34
Translated Document AFRICAN DEVELOPMENT BANK GROUP CAMEROON PUBLIC EXPENDITURE EFFICIENCY IMPROVEMENT SUPPORT PROJECT (PAEDEP) APPRAISAL REPORT OSGE/GECL October 2016 Public Disclosure Authorized Public Disclosure Authorized

CAMEROON - afdb.org

  • Upload
    others

  • View
    15

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CAMEROON - afdb.org

Translated Document

AFRICAN DEVELOPMENT BANK GROUP

CAMEROON

PUBLIC EXPENDITURE EFFICIENCY IMPROVEMENT

SUPPORT PROJECT (PAEDEP)

APPRAISAL REPORT

OSGE/GECL October 2016

Publi

c D

iscl

osu

re A

uth

ori

zed

Publi

c D

iscl

osu

re A

uth

ori

zed

Auth

ori

ezd A

uth

ori

zed

Page 2: CAMEROON - afdb.org

TABLE OF CONTENTS

I – Strategic Thrust and Rationale 1

1.1. Project Linkage to Country Strategy and Objectives .................................................. 1

1.2. Rationale for Bank Involvement ................................................................................. 1

1.3. Aid Coordination ......................................................................................................... 4

II - Project Description 4

2.1 Project Components .................................................................................................... 4

2.2 Technical Solutions Adopted and Alternative Solutions Considered ......................... 6

2.3 Type of Project ............................................................................................................ 6

2.4 Project Cost and Financing Mechanisms .................................................................... 7

2.5 Project Area and Beneficiaries .................................................................................... 8

2.6 Participatory Approach to Identification, Design and Implementation ...................... 8

2.7 Bank Group Experience and Lessons Reflected in Project Design ............................ 9

2.8 Key Performance Indicators ...................................................................................... 10

III - Project Feasibility 10

3.1 Economic and Financial Performance....................................................................... 10

3.2 Environmental and Social Impact ............................................................................. 11

IV – Implementation 12

4.1 Implementation Arrangements .................................................................................. 12

4.2 Monitoring ................................................................................................................. 14

4.3 Governance................................................................................................................ 14

4.4 Sustainability ............................................................................................................. 14

4.5 Risk Management ...................................................................................................... 15

4.6 Knowledge Development .......................................................................................... 15

V – Legal Framework 15

5.1 Legal Instrument ....................................................................................................... 15

5.2 Conditions Associated with the Bank’s Intervention ................................................ 16

5.3 Conformity with Bank Policies ................................................................................. 16

VI – Recommendation 16

Annex 1: Comparative Socio-economic Indicators of the DRC I

Annex 2: Analysis of the Bank’s Active Portfolio as of 30 June 2016 II

Annex 3: Summary Table of Donor Operations III

Annex 4: Justification of the Government Counterpart Contribution Amount V

Annex 5: Map of the Project Area VIII

Page 3: CAMEROON - afdb.org

Table 2.1-1 : Project Components and Cost Estimates .............................................................. 5

Table 2.4-1 : Estimated Project Cost by Component ................................................................. 7

Table 2.4-2 : Estimated Project Costs by Financing Source ...................................................... 7

Table 2.4-3 : Project Cost by Expenditure Category ................................................................. 8

Table 2.4-4 : Expenditure Schedule by Component .................................................................. 8

Page 4: CAMEROON - afdb.org

i

Acronyms and Abbreviations

ADF African Development Fund

AER Rural Electrification Agency

ADB (loan) African Development Bank (loan)

AfDB African Development Bank Group

ARMP Public Procurement Regulatory Authority

ARSEL Electricity Sector Regulatory Agency

CONSUPE Supreme State Control

CSFP Sectoral Committee on Public Finance

DGEPIP General Directorate for the Economy and Public Investment Programming

EDC Electricity Development Corporation

FEICOM Special Council Development Fund

GDP Gross Domestic Product

GESP Growth and Employment Strategy Paper

HDI Human Development Index

ICTs Information and Communication Technologies

IDEV Independent Development Evaluation

IMF International Monetary Fund

INTOSAI International Organization of Supreme Audit Institutions

MINEE Ministry of Energy and Water Resources

MINEPAT Ministry of the Economy, Planning and Regional Development

MINMAP Ministry of Public Contracts

MINTP Ministry of Public Works

PAP Priority Action Programme

PEFA Public Expenditure and Financial Accountability

PFMP Public Finance Modernization Plan

PIB Public Investment Budget

PPBME Planning, Programming, Budgeting, Monitoring and Evaluation

PSD Country Strategy Paper

RF Road Fund

RMF Road Maintenance Fund

SME Small and Medium-sized Enterprises

SONATREL National Electricity Transmission Company

TFP Technical and Financial Partners

UA Unit of Account

UNCTAD United Nations Conference on Trade and Development

WB World Bank

Currency Equivalents

July 2016

Monetary unit = CFA Franc (XAF)

UA 1 = XAF 826.499

UA 1 = EUR 1.25999

1 UA = USD 1.39884

Fiscal Year

[1st January – 31st December]

Page 5: CAMEROON - afdb.org

ii

Project Information Sheet

Client Information

BORROWER: Republic of Cameroon

EXECUTING AGENCY: Ministry of the Economy, Planning and Regional Development

(MINEPAT) through the Directorate General for the Economy

and Public Investment Programming (DGEPIP)

Financing Plan

Source Amount (UA) Instrument

ADF UA 11,210,000 Loan

ADB EUR 14,200,000 (UA 11,269,931) Loan

Government XAF 860,000,000 (UA 1,040,533)

TOTAL COST UA 23.520.464

Key ADB and ADF Financial Information (blend country)

ADB loan* ADF loan

Loan/Grant currency EUR UA

Interest Type Floating Fixed

Interest Rate Margin*

0.80% + Bank funding

margin + maturity

premium**

1%

Service commission Not applicable 0.75% per year of the disbursed

loan amount not reimbursed

Commitment fee Gradual from 0.25% to

0.75%

0.5% of the loan amount not

disbursed 120 days after signing

of the Loan Agreement

Other Expenses Not applicable Not applicable

Maturity 25 years 30 years

Grace period 8 years 5 years

Timeframe Half-yearly Half-yearly

FRR, NPV (baseline

scenario) Not Applicable Not Applicable

ERR (baseline scenario) Not Applicable Not Applicable

*PFT = Base rate + Funding margin + Lending spread + Maturity premium

**Maturity premium: The FFL introduces a maturity-based pricing structure and increases the maximum tenor of loans

and the grace period. Hence, for loans with Average Maturity above EVSL maximum Average Maturity, a maturity

premium is added to the applicable lending rate as follows:

If Average Maturity is < = 12.75, then No Maturity Premium is applied

If 12.75 < Average Maturity < = 15, then Maturity Premium = 10 bps

If 15 < Average Maturity < = 17, then Maturity Premium = 20 bps

Page 6: CAMEROON - afdb.org

iii

Duration – Milestones (projected)

Approval of the concept note

June 2015

Project appraisal August 2015

Project re-appraisal July 2016

Project approval November 2016

Effectiveness January 2017

Last disbursement 31 December 2020

Completion 30 March 2021

Last reimbursement / ADB loan December 2040

Last reimbursement / ADF loan December 2045

Page 7: CAMEROON - afdb.org

iv

Project Summary

General Project

Overview

Programme Title/ Number: Public Expenditure Efficiency Improvement Support Project (PAEDEP) /

SAP Code: P-CM-KA0-009

Geographical scope: National territory

Total Duration: 48 months (January 2017 – December 2020)

Funding: ADF loan: UA 11,210,000; ADB loan: EUR 14,200,000; Counterpart contribution: UA

1,040,533

Operational Instrument: Institutional support

Sector: Economic Governance

Project Outcomes

and Direct

Beneficiaries

The direct beneficiaries of project outcomes are the various Government services involved in planning,

budgeting and management of public investments (MINEPAT, MINFI, ARMP, MINMAP), as well as

technical structures tasked with the management of transport and energy infrastructure.

This project will improve the quality of projects designed under the Public Investment Programme and

consequently enhance the public investment budget implementation rate. These structures will benefit

from operational capacity building in strategic planning, project preparation and procurement.

Ultimately, the project will have an impact on economic growth, road maintenance and access to

electricity, by improving the quality of public investment expenditure in general, and in the

abovementioned two sectors in particular.

All beneficiaries contributed to the project’s design and are heavily involved in its implementation.

Needs Assessment

and Rationale

Over the past five years, Cameroon has embarked on an extensive public investment programme to

eliminate the main bottlenecks that hamper private sector development and economic growth. The

shortage of transport and energy infrastructure is indeed a major constraint to private sector development

and economic competitiveness. The poor level of project preparation is one of the main constraints to

the implementation of the public investment programme.

The Bank conducted a study on public investment management and expenditure reviews in the transport

and energy sectors. These studies revealed the institutional shortcomings that affect the quality of public

spending. Human and institutional capacity building needs were assessed based on these studies and

meetings with various structures.

Value-added of the

Bank

Over the past five years, the Bank has been the lead donor among the country’s technical and financial

partners meeting within the public finance sector committee. It has also been the lead donor for the

transport infrastructure sector since 2014. Studies conducted by the Bank on public investment

management and expenditure reviews have increased its knowledge of the areas covered by the project.

Consequently, the Bank has a comparative advantage in conducting reform dialogue in coordination

with the other TFPs. One of the major innovations of the project is support to the creation of a project

maturation fund and financing of the technical studies of backbone investment projects included in the

Government's emergency programme. Several departments within the Bank will be involved in

monitoring the project, namely the departments in charge of governance, transport, energy and the

Central Africa Region Department. The department in charge of fiduciary issues will also provide its

support.

Knowledge

Management

The project intends to conduct several studies, including a study on the privatization of road maintenance

management and the preparation of a renewable energy ATLAS. These studies will help to improve the

knowledge of the Bank and of all stakeholders. Moreover, they will be disseminated within the Bank

and at the national level and will form the basis for reforms and investments.

Page 8: CAMEROON - afdb.org

v

Project Implementation Schedule

Years

Activities / Months J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M

Prior to commencement

Board presentation

ADF loan effectiveness

ADB loan effectiveness

Recruitment of Coordinator and PMU

ExpertsEstablishment of PMU

Preparation of procedures manual

Project launching mission

Equipment and Supplies

Preparation of bidding documents

Launch of bidding process

Award and signature of contracts

Provision of assets and facilities

Consultancy services

Preparation of TORs and AMI

Preparation of short lists

Publication of requests for proposals

Procurement of consultancy services

Tech. assist.

Implementation of studies

Tech. assist.

Assist. Tech. ARMP

Tech. assist. MINEPAT

National consultants

Training

Local training

Sub-regional training

Study trips

Management

Operating expenditure

Mid-term Review

Monitoring/Evaluation 0

CPP meeting

Annual accounts audit

Final accounts audit

20212016 2017 2018 2019 2020

Page 9: CAMEROON - afdb.org

vi

Results-based Logical Framework

Country and Project Title: Cameroon - Public Expenditure Efficiency Improvement Support Project (PAEDEP)

Project Goal: Help to improve fiscal management and public expenditure impact in the energy and transport sectors

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION RISKS/ MITIGATION

MEASURES

Indicator

(including ISCs) Baseline situation Target

Imp

act

Growth acceleration

GDP growth rate

5.2% on average over the

2011-2015 period

5.5 % on average over the

2016-2020 period

GESP

implementation

report

OU

TC

OM

ES

Outcome 1: Improvement

in public investment

spending

Investment budget

implementation rate <50% in 2014 >70% in 2020

PIB implementation

report (MINEPAT)

Risk of a slowdown in

reform implementation:

Limited incentive for

political authorities to

adopt reforms in areas

covered by the project

Mitigation measure: Continued dialogue with

the authorities on various

reforms. The circular on

MTEFs is proof of the

authorities' commitment.

Outcome 2: Improved road

network maintenance

Annual execution rate

of the Road Fund budget

allocated for road maintenance

41.9% in 2014

>75% in 2020

Road Fund annual

report

Outcome 3: Improved

access to electricity

Electricity connection rate for

new customers in rural areas

35% in 2014

40% in 2020

Implementation

report of the Rural

Electrification Master

Plan

Component 1: Support to public investment project maturation and procurements

OU

TP

UT

S

1.1 Support to improve the

planning, monitoring and

implementation of public

investments

1.1.1 Methodological guide on

the maturation of investment

projects and PIB preparation

The Methodological Guide

adopted in 2010 is not

mastered by the sector

ministries on account of its

operational shortcomings (less than 50% of BIP

projects are mature)

Methodological guides

revised and adapted to the

needs of sector ministries

(Target: over 75% of BIP projects are mature as from

2017

Copy of the new

guide adopted by

DGEPIP

Risk pertaining to project

implementation capacity

due to dysfunction within

Government services

resulting from overlapping

duties. Average

Mitigation measure: One of the scheduled project

activities focuses on

clarifying the roles of

various stakeholders and

reviewing the institutional

frameworks.

Implementation of the

study findings will help to mitigate the dysfunction

risk within services that

benefit from the project.

Fiduciary risk: The low

level of governance in the

country could undermine

the efficient use of project resources.

Mitigation measure: An

accounting and financial

management system will be

instituted to ensure that the

management of project resources is consistent with

Bank rules and procedures.

1.1.2 Project data bank in

MINEPAT

No project data bank in

MINEPAT in 2015

Project data bank

operational in 2018

DGEPIP activity

report

1.1.3 Investment Projects

Maturation Fund

No Investment Projects

Maturation Fund in 2015

Investment Projects

Maturation Fund

operational in 2018

DGEPIP activity

report

1.1.4 Number of technical

studies, FDS and PDS conducted in the transport and

energy sectors through the

project maturation fund

0 studies in 2015

At least 6 complete studies

in the transport sector and 5 hydroelectricity site

studies before 2020

Copy of studies approved by MINTP

and MINEE

1.1.5 Monitoring and

evaluation system for the

public investment budget (PIB)

Monitoring and evaluation

system not operational in

2015

Revised monitoring system

that facilitates the

preparation of a

comprehensive report on

PIB implementation

DGE activity report

1.2 Support for

improvement of the public

procurement system

1.2.1 Public Procurement

Capacity Building Strategy No strategy in 2015 Strategy available in 2017

Copy of the strategy

adopted by ARMP

1.2.2 System for information

and archiving of public

procurement data and

documents

No integrated information

and archiving system

Archiving system

operational in 2018 ARMP activity report

1.2.3 Regular public

procurement audits (ARMP)

Irregular public procurement audits since

2010

Public procurement audits conducted on time from

2015 to 2019

ARMP activity report

Component 2: Support for strategic planning and management in the transport and energy sectors

2.1 Support for the strategic

planning of investments in

transport infrastructure and

road maintenance

management

2.1.1 Strategy for developing

infrastructure project maturation activities in MINTP

No strategy infrastructure

project maturation strategy

implemented in collaboration with other

sector ministries in 2015

Strategy prepared and

implemented as from 2018

Report of the MINTP

Department for Studies

2.1.2 Diagnostic study report

on road maintenance with a

view to reforming the sub-

sector

No holistic study on road

maintenance issues (assessment of road

maintenance through

privatization, road

maintenance under own

management; performance

of SMEs and their

contracting process ...)

Study report available in

2018 together with a

reform proposal

Report of the MINTP

Department for

Studies

2.1.3 SME database at MINTP

for better management of SME

stakeholders involved in road

maintenance

No SME database in 2015 Database operational in

2018

Report of the MINTP

Department for

Studies

Page 10: CAMEROON - afdb.org

vii

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION RISKS/ MITIGATION

MEASURES

Indicator

(including ISCs) Baseline situation Target

2.1.4 Number of road sector SMEs trained in the following

areas: tendering, contract

management, further training

for drivers and mechanics

No training in 2015

At least 50 SMEs trained

per year from 2016 to

2020, of which 30% are

owned by women

MATGENIE progress

report

2.2 Support the

improvement of energy

sector management and

regulatory framework

2.2.1 Study report on the

review of the institutional

framework of MINEE to

clarify stakeholder roles and responsibilities

No study in 2015 Study with proposals

available in 2018

Report of the MINEE

Directorate for

Energy

2.2.2 National energy

efficiency plan and its

institutional framework

No up-to-date national

energy efficiency plan in

2015

Up-to-date plan available

in 2018

Report of the MINEE Directorate for

Energy

Report of the MINEE

Directorate for

Renewable Energy 2.2.3 Preparation of a

renewable energies ATLAS

No renewable energies

ATLAS in 2015 ATLAS available in 2019

2.2.4 Establishment of a

framework for facilities

management and audit of

electrical systems (EDC).

No reliable framework of

managing the country’s

electricity facilities in 2015

System available in 2017 EDC progress report

2.2.5 Number of EDC

employees trained in financial/legal engineering and

project preparation techniques

under a PPP in the energy

sector

No training conducted in

2015

At least 10 persons trained per year from 2016 to

2020, of which 30% are

women

EDC progress report

KE

Y A

CT

IVIT

IES

COMPONENTS RESOURCES

Components Foreign

Exchange L.C Total Percentage

1. Support for public investment project maturation and procurements 4.370,8 3.144,2 7.515,1 32%

1.1 Support to improve the planning and monitoring-execution of public

investments

1.926,1 1.597,9 3.524,0 15%

1.2 Support for improvement of the public procurement system 2,444.7 1,546.4 3,991.1 17%

2. Support for strategic planning and management in the transport and

energy sectors

9,775.1 2,890.6 12,665.7 54%

2.1 Support for the strategic planning of investments in transport infrastructure and road maintenance management

4,253.0 1,617.9 5,871.0 25%

2.2 Support for improvement of the energy sector management and regulatory framework

5,522.1 1,272.7 6,794.8 29%

Project Management 225.4 2,043.8 2,269.2 10%

TOTAL BASE COST 14,371.3 8,078.7 22,450.0 95%

Contingency costs 718.6 351.9 1,070.5 5%

TOTAL PROJECT COST 15,089.9 8,430.6 23,520.5 100%

ADF 6,258.6 4,951.4 11,210.0 47.7%

ADB 8,831.3 2,438.7 11,269.9 47.9%

GOV’T 0.0 1,040.5 1,040.5 4.4%

Page 11: CAMEROON - afdb.org

1

REPORT AND RECOMMENDATIONS OF BANK GROUP MANAGEMENT TO THE BOARD OF DIRECTORS

CONCERNING A PUBLIC EXPENDITURE EFFICIENCY IMPROVEMENT SUPPORT PROJECT (PAEDEP) IN

THE REPUBLIC OF CAMEROON

Management submits this report and its recommendation on a proposal to award an African

Development Fund (ADF) loan of UA 11,210,000 and an ADB loan of EUR 14,200,000 to the

Government of the Republic of Cameroon to finance the Public Expenditure Efficiency Improvement

Support Project (PAEDEP).

I Strategic Thrust and Rationale

1.1. Project Linkage to Country Strategy and Objectives

1.1.1. The country's priority development pillars are defined in the 2010-2020 Growth and

Employment Strategy Paper (GESP). These pillars seek to: (i) raise the average annual growth rate to

5.5% during the 2010-2020 period; (ii) cut underemployment from 75.8% to at least 50% by 2020; and

(iii) reduce the monetary poverty rate from 39.9% in 2007 to 28.7% by 2020. To achieve the above

objectives, the Government intends to adopt a coherent integrated approach by implementing a three-

pronged strategy comprising: (i) a growth strategy; (ii) a jobs strategy; and (iii) a State governance and

strategic management improvement strategy. PAEDEP falls under GESP implementation since it is

aimed at achieving the following fundamental national development strategy objectives: (i) gradually

raise the share of public investment in total State spending from 20% to 30% (by 2020); (ii) allocate

resources massively to major public investment projects; and (iii) significantly simplify procurement

procedures.

1.1.2. Similarly, the project is consistent with two of the five operational priorities of the Bank’s

2013-2022 strategy, especially those relating to “infrastructure development” and “governance and

accountability”. It also facilitates the attainment of two of the Bank’s High Five priorities, namely: To

industrialize Africa; and to light up and power Africa. Lastly, the operation is consistent with two pillars

of the Bank’s 2015-2019 Country Strategy Paper (CSP) for Cameroon, namely: (i) consolidating

infrastructure to ensure inclusive and sustainable growth, and (ii) strengthening sectoral governance

to ensure the effectiveness and sustainability of structuring investments. The second CSP Pillar is aimed

at strengthening governance, particularly in the transport and energy sectors which receive most of the

Government’s key investments (over 27% of the public investment budget in 2014), and are also the

focus of Bank operations (78% of the active portfolio). Finally, the consolidation actions supported by

the project are consistent with Pillar I (Public sector management and economic management) and Pillar

II (sector governance) of the Bank’s Strategic Framework and second Governance Action Plan (GAP

II) 2014-2018.

1.2. Rationale for Bank Involvement

1.2.1 Over the past five years, the Government has embarked on the implementation of a vast public

investment programme to close the country's economic infrastructure gap. The shortage of key

infrastructure and the resulting increase in the cost of production factors are some of the stumbling

blocks to Cameroon's development. In 2014, the Government developed an emergency programme,

endowed with significant financial resources and more flexible mechanisms to accelerate the

implementation of structuring projects. In 2015, the Bank awarded the country a partial credit guarantee

to help raise funds to finance the emergency programme. However, annual implementation rates of the

various public investment budgets (PIB) have remained low and fail to permit the optimal absorption

of resources. Poor project quality at entry and bottlenecks in the public expenditure chain are the main

constraints responsible for this situation. The poor sustainability of certain works and ineffective

regulation in key sectors, including energy, have also been cited as some of the factors that negatively

affect the development of infrastructure needed to improve the well-being of the people. In granting a

partial credit guarantee to the Government, the Bank undertook to support the country in the maturation

of the projects within the emergency investment programme.

Page 12: CAMEROON - afdb.org

2

1.2.2 This project constitutes the first phase in a series of future support initiatives to eradicate the

major institutional and organizational bottlenecks that the Cameroonian Government has to grapple

with in public finance management (PFM) as well as transport and energy sector governance. On the

whole, the project is aimed at strengthening the institutional framework as well as the maturation,

programming and implementation public investments, while supporting the modernization and

streamlining of the fiduciary framework to ensure a sustainable improvement in public spending

efficiency. At the sectoral level, it will improve the sustainability of investments and the regulatory

framework in the transport and energy sectors.

1.2.3 Public Finance Management (PFM): Following the public expenditure and financial

accountability (PEFA) review conducted in 2007, the Government adopted the Law on State Fiscal

Regime (LSFR) on 26 December 2007, thus introducing the concept of results-based management

(RBM). A public finance modernization plan, adopted in December 2009 and updated in 2012, led to

significant achievements in streamlining budget management in Cameroon over the last five years. It

focuses on: (i) the adoption of multi-year budgeting that includes the Medium-Term Expenditure

Framework (MTEF) and programme budgets from 2013; (ii) the creation of the Inter-Ministerial

Programme Review Committee (CIEP) and; (iii) the establishment of Planning-Programming-

Budgeting-Monitoring and Evaluation (PPBME) units in sector ministries. Despite these encouraging

developments, the PFM system is still undermined by several challenges.

1.2.4 Indeed, the legal framework remains incomplete, thus undermining the monitoring and control

of budget execution. In terms of strategic planning, the programme budget still lacks clarity since there

are no sectoral strategies and Priority Action Plans (PAPs) based on the GESP. As regards programming

and budgeting, almost half of the public investment projects fail to satisfy the maturity and technical

preparation conditions and criteria. Consequently, there is no control over the project cycle and this

leads to under-consumption of the PIB. There are no good quality projects within the PIB, primarily

due to the very limited budgetary resources allocated to project studies by various sector ministries, as

well as the weak capacity of the Departments of Studies in these ministries to design projects internally.

As regards expenditure execution, the sole major achievement is the devolution of payment

authorization powers. The expenditure flow remains characterized by: (i) its protracted nature,

complexity and excessive recourse to waivers; and (ii) the practice of budgetary over-regulation which

leads to low consumption of appropriations. Reform of the public procurements system, introduced in

2012 through the creation of a Ministry of Public Contracts, has also given rise to inefficiency thus

underscoring the need for clarification of responsibilities and stakeholder capacity building. Lastly, the

PFM information system, composed of several, often compartmentalized, elements, also undermines

integrated budget management. The Autonomous Sinking Fund (CAA), which manages the public debt

and especially disbursements for investment projects funded by TFPs, is undermined by the fact that

the main software (CSDRMS) used by its services is obsolete and cannot integrate with other

management tools. Cameroon’s governance performance under the Mo Ibrahim index has regressed

from 49.9% in 2008 to 45.9 in 2014, although it remains above the Central African average (40.9%).

1.2.5 To address these shortcomings, the Government decided to build the national capacity for

budget planning and programming, project preparation/appraisal and loans/disbursements management.

It also plans to set up a project maturation fund to finance studies that will guarantee the quality projects

under the PIB. As regards public procurement, the Government convened a team of national experts in

2015 to review the procurement code.

1.2.6 After consultation with other technical and financial partners meeting within the Public

Finance Sectoral Committee (CSFP), the Bank decided to focus its support under this project on the

following public finance modernization pillars: (i) improvement of the planning, programming and

budgeting of investment expenditure; (ii) improvement of the procurement system; and (iii)

strengthening of the monitoring and evaluation mechanism.

Page 13: CAMEROON - afdb.org

3

Other TFPs within the CSFP will support the Government to improve information systems used in fiscal

resource management, public accounting and control systems. In Phase II of this project, the Bank will

expand its operations to other areas of public spending that have not been adequately covered by other

TFPs.

1.2.7 Transport Sector: The road transport sub-sector accounts for approximately 25% of public

investments. While budget expenditure in this sector has increased in absolute terms in recent years, its

performance has remained below the performance targets set by the authorities. Over 90% of initiated

projects are not completed within the prescribed timeframe. Cumbersome expenditure initiation

procedures, a sluggish procurement process and a protracted payments system all account for this

situation. Consequently, public spending on the road sub-sector still has only a very limited impact on

economic competitiveness. Contrary to the trend in sub-Saharan Africa, transport costs decline rather

slowly, despite a demand increase of over 15% annually.

1.2.8 As regards road maintenance and contrary to the trend in many sub-Saharan African countries,

management of the classified road network has not yet been assigned to a specialized road agency.

According to Decree No. 2013/334 of 13 September 2013 to organize the Ministry of Public Works

(MINTP), road network management falls under the General Directorate for Infrastructure Works. The

Road Fund (RF) established in 1998 and operational since 1 January 1999 is tasked with (i) raising

funds; (ii) safeguarding resources earmarked for the maintenance of priority and urban roads; and (iii)

ensuring that companies are paid for their services. This special public administrative body is placed

under the technical supervision of the Ministry of Public Works and the financial supervision of the

Ministry of Finance (MINFI). From its inception until 2011, the RF has operated as a first-generation

road fund. On account of the single treasury account principle applied through the law governing the

State financial system, the RF lost the autonomy that is crucial to its status and optimal functioning. The

consequence of this new situation has sometimes been protracted payment delays, deterioration of the

financial situation of service providers, and the RF’s loss of credibility vis-à-vis commercial banks.

Hence, this principle has become a threat to the effective implementation of the road maintenance

program and the sustainability of road infrastructure. The Government is studying the options for

upgrading the RF into a second-generation road fund. In its dialogue with TFPs and following the

National Road Council (CONAROUTE) session of May 2015, the Government is considering a

proposal to develop a plan in this regard.

1.2.9 Apart from the abovementioned financial difficulties, the SMEs operating in the sub-sector

also face technical constraints in terms of access to road maintenance equipment and the low

qualification of the staff tasked with management and maintenance of such equipment. The project

seeks to improve transport sector governance in the areas of planning, monitoring and evaluation as

well as road maintenance management. It will help to establish a database for SMEs and to build their

capacity in partnership with MATGENIE training centres.1

1.2.10 Energy Sector: The energy sector accounts for approximately 12% of public investments in

Cameroon. Significant investments have been made in this sector which, together with the transport

sector, accounted for 78% of Bank investments in Cameroon in 2014. A public expenditure review in

the energy sector conducted in 2014 with Bank support, helped to identify several shortcomings that

undermine investment efficiency in the sector. These include: (i) ill-adapted planning and decision-

making tools; (ii) institutional and regulatory shortcomings stemming from the absence of enabling

instruments for the 2011 electricity law and a failure to clarify the roles, duties and responsibilities of

key stakeholders in the electricity sub-sector; and (iii) the ill-adapted institutional capacity of key sector

stakeholders, including: the Ministry of Energy and Water Resources (MINEE), the Electricity Sector

1 The National Civil Engineering Equipment Pool (MATGENIE) is an industrial and commercial public body (EPIC) whose mission is to: (i) procure,

maintain, renew and lease out equipment used by administrative services and local government structures for the construction and maintenance of the

national road network; (ii) provide the same services, for a fee, to the private sector; and (iii) train public sector staff and SMES in the maintenance and operation of construction machinery.

Page 14: CAMEROON - afdb.org

4

Regulatory Agency (ARSEL), the National Electricity Transmission Company (SONATREL), the

Electricity Development Corporation (EDC) and the Rural Electrification Agency (AER).

1.2.11 As regards planning and decision-making tools, although MINEE prepared a Sector Strategy

Paper in 2011, the electricity sub-sector has no master plan to date. A certain number of reforms have

been made in the legal, institutional and regulatory framework. These include the promulgation of the

electricity law in 2011 and the establishment of many entities to manage the facilities (EDC), manage

the electricity transmission network (SONATREL), develop rural electrification (AER), and develop

and regulate renewable energy (ARSEL).

1.2.12 Furthermore, this institutional mechanism is still fraught with constraints related to interference

among the various stakeholders, legal framework shortcomings and the fact that the entity managing

power transmission networks is not yet operational. Clarification of the roles, duties and responsibilities

of key stakeholders in the electricity sub-sector is crucial to optimization of the initiatives and

investments made. Meanwhile, ARSEL capacity and mechanisms need to be built in the areas of

consumer protection, service quality regulation and control, and information systems strengthening. The

specific support provided to the electricity sub-sector under this project is aimed at helping the country

address the abovementioned challenges by building stakeholder capacity to conduct studies, and

providing them with planning and decision-making tools.

1.3. Aid Coordination

1.3.1 Aid coordination and cooperation with donors is the responsibility of the Ministry of the

Economy, Planning and Territorial Development (MINEPAT). The Bank's focal point is the Department

for Regional Integration (DIR) within MINEPAT. In compliance with the Paris Declaration’s alignment

principle, TFPs strive to align their operations on the GESP and contribute to the achievement of its

priorities. The Bank is an active member of the Multi-Partner Committee (CMP), and thus participates

in the thematic working groups that serve as a forum for discussion and coordination of the activities of

development partners in the country. After serving as the lead donor of the Public Finance Sector

Committee (CSFP) from 2009 to 2014, the Bank assumed chairmanship of the Transport Sector

Committee in December 2014. Bank operations in the public finance sector are prepared in consultation

with other CSFP members, including the World Bank, IMF, European Union, France and GIZ. Annex

3 presents the focus areas of each TFP and their respective positions under the various public finance

reform pillars.

1.3.2 Almost all projects in the transport and energy infrastructure sectors are co-financed with the

other development partners (World Bank, Japanese International Cooperation Agency (JICA), French

Development Agency and the Development Bank of Central African States). A new platform for

dialogue with MINEPAT was established in early 2016 on issues relating to public procurements,

exemptions/compensation and procedures for the use of the budget support instrument in Cameroon.

Annex 5 presents the respective positions of various TFPs in Cameroon. During the identification,

preparation and appraisal missions of the project, the Bank team held discussions with these key TFPs.

These discussions led to a harmonization of views on, inter alia, the project components and road

maintenance financing. All these partners recognized the importance and relevance of this project which

is perfectly consistent with the operations of other partners.

II Project Description

2.1 Project Components

2.1.1 The general objective of the project is to improve fiscal management and enhance the impact

of public spending in the energy and transport sectors. Specifically, the project seeks to achieve the

following outputs: improve public investment planning and programming in general and within the

Page 15: CAMEROON - afdb.org

5

energy and transport sectors in particular; improve the maturation and budgeting of public investments;

improve the public procurement control and audit system; improve the public investments monitoring

and evaluation system; improve road maintenance management; and improve quality regulation and

control in the energy sector.

2.1.2 The project has 3 (three) components, namely: (i) support the maturation of public investment

projects and procurements; (ii) support strategic planning and regulation in the transport and energy

sectors; and (iii) project management. The table below summarizes the project components, sub-

components and the main activities to be implemented.

Table 2.1-1

Project components and cost estimates (in UA million)

Components Description of Components

Component 1 – Support the maturation of public investment projects and procurements UA 7.51

million

Support project

maturation and

monitoring and

evaluation of the

execution of public

investments

UA 3.52 million

Revise the methodological guidelines and the investment project maturation framework;

Provide training in project development and ex-ante assessment of the economic and financial impact of projects;

Establish a project databank at DGEPIP, endowed with project maturation monitoring features; Conduct a study on and establish a project maturation fund;

Provide an initial endowment to operationalize the project maturation fund;

Ensure the maturation of transport and energy sector projects: FDS and PDS for road projects under the emergency program; comprehensive studies on 5-10 hydroelectric sites;

Establish mechanisms and a system for monitoring and evaluation of the PIB;

Provide the CAA with technical assistance in translating the debt management software (CSDRMS) into French and staff training.

Support improvement

of the public

procurement system

UA 3.99 million

Develop a capacity-building strategy on public procurements at the ARMP and support of its implementation

(arrangements for setting up a training centre at the ARMP; publication and dissemination of collections of public

procurement texts and standard documents);

Establish an information and archiving system for public procurement data and documents at the ARMP and MINMAP;

Assess the performance of independent observer missions and assist in the optimization of public procurement audits

conducted by the ARMP; Support the ARMP to engage in routine public procurement audits (technical assistance and funding of audits at least

for the years 2015 to 2017);

Build the capacity of ARMP/MINMAP staff and stakeholders involved in the award and control of public contracts.

Component 2: Support strategic planning and regulation in the transport and energy sectors

Support strategic

planning and

regulation in the

transport sector

UA 5.87 million

Institutional framework:

(i) Formulate a strategy to develop the activities of the Directorate General for Technical Studies within the process of infrastructure project maturation and implementation support;

(ii) Conduct a diagnostic study on the road maintenance framework with a view to engaging in sub-sector reform

(assessment of road maintenance privatization, Road Fund performance evaluation; road maintenance under own

management; SME performance and contracting process; road maintenance planning and programming performance;

reform proposal).

Management tools and systems

(i) Procure software for Interactive Mapping of Infrastructure Projects;

(ii) Update the project management and budget programming software (STRATEGIC);

(iii) Development an SME database at MINTP for better management of SME stakeholders involved in road maintenance.

Training

(i) Provide training in RBM; planning and development of MTEFs/ programme budgets; monitoring and evaluation;

(ii) Build stakeholder capacity in the management of road maintenance by service level (GENIS);

(iii) Build the capacity of SMEs involved in road maintenance (training in tendering procedures, contract management, mechanics and maintenance of technical equipment in MATGENIE training centres).

Page 16: CAMEROON - afdb.org

6

Support strategic

planning and

regulation in the energy

sector

UA 6.79 million

Institutional framework: Support in revising the institutional framework of MINEE in order to clarify the roles and

responsibilities of stakeholders: MINEE; ARSEL; AER; FEICOM; SONATREL, EDC (study and proposal of a new

institutional framework).

Strategic Planning: Development of an electricity sub-sector master plan; Update of the National Energy Efficiency

Plan and its institutional framework (MINEE); Capacity building in project planning and maturation, preparation of MTEFs and monitoring and evaluation for MINEE, ARSEL, SONATREL, EDC, AER (training and technical assistance

to these structures).

Management tools and systems: (i) Establish a system for facilities management and audit of electrical systems at EDC (technical assistance and

training);

(ii) Establish a modern electricity regulation system covering the following domains: (i) consumer protection and service quality regulation; (ii) mechanisms for controlling concessionaires in the performance of their public service tasks and

rate payment aspects; (iii) strengthening of the information systems (technical studies, procurement of technical

equipment, software, training); (iii) Prepare of a renewable energy ATLAS in Cameroon (studies, technical assistance, field surveys, publication of the

ATLAS, training in renewable energy development); and

(iv) Conduct a study on modelling of the electricity transmission network and procure specialized software for planning and modelling of electricity transmission structures, including staff training on the use of such structures;

Technical training of stakeholders in the following areas: electricity generation tools for rural areas not connected

to the national grid; quality standards in the evaluation of energy efficiency; financial/legal engineering and project design techniques under a PPP in the energy sector.

Component 3 Project management UA 2.26 million

TOTAL BASE COST UA 22.45 million

2.1.3 Technical Annexes C and B2 present the activities and detailed costs per component as well as

a comprehensive list of the goods and services to be procured under the project.

2.2 Technical Solutions Adopted and Alternative Solutions Considered

2.2.1 During project preparation and appraisal, the Bank explored several options relating to areas

of intervention, the number of institutions or beneficiaries to be supported and the type of capacity

building to be provided. One of the options pertaining to the key issue of project maturation was to fund

only the establishment of the institutional framework and capacity building for various stakeholders.

This option was rejected because of its limited impact. It was agreed that, in addition to capacity

building, consideration should also be given to the establishment of a project maturation fund and the

conduct of a certain number of technical studies with a view to developing mature projects for the

emergency programme. The project maturation fund will be established through a participatory process

with the support of technical assistance financed by the project. The fund will initially be provisioned

with national counterpart funds and an endowment provided for under the project. Operating

mechanisms and the fiduciary framework for management of the Fund must be deemed satisfactory by

the Bank and other PTFs. Ultimately, the Fund will receive resources from the other TFPs and the

national budget to ensure its sustainability.

2.3 Type of Project

2.3.1 PAEDEP is an institutional support project funded by an ADF loan and an ADB loan.

Cameroon has not yet fulfilled the criteria for programme-based operations, which are the ideal

framework for conducting reforms. Dialogue is ongoing with the Government and other TFPs to ensure

that the country benefits from such an instrument. In the meantime, institutional support remains the

best instrument for improving governance in public finance management and in the key economic

sectors (energy and transport). Through such support, the Bank also intends to consolidate the capacity

building already provided through investment projects in the energy and transport sectors.

Page 17: CAMEROON - afdb.org

7

2.4 Project Cost and Financing Mechanisms

2.4.1 The total project cost, net of taxes and customs duties, is estimated at UA 23.52 million (or

CFA.F 19.43 billion2), comprising UA 15.8 million in foreign exchange (64%) and UA 8.43 million in

local currency (36%). These costs include a 2% provision for physical contingencies and a 3% provision

for price increase, for expenditures in both foreign exchange and local currency. The ADF contribution

to project funding is UA 11.21 million, and covers the financing of equipment, training and technical

assistance, as well as a part of the operating costs. ADB funding amounts to EUR 14.2 million

(approximately 11.26 million) and principally covers the cost of equipment and feasibility studies of

energy and transport sector projects. The Government counterpart contribution is UA 1.04 million (or

4.4% of the total project cost3) and essentially covers financing of an initial provision for the project

maturation fund and operating costs. The tables below provide more details on the overall project costs

by component, expenditure category and funding source. The table of detailed costs is presented in a

technical annex.

Table 2.4-1

Estimated project cost by component

Components/Sub-components

Amounts (in CFA.F billion) Costs (in UA million)

%

Total Foreign

exchange

Local

currenc

y

Total Foreign

exchange

Local

currency Total

1. Support for the maturation of public

investment projects and procurements 3,612.5 2,598.7 6,211.2 4,370.8 3,144.2 7,515.1 32%

1.1 Support for improvement of the planning and monitoring and execution of public investments

1,592.0 1,320.6 2,912.6 1,926.1 1,597.9 3,524.0 15%

1.2 Support for improvement of the public

procurement system 2,020.5 1,278.1 3,298.6 2,444.7 1,546.4 3,991.1 17%

2. Support for strategic planning and

management in the transport and energy

sectors

8,079.1 2,389.1 10,468.2 9,775.1 2,890.6 12,665.7 54%

2.1 Support for the strategic planning of

investments in transport infrastructure and road

maintenance management

3,515.1 1,337.2 4,852.3 4,253.0 1,617.9 5,871.0 25%

2.2 Supporting the improvement of the energy sector management and regulatory framework

4,564.0 1,051.9 5,615.9 5,522.1 1,272.7 6,794.8 29%

Project Management 186.3 1,689.2 1,875.5 225.4 2,043.8 2,269.2 10%

TOTAL BASE COST 11,877.9 6,677.0 18,554.9 14,371.3 8,078.7 22,450.0 95%

ADF 4,926.4 3,897.4 8,823.9 5,960.6 4,715.6 10,676.2 48%

ADB 6,951.5 1,919.6 8,871.0 8,410.7 2,322.5 10,733.3 48%

GOV’T 0.0 860.0 860.000 0.0 1,040.5 1,040.533 5%

Provision for physical contingencies (2%) 237.6 116.3 353.9 287.4 140.8 428.2 2%

Provision for price increase (3%) 356.3 174.5 530.8 431.1 211.1 642.3 3%

TOTAL PROJECT COST 12,471.8 6,967.9 19,439.6 15,089.9 8,430.6 23,520.5 100%

Table 2.4-2

Estimated project costs by component and financing source (in UA thousand) Financing source Cost in

foreign

exchange

Cost in

local

currency

Total cost

in UA

%

ADF 6,258.63 4,951.37 11,210.00 48%

ADB 8,831.26 2,438.67 11,269.93 48%

Government 0.00 1,040.53 1,040.53 4%

Total cost 15,089.89 8,430.57 23,520.46 100%

2 At the exchange rate prevailing at appraisal in July 2016 (UA 1 = CFA.F 826.499) 3 Annex 3 presents the rationale for the relatively low level of Government contribution.

Page 18: CAMEROON - afdb.org

8

Table 2.4-3

Project cost by expenditure category (in UA million)

Expenditure categories

Cost in

foreign

exchange

(UA)

Cost in local

currency

Total cost

in UA %

A. Goods 2,044.1 546.4 2,590.4 11%

B. Services 11,937.7 4,572.5 16,510.2 71%

Technical assistance 10,476.6 3,217.4 13,694.0 59%

Training 1,461.1 1,355.1 2,816.2 12%

C. Operating costs 33.9 1,984.6 2,018.4 9%

D. Miscellaneous (maturation

fund) 355.7 636.4 992.1 4%

Total baseline cost 14,371.3 7,739.9 22,111.2 95%

Provision for physical contingencies

287.4 140.8 428.2 2%

Provision for price escalation 431.1 211.1 642.3 3%

Total project cost 15,089.9 8,091.8 23,181.7 100%

Table 2.4-4

Expenditure schedule by component (in UA thousand) Components/Sub-components 2017 2018 2019 2020 Total

1. Support for the maturation of public investment projects and

procurements 549.6 3,136.5 2,452.3 1,376.7 7,515.1

1.1 Support for the improvement of the planning and monitoring

and execution of public investments 157.3 1,397.0 1,247.5 722.3 3,524.0

1.2 Support for improvement of the public procurement system 392.3 1,739.5 1,204.9 654.4 3,991.1

2. Support for strategic planning and management in the

transport and energy sectors 1,766.2 4,887.7 3,296.4 2,715.5 12,665.7

2.1 Support for the strategic planning of investments in transport

infrastructure and road maintenance management 677.9 1,775.9 1,679.5 1,737.6 5,871.0

2.2 Supporting the improvement of the energy sector management

and regulatory framework 1,088.3 3,111.9 1,616.8 977.8 6,794.8

Project Management 721.8 515.8 515.8 515.8 2,269.2

TOTAL BASE COST 3,037.5 8,540.0 6,264.5 4,607.9 22,450.0

2.5 Project Area and Beneficiaries

2.5.1 The project area is the entire national territory of Cameroon. The direct project beneficiaries

are: the Ministry of the Economy, Planning and Territorial Development (MINEPAT), the Ministry of

Finance (MINFI), the Ministry of Public Contracts (MINMAP), the Ministry of Public Works (MINTP),

the Ministry of Energy and Water Resources (MINEE), the Public Contracts Regulatory Agency

(ARMP), the Electricity Sector Regulatory Agency (ARSEL), the National Electricity Transmission

Company (SONATREL), the Autonomous Sinking Fund (CAA), the Road Maintenance Fund (RMF),

the Rural Electrification Agency (AER), the Electricity Development Corporation (EDC), and the

National Civil Engineering Equipment Pool (MATGENIE). The indirect beneficiaries are: the

contracting agencies of the national public procurement system; PPBME units and programming-

budgeting officers in sectoral ministries; electricity production and distribution entities; and private

companies, especially those operating in the domains of public works, road maintenance and energy.

The final beneficiaries of the project are the national population, particularly women and the youth

whose concerns are better addressed through more effective budget management aligned on sector

strategies and focusing on job creation, with due consideration for equity, gender balance and inclusive

growth.

2.6 Participatory Approach to Identification, Design and Implementation

2.6.1 During project preparation, broad-based consultation was organized with stakeholders from

the public sector, private sector, Cameroonian civil society as well as technical and financial partners

represented in Cameroon. Consultations were held during meetings between the Bank team and the

officials from these structures. Most of the structures made detailed requests to the Bank in form of a

project information sheet. These requests formed the basis of discussions during project appraisal. This

Page 19: CAMEROON - afdb.org

9

approach, as well as the findings of public finance management diagnostic studies (PEFA, Public

Finance Modernization Plan) and the study on public expenditure efficiency, enabled the appraisal team

to better understand the constraints and challenges faced by the beneficiary structures of the project and

to factor their real needs into the design of project components. Most project sub-components provide

for capacity-building activities for non-State actors (civil society and private sector) especially on the

public procurement system (training, awareness-raising on the themes of transparency) and on the

development of an SME database for better management of SME stakeholders involved in road

maintenance etc.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1. In the area of governance, the Bank’s sole ongoing operation is the Support Project for

Modernization the Land Registration System and the Business Climate (PAMOCCA) approved in

November 2010.4 This project which focused on four cities of the country, received additional support

in 2013 to expand its activities to several other regions of the country. The commitment rate of ADF

resources under the project is estimated at approximately 80%, with a disbursement rate of 33%. The

excessively protracted nature of the procurement process in general, especially for the two largest

technical assistance contracts of the project, is primarily responsible for the low disbursement rate.

Thanks to increased monitoring and dialogue with the main contracting authority in the country, namely

the Ministry of Public Contracts (MINMAP), these two contracts and almost all other contracts have

now been signed, and activities have started. Apart from PAMOCCA, the Bank has funded several past

operations that have now been completed. The last operation was a governance reform support project

(GRSP) implemented in 2006-2012. The objectives of this project were to: (i) improve the efficiency

of public administration and the judicial system; (ii) improve public finance management (capacity

building for internal and external budget control structures and procurement system); and (iii) intensify

corruption control. The GRSP yielded mixed results, with an implementation rate of approximately

35%, after three years of extension. The completion report (ADF/BD/IF/2012/220) prepared in

November 2012 awarded a total score of 2/4 for the implementation of activities. According to the

report, the weak ownership of the project at the national level, the overly broad range of areas covered,

and the weak capacity of the project implementation unit were the main stumbling blocks to the

achievement of results.

2.7.2. These poor results were corroborated by the assessment conducted by IDEV in 2014 on the

implementation of the Bank's strategy and programme in Cameroon during the 2004-2013 period. In

addition to the above shortcomings, the IDEV report noted weak ownership of scheduled reforms by

the political authorities, and the Bank’s failure to factor the country's actual absorption capacity into the

design of operations. The report recommended better orientation of policy dialogue through targeted

analytical studies and proper consultation with other TFPs and civil society to generate strong demand

for enhanced internal governance. These recommendations were factored into the design of the current

operation. Indeed, the Bank, in consultation with other TFPs, has intensified dialogue with the

authorities on various development issues covered by the project. These include the maturation of

investment projects, reform of the procurement system, road maintenance efficiency, as well as

regulation and stakeholder capacity building in the electricity sector. This dialogue, which is conducted

within the Multi-Partner Committee (CMP), is underpinned by diagnostic studies carried out by the

Bank and other TFPs, namely the public expenditure efficiency study and the energy and transport

sector expenditure review. The project is based on the authorities’ firm commitment to implement

reforms in the various areas covered, namely: (i) public finance reform; (ii) revision of the public

procurement code; (iii) Road Fund and road maintenance management reform; and (iv) the

improvement of electricity sub-sector regulation. The project intends to support the Government in the

implementation of these key reforms.

4 Annex 2 presents an analysis of the Bank’s portfolio performance in Cameroon.

Page 20: CAMEROON - afdb.org

10

2.7.3. To accelerate project implementation, it was decided that focal points be designated in each

beneficiary structure and tasked with coordinating the drafting of terms of references and other technical

specifications of the studies to be conducted or of the equipment to be procured. During the project

preparation process, several beneficiary structures prepared preliminary terms of reference which were

submitted to the Bank. This will enable the commencement of procurements as soon as the loans become

effective.

2.8 Key Performance Indicators

2.8.1. The key performance indicators identified to measure expected outcomes at project completion

are presented in the results-based logical framework. These are essentially:

Project impact: GDP growth rate maintained at an average 5.5% from 2016 to 2020.

Project outcomes: (i) Investment budget implementation rate of at least 70% in 2020

compared to less than 50% in 2014; (ii) road maintenance budget implementation rate of

at least 75% by 2020 compared to 41.9% in 2014; and (iii) new customers’ electricity

connection rate of 40% in rural areas in 2020 compared to 35% in 2014.

Component 1 outputs: (i) All sectoral Priority Action Plans prepared by the end of 2017;

(ii) project data bank operational at DGEPIP in 2017; (iii) project maturation fund

operational in 2018; (iv) at least six comprehensive road project studies and five

comprehensive hydroelectricity site studies conducted between 2016 and 2016; (v)

exhaustive reports on monitoring and evaluation of the PIB from 2018; (vi) public

procurement audits conducted on time between 2016 and 2020; and (vii) public

procurement information and archiving systems operational in 2018.

Component 2 outputs: (i) Upgrade of the Road Maintenance Fund into a second-

generation fund; (ii) establishment of a database for SMEs involved in road maintenance

and training of SMEs; (iv) electricity sector master plan prepared in 2017; (v) renewable

energy ATLAS prepared by 2019; and (vi) modern systems established in 2018 for the

regulation and management of electricity sector facilities.

2.8.2. Progress towards the achievement of outcomes will be measured at regular intervals, using

various means, including: regular supervision missions from the Bank, submission of quarterly progress

reports, and the study of some outputs such as audit reports and minutes of focal point meetings held

under the guidance of sector experts, which will also serve as an important tool for coordinating

beneficiary structures and the executing agency. Objectively verifiable evidence of progress towards

achievement of the main targets will be obtained from reports, and quarterly portfolio monitoring

meetings organized by CMFO with the implementing units of Bank projects in Cameroon.

III Project Feasibility

3.1 Economic and Financial Performance

3.1.1. This project does not generate direct revenue that makes it possible to get a financial return on

investment. Its performance evaluation, therefore, focuses on the direct and indirect effects of its

economic and social achievements in the medium and long terms. In terms of its impact on economic

performance, it should be noted that PAEDEP implementation will provide Cameroon with greater

capacity and modern management tools across sectors and in the management of public investments.

Indeed, the project is expected to sustainably improve the quality of the State’s economic and financial

management, the efficiency of the expenditure process and the quality and relevance of public

investment projects.

Page 21: CAMEROON - afdb.org

11

3.1.2. Furthermore, enhanced capacity to develop MTEFs will make it possible to have a global

vision of the budget in the medium term and guarantee optimal allocation of resources to priority areas.

Besides, consolidation of the expenditure process through better project maturation and monitoring

should have a positive impact on the achievement of GESP development objectives. Indeed, more

rational use of the resources allocated to investments enhances macroeconomic and sectoral

management efficiency, leading to greater efficiency in economic and social programmes designed to

combat poverty. The resulting streamlined management will be an advantage for the Government in its

dialogue with TFPs that will be more likely to support economic programmes that are better designed

and consistent with national priorities. Ultimately, the expected outcome should be the consolidation of

economic growth thanks to a greater multiplier effect generated by public investments.

3.2 Environmental and Social Impact

Impact on the Environment and Climate Change

3.2.1 Project activities will have no negative impact on the environment. Consequently, the project

is classified in environmental category 3. Furthermore, the project is expected to finance the

environmental impact assessments for transport and energy sector projects. Besides, its activities on

human and institutional capacity building have no negative impact on climate change.

Social and Gender Aspects

3.2.2 Social Impact: The objective of the project is to increase the Government's capacity to

implement reforms and manage public resources efficiently and effectively. Hence, it will strengthen

and leverage the impact of the national budget on the provision of services and improve implementation

of the investment budget in priority areas, in accordance with GESP strategic pillars. Sound public

finance management is necessary to ensure that budget planning is conducive to macroeconomic

stability and the existence of a solid foundation for the provision of high quality services to the public.

The project will also yield positive externalities through the procurement of goods and services from

local small and medium-sized enterprises (SMEs), thus boosting business in these entities. Similarly,

the use of a significant number of supervisors, investigators and local data entry operators should boost

incomes and stimulate domestic consumption. Improvement of the situation of SMEs and electricity

sub-sector operators should, in turn, benefit the State budget in terms of the VAT and taxes that these

economic operators are expected to pay. Project implementation will therefore have a positive economic

and social impact.

3.2.3 Impact on Gender: Women constitute 50.6% of Cameroon's population estimated at 22.8

million inhabitants in 2014. They are moderately represented in political institutions such as the Senate

(21%), the National Assembly (31.1%), and the Government (14.5%). This notwithstanding, the

situation of women and the youth is far from favourable. From the economic standpoint, women

dominate the informal sector. In fact, they constitute 75% of the agricultural workforce and only 20%

of the formal sector workforce. The constraints to women's emancipation in Cameroon are numerous;

apart from their limited access to productive assets (less than 4% of women are landowners and only

25% them, compared to 60% of men, have access to credit in Cameroon) they dominate the mostly

informal economic sector, operating as business owners (30%). The gender inequality index resulting

from inequalities in three human development dimensions (reproductive health, empowerment and job

market) was unfavourable at 0.628 in 2012 (with 1 representing total inequality).

3.2.4 Gender issues remain topical in the transport and energy sectors. The lack of transport and

energy infrastructure significantly undermines women’s advancement and empowerment. On account

of these constraining circumstances such as the lack of highways and farm-to-market roads, women and

the youth, and particularly children, have difficulties transporting farm produce, sometimes having to

carry it on their heads. This situation limits access to health services and makes it difficult to provide

Page 22: CAMEROON - afdb.org

12

proper care because pharmaceutical products cannot be delivered easily. As regards energy, the lack of

electricity in rural households leads to deforestation of the available biomass to satisfy energy needs.

Furthermore, women and the youth are primarily responsible for fetching and transporting firewood to

satisfy household energy needs.

3.2.5 Cameroon's commitment to the effective implementation of women's rights has led it to ratify

most of the international and regional instruments that promote and protect fundamental human rights,

including those that specifically protect women's rights. In 2014, the Government adopted the National

Gender Policy developed with the support of the United Nations system, with the following major

strategic pillars: (i) promotion of equal economic and employment opportunities for both women and

men; (ii) increased women's participation and representation in public life and decision-making; and

(iii) strengthening of the institutional framework. The Multi-Sectoral Action Plan for implementing this

policy is being developed and should be operational in 2016. As regards public finance management,

the finance law prescribes the adoption of gender mainstreaming in budgets and programmes. However,

the legal provisions that guarantee effective gender mainstreaming in budget management are not yet

effective due to the lack of financial means to train stakeholders and conduct the awareness campaigns

needed to give these concerns the required focus during implementation of the public finance reform

strategy.

3.2.6 The Bank already supports infrastructure projects, especially in the transport sector. Bank-

financed transport sector projects in Cameroon include activities aimed at promoting the economic

empowerment of women through programmes that focus on training, dissemination of skills, facilitation

of access to land and financial systems in a bid to eliminate the bottlenecks to the improvement of their

incomes. These include: (i) the distribution of farming kits; (ii) the construction of multipurpose

facilities for processing and marketing of local produce; (iii) the construction of market-shed structures

and drying areas along the road; and (iv) strengthening of the financial and managerial capacities of

women by establishing a support fund for income-generating activities.

3.2.7 This project will help to address these constraints by effectively mainstreaming gender into

budget management. Support will be provided through technical assistance and capacity building in

gender-responsive budgeting, as well as gender mainstreaming in the PPBME (Planning-Programming-

Budgeting and Monitoring and Evaluation) processes of each ministry, which are tasked with the

development of PAPs (Priority Action Plans), MTEFs (Medium-term Expenditure Frameworks), APRs

(Annual Performance Reports), and APPs (Annual Performance Projects). Moreover, PAEDEP will

ensure that training is open to all women in the middle and senior levels of beneficiary institutions.

Hence, at least 30% of SMEs run by women in the transport sector will benefit from the training that

will be provided. Similarly, in the energy sector, at least 30% of female EDC staff will be trained in

financial/legal engineering.

IV Implementation

4.1 Implementation Arrangements

4.1.1 Institutional Arrangements: The implementation of project activities will involve several

beneficiary structures (BS) mainly in the ministries in charge of planning, procurement, finance, public

works, transport and energy. Moreover, given the multi-sectoral nature of the project, activities will be

coordinated by MINEPAT, which is responsible for the preparation and monitoring of public

investments in Cameroon. The Directorate General for the Economy and Programming of Public

Investments (DGEPIP) in MINEPAT was selected as the implementing agency of the project. Indeed,

this Directorate coordinates the preparation of MTEFs, the drafting of the public investment budget and

monitoring of its implementation, in coordination with line ministries and the Ministry of Finance. The

assessment of financial management capacity within MINEPAT, the wide range of activities to be

implemented under the project, and the multitude of stakeholders involved in its implementation, have

Page 23: CAMEROON - afdb.org

13

necessitated: (i) the establishment of a Project Management Unit (PMU) within DGEPIP; and (ii) the

recruitment of 3 (three) sector experts to ensure the technical coordination of activities related to the

public finance, energy and infrastructure sectors. Focal points designated by the beneficiary structures

will be coordinated by sector experts and will serve as interfaces between the PMU and beneficiaries.

The PMU will be responsible for the overall coordination and financial management of the project. Its

key personnel will comprise: a Coordinator, an Administrative and Finance Officer (AFO), a

Procurements Officer (PO), an Accountant, a Monitoring and Evaluation Officer and three sector

experts, all recruited on a competitive basis. A project steering committee composed of representatives

of project implementation structures will be responsible for validating and monitoring the project’s

strategic direction. The technical secretarial duties of the Steering Committee will be performed by the

Director General for the Economy. Technical Annex B.3 provides a detailed presentation of the

institutional mechanism.

4.1.2 Procurement Arrangements: The project procurement arrangements will be handled by the

Project Management Unit whose staff shall include an experienced procurements expert. Given the

findings of the public procurement framework assessment and in light of the risks identified and the

agreed mitigation measures, the procurement rules applicable to this project will be: (i) the procurement

policy for AfDB-financed operations approved on 14 October 2015 using the appropriate standard

bidding documents of the Bank; and (ii) national laws governing public procurements (including Decree

No. 2004/275 of 24 September 2004 to define the public procurement code and other subsequent

instruments) through use of the country’s standard bidding documents as well as the provisions of the

financing agreement. The procurement provisions are detailed in Technical Annex B.5 and in the

procurement plan (PP). This plan will be regularly updated during the project implementation phase.

4.1.3 Financial Management: The PMU will be responsible for the overall coordination and

financial management of the project. Its financial management staff will comprise: a Coordinator, an

Administrative and Finance Officer (AFO), a Procurements Officer (PO), a Monitoring and Evaluation

Officer and an Accountant, all recruited on a competitive basis. The provisions and

arrangements/conditions pertaining to financial management, disbursements and audit of the project are

detailed in Technical Annex B.4.

4.1.4 Disbursements: Disbursements under the project will be governed by the applicable provisions

in the Bank's disbursements manual. The disbursement methods proposed for the project are: (a) the

special account method (for small operating expenses and management of agreements); (b) the direct

payment method for payment of goods and services contracts; and (c) the reimbursement method in

case of pre-financing, by the national counterpart, of expenditures reserved for, and approved

beforehand by, the Bank. Nevertheless, counterpart funds will be disbursed annually in one instalment,

after promulgation of the Finance Law and presentation of expenditure records. In Cameroon, opening

of the special account is the responsibility of the CAA, which shall open the following special accounts

in the name of the PAEDEP, in local currency (XAF) and in a commercial bank deemed acceptable to

the Bank: (i) a special account to receive ADB resources. (ii) a special account to receive ADF resources

and; (iii) a special account to receive the counterpart contribution of the State of Cameroon.

4.1.5 Audit: Considering: (i) the limited human and financial resources of the Audit Bench of the

Supreme Court of Cameroon; (ii) the delay by this institution in auditing State accounts; and (iii) the

deadline constraints in submitting the external audit reports of the projects to the Bank, it is

recommended that, no later than 6 (six) months after project commencement, a private audit firm

acceptable to the Bank should be recruited on a competitive basis and in accordance with the AfDB-

approved terms of reference. The audit will cover all project activities funded with ADB, ADF and

counterpart resources. The audit report and management letter will be forwarded to the Bank annually,

no later than six months after closure of the fiscal year concerned.

Page 24: CAMEROON - afdb.org

14

4.1.6 The overall financial management risk was deemed to be substantial because financial

management measures will be implemented through and during the creation of a new PMU, and also

because the draft management and operating procedures of the project maturation fund are not available

at this stage, and will be available only after the study which will be conducted during project

implementation. The main risks identified and their mitigation measures are summarized in the table of

fiduciary risks found in Technical Annex B4.

4.2 Monitoring

4.2.1 The physical implementation of the project is expected to cover a period of 48 months, from

January 2017 to December 2020. The PMU will establish a software-driven monitoring and evaluation

system. The Monitoring and Evaluation Officer at the PMU will assist the Project Coordinator with

monitoring and evaluation activities. He will be responsible for real-time monitoring of project

execution using the logical framework indicators and relying on the focal points from the various

beneficiary structures. The monitoring and evaluation system will include performance indicators,

collected baseline situation data and measurements of project progress towards attainment of

intermediate targets and impacts. The monitoring system will also include monitoring of the

performance of the Coordinator and PMU experts to determine the level of achievement of their

indicators at contract renewal.

4.2.2 As soon as the loan agreements become effective, a launch mission will be organized to train

PMU officials on Bank procedures. Supervision missions will be organized at least twice a year.

Quarterly progress and annual reports will also be prepared and submitted to the Bank.

4.3 Governance

4.3.1 Project implementation could be affected by governance risks (fraud, corruption, misuse of

funds, ineligible expenditure, etc.) especially in the award and execution of contracts, financial

management, and the selection of trainees. These risks will be mitigated by: establishing a mechanism

for controlling procurement activities, which could be a project management manual that defines the

roles and responsibilities of various stakeholders; developing a detailed procurement plan that is results-

oriented and consistent with the project implementation schedule; and instituting rules as well as

selection and tendering processes that are adapted to project goals. As concerns financial management

of the project, the executing organ shall keep separate project accounts. This will make it possible to

identify expenditure by component, category and financing source. Project accounts will be audited

annually by a firm recruited for that purpose. Financial statements and audit reports will be submitted

to the Bank within six months following the close of the accounting period. Regular project monitoring

and supervision mainly through the Bank office in Cameroon will enhance the verification of project

governance and performance.

4.4 Sustainability

4.4.1 The first project sustainability factor is the willingness of the Government to meet challenges

that relate to continuous improvement of the institutional and regulatory framework for programming

and implementation of the public investment programs to ensure the acceleration of the public projects

maturation process and the sustainability of their impact and beneficial effects on the population’s well-

being. Indeed, the Government introduced programme budgets in 2013 and made it mandatory for all

ministries to prepare MTEFs in 2014. It also embarked on an in-depth reform of the public procurement

management and control system. The Government is also increasingly concerned with road maintenance

in the transport sector and regulation in the electricity sector. As regards road maintenance in particular,

the Government has set up a committee to review the upgrade of the current Road Fund to a second-

generation fund. The second sustainability factor is the mechanism that will be established under

PAEDEP to ensure the sustainable and effective transfer of knowledge and skills, through technical

Page 25: CAMEROON - afdb.org

15

assistance and training. This includes high-level training of trainers and local capacity building. The

project will ultimately build local capacity in training, planning, programming, budgeting and

monitoring and evaluation (PPBME) of investment programmes and policies by establishing

partnerships with national research and training structures.

4.4.2 Finally, the future project maturation fund will include a funding mechanism to ensure its

sustainability, with a view to developing quality projects for the investment budget.

4.5 Risk Management

Risks Magnitud

e Mitigation measures

Risk of a slowdown in

reforms: Limited incentive

for political authorities to

pursue reforms in areas

covered by the project.

Low

The project will engage in dialogue with the authorities on various

reforms at a fairly advanced stage. The adoption of a circular on

MTEFs by the Prime Minister and the Committee set up to review

the road fund are proofs of Government commitment. Dialogue

will be maintained under the CMP, with the involvement of other

TFPs in the implementation of the public finance modernization

programme, public procurement reform and reform of the RF and

road maintenance.

Risk related to project

implementation capacity,

resulting from a dysfunction

within Government services

due to overlap in duties.

Average

One of the scheduled project activities is to clarify the roles of

various stakeholders and review the institutional frameworks.

Implementation of the study findings will help to mitigate the risk

of dysfunction within services that benefit from the project.

Fiduciary risk: The

country’s low governance

level could undermine the

efficient use of project

resources, especially for the

project maturation fund.

Average

An accounting and financial management system will be

instituted to ensure that the management of project resources is

consistent with Bank rules and procedures. As regards the project

maturation fund, a study will be conducted on its establishment

procedures, and its technical, administrative and financial

management mechanisms. The Bank and other TFPs will

contribute to the terms of reference of the study so that fiduciary

aspects will be included under this project. Studies for eligible

projects will be funded through direct payments.

4.6 Knowledge Development

The types of knowledge that will be generated from project implementation include: (i) revision of the

macroeconomic forecast model; (ii) preparation of a renewable energy ATLAS for Cameroon; (iii) best

practices in implementing the PPBME chain across and within sectors (transport and energy); (iv) the

study to establish regulatory and assets management systems in the electricity sub-sector. The studies

will be disseminated within the administration and among non-State stakeholders through distribution

of the documents produced, procedures manuals and training sessions that will be organized under the

project. This knowledge will be generated through processes that involve production of the following

reports: reports of technical assistants, progress reports prepared by beneficiaries and the executing

agency, supervision reports and the project completion report. The knowledge and lessons learnt will

be disseminated within the Bank and in Cameroon through seminars and IDEV reports.

V- Legal Framework

5.1 Legal Instrument

The following two instruments will be used to finance the Public Expenditure Efficiency Improvement

Support Project:

- A loan agreement for ADF resources, not exceeding UA 11.21 million, signed between

the ADF and the Republic of Cameroon;

Page 26: CAMEROON - afdb.org

16

- A loan agreement for ADB resources, not exceeding EUR 14.2 million, signed between

the Bank Group and the Republic of Cameroon.

5.2 Conditions Associated with the Bank’s Intervention

Each loan agreement shall become effective subject to the Borrower’s fulfilment of the conditions

provided for in Section 12.01 of the Bank’s General Conditions for Loan and Guarantee Agreements.

Conditions precedent to consideration of the appraisal report by the Boards:

Review of the appraisal report by the Boards shall be subject to fulfilment by the Borrower of the

following conditions:

(i) Adoption of instruments to set up the project steering committee and the project

implementation unit; and

(ii) Recruitment of the PMU Coordinator, the Financial Management Officer and the

Procurements Officer. The experience and qualifications of the Coordinator and Experts

must be deemed acceptable to the Bank.

Implementation status of preconditions: (i) the draft text establishing the Steering Committee and the

Project Implementation Unit has been reviewed by the Bank. The final text was brought to the signature

of MINEPAT; (ii) the recruitment of members of the PIU is ongoing. The evaluation report of the

applications will be submitted to the Bank before the end of October, 2016.

Conditions precedent to first disbursement of the two loans:

First disbursement of ADF and ADB loan resources shall be subject to fulfilment of the following

conditions by the Borrower:

Provide proof of the opening of two bank accounts to receive ADF and ADB loan resources; and

Provide the Bank with proof of the opening of a special CFA.F account in the name of the project at a

commercial bank acceptable to the Bank, to receive counterpart contributions exclusively earmarked

for operating expenses.

5.3 Compliance with Bank Policies

This project is in compliance with all the Bank’s applicable policies.

VI Recommendation

Management recommends that the Boards of Directors should approve the proposal to grant an ADF

loan of UA 11.21 million and an ADB loan of EUR 14.2 million to the Republic of Cameroon, to finance

the Public Expenditure Efficiency Improvement Support Project under the conditions set out in this

report.

Page 27: CAMEROON - afdb.org

I

Annex 1

Comparative Socio-economic Indicators of the DRC

Year Cameroon Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 475 30 067 94 638 36 907Total Population (millions) 2016 23,9 1 214,4 3 010,9 1 407,8Urban Population (% of Total) 2016 55,1 40,1 41,6 80,6Population Density (per Km²) 2016 50,6 41,3 67,7 25,6GNI per Capita (US $) 2014 1 360 2 045 4 226 38 317Labor Force Participation *- Total (%) 2016 76,1 65,6 63,9 60,3Labor Force Participation **- Female (%) 2016 71,1 55,6 49,9 52,1Gender -Related Dev elopment Index Value 2007-2013 0,872 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2014 122 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2008-2013 29,3 42,7 14,9 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 2,5 2,5 1,9 0,4Population Grow th Rate - Urban (%) 2016 3,5 3,6 2,9 0,8Population < 15 y ears (%) 2016 42,3 40,9 28,0 17,2Population >= 65 y ears (%) 2016 3,2 3,5 6,6 16,6Dependency Ratio (%) 2016 83,6 79,9 52,9 51,2Sex Ratio (per 100 female) 2016 100,0 100,2 103,0 97,6Female Population 15-49 y ears (% of total population) 2016 24,0 24,0 25,7 22,8Life Ex pectancy at Birth - Total (y ears) 2016 56,4 61,5 66,2 79,4Life Ex pectancy at Birth - Female (y ears) 2016 57,6 63,0 68,0 82,4Crude Birth Rate (per 1,000) 2016 35,7 34,4 27,0 11,6Crude Death Rate (per 1,000) 2016 10,9 9,1 7,9 9,1Infant Mortality Rate (per 1,000) 2015 57,1 52,2 35,2 5,8Child Mortality Rate (per 1,000) 2015 87,9 75,5 47,3 6,8Total Fertility Rate (per w oman) 2016 4,6 4,5 3,5 1,8Maternal Mortality Rate (per 100,000) 2015 596,0 495,0 238,0 10,0Women Using Contraception (%) 2016 30,0 31,0 ... ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2013 7,7 47,9 123,8 292,3Nurses and midw iv es (per 100,000 people) 2004-2013 43,8 135,4 220,0 859,8Births attended by Trained Health Personnel (%) 2010-2015 64,7 53,2 68,5 ...Access to Safe Water (% of Population) 2015 75,6 71,6 89,3 99,5Healthy life ex pectancy at birth (y ears) 2013 50,3 54,0 57 68,0Access to Sanitation (% of Population) 2015 45,8 39,4 61,2 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2014 4,8 3,8 ... ...Incidence of Tuberculosis (per 100,000) 2014 220,0 245,9 160,0 21,0Child Immunization Against Tuberculosis (%) 2014 99,0 84,1 90,0 ...Child Immunization Against Measles (%) 2014 80,0 76,0 83,5 93,7Underw eight Children (% of children under 5 y ears) 2010-2014 15,1 18,1 16,2 1,1Daily Calorie Supply per Capita 2011 2 586 2 621 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 0,9 2,6 3,0 7,7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2015 113,6 100,5 104,7 102,4 Primary School - Female 2010-2015 106,9 97,1 102,9 102,2 Secondary School - Total 2010-2015 56,4 50,9 57,8 105,3 Secondary School - Female 2010-2015 51,9 48,5 55,7 105,3Primary School Female Teaching Staff (% of Total) 2010-2015 52,7 47,6 50,6 82,2Adult literacy Rate - Total (%) 2010-2015 75,0 66,8 70,5 98,6Adult literacy Rate - Male (%) 2010-2015 81,2 74,3 77,3 98,9Adult literacy Rate - Female (%) 2010-2015 68,9 59,4 64,0 98,4Percentage of GDP Spent on Education 2010-2014 3,0 5,0 4,2 4,8

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2013 13,1 8,6 11,9 9,4Agricultural Land (as % of land area) 2013 20,6 43,2 43,4 30,0Forest (As % of Land Area) 2013 40,7 23,3 28,0 34,5Per Capita CO2 Emissions (metric tons) 2012 0,3 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

August 2016

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

Cam eroon Africa

0

500

1000

1500

2000

2500

20

00

20

05

20

08

20

09

20

10

20

11

20

12

20

13

20

14

GNI Per Capita US $

Cam eroon Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Cameroon Africa

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

Cam eroon Africa

Page 28: CAMEROON - afdb.org

II

Annex 2

Analysis of the Bank’s Active Portfolio as of 30 June 2016

The Bank’s active portfolio in Cameroon as of 30 June 2016

comprised 20 projects worth a total commitment of UA

723,479 million (USD 1.012 billion), with a substantial

regional component (29.4%), broken down as follows: UA

602.977 million (USD 843.468 million) for the public sector

(10 national and 6 regional projects) and UA 120.501 million

(USD 168.561 million) for the private sector (4 projects). The

Congo Basin Forest Fund (CBFF) portfolio in Cameroon

comprises 2 ongoing projects that will end on 12/31/2016,

namely the IUCN Project and the Wildlife School Project in

Garoua. The public projects portfolio is divided among the

following sectors: transport and ICT (68%), water and

sanitation (12%), energy (13%), agriculture and the

environment (5%), and governance (2%).

The national public sector portfolio performance is deemed to be satisfactory with a score of 2.36 on 3

in 2014 and is on an upward trend. In the last four reviews, this score was 2.06 (in 2011), 2.15 (in 2012)

and 2.3 (in 2013). The actions taken by the Bank and the Borrower have resulted in a steady rise in the

value of this indicator since 2009 (see graph). The Bank’s actions include high-level dialogue with

national authorities, capacity-building for project management units and very close monitoring of the

files pending at the Bank. The Borrower’s actions essentially relate to the organization of regular

quarterly project monitoring meetings.

Rating of Active National Public Sector Projects Based on 2011-2014 Reviews

Projects

Satisfa

ction

of

conditi

ons

Procurements

performance

Financial

performance

Activities and

outcomes

Progress

status

Impact on

development

Overall

score Risk rating

Multi-sector

PAMOCCA 2.50 2.00 2.00 2.00 2.09 2.00 2.10 NON-PP/NON-PPP

Water and Sanitation Sector

PAEPA –MSU 2.00 1.50 2.40 2.00 2.00 2.00 1.98 NON-PP/NON-PPP

PAEPA –MRU 2.66 2.50 2.20 2.25 2.36 3.00 2.50 NON-PP/NON-PPP

Energy Sector

PRERETD 2.33 2.50 2.60 2.00 2.36 2.00 2.30 NON-PP/NON-PPP

LOM PANGAR 3.00 2.00 2.00 2.00 2.00 3.00 2.33 NON-PP/NON-PPP

Transport Sector

NUMBA-BACHUO 3.00 3.00 2.75 2.00 2.55 3.00 255 NON-PP/NON-PPP

BATCHENGA STUDY 3.00 2.00 2.75 2.00 2.55 3.00 2.55 NON-PP/NON-PPP

Agricultural Sector

GRASSFIELD II n/a n/a n/a n/a n/a n/a n/a

2014 review average 2.64 2.21 2.39 2.07 2.29 2.57 2.36

COMPARISON WITH PREVIOUS REVIEWS

2013 review average 2.49 1.92 2.50 2.00 2.25 2.35 2.30

2012 review average 2.15 2.15 2.14 1.93 1.92 2.38 2.15

2011 review average 2.19 2.03 1.92 1.81 1.79 2.33 2.06

KEY: PP = problematic project PPP = Potentially problematic project

Non-PP = non-problematic project Non-PPP = non-potentially problematic project

Excellent Performance (2.2 - 3.0)

Average Performance (1.6 - 2.1)

Poor Performance (0 - 1.5)

Source: SAP-PS and 2012 Portfolio Review Report. This table does not include the IRAD Support Project funded by the NTF and

2,04 2,06

2,15

2,3

2,36

1,8

1,9

2

2,1

2,2

2,3

2,4

2009 Review 2011 Review 2012 Review 2013 Review 2014 Review

Figure 3: Portfolio Performance Scores from 2009 to 2014

Page 29: CAMEROON - afdb.org

III

Annex 3

Summary Table of Donor Operations

Matrix of Donors in

Cameroon

2014

EU ** ** ** ** ** ** ** ** ** ** ** ** ** ** 4

Germany ** ** ** ** ** ** ** ** 4

Belgium

Denmark

Spain

France-AFD

France-SCAC

Italy

Luxemburg

United Kingdom ** ** ** ** ** ** ** ** ** ** 7

Other Bilateral Partners

Canada

United States

Japan ** ** ** ** ** ** ** ** ** ** 6

Switzerland

Multilateral Partners

IAEA

AfDB ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** 5

World Bank

** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** ** **

7

BDEAC

ECA

FAO

UNCDF

IFAD ** ** ** 1

IMF ** ** ** ** ** 1

UNFPA

OCHA/CERF

WHO ** ** ** ** 1

UNAIDS

WFP

UNDP ** ** ** ** ** ** ** ** ** ** ** ** 5

UNESCO

UNICEF

UNIFEM

Active TFPs 2 2 3 4 3 2 4 5 5 3 5 4 4 4 3 4 1 2 4 2 4 2 8 7 6 5 3 1 1 4 0

RURAL SECTOR SOCIAL SECTOR

NA

TIO

NA

L S

OL

IDA

RIT

Y A

ND

SO

CIA

L J

US

TIC

E

SO

CIA

L A

ND

FA

MIL

Y E

DU

CA

TIO

N

Nu

mb

er o

f S

ecto

rs p

er A

ctiv

e P

art

ner

DE

VE

LO

PM

EN

T O

F C

RO

P, L

IVE

ST

OC

K, F

ISH

ER

IES

AN

D

SIL

VIC

UL

TU

RA

L P

RO

DU

CT

ION

IMP

RO

VE

ME

NT

OF

TH

E L

IVIN

G E

NV

IRO

NM

EN

T

SU

ST

AIN

AB

LE

NA

TU

RA

L R

ES

OU

RC

E M

AN

AG

EM

EN

T

ST

RE

NG

HT

EN

ING

OF

TH

E I

NS

TIT

UT

ION

AL

LE

GA

L

FR

AM

EW

OR

K A

ND

CA

PA

CIT

Y-B

UIL

DIN

G

EDUCATION SECTOR HEALTH SECTOR GOVERNANCE SECTOR INFRASTRUCTURE SECTOR INDUSTRY AND SERVICES SECTOR

ST

AN

DA

RD

S A

ND

QU

AL

ITY

DE

VE

LO

PM

EN

T

TO

UR

ISM

DE

VE

LO

PM

EN

T A

ND

PR

OM

OT

ION

EM

PL

OY

ME

NT

AN

D V

OC

AT

ION

AL

TR

AIN

ING

INS

TIT

UT

ION

AL

FR

AM

EW

OR

K I

MP

RO

VE

ME

NT

PR

EV

EN

TIO

N A

ND

SO

CIA

L W

EL

FA

RE

DE

VE

LO

PM

EN

T O

F T

HE

NA

TIO

NA

L B

AC

KB

ON

E

INS

TIT

UT

ION

AL

CA

PA

CIT

Y-B

UIL

DIN

G

DE

NS

IFIC

AT

ION

OF

TH

E N

AT

ION

AL

EN

TR

EP

RIS

E F

AB

RIC

MA

RK

ET

AC

CE

SS

DE

VE

LO

PM

EN

T A

ND

SU

PP

OR

T

DE

NS

IFIC

AT

ION

OF

DE

VE

LO

PM

EN

T R

ES

EA

RC

H A

ND

INN

OV

AT

ION

DE

VE

LO

PM

EN

T

         Areas of Intervention by Cameroon's Development Partners in 2014

BA

SIC

ED

UC

AT

ION

, S

EC

ON

DA

RY

ED

UC

AT

ION

,

EM

PL

OY

ME

NT

AN

D V

OC

AT

ION

AL

TR

AIN

ING

HIG

HE

R E

DU

CA

TIO

N

MA

TE

RN

AL

, IN

FA

NT

AN

D A

DO

LE

SC

EN

T H

EA

LT

H

DIS

EA

SE

CO

NT

RO

L

HE

AT

H P

RO

MO

TIO

N

MA

NU

FA

CT

UR

ING

PR

OD

UC

TIO

N D

EV

EL

OP

ME

NT

AN

D

SU

PP

OR

T

PL

AN

ING

CA

PA

CIT

Y-B

UIL

DIN

G

FIN

AN

CIA

L M

AN

AG

EM

EN

T A

ND

CO

NT

RO

L C

AP

AC

ITY

-

BU

ILD

ING

ST

RE

NG

TH

EN

ING

OF

CIT

IZE

N A

ND

CIV

IL S

OC

IET

Y

PA

RT

ICIP

AT

ION

IN

PU

BL

IC A

FF

AIR

S M

AN

AG

EM

EN

T A

ND

LO

CA

L D

EV

EL

OP

ME

NT

MO

DE

RN

IZA

TIO

N O

F S

TA

TE

IN

ST

ITU

TIO

NS

(C

IVIL

SE

RV

ICE

, N

AT

ION

AL

AS

SE

MB

LY

, J

US

TIC

E)

INP

RO

VE

ME

NT

OF

TH

E B

US

INE

SS

EN

VIR

ON

ME

NT

AN

D

PR

OM

OT

ION

OF

PU

BL

IC-P

RIV

AT

E P

AR

TN

ER

SH

IP

CO

RR

UP

TIO

N C

ON

TR

OL

INF

RA

ST

RU

CT

UR

E M

AIN

TE

NA

NC

E

RE

HA

BIL

ITA

TIO

N O

F E

XIS

TIN

G I

NF

RA

ST

RU

CT

UR

E A

SS

ET

S

Source : Provisional Mapping Report/Labour Division

Page 30: CAMEROON - afdb.org

IV

Position of TFPs under the Various Pillars of Public Finance Reform

Public Finance Reform Intervention Pillars

TFP

AfDB (*) WB IMF EU GIZ/K

FW FRANCE

Thematic pillars

Planning-Programming-Budgeting X X X

Budget execution (revenue) X

External financing X

Budget execution (expenditure) X X X

Government accounting, X X X X

Cash flow and debt management X X

Internal and external control structures X X

Crosscutting pillars

IT systems X X X X X

Human resources and payroll management X X

Institutional and organizational framework of public

finance management and capacity building in piloting and

communicating on reforms

X X

(*) The Bank's position is in relation to the Public Expenditure Efficiency Improvement Support Project

Page 31: CAMEROON - afdb.org

V

Annex 4

Justification of the Government Counterpart Contribution Amount

1. The Public Expenditure Efficiency Improvement Support Project, estimated at a total of

UA 23.52 million, will be financed by the Bank Group and national counterpart contributions. The

Bank Group intervenes through an ADF loan of UA 11.21 million and an ADB loan of EUR 14.2

million, making a total of UA 22.48 million or 95.6% of the project cost. The national counterpart

contribution is estimated at UA 1.03 million, or 4.4% of the total project cost. This counterpart

contribution amount represents the amount of resources that the country can currently provide

without compromising project implementation.

2. The Government's counterpart contribution relative to Bank financing is below 10% of the

ADF funding and 50% of ADB funding, as required by the policy on eligible expenditures. Pursuant

to Section 4.2.2 of the Policy on Expenditure Eligible for Bank Group Financing (revised version

of 19 March 2008), which stipulates that Bank financing under the ADB and ADF windows, may

exceed the thresholds of 50% and 90%, the Government's counterpart contribution amount was

determined based on the following four criteria:

country commitment to implementing its general development programme;

financing allocated by the Country to sectors targeted by Bank assistance;

the country's budget situation and debt level; and

the upper limit on cost-sharing and guidelines specified in the Country Financing

Parameters.

Country Commitment to Implementing its General Development Programme

3. Drawing on the lessons learnt from implementation of its poverty reduction strategy after

attainment of the HIPCI Initiative in 2006, the Government formulated its development Vision 2035

in 2010. This long-term vision seeks to transform Cameroon into an emerging democratic State that

is united in diversity. Specifically, Vision 2035 is the reference framework for (i) substantially

reducing the poverty threshold; (ii) attaining the status of a middle-income country; (iii) becoming

a new industrialized country; and (iv) consolidating the democratic process and national unity.

4. These specific objectives informed the guidelines of the Growth and Employment Strategy

Paper (GESP) for 2010-2020 which covers the first ten years of Vision 2035. The main issues in

GESP implementation are growth acceleration, creation of formal jobs and poverty reduction.

Consequently, the targets are to (i) raise the growth rate to an annual average of 5.5% during the

2010-20 period; (ii) cut underemployment from 75.8% to at least 50% in 2020; and (iii) reduce the

poverty rate from 39.9% in 2007 to 28.7% in 2020.

5. To achieve these objectives, the Government decided to implement a three-pronged

strategy, following a coherent and integrated approach with the support of technical and financial

partners (TFPs), including the Bank. This three-pronged strategy comprises: (a) a growth strategy;

(b) a national governance and strategic management improvement strategy; and (c) a job strategy.

6. This operation is presented to the Boards in a specific context characterized by Cameroon's

graduation to the ADB window as a blend country. Indeed, given its recent macroeconomic

performance, Cameroon graduated in 2014 to the non-concessional windows of both the World

Bank and the AfDB Group. This double graduation attests to the confidence of the multilateral

institutions and enables the country to obtain resources from both the concessional and non-

concessional windows of the AfDB Group. It should enable the country to finance its development,

especially its ambitious infrastructure programme, on less expensive terms. The country's next target

is to graduate from "blend country" to "ADB country".

Page 32: CAMEROON - afdb.org

VI

7. In the area of governance, especially public finance governance, the Government

implemented major reforms in 2007 that led to the adoption of programme budgets from 2013. A

public finance modernization plan, jointly prepared with the TFPs, determined the priority reform

pillars. In the years to come, the Government intends to improve the preparation and implementation

of the public investment budget, enhance investment project maturation, review the procurement

code and gradually digitalise public procurement, improve energy sector regulation and promote

renewable energy, and lastly, enhance the maintenance of transport infrastructure.

8. This project is predicated on a strong Government commitment to implement the various

reforms designed to increase the impact of public spending in general and public investments in

particular, on the well-being of the people. The Government contributes to project implementation

mainly by financing the project maturation fund, as its way of taking ownership of the project to

ensure the sustainability of targeted outcomes. It also contributes to project management costs.

Country Allocations to Sectors Targeted by Bank Assistance

9. The road transport and energy sub-sectors respectively account for approximately 25% and

12% of public investments. Over the last five years, the Bank has allocated a significant amount of

resources to the financing of transport and energy infrastructure in Cameroon. All transport sector

activities cost a total of UA 265 million used to pave 503 km of road, with an estimated Government

contribution of UA 67 billion, or 25.8% of investments made during the review period. Bank

financing to the energy sector amounts to UA 165 million, of which 54% goes to the private sector.

These statistics attest to the importance that the Government attaches to the transport and energy

sectors, and reinforce the need to ensure the sustainability of investments in these sectors.

Budget Situation and Debt Level of the Country

10. Fiscal policy has remained moderately expansionist, owing to the implementation of major

infrastructure projects. The 2016 finance law, like those of 2014 and 2013, was drafted and

implemented using the programme budget method.5 The budget deficit was estimated at 5.3% of

GDP in 2015 compared to 3.9% in 2014. The current account deficit remains structural and

fluctuates between 14% and 15% of GDP, reflecting the marked decline in oil prices. The monetary

policy is aimed at stabilizing prices and the real effective exchange rate, by avoiding any crowding-

out of private investment by Government spending. However, inflation remains below the CEMAC

area convergence threshold of 3%.

Table 1: Key Macroeconomic Indicators of Cameroon

2011 2012 2013 2014 2015 Forecasts

2016

Real GDP growth 4.1% 4.6% 5.6% 5.9 5.9% 4.9%

Inflation (annual average) 2.9% 2.4% 2.1% 1.9% 2.70 2.2%

Total budget balance

(excluding grants) as % of

GDP

-3.1% -2.0% -4.3% -5.0% -6.1 -8.2%

Public debt (as % of GDP) 13.2% 15.4% 18.7% 28.0% 33.5% 38.0%

Current account balance (as

% of GDP) -3.0% -3.6% -3.9% -4.4% -5.8% -5.7%

Sources: Regional Economic Outlook: Sub-Saharan Africa (IMF), 2016.

5 Pursuant to CEMAC Directive No. 01/11-Ueac-190-CM-22 on finance laws, which institutes the transition from means-based budgeting to programme

budgeting.

Page 33: CAMEROON - afdb.org

VII

11. Debt ratios have remained below CEMAC thresholds since cancellation of the debt

under the HIPC Initiative in 2006. However, escalation of the national debt over the past three

years following the structural fall in oil prices increasingly poses a risk of debt distress.

According to IMF estimates,6 the public debt rose from 18.7% of GDP in 2013 to 28% in

2014, and then to 33.5% in 2015. Based on these trends, the public debt is projected to exceed

41.3% of GDP in 2017, which is more than double its value at end-2013, while debt servicing

should also double in the medium term. Given this adverse trend and the decline in export

earnings due to falling oil prices from 2014, Cameroon’s external debt distress risk gradually

increased from 'low' to 'medium' and, ultimately, 'high' from 2015.7

12. By contributing to the improvement of public expenditure efficiency and

effectiveness, this project is implementing the recommendation from the 2015 IMF Article IV

consultations, calling for more prudent public debt management and the improvement of

public expenditure profitability. Furthermore, the project will enable the Government to

enhance the planning and streamlining of its budgetary choices and especially its public

investments.

Cost-Sharing Upper Limits and Guidelines Specified in Country Financing Parameters

13. Country Financing Parameters (CFP) governing cost-sharing highlight the need for

national commitment to, and ownership of, project activities financed by the Bank. These

parameters also provide flexibility in determining the percentage of the national counterpart

contribution. The Bank reviewed the level of commitment and ownership based on criteria

that includes: (i) the contribution of project activities to the achievement of national

development goals set out in the Growth and Employment Strategy Paper (GESP) for 2010-

2020; (ii) alignment and linkages with the strategic pillars of the Bank’s 2015-2020 Country

Strategy Paper (CSP) for Cameroon approved in July 2015, and inclusion in the State budget

of the project financed by the Bank and other Technical and Financial Partners. The CFP

stipulates that the percentage of total costs financed by the Bank will be evaluated on a case-

by-case basis, depending on the context and specific considerations of the project, the level of

Government commitment to and ownership of project implementation, the level of co-

financing with other TFPs, and the country's budget situation. It should be noted that the

parameters are aligned on the World Bank’s CFP in Cameroon developed in 2005 when the

country was only eligible to concessional resources. The CFPs indicated that World Bank

funding could reach 100% of the total project cost (including taxes), despite the fact that co-

financing could be obtained for some projects, especially in the transport sector. These

parameters have not changed despite Cameroon's graduation to the status of an IBRD/IDA

"blend country" in April 2014 at the World Bank and an ADB/ADF “blend country” in July

2014 at the African Development Bank.

14. In conclusion, given the above facts, and at the request of the Government, it is

proposed that the national counterpart contribution be set at 4.4% of the total project

cost, net of taxes. The contribution of the Government of Cameroon (UA 1.04 million), will

be used to finance the investment projects maturation fund and some of the project

management costs.

6 Regional Economic Outlook Report, 2016: Sub-Saharan Africa 7 A new debt sustainability analysis will be jointly conducted for Cameroon by the IMF and the World Bank in October 2016, as part of the Article IV

consultations.

Page 34: CAMEROON - afdb.org

VIII

Annex 5

Map of the Project Area

The staff of the ADB Group have provided this map for the exclusive use of readers of this report to which it is appended. The appellations and the

demarcations on this map do not imply any judgment on the part of the ADB Group and its members concerning either the legal status of a territory

or the approval or acceptance of its boundaries.