Appendix 6 Amendment C107 Mobil Altona Refinery Proposed
Upload
others
View
1
Download
0
Embed Size (px)
344 x 292
429 x 357
514 x 422
599 x 487
Text of Appendix 6 Amendment C107 Mobil Altona Refinery Proposed
Ordinary Council Meeting Agenda
Amendment C107 – Mobil Altona Refinery – Proposed Removal of
Heritage Overlay
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
2
Executive Summary The Amendment applies to land recognised as the
Mobil Refinery in Altona (the site) at 351-381 Millers Road in
Altona North. The amendment applies only to part of the land
situated north of Kororoit Creek Road, bounded by Millers Road to
the west, Kororoit Creek Road to the south and the rail line to the
north and east (the site).
The site is currently zoned Special Use 2 (SUZ2) and is affected by
Heritage Overlay 202 (HO202), the Industrial Heritage Places Policy
and the Industry Policy in the Hobsons Bay Planning Scheme.
The heritage overlay currently triggers the requirement for a
planning permit for all buildings and works, including demolition,
new buildings and routine maintenance and repairs. When the
heritage overlay was first applied to the site in 2003, the intent
was to prepare an ‘incorporated document’ to identify the
circumstances that did not require a permit. To date, the
incorporated has not been prepared.
Mobil have raised ongoing concerns about the effect that the
heritage overlay has on triggering permit applications for works
that would not require a permit under the Special Use 2 Zone. Mobil
have requested Amendment C107 to the Hobsons Bay Planning Scheme to
remove the Heritage Overlay from the Altona Refinery
Mobil have submitted the Altona Refinery Conservation Management
Plan (CMP) in support of their application. The CMP concludes that
it is the ongoing use of the refinery that is the most important
conservation objective, rather than the retention of individual
elements of heritage fabric. It highlights that the removal of
elements of heritage fabric is appropriate and necessary to support
the ongoing use of the refinery.
It is recommended that the conclusion of the CMP be supported,
however it should be supported through the removal of the heritage
overlay rather than an incorporated plan. Indeed, Council’s own
Industrial Heritage Places Policy is based on the same
‘conservation by use’ principle and the assessment of planning
permit applications using the current planning framework has
repeatedly shown that the removal of heritage fabric in the Altona
Refinery is considered necessary and appropriate to facilitate the
historical use of the site, ensure its future viability and to
achieve a balance between economic and conservation
objectives.
The Amendment also corrects a minor error to the Schedule to the
Special Use Zone.
The proposal has been assessed against the strategic assessment
guidelines outlined in Ministerial Direction 11. The heritage
overlay and an incorporated plan are no longer required to achieve
conservation objectives at the Altona Refinery. In conclusion, it
is recommended that Hobsons Bay City Council seek authorisation
from the Minister to prepare and exhibit Planning Scheme Amendment
C107 to the Hobsons Bay Planning Scheme to remove the Heritage
Overlay form the land.
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
EXISTING LAND USE .................................................................................................................................. 4
Existing Planning Controls
.......................................................................
6
PARTICULAR PROVISIONS ......................................................................................................................... 9
LOCAL POLICY .......................................................................................................................................... 12
Industry Policy Clause 22.02 of the Hobsons Bay Planning Scheme ................................................ 12
Industrial Heritage Places Policy Clause 22.0111 of the Hobsons Bay Planning Scheme ............... 12
REFERENCE DOCUMENTS ....................................................................................................................... 14
Industrial Land Management Strategy June 2008 (ILMS) ................................................................... 16
The Industrial Development Design Guidelines 2008 ......................................................................... 16
Background
..............................................................................................
17
PLANNING PERMITS ................................................................................................................................ 18
Photo 2 – Thermofor Catalytic Cracker – to be demolished 2016 ...................................................... 20
Photo 3 – Administration Building – demolished 2014 ...................................................................... 20
CONSERVATION MANAGEMENT PLAN ................................................................................................... 21
Analysis
....................................................................................................
23
4
The Subject Site and Surrounds 1. Amendment C107 applies to land
recognised as the Mobil Refinery in Altona. The
amendment applies only to part of the land situated north of
Kororoit Creek Road, bounded by Millers Road to the west, Kororoit
Creek Road to the south and the rail line to the north and
east.
2. The site address is 351-381 Millers Road, Altona. The land is
legally described as Lot 5 TP850733, Lot 1 TP534082 and the eastern
portion of Lot 9 TP850733.
3. The site has an approximate width of 413m and depth of 462m,
with an approximate area of 19ha. The site has a relatively flat
topography.
4. The site fronts two main arterial roads, Millers Road and
Kororoit Road.
5. The Refinery’s main operations are focused on the site. Mobil
has broader land holdings in the area, directly adjacent to the
site. The adjacent properties to the east and to the northeast
comprise of a fuel storage tank farm, industrial and fuel
processing buildings and ancillary piping/transmission lines. The
property to the north is a service station, a staff car park and
vacant land with vehicle access achieved from both Kororoit Creek
Road and Millers Road.
6. The location and boundaries of the site are shown on Map 1 on
page 5.
EXISTING LAND USE
7. The site was originally used for the production of lubricants
and bitumen from 1949 and then became one of the key petroleum fuel
plant (refinery) in Australia in 1954.
8. The site is owned and operated by the Mobil Refining Australia
Pty Ltd, a subsidiary of ExxonMobil who is the largest publicly
traded international oil and gas company.
9. The refinery is an industry of State significance located in a
core industrial precinct of Hobsons Bay. The Refinery supplies half
of Victoria's fuel needs, playing a very important role in
Victoria’s fuel supply chain and transport system. It produces
around 12 million litres of refined products per day (enough to
fuel 300,000 cars).
10. The refinery operates 24 hours a day, 365 days a year
processing crude oil into the full range of petroleum products,
including unleaded petrol (60 per cent), diesel (30 per cent) and
jet fuel (per cent).
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
6
11. The refining process involves imported crude oil arriving via
tanker at Gellibrand wharf in Williamstown and then being
transported to the refinery via pipeline or tanker or Victorian
crude oil being transported by pipeline from the Gippsland/Bass
Strait oil and gas fields. At the refinery, the crude oil goes
through various processes and then the refined products are pumped
into storage tanks to await distribution. There are almost 100
storage tanks at the Altona Refinery.
12. Around 90 per cent of products are then transported by pipeline
from the refinery to Mobil Yarraville terminal and other oil
company terminals for distribution by road throughout Victoria and
into parts of South Australia and New South Wales. Jet fuel is
transported directly from the refinery to Somerton, where it is
then provided to Melbourne Airport. The refinery supplies LPG as
feedstock to the nearby Altona chemical complex, which in turn
supplies feedstocks to other petrochemical manufacturing plants at
Altona. These plants produce the raw materials from which a
multitude of consumer products are made including adhesives,
plastics, film, wire insulation, car batteries and tyres.
13. The refinery has invested $300 million in
maintenance/improvements since 2008 and is planning to invest
another $90 million in the facilities in the next three
years.
14. The Altona refinery current employs more than 350 people, with
around forty per cent living in nearby suburbs.
15. Mobil provides funding support to local schools, hospitals,
environmental projects and community organisations.
16. The Altona Refinery Community Liaison Committee, including
representatives of Hobsons Bay City Council, local residents and
refinery management, meets four times a year and meetings are open
to all interested people in the local area. A newsletter is
distributed to over 20,000 households to coincide with the
meetings. At the meetings, Mobil reports on the refinery’s
operations and environmental and safety performance and provides
updates on progress achieved to meet targets and initiatives.
Existing Planning Controls ZONING
17. The site is zoned Special Use Zone Schedule 2 Petroleum
Refining Area (SUZ2) in the Hobsons Bay Planning Scheme, as shown
in Map 2 on page 7.
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
Map 2 – Zoning Map
18. The provisions for the Special Use 2 Zone are contained in
Clause 37.01-2 of the Hobsons Bay Planning Scheme.
19. The purpose of the Special Use 2 Zone is:
to provide for the operation and modernisation of the petroleum
refining industry in a manner that does not affect the safety and
amenity of nearby residential areas
to provide for the orderly and proper development of the area and
for adequate landscaping to reduce the visual impact of the
refinery
20. The only permitted major land uses on this land are a petroleum
refinery, car park and service station. All other land uses are
prohibited.
21. For the purposes of the Special Use 2 Zone, a petroleum
refinery is defined as an industry using plant, equipment and
facilities for the conversion of crude oil and other feed stocks
into finished or intermediate petroleum products and by-products.
This includes facilities for the receipt of crude oil and other
feed stocks, facilities for the storage of crude oils, intermediate
and finished products and by-products, pumping, pipeline and
distribution facilities, units for the removal and control of
impurities and by-products, waste treatment facilities, utilities
including steam raising and electrical generating equipment,
control
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
rooms, laboratories, research facilities, administration,
warehousing, maintenance, training and amenity buildings and
facilities and other associated works.
22. The use of the land for a petroleum refinery is exempt from the
standard and reduced parking requirements of Clause 52.06 of the
Hobsons Bay Planning Scheme if parking is provided on the site to
the satisfaction of the responsible authority.
23. A permit is required to construct a building or construct or
carry out works. This does not apply to a building or works
which:
provide or alter plumbing and electrical services involve the minor
rearrangement of car parking areas and landscaping provided
that
these areas are not diminished rearrange, alter or renew plant if
the areas of plant external to existing buildings is not
increased are a temporary shed or structure, not exceeding 100
square metres in floor area,
which is outside driveway, car parking, loading or landscaping
areas any works carried out by a public authority or a municipal
council in association with
the development of new plant or buildings comply with a direction
or licence under the Dangerous Goods Act 1985 or a Waste
Discharge Licence, Works Approval or Pollution Abatement Notice
under the Environment Protection Act 1970
24. Before deciding on an application to construct a building or
construct or carry out works, the responsible authority must
consider a range of matters including:
the State Planning Policy Framework and the Local Planning Policy
Framework, including the Municipal Strategic Statement and local
planning policies
views of the Environment Protection Authority, the Department of
Natural Resources and Environment, the Minister administering the
Dangerous Goods Act 1985 and the relevant waterway management
authority (about any works proposed in the flood plain of Kororoit
Creek)
drainage of land adequacy of information supplied availability of
services the layout of the site and design of buildings including
methods of minimising the visual
impact of the refinery on nearby residential areas, Kororoit Creek
Road, Millers Road, Kororoit Creek, Altona Coastal Park and Cherry
Lake
the layout of the site and design of buildings including the
relationship of the buildings and works to the street and adjoining
properties and the set backs from Millers Road and Kororoit Creek
Road
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
PARTICULAR PROVISIONS
25. Other permit exemptions, potentially relevant to the Altona
Refinery are listed in Clause 62.02 of the Hobsons Bay Planning
Scheme and include:
buildings or works, which provide for fire protection under
relevant legislation gardening buildings or works which are a
modification necessary to comply with a direction
under the Dangerous Goods Act 1985 or the Occupational Health and
Safety Act 2004 or a Waste Discharge Licence, Works Approval or
Pollution Abatement Notice under the Environment Protection Act
1970
buildings and works associated with a telecommunications facility
if the requirements of Clause 52.19 are met
a temporary shed or temporary structure for construction purposes,
or a temporary portable land sales office located on the land for
sale
oil pipelines repairs and routine maintenance to an existing
building or works removal, destruction or lopping of trees and the
removal of vegetation demolition or removal of a building or works
unless a permit is specifically required for
demolition or removal
26. Advertising signs within the Special Use 2 Zone are Category 2.
Advertising sign provisions are at clause 52.05 of the Hobsons Bay
Planning Scheme. Category 2 provides for adequate identification
signs and signs that are appropriate to office and industrial
areas, with a limited level of advertising control. A planning
permit is not required for a business identification sign or pole
sign provided that the total advertisement area of all signs to
each premises does not exceed 8 square metres (sqm) (excluding a
direction sign). A permit is also not required for a direction sign
and an internally illuminated sign, provided the advertisement area
must does not exceed 1.5 sqm and the sign is more than 30 metres
from a residential zone or pedestrian or traffic lights. All other
signs require a planning permit. No signs are prohibited.
OVERLAYS
27. The purpose of the Heritage Overlay is:
to conserve and enhance heritage places of natural or cultural
significance to conserve and enhance those elements which
contribute to the significance of
heritage places to ensure that development does not adversely
affect the significance of heritage
places
28. The Heritage Overlay overrides any exemptions in the Special
Use 2 Zone and triggers the requirement for a planning permit to
undertake most development activities, including:
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
10
subdivide land demolish or remove a building construct a building
or construct or carry out works, including a fence,
externally
altering a building by structural work, rendering, sandblasting or
in any other way, constructing or displaying a sign, externally
painting an unpainted surface, externally paint a building if the
painting constitutes an advertisement, carry out works, repairs and
routine maintenance which change the appearance of a heritage place
or which are not undertaken to the same details, specifications and
materials
29. Before deciding upon an application in the Heritage Overlay,
Council must consider:
the State Planning Policy Framework and the Local Planning Policy
Framework, including the Municipal Strategic Statement and local
planning policies.
the significance of the heritage place and whether the proposal
will adversely affect the natural or cultural significance of the
place
any applicable statement of significance, heritage study and any
applicable conservation policy
whether the location, bulk, form or appearance of the proposed
building will adversely affect the significance of the heritage
place
whether the location, bulk, form and appearance of the proposed
building is in keeping with the character and appearance of
adjacent buildings and the heritage place
whether the demolition, removal or external alteration will
adversely affect the significance of the heritage place
whether the proposed works will adversely affect the significance,
character or appearance of the heritage place
whether the proposed subdivision will adversely affect the
significance of the heritage place
whether the proposed subdivision may result in development, which
will adversely affect the significance, character or appearance of
the heritage place
whether the proposed sign will adversely affect the significance,
character or appearance of the heritage place
whether the lopping or development will adversely affect the
health, appearance or significance of the tree
30. The site is covered by a Heritage Overlay as shown on the
Planning Scheme Map No.9 as HO202. The extent of the Heritage
Overlay is shown on map 3 on page 13. The provisions for the
Heritage Overlay are contained in Clause 43.01 of the Hobsons Bay
Planning Scheme and the relevant schedule. The Altona Refinery is
listed in the schedule to the Heritage Overlay as the Standard
Vacuum Refining Company Complex (former). The schedule to the
overlay provides further provisions for the overlay which may be
applied to individual overlays. This overlay states:
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
11
external paint controls internal alteration controls tree controls
do not apply buildings or fences are not exempt under clause
43.01.3 prohibited uses may not be permitted the refinery is not
included on the Victorian Heritage Register as being of state
significance or recorded as an Aboriginal heritage place there are
currently no incorporated plans under Clause 43.01-2
Map 3 – Heritage Overlay (HO202)
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
Industry Policy - Clause 22.02 of the Hobsons Bay Planning
Scheme
31. This policy applies to all land in the Industrial 1 Zone,
Industrial 3 Zone, Mixed Use Zone and Special Use Zone Schedules 2,
3, 4 and 5, including the subject site.
32. The policy basis notes that the extensive areas of industrial
land in Hobsons Bay is of vital economic importance to the
municipality and the State of Victoria and that Council has a
responsibility to the State and the region to help ensure the
continuing viability of major industries within its borders. Major
industries are substantial employers and are vital elements in
Victoria’s economic prosperity.
33. The policy notes that the use and development of this
industrial land is also of great importance in determining the
physical and environmental character of the municipality and that
it is particularly important that large industries play a major
role in ensuring that their locality is visually attractive.
34. It is policy to:
have regard to the Hobsons Bay Industrial Land Management Strategy
June 2008 and the Hobsons Bay Industrial Development Design
Guidelines June 2008 when considering any applications for
subdivision, use and/or development in any of the zones to which
this policy applies
require applications to be accompanied by an of the use of the
site, including the likely type and frequency of heavy vehicles,
the proposed routes to access the site and the anticipated level of
car parking that will be generated by the use of the site
ensure that the orientation of the site, landscaping and layout of
new development is designed to enhance the amenity of the area,
reduce energy use and optimises natural ventilation, daylight and
solar access
ensure landscaping is provided within frontage and side setbacks to
the street, to outdoor car parking areas and where appropriate,
along rear and side boundaries to the satisfaction of the
responsible authority
encourage quality architectural design within new industrial
developments to enhance the character and visual amenity of Hobsons
Bay
Industrial Heritage Places Policy - Clause 22.01-11 of the Hobsons
Bay Planning Scheme
35. This policy applies to land zoned Industrial 1, Industrial 3 or
Special Use that is included within the Heritage Overlay, including
the subject site.
36. The policy notes that a dominant theme in the development of
Hobsons Bay has been the growth of industry with some of Victoria’s
most significant industrial heritage now found
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
13
within the city. Industries associated with engineering and fuels
including coal, gas, electricity and petroleum have been dominant
in Hobsons Bay over a long period of time.
37. The policy notes that the conservation of industrial heritage
places presents specific management issues, as it is often the use
of the site that is of primary historical significance. While
fabric such as buildings or plant contributes to the significance
of industrial heritage places by illustrating development over
time, the on-going replacement and upgrading of this fabric is
often an integral part of the operation of the use. The policy
highlights that ‘Conservation by use’ is an important heritage
principle and on this basis, there may be circumstances where it
may be appropriate to permit the removal or alteration of fabric if
it will facilitate the historic use of a site and ensure its future
viability.
38. The objectives of the Industrial Heritage Places Policy
are:
to ensure the continued viability of industrial heritage places for
the uses and processes historically carried out on the site as an
essential part of their significance and conservation
to increase awareness about the importance of industrial heritage
in the municipality. to ensure that heritage issues are given
appropriate consideration at an early stage
when making decisions about the future use and development of
industrial sites to retain the distinctive cultural heritage
significance of industrial heritage places
which is derived from: o the traditional and on-going use of
industrial heritage places over a long period o the important
influence of the industrial heritage places on the economic
and
social development of the city o the sheer size and extent of
nineteenth century industries in Newport and
Spotswood, which demonstrates not only their local economic
importance, but also their importance to the economy of
Victoria
o the probable national significance of the Newport, Spotswood and
North Altona region as one of the most historically important
centres in relation to the development of the petroleum and
petrochemical industries in Australia
o the surviving examples of early industrial building types, plant
and equipment o the associated infrastructure such as railways,
pipe-lines, roads and wharves that
are essential in understanding the complex historical
interrelationships that occurred in the development of industries
(particularly the petroleum and petrochemical industries) in the
area
39. The Industrial Heritage Places Policy requires applications for
development to have regard to:
the continued viability of the historic use of the site the balance
between achievement of conservation objectives and economic
viability, and
occupational health and safety
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
14
the conservation of fabric of primary significance unless the
fabric has been made redundant and is to be replaced by new
buildings, plant or equipment
the retention of fabric of primary significance that is longer used
in-situ if there is not an immediate need to remove or relocate
it
keeping an appropriate record of any significant fabric that is
removed or demolished and is made to the satisfaction of the
Responsible Authority
40. It is policy that before deciding on an application the
Responsible Authority consider, as appropriate:
whether the proposed buildings, works or demolition will support
the viability of the historic industrial use carried out on the
site
whether there is an opportunity for redundant equipment to remain
in-situ as historic evidence or for interpretation
whether the proposed interpretation will provide adequate
information about the historic use and development of the
site.
REFERENCE DOCUMENTS
41. The following documents are referred to in the Municipal
Strategy Statement, Industry Policy and the Industrial Heritage
Places Policy and their content is required to be considered in any
application to develop land at the Altona Refinery:
Hobsons Bay Heritage Study Amended 2014
42. The Heritage Study documents the themes that have shaped the
municipality over the last 165 years and identifies 33 precincts
and 275 places of heritage significance in Hobsons Bay and provides
the strategic basis for the application of statutory controls via
the Heritage Overlay, heritage policies and guidelines to protect,
conserve and management the municipality’s heritage assets.
43. The Heritage Study contains a citation for the Altona Refinery
(described as the former Vaccuum Oil Company Complex). The Study
identifies the Altona Refinery, comprising buildings and plant
generally constructed between 1949 – 1960 at 351-381 Millers Road
in Altona North, as having local historical, social, technical and
aesthetic significance to the City of Hobsons Bay.
44. Historically, it is significant for its strong associations
with the development of the oil industry in Australia as one of the
oldest continuously operating oil refineries in the country. It is
also significant as a major refinery and office complex that
illustrates the immense industrial expansion of the City and
Victoria in the post World War 2 period. The size of the complex
had a significant impact on the economy of the State of Victoria
and led to the establishment of a petro-chemical complex within
this area with a number of
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
15
associated firms such as Australian Carbon Black by the 1960s. The
complex has associations with Standard-Vacuum Oil and later Mobil
Oil who have played important roles in the development of the
petrochemical industry in Victoria. Parts of the complex have
associations with the important architectural firm of Stephenson
& Turner.
45. Socially, it is significant for its strong associations with
the local community as one of the first major industries in the
Altona area and one of the largest employers over a long period. It
is also significant for its associations with the development of
the labour movement in Australia through the introduction of the
concept of collective bargaining techniques, which were first used
at this site.
46. Technically, it is significant for early plant and equipment
such as the Thermofor Catalytic Cracking Plant, which is unique in
the State.
47. Aesthetically, although altered, the c.1955 office block is
significant as a good example of modernist design that illustrates
the progressive nature of the Standard-Vacuum company and
investment made in the establishment of the complex at the
time.
48. The citation describes the complex as including the following
buildings:
the refinery itself comprising various equipment, pipes, tanks and
stacks, all set out on a rectilinear grid between the railway,
Millers Road and Kororoit Creek Road. It includes the 248 feet high
Thermofor Catalytic Cracking Plant (now decommissioned), which is
thought to be the last vertical catalytic cracker in
Australia
the auditorium, canteen and locker building, located at the
north-east corner of Kororoit Creek Road and Millers Road, which
has a flat roof, is clad with cream bricks and has aluminium framed
windows with green glass panels. This is one of the buildings
designed by Stephenson & Turner
the former office/laboratory building (now the medical centre),
which is a concrete block with a hip roof building facing Millers
Road
the former Administration buildings, designed by Stephenson &
Turner, on the south west corner of the Millers-Kororoit Creek
Roads intersection. This building was pictured in the guide to
architecture in Victoria, which was produced by the RVIA for the
1956 Olympics. This building has since been changed by a general
renovation in recent times
a tank farm on the south side of Kororoit Creek Road. The number of
tanks has been greatly expanded since the 1940s
49. The Study found that the integrity of the plant is high to its
1940s-50s development stages and thus it is perhaps the most
complete complex of its kind in the region from this key era.
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
Industrial Land Management Strategy June 2008 (ILMS)
50. The ILMS is referred to in the Municipal Strategic Statement
and the Industry Policy at Clause 22.02 of the Hobsons Bay Planning
Scheme and are used to assess an application to development land at
the Altona Refinery in the Special Use 2 Zone.
51. The ILMS classifies the Altona Refinery as a ‘core industrial
area’. Core industrial areas are defined as major concentrations of
industry, which are relatively unconstrained by residential or
other sensitive uses. These areas will be protected and provide
opportunities for new growth, including the expansion of existing
industries. Non-industrial protrusions into these areas are not
supported and rezoning of land to non-industrial zones will not be
permitted.
52. The Altona Refinery is identified as precinct 10 in the ILMS.
The strategic objectives for precinct 10 are to:
support the ongoing operation of the Core Petroleum Refining
Industry in Altona. improve the quality of the precincts
appearance, with good levels of peripheral
landscaping. maintain the open, natural habitat nature of the land
at the southwest corner. improve the appearance of the gateway
location. minimise the visual impact of the structures within the
refinery reduce impacts on residential amenity and the environment
encourage incremental improvements to the visual and natural
environment in the
vicinity of the refinery. improve the landscaped buffer around the
perimeter of the refinery maintain monochromatic painting of
storage tanks
53. The desired outcome is described as a Core Industrial area
housing Petroleum Refining activities, with improved interfaces to
all abuttal’s, and reduced amenity and environmental
impacts’.
The Industrial Development Design Guidelines 2008
54. The Industrial Development Design Guidelines (IDDG) are
referred to in the Industry Policy at Clause 22.02 of the Hobsons
Bay Planning Scheme and would be required to be used to assess an
application for development of land at the Altona Refinery in the
Special Use 2 Zone.
55. The objectives of the IDDG’s are:
to ensure that the strategies and objectives for industry in
Hobsons Bay, expressed in the Guidelines, the Strategy, Municipal
Strategic Statement and the local policies, are
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
17
given effect in the determination of applications for industrial
land uses and developments
to ensure that the objectives for each industrial precinct in the
Strategy are given effect in the determination of applications for
land uses and developments
to achieve high quality urban design and architecture that accords
with Clause 19.03, (Design and Built Form) of the Hobsons Bay
Planning Scheme
to improve the appearance and amenity of industrial areas to
enhance the liveability, amenity and safety of the City to promote
environmentally sustainable design
56. The IDDG’s provide guidance on the following matters:
site layout and built form traffic and car parking site access
loading and services areas road network landscaping storage
container storage waste lighting fencing water sensitive urban
design energy Efficient urban design sustainable building
materials.
57. In relation to the Altona Refinery (Industrial Precinct 10),
the guidelines recommend a building setback of 20m from Kororoit
Creek Road and 9m from other roads and a landscaping setback of 30m
from the railway line, 50m from adjoining industrial zones and 9m
from all roads.
Background INTRODUCTION OF HERITAGE CONTROLS ON THE ALTONA
REFINERY
58. The Altona Refinery was first identified as being of local
heritage significance in 2001 in Stage 1 of the Hobsons Bay
Heritage Study (referred to as the Altona, Laverton, & Newport
Districts Heritage Study).
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
18
59. The Study recommended that the Refinery’s heritage assets be
given statutory protection through the application of the heritage
overlay in the Hobsons Bay Planning Scheme.
60. The Heritage overlay was first applied to the Altona Refinery
site in 2003, through Amendment C17 to the Hobsons Bay Planning
Scheme. The heritage overlay applied in 2003 was known as HO149.
The heritage overlay was renumbered to HO202, as part of Amendment
C34 in 2006.
61. Mobil objected to the application of heritage controls through
Amendment C17 during the exhibition period in 2002, raising
concerns about the potential impact of the application of the
heritage overlay on the on-going viability of the refinery.
62. An Independent Planning Panel considered Mobil’s objection to
Amendment C17 in 2002. The Panel recommended that:
the extent of exhibited HO149 is supported the amendment be
modified to include an Incorporated Document to limit the
extent
of the discretionary powers created by clause 43.01 to the fabric
of those buildings and those works whose local heritage fabric has
been established by rigorous research. The Incorporated Document
should be drawn narrowly in the first instance to ensure that the
discretion is not applied to buildings and works that do not have a
clearly established local heritage
the Statement of Significance should be amended to exclude
reference to the office block across the intersection (not in the
heritage overlay) and to emphasis the value of the ongoing
operation of the refinery in support of the site’s heritage
values
63. Council adopted Amendment C17 on March 2003 and resolved to
prepare an Incorporated Document for the Altona Refinery, as
recommended by the Panel at a later stage.
PLANNING PERMITS
64. Between 2003 and 2014, Mobil have obtained a planning permit
from Council to demolish the following heritage fabric that was
identified in the Hobsons Bay Heritage Study:
the auditorium and canteen (demolition completed) the thermofor
catalytic cracker (demolition planned for 2016) administration
building (demolition completed)
65. The heritage fabric that has been permitted to be removed to
date has all been large highly visible buildings or plant. Although
they contribute to the heritage value of the Refinery, the removal
of these structures will ensure the ongoing viability of the
historic use of the property, thereby preserving the heritage
significance of the entire site.
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
19
66. Photographs of the heritage fabric permitted to be removed
since the introduction of the heritage overlay in 2003 are provided
in page 22. A condition of all permits was the requirement to
prepare a photographic archival record of the removed heritage
fabric.
67. Mobil has raised ongoing concerns about the need to obtain
permits to do essential works, due to the heritage overlay.
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
20
Photographs of heritage fabric permitted to be removed since the
introduction of heritage controls in 2003
Photo 1 – Canteen and Auditorium – demolished 2015
Photo 2 – Thermofor Catalytic Cracker – to be demolished 2016
Photo 3 – Administration Building – demolished 2014
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
CONSERVATION MANAGEMENT PLAN
68. In 2015, Mobil engaged Biosis Pty Ltd to prepare the Altona
Refinery Conservation Management Plan (CMP). A copy of the CMP is
provided in Appendix 1.
69. The CMP provides an assessment of the cultural heritage values
on the Altona Refinery and recommendations for future management.
It contains conservation policy to provide direction and guidelines
for conservation and adaptation or redevelopment of the site and
its component parts, in a manner that addresses the significant
elements. This is in the context of an operating facility, which
requires on-going modification and change to the physical
fabric.
70. The CMP identifies the following 11 elements as being of
primary significance:
administrative building switch and compressor house storage tanks
distillery and bitumen plant lubricating oil warehouse drum filling
building thermofor catalytic cracker (TCC) amenities (canteen and
auditorium) no.3 changeroom warehouse / fire station cooling
towers
71. The CMP identified the following six individual elements as
being of contributory significance:
solulizer laboratory boiler house mechanical workshop horton
spheres fluidised catalytic cracker
72. The location of individual significant elements are shown in
the map within the CMP.
73. The CMP outlines how each of the significant elements are
currently being used, their condition and planned use. In summary,
much of the historical fabric is considered to be redundant, needs
to be upgraded or removed, doesn’t have any prospects for adaptive
re- use, has asbestos, not fit for use, or is taking up space that
could be used for new plant.
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
22
74. At this stage, Mobil has indicated that future demolition of
the following elements of primary significance is considered
likely:
distillery and bitumen plan no.1 and no.2 cooling towers some of
the storage tanks administration building on Millers Road (refer to
Photo 1 )
Photo 4 – Administrative Building Millers Road - front
Photo 5 – Administrative Building Millers Road - rear
75. The CMP sets the following conservation policies for the Altona
Refinery:
setting and curtilage views, vistas and visual relationships new
buildings and works landscaping
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
archival recording and documentation interpretation
76. The CMP states that the requirements for the preparation of
archival records have been partly achieved through the preparation
of the CMP. Mobil has advised that they will provide a photographic
recording of all structures to the satisfaction of Council prior to
the Amendment being submitted to the Minister for approval.
77. A draft incorporated plan for the Altona Refinery was prepared
by Mobil for discussion with Council officers in 2015. The proposed
Incorporated Plan would have allowed the alteration and removal of
all heritage fabric, without a planning permit so long as Mobil
prepared and submitted photographic records of the fabric that was
to be removed. The proposed incorporated plan was effectively a
back door demolition permit. This is not an appropriate way to use
an Incorporated Plan and is contrary to the objective of the
Heritage overlay. Council must ensure that the Victorian Planning
Provisions are used appropriately.
Analysis 78. Even with the heritage overlay, Council’s Industrial
Heritage Places and Economic
Development policies in the Hobsons Bay Planning Scheme provide a
framework that supports the demolish of heritage fabric at the
Altona Refinery if considered under future planning permit
applications.
79. It is policy to support the Altona Refinery as an industry of
state significance in a core industrial area in Hobsons Bay.
Council’s Industry Heritage Policy has a ‘conservation by use’
basis, as recommended in the CMP that recognises the need to
achieve a balance between conservation objectives and economic
viability and occupational health and safety.
80. Clarifying the policy that heritage fabric at the Refinery can
be removed, means that statutory protection under the heritage
overlay or through an Incorporated Plan are no longer required. The
heritage overlay tool is used to limit change and removal of
heritage fabric.
81. Exxon Mobil operates in a fast paced global economic market,
competing with other larger refineries in the Asia-Pacific region.
Its key strategy to staying competitive is through continuous
improvements/upgrades to facilities and plant. Exxon Mobil have
plans for improvements worth $80 million in the next three
years.
82. Exxon Mobil have advised that the heritage overlay, triggering
a permit for all buildings and works, in the context of their
budgeting cycles, can reduce Mobil’s ability to compete for funding
for these works, particularly in terms of being ‘project
ready’.
83. The underlying Special Use 2 Zone still requires Mobil to
obtain a permit to construct a building and carry out works, with
some exceptions including:
Amendment C107 Altona Refinery
351-381 Millers Road, Altona
24
alterations to plumbing or electrical services minor rearrangement
of car parking areas and landscaping rearrange, alter or renew plan
if the areas of plant external to existing buildings is not
increased a temporary shed or structure not over 100sqm pipelines
and works to comply with a direction or licence under certain
OH&S
legislation
84. This still allows Council as the Responsible Authority to
control the visual amenity of the Refinery to ensure it is
consistent with the purpose of the Special Use 2 Zone, particularly
in relation to the protection of the visual amenity of the
area.
85. The CMP contains a thorough analysis of the history of the
Altona refinery and additional photographs of heritage
fabric.
86. Mobil have agreed to photograph all of the fabric within the
refinery that has been identified as having heritage values before
the completion of the Amendment process.
87. In addition, the changes to the buildings and works exemptions
under Clause 4.0 in Schedule 2 to the Special Use Zone should by
supported. This clause incorrectly references ‘other exemptions are
listed in Clause 62.01’. This clause relates to uses not requiring
a permit rather than buildings and works not requiring a permit.
Reference to this clause has been deleted from the schedule as
clause 62.01 applied irrespectively.
Conclusion 88. The conservation of the refinery can be achieved
without the need for statutory protection
by way of the heritage overlay or an incorporated plan. Council’s
Industry Heritage Policy has a ‘conservation by use’ basis, as
recommended in the CMP that recognises the need to achieve a
balance between conservation objectives and economic viability and
occupational health and safety. Although the CMP recommends an
Incorporated Plan as the mechanism to implement the CMP, a more
appropriate method of conservation by use is to remove the heritage
overlay from the site to allow the Refinery to operate free from
heritage requirements. An appropriate archival photographic record
of the heritage fabric will be completed prior to the amendment
being sent to the Minister for Planning for approval.
© Biosis 2012 – Leaders in Ecology and Heritage Consulting
www.biosis.com.au
Altona Refinery Conservation Management Plan
Prepared for Exxon Mobil
Biosis Pty Ltd
This document is and shall remain the property of Biosis Pty Ltd.
The document may only be used
for the purposes for which it was commissioned and in accordance
with the Terms of the
Engagement for the commission. Unauthorised use of this document in
any form whatsoever is
prohibited.
Disclaimer:
Biosis Pty Ltd has completed this assessment in accordance with the
relevant federal, state and
local legislation and current industry best practice. The company
accepts no liability for any
damages or loss incurred as a result of reliance placed upon the
report content or for any purpose
other than that for which it was intended.
Biosis offices
Mitchell ACT 2911
Alexandria NSW 2015
Fortitude Valley QLD 4006
Phone: (07) 3831 7400
Fax: (07) 3831 7411
for Exxon Mobil
Version 01 MT 7/1/2015
Version 02 GV 16/2/2015
Version 03 GV 28/8/2015
Katie Murphy - Tract Consultants Pty Ltd
Kendal Houghton – Biosis Pty Ltd
Liza McColl – Hobsons Bay City
Summary
This report documents an assessment of the cultural heritage values
of the Altona Petroleum Refinery, which
was established by Standard Vacuum Oil Company in the years
immediately after World War II. Initially
constructed as part of a move to make Australia more
self-sufficient in petroleum production, the refinery
went on to play a major role in the expansion of motoring and oil
production. The first plant was primarily for
bitumen and lubricating oil, but in the 1950s petroleum production
was greatly expanded with the
construction of the Thermofor Catalytic Cracker (TCC). Subsequent
expansions have seen adaptation to
different crude sources such as Gippsland Crude, a wider variety of
product such as LPG, and supply of
product to the Altona Petrochemical Complex. The refinery underwent
a major expansion in the 1990s with
the replacement of the TCC with the Fluidised Catalytic Cracker
(FCC).
The purpose of the present study is therefore to document the
history of the site, provide a physical
description and statement of significance, and make recommendations
for future management.
The conservation policy has been developed on the basis of the
assessment of the cultural heritage
significance of the Altona Refinery. The purpose of the
conservation policy is to provide direction and
guidelines for conservation and adaptation or redevelopment of the
site and its component parts, in a
manner that addresses the significant elements. This is in the
context of an operating facility which requires
on-going modification and change to the physical fabric.
Accordingly, the directions and guidelines included
here should be considered in determining future strategies and
outcomes for the Altona Refinery.
© Biosis 2012 – Leaders in Ecology and Heritage Consulting ii
Table of Contents
1.4 Consultation
..................................................................................................................................................................
6
1.5 Methodology
.................................................................................................................................................................
6
2 Historic Background
...................................................................................................................................
7
2.2 Oil and Petrol in Australia
...........................................................................................................................................
8
2.3 Vacuum Oil Company
...............................................................................................................................................
10
2.4 Vacuum Oil in Yarraville
...........................................................................................................................................
11
2.5 Establishment of Altona Refinery (1946-49)
........................................................................................................
15
2.6 Expansion and renewal (1950s)
.............................................................................................................................
19
2.7 Expansion (1960s-90s)
..............................................................................................................................................
29
2.8 Recent Developments
..............................................................................................................................................
31
3.1 Landscape context
....................................................................................................................................................
35
3.2.1 Administrative Building later Health Centre.
...........................................................................................
35
3.2.2 Switch House
..................................................................................................................................................
37
3.2.4 Lubricating oil warehouse
...........................................................................................................................
41
3.2.5 Drum filling building
......................................................................................................................................
42
3.2.6 Demolished structures
.................................................................................................................................
43
3.3.1 Amenities buildings
.......................................................................................................................................
44
3.3.2 Boiler house
....................................................................................................................................................
45
3.3.4 Mechanical workshop
...................................................................................................................................
46
3.3.6 Laboratory
.......................................................................................................................................................
47
3.3.7 Solutizer
...........................................................................................................................................................
48
3.3.10 Other building and plant
..............................................................................................................................
51
3.4 1960s and later additions
........................................................................................................................................
51
3.4.1 Fluidised Catalytic Cracker
...........................................................................................................................
52
4 Comparative Assessment
........................................................................................................................
53
5.2 Assessment against criteria
....................................................................................................................................
61
5.3 Significant Elements
..................................................................................................................................................
63
6.2 Terminology and Methods
......................................................................................................................................
66
6.3 Statutory Requirements
...........................................................................................................................................
67
6.4.1 Need for the works
........................................................................................................................................
67
6.4.2 Management
..................................................................................................................................................
68
6.4.4 Future operation of the refinery
................................................................................................................
70
6.5 Conservation Policies
................................................................................................................................................
71
6.5.1 Conservation Works
......................................................................................................................................
72
6.5.2 Repairs & Maintenance
................................................................................................................................
72
6.5.7 New Buildings & Works
................................................................................................................................
73
6.5.8 Landscaping
....................................................................................................................................................
73
6.5.10 Interpretation
.................................................................................................................................................
74
6.5.13 Implementation and Review of the Conservation Policy
......................................................................
75
7 Bibliography
...............................................................................................................................................
76
Appendix A Hobsons Bay Council Letter from Council 15.07.14
Alternative mechanisms to permits .............. 78
Appendix B Draft Letter from Council 10 August 2014 Planning scheme
Amendment ........................................ 1
Appendix C: Burra Charter
..................................................................................................................................................
10
© Biosis 2012 – Leaders in Ecology and Heritage Consulting iv
Figures
Figure 2: Site plan, Altona Refinery Source: Courtesy
Mobil..................................................................................................................
3
Figure 3: Plan of extent of existing Heritage Overlay control
................................................................................................................
5
Figure 4: Drivers, Vacuum Oil Company Depot, Yarraville
..................................................................................................................
10
Figure 5: Model of New Works for Vacuum Oil Company, The Argus 8
Jul 1925
...........................................................................
13
Figure 6: Construction of Vacuum Company Oil depot, Yarraville,
Victoria ca. 1929. This later view is probably for an
additional storage tank.
..............................................................................................................................................................................
13
Figure 7: Various logos used by Standard Vacuum and its successors
...........................................................................................
15
Figure 8: Model of the completed Refinery in 1950.
............................................................................................................................
16
Figure 9: Aerial view of refinery 1952
......................................................................................................................................................
17
Figure 10: Tank Farm, store and lube oil building under
construction.
...........................................................................................
17
Figure 11: Distillation tower from the slop tanks nearing
completion.
............................................................................................
17
Figure 12: Left to right – boiler house, transformer and switch
house, amenities in front, office behind, and stores
buildings
(COR refinery in distance) 17 Feb 1949.
..................................................................................................................................................
18
Figure 13: Operational flow diagram for original plant processes
....................................................................................................
18
Figure 14: Construction of the TCC 1954, photo Sievers, Wolfgang
National Library, nla.pic-vn3419110 ...............................
20
Figure 15: Process diagram with new TCC and final products
...........................................................................................................
21
Figure 16: Model of proposed Altona Refinery expansion (Exxon Mobil
Archives)
.......................................................................
22
Figure 17: Aerial View of Altona Refinery Feb 1953, showing
preparations for construction of TCC and new tanks ............
23
Figure 18: Plan of newly expanded refinery showing original and new
structures.
.....................................................................
23
Figure 19: Standard Vacuum Oil Refining Company Ltd, Refinery,
Altona, Victoria. Aerial View of General Development,
1952
................................................................................................................................................................................................................
24
Figure 20: Brief article on new office building by Stephenson &
Turner.
........................................................................................
25
Figure 21: Plaque unveiled 4 April 1955 opening ceremony, and the
dignitaries touring the plant
......................................... 25
Figure 22: Altona Refinery 1955, by Charles William Bud (1919-1989)
............................................................................................
26
Figure 23: Construction of cooling tower 1954, Sievers, Wolfgang,
National Library of Australia, nla.pic-an24882807 ....... 27
Figure 24: View of Mobil Altona Refinery showing Horton Spheres and
TCC, 1956 Sievers, Wolfgang, National Library of
Australia, nla.pic-an24876126
...................................................................................................................................................................
27
Figure 25: Refinery by night 1956 1954, Photo Sievers, Wolfgang,
National Library of Australianla.pic-an24883930 ......... 28
Figure 26: Staff of the Altona refinery, Victoria in 1954. Photo
Sievers, Wolfgang, National Library .nla.pic-an24876601 ...
28
Figure 27: Refinery from the Air in the 1950s – TCC operating and
first of the cooling towers in place
.................................. 29
Figure 28: Altona Refinery in the 1960s (Wolfgang Sievers photo
State Library Victoria)
............................................................
30
Figure 29: Automated control room in the 1960s (Wolfgang Sievers
Photo, State Library Victoria)
......................................... 31
Figure 30: Fluid Catalytic Cracker being transported through the
Western Suburbs to the refinery site
................................ 32
Figure 31: Gatehouse (demolished) with former Administration
building behind 6 Dec 1949 (Exxon Mobil Archives) ....... 36
Figure 32: Administrative Building under construction 9 Dec. 1948.
(Exxon Mobil Archives Photo Album 35/23) ................ 36
Figure 33: Administration building from the south east.
....................................................................................................................
37
Figure 34: Administration building from Millers Road
.........................................................................................................................
37
Figure 35: Switch and compressor house with (demolished) boiler
house behind 18/1/1948 (Exxon Mobil Archives album
39/44)
..............................................................................................................................................................................................................
38
Figure 36: Compressor and Switch gear building, 2015
......................................................................................................................
38
Figure 37: Pipe Still 27/7/1949 (Exxon Mobil Archives Albums 46/6)
................................................................................................
39
Figure 38: Vacuum distillation tower under construction 27/7/1949
(Exxon Mobil Archives Albums 46/26) .........................
39
Figure 39: Location of No 1 Crude unit reused for later plant, 2014
................................................................................................
40
Figure 40: Storage Tanks and pipe gantry from original Bitumen
plant, 2014
...............................................................................
40
Figure 41: Bitumen tanks and rail loading gantries from the north,
2015
......................................................................................
41
Figure 42: Lube. Oil building under construction 27/7/1949 (Exxon
Mobil Archives Albums 46[28)
........................................ 41
© Biosis 2012 – Leaders in Ecology and Heritage Consulting v
Figure 43: Lube Oil Warehouse from the Millers Road bridge,
2014................................................................................................
42
Figure 44: Bitumen Drum filling building with rail loading at top,
2014
..........................................................................................
42
Figure 45: Lube oil packing building, 2014
.............................................................................................................................................
43
Figure 46: Wagon Loading/Tanker filling station (demolished) 15 Dec
1949 (Exxon Mobil Archives, album No22) .............. 43
Figure 47: Amenities building – auditorium and canteen from the
south west, 2015
.................................................................
44
Figure 48: Canteen interior looking east, 2014
......................................................................................................................................
44
Figure 49: Auditorium interior facing south east, 2014
.......................................................................................................................
45
Figure 50: 1950s Boilerhouse and water tank on left, 1948 Switch
house centre, 1950s laboratory on right. .......................
45
Figure 51: TCC in the 1960s (Exxon Mobil Archives)
.............................................................................................................................
46
Figure 52: Mechanical Workshop in 2014 showing
recladding..........................................................................................................
46
Figure 55: Remaining Solutizer plant looking west, 2014
....................................................................................................................
48
Figure 56: Amenities building (Area 3 change room) adjacent to
solutizer, 2015
.........................................................................
48
Figure 57: Cooling Tower No 2.
.................................................................................................................................................................
49
Figure 58: Three Horton Spheres for storage of LPG,
2014................................................................................................................
50
Figure 59: Group of air force personnel 8 December 1955 in front of
Horton Spheres - identified as Standard-Vacuum
Refining Company Pty Ltd, Essendon, but probably Altona (Museum
Victoria Reg. No: MM 51251) .......................................
50
Figure 60: Fluidised Catalytic Cracker
......................................................................................................................................................
52
Figure 61: Yarraville Terminal (Bing bird's eye images), 2012
............................................................................................................
54
Figure 62: Lubricant blending tower and offices at BP Newport
terminal, 2012
...........................................................................
55
Figure 63: Storage and works sheds at Shell Newport Terminal, 2012
...........................................................................................
55
Figure 64: Pump house at BP Newport terminal, 2010
.......................................................................................................................
56
Figure 65: Brick stores building Esso oil depot, Simcock Ave
Spotswood, 2010 (demolished c2014)
....................................... 56
Figure 66: Concrete building Caltex Newport Terminal, 2010
...........................................................................................................
56
Figure 67: Shell terminal Newport (photo Sievers, SLV H2004.49/83)
(demolished) c1980
........................................................ 57
Figure 68: Former commonwealth Oil Refinery office building Altona
North, 2008
.....................................................................
57
Figure 69: Altona Petrochemical Complex, (Technology in Australia
1977-1988)..........................................................................
58
Figure 70: Longford Gas Plant
...................................................................................................................................................................
58
Figure 71: Catalytic Cracker at Shell Refinery Geelong during
construction (State Library Victoria)
......................................... 59
Figure 72: Locations of significant elements and management actions
.........................................................................................
65
Figure 73: Altona Refinery view from Kororoit Creek Road, Jessie
Deane, 2013.
..........................................................................
70
Figure 74: Example of industrial land reuse - Landschaftspark
Duisburg-Nord.
...........................................................................
71
Tables
Table 3: Management of primary significant buildings and structures
...........................................................................................
68
© Biosis 2012 – Leaders in Ecology and Heritage Consulting 1
1 Introduction
1.1 Background
Exxon Mobil has commissioned Biosis Pty Ltd to undertake a heritage
assessment and prepare a
Conservation Management Plan for the Altona Refinery, with the
objective of assisting management of
statutory approvals for future works which may impact heritage
values of the site.
The Conservation Management Plan describes the heritage values and
physical condition of the place, and
sets out a conservation policy for managing impacts and
change.
1.2 Study Area
The Study Area encompasses the Mobil Altona Refinery to the extent
of the land covered by Heritage Overlay
(HO202). This large site, located within the Special Use Zone –
Schedule 2 (SUZ2), extends north east from the
intersection of Millers and Kororoit Creek Roads in Altona and was
developed in a number of stages,
commencing in 1946 in the western part of the current site. The
refinery proper is bounded by Millers Road to
the west, Kororoit Creek Road to the south, the Werribee railway
line to the north and Altona railway line to
the east.
!
C h e r r y L a k e
Acknowledgement:VicMap Data Copyright © The State of Victoria,
Department of Environment and Primary Industries 2014
Matter: 18706, Date: 08 January 2015, Checked by: GV, Drawn by:
SKM, Last edited by: smitchell
Location:P:\18700s\18706\Mapping\18706_F1_Locality.mxd
Legend Study Area
0 200 400 600 800
Metres ±Biosis Pty LtdBallarat, Brisbane, Canberra, Melbourne,
Sydney, Wangaratta & Wollongong
!
!
!
!
!
!
!
!
!
1.3 Heritage Listing and Legislative Obligations
The Altona Refinery complex was first recognised as a site with
heritage significance (under the then name of
Petroleum Refineries Australia (PRA) Altona) along with a number of
other early twentieth century sites
relating to the oil industry in Melbourne’s inner western suburbs,
in the Western Region Industrial Heritage
Study undertaken in 1988-9.1 The refinery was not assessed in
detail in this study but was included in
Appendix E, Locational Index to Sites, in which it was given a
Level D significance ranking, which was
considered in this study to be of local significance.
The refinery was listed in Stage 1 of the Altona, Laverton &
Newport Districts Heritage Study (2001) which
provided a review for the newly amalgamated Hobsons Bay council
area.2 It was further investigated as part
of Stage 2 of the study. As a result of this investigation, the
following statement of significance was prepared:
Mobil Refining Australia offices and refinery complex, former
Standard Vacuum petroleum is significant to the
Western Region:
as a major refinery and office complex within the industrial
history of the City and part of the State’s
post WW2 industrial expansion (criterion A4);
for the recognition of the office block as a good example of design
in the 1956 architecture guide
(criterion E1); and
for significant plant such as the Thermofor Cracking Plant which is
unique in the State (criterion F1).
On the basis of this assessment, the refinery was recommended for
heritage overlay protection pursuant to
the Hobsons Bay Planning Scheme (initially as HO149). Interim
heritage controls were implemented and the
proposed amendment was then considered by a Ministerial panel and
advisory committee.
In 2002, a submission was made on behalf of the owners to the panel
and advisory committee in reference to
the Hobsons Bay Planning Scheme Amendment C17, on the proposed
inclusion of Mobil’s Yarraville Terminal
& Altona Refinery in the schedule to the heritage
overlay.3
The submission proposed a statement of significance as
follows:
The former Standard-Vacuum Refining Company's (now Mobil) refinery
at Altona as a whole is of historical, social
and technological/scientific significance, in the context of the
twentieth century history and development of
Altona and Melbourne's western suburbs generally, and the growth
and evolution of oil refining in Victoria.
From the time it was brought on stream in 1955, the Altona refinery
has had an enormous impact on the
economic and physical development of Altona and surrounding
suburbs. The refinery has additionally been a
major employer in the area and continues to be so. As one of two
operating oil refineries in Victoria, the Altona
site has also made a major contribution to the oil industry in the
State.
1 Gary Vines and Andrew Ward Western Region Industrial Heritage
Study, Melbourne's Living Museum of the West,
1989 2 Hobsons Bay heritage study, Graeme Butler and Associates,
David Helms Heritage Planning and Management (Firm)
Hobsons Bay (Vic.), 2003-2004. Infralib: 720.99451 WIL 3 Allom
Lovell & Associates Conservation Architects, 2002, Hobsons Bay
Planning Scheme Amendment C17,
Submission To The Panel And Advisory Committee on The Proposed
Inclusion of Mobil’s Yarraville Terminal & Altona
Refinery in The Schedule to the Heritage Overlay, prepared for URS
Australia, on Behalf of Mobil Refining Australia
© Biosis 2012 – Leaders in Ecology and Heritage Consulting 5
The refinery is also a site where the significance predominantly
derives from the process as a whole, and not
from the individual elements, although some of these, such as the
TCC (which was the only catalytic cracking
plant of this specific type to be commissioned in Australia), are
also of great interest.”
The panel report for Amendment C17 supported the extent of the
exhibited HO149 (which encompassed the
entire refinery site on the north east of the Miller Road and
Kororoit Creek Intersection), and further
recommended that:
The amendment should be modified to include an Incorporated
Document that excludes all of the areas of the
site from any requirement for a planning permit for buildings and
works pursuant to Clause 43.01.
The Statement of Significance should be amended to exclude
reference to the office block across the intersection
(not in the Heritage Overlay) and to emphasis the value of the
ongoing operation of the refinery in support of the
site’s heritage values.
The Panel's report is not binding on the Council or the Minister
but it must be taken into consideration before
the Council of the Minister makes a decision. If the Council does
not adopt a recommendation of the Panel it
must give reasons why not. A permanent heritage overlay was
implemented under Amendment C17, but the
council did not accept all of the recommendation of the Panel in
relation to the Mobil Site. The Minister
approved the amendment on this basis.
The extent of the heritage overlay control is shown on Figure 3,
and is further described in the explanatory
note contained in the schedule to the overlay, which is as
follows:
Whole site with emphasis on fabric from the 1949-53 era,
specifically the offices complex facing Millers Road and
the Thermofor Catalytic Cracking Plant plus land within nominally
10m of the former offices and plant.
Figure 3: Plan of extent of existing Heritage Overlay control
© Biosis 2012 – Leaders in Ecology and Heritage Consulting 6
1.4 Consultation
Consultation during the assessment was undertaken with the client,
Mobil Australia, and Council planning
department representatives. The latter endeavoured to establish
council expectations in respect of the form
of a potential incorporated document and permit exemptions. During
this consultation the council supported
the development of an incorporated document to manage the process
of upgrade and change to the plant.
Council resolved to prepare an Incorporated Document as part of
C17; however, because of a lack of Council
resources, Mobil was advised to prepare the document. During
preparation of the document, Council advised
that an incorporated document is not the appropriate regulatory
mechanism to have in place to manage the
heritage value of the Refinery and this report has instead been
prepared to document the significance of the
Refinery and to support a planning scheme amendment to remove the
heritage overlay.
Altona Refinery is owned and operated by Mobil Refining Australia
Pty Ltd, an affiliate of Exxon Mobil
Corporation. The terms Corporation, Company, affiliate, ExxonMobil,
Mobil, Esso, our, we and its as used in
this material may refer to Exxon Mobil Corporation, to one of its
affiliates or to any one or more of the
foregoing. The shorter terms are used merely for convenience and
simplicity.
1.5 Methodology
The historic heritage assessments are based on the following
general methodology:
Review of statutory and non-statutory heritage lists and registers,
to identify the location and
significance of heritage items, places, and archaeological sites in
the vicinity of the Study Area:
– National Heritage List (NHL);
– Commonwealth Heritage List (CHL);
– Victorian Heritage Register (VHR);
– Victorian Heritage Inventory (VHI);
– National Trust of Australia (Vic) Register;
Register of the National Estate (RNE).
Desktop assessment of the environmental context and previous land
use history of the Study Area
including a review of the Hobsons Bay Heritage Study and other
assessment documents;
Preparation of a thematic history of the Study Area, based on a
review of relevant primary and
secondary historical documentation, maps and photographs, including
examination and copying of
items from the Exxon Mobil archives;
Site inspection of the refinery, photography and analysis, to
confirm the location and condition of
known and potential heritage items;
Review of cultural heritage values (or heritage
significance);
Assessment of the impacts of the proposed development on the
cultural heritage values of items;
The assessments are consistent with the principles and guidelines
of the Burra Charter (The Australia ICOMOS
charter for the conservation of places of cultural
significance).
1.6 Limitations of the Study
Access was provided to the refinery by Exxon Mobil for this study,
including internal access to most buildings
and plant. However, safety requirements precluded closer inspection
of some parts of the site – this was not
considered to have impacted on the results. No other limitations
were present in undertaking the study.
© Biosis 2012 – Leaders in Ecology and Heritage Consulting 7
2 Historic Background
2.1 Origins of oil refining
The origins of the modern oil industry can be traced to the
development of distillation of Kerosene (a
proprietary brand of paraffin) from crude oil in the mid nineteenth
century. Oil fields were established in
Azerbaijan, Poland, Romania the USA and Canada by the mid
nineteenth century. Kerosene quickly replaced
other oils used for lighting, including whale oil and coal tar.
Crude oil was heated in a vertical chamber and
the resulting compounds or 'fractions' were condensed at various
points in the column. Fractional Distillation
allowed separation of tar, lubricating oils, petroleum and diesel
products. Initially the Kerosene component
was seen as the main saleable product, but with the popularity of
the automobile, the lighter petroleum
product became more important, and so new techniques were developed
to produce a greater proportion of
this from the crude and other fractions.
Catalytic cracking (a process of breaking a long-chain of
hydrocarbons into short ones) was developed in the
early twentieth century to extract higher proportions of the more
valuable fractions from oil. The first
commercial process was developed in 1915 by Almer M. McAfee for the
Gulf Refining Company with a batch
process using aluminum chloride. However this was too costly to be
adopted widely. In 1922, Houdry and
Prudhomme first developed a catalytic process for converting
lignite coal to gasoline. Houdry applied Fuller's
earth, (a clay mineral containing aluminosilicates) as a catalyst
in converting oil derived from lignite to gasoline
and then applied the process to the catalysis of petroleum oils
converting vaporized petroleum oil to gasoline.
In 1930 Houdry moved his laboratory to Paulsboro, New Jersey at the
invitation of the Vacuum Oil Company.4
In 1931, the Vacuum Oil Company merged with Standard Oil of New
York (Socony) to form the Socony-
Vacuum Oil Company. In 1933, a small Houdry unit processed 200
barrels per day of petroleum oil. The
Houdry process was subsequently adopted in the 1930s by
Socony-Vacuum and the Sun Oil Company to
achieve 50 percent of the cracked product converted to gasoline
compared with about 25 percent from the
thermal cracking processes.
Initially only semi-batch processing was undertaken but
Socony-Vacuum then achieved continuous operation
with a moving-bed process known as Thermofor Catalytic Cracking
(TCC), which used a bucket conveyor-
elevator to move the catalyst from the regeneration kiln to the
separate reactor section. A demonstration TCC
unit was operating successfully at Socony-Vacuum's Paulsboro
refinery in 1941 producing 500 barrels per
day, and a full-scale commercial TCC unit processing 10,000 barrels
per day came on stream in 1943 at the
Beaumont, Texas refinery of Magnolia Oil Company, an affiliate of
Socony-Vacuum. By the end of World War II
in 1945, TCC units were producing 300,000 barrels per day.5
The Houdry TCC units have been claimed as a major factor in the
winning of World War II by producing high-
octane gasoline, which was critical for the more efficient higher
compression ratio engines of the Spitfire and
the Mustang used by the British and US air forces.6
The fluid catalytic cracking process was initially investigated in
the 1920s by Standard Oil of New Jersey, but
research was abandoned due to the economic depression years 1929 to
1939. In 1938, a consortium called
4 Eger Murphree and the Four Horsemen: FCC, Fluid Catalytic
Cracking, http://nacatsoc.org/history/eger-murphree-and-
the-four-horsemen-fcc-fluid-catalytic-cracking/ 5 "Houdry Process
for Catalytic Cracking". American Chemical Society.
http://www.acs.org/content/acs/en/education/whatischemistry/landmarks/houdry.html
Retrieved 18 December, 2014. 6 Tim Palucka (Winter 2005). "The
Wizard of Octane: Eugene Houdry". Invention & Technology 20
(3).
© Biosis 2012 – Leaders in Ecology and Heritage Consulting 8
Catalytic Research Associates (CRA) comprising five oil companies
(Standard Oil of New Jersey, Standard Oil of
Indiana, Anglo-Iranian Oil, Texas Oil and Dutch Shell), two
engineering-construction companies (M.W. Kellogg
and Universal Oil Products) and a German chemical company (I.G.
Farben) resumed the project. The
Standard Oil of New Jersey (now Exxon-Mobil Company) developed the
first fluidized catalytic cracking unit
with pilot plant in the Baton Rouge, Louisiana Refinery commencing
in 1940. This process employed a low
velocity gas flowing through a powder to "lift" it enough to cause
it to flow in a manner similar to a liquid. The
first commercial fluid catalytic cracking plant (known as the Model
I FCC) began processing 13,000 barrels per
day of petroleum oil in the Baton Rouge Refinery in May
1942.7
2.2 Oil and Petrol in Australia
Oil products were imported into Australia in relatively large
quantities from the late nineteenth century,
initially to supply heating, lighting, motor fuels and lubricating
oils, kerosene and other products. Product was
shipped, stored, distributed and sold in ubiquitous metal
containers; the 4 gallon kerosene tin becoming a
standard.
By the 1890s, demand was such that several major British and
American companies established centralised
import depots and a network of local agencies: Shell (c. 1900),
Vacuum Oil (1895) and the Standard Oil Co.
(c.1900).8 The Vacuum-Colonial Company dominated the Australian oil
import market for the first two
decades of the twentieth century.
The need for greater efficiencies led to the creation of new bulk
handling facilities at Shell's Gore Bay facility in
Sydney and at an old wool store in Williamstown near Railway
(Nelson) Pier, both in use in 1901. The Standard
Oil Company established its own facility in Williamstown. 9 While
other firms established branches in
Australia, including Neptune in 1909 and the Texas Company (TEXACO)
in 1918.10 Bulk shipments
commenced at Gore Bay in 1903. However, the first bulk cargo of
motor spirit arrived in 1914.11
A number of petroleum companies set up import and distribution
facilities in the Spotswood-Yarraville area in
the inter-war period including:
Vacuum Oil Co., which constructed a substantial terminal on the
river at Yarraville in 1924-5 (now
Mobil’s Yarraville terminal)
Alba Petroleum (later Ampol), a wholly Australian owned company,
which constructed its storage
compound on the west side of Douglas Parade (on both sides of the
current Sun Avenue)
The Atlantic Oil Co. (later Esso), in Simcock Avenue,
Spotswood
HC Sleigh, operating a series of tanks south of Sun Avenue in the
late 1930s.12
7 Amos A. Avidan, Michael Edwards and Hartley Owen (Mobil Research
and Development) (January 8, 1990).
"Innovative Improvements Highlight FCC's Past and Future". Oil
& Gas Journal 88 (2). 8 Shell Company of Australia Limited.
Eighty Years at Newport. p. 1; the Sands and McDougall Melbourne
Directory for
1901 lists the Vacuum and Standard Oil Companies, both of which
hailed from the United States. 9 L Strahan. At the Edge of the
Centre. p. 362-3 10 Murray, 2001. Pp.28-9 11 R Wilkinson, A Thirst
For Burning. p. 171 12 The firm was established in Melbourne in
1895 and set up as an importer and distributor of petroleum
products in
1913. Something of an innovator in the industry, by the 1920s HC
Sleigh had opened 20 service stations in Melbourne
with drive-in facilities later described as ‘35 years ahead of
their time’. From the late 1940s it traded as Golden Fleece.
R
Wilkinson. A Thirst For Burning. p. 175.
© Biosis 2012 – Leaders in Ecology and Heritage Consulting 9
The British Imperial Oil Company Ltd (a subsidiary of Shell formed
in 1905) bulk distribution terminal
with the assistance of the Melbourne Harbour Trust, on the Yarra
River at Newport between 1913
and 1915, with large holding tanks, pumping equipment and bulk
distribution facilities.13
Use of motor cars in Australia expanded exponentially in the 1920s.
Numbers of registered motor cars, trucks
and bicycles In Victoria, doubled between 1917 and 1922 to 47,750
and was over 150,000 by 1928, with about
three-quarters of these vehicles being housed in or near
Melbourne.14
The fuel demands of this growth in motoring resulted in a
considerable expansion of the oil and petroleum
industry. In addition to bulk storage facilities and packing
plants, two refineries were constructed in Australia.
The first was the Commonwealth Oil Refineries (COR) in 1922 on a
site near Kororoit Creek, Laverton and the
second was built at Clyde, NSW, by John Fell & Co in 1926,
which was purchased by Shell in 1927-28.
The Commonwealth Oil Refinery Co. was established as a joint
venture between the Commonwealth
Government and the Anglo-Persian Oil Co. with crude oil unloaded at
a dedicated wharf and bulk sto
LOAD MORE