    Creating Work Packages (Production Orders)

    From Cloudis CMPIC Wiki

    Contents

    1 Maintain Work Packages

    1.1 Creating the work package1.1.1 Adding Cables to the Work Package

    1.1.2 Other useful queries and reports at this stage of the process

    1.1.3 Looking at more filters to use for Work Packages

    1.1.4 Additional flexibility in creating work packages

    1.2 Releasing the work package

    1.2.1 Cable cutting, reports, installation management

    1.2.1.1 Using Cable Recuts if required at any time.

    1.2.2 Print the cable pulling (running) sheet

    1.2.3 Record cable installation progress

    1.2.4 Look at a progress report

    1.2.5 Complete cable pulling progress

    2 Query Cables and Work Packages3 Work Package Release

    4 Work Package Release Status

    5 Cables on WP affected by Change Control

    6 Cables with Reallocated Work Package

    7 Reports

    7.1 Work Package Detail

    7.2 Detailed Cable Schedule

    7.3 Segment Report

    7.4 Positional Node Analysis

    7.5 Schedule of Local Cable Routes

    7.6 Production Cable Changes

    7.7 Cable Status by Block

    7.8 Cable Changes Summary8 References

    Maintain Work Packages

    Create and maintain Work Packages (WP) and the criteria used to select cables for the Work Package. From this screennavigate through to screen to link cables to the WP.

    Work packages (sometimes referred to as Production Orders) are the way in which cables are grouped together for installation.

    Once grouped together, the cables can then be tracked and managed as a single work package.

    There are many criteria that could be used when selecting cables to group together on a work package, but the key thing is thatthese work packages can be built up over a period of time, adding more cables as design progresses. So, before installationstarts, you can register the work packages to represent the different stages of the build, then gradually add cables to those workpackages (sequencing the cables as necessary) and then releasing those work packages once installation should begin.

    The cables can be grouped together by using one or more of the following criteria:

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    2/24

    When creating a Work Package, the user adds the selection criteria line by line using as many criteria as are required to filter thenumber of cables down to those required on the work package. If, after this filtering, there are more cables eligible for inclusion

    on the work package than is desirable then they can be added cable by cable from the filtered list.

    Creating the work package

    For the following example the cables will be grouped together by ROUTE SEGMENT. A route segment being a hanger, tray,

    penetration or other part of the nodal network.

    The first thing you need to do decide which segment(s) are to be used as the basis for the Work Package.You may already havethis information from a drawing or, you can use CMPIC to search for relevant segments.

    If you go to the Nodal Network > Create Nodal Network screen, using CMPIC searches you can find, for example, just the

    penetrations (MCTs) that you are interested in. You can see from the Used boxes which segments have cables on them. If youdouble click on one of these segments you will be able to see the list of cables routed on it.

    If you make a note of the segment ID(s) from the Create Nodal Network screen you can the use these in the creation of the WorkPackage.

    The Work Packages themselves are created in the Maintain Work Packages screen which can be found under: Cable Installation> Cable Work Packages > Maintain Work Packages (see screen shot below)

    In the Work Package ID field type an ID for the package.

    If you have more than one site at which the Work Package could be carried out, these sites can be created in Library Data andwill then be displayed here. To create sites, first create them in the Library Data > General Data > More > Maintain Sites screen.

    Then go into Library Data > Project Configuration screen. In the Build Details tab you need to double click in the Site ID field andselect one by one the sites that you created in Maintain Sites. Give each a priority number to dictate their position in any lists ofvalues of sites. These sites are now available to add to the Work Package.

    Note: You must have at least 1 site defined to be able to create a Work Package

    If Installation Teams have been entered in Library Data then the team responsible for this work package can be added by doubleclicking in the Installation Team field and selecting as applicable. Teams need to be defined in Reference Data against a type ofITEAM first, and could represent a team, person or sub-contract company. It is worthwhile adding Teams because CMPIC has a

    number of useful reports that can be generated by Team.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    3/24

    When you SAVE the record the date of creation will be populated.

    You can also set the Operator field to Equal To or Not Equal To the value that you are entering.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    4/24

    This takes you to the associated screen shown below.

    Your work package number will be in the top left hand field.

    Follow the instructions below.

    Use the Green Traffic light icon to retrieve the cables which match the criteria for the work package and have had their routes

    approved. Tick the boxes to the right of the cable list to select a few cables to go on the work package. Press the COPYSELECTEDbutton. This copies the cables into the working area. Press SET POSITION. This gives each cable a positionnumber. This number normally represents the order that the cables that have been cut are to be wound onto a smaller drum forcarrying to site or on board. The position can be set by: Cable Tag Number, Diameter, Length or Segregation and this criterion is

    set using the pull down list. Once set here, position can be modified later by the cable cutting team if need be.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    5/24

    Once you have set the position, click on the Link to Prodn WP button. You will get a message Linked nncables Close down this

    screen by using the EXIT icon on the toolbar. You are now back in the main Work Package screen and you have created a WorkPackage with associated cables.

    A note about Setting Tape Marks:

    If you use Tape Marks to identify the point to which a cable should be pulled e.g. an MCT, then these tape marks can be set by

    CMPIC so that the cutting team know the exact point that the mark should be made.

    To enable Tape Marks to be set, you need to have the project default setting switched on. This is found in the Production tab inthe Project Configuration screen. You may need to get your system administrator to switch this option on. THIS OPTION NEEDSTO BE ENABLED BEFORE YOU CREATE ANY WORK PACKAGES IF YOU WANT TO USE TAPE MARKS.

    If the project default for "Use tape marks?" is set ON, then when the work package is created, the position of the tape mark mustalso be recorded. The tape mark is the distance from a specific cable end to the common segment (hanger, tray or penetration).This distance is calculated automatically by CMPIC when the user selects which cable end the length should be calculated from.

    It can be populated in batch for cables which all originate in the same area. Otherwise you will need to type in the length

    manually in the field headed Tape. This will then note on the cutting sheet the length and from which end the tape mark shouldbe made.

    Adding Cables to the Work Package

    Once cables have been selected for inclusion on the Work Package and extra cables added at a later date, it's possible that the

    position ordering of cables on the Work Package is no longer correct. In the Pos Field it's possible to manually change the valuefor position to get cables in the correct order again. To do this, it may be necessary to give cables an artificially high or low

    position value, but the Resequence button will then update the Position so that it runs sequentially from 1 to the total number ofcables.

    The Query Cables and Work Packages (CMYF04) screen is useful because it can be used to list all cables which have yet to be

    allocated to a Work Package. There's also an output to CSV.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    6/24

    General installation notes for the work package should be entered at the top of this screen (see screenshot overleaf), whereas

    cable specific installation notes should be entered in the Details field at the bottom of the screen. The Work Packages report(CMYP/R01) details each work package and includes these instructions.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    7/24

    Other useful queries and reports at this stage of the process

    Segment Report. Lists all cables running through a particular segment. Useful when looking for cables which are all routed

    through a particular transit, hanger, tray etc.

    1.

    Positional Node Analysis. Lists all cables which start and/or finish in a particular area. Useful for finding cables to group on

    a work package.

    2.

    Work Package Pulling Statistics. Need a norms file for this, or else it will use the defaults, but it will show the estimated

    time required to install the selected work packages (and percentage complete as pulling begins).

    3.

    Work Package Progress by Team. Has options for "Work Package not allocated to a team", "Work Package assigned to

    team, no progress" etc etc. Very useful because you can see where in the planning process the work package has got to.

    4.

    You now have a work package with cables on it which we can now take to the cable cutting stage.

    Before doing so, however, we should look at other filter criteria that can be used when creating a work package.

    Looking at more filters to use for Work Packages

    So far we have just looked at using 2 segments (hangers, trays or MCTs for example) as the filter criteria for the cables to beassociated with the work package.

    In the case of segments, if you add more than one segment, the filter looks for cables which pass through ALLof the segmentslisted. If you refer to the Explain Filtertab on the Work Package creation screen, the filter explanation is: Route ContainsSegment '18929' And '18914' .

    If you add even more segment numbers to the filter, these will be included in this same filter and appended with an AND.

    In the case of all other filter criteria, the criteria are added as OR.

    See screenshot below.

    Additional flexibility in creating work packages

    Where you are looking to maximise the potential of the installation resource available, it could be that more than one set ofselection criteria for a work package would be useful.

    To cater for this possible requirement, you can create up to 10 sets of criteria against which CMPIC will fi lter and look for eligiblecables.

    To do this, you need to be in the Maintain Work Packages screen.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    8/24

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    9/24

    As explained above, you can create up to 10 sets of filter criteria. This can be useful in keeping each set quite simple andtherefore easily modified.

    If you choose to add the filter criteria to just one set, then there is no limit to the number of criteria you can add.

    Releasing the work package

    Once you are happy that all the cables required have been added to your work package, you need to release the work packageso that it can pass to the next stage of the process.

    Go to Cable Installation > Cable Work Packages > Work Package Release

    Click on the green traffic light to bring back the Work Packages awaiting release.

    Click in the box to the right of the work package you have created, and then click on RELEASE

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    10/24

    At this point Work Package Release Status (see below) is a useful screen.

    This is useful for:

    a) Planning because they can see all the work packages yet to release. b) Stores because they can see all the work packageswhich have been released to them but for which they have yet to produce the cutting sheet or, if an asterix is shown at the end ofthe row (just after the CS button) this signifies that a cutting sheet has been produced but there are still cables remaining on the

    work package which have not yet been published on a cutting sheet. c) Production because they can review the work packages

    which they have to install.

    This screen shows the status of each work package.

    If the work package list is longer than will fit on the one page, you can use the filters Not Released, or Released, no CS (nocutting sheet created as yet).

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    11/24

    As with all CMPIC screens you could also use the Query facility in the Prodn WP column to look for specific groups of recordse.g. %TEST% to retrieve all work package IDs including the string TEST.

    Under the Rel? column, you can see which work packages have been released.

    Once the work package has been released, you can arrange for the cables on the work package to be cut.

    Cable cutting, reports, installation management

    Go to Production Module > Cable cutting & pulling > Cable cutting schedule

    Use the green traffic light to retrieve your Work Package. Only Released Work Packages will be available.

    Refer to training manual section P4 Create Drums to find out how to add available material so that CMPIC can use it.

    Initially, all cables listed in the Cutting Schedule have their Drum ID set to TBC (or the no-drum identifier that was defined inproject defaults). You can select drums on a cable by cable basis by double clicking in the Drum No field which gives you the list

    of eligible drums (only drums with sufficient length remaining and located at the same site (if relevant) are displayed). This is

    useful if a particular drum is required or one which is located in a particular store (for ease of cutting) should be used.

    If a cable has been incorrectly assigned to a drum, you can reset its value back to TBC (or the default name for No Drum) and itslength will become available on the originally selected drum for use again.

    Alternatively, CMPIC can optimize the use of drums for you. Using the Optimize Drums button will attempt to allocate a drum to

    all cables with TBC; it prioritises drums as follows:

    Any "not normal" drum i.e. Any length which is saved in the Drum Schedule but which is not categorised as a Normal

    Drum. (These would include returned lengths, coiled lengths etc. These different categories can be added to your CMPIC

    system based on your own requirements).

    1.

    If only normal drums exist they wil l be chosen in order as follows:1.

    a drum that has already been allocated to another cable on the work package then

    a drum that has already been used, but not on this work package then

    a completely new drum

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    12/24

    Once you have added drum details, you will have material available. If you now double click in the Drum No field you will see

    eligible drums listed.

    You can select drums from the list cable by cable, or if you click on the Optimize Drums button, CMPIC will allocate drums based

    on the selection process outlined on the previous page.

    Once drums have been allocated to as many cables as possible, the cutting sheet can be printed using the Print button. This isthe instruction for stores to cut the cable. You can use Check Print which gives a preview of the cutting sheet, without actually

    updating any cable dates. The Print All option displays all cables on the work package, with their status (useful for large work

    packages).

    Click on the Print button, choose Final or For Use option and Preview the report on your screen.

    If you now take another look at the Drum Schedule, in the Drum Usage tab you will see that material has been ASSIGNED andthe drum lengths modified.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    13/24

    Now that you have printed the cutting sheet, in the Cutting Schedule screen you will see that the Issued to Store column has

    been updated with the date.

    The next stage is for someone to add the Date Cut once the cables have been cut and are ready to collect for installation.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    14/24

    As well as populating the Date Cut field, you can also add the name or clock number of the person who cut the cables, and thelocation of the coils or lengths. There are also fields for name of the person who collected the cables.

    Notes about the cutting process.

    The Print option publishes the cutting schedule for all cables on the work package which have not already been issued on a

    cutting schedule (or a recut is required).

    These reports also include an option to produce a label ident f ile. If selected, this wil l produce a CSV file which can then besubmitted to a cable marker system. (The label ident CSV file has fields for: Device to Device, Area to Area, Cable Type,Segregation, Length, Reeving Point (if used), Cable ID.)

    If a cable has been issued on a cutting sheet, so Issued to Store has a date, and stores subsequently discover there isinsufficient length on the drum, or it would be better to use a different drum, the only way to change the drum assigned is to use

    Revert Drum. This process is explained overleaf.

    Note: the Reeving Point is the ID of the hanger, MCT or tray that is being used as the point to which the cable wil l be pulled and

    which will correspond to the tape mark made on the cable. We refer to the same point as a Pull Point.

    Revert Drumis only available for cables which have not yet been cut, but which have an Issued To Store date. Selecting RevertDrum sets the Drum No back to TBC and releases that cable's hold on the drum length which is reallocated back to the drum forgeneral use. A new drum can then be assigned to the cable and its cutting sheet printed again.

    To Revert the drum, highlight the cable that you want to move to have cut from an alternative drum. Then click on Revert Drumbutton.

    You will get the alert shown below.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    15/24

    If you OK the alert, then you will be able to double click in the Drum No field and allocate an alternative drum.

    Once the drum has been allocated, the Issue to Store field will be blank. To populate this field, you Print the cutting sheet again

    using the Final or For Use option.

    Useful reports at this stage:

    Unallocated Drum report. This gives a list of all cables with a drum number of TBC i.e. no drum assigned, but where there

    is a suitable drum available, this is listed. It is a way of checking for cables which haven't yet been assigned a drum, but

    there is now material available. There is also an option to only show those cables for which there is no suitable drum

    available. This can be used to identify where more stock is required.

    Cables Cut Between Dates

    Drum Usage History. Useful if you find that a drum is faulty and you need to recall all cables cut from the drum, or if you

    just want to see how the material has been called-off. It also shows whether cables have actually been cut or if they are

    just reserving the length.

    Material Control report.

    Using Cable Recuts if required at any time.

    If a cable has been cut, then material will have been used from a drum. If a subsequent recut of the cable is required at any time,

    then you would need to add a recut. The Query Cable Recuts screen (CMYF12) provides visibility of cables which have been cutmore than once.

    To add a Recut, you follow this process:

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    16/24

    Note: if you are using Tape Marks.

    Adding the recut takes you back to the main Cable Cutting schedule.

    To enable CMPIC to allocate and assign cable accordingly, you now need to print a new cutting sheet.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    17/24

    The Cutting Report has details of the cables to cut and has temporary labels which can be cut out and used to identify the

    cables.

    Cut length - by default this is the design length rounded either up or down (controlled by a project default). However, this figurecan be modified if the installer is certain that a cable would be too long/short otherwise (there is a warning if the cut length is

    different to the design length).

    Double click in Store Despatch - it will fill in todays date.

    If you like, put in the name of the person who collected the cables from store.

    SAVE and EXIT

    Quick Update is available to populate any of the remaining fields eg. Date Cut and Cut By can be entered once and copied to all

    cables which have had their cutting sheet issued.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    18/24

    Print the cable pulling (running) sheet

    Go to: Production Module > Cable cutting & pulling > Reports > Cable running sheet.

    This report gives authority to the installation team to install the cables which have been cut as part of the Work Package youcreated.

    The report gives installation details for the cables.

    Notes:

    The running sheet (equivalent of Pull Sheet or Pull Card) can be produced even if the cables have not been cut (this is so

    sites aren't prevented from raising status to PSP (Pull Sheet Printed) because they are waiting for the arrival of material),

    but the running sheet will display an asterix against any cable which does not have a drum assigned (it doesn't actually

    have to be cut at that stage).

    1.

    Once cables have been drummed, reprinting the running sheet will display the cable without the asterix. Since the runningsheet is the instruction to install cables, the asterix gives the installer visibility of the cables which will be missing. Some

    sites may wish to supply the work package report (CMYR01) with the running sheet, because this shows any additional

    installation instructions (if used).

    2.

    Reprinting the running sheet gives the option to exclude any fully installed cables. This is useful if work is progressing in

    stages and not all cables can be installed at the same time, so the report just shows those cables not fully installed. If the

    3.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    19/24

    cable has been coiled and the point (node) at which it has been left is recorded in CMYF13 Cable Pulling Progress (note

    that the project default for Coil Location must be set to Node), then this node is also highlighted when the Reprint option is

    chosen.

    Other useful reports:

    Team Pulling Progress

    Work Package Progress by Team

    Work Assigned and Completed by team

    Record cable installation progress

    Go to: Production Module > Cable cutting & pulling > Cable pulling progress by WP

    Use the green traffic light to retrieve the list of work packages and scroll down until you find yours.

    Tick the box to the right of a cable.

    You can set the cable to be Fully or Partially Pulled (installed)

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    20/24

    To set a cable as Partially Pulled, tick the box to the right of the cable(s) to be registered as partially pulled.

    If you are using Tape Marks

    If you are using Tape Marks then clicking on the Set to Tape Mark will fill in the length of cable to the mark.

    If you now click on Set to Reeving point, you will be asked at which node the coil should be left.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    21/24

    This is so that when you later reprint the pull sheet for the next shift or the team which will continue the installation, the location of

    the coil will be highlighted on the report.

    You can now add the Team responsible by double clicking in the Team field.

    Click on Continue.

    You will see that the status of the cables is now Partially Pulled.

    You can return to these cables anytime and pull some more in, or register them as fully pulled.

    SAVE and EXIT

    Look at a progress report

    Go to:Production Module > Cable cutting & pulling > Reports > Progress/Statistics > Work Package Pulling Statistics

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    22/24

    Double click in the Work Package field. Select your work package.

    Click on PREVIEW.

    Take a look at the report which shows details of how much cable has been installed on your work package.

    Like many CMPIC reports this data can be output as a .csv file for use in Excel or reporting tools.

    Another option you can set up for this report is to link it to your own in-house norms for cable pulling. So if you have estimatedtime to pull in a given length of cable (by metre of foot) in a .CSV file then the report will calculate the time needed to complete

    the job. These norms are held outside of CMPIC in a location given to CMPIC so that it reads the .CSV when running the report.

    Complete cable pulling progress

    Go back to the Cable Pulling Progress by WP screen, retrieve your work package and update all cables to be Fully Pulled.

    SAVE & EXIT

    Query Cables and Work Packages

    Shows each cable and associated WP

    Using this screen query you can see which cables have been allocated to a Work Package and which have not.

    Results of the query can be output as a .csv file.

    Work Package Release

    Once a WP has been created and is ready for production, this screen is used to release it. Once the WP is released, all cables

    on it are released which allows them to have a pull sheet or running sheet created as part of the production process.

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    23/24

    By checking the boxes to the right of the Work Packages you want to release and then clicking on the Release button, this willprocess the Work Package.

    Work Package Release Status

    This query screen gives a summary of the various Work Package release statuses.

    By using the buttons you can see which Work Packages have not been released, or which have been released but have not hada cutting sheet printed yet.

    By clicking on the CS button you can also see cutting sheet information, where this exists.

    A red star to the right of the CS button indicates that there are still cables on the WP for which cutting sheets have not yet been

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...

    f 24 24.04.2014 11:34

  • 8/10/2019 CMPIC 7 Creating Work Packages (Production Orders)

    24/24

    produced.

    Cables on WP affected by Change Control

    If, by changing the route or other attr ibutes of a cable through Change Control, that cable no longer meets the criteria of the WPit is on, then it will appear in this screen query. This alerts the user that the cable has been removed from its original WP and is

    awaiting reallocation.

    Cables with Reallocated Work Package

    Shows list of cables which have been subject to reallocation of WP.

    Reports

    Work Package Detail

    Lists by work package the details of cables including length and from which drum cables were (or are to be) cut.

    Detailed Cable Schedule

    More detailed cable schedule (usually to customer design)

    Segment Report

    List of cables in each nodal network segment along with cable details.

    Positional Node Analysis

    Where used, coordinates appear with the node identifiers.

    Schedule of Local Cable Routes

    List of cables scheduled to or from devices located in a given area.

    Production Cable Changes

    List of cables which have been changed between two dates. Parameters for type of change.

    Cable Status by Block

    Where blocks are defined, lists cables within the block by status. Report parameters by block, cable status and whether the

    report is for cables which are fully contained within the block or which start and/or end in the block.

    Cable Changes Summary

    It is possible in CMPIC to create and maintain a list of Design Authorisation Notices (DANs) or Engineering Change Requests

    (ECRs). This report prints out changes to cables and devices which are covered by a given DAN or ECR. These DAN/ECRrecords are separate and in addition to the CMPIC Change Request raised to reduce the route or termination status of a cable atPSP and/or TSP.

    References

    Retrieved from "https://wiki.cloudis.com/mediawiki/index.php?title=Creating_Work_Packages_(Production_Orders)&oldid=4145"

    Categories: CMPIC Overview CMPIC FAQ CMPIC Help CMPIC Knowledge Base

    This page was last modified on 29 November 2012, at 05:10.

    This page has been accessed 89 times.

    Copyright Cloudis Ltd 2014

    ating Work Packages (Production Orders) - Cloudis CMPIC Wiki https://wiki.cloudis.com/wiki/Creating_Work_Packages_(Production_...