38
ASHRAE Std 62.1-2007 Ventilation for Acceptable Indoor Air Quality

ASHRAE presentation.ppt

  • Upload
    coolth2

  • View
    180

  • Download
    3

Embed Size (px)

DESCRIPTION

asf

Citation preview

Page 1: ASHRAE presentation.ppt

ASHRAE Std 62.1-2007 Ventilation for Acceptable Indoor Air Quality

Page 2: ASHRAE presentation.ppt

ASHRAE Std 62 update

An Outline General comments General

requirements Ventilation

requirements Construction and

O/M requirements Questions

Page 3: ASHRAE presentation.ppt

ASHRAE Standard 62

What’s Its History?62-2001•Prescriptive•Commissioning•O&M•Combustion air•Filtration

62-1999• IAQ-Health disclaimers• Smoking disclaimers• Clarified CO2as

ventilation metric

62-1989• Removed

Thermal Comfort• Ventilation Rate

Proc.• IAQ Proc.

62-1973first issued

62-1981Alternative Air Quality Proc.

1990 2000 20101970 1980

62.1-2004•Commercial and High Rise Res.•Enforceable code language•ETS vent. rates not covered•Vent. Rate. Proc. Modified•Occupant and area vent. rates

62.1-2007Updated

Page 4: ASHRAE presentation.ppt

ASHRAE Standard 62.1-2007 & Related Activities…

Std 62.1-2007 is the most current version

IMC adopted methodology and rates in 2007 Supplement

Several educational courses are available from ASHRAE

Page 5: ASHRAE presentation.ppt

62.1-2007 Purpose

1.1 Specify minimum ventilation rates and other measures intended to provide IAQ that is acceptable to human occupants and that minimizes adverse health effects.

1.2 Intended for regulatory application to new buildings, and additions

1.3 Guide the improvement of IAQ in existing buildings.

Page 6: ASHRAE presentation.ppt

62.1-2007 Scope 2.1 All spaces intended for human occupancy. 2.2 Defines requirements for ventilation, air-

cleaning design, commissioning, installation and O&M

2.3 Additional requirements and other standards may apply (labs, healthcare, industrial, etc.)

2.4 May be applied to both new and existing buildings, not intended to be used retroactively

2.5 Does not prescribe specific ventilation rates for smoking spaces

Page 7: ASHRAE presentation.ppt

62.1-2007 Scope Con’t 2.6 Ventilation requirements based on chemical,

physical, & biological contaminants 2.7 Consideration or control of thermal comfort is

not included 2.8 Contains requirements, in addition to

ventilation related to certain sources

Page 8: ASHRAE presentation.ppt

62.1-2007 Scope Con’t 2.9 Acceptable IAQ may not be reached in all

buildings meeting these requirements because of special conditions noted

Definition Acceptable Indoor Air Quality: air in which there are no known contaminants at harmful concentrations as determined by cognizant authorities and with which a substantial majority (80% or more) of the people exposed do not express dissatisfaction

Page 9: ASHRAE presentation.ppt

General Requirements4.0 Outdoor Air Quality 4.1 Regional Air Quality

Must determine NAAQS attainment status www.EPA.gov

If nonattainment, air cleaning is required in some cases

4.2 Local Air Quality Conduct observational

site survey to identify local sources of air contaminants

Page 10: ASHRAE presentation.ppt

General Requirements4.0 Outdoor Air Quality

4.3 Documentation Regional air quality compliance

status Local survey information Conclusions regarding

acceptability of outdoor air quality

Page 11: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.1 Natural Ventilation. Must meet minimum requirements for location and size of openings

5.2 Ventilation Air Distribution. Must provide means to adjust

(balance) Must be sure that mixing occurs in

RA/OA mixing plenums

Page 12: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment 5.3 Exhaust Duct Location. Operate exhaust

ducts(with harmful contaminants) at negative pressure

5.4 Ventilation System Controls. Control to assure proper ventilation under any operating condition

5.5 Airstream Surfaces. Use materials that have documented resistance to microbial growth and erosion

Page 13: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.6 Outdoor Air Intakes. Separate OA intake from outdoor contaminant sources Must comply with default minimum separation

distances in Table 5-1. Examples: Loading dock 25 ft Dumpster 15 ft Surface below intake 1 ft Cooling tower exhaust 25 ft

Must limit rain water penetration (using hood, proper velocity, etc.) or manage water that penetrates

Must use bird screens and prevent bird nesting

Page 14: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment 5.7 Local Capture of Contaminants.

Discharge air from non-combustion equipment with exhaust vents must be exhausted to outdoors

5.8 Combustion Air. Provide combustion air and exhaust air for indoor fuel-fired appliances Products of combustion from vented

appliances shall be vented directly outdoors.

Page 15: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.9 Particulate Matter Removal. Use a filter with a MERV 6 (or greater) upstream of dehumidifying coils and other wet-surface devices in supply stream

Page 16: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.10 Dehumidification Systems. Must limit indoor RH to 65% or less at

design dew point condition Exception to RH limit: where occupancy

requirements or processes dictate higher RH conditions.

Intake airflow must be greater than relief/exhaust during cooling (to minimize moist air infiltration)

Page 17: ASHRAE presentation.ppt

62°F DP62°F DP

At 75F, 65% rh

gives a 13F

“safety margin”

before

condensation

At 75F, 65% rh

gives a 13F

“safety margin”

before

condensation65% RH limit65% RH limit

General Requirements5.10 Dehumidification Systems

Page 18: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.11 Drain Pans. Assure drainage without flooding or carryover Slope: 1/8” per foot toward outlet Drain: At lowest point, large enough to prevent

overflow Drain seal: P-trap or other seal for negatively

pressurized drain pans to prevent ingestion of air while allowing complete drainage (fan on or off)

Pan size: length at least 1/2 coil height or as necessary to limit carryover

Page 19: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.12 Finned Tube Coils and Heat Exchangers Use drain pan Select to limit coil pressure drop to

0.75 in.wc.@ 500 fpm face velocity If higher pressure drop, provide

access on both sides for maintenance

Page 20: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.13 Humidifiers and Water Spray Systems Use potable water (or better) No downstream devices within

absorption distance 5.14 Access for Inspection,

Cleaning and Maintenance.

Page 21: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.15 Building Envelope and Interior Surfaces Weather barrier to prevent water penetration

into envelope Vapor retarder or other means to prevent

condensation on cold surfaces within envelope Seal all seams, joints, penetrations to limit

infiltration Insulate pipes, ducts expected to have surface

temperature below surrounding dew point

Page 22: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.16 Buildings with Attached Parking Garages. Limit infiltration of vehicular exhaust Maintain garage pressure at or below

adjacent occupied space Or, use a vestibule Or, otherwise design to minimize air

migration from garage to occupied space

Page 23: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment 5.17 Air Classification and Recirculation.

Limit recirculation or transfer of “dirty” air to “cleaner” spaces

5.17.1 Classification - Designate air leaving each space using Table 6.1

Class 1: Low contaminant concentration (office) Class 2: Moderate concentration (dining room) Class 3: Significant concentration (sick room) Class 4: Highly objectionable or potentially

harmful concentration

Page 24: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.17.1 ClassificationManage recirculation as follows Class 1 to anywhere Class 2 to self, similar Class 2 or Class

3 or Class 4 Class 3 to self Class 4 to outdoors

Page 25: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.17.2 Re-designation of air class Air Cleaning. May reclassify air cleaned

by passing it through an appropriate air-cleaning system

Transfer. Mixed classes are re-designated.

Energy Recovery. Energy recovery from class 2 (exhaust) airstreams must have no more than 10% leakage into a class 1 airstream.

Page 26: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.18 Requirements when building has both ETS and ETS-Free areas. Does not purport to achieve acceptable IAQ in ETS areas.

Spaces must be classified as ETS or ETS-Free

Air must be kept separate by means of walls, automatic door closers and pressurization

Page 27: ASHRAE presentation.ppt

General Requirements 5.0 Systems and Equipment

5.18 (continued) Recirculation or transfer from ETS

to ETS-Free is prohibited ETS areas must be exhausted to

the outdoors

Page 28: ASHRAE presentation.ppt

Ventilation Requirements 6.0 Procedures

6.1 General. Ventilation Rate Procedure or IAQ Procedure for outdoor airflow values for mechanical ventilation systems

6.1.1 Ventilation Rate Procedure. Prescribes rates & procedures based on typical space contaminant sources & source strengths

Page 29: ASHRAE presentation.ppt

Ventilation Requirements 6.0 Procedures

6.1.2 IAQ Procedure. Requires calculation of rates based on analysis of contaminant sources, concentration targets and perceived air quality targets.

Page 30: ASHRAE presentation.ppt

Construction Requirements 7.0 Construction/Start-Up

7.1 Construction Phase Don’t operate air handlers without filters Protect building materials Protect occupied

areas Limit migration of

construction contamination into occupied space

Page 31: ASHRAE presentation.ppt

Construction Requirements 7.0 Construction/Start-Up

7.1.5 Air Duct Construction shall be in accordance with the SMACNA duct construction standards and NFPA standards governing installation of HVAC systems

7.2 System Start-Up. Balance airflow values, test drain pans, clean up before starting, test damper controls

Page 32: ASHRAE presentation.ppt

Construction Requirements 7.0 Construction/Start-Up

7.2.6 Documents including balance report, construction drawings and design criteria with assumptions shall be provided to Owner

Page 33: ASHRAE presentation.ppt

Operating Requirements 8.0 Operation & Maintenance

8.2 Operations and Maintenance Manual. Develop and maintain a

building operations and maintenance manual which shall include a maintenance schedule with frequencies of tasks.

Building

Operation

Manual

Page 34: ASHRAE presentation.ppt

Operating Requirements 8.0 Operation & Maintenance

8.3 Ventilation System Operation. Operate in accordance with Building Operations Manual

8.4 Ventilation System Maintenance. Maintain in accordance with Building Operations Manual.

Page 35: ASHRAE presentation.ppt

Operating Requirements 8.0 Operation & Maintenance

8.4.1.4 Coil drains. Drain pans shall be inspected at least once a year and cleaned if required

8.4.1.8 Outside Air Flow Verification. For units >2,000 cfm the outside air flow shall be tested a minimum of every 5 years and adjustments shall be made to have the design flow provided to system

Page 36: ASHRAE presentation.ppt

ASHRAE 62.1 Standard is under continuous

maintenance process You can propose a change to the

standard Notice of proposed changes appears in

ASHRAE Standards Action You can comment on proposed changes You can request an interpretation

Page 37: ASHRAE presentation.ppt

ASHRAE 62.1

User’s manual for 62.1-2007 IMC & UMC Code adoption ALI Short Course and Professional

Development Course eLearning course IAQ Design Guideline is in the

works

Page 38: ASHRAE presentation.ppt

THANK YOU!