Upload
hatuyen
View
237
Download
0
Embed Size (px)
Citation preview
1
BID DOCUMENT
IIINNNTTTEEEGGGRRRAAATTTEEEDDD CCCOOOAAASSSTTTAAALLL ZZZOOONNNEEE MMMAAANNNAAAGGGEEEMMMEEENNNTTT PPPRRROOOJJJEEECCCTTT
SSSTTTAAATTTEEE PPPRRROOOJJJEEECCCTTT MMMAAANNNAAAGGGEEEMMMEEENNNTTT UUUNNNIIITTT
OOODDDIIISSSHHHAAA
Renovation of Hukitola Building at Hukitola Dist:Kendrapara
(Package No.- ICZM/W/WL/16/2013-14]
2013 – 14
ON BEHALF OF
PPPrrriiinnnccciiipppaaalll CCCCCCFFF (((WWWiiilllddd LLLiiifffeee))) &&& CCChhhiiieeefff WWWiiilllddd llliiifffeee wwwaaarrrdddeeennn 555ttthhh FFFllloooooorrr BBB...DDD...AAA... AAAppppppaaarrrtttmmmeeennnttt,,, PPPrrraaakkkrrruuutttiii BBBhhhaaawwwaaannn
NNNiiilllaaakkkaaannnttthhhaaa NNNaaagggaaarrr,,, NNNaaayyyaaapppaaalllllliii BBBhhhuuubbbaaannneeessswwwaaarrr
2
BLANK PAGE
3
SECTION-I CONTENTS
Section Description Page No.
1. a) Contents
b) Information about the Bid
c) Invitation For Bids ( IFB)
d) Agreement Form
3
5
6
31
2. a) Instruction to bidders (ITB)
b) Letter of acceptance
c) Form of Notice to proceed with the work
d) List of Documents to form the part of the agreement
08
29
30
3. Condition of contact
33
4. Contact Data
57
5. Technical Specifications
62
6. Drawing
110
7.
8.
Bill of Quantities (Contractor’s Bid )
Forms of securities
a) Bid Security
b) Performance guarantee
c) Performance bank guarantee ( unbalanced Item )
d) BG for advance payment
118
153
155
156
157
158
9. ENVIRONMENTAL MANAGEMENT POLICY
10. COASTAL REGULATORY ZONE ACT/POLICY
159
170
4
BLANK PAGE
5
GOVERNMENT OF INDIA
AND
GOVERNMENT OF ORISSA
INTIGRATED COASTAL ZONE MANAGEMENT PROJECT,
Bid Id. NO.ICZMP/WL/W/16/13-14
NATIONAL COMPETITIVE BIDDING
(Conservation , PH & Electrical – Composite Work)
NAME OF WORK : Renovation of Hukitola Building at Hukitola PERIOD OF SALE OF BIDDING : FROM 31.12.2013 To 30.01.2014 LAST DATE AND TIME FOR : DATE 31.01.2014TIME 4.00 HOURS RECEIPT OF BIDS
TIME AND DATE OF OPENING : DATE 31.01.2014 TIME 4.30 HOURS OF BIDS
PLACE OF SALE OF BIDS : ICZMP, State Project Management Unit
108, Suryanagar, Bhubaneswar-751003.
PLACE OF RECEIPT &OPENING OF BIDS : ICZMP, State Project Management Unit
108, Suryanagar, Bhubaneswar-751003.
OFFICER INVITING BIDS : The Project Director, SPMU
ICZM Society- ODISHA, Plot # 108,Unit – VII, Suryanagar , Bhubaneswar – 751 003
6
GOVERNMENT OF INDIA
AND
GOVERNMENT OF ORISSA
INTIGRATED COASTAL ZONE MANAGEMENT PROJECT(ICZMP)
NATIONAL COMPETITIVE BIDDING
Bid Invitation Notice No:- ICZMP/WL/W/16/2013-14 Date: 29.12.2013
1. The Government of India has received a credit from the International Development Association for the INTEGRATED COASTAL ZONE MANAGEMENT PROJECT (ICZMP)and Government of ODISHA intends to apply a part of the funds to cover eligible payments under the contracts for construction of works as detailed below. Bidding is open to all bidders from eligible source countries as defined in the IBRD Guidelines for Procurement. Bidders from India should, however, be registered with the Government of ODISHA/ other State Government/ Government of India or State/ Central Government undertakings. Bidders are advised to note the minimum qualification criteria specified in Clause 4 of the Instructions to Bidders to qualify for the award of the contract.
2. The Project Director, State Project Management Unit, Integrated Coastal Management Society of
ODISHA on behalf of The Conservator of forests (WL)-cum- Nodal Officer, ICZMP, Odisha, Bhubaneswar
now invites bids for the construction of works as detailed in the table below.
3. Bidding documents (and additional copies) may be purchased from Office of the Project Director, Integrated Coastal Zone Management Society of ODISHA, between 31.12.2013 to 30.01.2014,for a non-refundable fee (three sets) as indicated in table below, in the form of Demand Draft on any Scheduled bank payable at Bhubaneswar in favour of Project Director, Integrated Coastal Zone Management Society of ODISHA, Bhubaneswar. Interested bidders may obtain further information at the same address. Bidding documents requested by mail will be dispatched by registered/speed post on payment of an extra amount of Rs 500.00. The Project Director, Integrated Coastal Zone Management Society of ODISHA, Bhubaneswar will not be held responsible for the postal delay if any, in the delivery of the documents or non-receipt of the same. The notice and the bid document for the work can also be seen with option to download from the Project website http://www.iczmpodisha.org The down loaded bid document can be submitted along with non refundable fee mentioned in the Table towards the cost of the bid document. The Project Director, Integrated Coastal Management Society of ODISHA, Bhubaneswar will not accept the same if any portion of the downloaded document differs from the approved bid document available in the above mentioned office. In such cases the bidder would be responsible for ensuring that any addenda available in web site is also downloaded & incorporated. The download facility will be available from between 30.01.2014 upto 17.00Hrs
4. Bids must also be accompanied by Bid security of the amount specified for the work in the column (5) of the table below, drawn in favour of Project Director, Integrated Coastal Zone Management Society of ODISHA, Bhubaneswar. Bid security will have to be in any one of the forms as specified in the bidding document and shall have to be valid for 45 days beyond the validity of the bid.
5. Bids must be delivered to the Office of the Project Director, State Project Management Unit, Integrated Coastal Zone Management Society of ODISHA, Bhubaneswar, on or before 4.00 Hrs on 31.01.2014 and will be opened on the same day at 4.30 Hrs, in the presence of the bidders or their authorized representatives, who wish to attend. If the office happens to be closed on the date of receipt of the bids as specified, the bids will be received and opened on the next working day at the same time and venue.
6. Other details can be seen in the bidding documents
7
TABLE
(Name of work: Conservation of Heritage Building at Hukitola,Dist.Kendrapada)
Package No.: ICZMP/PM/W/16/2013-14
Package No. Name of the Work
Approximate Value of Work
(in Lakhs INR.)
Bid security
(in INR.)
Cost of Bid Document
(in Rs.)
Period of Completion
1 2 3 4 5 6
ICZMP/W/WL/16/201
3-14
Renovation of Hukitola Building at Hukitola under Kendrapara district.
100.30 1,00,300/- 5,250.00
12 months(inclusing rainy
season)
Addl. Project Director(O), Integrated Coastal Zone Management Project, Bhubaneswar
Memo No. Dt…
Copy to the Conservator of forests (WL)-cum- Nodal Officer, ICZMP, Odisha for information and necessary action.
Addl. Project Director(O),
Integrated Coastal Zone Management Project, Bhubaneswar
8
SECTION 1: INSTRUCTIONS TO BIDDERS
(ITB)
9
Section 1: Instructions to Bidders Table of Clauses
A. General Page No. D. Submission of Bids Page No.
1. Scope of Bid 10 19. Sealing and Marking of Bids 16
2. Source of Funds 10 20. Deadline for Submission of Bids 16
3. Eligible Bidders 10 21. Late Bids 17
4. Qualification of the Bidder 10 22. Modification and Withdrawal of Bids 17
5. One Bid per Bidder 13
6. Cost of Bidding 13
7. Site Visit 13
B. Bidding Documents E. Bid Opening and Evaluation
8. Content of Bidding Documents 13 23. Bid Opening 17
9. Clarification of Bidding Documents 13 24. Process to be Confidential 17
10. Amendment of Bidding Documents 14 25. Clarification of Bids 17
26. Examination of Bids and Determination
of Responsiveness 18
27. Correction of Errors 18
C. Preparation of Bids 28. Currency for Bid Evaluation
29. Evaluation and Comparison of Bids 18
11. Language of Bid 14 30. Preference for Domestic Bidders
12. Documents Comprising the Bid 14
13. Bid Prices 14 F. Award of Contract
14. Currencies of Bid and Payment 15
15. Bid Validity 15 31. Award Criteria 19
16. Bid Security 15 32. Employer's Right to Accept any Bid and
to Reject any or all Bids 19
17. Alternative Proposals by Bidders 16 33. Notification of Award 19
18. Format and Signing of Bid 16 34. Performance Security 19
35. Advance Payment and Security 20
36. Adjudicator 20
37. Corrupt or Fraudulent Practices 20
10
A. General
1. Scope of Bid
1.1 The Project Director, Integrated Coastal Zone Management Society of ODISHA., Bhubaneswar,
(referred to as Employer in these documents) invites bids for the construction of works (as defined
in these documents and referred to as "the works") detailed in the table given in IFB. The bidders
may submit bids for any or all of the works detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended completion date
specified in the Contract data.
2. Source of Funds
2.1 The Government of India has received a credit from International Development Association’
(hereinafter interchangeably called “the Bank”) towards the cost of Integrated Coastal Zone
Management Project and Government of ODISHA intends to apply a part of the funds to cover
eligible payments under the contract for the Works. Payments by the Bank will be made only at the
request of the borrower and upon approval of the Bank in accordance with the Credit Agreement,
and will be subject in all respects to the terms and conditions of that Agreement. Except as the
Bank may specifically otherwise agree, no party other than the borrower shall derive any rights
from the Credit Agreement or have any rights to the credit proceeds.
2.2 The credit agreement prohibits a withdrawal from the credit account for the purpose of any payment
to persons or entities, or for any import of goods, if such payment or import, to the knowledge of
the Bank, is prohibited by a decision of the United Nations Security Council, taken under Chapter
VII of the Charter of the United Nations.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all bidders from the eligible countries as defined under the IBRD
Guidelines for Procurement. Any materials, equipment, and services to be used in the performance
of the Contract shall have their origin in the eligible source countries.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a statement that
the Bidder is not associated, nor has been associated in the past, directly or indirectly, with the
Consultant or any other entity that has prepared the design, specifications, and other documents for
the Project or being proposed as Project Manager for the Contract. A firm that has been engaged by
the Borrower to provide consulting services for the preparation or supervision of the works, and any
of its affiliates, shall not be eligible to bid.
3.3 Government-owned enterprises in the Employer’s country may only participate if they are legally
and financially autonomous, operate under commercial law and are not a dependent agency of the
Borrower or Sub-borrower.
3.4 Bidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued
by the Bank in accordance with sub-clause 37.1.
4. Qualification of the Bidder
11
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary
description of the proposed work method and schedule, including drawings and charts, as
necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from
prequalified bidders will be considered for award for Contract. These qualified bidders should
submit with their bids any information updating their original prequalification applications or,
alternatively, confirm in their bids that the originally submitted prequalification information
remains essentially correct as of date of bid submission. The update or confirmation should be
provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include
the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration,
and principal place of business; written power of attorney of the signatory of the Bid to
commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of
works under way or contractually committed; and clients who may be contacted for further
information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for
the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's
reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and
availability of other financial resources);
(h) authority to seek references from the Bidder's bankers;
(i) information regarding any litigation or arbitration resulting from contracts executed by the
Bidder in the last five years or currently under execution. The information shall include the
names of the parties concerned, the disputed amount, cause of litigation, and matter in
dispute;
(j) proposals for subcontracting components of the Works which in aggregate add to more than
20 percent of the Bid Price (for each, the qualifications and experience of the identified sub-
contractor in the relevant field should be annexed; no vertical splitting of work for sub-
contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental
Management Plan, backed with equipment, materials and manpower planning and
deployment, duly supported with broad calculations and quality control procedures proposed
to be adopted, justifying their capability of execution and completion of the work as per
technical specifications within the stipulated period of completion as per milestones
12
4.4 ‘Bids from Joint ventures are not acceptable’.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five
years i.e 2008-2009 to 2012-2013:*
(a) Achieved, in at least one financial year, a minimum annual financial turnover (in all classes
of Civil Engineering works) of Rs. 101.00lakhs @
(b ) Satisfactorily completed (not less than 90% of contract value), as a prime contractor, (or as
subcontractor duly certified by the employer/main contractor) at least one similar work
(Conservation of building Works ) of value not less Rs 91.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work:
- HG Stone Masonry/Brick Work 25.00 Cum
- Tiled Flooring 505.00 Sqm
- Small Eye Laterite Stone Masonary 64.00 Cum
- General Vegetation Cleaning 300.00 Sqm.
- Chemical Cleaning micro-vegetation, Extraction of Salinity 500.00 Sqm.
d) The contractor or his identified sub-contractor should possess required valid electrical license issued
by The Electrical Inspector, Govt. of ODISHA or any appropriate authority of other State/Union of
India for executing the building electrification(Commercial-3ph ,440 Volts) works and should have
executed similar electrical works totaling Rs. 8.00 lakh in any one year.
(e) Not Required.
(f) Not Required..
(@)at 2013-2014 * price level. Financial turnover and cost of completed works of previous
years shall be given weightage of 10% per year based on rupee value to bring them to 2012-
2013 price level
4.5 B. Each bidder should further demonstrate:
B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the
following key and critical equipment for this work:
Item Capacity / type No/s.
Truck/ Tripper – 10 T 1
Fungicide Sprayer 1
Double bed de-ioniser
Plant
10 lit/hour (minium) 1
Needle/Immersion
Vibrators(fuel-
operated/electric)
25 mm / 40 mm 1
Water Tanker 5000 litres 1
Water Pump 1 H.P. 1
NOTE:
13
Based on the studies, carried out by the Engineer the minimum suggested major equipment to
attain the completion of works in accordance with the prescribed construction schedule are
shown in the above list.
The bidders should, however, undertake their own studies and furnish with their bid, a
detailed construction planning and methodology supported with layout and necessary
drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to
review their proposals. The numbers, types and capacities of each plant/equipment shall be
shown in the proposals along with the cycle time for each operation for the given production
capacity to match the requirements.
(b) availability for this work of a Project Manager(of minimum educational qualification
Diploma in Civil Engg.) with no less than five years' experience in similar works on full-
time basis and other key personnel (i) Temple Mason for executing the landscaping Stone
Masonary work for small eye laterite & Sandston) with adequate experience as required; and
(c) liquid assets and / or availability of credit facilities of no less than Rs 25 Lakhs in the
format given in Section 2.
(Credit lines / letter of credit / certificates from Banks for meeting the funds
requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are
invited in the IFB, the bidder must demonstrate having experience and resources sufficient to
meet the aggregate of the qualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the
bidder's compliance with the qualifying criteria except to the extent stated in 4.5 (A) above
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid
capacity is more than the total bid value. The available bid capacity will be calculated as under:
Assessed Available Bid capacity = ( A*N*1.5 - B ) where
A = Maximum value of Civil/Electrical engineering works executed in any one year during the
last five years (updated to 2013-14 price level) taking into account the completed as well as
works in progress.
N = Number of years prescribed for completion of the works for which bids are invited.
B = Value, at 2013-14 price level, of existing commitments and on-going works to be completed
during the next 12 months.
Note: The statements showing the value of existing commitments and on-going works as well as the
stipulated period of completion remaining for each of the works listed should be
countersigned by the Engineer in charge, not below the rank of an Executive Engineer or
equivalent.
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if
they have:
- made misleading or false representations in the forms, statements and attachments submitted
in proof of the qualification requirements; and/or
- record of poor performance such as abandoning the works, not properly completing the
contract, inordinate delays in completion, litigation history, or financial failures etc.; and/or
14
- participated in the previous bidding for the same work and had quoted unreasonably high bid
prices and could not furnish rational justification to the employer.
5. One Bid per Bidder
5.1 Each bidder shall submit only one bid for one contract. A bidder who submits or participates in
more than one Bid (other than as a subcontractor or in cases of alternatives that have been permitted
or requested) will cause all the proposals with the Bidder’s participation to be disqualified.
6. Cost of Bidding
6.1 The bidder shall bear all costs associated with the preparation and submission of his Bid, and the
Employer will in no case be responsible and liable for those costs.
7. Site visit
7.1 The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine the Site
of Works and its surroundings and obtain all information that may be necessary for preparing the
Bid and entering into a contract for construction of the Works. The costs of visiting the Site shall
be at the Bidder's own expense.
B. Bidding Documents
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed in the table below and addenda
issued in accordance with Clause 10:
Invitation for Bids
Section 1 Instructions to Bidders
2 Forms of Bid and Qualification Information
3 Conditions of Contract
4 Contract Data
5 Specifications
6 Drawings
7 Bills of Quantities
8 Forms of Securities
8.2 Of the three sets of the bidding documents supplied, two sets should be completed and returned
with the bid.
9. Clarification of Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify the
Employer in writing or by cable (hereinafter "cable" includes telex and facsimile) at the
Employer's address indicated in the invitation to bid. The Employer will respond to any request
for clarification which he received earlier than 15 days prior to the deadline for submission of
bids. Copies of the Employer's response will be forwarded to all purchasers of the bidding
documents, including a description of the enquiry but without identifying its source.
9.2 Pre-bid meeting:Deleted
15
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding documents by
issuing addenda.
10.2 Any addendum thus issued shall be part of the bidding documents and shall be communicated in
writing to all the purchasers of the bidding documents. Prospective bidders shall acknowledge
receipt of each addendum in writing to the Employer.
10.3 To give prospective bidders reasonable time in which to take an addendum into account in
preparing their bids, the Employer shall extend as necessary the deadline for submission of bids,
in accordance with Sub-Clause 20.2 below.
C. Preparation of Bids
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents comprising the Bid
12.1 The bid submitted by the bidder shall comprise the following:
(a) The Bid (in the format indicated in Section 2).
(b) Bid Security;
(c) Priced Bill of Quantities;
(d) Qualification Information Form and Documents;
(e) Certificate of VAT clearance.
and any other materials required to be completed and submitted by bidders in accordance with
these instructions. The documents listed under Sections 2, 4 and 7 of Sub-Clause 8.1 shall be
filled in without exception.
12.2 Bidders bidding for this contract together with other contracts stated in the IFB to form a package
will so indicate in the bid together with any discounts offered for the award of more than one
contract.
13. Bid Prices
13.1 The contract shall be for the whole works as described in Sub-Clause 1.1, based on the priced Bill
Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for all items
of the Works described in the Bill of Quantities along with total bid price (both in figures and
words). Items for which no rate or price is entered by the bidder will not be paid for by the
Employer when executed and shall be deemed covered by the other rates and prices in the Bill of
Quantities. Corrections, if any, shall be made by crossing out, initialing, dating and rewriting.
13.3 All duties, taxes, and other levies payable by the contractor under the contract, or for any other
cause shall be included in the rates, prices and total Bid Price submitted by the Bidder.
Note: “Bidders may like to ascertain availability of excise/custom duty exemption benefits available in India to
the contracts financed under World Bank loan/credits. They are solely responsible for obtaining such
16
benefits which they have considered in their bid and in case of failure to receive such benefits for reasons
whatsoever, the employer will not compensate the bidder (contractor). Where the bidder has quoted taking
into account such benefits, he must give all information required for issue of certificates in terms of such
notifications as per form attached to the Qualification Information in the bid. To the extent the employer
determines the quantity indicated therein are reasonable keeping in view the bill of quantities, construction
programme and methodology, the certificates will be issued within 60 [sixty] days of signing of contract
and no subsequent changes will be permitted. No certificate will be issued for items where no
quantity/capacity of equipment is indicated in the statement. The bids which do not conform to the above
provisions will be treated as non responsive and rejected. Any delay in procurement of the construction
equipment /machinery/goods as a result of the above shall not be a cause for granting any extension of
time.”
13.4 The rates and prices quoted by the bidder shall be fixed for the duration of the Contract and shall not be
subject to adjustment on any account.
14. Currencies of Bid and Payment
14.1 The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees.
15. Bid Validity
15.1 Bids shall remain valid for a period not less than ninety days after the deadline date for bid
submission specified in Clause 20. bid valid for a shorter period shall be rejected by the Employer
as non-responsive.
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request
that the bidders may extend the period of validity for a specified additional period. The request
and the bidders' responses shall be made in writing or by cable. A bidder may refuse the request
without forfeiting his bid security. A bidder agreeing to the request will not be required or
permitted to modify his bid except as provided in 15.3 hereinafter, but will be required to extend
the validity of his bid security for a period of the extension, and in compliance with Clause 16 in
all respects.
15.3 Not Applicable
15.4 Bid evaluation will be based on the bid prices without taking into consideration the above
correction.
16. Bid Security
16.1 The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in column 5 of
the table of IFB for this particular work. This bid security shall be in favour of The Project
Director, Integrated Coastal Zone Management Society of ODISHA, Bhubaneswar and may be in
one of the following forms:
- A bank guarantee issued by a nationalized / scheduled bank located in India or
- Certified cheque, Bank draft or Letter of Credit. or
- National Savings Certificates / KissanVikasPatra duly pledged.
- Term DepositeReiepts duly pledged
17
16.2 Bid Security issued as surety for the bid shall be valid for 135 days ( i.e 45 days beyond the
validity of the bid ) after deadline of submission of Bid .
16.3 Any Bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-
Clauses 16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4 The Bid Security of unsuccessful bidders will be returned within 28 days of the end of the bid
validity period specified in Sub-Clause 15.1.
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the
Agreement and furnished the required Performance Security.
16.6 The Bid Security may be forfeited
(a) if the Bidder withdraws the Bid after Bid opening during the period of Bid validity;
(b) if the Bidder does not accept the correction of the Bid Price, pursuant to Clause 27; or
(c) in the case of a successful Bidder, if the Bidder fails within the specified time limit to
(i) sign the Agreement; or
(ii) furnish the required Performance Security.
17. Alternative Proposals by Bidders
17.1 Bidders shall submit offers that comply with the requirements of the bidding documents,
including the basic technical design as indicated in the drawing and specifications. Alternatives
will not be considered.
18. Format and Signing of Bid
18.1 The Bidder shall prepare one original and one copy of the documents comprising the bid as
described in Clause 12 of these Instructions to Bidders, bound with the volume containing the
Form of Bid, and clearly marked "ORIGINAL" and "COPY" as appropriate. In the event of
discrepancy between them, the original shall prevail.
18.2 The original and copy of the Bid shall be typed or written in indelible ink and shall be signed by a
person or persons duly authorized to sign on behalf of the Bidder, pursuant to Sub-Clauses 4.3.
All pages of the bid where entries or amendments have been made shall be initialed by the person
or persons signing the bid.
18.3 The Bid shall contain no alterations or additions, except those to comply with instructions issued
by the Employer, or as necessary to correct errors made by the bidder, in which case such
corrections shall be initialed by the person or persons signing the bid.
18.4 The Bidder shall furnish information as described in the Form of Bid on commissions or
gratuities, if any, paid or to be paid to agents relating to this Bid, and to contract execution if the
Bidder is awarded the contract.
D. Submission of Bids
19. Sealing and Marking of Bids
18
19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the
envelopes as "ORIGINAL" and "COPY". These envelopes (called as inner envelopes) shall
then be put inside one outer envelope.
19.2 The inner and outer envelopes shall
(a) be addressed to the Employer at the following address:
The Project Director, ICZMP, 108- Surya Nagar, Bhubaneswar and
(b) bear the following identification:
- Renovation of Hukitola Building at Hukitola
- Bid Reference No. :.ICZMP/WL/W/16/2013-14
- DO NOT OPEN BEFORE. : 4.30 hours. On 31.01.2014
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the
name and address of the bidder to enable the bid to be returned unopened in case it is declared
late, pursuant to Clause 21.
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no
responsibility for the misplacement or premature opening of the bid.
20. Deadline for Submission of the Bids
20.1 Bids must be received by the Employer at the address specified above not later than 4.00 hours.
on dt.31.01.2014. In the event of the specified date for the submission of bids declared a holiday
for the Employer, the Bids will be received up to the appointed time on the next working day.
20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in
accordance with Clause 10, in which case all rights and obligations of the Employer and the
bidders previously subject to the original deadline will then be subject to the new deadline.
21. Late Bids
21.1 Any Bid received by the Employer after the deadline prescribed in Clause 20 will be returned
unopened to the bidder.
22. Modification and Withdrawal of Bids
22.1 Bidders may modify or withdraw their bids by giving notice in writing before the deadline
prescribed in Clause 20.
22.2 Each Bidder's modification or withdrawal notice shall be prepared, sealed, marked, and delivered
in accordance with Clause 18 & 19, with the outer and inner envelopes additionally marked
"MODIFICATION" or "WITHDRAWAL", as appropriate.
22.3 No bid may be modified after the deadline for submission of Bids.
22.4 Withdrawal or modification of a Bid between the deadline for submission of bids and the
expiration of the original period of bid validity specified in Clause 15.1 above or as extended
pursuant to Clause 15.2 may result in the forfeiture of the Bid security pursuant to Clause 16.
19
22.5 Bidders may offer discounts to, or modify the prices of their Bids only by submitting Bid
modifications in accordance with this clause, or included in the original Bid submission.
E. Bid Opening and Evaluation 23. Bid Opening
23.1 The Employer will open all the Bids received (except those received late), including
modifications made pursuant to Clause 22, in the presence of the Bidders or their representatives
who choose to attend at 4:30 Hrs on dt. 31.01.2014 at the place specified in Clause 20. In the
event of the specified date of Bid opening being declared a holiday for the Employer, the Bids
will be opened at the appointed time and location on the next working day.
23.2 Envelopes marked "WITHDRAWAL" shall be opened and read out first. Bids for which an
acceptable notice of withdrawal has been submitted pursuant to Clause 22 shall not be opened.
Subsequently all envelopes marked “Modification” shall be opened and the submissions therein
read out in appropriate detail.
23.3 The Bidders' names, the Bid prices, the total amount of each Bid and of any alternative Bid (if
alternatives have been requested or permitted), any discounts, Bid modifications and withdrawals,
the presence or absence of Bid security, and such other details as the Employer may consider
appropriate, will be announced by the Employer at the opening. No bid shall be rejected at bid
opening except for the late bids pursuant to Clause 21. Bids [and modifications] sent pursuant to
Clause 22 that are not opened and read out at bid opening will not be considered for further
evaluation regardless of the circumstances. Late and withdrawn bids will be returned un-opened
to bidders.
23.4 The Employer shall prepare minutes of the Bid opening, including the information disclosed to
those present in accordance with Sub-Clause 23.3.
24. Process to Be Confidential
24.1 Information relating to the examination, clarification, evaluation, and comparison of Bids and
recommendations for the award of a contract shall not be disclosed to Bidders or any other
persons not officially concerned with such process until the award to the successful Bidder has
been announced. Any effort by a Bidder to influence the Employer's processing of Bids or award
decisions may result in the rejection of his Bid.
25. Clarification of Bids
25.1 To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his
discretion, ask any Bidder for clarification of his Bid, including breakdowns of the unit rates. The
request for clarification and the response shall be in writing or by cable, but no change in the
price or substance of the Bid shall besought, offered, or permitted except as required to confirm
the correction of arithmetic errors discovered by the Employer in the evaluation of the Bids in
accordance with Clause 27.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to its bid
from the time of the bid opening to the time the contract is awarded. If the Bidder wishes to bring
additional information to the notice of the Employer, it should do so in writing.
20
25.3 Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid
comparison or contract award decisions may result in the rejection of the Bidders’ bid.
26. Examination of Bids and Determination of Responsiveness
26.1 Prior to the detailed evaluation of Bids, the Employer will determine whether each Bid (a) meets
the eligibility criteria defined in Clause 3; (b) has been properly signed; (c) is accompanied by the
required securities and; (d) is substantially responsive to the requirements of the Bidding
documents.
26.2 A substantially responsive Bid is one which conforms to all the terms, conditions, and
specifications of the Bidding documents, without material deviation or reservation. A material
deviation or reservation is one (a) which affects in any substantial way the scope, quality, or
performance of the Works; (b) which limits in any substantial way, inconsistent with the Bidding
documents, the Employer's rights or the Bidder's obligations under the Contract; or (c) whose
rectification would affect unfairly the competitive position of other Bidders presenting
substantially responsive Bids.
26.3 If a Bid is not substantially responsive, it will be rejected by the Employer, and may not
subsequently be made responsive by correction or withdrawal of the non-conforming deviation or
reservation.
27. Correction of Errors
27.1 Bids determined to be substantially responsive will be checked by the Employer for any
arithmetic errors. Errors will be corrected by the Employer as follows:
(a) where there is a discrepancy between the rates in figures and in words, the rate in words
will govern; and
(b) where there is a discrepancy between the unit and the line item total resulting from
multiplying the unit rate by the quantity, the unit rate as quoted will govern.
27.2 The amount stated in the Bid will be adjusted by the Employer in accordance with the above
procedure for the correction of errors and, with the concurrence of the Bidder, shall be considered
as binding upon the Bidder. If the Bidder does not accept the corrected amount the Bid will be
rejected, and the Bid security may be forfeited in accordance with Sub-Clause 16.6 (b).
28. Deleted
29. Evaluation and Comparison of Bids
29.1 The Employer will evaluate and compare only the Bids determined to be substantially responsive
in accordance with Clause 26.
29.2 In evaluating the Bids, the Employer will determine for each Bid the evaluated Bid Price by
adjusting the Bid Price as follows:
(a) making any correction for errors pursuant to Clause 27; or
(b) making an appropriate adjustments for any other acceptable variations, deviations; and
(c) making appropriate adjustments to reflect discounts or other price modifications offered
in accordance with Sub Clause 22.5.
21
29.3 The Employer reserves the right to accept or reject any variation, deviation, or alternative offer.
Variations, deviations, and alternative offers and other factors which are in excess of the
requirements of the Bidding documents or otherwise result in unsolicited benefits for the
Employer shall not be taken into account in Bid evaluation.
29.4 The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of
Contract, during the period of implementation of the Contract, will not be taken into account in
Bid evaluation.
29.5 If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer's estimate of
the cost of work to be performed under the contract, the Employer may require the Bidder to
produce detailed price analyses for any or all items of the Bill of Quantities, to demonstrate the
internal consistency of those prices with the construction methods and schedule proposed. After
evaluation of the price analyses, the Employer may require that the amount of the performance
security set forth in Clause 34 be increased at the expense of the successful Bidder to a level
sufficient to protect the Employer against financial loss in the event of default of the successful
Bidder under the Contract.
30. Deleted
F. Award of Contract
31. Award Criteria
31.1 Subject to Clause 32, the Employer will award the Contract to the Bidder whose Bid has been
determined to be substantially responsive to the Bidding documents and who has offered the
lowest evaluated Bid Price, provided that such Bidder has been determined to be (a) eligible in
accordance with the provisions of Clause 3, and (b) qualified in accordance with the provisions of
Clause 4.
31.2 If, pursuant to Clause 12.2 this contract is being let along with other contracts, the lowest
evaluated Bid Price will be determined when evaluating this contract in conjunction with other
contracts to be awarded concurrently, taking into account any discounts offered by the bidders for
the award of more than one contract.
32. Employer's Right to Accept any Bid and to Reject any or all Bids
32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid, and to
cancel the Bidding process and reject all Bids, at any time prior to the award of Contract, without
thereby incurring any liability to the affected Bidder or Bidders or any obligation to inform the
affected Bidder or Bidders of the grounds for the Employer's action.
33. Notification of Award and Signing of Agreement
33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to
expiration of the Bid validity period by cable, telex or facsimile confirmed by registered letter. This
letter (hereinafter and in the Conditions ofContract called the "Letter of Acceptance") will state the
sum that the Employer will pay the Contractor in consideration of the execution, completion, and
maintenance of the Works by the Contractor as prescribed by the Contract (hereinafter and in the
Contract called the "Contract Price").
22
33.2 The notification of award will constitute the formation of the Contract, subject only to the furnishing
of a performance security in accordance with the provisions of Clause 34.
33.3 The Agreement will incorporate all agreements between the Employer and the successful Bidder. It
will be signed by the Employer and kept ready for signature of the successful bidder in the office of
employer within 28 days following the notification of award along with the Letter of Acceptance.
33.4 Upon the furnishing by the successful Bidder of the Performance Security, the Employer will
promptly notify the other Bidders that their Bids have been unsuccessful.
34. Performance Security
34.1 Within 21 days of receipt of the Letter of Acceptance, the successful Bidder shall deliver to the
Employer a Performance Security in any of the forms given below for an amount equivalent to 5% of
the Contract price plus additional security for unbalanced Bids in accordance with Clause 29.5 of ITB
and Clause 52 of Conditions of Contract:
- A bank guarantee issued by a nationalized / scheduled bank located in India or a reputable
bank located abroad in the form given in Section 8; or
34.2 If the performance security is provided by the successful Bidder in the form of a Bank Guarantee, it
shall be issued either (a) at the Bidder's option, by a Nationalized/Scheduled Indian bank or (b) by a
foreign bank located in India and acceptable to the Employer or (c) by a foreign bank through a
correspondent Bank in India [scheduled or nationalized].
34.3 Failure of the successful bidder to comply with the requirements of sub-clause 34.1 shall constitute a
breach of contract, cause for annulment of the award, forfeiture of the bid security, and any such other
remedy the Employer may take under the contract, and the Employer may resort to awarding the
contract to the next ranked bidder.
35 Advance Payment and Security
35.1 The Employer will provide an Advance Payment on the Contract Price as stipulated in the Conditions
of Contract, subject to maximum amount, as stated in the Contract Data.
36. Adjudicator
36.1 The Employer proposes that Sri Sridhar Behera, Retd Engineer-in-Chief. WRD Deptt.,Govt. of
Odisha be appointed as Adjudicator under the Contract, at a daily fee of Rs. 3000/-plus reimbursable
expenses. If the Bidder disagrees with this proposal, the Bidder should so state in the Bid. If in the
Letter of Acceptance, the Employer has not agreed on the appointment of the Adjudicator, the
Adjudicator shall be appointed by Institution of Engineers, India , at a daily fee of Rs. 3000.00 per
sitting plus reimbursable expenses, at the request of either party.
37. Fraud and Corruption
37.1 It is the Bank’s policy to require that Borrowers (including beneficiaries of Bank loans), as well
as bidders, suppliers, and contractors and their agents (whether declared or not), personnel,
subcontractors, sub-consultants, service providers or suppliers, under Bank-financed contracts, observe
23
the highest standard of ethics during the procurement and execution of such contracts. 1 In pursuance of
this policy, the Bank:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) “corrupt practice”2 is the offering, giving, receiving or soliciting, directly or indirectly, of
anything of value to influence improperly the actions of another party;
(ii) “fraudulent practice”3 is any act or omission, including a misrepresentation, that knowingly or
recklessly misleads, or attempts to mislead, a party to obtain a financial or other benefit or
to avoid an obligation;
(iii) “collusive practice”4 is an arrangement between two or more parties designed to achieve an
improper purpose, including to influence improperly the actions of another party;
(iv) “coercive practice”5 is impairing or harming, or threatening to impair or harm, directly or
indirectly, any party or the property of the party to influence improperly the actions of a
party;
(v) “obstructive practice” is
(aa) deliberately destroying, falsifying, altering or concealing of evidence material to the
investigation or making false statements to investigators in order to materially
impede a Bank investigation into allegations of a corrupt, fraudulent, coercive or
collusive practice; and/or threatening, harassing or intimidating any party to prevent
it from disclosing its knowledge of matters relevant to the investigation or from
pursuing the investigation, or
(bb) acts intended to materially impede the exercise of the Bank’s inspection and audit
rights provided for under par. 1.14 (e) below.
(b) will reject a proposal for award if it determines that the bidder recommended for award has, directly
or through an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in
competing for the contract in question;
(c) will cancel the portion of the loan allocated to a contract if it determines at any time that
representatives of the Borrower or of a beneficiary of the loan engaged in corrupt, fraudulent,
collusive, or coercive practices during the procurement or the execution of that contract, without the
Borrower having taken timely and appropriate action satisfactory to the Bank to address such
practices when they occur;
(d) will sanction a firm or individual, at any time, in accordance with prevailing Bank’s sanctions
procedures,aincluding by publicly declaring such firm or individual ineligible, either indefinitely or
1In this context, any action taken by a bidder, supplier, contractor, or any of its personnel, or its agents, or its sub-
consultants, sub-contractors, service providers, suppliers and/or their employees to influence the procurement
process or contract execution for undue advantage is improper. 2 For the purpose of these Guidelines, “another party” refers to a public official acting in relation to the
procurement process or contract execution]. In this context, “public official” includes World Bank staff and
employees of other organizations taking or reviewing procurement decisions. 3 For the purpose of these Guidelines, “party” refers to a public official; the terms “benefit” and “obligation” relate
to the procurement process or contract execution; and the “act or omission” is intended to influence the procurement
process or contract execution. 4 For the purpose of these Guidelines, “parties” refers to participants in the procurement process (including public
officials) attempting to establish bid prices at artificial, non competitive levels. 5For the purpose of these Guidelines, “party” refers to a participant in the procurement process or contract execution.
24
for a stated period of time: (i) to be awarded a Bank-financed contract; and (ii) to be a nominatedb
sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible
firm being awarded a Bank-financed contract;
(e) will have the right to require that a provision be included in bidding documents and in contracts
financed by a Bank loan, requiring bidders, suppliers and contractors to permit the Bank to inspect
their accounts and records and other documents relating to the bid submission and contract
performance and to have them audited by auditors appointed by the Bank.
37.2Furthermore, Bidders shall be aware of the provision stated in sub-clause 23.2 and 59.2 (h) of the
Conditions of Contract.
aA firm or an individual may be declared ineligible to be awarded a Bank-financed contract upon completion of the
Bank’s sanctions proceedings as per its sanctions procedures, including inter alia: (i) temporary suspension or early
temporary suspension in connection with an ongoing sanctions proceeding; (ii) cross-debarment as agreed with other
International Financial Institutions, including Multilateral Development Banks; and (iii) the World Bank Group
corporate administrative procurement sanctions procedures for fraud and corruption. b A nominated sub-contractor, consultant, manufacturer or supplier, or service provider (different names are used
depending on the particular bidding document) is one which has: (i) either been included by the bidder in its pre-
qualification application or bid because it brings specific and critical experience and know-how that allow the bidder
to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower.
25
SECTION 2: FORMS OF BID, QUALIFICATION INFORMATION AND
LETTER OF ACCEPTANCE
Table of Forms:
- CONTRACTOR’S BID
- QUALIFICATION INFORMATION
- LETTER OF ACCEPTANCE
- NOTICE TO PROCEED WITH THE WORK
- AGREEMENT FORM
26
Contractor's Bid
Description of the Works: Renovation of Hukitola Building at Hukitola
GENTLEMEN,
Having examined the bidding documents including addendum, we offer to execute the Works described above in
accordance with the Conditions of Contract, Specifications, Drawings and Bill of Quantities accompanying this Bid
for the Contract Price of _________ [in figures] (__________________________________________________)
[in letters].6
The advance Payment required is: Rupees ________________.
We accept the appointment of ________________________ as the Adjudicator.
(OR)
We do not accept the appointment of ___________________ as the Adjudicator and propose instead that
_______________________ be appointed as Adjudicator whose daily fees and biographical data are attached.
This Bid and your written acceptance of it shall constitute a binding contract between us. We understand that you
are not bound to accept the lowest or any Bid you receive.
We hereby certify that we have taken steps to ensure that no person acting for us or on our behalf will engage in
bribery.
We also undertake that, in competing for (and, if the award is made to us, in executing) the above contract, we will
strictly observe the laws against fraud and corruption in force in India namely “Prevention of Corruption Act 1988”.
Commissions or gratuities, if any, paid or to be paid by us to agents relating to this Bid, and to contract execution if
we are awarded the contract, are listed below :
Name and address of agent Amount Purpose of Commission or gratuity
______________________ ________ ____________________________
______________________ ________ ____________________________
(if none, state “none”)
We hereby confirm that this Bid complies with the Eligibility, Bid Validity and Bid Security required by the Bidding
documents.
Yours faithfully,
Authorized Signature:
Name & Title of Signatory: _________________________________________________________________
Name of Bidder : ______________________________________________
Address : __________________________________________________________________
3 To be filled in by the Bidder, together with his particulars and date of submission at the bottom of the Form of Bid.
27
Qualification Information
The information to be filled in by the Bidder in the following pages will be used for purposes of postqualification as
provided for in Clause 4 of the Instructions to Bidders. This information will not be incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder
[Attach copy]
Place of registration: _______________________________
Principal place of business: _______________________________
Power of attorney of signatory of Bid
[Attach]
1.2 Total value of Civil Engineering construction_
work executed and payments received in the last five years**
(in Rs. Lakh)
2008-2009_____________________
2009-2010_____________________
2010-2011_____________________
2011-2012_____________________
2012-2013_____________________
1.3.1 Work performed as prime contractor (in the same name) on works of a similar nature over the last five
years. **
____________________________________________________________________________________________
Project
Name
Name
of the
Employer*
Descrip-
tion of
work
Contract
No.
Value of
contract
(Rs.
Million)
Date of
issue of
work
order
Stipulated
period of
completion
Actual date
of
completion*
Remarks
explaining
reasons for
delay and
work
completed
____________________________________________________________________________________________
____________________________________________________________________________________________
1.3.2 Quantities of work executed as prime contractor (in the same name and style) in the last five years: **
Year Name Name Quantity of work performed (cum) @ Remarks*
of the
Work
of the
Employer*
Cement concrete
(including RCC&PCC)
Masonry E/works (indicate contract Ref)
2008-2009
2009-2010
2010-2011
2011-2012
2012-2013
*Attach certificate(s) from the Engineer(s)-in-Charge
@The item of work for which data is requested should tally with that specified in ITB clause 4.5A(c).
** immediately preceding the financial year in which bids are received.
Attach certificate from Chartered Accountant.
28
1.4 Information on Bid Capacity (works for which bids have been submitted and works which are yet to be
completed) as on the date of this bid.
(A) Existing commitments and on-going works:
____________________________________________________________________________________________
Description Place Contract No. Name Value of Stipulated Value of works* Anticipated
of & & Date and Contract period of remaining to be date of
Work State Address (Rs. million) completion completed completion
of Employer (Rs. million)
(1) (2) (3) (4) (5) (6) (7) (8)
____________________________________________________________________________________________
__________________________________________________________________________________________
(B) Works for which bids already submitted:
____________________________________________________________________________________________
Description Place Name and Estimated Stipulated Date when Remarks
of & Address of value of works period of decision is if any
Work State Employer (Rs. million) completion expected
(1) (2) (3) (4) (5) (6) (7)
* Attach certificate(s) from the Engineer(s)-in-Charge.
1.5 The following items of Contractor's Equipment are essential for carrying out the Works. The Bidder should
list all the information requested below. Refer also to Sub Clause 4.3 (d) of the Instructions to Bidders.
_______________________________________________________________________________________
Item of Requirement Availability proposals Remarks
equipment No. Capacity Owned/leased/ Nos/ Age/ (From whom to be
to be procured capacity condition purchased)
_______________________________________________________________________________________
* * * * * * *
* * * * * * *
_______________________________________________________________________________________
1.6 Qualifications and experience of key personnel proposed for administration and execution of the Contract.
Attach biographical data. Refer also to Sub Clause 4.3 (e) and 4.5 (B) (b) of instructions to Bidders and Sub
Clause 9.1 of the Conditions of Contract.
_______________________________________________________________________________________
Years of Years of experience in
Position Name Qualifications experience the proposed position
(general)
_______________________________________________________________________________________
Project Manager * * * *
* * * * *
* * * * *
* * * * *
etc.
_______________________________________________________________________________________
29
1.7 Proposed subcontracts and firms involved. [Refer ITB Clause 4.3 (j)]
_______________________________________________________________________________________
Sections Value of Sub-contractor Experience in
of the works Sub-contract (name and address) similar work
_______________________________________________________________________________________
* * * *
* *
* * * *
* *
* * * *
* *
______________________________________________________________________________________
1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors' reports (in case of
companies/corporation), etc. List them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand, lines of credit,
etc. List them below and attach copies of support documents [sample format attached].
1.10. Name, address, and telephone, telex, and fax numbers of the Bidders' bankers who may provide references if
contacted by the Employer.
1.11 Information on litigation history in which the Bidder is involved.
__________________________________________________________________________________
Other party(ies) Employer Cause of dispute Amount involved Remarks showing
present status
__________________________________________________________________________________
__________________________________________________________________________________
1.12 Statement of compliance under the requirements of Sub Clause 3.2 of the instructions to Bidders.
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and charts as necessary
to comply with the requirements of the Bidding documents. [Refer ITB Clause 4.1 and 4.3 (k)].
2. Joint Ventures - Deleted
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the requirements of Clause 4 of the
Instructions to the Bidders, if applicable.
____________________________________________________________________________________________
30
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR AVAILABILITY OF CREDIT FACILITIES –
* CLAUSE 4.5 [B] [c] OF ITB
BANK CERTIFICATE
This is to certify that M/s. …………………………… is a reputed company with a good financial standing.
If the contract for the work, namely …………………………………………………………. [funded by the World
Bank] is awarded to the above firm, we shall be able to provide overdraft/credit facilities to the extent of Rs.
…………… to meet their working capital requirements for executing the above contract.
__ Sd. __
Name of Bank
Senior Bank Manager
Address of the Bank
31
(Name of the Project)
(Declaration regarding customs/excise duty exemption for materials/
construction equipment bought for the work)
Form ……….
(Bidder’s Name and Address)
To: ………………………
(Name of the Employer)
Dear Sir:
Re: [Name of Work] ………………………… -
Certificate for Import/Procurement of Goods/Construction Equipment
1. We confirm that we are solely responsible for obtaining customs/excise duty waivers which we have
considered in our bid and in case of failure to receive such waivers for reasons whatsoever, the Employer will
not compensate us.
2. We are furnishing below the information required by the Employer for issue of the necessary certificates in
terms of the Government of India Central Excise Notification No. 108/95 and Customs Notification No.
85/99.
3. The goods/construction equipment for which certificates are required are as under:
Items Make/
Brand
Name
Capacity
[where
applicable]
Quantity Value State whether it will
be procured locally
or imported [if so
from which country]
Remarks regarding
justification for the
quantity and their
usage in works
Goods
[a]
[b]
Construction Equipment
[a]
[b]
4. We agree that no modification to the above list is permitted after bids are opened.
5. We agree that the certificate will be issued only to the extent considered reasonable by the Employer for the
work, based on the Bill of Quantities and the construction programme and methodology as furnished by us
alongwith the bid.
6. We confirm that the above goods will be exclusively used for the construction of the above work and
construction equipment will not be sold or otherwise disposed of in any manner for a period of five years
from the date of acquisition.
Date: ___________________ (Signature) ____________________
Place: __________________ (Printed Name) _________________
(Designation) __________________
(Common Seal) ________________
This certificate will be issued within 60 days of signing of contract and no subsequent changes will be permitted.
32
Letter of Acceptance
(letterhead paper of the Employer)
________________________[date]
To: _________________________________________________________________________[name and address
of the Contractor]
Dear Sirs,
This is to notify you that your Bid dated ____________ for execution of the ________________________
___________________________________________________________ [name of the contract and identification
number, as given in the Instructions to Bidders] for the Contract Price of Rupees ———————————
____________________________________ (_____________) [amount in words and figures], as corrected and
modified in accordance with the Instructions to Bidders1 is hereby accepted by our Agency.
We accept/do not accept that __________________________ be appointed as the Adjudicator2.
We note that as per bid, you do not intend to subcontract any component of work.
[OR]
We note that as per bid, you propose to employ M/s. .......................................... as sub-contractor for executing
….........................................
[Delete whichever is not applicable]
You are hereby requested to furnish Performance Security, plus additional security for unbalanced
bids in terms of ITB clause 29.5, in the form detailed in Para 34.1 of ITB for an amount of Rs.————— within
21 days of the receipt of this letter of acceptance valid upto 28 days from the date of expiry of Defects Liability
Period i.e. upto ........... and sign the contract, failing which action as stated in Para 34.3 of ITB will be taken.
We have reviewed the construction methodology submitted by you alongwith the bid in response to ITB
Clause 4.3[k] and our comments are given in the attachment. You are requested to submit a revised Program
including environmental management plan as per Clause 27 of General Conditions of Contract within 14 days of
receipt of this letter.
Yours faithfully,
Authorized Signature
Name and Title of Signatory
Name of Agency
1 Delete "corrected and" or "and modified" if only one of these actions applies. Delete "as corrected and
modified in accordance with the Instructions to Bidders" if corrections or modifications have not been effected.
2 To be used only if the Contractor disagrees in his Bid with the Adjudicator proposed by the Employer in the
"Instructions to Bidders."
33
Issue of Notice to proceed with the work (letterhead of the Employer)
————— (date)
To
—————————————— (name and address of the Contractor)
——————————————
——————————————
Dear Sirs:
Pursuant to your furnishing the requisite security as stipulated in ITB clause 34.1 and signing of the contract
agreement for the construction of —————— @ a Bid Price of Rs.——————, you are hereby instructed to
proceed with the execution of the said works in accordance with the contract documents.
Yours faithfully,
(Signature, name and title of
signatory authorized to sign on
behalf of Employer)
34
Agreement Form
This agreement, made the ___________________ day of ______________19_______,
between______________________________________________________________________________________
____________________________________[name and address of Employer]
(hereinafter called “the Employer)” of the one part and ______________________________________________
_____________________________________________________________________________________________
___________________________________________________[name and address of contractor] (hereinafter called
“the Contractor” ) of the other part.
Whereas the Employer is desirous that the Contractor execute _____________________________
_____________________________________________________________________________________________
___________________________________________________________________________________[ name and
identification number of Contract] (hereinafter called “the Works”) and the Employer has accepted the Bid by the
Contractor for the execution and completion of such Works and the remedying of any defects therein, at a contract
price of Rs.................................................................................
NOW THIS AGREEMENT WITNESSETH as follows:
1. In this Agreement, words and expression shall have the same meanings as are respectively assigned to them in
the Conditions of Contract hereinafter referred to, and they shall be deemed to form and be read and construed
as part of this Agreement.
2. In consideration of the payments to be made by the Employer to the Contractor as hereinafter mentioned, the
Contractor hereby covenants with the Employer to execute and complete the Works and remedy any defects
therein in conformity in all aspects with the provisions of the Contract.
3. The Employer hereby covenants to pay the Contractor in consideration of the execution and completion of the
Works and the remedying the defects wherein the Contract Price or such other sum as may become payable
under the provisions of the Contract at the times and in the manner prescribed by the Contract.
4. The following documents shall be deemed to form and be read and construed as part of this Agreement, viz.:
i) Letter of Acceptance;
ii) Notice to proceed with the works;
iii) Contractor’s Bid;
iv) Contract Data;
v) Conditions of contract (including Special Conditions of Contract);
vi) Specifications;
vii) Drawings;
viii) Bill of Quantities; and
ix) Any other document listed in the Contract Data as forming part of the contract.
35
In witness whereof the parties thereto have caused this Agreement to be executed the day and year first before
written.
The Common Seal of ____________________________________________________________
was hereunto affixed in the presence of:
Signed, Sealed and Delivered by the said _________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
in the presence of:
Binding Signature of Employer _________________________________________________ ___
Binding Signature of Contractor _____________________________________________________
36
SECTION 3: CONDITIONS OF CONTRACT
37
Conditions of Contract
Table of Contents
A. General Page No. C. Quality Control Page No.
1. Definitions 35 33. Identifying Defects 41
2. Interpretation 36 34. Tests 41
3. Language and Law 37 35. Correction of Defects 41
4. Engineer's Decisions 37 36. Uncorrected Defects 42
5. Delegation 37
6. Communications 37
7. Subcontracting 37 D. Cost Control
8. Other Contractors 37 37. Bill of Quantities 42
9. Personnel 37 38. Changes in the Quantities 42
10. Employer’s & Contractor's Risks 38 39. Variations 42
11. Employer's Risks 38 40. Payments for Variations 42
12. Contractor’s Risks 38 41. Cash Flow Forecasts 42
13. Insurance 38 42. Payment Certificates 43
14. Site Investigation Reports 38 43. Payments 43
15. Queries about the Contract 44. Compensation Events 43
Data 38 45. Tax 44
16. Contractor to Construct the 46. Currencies 44
Works 39 47. Price Adjustments 44
17. The Works to Be Completed by 48. Retention 44
the Intended Completion Date 39 49. Liquidated Damages 45
18. Approval by the Engineer 39 50. Bonus 45
19. Safety 39 51. Advance Payment 45
20. Discoveries 39 52. Securities 45
21. Possession of the Site 39 53. Dayworks
22. Access to the Site 39 54. Cost of Repairs 45
23. Instructions 39
24. Disputes 40
25. Procedure for Disputes 40 E. Finishing the Contract
26. Replacement of Adjudicator 40
55. Completion 46
B. Time Control 56. Taking Over 46
27. Program 40 57. Final Account 46
28. Extension of the Intended 58. Operating and Maintenance Manuals 46
Completion Date 40 59. Termination 46
29. Acceleration 41 60. Payment upon Termination 47
30. Delays Ordered by the 61. Property 47
Engineer 41 62. Release from Performance 47
31. Management Meetings 41 63. Suspension of World Bank Loan 47
32. Early Warning 41 or Credit
64. Corrupt or Fraudulent Practices 47
F. Special Conditions of Contract 49
38
Conditions of Contract
A. General
1. Definitions
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of Contract but
keep their defined meanings. Capital initials are used to identify defined terms.
The Adjudicator is the person appointed jointly by the Employer and the Contractor to resolve
disputes in the first instance, as provided for in Clauses 24 and 25. The name of the Adjudicator is
defined in the Contract Data.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.
Compensation Events are those defined in Clause 44 hereunder.
The Completion Date is the date of completion of the Works as certified by the Engineer in
accordance with Sub Clause 55.1.
The Contract is the contract between the Employer and the Contractor to execute, complete and
maintain the Works. It consists of the documents listed in Clause 2.3 below.
The Contract Data defines the documents and other information which comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the Works has been accepted by
the Employer.
The Contractor's Bid is the completed Bidding document submitted by the Contractor to the
Employer.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in
accordance with the provisions of the Contract.
Days are calendar days; months are calendar months.
A Defect is any part of the Works not completed in accordance with the Contract.
The Defects Liability Period is the period named in the Contract Data and calculated from the
Completion Date.
The Employer is the party who will employ the Contractor to carry out the Works.
The Engineer is the person named in the Contract Data (or any other competent person appointed and
notified to the contractor to act in replacement of the Engineer) who is responsible for supervising the
execution of the works and administering the Contract.
Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to construct the
Works.
The Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.
39
The Intended Completion Date is the date on which it is intended that the Contractor shall complete
the Works. The Intended Completion Date is specified in the Contract Data. The Intended Completion
Date may be revised only by the Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for incorporation in the
Works.
Plant is any integral part of the Works which is to have a mechanical, electrical, electronic or
chemical or biological function.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding documents and are factual
interpretative reports about the surface and sub-surface conditions at the site.
Specification means the Specification of the Works included in the Contract and any modification or
addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall commence
execution of the works. It does not necessarily coincide with any of the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry out a
part of the work in the Contract which includes work on the Site.
Temporary Works are works designed, constructed, installed, and removed by the Contractor which
are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer which varies the Works.
The Works are what the Contract requires the Contractor to construct, install, and turn over to the
Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also means female or
neuter, and the other way around. Headings have no significance. Words have their normal meaning
under the language of the Contract unless specifically defined. The Engineer will provide instructions
clarifying queries about the Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the Conditions of Contract to
the Works, the Completion Date, and the Intended Completion Date apply to any Section of the
Works (other than references to the Completion Date and Intended Completion date for the whole of
the Works).
2.3 The documents forming the Contract shall be interpreted in the following order of priority:
(1) Agreement
(2) Letter of Acceptance, notice to proceed with the works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Special Conditions of Contract
(6) Specifications
40
(7) Drawings
(8) Bill of Quantities and
(9) any other document listed in the Contract Data as forming part of the Contract.
3. Language and Law
3.1 The language of the Contract and the law governing the Contract are stated in the Contract Data.
4. Engineer's Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters between the
Employer and the Contractor in the role representing the Employer.
5. Delegation
5.1 The Engineer may delegate any of his duties and responsibilities to other people except to the
Adjudicator after notifying the Contractor and may cancel any delegation after notifying the
Contractor.
6. Communications
6.1 Communications between parties which are referred to in the conditions are effective only when in
writing. A notice shall be effective only when it is delivered (in terms of Indian Contract Act).
7. Subcontracting
7.1 The Contractor may subcontract with the approval of the Engineer but may not assign the Contract
without the approval of the Employer in writing. Subcontracting does not alter the Contractor's
obligations.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities,
and the Employer between the dates given in the Schedule of Other Contractors. The Contractor shall
as referred to in the Contract Data, also provide facilities and services for them as described in the
Schedule. The employer may modify the schedule of other contractors and shall notify the contractor
of any such modification.
9. Personnel
9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as referred to
in the Contract Data to carry out the functions stated in the Schedule or other personnel approved by
the Engineer. The Engineer will approve any proposed replacement of key personnel only if their
qualifications, abilities, and relevant experience are substantially equal to or better than those of the
personnel listed in the Schedule.
9.2 If the Engineer asks the Contractor to remove a person who is a member of the Contractor’s staff or
his work force stating the reasons the Contractor shall ensure that the person leaves the Site within
seven days and has no further connection with the work in the Contract.
10. Employer’s and Contractor's Risks
10.1 The Employer carries the risks which this Contract states are Employer’s risks, and the Contractor
carries the risks which this Contract states are Contractor’s risks.
41
11. Employer's Risks
11.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly affect the
execution of the Works in the Employer’s country, the risks of war, hostilities, invasion, act of foreign
enemies, rebellion, revolution, insurrection or military or usurped power, civil war, riot commotion or
disorder (unless restricted to the Contractor’s employees), and contamination from any nuclear fuel or
nuclear waste or radioactive toxic explosive, or (b) a cause due solely to the design of the Works,
other than the Contractor’s design.
12. Contractor’s Risks
12.1 All risks of loss of or damage to physical property and of personal injury and death which arise during
and in consequence of the performance of the Contract other than the excepted risks are the
responsibility of the Contractor.
13. Insurance
13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor, insurance cover
from the Start Date to the end of the Defects Liability Period, in the amounts and deductibles stated in
the Contract Data for the following events which are due to the Contractor’s risks:
(a) loss of or damage to the Works, Plant and Materials;
(b) loss of or damage to Equipment;
(c) loss of or damage of property (except the Works, Plant, Materials and Equipment) in
connection with the Contract; and
(d) personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the
Engineer’s approval before the Start Date. All such insurance shall provide for compensation to be
payable in the types and proportions of currencies required to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required, the Employer may
effect the insurance which the Contractor should have provided and recover the premiums the
Employer has paid from payments otherwise due to the Contractor or, if no payment is due, the
payment of the premiums shall be a debt due.
13.4 Alterations to the terms of an insurance shall not be made without the approval of the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
14. Site Investigation Reports
14.1 The Contractor, in preparing the Bid, shall rely on any site Investigation Reports referred to in the
Contract Data, supplemented by any information available to the Bidder.
15. Queries about the Contract Data
15.1 The Engineer will clarify queries on the Contract Data.
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the Works in accordance with the Specification and
Drawings, and as per instructions of Engineer.
42
17. The Works to Be Completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date and shall carry out the
Works in accordance with the program submitted by the Contractor, as updated with the approval of
the Engineer, and complete them by the Intended Completion Date.
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary Works to
the Engineer, who is to approve them if they comply with the Specifications and Drawings.
18.2 The Contractor shall be responsible for design of Temporary Works.
18.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the Temporary
Works.
18.4 The Contractor shall obtain approval of third parties to the design of the Temporary Works where
required.
18.5 All Drawings prepared by the Contractor for the execution of the temporary or permanent Works, are
subject to prior approval by the Engineer before their use.
19. Safety
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly discovered on the Site is
the property of the Employer. The Contractor is to notify the Engineer of such discoveries and carry
out the Engineer's instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is
not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of
the relevant activities and this will be Compensation Event.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site,
to any place where work in connection with the Contract is being carried out or is intended to be
carried out and to any place where materials or plant are being manufactured / fabricated / assembled
for the works.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer which comply with the applicable laws
where the Site is located.
23.2 Inspections and Audits by the Bank
The Contractor shall permit the Bank and/or persons appointed by the Bank to inspect the
Site and/or the accounts and records of the Contractor and its subcontractors relating to
the performance of the Contract, and to have such accounts and records audited by
auditors appointed by the Bank if required by the Bank. The Contractor’s attention is
43
drawn to Clause 64 [Corrupt or Fraudulent Practices] which provides, inter alia, that acts
intended to materially impede the exercise of the Bank’s inspection and audit rights
provided for under Sub-Clause 23.2 constitute a prohibited practice subject to contract
termination (as well as to a determination of ineligibility under the Procurement
Guidelines).
24. Disputes
24.1 If the Contractor believes that a decision taken by the Engineer was either outside the authority given
to the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred
to the Adjudicator within 14 days of the notification of the Engineer's decision.
25. Procedure for Disputes
25.1 The Adjudicator shall give a decision in writing within 28 days of receipt of a notification of a
dispute.
25.2 The Adjudicator shall be paid daily at the rate specified in the Contract Data together with
reimbursable expenses of the types specified in the Contract Data and the cost shall be divided equally
between the Employer and the Contractor, whatever decision is reached by the Adjudicator. Either
party may refer a decision of the Adjudicator to an Arbitrator within 28 days of the Adjudicator's
written decision. If neither party refers the dispute to arbitration within the above 28 days, the
Adjudicator's decision will be final and binding.
25.3 The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special
Conditions of Contract.
26. Replacement of Adjudicator
26.1 Should the Adjudicator resign or die, or should the Employer and the Contractor agree that the
Adjudicator is not fulfilling his functions in accordance with the provisions of the Contract, a new
Adjudicator will be jointly appointed by the Employer and the Contractor. In case of disagreement
between the Employer and the Contractor, within 30 days, the Adjudicator shall be designated by the
Appointing Authority designated in the Contract Data at the request of either party, within 14 days of
receipt of such request.
B. Time Control
27. Program
27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a
Program including Environmental Management Plan showing the general methods, arrangements,
order, and timing for all the activities in the Works along with monthly cash flow forecast.
27.2 An update of the Program shall be a program showing the actual progress achieved on each activity
and the effect of the progress achieved on the timing of the remaining work including any changes to
the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval, an updated Program at intervals no longer
than the period stated in the Contract Data. If the Contractor does not submit an updated Program
within this period, the Engineer may withhold the amount stated in the Contract Data from the next
payment certificate and continue to withhold this amount until the next payment after the date on
which the overdue Program has been submitted.
27.4 The Engineer's approval of the Program shall not alter the Contractor's obligations. The Contractor
may revise the Program and submit it to the Engineer again at any time. A revised Program is to show
the effect of Variations and Compensation Events.
44
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a Compensation Event occurs or a
Variation is issued which makes it impossible for Completion to be achieved by the Intended
Completion Date without the Contractor taking steps to accelerate the remaining work and which
would cause the Contractor to incur additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended Completion Date within 21
days of the Contractor asking the Engineer for a decision upon the effect of a Compensation Event or
Variation and submitting full supporting information. If the Contractor has failed to give early warning of
a delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered
in assessing the new Intended Completion Date.
29. Deleted
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within the Works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a management meeting. The business
of a management meeting shall be to review the plans for remaining work and to deal with matters raised
in accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings and is to provide copies of his record to
those attending the meeting and to the Employer. The responsibility of the parties for actions to be taken is
to be decided by the Engineer either at the management meeting or after the management meeting and
stated in writing to all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future events or
circumstances that may adversely affect the quality of the work, increase the Contract Price or delay the
execution of works. The Engineer may require the Contractor to provide an estimate of the expected effect
of the future event or circumstance on the Contract Price and Completion Date. The estimate is to be
provided by the Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and considering proposals for how the effect
of such an event or circumstance can be avoided or reduced by anyone involved in the work and in
carrying out any resulting instruction of the Engineer.
C. Quality Control 33. Identifying Defects
33.1 The Engineer shall check the Contractor's work and notify the Contractor of any Defects that
are found. Such checking shall not affect the Contractor's responsibilities. The Engineer may
instruct the Contractor to search for a Defect and to uncover and test any work that the
Engineer considers may have a Defect.
33.2 The contractor shall permit the Employer’s Technical auditor to check the contractor’s work
and notify the Engineer and Contractor of any defects that are found. Such a check shall not
45
affect the Contractor’s or the Engineer’s responsibility as defined in the Contract
Agreement.
34. Tests
34.1 If the Engineer instructs the Contractor to carry out a test not specified in the Specification to
check whether any work has a Defect and the test shows that it does, the Contractor shall pay
for the test and any samples. If there is no Defect the test shall be a Compensation Event.
35. Correction of Defects
35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects
Liability Period, which begins at Completion and is defined in the Contract Data. The
Defects Liability Period shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within
the length of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a Defect within the time specified in the Engineer’s
notice, the Engineer will assess the cost of having the Defect corrected, and the Contractor
will pay this amount.
Note: Where in certain cases, the technical specifications provide for acceptance of works within specified
tolerance limits at reduced rates, Engineer will certify payments to Contractor accordingly.
D. Cost Control
37. Bill of Quantities
37.1 The Bill of Quantities shall contain items for the construction, installation, testing, and
commissioning work to be done by the contractor.
37.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the
quantity of the work done at the rate in the Bill of Quantities for each item.
38. Changes in the Quantities
38.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for
the particular item by more than 25 percent, provided the change exceeds 1% of Initial
Contract Price, the Engineer shall adjust the rate to allow for the change.
38.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract
Price is exceeded by more than 15 percent, except with the Prior approval of the Employer.
38.3 If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost
breakdown of any rate in the Bill of Quantities.
39. Variations
39.1 All Variations shall be included in updated Programs produced by the Contractor.
40. Payments for Variations
46
40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates)
for carrying out the Variation when requested to do so by the Engineer. The Engineer shall
assess the quotation, which shall be given within seven days of the request or within any
longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities
and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub
Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to
change, the rate in the bill of Quantities shall be used to calculate the value of the Variation.
If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation
does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall
be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the
Engineer with a quotation within a reasonable time specified by the engineer in accordance
with Clause 40.1), the Engineer may order the Variation and make a change to the Contract
Price which shall be based on Engineer’s own forecast of the effects of the Variation on the
Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being
given and considered without delaying the work, no quotation shall be given and the
Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been
avoided by giving early warning.
41. Cash flow forecasts
41.1 When the Program is updated, the contractor is to provide the Engineer with an updated cash flow
forecast.
42. Payment Certificates
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the
work completed less the cumulative amount certified previously along with details of
measurement of the quantity of works executed in a tabulated form as approved by the
Engineer.
42.2 The Engineer shall check the details given in the Contractor's monthly statement and within
14 days certify the amounts to be paid to the Contractor after taking into account any credit
or debit for the month in question in respect of materials for the works in the relevant
amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured
Advance).
42.3 The value of work executed shall be determined by the Engineer after due check
measurement of the quantities claimed as executed by the contractor.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill
of Quantities completed..
42.5 The value of work executed shall include the valuation of Variations and Compensation
Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the
proportion of any item previously certified in any certificate in the light of later information.
47
43. Payments
43.1 Payments shall be adjusted for deductions for advance payments, retention, other recoveries
in terms of the contract and taxes, at source, as applicable under the law. The Employer
shall pay the Contractor the amounts certified by the Engineer within 28 days of the date of
each certificate. If the Employer makes a late payment, the Contractor shall be paid interest
on the late payment in the next payment. Interest shall be calculated from the date by which
the payment should have been made upto the date when the late payment is made at 8% per
annum.
43.2 If an amount certified is increased in a later certificate or as a result of an award by the
Adjudicator or an Arbitrator, the Contractor shall be paid interest upon the delayed payment
as set out in this clause. Interest shall be calculated from the date upon which the increased
amount would have been certified in the absence of dispute.
43.3 Items of the Works for which no rate or price has been entered in will not be paid for by the
Employer and shall be deemed covered by other rates and prices in the Contract.
44. Compensation Events
44.1 The following are Compensation Events unless they are caused by the Contractor:
(a) The Employer does not give access to a part of the Site by the Site Possession Date
stated in the Contract Data.
(b) The Employer modifies the schedule of other contractors in a way which affects the
work of the contractor under the contract.
(c) The Engineer orders a delay or does not issue drawings, specifications or instructions
required for execution of works on time.
(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon
work which is then found to have no Defects.
(e) The Engineer unreasonably does not approve for a subcontract to be let.
(f) Ground conditions are substantially more adverse than could reasonably have been
assumed before issuance of Letter of Acceptance from the information issued to
Bidders (including the Site Investigation Reports), from information available publicly
and from a visual inspection of the Site.
(g) The Engineer gives an instruction for dealing with an unforeseen condition, caused by
the Employer, or additional work required for safety or other reasons.
(h) Other contractors, public authorities, utilities or the Employer does not work within
the dates and other constraints stated in the Contract, and they cause delay or extra
cost to the Contractor.
(i) The advance payment is delayed.
(j) The effect on the Contractor of any of the Employer’s Risks.
(k) The Engineer unreasonably delays issuing a Certificate of Completion.
(l) Other Compensation Events listed in the Contract Data or mentioned in the Contract.
48
44.2 If a Compensation Event would cause additional cost or would prevent the work being completed
before the Intended Completion Date, the Contract Price shall be increased and/or the Intended
Completion Date is extended. The Engineer shall decide whether and by how much the Contract Price
shall be increased and whether and by how much the Intended Completion Date shall be extended.
44.3 As soon as information demonstrating the effect of each Compensation Event upon the Contractor's
forecast cost has been provided by the Contractor, it is to be assessed by the Engineer and the Contract
Price shall be adjusted accordingly. If the Contractor's forecast is deemed unreasonable, the Engineer
shall adjust the Contract Price based on Engineer’s own forecast. The Engineer will assume that the
Contractor will react competently and promptly to the event.
44.4 The Contractor shall not be entitled to compensation to the extent that the Employer's interests are
adversely affected by the Contractor not having given early warning or not having cooperated with the
Engineer.
45. Tax
45.1 The rates quoted by the Contractor shall be deemed to be inclusive of the sales and other taxes that the
Contractor will have to pay for the performance of this Contract. The Employer will perform such
duties in regard to the deduction of such taxes at source as per applicable law.
46. Currencies
46.1 All payments shall be made in Indian Rupees.
47. Price Adjustment
47.1 Deleted.
47.2 Deleted.
48. Retention
48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the
Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor
and half when the Defects Liability Period has passed and the Engineer has certified that all Defects
notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money (balance half) with
an “on demand” Bank guarantee.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the Contract
Data for each day that the Completion Date is later than the Intended Completion Date (for the whole
of the works or the milestone as stated in the contract data). The total amount of liquidated damages
shall not exceed the amount defined in the Contract Data. The Employer may deduct liquidated
damages from payments due to the Contractor. “Time is the essence of the contract and payment or
deduction of liquidated damages shall not relieve the contractor from his obligation to complete the
work as per agreed construction program and milestones or from any other of the contractor’s
obligations and liabilities under the contract.”
49.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer
shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment
certificate. The Contractor shall be paid interest on the over payment calculated from the date of
payment to the date of repayment at the rates specified in Sub Clause 43.1.
49
50. Deleted.
51. Advance Payment
51.1 The Employer shall make advance payment to the Contractor of the amounts stated in the Contract
Data by the date stated in the Contract Data, against provision by the Contractor of an Unconditional
Bank Guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal
to the advance payment. The guarantee shall remain effective until the advance payment has been
repaid, but the amount of the guarantee shall be progressively reduced by the amounts repaid by the
Contractor. Interest will not be charged on the advance payment.
51.2 The Contractor is to use the advance payment only to pay for Equipment, Plant and Mobilization
expenses required specifically for execution of the Works. The Contractor shall demonstrate that
advance payment has been used in this way by supplying copies of invoices or other documents to the
Engineer.
51.3 The advance payment shall be repaid by deducting proportionate amounts from payments otherwise
due to the Contractor, following the schedule of completed percentages of the Works on a payment
basis. No account shall be taken of the advance (mobilization and equipment only) payment or its
repayment in assessing valuations of work done, Variations, price adjustments, Compensation Events,
or Liquidated Damages.
51.4 Secured Advance:
- Deleted-.
52. Securities
52.1 The Performance Security shall be provided to the Employer no later than the date specified in the
Letter of Acceptance and shall be issued in an amount and form and by a bank or surety acceptable to
the Employer, and denominated in Indian Rupees. The Performance Security shall be valid until a date
28 days from the date of expiry of Defects Liability Period and the additional security for unbalanced
bids shall be valid until a date 28 days from the date of issue of the certificate of completion.
53. Deleted
54. Cost of Repairs
54.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and
the end of the Defects Correction periods shall be remedied by the Contractor at the Contractor's cost
if the loss or damage arises from the Contractor's acts or omissions.
E. Finishing the Contract
55. Completion
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the Works and the
Engineer will do so upon deciding that the Work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the Engineer issuing a
certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed account of the total amount that the Contractor
considers payable under the Contract before the end of the Defects Liability Period. The Engineer
50
shall issue a Defect Liability Certificate and certify any final payment that is due to the Contractor
within 56 days of receiving the Contractor's account if it is correct and complete. If it is not, the
Engineer shall issue within 56 days a schedule that states the scope of the corrections or additions that
are necessary. If the Final Account is still unsatisfactory after it has been resubmitted, the Engineer
shall decide on the amount payable to the Contractor and issue a payment certificate, within 56 days
of receiving the Contractor’s revised account.
58. Operating and Maintenance Manuals
58.1 If “as built” Drawings and/or operating and maintenance manuals are required, the Contractor shall
supply them by the dates stated in the Contract Data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract
Data, or they do not receive the Engineer’s approval, the Engineer shall withhold the amount stated in
the Contract Data from payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party causes a fundamental
breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the following:
(a) the Contractor stops work for 28 days when no stoppage of work is shown on the current
program and the stoppage has not been authorized by the Engineer;
(b) the Engineer instructs the Contractor to delay the progress of the Works and the instruction is
not withdrawn within 28 days;
(c) the Employer or the Contractor is made bankrupt or goes into liquidation other than for a
reconstruction or amalgamation;
(d) a payment certified by the Engineer is not paid by the Employer to the Contractor within 56
days of the date of the Engineer's certificate;
(e) the Engineer gives Notice that failure to correct a particular Defect is a fundamental breach of
Contract and the Contractor fails to correct it within a reasonable period of time determined by
the Engineer;
(f) the Contractor does not maintain a security which is required;
(g) the Contractor has delayed the completion of works by the number of days for which the
maximum amount of liquidated damages can be paid as defined in the Contract data; and
(h) if the Contractor, in the judgment of the Purchaser has engaged in fraud and corruption, as
defined in GCC Clause 64, in competing for or in executing the Contract.
59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for a cause other
than those listed under Sub Clause 59.2 above, the Engineer shall decide whether the breach is
fundamental or not.
59.4 Notwithstanding the above, the Employer may terminate the Contract for convenience.
59.5 If the Contract is terminated the Contractor shall stop work immediately, make the Site safe and
secure and leave the Site as soon as reasonably possible
51
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the
Engineer shall issue a certificate for the value of the work done less advance payments received up to
the date of the issue of the certificate, less other recoveries due in terms of the contract, less taxes due
to be deducted at source as per applicable law and less the percentage to apply to the work not
completed as indicated in the Contract Data. Additional Liquidated Damages shall not apply . If the
total amount due to the Employer exceeds any payment due to the Contractor the difference shall be a
debt payable to the Employer.
60.2 If the Contract is terminated at the Employer's convenience or because of a fundamental breach of
Contract by the Employer, the Engineer shall issue a certificate for the value of the work done, the
reasonable cost of removal of Equipment, repatriation of the Contractor's personnel employed solely
on the Works, and the Contractor's costs of protecting and securing the Works and less advance
payments received up to the date of the certificate, less other recoveries due in terms of the contract
and less taxes due to be deducted at source as per applicable law.
61. Property
61.1 All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be the
property of the Employer, if the Contract is terminated because of a Contractor’s default.
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war or by any other event entirely outside the control of
either the Employer or the Contractor the Engineer shall certify that the Contract has been frustrated.
The Contractor shall make the Site safe and stop work as quickly as possible after receiving this
certificate and shall be paid for all work carried out before receiving it and for any work carried out
afterwards to which commitment was made.
63. Suspension of World Bank Loan or Credit
63.1 In the event that the World Bank suspends the Loan or Credit to the Employer, from which part of the
payments to the Contractor are being made:
(a) The Employer is obligated to notify the Contractor of such suspension within 7 days of having
received the World Bank’s suspension notice.
(b) If the Contractor has not received sums due to it upon the expiration of the 28 days for payment
provided for in Sub-Clause 43.1, the Contractor may immediately issue a 14-day termination
notice.
64. Corrupt or Fraudulent Practices:
64.1 If the Employer determines that the Contractor has engaged in corrupt, fraudulent, collusive, coercive or
obstructive practices, in competing for or in executing the Contract, then the Employer may, after giving 14
days notice to the Contractor, terminate the Contractor's employment under the Contract and expel him from
the Site, and the provisions of Clause 59 shall apply as if such expulsion had been made under Sub-Clause
59.2 [Termination by Employer].
64.2 Should any employee of the Contractor be determined to have engaged in corrupt, fraudulent, collusive,
coercive, or obstructive practice during the execution of the Works, then that employee shall be removed in
accordance with Clause 9.
64.3 For the purposes of this Sub-Clause:
52
(i) “corrupt practice”7 is the offering, giving, receiving or soliciting, directly or indirectly, of anything of
value to influence improperly the actions of another party;
(ii) “fraudulent practice”8 is any act or omission, including a misrepresentation, that knowingly or
recklessly misleads, or attempts to mislead, a party to obtain a financial or other benefit or to avoid
an obligation;
(iii) “collusive practice”9 is an arrangement between two or more parties designed to achieve an improper
purpose, including to influence improperly the actions of another party;
(iv) “coercive practice”10 is impairing or harming, or threatening to impair or harm, directly or indirectly,
any party or the property of the party to influence improperly the actions of a party;
(v) “obstructive practice” is
(aa) deliberately destroying, falsifying, altering or concealing of evidence material to the
investigation or making false statements to investigators in order to materially impede a Bank
investigation into allegations of a corrupt, fraudulent, coercive or collusive practice; and/or
threatening, harassing or intimidating any party to prevent it from disclosing its knowledge of
matters relevant to the investigation or from pursuing the investigation, or
(bb) acts intended to materially impede the exercise of the Bank’s inspection and audit rights
provided for under clause 23.2.
F. Special Conditions of Contract
1. LABOUR :
The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the
engagement of all staff and labour, local or other, and for their payment, housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail, in such form and at
such intervals as the Engineer may prescribe, showing the staff and the numbers of the several classes of
labour from time to time employed by the Contractor on the Site and such other information as the Engineer
may require.
2. COMPLIANCE WITH LABOUR REGULATIONS :
During continuance of the contract, the Contractor and his sub contractors shall abide at all times by all
existing labour enactments and rules made there under, regulations, notifications and bye laws of the State or
Central Government or local authority and any other labour law (including rules), regulations, bye laws that
may be passed or notification that may be issued under any labour law in future either by the State or the
Central Government or the local authority. Salient features of some of the major labour laws that are
applicable to construction industry are given below. The Contractor shall keep the Employer indemnified in
case any action is taken against the Employer by the competent authority on account of contravention of any of
the provisions of any Act or rules made there under, regulations or notifications including amendments. If the
7 For the purpose of these Guidelines, “another party” refers to a public official acting in relation to the
procurement process or contract execution]. In this context, “public official” includes World Bank staff and
employees of other organizations taking or reviewing procurement decisions. 8 For the purpose of these Guidelines, “party” refers to a public official; the terms “benefit” and “obligation” relate
to the procurement process or contract execution; and the “act or omission” is intended to influence the procurement
process or contract execution. 9 For the purpose of these Guidelines, “parties” refers to participants in the procurement process (including public
officials) attempting to establish bid prices at artificial, non competitive levels. 10
For the purpose of these Guidelines, “party” refers to a participant in the procurement process or contract
execution.
53
Employer is caused to pay or reimburse, such amounts as may be necessary to cause or observe, or for non-
observance of the provisions stipulated in the notifications/bye laws/Acts/Rules/regulations including
amendments, if any, on the part of the Contractor, the Engineer/Employer shall have the right to deduct any
money due to the Contractor including his amount of performance security. The Employer/Engineer shall also
have right to recover from the Contractor any sum required or estimated to be required for making good the
loss or damage suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees of the
Employer at any point of time.
SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE TO ESTABLISHMENTS
ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK
(The law as current on the date of bid opening will apply)
a) Workmen Compensation Act 1923: The Act provides for compensation in case of injury by accident arising
out of and during the course of employment.
b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on satisfaction of certain
conditions on separation if an employee has completed 5 years service or more or on death the rate of 15 days
wages for every completed year of service. The Act is applicable to all establishments employing 10 or more
employees.
c) Employees P.F. and Miscellaneous Provision Act 1952 (since amended): The Act Provides for monthly
contributions by the employer plus workers @ 10% or 8.33%. The benefits payable under the Act are :
(i) Pension or family pension on retirement or death, as the case may be.
(ii) Deposit linked insurance on the death in harness of the worker.
(iii) payment of P.F. accumulation on retirement/death etc.
d) Maternity Benefit Act 1951: The Act provides for leave and some other benefits to women employees in case
of confinement or miscarriage etc.
e) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare measures to be
provided by the Contractor to contract labour and in case the Contractor fails to provide, the same are
required to be provided, by the Principal Employer by Law. The Principal Employer is required to take
Certificate of Registration and the Contractor is required to take license from the designated Officer. The Act
is applicable to the establishments or Contractor of Principal Employer if they employ 20 or more contract
labour.
f) Minimum Wages Act 1948: The Employer is supposed to pay not less than the Minimum Wages fixed by
appropriate Government as per provisions of the Act if the employment is a scheduled employment.
Construction of Buildings, Roads, Runways are scheduled employments.
g) Payment of Wages Act 1936: It lays down as to by what date the wages are to be paid, when it will be paid
and what deductions can be made from the wages of the workers.
h) Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of equal nature to
Male and Female workers and for not making discrimination against Female employees in the matters of
transfers, training and promotions etc.
i) Payment of Bonus Act 1965: The Act is applicable to all establishments employing 20 or more employees.
The Act provides for payments of annual bonus subject to a minimum of 8.33% of wages and maximum of
20% of wages to employees drawing Rs.3500/-per month or less. The bonus to be paid to employees getting
Rs.2500/- per month or above upto Rs.3500/- per month shall be worked out by taking wages as Rs.2500/-per
54
month only. The Act does not apply to certain establishments. The newly set-up establishments are exempted
for five years in certain circumstances. Some of the State Governments have reduced the employment size
from 20 to 10 for the purpose of applicability of this Act.
j) Industrial Disputes Act 1947: The Act lays down the machinery and procedure for resolution of Industrial
disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off
or retrenching the employees or closing down the establishment.
k) Industrial Employment (Standing Orders) Act 1946: It is applicable to all establishments employing 100 or
more workmen (employment size reduced by some of the States and Central Government to 50). The Act
provides for laying down rules governing the conditions of employment by the Employer on matters provided
in the Act and get the same certified by the designated Authority.
l) Trade Unions Act 1926: The Act lays down the procedure for registration of trade unions of workmen and
employers. The Trade Unions registered under the Act have been given certain immunities from civil and
criminal liabilities.
m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of children below 14
years of age in certain occupations and processes and provides for regulation of employment of children in all
other occupations and processes. Employment of Child Labour is prohibited in Building and Construction
Industry.
n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Service) Act 1979: The Act is
applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary
(who has recruited workmen in one state for employment in the establishment situated in another state). The
Inter-State migrant workmen, in an establishment to which this Act becomes applicable, are required to be
provided certain facilities such as housing, medical aid, travelling expenses from home upto the establishment
and back, etc.
o) The Building and Other Construction workers (Regulation of Employment and Conditions of Service) Act
1996 and the Cess Act of 1996: All the establishments who carry on any building or other construction work
and employs 10 or more workers are covered under this Act. All such establishments are required to pay cess
at the rate not exceeding 2% of the cost of construction as may be modified by the Government. The
Employer of the establishment is required to provide safety measures at the Building or construction work
and other welfare measures, such as Canteens, First-Aid facilities, Ambulance, Housing accommodations for
workers near the work place etc. The Employer to whom the Act applies has to obtain a registration
certificate from the Registering Officer appointed by the Government.
p) Factories Act 1948: The Act lays down the procedure for approval at plans before setting up a factory, health
and safety provisions, welfare provisions, working hours, annual earned leave and rendering information
regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises
employing 10 persons or more with aid of power or 20 or more persons without the aid of power engaged in
manufacturing process.
3. SUB-CONTRACTING (GCC Clause 7)
Please add the following as Clause 7.2:
The contractor shall not be required to obtain any consent from the employer for:
a) the sub-contracting of any part of the Works for which the Sub-contractor is named in the contract;
b) the provision of labour; and
c) the purchase of materials which are in accordance with the standards specified in the Contract.
Beyond this if the contractor proposes sub-contracting any part of the work during execution of works,
because of some unforeseen circumstances to enable him to complete the work as per terms of the contract,
the Engineer will consider the following before according approval:
55
- The contractor shall not sub-contract the whole of the Works.
- The contractor shall not sub-contract any part of the Work without prior consent of the Engineer. Any
such consent shall not relieve the contractor from any liability or obligations under the contract and he
shall be responsible for the acts, defaults and neglects of any sub-contractor, his agents or workmen as
fully as if they were the acts, defaults or neglects of the contractor, his agents or workmen.
- The Engineer should satisfy whether (a) the circumstances warrant such sub-contracting; and (b) the
sub-contractors so proposed for the Work possess the experience, qualifications and equipment
necessary for the job proposed to be entrusted to them in proportion to the quantum of work to be sub-
contracted.
- If payments are proposed to be made directly to that sub-contractor, this should be subject to specific
authorization by the prime contractor so that this arrangement does not alter the contractor's liability or
obligations under the contract.
4. ARBITRATION (GCC Clause 25.3)
The procedure for arbitration will be as follows :
25.3 (a) In case of Dispute or difference arising between the Employer and a domestic contractor relating to
any matter arising out of or connected with this agreement, such disputes or difference shall be settled
in accordance with the Arbitration and Conciliation Act, 1996. The arbitral tribunal shall consist of 3
arbitrators one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be
chosen by the two Arbitrators so appointed by the Parties and shall act as Presiding arbitrator. In case
of failure of the two arbitrators appointed by the parties to reach upon a consensus within a period of
30 days from the appointment of the arbitrator appointed subsequently, the Presiding Arbitrator shall
be appointed by the President of the Institution of Engineers
(India)_____________________________________________
(Note: 1. All bidders are expected to indicate clearly in the bid, if they proposed sub-contracting elements of the works amounting to more than 20
percent of the Bid Price. For each such proposal the qualification and the experience of the identified sub-contractor in the relevant field should be
furnished alongwith the bid to enable the employer to satisfy himself about their qualifications before agreeing for such sub-contracting and include it in
the contract. In view of the above, normally no additional sub-contracting should arise during execution of the contract. 2. However, [a] sub contracting for certain specialized elements of the work is not unusual and acceptable for carrying out the works
more effectively; but vertical splitting of the works for subcontracting is not acceptable. [b] In any case, proposal for sub-contracting in
addition to what was specified in bid and stated in contract agreement will not be acceptable if the value of such additional sub-
contracting exceeds 25% of value of work which was to be executed by Contractor without sub-contracting.
3. Assignment of the contract may be acceptable only under exceptional circumstances such as insolvencies/liquidation
or merger of companies etc.
(b) In the case of dispute with a Foreign contractor the dispute shall be settled in accordance with
provisions of UNCITRAL Arbitration Rules. The Arbitral Tribunal shall consist of three Arbitrators one each to be
appointed by the Employer and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so
appointed by the Parties, and shall act a presiding arbitrator. In case of failure
of the two arbitrators appointed by the parties to reach upon a consensus within a period of 30 days
from the appointment of the arbitrator appointed subsequently, the Presiding arbitrator shall be
appointed by the President of the Institution of Engineers (India)
(c) If one of the parties fails to appoint its arbitrator in pursuance of sub-clause (a) and (b) above within
30 days after receipt of the notice of the appointment of its arbitrator by the other party, then the
President of the Institution of Engineers (India) both in cases of the Foreign Contractor as well as
Indian Contractor, shall appoint the arbitrator. A certified copy of the order of the President of the
Institution of Engineers (India), making such an appointment shall be furnished to each of the parties.
(d) Arbitration proceedings shall be held at Bhubaneswar, India, and the language of the arbitration
proceedings and that of all documents and communications between the parties shall be English.
56
(e) The decision of the majority of arbitrators shall be final and binding upon both parties. The cost and
expenses of Arbitration proceedings will be paid as determined by the arbitral tribunal. However, the
expenses incurred by each party in connection with the preparation, presentation, etc. of its
proceedings as also the fees and expenses paid to the arbitrator appointed by such party or on its
behalf shall be borne by each party itself.
(f) Where the value of the contract is Rs.50 millions and below, the disputes or differences arising shall
be referred to the Sole Arbitrator. The Sole Arbitrator should be appointed by agreement between the
parties; failing such agreement, by the appointing authority, namely the President of the Institution of
Engineers (India)/.
(g) Performance under the contract shall continue during the arbitration proceedings and payments due to
the contractor by the owners shall not be withheld, unless they are the subject matter of the arbitration
proceedings.
5. PROTECTION OF ENVIRONMENT:
Add the following as GCC Clause 16.2:
The contractor shall take all reasonable steps to protect the environment on and off the Site and to avoid
damage or nuisance to persons or to property of the public or others resulting from pollution, noise or other
causes arising as a consequence of his methods of operation.
During continuance of the contract, the contractor and his sub-contractors shall abide at all times by all
existing enactments on environmental protection and rules made thereunder, regulations, notifications and
bye-laws of the State or Central Government, or local authorities and any other law, bye-law, regulations that
may be passed or notification that may be issued in this respect in future by the State or Central Government
or the local authority.
Salient features of some of the major laws that are applicable are given below :
The Water (Prevention and Control of Pollution) Act, 1974, This provides for the prevention and control of
water pollution and the maintaining and restoring of wholesomeness of water. 'Pollution' means such
contamination of water or such alteration of the physical, chemical or biological properties of water or such
discharge of any sewage or trade effluent or of any other liquid, gaseous or solid substance into water
(whether directly or indirectly) as may, or is likely to, create a nuisance or render such water harmful or
injurious to public health or safety, or to domestic, commercial, industrial, agricultural or other legitimate
uses, or to the life and health of animals or plants or of aquatic organisms.
The Air (Prevention and Control of Pollution) Act, 1981, This provides for prevention, control and abatement
of air pollution. 'Air Pollution' means the presence in the atmosphere of any 'air pollutant', which means any
solid, liquid or gaseous substance (including noise) present in the atmosphere in such concentration as may be
or tend to be injurious to human beings or other living creatures or plants or property or environment.
The Environment (Protection) Act, 1986, This provides for the protection and improvement of environment
and for matters connected therewith, and the prevention of hazards to human beings, other living creatures,
plants and property. 'Environment' includes water, air and land and the inter-relationship which exists among
and between water, air and land, and human beings, other living creatures, plants, micro-organism and
property.
The Public Liability Insurance Act, 1991, This provides for public liability insurance for the purpose of
providing immediate relief to the persons affected by accident occurring while handling hazardous substances
and for matters connected herewith or incidental thereto. Hazardous substance means any substance or
preparation which is defined as hazardous substance under the Environment (Protection) Act 1986, and
exceeding such quantity as may be specified by notification by the Central Government.
57
5.2 Environment Management Plan
The Environment Management Plan (EMP) is a set of measures for avoidance, minimization and mitigation of
adverse environmental impacts. The Contractor will abide by the environmental, occupational health and safety
measures listed in the Environment Management Plan (EMP) given in the table below during preparation and
execution of Works. Adverse impact/s on the environment caused due to non-adherence of legal and EMP
requirements during preparation and execution of civil works shall be made good at the Contractor’s own expenses.
The Engineer’s check and certification for payment, in accordance to requirements under Clause 42.2 of GCC, shall
also include the performance review of the Contractor with regard to EMP compliance.
The complete document on Environmental and Social Management Framework (ESMF) from which these
conditions have been derived/listed is available with the Engineer and State Disaster Management Authority
(SDMA) for the Contractor’s reference. It is also available on the websites of National Disaster Management
Authority (NDMA) and State Disaster Management Authority (SDMA).
S.
No. Activity Measures to be Implemented by the Contractor
1. Work Plan for
EMP
implementation
The Contractor’s Project Manager shall be responsible for implementation of EMP provisions and
will coordinate the over-all implementation of the said plan. Along with the Work Programme, the
Contractor shall submit a plan including method statement and timeline about specific actions that will be taken by him to implement the provisions laid out in the EMP.
2. Regulatory
Permissions and Consents
The Contractor shall obtain all requisite statutory clearances prior to commencement of civil works,
which includes obtaining permission/consent for plants, water extraction and borrow areas operations. This includes:
Consent for establishment and operation of plant (for concrete work) from SPCB
PUC certification for all vehicles/equipment used for/during construction
Permission/consent of the District Administration/Mining Department/other agencies for quarrying and/or borrowing operations for materials like sand and earth
Permission for water extraction, if applicable in the local area context.
The Contractor shall abide by all conditions laid out in the said clearances.
3. Consultation and
Community Consent
The Contractor shall consult and obtain written consents of landowners (individual/panchayat/govt.
agency) for temporary use of land for all construction related activities including:
(a) setting-up and operation of construction camp including labour camps, stock yards etc.
(b) borrow areas and
(c) disposal of debris and other waste material.
4. Construction/
Labour Camp
(a) Location: The camp and plant site/s location and establishment shall be done in a manner that
does not interfere or disturb the activities of local inhabitants, particularly those of schools and
health facilities. Written permission (no objection certificate) shall be taken from the Gram
Sabha and the land owner prior to location selection and a copy shall be submitted to the
Engineer for approval.
(b) Camp site shall not be located within 250 mts. from a water body including village ponds.
(c) A distance of at least 500 mts. shall be maintained from designated/protected natural habitats
(such as National Parks, Sanctuaries, Biosphere Reserves, ReserveForests and Ramsar Sites) and Coastal Regulation Zone.
(b) Accommodation and Basic Amenities: All weather shelter with the required tenement size and
toilets shall be provided, as per provisions of Labour Laws. Separate toilet facilities shall be
provided for women workers. If a common mess is not provided/operated, additional space for
cooking shall be provided. The contractor shall ensure that hygienic conditions are maintained
during the operation of such camps/facilities.
(c) Fuel for Cooking: The Contractor shall ensure that fuel wood is not used as a cooking medium
in the construction/labour camp.
(d) Potable water supply: Drinking water supply of at least 40 lpcd with the required supply points
shall be provided.
(e) Fire Safety: Adequate fire safety precautions shall be taken and required fire safety equipment
(such as fire extinguishers) shall be provided by the Contractor.
58
S.
No. Activity Measures to be Implemented by the Contractor
5. Site Clearance (a). No tree cutting is to carried out without the written instruction from the Employer, who in turn
will ensure that relevant regulatory permission/s (including those from Forest Dept., if required)
are obtained prior to cutting of such trees.
(b) The non-timber grade trees are to be stacked and possession is to be given to
Employer/concerned Govt. Department.
(c) The Contractor shall strip, store and preserve top soil from the site of construction work and in
the stock yards prior to stacking of materials. The top soil shall be reinstated in the Tourist Guide Centre compound after the construction is over.
6. Protection of
Properties and Resources
The Contractor shall take due care to protect and prevent damages to the following resources during
preparatory and construction work:
a. Water supply lines
b. Irrigation canals
c. Cart, cattle and/or foot trail/tracks
d. Cultural properties and sites/structures of religious importance
e. Houses, Farmlands, Orchards and/or Trees
f. School and other existing buildings adjacent to the site of construction
In case of damage due to construction activity, the restoration/repairs shall be carried out by the
Contractor at his own cost.
7. Quarry
Operations
The Contractor shall procure material from quarries that have been approved/licensed by the State
Govt. A copy of such an approval shall be submitted to the Engineer prior to procuring material.
8. Borrow Areas (a) Borrow areas for the project will be selected by the Contractor following the stipulations given
below. The finalization of all such locations shall be dependent on the approval of the Engineer
on technical and environmental grounds. This includes on-site verification to cross-check the
accuracy of details provided by the Contractor. Only after receipt of the written approval from the Engineer, the Contractor shall enter into a formal agreement with landowner.
(b) The Contractor shall not procure any kind of construction material (such as aggregates, sand and
earth) from ecologically protected areas.
(c) Identification and Selection
1. The borrow area should not be located in agriculture field/s unless unavoidable i.e. barren
land is not available. In case borrowing needs to be done on an agricultural land, top-soil
stripping, stacking and preservation is a must.
2. Borrow pits shall not be located within a distance of 100 mts. from any NH, SH or other
roads.
3. Borrow pits shall be preferably located 500 mts. away from settlements/ habitations.
4. No borrow pits shall be located within 500 mts. from schools, colleges, playgrounds,
religious structures and health centres.
5. No borrow area shall be opened within 500 mts. from a reserved or protected forest area,
protected sites, wildlife movement zone and cultural heritage site.
6. No tree cutting shall be undertaken.
7. Borrow area near any surface water body will be at least 100 mts. away.
(d) Operation
1. Area up to which material will be extracted shall be clearly demarcated on ground.
2. A 15 cm topsoil layer will be stripped and preserved in stockpiles.
3. Borrowing of earth should be preferably limited to a depth of 1.5 mtr from the existing
ground level.
4. Slope at the edges will be maintained not steeper than 1:3 (Vertical: Horizontal).
59
S.
No. Activity Measures to be Implemented by the Contractor
(e) Rehabilitation of Borrow Areas
1. Rehabilitation shall be satisfactorily undertaken immediately after the use has ceased and at
least three weeks prior to monsoon.
2. Preserved top soil has be spread uniformly over land (except in cases where borrow area is
developed as a water body) used as a borrow area.
9. Water Extraction/ Use
Water for construction and for use at construction camps (including labour camps) is to be extracted
with prior written permission of (a) the individual owner, in case the source is private well/tube
well; (b) Gram Panchayat in case the source belongs to community; and (c) Irrigation Department in case the source is an irrigation canal or a river.
10. Safety of Road
Users and Local Residents
(a) Traffic safety arrangements (including provision of warning signage, speed breakers etc.) shall
be made by the Contractor to ensure safety of road users and local people, particularly in the
internal village roads which will be used for transporting materials.
(b) Material shall be covered during transportation to prevent spillage, accidents and pollution.
(c) All required measures to ensure safety of local residents including children and other near-by
residents shall be taken up by the Contractor. This shall include provisions to prevent
unauthorised entry into the construction site and camp; fire and electrical safety measures; pre-cautions around excavation such as barricading and warning signs and safe storage of material.
11. Worker’s Safety (a) All measures required for ensuring safety and health of the workers shall be taken up by the
Contractor. This includes provision and enforcement of appropriate personal protective
equipment; first aid facility; emergency response arrangement; proper storage of hazardous/
toxic and polluting materials and; measures for ensuring fire, electrical and mechanical safety arrangements in camp and in work site.
(b) All methods, steps and measures required for ensuring safety of workers, particularly those
needed while undertaking work in or around excavations; working at height; and; while handling inflammable, toxic and/or hazardous materials shall be ensured by the contractor.
(c) Material safety data sheet record of fuel and other inflammable chemicals shall be maintained at
the site.
12. Air Pollution (a) Wind barriers or screens shall be provided in the downwind direction at air pollution causing
sources like plant sites and fine material storage stock yards.
(b) Fugitive dust emissions have to be eliminated by providing dust suppression/control measures,
such as water sprinkling and cover on materials, based on activity and site conditions.
(c) All plants and equipment shall comply with pollution control norms.
(d) Water shall be sprinkled at least twice during dry day on haulage roads passing through or near
settlements (including at least 100 m before the settlement).
13. Water pollution (a) All measures (including provision of temporary silt fencing to control sediment run-off) required
for avoiding adverse impacts to water bodies (such as ponds, streams, canals and rivers), water
sources (such as hand pumps and wells) and adjacent farmland shall be undertaken by the Contractor.
(b) Storage of materials like fuel, chemicals and cement shall be done in a manner (with impervious
layer on bottom and a covered shed on top) that does not contaminate land and ground/surface water.
14. Noise Pollution (a) All noise causing activities shall be stopped during night time (9:00 PM to 6:00 AM). The
Contractor shall schedule construction works in consultation with local Panchayat Authority and
School Principal to ensure least disturbance to school children and other adjacent residents.
(b) Ear plugs shall be provided to the labour facing risk from high noise pollution such as plant site
and those working near generators, heavy equipment/machinery.
(c) Appropriate noise controlling devices including acoustic generators shall be used to minimise
noise during construction work and operation of camp.
60
S.
No. Activity Measures to be Implemented by the Contractor
15. Disposal of
Debris/Wastes
(a) Debris and other construction waste, if any, shall be disposed in locations pre-approved by the
Engineer in a manner that it does not contaminate the environment.
(b) Location of Debris Disposal Sites: Debris disposal sites shall be located preferably away from
farmlands, water sources and water bodies. In no case, debris shall be disposed within 500 mts. of ecologically sensitive areas, including forests, wetlands and protected natural habitats.
16. Restoration and
Rehabilitation of
Sites
All work sites and areas under temporary use (including construction and labour camps, plant sites,
haul roads and borrow areas) shall be restored/ rehabilitated to a better condition (if not at least to its
original condition) and to the satisfaction of the Engineer and land owner upon completion of
construction work by the Contractor.
Completion of work (as covered under clause 55.1 of GCC) will also include completion of
rehabilitation and clean-up of the work sites including camps, plants, in and around the construction
site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas
and other sites/locations used for material sourcing.
17. Liabilities Any liability arising out of Contractor’s agreement with landowners/ local people/gram panchayat
(including those related to temporary use of land, water extraction and disposal of debris) shall be settled by the Contractor.
61
SECTION 4: CONTRACT DATA
62
Contract Data
Items marked "N/A" do not apply in this Contract.
The following documents are also part of the Contract: Clause Reference
· The Schedule of Operating and Maintenance Manuals [58]
· The Schedule of Key Personnel [09]
· The Methodology and Program of Construction & Environmental Management Plan [27]
· The Schedule of Key and Critical equipment to be deployed [27]
on the work as per agreed program of construction
The Borrower is Government of India and Government of ODISHA is a participating state in the
Integrated Coastal Zone Management project
The World Bank means International Development Association [1.1]
and loan refers to an IDA Credit
The Employer is
Name: The Conservator of forests (WL)-cum- Nodal Officer, ICZMP, Odisha, O/O PCCF, Bhubaneswar.
Name of authorized Representative: Mrs. Meeta Biswal, IFS The Engineer is
(Give a name with address) (1.1)
Name:
The Adjudicator appointed jointly by the Employer and Contractor is:
*Name : Sri Sridhar Behera,
Address : Retd Engineer-in-Chief. WRD Deptt.,Govt. of Odisha
The name and identification number of the Contract is: ICZMP/WL/W/16/13-14
The Works consist of Renovation of Hukitola Building at Hukitola
The work is to be executed in the financial year 2013-14. (1.1) [brief summary, including relationship to other contracts under Project
The Start Date shall be the date of issue of notice to proceed with the work (1.1)
The Intended Completion Date including rainy season for the whole of the Works is 12 (Twelve)
months
with the following milestones: [17, 28]
Milestone dates:
63
Physical works to be completed Period from the date of issue of notice to proceed with
the work
Milestone 1 i.e Removal of vegetation,damaged,old lime & cement plaster
Surface etc. 3 months.
Milestone 2 i.e. All lime/cement plaster work, fixing of tile 6 months.
Milestone 3 i.e. Balance Work including painting & Finishing, 12 months.
The following documents also form part of the Contract: [2.3]
_____________________NIL________________
The Contractor shall submit a revised Program including Environmental
Management Plan for the Works (in such form and detail as the
engineer shall reasonably prescribe) within 14 days of
delivery of the Letter of Acceptance. [27]
The Site Possession Dates shall be: Seven days
from the date of signing the Agreement [21]
The Site is located at Hukitola under Kenrapada district
The Defects Liability Period is 365 days from the date of certification of completion of works.
[35]
Insurance requirements are as under: [13]
Minimum Cover for
Insurance
Maximum deductible
for Insurance
(i) Works and Plant and
Materials
Contract value 5% of the Contract
Value
(ii) Loss or damage to
Equipment
Total book value of the
equipment brought to the
site by the contractor
5% of the figure
alongside
(iii
)
Other Property
Rs.10,00,000/- Rs.10,000/-
(iv
)
Personal injury or death
insurance:
a) for other people;
As per Workmen’s
Compensation Act 1923
and other Acts in force.
As per Workmen’s
Compensation Act
1923 and other Acts in
force.
b) for Contractor’s
Employees
In accordance with the statutory requirements
applicable to India
64
The following events shall also be Compensation Events: NIL [44]
The period between Program updates shall be 30 days. [27]
The amount to be withheld for late submission of an updated
Program shall be Rs. 3000.00 per day [27]
The language of the Contract documents is English [3]
The law which applies to the Contract is the laws of Union of India [3]
The currency of the Contract is Indian Rupees. [46]
Fees and types of reimbursable expenses to be paid to the Adjudicator [25]
Rs. 3000.00 per sitting plus reimbursable expenses, (i.e.) Traveling, boarding & lodging
expenses.
In case appointed by the President, Institute of Engineers, India at a daily fee per sitting as
suggested
by the Institute of Engineers, India.
Appointing Authority for the Adjudicator: The President, Institution of Engineers (India)[26]
The formula(e) for adjustment of prices are:[Deleted] [47]
The proportion of payments retained (retention money) shall be 06 % from each bill
subject to a maximum of 05% of final contract price [48]
The liquidated damages for the whole of the works are
per day and that for the milestone are as under : [49]
For milestone 1 Rs. 3000.00 per day
For milestone 2 Rs. 6000.00 per day
For milestone 3 Rs.12000.00 per day
The maximum amount of liquidated damages for the whole of the works [49]
is ten percent of final contract price.
The amounts of the advance payment are: [51]
Nature of
Advance
Amount (Rs.) Conditions to be fulfilled
1. Mobilization 5% of the Contract price On submission of un-conditional Bank
Guarantee.
(to be drawn before end of 20% of Contract
period)
65
2. Secured
advance for
non-
perishable
materials
brought to site
75% of Invoice value or
Market value - lower of the
two.
a) The materials are in-accordance with the
specification for Works;
b) Such materials have been delivered to
site, and are properly stored and protected
against damage or deterioration to the
satisfaction of the Engineer. The
contractor shall store the bulk material in
measurable stacks.;
c) The Contractor’s records of the
requirements, orders, receipt and use of
materials are kept in a form approved by
the Engineer and such records shall be
available for inspection by the Engineer;
d) The contractor has submitted with his
monthly statement the estimated value of
the materials on site together with such
documents as may be required by the
Engineer for the purpose of valuation of
the materials and providing evidence of
ownership and payment thereof;
e) Ownership of such materials shall be
deemed to
vest in the Employer for which the
Contractor
has submitted an Indemnity Bond in an
acceptable format; and
f) The quantity of materials are not
excessive
and shall be used within a reasonable
time as
determined by the Engineer.
(The advance payment will be paid to the Contractor no later than 15 days after fulfillment of the
above conditions).
Repayment of secured advance:
The advance shall be repaid from each succeeding monthly payments to the
extent materials [for which advance was previously paid pursuant to Clause
51.4 of G.C.C. and 51(3) of Contract Data on prepage] have been
incorporated into the Works.
The Securities shall be for the following minimum amounts equivalent as a
percentage of [52]
the Contract Price:
66
Performance Security for 5 per cent of contract price plus Rs. ..................... as additional
security for unbalanced bids [in terms of ITB Clause 29.5].
The standard form of Performance Security acceptable to the Employer shall be an
unconditional
Bank Guarantee of the type as presented in Section 8 of the Bidding Documents.
*The date by which operating and maintenance manuals are required is within 28 days of
issue [58]
of certificate of completion of whole or section of the work, as the case may be.
*The date by which “as-built” drawings (in scale 1:100) in 2 sets are required is within
28 days of issue of certificate of completion of whole or section of the work, as the case
may be. [58]
The amount to be withheld for failing to supply “as built” drawings and/or
operating and [58]
maintenance manuals *by the date required is Rs.30,000.00
The following events shall also be fundamental breach of contract: [59.2]
1. The Contractor has contravened Sub-clause 7 of GCC read with SCC
and Clause 9.0 of GCC
2. The contractor does not adhere to the agreed construction program and
agreed environmental management plan (Clause 27 of GCC) and also
fails to take satisfactory remedial action as per agreements reached in
the management meetings (Clause 31) for a period of 60 days.
3. The contractor fails to carry out of the instructions of Engineer within a
reasonable time determined by the Engineer in accordance with GCC
Clause 16.1 and 23.1.
The percentage to apply to the value of the work not completed representing the
Employer's [60]
additional cost for completing the Works shall be 20 percent.
67
SECTION 5
TECHNICAL SPECIFICATIONS
68
1. TECHNICAL SPECIFICATION FOR CIVIL WORKS
1.1 General :
1.1.1 Scope of work :
The work contemplated under this contract includes general Builder’s work for the aforesaid
project, all as detailed in the Bill of Quantities, Specifications and drawings and to complete
the said work in every respect in accordance with this contract and with the directions and to
the satisfaction of the Engineer-in-charge.
Such other works which are not included in the aforesaid Bill of quantities are generally
intended to be executed through a separate agency. Notwithstanding the above, the
Engineer-in-Charge reserves the right to order additional works under the same Contract.
The Engineer-in-charge also reserves the right to omit any item of work included in the
aforesaid Bill of quantities and award the same to any other contractor or not perform it at all
at his discretion and the Contractor shall not have any claim because of the same.
The Contractor for this work shall be required to work in co-operation and co-ordination with
other agencies on site and give them all reasonable assistance and help for the execution of
the work in an efficient manner all as directed. The words “approved” or “as directed” shall be
deemed to convey approval or the discretion of the Engineer-in-charge of the work.
1.1.2 Indian Standard Specification :
The particular Specifications for the work are as detailed hereinafter. These specifications
shall be read in conjunction with the relevant Indian Standard Specifications. The obtainable
local practice as detailed in various regional handbooks of practice may be used subject to
specific approval from the Engineer-in-charge. Where the specifications in any of the
standards are at variance with the specifications detailed herein, the specifications herein
shall govern.
1.1.3 Quality of Materials & General Standards of work :
The contractor under this contract commits himself to use materials conforming to relevant
Indian Standards / Codes and assumes full responsibility for the quality of all materials
incorporated or brought for incorporation in the work, the work shall be executed in
accordance with acceptable engineering practice and as per direction of the Engineer-in-
charge.
1.1.4 Scaffolding :
All scaffolding and ladders required for the proper execution of the work shall be provided by
the contractor. The scaffolding should be stout and strong to prevent any collapse or
displacement. Proper measures for safety of workmen working on scaffolding should be
taken by the contractor.
The mode of measurements, wherever possible is specifically mentioned in these
documents. Where it has not been mentioned, it shall be as per provision of the relevant
69
Indian Standards. All the measuring tapes and other accessories necessary, shall be
provided by the contractor.
The bidder along with his bid shall furnish a list of tools, plant and machinery which he
intends to use on the works in Bid document. The list should indicate the exact type of
machine, its capacity, year of manufacture, kind and capacity of propelling force, spare parts
readily available and all other pertinent information. The contractor is obliged to use the
machinery mentioned in his list if the Engineer-in-charge considers it necessary.
1.1.5 Surveying and staking :
It is the express responsibility of the contractor to bring to site all surveying instruments
necessary for the marking out, fixation of levels, etc. and conduct these survey operations
himself with utmost accuracy. The contractor shall put up stable bench marks etc. as
necessary for the work. Engineer-in-charge / his representative will be present when this
work is being carried out and will inspect all these operations with the contractor’s
assistance. The contractor shall be entirely responsible for accurate setting out the work and
he shall at his own expense make good any defects arising from errors in the line and levels.
1.1.6 Dewatering :
Dewatering of accumulated water in all locations on work site from whatever source of cause
until the virtual completion of the entire work shall be done by the contractor at his own
expenses and shall not be separately paid for. The rates quoted by the contractor shall be
deemed to be inclusive of this.
1.1.7 Access to site, approach roads and roads within the premises :
The contractor shall at his own cost provide all approach roads required for the purpose of
carrying out the work in the most expeditious and efficient manner and shall remove the
temporary roads on completion. He shall acquaint himself thoroughly regarding condition and
suitability of public roads leading up to the limits of the premises and will provide vehicles for
transportation of materials which meet the requirements of these road conditions. It shall also
be the responsibility of the contractor to maintain at his own cost the road till the construction
is completed. The bidder is also to acquaint himself with local laws and bylaws and comply
with all police and highway authority requirements.
1.2 Earth work:
1.2.1 Excavation:
Excavation for trenches over areas and for pits, etc. shall be done to widths, lines and levels
as shown in drawings or to such lesser or greater widths, lines and levels as directed. The
bottom and side of excavation, required levels, profile, etc. watered and thoroughly rammed.
Where the contractor excavated below required level in good ground inadvertently or
carelessness he shall make up the void in concrete M-10 at his own expense. During
excavation the contractor shall take necessary precaution to retain earth, so that the earth
will not slide or fall down to avoid any accident and hamper the progress of work. He will take
necessary steps to prevent the damage to adjacent structure or existing services. He shall
70
repair and make good any such damages at his own expense to the satisfaction of the
owner. A suitable path for men and materials around the excavated pit should be maintained
throughout the work. Stacking or excavated earth from trenches, bids etc. shall be done
away from the pit at a minimum distance equivalent to the depth of pit/trenches/foundation
up to a initial lead and lift as directed by the Engineer-in-Charge.
1.2.2 Dewatering:
All water that may get accumulated in excavations during the progress of work from
whatever cause or source, shall be bailed or pumped out as necessary. The rates for
excavation shall be deemed to include the same, if not otherwise specified.
1.2.3 Timbering & excavation (Shoring)
Where the soil is soft and sides of excavation needs supporting, suitably designed planking
and strutting shall be provided. The rates for excavation shall be deemed to include all
planking and strutting as necessary.
1.2.4 Refilling around foundations:
Refilling around foundations shall be done with approved excavated materials. Refilling shall
be done in layers not exceeding 15cms thick, watered adequately and consolidated with
pneumatic tampers or other suitable compactors. The finished surface of filling shall be
slightly proud to bring it to finished level after watering and consolidation as directed. The
rates for refilling around foundations shall be deemed to include this.
All materials considered surplus shall be removed to destinations and disposed off as
directed. The disposal of the materials can be in any of the following ways as directed by the
Engineer-in-Charge of the work.
1. Filling in low lying areas.
2. Filling in at places of filling such as under floors, in roads etc.
3. Stacking of materials in pre-designated stacking yard.
4. Removal of materials outside the plot for disposal.
1.2.5 Filling:
Filling under floors or other places indicated shall be done with good quality sand conforming
to zone 2 or 3 I.S: 383. Filling shall be done in layers, each layer watered adequately and
consolidated to specified density by suitable compacting equipment. Thickness of each layer
shall not exceed 15 cm. The surface of the filling shall be finished to lines and levels as
required. The filling shall be compacted in such a manner as to guarantee full stability.
However, the site filling shall be done with Fly Ash from a source as instructed by the
Employer in writing. While the cost of Fly ash shall be borne by the employer, the
transportation and labour costs shall be the responsibility of the contractor.
1.2.6 Measurement:
71
Measurement for all excavation, filling, carting away and earthwork shall be in solid
measure. The rates quoted by the bidders are thus for solid measure units. The following
factors shall be applied to obtain quantities of solid measure.
Excavation : No reduction in volume
Filling, watered and : Volume shall be determined by levels
Consolidated in layers before and after compacted filling and by
measuring the lengths and breadth as required.
The mode of measurement for various types of excavations shall be as under:
a) In case of trenches, pits and areas, measurement shall be on the basis of width of
foundations and the depth of bottom of foundation (bottom of bed concrete, if provided)
formation.
b) In case of pipe trenches and drains, measurement of width of trench shall be diameter of
the pipe plus an allowance of 50 cms. To allow for collars, flanges etc.
c) Excavation in rock shall be measured up to levels indicated or required. No undulations as
physically appearing after excavations shall be taken into consideration while arriving at the
quantities. The rates quoted by the contractor shall be deemed to include for this and no
extra is admissible.
1.2.7 Sub-grade Conditions:
When no data is available of soil formation and depth of water table of proposed work site,
the contractor should make his own arrangements of preliminary site investigation by actual
inspection of the site and surrounding areas to assess the nature of soil and to foresee the
difficulties that may arise during construction period. The contractor shall acquaint himself
of the above before filling up of the bid.
No claim whatsoever will be entertained on any account of conducting these exploratory
works or lack of investigation on the part of the contractor.
1.3 Plain & Reinforced Concrete, Controlled Concrete
1.3.1 General :
Concrete and reinforced concrete work shall be carried generally in conformity with the latest
Indian Standards IS: 456 and for provisions indicated here in below. All work is to be carried
out with utmost precision and up to date scientific know how and the contractor shall employ
thoroughly competent staff to achieve acceptable standards conforming to technical
specifications.
1.3.2 Cement:
Portland slag cement (IS: 455) shall be used wherever so directed by the Engineer in Charge
or as shown in drawings or Bill of Quantities. If directed, the contractor shall purchase
cement as fresh as possible after manufacture and where there is reason to believe the
cement has been long stored, the Engineer-in-charge may demand a Laboratory Test
72
Certificate regarding the character of cement and the contractor shall furnish the same at no
extra cost. The Engineer-in-charge shall reject any cement which in his opinion does not
meet the required standards.
All bags and containers in which cement is packed shall be stored in a dry, weather tight,
properly ventilated structure with adequate provision for prevention and absorption of
moisture. The contractor shall at all times maintain for the inspection of the Engineer-in-
Charge a log book indicating the receipt of cement, brand and agent from whom obtained
and the age of cement. Cement, which has caked or perished by being wet or otherwise
shall on no account be used on the work.
Cement shall be consumed on the works in the same sequence as that of their receipt at
site. Cement reclaimed from cleaning of bags or from spillage from containers, or otherwise
shall on no account be used.
Portland Slag Cement is to comply to the relevant Indian Standard Specifications IS 455.
This standard stipulates that the slag constituent shall be not less than 25 per cent and not
more than 65 per cent of the Portland Slag Cement.
1.3.3 Fine Aggregate :
(i) Fine aggregate shall conform to latest Indian standards (IS:383). Sand shall be natural
sand, crushed gravel sand or crushed stone sand but it must be a well-graded sand
conforming to IS grading and its FM be 2.4 to 3.2. Use of sea sand is prohibited. It
shall be composed of hard siliceous material and shall be clean and of sharp angular grit
type. Sand shall be properly graded minimizing all voids.
(ii) Allowance for bulking of wet sand shall be made. Bulkage limit is to be restricted to less
than 20%. Silt content in sand should not be more than 5%. Laboratory equipment such
as measuring jars etc. are to be kept at site for time to time checking of bulkage and silt
content.
(iii) Sand shall be free from any harmful organic impurities. Quick colour test should be made
at site for the consignment of sand receiver. Colour test details are given below:
Colour Test of Sand:
The sand shall be tested with 3% solution of caustic soda (Sodium Hydroxide), which is
called “Colour Test”. This is a reliable indicator of the presence or otherwise of any organic
matter in sand as under.
(i) A colour less liquid indicates clean sand free from organic matter.
(ii) A straw coloured liquid indicates some organic matter but not enough to be seriously
objectionable; and
(iii) A dark colour means that the sand contains injurious amount of organic matter and
should not be used unless it is washed and a retest shows that it is satisfactory.
1.3.4 Coarse Aggregate:
73
Coarse aggregate shall be approved hard aggregate conforming to latest Indian Standards
(IS: 383) details of which are as follows.
(i) Deleterious materials : less than 5%
(ii) Specific gravity : not less than 2.6 (2.6 to 3)
(iii) Water absorption value : about 1% by weight
(iv) Aggregate crushing value : for wearing surface less than 30%
for other concrete surface less than 45%
(v) Aggregate impact value : for wearing surface less than 30%
for concrete other than wearing surface less
than 45%
(vi) Aggregate abrasion value : for wearing surface less than 30%
for concrete other than wearing
surface less than 50%.
(vii) Soundness (sodium
sulphate method) : less than 12%
Aggregate, Gradation, storage, etc.
Aggregates of various specified sizes shall be stock piled properly and separately.
Aggregates shall be clean and shall not contain any foreign matter, silt, loose or
destructive substances, harmful chemicals etc.
Aggregates shall be stored in proper bins, which shall have good drainage to prevent
the inclusion of foreign matter and preserve the gradation. Sufficient live storage shall
be maintained to permit segregation of successive shipment, placing of concrete at
the required rate and such procedures as inspection and testing.
If directed, the aggregate shall be washed before use. The grading of aggregate for
use on works shall be as per the Indian Standards (IS : 456 )
1. Grading of Coarse Aggregate as per IS: 456
Sl No. IS size % Passing for graded aggregate of nominal size.
40mm 20mm 16mm 12.5
1 40mm 95-100 100 - -
2 20mm 30-70 95-100 100 -
3 16mm - - 90-100 100
4 12.5mm - - - 90-100
5 10mm 10-35 25-55 30-70 40-85
6 4.75mm 0-5 0-10 0-10 0-10
7 2.36mm - - - -
2. Grading of Single Size Aggregate as per IS: 456
Sl No. IS size % Passing for single aggregate of nominal size.
74
40mm 20mm 16mm 12.5mm 10.00 mm
1 40mm 85-100 100 - - -
2 20mm 0-20 85-100 100 - -
3 16mm - - 85-100 -100 -
4 12.5mm - - - 85-100 100
5 10mm 0-5 0-20 0-30 0-45 85-100
6 4.75mm - 0-5 0-5 0-10 0-20
7 2.36mm - - - - 0-5
Proper sieve analysis shall be carried out to determine the best gradation obtainable from the
available aggregates. The sieve analysis shall be performed as per standard practice and as laid
out in the relevant Indian standards.
1.3.5 Water :
Water for all concrete work shall be clean, free from deleterious matter such as oils, acids,
alkalis, sugar and vegetable matter. Permissible limits for solids shall conform to IS 456.
Every attempt shall be made to use water which is fit for drinking purposes. Water storage
facilities provided by the contractor shall be maintained properly to preclude contamination
of water by any of the harmful substances. The quantity of water to be added to concrete
for mixing shall be such as to afford workability consistent with strength requirements.
Water cement ratio shall be maintained constant as specified (0.45 for RCC and recorded
in every batch of concrete. P.H. of water shall be in the range 6-9.
The permissible limits, as per IS 456- areas following :
SL. NO. Tested as per Permissible Limit (Max)
(i) Organic------------------- IS 3025 (part – 18)-------------------200 mg/litre
(ii) In organic ---------------- IS 3025 (part 18) --------------------3000 mg/litre
(iii) Sulphates ( as SO3) ----- IS 3025(part 24)---------------------400 mg/litre
(iv) Chlorides (as Cl)--------- IS 3025 (part 32)---------------------2000 mg/litre for
concrete not containing embedded
steel and 500 mg / litre for RCC work.
(v) Suspended matter----- IS 3025 (part – 17) ---------------------2000 mg/litre
The water cement ratio, being of paramount importance governing the durability of
concrete, it should be of the lowest feasible value. In the subject under reference, it should
be 0.45 for M30 RCC and to achieve sufficient workability, it may be necessary to use
suitable super-plasticizer in the concrete mix to ensure efficient placement of concrete.
1.3.6 Plasticizers: -
The commonly available admixtures with good to high plastic zing effects are:
(i) Modified ligninsulphonates (MLS)
(ii) Sulphonated melamine condensates (SMF)
75
(iii) Sulphonated naphthalene condensates (SNF)
(iv) Poly Carboxylic ethers (CE)
Typical performance of water reducing admixtures are outlined below:
Type of super-plasticiser Typical dosage by cement weight Water reduction
MLS 0.2-0.8% Up to 10%
SMF 1.0-3.0% Up to 25%
SNF 0.8-2.0% Up to 25%
CE (Poly Carboxylic ethers)
0.5-1.5% Up to 40%
The super-plasticiser based on Poly Carboxylic Ethers (CE) is proving much better than others.
The type and dosage of Super-plasticiser to be used shall be subject to the approval of the
Engineer-in-charge. The dosage shall be arrived at through lab. tests / mix design tests as
approved by the Engineer-in-charge.
1.3.7 Types of concrete, strengths etc. :
The Bill of quantities specifies various types of concrete. The strengths corresponding to
these types is as per table below :
i. Types of Concrete
Sl.
No.
Type of Concrete 28 day Characteristic Design strength N/mm2
28 day Target Design Strength N/mm2.
1 M-15 15 15 + 1.65 X 3.5 =20.8
2 M-20 20 20 + 1.65 X 4.0 = 26.6
3. M-30 30 30 + 1.65 X 5.0 = 38.2
Note : The established values of standard Deviations shall be used. When adequate test
results (30 or more) are available and the target strengths revised thereafter. Efforts shall be
made to bring the standard Deviations up to date, preferably once a month.
Even though the Bill of quantities specifies various types of concrete, it is possible that the
type may be altered to suit the site conditions. The compressive strength indicated above
pertains to compressive strength tests on “work test cubes 15 x 15 x 15 cm, after normal
curing for 28 days. The strength of preliminary test cubes shall be as per IS : 456.
The type of concrete for any particular situation of work shall be as per drawings.
Any construction in the coastal areas may be considered as exposed to “severe”
environmental condition. In assessing the level of severity, it shall be prudent to adopt a
realistic attitude and be even some what conservative in respect of the extent of coastal zone
for the ultimate durability of the structures.
Thus, besides using. Portland Slag Cement, the specific requirement on “durability aspects”,
as per Indian Standard IS 456, in respect of the following parameters, must be met :-
76
Minimum Cement Content
Maximum Water / Cement ratio
Cover to Steel Reinforcement.
All these requirements are related to the various ‘environmental exposure conditions. The
standard IS 456 classifies the environment into 5 levels of severity, that is mild, moderate,
severe, very severe, and extreme.
The parameters relating to minimum cement content and maximum water / cement
ratio, as per IS 456, are summarized below along with the minimum grade of concrete
:-
Exposure Environment
Exposure Classifi- cation
Plain Concrete Reinforced Concrete
Min. (*) Cement content) kg/m
3
Max. water cement ratio
Mini. (*) Grade of concrete
Min.(*) Cement content) kg/m
3
Max. water cement ratio
Min. Grade of concrete
Coastal concrete sheltered from saturated salt air.
Moderate 240 0.60 M15 300 0.50 M25
Concrete exposed to coastal environment
Severe 250 0.50 M20 320 0.45 M30
Concrete exposed to sea water spray / or in contact with aggressive soils / ground water
Very Severe
260 0.45 M20 340 0.45 M35
Arrangement for slump cone test shall be kept at site to arrive at workability whenever
theEngineer-in-charge wants to check at site. Arrangement for compacting factor test shall
also be made to Tests for determination of strength of concrete.
ii. Strength of Concrete
As will be apparent from the Bill of quantities, the strength of concrete specified is the criteria and the
contractor shall make every effort to obtain the strength by good quality. Control. In case of concrete,
which does not obtain the specified strength at 28 days, such work shall be demolished and
reconstructed to obtain the requisite strengths, as directed by the Engineer-in-charge. It has also to
be ensured that the concrete conforms to the durability requirements viz. all requisite parameters
concerning minimum cement content, maximum free water cement ratio and the specified cover to
steel as well as good workmanship to obtain full compaction of concrete with non honey-combing in
the finished concrete etc. have to be meticulously implemented on the job including fully efficient
curing of concrete surfaces. To determine whether concrete in any particular part of the work is of
the requisite strength or not, test cubes (works test cubes) shall be made from samples collected
from the concrete being poured for the particular part and determined as per acceptance criteria
detailed hereinafter. The salient features for the collection of samples is as indicated below.
Testing of Concrete Cubes for determining Compression strength:
1. Quality
77
As specified
2. Compression strength
Shall be as specified for the particular type of concrete.
3. Criteria for acceptance of work
Part or element pf concrete work shall be deemed to be acceptable, provided the three cubes tested for 28 days strength conform to the following as per IS 456.
iii. Acceptance criteria of concrete cubes. (As per IS 456)
The Concrete shall be deemed to comply with the strength requirements when both the following conditions are met.
(a) The mean strength – determined from any group of 4 non-over lapping consecutive test:
(b) Any individual test result complies with the appropriate limits in column 3 of the following Table-A
Table A. Characteristic Compressive Strength Compliance Requirement
Specified Mean of the Group of Individual Test Grade 4 Non-Over lapping Results in N/mm
2
Consecutive Test Results In N /mm
2
1 2 3
M15 ≥ fck + 0.825 X established Standard deviation (rounded Off to nearest 0.5 N / mm
2) ≥ fck –3 N /mm
2
OR
fck + 3 N /mm2
which ever is greater M 20 ≥ fck + 0.825 X established standard deviation (rounded off to nearest 0.5 N /mm
2 ≥ fck – 4 N / mm
2
OR fck + 4 N / mm2
Whichever is greater fck = 28 days characteristic compressive strength
In the absence of established value of standard deviation, the following values of standard
deviation shall be assumed, and attempt should be made to obtain results of 30 samples as
early as possible to establish the value of standards deviation of the specified grade of concrete.
Assumed Standard Deviation Grade of Concrete Assumed Standard Deviation (N /mm
2)
M10 & M15 3.5 M20 & M25 4.0 M30, M35 & Above 5.0
The above values correspond to the site control having proper storage of cement’ weigh
batching of all materials; controlled addition of water regular checking of all materials’ aggregate
grading and moisture content; and periodical checking of workability and strength. Where there
is deviation from the table, the values give above shall be increased by 1 N /mm2.
78
Concrete shall be liable to be rejected if it is porous of honey combed, its placement has been
interrupted without providing a proper construction joint, the reinforcement has been displaced
beyond the tolerance specified or the construction tolerances have not been met. The concrete
shall be accepted only after the contractor carries out suitable remedial measures to the full
satisfaction of the Engineer-in-charge.
In case of doubt regarding the grade of concrete used, either due to poor workmanship or based
on results of cube strength tests, core tests shall be carried out. The points from which cores are
to be taken and the number of cores required shall be at the discretion of the Engineer-in-charge
and shall be representative of the whole of concrete concerned. In no case, however, shall fewer
than three cores be tested in accordance with IS – 516. Concrete in the member represented by
a core test shall be considered acceptable if the average equivalent cube strength of the core is
equal to at least 85% of the cube strength of the grade of concrete specified for the
corresponding age and no individual core has a strength less than 75%.
1.3.8 Quantum of Cubes and testing as per IS 456.
The minimum frequency of sampling of concrete of each grade shall be in accordance with
the following.
Quantity of Concrete No. of samples
In the work (m3)
1 - 5 1
6 - 15 2
16 - 30 3
31 - 50 4
51 and above 4 + one additional sample for
each additional 50 m3 or part there of.
NOTE: At least one sample shall be taken from each shift. 3 test specimens shall be made from
each sample for testing at 28 days. Additional 3 specimen cubes be cast to determine the strength of
concrete at 7 days.
The direction of the Engineer-in-charge in this regard shall be final and binding.
Batching and making of concrete:
All batching of aggregates and cement shall be by weight. All the necessary equipment such as
weighing equipment, devices for determination of moisture and bulk in sand, slump cone etc. shall
be provided by the contractor. Concrete shall be machine mixed in appropriate mechanical concrete
mixtures until there is a uniform distribution of materials and uniform colour and consistence is
achieved and under no circumstances for less than two and half minutes.
79
A wooden board approximately 30 cms. X 40 cms. Shall be put up at the concrete mixture on which
shall have been legibly written in English and the local language, the quality of concrete that is being
mixed, the proportions and other relevant data.
1.3.9 Cubes:
The size of cubes to be prepared and tested shall be 15 X 15 X 15 cm (6” x 6” x 6”)
Cubes each are intended for testing at 7 and 28 days respectively and determining the strength.
Cubes tested at 7 days should give a strength of not less than 70% of the corresponding strength of
structural members and also for works at various levels. It shall also be collected whenever the usual
quality for a particular strength is suspect. The acceptance criteria of concrete cubes as given above
and in IS: 456 is to be followed. The test results of the sample shall be the average of the strength of
3 specimens. The individual variation shall not be more than ± 15% of the average. If more, the test
results of the sample are invalid.
1.3.10 Preparation and Testing of Cubes:
Casting of cubes, preparation of moulds for the same, processing and curing the cubes and testing
the same shall be as per detailed instruction laid down in the relevant Indian Standard as amended
up to date.
1.3.11 Equipment modules testing etc.
It is entire responsibility of the contractor to prepare and get the cubes tested and provide for all
materials, labour, modules, equipment, faculty and charges for testing etc. The contractor’s rate for
concrete work shall be deemed to include for these and no extra payment whatsoever is admissible
on this account.
1.3.12 Slump:
The slump cone tests shall be required to be performed to establish workability and the same shall
be carried out free of cost. Suitable Plasticiser / Superplasticiser may need to be used, as directed
by the Engineer-in-charge, in M-20 M-30 & grade RCC to obtain therequisite workability of concrete
at the specified water cement ratio.
1.3.13 Form Work:
Form work shall be properly designed and constructed such that it is rigid enough to remain free
from bulging, sagging or replacement during placing of concrete. It should also be so constructed as
to facilitate removal of the same without damage to concrete. The formwork shall be adequately
watertight to prevent any loss of liquid and grout. All formwork shall be accurately erected in regard
to size, levels etc. In case of timber form work, the surface of forms in contact with concrete surface
shall be wrought. The joints between boards shall be close fitting and very thin for the concrete
surfaces designed to have exposed finish and not intended to be plastered. Surface of forms coming
in contact with concrete shall be treated with approved emulsions or mineral oil. It shall be ensured
that these emulsions do not stain or discolour the natural colour of concrete.
All form work shall be removed as per latest IS 456. Form work shall be removed without shock or
vibration. Edges of beams and columns if required to have chamfers shall be obtained by suitably
80
fixing triangular edge beads 20mm x 20mm to the forms. (No extra is admissible to the contractor on
account of these incidental and minor works for sizes up to and including 20mm x 20mm). Likewise
where drip notches are necessary they should be formed by suitably shaped fillets nailed in forms.
Form work for all beams and other horizontal construction members shall be built to an upward
camber of 1/300” of the span (in the center) to nullify the effects of optical
illusion. The camber shall be in addition to such camber as may be required and shown in the Static
Calculations.
The tolerance on the shapes, lines and dimensions shown in the drawings shall be within the
limits given below:
(i) Deviation from specified dimensions of cross-section of columns and beams……………………………..+ 12mm - 6 (ii) Deviation from dimensions of footings
1. Dimensions in plan…………………………+ 50mm - 12
2. Eccentricity………………………………….0.02 times the width of the Of deviation but not more than 50mm.
3. Thickness…………………………………...± 0.05 times the specified Thickness.
(iii) Plumb, specified Batter, the lines & surface of Columns walls etc…………………………….± 12 mm (in 3m of height) ± 18 mm (in 6m of height) & ± 30 mm (in 12m of height)
After the forms have been erected to line and grade, the same shall be meticulously inspected
as to their adequacy. If the forms are not tight, there will be loss of mortar, which shall result in
honey-combing of concrete or a loss of water which shall cause sand streaking. If the inspection
reveals that the forms are not braced sufficiently to stay in alignment during concrete placement,
concreting operation shall not be commenced till the Contractor sets right the deficiencies and
the forms re-inspected and found O.K. it shall also be checked during inspection that the
formwork as erected conforms to the specified line, grade, alignment to the specified tolerance
limits. Fully adequate rigidity of forms is of paramount importance since the tolerance limits
specified are for the finished concrete and not for the forms. Consolidation of concrete by the
vibrator requires that the forms be tight and strong. Stability is a very important consideration in
the form work and the Contractor shall be made to understand that the common deficiencies
resulting in failure of formwork.
(i) Inadequate cross bracing: (ii) Inadequate horizontal bracing: (iii) failure to regulate the rate of
placement of concrete in the forms and (iv) abnormal form displacements during & after concrete
placement due to inadequate provision for lateral pressures.
The contractor should ensure that ready access is provided for proper placement of concrete,
vibration of concrete, and for inspection of these operations.
1.3.14 Horizontal Construction Joints :
81
A very common blemish on formed concrete surfaces in the off “set” often found at horizontal
construction joints where forms have given way (viz yielded) a fraction of couple of centimeters
at the bottom of the new lift. These off –sets should be prevented by so setting the forms as to fit
snugly & tight against the top of concrete in the previous lift and then securing the forms so as
to remain in tight contact during the concrete placement operation. The anchoring shall be done
by using an ample number of ties and bolts above and within a few centimeters of the
construction joint. The ties in the top of previous lift cannot be relied on to prevent a slight
spreading of the forms at the joint. Forms shall overlap the hardened concrete in the lift
previously placed by not more than about 50 mm, though 25 mm lap is considered satisfactory.
The Contractor should take utmost care to ensure that the construction joints are smooth, free
from sharp deviations, projections or edges.
1.3.15 Spalling from the face of concrete :
Occasionally, spalling may occur from the face of concrete when forms are removed. This is
often caused by rough spots on the forms where mortar adheres strongly enough to overcome
the tensile strength of green concrete. Such areas on the forms must be cleaned, polished and
the covered with form oil by the contractor. Wire brushing of timber forms shall be done very
carefully to remove the set-mortar.
1.3.16 Filling of Bolt Holes
(she – Bolts ) or Holes of ties / Rods. The holes left in the concrete surfaces by the She – bolts
or rods etc. shall be duly reamed, cleared, cleaned and filled with – “dry pack mortar” by the
Contractor within a reasonable period of the removal of formwork. Such filling shall be made
flush with the concrete surface. No holes shall be left without the dry-pack mortar filling.
1.3.17 Inspection of Forms :
The Contractor shall inform the Engineer-in-charge well in time (well before commencement of
placement of concrete in the forms) to enable him or his representative to inspect the formwork
as to its adequacy, suitability, alignment, strength and overall fitness. However, such inspection
shall not relieve/ absolve the Contractor of his SOLE RESPONSIBILITY for the proper formwork,
and safety of men, materials, equipment and the consequent results / consequences.
1.3.18 Transporting and Pouring of Concrete :
No mixing of concrete shall be started unless the situation where they are to be poured are
prepared and kept ready. Concrete shall be poured immediately on preparation. Transporting of
concrete shall be done as speedily as possible and also in a manner to prevent segregation of
aggregates. No re-tempered concrete shall be allowed to be used on the works. No concrete
shall be allowed to fall from a height more than 1.2o Mt. Where the concrete is to be placed at
more depth it should be done through chute as directed by Engineer-in-charge.
Lift of concreting shall normally be not greater than 2.00 m in height.
Before fresh concrete is placed against an already cast and hardened section, such surfaces
shall be roughened, swept clean, moistened with water and treated with cement slurry. Fresh
concrete shall then be poured as required. Under no circumstances, concrete mixed for more
82
than 20 minutes shall be used where initial setting has commenced. Dewatering of excavations
for concreting where necessary shall be carried out by the contractor as directed and the rates
quoted by the contractor are deemed to be inclusive of such dewatering. No concreting shall be
done in adverse weather condition without proper precautions or approval from Engineer-in-
charge. No hand-mixing of concrete shall be allowed. In an exceptional / unavoidable
circumstance, it shall be allowed under the specific approval of Engineer-in-charge and that too
for a small or restricted quantity only , and in such a situation, 10% more cement shall be used
than that used when concrete ingredients are machine mixed.
1.3.19 Consolidation and processing of Concrete :
Concrete for all works shall be compacted by means of suitable vibrating equipment. Spare
vibrators needles which are in complete working condition shall always be kept ready at sites to
be put into commission incase of failure of the vibrators or needles under use. The vibrators shall
be operated by skilled personnel, thoroughly instructed as regards the mode, frequency, duration
etc. regarding vibration.
1.3.20 Finish to concrete surfaces :
Finish to concrete surfaces at various situations shall be as per directions of engineer-in-charge.
Where, form finish is specified, the final surface shall be smooth and even and no-undulations,
ridges, spots etc. shall be permitted. They shall be laid to pattern as directed. In case surfaces
intended and directed for form finish, exhibit any of the defects above mentioned, the surfaces
shall be rubbed with carborundum and finished as directed at the risk and cost of the contractor.
The decision as to the acceptability or otherwise of a surface will be notified by engineer-in-
charge and the contractor will implement the instructions accordingly. The honey-combed
concrete shall be meticulously rectified to the full satisfaction of the engineer-in-charge.
1.3.21 Concrete Cover for Reinforcement :
Where not specifically indicated in the drawings, concrete cover for reinforcement shall be as per
the latest Indian Standards and as per directions at site from time to time. Proper concrete cover
blocks to suite various covers as required shall be provided in adequate numbers sufficiently
ahead of the work.
In respect of the nominal cover to all steel reinforcements including links., it should not be less
than the following to meet the durability requirement ( as per IS 456:2000) :-
Exposure Environment Exposure classification Nominal concrete cover in mm not less than
Concrete surfaces sheltered from saturated air in coastal areas
Moderate 30
Concrete exposed to coastal environment
Severe 45
Concrete exposed to sea water spray / or in contact with
Very Severe 50
83
aggressive soils / water.
The actual cover should not deviate from the required nominal cover by +10mm and -
0mm.
1.3.22 Construction Joints :
Construction joints in concrete work shall be provided as far as possible only at predetermined
places in consultation with Engineer- in-charge. Joints shall be provided as specified in latest
Indian standards or as directed by Engineer-in-charge.
1.3.23 Curing :
It is very important that all cement concrete work shall be cured properly. All concrete work shall
be kept continuously in a damp or wet condition by pouring or by covering with a layer of moist
sack, canvas, hession or similar material for a minimum period of 14 days from the date of
concreting as per IS 456, prolonged curing beyond even 14 days shall be desirable (viz keeping
the concrete continuously wet). Since the Water –cement ratio of concrete shall be low (0.45 for
RCC M30 grade concrete & 0.5 for M20 grade concrete as per IS 456:2000 Table 5), it is all the
more important to ensure prevent of moisture loss from the concrete through fool-proof and
prolonged curing. Water used for curing shall also be free from any deleterious substances and
shall generally be fit for drinking. The work shall be adequately protected from drying, winds and
direct sun rays. The contractor should arrange at his own cost a temporary water supply line with
provision of suitable lines, pump etc. for curing and constructional purpose to reach all heights.
The contractor shall not be allowed to commence the work of concrete placement until he makes
all the curing arrangements to the full satisfaction of the engineer-in-charge (viz. water tanks,
pumps, delivery lines, spray nozzles etc. as well as the requisite crew earmarked specifically for
undertaking curing). Payment for the concrete placed shall be made only after its specified
curing has been done to the full satisfaction of the engineer-in-charge.
1.3.24 Membrane Curing :
Curring constitutes one of the most vital requirement for the strength & durability of concrete.
Any slackness in curing or doing inadequate curring will adversely affect the durability of
concrete. Fool-proof curring by the contractor is, therefore, a “must”. In case the Engineer-in-
charse finds that the moist curring(viz water curring) by the contractor is not being efficiently
done (particularly on the under sides of slabs & beams etc.), he shall direct him to resort to the
curring by membrane forming “curring compound”. The curing compound should be white
pigmented of approved quality conforming to ASTM-C-309-81 Type-2. This should meet the
requirement of water retention test as per ASTM designation C-158-80. Loss of water in this test
for acceptable curing compound should not be more than 0.55kg/m2 of exposed surface in 72
hours . The curing compound should also meet the day light reflectance test . Curing compound
is to be sprayed with a nozzle . It should be applied as soon as the bleeding water disappears
,leaving a dull appearance. This is when there is no free moisture on the surface. If applied too
early, the free moisture will prevent the compound from forming a moisture-proof film. If applied
too late, some of the moisture will have already been lost that should have been retained for the
hydration process. Proper time range will vary from about 30minutes to 2 hours after placement
84
of concrete depending upon humidity and temperature.Uniform coverage of curing compound on
the concrete surface is very important and, accordingly, it should be mechanically sprayed with a
nozzle. The dosage of curing compound sprayed on the concrete surface should normally be not
more than 1litre for about 3.75m2
(sq m) concrete surface area. The contractor shall be allowed
to use the curing compound only upon his furnishing its test reports in respect of the water
retention tests & day light reflectance test. The Engineer may also get the curing compound
tested in a reputed laboratory for its suitability. Payment for the concrete placed shall be made
only after the completion of proper application of membrane-forming curing compound.
1.3.25 Opening and inserts :
All opening and inserts which are designated in due time or as required for services, will be
exactly provided by the contractor including supply of materials. The contractor should also fix
the anchors or such items which maybe supplied by the proprietor in exact position and in
perfect lines and levels, inserts apply to such items as timber, dowels, bolts, loop, brackets,
suspension, irons, hooks , screws, plates, pipe, pipe of various types and diameter etc.
Openings in concrete or masonry must be provided in exact location, to correct shape, size and
depth or slightly bigger, as shown in drawings or as instructed. It must be clearly understood that
provisions of inserts and openings as contemplated in this contract are to be carried out with
“utmost precision” and any deviation of the same from that as shown in drawing or instructed
have to be rectified by the contractor at his own cost and responsibility. The contractor should
make provision of openings to deep beams and their members at bottom or at lower level as
necessary for cleaning purpose prior to concreting.
1.3.26 Steel reinforcement:
All reinforcement for concrete work shall be corrosion resistance steel (CRS 42) and conforming
strictly to the latest Indian Standards. They shall be of tested quality. Reinforcement shall be
fabricated to shapes and dimensions shown on the drawing and shall be placed where indicated
on the drawings or required to carry out the intent of drawing and specifications or as directed by
Engineer in charge. Before placing, reinforcement shall be thoroughly cleaned of loose rust,
coating etc. which would result in reducing or destroying the bond. Oiling the bars to clean them
is strictly prohibited. Bending, straightening, cutting etc. operations shall be carried out in a
manner not injurious to the material. Assembly of reinforcement, placing of reinforcement,
Tolerance for Cover, welding of joints etc. shall generally conform to the Indian Standard
specifications. IS 456.
1.3.27 Placing of Reinforcement.
Before the reinforcement is placed, the surfaces of bars and the surfaces of any metal bar
supports shall be cleaned of all rust, loose mill scale, dirt grease and any other objectionable
matter.
(ii) All reinforcement bars shall be accurately placed in exact position shown in drawings
and shall be securely held in position during placement of concrete by annealed
binding wire, and by using stays, blocks, metal chairs, spacers or other approved
devices at sufficiently close intervals (less than 1 m interval) so that the bars do not
sag.
85
(iii) Wire for binding reinforcement shall be soft and of annealed mild steel of 16 SWG
and shall conform to IS 280
(iv) The bars shall not be allowed to sag between the supports and also not allowed to
be displaced during concrete placement. Also, the contractor has to ensure that no
disturbance is caused to the reinforcement bars already placed in concrete.
(v) All devices used for positioning of bars shall be of non-corrodible material. Metal
supports shall not extend to the surface of concrete except where shown in the
drawings. Pieces of broken stone or brick or wooden block shall not be used.
(vi) The contractor must ensure that the CONCRETE COVER AS SPECIFIED IS
METICULOUSLY PROVIDED.
All bars protruding from concrete and to which other bars are to be spliced,
and which are likely to be exposed for a long period. SHALL BE PROTECTED BYA
THICK COAT OF NEAT CEMENT GROUT.
(vii) Reinforcing bars of 25 mm in diameter and less may be either lapped or but welded
whichever is considered more practical by the Engineer.
(viii) Reinforcing bars of 28 mm in diameter and larger may be connected by butt welding
provided that the lapped devices will be permitted if found to be more practical than
butt welding and furthermore that the lapping does not encroach on cover limitation
or hinder concrete or reinforcement placement. Electric are welding shall, preferably,
be used.
(ix) Tolerance for Cover. Unless specified otherwise, actual concrete cover should not
deviate from the required /specified nominal cover by + 10 mm.
All reinforcement shall be bent cold. Unless otherwise directed, reinforcement
shall not be spliced at points of maximum stresses. Engineer in charge shall be
informed of the same before such splicing is taken up. Laps and splicing shall
conform to the latest Indian Standards.
Reinforcement shall be accurately tied at all intersections and laps with 16
SWG soft drawn binding wire, such that the reinforcement will give a rigid structure.
Binding wire will not be measured or accounted for separately. The contractor’s rate
for reinforcement will be measured and paid for according to bending lists without
allowances for cutting, wastage, binding wire etc. authorised laps, hooks, chairs,
spacers etc. shall however be accounted for in case, the contractor or engineer
desires to resort to welding or swivel nuts, there shall however be made as if the laps
have been provided and no extra claim whatsoever shall be admissible on this
account
Reinforcement shall be assembled in place with proper concrete cover blocks
to suite various covers as required.
1.3.28 Measurements:
86
All measurements shall be as given below or where not given as per latest IS : 1200.
Concrete will be compensated for according to its actual volume.
The computation will be based upon the construction plans only and no site
measurements shall be taken for this purpose. All incidental work stated in the Technical
specifications and also dewatering at the time of concreting are deemed to have been
included for in the unit prices quoted by the contractor. Opening with an area larger than
0.1sqm shall be deducted from concrete quantity and where openings are smaller, these
shall not be deducted.
Form work will be measured and paid for according to their contact area. The unit
prices of the forms incorporates all scaffolds, nails, clamps, and all incidental work. Openings
with an area larger than 2m2 shall be deducted from work quantities and the form work
required for sides of such openings shall be paid for. Openings of less than 1 m2 area shall
not be deducted from work quantities and no allowance for from work for sides of such
openings shall be made.
Reinforcement steel will be compensated for according to the approved bending lists
without allowances for cutting, rolling margin and waste. Binding wire, cover blocks etc. will
not be measured or paid for separately. The contractor shall prepare the Bar Bending
Schedules and incorporate the same on the reinforcement drawings as directed and submit it
to engineer in charge for approval.
All openings and inserts which are indicated in drawings and as per requirements for
services shall be provided at exact positions and no payments shall be made for providing or
fixing these. Only such openings or inserts which have not been indicated earlier or such
additional openings / inserts required specially due to changes made by engineer in charge
shall be paid for. Excepting for the above, all other measurements shall be as per
stipulations under the latest Indian Standards Mode of Measurements for Building works.
Information on cement concrete
Sl.
No.
Information Item No.1 of BOQ
Item No.4 of BOQ
Item No.5 of BOQ
Item No.6 of BOQ
Item No.22 of BOQ
1. Type of Mix
(Design mix or nominal mix)
Design Mix Design mix
Design mix Design mix
Nominal mix
2. Grade designation M30 M15 M20 M30 M20
3. Type of cement Slag cement (I.S : 455 )
Slag cement (I.S : 455)
Slag cement (I.S : 455 )
Slag cement (I.S : 455 )
Slag cement (I.S : 455 )
87
4. Maximum nominal size of aggregates (mm)
20 20 20 20 12
5. Minimum cement content(kg) / m
3 of cement
(for design mix content)
320 - 250 320 -
6. Maximum water cement ratio ( for design mix concrete)
0.45 - 0.50 0.45 -
7. Maximum quantity of water for 50 Kg. Of cement (Nominal mix)
- - 32 - 32
8. Workability
(slump in mm)
100 to 150 (water-free unlined holes) 150 to 200 (for concreting by tremie)
75 to 100 50-75 25-75 -
9. Exposure condition Severe Severe Severe Severe Severe
1.4 Under reamed Piles :
Latest I.S. specifications to be followed for execution of the items are (1) I.S. 2911 (Part – III
& part IV) . revised, (2) I.S. 455 (3) I.S.-1489, (4) I.S. -456, (5) I.S. 383, (6) I.S. 1786 & (7)
I.S. -2720.
1.4.1 General: At the time of filling his tender, the contractor shall visit and inspect existing site to
examine the nature of ground, type of soil levels etc. No claim or allowance what so ever
shall be admissible on this account or on account of omissions in the levels or the description
of the ground turning out to be different from what was shown on the drawings.
1.4.2 Setting out: The contractor shall locate and layout all the piles at his own cost or as per
drawings and approval of the Engineer in charge. If at any time during the progress of the
work any error shall appear or arise in the position, levels, divergence & alignment of any
part of the work, the contractor on being required to do so by the engineer in charge shall at
his own cost rectify such errors to the satisfaction of the engineer in charge unless such error
is based on incomplete data supplied to the contractor. The contractor shall carefully protect
all bench marks. Pillars, sight rails, pegs and other things used tin setting out.
1.4.3 Material:
i. Concrete: The concrete for piling work shall be controlled as per specifications for the
cement concrete and of grade specified on the drawings.
88
ii. Reinforcement: The reinforcement for piling work shall be as per specifications for
the cement concrete and of grade specified on the drawings.
iii. Bentonite : Bentonite as brought to the site and prior to mixing shall be in accordance
with the following specifications :
(a) a certificate is to be obtained by the contractor from manufacture of the bentonite
powder stating the manufacturer’s consignment and the properties of consignment as
determined by the manufacturer. The certificate shall be made available to the engineer in
charge on request.
(b) The bentonite powder shall be mixed thoroughly with clean fresh water. The
percentage of bentonite used to make the suspension shall be such as to maintain the
stability of the excavation trench / bore.
(c ) Control tests are to be carried out on the bentonite suspension using suitable
apparatus to determine.
A. The density
B. The viscosity
C. The shear strength
D. The PH value of the freshly mixed bentonite
These tests shall be carried out initially until consistent working pattern has been
established.
1. When the tests show consistent behaviour some or all tests maybe discontinued at
the discretion of the engineer in charge.
2. Prior to placing concrete the contractor shall ensure that contaminated bentonite
suspension has not accumulated in the bottom of the trench to impair the free flow of
concrete. The contractor shall state the method of testing checking this item along
with the tender and obtain approval of the engineer in charge prior to
commencement of the work.
3. The temperature of the water used in mixing bentonite suspension and of the
suspension and of the suspension supplied to the trench excavation shall not be less
than 5 deg. Centigrade.
4. During construction the level of the bentonite suspension in the trench shall be
maintained within the depth of the guide walls and at a level not less than 1.0 m.
above the level of external standing water if any.
5. In the event of the sudden loss of bentonite suspension, the trench shall be backfilled
without delay and the instruction of the engineer-in-charge shall be obtained on
further course of action.
6. Where saline or chemically contaminated water is encountered, special measures
shall be taken as desired by the Engineer-in-charge.
89
7. All reasonable steps shall be taken to prevent the spillage of bentonite suspension
on the site away from the immediate vicinity of the wall. Discarded bentonite and
suspension, which has been pumped from the trench, shall be immediately removed
from the site.
1.4.4 Piling System.
i. These specifications cover only bored cast-in-situ under reamed piles.
ii. Termination levels of piles shall be as shown on the drawings or as decided by the
engineer-in-charge during the progress of construction keeping in view the initial test
result.
iii. In order to satisfy himself about the adequacy of the proposed length and anticipated
safe load carrying capacity of the piles the contractor shall examine the soil data
available with the engineer-in-charge.
iv. A pile capacity assumed by the contractor in his quotation whether it is the one that is
given in the drawing or is the one computed by him will be guaranteed by him.
v. The assumed safe carrying capacity of the piles shall confirm to relevant I.S.
specification for working piles.
vi. If the interpretation of load test indicates that the safe bearing capacity of the piles is less
than the assumed and guaranteed by the contractor additional piles will be provided by
the contractor at his own cost.
vii. The contractor shall guarantee safe bearing capacity of all piles.
1.4.5 Under Reamed Piles:
i. Under reamed piles shall generally be in accordance with the relevant provisions of IS
2911.
ii. The diameter of the under reamed bulb shall be 2.5 times the diameter of the pile stem.
iii. Unless shown the center to center spacing to the piles shall not be less than twice the
diameter of the bulb.
iv. The piles shall be designed to carry compressive as well as up lift forces due to ground water
head.
v. The theoretical calculation of the load carry capacity and the uplift or anchorage capacity of
the piles based on the soil conditions shall be submitted to the Engineer-in-charge.
vi. Effect of grouping the piles shall be considered in the design calculations.
vii. The Engineer-in-charge reserves the full right of demanding modification or complete
revision of design calculations submitted by the contractor.
viii. The Engineer-in-charge reserves the full right to adjust the bearing capacity of the piles
depending on the performance of test loading.
1.4.6 Construction of Techniques:
90
i. Safety of existing structure: The contractor shall take every precaution to avoid damage to
the existing structures in the vicinity as a result of construction of pile foundations. All claims
arising out of damage to the existing structure due to the construction of piles shall be done
by contractor.
ii. Bore holes: Boreholes shall be made by any standard method. The contractor will submit
along with the tender a description of the equipment and of the method of the boring he
proposes to use for checking and approval by the Engineer-in-charge.
iii. If high water table is encountered causing possible instability of the bores, boring and under
reaming shall be carried out using a suitable fluid such as betonies slurry. In addition normal
spiral or modified augers having arrangements to avoid back suction shall be used.
1.4.7. Placing of Concrete:
i. The boreholes shall be cleaned of all soil cuttings and sediments before placing concrete.
ii. Concrete shall be placed through a funnel so as to fill the entire volume of borehole without
formation of voids. Mechanical vibrators shall not be used.
iii. Under water concreting shall be carried out by displacement method and a termite pipe of
diameter of not less than 15 cm having suitable protective arrangement at the lower end may
be used.
iv. The minimum pile stem diameter for under water concreting shall be 25 cm.
v. The volume of concrete placed shall be observed in the case of first few lines. The average
figure thus obtained shall be used to check possible undue variations in the volume in the
subsequent piles. In case of significant variations, the contractor shall investigate the
possible causes to the complete satisfaction of the Engineer-in-charge whose decision in this
regard will be final and binding on the contractor.
vi. When using the bentonite slurry technique utmost care shall be taken to avoid mixing of
slurry with concrete. In any case the method of concreting shall be subject to the approval of
the Engineer-in-charge.
1.4.8 Finish Pile Heads:
i. The top of the piles shall be brought up above the specified cut off level by at least 30cm.
To permit all the laitance and weak concrete to be removed and to ensure that the pile
can be properly keyed into the pile cap by a minimum of 5 cm. This additional concrete
shall not however be paid extra.
ii. The reinforcement in the pile shall be exposed for a length of at least 50 times the
diameter of the Tord steel used or as specified in the drawings beyond the theoretical
point of cut off of the pile to permit to be adequately bended into the pile cap.
1.4.9 Control of Alignment and Tolerances:
i. Errors in setting out shall not exceed 12mm, measured horizontally from the center of the
piles.
91
ii. If the piles are not found to be in the exact position or out of plumb by more than 1% or if
they are found to be skew or defective in any other manner, they shall be rejected and
the decision of the Engineer-in-charge will be final and binding in this regard.
1.4.10 Defective Piles:
i. The Engineer-in-charge will have full authority to reject any pile at the time of
chipping of excess concrete to bring the level of the pile head to the cut off level, in
case it is found that,
a. Diameter of the pile at the cut off level is smaller than the diameter specified.
b. Location of the pile is outside the limitations prescribed in these specifications.
c. Concrete at the cut off level is of poor quality or is of less strength than had been
specified.
d. Diameter of bars, spacing, shapes or lengths of piles reinforcement do not conform
to details given in the drawings or the reinforcement cage is disfigured, distorted,
displaced or other wise damaged in any manner.
e. Anchorage length of the reinforcement bars at the cut of level is inadequate.
ii. The contractor shall make good the piles, pull out the piles or provide new piles in
place of the rejected piles at his own cost and without any additional cost to the client
even if the pile had been accepted at the time of boring. The final acceptance of all
piles shall be made after the pile head has been brought to the cut off level, all
reinforcement required to be embodied in pile cap exposed and after all
measurement have been completed vis a vis the layout of the piles.
1.4.11 Load Tests:
i. Testing Procedure: The contractor, along with his tender, shall submit a description
of his procedure for carrying out load tests. The engineer-in-charge reserves the full
right to demand a modification of the test procedure proposed by the contractor at no
extra cost.
ii. Number of Initial test Piles: To determine the safe load of a pile or group of piles the
cyclone shelter as per IS 2911 (Part IV). No payment shall be made for initial test
piles and it’s testing. The contractor should include in his rate his expenditure
towards initial load test piles and initial load testing.
iii. Routine Load test: Routine test shall be conducted on 2% of the total number of
piles, for which the contractor will be paid as per relevant items in the BOQ.
iv. Equipment: The contractor shall provide all necessary equipment for applying specified
vertical load on the top of the test pile and for measuring the settlement of the pile.
v. Loading device: the device for giving the vertical load shall be of suitable design to
avoid impact, lateral forces, tilting etc. and shall have an arrangement for gradual
application of load and for readings at close intervals. The load shall be in the form of
suitable Kent ledge.
92
vi. Apparatus for measuring settlement: The apparatus for measuring settlement shall
consist of a dial gauge permitting a reading of 0.02 mm accuracy. The dial gauges
shall be fixed to the datum bar whose ends rest upon non-movable supports. The
supports for datum bar with reference to which the settlement of the pile would be
measured shall be at least 5 d away, clear from piles, “d” being the diameter of the
piles.
vii. Loading procedure: the head of the pile shall be at the cut off level and shall be capped
in such a manner as to prepare a horizontal place – bearing surface. The maximum
test load shall be twice the anticipated working load on the pile Alternative loading and
un loading shall be carried out for 25, 50, 75, 100, 125, 150, 175, 200 percent of the
anticipated safe test load. Settlement and time shall be recorded in the beginning and
end of loading and also for at least 2 hours after completion of each loading and
unloading.
viii. Sustained loading: The maximum test load of twice the anticipated working load on the
pile shall be applied in increments of 25, 50, 75, 100, 125, 150, 175, and 200 per cent
of the anticipated working load. Settlement reading shall be taken to the accuracy of
0.02 mm before and after the application of each new load increment. Additional load
shall not be applied until the rate of settlement under the previous increments is less
than 0.02 mm per hour or 2 hours have elapsed which ever occurs first. When loading
has been completed, the full test load shall remain on the pile for 24 hours or for a
longer period if the necessity is there or if indicated by the rate of the settlement of the
pile and settlement reading shall be taken during and at the end of the period. During
the unloading of the pile, the rebound shall be measured when the load remaining on
the pile amount to 75, 50, 25 and 0% of the full test load with decrements of load
released at not less than half hour intervals and with measurements of the rebound
being released at not less than half hour intervals and with measurements of the
rebound being made immediately before and after each decrement. The final rebound
shall be recorded 24 hours after the entire test load has been removed.
ix. Reports: The contractor shall submit the report of the load test, which shall include the
following information.
a) A description of the soil condition at the location of each test pile.
b) A description of the pile and its boring record including boring time, rate,
types of soil strata encountered and the stability of the sides, density of the bentonies
used and any other relevant data.
c) A tabulation of the loads and settlement readings during the loading and
unloading of the pile.
d) Time load settlement curves.
e) Remarks concerning unusual occurrences if any during boring or loading of piles.
1.4.12 Basis of measurement:
93
i. The length of the pile shall be measured from the theoretical cur-off point of the pile
to its termination level.
ii. The length of the empty boring will be measured from the top of existing ground level
at the time of starting of the particular pile to top of the theoretical point if cut off of
the particular pile.
iii. The rate for the piles shall include the boring concreting with slump as per IS
specifications complete in all respects in respective of the construction technique
used unless otherwise specified in the schedule of quantities.
iv. The rate for load testing shall include the cost of all different operations involved like
arrangements of the equipment including all Kent ledge, or dial gauge as well as
preparation and furnishing of reports complete in all respect.
v. The payment for the routine test pile or group of piles shall be made to the contractor
only when the test is found to be satisfactory. For tests, which are found to be
unsatisfactory, or which are not completed due to any reason whatsoever, no
payment shall be made to the contractor.
1.4.13 Interpretation of test results:
i. All test results and piling records shall be submitted to the engineer-in-charge in
duplicate for his confirmation.
ii. Test results shall generally be interpreted is per relevant Indian Standard Code of
practice. The engineer-in-charge may refer the test results to the consultants for their
opinion and decision.
1.5 MASONRY
1.5.1 Materials:
i. Brick:
(a) All bricks shall be table moulded, burnt bricks of required class & quality. They shall be hard
sound and well burnt with sharp edges and of uniform sizes & shapes. Bricks shall be a
neither under burnt nor over burnt and shall be free from cracks, stone floats, or other such
defects.
(b) When immersed in water for 24 hours, a brick shall not absorb more water than 20% of its dry
weight. All bricks shall be identical / equal to samples submitted and approved by Engineer-
in-charge before the commencement of the work. Crushing strength of the class bricks shall
not be less than 75kg. / cm2. Metallic sound of brick is also a criteria for the above class and
quality.
ii. Sand
IS gradation of sand for masonry and plastering work should be as follows:
The sand shall be well graded so as to impart good workability and good finishing. The gradation
requirement of sand shall be as follows:
94
1. Sand for masonry work( As per IS 2116)
Sl.
No.
IS Sieve size Percentage of passing by weight
1. 4.785 mm 100
2. 2.36 mm 90-100
3. 1.18 mm 70-100
4. 600 microns 40-100
5. 300 microns 5-70
6. 150 microns 0-15
2. Sand for Plastering (As per IS 1542)
Sl.
No.
IS Sieve size Percentage of passing by weight
1. 10 mm 100
2. 4.75 mm 95-100
3. 2.36 mm 95-100
4. 1.18 mm 90-100
5. 600 microns 80-100
6. 300 microns 20-65
7. 150 microns 0-50
iii. Cement: As described under clause 1.3.2 of technical specification
iv. Additives :
Additives, like integral water proofing compounds, shall be of the approved type from
reputed manufacturers. These shall be used strictly in accordance with the
manufacture’s instructions/ specifications. The additives shall confirm to IS 9103.
1.5.2 Samples:
When demanded by engineer-in-charge, the contractor shall produce samples of materials /
carryout samples of work for Engineer-in-charge. All materials used as also works carried out
95
shall conform to the quality of approved samples Production of these samples shall be at
contractors cost.
1.5.3 Brick masonry:
Brick shall be soaked in clear water for at least six hours in a vat before use. The average
water absorption of brick after immersion in water shall not be more than 20 % by weight.
Bricks shall be laid in English bond unless specified otherwise. No half or quarter brick
shall be used except as closures. Bricks shall be accurately raised to plumb.
Brick work shall be raised uniform all round and no part shall be raised more than 1 meter
above another at any time. And the work shall be properly toothed and racked back.
In case of 12.5 cm thick brick walls, hoop iron reinforcement 25mm x 12 to 16 gauge or
wire netting reinforcement shall be provided in every fourth course. The reinforcement shall
be properly bedded in mortar, properly lagged etc. all as directed.
The contractor will have to build in holdfast and such other fittings in brick work without
extra cost.
Joints in brick work shall not be more than 10 mm thick. Brick work shall not be raised
more than 10 to 12 courses a day. The work shall be kept watered thrice a day for 10 days
and afterwards twice a day for 3 weeks. All joints shall be thoroughly flushed with mortar
at every course. Care shall be taken to see that bricks are properly bedded and all vertical
joints completely filled to the full depth. The joining of brick work shall be hauled out to a
depth not less than 10 mm as the work proceeds. The surface of brick work shall be
cleaned down and watered properly before the mortar sets.
Construction joints are to be provided at an interval of 30m in case of boundary wall or
where the length of brick wall is long.
The contractor shall also make or leave holes recesses as required and fill in the same at a
later date with lean concrete of m.5 as directed with no extra cost.
“FALG” bricks of proper size & quality as approved by engineer-in-charge can be used in
walls in place of clay bricks. Hollow concrete blocks of approved size, strength& quality
can also be allowed to be used in masonry as approved by engineer-in-charge at site in
place of clay bricks.
1.5.4 Measurements:
i. General
All the rates quoted by the contactor shall be for a fully finished item of work and shall include for
all material, labour, miscellaneous works like storage, loading / unloading, scaffolding, hoisting
gear etc. and also all taxes, duties, overhead, profits, etc.
ii. Masonry
Accounts on masonry shall be settled on the basis of cubic meters or square meters as indicated
in the bill of quantities. Quantities will be decided on the basis of pertinent plants. Openings and
96
recesses which exceeds 0.10 cum will be deducted from the quantities. Openings left initially on
specific instructions or as required shall be closed at a later date, if so instructed by Engineer-in-
charge, at no extra cost. Similarly, all openings, recesses, grooves etc, shall be provided at no
extra cost. All materials supplied by clients shall be fixed in masonry free of charge.
1.6 CEMENT PLASTERING (Internal & External):
The cement plaster shall be 8 mm, 12mm or 20mm or any thickness as specified in the item.
i. Scaffolding:
For all exposed brick work or tile work, double scaffolding having two sets of vertical supports
shall be provided. The supports shall be sound and strong, tied together with horizontal pieces
over which scaffolding planks shall be fixed. For all other brick work in buildings, single
scaffolding shall be permitted. In such cases the inner end of the horizontal scaffolding pole shall
rest in a hole provided only in the header course for the purpose. Only one header for each pole
shall be left out. Such holes for scaffolding shall, however, not be allowed in pillars / columns
less than one meter width or immediately near the skew portion of arches. The holes left in
masonry works for scaffolding purposes shall be filled with lean concrete and made good before
plastering.
ii. Preparation of surface:
The joints shall be raked out properly. Dust and loose mortar shall be brushed out. Efflorescence
if any shall be removed by brushing and scarping. The surface shall then the thoroughly washed
with water, cleaned and kept wet before plastering is commenced.
In case of concrete surface if a chemical retarder has been applied to the formwork, the surface
shall be roughened by wire brushing and all the resulting dust and loose particles cleaned off
and care shall be taken that none of the retarders is left on the surface.
iii. Application of Plaster:
Ceiling plaster shall be completed before commencement of wall plaster.
Plastering shall be started from the top and worked down towards the floor. All scaffolding pole
holes shall be properly filled in advance of plastering as the scaffolding is being taken down. To
ensure even thickness and true surface, plaster about 15 cm x 15 cm shall be first applied,
horizontally and vertically at not more than 2m. intervals over the entire surface to serve as
gauges. The surfaces of these gauged areas shall be truly on the plane of the finished plaster
surface. The mortar shall then be laid on the wall, between the gauges with trowel. The mortar
shall be applied in a uniform surface slightly more than the specified thickness. This shall be
beaten with thin strips of bamboo about 1 meter long to ensure thorough filling of the joints, and
then brought to a true surface, by working a wooden straight edge reaching across the gauges,
with small upward and side ways movements at a time. Primarily the surface shall be finished off
true with trowel or wooden float according as a smooth or a sandy granular texture is required.
Excessive trowel in or over working the float shall be avoided. During this process, a solution of
like putty shall be applied on the surface to make the later workable.
97
All corners, angles and junctions shall be truly vertical or horizontal as the case may be and shall
be carefully finished. Rounding or chamfering corners, junctions etc. where required shall be
done with out any extra payment. Such rounding or chamfering shall be carried out with proper
templates to the sizes required.
In suspending work at the end of the day, the plasters shall be left out clean to line both
horizontally and vertically, when recommencing the plastering, the edge of the old work shall be
scraped cleaned and wetted with lime putty before plaster is applied to the adjacent areas, to
enable the two to properly joint together. Plastering work shall be closed at the end of the day on
the body of wall and not nearer than 15 cm to any corners. Its shall not be closed on the body of
the features such as plasters bands and cornices nor at the corners. Horizontal joints in
plasterwork shall not also occur on the parapet tops and copings as these invariable lead to
leakage.
No portion of the surface shall be left out initially to be patched up later on.
Finish:
The plaster shall be finished to a true and plumb surface and to the proper degree of
smoothness as required. The works shall be tested frequently as the work proceeds with a
true straight edge not less than 2.5.m long and with plumb bobs. All horizontal lines and
surfaces shall be tested with a level and all jambs with a plumb bob as the work proceeds.
iv. Thickness:
The thickness of the plaster specified shall be measured exclusive of the thickness of the key
i.e. grooves or open joints in brickwork. The average thickness of plaster shall not be less
than the specified thickness. The minimum thickness of any portion of the surface shall not
be less than the specified thickness by more than 3mm. The average thickness should be
regulated at the time of plastering by keeping suitable thickness of the gauges. Extra
thickness required in dubbing behind rounding of corners at junctions of wall or in plastering
of masonry cornices etc. will be ignored.
Curing shall be started 24 hrs after finishing the plaster. The plaster shall be kept wet for a
period of 7 days. During this period it shall be suitably protected from all damages at the
contractor’s expense by such means as the engineer may approve. The dates on which
plastering is done shall be legibly marked on the various section plastered so that curing for
the specified period thereafter can be watched.
Any cracks which appear in the surface and all portions, which sounds hollow when tapped
or are found to be soft or other wise defective, shall be cut out in rectangular shape and re
done as directed by the Engineer-in-charge.
1.7 CEMENT PLASTER WITH A FLOATING COAT OF NEAT CEMENT:
The cement plaster shall be 8mm, 12mm or 20mm 16 mm thick, finished with a floating coat
of neat cement, as described in the item.
When the plaster has been brought to a true surface with the wooden straight edge, It shall
be uniformly treated over its entire area with a paste of neat cement and rubbed smooth, so
98
that the whole surface is covered with neat cement slurry 1.5mm thick while the plaster
surface is still fresh. Smooth finishing shall be completed with trowel immediately and in no
case later than half an hour adding water to the plaster mix.
2. TECHNICAL SPECIFICATION FOR SANITARY & PLUMBING WORKS
Not Required.
3. TECHNICAL SPECIFICATION FOR ELECTRICAL INSTALLATION WORK UNDER ICZMP-,ORISSA
3.1 General Requirements
The installations shall generally be carried out in conformity with the requirements of Indian
Electricity Act, 1910 as amended up to date and Indian Electricity Rules, 1956 framed there under,
the relevant regulations of the Electric Supply Authority concerned and also with the specifications
laid down in the Indian Standard IS:732/1963 "Code of Practice (Revised) for Electrical Wiring
Installations (System Voltage not exceeding 650V)". The work shall be executed as per National
Electrical Code and if any item is not covered there under or there is any doubt, the specification
approved by the Engineer-in-charge will be final and binding.
3.1.1 Ambient Conditions
All Electrical installations and equipments shall be suitable to work in following ambient
conditions.
Maximum Temperature : 50 degree Celsius
Relative Humidity : 100%
In the vicinity of : _________, Orissa.
System Conditions
The Electrical installations and equipments shall be suitable for operation in following system
conditions.
Supply voltage : 415 Volts +/-10%
Supply frequency : 50Hz +/-5%
Number of Phases : Three
3.1.1 Scope
3.1.2 Materials:-
All materials, fittings, appliances used in electrical installations shall confirm to Indian Standard
Specifications wherever these exist. A list of approved materials is attached in annexure-I. Materials
not included in the list as well as any particular make should be approved by the Consultant or
99
Engineer-in-charge before use. All required materials covered under this specification except
mentioned otherwise clearly, shall be supplied and installed by the contractor complete in all respect.
The materials and accessories required for completing the work will form part of the work although
they have not been specified separately.
Selection of materials and installation work shall be such as to simplify operation, inspection,
maintenance and testing. The work shall include all reasonable precautions and provisions for safety
of operation and maintenance personnel.
3.1.3 Standard:-
(a) Unless otherwise specified, all materials covered under this specification shall be
designed, manufactured, tested and installed in conformity with the latest Indian
Standard Specifications. In case such Indian Standard Specifications are not published
equivalent British Standard Specifications shall be followed. All equipments shall confirm
to latest Indian Electricity Rules, PWD and Local/State laws or byelaws as regards to
safety, earthing and other essential provisions specified therein.
(b) All equipments and materials selected shall also be supplied and installed taking into
consideration the Factories Act, Fire Regulations and Local laws or byelaws. All light
fittings and equipments selected shall be of well tied out design. All materials used in the
assembly of fittings and their accessories shall be of high quality and manufactured in
accordance with the best modern practice.
(c) All the materials supplied by the contractor according to the contract conditions will be
subject to inspection and approval by the Consultant or/and Engineer-in-charge or their
authorised representative from time to time. The contractor shall extend all required
facilities for such inspection free of cost. At the time of inspection, the inspecting officer
shall have full liberty to reject any such material, which does not confirm to specifications
or the requirements. No claim for any rejected materials shall be entertained by the
owner. The contractor shall remove all rejected materials from the site at his own cost.
(d) No surplus material procured by the contractor will be accepted by the owner.
(e) The contractor will be responsible to get electrical installations inspected by the Electrical
Inspector of the State Government and to obtain the statutory clearance for energisation.
The owner, on production of documentary evidences, will reimburse the necessary
inspection fees.
(f) The contractor should possess valid electrical contract licence and labour licence issued
by the appropriate statutory authority of the State Government during the execution of
the contract.
3.1.4 Inspection and Approval
The contractor shall put up samples of all major items for inspection and testing by the
Consultant and/or Engineer-in-charge for which the contractor shall furnish minimum 10 days clear
notice in advance to enable them to depute their Inspecting Officer. Similar procedure shall be
adopted for the approval of s
100
Samples of minor materials/ accessories to be used for the work.
3.2.0 GENERAL TECHNICAL SPECIFICATION OF MATERIALS
3.2.1 Switches & Plug Sockets:-
All switches, 5A plug sockets, power plug sockets, TV sockets and Telephone sockets shall be
flush mounting type with ISI mark of approved make. The switches and plug sockets shall confirm to
IS:3854/1988, IS:1293/1988, IS:6538/1971 & IS:4615/1968.
3.2.2 Fan Regulators & Dimmers:-
Electronic type fan regulators and light dimmers of approved make shall generally be used and
shall be of flush mounting type.
3.2.3 Wires:-
The wires used for internal electrical wiring shall be of single core PVC insulated sheathed/
unsheathed 1100V grade stranded copper/ aluminium conductor wires (suitably colour coded to
distinguish different phases and neutral) of approved make with ISI mark. The wires shall confirm to
IS:694 (Part-I & Part-II)/1964. The minimum cross sectional area of conductors for the different uses
shall be as specified below.
(a) Lighting point wiring : 1.5sqmm Copper or 2.5sqmm Aluminium.
(b) Power point wiring : 2.5sqmm Copper or 4.0sqmm Aluminium.
(c) HPSV/HPMV Luminaries : 2.5sqmm Copper or 4.0sqmm Aluminium.
(d) Circuit wiring : 2.5sqmm Copper or 4.0sqmm Aluminium.
(e) Sub-main wiring : 4.0sqmm copper or 6.0sqmm Aluminium.
3.2.4 Non-Metallic Conduit and Accessories:-
All non-metallic conduits shall confirm to IS:2509/1963 and their accessories to IS:3419/1965.
The conduits may be either threaded type or plain type and shall be used with the corresponding
accessories.
3.2.5 Switch Boxes:-
Metal boxes for switchboards shall be made of GI. sheet and round junction boxes shall be
made of cast iron. The minimum wall thickness of GI. boxes shall be 1.5mm (16swg) and cast iron
boxes shall be 3mm. Fan hook boxes shall be made of m.s./GI sheet of 1.5mm wall thickness with a
10mm round steel hook inside. The size of the fan hook box shall be 150mm dia and 65mm high. All
GI boxes shall have not less than 4 screwed holes for fixing the top cover and a earthing stud. All
metal boxes shall be provided with a cover of phenolic laminated sheet (Bakelite sheet), not less
than 3mm thick fastened to the box with brass screws and cup washers. The covers should have a
minimum overlap of 12.5mm on all sides of the box for concealed wiring. The boxes shall be painted
both inside and outside in case of m.s., with two coats of anticorrosive primer and two coats of
101
enamelled paint of approved shade. Adequate numbers of half punched holes shall be provided for
conduit entry.
The following sizes of GI boards shall normally be used unless otherwise specified.
Switch board size
Length Breadth Height
100mm 100mm 50mm
100mm 100mm 65mm
150mm 100mm 65mm
200mm 150mm 65mm
250mm 200mm 65mm
300mm 250mm 65mm
450mm 300mm 65mm
3.2.6 Angle/ Batten/ Pendant Holder & Ceiling Rose:-
Brass or Bakelite type 5A, 250V, Angle Holders, Batten Holders, Pendant Holders & three way
ceiling rose confirming to IS:732(Part-2)/1982 & IS:371/1979 of approved make and design with ISI
mark shall be used.
3.2.7 Distribution Boards:-
All the L.T. Distribution Boards shall be suitable for operation in 3 phase/ single phase,
415/240 Volts, 50Hz, neutral grounded at transformer system and a short circuit level of not less
than 35MVA at 415 Volts. All Distribution Boards shall generally confirm to all relevant Indian
Standards amended up to date.
Distribution boards shall be of wall/ floor mounting type and totally enclosed having hinged
doors, dust, damp and vermin proof construction. These should be made out of CRCA sheet steel
and the enclosure should be acid treated for rust proofing, thoroughly cleaned, painted with two
coats of anticorrosive primer and two coats of white enamel paint for interior and industrial grey
enamel paint for exterior. All doors and covers shall be fully gasketed with neoprene PVC strips and
shall be lockable. All the hinged doors shall be effectively earthed with flexible copper wires.
Cadmium plated fixing screws shall enter holes tapped into an adequate thickness of metal or
provided with hank nuts. Self-threading screws shall not be used.
102
The distribution boards shall be of adequate size with a provision of 25% spare space to
accommodate possible future additional switch-gears. Knock out holes of appropriate sizes and
number shall be provided on detachable plates in the board in conformity with the location of
incoming and outgoing cables/ conduits. The switches shall be so arranged that fuses are not alive
when the switch is in OFF position. No apparatus shall project beyond and edge of the panel. No
switch body shall be mounted within 25mm of any edge of the panel and no holes, either than meant
for fixing the panel shall be drilled within 13mm of the edge of the panel. The various live parts shall
be effectively screened by barriers of non-hygroscopic, non-inflammable insulating materials or shall
be so spaced that an arc can be maintained between such parts and earth. All items of switch-gears
shall be readily accessible and all connections, including those to instruments and apparatus, be
easily traceable.
The busbars and interconnections shall be of electrolytic annealed copper/ high conductivity
electrolytic wrought aluminium of rectangular cross section suitable for carrying full load current for
phases & neutral busbars and shall be extensible on either side. The maximum current density shall
be 1.00 Amp/sqmm for Aluminium and 1.25 Amp/sqmm for copper busbars. The busbars shall be
supported on SMC/ DCM/ Glass fibre reinforced polyester, non-breakable non-hygroscopic
insulators at regular intervals to withstand the forces arising from short circuit in the system. All
busbars shall be provided in a separate chamber and properly ventilated. The minimum clearance
between the phases shall be 25mm and between phase and earth shall be 20mm. The
interconnection between busbars and switchgears of rating above 63A shall be through strips having
125% of the switch-gear current rating. All busbars shall be suitably insulated by means of heat
resistant PVC sleeves or PVC insulating tapes and colour coded in phase sequence of R-Y-B & N.
The entire busbar shall be covered on the front with a Bakelite sheet barrier. In longer sections of
busbars, provision shall be made for thermal expansion by providing flexible joints made out of multi-
foil thin copper/ aluminium foils. All joints shall be of clamped type as far as possible else of bolted
construction with double cover fish-plates.
All connections between pieces of apparatus or between apparatus and terminal on a board
shall be neatly arranged in a definite sequence, following arrangements of the apparatus mounted
there on, avoiding unnecessary crossings. Wire interconnections shall be colour coded and
connected to terminals only by soldered lugs, crimped lugs without cutting away the strands. No
interconnecting wires shall come in contact with the live busbars other than the terminal points. The
arrangement of busbars shall confirm to IS:375/1963.
An enamelled danger notice plate shall be provided on the boards connected to medium
voltage supply & above.
Adequate space shall be provided for accommodating various instruments. These shall be
accessible for testing and maintenance without any accidental contact with live parts of circuit
breakers, switch-gears, busbars and interconnections. The indicating lamps shall be provided with
individual switch and fuses. The voltmeters shall be provided with fuses for each phase. The control
wires shall be of 2.5sqmm copper for CT circuits and 1.5sqmm copper for the rest. The control wires
shall be neatly bunched together inside PVC trunking securely fasten to the compartment properly
marked with ferrules at the end. A separate tamper proof compartment with locking arrangements as
per the requirements of the supply authority shall be provided for housing of the energy meters.
103
(a) Branch Distribution Boards (BDB):-
The branch distribution boards shall be surface mounted or concealed type and made out of
1.6mm (16 swg) CRCA sheet steel. At least one number hexagonal earthing stud for single phase
BDBs and two numbers earthing studs for three phase BDBs shall be provided. The components of
the BDBs shall be mounted on a detachable 2mm thick CRCA sheet steel frame works for easy
maintenance. The minimum size of wires to be used as interconnecting wires shall be 2.5 sqmm
copper or 4.0 sqmm aluminium. Each outgoing circuit of the BDB shall be provided with a fuse/ MCB
on the phase or live conductor. The earthed neutral conductor shall be connected to a common link
and be capable of being disconnected individually for testing purpose. Door interlocking with MCBs
shall be provided such that doors shall open only with MCBs in OFF position. All the live parts inside
the BDB shall be covered with a Bakelite sheet with at least 3mm thick.
(b) Main Distribution Boards and Sub Distribution Boards:-
The Main Distribution Boards (MDB) and Sub Distribution Boards (SDB) shall be wall mounted
or floor mounted type and made out of 2.0mm (14swg) CRCA sheet steel. In case of wall mounted
boards the entire sheet steel enclosure shall be mounted on a m.s. angle frame work with adequate
fixing arrangement for grouting. In case of floor mounted boards the enclosure shall be fixed to a
m.s. angle framework with m.s. base channels. All the incoming and outgoing switch-gears and
breaker other than MCBs shall be fixed in separate compartments.
All switch-gears above 63A rating and breakers shall be provided with door interlocks so as to
open only in OFF position. All MCCBs shall be provided with external operating handle. The ON,
OFF, TRIP (where available), Rating marking and nomenclature plates shall be provided near
operating handle. A continuous earth bus made out of Galvanised Iron or Aluminium strips of
adequate size shall provided at the bottom of panel for the entire length. Arrangement shall be made
at both the ends of earth bus for easy entry and termination of earthing lead from external earth
installations.
Cable compartments of adequate size shall be provided for easy termination of all incoming
and outgoing cables entering from bottom or top. Proper cable supports shall be provided in cable
compartments. All incoming and outgoing terminals shall be brought out to terminal blocks or to a
extended rigid strip directly from the switch-gear/ breaker. Separate cable compartments shall be
provided for incoming and outgoing cables. Ventilation arrangement in the form of finely divided wire
mesh shall be provided at both sides towards the top.
3.2.8 Miniature Circuit Breaker (MCB):-
The miniature circuit breakers of approved make shall be ISI marked and capable of
withstanding minimum 25000 switching operations and fully automatic with provision of thermal and
magnetic tripping arrangements. All MCBs shall be of minimum 9KA short circuit rating and confirm
to IS:8828/1993 & BS:3871.
3.2.9 Changeover Switches:-
The changeover switches shall be load break types having three distinct position of operation.
The ON and OFF positions of the switch shall be clearly indicated. The door interlock with defeat
104
mechanism shall be provided for switch units confirming IS:8623/1977. The changeover switches
shall confirm to IS:4064/1978 and IEC:408 and bear ISI mark.
3.2.10 Rewireable Fuses
The re-wireable fuses (Kitkat) shall be semi-enclosed type consisting of a re-wireable fuse
carrier and fuse base and shall be made out of either porcelain or Bakelite. The breaking capacity of
these fuses shall be 4000 Amp on 400 Volt. These shall bear ISI mark.
3.2.11 Energy Meters (KWH Meter)
The Energy Meters (KWH meter) shall be either whole current or CT operated type. These
shall be duly tested and calibrated by the supply authority prior to fixing and necessary test
certificate shall be furnished.
3.2.12 LT Power Cables
The LT power cables shall be of PVC insulated and PVC sheathed, 1100 Volt grade, single
core or multi core, un-armoured or GI wire / strip armoured, stranded aluminium conductor cables of
approved make and should bear ISI mark. The armoured cables shall confirm to IS:1554(Part-
I)/1976 and un-armoured cables to IS:694/1977.
3.2.13 Fluorescent Fittings
The Fluorescent fittings shall be of the following type.
(a) Box type fitting
All Fluorescent fittings shall be of approved make and in general confirm to IS:1913/1969.
These shall be complete with all standard accessories as per specification such as choke, capacitor,
starter and lamp holder etc duly factory wired. Provision shall be extended to earth all the metallic
part of the fixtures and all the detachable metal parts such as stove enamelled reflector of industrial
fitting, metallic louver of mirror optic fitting etc shall be provided with loop earthing by flexible wire.
The choke shall be copper wound and polyester filled. Powerfactor improvement capacitor shall be
provided confirming to IS:7752(Part-I)/1975 and of such rating to improve the power factor to 0.9.
3.2.14 Incandescent Fittings
The Incandescent fittings shall be of the following type.
(a) Ceiling flush type
(b) Bulk head type
These shall be complete with all standard accessories as per specification and provision for
earthling the metallic parts of the fitting.
3.2.15 Street Light Luminaries
The street light luminaries shall be of the following types.
(a) HPSV street light fitting
105
These shall be of approved make complete with all standard accessories as per specification
such as ballast, capacitor, igniter, starter, lamp holder etc and shall have provision for earthling of all
the metallic parts of the fitting. The luminaries shall in general conform to IS:10322 (Part-1 to Part-5).
3.2.16 Ceiling Fans
The a.c ceiling fans shall be of approved make & brand and suitable for operation on 230V
50Hz single-phase supply. The fans shall consist of all standard accessories such as 300mm long
down rod, canopies, shackle, 3 or 4 fan blades, capacitors etc but excluding speed regulator. The
fan motor shall be of permanent capacitor run totally enclosed with double ball bearing and the
winding shall be made of super enameled copper wire with class-E insulation. These fans shall
confirm to IS:374/1979 with amendment number 1, 2 & 3.
3.2.17 Exhaust Fans
The exhaust fans shall be of approved make & brand and suitable for operation on single/
three phase 230/ 415V 50Hz supply. The fans shall consist of all standard accessories such as
impeller blade, fixing frames, capacitors, anti vibration pads etc. The exhaust fan motor shall be of
permanent capacitor run, continuous rated, totally enclosed with double ball bearing and the winding
shall be made of super enamelled copper wire with class-A /class-E insulation. Sound level of the
exhaust fans shall not exceed 60db for domestic application and 65db for industrial application.
Gravity louver shutters made out of aluminium sheets with a steel frame/ wire guard shall be
provided with these fans. These shall have IP:44 degree of protection. The exhaust fans shall bear
ISI mark and confirm to IS:2312
3.3.0 INSTALLATION
3.3.1 Portions of Wiring
3.3.1a Point Wiring
Point wiring shall consist of a switch on the board and wiring up to termination point via the
control switch and neutral. These termination points can be :
(a) A ceiling rose or connector in case of call bell or ceiling fan or exhaust fan point wiring. The
wiring from ceiling rose or connector to ceiling fan or exhaust fan point shall be considered
with the installation of fans.
(b) A ceiling rose in case of directly fixed type fluorescent fixtures, suspended pendants.
(c) A back plate in case of suspended type fluorescent fixtures, suspended or stiff pendants,
wall brackets, bulk heads, spot light similar fittings.
(d) A lamp holder in case of angle or batten holders.
(e) A convenient wall plug in case of plug on board or separate board points.
Wiring for light points and fan points shall be carried out with minimum 1.5 sqmm copper
stranded conductor wire. For the purpose of measurement the points are classified as below
wherever specified.
106
(a) Short points : Up to 3.0m long
(b) Medium points : 3.0m to 6.0m long
(c) Long points : 6.0m to 10.0m long
(d) Special long points : Above 10.0m long (As specified)
Where classification of points are not specified, the point wiring shall mean wiring to the all
types points as described above irrespective of the length of the point.
The wiring whether concealed or surface shall be easily accessible for inspection. Power and
Heating sub-circuits shall be kept separate and distinct from lighting and fan sub-circuits. The
balancing of circuits in three phase installations shall be arranged before hand. Circuits of different
phases of a.c. system shall be kept minimum 2.0m apart or enclosed in earthed metal casing.
Medium voltage wiring and associated apparatus shall comply, in all respect, with the requirements
of rules 50, 51 and 61 of Indian Electricity Rules, 1956.
The position of runs of wiring and the exact position of all points, switch boards, distribution
boards shall be marked in the building for approval of Engineer-in-charge prior to execution. The
wiring shall be carried out in looping back system in which the phaseconductor shall be looped at the
switch box and that of neutral at the junction box and point terminals. In no case, joint shall be made
bare or by twisting the conductors.
Lights and fans may be wired on a common circuit. Such circuit shall not have more than a
total of either 10 points or a load of 800 watts.
For the purpose of determining load per circuit, the following rating for points shall be
assumed.
(a) Light points (Incandescent) : 60 watts
(4' fluorescent tubes) : 40 watts
(2' fluorescent tubes) : 20 watts
(b) Ceiling fan points : 80 watts
(c) Exhaust fan points : 80watts
(d) 5Amp plug points : 100 watts
(e) 15Amp plug points : 1000 watts
Unless and otherwise specified, the following minimum mounting height of the bottom most
part of the fittings and fixtures from finished floor level shall be maintained.
107
(a) Distribution Boards : 2.130 metre
(b) Switch board : 1.300 metre
(c) 5A & 15A plugs on separate
board
: 0.300 metre
(d) Ceiling fan : 2.750 metre
(e) Light fittings : 2.600 metre
(f) TV antenna and Telephone
outlets
: 0.300 metre
3.3.1b Circuit Wiring
Circuit wiring shall mean wiring from BDB/ SDB upto the junction boxes for switch boards
containing 5A/15A switches and plugs. For the purpose of measurement, in case of multiple switch
boards under one circuit, the circuit wiring shall mean the sum of the length of wiring from BDB/ SDB
upto junction box of first switch board and junction box of first switch board to the junction box of
next switch board and so on. The minimum size of conductor for circuit wiring shall be 2.5 sqmm
copper or 4.0 sqmm aluminium. A circuit shall not contain more than 2 number power plugs. If not
specified in point wiring to power plugs, the wiring to the same shall be treated as circuit wiring.
3.3.1c Sub-main Wiring
Sub-main wiring shall mean wiring from Main switch/ Meter board upto BDB/ SDB. The
minimum size of wire shall be 4.0sqmm copper or 6.0sqmm COPPER. There shall be no jointing of
wires as far as practicable. PVC ferrules shall be provided at both the ends of the wire for easy
identification.
3.3.2 Types of Wiring
3.3.2a Concealed Non-metallic Conduit Wiring
The concealed non-metallic conduit wiring shall be completed in the following three phases.
(a) Conduit laying in roof before casting.
(b) Conduit laying in walls & fixing of switch board before plastering.
(c) Wire drawing inside conduit, fixing of switch, socket accessories, testing of
installations complete.
The size of conduit shall be so chosen that the wires provided inside shall not occupy more
than 50% of the cross sectional area. The maximum permissible number of single core wires, which
can be drawn inside non-metallic conduit, shall be as per the table given below.
108
Size of wire in mm2 Size of conduit in mm
(Maximum no. of wires permissible)
Remarks
16 20 25 32 40 50
1.0 mm2 5 7 13 - - -
1.5 mm2 4 6 10 - - -
2.5 mm2 3 5 10 - - -
4.0 mm2 2 3 6 10 - -
6.0 mm2 - 2 5 9 - -
10.0 mm2 - - 4 7 9 -
16.0 mm2 - - 2 4 5 -
25.0 mm2 - - - 2 4 6
35.0 mm2 - - - - 2 5
50.0 mm2 - - - - 2 3
A detail conduit route layout avoiding unnecessary crossing shall be prepared by the
contractor and get it approved from Engineer-in-charge prior to laying of conduit in roof slab. The
conduits and junction & fan hook boxes shall be rigidly tied to the reinforcement of the slab.
Minimum 75mm x 75mm size sheet metal inspection cum pull box shall be provided within 5 metre
run of conduit. Suitable type expansion joint fittings shall be provided along the conduit run crossing
the expansion joint of the building. The junction boxes shall be provided 300mm off the centre for 4'
long tube light fitting and 150mm off the centre for 2' long tube light fitting. Dummy or spare conduits
shall be laid wherever required as per direction of Engineer-in-charge.
The drops from the roof slab in walls and columns shall be made vertical as far as
practicable. Horizontal run of conduit on brick or stone masonry walls shall be avoided. The conduit
and the switch boards shall be fixed in the wall by cutting chase and neatly finished with plastering
after fixing. All curves in the conduit pipe shall be made by bending pipe with a long radius which will
permit easy drawing of conductors. The m.s. boxes shall be provided with temporary covers to safe
guard against filling of cement mortar etc within the tendered cost.
The wires shall be properly colour coded and carefully drawn inside the conduit through use
of fish wire. All the metal boards shall be suitably earthed by earth continuity conductor. All
Conductors shall be provided with cable sockets at termination points expect at switchboard looping
109
and joint boxes. Wires carrying current in a conduit shall be so bunched that the outgoing and the
return wire are drawn into the same conduit. Wires of different phases from different circuits shall not
run in one conduit. In three phase installation, plans shall be made for balancing of loads in all
phases before commissioning.
3.3.3 Cable Laying & Installation
The cables shall be of approved make and tested at factory in presence of Engineer-in-
charge or his authorised representative. The cables shall be despatched to the work site packed on
wooden drums with both ends properly sealed. Jointing of the cables in between the terminal points
shall be avoided as far as possible. For longer length of cable exceeding the normal length of
manufacture, cables may be joined by means of jointing kits only. The cables shall be tested for
insulation resistance by 500-volt insulation Megger for cables upto 1100 volt grade and by 2500 volt
insulation Megger for cables beyond 1100V grade prior to laying of the same. Cable loops for future
requirement shall be kept at both ends as per direction of the Engineer-in-charge.
One number 6 swg G.I. wire in case of single phase 230V a.c. system and either 2
numbers 6 swg G.I. wire or 2 numbers suitable size G.I. flat in case of multi phase 400V or more
a.c. system shall run all along the trench or tray with the cables as earth continuity conductor. The
supply and laying of earth continuity conductor such as G.I. wire or flat has been considered
separately in the schedule of quantity.
Minimum bending radius for PVC insulated armoured cables shall be 1200mm. At joints and
terminals, the individual cores of multi-core cable should never be bent so that radius of bending is
less than 12 times the overall diameter of the cable.
Wherever more than one cable shall exist, suitable marker tags inscribed with cable
identification details shall be permanently attached to all cables in the man hole, pulpits, joints, open
ducts, under ground cables etc at suitable intervals.
The laying and installation of cable shall be carried out as per IS:1255/1983. The methods of
cable laying shall be of following types depending upon the requirements.
(a) Laying directly under ground
(b) Laying inside ducts
(c) Laying on racks or trays in air
(d) Laying along building structural elements
3.3.3a Laying Directly Under Ground
Cable trenches shall be excavated cutting all types of soil and rock upto a minimum depth of
750mm for L.T. cables & 1200mm for H.T. cables and of appropriate width (not less than 350mm) to
accommodate the cables and cable protecting materials within the tendered rate.
The sides and bottom of the trench shall be dressed and filled with 75mm thick layer of fine
sand. The cables shall then be laid with bricks on both side of each cable continuously along the
length. Space between the bricks shall be filled with fine sand upto 75mm above the top of the cable.
The top layer bricks shall be placed side by side continuously as protective cover. The horizontal
110
distance between the adjacent cables shall be minimum 200mm. The clearance between the outer
cable to the sides of the trench shall be at least 150mm.
In case of multiple tiers, same procedure shall be applied keeping a vertical clearance of
300mm among the tiers and the top most layer shall be kept at a depth of 750mm for LT cables and
1200mm for H.T. cables from finished ground level.
The trench shall then be filled up with the excavated materials free from stone or sharp
edged debris and duly compacted. A crown of earth neither less than 50mm nor more than 100mm
in the centre and tapering towards the sides of the trench shall be left to allow for subsidence.
Cable route markers shall be installed at salient and strategically located points parallel to
and 500mm or so away from the edge of the trench for easy identification of cable routes at a
maximum interval of 10 metre for straight run.
In locations such as road crossing, pipe line crossing, entry to buildings or poles in paved
area etc, the cables shall be laid in pipes or closed ducts. Pipes provided for entry to building shall
slope upward to prevent entry of water to the building. Stone ware, cast iron, NP-2 class RCC pipes
or medium class M.S./G.I. pipe of appropriate diameter shall be laid during the construction to avoid
damage later on.
In case of stone ware pipes, a 100mm thick 1:3:6 cement concrete covering shall be
provided. In case of cast iron or RCC pipes no concrete covering is required. The collars in case of
RCC pipes shall be embedded by 1:2:4 cement concrete. Top surface of pipe shall be at a minimum
depth of 1.0 metre. The minimum size of hume pipes shall not be less than 100mm in diameter for a
single cable and not less than 150mm for multiple cables.
The diameter of the cable protecting pipes shall be at least 1.5 times the outer diameter of
the cable. In one pipe, single core cables shall not be laid individually but instead, all the three/four
cables of the same system shall be laid.
3.3.3b Laying along Building Structural Elements
Cables can be routed inside the buildings along the structural elements such as walls,
columns etc or inside trenches or hume pipes or G.I. pipes under floor. The cables shall be laid or
fixed along the wall or column with the help of M.S./G.I. flat clamps or saddles with an interval not
exceeding 0.5 metre. The cables inside brick masonry trenches shall be laid on racks or directly
above the floor of the trench and the trench shall be covered with m.s. chequred plates. In case of
laying inside hume pipes or G.I. pipes, man hole chamber with RCC cover shall be provided at
suitable location for easy maintenance. The cables shall not intersect each other along its route.
3.3.4 Jointing of Cables
The quality of joints shall be such that it does not add any resistance to the circuit. The
materials and techniques employed for jointing should give adequate mechanical and electrical
protection to the joints under all service conditions. The joints shall be resistant to all corrosion and
chemical reactions. The following three basic types of cable joints shall be used.
(a) Straight through joints
111
(b) Tee or branch joints
(c) Termination or sealing joints
3.3.5 Installation of Distribution Boards
All main switch-gears shall be installed in dry situation as near as possible to the point of
supply. The neutral wires shall be continuous except at the linked switch-gear. Main distribution
boards shall be installed in well-ventilated rooms or cupboards accessible to only authorised persons
or recessed having locking arrangement. The distribution boards shall not be installed in damp
situations, in the vicinity of storage batteries, places exposed to chemical fumes or where
inflammable or explosive dust, vapour or gas is likely to be present. These boards shall not be
erected above gas stoves, sinks, in bath rooms, lavatories, toilets, kitchens, places exposed to
weather or within 2.5 metre of a washing unit in the washing rooms and wash basins.
Fixing of distribution boards in places likely to be exposed to weather, drip or abnormal moist
atmosphere shall be avoided. Where it is unavoidable, out door distribution boards with outer casing
on the switch boards shall be installed making it weather proof and shall be provided with gland or
bushings or adapted to receive screwed conduit according to the manner in which cables are run.
The indoor distribution boards shall be mounted concealed or semi-concealed or surface to
the wall or on foundations above the floor. The panels shall be so mounted that it is accessible for
fuse replacement and operation of switch-gears & breakers.
The top most height of the panel shall not be more than 2 metre from the floor level. In case
of Branch Distribution Boards shall generally be installed at a height of 2.13 metre from finished floor
level. A minimum clearance of 1 metre shall be provided from the surface of door opening of the
boards for maintenance.
All distribution boards shall be marked lighting or power, voltage, number of phases of
supply, circuit list, current rating of the circuit and rating of fuse element. All wiring and
terminations shall be provided with cable lugs and neatly arranged.
Adequate space shall be provided on bottom or top or back as required for easy cable and
conduit entry. The cables shall be terminated at the distribution board with corresponding size of
brass cable gland. The glands shall be fixed tightly to the panel without allowing any gap or opening
on the hole. The armours of the cable shall be suitably earthed. For conduit entry, PVC couplings for
non-metallic flexible conduit and brass coupling for G.I. flexible conduit shall be used. No holes shall
be kept open on any side of distribution board.
Distribution boards shall be earthed at two points from two separate & distinct earth
electrodes in case of three phase boards and one point in case of single phase boards effectively by
means of G.I. wire or flat as specified.
3.3.6 Installation of Fluorescent Fixtures
The fluorescent fixtures shall be either directly fixed on walls or ceiling or suspended from
ceiling of buildings. The contractor shall make proper marking for alignment and level of fitting as per
the drawing prior to installation and get it approved from Engineer-in-charge. The contractor shall
assemble and install the fittings as per the manufacturer's instructions. Connection from ceiling rose
112
or connector shall be done with 3 core 1.5 sqmm flexible copper cord. Each fitting shall be effectively
earthed.
For fixing the fitting directly on walls and ceiling, the same shall be fixed on two numbers
seasoned wooden round blocks. The round blocks shall be duly painted and fixed to wall or ceiling
by means of PVC fill plugs and screws.
In case of fitting being suspended from ceiling, the same shall be fixed by means of two
numbers 16 swg stove enamelled m.s. conduit down rods along with cast aluminium ball sockets,
conduit check nuts, circular Bakelite cover etc. The down rods shall be painted with 2 coats of
enamel paint of approved shade. The fixing arrangement to the ceiling shall be capable of sustaining
the entire load of fitting and down rod. The minimum mounting height of the fitting shall not be less
than 2.5 metre from the finished floor level.
3.3.7 Installation of Incandescent Fittings
The incandescent fittings shall be rigidly fixed to wall or ceiling using Bakelite sheet. The
metal parts of the fitting shall be effectively earthed by the earth continuity conductor. The flexible
pendants, chandeliers etc shall be suspended from a hook provided in the slab during casting. The
bulkhead fittings shall be recessed/ surface mounted on wall or ceiling.
3.3.8 Installation of Street Light Fittings
The street light fittings shall be fixed by means of either suitable G.I. bracket or on arms of
tubular pole. The G.I. bracket shall be fixed by means of minimum two pairs of m.s. flat clamps duly
painted. Loop-in-loop-out junction boxes shall be embedded inside the bottom foundation of the
support wherever required. The wiring to the fitting shall be carried out by minimum 2 core 2.5
sqmm PVC insulated stranded copper wire along with 16 swg hard drawn bare copper earth
continuity conductor. The fitting shall be assembled and mounted as per the manufacturer's
instructions.
3.3.9 Installation of Ceiling Fans
Unless otherwise specified, the bottom most part of the ceiling fans shall normally be kept at
a height of 2.75 metre above finished floor level. In no case, it shall be lower than 2.4 metre above
the finished floor level. A minimum clearance of 300mm shall be maintained from the ceiling/beam to
the plane of fan blades. The mounting height of all ceiling fans installed inside a hall or room shall be
same. The metal parts of the ceiling fans shall be effectively earthed. The fans shall be assembled
and mounted as per the manufacturer’s instructions.
The wiring to the ceiling fan from the nearest point shall be carried out with 3 core 1.5 sqmm
PVC insulated stranded copper conductor cords. The down rod & clamp shall be painted with
enamel paint of approved shade without involving any extra cost. Round bakelite sheet shall be
provided on the fan hook boxes.
3.3.10 Installation of Exhaust Fans
Exhaust fans shall be fitted by means of rag bolts embedded in the wall. The required holes
in the wall shall be made and finished neatly with cement plaster and brought to the original finish of
the wall within the tendered rates. Gravity louvre shutters of suitable size shall be fixed on the
113
outside wall covering the hole for the exhaust fan in order to restrict the inrush of rainwater etc. A
wire mesh shall be provided in place of gravity louvre shutters to restrict the entry of birds where
there is no chance of inrush of rainwater. All the metal parts of the exhaust fans shall be effectively
earthed. The fans shall be assembled and mounted as per the manufacturer’s instructions. The
wiring to the exhaust fan from the nearest point shall be carried out with 3 core 1.5 sqmm PVC
insulated stranded copper conductor cords.
3.3.11 Installation of Earthing
The earthing installations shall generally conform to IS:3043/1966 and requirements of
Indian Electricity Rules, 1956.
All three-phase medium voltage equipments shall be earthed by two separate and distinct
connections with earth through earth electrodes. Single phase equipments shall be earthed at least
at one point. In case of high & extra high voltages, the neutral point shall be earthed by not less than
two separate and distinct connetion with earth each having its own electrode.
An earthing electrode shall not be situated within a distance of 1.5 metre from the building
whose installation system is being earthed. The cross sectional area of earth continuity conductor in
electrical installation shall no where be less than 16swg copper or 14swg GI wire. The earth
resistance for various installations shall be restricted within the following maximum permissible
limits.
Non industrial Buildings : 5 ohms
Earth continuity inside an installation : 1 ohm(From electrode to any point in installation)
The following types of earthing installations shall in general be provided.
(a) Pipe earthing
3.3.12 Pipe Earthing
Pipe earth electrodes shall be of perforated class B G.I. pipe of specified length and
diameter. Galvanising of pipes shall conform to relevant ISS. The G.I. pipe electrode shall be cut
tapered at the bottom and provided with holes of 12mm dia drilled not less than 75mm from each
other in zigzag manner upto 500mm from the top of the electrode. A pair of 50mm x 5mm G.I. flat
clamp with 2 nos 18mm dia drilled holes on either side shall be welded to the electrode at about
150mm below the top of the pipe.
The electrode shall be buried in the ground vertically with its top not less than 200mm below
the ground level. The pipe earth electrode shall be surrounded by, either salt & charcoal in alternate
layers or a homogeneous mixture of the both, for a radius of about 150mm and upto a height of
about 250mm below the top of the electrode. The balance portion of the excavated pit shall be filled
with good quality soil and properly compacted.
A brick masonry chamber with hinged cast iron/ removable RCC inspection cover of size
300mm x 300mm shall be constructed within the tendered rate. Watering arrangement shall be
made with funnel and wire mesh fixed by means of a reducer socket on the top of the electrode.
114
3.3.13 Installation of Earthing Leads
The earthing lead connecting the earth electrode to the apparatus or installation directly shall
be of the same material as earth electrode. The earthing leads shall be either wires or strips of
adequate size as specified and of either G.I. or tinned copper. The G.I. leads shall be connected to
the electrode by means of 16mm dia G.I. nut bolts with flat & spring washer and the tinned copper
leads shall be connected to the electrode by means of 16mm dia brass nut bolts with flat & spring
washer.
All earth connections shall be visible for inspection. The earthing lead from electrode
onwards shall be suitably protected from mechanical injury by means of 20mm dia G.I. pipe for G.I.
wires. The portion of this protection pipe within ground shall be buried at least 300 mm deep from
ground level. (Subject to increase upto a depth of 600mm in road crossings and pavements.) The
portion within the building shall be recessed or clamped at not more than 500mm interval in the
walls/ columns/ beams etc and recessed in the floors. Joints in the earthing lead from earth
electrode to apparatus shall be avoided as far as practicable. However if joints are inevitable, same
shall be done by welding or proper bolting in case of G.I. strips and brazing or proper bolting in case
of tinned copper strips. The welded joints in G.I. strips shall be applied with bituminous paint and
wrapped with bituminous tape.
3.4.0 TESTING
Before a completed installation or an addition to an existing installation is put into service, the
following tests shall be carried out by the electrical contractor in presence of Engineer-in-charge.
(i) Polarity test
(ii) Insulation resistance test
(iii) Earth continuity test
(iv) Earth electrode resistance test
3.4.1 Polarity Test
It shall be ensured by this test that the single pole switches have been fitted on the live side
of the circuit they control. In a two-wire installation, test shall be made to verify that all switches in
every circuit have been fitted to phase conductor or non-earthed conductor of the circuit. In three or
four-wire installation, test shall be performed to verify that every non-linked single pole of switch is
connected to one of the phase conductor of supply.
3.4.2 Insulation Resistance Test
The insulation resistance shall be measured by applying between earth and whole system of
conductors or any section thereof with all fuses in place and all switches closed and except in earth
concentric wiring, all lamps in position or both poles of installation otherwise electrically connected
together, a d.c. voltage of not less than twice the working voltage, provided that it does not
exceed 500 volts for medium voltage circuit. Where the supply is derived from 3 wire a.c. or d.c. or
polyphase a.c. system the neutral pole of which is connected to earth direct or through added
115
resistance, the working voltage shall be deemed to be that which is maintained between the outer or
phase conductor and neutral.
The insulation resistance of an installation measured as above shall not be less than 50
Mega-Ohms divided by the number of points of the circuit provided that the whole installation shall
be required to have insulation resistance greater than one Mega-ohm.
Control rheostats, heating and power appliances and electric signs may, if desired, be
disconnected from the circuit during the test, but in this case the insulation resistance between the
case of frame and all live parts of each rheostat, appliances and signs shall not be less than half a
Mega-ohm.
The insulation resistance shall also be measured between all conductors connected to one
pole or phase conductor of the supply and all conductors connected to the neutral or the other pole
or phase conductor of supply. Such test shall be made after removing all metallic connections
between two poles of the installation. The insulation resistance between the conductors of
installation shall not be less than that specified above.
3.4.3 Earth Continuity Test
The earth continuity conductor including metal conduits and metallic envelope of cables in all
cases shall be tested for electric continuity and electrical resistance of the same along with the
earthing lead but excluding any added resistance of earth leakage circuit breaker measured from the
connection with the earth electrode to any point in the earth continuity conductor in the completed
installation shall not exceed 1 ohm.
3.4.4 Earth Electrode Resistance Test
The resistance of each earth electrode shall be tested with an earth tester and the combined
earth resistance of the earth grid of an installation shall be maintained as mentioned below.
Distribution Substations : 2 ohms
Industrial Buildings : 4 ohms
Non industrial Buildings : 5 ohms
Earth continuity inside an
installation
: 1 ohm(From electrode to any point in
installation)
3.4.5 The completed installation shall be taken over only if the results obtained from the above tests
are within the limits mentioned above and in accordance with I.E. Rules. On completion of
testing of installation, a certificate shall be furnished by the contractor countersigned by the
certified supervisor having a valid electrical supervisory licence issued by Electrical Licensing
Board of the State Government under whose direct supervision the installation was carried out.
This certificate shall be in a prescribed form obtainable from local supply authority.
3.5.0 SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL INSTALLATION
116
3.5.1 Authorities
The contractor while executing the work shall obey to the provisions of the Government Acts
relating to the work and the regulations and by-laws of statutory bodies or local authorities and
supply authorities. The contractor shall undertake to provide all test certificates and make necessary
arrangements to obtain electric supply.
3.5.2 Drawings
The installations work shall be carried out as per the approved execution drawings. Prior to
laying of conduits or cables, the contractor shall submit drawings for same indicating the route,
conduit size and numbers, location of inspection boxes etc. for approval.
The contractor on completion of the installation shall submit the following drawings in tracing
paper.
As built electrical layout drawings of each floor showing the position of points & outlets, type
of fittings & fixtures, location of switch boards & distribution boards, circuit & phase indication,
position of earth electrodes, cable & conduit routes, position of lightning terminals & conductors etc
neatly drawn.
As built schematic single line diagram of the entire installation showing
(i) all distribution boards having description of capacity, system & source of supply, type & their
numbers;
(ii) location, size, type, length of main and sub-main cables/ wires;
(iii) load details of each circuit or ways of distribution board or switch gear.
The drawings shall furnish the identification details such as name of work, job no., accepted
tender no., date of completion, site location, name & address of owner, name & address of
consultant, signature & name of contractor, his address, scale of drawing.
3.5.3 Commercial
All types of laborers referred in the schedule such as masons, electricians, wiremen, cable
jointers, helpers, labourers etc are required to carry out electrical installation work to a building with
all necessary tools and plants with them.
After completion of the installation, the contractor shall test the same in the presence of
Engineer-in-charge for safety and durability as per IS specification and I.E. Rules. He shall get the
electrical installation inspected by the Electrical Inspecting Authority and obtain necessary inspection
report and statutory clearance to energise the installation at his own cost. However all fees for
inspection prescribed by the statutory authority paid by the contractor shall be reimbursed by the
owner on production of documentary evidence. The contractor shall submit necessary test
certificates as and when required.
117
After completion of testing, necessary statutory inspection by competent authority and
contract/ agreement with local supply authority, the contractor at his own cost shall arrange for final
commissioning and energisation of installations before final handing over to the owner.
Rate quoted shall include all cost of labours with tools and plants, sundries and accessories,
transportation of materials from local store, insurance, storage and handling, providing watch and
ward to the installation carried out by him and materials in his custody, and expenses for maintaining
the installation in proper order till final taking over. The contractor shall make good the damages
caused during the course of work at his own cost.
Only materials of approved make shall be used. All other materials not included in the list of
approved materials shall be got approved from Engineer-in-charge. If required, the materials may be
sent for testing to any standard testing laboratory for conforming the quality and specification as per
ISS. The cost towards testing shall be borne by the contractor. No surplus material procured by the
contractor shall be accepted by the owner.
The work shall be carried out in accordance with the specification of the schedule complete
with cost of all materials (except otherwise mentioned), all types of labour involved, all types of tools
& plants required, sundries and accessories and as per the drawing, design and direction of
Engineer-in-charge.
The electrical installation work shall be carried out by a registered and licensed electrical
contractor duly authorised by the local Electrical Licensing Authority. The work shall be directly
supervised by a Licensed Electrical Supervisor. Copy of valid license and details of previously
executed works of the contractor and his supervisor shall be furnished along with the tender.
3.5.4 Terms of Payment
Payment, upto maximum 80% of the quoted rate on each item completed but awaiting
testing and commissioning, shall be made. Another 10% payment shall be made after successful
testing in presence of Engineer-in-charge & inspection by statutory authority. The balance 10%
payment shall be made after completion of work with final commissioning, energisation, handing
over to owner & submission of performance bank guarantee.
3.5.5 Performance Guarantee
The entire electrical installations carried out by the contractor shall be guaranteed for a
trouble free operation against any bad workmanship, bad quality of material used for a minimum
period of 12 months from the date of taking over by the owner or 18 months from the date of
118
commissioning, whichever is earlier. Any defects found during this period shall be rectified and all
faulty materials shall be replaced by the contractor free of cost.
The performance guarantee shall be executed in shape of a bank guarantee, in the
prescribed format of the owner, amounting to 5% of the total value of electrical works executed,
through any Nationalised Bank valid till completion of the guarantee period.
4. TECHNICAL SPECIFICATION FOR CHEMICAL CONSERVATION WORKS
4.1.1 Scope of work :
The work contemplated under this contract includes general Conservation work for the
aforesaid project, all as detailed in the Bill of Quantities, Specifications and drawings and to
complete the said work in every respect in accordance with this contract and with the
directions and to the satisfaction of the Engineer-in-charge.
Such other works which are not included in the aforesaid Bill of quantities are generally
intended to be executed through a separate agency. Notwithstanding the above, the
Engineer-in-Charge reserves the right to order additional works under the same Contract.
The Engineer-in-charge also reserves the right to omit any item of work included in the
aforesaid Bill of quantities and award the same to any other contractor or not perform it at all
at his discretion and the Contractor shall not have any claim because of the same.
The Contractor for this work shall be required to work in co-operation and co-ordination with
other agencies on site and give them all reasonable assistance and help for the execution of
the work in an efficient manner all as directed. The words “approved” or “as directed” shall be
deemed to convey approval or the discretion of the Engineer-in-charge of the work.
4.1.2 Indian Standard Specification :
The particular Specifications for the work are as detailed hereinafter. These specifications
shall be read in conjunction with the relevant Indian Standard Specifications. The obtainable
local practice as detailed in various regional handbooks of practice may be used subject to
specific approval from the Engineer-in-charge. Where the specifications in any of the
standards are at variance with the specifications detailed herein, the specifications herein
shall govern.
4.1.3 Quality of Materials & General Standards of work :
The contractor under this contract commits himself to use materials conforming to relevant
Indian Standards / Codes and assumes full responsibility for the quality of all materials
incorporated or brought for incorporation in the work. The chemical should be of reputed
firms like M/s. Ranbaxy/Fisher Scientific (Qualigens)/ Merck/CDH and Wacker. The work
shall be executed in accordance with acceptable engineering practice and as per direction of
the Engineer-in-charge.
4.1.4 Scaffolding :
119
All scaffolding and ladders required for the proper execution of the work shall be provided by
the contractor. The scaffolding should be stout and strong to prevent any collapse or
displacement. Proper measures for safety of workmen working on scaffolding should be
taken by the contractor.
The mode of measurements, wherever possible is specifically mentioned in these
documents. Where it has not been mentioned, it shall be as per provision of the relevant
Indian Standards. All the measuring tapes and other accessories necessary, shall be
provided by the contractor.
The bidder along with his bid shall furnish a list of tools, plant and machinery which he
intends to use on the works in Bid document. The list should indicate the exact type of
machine, its capacity, year of manufacture, kind and capacity of propelling force, spare parts
readily available and all other pertinent information. The contractor is obliged to use the
machinery mentioned in his list if the Engineer-in-charge considers it necessary.
4.1.5 Access to site, approach roads and roads within the premises :
The contractor shall at his own cost provide all approach roads required for the purpose of
carrying out the work in the most expeditious and efficient manner and shall remove the
temporary roads on completion. He shall acquaint himself thoroughly regarding condition and
suitability of public roads leading up to the limits of the premises and will provide vehicles for
transportation of materials which meet the requirements of these road conditions. It shall also
be the responsibility of the contractor to maintain at his own cost the road till the construction
is completed. The bidder is also to acquaint himself with local laws and bylaws and comply
with all police and highway authority requirements.
4.1.6 Water :
Water for all the steps for the conservation work must be clean, neutral & free from salinity.
For this purpose, soft water should be used by installing Double Bed De-ionider Plant. The
De-ioniser Plant must be regenerated in regular interval to get salt free water.
4.2 Conservation work :
4.2.1 General vegetational cleaning
Cutting/Extraction of small plants from the fort complex and from the structure also
4.2.2. Chemical Cleaning
Chemical Cleaning of micro-vegetation, dust & dirt using 2% liquid Ammonia Solution and Non-
ionic detergent by soft brushing followed by through washing with plenty of de-ionized water.
4.2.3. Extraction of Salinity
Extraction of soluble salt by repeated paper-pulp treatment using de-ionized water
confirmation by testing with acidified silver nitrate solution.
4.2.4. Consolidation
Consolidation of the weak stone/brick surface by Wacker OH-100.
120
4.2.5. Fungicidal Treatment
After two weeks of the application of consolidant, fungicidal tratment by spraying 2%
aqueous sodium pentachlorophenate solution.
4.2.6. Hydrophobic Treatment
Hydrophobic treatment by application of Wacker BS - 290 diluted with mineral Turpentine oil in 1:16 ratio.
121
SECTION 6: DRAWINGS
124
SECTION 7: BILL OF QUANTITIES
BOQ FOR CONSERVATION OF HERITAGE BUILDING AT HUKITOLA, DIST- KENDRAPARA
Sl. No
Description of items. Qty
Unit Rate (Rs)
Amount (Rs)
1 Removal of vegetation by careful cutting and eredication of the roots of the plants as much as possible without affecting the structure and protective treatment with paste against the regrowth of vegetation, including filling of cracks and cavities with Lime mortar mix after drying of roots. including all cost of labour, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
325.15
Sqm
Rate in Words 2 Provision of scaffolding support from below to the
ceiling to prevent collapse of the ceiling before strengthing and stabilization of ceiling . including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
456.84 Sqm
Rate in Words 3 Provision for cost of iron joist ISMB 400 x 140mm in
built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer including all cost of labour, materials, conveyance, loading, unloading, T&P etc. all complete as per the direction of Engineer-in-charge.
18224.93 Kg
Rate in Words 4 Provision for labour and mason for carefully
removal of damaged iron I-section and replacing the new ISMB 400 x 140mm joist and removing the debris away from site including all cost of labour, conveyance, taxes, T&P, etc., including all lead and lift all complete as per directions of Engineer-in-charge.
18224.93 Kg
Rate in Words
125
5 Removing old lime or cement plaster from walls including raking out joints 12mm deep and removing the debris away from site including all cost of labour, conveyance, taxes, T&P, etc., including all lead and lift all complete as per directions of Engineer-in-charge.
2409.06 Sqm
Rate in Words 6 Cleaning the surface by water jet and applying an
arcylic polymer based water proffing compound in two parts to be mixed throughly by a slow speed (100-150 RPM) forced action mixture in three coats over the RCC surface including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
454.37 Sqm
Rate in Words 7 Carefully taking out the loose and damaged brick
from ceiling and removing the debris away from site including all cost of labour, conveyance, taxes, T&P, etc., including all lead and lift all complete as per directions of Engineer-in-charge.
25.09 Cum
Rate in Words 8 Dismantling and removing cement or lime concrete
including stacking the useful materials for reuseand removing the debris away from site including all cost of labour, conveyance, taxes, T&P, etc., including all lead and lift all complete as per directions of Engineer-in-charge.
a) Floor 69.58 Sqm
Rate in Words
b) Roof 37.11 Sqm
Rate in Words 9 Cracks treatment: Small fractures should be cut
along the line of feature and clean with water jet and plugged with lime mortar with Crack -X powder or Paste placed by hand. When the mortar has cued the fracture should be grouted with liquid mortar { The quantity of water should be enough to create a very mobile grout with 10% Dr fix Pagel ZS 10 with 1:1 limemortar ( 1 limeputty : 1 fine sand)}including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
50.00 Mtr
Rate in Words
126
10 Larger(wide) Cracks Treatment: For stitching work a chase of 600mm to 900mm and atleast 100mm deep should be cut across the fracture by diamond cutter machine. The chase should be cut clean and wash, the wetted chase area than filled one third with lime mortar 1:1 ( 1 lime putty : 1 course sand.) with Dr fix Pagel ZL 10 . A stainless steel strip of same size should be pressed home into the mortar and the chase flush filled. The stitches should be set across large fractures at approximately 1m centres. After stitching the fracture should be grouted with a liquid mortar.
25.00 Mtr
Rate in Words
11 Bonding Work for plaster repairing surface : Providing and painting with Dr fix MPB a polymer resin such as acrylic copolymers after properly cleaning the surface from imperative (dust and grease free) to be plastered just before plastering so that the mortar must be applied while the bond coat is still ' tacky'. Conservator must be vigilance for" If the bond coat has cured / dried, the original surface must be uncovered and the process started again. including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
2409.06 Sqm
12 Brick work with K.B. bricks 25cm x 12cm x 8cm having crushing strength not less than 75 Kg/cm2 with dimensional tolerance ±8 percent in lime mortar (1:2) in superstructure. including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
25.09 Cum
Rate in Words
13 20mm. thick lime plaster (1:2) on brick work including racking out joints, scraping and cleaning the surface and finishing the plaster surface smooth using wooden floats only to proper plumbs and level and making grooves and beads to give required ornamental finish as per drawings including cost of all materials, conveyance, loading and unloading, all taxes and royalties, all labour, scaffolding, watering and curing, sundries and T&P etc all complete as per direction of the Engineer -in-charge
1949.79 Sqm
Rate in Words
14 12mm. thick lime plaster (1:2) on brick work including racking out joints, scraping and cleaning the surface and finishing the plaster surface smooth using wooden floats only to proper plumbs and level and making grooves and beads to give required ornamental finish as per drawings including cost of all materials, conveyance, loading and unloading, all taxes and royalties, all labour, scaffolding, watering and curing, sundries and T&P etc all complete as per direction of the Engineer -in-
459.27 Sqm
127
charge
Rate in Words
15 Providing and laying of 100mm thick lime concrete floor on a sub- base of 150mm thick coarse sand and brick ballast of 65mm nominal size. The lime concrete prepared by mixing lime mortar (1lime putty: 1 fine sand: 1 surkhi: 1 khaka) to the brick aggregate of 40mm to 20mm nominal size in a traditional lime chakki. Lime concrete evenly spread on the sub- base and manually beaten with a wooden durmuth with water for expelling air and shrinkage gaps, including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
69.58 Cum
Rate in Words
16 Water proofing for lime terrace deck slab including preparation of the surface : The top surface should be cleaned of all dirt, loose material & kept dry. In case of pot holes / cracks, the same shall be repaired with applying polymer based water proofing compound in two parts to be mixed througly by a slow speed (100 to 150 RPM) Forced action mixture in three coats over the surface. After repairing the surface a layer of galvanized chicken mesh should be laid and finished with 750mm thick lime concrete (1:1:1:1)including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
487.24 Sqm
Rate in Words
17 Fixing terracotta tiles on 25mm thick bed of lime mortar 1:2 (1 lime: 2 sand) including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
504.83 Sqm
Rate in Words
18 Renovation in fine dressed laterite stone in (1:2) lime mortar for moulding work. including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
17.78 Cum
Rate in Words
128
19 Raking out joints of stone masonry surface to the required width and depth, with due care and precaution, by mechanical / manual means, including preparing and cleaning the surface for re-pointing/ refilling of joints, including disposal of rubbish to the dumping ground within 50 metre lead.including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
1300.61 Sqm
Rate in Words
20 Flush pointing over joints of dressed stone work with lime mortar mixing 1:1.5 ratio and gur, methi, gugal etc. are to be mixed as per old traditional practice. including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
1300.61 Sqm
Rate in Words
21 Cleaning the stone surface and removing dirt, dust, bird dropping, grease, oil, algae, fungus, monkey beats, vegetable growth etc., including providing, applying and washing the surface with liquid Ammonia Chemical of 5% solution and other chemical cleaning agent as approved by Archaeological Survey of India/ Engineerin-charge, of approved brand and manufacturer, with the help of required scrubbers and also cleaning with machine operated water jet mixed with desired quantity of fine silica where ever required, without causing any scratching/ damage to the stone surface and finally washing the surface with clean water with the help of pressure jet machine, (The rate is inclusive of all materials & labours involved except scaffolding).including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
1300.61 Sqm
Rate in Words
22 Supplying, fitting and fixing in position well seasoned & dressed Sal wood choukhats in doors free from defects such as dead knots, flows etc. in all floors including two coats of termite proof wood preservatives to Rear surface of frames which is in contact with concrete and masonry surface fitted with 6 nos. of W.I. Clamps and required screws of approved quality including cutting legs to sizes, cutting holes in walls, fixing in CC 1:2:4 including cost, conveyance, royalties and taxes of all materials and cost of all labour, sundries, T & P etc. required for the workall complete as per the directions of Engineer -in-charge.
a) Plane Work 3.38 Cum
Rate in Words
b) Arch Work 0.34 Cum
129
Rate in Words
23 Providing and fixing 38mm thick piasal pannel shutter 38mm style and 22mm to 25 mm thick pannel plank complete with iron fitting fixtures and wooden hinged cleats etc. fitted and fixed in position for doors and windows. Rate shall include cost of all materials, labours, taxes, transportation, loading, unloading etc. complete as per the direction of Engineer -in-charge .
54.47 Sqm
Rate in Words
24 Providing and fixing of plain Jafferi of 35x10mm laths placed 35mm apart including fixing 50mmx12mm beading complete excluding outer frame.etc including all cost of labour, materials, conveyance, taxes, T&P, etc., including all lead and lift all complete as per the directions of Engineer-in-Charge.
20.12 Sqm
Rate in Words
25 Painting and Finishing walls & ceiling with Three coat of white washing with shell lime for new/old work. Including all cost of material, labour, T&P etc all complete as per the direction of Engineer -In-Charge.
2409.06 Sqm
Rate in Words
26 Painting synthetic enamel paint of approved brand and manufacturer of required colour to give an even finish with two or more coats on new/old work of wood and steel over a coat of suitable shade with primer of approved brand and manufacturer's instructions including cost of all materials with taxes and transportation, all labour, scaffolding, sundries, T&P etc. All complete as per the direction of the Engineer -in-charge.
148.49 Sqm
Rate in Words
27 Providing and fixing CI rain water pipe 100 mm dia centrifugually cast iron socketed pipe etc complete including cost of all materials with taxes and transportation, all labour, scaffolding, sundries, T&P etc. All complete as per the direction of the Engineer -in-charge.
76.20 Mtr
Rate in Words
28 Replacing rain water pipe hoppers(funnel) mouth inlet matching with original etc complete including cost of all materials with taxes and transportation, all labour, scaffolding, sundries, T&P etc. All complete as per the direction of the Engineer -in-charge.
9.00 Nos
Rate in Words
29 Earth work in hard soil or gravelly soil within 50m initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm laying in layers not exceeding 0.3m in depth and as per direction of the department.
14.08 Cum
Rate in Words
130
30 Filling in foundation, trenches and plinth with river sand, well watered and compacted in layers of with top surface dressed and leveled to proper gradient including cost of all materials, conveyance, all taxes and royalties, loading and unloading, including cost of all labour, sundries ,T & P etc. complete as per directions of the Engineer -in-charge.
39.03 Cum
Rate in Words
31 Renovation in fine dressed laterite stone in (1:2) lime mortar for plane work after spraying water over the Laterite to clean it from the dust/ mud particles before use as per drawings. including cost, conveyance, all taxes, royalties, loading and unloading of all materials, including cost of all labour, scaffolding, watering and curing, sundries, T&P etc. complete as per the direction of the Engineer-in-charge.
43.68 Cum
Rate in Words
32 Resetting the broken and disintegrated architectural members with lime mortar (1:2).including cost, conveyance, all taxes, royalties, loading and unloading of all materials, including cost of all labour, scaffolding, watering and curing, sundries, T&P etc. complete as per the direction of the Engineer-in-charge.
31.70 Job
Rate in Words
Rate in Words
Electrification Work
I. POINT WIRING :- 1 Surface Wiring to light / fan point in 5/8" or
3/4"dia. good quality PVC pipe with 1.5 sq.mm PVC insulated FRLS Cu.wire (2 run) & 1.0 sq.mm PVC insulated Cu.wire (1 run) for running earth complete with 1 no .6Amp. plate type Modular switch, (Polycarbonate) and G.I box of adequate size including PVC bend, saddle, elbow, etc and other necessary materials & labour.
a) Primery Point controlled by 6A Switch. 60 point
b) Secondary Point controlled by 6A Switch.(Only 3mtr wire in Pipe) 42 point
Rate in Words 2 Supplying and fixing a set of 1 no modular grid plate
mounted 240 volt 6 amp 4 pin universal round/flat pin combined shuttered socket outlet with 240 volt 6 amp control switch, all housed in a 3 module recessed zinc chromate passivated flush metal box including moulded cover plate etc. complete as required.(On switch Board & separate Board)
22 No.
Rate in Words
131
3 Supplying and fixing a set of 1 no modular grid plate mounted 240 volt 6/16 amp 4 pin universal round/flat pin combined shuttered socket outlets each with 240 volt 16 amp control switch, all housed in a single 4 module recessed zinc chromate passivated flush metal box including one moulded cover plate etc. complete as required.
1 No.
Rate in Words
4 Supply and fixing Power Unit consists of 20A 10 KA SP MCB with 20 A Socket for AC (1.0/1.5/2.0Tr) , all housed in a single 4 module recessed zinc chromate passivated MS box including 4 moulded cover plate etc. complete as required. (1.0/1.5/2.0 Tr. Window/Split AC)
Rate Only point
Rate in Word 5 Supplying, fixing & testing of phone point with
suitable 1 module modular boxes & 1 no. of RJ 11 modular socket & complete with all other materials & labour.
1 No.
Rate in Word 6 Supply and fixing of TV antenna Socket outlet
completely providing 1 no. of TV antenna socket & Top , moulded case metal box & plate of adequate size including PVC bend, saddle, elbow, etc. & other necessary materials & labour.
Rate Only point
Rate in Word 7 Surface Wiring to Calling Bell point in 5/8" or
3/4"dia. good quality PVC pipe with 1.0 sq.mm PVC insulated Cu.wire (2 run) complete with 1 no .6Amp. bell push with indicator, 1 module white metal plate & G.I box of adequate size including PVC bend, saddle, elbow, etc and all other necessary materials & labour.
Rate Only point
Rate in Word 8 Circuit or Sub-main wiring in existing 20mm or
25mm dia PVC conduit with following sizes PVC insulated un-sheathed Single Core FRLS Cu. conductor wire of approved make with all other required materials & labour complete as per the direction of Engineer-in-Charge. complete as per the direction of Engineer-in-Charge.
a) (2 x 1.5 + 1 x 1.0) sq.mm copper wire for 6A Light plug Point.. 420 mtr
Rate in Word
b) (2 x 2.5 + 1 x 1.5) sq.mm copper wire for 6/16A Plug & Lighting switch board . 20 mtr
Rate in Word
c) (2 x 4 + 1 x 2.5) sq.mm copper wire for Gyser & AC Point
Rate Only mtr
Rate in Word
132
d) (2 x 6 + 1 x 4) sq.mm copper wire for L+P DB (from Pnel to BDB) 50 mtr
Rate in Word
e) 0.5mm 2 pair telephone wire 25 mtr
Rate in Word
f) RJ-6 Coaxial TV wire Rate Only mtr
Rate in Word 9 Supply & fixing of 1 ph. 8 way, Single pole and
Neutral, sheet steel MCB double door distribution box complete with tinned copper busbar, neutral link, earth bar, din rail, detachable gland plate including 6 nos of 6 to 32 Amps rating, 240Volts, 'C' curve Single pole Miniature Circuit Breaker & 1 no. of 32A,10KA DP MCB, of approved make complete with connections, testing and commissioning including all other materials etc. as required. - FOR L+P DB & External Light DB.
3 No.
Rate in Word
10 Earthing with G.I earth plate electrode of 600 mm x 600 mm x 3 mm thick including accessories and providing masonary enclosure with cover plate having locking arrangement and watering pipe, including 25 x 3 mm size G.I. flat etc. complete with charcole / coke and salt etc. as required.
1 No.
Rate in Word 11
Supply and laying of 6 SWG GI. Wire ISI marked at 0.5mtr below ground level for conductor earth electrode including soldering etc. as required
25 mtr.
Rate in Word 12 Supply, Installation, Testing, and commissioning of
32A,440V DP MCI Unit in Metal one way Enclouser etc including all other materials as required.
Rate Only No.
Rate in Word 13 Supplying and fixing hard drawn PVC recessed
and/or surface conduits including cost of providing saddles, elbow, bend etc for surface conduiting and/or cost of cutting and filling chases for recessed conduiting complete as per specifications, as required and as below.
i) 20mm dia. 150 mtr.
Rate in Word
ii) 25 mm dia. 80 mtr.
Rate in Word
iii) 32 mm dia. Rate Only mtr.
Rate in Word
133
14 Supply, laying, testing and commissioning of following sizes of 1100 volt grade PVC insulated and PVC sheathed aluminium conductor cable directly buried in ground including the cost of trench excavation, sand bedding, brick protection, back filling, route markers and including the cost of dressing to ensure minimum 1D gap between adjacent cables, identifiction tags, etc. complete as per specifications, as required and as below.
a) 2c x 10 sq.mm ,1.1kv grade AYFY/Al. Cable.From Solar Panel to panel board. 70 mtr
Rate in Word
b) 2c x 4 sq.mm ,1.1kv grade AYFY/Al. Cable.From DB to Light point to light point & 1hp Motor Point(External)
Rate Only mtr
Rate in Word
15 Supply , Installation, testing & commisioning of the following Out door Floor mounted panel board of 240V , 50Hz. Power supply made out of 2mm thick for outdoor & 1.6mm thick for indoor CRCA steel duly derusted &Powder Coatedof approved shade over a coat of primer, dust, damp & vermin proof, cubcle fixed on M.S angle channel base, having hinged door and compartmental arrangement for each equipment and suitable size of Aluminium busbar duly sleeved by colour coded sleeves with required ratings / sqinch appropriate current density in the panel running vertically, having provision for cable entry at bottom, providing Earthing point to terminate 25mm x 3mm G.I flat, Nomenclature plate, Enamelled danger board, earthing studs as per specification mentioned below duly factory wired confirming to the relevant ISS.
a) 1 no.40A, 10kA, 415V DP MCB as I/C. b) 63A SPN Al Bus-bar c) 3 nos.32A DP MCB & 2nos 25A DP MCB as O/G.
The Fedeer Box should contain Toggle switch, 1 ph. Indicator, Digital Voltmeter (0-500v) & should be fixed at wall along with other necessay materials and labour.
1 No.
Rate in Word
II. FITTING & FIXTURE :- 1 Supply, Installation, Testing, and commissioning of
Exhaust fan 300mm dia 900mm suitable to work on 230/250 volts, 50HZ complete with mounting frame and louvers including making the hole to suit the size of above fan, making good the damage, connections, with 1.5 sq.mm PVC insulated, copper conductor, single core cable etc as required.(Make : HAVELLS/USHA/KHAITAN).
Rate Omly No.
134
Rate in Word 2 Supply, Installation, Testing, and commissioning of
decorative ceiling fan 1200 mm sweep 230/250 volts, 50HZ complete with suitable, clamp, downrod (as per site requirement), blades, canpoy, rubber, shackle, and connections with 1.5 sq.mm PVC insulated copper conductor cable etc as required.(Make:HAVELLS/USHA/KHAITAN).
12 No.
Rate in Word 3 Supply and fixing of capacitor switching circuit,works
at 120 to 280 volts,Heavy duty, Noiseless 120W step type Fan regulator complete with all other necessary materials & labour.
12 No.
Rate in Word
4 Supply, Installation,Testing & commissioning of Surface mounting 1 x 10W LED tube light fitting with housing chanel of approved make complete with all materials & labour.(Make : Philips,Cat No.-10W840T8IND/Eqv.-CG/Bajaj).
30 No.
Rate in Word 5 Supplying & Fixing of angle / Batten Holder fitting
complete with 1 no of 4 watt LED Lamp of approved make complete with all other necessary fixing materials including termination & labour..(Make : Philips,Cat No.-my VISIOn A60 IND/Eqv.-/CG/Bajaj).
10 No.
Rate in Word 6 Supply, Installation,Testing & commissioning of wall
mounted decorative Spot/Picture light with glass steel body suitable for 8W , CFL fitting of approved make complete with all materials & labour.(Make : Philips,Cat No.-919515610057/Eqv.-Eqv.-/CG/Bajaj).
50 No.
Rate in Word
7 Supply, Installation,Testing & commissioning of Bollard Light with IP 44 integral LED Light 0.8mtr height suitable for 5 x 1W LED fitting i of approved make complete with all materials & labour(Make : Philips,Cat No.-BCP150LED- 7043).
20 No.
Rate in Word
Total
Note:
(1) Item for which no rate or price has been entered in will not be paid for by the
Employer when executed and shall be deemed covered by the other rates and
135
prices in the Bill of Quantities (refer: ITB Clause 13.2 and GCC Clause
43.3).
(2) Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB
Clause 14.1].
(3) Where there is a discrepancy between the rate in figures and words, the rates
in words will govern.
[ITB Clause 27.1(a) ]
4) Where there is a discrepancy between the unit rate and the line item total
resulting from multiplying the unit rate by quantity, the unit rate quoted shall
govern [ITB Clause 27.1 (b)].
136
SECTION 8: FORMS OF SECURITIES
Acceptable forms of securities are annexed. Bidders should not complete the Performance and Advance Payment Security forms at this time. Only the successful Bidder will be required to provide Performance and Advance Payment Securities in accordance with one of the forms, or in a similar form acceptable to the Employer. Annex A: Bid Security (Bank Guarantee) Annex B: Performance Bank Guarantee Annex B1: Performance Bank Guarantee for Unbalanced Items Annex C: Deleted Annex D: Bank Guarantee for Advance Payment
137
Annex A
BID SECURITY (BANK GUARANTEE)
WHEREAS, _______________________ [name of Bidder] (hereinafter called "the Bidder") has submitted his Bid
dated _______________________ [date] for the construction of _____________________________________
[name of Contract] (hereinafter called "the Bid").
KNOW ALL PEOPLE by these presents that We ______________________________ [name of bank] of
____________________________ [name of country] having our registered office at
___________________________________ (hereinafter called "the Bank") are bound unto
______________________________[name of Employer] (hereinafter called "the Employer") in the sum of
___________________1 for which payment well and truly to be made to the said Employer the Bank binds itself, his
successors and assigns by these presents.
SEALED with the Common Seal of the said Bank this _________ day of __________ 19____.
THE CONDITIONS of this obligation are:
(1) If after Bid opening the Bidder withdraws his bid during the period of Bid validity specified in
the Form of Bid;
or
(2) If the Bidder having been notified of the acceptance of his bid by the Employer during the
period of Bid validity:
(a) fails or refuses to execute the Form of Agreement in accordance with the Instructions
to Bidders, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the
Instruction to Bidders; or
(c) does not accept the correction of the Bid Price pursuant to Clause 27;
we undertake to pay to the Employer up to the above amount upon receipt of his first written demand, without the
Employer having to substantiate his demand, provided that in his demand the Employer will note that the amount
claimed by him is due to him owing to the occurrence of one or any of the three conditions, specifying the occurred
condition or conditions.
This Guarantee will remain in force up to and including the date ____________________2 days after the deadline
for submission of Bids as such deadline is stated in the Instructions to Bidders or as it may be extended by the
Employer, notice of which extension(s) to the Bank is hereby waived. Any demand in respect of this guarantee
should reach the Bank not later than the above date.
DATE _______________ SIGNATURE OF THE BANK _________________________
WITNESS ____________ SEAL _______________________________________
_________________________________________________________________
[signature, name, and address]
____________________________
1 The Bidder should insert the amount of the guarantee in words and figures denominated in Indian Rupees.
This figure should be the same as shown in Clause 16.1 of the Instructions to Bidders.
2 45 days after the end of the validity period of the Bid.
138
Annex B/1
PERFORMANCE BANK GUARANTEE
To: ______________________________________________ [name of Employer]
_________________________________________ [address of Employer]
WHEREAS _________________________ [name and address of Contractor] (hereinafter called "the
Contractor") has undertaken, in pursuance of Contract No. _____ dated ________________ to execute
__________________________ [name of Contract and brief description of Works] (hereinafter called "the
Contract");
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you
with a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance with his
obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
Contractor, up to a total of ____________________ [amount of guarantee]1___________________________ [in
words], such sum being payable in the types and proportions of currencies in which the Contract Price is payable,
and we undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums
within the limits of ____________________ [amount of guarantee]1 as aforesaid without your needing to prove or
to show grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before presenting us
with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract or of the
Works to be performed thereunder or of any of the Contract documents which may be made between you and the
Contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any
such change, addition or modification.
This guarantee shall be valid until ……… (i.e.) 28 days from the date of expiry of the Defects Liability
Period.
Signature and seal of the guarantor _____________________________
Name of Bank ____________________________________________
Address ____________________________________________
Date ____________________________________________
__________________
1 An amount shall be inserted by the Guarantor, representing the percentage of the Contract Price specified in
the Contract and denominated in Indian Rupees.
139
Annex B/II
PERFORMANCE BANK GUARANTEE (for unbalanced items)
To: ______________________________________________ [name of Employer]
_________________________________________ [address of Employer]
WHEREAS _________________________ [name and address of Contractor] (hereinafter called "the
Contractor") has undertaken, in pursuance of Contract No. _____ dated ________________ to execute
__________________________ [name of Contract and brief description of Works] (hereinafter called "the
Contract");
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you
with a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance with his
obligations in accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
Contractor, up to a total of ____________________ [amount of guarantee]1___________________________ [in
words], such sum being payable in the types and proportions of currencies in which the Contract Price is payable,
and we undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums
within the limits of ____________________ [amount of guarantee]1 as aforesaid without your needing to prove or
to show grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before presenting us
with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract or of the
Works to be performed thereunder or of any of the Contract documents which may be made between you and the
Contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any
such change, addition or modification.
This guarantee shall be valid until …….. (i.e.) 28 days from the date of issue of the certificate of
completion of works.
Signature and seal of the guarantor _____________________________
Name of Bank ____________________________________________
Address ____________________________________________
Date ____________________________________________
__________________
1 An amount shall be inserted by the Guarantor, representing additional security for unbalanced Bids, if any
and denominated in Indian Rupees.
140
Annex D
BANK GUARANTEE FOR ADVANCE PAYMENT
To: __________________________________________ [name of Employer]
__________________________________________ [address of Employer]
___________________________________________[name of Contract]
Gentlemen:
In accordance with the provisions of the Conditions of Contract, subclause 51.1 ("Advance Payment") of
the above-mentioned Contract, ________________________________ [name and address of Contractor]
(hereinafter called "the Contractor") shall deposit with ________________________ [name of Employer] a bank
guarantee to guarantee his proper and faithful performance under the said Clause of the Contract in an amount of
_____________ [amount of guarantee]1_________________________________ [in words].
We, the ____________________ [bank or financial institution], as instructed by the Contractor, agree
unconditionally and irrevocably to guarantee as primary obligator and not as Surety merely, the payment to
____________________ [name of Employer] on his first demand without whatsoever right of objection on our part
and without his first claim to the Contractor, in the amount not exceeding ____________________ [amount of
guarantee]1 __________________________________ [in words].
We further agree that no change or addition to or other modification of the terms of the Contract or of
Works to be performed thereunder or of any of the Contract documents which may be made between
_____________________ [name of Employer] and the Contractor, shall in any way release us from any liability
under this guarantee, and we hereby waive notice of any such change, addition or modification.
This guarantee shall remain valid and in full effect from the date of the advance payment under the
Contract until _________________________ [name of Employer] receives full repayment of the same amount from
the Contractor.
Yours truly,
Signature and seal: _______________________________
Name of Bank/Financial Institution: _________________
Address: _______________________________________
Date: ____________________
141
SECTION : 9
ENVIRONMENTAL MANAGEMENT PLAN
Environmental Management Plan (EMP) is the key to ensure a safe and clean environment. The
desired results from the environmental management measures proposed may not be obtained without a
management plan to assure its proper implementation & function. The EMP envisages the plans for the
proper implementation of management measures to reduce the adverse impacts arising out of the project
activities.
The Contractor will abide by the environmental, occupational health and safety measures listed in the
Environment Management Plan (EMP) given in the table below during preparation and execution of
Works. Adverse impact/s on the environment caused due to non-adherence of legal and EMP
requirements during preparation and execution of civil works shall be made good at the Contractor’s own
expenses.
Table-1 Environmental Management Plan
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
1. Work Plan for EMP
implementation
The Contractor’s Project Manager shall be
responsible for implementation of EMP
provisions and will coordinate the over-all
implementation of the said plan. Along with
the Work Programme, the Contractor shall
submit a plan including method statement and
timeline about specific actions that will be
taken by him to implement the provisions laid
out in the EMP.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
2. Arrangements for
temporary land
The Contractor as per prevalent rules shall
carry out negotiations with the landowners for
obtaining their consent for temporary use of
lands for workers camp, construction sites etc.
Written permission (no objection certificate)
shall be taken from the Gram Sabha and the
land owner prior to location selection and a
copy shall be submitted to OSDMA for
approval.
It is the responsibility of the Contractor to
clean up the site prior to handling over to the
owner (after construction or completion of the
activity)
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
142
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
3. Construction/Labour
camp – location
Construction camps shall not be proposed
within 500 m from the nearest settlements
to avoid conflicts and stress over the
infrastructure facilities with the local
community.
Camp site shall not be located within 250
m from a water body including village pond
A distance of at least 500 m shall be
maintained from designated/protected
natural habitats (such as National Parks,
Sanctuaries, Biosphere Reserves, Reserve
Forests and Ramsar Sites, if any) and
Coastal Regulation Zone.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
4. Labour Camp
Management
Accommodation:
The Contractor shall follow all relevant
provisions of the Factories Act, 1948 and the
Building and the other Construction Workers
(Regulation of Employment and Conditions of
Service) Act, 1996 for construction and
maintenance of labour camp.
Potable water: The Contractor shall:
a) Supply of sufficient quantity of potable
water (at least 40 lpcd) in labour camp at
suitable and easily accessible places and
regular maintenance of such facilities.
b) If any water storage tank is provided, the
bottom of the tank shall be kept at least
1mt. above the surrounding ground level.
Fuel for Cooking: The Contractor will be
responsible for providing LPG Cylinder/
Kerosene in labour camp to avoid cutting of
trees for fuel wood from the adjoining areas.
Sanitation and sewage system: The
Contractor shall ensure that:
The sewage system for the camp shall be
designed, built and operated in such a
fashion that it should not pollute the ground
water or nearby surface water.
Separate toilets/bathrooms, shall be
arranged for men and women
Adequate water supply is to be provided in
all toilets and urinals
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
143
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
All toilets in workplaces are with dry-earth
system (receptacles) which are to be
cleaned and kept in a strict sanitary
condition
Night soil (human excreta) is to be
disposed off by putting layer of it at the
bottom of a permanent tank prepared for
the purpose and covered with 15 cm. layer
of waste or refuse and then covered with a
layer of earth for a fortnight.
Waste disposal: The Contractor shall provide
garbage bins in the camps and ensure that
these are regularly emptied and disposed off
in a hygienic manner.
Fire Safety: Adequate fire safety precautions
shall be taken and required fire safety
equipment (such as fire extinguishers) shall
be provided by the Contractor.
5. First aid The Contractor shall arrange for –
A readily available first aid unit including
adequate supply of sterilized dressing
materials and appliances as per the
Factories Rules in work zone
Availability of suitable transport at all times
to take injured or sick person(s) to the
nearest hospital
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
6. labour’s Safety The Contractor shall provide:
Protective footwear and protective goggles
to all workers employed on mixing cement,
concrete etc.
Protective goggles and clothing to workers
engaged in stone breaking activities
Earplugs to workers exposed to loud noise,
and workers working in concrete mixing
operation.
Adequate safety measures for workers
during handling of materials at site.
The Contractor shall comply with all the
precautions as required for ensuring the
safety of the workmen as per the International
Labour Organization (ILO) Convention No. 62
as far as those are applicable to this contract.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
144
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
The Contractor shall make sure that during
the construction work all relevant provisions of
the Factories Act, 1948 and the Building and
other Construction Workers (regulation of
Employment and Conditions of Services) Act,
1996 are adhered to.
The Contractor shall not employ any person
below the age of 14 years for any work and
no woman shall be employed on the work of
painting with products containing lead in any
form.
The Contractor shall also ensure that no paint
containing lead or lead products is used
except in the form of paste or readymade
paint. He shall provide facemasks for use to
the workers when paint is applied in the form
of spray or a surface having lead paint is
rubbed and scraped. The Contractor shall
mark ‘no smoking’ in high risk areas. These
shall be reflected in the Construction Safety
Plan to be prepared by the Contractor during
mobilization and shall be approved by
OSDMA.
Material safety data sheet record of fuel and
other inflammable chemicals shall be
maintained at the site.
7. Labour requirements Local people shall be given preference for
unskilled and other jobs created during
construction phase of the project. The
contractor would notify requirement of
unskilled labours in nearby/surrounding
villages. In case local labours are not
interested/available then a certificate/letter
shall be issued by the Panchayat officials to
the Contractors in this regard.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
8. Site Clearance Only ground cover/shrubs that impinge
directly on the permanent works or necessary
temporary works shall be removed with prior
approval from OSDMA. The Contractor, under
any circumstances shall not cut or damage
trees. Trees identified under the project shall
be cut only after receiving clearance from the
State Forest Department or after the receipt of
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
145
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
written permission from OSDMA.
9. Preservation of top
soil
The topsoil from all areas of cutting and all
areas to be permanently covered shall be
stripped to a specified depth of 15 cm and
stored in stockpiles. A portion of the
temporarily acquired area shall be earmarked
for storing topsoil. The following precautionary
measures shall be taken to preserve them till
they are used:
(a) Stockpile shall be designed such that the
slope does not exceed 1:2 (vertical to
horizontal), and height of the pile is restricted
to 2 m. To retain soil and to allow percolation
of water, the edges of the pile shall be
protected by silt fencing
(b) Stockpiles shall not be surcharged or
otherwise loaded and multiple handling shall
be kept to a minimum to ensure that no
compaction shall occur.
The top soil shall be reinstated in the Tourist
Guide Centre compound after the construction
is over. Residual topsoil, if there is any shall
be utilized for the plantation.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
10. Construction
vehicles, equipment
and machinery
All vehicles, equipment and machinery to be
procured and brought to site for construction
shall confirm to the relevant Bureau of India
Standard (BIS) norms and the manufacturer’s
specifications. The discharge standards
promulgated under the Environment
Protection Act, 1986 shall be strictly adhered
to. Noise limits for construction equipment to
be procured shall not exceed the value
specified in the Environment (Protection)
Rules, 1986.
The equipment proposed to be used for
construction and installed close to
waterway/streams, must be checked and
certified fit, especially with respect to the
potential leakage of oil and grease.
The inspection should verify that:
Equipment is clean (free of mud, dirt and
oil)
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
146
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
Equipment is in good working order.
A drip pan is available for equipment that
shall be stored on site.
Contractor has a spill kit
Operator is trained on the refuelling,
maintenance and emergency spill
procedures.
Adequate inspections shall be conducted
during the construction period.
11. Quarry Operations The Contractor shall procure material from
quarries that have been approved/licensed
by the Orissa State Govt. A copy of such an
approval shall be submitted to the OSDMA
prior to procure the material.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
12. Construction water Water for construction and for use at
construction camps (including labour camps)
is to be extracted with prior written
permission of (a) the individual owner, in
case the source is private well/tube well; (b)
Gram Panchayat in case the source belongs
to community; and (c) Irrigation Department
in case the source is an irrigation canal or a
river.
The Contractor shall take all precaution to
minimize the wastage of water in the
construction process.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
13. Air pollution The Contractor shall take every precaution
(water sprinkling etc.) to reduce the level of
fugitive dust generating from construction
site.
Water shall be sprinkled at least twice
during dry day on haulage roads passing
through or near settlements (including at
least 100 m before the settlement).
Wind barriers or screens shall be provided
in the downwind direction at air pollution
causing sources like plant sites and fine
material storage stock yards.
Truck carrying construction materials will
be duly covered to avoid spilling.
The Contractor shall ensure that all
vehicles, equipments and machineries
used for construction are regularly
maintained and confirm that pollution
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
147
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
emission levels comply with the relevant
requirements of State Pollution Control
Board (SPCB).
The Contractor shall submit PUC
certificates for all vehicles/ equipment/
machinery used for the project and
maintain a record of the same during the
contract period.
14. Noise pollution The Contractor shall confirm
the following:
All plants and equipments used in
construction shall strictly conform to the
CPCB noise standards.
All vehicles and equipment used in
construction shall be fitted with exhaust
silencers.
Servicing of all construction vehicles and
machinery shall be done regularly and
during routine servicing operations, the
effectiveness of exhaust silencers shall be
checked and if found defective shall be
replaced.
At the construction sites within 150 m of the
nearest habitation, noisy construction work
shall be stopped during the night time
between 9.00 pm to 6.00 am.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
15. Water Pollution Water pollution from construction
wastes
The Contractor will take all precautionary
measures to prevent the wastewater
generated during construction from
entering into streams, water bodies or the
irrigation system. He will avoid construction
works close to streams or water bodies
during monsoon.
All measures (including provision of
temporary silt fencing to control sediment
run-off) required for avoiding adverse
impacts to water bodies (such as ponds,
streams, canals and rivers), water sources
(such as hand pumps and wells) and
adjacent farmland shall be undertaken by
the Contractor.
Water pollution from fuel and lubricants
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
148
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
The Contractor will ensure that all
construction vehicle parking location,
fuel/lubricants storage sites, vehicle,
machinery and equipment maintenance
sites are located at least 100 m away from
any water body. The Contractor will also
ensure that spillage of fuels and lubricants
do not contaminate the ground.
If fuel storage and re-fuelling areas are
located on agricultural land or areas
supporting vegetation, the top soil will be
stripped, stockpiled and returned after
cessation of such activities.
Storage of materials like fuel, chemicals
and cement shall be done in a manner
(with impervious layer on bottom and a
covered shed on top) that does not
contaminate land and ground/surface
water.
16. Solid Waste Solid waste from the project during
construction will be mainly domestic scraps &
wastes from the construction camp and
construction spoils from construction sites.
• The small amount of construction debris
will be disposed of in suitable pre-identified
or existing dumping areas in tune with the
local condition to avoid land degradation &
water logging due to indiscriminate
dumping.
• Dumping areas will be biologically
reclaimed through top soil cover.
• Regular inspection of haul roads,
construction site & camp will be carried out
to ensure regular and timely removal of
construction debris to the dumping sites.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
17. Drainage & Flood
Control
The Contractor will ensure that construction
materials like earth, stone are disposed off
so as not to block the flow of water of any
watercourse and cross drainage channels.
Contractor Wild Life ( Mangrove
Forest Division),
Bhubaneswar
18. Restoration and
Rehabilitation of
Sites
All work sites and areas under temporary use
(including construction and labour camps,
plant sites, haul roads and borrow areas) shall
Contractor Wild Life ( Mangrove
Forest Division),
149
Sl. Activity Management Measures Responsibility
No. Planning &
Execution
Supervision
be restored/ rehabilitated to a better condition
(if not at least to its original condition) and to
the satisfaction of land owner upon completion
of construction work by the Contractor.
Completion of work will also include
completion of rehabilitation and clean-up of
the work sites including camps, plants, in and
around the construction site; disposal of
debris/construction wastes at pre-approved
locations and; restoration of borrow areas and
other sites/locations used for material
sourcing.
Bhubaneswar
19. Liabilities Any liability arising out of Contractor’s
agreement with landowners/ local
people/gram panchayat (including those
related to temporary use of land, water
extraction and disposal of debris) shall be
settled by the Contractor.
GUIDELINES FOR REHABILITATION OF BORROW/ QUARRY AREAS
General: The contractor is required to take quarry material only from licensed quarries. In the
case of existing quarries the contractor through the Engineer’s representative will have to ensure
that all actions in these quarries are in accordance with the environmentally sound and acceptable
manner.
In case the contractor establishes additional quarries and dedicated crusher plants, the
contractor has to ensure that all actions are in accordance with the environmental requirements.
In the case of borrow areas, Contractor need to specify a detailed arrangement including the
agreement with the owner of the land. The Contractor must comply with provisions of taxes,
levies, royalties etc. of the State.
Management Plan for Borrow / Quarry Areas
The contractor needs to develop a Borrow and Quarry area management plan providing at
least the following details:
Name, location and ownership of the borrow or quarry area;
Existing land use of the area (including the access road to be developed) to be quarried;
Approximate quantity of the material available;
The number of trees and the species of the trees to be removed;
Total area involved;
150
Arrangement with the owner;
Whether purchased or leased;
A statement from the owner saying the actual arrangement (not in terms of exact monitory
compensation) with him is agreeable for him;
The exact restoration plan indicating the number of trees that will be planted;
The action plan for leveling and landscaping in order to bring the area in conformity to the neighboring
land uses; and
The access roads rehabilitation.
Compliance certificate of tax, levy, royalty etc. provisions.
Rehabilitation of Borrow/ Quarry Areas
The objective of the rehabilitation programme is to reinstate the quarry /borrow pit sites to a safe and
secure area, which the general public should be able to safely enter and enjoy. Securing borrow pits
/quarry sites in a stable condition should be a fundamental requirement of the rehabilitation process. This
could be achieved by filling the quarry/ borrow pit with suitable materials to approximately the access
road level.
Quarries and borrow pits may be backfilled with rejected construction wastes and will be given a
vegetative cover. If this is not possible, then excavation slopes will be smoothed and depression will be
filled in such a way that it looks more or less like the original ground surface.
During works execution, the contractor shall ensure preservation of trees during piling of materials;
spreading of stripping material to facilitate water percolation and allow natural vegetation growth; re-
establishment of previous natural drainage flows; improvement of site appearance; digging of ditches to
collect runoff; and maintenance of roadways where a pit or quarry is declared useable water source for
livestock or people nearby. Once the works are completed, the contractor shall restore the environment
his own expense around the work site to its original splits.
151
SECTION : 10 COASTAL REGULATORY ZONE ACT
1. No change in scope of the work shall be made without prior approval of Orissa State Coastal
Zone Management Authority (OSCZMA).
2. It shall be ensured that the local environment is not adversely affected in any manner during the
construction phase and subsequently.
3. No mangroves should be affected/ destroyed during the construction and operation of the
project.
4. There should be no disturbance to the sea turtle habitats and breeding and spawning grounds of
fish.
5. The dredging material from the project should not be dumped in any part of the eco-sensitive
area.
6. Concreting and other fabrication jobs, if any, should be undertaken in yard on the land located
sufficiently away from the high tide line as well as CRZ area and the transfer of materials to the
site should be through a pre-decided corridor. Similarly, the movement of construction barges,
machinery etc. should be restricted the pre-decided operational area.
7. Temporary colonies for the labour work force etc. should be established sufficiently away from
the high water line and proper sanitation including toilets and bathrooms should be provided to
the inhabitants to prevent abuse of the inter-tidal area.
8. It should be ensured that inter-tidal and super tidal areas are restored to their original contours
after the construction is completed. General clean up along the corridor, adjacent areas and
inter-tidal regions should be taken up and extraneous materials such as drums, sacks, metal
scrap, ropes, excess sediment, make shift huts and cabins should be cleared from the site.
9. The effluents shall be discharged only after proper treatment. Sewage treatment facility should
be provided in accordance with the CRZ Notification, 1991.
10. Necessary precaution and design criteria should be used for construction and operation keeping
in view the possible impact of cyclone / tsunami on the structures.
11. A green belt shall be developed using native tree species/plants which should preferably be
resistant to high wind speed.
12. No ground water shall be tapped for the project within the coastal regulation zone.
13. The total covered area on all floors shall not exceed 33 percent of the plot size, the overall
height of construction shall not exceed 9 meters and should be strictly in accordance with the
provisions of CRZ notification, 1991.
152
14. The project proponent shall obtain necessary forest clearance if any from the competent
authorities prior to construction of the Food Court.
15. To prevent discharge of wastes into the marine environment, adequate system for collection,
treatment and disposal of wastes should be followed as per the standards of State Pollution
Control Board.
General Conditions :
1. Adequate provision for infrastructure facilities including water supply, fuel and sanitation must
be ensured for construction workers during the construction phase of the project to avoid any
damage to the environment.
2. Appropriate measures must be taken while undertaking digging activities to avoid any likely
degradation of water quality.
3. Adequate precautions should be taken during transportation of the construction material so
that it does not affect the environment adversely.
4. Borrow pits for each quarry sites for road construction material and dump sites must be
identified keeping in view the following
No excavation or dumping or dumping on private property be carried out without
written consent of the owner.
No excavation or dumping shall be allowed on wetlands, forest areas or other
ecologically valuable or sensitive locations.
Excavation work should be done in close consultation with the Soil Conservation and
Watershed development Agencies working in the area
Construction spoils including bituminous material and other hazardous materials must
not be allowed to contaminate water courses and the dump sites for such materials
must be secured so that they should not leach into the ground water.
5. The construction material should be obtained only from approved quarries. In case new quarries
are to be opened, specific approvals from the competent authority should be obtained in this
regard.
6. The borrow pits and other scars created during the road construction should be properly leveled
and reclaimed.
7. Roof –top rain water harvesting should be implemented.
8. The project proponent will set up separate environment management cell for effective
implementation of the stipulated environmental safeguards under the supervision of a Senior
Executive.
153
9. In the event of a change in project profile or change in the implementation agency, a fresh
reference shall be made to the OSCZMA.
10. A copy of clearance letter will be marked to concerned Panchayat/local NGO, if any, from whom
recommendation/clearance has been received while processing the proposal.
11. The OSCZMA or any other competent authority may alter/modify the above conditions or
stipulate any further condition in the interest of environment protection.
12. Failure to comply with any of the conditions mentioned above may result in withdrawal of this
clearance and attract action under the relevant provisions of the Environment (Protection) Act,
1986.
13. Full support shall be extended to the officers of this Forest & Environment Department by the
project proponent during inspection of the project for monitoring purposes by furnishing full
details and action plan including action taken reports in respect of mitigation measures and
other environmental protection activities.
14. A six monthly monitoring report shall be submitted by the project proponent to the OSCZMA
regarding the implementation of the stipulated conditions.
15. The project proponent shall inform the OSCZMA, the date of financial closure and final approval
of the project by the concerned authorities and the date of start of land development work.
16. The information that the project has been accorded environmental clearance shall be publicized
in the local area by the project proponent by way of advertisement in at least two newspapers
one of which is in vernacular language having wide circulation in the area, besides display on
the notice board of the local GP.
17. The above conditions will be enforced inter-alia, under the provisions of the Water
(Prevention & Control of Pollution) Act, 1974, the Air (Prevention & Control of Pollution) Act,
1981, the Environment (Protection) Act, 1986 and the Public Liability Insurance Act, 1991 along
with their amendments and rules made there under and also any other orders passed by the
Hon’ble Supreme court of India/High court of Orissa and any other court of Law relating to the
subject matter.