    CAUSES & REMEDIAL MEASURESOF BREACHES IN IRRIGATION

    CANALS

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    3/28

    3

    Introduction

    STATISTICS OF PUNJAB IRRIGATION SYSTEM

    Barrages 14

    Length of Irrigation Canals 23,184 Miles

    CCA 21 Million Acres

    Canal Systems 24

    Capacity of Canal System 1.1 lacs cusecs

    Outlets 58,000

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    4/28

    4

    Objectives

    Identification of causes for occurrence of

    breaches.

    How to avoid breaches by Proper upkeep &

    maintenance of channels.

    Remedial Measures.

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    5/28

    5

    Sources/Causes of Breaches

    Natural Disasters

    Human Interference

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    6/28

    6

    Occurrence Of Breaches Due To

    Natural Disasters

    Heavy Rains

    Wind Storms

    Falling Of Dead And Hollow Trees

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    7/28

    Heavy Rains

    7

    CANAL FLOWING ABOVE FSL DUE TO HEAVY RAIN

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    8/28

    Wind Storms

    8

    WIND WAVE ACTION CAUSING EROSION AND ULTIMATELY BREACH

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    9/28

    Falling of Dead Trees

    9

    TREE CAUSING HEADING UP U/S CAUSING OVERFLOW OF WATER

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    10/28

    Occurrence Of Breaches Due To

    Human Interference Obstruction of Flow

    Cutting of Banks

    Tampering Channel Heads

    Trespassing Encroachment of Banks

    Unauthorized Use of

    service Roads

    Breaching of Banks due toPiping

    Breaching of Banks from

    Instability

    Poor Compaction of Banks

    Sudden Draw down ofwater/Sloughing

    Vegetation Growth

    Construction of Water

    Course along the channel

    10

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    11/28

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    12/28

    Cutting of Banks/Removal of outlets

    12

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    13/28

    Trespassing

    13

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    14/28

    Encroachment of Banks

    14

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    15/28

    Unauthorized Use of Service Roads

    15

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    16/28

    Breaching of Banks due to Piping

    16

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    17/28

    Breaching of Banks from Instability

    17

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    18/28

    Poor Compaction of Banks

    18

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    19/28

    Damage due to Sudden Draw down

    19

    SLOUGHING

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    20/28

    Vegetation Growth

    20

    GROWTH OF VEGETATION

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    21/28

    Construction of Water Course along

    the Channels

    21

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    22/28

    How To Avoid Breaches?

    Proper maintenance of canal

    Formation of berms

    Dowels to be provided

    Sarkanda growth to be inhibited

    Dead trees to be removed

    Escape channels must be

    operational

    Trespassing to be prohibited

    Unauthorized use of service

    road to be avoided

    Strict action against the culprits

    of water theft

    Syphon pipes of tube wells to be

    avoided

    Porcupine holes and Raingharas shall be attended

    forthwith

    Water courses along the

    channel must be avoided

    Proper surveillance of channelsshould be done

    Construction of recharge wells

    22

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    23/28

    Closing of Breaches Arranging reduction of canal supply from head of the channel.

    Closing of channel as per regulation orders.

    Collection of earth on upstream and downstream of the bank.

    A ring bund is marked at the breach site for filling of earth when

    less or no water is passing through the breach.

    Earth filling on the alignment on the ring bund shall be done withcompaction in layers till the top level of the bank is attained.

    Bamboos / Killa bushing is done in the design berm width along the

    breach site with 50 ft. up / down stream of the breach.

    Additional Pushta with the bank is also provided at the breach site

    to cover the Hydraulic gradient.

    Upon complete satisfaction that the breach site is properly

    closed,canal supply is restored in the channel as per regulation

    orders.

    23

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    24/28

    Conclusion

    Human Interference plays an important part as

    the cultivators dont want to miss any

    opportunity to irrigate their lands.

    Cultivators are compelled to do so because ofincrease in intensity of irrigation.

    Field staff Negligence.

    24

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    25/28

    Recommendations

    Escape Channels should be opened in heavy

    rains to divert and enhance capacity of the

    channels.

    The recharge well would be used to take thewater diverted from the irrigation channels

    whenever there was no demand of water from

    farmers. The farmers would be urged torelease water into the recharge well instead of

    closing the outlets.

    25

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    26/28

    Cont

    The capacity of irrigation channels should be doubledto match with the intensity.

    All Minor Distributaries, Minors and Sub Minors are

    required to be lined especially in brackish zones.

    Enforcement of law and order should be ensured in

    letter and spirit to eliminate cuts and breaches in

    irrigation channels. 1 No. ASI and 3 No. Constables

    should be deployed with the SDCOs for summoning

    the culprits under Section 70 of Canal and Drainage

    Act and frequent watching of channels in the critical

    reaches.

    26

  • 8/12/2019 Breaches in Canal, Causes & remedial measures

    27/28

    Cont

    The offenders causing damages to the channelsby making deliberate cuts should be tried

    under Section 70 of Canal and Drainage Act

    1873, amended 2006.

    FIRs should be registered against the culprits

    and such type of offences should be declared as

    non-bail able.

    Close liaison among Irrigation, Police andRevenue Department is required at particular

    hierarchy to get the optimum results.

    27