Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
This procedure outlines the system of control and inspections to be adopted for the fixing
on site of tiles and mosaics.
PROJECT: PROJECT NAME
SECTION:
FINISHING
DATE OF ISSUE
Dec. 2012
SUBJECT:BY:
QA/QC ENGINEER
Ceramic Tiles, Terrazzo Tiles
And Mosaics Method
Statement
APPROVED BY:
QEHS MANAGER
ACTIONVERIFY
1. SCOPE
This procedure outlines
the system of control
and inspections to be
adopted for the fixing on
site of tiles and mosaics.
2. PROCEDURE
.1 A method
statement shall be
prepared and
approved. It shall
include:
i) Acceptance
conditions for
laying e.g.
Project
Manager
Project
Engineer
Store-
keeper
Project
Manager
Method
Statement
Sample
approval
Instructions
FINI/05/A
FINI/05/A
maximum
moisture content
of substrate,
levelness,
soundness,
cleanliness,
environment.
ii) Surface
preparation and
bonding e.g.
bonding agent,
bed mix
proportions,
adhesives.
iii) Specific
requirements with
regard to setting
out, alignment of
joints and cutting.
iv) Method of
protecting finished
work.
v) Source
documents for
tiles, adhesive
.2 A sample of tiles
shall be prepared on the
wall in accordance with
the specifications laid
Project
Engineer
down in the contract and
approved by the
Consultant.
.3 Storage of tiles:
i) Tiles shall be
delivered to site
palletised, on a
clean hard
surface free from
contamination by
mud or surface
water.
ii) Ensure that
manufacturer’s
instructions in
respect of storage
conditions of
adhesives are
strictly followed.
.4 The Project
Director/Manager or his
designate will confirm
that materials are in
compliance with contract
specification
requirements.
.5 In the case of
internal wall tiling, work
will not proceed until all
concealed conduits,
pipes, electrical cables
and boxes etc. that
penetrate the tiling have
been fixed securely in
position and making
good is complete. Obtain
written clearance from
MEP Co-ordinator that
all their works in that
area is clear for taking
up the tiling work.
PROJECT: PROJECT NAMERef No. FINI/05
PAGE 2 OF 3
SECTION:
FINISHING
DATE OF ISSUE
Dec. 2012
SUBJECT:BY:
QA/QC ENGINEER
CERAMIC TILES, TERRAZZO
TILES AND MOSAICS
APPROVED BY:
QEHS MANAGER
ACTIONVERIFY
.6 Site operatives must
observe the following while
fixing tiles in addition to the
specifications laid down in the
contract document.
Gen.
Foreman
FINI/05/A
FINI/05/A
i) In the case of
internal wall tiles, the
setting out course or
layout course is
established.
ii) The level and
events of the wall
surface should not
exceed the allowable
tolerance as specified
in the contract. Any
such defect should be
rectified before
proceeding further.
iii) While setting out
for floor tiling, establish
a datum level for the
finished floor and
control the overall level
of the finished floor by
means of series of spot
levels. The Site
Engineer will involve
Consultant’s
representative while
fixing levels.
iv) Avoid cutting tiles
as far as possible. If
cutting cannot be
avoided locate cut tiles
where they will be least
Gen.
Foreman
noticeable, if in doubt
refer to specification.
v) The sequence of
fixing tiles shall be as
follows unless specified
otherwise in the
contract:
Floor tiles – from
the centre of room
Internal walls –
Upward from the
setting out course
up to the specified
height (in case of
false ceiling)
otherwise from top
and downwards up
to starting level.
External walls –
always from top to
bottom covering one
horizontal strip after
another but
preferably to be
done in bays.
vi) The mortar or adhesive is
spread on the surface using a trowel
or blade in thin layers as specified.
vii) Before placing the
next tile take care to
allow correct joint width
by placing the correct
spacers in all corner
joints.
viii) Do not start joint
grouting work till tiles
are properly fixed to the
surface. Normally the
time period varies
between 24 hrs to 48
hrs.
.7 Protection and
Cleaning:
i) Protect external
tiling and mosaics from
rain and sun until the
bed and joints have set.
Continue the protection
for the period specified.
PROJECT: PROJECT NAMERef No. FINI/05
PAGE 3 OF 3
SECTION:
FINISHING
DATE OF ISSUE
Dec. 2012
SUBJECT:BY:
QA/QC
ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS
APPROVED BY:
QEHS MANAGER
ACTIONVERIFY
ii) Do not allow tiling and mosaics to be
wetted in shower bath areas for the period
as specified, until the bedding and joints
have set and hardened.
iii) Do not permit any traffic at all on the
flooring till the tiles are set afterwards
permit light foot traffic only.
iv) For general protection spread white
no-staining saw dust over the floor but not
earlier than the period during which grout is
hardened.
PROJECT: PROJECT NAME SITE NO.:
CERAMIC TILES, TERRAZZO TILES AND MOSAICSSheet No.
SUBCONTRACTOR: CLIENT
SECTION OF WORK ____________________________LOCATION
_________________
STAGEITEM
Checked
by
DATE
PREPARATION1. Method statement approved.PE
2. Materials to specification (including suitability of adhesive).SE
3. Check storage condition of materials.
SK
4. Establish line and level.SU5. Check moisture content of substrate.
GF
6. Liaise with MEP section for completion of their works.PE/MEP
7. Acceptance of substrateGF
8. Sample area acceptable.PE
APPROVAL TO PROCEED WITH
LAYINGQA/QC
INSTALLATION9. Check setting-outSU
10. Check line and level.SU
11. Check mixing, colour and
application of grout.GF
12. Check sequence of fixing tiles.SE
APPROVAL TO PROCEEDQA/QC
POST13. Check initial cleaning of work.GF
INSTALLATION14. Check protection applied correctly.
GF
APPROVAL TO PROCEEDCM