Blue Water Bridge. Project Update Michael Szuch, P.E. MDOT. Blue Water Bridge. Over 5,250,000 vehicles Busiest commercial crossings on the northern border. Border Wait Times – Our Biggest Challenge. Peak Volumes During Summer Months May through September Holiday/ Special Events - PowerPoint PPT Presentation

Citation preview

Page 1: Blue Water Bridge

Blue Water BridgeProject Update

Michael Szuch, P.E. MDOT

Page 2: Blue Water Bridge

Blue Water Bridge

• Over 5,250,000 vehicles• Busiest commercial crossings on the northern

border

Page 3: Blue Water Bridge

Border Wait Times – Our Biggest Challenge

• Peak Volumes During Summer MonthsMay through SeptemberHoliday/ Special Events

• Wait times (30 minutes to 2+ hours)

Page 4: Blue Water Bridge

What we are trying to avoid…

What we had…

Page 5: Blue Water Bridge

Addressing Concerns

• 2002-2009-Environmental Study to Design and Approve a new U.S. Plaza to alleviate the congestion

$$$$ No Funding $$$$

• 2010-2011- Revised Solution for the U.S. PlazaAlso Stalled $$ No Funding $$

Page 6: Blue Water Bridge

In the Short - Term

• We must improve wait times!

• Creating a unique partnership including:– Blue Water Bridge Canada (BWBC)– Michigan Department of Transportation (MDOT)– US-CBP– US-GSA

Page 7: Blue Water Bridge

Consider the Constraints• Funding• Land locked - The U. S. Plaza is elevated 25 feet

Page 8: Blue Water Bridge

Solution

• Additional Primary Inspection Lanes– Increase Processing Capacity– Reduce Wait Times

• To include– 3 Stacked Booths– 3 Staggered Booths

Page 9: Blue Water Bridge
Page 10: Blue Water Bridge

Project Details

• Design - Fall of 2011• Let – February 2012• Construction – Spring/Summer 2012• Project costs = $1.5million

Page 11: Blue Water Bridge

Construction

Page 12: Blue Water Bridge

Setting the booths

Page 13: Blue Water Bridge

Schedule Milestones

• First 3 stacked booths open –2012 Memorial Day Holiday

• Next 3 staggered booths open – 2012 Independence Holidays

Page 14: Blue Water Bridge

Stacked BoothsOpened 5/25/12

Page 15: Blue Water Bridge

Staggered BoothsOpened 6/30/12

Page 16: Blue Water Bridge

Challenges

• CBP Statement of Work

• Proprietary Hardware

• IT Configuration and Coordination

Page 17: Blue Water Bridge

IN THE END…We have seen positive outcomes with the project:

•Positive Press as seen here on tollroadsnews.com•Typical wait times under 20 minutes•Compliments from U.S. Customs Management and Staff of the booths themselves•Increased revenue at the Duty Free and Currency Exchange, due to shorter crossing times.

Page 18: Blue Water Bridge

Questions???