Status of the TRIGA Fuel Fabrication Facility
Presented at the 2015 TRTR
Boston, Massachusetts
8 October 2015
Anthony Veca, Amory Quinn, General Atomics Inc.
Ghislain Boisrame, Dominique Geslin, AREVA
Status of the TRIGA Fuel Fabrication Facility
• Training, Research, Isotopes,
General Atomics (TRIGA)
• First reactor critical May 3, 1958 in San Diego, California
• 66 TRIGA facilities have
been constructed to date >1100 reactor years and 50,000 pulses
• Steady-state operating power
levels to 14 MW(t)*
• Pulsing to 22,000 MW(t)
®TRIGA is a registered trademark of General Atomics
*Tested at 16.5 MW(t)
Status of the TRIGA Fuel Fabrication Facility
• TRIGA fuel fabrication carried out at GA’s San Diego Campus
from1958 through 1995
• Fuel development o U content o U-235 enrichment
• Reactor design o Standard TRIGA o MTR Conversion
• Fuel element designs o Low Power Designs o High Power Design
TRIGA Fuel Fabrication Facility
Status of the TRIGA Fuel Fabrication Facility
38-mm Diameter Fuel Element
25 rod Fuel Cluster
13.8 mm Diameter Fuel Rod
High Performance Fuel Design
Standard Fuel Design
MTR Replacement
4 – Rod Cluster
Status of the TRIGA Fuel Fabrication Facility
• Licensing fees for the fuel fabrication facility in San Diego became expensive during the early 90s
• GA investigated relocating the fuel fabrication facility to reduce the escalating costs
• TRIGA International, SAS TI was founded o A 50 / 50 Joint Venture between General Atomics and CERCA (AREVA)
o A French company with headquarter in Paris, Fabrication facility in Romans sur Isere
Status of the TRIGA Fuel Fabrication Facility
• The TI joint venture has been very successful
• Fabricated more than 1000 fuel elements
• Converted 7 TRIGA reactors from the use of HEU to LEU o Romania (1/2 core)
o Texas A&M University
o Washington State University
o Oregon State University
o Wisconsin University
o Neutron Radiography TRIGA (Idaho National Laboratory) o Mexico City (ININ)
• Provides replacement fuel for TRIGA reactors as part of the US-DOE University Program
• Provides replacement fuel for other worldwide TRIGA REACTORS
TRIGA International Experience
Status of the TRIGA Fuel Fabrication Facility
• GTRI HEU/LEU conversions were coming to an end with the completion of the ININ Mexico City conversions (1Q – CY 12)
• TI fuel fabrication facility faced uncertain future
o French Safety Authority (ASN) required safety upgrades
o Maintenance and other facility upgrades
o There were very few new orders
• TI informed the TRIGA community in early 2010 that fuel
fabrication would be stopped to make the necessary upgrades
• Fukushima accident and the ensuing regulatory changes
complicated situation even further
• Strategies for restarting the facility were being considered based
on TRIGA community fuel needs
Status of the TRIGA Fuel Fabrication Facility
• Upgrade Strategy for TI’s fuel fabrication facility
o Maintain Facility in its current location
o Upgrade/repair/maintain current process and fabrication equipment
o A fuel fabrication facility capable of meeting current needs
Status of the TRIGA Fuel Fabrication Facility
• Upgrade strategy presented to DOE-NNSA
• Strategy viewed favorably, NNSA would support it.
o Blanket Master Contract (BMC) – Aug 2013
• SOW for fuel fabrication restart 2nd Qtr. 2017
o Release 1 to BMC: $2.85M – Sept 2013
• Feasibility study and preliminary/final design phases
• Period of Performance Oct. 2013 – Dec. 2014
o Release 2 to BMC: Proposed - $6.175M – Nov 2014
• Regulatory Submissions and subcontract awards
• Period of performance Jan 2015 – Jun 2016
Status of the TRIGA Fuel Fabrication Facility
Fuel Fabrication Facility Upgrade Schedule
J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
Site Work and Tesing
TIME NOW
Licensing
Feasibility
Detailed Design
Procurement
Supplier Studies and Manufacturing
Process
Qualification
2013 2014 2015 2016 2017 2018
Product Qualifiaction
Start Fuel Fabrication
Status of the TRIGA Fuel Fabrication Facility
• NNSA stated that their continued support of the TRIGA fuel fabrication facility upgrade was no longer within the objectives established by congress because it was not directly supporting HEU/LEU conversion
o Therefore they could no longer fund the upgrade activities
• However NNSA wanted to find an equitable stopping point within
the current funded Release 2 Contract
o TI working with the INL Project Manager developed five options to complete
the NNSA involvement with the TFFF Upgrade
• NNSA selected Option 3 for their termination of the TFFF Upgrade
o Support the completion of the final design for the facility upgrade
o Support all safety/licensing up to the completion of the Article 26s (PSARs)
and their submittals to the ASN
o Support all subcontractor design and specifications and vendor selection
o No procurement
Status of the TRIGA Fuel Fabrication Facility
• TRIGA community responded with very aggressive and positive support for continuing the TFFF Upgrade
• IAEA held a special consultancy with US and International representation
o IAEA urged all members to contact DOE-NNSA and DOE-NE to gather
support
• TRTR also urged members to contact lobbyists and other support groups to write letters to DOE and congressional members
• DOE – NE Support
o Kenny Osborne championed the TRIGA International cause,
o Provided the high level support needed to re-establish the TFFF Upgrade
project
o Provided the funding required to continue the Upgrade project
Status of the TRIGA Fuel Fabrication Facility
1 Kick-Off Meeting X 10/15/2013
2 Project Execution Plan X 11/15/2013
3 Risk Analysis Report X 12/31/2013
4 Meeting with ASN X 2/28/2014
5 Feasibility Study Documentation X 3/15/2014
6 Start Preliminary/Final Design Phase X 3/31/2014
7 Preliminary/Final Design Execution Plan X 4/28/2014
8 Draft Article 26 (PSAR) X 7/31/2014
9 Issue Article 26 (PSAR) to ASN X 1/31/2016
10 Final Prelim/Final Design Studies X 9/30/2015
Forecasted
Date
Release 1
Deliverable NNSA NE
Status of the TRIGA Fuel Fabrication Facility
1 Kick Off Meeting x 1/15/2015
2 Project Execution Plan x 1/30/2015
3 Dismantling Article 26 (PSAR) x 9/30/2015
4 Hydride furnace - Subcontract Award Doc x 9/30/2015
5 Fusion Furnace - Subcontract Award Doc x 9/30/2015
6 Misc and Ventilation - Subcontract Award Doc x 11/30/2015
7 Begin site work order x 2/28/2016
8 ASN approval for dismantling x 2/28/2016
9 Hydride fuel design document x 5/31/2016
10 Vendor design docs misc and ventilation x 6/30/2016
11 Vendor design docs fusion furnace and hoods x 5/31/2016
12 Work Status Report - completion of work. x 5/31/2016
13 ASN approval for modifications Art 26 (PSAR) x 12/26/2015
14 Fabrication Facility Equipment accept criteria
15 Approved Testing Document for initial test
14 Additional Safety requirements x 10/31/2015
Release 2
Deliverable NNSA NEForecasted
Date
Status of the TRIGA Fuel Fabrication Facility
• Release 3 Contract o Complete building and equipment installations and testing
o Scope of Work
• Finalize all procurements
• Receive all equipment on site
• Install all equipment
• Make necessary modifications
• Revise existing operations and maintenance procedures
o Period of Performance, August 2016 to July 2017
• Release 4 Contract o Process / Product Qualification
o Scope of Work
• Verify process parameters using depleted uranium
• Train operators
• Finalize Procedures
o Period of Performance, June 2017 to December 2017
Status of the TRIGA Fuel Fabrication Facility
2015 2016 2017 2018
RFP for 7 subcontracts
(submittal, bids, vendor selection, contract awrard)
Design studiesArt 26 Upgrade
Design studiesArt 26 Dismantling
ART26 Upgrade submittal
ART26 Dismantling submittal
ASN RAIs
KOM, PMP, SCHEDULE...
ART26 Upgrade ASN approval
ART26 Dismantling ASN approval
ASN RAIs
ART26 for TRIGA into ATLAS
ART26 ATLAS submittal
ASN RAIsART26 ATLAS ASN approval
Vendor studies (Hydride furnace)
Vendor studies (Fusion furnace)
Vendor studies (Dismantling)On-s ite vendors installation and testing
Process qualification
Product qualification
Manufacturing (HVAC, Hoods and GB, Misc Works, MES)
Hydride furnace manufacturing
Fus ion furnace manufacturing
Dismantling operations
Vendor studies (Misc works, HVAC, Hoods and GB, MES) Fuel fabrication
Commissionningreport to ASN
ASN approval
Schedule for completion of TFFF Upgrade
Status of the TRIGA Fuel Fabrication Facility
• The TRIGA International fuel fabrication facility has played a key role in the supply of TRIGA fuel elements o Replacement fuel for US and International facilities
o Replacement fuel for GTRI’s HEU/LEU conversion program
• The TI facility needed safety and maintenance upgrades to meet latest French regulatory standards including post – Fukushima requirements
• DOE-NNSA originally committed to upgrade the facility
• Following the Release 2 contract DOE-NNSA determined that it could not longer support the upgrade o Agreed to a closeout option which included completion of licensing and
vendor selection
• DOE-NE championed the cause and decided to support the completion of the facility upgrade
• Smooth transition from NNSA to NE o Minor deliverable mods to be negotiated
• Restart of fabrication – end of CY 2017
Conclusion