Upload
werner-conny
View
239
Download
0
Embed Size (px)
Citation preview
8/18/2019 CGMP Complete
1/128
The Institute of
Quality Assurance
PharmaceuticalQuality Group
A Guide to the GMP requirementsof PS 9000:2001 Pharmaceuticalpackaging materials
8/18/2019 CGMP Complete
2/128
The Institute of Quality Assurance
Pharmaceutical Quality Group
PS 9004
A Guide to the GMP requirements
of PS 9000:2001 Pharmaceutical packaging materials
September 2004
i
8/18/2019 CGMP Complete
3/128
ii
8/18/2019 CGMP Complete
4/128
P S
9 0 0 4
g u i d
e P S 9 0 0
4 g u i d e
PS 9004 guide
ISO 9000
+
GMP
for Pharmaceuticalpackaging materials
=PS 9000
Figure 1. Model of PS 9004: a Guide to the GMP requirements of PS 9000
iii
The symbol is used in Part 1 to identify risk areas.
8/18/2019 CGMP Complete
5/128
iviv
ISBN 0-906810-79-5
PS 9004: 2004
For further information about the Pharmaceutical Quality Group (PQG) and
any additional information or updates on PS 9000 or PS 9004 visit the PQG
website on: www.pqg.org
PS 9004 is available from:
IQA Information Service
12 Grosvenor Crescent
London SW1X 7EE
Tel: + 44 (0)20 7245 6722
Fax: + 44 (0)20 7245 6788
e-mail: [email protected]
website: www.iqa.org
8/18/2019 CGMP Complete
6/128
v
COPYRIGHT
PS 9004 copyright
© 2004 Institute of Quality Assurance (IQA)
This PS 9004 guide is copyright protected by IQA/Pharmaceutical Quality
Group(PQG). However in pursuit of their objectives to promote quality
throughout the pharmaceutical manufacturing and supply industries,
permission is given to use the contents for quality system improvement
in education, training, auditing or for certification purposes, provided
acknowledgement of the source of the material (PS 9004 IQA/PQG Copyright)
is given. Reproduction,storage in a retrieval system,transmission in any form
or by any means,electronic, photocopying, recording or otherwise FOR ANY
OTHER PURPOSE without prior permission being secured is prohibited.
Requests for permission to reproduce should be addressed to the IQA at the
address below:
IQA Information Service
12 Grosvenor Crescent
London SW1X 7EE
Tel: + 44 (0)20 7245 6722
Fax: + 44 (0)20 7245 6788
e-mail: [email protected]
Reproduction may be subject to royalty payments or a licensing agreement.
Violators may be prosecuted.
v
8/18/2019 CGMP Complete
7/128
vi
8/18/2019 CGMP Complete
8/128
vii
MHRA FOREWORD
The EU Guide to Good Manufacturing Practice (GMP) emphasizes the need for
pharmaceutical manufacturers and assemblers to ensure that the packaging
materials that they use are of the appropriate quality. Not only is this in the
interests of patient safety, but also in the pharmaceutical industry where
the increasing use of automated packaging processes relies heavily on the
consistent quality of packaging components.
Each year the Medicines and Healthcare products Regulatory Agency
(MHRA) receives and investigates a number of reports of quality defects
concerning medicinal products. A significant proportion of these concern
packaging errors, some of which are attributable to the use of packaging
materials not of the desired quality. The introduction of PS 9000 in 2001 by
the Pharmaceutical Quality Group of the Institute of Quality Assurance was
a key step in promoting the understanding of GMPs relevant to the suppliers
of packaging materials to the pharmaceutical industry. PS 9000 focused on
the development and implementation, by suppliers, of a quality management
system designed to provide assurance of the quality of their products and to
enhance customer satisfaction. Its contribution was welcomed by both industry
and the Regulator. PS 9004 is aimed at increasing the awareness of the quality
management system requirements embodied in PS 9000. This comprehensive
and easy to follow guide explains further the GMP requirements of PS 9000.
It adopts a risk assessment approach to the identification and implementation
of preventive action and uses case studies to illustrate areas of GMP risk.
The MHRA encourages the introduction of PS 9004 designed to improve
product and service quality in the supply of packaging materials for medicinal
products, for the benefit of patients and the pharmaceutical industry as a
whole.
John Taylor Quality and Systems Manager
Inspection and Enforcement Division, MHRA
8/18/2019 CGMP Complete
9/128
viii
8/18/2019 CGMP Complete
10/128
ix
GENERAL INTRODUCTION
What is PS 9004?
This guide aims to assist suppliers of pharmaceutical packaging materials to
understand and implement the Quality Management System (QMS) of ISO
9001 and the application standard of PS 9000. It supplements the following
documents:
• ISO 9001 which specifies the requirements of the international QMS
standard
• ISO 9004 gives guidance on ISO 9001
• PS 9000 is an application standard written by the PQG for suppliers of
pharmaceutical packaging materials that integrates ISO 9001 and ISO
9004 together with additional Good Manufacturing Practices (GMP)
requirements particular to these suppliers
Companies complying with PS 9000 will comply with ISO 9001 and also the
additional GMP requirements endorsed by the highly regulated pharmaceutical
industry.
This guide is constructed around the clause structure of PS 9000 (and therefore
ISO 9001) to:
• clearly explain the GMP requirements of PS 9000
• list many of the risk areas associated with packaging processes and identify
relevant ISO 9001 and PS 9000 clauses
• provide examples of process inputs and process outputs typical of suppliers
of pharmaceutical packaging materials, and relate these to the QMS
requirements of ISO 9001 and the additional GMP requirements of PS
9000
• give examples of actual case histories of problems arising from the supply of
defective pharmaceutical packaging materials and where the consequences
would have been avoided by correct application of the GMP requirements
of PS 9000. These case histories help to explain the requirements and
provide a valuable training resource
8/18/2019 CGMP Complete
11/128
x
How to use this Guide
PS 9004 has been organized in the following way:
• Part 1 consists of a selection of process schematics, illustrating typical
operations of a packaging supplier, and giving examples of some of the
more significant risks caused by inadequate manufacturing practices
• Part 2 gives guidance on the clauses of PS 9000, by taking the user through
each major section and providing examples to illustrate suggested process
inputs and outputs
• Annex A gives expanded explanatory notes on several key concepts used in
PS 9000
• Annex B gives a listing of other external regulatory references, which are
the background to pharmaceutical GMP and which are directly relevant to
PS 9000 requirements
• the text is primarily black but blue is used for PS 9000 related GMP text
• red text is used to highlight the ‘Risk Areas’
The user can cross refer between the schematics in Part 1 and the process
information in Part 2. In addition, the user can move from Part 2 to the additional
explanations in the annexes.
The annexes contained within this Guide are a stand-alone explanation of key
concepts and external GMP references. The PS 9000 cross-references are for
illustrative purposes and are not a definitive list of clauses or references.
The How to use section, which follows the contents list, shows the user how to
navigate between the different sections of the Guide.
As the range of organizations that may implement PS 9000 is great, both in
terms of size and type of business, the guidance given here is illustrative and
advisory.
Why was the PS 9004 Guide written?
There are three main reasons:
• to guide professional quality specialists towards the implementation and
inspection of a Quality Management System (QMS) in accordance with PS
9000
• to support the training of all the various stakeholders in the PS 9000 process
(top management, quality professionals, staff at all levels of packaging
8/18/2019 CGMP Complete
12/128
xi
material suppliers and their customers)
• to provide those people who are not quality specialists with a better
understanding of the aims, objectives and implementation of PS 9000
How was the PS 9004 Guide written?
A group of experienced quality professionals selected from the packaging supply
industry and pharmaceutical customers was recruited by the Pharmaceutical
Quality Group Partners Team and given the task of preparing this Guide.
Many of the people who contributed to the writing of PS 9000 also participated
in the creation of this Guide.
Specific acknowledgements are given for the contributions of the
following people:
Roy Evans PS 9004 Team Leader
David Abraham Supplier
Ian Harwood Pharmaceutical
Jill Jenkins Pharmaceutical
Daniel Peek Supplier
Richard Rowlett Supplier
Mike Shorten Pharmaceutical
Steve Taylor Pharmaceutical
Additional contributions:
Caroline Fowler Pharmaceutical
Peter Gough Pharmaceutical
Ian Holloway Regulator
Steve Merrit Pharmaceutical
Ashley McCraight Consultant
Jeff Monk Training
Dominic Parry Training
Steve Pike Accredited certification
Norman Randall Consultant
Trevor Stabb Consultant
Paul Stockbridge Consultant
QA review:
Tony Harper Consultant and accredited certification
Afshin Hosseiny Consultant
8/18/2019 CGMP Complete
13/128
xii
QA review (con’t):
Jean Lanet Consultant
Iain Moore Supplier
Steve Moss Pharmaceutical
Ashok Chand Pharmaceutical
John Turner Consultant
The PQG Partners Team and Steering Committee:
Roy Evans
Tony Harper
Femi Ibironke
Jill Jenkins
Ashley McCraight (PT Chairman)
Steve Moss
Norman Randall (SC Chairman)
Ian Richardson
In addition, the PQG is appreciative of the management of Patheon UK
Limited. for the use of their resources and facilities.
8/18/2019 CGMP Complete
14/128
xiii
CONTENTS
Section Page
How to use this guide xv
Part 1 – Process schematics and case studies 1
Overview of business processes 2
Schematic 1 Top level business processes 2
Schematic 2 From the customer 4
Schematic 3 Planning 6
Schematic 3 (a) Warehouse (purchased materials and in-process) 8
Schematic 4 Preparation 10
Schematic 4 (a) Print impression media controls 12
Schematic 5 Production 14
Schematic 6 Checking and final release 16
Schematic 7 Distribution 18
Case studies 21
Part 2 – Guidance on PS 9000 GMP clauses 35
Clause 4 Quality management system 37
Clause 5 Management responsibility 39
Clause 6 Resource management 45
Clause 7 Product realization 49
Clause 8 Measurement, analysis and improvement 59
Clause 9 Contamination control 66
Clause 10 Printed materials 68
Clause 11 Origination/artwork 70
Clause 12 Print impression media 72
Clause 13 Print and conversion processes 74
8/18/2019 CGMP Complete
15/128
8/18/2019 CGMP Complete
16/128
xv
HOW TO USE THIS GUIDE
STEP 1
Choose a schematic from the ‘Overview of business process’ diagram in Part 1 of
this guide. (e.g. Schematic 3(a) is illustrative)
STEP 2
From your schematic, choose a particular stage of the process to examine, e.g.
Store material (see below).
SCHEMATIC 3 (a) - WAREHOUSE
STEP 3
Consider the Risk Areas shown in red and the real life case study (if shown) - these
are detailed at the end of Part 1, following the schematics.
Deliverychecks
• Document errors
• Missing
documents
7.4.3
7.5.3
Qualityinspection
• Labelling errors
• Incorrect goods
7.4
7.4.3
Storematerial
• Pest
Infestation
Case study G
7.5.5:
Preservationof product
9:
Contamina-
tion control
Issuematerial
• Incorrect
materials
7.5.3
See Part 2
for more
details
Risk areas
8/18/2019 CGMP Complete
17/128
xvi
STEP 4
Using the references shown in the schematic, move to the corresponding section
in Part 2, entitled ‘Guidance on PS 9000 GMP clauses’. This gives reasons for the
‘extra’ GMPs and shows examples of processes, inputs and outputs.
General synopsis: Clause 9 Contamination control
The capability of facilities and equipment, achieved through their design, location,
etc.
Reasons for the ‘extra’ GMP requirements
The highest priority of the pharmaceutical industry is... etc.
Process inputs Processes Process outputs
and evidence
Cross refer to
Schematic/Annex
Specification
for design of
new facilities,
processes, or
environment
Specialistsupport for
pest control
Standards for
environmental
conditions
Processes which
identify/control:
• operating areas
• pest control
• cleaning proce-
dures
Records of:
• processing
• cleaning
schedules
• material disposal
• incidents/audit
reports
Schematic 3(a)
Schematic 4(a)
Schematic 5
Annex A - all parts
STEP 5
Use the cross references to move back to a relevant process schematic, alterna-
tively refer to Annex A or B for further guidance.
ANNEX A
Additional Explanation of Key Concepts
ANNEX B
Other external GMP references.
8/18/2019 CGMP Complete
18/128
1
The Institute of Quality Assurance
Pharmaceutical Quality Group
PS 9004
A Guide to the GMP requirements
of PS 9000:2001 Pharmaceutical packaging materials
PART 1 - PROCESS SCHEMATICS
PS 9000 GMP references are reproduced in blue
Risk areas are reproduced in red
8/18/2019 CGMP Complete
19/128
2
OVERVIEW OF BUSINESS PROCESSES
Schematic 1: Top level business processes
Schematic 2:From the customer
Schematic 3:Planning
Schematic 4:Preparation
Schematic 3 (a):Warehouse
Schematic 4 (a):Print impressionmedia controls
SCHEMATIC 1: TOP LEVEL BUSINESS PROCESSES
Quality management system
Managementcommitment
• Inadequate
incorporationof PS 9000
requirements
• QMS not
communicated
and/or
supported
by senior
management
4 QMS
5.1 Management
commitment
5.5
Responsibility,
authority andcommunication
Objectives
• Unclear
businesstargets/goals
• No clear
direction as
objectives not
published
5.3 Quality
Policy
5.4 Planning
Resourceallocation
• Too few people
for qualitycompliant
operation
• Wrong/
inadequate
equipment
• Inadequate
premises
• Inadequate
training
6.1 Provision of
resources
6.2 Human
resources
Refer to the hypothetical examples which
are located after the schematics.
See Part 2
for more
details
Risk areas
8/18/2019 CGMP Complete
20/128
3
Schematic 5:Production
Schematic 6:Checking and finalrelease
Schematic 7:Distribution
This diagram shows the main business processes from customerrequirements through to delivery of final product and provides an indexto the schematics
Audit andmeasurement
• Inadequate
performancemeasures
• Poorly controlled
processes
• Unreliable
information for
management
decisions
• Poor compliance to
internally established
processes/ procedures
• Insufficient proof
of continuous
improvement
8.1 Measurement,
analysis and
improvement -
general
Managementreview
• Quality System
measures notreviewed
• Lack of senior
management
involvement/
leadership
• No continual
process
improvement
5.1 Management
commitment
5.6 Management
review
8.5 Improvement
Quality management system
Feedback/communication
8/18/2019 CGMP Complete
21/128
4
SCHEMATIC 2: FROM THE CUSTOMER
Organization Customerrequest/ requirements
• Requirements
unclear
• Requirements
incorrectly
specified
• Requirementsmisunderstood
• Requirements
incorrectly
accepted
See case study A
5.2 Customer
focus
7.2 Customer-
related processes
Supplyrequirements(what, how,when)
• Unclearly
specified
• Failure to meet
customer
expectation• Rejection by
customer
Customerdesign
• Poor design
• Inadequate detail
• Failure tofunction
• Poor
performance at
customers site
• Rejection by
customer
• Potential risk to
patient
• Inadequate
testing/validationSee case studies
A and B
Feedback
7.2 Customer-related processes
7.3 Design and development
See Part 2
for more
details
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
22/128
5
Assessmentof capability
• Incorrect
assessment
of capability
e.g. resource,
technology,
systems,
environment• Fail to meet
delivery/quality
6.1 Provision of
resources
6.3 Infrastructure
6.4 Work
environment
7.1 Planning
of product
realization
Agreedcontract/ agreementand confirmedorder
• Lack of formal
contract/
agreement
• Failure toagree contract
requirements
• Poor
communication
7.2.3 Customer-
related processes
Planning
8/18/2019 CGMP Complete
23/128
6
SCHEMATIC 3: PLANNING
Receive orderfrom customer
Order review andcustomer feedback(where required)
• Incorrect specification
chosen
• Inadequate
communication with
customer
• Order details incorrect• Supply incorrect product
• Supply error (quantity/
schedule)
• Proof approval error
• Specification not
approved
See case studies
C and D
5.2 Customer focus
7.2 Customer-related
processes
7.3 Design and
development
Availability checkson documentation,materials, toolingand equipment
• Incorrect material checked
or issued (e.g. wrong foil
gauge)
• Wrong print media
(version or item)• Non-availability of
equipment (e.g.
maintenance/validation
status)
• Unapproved production
process (e.g. not
approved by customer)
• Unsuitable/unapproved
material/changes
• Missing/incorrect
documentation (e.g.
missing mould inspection
record)
7.4 Purchasing
7.5 Production and service
provision
11 Origination/artwork
12 Print impression media
See Part 2
for more
details
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
24/128
7
Purchasing and printmedia provision
• Inadequate supplier
control
• Nonconforming
purchased materials or
service
• Inability to obtain raw
material• Inadequate security (e.g.
printing plates)
• Insecure data links (e.g.
validation of ISDN link)
• Incorrectly identified
materials (e.g.
mislabelling of stock
from supplier)
See case study E
4.2 Documentation
requirements
7.4 Purchasing
8.3 Control of
nonconforming product
11 Origination/artwork
12 Print impression media
Production scheduleand feedback fromproduction
• Inadequately defined
plan/schedule (e.g.
insufficient time for
line clearance or
maintenance)
• Inadequate programmetime to follow procedures
• Problems in production
7.1 Planning of product
realization
7.5 Production and service
provision
8 Measurement, analysis
and improvement
Preparation for start of production
Feedback
8/18/2019 CGMP Complete
25/128
8
SCHEMATIC 3 (a): WAREHOUSE (purchased materials and in-process)
Delivery from supplier/sub-contractor
Deliverydocumentation andoff-loading checks
• Errors not identified
between delivery
documentation &
purchase order
• Missing delivery/QC
documentation• Transit damage or wet
boxes not identified
before off-loading
• Incorrect goods
7.4.3 Verification of
purchased product
7.5.3 Identification and
traceability
Goods checks andquality inspection
• Inadequate checks
performed
• Labelling errors not
identified
• Incorrect goods sent
• Rogue box within delivery
• Inadequate batch coding• Non representative sample
taken or provided
• Transit/water damage not
detected
• Inadequate packaging/
sealing not detected
• Incorrect quality status
input to system
See case study F
7.4 Purchasing
7.4.3 Verification of
purchased product
See Part 2
for more
details
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
26/128
8/18/2019 CGMP Complete
27/128
10
SCHEMATIC 4: PREPARATION
Production
plan
Preparation/
pre-productionchecks ofpurchased rawmaterials
• Error in checking
raw material
• Quality status
incorrect
• Availability status
incorrect
Materials
management
Errors in:
• Co-ordination
of all required
resources
• Combining/
assembly/ Bills
of Material
• Timing/change
management
• Machine
allocation
7.1 Planning
of product
realization
7.2 Customer
related
processes
Preparation/ pre-productionchecks oftooling andequipment
• Error in checking
tooling/equipment
• Change controlerror
• Validation status
error
• Maintenance
omission/ error
• Availability status
incorrect
See case study H
7.4 Purchasing
7.5 Production and service provision
10 Printed materials
11 Origination/artwork
12 Print impression media
13 Print and conversion process
See Part 2
for more
details
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
28/128
11
Issue of tooling
• Issue incorrect tool
• Issued with incorrect
status
• Issue in poor
condition
• Issue printing plates
in insecure manner
See case studies
I, J and K
7.5 Production and
service provision
12 Print impression
media
Issue of
materialsanddocumentation
• Issue incorrect
materials
• Incorrect quantity
issued
• Issued with incorrect
status
• Issue incorrect
documentation
• Unapproved
documentation
4.2 Documentation
requirements
7.5 Production and
service provision
11 Origination/artwork
12 Print impression
media
Production
8/18/2019 CGMP Complete
29/128
12
SCHEMATIC 4 (a): PRINT IMPRESSION MEDIA CONTROLS
Customer supplieddesign text
New printmedia design
• Errors in media
undetected by
checks
• Individual plate
incorrectly coded
• Set of plates
incorrectly coded
• Failure to secure
customer proofapproval
• Failure to log
customer
approval
See case study L
11 Origination/
artwork
12.1 General
12.2 Matched
plates
Securestorage andcontrolledissue ofplates
• Mix-up with
plates from
another product
• Uncontrolled
access of
personnel• Physical
damage to
plates
• Inadequate
records of issue
introducing
admixture risk
in production
Controlsover partialre-designsand obsoletedesigns
• Incorrect plates
retained
• Insecure disposal
• Superseded platesnot rendered
unusable
• Incorrect plate
identification
• Error in
replacement plate/
matching set
• Documentation
errors
• Customerapproval error
See case study M
12.2 Matched plates
12.3 Copy / design change
12.5 Quarantine and destruction
13.2 Changeover systems See Part 2
for moredetails
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
30/128
13
Line use ofplates
Failure to :
• Check design
• Clear line of
previous plates
• Perform start-up
printing checks
• Record checks
• Keep samples
See case
study N
9.1.7 Line
clearance
12.4 Verification
13.1 Print
machine set-up
(make-ready)13.2 Changeover
systems
13.3 Retained
samples
Controls overreplacementplate (samedesign)
• A new first off
check is not
performed or
recorded (e.g.plate made
from existing
approved
source)
• New origination
& new batch
checks not
performed or
recorded (e.g.
plate createdfrom a new
source)
13.4 Replacement
print media
Line clearanceand controlledreturn ofplates to store
• Plate left on
machine in error
• Inadequate
records of return
to store
9.1.7 Line
clearance
12.1 General
Production
8/18/2019 CGMP Complete
31/128
14
SCHEMATIC 5: PRODUCTION
Preparation Line clearcheck
• Admixture from
previous batch
• Erroneous use
of previous
documents
• Use of a plate
from previous job
7.5 Production
and service
provision
9.1.7 Line
clearance
10 Printed
materials11 Origination/
artwork
Documents/ materials/ tooling to line
• Use of incorrect
documents/
materials
• Failure to use
documents
correctly• Incorrect
quantities
• Defective moulds/
equipment/plates
See case study O
4.2 Documentation
requirements
7.5 Production and
service provision
Set upchecks andproductionstart
• Errors in
data input to
machine, e.g.
settings
• Setting errorundetected
• Start up waste
inadequately
segregated
from main
batch
• Unauthorized
start up
5.5 Respon-
sibility,
authority and
communication
7.6 Control of
monitoring
and measuringdevices
9 Contamination
controls
10 Printed
materials
12 Print
impression
media
See Part 2for more
details
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
32/128
15
Production/inprocess control
• Quality variation due
to environment e.g.
temperature, humidity
• Contamination e.g.
insects, dust
• Defective / out of spec
or wrong materials• Visual defects not
detected
• Inadequate IPC of transit
packaging
• Labelling errors
• IPC errors
• Material usage error
• Failure to identify/
segregate non
conforming product
• Recording error
See case studies P, Q
6.4 Work environment
7.5 Production and
service provision
8.2 Monitoring and
measurement
8.3 Control ofnonconforming product
11 Origination/artwork
Production completionand line clearance
Risk to next job due to:
• lack of GMP training
• failure to clear line
• inadequate waste disposal
• documentation not signed
off therefore status unclear
• clearance of electronicfiles/settings
See case study R
6.2.2 Competence,
awareness and training
8.2 Monitoring and
measurement
9 Contamination controls
10 Printed materials
13 Print and conversionprocesses
Checking andfinal release
Feedback
8/18/2019 CGMP Complete
33/128
16
SCHEMATIC 6: CHECKING AND FINAL RELEASE
Production End product
QC testing
• Inadequate training
• Test method not
validated
• Out of Specification
results not investigated
• Inadequate procedures
• Release decision
contradicts data
• Inconsistent sampling/ risk
• Equipment/test
equipment inadequate
• Calibration errors/
omissions
See case study S
6.2.2 Competence,awareness and training
7.6 Control of monitoring
and measuring devices
8 Measurement, analysis
and improvement
8.4 Analysis of data
Review of batch
documents and QCtesting
• Missing/incorrect
document
• Missing/incorrect sample
• Signature omissions,
unauthorized check
signature
• Errors of information/data
entry• Checks out of sequence
• Abnormal events not
reviewed
See case study T
5.5 Responsibility, authorityand communication
6.2 Human resources
4.2 Documentation
requirements
13 Print and conversion
process
See Part 2
for more
details
Risk areas
Refer to the case studies
which are located after
the schematics.
8/18/2019 CGMP Complete
34/128
17
Create certificate of
test or conformance
• Errors / omissions
• Signature invalid
• Inappropriate data
supplied
• Incorrect specifications/
tolerances
• Incorrect release decision
• Certificate text differsfrom batch details
See case study U
8.2 Monitoring andmeasurement
8.3 Control of
nonconforming product
Check box labels
against batchinformation
• Incorrect/missing label
• Label data error/
omission
• Label reconciliation
• Incorrect QC status label
See case studies V and W
7.5 Production and serviceprovision
Distribution
8/18/2019 CGMP Complete
35/128
18
SCHEMATIC 7 - DISTRIBUTION
Checking and
final release
Receipt of product
into storage/holding(goods outwarehouse)
• Error in system
transaction (receipt)
• Inadequate segregation
from other goods
• Storage damage
7.5 Production and service
provision
10 Printed materials
Order preparation
(picking and transitpackaging)
• Picking wrong product
• Damage to product due
to inappropriate transit
packaging
• Pallets not suitable for
customer handling
• Error in transaction (issue)
See case study X
7.5 Production and service
provision
See Part 2
for more
details
Risk areas
Refer to the case studieswhich are located after
the schematics.
8/18/2019 CGMP Complete
36/128
19
Dispatch area/
goods check anddocumentation
• Errors of quantity
• Incorrect labelling
• Error in dispatch note
• Admixture of boxes
See case study Y
Transport to the
customer
• Transit damage e.g. poor
pallet stacking, poor
weather protection
• Contamination in transit
• Inadequate control of
hauliers
See case study Z
The customer
7.5 Production and service provision
8/18/2019 CGMP Complete
37/128
20
8/18/2019 CGMP Complete
38/128
21
The Institute of Quality Assurance
Pharmaceutical Quality Group
PS 9004
A Guide to the GMP requirements
of PS 9000:2001 Pharmaceutical packaging materials
PART 1 - CASE STUDIES
8/18/2019 CGMP Complete
39/128
22
8/18/2019 CGMP Complete
40/128
23
Part 1 – Examples and Case studies
These examples and ‘real life’ case studies should be used with the
relevant Schematic, to illustrate specific GMP risk areas and the
appropriate QMS processes involved.
HYPOTHETICAL EXAMPLE FOR SCHEMATIC 1 –
TOP LEVEL BUSINESS PROCESSES
The senior management of a booklet printing company believes that PS
9000 certification will aid company profitability and smooth throughput
because of consistent demand from the pharmaceutical industry, which
is not adversely affected by recessions. The company has an enthusiastic
Quality Manager who has produced a comprehensive manual with up to
date and relevant procedures. However, the Quality Manager is beginning
to feel like a ‘voice in the wilderness’ as there is little evidence that senior
management is driving the whole organization to become aligned to the
requirements of the standard. The lack of senior management commitment
to the continual improvement philosophy and the Good Manufacturing
Practices of the pharmaceutical industry means that only superficial actions
are taken in areas considered highly visible to visiting auditors. Key individu-
als are unclear about the standards required of them. The level of customer
complaints remains high, some of these complaints being serious mix-ups.
Productivity stays unchanged with a high level of wastage. Workforce moral
is low and many staff are demotivated.
The company is then purchased by another company that already supplies
cartons to the pharmaceutical industry - allowing them to offer a better
product range to the customer. The corporate re-organization results in key
changes in senior management at the booklet factory. The new managers
know their prime objective is to encourage each and every employee to
understand the particular needs of their pharmaceutical customers. They
understand the value of PS 9000 in a competitive market, but know that the
real benefits are much deeper than merely achieving the ‘badge’. The Qual-
ity Manager begins to feel encouraged and genuinely part of the team. The
frequency of management review meetings is increased with the emphasis
changed to progressing preventive actions for nonconformities and review-
8/18/2019 CGMP Complete
41/128
24
ing clear measures of performance for key parameters such as complaint
rates. The senior management commitment begins to permeate throughout
the staff and becomes evident in many areas such as resourcing, training,
customer service, and improved product quality. The board of directors
soon recognises that the PS 9000 implementation process is enabling them
to profitably expand their business, improve relationships with their custom-
ers, whilst still significantly reducing their cost of quality.
CASE STUDIES FOR SCHEMATIC 2 – FROM THE CUSTOMER
A Focus - Customer request/requirements
Bar coded product labels could not be read by customer’s electronic read-
ers due to shading of background colour, caused by inadequate testing
and validation. The packing orders at the pharmaceutical company were
delayed which threatened the availability of the medicinal products to the
end customers. The labels had to be destroyed, incurring the direct expense
of replacement. The product was redesigned with solid background, and all
graphics designers were made aware of the issue and to consider the pos-
sible need for trials on change of design or introduction of a new design.
B Focus – Customer design
A market need for a needle protection mechanism was specified, but
translation of this into a final design was lengthy and complicated. The
component did not perform reliably due to limited experimental validation.
The problems were addressed through increased communication with the
supplier to make the design more robust, involving revalidation and testing.
This extended work caused a delay in providing the improved safety prod-
uct to the patient. An organizational review followed to ensure that in future,
adequate resource is devoted at the design and testing stages of product
development.
CASE STUDIES FOR SCHEMATIC 3 – PLANNING
C Focus – Order review and customer feedback
The wrong material was ordered by the supplier’s UK sales office from their
own factory. Normally, orders were placed for 40 micron PVDC coated PVC
8/18/2019 CGMP Complete
42/128
25
(for tablet blister packing), but on this occasion a new order for 60 micron
coated film was incorrectly notified by the sales office to the factory in Ger-
many as 40 micron; the incorrect material was delivered and used causing
a regulatory noncompliance and potentially inadequately protecting the
tablets from moisture. Significant work was necessary by the pharmaceuti-
cal company to assess stability data to determine the acceptability of the
packed tablet batches. The root cause was established through customer
audit of the ordering system at the sales office. An independent check of
order details was implemented to prevent repetition.
D Focus – Order review and customer feedback
The printer’s proof was incorrectly read by the supplier as ‘approved’ when
it was actually ‘rejected’; also the wrong file was used to make replace-
ment printing plates. Cartons for a heart condition medicinal product were
printed and used showing on one end flap 14 tablets instead of 28. The
consequence of this was that stock had to be recalled from the distribu-
tion centres to enable a rework. This delayed the critical medicinal product
reaching the market. Working together, customer and organization, the
complete sequence of events was reconstructed. In addition to awareness
training, the rules regarding issuing artworks and file management between
organization and platemaker were made more robust.
E Focus – Purchasing and print media provision
Leaflets with a different paper weight were supplied, due to problems with
availability of normal paper. This caused insertion difficulties on the phar-
maceutical packing line, high wastage of components and loss of some
pharmaceutical product. The supplier was advised of the existing change
control clause in the quality agreement/contract and procedures were
revised. The supplier managed to obtain further supplies of normal paper.
CASE STUDIES FOR SCHEMATIC 3 (a) –
WAREHOUSE (PURCHASED MATERIALS & IN-PROCESS)
F Focus – Goods checks and quality inspection
Self-adhesive labels were failing to stick to glass vials at the customer’s
premises because a different adhesive had been used. This had been
caused by the supplier switching their source of unprinted label material.
8/18/2019 CGMP Complete
43/128
26
The raw material was thought to be of equivalent quality and no extra qual-
ity checks were performed at goods-inwards. The change was introduced
without informing the customer therefore no formal change control or a
risk assessment could be performed. The problem caused chaos on the
customer’s packing line and it was not certain how well the labels were
affixed to ‘apparently’ satisfactory packed vials. The label printing company
pursued the quality issue with its supplier and proper trials of alternatives
were subsequently conducted with the pharmaceutical company. In addi-
tion, revisions were made to the change control system.
G Focus – Store material
Two dead mice were found inside the pallet wrapping of a consignment of
plastic bottles to be used for an antiseptic liquid product. This caused major
disruption to the output of the pharmaceutical filling plant. All the stock of
bottles had to be manually inspected for contamination. It was necessary to
audit the supplier and its remote warehouse. Immediate action involved the
relocation of bottle storage back into the main factory. The root cause was
inadequate warehouse pest controls at the supplier’s remote warehouse. It
prompted an extensive programme of work to improve the standards at the
site. The product was a low margin item for the pharmaceutical company
and it has since been sold off to another company. Although many other
factors were involved, this episode only added to the reasons to sell this
part of the business.
CASE STUDIES FOR SCHEMATIC 4 – PREPARATION
H Focus – Preparation/pre-production checks of tooling and
equipment
Mould tool used to produce parts for a syringe was used in production
when the validation documentation had not been fully approved and signed
off. This contributed to high variability in functional performance of the
assembled syringe with some batches of parts rejected, and it necessitated
ongoing improvement work. It also delayed the launch of the pharmaceuti-
cal product which in this case was a life saving cancer product. The opera-
tional procedures were revised and the operators were retrained.
8/18/2019 CGMP Complete
44/128
27
I Focus – Issue of tooling
Syringe labels were printed correctly, but were cut with corners of the wrong
profile/shape due to the issue of an incorrect cutter to the press. The labels
were rejected by the pharmaceutical company at the expense of the print-
ers. The time needed to replace the labels meant rescheduling of packing
was necessary at the pharmaceutical company. The cutter identification
process was reviewed & storage standards were improved.
J Focus – Issue of tooling
Cartons were produced with a varnish free area in the wrong position due
to the issue of an incorrect varnish plate. The purpose of a varnish free area
is to ensure the printing of variable data (e.g. lot & expiry) is clear and per-
manent. This error was identified at the pharmaceutical company. The risk
existed that variable data applied by the pharmaceutical company could
be easily smudged or erased when in the market and this would clearly be
a critical problem. The supplier reviewed the varnish plate issuing process
and made improvements to the system which linked varnish plate usage to
print plate usage.
K Focus – Issue of tooling
Mould tool for a syringe plunger rod was issued to production despite
being overdue for refurbishment. This resulted in minor plastic ‘flash’ being
present on the mouldings. If this problem became more serious then loose
particles of plastic could break off and contaminate the pharmaceutical
syringe pack. The supplier applied for a concession from the customer and
this was granted for a limited period because of the extent of the problem.
The case highlighted the need for proper planned preventive maintenance
and sufficient resources allocated to facilitate it.
CASE STUDIES FOR SCHEMATIC 4 (a) –
PRINT IMPRESSION MEDIA CONTROLS
L Focus – New print media design
Artwork supplier made a “cut & paste” error which resulted in cards being
part printed with Polish text in the main body of Portuguese text. The cards
were for an anti-cancer injection. Fortunately the error was noticed dur-
ing in-process checks of printing. The error had the potential to become
8/18/2019 CGMP Complete
45/128
28
a product recall if it had reached the end user. An extensive review of the
artwork supplier’s procedures was completed and a further proof-reading
check was introduced.
M Focus – Controls over partial redesigns & obsolete designs
The printed foil for tablet blister strips (used to treat a heart condition) was
incorrectly printed with two different identifying codes on the foil (different
by one digit). The error occurred during the ‘step and repeat’ process to
generate a single replacement cylinder. The error was only found on inspec-
tion at the pharmaceutical company. In this case, no packed stock was lost,
but the error could have been more serious. The supplier took the issue up
with its cylinder manufacturer and reviewed its inspection procedure for first
off sample inspection following cylinder replacement.
N Focus – Line use of plates
A printing plate was left on the leaflet press by the operator after leaving the
area to retrieve a spare part. Upon return the operator continued printing,
but against the job documentation for the next job. The item was visually
very similar and all subsequent checks by operators and QC failed to spot
the admixture that had been created. The problem was found on goods
inwards checks by the customer, and resulted in a detailed audit of proce-
dures by the customer. Line clearance checks were reviewed, procedures
around bar code scanning at the suppliers were enhanced and refresher
training was delivered.
CASE STUDIES FOR SCHEMATIC 5 – PRODUCTION
O Focus – Documents/materials/tooling to line
During the folding stage of leaflet production two orders were mixed up. Job
A was folded, scanned, labelled and released against Job B documenta-
tion, and Job B documentation was folded, scanned, labelled and released
against Job A documentation. The mixed-up orders were then delivered to
the pharmaceutical company where the error was discovered. The potential
for incorrect leaflets to be packed into pharmaceutical packs was increased.
The supplier’s investigation identified the root cause as human failure to fol-
low established procedures. In addition the codes for the bar code scanner
are now input from an independent source (a PS 9000:2001 requirement).
8/18/2019 CGMP Complete
46/128
29
P Focus – Production/in-process control
A delivery of poorly printed foil, used for tablet blister strips, was caused
by inadequate ‘flagging’ of defective material during printing. The ‘flagged’
material is removed during later stages of slitting and rewinding. The defec-
tive material was detected on the customer’s packing line and lead to the
scrapping of some packed pharmaceutical product. The supplier’s printers
and the operators responsible for removal of the ‘flagged’ material were
given refresher training to ensure all defective material is removed, up to
and around the ‘flagged’ point in the reel.
Q Focus – Production/in-process control
Plastic tablet bottles were manufactured with a wall thickness that was
below specification. This was caused by poor appreciation of the cus-
tomer’s requirements, inadequate in-process monitoring and an inability to
segregate product that was out of specification. Packed pharmaceutical
product had to be quarantined until all aspects of the problem had been
assessed by the pharmaceutical company’s QA Department. The issue was
resolved through improved specification regarding the criticality of certain
dimensions, increased in-process measuring regime and enhanced segre-
gation procedures.
R Focus – Production completion & line clearance
On a reel of label/leaflet combinations, six ‘rogue’ components (of similar
appearance) were found at intermittent points in the reel, by the pharmaceu-
tical customer. This was despite a scanning operation being in place at the
supplier. The root cause was human error involving inadequate line clear-
ance and replacing incorrect labels back onto the web during rewinding/
scanning. Although the rule existed which forbade this practice, the
operator had recently been transferred from a department supplying non-
pharmaceutical customers where this rule was not in place. The supplier
commenced a fundamental review of procedures and operator retraining.
CASE STUDIES FOR SCHEMATIC 6 – CHECKING & FINAL RELEASE
S Focus – End product QC testing
An out of specification result on a test machine record was transcribed
incorrectly as satisfactory on the summary sheet, causing an incorrect
8/18/2019 CGMP Complete
47/128
30
release decision of a batch of syringes. Although, in this case no harm was
caused, it highlighted a risk area, should the error have occurred on another
safety related function of the syringe. Refresher training was delivered to the
operator concerned.
T Focus – Review of Batch documents & QC testing
Carton barcode scanner was switched off during the night shift without
QA authorization and not noticed upon review of documentation. This
meant that the product had been made without the safeguards required
by, and contractually agreed with the customer. The product was therefore
inadequately checked for the absence of rogue components. The affected
order was rejected and scrapped. A detailed audit was performed by the
pharmaceutical company and numerous significant procedural enhance-
ments were made.
U Focus – Create Certificate of Test or Conformance
Irradiated syringes were released for use despite radiation dose figures
being omitted from the certificate of test. In this case the dosage was
actually satisfactory, however the omission / error had the potential to
threaten the sterility of the syringes thus endangering the patient, and to
compromise the pharmaceutical sterile filling facility. The certificates are
now double checked before release from the irradiation contractor.
V Focus – Check box labels against batch information
A box of shampoo closures was delivered amongst a consignment of tablet
bottle closures, caused by box labelling error & poor segregation practices.
This resulted in admixture on the filling line at the pharmaceutical company,
line downtime, and some lost product. The supplier had been audited on
numerous occasions but lack of commitment to eliminate such problems
ultimately lead to a change of supplier for the component.
W Focus – Check box labels against batch information
A keying-in error of leaflet product identity code to outer box label printer
caused rejection upon delivery to customer. Apart from the disruption
caused by the rejection, there was a risk that the material could have been
received into stock as a different item, i.e. admixture. The preventive action
eventually implemented was to link the box label printer to the mainframe
8/18/2019 CGMP Complete
48/128
31
computer thus removing the necessity to manually key the data into a
standalone label printer.
CASE STUDIES FOR SCHEMATIC 7 – DISTRIBUTION
X Focus – Order preparation (picking & transit packaging)
An admixture of boxes of labels was found on receipt by the customer
caused by a picking error made due to poor warehouse lighting and lack
of a double check. In another incident an admixture of batch of cartons
occurred, caused by a picking error due to poor batch segregation in
the warehouse. Both batch defectives were found during the customer’s
receipt checking, but they caused disruption to the product scheduling
programmes because of the need to return the material to the supplier for
sorting/replacement. The corrective and preventive actions, in both cases,
involved a fundamental review of the conditions (and checks made) in the
warehouse and implementation of improved lighting and segregation mea-
sures.
Y Focus – Despatch area/goods check & documentation
Despatch note details accompanying the delivery differed from physical
quantity delivered. This resulted in delays in product release and schedul-
ing disruption while the supplier was contacted. The supplier’s despatch
checking procedures were reviewed, no fundamental weaknesses were
found. In this case, a one-off error had occurred and the issue was dis-
cussed with the individual concerned.
Z Focus – Transport to the customer
Goods were damaged in transit due to movement of the load and inade-
quate control while the vehicle was being loaded. In another incident, goods
were damaged by water penetration due to a poorly closed and maintained
“curtain” of a flexible sided vehicle. Both examples resulted in the need for
product inspection at the customer, and the return of damaged material to
the supplier leaving too few components to meet requirements. In the first
case, the checks made on loading were increased and in the second exam-
ple the company decided it was feasible to switch to hard sided vehicles to
eliminate the risk of water penetration.
8/18/2019 CGMP Complete
49/128
32
Using the Case Studies - Guidance for Trainers
Introduction
The case studies that have been described here can be used as valuable aides to
training programmes, for use either by a supplier or a pharmaceutical company. It
is recommended that you select one or more of the case studies that are appro-
priate to your business and design an activity that will encourage your trainees to
discuss the particular subject you would like them to understand. An example of a
training exercise protocol is provided below based on a case study selected from
Schematic No. 3. Developing a short set of questions similar to those illustrated
below should help improve understanding. It will probably be beneficial if such Q &
A sets were developed jointly after discussion between pharmaceutical customers
and their suppliers.
It will certainly be helpful to provide explanations and visual aides relevant to the
case study. For example in the example illustrated below it would be helpful if:
i) For a laminate that you use or manufacture explain which illness(es) the tablets,
that are packed within it, are used to treat.
ii) A copy of an analogous page of a Product Authorisation (Licence) was shown
and the legal basis of such licences explained.
iii) The function of PVDC in the laminate was explained.
Training Exercise
Case study No. C
Title: Mix-up in the weight of PVDC on a PVC based blister film
In this case study, the wrong material was ordered from the factory.
Nomally, orders were placed for 40 micron PVDC coated PVC (for tablet
blister packing) - and etc.
Training objectives
Discuss the case study in groups and decide your answers to the following ques-
tions:
Q 1. Which requirement(s) of PS 9000 do you consider had not been effectively
implemented?
State the clause numbers and your reasons.
8/18/2019 CGMP Complete
50/128
33
Q 2. Why do you think that the thickness of the PVDC could affect the stability of
the tablets that were to be packed in the laminate?
Q 3. If this mistake had not been detected what do you think the implications
might have been to:
i) The manufacturer of the laminate film?
ii) The pharmaceutical customer?
8/18/2019 CGMP Complete
51/128
34
8/18/2019 CGMP Complete
52/128
35
The Institute of Quality Assurance
Pharmaceutical Quality Group
PS 9004
A Guide to the GMP requirements
of PS 9000:2001 Pharmaceutical packaging materials
PART 2 - GUIDANCE ON PS 9000 GMP CLAUSES
PS 9000 GMP related text is reproduced in blue
8/18/2019 CGMP Complete
53/128
36
8/18/2019 CGMP Complete
54/128
37
G e n e r a l s y n o p s i s - C l a u
s e 4 Q u a l i t y m a n a g e m e n t s y s t e m
A Q M S p r o v i d e s a b a s i s f o
r c o n t i n u o u s i m p r o v e m e n t o f t h e o r g a n i z a t i o n ’ s e f f e c t i v e n e s s a n d e f f i c i e n c
y , w h i l s t s t i l l c o n s i d e r i n g
t h e v a r i o u s n e e d s o f a l l s t
a k e h o l d e r s ( e . g . c u s t o m e r s , s u p p l i e r s , i n v e s t o r s , e m p l o y e e s ) .
C l a u s e 4 . 1 G e n e r a
l r e q u i r e m e n t s
D e t a i l e d c o n s i d e r a t i o n i s r e q u i r e d o f t h e n e e d s o f s t a k e h o l d e r s ,
t h e p
r o c e s s e s t o m e e t t h o s e n e e d s a n d t o m e
a s u r e p e r f o r m a n c e .
T h e r e a r e n o ‘ e x t r a ’ P S 9 0 0
0 G M P s w i t h i n t h i s c l a u s e .
T h e r e a r e i m p o r t a n t G M P p r i n c i p l e s i n t h i s a r e a ,
b u t t h e
y a r e a d e q u a t e l y
e x p r e s s e d i n I S O 9 0 0 1 a n d
I S O 9 0 0 4 .
P r o c e s s i n p u t s
P r o c e s s e s
P r o c e s s o u t p u t s a n d
e v i d e n c e
C r o s s r e f e r t o
S c h e m a t i c / A n n e x
•
I d e n t i f i e d p r o c e s s e s
t h a t m e e t o r g a n i z a t i o n
s t r a t e g i c o b j e c t i v e s
•
C u s t o m e r r e q u i r e m e n t s
•
R e g u l a t o r y
r e q u i r e m e n t s
P r o c e s s e s w h i c h :
•
d e f i n e ,
i m p l e m e n t a n d m a i n t a i n Q M S
p r o c e s s e s ( i n c l u d i n g m a n a g e m e n t
a n d
o p e r a t i o n a l a c t i v i t i e s )
•
d e t e r m i n e p e r s o n n e l r e q u i r e d t o c a r r y o u t
p r o c e s s e s a n d t r a i n i n g n e e d s
•
p r o v i d e p r e m i s e s a n d e q u i p m e n t f
o r t h e
p r o c e s s e s
•
d e f i n e a n d i m p l e m e n t c o n t r o l s t o m e a s u r e
p e r f o r m a n c e o f Q M S p r o c e s s e s i n
c l u d i n g
o u t s o u r c i n g
•
W r i t t e n p r o c e d u r e s
e s s e n t i a l t o
Q u a l i t y S y s t e m
•
O r g a n i z a t i o n s t r u c t u r e
t h a t s u p p o r t s Q M S
•
A d e q u a t e p r e m i s e s
a n d e q u i p m e n t
•
D a t a f r o m p r o c e s s e s
a n d m e a s u r e m e n t
s y s t e m s
S c h e m a t i c 1
8/18/2019 CGMP Complete
55/128
38
C l a u s e 4 . 2 D o c u m e n t a t i o n r e q u i r e m e n t s
D o c u m e n t a t i o n i s a f u n d a m e n t a l p a r t o f t h e Q M S t h a t d e f i n e s w h a t t h e o r g a n i z a t i o n d o e s , p r o v i d e s t r a c e a b i l i t y a n d e v i d e n c e o f i t s
a c t i v i t i e s .
R e a s o n s f o r t h e ‘ e x t r a ’ G M
P r e q u i r e m e n t s ( r e f e r t o P S 9 0 0 0 c l a u
s e s 4 . 2 . 2 ; 4 . 2 . 3 ; 4 . 2 . 4 )
P h a r m a c e u t i c a l c o m p a n i e s
h a v e , o n o c c a s i o n s , e x p e r i e n c e d p r o b l e m
s i n t h e r e t r i e v a l o f a c c u r a t e h i s t o r i c a l d a t a f r o m s u p p l i e r s a n d
t h e s e h a v e b e e n a t t r i b u t e d t o i n a d e q u a t e d a t a s y s t e m v a l i d a t i o n a n d
d a t a c o n t r o l s .
T h e p r o c e s s r e f e r e n c e s a b
o v e a r e p a r t o f a s y s t e m
o f d a t a t r a c e a b i l i t y t h a t c a n
p r o v i d e a c o m p l e t e h i s t o r y o f t h e c o m p o n e n t ’ s m a n u f a c t u r e .
T h i s c a n b e v i t a l l y i m
p o r t a n t i f t h e r e i s a
p r o b l e m i n t h e u s e o f t h e p h
a r m a c e u t i c a l p r o d u c t i n t h e m a r k e t p l a c e .
T h e p h a r m a c e u t i c a l c o m p a n y h a s a r e g u l a t o r y o b l i g a t i o n t o r e t a i n p r o d u c t i o n a n d p a c k i n g d a t a f o r o n e y e a r b e y o n d t h e s h e l f - l i f e o f
t h e p r o d u c t . T h e r e i s t h e r e f o r e a c o r r e s p o n d i n g r e s p o n s i b i l i t y ( s e e A n
n e x B ) u p o n t h e c o m p o n e n t s u p p l i e r t o e
s t a b l i s h a n d m a i n t a i n
a c c u r a t e a n d s e c u r e d a t a c o n t r o l a n d r e t e n t i o n s y s t e m s .
P r o c e s s i n p u t s
P r o c e s s e s
P r o c e s s o u t p u t s a n d
e v i d e n c e
C r o s s r e f e r t o
S c h e m a t i c / A n n e x
•
D o c u m e n t s t h a t n e e d
t o b e c o n t r o l l e d
•
S t a n d a r d s a n d
r e g u l a t o r y r e q u i r e m e n t s
•
C u s t o m e r r e q u i r e m e n t s
( s p e c i f i e d a n d
u n s p e c i f i e d )
•
R e s p o n s i b i l i t i e s f o r
d o c u m e n t s ( e . g .
a u t h o r s , a p p r o v e r s ,
e t c . )
•
P r o c e s s m a p s
P r o c e s s e s w h i c h :
•
c o n t r o l t h e d o c u m e n t a n d d a t a m a
n a g e m e n t
f o r a n y m e d i a t y p e t o c o v e r l i f e - c y
c l e
•
e n s u r e t h e s e c u r i t y o f e l e c t r o n i c d o c u m e n t s i s
e q u a l t o t h a t o f p a p e r d o c u m e n t s
•
p r o v i d e a u d i t t r a i l f o r e l e c t r o n i c d o
c u m e n t s a n d
d a t a
•
c o n t r o l b a c k u p a n d r e c o v e r y o f d a
t a
•
c o n t r o l v a l i d a t i o n o f h a r d w a r e / s o f t w a r e u s e d
f o r d o c u m e n t a n d d a t a m a n a g e m e
n t
•
c o n t r o l a r c h i v i n g / r e t e n t i o n o f d o c u
m e n t s a n d
d a t a
•
d e f i n e t h e e x t e n t t o w h i c h P S 9 0 0 0 a p p l i e s
w i t h i n t h e Q M S
•
Q u a l i t y m a n u a l
•
P r o c e d u r e s t h a t
s u p p o r t t h e d o c u m e n t
a n d d a t a m a n a g e m e n t
s y s t e m
•
C l e a r a c c o u n t a b i l i t i e s
a n d r e s p o n s i b i l i t i e s
R e c o r d s o f :
•
d o c u m e n t a t i o n
c h a n g e s
•
t r a i n i n g
•
v a l i d a t i o n
S c h e m a t i c 3
S c h e m a t i c 4
S c h e m a t i c 5
S c h e m a t i c 6
A n n e x B
8/18/2019 CGMP Complete
56/128
39
G e n e r a l S y n o p s i s - C l a u
s e 5 M a n a g e m e n t r e s p o n s i b i l i t y
M a n a g e m e n t ’ s r e s p o n s i b i l i t y t o e n s u r e a n e f f e c t i v e Q M S w h i c
h r e c o g n i s e s t h e n e e d s o f t h e o r g a n i z a t i o n , c u s t o m e r s a n d
o t h e r k e y s t a k e h o l d e r s .
C l a u s e 5 . 1 M a n a g e m
e n t c o m m i t m e n t
T o p m a n a g e m e n t d e f i n e s t h
e o r g a n i z a t i o n ’ s s t r a t e g y a n d i s r e s p o n s i b
l e f o r d e m o n s t r a t i n g c o m m i t m e n t t o t h e Q M S .
C o n t i n u a l
i m p r o v e m e n t o f t h e s y s t e m
a n d i t s p r o c e s s e s a r e n e c e s s a r y t o e n s u r e c u s t o m e r a n d r e g u l a t o r y n e e d s a r e f u l l y
s a t i s f i e d .
T h e r e a r e n o ‘ e x t r a ’ P S 9 0 0
0 G M P ’ s w i t h i n t h i s c l a u s e .
T h e r e a r e i m p
o r t a n t G M P p r i n c i p l e s i n t h i s a r e a ,
b u t t h e y a r e a d e q u a t e l y
e x p r e s s e d i n I S O 9 0 0 1 a n d
I S O 9 0 0 4 .
P r o c e s s i n p u t s
P r o c e s s e s
P r o c e s s o u t p u t s a n d
e v i d e n c e
C r o s s r e f e r t o
S c h e m a t i c / A n n e x
•
C o m p a n y s t r a t e g y /
p u r p o s e
•
A d e q u a t e r e s o u r c e s t o
m e e t r e q u i r e m e n t s
P r o c e s s e s w h i c h :
•
e s t a b l i s h q u a l i t y p o l i c y
•
e s t a b l i s h q u a l i t y o b j e c t i v e s
•
r e q u i r e a M a n a g e m e n t R e v i e w a s a m e a n s o f
c o n t i n u a l i m p r o v e m e n t
•
e n s u r e s t h e c o m m u n i c a t i o n w i t h s t a f f t o h e l p
t h e m u n d e r s t a n d a n d c o n t r i b u t e t o
Q M S
i m p l e m e n t a t i o n ( e . g . c o n t i n u o u s i m
p r o v e m e n t
o b j e c t i v e s , c u s t o m e r s a t i s f a c t i o n t a r g e t s , e t c . )
•
E v i d e n c e o f s t a f f
u n d e r s t a n d i n g a n d
c o m m i t m e n t
•
C u s t o m e r s a t i s f a c t i o
n
m e a s u r e s
C l e a r l y d o c u m e n t e d :
•
q u a l i t y p o l i c y
•
q u a l i t y o b j e c t i v e s
•
i m p r o v e m e n t p l a n s
S c h e m a t i c 1
8/18/2019 CGMP Complete
57/128
40
C l a u s e 5 . 2 C u s t o m e r f o c u s
A k e y r e q u i r e m e n t t o p r o v i d
e s u i t a b l e p r e m i s e s , p e o p l e , a n d p r o c e s s e s ,
i n o r d e r t o e n h a n c e c u s t o m e r s a t i s f a c
t i o n .
R e a s o n s f o r t h e ‘ e x t r a ’ G M
P r e q u i r e m e n t s
P h a r m a c e u t i c a l I n d u s t r y e x p e r i e n c e s h o w s t h a t f r o m t h e p r o d u c t d e v
e l o p m e n t s t a g e o n w a r d s , c o m p l i a n t p h a r
m a c e u t i c a l q u a l i t y
r e q u i r e s f a c i l i t i e s a n d s t a f f t o b e ‘ f i t f o r p u r p o s e ’ , i . e .
‘ s u i t a b l e f a c i l i t i e s a n d c o m p e t e n t s t a f f ’ , a n d t h a t t h i s G M P
r e q u i r e m e n t i s e q u a l l y
a p p l i c a b l e t o t h e s u p p l i e r o f p h a r m a c e u t i c a l p a c k a g i n g c o m p o n e n t s .
P r o d u c t s e c u r i t y a n d t h e a v o i d a n c e o f c r o s s c o n t a m i n a t i o n u n d e r p i n s a l l p h a r m a c e u t i c a l q u a l i t y , s i n c e t h e s e a r e b a s i c i s s u e s t h a t c a n
l e a d t o p e o p l e t a k i n g t h e w r o n g m e d i c i n e ,
d a m a g i n g t h e p h a r m a c e u t i c a l c o m p a n y ’ s b u s i n e s s , a n d p u b l i c c o n f i d e n c e i n i t .
( S e e a l s o
A n n e x A ,
‘ C o u n t e r f e i t ’ t h a t c o v e r s i n d e t a i l t h e n e e d s f o r c o n t r o l s i n a
r e a s i n v o l v i n g d i s p o s a l o f a r t w o r k , p r o c e s s d e f e c t i v e s a n d w a s t e
m a t e r i a l s , e t c . ) .
B e g i n n�