum Price

Page 23: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

CONTRACT TYPES

Lump Sum

One price which includes fee, cost of work, and general conditions

Assigns majority of the risk to the contractor

Potentially higher markup by GC to take care of unforeseen contingencies

Risk of elimination of scope or use of low quality materials to stay within budget

Change orders should be scrutinized

Page 24: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Time and Material

Owner pays for actual cost of work (labor, material, equipment cost, etc.) plus a markup

Markup is a set percentage

Owner must establish labor rates, material costs, and equipment rates prior to contract

No incentive for GC to reduce costs

Risk of low productivity by GC

More supervision required by owner

Job cost ledger must be audited

CONTRACT TYPES

Page 25: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Cost Plus

GC is reimbursed for specified allowable costs plus a fixed fee

Owner assumes risk for cost overruns

No incentive by GC to reduce cost

Low productivity by GC

More supervision required by owner

Job cost ledger must be audited

CONTRACT TYPES

Page 26: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Guaranteed Maximum Price (GMP)

GC is reimbursed for specified allowable costs plus a fixed fee

GC guarantees the project will be built within a predetermined amount / assumes risk for cost overruns

Savings can be shared with the GC as incentive

Job cost ledger must be audited

CONTRACT TYPES

Page 27: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Guaranteed Maximum Price (GMP)

Example savings model (50/50 split)GMP amount of $10,500,000

Cost of work: $10,000,000

Savings (50% of $500K): $250K

Amount due to GC: $10,250,000

CONTRACT TYPES

Page 28: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction
Page 29: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

What project(s) should be selected for an audit?

Size (Contract Value)

High Profile/High Risk

Fast-Track Schedule

Complex Contract Terms

Type of Contract

Experience of Owner Representative

Experience of internal Project Management Team

Experience of General Contractor

Page 30: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

What should be included in your audit approach?

If possible, auditor involvement should occur before contract signing

Contract language should be updated to reflect the type of project and contract

– Identify contradictory language

– Lack of specific provisions (insurance, audit clause, etc.)

– Clarification on allowable and unallowable costs

– Penalties in place for nonconformance with contract

– Include requirements for a detailed breakdown of construction cost for cost segregation studies once work is complete

Page 31: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Getting started: Who are the players?

– Who, what, when, where, how, and why

– Owner’s project management team or third-party construction manager

– General contractor and subcontractors

– Architect

Utilize a questionnaire to get a perspective

– Who, what, when, where, how, and why

Page 32: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Process and procedure control review

– Competitive bidding

– Capital approvals/expenditures

– Compliance with policy and procedures

– Payment applications

– Change order process

– Estimating and scheduling

Financial review

– Reporting system - internal

– Financial reports

• Reports agree with actual costs incurred

– Payment application processing

– Change order costs

Page 33: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Auditing internal procedures, bid processes, change orders and pay applications are not the beginning and the end.

There are several key risk areas that lend themselves to unnecessary costs that effect your organization’s performance.

Of course this list is not the beginning or the end …

Page 34: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Change orders

General conditions (allowable vs. unallowable cost)

Equipment rental costs

Labor and labor burden

Subcontractor payments

Bid process

Subcontractor contracts

Page 35: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Change Orders

High risk

Owner’s contract must include detailed requirements for estimating/pricing and the ultimate billings of costs

Strong procedures and processes must be in place

Markup percentages vary by level of contractor

Adequate support often not provided

Review of labor rates, if not agreed upon in advance, is time consuming

Page 36: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

GeneralConditions

High risk

Owner’s contract must include detailed requirements on what is considered allowable and unallowable

Too many supervisors on site

Excessive entertainment and travel

Sales tax on exempt projects

Rebates or cash discounts not passed to owner

Excessive relocation, moving, transportation, and communication costs

Page 37: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Equipment& Rental

Costs

High risk

Owner’s contract and plans must include detailed requirements as to what equipment is expected to be used on the job

Contract should indicate what equipment is anticipated to be rented through the GC

Contract needs to specify what is allowed

Use industry benchmark data

Charges in excess of total value- AED Green Book for example

Page 38: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Labor & Labor

Burden

Labor burden percent used is often incorrect

Labor burden often includes non-reimbursable items:- Bonuses- Parties- Education

Unemployment tax still charged after maximum reached

Ease on owner and auditors if rates, including labor burden, are agreed upon for all crafts before work starts

If not, contracts must define what is allowable in labor burden build ups

Page 39: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Subcontractor

Payments

Back charges not passed through

Markups calculated incorrectly

Duplicate COs

Errors in payment application

BidProcess

Need sound internal policies, procedures, and processes

Adequate bid schedule

General Contractor/Project Managers competing for packages of work

Design documents completed

Page 40: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

High-Risk Areas and Common Issues

Subcontractor Contracts Critical for contracts with a Guaranteed Maximum

Price (GMP)

Variances (under-runs) accrue to the owner

Risks

• Buyouts are not reviewed/managed by owner

• The GC transfers the variance to its self-performed budgeted line items

Page 41: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Case Study #1Case Study #1

Background and business objective

The project, a new retail facility completed for $9 million, was 100% complete when the client requested audit assistance.

The construction agreement was for a Guaranteed Maximum Price. The audit scope included analysis of the construction contract and an evaluation of the contractor's billing to determine compliance.

The owner also requested recommendations for best practices and/or procedural improvements that could be incorporated into the owner's project management process.

Page 42: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Case Study #1Case Study #1

Approach and solution

The first objective of the audit was to review documentation of costs incurred and paid for by the owner in completion of the project to determine if the requests for reimbursement were in alignment with the applicable contracts.

The scope of the audit included all costs invoiced by the general contractor including subcontractor costs, in addition to direct costs paid for by the owner.

The second objective of the audit was to obtain an understanding of the control environment surrounding this particular project to determine if any control deficiencies were noted.

Page 43: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Case Study #1Case Study #1

Outcomes and results achieved

Potential overcharges totaling $250,000 (2.8% of the contract value) was identified due to inaccurate labor burden billing rates. The general contractor billed labor billed ups (FUTA, SUTA, workers compensation, insurance, etc.) at full regulatory rates rather than the actual rates incurred and to be billed per contract requirements. This was identified by viewing actual detailed labor records provided by the General Contractor.

Provided the owner with over 10 process and procedural improvements to easily identify and prevent these costs from being passed through during the course of projects going forward.

Page 44: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Case Study #1Case Study #2

Background and business objective

The project, a new outpatient facility completed for $42 million, was approximately 50% complete when the client requested audit assistance.

The construction agreement was for a Guaranteed Maximum Price.

The audit scope included analysis of the construction contract and an evaluation of the contractor's billing, specifically equipment rental rates and general contractor markups, to determine compliance.

Client PM identified what he thought were excessive equipment rates on job cost

report.

Page 45: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Case Study #1Case Study #2

Approach and solution

The objective of the audit was to review documentation of costs incurred and paid for by the owner in completion of the project to determine if the requests for reimbursement were in alignment with the applicable contracts.

Specifically, a full detailed review of equipment rental rates and markup percentages on change orders was performed.

Approximately $8 million was added via change orders for the project. The scope of the audit included all costs invoiced by the general contractor including sub-contractor costs, in addition to direct costs paid for by the owner.

Page 46: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Case Study #1Case Study #2

Outcomes and results achieved

Potential overcharges totaling $100,000 were identified due to:

• General contractor owned rental equipment billed in excess of the fair market value.

• Overhead and profit were calculated by applying 5% overhead before applying 10% profit by general contractors and subcontractors resulting in a tiered profit margin.

These overcharges were identified by reviewing general contractor rental equipment charges applied to the job and comparing their fair value to the charges applied to the job.

Approximately 90% of the tools/equipment charged to the job were billed in excess of the fair market value. The tiered markup was identified by recalculating markups applied by the general contractor and subcontractors on change orders

Page 47: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Exercise # 1See handouts

Page 48: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Exercise #2

1. You have been asked to review equipment rental charges submitted by the General Contractor (GC) to ensure they are in line with regional market rates

2. Contract states the GC will pass along 100% of the AED Green Book costs to the owner

3. You select a few charges to determine accuracy and compliance with contract

Page 49: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Equipment Time used Amount charged

Telescopic BoomSelf-propelled 51-60ft

3 wks, 1 day $3,390

Crane-Hydraulic35-39.9 ton

3 days $1,533

Fork lift2k-3k lbs.

5 days $600

Equipment Monthly $ Weekly $ Daily $

Telescopic BoomSelf-propelled 51-60ft

$2,847 $1,019 $333

Crane-Hydraulic35-39.9 ton

$4,600 $1,533 $511

Fork lift2k-3k lbs.

$1,124 $369 $120

Charges per pay applications

Page 50: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Summary

Procurement of capital construction assets involves high risk activities and complicated execution processes.

Construction Audits and Cost Segregation Studies are not an expense – they are necessary for sound, effective cost management that reduces total project costs.

Construction Audits are an essential internal control process to maximize capital program effectiveness.

Auditor involvement in the beginning provides a tone of oversight and often results in limited cost overruns or overcharges/billing errors.

Page 51: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction
Page 52: Construction Auditing Risks and Capital Project Recovery Strategies for 2014 and Beyond Presented by: Matt R. Gardner, CCA, CICA Practice Leader – Construction

Thank you!

Questions?

Matt R. Gardner, CCA, CICA Practice Leader – Construction Audit ServicesHonkamp Krueger & Co., P.C. | 888-556-0123

[email protected] | www.honkamp.com