Upload
rt1973
View
215
Download
0
Embed Size (px)
Citation preview
8/3/2019 BMS Corrected Table
1/14
MANAGEMENT OF PLANNED MAINTENANCE
AUTOMATIC CONTROL & BMS SYSTEMS TASK INSTRUCTIONS TASK
MANAGEMENT OF PLANNED MAINTENANCE
AUTOMATIC CONTROL AND BMS SYSTEMSTASKS43.1, 43.2, 43.3
HEALTH AND SAFETY
1.1 Comply with any specific warning notices or site restrictions as identified within the site
safety plan held by the responsible person, and with any other specific/temporary hazards
identified during site induction/at time of visit.
1.2 Relevant PPE shall be used as indicated by the relevant risk assessment
1.3 Caution should be exercised where surface temperatures are above 50C to avoid injury
through accidental contact.1.4 A specific risk assessment, to satisfy The Management of Health & Safety at Work
Regulations and any other statutory regulations,ect... must be made prior to carrying outany task detailed below. Risk assessments are to be carried out by the operatives
employer
1.5 Where required under safe working procedures, a permit to work shall be obtained from
the responsible person before any work is commenced. For other, limited tasks suitablecare shall be taken to ensure proper electrical isolation of plant before removing covers
etc. or before working on normally moving parts
2. GENERAL REQUIREMENTS
2.1 This task is to be undertaken only by suitably and properly trained staff having
knowledge of the installed system, an up to-date awareness of the manufacturersequipment including computer hardware and software, have access to up to-date
diagnostic equipment, have good technical support, and are supported by adequate stocks
of spares.
2.2 To ensure that the systems being controlled are operating within stated parameters.
2.3 Liase with the building managers where access to building internal areas is required
before starting and when finishing work.
2.4 All measuring equipment shall have a current certificate of calibration: Certificate No
shall be written on PPM work sheet2.5 It is the Responsible Persons responsibility to produce an inventory of all actuators,
sensors, and control devices in each building for issue with the checklist.
2.6 Checklist 1 is for use with Task 043.12.7 Checklist 2 is for use with Task 043.2
2.8 Checklist 3 is for use with Task 043.3
2.9 The attached Checklist is to be included on the Work Docket issued to the craftsman. A
copy of the Task Instructions is to be available to the craftsman for information
2.10 Record all inspection findings. All items requiring repair shall be listed on the PPM
work docket, any repairs carried out under the Contract Lump Sum shall be indicated assuch, any other items in this category requiring shut downs or spares shall be carried out
8/3/2019 BMS Corrected Table
2/14
MANAGEMENT OF PLANNED MAINTENANCE
following agreed procedures. Any deviation from accepted operation or any defects
considered to present a safety hazard shall be reported to the responsible person, who
will advise the client as required.
2.11 The attached task instructions highlight the basic elements that should be carried out as a
minimum requirement. The sub-contractor may adopt these instructions or submit theretheir own method statements for approval. The task instructions provided are generic in
form and will require modifying to suit specific equipment/systems being maintained. It
should be noted that the full requirements of the relevant reference documents must becomplied with; the list provided here is not exhaustive. Lead reference documents:
Heating and Ventilation Contractors Association Standard Maintenance Specification
Volume 3 Control Energy and BMS Systems: 1998 BS EN 12098-1:1997 Controls for heating systems. Outside temperature control equipment
for hot water heating systems. BS EN 12098-2:2001 Controls for heating systems. Optimum Stop-Start control equipment
for hot water heating systems. 01/710844DC prEN 12098-3. Controls for heating system. Part 3 outside temperature
compensated control equipment for electrical heating systems.
BS 5384:1977 Guide to the selection and use of control systems for heating, ventilation and
Air Conditioning installations. 99/712285 DC-prEN 13646. Building control systems equipment characteristics. 99/712286 DC-prEN ISO 16484. Building control systems. Part 1 Overview and
definitions.
99/712287 DC-prEN ISO 16484. Building control systems. HVAC control systemfunctionality.
MEEG Vol. 5 Section12
HSE Guidance Note GS 38-Electrical test equipment for use by electricians 1995
HS(R) 25 - Memorandum of Guidance on the Electricity at Work Regulations 1989.
HSG 85 Electricity at Work. Safe working Practices 1993
Task Numbers AD-PPM-043 is to be shown on all work dockets as appropriate
*Mandatory Frequencies to individually assess per site, approved through Authorizing EngineersTable below guideline only.
Task No Task LeadRef.
Status Frequency Remarks
43.1 Check operation of all safety
alarms, interlocks, indicators
and devices. Back-up all
software & archive. Inspect allpanels internally and
HVC
AVol. 3
Mandatory 6
MONTHLY
(6M) or asreqd
8/3/2019 BMS Corrected Table
3/14
MANAGEMENT OF PLANNED MAINTENANCE
externally.
43.2 Check
operation/function/accuracy of
all sensors, actuators, alarms,
time programmes
HVC
AVol. 3
Mandatory ANNUALL
Y (1Y)
43.3 Inspect, clean, service, adjust
& overhaul all components ofthe system
HVC
AVol. 3
Mandatory ANNUALL
Y (1Y)
TASK 043.1 (6M) CHECK OPERATION OF SAFETY ALARMS, INTERLOCKS INDICATORS AND DEVICES.
BACKUP ALL SOFTWARE AND ARCHIVE. INSPECT ALL PANELS INTERNALLY & EXTERNALLY
PROCEDURES
CENTRAL OPERATOR STATION
1. Cables and connectors. Check security, integrity and for physical damage.2. Perform routine diagnostic tasks on computer (where appropriate) and check operation.This routine will check all aspects of computer hardware and software.
8/3/2019 BMS Corrected Table
4/14
MANAGEMENT OF PLANNED MAINTENANCE
3. Check operation and clean, Disc drives, Tape drives, Tape cassettes, Keyboards,VDUs, Monitors, Printers etc. (where appropriate), according to the manufacturer's
instructions.
4. Clock battery. Check and replace if necessary
5. Cooling fans. Check condition, clean and lubricate if necessary6. Filters Inspect and clean or change as necessary.7. Mouse. Check for smooth operation and clean ball as necessary.8. Software archives. Take back up copy of site-specific data files. Verify operatingprogrammes and functionality. Ensure that security is retained and that any updating of files
is incorporated.
COMMUNICATIONS
1. Data Communications Check integrity of data flow in both directions. If more than onepath exists all must be verified.
2. Central station units Check operation and visually inspect. Check environmentalconditions of all equipment are within prescribed limits, including modems, line drivers,telemetry cables and interface units
3. Central station/out stations Check integrity of data flow in both directions. If more thanone data path exists, all must be verified. Caution - There may be interaction with specialist
applications.
4. Out station hardware. Check mechanical and environmental condition. Noteenvironmental conditions e.g. temperature; humidity should be within manufacturer's
recommended limits.
5. Power supplies. Carry out voltage check on all power supplies. Check automaticrestart, re-booting of software programmed.
6. Stand-by batteries/ uninterrupted power supplies (UPS). Check against manufacturer'sspecification7. Digital inputs. Check by activating (from fixed sensing/control device) Note Careshould be taken to isolate local operation.
8. Digital outputs. Check operation of output stopping by operating routine (whereappropriate). Check switching by software interlocks should include starting and stopping
operations. Note does not apply to connected devices.
9. Analogue inputs. Read and check calibration of analogue inputs.10. Analogue outputs. Check for accuracy of output signal.11. Manual override (physical). Check status. Review and report to client.12. Installed program me. Check integrity, of alarms, interlocks, and optimization.
SOFTWARE FUNCTIONS
1. Control loops: - Check integrity of the installed program me, Check sequence andoperation of control outputs. Check stability of plant, frequency should be agreed with client.
This action should be related to the critical nature of the operation.
8/3/2019 BMS Corrected Table
5/14
MANAGEMENT OF PLANNED MAINTENANCE
2. Optimized start/stop. Verify operation by interrogating software/hardware copy.Building layouts and occupational requirements are seldom of a static nature. Therefore
control strategies and their suitability need to be reassessed on a regular basis.
3. Time clock. Check real time clock for accuracy throughout system.
4. Time switching. Review current operating parameters according to client's needs.5. Data logging. Review existing logs Report to client on the need to review existingarrangements.
6. Alarms (a) faults, (b) out of limit alarms. Check alarms and software interlocks withsafety implications are operating correctly. Check alarm priorities, routings and reactions.
The checking of possible reactions to certain critical alarms and programmers must be
carefully co-ordinate with other trades and building tenants. Where there are safety
implications, verify alarm integrity. Review system of reporting outstanding alarm conditions
and report discrepancies.
7. Alarm management. Review frequencies of generated alarms. Report as appropriate toclient.
8. Power failure and restoration. Check plant start up sequence.9. Generators loading program me. Check plant start up sequence.10. Maximum demand/load shedding Check sequence and operation.11.Load cycling. Check operation.
12. Software interlocks. Verify operation.
13. Plant rotation point, e.g. interfaces with other building services systems such as :-(a) fire,
(b) security, and (c) access.
14. Manual status review Check manual overrides and effect on system, and effect on systemoperation. At client access level review parameters, lockouts, changes, all points inmanual override and forced analogue values. Review findings with client.
OPERATION OF SAFETY ALARMS
Simulate alarm conditions in all controlled systems and prove system fails to program safe
condition.
BACKUP ALL SOFTWARE AND ARCHIVE
The backup copying of data/history to disk is to be carried out. Following backup remove all
unnecessary files and information from hard disc and de-fragment. Leave system in fullyoperational condition.
TASK 43.2 (1Y) CHECK OPERTION/FUNCTION/ACCURACY OF ALL SENSORS,
ACTATORS, ALARMS, and TIME PROGRAMMES
PROCEDURES
SENSORS (e.g. Pressure, Temperature, Relative and Absolute Humidity, Air Quality, CO2,
Velocity, Smoke and Gas, Occupancy and Light Sensitivity)
Check all field devices. Field devices include sensors and actuators linked directly to the
BMS. Sensors and actuators should be recalibrated and maintained at recommended intervalsstated in the maintenance instructions supplied by the manufacturer. This procedure applies
8/3/2019 BMS Corrected Table
6/14
MANAGEMENT OF PLANNED MAINTENANCE
to all types of sensors and thermostats and requires that all safety precautions and safe
working practices be observed.
1. Check security of mountings. Inspect for physical damage.
2. Check for cleanliness. Obscuration of sensors with dust can reduce sensitivity andeffect the signal3. Check termination for tightness and corrosion on Electric cable, and Pneumatic pipework. Check the cable/pipe work locally for fixing and condition.
4. Calibrate sensors. Note settings prior to commencing maintenance.5. Status points which operate very infrequently (e.g. frost status, high/low level limitsetc) are to be activated.
6. The actual value at the sensor should be measured and the value obtained compared tothat displayed at the outstation, central facility etc and corrected accordingly at the central
monitor.
7. Compare the measured value to the control point set value.8. Check the stability of the plant visually and with the aid of a trend log, alter settings toachieve stability.
9. Thermally test for let-by on all valves.10. Change the position of the valve from maximum to minimum, using override facilitieswithin the software, and visually check the operation of the valve, note the sequence of
operation and stroke of all the actuators.11. Inspect all valves for leaks and damage. Clean, service, adjust, and overhaul, asnecessary all components of the system.
12. Sampling pipe work and connections. Inspect for leakage and corrosion. Check forcorrect configuration.
13. Check effect for location influence on sensors. Examples are solar gain, proximity towarm extract vents, cooling towers, etc.14. Test the plant fail-safe position/condition in the event of a power failure with asimulated mains failure condition.
15. Verify correct location and installation as per manufacturer's instructions and check forany extraneous influences.
16. Pneumatics. Particular attention should be paid to the quality of the instrument air.
Check for contamination by dirt, oil or water.17. All sensors should be maintained in accordance with the manufacturer'srecommendations.
18. Special sensors such as are used for glycol concentration, detection of smoke and gas,and sensors used in water treatment may require specialist attention.
When cleaning or working in ducts it is essential that all sensors should be withdrawn
from the duct to prevent damage. Care should also be taken to prevent any damage to
linkages or other control devices
8/3/2019 BMS Corrected Table
7/14
MANAGEMENT OF PLANNED MAINTENANCE
TASK 43.3(1Y) INSPECT, CLEAN, SERVICE, ADJUST & OVERHALL ALLCOMPONENTS OF THE SYSTEM
PROCEEDURES
This procedure applies to all types of automatic control valves and requires that before any
maintenance is undertaken all safety precautions must be adhered to including systemisolation. Care must be taken to ensure that any maintenance does not unduly interfere with
environmental operating conditions.
8/3/2019 BMS Corrected Table
8/14
MANAGEMENT OF PLANNED MAINTENANCE
AUTOMATIC CONTROL VALVES (e.g. Rotary, Butterfly and Ball, Self-Acting,
Solenoid, Check, Pressure Control and Safety, Seat Valves)
There are a large number of valve manufacturers who each call for specific maintenance and lubrication
procedures for their products and to avoid undue repetition it is to be taken as read that the Manufacturer's
maintenance and lubrication instructions for each type shall be used.
1. Inspect, where changes, disconnections or unrecorded settings are found, report and
discuss with client.
2. Note any settings made; i.e.min/max travel balancing valve setting etc.
3. Check valve body and fixings for any signs of corrosion or mechanical damage.
4. Check that pipe flange or screw connections are not leaking.
5. Where fitted, check that the actuator yoke and linkages are secure and not bent or damaged(see page 33).
1. Check correct installation of valve with reference to both type and manufacturer.2. Operate and check for correct travel.3. Check that valve is not letting by excessively. Strip and clean as required4. Inspect for gland leakage
ACTUATORS (e.g. Electrical, Hydraulic, Pneumatic)
When working on equipment it should be noted that any auxiliaries fitted may have supplies
fed from a separate circuit to that of the actuator. Therefore should the actuator supply be
disconnected it should not be taken for granted that the auxiliary supply has also beendisconnected.
Power fail - Motor return actuators are commonly enabled to return to the desired position by
means of an electricity supply independent from the rest of the building. Care should be
taken to monitor the amount of operations left in the batteries and they should be
replaced according to the manufacturer's instructions. Disposal of batteries calls for
special arrangements, which should conform to COSHH requirements.
To check that the actuator is performing its correct task, it is immaterial as to whether it ismounted on a damper, louver, valve or any other piece of equipment. Its purpose is to control
to a position between two limits, by opening, closing or moving appropriate pieces of
equipment.
In the event that the actuator is performing a safety function (i.e. on a fire and smoke damper) it shall
be operated in simulated emergency conditions to prove it actual operation. Lives and property could
depend upon this actuator working properly.
1. Cables. Check for signs of heat, damage, and chafing or water ingress.
2. Mounting. Check mounting is in accordance with the manufacturer's recommendation.3. Anchor points. Check security.
8/3/2019 BMS Corrected Table
9/14
MANAGEMENT OF PLANNED MAINTENANCE
4. Mechanical protection. Check for soundness.
5. Earth bonding. Check connection.
6. Actuator torque. Check torque with a torque wrench. This check is of particular importance
on spring return type actuators because the spring will only have a maximum life span.
Elasticity of the spring and hence the torque will reduce with time, if the torque isinsufficient to complete the action, this could be a hazard to life and property.
7. Working conditions. Check actuator is operating within its design ambient conditions.
8. Check supply voltage and those polarities are correct.
9. Check for presence of control signal and that polarity is correct.
10. Check operation of Auxiliary control functions i.e. on/off switches, frost protection,
position indicators, and feedback potentiometers.11. Check to prove actuator will mechanically open/close valve or damper to its working
limits.
12. Actuator position on power failure. Check for correct position for application when power
fails.
13. Check for signs of leakage of hydraulic fluid or compressed air around actuator seals.14. Check condition of glands and seals. Check pipe work for deterioration. On hydraulic
fluid or compressed air systems
15. Linkage assembly, i.e. nuts bolts, spring, valve stem or damper assembly. Check for wear,
security, and corrosion
16. Check calibration - controller output to actuator position. Note: more than one actuatormay be fed from the control supply.17. Check to ensure that the switches are made to make or break at the correct position and
that they perform their correct function.
CONTROLLERS (e.g. Optimizer, Compensator, Single Input, Unit/Sensor Controllers,
Control Timers, Step Controllers, Time Switches, Multi Input, Indicators, Alarm
Modules, Level Controllers, Speed Controllers, Transducers)
This schedule applies to all types of controllers and requires that all safety precautions and safe working
practices be observed.
SPEED CONTROLLERS Electronic inverter type.
WARNING: - Due to the very high voltages present within this type of controller it is
essential that all safety precautions be strictly followed. The equipment must only be
serviced by competent and qualified personnel. The manufacturer's testing and
maintenance procedures including all safety precautions must be strictly followed.
1. Note all set points found.
2. Check mechanically for security of fixings, incoming cables, pneumatic pipe work andterminal connections for tightness.
8/3/2019 BMS Corrected Table
10/14
MANAGEMENT OF PLANNED MAINTENANCE
3. Visually check controller for signs of damage. (i.e. ingress of dust or moisture).
4. Check all power, pneumatic air and supply tolerances as per manufacturer's
recommendation, and adjust as necessary.
5. Pneumatics. Pay particular attention to the quality of the instrument air. Check for
contamination by dirt, water or oil.6. Outside/Inside air temperature sensor Check for calibration and display accuracy.7. Check program me setting is correct.8. Check Battery condition9. Check that output devices respond to command signals.10.Check Flow temperature sensor.11.Check Controllers and calibrate for correct relationship between outside and flow
temperatures.
12.Check system under control for proper operation.13.Check time taken to complete operation against setting and adjust if required.14.Inspect and check each cam setting/switch assembly.15.Drive motor/gear box. Check operation in both directions16.Check Time switch settings for correct installation within the memory for particular
application. Add, delete or adjust if necessary.
17.Replace battery according to manufacturer's recommendations. All batteries should bedisposed of only in accordance with COSHH requirements.
18.Inspect Transformers for signs of overheating and insulation breakdown.
CONTROL PANELS (e.g. Electrical Services, Starters, Control Relays, Switches,
Lamps, Meters, and Alarms)When working on or testing Control panels it is essential that all local and national
statutory regulations should be observed at all times.
Care should be taken to make sure that all remote circuits associated with the switchgear arepositively isolated before any work is carried out. The isolation should be 'secure' that is it
should either be at the point of work or precautions should be taken to prevent anyone else
switching on again when work is in progress. A circuit, whether power or control should
never be assumed to be 'dead'. Voltage tests should always be carried out with proven test
equipment i.e. a voltage tester should first be checked on a known live source immediately
before use and again after use.
Whenever cables are disconnected from switchgear in the course of maintenance or
replacement, ensure that the cables are suitably insulated and marked for identification for
reconnection.
Visually inspect to ensure plant is operating as expected. Check that any meters fitted show a
correct reading, and any timers are set at the correct times for operation. Check readings
against a known source.
8/3/2019 BMS Corrected Table
11/14
MANAGEMENT OF PLANNED MAINTENANCE
Controllers, electrical and pneumatic control equipment - Electronic controllers and
pneumatic equipment may be found in control panels and details regarding maintenance
schedules can be found in the appropriate sections of this schedule.
1. Check Panel exterior for any physical or mechanical damage. Door locks should bechecked.
2. Inspect Mains isolator (also cubicle isolator) for correct mechanical and electrical
operation. Lubricate any moving parts as required. Check correct operation of door
interlock mechanism and adjust if necessary. Clean out interior.
3. Inspect fuse carrier/fuse holder for signs of overheating. Check fuses rating and
terminations for tightness. Apply grease to fuse holder if required
4. Inspect Circuit breakers for signs of overheating and replace if necessary. Inspect
connections and tighten if necessary. Check operation by tripping or "test" facility, if
fitted.
5. Test Residual current devices. (RCDs) operation using test facility.
6. Carry out electrical test procedures per IEE Regs.7. Check Power contactors for correct mechanical and electrical operation
(a) Strip and clean interior
(b) Inspect and clean magnetic pole faces
(c) Inspect shaded ring for damage and fixed and moving contacts for wear orpitting".
(d) Inspect coil for overheating or insulation breakdown.
(e) Clean out arc shutes. On re-assembly avoid damage or loosening of springs or
contacts, ensure correct mechanical operation and check all electrical connectionsfor tightness and security.
8. Carry out maintenance on all types of Starters as per manufactures instructions.
9. Inspect Thermal overloads for signs of overheating.10. Inspect Magnetic overloads for signs of overheating
11. Check oil levels in dashpots and replenish to correct levels if needed.
12. Inspect Panel wiring for signs of overheating or burn marks.
13. Check that panel is correctly bonded to earth
14. Carry out Flash test within 1.5kV-3.0kV range to detect potential deterioration of the
system. CAUTION - Care should be taken to isolate sensitive equipment.15. Check and energize Circuit to ensure that the indicator is operational. Replace any blown
or discolored bulbs as required.
16. Inspect and check that all grilles are free of any obstructions, clean as required.
17. Inspect and check operation of fan unit
8/3/2019 BMS Corrected Table
12/14
MANAGEMENT OF PLANNED MAINTENANCE
Establishment____________________ Task Group 8
Automatic Control and BMS Systems
Location_________________________ Checklist No1
System-Heating, Cooling Tasks-043.1
System Type-
Frequency- (6M)
Complete cells with S/NS as required
Record any defects here: -
Date-Week Comm. Week No Initials
Task 043.1 Check operation of all safety alarms, interlocks, indicators and devices. Back-up
all software & archive. Inspect all panels internally and externally.CENTRALOPERATORSTATION
COMMUNI-
CATIONS
Check cables and
connectors for
security
Check andreplaceClock
battery ifnecessary
Check and
clean, all
drives,
Keyboards,VDUs, and
Printers
Check and
clean Cooling
fans,
Inspect
Filters and
clean or
change asnecessary
Check
Mouse
clean ball
asnecessary
Back up
Software
archives.
Copysite-
specific
data files
Verify
operating
programmes
Check integrity of
data flow in both
directions
Check
environment
al conditions
are within
limits, for
modems,
line drivers,
telemetry
cables and
interface
units
Check Central
station/out
stations
integrity of
data flow in
both directions
Carry out
voltage check
on all power
supplies.
Check
automatic
restart
Check
Stand-by
batteries/
uninterrup
ted power
supplies
(UPS).
Check
Digital
inputs.
Activating
(from fixed
sensing/con
trol device)
Check
Digital
outputs
operation
Analogue
inputs. Read
and check
calibration of
analogue
inputs.
Read and checkcalibration of
analogue inputs.Analogueoutputs.
Check for
accuracy of
output
signal.
Installedprogramme.
Check
integrity, of
alarms,
interlocks, and
optimisation.
SOFTWARE
FUNCTIONS
Check integrity of the
installed programme,Optimised
start/stop.
Verify
operation
Check real time
clock for
accuracy
Data logging.
Review
existing logs
Check
alarms and
software
interlocks
with safety
implication
s
Alarm
manageme
nt. Review
frequencies
of
generated
alarms
Power
failure
and
restorati
on.
Check
plant
start up
sequence.
Software
interlocks.
Verify
operation
Generator loading
programme. Check
plant start up
sequence.
Maximum
demand/load
shedding
Check
sequence
and
operation.
Check
interfaces with
other systems
as fire, security,
and access.
Check
manual
overrides and
effect on
system
OPERATION
OF SAFETY
ALARMS
Simulate alarm
conditions in all
controlled systems
fails to programmed
safe condition
BACKUP
ALL
SOFTWARE
AND
ARCHIVE
Remove all
unnecessary
files and
information
from hard disc
and de-fragment
Leave system
in fully
operational
condition.
8/3/2019 BMS Corrected Table
13/14
MANAGEMENT OF PLANNED MAINTENANCE
Establishment_____________________ Task Group 8Building Management Systems
Location_________________________ Checklist No2
System-Building Management Systems Tasks-043.2Control EquipmentFrequency- (Y)Indicate S/NS as requiredRecord any defects here: -
Date-Week Comm. Week No.
Check operation/function/accuracy of all sensors, actuators, alarms, time programmes
Date Room Description Equipment type Condition ofequipment
Equipmentoperates correctly
Equipment leftworking in
automatic
Initial
8/3/2019 BMS Corrected Table
14/14
MANAGEMENT OF PLANNED MAINTENANCE
Establishment_____________________ Task Group 8Building Management Systems
Location_________________________ Checklist No3
System-Building Management Systems Tasks-043.3
Control EquipmentInsert S/NS or readingFrequency- (Y)
Record any defects here: - Date-Week Comm. Week No.
Inspect, clean, service, adjust & overhaul all components of the system
Automatic ControlValves
Notesettingsmax/mintravel etc.
Valveconditionand fixing
Linkages condition Correctlyinstalled
Valve letby
Gland leakage Initials
Valve No
Valve No
Valve No
Valve No
Valve No
Actuators Checkactuatortorque
Actuatorconditionand fixing
Supply voltage andpolarities correct
Controlsignal
present andcorrect
Checkauxiliarycontrol
functions
Controlleroutput toactuatorposition
calibration
Actuator No
CONTROLLERState type ofcontroller e.g.
optimiser, levelcontrol
Note all setpoints
Controllerconditionand fixing
Check calibration ofassociated sensors
Programsetting and
timescorrect
Checkpower
suppliesand
batteryback up
Calibrate forcorrect
relationshipbetweensensors
Control Panels Notesettings
Panelconditionand fixing
Condition of electricalservices
Checkcondition of
and testelectrical
equipment
Carry outmaintenan
ce ofstarters
Carry out flashtest 1.5kV-3kV
Panel No
Panel No