CGMP Complete

Embed Size (px)

Citation preview

  • 8/18/2019 CGMP Complete

    1/128

    The Institute of

    Quality Assurance

    PharmaceuticalQuality Group

    A Guide to the GMP requirementsof PS 9000:2001 Pharmaceuticalpackaging materials

  • 8/18/2019 CGMP Complete

    2/128

    The Institute of Quality Assurance

    Pharmaceutical Quality Group

    PS 9004

     

    A Guide to the GMP requirements

    of PS 9000:2001 Pharmaceutical packaging materials

    September 2004

     

    i

  • 8/18/2019 CGMP Complete

    3/128

    ii

  • 8/18/2019 CGMP Complete

    4/128

        P    S

         9    0    0   4 

       g     u    i   d

       e P     S     9    0    0    

    4      g   u   i    d     e   

    PS 9004 guide

    ISO 9000

    +

    GMP

    for Pharmaceuticalpackaging materials

    =PS 9000

    Figure 1. Model of PS 9004: a Guide to the GMP requirements of PS 9000 

    iii

    The symbol is used in Part 1 to identify risk areas.

  • 8/18/2019 CGMP Complete

    5/128

    iviv

    ISBN 0-906810-79-5

    PS 9004: 2004

    For further information about the Pharmaceutical Quality Group (PQG) and

    any additional information or updates on PS 9000 or PS 9004 visit the PQG

    website on: www.pqg.org

    PS 9004 is available from:

    IQA Information Service

    12 Grosvenor Crescent

    London SW1X 7EE

    Tel: + 44 (0)20 7245 6722

    Fax: + 44 (0)20 7245 6788

    e-mail: [email protected]

    website: www.iqa.org

  • 8/18/2019 CGMP Complete

    6/128

    v

    COPYRIGHT

    PS 9004 copyright

     © 2004 Institute of Quality Assurance (IQA)

    This PS 9004 guide is copyright protected by IQA/Pharmaceutical Quality

    Group(PQG). However in pursuit of their objectives to promote quality

    throughout the pharmaceutical manufacturing and supply industries,

    permission is given to use the contents for quality system improvement

    in education, training, auditing or for certification purposes, provided

    acknowledgement of the source of the material (PS 9004 IQA/PQG Copyright)

    is given. Reproduction,storage in a retrieval system,transmission in any form

    or by any means,electronic, photocopying, recording or otherwise FOR ANY

    OTHER PURPOSE without prior permission being secured is prohibited.

    Requests for permission to reproduce should be addressed to the IQA at the

    address below:

      IQA Information Service

      12 Grosvenor Crescent

      London SW1X 7EE

      Tel: + 44 (0)20 7245 6722

      Fax: + 44 (0)20 7245 6788

      e-mail: [email protected]

    Reproduction may be subject to royalty payments or a licensing agreement.

    Violators may be prosecuted.

    v

  • 8/18/2019 CGMP Complete

    7/128

    vi

  • 8/18/2019 CGMP Complete

    8/128

    vii

    MHRA FOREWORD

    The EU Guide to Good Manufacturing Practice (GMP) emphasizes the need for

    pharmaceutical manufacturers and assemblers to ensure that the packaging

    materials that they use are of the appropriate quality. Not only is this in the

    interests of patient safety, but also in the pharmaceutical industry where

    the increasing use of automated packaging processes relies heavily on the

    consistent quality of packaging components.

    Each year the Medicines and Healthcare products Regulatory Agency

    (MHRA) receives and investigates a number of reports of quality defects

    concerning medicinal products. A significant proportion of these concern

    packaging errors, some of which are attributable to the use of packaging

    materials not of the desired quality. The introduction of PS 9000 in 2001 by

    the Pharmaceutical Quality Group of the Institute of Quality Assurance was

    a key step in promoting the understanding of GMPs relevant to the suppliers

    of packaging materials to the pharmaceutical industry. PS 9000 focused on

    the development and implementation, by suppliers, of a quality management

    system designed to provide assurance of the quality of their products and to

    enhance customer satisfaction. Its contribution was welcomed by both industry

    and the Regulator. PS 9004 is aimed at increasing the awareness of the quality

    management system requirements embodied in PS 9000. This comprehensive

    and easy to follow guide explains further the GMP requirements of PS 9000.

    It adopts a risk assessment approach to the identification and implementation

    of preventive action and uses case studies to illustrate areas of GMP risk.

    The MHRA encourages the introduction of PS 9004 designed to improve

    product and service quality in the supply of packaging materials for medicinal

    products, for the benefit of patients and the pharmaceutical industry as a

    whole.

    John Taylor Quality and Systems Manager

    Inspection and Enforcement Division, MHRA

  • 8/18/2019 CGMP Complete

    9/128

    viii

  • 8/18/2019 CGMP Complete

    10/128

    ix

    GENERAL INTRODUCTION

    What is PS 9004?

    This guide aims to assist suppliers of pharmaceutical packaging materials to

    understand and implement the Quality Management System (QMS) of ISO

    9001 and the application standard of PS 9000. It supplements the following

    documents:

    • ISO 9001 which specifies the requirements of the international QMS

    standard

    • ISO 9004 gives guidance on ISO 9001

    • PS 9000 is an application standard written by the PQG for suppliers of

    pharmaceutical packaging materials that integrates ISO 9001 and ISO

    9004 together with additional Good Manufacturing Practices (GMP)

    requirements particular to these suppliers

    Companies complying with PS 9000 will comply with ISO 9001 and also the

    additional GMP requirements endorsed by the highly regulated pharmaceutical

    industry.

    This guide is constructed around the clause structure of PS 9000 (and therefore

    ISO 9001) to:

    • clearly explain the GMP requirements of PS 9000

    • list many of the risk areas associated with packaging processes and identify

    relevant ISO 9001 and PS 9000 clauses

    • provide examples of process inputs and process outputs typical of suppliers

    of pharmaceutical packaging materials, and relate these to the QMS

    requirements of ISO 9001 and the additional GMP requirements of PS

    9000

    • give examples of actual case histories of problems arising from the supply of

    defective pharmaceutical packaging materials and where the consequences

    would have been avoided by correct application of the GMP requirements

    of PS 9000. These case histories help to explain the requirements and

    provide a valuable training resource

  • 8/18/2019 CGMP Complete

    11/128

     x

    How to use this Guide

    PS 9004 has been organized in the following way:

    • Part 1 consists of a selection of process schematics, illustrating typical

    operations of a packaging supplier, and giving examples of some of the

    more significant risks caused by inadequate manufacturing practices

    • Part 2 gives guidance on the clauses of PS 9000, by taking the user through

    each major section and providing examples to illustrate suggested process

    inputs and outputs

    • Annex A gives expanded explanatory notes on several key concepts used in

    PS 9000

    • Annex B gives a listing of other external regulatory references, which are

    the background to pharmaceutical GMP and which are directly relevant to

    PS 9000 requirements

    • the text is primarily black but blue is used for PS 9000 related GMP text 

    • red text is used to highlight the ‘Risk Areas’ 

    The user can cross refer between the schematics in Part 1 and the process

    information in Part 2. In addition, the user can move from Part 2 to the additional

    explanations in the annexes.

    The annexes contained within this Guide are a stand-alone explanation of key

    concepts and external GMP references. The PS 9000 cross-references are for

    illustrative purposes and are not a definitive list of clauses or references.

    The How to use section, which follows the contents list, shows the user how to

    navigate between the different sections of the Guide.

    As the range of organizations that may implement PS 9000 is great, both in

    terms of size and type of business, the guidance given here is illustrative and

    advisory.

    Why was the PS 9004 Guide written?

    There are three main reasons:

    • to guide professional quality specialists towards the implementation and

    inspection of a Quality Management System (QMS) in accordance with PS

    9000

    • to support the training of all the various stakeholders in the PS 9000 process

    (top management, quality professionals, staff at all levels of packaging

  • 8/18/2019 CGMP Complete

    12/128

     xi

    material suppliers and their customers)

    • to provide those people who are not quality specialists with a better

    understanding of the aims, objectives and implementation of PS 9000

    How was the PS 9004 Guide written?

    A group of experienced quality professionals selected from the packaging supply

    industry and pharmaceutical customers was recruited by the Pharmaceutical

    Quality Group Partners Team and given the task of preparing this Guide.

    Many of the people who contributed to the writing of PS 9000 also participated

    in the creation of this Guide.

    Specific acknowledgements are given for the contributions of the

    following people:

      Roy Evans PS 9004 Team Leader

      David Abraham Supplier

    Ian Harwood Pharmaceutical

    Jill Jenkins Pharmaceutical

      Daniel Peek Supplier

    Richard Rowlett Supplier

    Mike Shorten Pharmaceutical

    Steve Taylor Pharmaceutical

    Additional contributions:

      Caroline Fowler Pharmaceutical

      Peter Gough Pharmaceutical

      Ian Holloway Regulator

      Steve Merrit Pharmaceutical

      Ashley McCraight Consultant

      Jeff Monk Training

      Dominic Parry Training

      Steve Pike Accredited certification

    Norman Randall Consultant

      Trevor Stabb Consultant

      Paul Stockbridge Consultant

    QA review:

      Tony Harper Consultant and accredited certification

    Afshin Hosseiny Consultant

  • 8/18/2019 CGMP Complete

    13/128

     xii

    QA review (con’t):

      Jean Lanet Consultant

      Iain Moore Supplier

      Steve Moss Pharmaceutical

    Ashok Chand Pharmaceutical

      John Turner Consultant

     

    The PQG Partners Team and Steering Committee:

      Roy Evans

      Tony Harper

      Femi Ibironke

      Jill Jenkins

    Ashley McCraight (PT Chairman)

      Steve Moss

      Norman Randall (SC Chairman)

    Ian Richardson

    In addition, the PQG is appreciative of the management of Patheon UK

    Limited. for the use of their resources and facilities.

  • 8/18/2019 CGMP Complete

    14/128

     xiii

    CONTENTS

    Section Page

    How to use this guide xv

    Part 1 – Process schematics and case studies 1

      Overview of business processes 2

      Schematic 1 Top level business processes 2

      Schematic 2 From the customer 4

      Schematic 3 Planning 6

      Schematic 3 (a) Warehouse (purchased materials and in-process) 8

      Schematic 4 Preparation 10

      Schematic 4 (a) Print impression media controls 12

      Schematic 5 Production 14

      Schematic 6 Checking and final release 16

      Schematic 7 Distribution 18

      Case studies 21

    Part 2 – Guidance on PS 9000 GMP clauses 35

      Clause 4 Quality management system 37

      Clause 5 Management responsibility 39

      Clause 6 Resource management 45

      Clause 7 Product realization 49

      Clause 8 Measurement, analysis and improvement 59

      Clause 9 Contamination control 66

      Clause 10 Printed materials 68

      Clause 11 Origination/artwork 70

      Clause 12 Print impression media 72

      Clause 13 Print and conversion processes 74

  • 8/18/2019 CGMP Complete

    15/128

  • 8/18/2019 CGMP Complete

    16/128

     xv

    HOW TO USE THIS GUIDE

    STEP 1

    Choose a schematic from the ‘Overview of business process’ diagram in Part 1 of

    this guide. (e.g. Schematic 3(a) is illustrative)

    STEP 2

    From your schematic, choose a particular stage of the process to examine, e.g.

    Store material (see below).

    SCHEMATIC 3 (a) - WAREHOUSE

    STEP 3

    Consider the Risk Areas shown in red and the real life case study (if shown) - these

    are detailed at the end of Part 1, following the schematics.

    Deliverychecks

    • Document errors

    • Missing

    documents

    7.4.3

    7.5.3

    Qualityinspection

    • Labelling errors

    • Incorrect goods

    7.4

    7.4.3

     

    Storematerial

    • Pest

    Infestation

    Case study G

    7.5.5:

    Preservationof product

    9:

    Contamina-

    tion control

    Issuematerial

    • Incorrect

    materials

    7.5.3

     

    See Part 2

    for more

    details

    Risk areas

  • 8/18/2019 CGMP Complete

    17/128

     xvi

    STEP 4

    Using the references shown in the schematic, move to the corresponding section

    in Part 2, entitled ‘Guidance on PS 9000 GMP clauses’. This gives reasons for the

    ‘extra’ GMPs and shows examples of processes, inputs and outputs.

    General synopsis: Clause 9 Contamination control

    The capability of facilities and equipment, achieved through their design, location,

    etc.

    Reasons for the ‘extra’ GMP requirements

    The highest priority of the pharmaceutical industry is... etc.

    Process inputs Processes Process outputs

    and evidence

    Cross refer to

    Schematic/Annex

    Specification

    for design of

    new facilities,

    processes, or

    environment

    Specialistsupport for

    pest control

    Standards for

    environmental

    conditions

    Processes which

    identify/control:

    • operating areas

    • pest control

    • cleaning proce-

    dures

    Records of:

    • processing

    • cleaning

    schedules

    • material disposal

    • incidents/audit

    reports

    Schematic 3(a)

    Schematic 4(a)

    Schematic 5

     Annex A - all parts

    STEP 5

    Use the cross references to move back to a relevant process schematic, alterna-

    tively refer to Annex A or B for further guidance.

     ANNEX A 

     Additional Explanation of Key Concepts

     ANNEX B

    Other external GMP references.

  • 8/18/2019 CGMP Complete

    18/128

    1

    The Institute of Quality Assurance

    Pharmaceutical Quality Group

    PS 9004

     

    A Guide to the GMP requirements

    of PS 9000:2001 Pharmaceutical packaging materials

    PART 1 - PROCESS SCHEMATICS

    PS 9000 GMP references are reproduced in blue

    Risk areas are reproduced in red

     

  • 8/18/2019 CGMP Complete

    19/128

    2

    OVERVIEW OF BUSINESS PROCESSES

    Schematic 1: Top level business processes

    Schematic 2:From the customer

    Schematic 3:Planning

     

    Schematic 4:Preparation

    Schematic 3 (a):Warehouse

    Schematic 4 (a):Print impressionmedia controls

     

    SCHEMATIC 1: TOP LEVEL BUSINESS PROCESSES

    Quality  management  system

    Managementcommitment

    • Inadequate

    incorporationof PS 9000

    requirements

    • QMS not

    communicated

    and/or

    supported

    by senior

    management

    4 QMS

    5.1 Management

    commitment

    5.5

    Responsibility,

    authority andcommunication

    Objectives

    • Unclear

    businesstargets/goals

    • No clear

    direction as

    objectives not

    published

    5.3 Quality

    Policy

    5.4 Planning

    Resourceallocation

    • Too few people

    for qualitycompliant

    operation

    • Wrong/

    inadequate

    equipment

    • Inadequate

    premises

    • Inadequate

    training

    6.1 Provision of

    resources

    6.2 Human

    resources

     Refer to the hypothetical examples which

    are located after the schematics.

     See Part 2

    for more

    details

    Risk areas

  • 8/18/2019 CGMP Complete

    20/128

    3

    Schematic 5:Production

    Schematic 6:Checking and finalrelease

    Schematic 7:Distribution

    This diagram shows the main business processes from customerrequirements through to delivery of final product and provides an indexto the schematics

     Audit andmeasurement

    • Inadequate

    performancemeasures

    • Poorly controlled

    processes

    • Unreliable

    information for

    management

    decisions

    • Poor compliance to

    internally established

    processes/ procedures

    • Insufficient proof

    of continuous

    improvement

    8.1 Measurement,

    analysis and

    improvement -

    general

    Managementreview

    • Quality System

    measures notreviewed

    • Lack of senior

    management

    involvement/ 

    leadership

    • No continual

    process

    improvement

    5.1 Management

    commitment

    5.6 Management

    review

    8.5 Improvement

    Quality management system

    Feedback/communication

  • 8/18/2019 CGMP Complete

    21/128

    4

    SCHEMATIC 2: FROM THE CUSTOMER

     

    Organization Customerrequest/ requirements

    • Requirements

    unclear

    • Requirements

    incorrectly

    specified

    • Requirementsmisunderstood

    • Requirements

    incorrectly

    accepted

    See case study A 

    5.2 Customer

    focus

    7.2 Customer-

    related processes

    Supplyrequirements(what, how,when)

    • Unclearly

    specified

    • Failure to meet

    customer

    expectation• Rejection by

    customer

    Customerdesign

    • Poor design

    • Inadequate detail

    • Failure tofunction

    • Poor

    performance at

    customers site

    • Rejection by

    customer

    • Potential risk to

    patient

    • Inadequate

    testing/validationSee case studies

     A and B

     

    Feedback

    7.2 Customer-related processes

    7.3 Design and development

     See Part 2

    for more

    details

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    22/128

    5

     Assessmentof capability 

    • Incorrect

    assessment

    of capability

    e.g. resource,

    technology,

    systems,

    environment• Fail to meet

    delivery/quality

    6.1 Provision of

    resources

    6.3 Infrastructure

    6.4 Work

    environment

    7.1 Planning

    of product

    realization

     Agreedcontract/ agreementand confirmedorder

    • Lack of formal

    contract/ 

    agreement

    • Failure toagree contract

    requirements

    • Poor

    communication

    7.2.3 Customer-

    related processes

    Planning

  • 8/18/2019 CGMP Complete

    23/128

    6

     

    SCHEMATIC 3: PLANNING

    Receive orderfrom customer 

    Order review andcustomer feedback(where required)

    • Incorrect specification

    chosen

    • Inadequate

    communication with

    customer

    • Order details incorrect• Supply incorrect product

    • Supply error (quantity/ 

    schedule)

    • Proof approval error

    • Specification not

    approved

    See case studies

    C and D

    5.2 Customer focus

    7.2 Customer-related

    processes

    7.3 Design and

    development

     Availability checkson documentation,materials, toolingand equipment

    • Incorrect material checked

    or issued (e.g. wrong foil

    gauge)

    • Wrong print media

    (version or item)• Non-availability of

    equipment (e.g.

    maintenance/validation

    status)

    • Unapproved production

    process (e.g. not

    approved by customer)

    • Unsuitable/unapproved

    material/changes

    • Missing/incorrect

    documentation (e.g.

    missing mould inspection

    record)

    7.4 Purchasing

    7.5 Production and service

    provision

    11 Origination/artwork

    12 Print impression media

     

    See Part 2

    for more

    details

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    24/128

    7

    Purchasing and printmedia provision

    • Inadequate supplier

    control

    • Nonconforming

    purchased materials or

    service

    • Inability to obtain raw

    material• Inadequate security (e.g.

    printing plates)

    • Insecure data links (e.g.

    validation of ISDN link)

    • Incorrectly identified

    materials (e.g.

    mislabelling of stock

    from supplier)

    See case study E

    4.2 Documentation

    requirements

    7.4 Purchasing

    8.3 Control of

    nonconforming product

    11 Origination/artwork

    12 Print impression media

     

    Production scheduleand feedback fromproduction

    • Inadequately defined

    plan/schedule (e.g.

    insufficient time for

    line clearance or

    maintenance)

    • Inadequate programmetime to follow procedures

    • Problems in production

    7.1 Planning of product

    realization

    7.5 Production and service

    provision

    8 Measurement, analysis

    and improvement

     

    Preparation for start of production

    Feedback

  • 8/18/2019 CGMP Complete

    25/128

    8

     

    SCHEMATIC 3 (a): WAREHOUSE (purchased materials and in-process)

    Delivery from supplier/sub-contractor 

    Deliverydocumentation andoff-loading checks

    • Errors not identified

    between delivery

    documentation &

    purchase order

    • Missing delivery/QC

    documentation• Transit damage or wet

    boxes not identified

    before off-loading

    • Incorrect goods

     

    7.4.3 Verification of

    purchased product

    7.5.3 Identification and

    traceability

    Goods checks andquality inspection

    • Inadequate checks

    performed

    • Labelling errors not

    identified

    • Incorrect goods sent

    • Rogue box within delivery

    • Inadequate batch coding• Non representative sample

    taken or provided

    • Transit/water damage not

    detected

    • Inadequate packaging/

    sealing not detected

    • Incorrect quality status

    input to system

    See case study F

     7.4 Purchasing

    7.4.3 Verification of

    purchased product

     

    See Part 2

    for more

    details

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    26/128

  • 8/18/2019 CGMP Complete

    27/128

    10

    SCHEMATIC 4: PREPARATION

     Production

     plan

    Preparation/ 

    pre-productionchecks ofpurchased rawmaterials

    • Error in checking

    raw material

    • Quality status

    incorrect

    • Availability status

    incorrect

    Materials

    management

    Errors in:

    • Co-ordination

    of all required

    resources

    • Combining/

    assembly/ Bills

    of Material

    • Timing/change

    management

    • Machine

    allocation

     7.1 Planning

    of product

    realization

     7.2 Customer

    related

    processes

    Preparation/ pre-productionchecks oftooling andequipment

    • Error in checking

    tooling/equipment

    • Change controlerror

    • Validation status

    error

    • Maintenance

    omission/ error

    • Availability status

    incorrect

    See case study H

     7.4 Purchasing

    7.5 Production and service provision

    10 Printed materials

    11 Origination/artwork

    12 Print impression media

    13 Print and conversion process

     See Part 2

    for more

    details

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    28/128

    11

    Issue of tooling

    • Issue incorrect tool

    • Issued with incorrect

    status

    • Issue in poor

    condition

    • Issue printing plates

    in insecure manner

    See case studies

    I, J and K 

     7.5 Production and

    service provision

    12 Print impression

    media

    Issue of

    materialsanddocumentation

    • Issue incorrect

    materials

    • Incorrect quantity

    issued

    • Issued with incorrect

    status

    • Issue incorrect

    documentation

    • Unapproved

    documentation

     4.2 Documentation

    requirements

     7.5 Production and

    service provision

    11 Origination/artwork

    12 Print impression

    media

    Production

  • 8/18/2019 CGMP Complete

    29/128

    12

    SCHEMATIC 4 (a): PRINT IMPRESSION MEDIA CONTROLS

     Customer supplieddesign text 

    New printmedia design

    • Errors in media

    undetected by

    checks

    • Individual plate

    incorrectly coded

    • Set of plates

    incorrectly coded

    • Failure to secure

    customer proofapproval

    • Failure to log

    customer

    approval

    See case study L

    11 Origination/

    artwork

    12.1 General

    12.2 Matched

    plates

    Securestorage andcontrolledissue ofplates

    • Mix-up with

    plates from

    another product

    • Uncontrolled

    access of

    personnel• Physical

    damage to

    plates

    • Inadequate

    records of issue

    introducing

    admixture risk

    in production

     

    Controlsover partialre-designsand obsoletedesigns

    • Incorrect plates

    retained

    • Insecure disposal

    • Superseded platesnot rendered

    unusable

    • Incorrect plate

    identification

    • Error in

    replacement plate/

    matching set

    • Documentation

    errors

    • Customerapproval error

    See case study M

     12.2 Matched plates

    12.3 Copy / design change

    12.5 Quarantine and destruction

    13.2 Changeover systems See Part 2

    for moredetails

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    30/128

    13

    Line use ofplates

    Failure to :

    • Check design

    • Clear line of

    previous plates

    • Perform start-up

    printing checks

    • Record checks

    • Keep samples

    See case

    study N

    9.1.7 Line

    clearance

    12.4 Verification

    13.1 Print

    machine set-up

    (make-ready)13.2 Changeover

    systems

    13.3 Retained

    samples

    Controls overreplacementplate (samedesign)

    • A new first off

    check is not

    performed or

    recorded (e.g.plate made

    from existing

    approved

    source)

    • New origination

    & new batch

    checks not

    performed or

    recorded (e.g.

    plate createdfrom a new

    source)

    13.4 Replacement

    print media

     

    Line clearanceand controlledreturn ofplates to store

    • Plate left on

    machine in error

    • Inadequate

    records of return

    to store

     

    9.1.7 Line

    clearance

    12.1 General

     

    Production

  • 8/18/2019 CGMP Complete

    31/128

    14

    SCHEMATIC 5: PRODUCTION

    Preparation Line clearcheck

    • Admixture from

    previous batch

    • Erroneous use

    of previous

    documents

    • Use of a plate

    from previous job

    7.5 Production

    and service

    provision

    9.1.7 Line

    clearance

    10 Printed

    materials11 Origination/

    artwork

    Documents/ materials/ tooling to line

    • Use of incorrect

    documents/

    materials

    • Failure to use

    documents

    correctly• Incorrect

    quantities

    • Defective moulds/ 

    equipment/plates

    See case study O

    4.2 Documentation

    requirements

    7.5 Production and

    service provision

    Set upchecks andproductionstart

    • Errors in

    data input to

    machine, e.g.

    settings

    • Setting errorundetected

    • Start up waste

    inadequately

    segregated

    from main

    batch

    • Unauthorized

    start up

    5.5 Respon-

    sibility,

    authority and

    communication

    7.6 Control of

    monitoring

    and measuringdevices

    9 Contamination

    controls

    10 Printed

    materials

    12 Print

    impression

    media

     

    See Part 2for more

    details

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    32/128

    15

    Production/inprocess control

    • Quality variation due

    to environment e.g.

    temperature, humidity

    • Contamination e.g.

    insects, dust

    • Defective / out of spec

    or wrong materials• Visual defects not

    detected

    • Inadequate IPC of transit

    packaging

    • Labelling errors

    • IPC errors

    • Material usage error

    • Failure to identify/ 

    segregate non

    conforming product

    • Recording error

    See case studies P, Q

    6.4 Work environment

    7.5 Production and

    service provision

    8.2 Monitoring and

    measurement

    8.3 Control ofnonconforming product

    11 Origination/artwork

    Production completionand line clearance

    Risk to next job due to:

    • lack of GMP training

    • failure to clear line

    • inadequate waste disposal

    • documentation not signed

    off therefore status unclear

    • clearance of electronicfiles/settings

    See case study R

    6.2.2 Competence,

    awareness and training

    8.2 Monitoring and

    measurement

    9 Contamination controls

    10 Printed materials

    13 Print and conversionprocesses

    Checking andfinal release

    Feedback

  • 8/18/2019 CGMP Complete

    33/128

    16

     

    SCHEMATIC 6: CHECKING AND FINAL RELEASE

    Production End product

    QC testing

    • Inadequate training

    • Test method not

    validated

    • Out of Specification

    results not investigated

    • Inadequate procedures

    • Release decision

    contradicts data

    • Inconsistent sampling/ risk

    • Equipment/test

    equipment inadequate

    • Calibration errors/ 

    omissions

    See case study S

    6.2.2 Competence,awareness and training

    7.6 Control of monitoring

    and measuring devices

    8 Measurement, analysis

    and improvement

    8.4 Analysis of data

    Review of batch

    documents and QCtesting

    • Missing/incorrect

    document

    • Missing/incorrect sample

    • Signature omissions,

    unauthorized check

    signature

    • Errors of information/data

    entry• Checks out of sequence

    • Abnormal events not

    reviewed

    See case study T

    5.5 Responsibility, authorityand communication

    6.2 Human resources

    4.2 Documentation

    requirements

    13 Print and conversion

    process

     

    See Part 2

    for more

    details

    Risk areas

    Refer to the case studies

    which are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    34/128

    17

    Create certificate of

    test or conformance

    • Errors / omissions

    • Signature invalid

    • Inappropriate data

    supplied

    • Incorrect specifications/ 

    tolerances

    • Incorrect release decision

    • Certificate text differsfrom batch details

    See case study U

    8.2 Monitoring andmeasurement

    8.3 Control of

    nonconforming product

    Check box labels

    against batchinformation

    • Incorrect/missing label

    • Label data error/

    omission

    • Label reconciliation

    • Incorrect QC status label

    See case studies V and W

    7.5 Production and serviceprovision

    Distribution

  • 8/18/2019 CGMP Complete

    35/128

    18

     

    SCHEMATIC 7 - DISTRIBUTION

    Checking and

    final release

    Receipt of product

    into storage/holding(goods outwarehouse)

    • Error in system

    transaction (receipt)

    • Inadequate segregation

    from other goods

    • Storage damage

    7.5 Production and service

    provision

    10 Printed materials

    Order preparation

    (picking and transitpackaging)

    • Picking wrong product

    • Damage to product due

    to inappropriate transit

    packaging

    • Pallets not suitable for

    customer handling

    • Error in transaction (issue)

    See case study X 

    7.5 Production and service

    provision

     

    See Part 2

    for more

    details

    Risk areas

    Refer to the case studieswhich are located after

    the schematics.

  • 8/18/2019 CGMP Complete

    36/128

    19

    Dispatch area/ 

    goods check anddocumentation

    • Errors of quantity

    • Incorrect labelling

    • Error in dispatch note

    • Admixture of boxes

    See case study Y 

    Transport to the

    customer

    • Transit damage e.g. poor

    pallet stacking, poor

    weather protection

    • Contamination in transit

    • Inadequate control of

    hauliers

    See case study Z

    The customer 

    7.5 Production and service provision

  • 8/18/2019 CGMP Complete

    37/128

    20

  • 8/18/2019 CGMP Complete

    38/128

    21

    The Institute of Quality Assurance

    Pharmaceutical Quality Group

    PS 9004

     

    A Guide to the GMP requirements

    of PS 9000:2001 Pharmaceutical packaging materials

    PART 1 - CASE STUDIES

     

  • 8/18/2019 CGMP Complete

    39/128

    22

  • 8/18/2019 CGMP Complete

    40/128

    23

    Part 1 – Examples and Case studies

    These examples and ‘real life’ case studies should be used with the

    relevant Schematic, to illustrate specific GMP risk areas and the

    appropriate QMS processes involved.

    HYPOTHETICAL EXAMPLE FOR SCHEMATIC 1 –

    TOP LEVEL BUSINESS PROCESSES

    The senior management of a booklet printing company believes that PS

    9000 certification will aid company profitability and smooth throughput

    because of consistent demand from the pharmaceutical industry, which

    is not adversely affected by recessions. The company has an enthusiastic

    Quality Manager who has produced a comprehensive manual with up to

    date and relevant procedures. However, the Quality Manager is beginning

    to feel like a ‘voice in the wilderness’ as there is little evidence that senior

    management is driving the whole organization to become aligned to the

    requirements of the standard. The lack of senior management commitment

    to the continual improvement philosophy and the Good Manufacturing

    Practices of the pharmaceutical industry means that only superficial actions

    are taken in areas considered highly visible to visiting auditors. Key individu-

    als are unclear about the standards required of them. The level of customer

    complaints remains high, some of these complaints being serious mix-ups.

    Productivity stays unchanged with a high level of wastage. Workforce moral

    is low and many staff are demotivated.

    The company is then purchased by another company that already supplies

    cartons to the pharmaceutical industry - allowing them to offer a better

    product range to the customer. The corporate re-organization results in key

    changes in senior management at the booklet factory. The new managers

    know their prime objective is to encourage each and every employee to

    understand the particular needs of their pharmaceutical customers. They

    understand the value of PS 9000 in a competitive market, but know that the

    real benefits are much deeper than merely achieving the ‘badge’. The Qual-

    ity Manager begins to feel encouraged and genuinely part of the team. The

    frequency of management review meetings is increased with the emphasis

    changed to progressing preventive actions for nonconformities and review-

  • 8/18/2019 CGMP Complete

    41/128

    24

    ing clear measures of performance for key parameters such as complaint

    rates. The senior management commitment begins to permeate throughout

    the staff and becomes evident in many areas such as resourcing, training,

    customer service, and improved product quality. The board of directors

    soon recognises that the PS 9000 implementation process is enabling them

    to profitably expand their business, improve relationships with their custom-

    ers, whilst still significantly reducing their cost of quality.

    CASE STUDIES FOR SCHEMATIC 2 – FROM THE CUSTOMER

     A Focus - Customer request/requirements

    Bar coded product labels could not be read by customer’s electronic read-

    ers due to shading of background colour, caused by inadequate testing

    and validation. The packing orders at the pharmaceutical company were

    delayed which threatened the availability of the medicinal products to the

    end customers. The labels had to be destroyed, incurring the direct expense

    of replacement. The product was redesigned with solid background, and all

    graphics designers were made aware of the issue and to consider the pos-

    sible need for trials on change of design or introduction of a new design.

    B Focus – Customer design

     A market need for a needle protection mechanism was specified, but

    translation of this into a final design was lengthy and complicated. The

    component did not perform reliably due to limited experimental validation.

    The problems were addressed through increased communication with the

    supplier to make the design more robust, involving revalidation and testing.

    This extended work caused a delay in providing the improved safety prod-

    uct to the patient. An organizational review followed to ensure that in future,

    adequate resource is devoted at the design and testing stages of product

    development.

    CASE STUDIES FOR SCHEMATIC 3 – PLANNING

    C Focus – Order review and customer feedback

    The wrong material was ordered by the supplier’s UK sales office from their

    own factory. Normally, orders were placed for 40 micron PVDC coated PVC

  • 8/18/2019 CGMP Complete

    42/128

    25

    (for tablet blister packing), but on this occasion a new order for 60 micron

    coated film was incorrectly notified by the sales office to the factory in Ger-

    many as 40 micron; the incorrect material was delivered and used causing

    a regulatory noncompliance and potentially inadequately protecting the

    tablets from moisture. Significant work was necessary by the pharmaceuti-

    cal company to assess stability data to determine the acceptability of the

    packed tablet batches. The root cause was established through customer

    audit of the ordering system at the sales office. An independent check of

    order details was implemented to prevent repetition.

    D Focus – Order review and customer feedback

    The printer’s proof was incorrectly read by the supplier as ‘approved’ when

    it was actually ‘rejected’; also the wrong file was used to make replace-

    ment printing plates. Cartons for a heart condition medicinal product were

    printed and used showing on one end flap 14 tablets instead of 28. The

    consequence of this was that stock had to be recalled from the distribu-

    tion centres to enable a rework. This delayed the critical medicinal product

    reaching the market. Working together, customer and organization, the

    complete sequence of events was reconstructed. In addition to awareness

    training, the rules regarding issuing artworks and file management between

    organization and platemaker were made more robust.

    E Focus – Purchasing and print media provision

    Leaflets with a different paper weight were supplied, due to problems with

    availability of normal paper. This caused insertion difficulties on the phar-

    maceutical packing line, high wastage of components and loss of some

    pharmaceutical product. The supplier was advised of the existing change

    control clause in the quality agreement/contract and procedures were

    revised. The supplier managed to obtain further supplies of normal paper.

    CASE STUDIES FOR SCHEMATIC 3 (a) –

    WAREHOUSE (PURCHASED MATERIALS & IN-PROCESS)

    F Focus – Goods checks and quality inspection

    Self-adhesive labels were failing to stick to glass vials at the customer’s

    premises because a different adhesive had been used. This had been

    caused by the supplier switching their source of unprinted label material.

  • 8/18/2019 CGMP Complete

    43/128

    26

    The raw material was thought to be of equivalent quality and no extra qual-

    ity checks were performed at goods-inwards. The change was introduced

    without informing the customer therefore no formal change control or a

    risk assessment could be performed. The problem caused chaos on the

    customer’s packing line and it was not certain how well the labels were

    affixed to ‘apparently’ satisfactory packed vials. The label printing company

    pursued the quality issue with its supplier and proper trials of alternatives

    were subsequently conducted with the pharmaceutical company. In addi-

    tion, revisions were made to the change control system.

    G Focus – Store material

    Two dead mice were found inside the pallet wrapping of a consignment of

    plastic bottles to be used for an antiseptic liquid product. This caused major

    disruption to the output of the pharmaceutical filling plant. All the stock of

    bottles had to be manually inspected for contamination. It was necessary to

    audit the supplier and its remote warehouse. Immediate action involved the

    relocation of bottle storage back into the main factory. The root cause was

    inadequate warehouse pest controls at the supplier’s remote warehouse. It

    prompted an extensive programme of work to improve the standards at the

    site. The product was a low margin item for the pharmaceutical company

    and it has since been sold off to another company. Although many other

    factors were involved, this episode only added to the reasons to sell this

    part of the business.

    CASE STUDIES FOR SCHEMATIC 4 – PREPARATION

    H Focus – Preparation/pre-production checks of tooling and

    equipment

    Mould tool used to produce parts for a syringe was used in production

    when the validation documentation had not been fully approved and signed

    off. This contributed to high variability in functional performance of the

    assembled syringe with some batches of parts rejected, and it necessitated

    ongoing improvement work. It also delayed the launch of the pharmaceuti-

    cal product which in this case was a life saving cancer product. The opera-

    tional procedures were revised and the operators were retrained.

  • 8/18/2019 CGMP Complete

    44/128

    27

    I Focus – Issue of tooling

    Syringe labels were printed correctly, but were cut with corners of the wrong

    profile/shape due to the issue of an incorrect cutter to the press. The labels

    were rejected by the pharmaceutical company at the expense of the print-

    ers. The time needed to replace the labels meant rescheduling of packing

    was necessary at the pharmaceutical company. The cutter identification

    process was reviewed & storage standards were improved.

    J Focus – Issue of tooling

    Cartons were produced with a varnish free area in the wrong position due

    to the issue of an incorrect varnish plate. The purpose of a varnish free area

    is to ensure the printing of variable data (e.g. lot & expiry) is clear and per-

    manent. This error was identified at the pharmaceutical company. The risk

    existed that variable data applied by the pharmaceutical company could

    be easily smudged or erased when in the market and this would clearly be

    a critical problem. The supplier reviewed the varnish plate issuing process

    and made improvements to the system which linked varnish plate usage to

    print plate usage.

    K Focus – Issue of tooling

    Mould tool for a syringe plunger rod was issued to production despite

    being overdue for refurbishment. This resulted in minor plastic ‘flash’ being

    present on the mouldings. If this problem became more serious then loose

    particles of plastic could break off and contaminate the pharmaceutical

    syringe pack. The supplier applied for a concession from the customer and

    this was granted for a limited period because of the extent of the problem.

    The case highlighted the need for proper planned preventive maintenance

    and sufficient resources allocated to facilitate it.

    CASE STUDIES FOR SCHEMATIC 4 (a) –

    PRINT IMPRESSION MEDIA CONTROLS

    L Focus – New print media design

     Artwork supplier made a “cut & paste” error which resulted in cards being

    part printed with Polish text in the main body of Portuguese text. The cards

    were for an anti-cancer injection. Fortunately the error was noticed dur-

    ing in-process checks of printing. The error had the potential to become

  • 8/18/2019 CGMP Complete

    45/128

    28

    a product recall if it had reached the end user. An extensive review of the

    artwork supplier’s procedures was completed and a further proof-reading

    check was introduced.

    M Focus – Controls over partial redesigns & obsolete designs

    The printed foil for tablet blister strips (used to treat a heart condition) was

    incorrectly printed with two different identifying codes on the foil (different

    by one digit). The error occurred during the ‘step and repeat’ process to

    generate a single replacement cylinder. The error was only found on inspec-

    tion at the pharmaceutical company. In this case, no packed stock was lost,

    but the error could have been more serious. The supplier took the issue up

    with its cylinder manufacturer and reviewed its inspection procedure for first

    off sample inspection following cylinder replacement.

    N Focus – Line use of plates

     A printing plate was left on the leaflet press by the operator after leaving the

    area to retrieve a spare part. Upon return the operator continued printing,

    but against the job documentation for the next job. The item was visually

    very similar and all subsequent checks by operators and QC failed to spot

    the admixture that had been created. The problem was found on goods

    inwards checks by the customer, and resulted in a detailed audit of proce-

    dures by the customer. Line clearance checks were reviewed, procedures

    around bar code scanning at the suppliers were enhanced and refresher

    training was delivered.

    CASE STUDIES FOR SCHEMATIC 5 – PRODUCTION

    O Focus – Documents/materials/tooling to line

    During the folding stage of leaflet production two orders were mixed up. Job

     A was folded, scanned, labelled and released against Job B documenta-

    tion, and Job B documentation was folded, scanned, labelled and released

    against Job A documentation. The mixed-up orders were then delivered to

    the pharmaceutical company where the error was discovered. The potential

    for incorrect leaflets to be packed into pharmaceutical packs was increased.

    The supplier’s investigation identified the root cause as human failure to fol-

    low established procedures. In addition the codes for the bar code scanner

    are now input from an independent source (a PS 9000:2001 requirement).

  • 8/18/2019 CGMP Complete

    46/128

    29

    P Focus – Production/in-process control

     A delivery of poorly printed foil, used for tablet blister strips, was caused

    by inadequate ‘flagging’ of defective material during printing. The ‘flagged’

    material is removed during later stages of slitting and rewinding. The defec-

    tive material was detected on the customer’s packing line and lead to the

    scrapping of some packed pharmaceutical product. The supplier’s printers

    and the operators responsible for removal of the ‘flagged’ material were

    given refresher training to ensure all defective material is removed, up to

    and around the ‘flagged’ point in the reel.

    Q Focus – Production/in-process control

    Plastic tablet bottles were manufactured with a wall thickness that was

    below specification. This was caused by poor appreciation of the cus-

    tomer’s requirements, inadequate in-process monitoring and an inability to

    segregate product that was out of specification. Packed pharmaceutical

    product had to be quarantined until all aspects of the problem had been

    assessed by the pharmaceutical company’s QA Department. The issue was

    resolved through improved specification regarding the criticality of certain

    dimensions, increased in-process measuring regime and enhanced segre-

    gation procedures.

    R Focus – Production completion & line clearance

    On a reel of label/leaflet combinations, six ‘rogue’ components (of similar

    appearance) were found at intermittent points in the reel, by the pharmaceu-

    tical customer. This was despite a scanning operation being in place at the

    supplier. The root cause was human error involving inadequate line clear-

    ance and replacing incorrect labels back onto the web during rewinding/ 

    scanning. Although the rule existed which forbade this practice, the

    operator had recently been transferred from a department supplying non-

    pharmaceutical customers where this rule was not in place. The supplier

    commenced a fundamental review of procedures and operator retraining.

    CASE STUDIES FOR SCHEMATIC 6 – CHECKING & FINAL RELEASE

    S Focus – End product QC testing

     An out of specification result on a test machine record was transcribed

    incorrectly as satisfactory on the summary sheet, causing an incorrect

  • 8/18/2019 CGMP Complete

    47/128

    30

    release decision of a batch of syringes. Although, in this case no harm was

    caused, it highlighted a risk area, should the error have occurred on another

    safety related function of the syringe. Refresher training was delivered to the

    operator concerned.

    T Focus – Review of Batch documents & QC testing

    Carton barcode scanner was switched off during the night shift without

    QA authorization and not noticed upon review of documentation. This

    meant that the product had been made without the safeguards required

    by, and contractually agreed with the customer. The product was therefore

    inadequately checked for the absence of rogue components. The affected

    order was rejected and scrapped. A detailed audit was performed by the

    pharmaceutical company and numerous significant procedural enhance-

    ments were made.

    U Focus – Create Certificate of Test or Conformance

    Irradiated syringes were released for use despite radiation dose figures

    being omitted from the certificate of test. In this case the dosage was

    actually satisfactory, however the omission / error had the potential to

    threaten the sterility of the syringes thus endangering the patient, and to

    compromise the pharmaceutical sterile filling facility. The certificates are

    now double checked before release from the irradiation contractor.

     V Focus – Check box labels against batch information

     A box of shampoo closures was delivered amongst a consignment of tablet

    bottle closures, caused by box labelling error & poor segregation practices.

    This resulted in admixture on the filling line at the pharmaceutical company,

    line downtime, and some lost product. The supplier had been audited on

    numerous occasions but lack of commitment to eliminate such problems

    ultimately lead to a change of supplier for the component.

    W Focus – Check box labels against batch information

     A keying-in error of leaflet product identity code to outer box label printer

    caused rejection upon delivery to customer. Apart from the disruption

    caused by the rejection, there was a risk that the material could have been

    received into stock as a different item, i.e. admixture. The preventive action

    eventually implemented was to link the box label printer to the mainframe

  • 8/18/2019 CGMP Complete

    48/128

    31

    computer thus removing the necessity to manually key the data into a

    standalone label printer.

    CASE STUDIES FOR SCHEMATIC 7 – DISTRIBUTION

     X Focus – Order preparation (picking & transit packaging)

     An admixture of boxes of labels was found on receipt by the customer

    caused by a picking error made due to poor warehouse lighting and lack

    of a double check. In another incident an admixture of batch of cartons

    occurred, caused by a picking error due to poor batch segregation in

    the warehouse. Both batch defectives were found during the customer’s

    receipt checking, but they caused disruption to the product scheduling

    programmes because of the need to return the material to the supplier for

    sorting/replacement. The corrective and preventive actions, in both cases,

    involved a fundamental review of the conditions (and checks made) in the

    warehouse and implementation of improved lighting and segregation mea-

    sures.

     Y Focus – Despatch area/goods check & documentation

    Despatch note details accompanying the delivery differed from physical

    quantity delivered. This resulted in delays in product release and schedul-

    ing disruption while the supplier was contacted. The supplier’s despatch

    checking procedures were reviewed, no fundamental weaknesses were

    found. In this case, a one-off error had occurred and the issue was dis-

    cussed with the individual concerned.

    Z Focus – Transport to the customer

    Goods were damaged in transit due to movement of the load and inade-

    quate control while the vehicle was being loaded. In another incident, goods

    were damaged by water penetration due to a poorly closed and maintained

    “curtain” of a flexible sided vehicle. Both examples resulted in the need for

    product inspection at the customer, and the return of damaged material to

    the supplier leaving too few components to meet requirements. In the first

    case, the checks made on loading were increased and in the second exam-

    ple the company decided it was feasible to switch to hard sided vehicles to

    eliminate the risk of water penetration.

  • 8/18/2019 CGMP Complete

    49/128

    32

    Using the Case Studies - Guidance for Trainers

    Introduction

    The case studies that have been described here can be used as valuable aides to

    training programmes, for use either by a supplier or a pharmaceutical company. It

    is recommended that you select one or more of the case studies that are appro-

    priate to your business and design an activity that will encourage your trainees to

    discuss the particular subject you would like them to understand. An example of a

    training exercise protocol is provided below based on a case study selected from

    Schematic No. 3. Developing a short set of questions similar to those illustrated

    below should help improve understanding. It will probably be beneficial if such Q &

     A sets were developed jointly after discussion between pharmaceutical customers

    and their suppliers.

    It will certainly be helpful to provide explanations and visual aides relevant to the

    case study. For example in the example illustrated below it would be helpful if:

    i) For a laminate that you use or manufacture explain which illness(es) the tablets,

    that are packed within it, are used to treat.

    ii) A copy of an analogous page of a Product Authorisation (Licence) was shown

    and the legal basis of such licences explained.

    iii) The function of PVDC in the laminate was explained.

    Training Exercise

    Case study No. C

    Title: Mix-up in the weight of PVDC on a PVC based blister film

    In this case study, the wrong material was ordered from the factory.

    Nomally, orders were placed for 40 micron PVDC coated PVC (for tablet

    blister packing) - and etc.

    Training objectives

    Discuss the case study in groups and decide your answers to the following ques-

    tions:

    Q 1. Which requirement(s) of PS 9000 do you consider had not been effectively

    implemented?

      State the clause numbers and your reasons.

  • 8/18/2019 CGMP Complete

    50/128

    33

    Q 2. Why do you think that the thickness of the PVDC could affect the stability of

    the tablets that were to be packed in the laminate?

     

    Q 3. If this mistake had not been detected what do you think the implications

    might have been to:

      i) The manufacturer of the laminate film?

      ii) The pharmaceutical customer?

  • 8/18/2019 CGMP Complete

    51/128

    34

  • 8/18/2019 CGMP Complete

    52/128

    35

    The Institute of Quality Assurance

    Pharmaceutical Quality Group

    PS 9004

     

    A Guide to the GMP requirements

    of PS 9000:2001 Pharmaceutical packaging materials

    PART 2 - GUIDANCE ON PS 9000 GMP CLAUSES

      PS 9000 GMP related text is reproduced in blue

  • 8/18/2019 CGMP Complete

    53/128

    36

  • 8/18/2019 CGMP Complete

    54/128

    37

       G  e  n  e  r  a   l  s  y  n  o  p  s   i  s  -   C   l  a  u

      s  e   4   Q  u  a   l   i   t  y  m  a  n  a  g  e  m  e  n   t  s  y  s   t  e  m

       A   Q   M   S  p  r  o  v   i   d  e  s  a   b  a  s   i  s   f  o

      r  c  o  n   t   i  n  u  o  u  s   i  m  p  r  o  v  e  m  e  n   t  o   f   t   h  e  o  r  g  a  n   i  z  a   t   i  o  n   ’  s  e   f   f  e  c   t   i  v  e  n  e  s  s  a  n   d  e   f   f   i  c   i  e  n  c

      y ,  w   h   i   l  s   t  s   t   i   l   l  c  o  n  s   i   d  e  r   i  n  g

       t   h  e  v  a  r   i  o  u  s  n  e  e   d  s  o   f  a   l   l  s   t

      a   k  e   h  o   l   d  e  r  s   (  e .  g .  c  u  s   t  o  m  e  r  s ,  s  u  p  p   l   i  e  r  s ,   i  n  v  e  s   t  o  r  s ,  e  m  p   l  o  y  e  e  s   ) .

       C   l  a  u  s  e   4 .   1   G  e  n  e  r  a

       l  r  e  q  u   i  r  e  m  e  n   t  s

       D  e   t  a   i   l  e   d  c  o  n  s   i   d  e  r  a   t   i  o  n   i  s  r  e  q  u   i  r  e   d  o   f   t   h  e  n  e  e   d  s  o   f  s   t  a   k  e   h  o   l   d  e  r  s ,

       t   h  e  p

      r  o  c  e  s  s  e  s   t  o  m  e  e   t   t   h  o  s  e  n  e  e   d  s  a  n   d   t  o  m  e

      a  s  u  r  e  p  e  r   f  o  r  m  a  n  c  e .

       T   h  e  r  e  a  r  e  n  o   ‘  e  x   t  r  a   ’   P   S   9   0   0

       0   G   M   P  s  w   i   t   h   i  n   t   h   i  s  c   l  a  u  s  e .

       T   h  e  r  e  a  r  e   i  m  p  o  r   t  a  n   t   G   M   P  p  r   i  n  c   i  p   l  e  s   i  n   t   h   i  s  a  r  e  a ,

       b  u   t   t   h  e

      y  a  r  e  a   d  e  q  u  a   t  e   l  y

      e  x  p  r  e  s  s  e   d   i  n   I   S   O   9   0   0   1  a  n   d

       I   S   O   9   0   0   4 .

       P  r  o  c  e  s  s   i  n  p  u   t  s

        P  r  o  c  e  s  s  e  s

       P  r  o  c  e  s  s  o  u   t  p  u   t  s  a  n   d

      e  v   i   d  e  n  c  e

       C  r  o  s  s  r  e   f  e  r   t  o

       S  c   h  e  m  a   t   i  c   /   A  n  n  e  x

      •

       I   d  e  n   t   i   f   i  e   d  p  r  o  c  e  s  s  e  s

       t   h  a   t  m  e  e   t  o  r  g  a  n   i  z  a   t   i  o  n

      s   t  r  a   t  e  g   i  c  o   b   j  e  c   t   i  v  e  s

      •

       C  u  s   t  o  m  e  r  r  e  q  u   i  r  e  m  e  n   t  s

      •

       R  e  g  u   l  a   t  o  r  y

      r  e  q  u   i  r  e  m  e  n   t  s

       P  r  o  c  e  s  s  e  s  w   h   i  c   h  :

      •

       d  e   f   i  n  e ,

       i  m  p   l  e  m  e  n   t  a  n   d  m  a   i  n   t  a   i  n   Q   M   S

      p  r  o  c  e  s  s  e  s   (   i  n  c   l  u   d   i  n  g  m  a  n  a  g  e  m  e  n   t

      a  n   d

      o  p  e  r  a   t   i  o  n  a   l  a  c   t   i  v   i   t   i  e  s   )

      •

       d  e   t  e  r  m   i  n  e  p  e  r  s  o  n  n  e   l  r  e  q  u   i  r  e   d   t  o  c  a  r  r  y  o  u   t

      p  r  o  c  e  s  s  e  s  a  n   d   t  r  a   i  n   i  n  g  n  e  e   d  s

      •

      p  r  o  v   i   d  e  p  r  e  m   i  s  e  s  a  n   d  e  q  u   i  p  m  e  n   t   f

      o  r   t   h  e

      p  r  o  c  e  s  s  e  s

      •

       d  e   f   i  n  e  a  n   d   i  m  p   l  e  m  e  n   t  c  o  n   t  r  o   l  s   t  o  m  e  a  s  u  r  e

      p  e  r   f  o  r  m  a  n  c  e  o   f   Q   M   S  p  r  o  c  e  s  s  e  s   i  n

      c   l  u   d   i  n  g

      o  u   t  s  o  u  r  c   i  n  g

      •

       W  r   i   t   t  e  n  p  r  o  c  e   d  u  r  e  s

      e  s  s  e  n   t   i  a   l   t  o

       Q  u  a   l   i   t  y   S  y  s   t  e  m

      •

       O  r  g  a  n   i  z  a   t   i  o  n  s   t  r  u  c   t  u  r  e

       t   h  a   t  s  u  p  p  o  r   t  s   Q   M   S

      •

       A   d  e  q  u  a   t  e  p  r  e  m   i  s  e  s

      a  n   d  e  q  u   i  p  m  e  n   t

      •

       D  a   t  a   f  r  o  m  p  r  o  c  e  s  s  e  s

      a  n   d  m  e  a  s  u  r  e  m  e  n   t

      s  y  s   t  e  m  s

       S  c   h  e  m  a   t   i  c   1

  • 8/18/2019 CGMP Complete

    55/128

    38

       C   l  a  u  s  e   4 .   2   D  o  c  u  m  e  n   t  a   t   i  o  n  r  e  q  u   i  r  e  m  e  n   t  s

       D  o  c  u  m  e  n   t  a   t   i  o  n   i  s  a   f  u  n   d  a  m  e  n   t  a   l  p  a  r   t  o   f   t   h  e   Q   M   S   t   h  a   t   d  e   f   i  n  e  s  w   h  a   t   t   h  e  o  r  g  a  n   i  z  a   t   i  o  n   d  o  e  s ,  p  r  o  v   i   d  e  s   t  r  a  c  e  a   b   i   l   i   t  y  a  n   d  e  v   i   d  e  n  c  e  o   f   i   t  s

      a  c   t   i  v   i   t   i  e  s .

       R  e  a  s  o  n  s   f  o  r   t   h  e   ‘  e  x   t  r  a   ’   G   M

       P  r  e  q  u   i  r  e  m  e  n   t  s   (  r  e   f  e  r   t  o   P   S   9   0   0   0  c   l  a  u

      s  e  s   4 .   2 .   2  ;   4 .   2 .   3  ;   4 .   2 .   4   )

       P   h  a  r  m  a  c  e  u   t   i  c  a   l  c  o  m  p  a  n   i  e  s

       h  a  v  e ,  o  n  o  c  c  a  s   i  o  n  s ,  e  x  p  e  r   i  e  n  c  e   d  p  r  o   b   l  e  m

      s   i  n   t   h  e  r  e   t  r   i  e  v  a   l  o   f  a  c  c  u  r  a   t  e   h   i  s   t  o  r   i  c  a   l   d  a   t  a   f  r  o  m  s  u  p  p   l   i  e  r  s  a  n   d

       t   h  e  s  e   h  a  v  e   b  e  e  n  a   t   t  r   i   b  u   t  e   d   t  o   i  n  a   d  e  q  u  a   t  e   d  a   t  a  s  y  s   t  e  m  v  a   l   i   d  a   t   i  o  n  a  n   d

       d  a   t  a  c  o  n   t  r  o   l  s .

       T   h  e  p  r  o  c  e  s  s  r  e   f  e  r  e  n  c  e  s  a   b

      o  v  e  a  r  e  p  a  r   t  o   f  a  s  y  s   t  e  m

      o   f   d  a   t  a   t  r  a  c  e  a   b   i   l   i   t  y   t   h  a   t  c  a  n

      p  r  o  v   i   d  e  a  c  o  m  p   l  e   t  e   h   i  s   t  o  r  y  o   f   t   h  e  c  o  m  p  o  n  e  n   t   ’  s  m  a  n  u   f  a  c   t  u  r  e .

       T   h   i  s  c  a  n   b  e  v   i   t  a   l   l  y   i  m

      p  o  r   t  a  n   t   i   f   t   h  e  r  e   i  s  a

      p  r  o   b   l  e  m   i  n   t   h  e  u  s  e  o   f   t   h  e  p   h

      a  r  m  a  c  e  u   t   i  c  a   l  p  r  o   d  u  c   t   i  n   t   h  e  m  a  r   k  e   t  p   l  a  c  e .

       T   h  e  p   h  a  r  m  a  c  e  u   t   i  c  a   l  c  o  m  p  a  n  y   h  a  s  a  r  e  g  u   l  a   t  o  r  y  o   b   l   i  g  a   t   i  o  n   t  o  r  e   t  a   i  n  p  r  o   d  u  c   t   i  o  n  a  n   d  p  a  c   k   i  n  g   d  a   t  a   f  o  r  o  n  e  y  e  a  r   b  e  y  o  n   d   t   h  e  s   h  e   l   f  -   l   i   f  e  o   f

       t   h  e  p  r  o   d  u  c   t .   T   h  e  r  e   i  s   t   h  e  r  e   f  o  r  e  a  c  o  r  r  e  s  p  o  n   d   i  n  g  r  e  s  p  o  n  s   i   b   i   l   i   t  y   (  s  e  e   A  n

      n  e  x   B   )  u  p  o  n   t   h  e  c  o  m  p  o  n  e  n   t  s  u  p  p   l   i  e  r   t  o  e

      s   t  a   b   l   i  s   h  a  n   d  m  a   i  n   t  a   i  n

      a  c  c  u  r  a   t  e  a  n   d  s  e  c  u  r  e   d  a   t  a  c  o  n   t  r  o   l  a  n   d  r  e   t  e  n   t   i  o  n  s  y  s   t  e  m  s .

       P  r  o  c  e  s  s   i  n  p  u   t  s

        P  r  o  c  e  s  s  e  s

       P  r  o  c  e  s  s  o  u   t  p  u   t  s  a  n   d

      e  v   i   d  e  n  c  e

       C  r  o  s  s  r  e   f  e  r   t  o

       S  c   h  e  m  a   t   i  c   /   A  n  n  e  x

      •

       D  o  c  u  m  e  n   t  s   t   h  a   t  n  e  e   d

       t  o   b  e  c  o  n   t  r  o   l   l  e   d

      •

       S   t  a  n   d  a  r   d  s  a  n   d

      r  e  g  u   l  a   t  o  r  y  r  e  q  u   i  r  e  m  e  n   t  s

      •

       C  u  s   t  o  m  e  r  r  e  q  u   i  r  e  m  e  n   t  s

       (  s  p  e  c   i   f   i  e   d  a  n   d

      u  n  s  p  e  c   i   f   i  e   d   )

      •

       R  e  s  p  o  n  s   i   b   i   l   i   t   i  e  s   f  o  r

       d  o  c  u  m  e  n   t  s   (  e .  g .

      a  u   t   h  o  r  s ,  a  p  p  r  o  v  e  r  s ,

      e   t  c .   )

      •

       P  r  o  c  e  s  s  m  a  p  s

       P  r  o  c  e  s  s  e  s  w   h   i  c   h  :

      •

      c  o  n   t  r  o   l   t   h  e   d  o  c  u  m  e  n   t  a  n   d   d  a   t  a  m  a

      n  a  g  e  m  e  n   t

       f  o  r  a  n  y  m  e   d   i  a   t  y  p  e   t  o  c  o  v  e  r   l   i   f  e  -  c  y

      c   l  e

      •

      e  n  s  u  r  e   t   h  e  s  e  c  u  r   i   t  y  o   f  e   l  e  c   t  r  o  n   i  c   d  o  c  u  m  e  n   t  s   i  s

      e  q  u  a   l   t  o   t   h  a   t  o   f  p  a  p  e  r   d  o  c  u  m  e  n   t  s

      •

      p  r  o  v   i   d  e  a  u   d   i   t   t  r  a   i   l   f  o  r  e   l  e  c   t  r  o  n   i  c   d  o

      c  u  m  e  n   t  s  a  n   d

       d  a   t  a

      •

      c  o  n   t  r  o   l   b  a  c   k  u  p  a  n   d  r  e  c  o  v  e  r  y  o   f   d  a

       t  a

      •

      c  o  n   t  r  o   l  v  a   l   i   d  a   t   i  o  n  o   f   h  a  r   d  w  a  r  e   /  s  o   f   t  w  a  r  e  u  s  e   d

       f  o  r   d  o  c  u  m  e  n   t  a  n   d   d  a   t  a  m  a  n  a  g  e  m  e

      n   t

      •

      c  o  n   t  r  o   l  a  r  c   h   i  v   i  n  g   /  r  e   t  e  n   t   i  o  n  o   f   d  o  c  u

      m  e  n   t  s  a  n   d

       d  a   t  a

      •

       d  e   f   i  n  e   t   h  e  e  x   t  e  n   t   t  o  w   h   i  c   h   P   S   9   0   0   0  a  p  p   l   i  e  s

      w   i   t   h   i  n   t   h  e   Q   M   S

      •

       Q  u  a   l   i   t  y  m  a  n  u  a   l

      •

       P  r  o  c  e   d  u  r  e  s   t   h  a   t

      s  u  p  p  o  r   t   t   h  e   d  o  c  u  m  e  n   t

      a  n   d   d  a   t  a  m  a  n  a  g  e  m  e  n   t

      s  y  s   t  e  m

      •

       C   l  e  a  r  a  c  c  o  u  n   t  a   b   i   l   i   t   i  e  s

      a  n   d  r  e  s  p  o  n  s   i   b   i   l   i   t   i  e  s

       R  e  c  o  r   d  s  o   f  :

      •

       d  o  c  u  m  e  n   t  a   t   i  o  n

      c   h  a  n  g  e  s

      •

       t  r  a   i  n   i  n  g

      •

      v  a   l   i   d  a   t   i  o  n

       S  c   h  e  m  a   t   i  c   3

       S  c   h  e  m  a   t   i  c   4

       S  c   h  e  m  a   t   i  c   5

       S  c   h  e  m  a   t   i  c   6

       A  n  n  e  x   B

  • 8/18/2019 CGMP Complete

    56/128

    39

       G  e  n  e  r  a   l   S  y  n  o  p  s   i  s  -   C   l  a  u

      s  e   5   M  a  n  a  g  e  m  e  n   t  r  e  s  p  o  n  s   i   b   i   l   i   t  y

       M  a  n  a  g  e  m  e  n   t   ’  s  r  e  s  p  o  n  s   i   b   i   l   i   t  y   t  o  e  n  s  u  r  e  a  n  e   f   f  e  c   t   i  v  e   Q   M   S  w   h   i  c

       h  r  e  c  o  g  n   i  s  e  s   t   h  e  n  e  e   d  s  o   f   t   h  e  o  r  g  a  n   i  z  a   t   i  o  n ,  c  u  s   t  o  m  e  r  s  a  n   d

      o   t   h  e  r   k  e  y  s   t  a   k  e   h  o   l   d  e  r  s .

       C   l  a  u  s  e   5 .   1   M  a  n  a  g  e  m

      e  n   t  c  o  m  m   i   t  m  e  n   t

       T  o  p  m  a  n  a  g  e  m  e  n   t   d  e   f   i  n  e  s   t   h

      e  o  r  g  a  n   i  z  a   t   i  o  n   ’  s  s   t  r  a   t  e  g  y  a  n   d   i  s  r  e  s  p  o  n  s   i   b

       l  e   f  o  r   d  e  m  o  n  s   t  r  a   t   i  n  g  c  o  m  m   i   t  m  e  n   t   t  o   t   h  e   Q   M   S .

       C  o  n   t   i  n  u  a   l

       i  m  p  r  o  v  e  m  e  n   t  o   f   t   h  e  s  y  s   t  e  m

      a  n   d   i   t  s  p  r  o  c  e  s  s  e  s  a  r  e  n  e  c  e  s  s  a  r  y   t  o  e  n  s  u  r  e  c  u  s   t  o  m  e  r  a  n   d  r  e  g  u   l  a   t  o  r  y  n  e  e   d  s  a  r  e   f  u   l   l  y

      s  a   t   i  s   f   i  e   d .

       T   h  e  r  e  a  r  e  n  o   ‘  e  x   t  r  a   ’   P   S   9   0   0

       0   G   M   P   ’  s  w   i   t   h   i  n   t   h   i  s  c   l  a  u  s  e .

       T   h  e  r  e  a  r  e   i  m  p

      o  r   t  a  n   t   G   M   P  p  r   i  n  c   i  p   l  e  s   i  n   t   h   i  s  a  r  e  a ,

       b  u   t   t   h  e  y  a  r  e  a   d  e  q  u  a   t  e   l  y

      e  x  p  r  e  s  s  e   d   i  n   I   S   O   9   0   0   1  a  n   d

       I   S   O   9   0   0   4 .

       P  r  o  c  e  s  s   i  n  p  u   t  s

       P  r  o  c  e  s  s  e  s

       P  r  o  c  e  s  s  o  u   t  p  u   t  s  a  n   d

      e  v   i   d  e  n  c  e

       C  r  o  s  s  r  e   f  e  r   t  o

       S  c   h  e  m  a   t   i  c   /   A  n  n  e  x

      •

       C  o  m  p  a  n  y  s   t  r  a   t  e  g  y   /

      p  u  r  p  o  s  e

      •

       A   d  e  q  u  a   t  e  r  e  s  o  u  r  c  e  s   t  o

      m  e  e   t  r  e  q  u   i  r  e  m  e  n   t  s

       P  r  o  c  e  s  s  e  s  w   h   i  c   h  :

      •

      e  s   t  a   b   l   i  s   h  q  u  a   l   i   t  y  p  o   l   i  c  y

      •

      e  s   t  a   b   l   i  s   h  q  u  a   l   i   t  y  o   b   j  e  c   t   i  v  e  s

      •

      r  e  q  u   i  r  e  a   M  a  n  a  g  e  m  e  n   t   R  e  v   i  e  w  a  s  a  m  e  a  n  s  o   f

      c  o  n   t   i  n  u  a   l   i  m  p  r  o  v  e  m  e  n   t

      •

      e  n  s  u  r  e  s   t   h  e  c  o  m  m  u  n   i  c  a   t   i  o  n  w   i   t   h  s   t  a   f   f   t  o   h  e   l  p

       t   h  e  m  u  n   d  e  r  s   t  a  n   d  a  n   d  c  o  n   t  r   i   b  u   t  e   t  o

       Q   M   S

       i  m  p   l  e  m  e  n   t  a   t   i  o  n   (  e .  g .  c  o  n   t   i  n  u  o  u  s   i  m

      p  r  o  v  e  m  e  n   t

      o   b   j  e  c   t   i  v  e  s ,  c  u  s   t  o  m  e  r  s  a   t   i  s   f  a  c   t   i  o  n   t  a  r  g  e   t  s ,  e   t  c .   )

      •

       E  v   i   d  e  n  c  e  o   f  s   t  a   f   f

      u  n   d  e  r  s   t  a  n   d   i  n  g  a  n   d

      c  o  m  m   i   t  m  e  n   t

      •

       C  u  s   t  o  m  e  r  s  a   t   i  s   f  a  c   t   i  o

      n

      m  e  a  s  u  r  e  s

       C   l  e  a  r   l  y   d  o  c  u  m  e  n   t  e   d  :

      •

      q  u  a   l   i   t  y  p  o   l   i  c  y

      •

      q  u  a   l   i   t  y  o   b   j  e  c   t   i  v  e  s

      •

       i  m  p  r  o  v  e  m  e  n   t  p   l  a  n  s

       S  c   h  e  m  a   t   i  c   1

  • 8/18/2019 CGMP Complete

    57/128

    40

       C   l  a  u  s  e   5 .   2   C  u  s   t  o  m  e  r   f  o  c  u  s

       A   k  e  y  r  e  q  u   i  r  e  m  e  n   t   t  o  p  r  o  v   i   d

      e  s  u   i   t  a   b   l  e  p  r  e  m   i  s  e  s ,  p  e  o  p   l  e ,  a  n   d  p  r  o  c  e  s  s  e  s ,

       i  n  o  r   d  e  r   t  o  e  n   h  a  n  c  e  c  u  s   t  o  m  e  r  s  a   t   i  s   f  a  c

       t   i  o  n .

       R  e  a  s  o  n  s   f  o  r   t   h  e   ‘  e  x   t  r  a   ’   G   M

       P  r  e  q  u   i  r  e  m  e  n   t  s

       P   h  a  r  m  a  c  e  u   t   i  c  a   l   I  n   d  u  s   t  r  y  e  x  p  e  r   i  e  n  c  e  s   h  o  w  s   t   h  a   t   f  r  o  m   t   h  e  p  r  o   d  u  c   t   d  e  v

      e   l  o  p  m  e  n   t  s   t  a  g  e  o  n  w  a  r   d  s ,  c  o  m  p   l   i  a  n   t  p   h  a  r

      m  a  c  e  u   t   i  c  a   l  q  u  a   l   i   t  y

      r  e  q  u   i  r  e  s   f  a  c   i   l   i   t   i  e  s  a  n   d  s   t  a   f   f   t  o   b  e   ‘   f   i   t   f  o  r  p  u  r  p  o  s  e   ’ ,   i .  e .

       ‘  s  u   i   t  a   b   l  e   f  a  c   i   l   i   t   i  e  s  a  n   d  c  o  m  p  e   t  e  n   t  s   t  a   f   f   ’ ,  a  n   d   t   h  a   t   t   h   i  s   G   M   P

      r  e  q  u   i  r  e  m  e  n   t   i  s  e  q  u  a   l   l  y

      a  p  p   l   i  c  a   b   l  e   t  o   t   h  e  s  u  p  p   l   i  e  r  o   f  p   h  a  r  m  a  c  e  u   t   i  c  a   l  p  a  c   k  a  g   i  n  g  c  o  m  p  o  n  e  n   t  s .

       P  r  o   d  u  c   t  s  e  c  u  r   i   t  y  a  n   d   t   h  e  a  v  o   i   d  a  n  c  e  o   f  c  r  o  s  s  c  o  n   t  a  m   i  n  a   t   i  o  n  u  n   d  e  r  p   i  n  s  a   l   l  p   h  a  r  m  a  c  e  u   t   i  c  a   l  q  u  a   l   i   t  y ,  s   i  n  c  e   t   h  e  s  e  a  r  e   b  a  s   i  c   i  s  s  u  e  s   t   h  a   t  c  a  n

       l  e  a   d   t  o  p  e  o  p   l  e   t  a   k   i  n  g   t   h  e  w  r  o  n  g  m  e   d   i  c   i  n  e ,

       d  a  m  a  g   i  n  g   t   h  e  p   h  a  r  m  a  c  e  u   t   i  c  a   l  c  o  m  p  a  n  y   ’  s   b  u  s   i  n  e  s  s ,  a  n   d  p  u   b   l   i  c  c  o  n   f   i   d  e  n  c  e   i  n   i   t .

       (   S  e  e  a   l  s  o

       A  n  n  e  x   A ,

       ‘   C  o  u  n   t  e  r   f  e   i   t   ’   t   h  a   t  c  o  v  e  r  s   i  n   d  e   t  a   i   l   t   h  e  n  e  e   d  s   f  o  r  c  o  n   t  r  o   l  s   i  n  a

      r  e  a  s   i  n  v  o   l  v   i  n  g   d   i  s  p  o  s  a   l  o   f  a  r   t  w  o  r   k ,  p  r  o  c  e  s  s   d  e   f  e  c   t   i  v  e  s  a  n   d  w  a  s   t  e

      m  a   t  e  r   i  a   l  s ,  e   t  c .   ) .

       B  e  g   i  n  n�