Best Upgrade Practices for AdoptingOracle E-Business suite - R12.1.3

Whitepaper

Published on: January 2014 | Author: Ravindra Kulkarni | Email Address: [email protected]

Page 2: Best upgrade practices for adopting Oracle E-Business ... · Best upgrade practices for adopting Oracle E-Business suite to R12.1.3 Table of ... view of information ... reviewed R12

WhitepaperBest upgrade practices for adopting Oracle E-Business suite to R12.1.3

Table of Contents

1. Introduction

2. Why Upgrade?

3. The Upgrade Phases

4. Oracle Upgrade Best Practices

4.1. Pre Upgrade Best Practices

4.2. Post Upgrade Best Practices

5. Conclusion

2© Hexaware Technologies. All rights reserved. www.hexaware.com

03

03

03

04

04

05

05

Page 3: Best upgrade practices for adopting Oracle E-Business ... · Best upgrade practices for adopting Oracle E-Business suite to R12.1.3 Table of ... view of information ... reviewed R12

Introduction

This white paper describes major upgrade areas to consider in determining whether an upgrade is appropriate for your Organization. It also

offers practical advice from Oracle support, consulting and development Organization on how doing an R12 upgrade. This white paper tells

you “things you need to do” before and after R12 upgrade project.

Why Upgrade?

Business owners have realized that their key enterprise applications must be upgraded regularly to benefit from many compelling reasons

such as:

● Unlocking new mature functionalities to keep your organization well positioned to meet business objectives.

● Staying current with the highest and latest levels of the product support. The extended support to R11.5.10.2 is ending on December,

2014.

● Enables you with best performance and usage of enhanced features like functional capabilities, technical infrastructure etc. which

enables you to increase application’s efficiency for your business.

[Refer Oracle Applications Documentation Resources Release 12 Note 394692.1] For more detailed information of finance and procurement

upgrade impacts, see Oracle Financials and Oracle Procurement Functional Upgrade Guide: Release 11i to Release 12.

An upgrade is similar to implementation; however upgrade can be more efficient than implementation as it leverages earlier implementation

efforts and business processes. Also, the upgrade can be executed within the existing change management system by your organization.

Below graphic presents the standard upgrade phases at a high level:

3

Whitepaper

© Hexaware Technologies. All rights reserved. www.hexaware.com

Best upgrade practices for adopting Oracle E-Business suite to R12.1.3

The Upgrade Phases

Ap

plicati

on

Vers

ion

11.5

.10.2

Curr

ent E

nvironm

ent

Stu

dy

Syste

m R

evie

w

Data

base U

pgra

de

Applic

ation U

pgra

de

Applic

ation P

atc

hin

g

Function T

esting

User

Tra

inin

g

UA

T

Pro

duction M

igra

tion

and G

o L

ive

Post P

roduction S

upport

Pla

nnin

g

Planning &

InitiationAnalysis Upgrade UAT Go Live

PostProduction

Support

Page 4: Best upgrade practices for adopting Oracle E-Business ... · Best upgrade practices for adopting Oracle E-Business suite to R12.1.3 Table of ... view of information ... reviewed R12

4

Whitepaper

© Hexaware Technologies. All rights reserved. www.hexaware.com

Best upgrade practices for adopting Oracle E-Business suite to R12.1.3

This section describes R12 best practices for pre and post upgrade and testing activities.

Pre Upgrade Best Practices

Oracle Upgrade Best Practices

● Evaluation: Before initiating upgrade, it is important to thoroughly evaluate the new release to confirm the capabilities and enhance-

ments which will provide expected benefits and justified returns from the upgrade to the business. Information on release notes can

help in determining what exactly will change in the newly upgraded system along with the new features. [Refer Oracle note 461705.1

which provide a consolidated view of information you may need for an upgrade project]

● Planning: A successful upgrade begins with a crystal clear definition of project scope and detailed project plan. Though R12 has new

significant changes in data model and functionality specifically in financial modules, defining realistic schedule for upgrade project

considering implemented modules in R11, integration with other third party systems and respective development, expected new

modules to be introduced in R12, end user training and their confidence to go with R12, any change in terms of hardware or operating

system or merging multiple instances into one single global instance should be considered while planning the project scope and

timelines. You may separate such activities as a separate project than upgrade to minimize the risk. Though standard upgrade moves

you from R11 to R12 with same setups and functionality with additional and default functionality about tax, sub-ledger accounting, still

you have option to implement new functionality at desired time.

● Data validation approach: A minimal upgrade requires some functional setups which come by default like Trading Community

Architecture (TCA) for customer/ supplier data, payments and E-business tax. If you have inconsistencies within R11 setups, then you

should resolve them before R12 upgrade. You can run “Accounting Setup Manager Pre-upgrade Diagnostics” report to view R11 setup

for financial modules, through you can identify setups that are potentially problematic. Also, results of standard reports from each

module would also help to know successful upgrade – the reports have to run before and after upgrade as well.

● Technical Iterations: Executing technical upgrade is critical initial phase. A best approach would suggest at least three iterations. The

first iteration may be taken up to identify hurdles/ issues throughout upgrade (including functional/ technical configurations and testing

activities). The second would be taken up to minimize issues which are identified within first iteration and further UAT activities. The

third iteration would be taken up to identify exact down time (including all end to end activities) and help for Production upgrade.

Capturing regular backups throughout the upgrade process would be enabling you to restore the environment to a specific point rather

than re-initiating the entire process.

● Fall-back planning: Approaching towards the production stage upgrade, fallback planning is most essential and important. You can

have multiple modes of backup which are capable enough to restore immediately and enable end users to work on. One round of

resting on restoring the environment is recommended.

● Pre-requisites: You can start the upgrade post completing month end activities, clearing all interfaces and posting all journals to

General Ledger, closing all sub-ledger/ ledger periods. All such activities (including DBA, functional and technical) have to be sequen-

tially listed down with priority, navigation, activity owner, specific notes (if any) and respective estimated time against the activity. Many

of such activities can be done in parallel mode to minimize upgrade time. Closure of major service requests prior to upgrade is highly

required. Allocation to appropriate owners to activities and involvement of respective business users to their activities is most important

for this project. Running of key reports before and after upgrade is one of the important activities in terms of data verification and recon-

ciliation.

● Cook-Book concept: Cook-Book includes end to end activities along with various phases which are sequentially listed down. Each

activity should have respective owner, activity duration, activity sequence, activity mode (parallel/ standalone). Building and maintain-

ing ‘Cook-Book’ is a proven concept which requires experience to minimize cutover time, avoid last minute surprises and a very

successful upgrade project.

Page 5: Best upgrade practices for adopting Oracle E-Business ... · Best upgrade practices for adopting Oracle E-Business suite to R12.1.3 Table of ... view of information ... reviewed R12

5

Whitepaper

© Hexaware Technologies. All rights reserved. www.hexaware.com

Best upgrade practices for adopting Oracle E-Business suite to R12.1.3

A detailed, well planned and coordinated production upgrade is important in successful upgrade and minimizing risk factors.

Below is high level pictorial view of Cook-Book:

Post Upgrade Best Practices

Conclusion

● End User Training: Organize key user training and make them familiar to R12 environment, new features and functionalities. Prepare

training documentation and update user guide to reflect changes in both functionality and business processes.

At cutover, the final “Production” upgrade pass is completed.

● Smoke Testing: Formulate robust testing strategy with required testing rounds, team involvement with overall performing to see an

end to end testing of all business scenarios. In addition to CRP testing to validate setups, ensure that you do full functional testing with

business users. Testing should be guided by detailed test scripts in advance along with enough time to complete end to end scenarios.

● Data Reconciliation: Running Oracle’s standard reporting from each module (based on each and every operating unit implemented)

and mapping the outputs with R11 instance reports is the standard approach of data reconciliation. The majority of reports are from

financial modules which need to run and validate.

● Hand Hold Period: Keep your key project members in place at least for successful closure of the first financial period within the new

R12 environment to increase end user confidence level. Consider doing a mock period closing at least 5 days before the actual close.

The team can monitor the R12 environment, logging the service requests (if required). Re-examine user roles and responsibilities due

to change in business processes introduced in R12. For example, global process owners reviewed R12 process changes with

business users and redefined roles and responsibilities accordingly.

Oracle R12 has been adopted by many enterprises across the globe and is well accepted as the most reliable, stable from the family of

Oracle EBS suite. Thus, it is crucial for existing 11i users or may be older versions to consider future business process alignment, scalabil-

ity and lowest TCO while mapping to Oracle R12 and eventually Fusion Application.

Oracle is committed to supporting customer investments in technology platforms for applications as well as certified infrastructure

products (hardware, operating systems, databases and middleware). Details can be accessed at the following location:

http://www.oracle.com/us/support/lifetime-support/index.html

Page 6: Best upgrade practices for adopting Oracle E-Business ... · Best upgrade practices for adopting Oracle E-Business suite to R12.1.3 Table of ... view of information ... reviewed R12

6

Whitepaper

© Hexaware Technologies. All rights reserved. www.hexaware.com

Best upgrade practices for adopting Oracle E-Business suite to R12.1.3

Hexaware is an Oracle Platinum Partner, offering comprehensive services across the entire value chain of Oracle E-Business suite. With our

right blend of industry domain expertise, Oracle Solution Experts, Tools & Accelerators and best practices, we enable you with the right

solution required for maximizing returns from your Oracle investments. Our right-fit approach delivers key solution milestones that help

organizations to stay ahead of the business curve. As a premier Oracle Service Provider, our services range right from Consulting, Imple-

mentations & Rollouts, Integration's, Upgrades & Migration, Application Management & Support, Custom Developments &

Enhancements, Database Support and Testing.

About Hexaware and Oracle Practice

Address

1095 Cranbury South River Road, Suite 10, Jamesburg, NJ 08831. Main: 609-409-6950 | Fax: 609-409-6910

Safe HarborCertain statements on this whitepaper concerning our future growth prospects are forward-looking statements, which involve a number of risks, and uncertainties that could cause actual results to differ materially from those in such forward-looking statements. The risks and uncertainties relating to these statements include, but are not limited to, risks and uncertainties regarding fluctuations in earnings, our ability to manage growth, intense competition in IT services including those factors which may affect our cost advantage, wage increases in India, our ability to attract and retain highly skilled professionals, time and cost overruns on fixed price, fixed-time frame contracts, client concentration, restrictions on immigration, our ability to manage our international operations, reduced demand for technology in our key focus areas, disruptions in telecommunication networks, our ability to successfully complete and integrate potential acquisitions, liability for damages on our service contracts, the success of the companies in which Hexaware has made strategic investments, withdrawal of governmental fiscal incentives, political instability, legal restrictions on raising capital or acquiring companies outside India, and unauthorized use of our intellectual property and general economic conditions affecting our industry.