59
Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast James Vermeulen, PQS, LEED AP – Co CEO Blair Tennant, LEED AP – Project Manager www.vermeulens.com Toronto Boston Dallas Los Angeles

Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast

Embed Size (px)

DESCRIPTION

Beyond Estimation TM The Cost Reconciliation Tracker TM Construction Cost Forecast James Vermeulen, PQS, LEED AP – Co CEO Blair Tennant, LEED AP – Project Manager. Toronto Boston Dallas Los Angeles. www.vermeulens.com. - PowerPoint PPT Presentation

Citation preview

Page 1: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

Beyond Estimation TM

The Cost Reconciliation Tracker TM

Construction Cost Forecast

James Vermeulen, PQS, LEED AP – Co CEO

Blair Tennant, LEED AP – Project Manager

www.vermeulens.com

Toronto Boston Dallas Los Angeles

Page 2: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

2

Vermeulens is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request.

This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Page 3: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

3

Cost Reconciliation Tracker Present trends in median trade costs from January 2008 - Current

Quantify current cost reductions and provide future cost projections.

Construction Cost Inflation Understand historic trends in construction cost inflation

Where we were. Where we are. Where we are going.

Cost Drivers Examine the cost impact of: Volume, Commodities, Labor & Profit Margin

Economic Drivers Examine the cost impact of: Commodity Pricing, Equity Markets, Exchange Rates & Employment

LEARNING OBJECTIVES

Page 4: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

Where we were

4

Page 5: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

5

Page 6: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

6

Page 7: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

7

High/Low -4.1%

Low / Current +3.7%

Growth RatesQ3 09 +1.6%Q4 09 +4.9%Q1 10 +3.7%Q2 10 +1.7%Q3 10 +2.5%

Page 8: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

Cost Reconciliation Tracker TM

8

Page 9: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

9

Code Group VCC CM CM-VCC VCC CM CM-VCC

01 Allowances $1,156,805 $2,422,380 $1,265,575 $2,651,790 $2,672,730 $20,940

02 Site Work $2,636,810 $3,773,428 $1,136,618 $2,918,155 $2,882,279 ($35,876)

03 Concrete $5,840,270 $5,065,081 ($775,190) $5,065,361 $5,065,081 ($280)

04 Masonry $1,547,241 $1,767,385 $220,144 $1,615,526 $1,609,395 ($6,130)

05 Metals $17,945,452 $17,804,383 ($141,069) $15,675,089 $15,577,004 ($98,085)

06 Wood/Plastic $3,172,732 $3,831,671 $658,939 $3,694,276 $3,600,999 ($93,277)

07 Thermal/Moisture Protection $2,903,951 $3,046,873 $142,922 $3,099,398 $3,086,080 ($13,319)

08 Doors/Windows $17,219,666 $15,756,579 ($1,463,087) $15,214,307 $15,299,926 $85,619

09 Finishes $9,635,770 $9,399,224 ($236,546) $10,135,975 $10,137,758 $1,782

10 Specialties $1,335,983 $1,163,012 ($172,971) $1,410,825 $1,418,709 $7,884

11 Equipment $1,127,700 $1,852,358 $724,658 $1,692,000 $1,693,414 $1,414

12 Furnishings $784,846 $302,393 ($482,453) $559,342 $573,596 $14,255

13 Special Construction $300,000 $148,575 ($151,425) $150,000 $148,575 ($1,425)

14 Conveying Systems $4,858,875 $7,212,645 $2,353,770 $5,963,888 $5,993,138 $29,250

15 Mechanical $28,949,381 $35,232,816 $6,283,436 $29,127,187 $29,493,221 $366,034

16 Electrical $15,451,608 $16,700,277 $1,248,669 $16,476,313 $16,451,613 ($24,700)

17 Permits & Fees $19,075,543 $20,452,111 $1,376,568 $20,043,336 $20,051,467 $8,130

18 Contingencies $16,841,472 $14,102,030 ($2,739,443) $15,684,472 $15,697,176 $12,704

19 Enabling $22,704,456 $22,704,458 $2 $22,704,458 $22,704,458 $0

20 Total Construction Costs $173,488,558 $182,737,674 $9,249,116 $173,881,696 $174,156,616 $274,920

Page 10: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

10

115 Projects

Page 11: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

STRUCTURAL STEEL ($/TON)

11

$2,940 - $3,300 $3,260- $3,565

+9%

$180 Deviation

$3,120 Average

$150 Deviation

$3,410 Average

$2,785- $3,140

-13%

$2,965 Average

$2,410- $2,855

-11%

$2,635 Average

$2,385- $2,723

-1%

$2,610Average

$2,285- $2,530

$2,408Average

-9%

-29%

Page 12: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

CONCRETE SLAB ON DECK ($/SF)

12

$5.1 - $6.1

+2%

$5.1 - $6.3

-14%

$4.6 - $5.3

-8%

$4.3 - $4.8 $4.3 - $4.9

+3%

$4.5 - $5.3

-21%

+5%

Page 13: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

MASONRY - CMU ($/SF)

13

$16.0 - $17.9 $15.6 - $17.7 $14.7 - $16.7 $14.8 - $15.6 $12.8- $14.9 $15.8- $17.7

-18%

Page 14: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

ROOFING MEMBRANE ($/SF)

14

$13.2 - $16.5 $14.0 - $17.0 $14.8 - $16.9 $13.4 - $14.8

-11%

$12.7 - $15.0

-2% +8%

$13.2 - $15.1

+2%

-13%

Page 15: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

CURTAINWALL ($/SF)

15

$99- $118

+4%

$95- $114 $84- $101

-15%

$84- $96

-3%

$76- $88

-8%

$86- $96

+12%

-24%

Page 16: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

DRYWALL PARTITIONS ($/SF)

16

$7.1 - $8.2 $7.1- $7.9

-1%

$6.4- $7.4

-9%

$5.7- $6.8

-9%

$6.5- $7.2 +10%

$6.1- $6.8

-7%

-18%

Page 17: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

ELEVATORS ($/STOP)

17

$31,500 - $37,000

$58,000 - $70,000

Page 18: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

PLUMBING – BRANCH PIPE ($/LF)

18

$26- $29 $28 - $30

+4%

$26 - $29

-4%

$25 - $27

-5%

$24 - $25

-7%

$24 - $26

+4%

-16%

Page 19: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

DUCTWORK ($/LBS)

19

$7.4 - $8.4 $7.8 - $8.5

+3%

$7.0 - $7.9

-8%

$6.8 - $7.5

-4%

$7.1- $7.4

+1%

$7.0- $7.4

-1%

-12%

Page 20: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

CONTROLS ($/PT)

20

$1,130 - $1,270

+3%

$1,110 - $1,220 $1,000 - $1,110

-12%

$1,000 - $1,090

-1%

$970 - $1,050

-1%

$951 - $1,040

-5%

-17%

Page 21: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

ELECTRICAL FEEDER ($/LF)

21

$127 - $141

+6%

$114 - $139 $97 - $114

-21%

$93 - $112

-3%

$100 - $114

+4%

$96 - $105

-6%

-25%

Page 22: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

GENERAL REQUIREMENTS \ CONDITIONS

22

7.7% - 11.5% 7.4% - 11.2%

-3%

8.3% - 10.9%

+4%

8.3% - 9.7%

-6%

8.2% - 9.6%

-1%

8.4% - 11.3%

+12%

-10%

Page 23: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

GENERAL REQUIREMENTS \ CONDITIONS

23

1.4%

1.1%1.3% 1.3%

1.5%

1.0%

0.6%

Page 24: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

CONTRACTOR’S FEE (%DIRECTS)

24

2.8% - 3.4% 2.8% - 3.5%

+2%

2.6% - 3.3%

-6%

2.6% - 3.1%

-3%

2.4% - 3.1%

-4%

2.0% - 2.7%

-15%

-25%

Page 25: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

ESCALATION CONTINGENCY (% DIRECTS)

25

6% - 8%

Page 26: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

COST RECONCILIATION

TRACKER SUMMARY

26

Page 27: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

27

TRADE 2008 PEAK – BOTTOM 2010

Concrete -21%

Masonry -18%

Steel -29%

Roofing -13%

Curtainwall -24%

Drywall -18%

Plumbing -16%

Ductwork -12%

Controls -17%

Feeder -25%

GC’s & GR’s -10%

Contractor’s Fee -25%

TRADE SUMMARY

Page 28: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

28

TYPICAL INSTITUTIONAL PROJECT – DIRECT TRADE COST

CONSTRUCTION COST IMPACT

Assumes trade-weighted average of individual percentage trade reduction

Peak 2008 – Bottom 2010

-14%

Page 29: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

WHITING-TURNER CONTRACTING

29

Peak 2008 – Q3 2010

-13.2%

Page 30: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

30

BUDGET EXAMPLE

Q3 2008 - $100M

14% Escalation Q2 2010 - $114M

14% Market AdjQ2 2010 - $86M5%

Bids @

Cost

Q2 2010 - $82M

-25%

-5%

-28%

Page 31: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

31

Recession Bottom Growth

Design Contingency

Preliminary Design 10% - 15% same same

Schematic Design 6% - 9% same same

Design Development 3% - 6% same same

Contract Documents 0% - 3% same same

Construction Contingency 3% - 5% same same

Escalation Contingency negative zero 4% - 8%

Bidding Contingency -5% to 0% -5% to 0% 0% to +5%

Project Contingency (Owner) 15% - 10% 15% - 10% 10% - 5%

CONTINGENCY

Page 32: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

WHEN WILL

THE

WINDOW CLOSE ?

32

Page 33: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

33

COST DRIVERS

Volume

Commodity Pricing

Labor Productivity

Profit Margins

Page 34: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

34

• MaterialRaw Goods

• Markup Overhead, Equipment, Profit: (Manufacturer & Contractor)

STRUCTURAL STEEL PRICING

Page 35: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

35

US DOLLAR RISK HEDGE

High/Low -26%

Low / Mar 09 +18%

Mar09/Current -11%

Page 36: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

36

US DOLLAR RISK HEDGE

Low / High +123%

High / Mar 09 -58%

Mar09/Current +91%

Page 37: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

37

Page 38: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

38

US DOLLAR IMPACT ON COMMODITIES

Low/High +164%

High/ Mar 09 -56%

Mar09/Current +57%

Page 39: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

39

Page 40: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

40

Page 41: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

41

Page 42: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

42

Page 43: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

43

CONSTRUCTION EMPLOYMENT

High/Low Total – 6% Construction – 28%

Low/Current Total + 1% Construction +0.3%

Page 44: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

44

$140B Stimulus Package

CONSTRUCTION VOLUME

High/Low

Total –35% Infra –11% Res –66% Non Res –37%

Low/Current

Total +2% Infra +11% Res +6% Non Res +0.5%

Page 45: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

45

Page 46: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

46

CONSTRUCTION COST INDEX

Trendline Avg

W-T 3.5%ENR 3.0%Gov 2.6%

% Decline(Peak – Current)

W-T -11.6%Gov -4.9%ENR +2.5%

Page 47: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

47

Page 48: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

48

Page 49: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

49

Page 50: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

50

Page 51: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

51

Page 52: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

52

Page 53: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

53

Indicator Bottom Increase •Equities March 09 +91%

•Commodities March 09 +57%

•GDP Q2 09 + 4%

•Employment Dec 09 + 1 %

•Non Res Volume Oct 10 +0.5%

Economic Summary

Page 54: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

54

COST DRIVERS

Volume

Commodity Pricing

Labor Productivity

Profit Margins

2009 2010 2011

Page 55: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

55

Page 56: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

56

•Peak 2008 to Bottom 2010: -14.0%

•1st Half 2011: + 2.0% + 1.0% + 0.0%•2nd Half 2011: + 2.5% + 1.5% + 0.5%

Cost Outlook

High

VolumeModerate

Volume Low

Volume

Page 57: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

57

1. Major Economic Indicators have bottomed.

2. Construction Prices are bottoming.

3. Cost Escalation must be factored into construction budgets moving forward.

Summary

Page 58: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

58

•CM Selection Must Have Full Estimate and Schedules

•Negotiate GMP Post Bid Buyout

•Continue Design & Preconstruction

•Watch Equity Markets for Sustained Rebound

Recommendations

Page 59: Beyond Estimation  TM The Cost Reconciliation Tracker  TM Construction Cost Forecast

59

•Track Record

•Project Volume & Benchmarking

•Consensus Approach in Reconciliation

•The Reconciliation Tracker

•Conceptual Estimating

•Brand

•Trusted Advisor

Why Vermeulens