    Woolwich Station Box Project NewsletterIssue No.16 November / December 2012

    Crossrail is the new high frequency railway which will link Maidenhead and Heathrow in the west, throughnew tunnels and stations under central London, with Shenfield and Abbey Wood in the east. It will act as acatalyst for regeneration across London. Rail capacity will be increased by 10%, new journey opportunitieswill be created, journey times cut and overcrowding relieved. For further information about Crossrail visitwww.crossrail.co.uk .

    Berkeleys construction of the station box is progressing well and is on programme to achieve an earlyhandover of the east section of works to Crossrail at the beginning of March 2013. This early handoversupports efforts to progress the transfer of tunnel boring machines through the station box and enabletunnelling under the River Thames to link Abbey Wood and Woolwich with the rest of the Crossrail network.

    The base slab of the station box was completed in early November and works are now focussed onconstructing the 172m long Box roof slab and supporting columns by the end of the year. In January andFebruary Berkeley will be completing various smaller works within the box and at surface prior to handover.

    Condition surveys of the streets and pavements local to the station box worksite were surveyed prior to theworks commencing. Now that the main works are nearly complete, the project has commissioned ascheme of road repairs to make good any damage that may have arisen during construction of the stationbox. The majority of these works will take place in December.

    In November Crossrail Ltd awarded the Berkeley Station Box project with a Green Line Award forexcellence in environmental management. The project is proud to be one of the first to be recognised inthis way

    Above: Station Box from the north-west

    The basement of the Over-Site Development (OSD) hasprogressed significantly since the previous newsletter.Three tower cranes are now servicing both the OSDand the station box offering considerable benefits toboth schemes.

    Berkeleys OSD basement construction will continueafter handover of the station box to Crossrail. The twostorey basement, which will ultimately serve the mixeduse development above, is forecast for completion inthe summer (2013).

    May we take this opportunity to thank you for yourcontinued cooperation and assistance during theconstruction works and wish you all a wonderfulChristmas and a very happy New Year.

    Berkeleys completion of the station box project ahead of schedule will be a significant achievement. Inorder to mark the event Berkeley are planning a second residents open day together with othercelebrations during the afternoon and evening of 27 February 2013, further information to be providedsoon.

  • 7/30/2019 Berkeley Homes pay for Woolwich Crossrail station box

    2/2

    Above: Station column construction Above: Rolling falsework support for roof construction

    Above: Roof construction Above: Removal of lower temporary props in the west

    Above: Oversite Development temporary propping and foundations construction nearing completion

    If you have any queries or concerns, please call David Collins on 020 8301 8780 or [email protected]. Out of normal site hours please call Peter Buckley on 07790 455 939.

    If you feel we have not resolved your query please contact the Crossrail 24 hour helpdesk on 0345 6023813 or email [email protected].

    Yours sincerely

    Shane TaylorPROJECT MANAGER