30
Asiana Flight 214: Storm Drain and Soil Remediation Bay Pollution Prevention Program Presenter: Jennifer Acton [email protected]

Asiana Flight 214: Storm Drain and Soil Remediation

  • Upload
    vobao

  • View
    226

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Asiana Flight 214: Storm Drain and Soil Remediation

Asiana Flight 214:

Storm Drain and Soil

Remediation

Bay Pollution Prevention Program

Presenter: Jennifer Acton [email protected]

Page 2: Asiana Flight 214: Storm Drain and Soil Remediation

Summary of Emergency Remediation Efforts

• Overview of Initial Contamination

• Evaluation of Storm Drain System

• Emergency Soil Remediation

• Storm Drain Remediation

• Post-Emergency Remediation Activities

• Lessons Learned

Page 3: Asiana Flight 214: Storm Drain and Soil Remediation

Overview of Initial Contamination

• July 6, 2013, Asiana Flight 214 made a crash landing

onto Runway 28L.

• The right wing of the aircraft, which was leaking jet fuel,

came to rest directly over a storm drain catch basin.

• Approximately 2950 gallons of jet fuel was spilled onto

the soil or into the storm drain system.

• Due to the resulting fire, AFFF firefighting foam entered

the storm drain system.

Page 4: Asiana Flight 214: Storm Drain and Soil Remediation

Right Wing & Adjacent Catch Basin

Page 5: Asiana Flight 214: Storm Drain and Soil Remediation

Left Wing and Adjacent Catch Basin

Page 6: Asiana Flight 214: Storm Drain and Soil Remediation

Evaluation of Storm Drain System

• Immediately following the crash, both storm drain pump stations

servicing the affected area (1A and 1B respectively) were taken

offline.

• Water samples were collected from pump stations 1A & 1B and

subsequently analyzed. 1B was determined to be free of

contamination, while both jet fuel and AFFF were detected in 1A.

• BPPP staff walked the crash site to evaluate which catch basins

and storm drain pipes had been affected.

Page 7: Asiana Flight 214: Storm Drain and Soil Remediation

Map of Affected Storm Drains

Page 8: Asiana Flight 214: Storm Drain and Soil Remediation

View of Aircraft from Station 1A

Page 9: Asiana Flight 214: Storm Drain and Soil Remediation

AFFF Foam in Wet Well

Page 10: Asiana Flight 214: Storm Drain and Soil Remediation

Emergency Soil Remediation

• Meeting conducted with RWQCB to propose the Emergency soil

remediation plan.

• Surveying the crash site and collection of (7) base samples

• After the aircraft had been transported offsite, (4) visually contaminated

areas were found. Contaminated soil was removed.

• Contamination was confirmed by the analysis of soil samples collected by

contracted geologist.

• All contaminated soil and asphalt were placed in 20 yard bins, and were

subsequently sampled and transported to an accredited landfill.

Page 11: Asiana Flight 214: Storm Drain and Soil Remediation

Map of Base Samples

Page 12: Asiana Flight 214: Storm Drain and Soil Remediation

Map of Contaminated Samples

Figure from Site investigation report prepared by Burns & McDonnell Engineering Company

Page 13: Asiana Flight 214: Storm Drain and Soil Remediation

Storm Drain Remediation

• Immediately following the crash, pump stations 1A and 1B were both

taken offline.

• Removal of the contaminated water from pump station 1A wet well so

flushing of the storm drainage lines could take place.

• Constant pumping out of affected wet well from any excessive tidal

infiltration to prevent flooding.

• Cleaning and flushing affected storm drainage lines near Asiana 214 final

resting point. (Approximately 3,200 feet of pipe)

• Testing water in storm drainage system and wet well.

Page 14: Asiana Flight 214: Storm Drain and Soil Remediation

Removal of Water from Pump Station 1A

Page 15: Asiana Flight 214: Storm Drain and Soil Remediation

Boring Hole into Drainage Pipe

Page 16: Asiana Flight 214: Storm Drain and Soil Remediation

Pumping Water Out of Drainage Pipe

Page 17: Asiana Flight 214: Storm Drain and Soil Remediation

Triple Flushing of Drainage Pipe

Page 18: Asiana Flight 214: Storm Drain and Soil Remediation

Steel Plate for Bore Hole

Page 19: Asiana Flight 214: Storm Drain and Soil Remediation

Cleaning of Pump Station 1A

Page 20: Asiana Flight 214: Storm Drain and Soil Remediation

Cleaning of Pump Station 1A

Page 21: Asiana Flight 214: Storm Drain and Soil Remediation

Post-Emergency Remediation Activities

• After triple flushing the storm drain pipe that runs under Runway

28L, samples were collected to ensure all contaminants had been

removed. Analysis of these samples confirmed that the line was

indeed clean.

• After triple flushing affected pump station, A 96h Acute Fish

Bioassay Screen was performed using tidal infiltration collected

from the station’s wet well.

• The 96h static renewal, 1x24hr passed the effluent toxicity test with

a 100% survival rate.

Page 22: Asiana Flight 214: Storm Drain and Soil Remediation

Post-Emergency Remediation

Activities

• The analytical data was submitted to the Regional Water Board.

After the RWQCB approval, pump station 1A was placed back

online.

• As a precautionary measure, booms were placed in the pump

station and around the outfall.

• All contaminated water, sand and soil were transported to

approved disposal facilities.

Page 23: Asiana Flight 214: Storm Drain and Soil Remediation

Lessons Learned

• 24/7 Spill Notification Individual

• Emergency Contracting Procedures in Place

• Be Prepared for the Unexpected

Page 24: Asiana Flight 214: Storm Drain and Soil Remediation

Long Term Soil & Groundwater

Remediation

Presenter: Emily Sing

Associate Engineer | Environmental Services and

Sustainability

Page 25: Asiana Flight 214: Storm Drain and Soil Remediation

Moving On

Develop Site

Investigation Report

Estimate volume of Contaminated soil and ground water

* All activities were conducted by Asiana, approved by the Regional Board and SFO

Develop Workplan Identify extent of contamination

Page 26: Asiana Flight 214: Storm Drain and Soil Remediation

Figure from Site investigation report prepared by Burns & McDonnell Engineering Company

Page 27: Asiana Flight 214: Storm Drain and Soil Remediation

• 50 boreholes • 10 feet deep • Analyzed for soil contamination in 3 ft. intervals • Analyzed for groundwater contamination

Figure from Site investigation report prepared by Burns & McDonnell Engineering Company

Page 28: Asiana Flight 214: Storm Drain and Soil Remediation

Estimated Remaining Contamination

Medium Estimated Quantity

Groundwater, Gallons 81,000

Soil, Tons 2,839

Estimated Quantities under review

Page 29: Asiana Flight 214: Storm Drain and Soil Remediation

Moving On

Develop Workplan

Develop Site

Investigation Report

Identify extent of contamination

Estimate volume of Contaminated soil and ground water

Develop

Remediation Plan

• Identify clean up standards and schedule for clean up

Page 30: Asiana Flight 214: Storm Drain and Soil Remediation

Questions?