368
Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website. Environmental and Social Performance Report November 2012 Pakistan: Karachi Electric Supply Company Post Privatization Rehabilitation, Upgrade and Expansion Prepared by Karachi Electric Supply Company Karachi, Pakistan

Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2

The Environmental and Social Performance Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website.

Environmental and Social Performance Report November 2012

Pakistan: Karachi Electric Supply Company Post Privatization Rehabilitation, Upgrade and Expansion

Prepared by Karachi Electric Supply Company Karachi, Pakistan

Page 2: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 3: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 4: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES2013

KESC

KESC RESPONSEAGAINST ANNUAL MONITORING REPORT 2011-12

AUGUST - 2013

ASIAN DEVELOPMENT BANK QUERIES2013

KESC

KESC RESPONSEAGAINST ANNUAL MONITORING REPORT 2011-12

AUGUST - 2013

ASIAN DEVELOPMENT BANK QUERIES2013

KESC

KESC RESPONSEAGAINST ANNUAL MONITORING REPORT 2011-12

AUGUST - 2013

Page 5: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KESC authorized representative to be contacted on the AMR:

Name : Chander PerkashTitle : General Manager (Corporate Compliance)Tel : +9221-32647048Cell : +92300- 2910106Email : [email protected]

ADDRESS:

12th Floor, Technology ParkShahra-e-Faisal,Karachi - Pakistan.Phone: +9221-32647048

Page 6: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

PageNo.

SectionNo.

Description/Titleof Section

Comments / Remarks KESC response

20 3.2.2 On publicconsultation

Please provide (i) scheduleof consultations withvarious stakeholders, (ii)summary of issues raised byrespective stakeholdergroups, and (iii) how theseissues were resolved.

Does the "open door" policyfor community consultationrefer to KESC's grievancemechanism? Who or whatunit can an aggrieved partyapproach? Where is thisperson or unit located?Please discuss whatissues/complaints wereraised, and how these issueswere resolved.

As a part of SEIA, area stakeholderare consulted and a general publichearing which is open for all isorganized before each project toensure maximum input from public.

Whistle Blower Policy is in place forboth internal and Externalstakeholders.

AZM Speakup – Whistle BlowerPolicy:

Communication Platforms through adedicated helpline number, emailaddress and text messaging option isestablished. External customers canalso write to us on our very activesocial media platforms of twitterand face book. The messages arereceived by our customer servicesdepartment and passed on, if needbe to the highest managementauthority.

Direct Community relationships arealso established by our stakeholdermanagement teams under thesustainability managementdepartment. They work along withthe operational team to resolveproblems.

A separate helpline and customercare contact is established forindustrial customers.

21 3.2.3(2nd

paragraph)

Social andCommunityEngagements

Please provide ADB a copyof the Multi-StakeholderEngagement Strategy.

Attached as Appendix “H”

34 3.2.7 Social Media andAssets Branding

Please discuss the contentof the VSS scheme.

Final VSS (as distinct to VSS offeredon 31st Dec.2010) was offered toNon Core employees on 29th June

Page 7: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Was the VSS schemediscussed with and foundacceptable by the laborunion? During discussions,what were the concernsraised and agreementsreached? What are theremaining issues with theunion, if any?

2011 and remained in force upto10th Feb. 2012.

It provided the following benefits:

1. Ex Gratia payment of oneBasic Pay for every month ofremaining service subject toa maximum of 85,

2. Encashment ofEarn/Privilege LeaveBalance

3. Provident Fund as perCompany Rules

4. Gratuity as per entitlement5. Upfront Payment of post

retirement Medical [email protected] Basic Pay

6. Upfront payment of cashequal to 5 years postretirement. electricitybenefits

7. Salary for illegal absencesduring period of illegalstrikes

8. Total pay out of FVSS to be5-15% higher than that ofVSS offered on 31 December2010.

(The Minimum total FVSS Pay out:::Not less than Rs.721,000/=disregard of length of service)

The following formal Meetings wereheld with Unions:

1. Two meetings were heldwith the then CBA, namelyLabour Union on 23 Mayand 25th May 2011.Subsequently on 3rd June2011 Supreme Courtannounced its Landmarkdecision declaring that NIRChad not any jurisdiction overthe organizations

Page 8: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

incorporated and operatingin provinces. As aconsequence all the unionsregistered with NIRCbecame defunct and losttheir status as CBA. Weissued an AdministratorCircular to the effect on 10th

June 2011, which waschallenged by the defunctLabour Union in the HighCourt and still holds, as ithas not been set aside bythe Sindh High Court.

2.. After the loss CBA status by LU,Management invited all the defunctUnions, i.e. KESUTY Union, LabourUnion and Peoples Workers Union,who had come together on theplatform of Mazdoor Etihad.

Two meetings were held with themon 17 June and 23 June to discussthe issue of surplus noncore staffbut due to intransigence of theactivists of defunct LU no agreementcould be reached with the defunctUnions. But these meetingsbrought forth the differences amongthem and KESUTY Union parted itsway from Mazdoor Etihad andpublically criticized former CBA forits intransience and noncompromising attitude.

Consequently the Management hasto unilaterally announce the aboveFVSS on 29 June 2011.

The Union Leaders in their abovemeetings raised the followingpoints.

1. Policy of outsourcing bereversed and all noncorestaff be taken back on their

Page 9: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

jobs.2. All those dismissed/

terminated for violentmisconduct, unauthorizedabsence during illegal strikesor dismissed on theftcharges after domesticinquiry be reinstated withback benefits.

3. Those who absented fromwork to participate in illegalstrike be paid salary for theperiod of unauthorizedabsence.

On 26thJuly In Governor HouseGovernment officials held separatemeetings with the Management andleaders of the defunct Unions andthe following agreement wasexecuted;

1. Post FVSS retrenchment deferred.

2. Dispute Resolution Committee ofrepresentatives of Administration,KESC Management, and defunctUnions be formed within one weekto address disputed matters.

No agreement could nottake place on the formationof the Dispute ResolutionCommittee due touncompromising behaviourof defunct Labour Union.

35 3.2.7 In what context did KESCemployees suffer during theprotests? Were theyharassed by the laborunion? But are theymembers of the union?

1. There were numerousincidents of physical assaulton the teams attendingcustomers complaints.Contingents of armed workerrode on motor bikes andresorted to violence againstthe team of workers carryingon repairs and maintenancein the different parts of thecity. Team of workers were

Page 10: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

fired at and harassed andthreatened for life.

2. Employees were forced toclose complaintcentres/offices.

3. The officers were encircledand besieged employeeswere released by the Lawenforcement agencies.

4. Dispatch of PMTs and othermaterials from Central Storesto different locations wasforcibly stopped to ensurethat customers were notattended and rectified intime.

There were armed attacks at officesand there were incidents ofencounter with police which hascome to the rescue of besiegedoffices/employees.

40 3.3 Major Challengesand Issues for theCompany

With the reported five (5)fatal accidents, pleasediscuss:

(i) what measureswere put inplace to avoid orminimize theseaccidents?

(ii) what is KESC'shuman resourcepolicy regardingworkers'involved in fatalaccidents? DoesKESC providelife/healthinsurance to itsworkers? Whatassistance orcompensationdid KESCprovide to theworkers (andtheir families)involved in

Measures to prevent reoccurrencesare attached as APPENDIX – “B”

Notable measures include

Development of SOP forLine Isolation

Improvement incompetence level throughtraining and awareness

Increased safety inspections Enhancement of reward for

compliance of SOPs and Strictness of reprimands

against non-adherence ofSOPs.

The legal heirs of those who die infatal accidents are provided thefollowing special benefits;

Insurance: Rs200,000= Special

Compensation/Insurance: Rs300,000/=

Page 11: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

these accidents? Funeral expenses:Rs.20,000/=

Post funeral expenses: Rs.50,000/=

Widow’s Grant: Rs. 20,000/= Saleeka Sewing Machine for

widow.

In addition the heirs also arepaid/allowed their following normalbenefits:

Gratuity Provident Balance Encashment of Leave

Balance Besides the children of

deceased get medicalbenefit till the age of 25.

Widow medical for 5 years.

Medical for children upto age of 2540 3.3 The section discusses the

negative media coverage ofthe project totaling to 764news items. Please clarify ifthis monitoring of newsitems includes those of thelabor disputes between theunion and KESC, covered bynational/local newspapers?

It covers the total of news itemsrelating to KESC. The 764 newsitems may include the itemspublished relating to labor disputesbetween unions and KESC.

231 Nos. were related to the loadshedding and power break downissues, 180 were views of the publicoffice holders, political parties,business and industry leaders, 141were letters to the editors focusingKESC’s business operations and 212news items were KESC point ofviews and clarifications.

41 4.0 Compliance withAction Plan

(Revised:October 02,2009)

The table indicates“Compliance with ActionPlan (Revised: October 02,2009). Is there a moreupdated table for thereporting period (July 2011– June 2012).

The status of compliance to ActionPlan is updated for the period June2013. APPENDIX “C”.

44 4.0

(Item

Compliance withAction Plan

Why is the Bin QasimCapacity EnhancementProject indicated as

Initial feasibility was conducted for575 MW, when design commencedand specifications were drawn it

Page 12: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

8) (Revised:October 02,2009)

575MW? Shouldn’t this be560MW?

became as 560 MW. At ISOconditions its 572 MW gross.

46 5.1.1 HSEOrganization,Budget andReporting Line

Please provide annual datafrom 2007–2012 of KESC'shuman resources/staff(male:female:total).

Please discuss anysignificant reductions instaff or employment of newstaff.

Please discuss/summarizeKESC's human resourcespolicies in terms of (i)policies that promoteopportunities oradvancement of womenemployees, (ii) policies thatpromote local employment,especially those to theaffected communities,and(iii) policies that complywith the national labor lawsand with the relevantinternational laborstandards.

Year Male FemaleTotalHeadcount

30Jun2007

17494 348 17,842

30Jun2008

17,278 351 17,629

30Jun2009

16,806 381 17,187

30Jun2010

16,548 396 16,944

30Jun2011

15,623 298 15,921

30Jun2012

11,165 212 11,377

Numbers of employees havereduced because few employeeshave taken voluntary separations.Few employees have also retired.

i) There were no concept for womenemployment in KESC but newmanagement promotesemployment opportunity for womenand numbers of female employeeshave been increasing.

ii) We highly promote localemployment opportunities, most ofour employees belong toKarachi/Sindh.

Recruitment is made on merit.Almost all new recruits are residentsof Karachi or its adjoining areas.

We are fully compliant of labour andWelfare Laws and relevantinternational standards and

Page 13: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

practices as adopted by theGovernment of Pakistan.

47 5.1.2 Please refer tothe table entitledDetails of S& EAssessmentprepared duringthe reportingyear.

The quoted “Appendix B”which refers to the EPA NOC132 KV Gulistan E JauharGrid,mentions the NOC willbe emailed. Please provideADB a copy of this NOC.

Please clarify if the new 220KV Grid Station to beconstructed at Gulistan-e-johar is under the originalscope of work for ADBfinancing.

If yes, it would be helpful todiscuss results of the S&EAssessments done. Thereport also notes that theEIA considered thecumulative impacts tovulnerable people, henceplease discuss the impactsand the measures designedto avoid or minimize socialimpacts. Please also sharecopies of these new EIA/IEEsto ADB.

NOC for Gulistan-e-Jauhaur Grid isAttached as APPENDIX – “D”

No, it was not a part of ADBfinancing

SEIA of 220 KV Gulistan-e-JauharGrid is attached asAPPENDIX – “E”

48 5.1.5 S&E Performance In the preparation of thefirst Sustainability Report, itis good that activities ofaffected and nearbycommunities as well asother stakeholders will beconsidered. Since KESCplans to maintain thispractice, KESC may considertaking into considerationthe workers and labor unionamong its stakeholders as itis critical to consider theworkers and the unionpartnership in forging amore sustainablerelationship and growth for

Since there is no union in place,communication with employeesspecially the non Management Staffis important. All employees of KESCwent through a vision and valuesystem training program whichinculcated confidence in the overallemployee base. This also gave usopportunity to establish acommunication platform for allemployees.

We value an open dialog on integrityand responsibility in our actions withour employees. A directcommunication bridge has beencreated between the leadership andthe employees through various

Page 14: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

the company. communication mediums whichincludes a confidential emailaddress, PO BOX and hotline.Employees can directly reportmisconduct or any unethical practicethrough these mediums. Disclosureof names is not necessary.

Our employees are also encouragedto report their views on processesand practices to their manager orthe Business Ethics Committee.These reporting mechanisms arepart of the complaints procedureand are described in our code ofconduct.

Employees are also encouraged togive suggestions and feedback on aspecific topic or idea. Investigationson a specific compliant are orderedby the highest authority of therelevant department. Weinvestigate all alleged breaches ofour code and apply appropriatemeasures when complaints turn outto be substantiated.

49 5.2.1 InternalGrievanceMechanism andWorkers Issues

Please discuss KESC'sgrievance mechanism interms of structure,composition, and procedurein resolving labor disputes.In the past 2 years (or atleast during the reportingyear), describe how manyworker complaints havebeen received, the nature ofcomplaints, andactions/measures adoptedto resolve these issues.

Moreover, it is noted thatKESC policy allows itsworkers/staff to organize orjoin the labor unions. Please

Grievance Procedure is as such;

1. Every employee is free toraise his grievance with hisimmediate supervisor, orwith Supervisors supervisor.In case he is not satisfiedwith their response, he mayraise it with Head IndustrialRelations/ HR.

2. In case an employee isaggrieved by the decision ofan inquiry Committee, hemay submit a grievancepetition to the ReviewCommittee as provided forin the Law.

Page 15: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

provide data on how manyworkers are labor unionmembers. Describerelationship of KESC withthe existing workersorganizations.

All the unions have been rendereddefunct as a corollary the aboveSupreme Court decision. ButManagement’s relations with theactivists of various Unions who arestill in the service of the Companyare cordial.

49 5.2.2 Status of CBA inKESC

In addition to the status ofthe various labor unions orworkers' organizations inthe courts, please alsoprovide additionalinformation on the last CBAnegotiated, and theexpected negotiation ofnext CBA.

Last CBA was determined under aFederal Law on 21st August 2009 fora period of 2 years expiring on 20August 2011. It served a Charter ofDemand and after negotiations aSettlement was signed with them on3rd April 2010.

At present there is legal dispute as aconsequence of the 18th

amendment in the Constitutionwhich transferred the subject ofLabour to the Provinces. Once theSindh High Court decides as to theLaws which will regulate industrialrelations in future. Hence it is notpossible to indicate the date of nextreferendum for determination ofnew CBA.

49 5.2.4 InvoluntaryRetrenchment

It is noted that noretrenchment was donefrom July 2011 to June 2012.However, about 4,000 KESCworkers were retrenched inJan-Feb 2011(http://www.pakworkers.com/kesc/kesc-workers-bite-the-hand-that-gave-them-golden-handshake/). Furtherto this, retrenched workerssubmitted a memorandumto the Supreme Court, andin December 2012, 67disabled workers wereordered reinstated(http://www.accessmylibrary.com/article-1G1-280550158/retrenchment-kesc-workers-submit.html ;)http://dawn.com/2012/12/18/reinstatement-of-67-

As stated in response to 01 aboveFVSS was launched on 29th June2011 for a period of 2 weeks ending15th July but to facilitate theemployees and in deference to thedecision in the Governor House on26th July the FVSS option was keptopen till 1oth Feb,2012.

After the closure of FVSS only about1182 of the 4500 remained on thepay Roll and they were retrenchedin February 2012.

Some disabled employees filed apetition in the Supreme Court andthe Court ordered theirreinstatement. The decision hasbeen pended as Management hasfiled a review petition in the Court.

Page 16: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

disabled-employees-in-kesc-ordered/ ).

It is noted that KESC hasprepared and finalized avoluntary separationscheme (VSS) in June 2011.Please share a copy to ADB.

Does KESC have a laborrestructuring plan tomitigate the retrenchments?

In relation to the laborrestructuring plan and/orthe VSS, please discuss: (i)rationale for theretrenchments, (ii)assessment on the expectednumber of workers to beretrenched, (iii) has thisbeen prepared inconsultation with theworkers and the laborunions? (iv) what mitigationmeasures/options werepresented to the workers(e.g. unemploymentinsurance, severancepayments, early retirementpensions, retraining,redeployment,compensation, and otherassistance such ascounseling, job brokerage,etc.) (v) discuss status ofimplementation of the laborrestructuring plan or VSS,including schedule ofretrenchments in past yearsand in the future, number ofworkers compensated /assisted, etc.

Please also providedocumentation ofconsultations with workers.

Copy of the FVSS Scheme is attachedas APPENDIX “F”

1. Noncore functions wereoutsourced to thecompetent serviceproviders.

2. About 4500 employees whowere performing non corefunctions were renderedsurplus and were offeredvoluntary separation with abenevolent separationpackage.

3. Only 1180 employees whodid not opt for voluntaryseparation were retrenchedas provided for in the Law.Those retrenched were alsooffered all the benefitswhich were offered to theOptees of FVSS. In additionthey were also given onemonth’s salary as admissibleto the retrenched under theLaw.

4. The benefits given to theOptees of FVSS/retrenchedwere excessively benevolentand humane. Evenemployees with 1-2 yearsservice were offered aminimum pay out ofRs.721000/= or so.Maximum payout was aboutRs.4.9 Million.

The Management tried hard tonegotiate terms of VSS with theUnions. The copies of the emailsexchanged with unions in May, andJune 2011 are attached atAPPENDIX “G”. Copy of decisionstaken in the Governor House on 26July is attached at APPENDIX “H”The futile correspondence for theformation of Dispute ResolutionCommittee as envisaged in the

Page 17: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

meeting in the Governor House on26th July 2011 is attached asAPPENDIX “I”

We do not plan to retrench furtheremployees in immediate future.Both the past voluntary andinvoluntary schemes have beendetailed above.

51 5.2.7 Description ofAccidents

Statement inconsistency: “Atotal Thirty (21) incidents…”

Typing error; total of 21 accidentsoccurred during the reporting period(July 2011 – June 2012) reattachedas APPENDIX- “J”

54 5.3.5 Air EmissionPerformance ofthe Company

Kindly complete theSummary table of airemissions performance ofKESC during the reportingperiod 2009-2010. Itappears incompleteespecially the last 4columns.

Please confirm if there isalso a more updated tablefor the reporting period July2011 to June 2012.

The summary table is for the periodfrom July 2011 to June 2012 which isupdated and reattached asAPPENDIX “K”

55 Please fill out the blanktable on page 55 (columnsfrom Year 2006 to Year2012.)

Attached as APPENDIX “K”

56 5.4.2 General PublicInjuries andFatalities. Pleaserefer to thesummary table bentitledIncidents/Fatalities Associatedwith theCompany’sAssets.

Statement inconsistency: "Atotal of fifty seven (30)fatalities...."

Please discuss theprocedures on how thecompany compensates theaffected persons.

Typing error; a total of 27 publicfatalities occurred during the period2011 – 12. APPENDIX “ N”

56 5.4.3 EmergencyPreparedness,Response Plansand Community

With the number offatalities among the public(community people) in thepast years, we agree with

Work on Emergency Preparednessand response Plans for communitiesare in progress and considering thebusiness area and complexity

Page 18: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Participation KESC that it is critical that anEmergency Preparednessand Response Plans for theCommunities be preparedsoonest.

involved of KESC this exercise istaking its time.

116 Appendix B

EPA NOC 132 KVGulistam-E-Jauhar Grid

Refer to comment for page47. Please provide thescanned copy of the NOC.

Attached as APPENDIX – “D”

203 EHS Audit of T&D Assets(Findings andRecommendations)

Please provide the date theEHS audit was conducted.And who conducted the EHSAudit.

Please indicate whatfindings in the EHS AuditTable have been addressedor corrected already.

EHS Audit of T&D Assests wasconducted by M/S EcoConServEnvironmental Solutions a companybased in Cairo, Egypt during theperiod 08th -15th April, 2010

Compliance status of the auditfindings is attached as APPENDIX“M”

295 EHS Audit of T&D Assets(Findings andRecommendations)

Please clarify if this EHSAudit of T & D Assets(Findings andRecommended Actions) isthe same on page 203.

It is same

Page 19: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “A”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “A”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “A”

Page 20: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SEEDS: Stakeholder Engagement & Enrichment Drives forSustainability

We firmly believe that KESC's own turnaround and sustainability isfundamentally linked to the economic, social and environmental valuesthat we create for a diverse set of stakeholders whom we serve andengage on a daily basis.

SEEDS is a holistic approach that fully recognizes the impact of ourperformance in sustainable development across our stakeholders’ universe. A 360 degree valuecreation model, SEEDS essentially drives four distinct programs– ESG Initiatives, SocialInvestment Programs, Stakeholder Engagement and Thought Leadership.

ESGInitiatives

SEEDS: Stakeholder Engagement & Enrichment Drives forSustainability

We firmly believe that KESC's own turnaround and sustainability isfundamentally linked to the economic, social and environmental valuesthat we create for a diverse set of stakeholders whom we serve andengage on a daily basis.

SEEDS is a holistic approach that fully recognizes the impact of ourperformance in sustainable development across our stakeholders’ universe. A 360 degree valuecreation model, SEEDS essentially drives four distinct programs– ESG Initiatives, SocialInvestment Programs, Stakeholder Engagement and Thought Leadership.

KESC’sSEEDS

StakeholderEngagement

SocialInvestmentPrograms

ThoughtLeadership

ESGInitiatives

SEEDS: Stakeholder Engagement & Enrichment Drives forSustainability

We firmly believe that KESC's own turnaround and sustainability isfundamentally linked to the economic, social and environmental valuesthat we create for a diverse set of stakeholders whom we serve andengage on a daily basis.

SEEDS is a holistic approach that fully recognizes the impact of ourperformance in sustainable development across our stakeholders’ universe. A 360 degree valuecreation model, SEEDS essentially drives four distinct programs– ESG Initiatives, SocialInvestment Programs, Stakeholder Engagement and Thought Leadership.

SocialInvestmentPrograms

Page 21: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

Stakeholder EngagementVarious tools and methods have been employed to create meaningful, multidirectional links with all ourstakeholders.

Brand ManagementTo bring about a lasting change, KESC has had to focus on educating the consumers and shifting theirperception, thereby leading to a shift in behaviours. By employing various awareness based, anti-theftand recovery campaigns, KESC has achieved great success in this respect. These campaigns have usedadvertising as an important tool and, as research has shown, have improved the image of the companydramatically. Our goal is to create business value to continuously build and enhance the brand equity ofKESC with the help of effective and cohesive multi-channel communication. At the same time our effortshave also been geared towards creating awareness, changing behaviors and bringing about a positiveperception shift through tactical communication.

Special Initiatives Taken:

Implemented existing identity with communication guidelines

KESC Centenary Program to highlight our 100th year as a company

3600 campaigns on monsoon specific public safety

Testimonial based IBC campaigns to introduce the state-of-the-art offices providing onewindow solutions and quality service with government requirements via differentmediums

Recovery campaign

Marketing Initiatives:

17 TVCs

Over 450 press ads

KESC Offices Branding: Branded over 37 key KESC locations with our Corporate identityas well as AZM values

Branding of different premises of our SIP Partners under the Empowerment Programat strategic locations

Preparation Annual Report and Sustainability Report

Branding of Various Corporate Events

Page 22: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

AZM HUSN-E-NAAT COMPETITION

THOUGHT LEADERSHIP FORUMS

AZM MANAGEMENT CONFERENCES

Town Hall Meeting

CONSUMER ENGAGEMENT:

SMS & Email:Over 7.9million E-mails and 8.5 million SMS were sent to external stakeholders during the reportingperiod, informing them of various initiatives, updates and developments at KESC.

Brand Tracker ResultsKESC Brand Equity Index has shown steady increase from last 4 waves and now the Brand Equity Indexhas reached to a respectable 3.2.KESC’s performance has improved on all of the perception indicators.All Service and Billing indicators for KESC have increased as well. All company attributes posted somegains. Despite gains all of these attributes, except one, are much lower than the 60% Top2 boxacceptable scores suggested according to Nielsen’s methodology. For Theft positive indicators havegone down while negative indicators have gone up.

Media ManagementWe have strengthened contacts with media from different tiers. This ensures that KESC’s stance on allissues is portrayed accurately. We maintain an open, accessible and transparent relationship. Over thelast few years we have been playing an active role in educating the media about the real time challenges

and problems faced by the energy sector. We have continued to hold interactive dialogues and sessions.As a result the media’s role in the power sector has evolved into becoming more critical and responsible.

183 news items about Load Shedding & Power Breakdowns including KESC’s pointof view

90 Statements about Political Parties, Industry, Business & Trade Associations115 Letter to Editors/Articles/Editorials containing positive suggestions and critical

analysis145 articles showcasing KESC’s Point of View

Social MediaKESC has increased its presence on social media focusing on Facebook, Twitter & LinkedIn to allow directand real-time interaction with external stakeholders, making us the first utility sector company inPakistan to utilize these mediums for complaint resolution, consumer queries at the same time keepingthe public informed.

Page 23: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

4

External Stakeholders

The Movers & Shakers of the Energy sector

KESC’s management and leadership are engaged in a constant dialogue with all key stakeholders in theenergy sector, be it ministries, regulatory bodies, power sector players or key suppliers with focus oncritical policy issues of the overall power sector. We have requested and initiated review of the NEPRAAct, review of the Electricity Act, and have also raised issues of inconsistencies between these two.Electricity theft, electricity conservation, fuel supply constraints, tariff rationalization and circular debtare issues brought forward for the first time by KESC.KESC is the only power sector organisation which ison the Prime Minister’s commission constituted through the Ministry of Water and Power onelimination of subsidy and finding solutions to the power crisis in the country.

Industries & Trade Associations

Our regional heads and CEO secretariat are in direct dialogue with all key trade associations andindustries in order to keep them informed about the real time challenges and problems faced by KESC.They are engaged through various trade association platforms on different power sector issues like fuelshortages, energy efficiency and tariff hikes, etc. Their advice is sought in advance for any issue that willhave an effect on their performance.

Shareholders

Annual and quarterly financial reports are printed regularly for the shareholders and overall stakeholderuniverse. This Sustainability Report is our initiative to report in detail the economic, social andenvironmental initiatives of our organisation. By providing a more detailed perspective of our operationsto our stakeholders, we feel that we are fulfilling our promise of open, transparent communication. AnAnnual General Body Meeting is held to address and clarify developments and conflicts of interest.

Key Stakeholder DatabaseTo encourage the sharing of complete information, an extensive database comprising key stakeholdersacross the spectrum has been developed to inform them of key initiatives taken by the company on atimely basis. It is also used as a method to communicate important developments related to theorganization. Over the last fiscal year, some 16 million emails have been sent.

External NewsletterUmeed, our external electronic newsletter reaches over 300,000 stakeholders on a monthly basis viaemail. It covers major events and updates for the month. The objective is to communicate Energy Sectorand KESC related issues and developments to the citizens of Karachi.

WebsiteOur website, www.kesc.com.pk, showcases our operational, environmental and social investments andprovides updated reported information. It is also a major facilitation tool for customers to downloadtheir bills, get new connection related information and register their complaints.

Internal Stakeholders

Emails are a general mode of communication that the KESC management uses to interact with allemployees. Any general information, development, announcement or issue is communicated through

Page 24: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

5

email memos in English and Urdu. The employees can also address the KESC management through thismedium to express their views, air grievances and give feedback.

IntranetThe company’s intranet serves as a communication platform for employees.The purpose of the portal isto keep business units updated with the most recent activities taking place within the organization,along with providing a secure place to share and access data when required.

Internal NewsletterAzm is our monthly internal newsletter in Urdu, which updates and unites the community of our 11,000plus employees to keep them abreast of all recent developments.

Page 25: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

6

Different programs and events were held throughout the year to interact with all tiers of employees inmeaningful ways:

AZM – Culture Change DriveDriving productivity through people – AZM is perhaps the largest change management program in the corporatehistory of Pakistan, covering our top leadership, middle management and our non-management staff by holdingsessions to instill uniform and responsible values in all our employees while strengthening management-employeerelationships. In total, almost11,000 employees have been reached with this initiative. In the last fiscal year wecovered our Non-Management Staff and our Middle Management.

AZM Husn-e-Naat KhwaniIn the holy month of Ramzan, a company-wide Naat contest was arranged and conducted, starting with auditionsand short listing. 20 contestants took part in the finale where they were assessed by a panel of expert judges fromQ-Tv and ranked accordingly.

Town Hall Meeting

A town hall meeting was organized with the intention to provide a platform for employees to expresstheir views and be apprised of where the organization stands, and where it is heading. The occasionwas also used to celebrate the careers of some of our longest-serving employees with mementospresented to a number of our most loyal staff.

Disclosure on Stakeholders engagement by type and frequency

Stakeholder group Type of engagement Frequency of Engagement 2009-12

Federal & ProvincialMinistries

Meetings and written communications onvarious issues

Ongoing on day to day basis/ Regularparticiaption in all Energy Conferences heldannually

Regulatory Bodies (NEPRA - SECP)

NEPRA - meetings for tariff/ meeting forcustomer compliant resolution / Annual Report

Bimontly / Monthly meetings / Annualperformance report

Federal & ProvincialGovernments

Meetings and written communications onvarious issues/ SMART Program report

Ongoing on day to day basis/ MontlyEnvironmental SMART report

Stock exchange Financial reports Annual / Half yearly and quarterly Financialreports

EnviromentalEnforcement Bodies

SMART Report Monthly

Media

Press Releases 1050

Press Conferences 85

Page 26: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

7

NGOs Meetings on Various issues / Writtencommunications/ Umeed/ Emails/ SMS

Ongoing

Consumer Groups Meetings on Various issues / Writtencommunications/ Umeed/ Emails/ SMS

Ongoing

Social ActionGroups

Meetings on Various issues / Writtencommunications/ Umeed/ Emails/ SMS

Ongoing

Opinion Leaders Umeed ( newsletters ) emails / sms / ThoughtLeadership Forum /

Monthly newsletter/ bi monthly thoughtleadership forum / emails - SMS as per need

EducationalInstitutions

Youth Engagement Interactive forum 350

Educational visits to Plants 39

Sponsorship of various educational events 16

Strategic BusinessPartners

Meetings on various issues / WrittenCommunications

Ongoing on day to day basis

Professional Bodies Meetings on various issues / WrittenCommunications / Newsletters/EMAILERS

Ongoing written/verbal communication/Monthly correspondence throughnewsletters and emailers.

Foreign Missions Meetings with strategic leadership level As per scheduled visits

BOD/Investors BOD meetings / KES Power meetings Quarterly/ Annual

Industry/Commerce/Trade Associations

Corporate Advisory Panels / Wriitencommunications /Meetings

Ongoing written/verbal communication/12 Structured advisory Panels on strategicleadership level

Industrial &CommercialCustomers

Corporate Advisors/ Written communications/Meetings

Ongoing written-verbal communication/Meetings with strtegic leadership level asper need

Key Suppliers &Service Providers

Meetings on various issues / WrittenCommunications

Ongoing on day to day basis

FinancialInstitutions/Partners

Annual Performance Reporting to IFC / ADBand other financial partners

Annual Reports /Ongoing writtencommunication / Meetings

TechnologyPartners

Meetings on various issues / WrittenCommunications

Ongoing on day to day basis

Customers Khuli Katcheri ( Open Forums with thecustomersto resolve customer complains and

18 forums - 4500 customers directly servedby the leadership team

Page 27: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

8

queries)

SMS 28 Million

Emails 4.36 Million

Electronic Programs (News Ticker updates ) 3100 Tickers

Electronic Appearance in various programs ./News beepers

200 appearances / 180 beepers

SocialMedia

10,000 tweets / 3,100 followers

Website Daily Updates / Bill payment facility

Print Ads in the newspapers /Radio and TVspots

9897 spots

Community Community Panel Meetings 23 Panel Meetings

Page 28: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “B”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “B”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “B”

Page 29: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

S. # Date Name Root Cause Recommendations

1 9-Jul-2011 M. Ishaque

* Act of Sabotage – Meant to disrupt operations* Supervisory Error – Short & ground not ensured, whichwould have tripped the feeder incase of supply restoration

• No HT/LT rectification work be permitted by concernedGMs/DGMs/AEs, unless complete line isolation and wearing of PPEs isensured• Effective communication be ensured through frequent coordination& free flow of information.

2 3-Aug-2011 M.Arif* Improper Isolation - Short and ground not carried out* Human Factor - Due to vast experience on the job thedeceased attempted to rectify the fault without takingnecessary Safety precautions.

* 5 safety marks (50%) to be deducted in PMS of ManagerMaintenance (corrective) IBC - KIMZ.* Designated supervisor to be deputed at dispatch centres* No HT/LT rectification work be permitted by concernedGMs/DGMs/AEs, unless complete line isolation and wearing of PPEs isensured

Fatal Accidents 2011-12 - Actions - IFC

2 3-Aug-2011 M.Arif* Improper Isolation - Short and ground not carried out* Human Factor - Due to vast experience on the job thedeceased attempted to rectify the fault without takingnecessary Safety precautions.

* 5 safety marks (50%) to be deducted in PMS of ManagerMaintenance (corrective) IBC - KIMZ.* Designated supervisor to be deputed at dispatch centres* No HT/LT rectification work be permitted by concernedGMs/DGMs/AEs, unless complete line isolation and wearing of PPEs isensured

3 15-Aug-2011 M. Shafique

* Supervisory Error - The site supervisor was not presentwith gang at time of rectification* Procedure Violation - 1. Negligence on the part ofdeceased to follow procedures and adherence to safepractices.

* Strict disciplinary action to be taken against Site supervisor anddispatch supervisors morning & evening shifts* GM, DGM & Manager to be warned for staying totally aloof andunaware of happenings within their area of responsibility* Job responsibilities of GM down below to be revisited and revised toinclude safety parameters

4 4-Jan-2012 M.Nazir

Human factor – Incorrect Decision making based on wrongassumption

• Team composition to be reviewed, especially in far flung areas,where network and operation teams are considered as one,irrespective of nature of work.• Behavior Based training to be conducted by Corporate HSEQ Dept.especially for employees with more than 5 yrs service in the samedepartment

4 4-Jan-2012 M.Nazir

Human factor – Incorrect Decision making based on wrongassumption

• Team composition to be reviewed, especially in far flung areas,where network and operation teams are considered as one,irrespective of nature of work.• Behavior Based training to be conducted by Corporate HSEQ Dept.especially for employees with more than 5 yrs service in the samedepartment

5 4-Apr-2012 Ghulam Murtaza

• Wrong isolation - In that OPN supervisor( deceased )disconnected the wrongly marked HT cable.• Non usage of PPE's and SPE's - Use of 11 KV live linetester , could have prevented the accident during work

• Strict disciplinary action to be taken against the EMO Ghulam QadirNiazi of Opn Moosa lane• Disciplinary action to be taken against the shift EngineersMuhammad Amaduddin & Naveed Mahmood of Opn control R- 1• 10 safety marks of GM,DGM & Manager – HT (OPN) R-I to bededucted in APA - 2012, for not ensuring system safety• Cable marking especially old cables which have been fault free forsome time need to be identified• Role of shift engineer to be enhanced for operation

5 4-Apr-2012 Ghulam Murtaza

• Wrong isolation - In that OPN supervisor( deceased )disconnected the wrongly marked HT cable.• Non usage of PPE's and SPE's - Use of 11 KV live linetester , could have prevented the accident during work

• Strict disciplinary action to be taken against the EMO Ghulam QadirNiazi of Opn Moosa lane• Disciplinary action to be taken against the shift EngineersMuhammad Amaduddin & Naveed Mahmood of Opn control R- 1• 10 safety marks of GM,DGM & Manager – HT (OPN) R-I to bededucted in APA - 2012, for not ensuring system safety• Cable marking especially old cables which have been fault free forsome time need to be identified• Role of shift engineer to be enhanced for operation

Page 30: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Actions* Line Isolation SOP devised and being im[plementedeffectively* For effective communication multiple sources being usedlike wireless, e-mail, Black Berry & mobile phones andcontinuous coordination between concerned departmentsbeing ensured* 05 safety marks of manager CM Mr. Atique has beendeducted* Designated supervisors has beed designated at all operationcenters* Line isolation SOP devised and beining implementedthrough out company

Fatal Accidents 2011-12 - Actions - IFC

* 05 safety marks of manager CM Mr. Atique has beendeducted* Designated supervisors has beed designated at all operationcenters* Line isolation SOP devised and beining implementedthrough out company* Site supervisor (3rd party) dismissed and black listed anddispatch supervisors shahid and Jameel dismissed fromservice* GM, DGM & Manager HT operation R-III issued recordablewarnings* JDs of GM down below revised and safety parametersincluded* Team composition changed and separate operation teamplaced at Hub Choki operation center* Behavior based Safety training arranged through outcompany in April - June 2012 by CHSEQ

* Team composition changed and separate operation teamplaced at Hub Choki operation center* Behavior based Safety training arranged through outcompany in April - June 2012 by CHSEQ

* Site supervisor Ghulam Qadir dismissed from service* Anniual increment and promotion of Shift EngineersAmaduddin & Naveed with held*10 safety marks of GM, DGM & manager Operationdeducted from APA 2012Cable marking of all cables being checked and verified oncontinuous basis* Shif Engineer role in operations has been enhanced and nooperation center can perform any operation withoutpermisiion of shift engineer

* Site supervisor Ghulam Qadir dismissed from service* Anniual increment and promotion of Shift EngineersAmaduddin & Naveed with held*10 safety marks of GM, DGM & manager Operationdeducted from APA 2012Cable marking of all cables being checked and verified oncontinuous basis* Shif Engineer role in operations has been enhanced and nooperation center can perform any operation withoutpermisiion of shift engineer

Page 31: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “C”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “C”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “C”

Page 32: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

ACTION PLAN – COMPLIANCE STATUS (April – June 2013)

January 30, 2007Revised October 2, 2009

Action Plan by Karachi Electric Supply Corporation Ltd. (KESC)- Environmental and Social Aspects –

No. Action ImplementationSchedule

Verified by: Compliance Status

1 Follow up on the Social and EnvironmentalImpact Assessment (SEIA), dated January2007 for the Capacity Enhancement Project(Bin Qasim): Present the Environmental

Management Plan and the SocialManagement Plan with concretespecifications

For constructionphase: prior tostart of theconstruction

For operationalphase:prior to start ofcommercialoperation

Copies of theEMP and SMPfor bothconstruction andoperationalphases.

Complied (SeeAnnexure “A” &

“B” )

Complied (SeeAnnexure “L”)

2 Prepare SEIAs and conduct consultationfor new investment projects (e.g.development of new transmission lines,development of new grid stations) whichare subject to Pakistan EIA regulations

In accordancewith thedevelopmentschedule of theprojects

Copies of (i)SEIAs prepared,(ii) minutes ofthe consultationsheld

Complied (LatestEIA Conducted for132 KV OH/UGTransmission Linefrom Baldia tovalika Grid stationand is available atour web site:http://www.kesc.com.pk/en/section/mediacenter/downloads

3 Conduct Environmental, Health and Safety(EHS) Audit for the Transmission andDistribution (T&D) Assets (or “EHS T&DAudit”) to identify areas of concerns andpropose corrective actions on the followingfields:

A. Hazardous waste management(such as PCBs, used oil, etc.)

B. Health and safety management: Minimum clearance

distance fromtransmission lines / highvoltage equipment

Appropriate fencing,appropriate safety signs

Reporting / awarenesspromotion

C. Electromagnetic fieldmanagement (e.g. compliancewith ICNIRP Guidelines foroccupational and general public

Audit to becompleted byDecember 31,2010.

Quarterly reportonimplementationstatus to besubmitted to IFCby:Dec 31, 2009Mar 31, 2010June 30, 2010Sep 30, 2010

Copies of auditreport / quarterlyreports

Complied ( SeeAnnexure “C” )

Page 33: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

exposure to EMF).D. Transmission lines right-of-way

regulation compliance.4 Implement recommended corrective

actions by the EHS T&D AuditImplementationschedule to bediscussed andagreed betweenKESC and IFCafter completionof the EHS T&DAudit.

-

5 Conduct asbestos audit for existing thermalpower stations (except for KorangiThermal Power Station of which audit wascompleted and the certificate datedDecember 14, 2006 has been obtained byKESC).

Asbestos auditto be completedby March 31,2011

Copies ofasbestos auditreport

Complied ( SeeAnnexure “D”)

6 Implement recommended corrective actions by ECTECH’s Environmental Audit that was conducted forthe generation assets in the area of ambient air quality, wastewater treatment, and noise. Actions include:

A. Conduct regular monitoring ofambient air quality aroundexisting thermal power stations.

2009 andannually

Copy of themonitoringresults to beincluded in theAnnualMonitoringReports

Complied ( SeeAnnexure “E”)

B. Conduct treatment of wastewaterat existing thermal power stationsor send wastewater to a collectivetreatment plant.

Completiondate: March 31,2011.

Copy of theprogress report.

On-going

7 Strengthen the Company’s Environmental, Health and Safety, and Social Management System to ensurethat the Company will conduct business in accordance with IFC’s Performance Standards on Social andEnvironmental Sustainability (April 30, 2006). Actions proposed by KESC include:

A. Establishment of Health, Safetyand Environment (HSE) Policy

Integrated HSEPolicy to beestablished byJune 30, 2010.

Copy of theIntegrated HSEPolicy.

Complied ( SeeAnnexure “G”)

B. Preparation of HSE manuals December 31,2009.

Copy of the listof HSE manuals.

Complied ( SeeAnnexure “F”)

C. Establishment of cultural propertyprotection policy / procedures

December 31,2009.

Copies of thepolicy /procedures.

Complied ( SeeAnnexure “H”)

8 Update and implement the Environmental Management Plan and Social Management Plan described inSection 7 of the Social and Environmental Impact Assessment (SEIAs) for the 220MW Korangi CapacityEnhancement Project and for the 575MW Bin Qasim Capacity Enhancement Project, including:

A. Air Emissions – Bin Qasim: Stackheight has been kept at 45 meters,Dry Low NOx Combustor toachieve 9 ppm (at 15%O2) on gas,and water injection to achieve 42ppm (at 15%O2) on non-gaseousfuels.

Operationalphase EMP to besubmitted priorto commercialoperation of BinQasim CapacityEnhancementProject.

Copies of theoperationalphase EMP andrelevant designspecificationsused forconstruction ofthe plant.

Complied (AirEmissions –Korangi has beencompleted.BQCCPoperational PhaseEMP is attached asAnnexure “K”)

B. Thermal Effluent – Bin Qasim:Design cooling water intake

Operationalphase EMP to be

Copies of theoperational

Complied (ThermalEffluent –

Page 34: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

structure to minimize entrainmentand impingement of marineorganisms including limiting thethrough slot velocities of thescreen to less than 0.5 feet persecond.

submitted priorto commercialoperation of BinQasim CapacityEnhancementProject.

phase EMP andrelevant designspecificationsused forconstruction ofthe plant.

BQCCPP EMP isAttached asAnnexure “K”)

C. Install wastewater treatment toensure that liquid effluents fromthe expansion projects will meetthe effluent limits provided in theThermal Power: Guidelines fornew Plants, World Bank GroupPollution Prevention andAbatement Handbook 1998including: TSS 50 mg/l, Oil andgrease 10 mg/l, Total residualchlorine 0.2 mg/l, Chromium(total) 0.5 mg/l, Copper 0.5 mg/l,Iron 1.0 mg/l, Zinc 1.0 mg/l, andpH 6-9.

Operationalphase EMP to besubmitted priorto commercialoperation of BinQasim CapacityEnhancementProject.

Copies of theoperationalphase EMP andrelevant designspecificationsused forconstruction ofthe plant.

Complied (Wastewater Treatmentplant is installedand in operation.

9 Make operable the Continuous EmissionMonitoring System (CEMS) installed atBin Qasim Thermal Power Station

March 31, 2011 CEMSmonitoringresults to beincluded inAnnualMonitoringReports

Third PartyMonitoring isbeing conductedregularly andreports areprepared.(Annexure “E”)

10 Prepare and implement KESC’sCommunity Development Plan forcommunities identified in the SEIAs of theKorangi Expansion Project and Bin QasimExpansion Project

Ibrahim HyderiCommunityDevelopmentProject to becompleted byJune 2010.

Bin QasimCommunityDevelopmentProject –developmentinterventions tobe initiated byJanuary 2010.Completion dateto be determined.

Copy of thecompletionreport (IbrahimHyderiCommunityDevelopmentProject).

Copy of theproject designdocument forBin QasimCommunityDevelopmentProject.

Complied ( SeeAnnexure “I”)

On-going ( SeeAnnexure “J”)

CHANDER PERKASHGM (Corporate Compliance)

Page 35: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “D”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “D”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “D”

Page 36: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 37: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 38: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “E”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “E”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “E”

Page 39: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Submitted By:

m

ay 

u

Environmental Impact Assessment  

Erection & Com  missioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 

                              

       

Final May 

 Report 05 , 2011 

 

      

Submitted by

NEC Consultants Private Limited

Page 40: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

K

a rachi

n e ee

Environmental   

  Erection & Com 

Impact Assessment   

missioning of 132 kV 

Hybrid Grid Station at Gulistan‐e‐Jauhar  

      

Final Report May 05, 2011 

       

Submitted to: Mr. Chander Perkash General Manager OHSE 

Karachi Electricity Supply Corporation, 8th Floor, State Life Building # 11, Main Abdullah Haroon Road, 

Karachi.         

Submitted by:           

NEC Consultants (Pvt.) Limited Principal House, Mezzanine Floor, Plot No. 39C & 41C 22nd Commercial Str  et Off: Khayaban‐e‐Ittehad 

Phase – II Extension, DHA, Karachi Tel: (92 21) 3589 3341 – 43 Fax: (92 21) 3589 3340 

       E‐mail:  [email protected] [email protected] Website: www.nec.com.pk 

   

For any clarification about this Report, please contact Mr. Ibad ur Rehman, Manager (Environmental Studies Division – Southern Zone) at NEC Karachi office. 

Page 41: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  i

 

   

TABLE OF CONTENTS 

ToC    

List of Acronyms  vi Executive Summary  viii 

 Chapter – 1: Introduction  1 

 

1.1 Background 11.2 Objectives and Scope 21.3 Methodology 41.3.1 Data Analysis 51.3.2 Reporting 6

1.4

Limitations 6

Chapter – 2: Project Description  7  

2.1 Project Introduction 72.2 Project Need and Justification 82.3 Project Brief 92.3.1 Hybrid Integrated System (HIS) Arrangement 92.3.2 Project Specification 102.3.3 Grid Station Description 112.3.4 Transmission Lines 13

2.4

Project Construction 132.5 Erection and Commissioning 132.6 Operation and Maintenance 132.6.1 Maintenance of Transformers 14

2.7

Land Use and Ownership 142.8 Analysis of Alternatives 142.8.1 No Project Alternative 152.8.2 Project Sites Alternatives 152.8.3 Alternative Technologies for Grid Stations 152.8.4 Transmission Line Alternatives 162.8.5 Type of Circuit Breakers 172.8.6 Types of Transformer Oil 17

Chapter – 3:  Legislation, Guidelines and Institutional Framework  19  

3.1 General 193.2 Background 19

Page 42: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  ii

Environmental Impact Assessment 

 

3.3 Environmental Legislations 203.3.1 National Regulations 203.3.2 Pakistan Environmental Protection Act, 1997 213.3.3 Pakistan Environmental Protection Agency Review of IEE and EIA

Regulations, 2000

223.3.4 National Environmental Quality Standards (NEQS) 233.3.5 Pakistan Penal Code 1860 233.3.6 The Forestry Act, 1927 243.3.7 The Antiquities Act, 1975 243.3.8 Factories Act 1934 243.3.9 Electricity Act 1910 24

3.4

NEPRA Licensing (Application & Modification Procedure) Regulations – 1999

243.5 Guidelines 253.5.1 General Guidelines 25

3.6

Institutional Setup for Environmental Management

253.6.1 Pakistan Environmental Protection Council (PEPC) and the Pakistan 

Environmental Protection Agency (Pak‐EPA)

253.6.2 Sindh Environmental Protection Agency (SEPA) 26

3.7

Other Relevant Laws

263.7.1 IFC Environmental, Health, and Safety Guidelines for Electric Power 

Transmission and Distribution

26

Chapter – 4: Environmental Description of Project Area  27  

4.1 Physical Environment 274.1.1 Location and Surrounding 274.1.2 Soil and Geology 284.1.3 Water 314.1.4 Drainage System and Wastewater 324.1.5 Noise 324.1.6 Ambient Air Quality 334.1.7 Temperature and Humidity 334.1.8 Climate Wind Condition 34

4.2

Biotic and Natural Environment 364.2.1 Flora 364.2.2 Fauna 364.2.3 Ecosystem Sensitivities 364.2.4 Aesthetics 36

4.3

Status of Socio‐Economic Environment 374.3.1 Study Area 374.3.2 Administrative & Political Units 384.3.3 Population of Study Area 40

Page 43: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  iii

Environmental Impact Assessment 

 

4.4 General Profile of the Area 414.4.1 Human Settlements 414.4.2 Type of Houses 424.4.3 Castes, Ethnicity and Social Groups 434.4.4 Family & Household Sizes 444.4.5 Professions & Occupations 444.4.6 Religious Sites 444.4.7 Sites of Archaeological and Cultural Significance 444.4.8 Recreational Sites 454.4.9 Health Status and Facilities 454.4.10 Education 464.4.11 Social Status of Women 474.4.12 Children’s Mobility 474.4.13 Transportation & Road Infrastructure 474.4.14 Utilities Management 48

4.5

Stakeholder Consultation 48

Chapter 5: Identification and Assessment of Environmental Impacts  49  

5.1 Potential Environmental Impacts Due to Project Design 505.2 Potential Environmental Impacts due to Project Location 505.3 Potential Environmental Impacts during Construction 505.3.1 Air Quality 505.3.2 Water Quality 505.3.3 Soil Characteristics 515.3.4 Ambient Noise 515.3.5 Flora 525.3.6 Fauna 525.3.7 Socio‐Economic Conditions 525.3.8 Health & Safety 52

5.4

Installation & Commissioning Phase

535.4.1 Environmental & Safety Issues 53

5.5

Potential Environmental Impacts during Operation

535.5.1 Air Emissions 575.5.2 Liquid Discharges 575.5.3 Solid Waste Generation 595.5.4 Ambient Noise 595.5.5 Flora 605.5.6 Fauna 605.5.7 Socio‐economic Conditions 605.5.8 Health & Safety 60

Page 44: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  iv

Environmental Impact Assessment 

 

Chapter – 6: Mitigation Measures  65  

6.1 Introduction 656.2 Key Environmental Issues 656.3 Mitigation Measures at Different Phases of the Project 666.3.1 Mitigation Measures at Design Phase 666.3.2 Mitigation Measures at Construction Phase 666.3.3 Mitigation Measures at Operation Phase 67

6.4

Occupational Health & Safety

72

Chapter – 7: Environmental Management Plan (EMP)  74  

7.1 General 747.2 Purpose & Need of the EMP 747.3 Objectives of the EMP 757.4 Scope of the EMP 757.5 Responsibilities 757.6 Commitment to Environmental, Health and Safety (EHS) 757.7 Structure of the EMP 767.8 Key Environmental Issues 767.9 Impact Mitigation Plan 767.10 Organizational Structure; Roles & Responsibilities 777.10.1 Roles & Responsibilities 78

7.11

Training Program

797.11.1 Awareness Training 797.11.2 EMP Orientation Training 797.11.3 Job Specific Training 797.11.4 Disaster Management Training 807.11.5 Identification of the Need for New or Additional Training 80

7.12

Environmental Monitoring Plan

807.13 Reporting 817.14 Disaster Management Plan 827.14.1 Preventive Action 827.14.2 Communication System 837.14.3 Emergency Action Committee 837.14.4 Implementation of DMP 83

List of Tables: 

 Table 2.1: Comparison of AIS & GIS Technologies  16 Table 2.2: Comparison of Overhead & Underground Transmission Routes  17 Table 4.1: Ambient Air Quality at Site  33 Table 4.2: Monthly Amount of Precipitation, Mean Relative Humidity & Temperature 

in Karachi  34 

Page 45: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  v

 Environmental Impact Assessment 

 

Table 4.3: Mean Monthly Wind Speed (knots) & Wind Direction (at 1200 UTC)  35 Table 5.1: Potential Environmental Impacts During Operation Phase  54 Table 5.2: ICNIRP Guidelines for EMF Public and Occupational Exposure  62 Table 5.3: Typical Measured Values for Magnetic Field Next to Transformer  62 Table 5.4: Typical Measured Magnetic Field Next to KESC Power Lines  62 Table 5.5: Fire Extinguishing Arrangement  64 Table 6.1: Major Potential Impacts & Mitigation Measures at Operation Phase  68 Table 6.2: Suggested Routine Inspection & Maintenance Schedule  70 

 List of Figures: 

 Figure 2.1: Project Site & Surrounding  8 Figure 2.2: Typical HIS  11 Figure 4.1: Location & Surrounding of Project Site  28 Figure 4.2: Active Faults on Eastern Side of Karachi  31 Figure 4.3: Karachi Wind Rose  35 Figure 4.4: Important Landmarks of Study Area  37 Figure 4.5: Map Showing Different Blocks of Gulistan‐e Jauhar  39 Figure 4.6: Figure 4.5: Map Showing Different Blocks of Gulistan‐e Jauhar  40 Figure 5.1: Magnetic Field Produced by Underground & Overhead Cables  61 Figure 7.1: Organizational Structure  77 

 List of Annexure: 

 Annexure – 1:  Grid Station’s Layout Plan Annexure – 2:  Pakistan Environmental Protection Act (PEPA) 1997 Annexure – 3:  Schedule I, II & III of PEPA Regulations 2000 Annexure – 4:  Revised NEQS, 2000 Annexure – 5:  Factories Act, 1934 – Relevant Applicable Laws Annexure – 6:  NEPRA Licensing Regulations Annexure – 7:  Geological Map of Project Area Annexure – 8:  Soil Test Report Annexure – 9:  Tectonic Map of Pakistan Annexure – 10: Drainage Map of Karachi Annexure – 11: Ambient Air Quality Test Report Annexure – 12: Socio‐economic Questionnaire Annexure – 13: Mile Stone Schedule Annexure – 14: Typical MSDS for Transformer Oil Annexure – 15: Typical Protection System for 132kV Overhead Transmission Lines Annexure – 16: SF6 Gas Containment Plan 

Annexure – 17: Impact Mitigation Plan Annexure – 18: Environmental Monitoring Plan Annexure – 19: Disaster Management Plan 

Page 46: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  vi

   

 

LIST OF ACRONYMS 

LoA     

AIS  Air Insulated Substation BU G&T  Business Unit Generation & Transmission CDGK  City District Government Karachi CEO  Chief Executive Officer CO  Carbon Monoxide dB  Decibel DMP  Disaster Management Plan ELF  Extremely Low Frequency EMF  Electromagnetic Field EMP  Environmental Management Plan EPA  Environmental Protection Agency EPRCP  Environmental Planning and Resource Conservation Project GIS   Gas Insulated Substation GSM  Grid System Maintenance GSO  Grid System Operation GWP  Global Warming Potential HIS  Hybrid Integrated System HSEQ  Health, Safety, Environment & Quality Assurance ICNIRP  International Commission on Non‐Ionizing Radiation Protection IEE  Initial  Environmental  Examination IFC  International  Finance Corporation kV  Kilo Volts KESC  Karachi Electric Supply Company KWSB  Karachi Water and Sewage Board LDC  Load Dispatch Centre mg/l  Milligrams per Liter MSDS  Material Safety Data Sheet MW  Megawatt NA  National Assembly NAAQS  National Ambient Air Quality Standards NCS  National Conservation Strategy NEP  National Environment Policy NEPRA  National Electric Power Regulation Authority NEQS  National Environmental Quality Standards NGO  Non‐Governmental Organization NOC  No Objection Certificate NOx  Oxides of Nitrogen O&M  Operation & Maintenance OHS  Occupational Health and Safety 

Page 47: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  vii

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

Environmental Impact Assessment  

PCB  Poly‐Chlorinated Biphenyl PEPA  Pakistan Environmental Protection Act PEPC  Pakistan Environmental Protection Council PEPCO  Pakistan Electric Power Company PEPO  Pakistan Environmental Protection Ordinance PLDP  Platform at dead end Pole PM  Particulate Matters PMD  Pakistan Metrological Department PPEs  Personal Protective Equipments PTCL  Pakistan Telecommunication Limited ROW  Right Of Way SEPA  Sindh Environmental Protection Agency SF6  Sulphur hexafluoride gas SOPs  Standard Operating Procedures SOx  Oxides of Sulphur SSGC  Sui  Southern Gas  Company T&D  Transmission & Distribution TDS  Total Dissolved Solids TSS  Total Suspended Solids UC  Union Council USEPA  United States Environmental Protection agency 

Page 48: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  viii

 

ES  EXECUTIVE SUMMARY 

 

  

Introduction:  This summary  is based on  the Environmental  Impact Assessment  (EIA) carried out  for  the 132  kV  Hybrid  Grid  Station  along  with  associated  transmission  lines  by  Karachi  Electric Supply Corporation at Block‐16 Gulistan‐e‐ Jauhar. The commissioning of this grid will also relieve the overloaded grids of Gulistan‐e‐Jauhar, Gulshan‐e‐Iqbal and KDA Scheme‐33, thus meeting the partial requirement of future load growth in the adjoining areas. 

 The  aim  of  Environmental  Impact  Assessment  (EIA)  is  to  assist  in  the  decision  making process and to ensure that the project is environmentally sound and legally compliant. 

 Project Proponent: 

 The  Karachi  Electric  Supply  Corporation  (KESC)  is  an  integrated  electric  utility  supplying power to the city of Karachi. KESC is engaged in generation, transmission and distribution of electricity  in a  service area  that  includes about 6,000  square  kilometers and a population between 12‐14 million. 

 The Company owns 1,756 MW of generation capacity (oil and gas‐fired) of which 1,336 MW is  currently  operational.  KESC  transmission  network  consists  of  220kV,  132kV  and  66kV circuits  with  51  grid  stations  and  its  distribution  network  includes  3,800  km  of  11kV underground cable, 2,000 km of 11kV overhead cable, 8,000 distribution transformers and over 10,000 km of 400V distribution lines. 

 The  Company  has  started  its  “System  Stabilization,  Rehabilitation  and  Loss  Reduction Program”, after being privatized in 2005. The program is now being implemented in order to expand generation capacity by adding clean and more energy efficient gas‐fired combined cycle units at existing thermal power stations on a fast track basis and upgrade/ rehabilitate its existing transmission and distribution assets in order to reduce its energy losses. This will include replacement of old grid stations and construction of new 220/132 kV overhead and underground transmission lines. 

 Need of EIA: 

 The project  falls under  the project category of “Transmission  lines  (11 KV and above) and Grid Stationsa” as per  the guidelines  issued by  the Environmental Protection Agency  (EPA) under  the  Pakistan  Environmental  Protection  Act  1997  (PEPA  1997).  According  to  these guidelines, projects under this category require an EIA to be conducted. 

  

 a   Pakistan Environmental Protection Agency (Review of IEE and EIA) regulations, 2000 

Page 49: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  ix

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Project Justification:  The electricity demand has been increasing during the past years and this trend is expected to continue as a result of the on‐going economic uplift in the city. The key factors fueling the increasing power demand include  increasing population,  industrialization and improvement in  per  capita  income.  In  order  to match  the  exponential  increase  in  the  power  demand, regular  investments  in  various  segments  of  the  power  network  is  vitally  important. Otherwise, the gap between supply and demand will keep on increasing. 

 The objectives of  the project are  to help  increase  the efficiency,  reliability, and quality of electricity  supply  in  terms  of  the  overall  technical  and  commercial  viability,  continuous availability  and  the  improved  voltage  profile  of  electric  supply.  The  Project  shall  also facilitate electricity sector reforms, investment planning, financing and technical assistance. The project will cater to the future needs of Gulshan‐e‐Iqbal, Gulistan‐e‐Jauhar, Gulshan‐e‐ Jamal, Mujahid Colony, Phelwan Goth, Askari‐IV and adjoining areas. 

 Project Description: 

 KESC  is  constructing  an  Electric  Grid  Station  at  Gulistan‐e‐Jauhar,  Block‐16.  The  project comprises of erection,  installation and commissioning of 132 kV Hybrid Grid Station along with power  transformer,  circuit breakers,  related  equipments  and  transmission  lines with complete civil works. 

 The following are the highlights of the project; 

 Parameter Description

Project Capacity 2×40MVA

Area Required 0.92 acres

Cost of Project PKR 474.4 Million (excluding land)

O&M Cost PKR 2 Million

Workforce Requirement

Construction 20 to 150 Persons

Operation 4 to 5 Persons Hybrid Grid Station is a combination of conventional AIS & modern GIS technologies.  Here, components of AIS and GIS are typically integrated in the same bay and this combination is applied across the whole Grid Station. The  integrated use of technologies leads to effective cost  savings  while  providing  a  safer  alternative  in  comparison  to  the  conventional  grid stations. 

 The HIS Grid Station  is an outdoor station with control and monitoring through state of art automation  system. The PASS  (Plug and Switch System) modules have been employed  for the first time in Pakistan. Here, circuit breaker, disconnecting and earthing switches are GIS based while busbar, current and voltage transformers and serge arresters are air exposed. 

Page 50: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  x

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Land use & Ownership:  KESC owns a 2 acres plot on a commercial  land, close to the residential area of Gulistan‐e‐ Jauhar Block‐16. Approximately 0.92 acres is used for construction of the grid station. At one end of  the  plot  is  KESC’s Virtual  Integrated Business Center  (VIBC),  the  central portion  is kept open for possible future construction of KESC’s hospital. The  infrastructure and utility services  are  already  available  in  the  area  and  have  the  capacity  to  serve  the  anticipated requirements of the project. Land acquisition and resettlement due to construction of grid station  is not  an  issue. Underground  cables  are provided  from  the  grid  station up  to  the main  road. Overhead  transmission  line  route  is along  the New Service Line Road  from  the grid station boundary wall up to Samama Junction, close to University Road. 

 Environmental Description of the Project Area: 

 Physical Environment:  The  project  area  has  a maximum  elevation  of  139  ft  (42m)  above mean  sea  level.  Ground  water  table  is  high  due  to  which  pile  foundations  are  being provided. At operational stage, water will be obtained from KWSB  line. Drinking water will be  purchased  and  provided  through  dispensers. Wastewater  is  discharged  into  the main municipal drain. Ambient Noise  values  are  found  to be  in  the  range of 55‐60 dB. Overall levels  of  Ambient Air Quality were  found within  prescribed  limits  of  reference  standards except  for  particulate  level  that  was  quite  higher  at  the  site  due  to  construction  being carried out within the project premises. 

 Biotic Environment:  The  study  area  has  patches  of  grass  and  shrubs;  however  it  was observed  from  the  field survey  that no special  floral and  faunal species exists close  to  the project site. 

 Social Environment: The settlements  in the close proximity of the project are mostly  large apartment  complexes  housing  middle  class  families  of  different  ethnic  and  religious backgrounds. The  buildings  are quite well‐maintained  and  general  amenities of  livelihood are present  in  the area. The neighborhood  in  the study area  is characterized by people of different ethnic and religious backgrounds living together with a lot of common and shared facilities and space. 

 Major Potential Impacts & Mitigations Measures: 

 Water Resources: The  construction activities of  the project are not expected  to have any major  impact  on  the  surface  or  ground  water  quality  of  the  area.  Adequate  drainage, drinking water and sanitation  facilities  in  the  temporary camp of construction workers are provided by the contractors to avoid the surface water pollution. 

 Water will not be used  for operation and maintenance activities. The quantity of domestic wastewater generated during this phase  is assessed to be very  low due  to small number of operating  staff  residing  at  the  grid  station.  The  storm water will  be  directed  to  the main sewer line outside the project boundary. 

Page 51: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  xi

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Air Quality:  The  major  sources  of  air  pollution  during  construction  are  emissions  from vehicles, generator sets, and heavy construction equipment; and fugitive dust  from vehicle movement  and  soil  excavation.  Impacts  are  minimized  through  established  mitigation measures which include suppression of fugitive dust by water spraying, use of low emission vehicles and construction equipment, and good maintenance of engines. 

 SF6  released into the atmosphere is considered a greenhouse gas with a significantly higher global warming potential (GWP) than CO2

b. Despite the fact that SF6 gas is very stable, it will partly decompose  in association with electric discharges and arcs, resulting  in gaseous and solid  decomposition  products.  There  are  established  routines  for  service  personnel when opening SF6  filled equipment for maintenance or scrapping. Therefore, SF6 Gas containment plan should be strictly followed. 

 Soil Characteristics: Soil may be contaminated as a result of fuel/oils/chemicals spillage and leakage,  and  inappropriate  disposal.  The waste would  be  generated  from  site  clearance, excavation, concrete batching, concrete conveyance and construction of substructures and superstructures. Waste oils will be collected in drums and sold to the recycling contractors. The inert recyclable waste from the site (such as card board, drums, broken/used parts, etc.) will be sold to recycling contractors. 

 The grid station premises will not be used as permanent storage area during operation. The essential spares and other wastes generated including wastes from repair and maintenance activities   will   be   sent  to   GSM   Department.   These   wastes   typically   would   be   put    in containers, characterized and labeled, possibly stored briefly, and transported by a licensed hauler to an appropriate permitted off‐site disposal  facility as a standard practice. Any soil contaminated  by  the  oil  spillage  will  be  removed  and  disposed  off  appropriately  in accordance with the MSDS of the spilled oil. 

 Ambient Noise:  The major  sources  of  noise  during  construction  activities  are  excavation, transportation,  loading/unloading  of materials  and  operation  of  construction  equipments etc.  These  are  temporary  in  nature  and  are mitigated  by  careful  planning  of machinery operations and time schedules. 

 During the operation phase of the project, there will be humming noise generated from the grid station due to transformers operation which will be felt only up to 50 m from the grid station area. Transformer noise  level  is designed  to  remain below 65 dB. The grid  station area will be surrounded by a wall having sound attenuation effect. 

 Ecological Setting: The site clearance would not bring about major changes to the existing flora as  there are no rare, endangered or endemic  terrestrial plants species present  in the study area. The underground cables will be laid within the project boundaries and no major land portion containing flora will be disturbed. Since the excavation work is done along the footpaths  of  service  road, natural  vegetation  is not  disturbed;  however  eleven  (11)  trees have been  removed  for overhead  transmission  line  route,  stretched over  a  length of one kilometer. 

 

 b EHS Guidelines by IFC 

Page 52: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  xii

 Environmental Impact Assessment 

 

The faunal species in the study area is mainly of those associated with manmade habitat and is not expected to be affected by the grid station’s construction or operation. 

 Socio‐economic Impact: The socioeconomic impacts of the project on the surrounding area are  expected  to  be  on  the  higher  side  in  terms  of  their  significance.  The  socioeconomic status of  the area would  improve  to a considerable extent as  the price of property would shoot up due to firm and assured uninterrupted power supply from KESC. 

 The construction of grid station and associated transmission lines will play an important role not only to strengthen and stabilize electricity distribution system  in existing areas but will also  improve  electricity  supply  to  adjoining  areas. Main  beneficiaries will  be  the  general public including students of the nearby area. 

 Health and Safety:  Various  activities  during  the  construction  phase  of  the  project  could have health &  safety  impacts on workers and  the people  living  in  the nearby vicinity. The contractor should employ every possible precaution. 

 Accidents may occur due to electrocuting,  lightening, fires and explosions during operation phase. The  lightening arresters will be provided at strategic  locations. Sufficient number of fire  extinguishers  will  also  be  provided  for  emergency  needs.  Safety  and  emergency procedures manual will be kept at grid station. KESC has measured EMF values for  existing 132/11 kV transformers and transmission  lines, they are well within the exposure  limits as established by ICNIRP Guidelines for general public as well as the maintenance staff. 

 Transformer Oil Leakage & Seepage: Highly  refined, mineral base oil will be  used  in  the transformers  and  transmission  lines  for  cooling  transformers  and  providing  insulation between  live  components,  it  is  regularly monitored  to  ensure  that  the  constituents  are within permissible  limits as recommended by the manufactures.  If the oil has degenerated both  chemically  and  physically,  it  is  upgraded  /  recycled  through  dehydration  and regeneration process. 

 Tables  A &  B  highlights  the major  potential  impacts  and  suggested mitigation measures during Construction and Operation phases, respectively. 

 Table – A 

Major Potential Impacts & Mitigations Measures at Construction Phase 

 S. No.

Aspect Possible Environmental 

Impact Recommended Mitigation 

Measures

1

Clearing of shrubs

Loss of vegetation

Compensatory plantation around the grid station to improve aesthetics

2

Excavation

Dust Generation Frequent watering, immediate clearance of excavated earth

3

Transportation of materials

Deterioration of Air Quality

• All vehicles & equipments to be regularly tuned & maintained

Page 53: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  xiii

Environmental Impact Assessment 

 

S. No.

Aspect Possible Environmental 

Impact Recommended Mitigation 

Measures

Noise • Construction equipments will 

conform to the standards

Impact on Water Quality

• Repair & Maintenance of machinery or equipments will not be allowed at site 

• Spillage of fuel or lubricants will be avoided with best construction/handling procedures

Table – B 

Major Potential Impacts & Mitigations Measures at Operation Phase 

 S. No.

Aspect Possible Environmental 

Impact Mitigation Measures

1

SF6 Gas Leakage

Greenhouse Effect • SF6 Containment Plan to be 

followed

2

Transformer Oil Leakage/seepage

Soil /Ground water Contamination

• Transformers will be built on impervious  base 

• Collected waste oil will be disposed in accordance with MSDS

4

Transformer Noise

Increased Noise Level

• Surrounding wall with sound attenuation effect 

• Proper maintenance of  the equipments & machineries inside grid

5

Domestic wastewater generation

Impact on Water Quality

• Septic tank/ soak pit will be constructed

6

EMF Generation

Health Risks to patients & workers

• Health‐based exposure limits be mandated to protect public health.

7

Short Circuiting

Fire Incidents

• SF6 is not combustible 

• Appropriate Fire Extinguishing Equipments for transformers 

• Emergency Response Plan to be made available at each grid station.

8

Socioeconomic Impacts

Assured Uninterrupted Power Supply & Increased Price of Property

‐‐

Page 54: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  xiv

Environmental Impact Assessment 

 

Environmental Monitoring Plan:  According to NEQS (self monitoring & reporting by industries) Rule 2001, the project neither falls under Category A nor under Category B of Schedule‐I. The grid station  is not expected to emit any priority pollutant as mentioned in the above rules during the operational phase. 

 Increase  in  transportation  is not expected during  the operation and maintenance activity, therefore monitoring  for vehicular emissions  is not recommended. Similarly, monitoring of effluent  discharge  is  also  not  recommended  as  only  four  to  five  persons will  be  residing within  the  grid  building  and  the  domestic  wastewater  discharged  after  treatment  from septic tank and soak pit in comparison to pollution load of main KWSB sewer line would be negligible. 

 The solid wastes generation from the grid station should be monitored so as to ensure that no  immediate  and  long‐term  environmental  and  health  problems  are  caused.  EMF monitoring  is also  recommended  for  the grid  station, biannually. The management would ensure compliance of monitoring results with the Pakistan‐EPA standards and ICNIRP limits, respectively. Regular testing of transformer oil is also recommended. 

 Conclusion: 

 This EIA study has identified and assessed potential environmental impacts of the project, as per the guidelines issued by the Environmental Protection Agency (EPA) under the Pakistan Environmental Protection Act 1997 (PEPA 1997).  Overall, the EIA study has concluded that the  project would  be  environmentally  acceptable,  and  in  compliance with  environmental legislation  and  standards. With  the  implementation  of  environmental  control measures, there  would  be  minimal  or  no  adverse  residual  impacts  from  the  Project.  This  will  be checked by a comprehensive environmental monitoring plan. 

Page 55: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

 

     

INTRODUCTION 

CHAPTER 

1  

   

1.1  Background  

This  report discusses  the Environmental  Impact Assessment  (EIA) of 132 kV Hybrid Integrated System  (HIS) Grid Station along with associated  transmission  lines being set up by   Karachi Electric Supply Company  (herein after  referred  to as KESC). The Grid  Station  is  located within  an  open  plot,  owned  by  KESC  in  Gulistan‐e‐Jauhar Block‐16.  The  project  will  ensure  load  reduction  on  presently  overloaded  grid stations and transmission lines of Gulistan‐e‐Jauhar, Gulshan‐e‐Iqbal and part of KDA Scheme‐33. It will also improve the voltage profile as well as the system reliability. 

 The project falls under the project category of “Transmission lines (11 KV and above) and Grid Stations1” as per the guidelines issued by Environmental Protection Agency (EPA) under the Pakistan Environmental Protection Act 1997 (PEPA 1997). According to these guidelines, projects under this category require an EIA to be conducted. 

 The Project Proponent: 

 The Karachi Electric Supply Company (KESC) is an integrated electric utility supplying power  to  the  city  of  Karachi.  KESC  is  engaged  in  generation,  transmission  and distribution   of   electricity    in   a   service   area   that    includes   about   6,000   square kilometers and a population between 12‐14 million. 

 The Company owns 1,756 MW  of  generation  capacity  (oil  and  gas‐fired)  of which 1,336 MW  is  currently  operational.  KESC  transmission  network  consists  of  220kV, 132kV and 66kV circuits with 51 grid stations and  its distribution network  includes 3,800  km  of  11kV  underground  cable,  2,000  km  of  11kV  overhead  cable,  8,000 distribution transformers and over 10,000 km of 400V distribution lines. 

 The Company has started its “System Stabilization, Rehabilitation and Loss Reduction Program”, after being privatized  in 2005. The program  is now being  implemented in order to expand generation capacity by adding clean and more energy efficient gas‐ fired  combined  cycle units  at existing  thermal power  stations on a  fast  track basis and upgrade/ rehabilitate its existing transmission and distribution assets in order to reduce  its  energy  losses.  This  includes  replacement  of  old  grid  stations  and construction of new 220/132 kV overhead and underground transmission lines. 

      

1 Pakistan Environmental Protection Agency (Review of IEE And EIA) Regulations, 2000 

Page 56: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  2

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

The Consultants: 

 KESC management hired NEC Consultants  (Pvt.)  Ltd.  (herein after  referred as NEC) for  conducting  the  above mentioned  EIA. NEC put  together  a  team of  consultants belonging  to  different  subject  areas  to  complete  the  assignment.  The  consulting team comprises of the following members: 

 Mr. Ibad ur Rehman  Team Leader & EIA Expert Mr. Abid Sheikh  Electrical Engineer Ms. Beena Riaz  Environmental Engineer Mr. Abdul Fattah  Chemical Engineer Ms. Amna Shariq  Environmental Scientist Ms. Aleena Afridi  Socio‐Economic Expert 

 1.2  Objectives and Scope 

 The  overall  objective  of  this  study  is  to  elucidate  the  anticipated  aspects  of  the proposed intervention and their impacts on the surrounding environment in order to propose  necessary mitigation measures  to  prevent/minimize  adverse  impacts.  To achieve  this  objective,  an  assessment  of  the  existing  environmental  status  of  the project  site  is a prerequisite and  therefore  included  in  this  study by  collecting and reviewing the baseline data of various environmental attributes. 

 More specific objectives of this EIA report include: 

 

 

• To meet  the  statutory  requirements  set  forth  by  the  Pakistan  Environmental Protection Act (PEPA) 1997. 

• To  facilitate  decision  making  by  the  Sindh  Environmental  Protection  Agency (SEPA) regarding grant of NOC for the project. 

• To establish a baseline of existing environmental status at the project site prior to  project  initiation  by  collecting  secondary  and  primary  data/information  on physical, biological and socio‐economical environment of the project area. 

• To  help  the  project  proponents  to  incorporate  necessary measures  for  legally compliant and socially acceptable environmental performance of their project. 

• To identify significant environmental impacts (both positive and negative) during all stages of the project and propose mitigation measures for negative impacts. 

 The scope of the assignment is derived from the PEPA guidelines. As per the scope of work, the EIA report consists of the following sections: 

 Description of the Project: Complete description of the relevant parts of the project has  been  provided,  using  appropriate  visual  aids  (maps,  photographs,  satellite imageries etc.) where necessary. 

 Analysis of Project Alternatives: Alternatives of the project are examined including: no‐action option and alternate technology option. 

Page 57: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  3

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Legislative and Regulatory Considerations: The relevant  legislation, regulations and standards,  and  environmental  policies  which  are  applicable  to  the  project  are described. The appropriate authority  jurisdictions  that will  specifically apply  to  the project are also identified. 

 Description of  the  Environment: The baseline data on  the  relevant environmental characteristics  of  the  study  area  was  assembled,  evaluated  and  presented.  This section  includes  the detailed description of  the  following  environmental  attributes within  the project  area. The  ‘project area’  is defined  as  the  area within which  the impact of the project may be expected. 

 Physical Environment: Locations and surroundings, site plans and layout, geography, polar coordinates, soils and geology, topography and drainage system, seismic zone, water  resources,  air  and water quality, public water  supplies,  climate  (wind  speed and direction, temperature, precipitation, humidity) and ambient noise. 

 Biotic and Natural Environment: Flora and fauna of the terrestrial ecosystems, rare or endangered species and sensitive habitat. 

 Socio‐economic  Environment:  Demographics,  employment,  land  use,  community structure, public health, communal facilities or services, sites affected by the project and community perceptions about the project. 

 Validation of available information was done by characterizing the extent and quality of  collected  data.  This  helped  in  indicating  the  significant  information  deficiencies and any uncertainties associated with the prediction of impacts. 

 Potential Impacts of the Project:  Impacts related to the project were identified and distinction  for  significant  impacts was made between positive  and negative, direct and  indirect,  short  and  long  term,  during  different  phases  of  the  project.  Impacts that  are  cumulative,  unavoidable  or  irreversible  have  also  been  identified.  Special attention was paid to: 

 • Impacts of the project on ambient noise levels. 

• Impacts of the project on the ambient air quality. 

• Impacts of the project on water quality. 

• Impacts of the project on soil characteristics. 

• Impacts of the project on socio‐economic condition. 

• Impacts of the project on health and safety.  

Mitigation measures  of  Adverse  Impacts:  Possible measures  to  prevent  or  reduce significant  negative  impacts  to  acceptable  levels  have  been  identified. Recommendations to adopt feasible mitigation measures were included in the report. 

 Development of a Monitoring and Management Plan: The  critical  issues  requiring monitoring  to ensure compliance  to mitigation measures are  identified and  impact management and monitoring plan for operations has been presented. 

Page 58: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  4

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

1.3  Methodology  

The consulting team was mobilized after  the acceptance of proposal  for EIA of 132 kV HIS Grid Station and allied transmission lines by KESC. The methodology adopted by  the  consultants  for  this  assignment  was  agreed  with  the  proponents  at  the proposal stage. The following methodology was adopted: 

 Orientation Session: Meetings and discussions were held with relevant key officials of KESC. This activity was aimed at achieving a common ground of understanding on various issues of the EIA study. 

 Development  of  Data  Acquisition  Plan:  Following  the  concept  clarification  and understanding, a detailed data acquisition plan was developed for the internal use of the consulting team. This plan was revised and updated throughout the EIA process. The  plan  identified  specific  requirements  of  the  primary  and  secondary  data  and their  sources;  determined  time  schedules  and  responsibilities  for  their  collection; and  indicated  the  logistics  and  facilitation  needs  for  the  execution  of  the  data acquisition plan. 

 Secondary  Data  Collection  and  Review:  The  secondary  data  about  the  physical, technical, and  institutional aspects of  similar projects available with NEC and KESC were   also   reviewed.  The   additional   data  was   collected   from   the   following departments: 

 • Union Council (UC‐10) of Gulshan‐e‐Iqbal 

• Pakistan Meteorological Department 

• Botany  Department, University of Karachi 

• Geological Survey of Pakistan 

• Population Census Organization  

On the basis of the secondary information and its review, a primary survey plan was developed. Gap  analysis was  also  carried  out  to  identify  exhaustively  all  the  data required to conduct an EIA study. 

 Primary Data Collection: Primary data was collected for the parameters identified in the gap analysis. Socioeconomic surveys were conducted for the human settlements located near the grid station. The survey tools  included questionnaires and  focused discussions. 

 In addition, the data for the following parameters was also collected for establishing the existing environmental baseline. 

 • Noise Levels at site 

• Ambient Air Quality at site 

• Soil Characteristics 

Page 59: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  5

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Site Visits:  The consulting team made visits to the project site. The visits were made by all team members in order to collect necessary data pertaining to their respective areas of responsibility for the assignment. 

 The consultants also held meetings with the relevant key professionals of KESC and other  organizations  to  obtain  information  regarding  environmental  conditions  in connection with the project site. 

 During  these  visits,  team  members  took  photographs  and  observed  existing environmental  conditions.  The  visits  also  helped  in  verifying  various  pieces  of information available in the secondary sources. 

 1.3.1  Data Analysis 

 Impact  Identification  and  Screening:  Based  on  the  information  collected  through primary and secondary sources, various actions or activities having potential to cause damage  to the environment are  listed  in chapter 5. The aspects were  identified  for each   phase   of    the   project    including   designing,   construction,    installation   and operation  phase.  Methods  described  in  EPA  Guidelines  were  also  referred  for identification and screening of aspects and their impacts. 

 Impact  Prediction  and  Evaluation:  For  evaluation  and  prediction  of  various environmental  impacts, quantitative and qualitative descriptions of  the anticipated project  impacts were made. The  identified  impacts were further evaluated for their significance level. 

 For detailed analysis of environmental impacts, evaluation matrices were developed. In  these matrices each aspect with  its  significance  level  in  terms of  its potential of creating an impact on surrounding environment is listed. 

 Development  of Mitigation Measures:  Based  on  the  significance  of  the  impacts, mitigation measures for each significant negative  impact were suggested. Approach for  suggesting  mitigation  measure  was  as  follows,  in  the  descending  order  of preference: 

 • Avoiding the impact altogether by not taking a certain action or parts of an action 

i.e. evaluation of project alternatives; • Minimizing  impacts  by  limiting  the  degree  or magnitude  of  the  action  and  its 

implementation; • Rectify   the   impact   by   repairing,   rehabilitating,   or   restoring   the   affected 

environment; • Reduce  or  eliminate  the  impact  over  time  by  preservation  and  maintenance 

operations during the life of the action; and • Compensate  for  the  impact  by  replacing  or  providing  substitute  resources  or 

environments. 

Page 60: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  6

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

A  conceptual  environmental  management  plan  for  smooth  and  effective implementation  of  all  recommended  mitigation  measures  was  developed  and included in the EIA report. 

 1.3.2  Reporting 

 The EIA report has been prepared under the guidelines  issued by the PEPA 1997.  It has been finalized after review and comments made by the KESC management. The final report  is being submitted to the management of KESC for onwards submission to the SEPA. 

 The  environmental  impact  assessment  report  is  concise  and  limited  to  significant environmental  issues. The main  text has been  focused on  findings, conclusions and recommended  actions.  It  is  supported  by  summaries  of  the  data  collected  and citations for any references used in interpreting those data. 

 1.4  Limitations 

 This EIA document has been prepared by drawing inferences from site visits, primary data  and  secondary  sources of  information. The  study has been  conducted by  the consultants  in  a manner  consistent  with  the  level  of  care  and  skill  exercised  by members of environmental engineering and consulting profession. The Consultants have tried to cover all important aspects and relevant impacts of the 132 kV HIS grid station and associated transmission lines. 

 The  conclusions  in  this  study  are  based  on  primary  and  secondary  data,  results derived   from   earlier   studies   and   a   subjective   evaluation   of   the   possible environmental  aspects  during  construction  and  operations  of  the  project.  In evaluating  the project,  the  consulting  team has  relied on  information  provided by the management of KESC. The consultants assume that  the  information provided  is factual and accurate. Also the consultants accept no responsibility for any deficiency, misstatement  or  inaccuracies  contained  in  this  report  as  a  result  of  omission  or misrepresentation by any person interviewed or contacted. The mitigation measures and other  recommendations put  forth  in  this  report are of  the  level of  conceptual design and implementation framework. 

Page 61: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  7

      

PROJECT DESCRIPTION 

CHAPTER 

2    

2.1  Project Introduction  

The Karachi Electric Supply Company  (KESC)  is engaged  in generation,  transmission and distribution of electric power not only  to  the city of Karachi but also  towns of Dhabeji and Gharo and few adjacent areas of Baluchistan. The management of KESC has  launched  a  program  titled  “System  Stabilization,  Rehabilitation  and  Loss Reduction Program”  to expand  generation  capacity by adding energy efficient gas‐ fired  combined  cycle units  at existing  thermal power  stations on a  fast  track basis and upgrade / rehabilitate its existing transmission and distribution assets in order to reduce its energy losses. The transmission and distribution rehabilitation will include grid  stations  and  construction  of  new  220/  132  kV  overhead  and  underground transmission lines. 

 In this connection, KESC is going to install a separate Electric Grid Station at Block‐16, Gulistan‐e‐Jauhar. This project  comprises of erection and commissioning of 132 kV HIS Grid Station along with power transformer, circuit breakers, related equipments, underground and overhead transmission lines with complete civil works. 

 This Hybrid Integrated System grid station will substantially improve the distribution network  in  Gulshan‐e‐Iqbal,  Gulistan‐e‐Jauhar,  Gulshan‐e‐Jamal,  Mujahid  Colony, Phelwan Goth, Askari‐IV and adjoining areas. Here, two (02) power transformers of 40 MVA each will be established. 

 The area required  for construction of the Grid Station  is 0.92 acres (200  ft ×200  ft). Total area of the plot is 2 acres, it has geographic coordinates of 24o 54’ 51”N & 67o 07’ 16.2”E. The capital cost of the grid station is around PKR 474.4 Million excluding the  land  cost,  as  the  piece  of  land  is  owned  by  KESC.  The  estimated  annual operational and maintenance cost  is PKR 2.0 Million. The human resource required during the construction phase ranges from 20‐150 persons depending upon the work load.  During  installation  period,  20‐25  persons  would  be  engaged  for  about  3‐4 months.  It  is  estimated  that  the  grid  station would  need  a  crew  of  about  4  to  5 personnel  responsible  for Operation & Maintenance  activities  for which necessary facilities  for  communication,  accommodation, water  supply  and  sewerage  disposal shall be provided. 

 Since the  land  is owned by KESC, the  land acquisition problem  is not there. Tenders for  procurement  of  equipments,  erection  of  sub‐station  equipments,  testing  and commissioning has already being initiated. The project will commence soon after the acquisition of NOC from EPA‐Sindh. 

Page 62: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  8

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Figure 2.1: Project Site & Surrounding 

 2.2  Project Need and Justification 

 The  electricity  demand  has  always  been  increasing  and  this  trend  is  expected  to continue  as  a  result  of  the  on‐going  economic  uplift  in  the  city.  The  key  factors fueling the increasing power demand include increasing population, industrialization and improvement in per capita income. In order to match the increasing trend in the power  demand,  regular  investments  in  various  segments  of  the  power  network  – generation,  transmission  and  distribution  –  is  vitally  important,  otherwise  the  gap between  supply  and  demand will  keep  on  increasing. With  the  goal  of  providing uninterrupted power to Karachi, the new management of KESC has developed short and  long  term  road maps  by  not  only  improving  the  generation  capacity  but  also adding   a   number   of   grid   stations    to    the   existing   network   along   with   new transmission and distribution lines. 

Page 63: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  9

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Electricity  generation  stations  throughout  Karachi  are  interconnected  in  a  system called power grid station system. This allows electricity generated in one part of the city  to  be  sent  to  users  in  another  part.  It  also  allows  distant  power  generation stations to provide electricity for areas whose power generators may have failed or been destroyed by some accident or sabotage. The power transmission is directed by several  control  centers.  Experts  there  can monitor  the  distribution  of  power  and reroute  electricity  from  areas of  low  demand  to  areas of high  demand.  There  are automatic switches that can direct the routing of power to where it is needed. From the high voltage transmission lines, power goes to neighborhood substations. There, the electricity is stepped down from high voltage to low that could be used in homes and offices. 

 High or unbalanced demands for power that develop suddenly can upset the smooth distribution of electricity  in a grid.  In  some cases,  this can cause a blackout  in one section  of  a  grid,  or  even  ripple  throughout  the whole  grid,  sequentially  shutting down one section after another. Once large sections of a grid are shut down, it may be difficult or impossible to restore power from neighboring grids. In periods of high demand,  such as  summer, often  those nearby grids also are under  stress and may not  have  spare  power. When  power  is  restored,  it  can  cause  a  sudden  surge  in demand that the system may not be able to accommodate. 

 The  objectives  of  this  project  are  to  help  increase  the  efficiency,  reliability  and quality  of  electricity  supply  in  terms  of  the  overall  technical  and  commercial  loss reduction, continuous availability and the improved voltage profile of electricity. The Project shall also facilitate electricity sector reforms,  investment planning, financing and technical assistance. 

 The grid station will not only allow for the reliable supply of electricity to the areas of Gulistan‐e‐Jauhar but will also  cater  to  its  future needs. The  commissioning of  this grid will  also  relieve  the overloaded  grids of Gulshan‐e‐Iqbal  and  KDA  Scheme  33, thus meeting the partial requirement of future load growth in the adjoining areas. It will also reduce the operation and maintenance cost of the system by  improving  its efficiency, reliability and quality of service. It would also increase the transformation capacity  for  future  demand  and  strengthen  the  electricity  distribution  system networks to reduce losses and improve supply. 

 2.3  Project Brief 

 2.3.1  Hybrid Integrated System (HIS) Arrangement 

 The  power  industry  has  always  been  expected  to  provide  a  secure,  economically efficient and sustainable power supply, but over the past years, power markets have changed  significantly.  Demand  has  soared,  markets  have  been  liberalized  and renewable energy sources have been introduced. The changes have been felt across the world,  including Pakistan. Today’s emphasis on energy efficiency, prompted by environmental  issues and dwindling natural  resources, has  led  to  the development of new technologies for both the generation and the transmission systems. 

Page 64: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Electric power  is generated,  transmitted and distributed  in  the  form of Alternating Current. The electric power  is produced at  the power station, which are  located at favorable  places,  generally  quite  away  from  the  consumers.  It  is  delivered  to  the consumer through a large network of transmission and distribution. At many place in the  line  of  power  system,  it  becomes  desirable  and  necessary  to  change  some characteristic of electric supply  including voltage and current  flow. The assembly of apparatus used to change these characteristics is termed as grid station. 

 

To maintain a balance between electricity generation and consumption, power grids must become more  flexible and  responsive, both  in  their  structure and operation. New   technologies   play   a   central   part    in   meeting   these   demands,   and   many innovative  and  proven  solutions  are  available.  The  challenge  is  to  integrate  these solutions  into  the grid renovating established networks  to provide modern,  flexible and sustainable systems. Hybrid Grid Station  is a combination of conventional AIS & modern GIS technologies.  Here, components of AIS and GIS are typically  integrated in the same bay and this combination is applied across the whole Grid Station. 

 The HIS Grid Station is an outdoor station with control and monitoring through state of art automation  system. The PASS  (Plug and  Switch  System) modules have been employed  for  the  first  time  in  Pakistan.  Here,  circuit  breaker,  disconnecting  and earthing switches are GIS based while busbar, current and voltage transformers and serge  arresters  are  air  exposed.  A  feed  of  double  circuit  from  the  closest  132  kV circuit is made and several 11 kV circuits/lines are emanated for distribution system. The  132  kV  lines  are  provided  underground  from  the  grid  station  up  to  PLDP (platform  at  dead‐end  pole)  at main  road,  from  there  overhead  transmission  line continues till Samama Junction, near University Road. 

 2.3.2   Project Specification 

 

The Hybrid Grid station will comprise of:2  

• Power Transformer o 2×40 MVA o Voltage ratio  132/11 kV 

 • Feeder Bays (05) 

o Transmission Line Bays (02) o Bus Coupler (01) o Power Transformer Bays (02) 

 • 22 x 11 kV feeders planned 

 • Feeder’s average length  2‐4 km 

 Layout Plan of Grid Station is enclosed as Annexure – 1. 

 

  

2 Data provided by KESC Management 

Page 65: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

                             

Figure 2.2: Typical HIS  2.3.3  Grid Station Description 

 Electric power grid station consists of following essential parts: 

 

 

• Main (high or extra‐high voltage) circuits, also called primary circuits; 

• Auxiliary circuits also called secondary circuits. 

 Main Circuits: The main circuit of the grid station is composed of busbar systems and connections of power lines, power transformers and switching devices. 

 Auxiliary  Circuits: Auxiliary  circuits  are  electrical  circuits  containing measurement, signaling, control and protection devices. 

 Support  Facilities:  Certain  facilities  required  for  operation & maintenance  of  grid stations as described below shall be provided in the said project; 

Page 66: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

o Batteries Room:  There will be  a  separate  control  room building  that will  have AC/ DC distribution room battery and charger room. Batteries are very important part of the grid. It works as a standby storage device that provides D.C power to the  grid’s  D.C  supply  equipment  in  case  of  failure  of  A.C  supply.  Different protection  devices  i.e.  relays,  circuit  breakers  and  other  control  equipment  of relay  room, 11kV  control  room, 132kV  control  room  and  yard operates on D.C supply  that  is normally  supplied by  a  rectifier.  In  case of  failure of A.C  power, batteries work as a standby source of D.C supply. 

 o Computer Control of Grid Station Bay:  It  is an automatic execution of sequence 

of  switching operations by  a  computer  system which  are necessary  for normal activities within a  grid  station  (e.g.  connecting  a  line  to busbar,  switching over lines from one busbar to another etc). 

 o Lighting & Communication: Adequate normal and emergency AC & DC  lighting 

shall  be  provided  in  the  control  room  of  the  substation.  The  switchyards  shall also be provided with adequate lighting. A telephone line shall be provided at the grid station as means of effective communication. 

 o Protective Relay:  It  is a device that detects the  fault and  initiates the operation 

of circuit breaker  to  isolate  the defective element  from  the  rest of  the  system. The  relay detects  the  abnormal  condition  in  the  electrical  circuit by  constantly measuring  the electrical quantities. The  electrical quantities which may  change under  fault  condition  are  voltage,  current,  frequency  and  phase  angle.  Having detected the fault, the relay operates to close the trip circuit of circuit breaker. 

 o Fire  Fighting  System:  Fire  suppression  systems  are  used  in  conjunction  with 

smoke  detectors  and  fire  alarm  systems  to  improve  and  increase  safety conditions. 

 

 

Insulation  Medium:  Sulphur  Hexafluoride  Gas  (SF6)  is  employed  as  insulation  in some parts of the installation including disconnecting and earthing switches and also in  the  circuit‐breaker  for arc‐quenching. SF6   is an electronegative gas;  its dielectric strength  at  atmospheric  pressure  is  approximately  three  times  that  of  air.  It  is incombustible, non‐toxic, odorless, chemically  inert with arc‐quenching properties 3 to 4 times better than air at the same pressure. The remaining parts such as 132kV busbar, current and voltage transformers and serge arresters, are air exposed. 

 Power Transformer: A power transformer is a device which is used to step up or step down the voltage without changing the frequency. The operation of step up or step down  is normally decided by requirement whether electric power has to be utilized or transmitted. For the HIS grid station, the power transformer will be used to step down 132 kV to 11 kV.   Internal part of transformer will be filled with highly purified mineral  oil  (known  as  transformer  oil)  for  insulating,  reducing  corona  and  arcing purposes. It is also used as cooling medium at high temperatures. 

Page 67: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

2.3.4  Transmission Lines 

 Transmission  lines  are  high‐voltage  underground/overhead  power  lines  ‐  the  lines operated  for  long‐distance  transmission  of  electricity  in  order  to  reduce  power losses, while distribution  lines are at  lower voltages than transmission and are used for  distributing  electricity  round  an  area. Underground  transmission  lines  are  laid from  the  grid  station  to PLDP point  at  the main  road. The  total  length  for 132  kV overhead  lines  is  about  1.2  km  from  this  point  up  to  Samama  junction  near University  road.  Several  11  kV  distribution  lines  will  also  emanate  from  the  grid station. 

 

2.4  Project Construction  

The  land  for  the  grid  station  has  been  identified  and  provided  by  KESC.  The constructed  HIS  Grid  Station  would  occupy  an  area  of  approximately  0.92  acres (3720 sq meters). The major construction activities comprise of the following: 

 Construction of Sub‐Structure: Piling  is done up  to a depth of 14‐16m due  to high water  table  and  typical  soil  characteristics.  Construction  of  sub‐structure  includes construction  of  tanks,  base  slabs,  and  other  earth  work.  The  activities  that  are executed  at  site  include  excavation,  leveling  and  grading,  formwork,  steel  cutting and binding, concrete mixing and placement etc. 

 Construction  of  Super‐Structure:  This  largely  includes  construction  of  concrete building  structure  and  tanks  along  with  other  ancillary  works,  formwork,  steel cutting,  bending  and  binding,  concrete mixing,  transport  and  pouring,  plastering, painting  and  polishing,  chemical  coating,  installation  of mechanical  and  electrical equipments, piping and glazing works etc. 

 Utility  Connections:  This  would  mainly  include  provision  of  power  for  electrical equipments.  It would  also  include  cabling work  involved  in  transmitting  power  to various  areas.  Basic  infrastructure  to  support  the  construction  of  the  facilities  is available in the area. 

 

2.5  Erection and Commissioning  

Gantry  cranes  and  scaffolding  will  be  required.  Cranes  of  5  Tons  capacity  are recommended for complete bays, lifting gear of 2 to 4 Tons capacity is sufficient for assembling prefabricated GIS units. Cleanliness on site  is very important, in order to avoid dirt on the exposed parts of joints. 

 

2.6  Operation and Maintenance  

The  grid  station  will  be  manned  round  the  clock  and  all  important  parameters (voltage,  load,  power  factor,  etc.)  monitored.  Daily  log  sheets  will  be  filled  by recording   the   key   data.   Any   abnormality   will   be   recorded   and   concerned departments informed for taking remedial measures. The key activities will include: 

Page 68: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

• Operation of grid stations 

• Scheduled maintenance 

• Checking/testing of transformers 

• Testing of breakers 

• Testing of protection system 

• Transmission line patrolling 

• Replacement of insulators 

• Emergency maintenance 

• Locating the fault 

• Carrying out repairs or replacements 

• Restoring the system to the normal operating conditions 

 2.6.1  Maintenance of Transformers 

 The minor repairs for the power transformers will be carried out at the grid station, however  for  the  major  repairs,  transformers  will  be  transported  to  KESC’s  Grid Station Maintenance Workshop. 

 2.7  Land Use and Ownership 

 As mentioned earlier, KESC owns a 2 acres plot in Block‐16,  Gulistan‐e‐Jauhar.  Approximately  0.92 acres  is used  for construction of  the grid. At one end  of  the  plot  is  KESC’s  Virtual  Integrated Business   Center  (VIBC),   the   central   portion   is kept  open  for  possible  future  construction  of KESC’s  hospital.  The  infrastructure  and  utility services  are  already  available  in  the  area  and have  the  capacity  to  serve  the  anticipated requirements of the project. Land acquisition and resettlement  due  to  construction  of  grid  station is not an issue. 

 Acquisition for Right of Way:  The contractors are responsible for acquiring right of way on behalf of the proponent throughout the alignment of transmission lines. The contractors  obtain  permits‐to‐work  way  leaves  and  approval  from  other departments/ authorities and right of way from private owners, when required. KESC 

also assists the contractor in this regard.3  2.8  Analysis of Alternatives 

 The  alternatives  to  the grid  station are discussed below. These  include no project alternative, alternate project sites and the alternate technology options. 

    

3 Source; KESC Management 

Page 69: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

2.8.1  No Project Alternative 

 The  justification of the project has already been discussed  in the previous sections. The project seeks not only the up gradation of the secondary transmission and grid network  of  KESC  system  but  also  allows  for  the  reliable  supply  of  electricity  to Gulistan‐e‐Jauhar,  Gulshan‐e‐Iqbal  and  part  of  KDA  Scheme  33, where  demand  is expected to grow  manifolds in future. The grid station will also ensure uninterrupted power supply  to  the  future hospital of KESC.  In case  the project  is not undertaken, KESC  system  will  not  be  able  to  cope  with  this  increasing  demand.  The  existing system will  remain  over‐loaded,  line  losses will  also  remain  high  and  the  system reliability  will  progressively  decrease  with  an  increasing  pressure  on  the  system. KESC will also forego the opportunity of increasing its consumers as well as revenue associated  with  the  system  expansion.  In  view  of  the  above,  the  ‘No  Project’ alternative is not considered a preferred option. 

 2.8.2  Project Sites Alternatives 

 Setting of a grid  station  is primarily governed by  various environmental and  social considerations including the following; 

 

 

• Availability and location of land 

• Road accessibility 

• Proximity to any settlement 

• Presence of any wildlife/natural vegetation of any significance 

• Possibility and  impact of any air or water contamination caused by  the project activities 

• Possibility of damage to any public infrastructure 

• Other Environmental consideration 

 The site was selected and approved by the KESC officials after considering all aspects mentioned above. The plot  is owned by KESC,  is at a reasonable safe distance  from the surrounding residential areas and is also easily accessible through a wide road. At one end of the plot, KESC’s Virtual Integrated Business Center (VIBC)  is constructed. KESC plans to build a hospital on the remaining portion of the plot. 

 2.8.3  Alternative Technologies for Grid Stations 

 Conventional Grid Stations (AIS): The conventional grid stations have open yards for transformers  and  their  accessories while  the  control panels  and  feeder panels  are placed  indoors. These grid  stations  require a  large area  (about 4 acres), which  is a problem in congested urban areas. The environmental and socioeconomic aspects of this type of grid station include safety hazard for the nearby population, particularly in the congested urban areas. 

 Gas  Insulated Grid Stations (GIS): The gas  insulated grid stations (GIS) on the other hand employ a very compact design and most of equipment is fully enclosed and gas insulated. This allows the entire system to be placed indoors in considerably smaller 

Page 70: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

space compared to the conventional design. However, the cost of these grid stations is higher than the conventional ones. 

 Hybrid  Integrated System Grid Stations  (HIS):  In view of the  fact that the new grid station is being planned within the boundary walls of an open plot, owned by KESC in a  fairly  limited  space  within  an  urban  area,  a  combination  of  the  above  two technologies  is  adopted  which  is  termed  as  Hybrid  Integrated  System  (HIS).  The integrated use of  technologies will  lead  to effective  cost  savings while providing  a safer alternative in comparison to the conventional grid stations. 

 Table 2.1 presents a comparison of the two technologies, combined in the project; 

 Table 2.1 

Comparison of AIS & GIS Technologies  

Aspects

AIS GIS

Space Saving

Large space required Up to 90% space saving in comparison to AIS

Capital Cost Low High Civil Works & Maintenance Cost

High Low

Operational Life 25‐30 years 40‐50 years

Operational Safety Medium High

EMF Effects Reduces Electrical & Magnetic Fields

Removes Electrical & Reduces Magnetic Fields

Flexibility Can be extended or modified easily

Cannot be extended or modified

2.8.4  Transmission Line Alternatives 

 The most preferable  route  is  the one which avoids settlements and other sensitive areas.  During  the  field  visits,   it  was  observed  that  the  selected  route  was  a reasonable  option  that  did  not  have  an  unacceptable  level  of  environmental  and social  impacts.  Furthermore,  appropriate mitigation measures  are  incorporated  in the   design   and    implementation   of    the   works    to   reduce    the    impacts.   These alternatives  include  construction  of  traditional  overhead  transmission  lines  and underground  cable  system.  Table  2.2  presents  a  comparison  of  these  two alternatives. 

Page 71: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Table 2.2 Comparison of Overhead & Underground Transmission Routes 

 

Aspects

Overhead Underground

Technical Comparatively less skilled manpower required

Trained manpower required

Economical

Lower O&M Cost, preferred for longer routes

Higher O&M Cost (about 3 times the overhead option), preferred for shorter routes

Environmental Can threaten endangered bird species

Increase in soil disturbance & chance of soil contamination

Social

No threat to existing utilities

Possible disturbance to the public utilities & traffic during construction phase

Safety

Poles are susceptible to fall during bad weather causing damage to life & property

Relatively safer

Health

Possible EMF exposure Effectively reduces the electric field exposure

Conclusively,  under  the  current  technical  and  socio‐economic  conditions,  the underground transmission  line presents a better option for 132 kV routes up to the boundary wall  of  the  grid  station  premises  keeping  in  view  the margin  for  future construction of KESC’s Hospital on the plot while overhead lines are a better option for  one  kilometer  transmission  line  route  outside  the  premises  up  to  Samama Junction near University Road as it involves minimum soil disturbance and would not disturb the existing public utilities. 

 2.8.5  Type of Circuit Breakers 

 Traditionally, oil‐filled circuit breakers are  installed at  the 132 kV and 11 kV  levels. However, now SF6 circuit breakers are available for 132 kV and above, and vacuum circuit breakers are available  for  the 11 kV  systems, which have very effective arc‐ quenching characteristics, compared to the old oil‐type breakers. The environmental aspects  of  the  oil‐filled  circuit  breakers  essentially  pertain  to  the  soil  and  water contamination caused by the possible oil leakage. Therefore, modern circuit breakers are the preferred option for the project. 

 2.8.6  Types of Transformer Oil 

 Traditionally,  transformer  oil  is meant  for  providing  insulation  and  cooling  of  the transformer  windings.  Previously  poly‐chlorinated  biphenyl  (PCB),  a  man‐made chemical  known  for  its  excellent  dielectric  properties  was  used.  However,  this chemical was found to be highly toxic, and more importantly, chemically very stable that would  not  decompose  or  disintegrate  naturally.  Due  to  this  property,  it was included  in a group of chemicals collectively known as persistent organic pollutants (POPs). 

Page 72: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  1

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

In view of their extremely harmful effects, use of this oil is not a preferred option for all applications,  including  the  current project. As mentioned earlier, highly‐refined, mineral  insulating oils  is used  to cool  transformers and provide electrical  insulation between live components. 

Page 73: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  19

    

LEGISLATION, GUIDELINES 

AND INSTITUTIONAL FRAMEWORK 

CHAPTER 

3  

  

3.1  General  

This chapter describes the current legal framework which is applicable on the project in  context  of  environment  and  sustainable  development.  The  institutional arrangement  that  exists  in  Pakistan  and  may  influence  the  environmental management of  the project  is  also discussed  in  this  chapter.  In  addition  to  above, this  chapter  also  emphasizes  on  the  procedure  required  to  be  followed  by  the project proponent for the submission of EIA Report to relevant EPA. 

 3.2  Background 

 The Government of Pakistan realized the  importance of environmental preservation way back  in the early 1980’s. A variety of environment‐related acts and ordinances existed, but the Pakistan Environmental Protection Ordinance 1983  (PEPO) was  the first   effort   to  deal   with   environmental   concerns   systematically.  The  ordinance created  a  legal  basis  for  comprehensive  environmental  policy  making,  the establishment  and  enforcement  of  standards,  environmental  impact  assessments 

and the inclusion of environmental considerations in development policies4. In 1984, Pakistan Environmental Protection Agency (Pak‐EPA) was established as the primary government  institution dealing with environmental  issues. NEQS  for municipal and liquid industrial effluent, industrial gaseous emissions and motor vehicle exhaust and noise, were issued by Pak‐EPA  in 1994. The NEQS has been modified and updated a couple  of  time  since.  PEPO  1983  was  replaced  with  the  Pakistan  Environmental Protection Act in 1997 i.e. PEPA 1997. 

 The UN  International  Summit on  Environment was held  in 1992  in Rio de  Janeiro. Pakistan  also  became  a  signatory  of  this  summit.  After which  the Government  of Pakistan developed a National Conservation Strategy  (NCS) which was approved by the Government of Pakistan on March 1992. It was decided that all reports regarding strategies, policies  and program  for  sustainable development will  be drawn  up  on 

the basis of  the NCS5. Another major environmental policy  initiative  formulated  in 1999 was Environmental Planning and Resource Conservation Project (EPRCP)6. 

      

4 “Industrial policy and the Environment in Pakistan”: United Nations industrial development   organization; 11 December, 2000; pg.8. 

5 “A model process to develop a National Agenda”: Pakistan National Conservation Strategy; pg1. 6  “Industrial policy and  the Environment  in Pakistan”: United Nations  industrial development  organization; 

11 December, 2000; pg.9. 

Page 74: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  20

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

To provide  the necessary guidelines  for  the preparation,  submission and  review of IEE  and  EIA,  Pak‐EPA  review  of  IEE  and  EIA  Regulations,  2000  and  Pakistan Environmental Assessment Procedures were published. 

 3.3  Environmental Legislations 

 The  key  environmental  regulations  and  legislations  which  are  applicable  to  the project are discussed below. 

 3.3.1  National Regulations 

 The  environmental  policy  framework, which will  govern the project,  is the NCS of Pakistan. The Pakistan NCS  is a broad  based  policy  statement  aimed  at  achieving environmentally  sustainable  social  and  economic development  in Pakistan. The three overriding objectives of the NCS are: 

 

 

• Conservation of natural resources 

• Sustainable development 

• Improved efficiency in the use and management of resources 

 Three operating principles are identified to achieve these objectives. These are: 

 

 

• Greater public participation in development and environmental management 

• A merging of environmental and economic decision making 

• Lasting improvements in the quality of life  

 

The NCS  specifies  the basic guidelines  for an  integrated effort aimed at protecting the  environment  and  the  natural  resources  of  the  country.  This  broad  framework provides a comprehensive point of  reference  for all agencies, departments, private sector  companies,  financial  institutions,  and  donor  agencies  for  undertaking 

systematic efforts to bring about an effective change for sustainable development7.  

The  grid  station  is  aligned  with  the  above  mentioned  operating  principles.  The project aims to attain the NCS objectives at  its own  level: by  improving the national power  transmission  and  distribution  capacity;  by  enhancing  load  bearing  capacity and capability of power system; and by system stabilization in order to cater for the existing and future load needs. 

 

        

7 Qadar S., and Dogar A. R., Pakistan’s Environmental Laws & Their Compliance, Lahore Law Times Publications, 2002. 

Page 75: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  21

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

3.3.2  Pakistan Environmental Protection Act, 1997  

 

PEPA 1997  is  the  apex environmental  law of  the  country. Under  section 12 of  the 

Act,  it  is mandatory  for  the proponents of  the projects8  to execute  the  IEE and/ or EIA  (where warranted), and get  the approval  from provincial EPA. A  copy of PEPA 1997 is attached as Annexure – 2 of this report. 

 The   following   rules   and   regulations   have   been    issued   under   the   Pakistan Environmental Protection Act, 1997. 

 Rules: 

• National   Environmental  Quality   Standards   (Self‐ monitoring   and   Reporting   by   Industries)   Rules, 2001. 

• Provincial  Sustainable  Development  Fund (Procedure) Rules, 2001. 

• Pakistan  Sustainable  Development  Fund (Utilization) Rules, 2001. 

• Pollution   Charge   for   Industry   (Calculation   and Collection) Rules, 2001. 

• Environmental  Tribunal  Procedures  and Qualifications Rules, 2000. 

• Environmental Samples Rules, 2001. 

• Hazardous Substance Rules, 2000. 

 Regulations: 

• Review of IEE / EIA Regulations, 2000. 

• National   Environmental   Quality   Standards    (Certification   of   Environmental Laboratories) Regulations, 2000. 

 The  PEPA  has  entrusted  the  authority  of  review  and  to  approve  environmental assessments  to  the  provincial  EPA.  The  project  falls  under  the  jurisdiction  of  the Sindh Environmental Protection Agency (SEPA). This EIA report is being submitted to SEPA  for  its  review and grant of NOC. Under  the Act,  the EPA will do  its utmost  to process  the  application  within  90  days  of  its  submission.  The  project  could  be deemed to be approved if SEPA does not inform otherwise within 04 months of the submission of EIA report. 

    

8  The Act  defines  a  Project  as:  “Any  activity,  plan,  scheme,  proposal  or  understanding  involving  any change in the environment and includes: 

− Construction or use of buildings or other works; − Construction or use of roads or other transport systems; − Construction or operation of factories or other installations; − Mineral prospecting, mining, quarrying, stone‐crushing, drilling, and the like; − Any change of land use or water use; and − Alteration, expansion,  repair, decommissioning or abandonment of existing buildings or other works, 

roads or other transport systems, factories or other installations.” 

Page 76: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  22

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

3.3.3  Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, 2000 

 Two types of environmental assessments can be carried out i.e. IEE and EIA. EIAs are carried out for the projects that have a potentially significant environmental impact, and IEEs are conducted for relatively smaller projects with relatively lesser significant impacts. 

 The  Pakistan  Environmental  Protection Agency Review  of  IEE  and  EIA  regulations, 2000 prepared by Pak‐EPA under the powers conferred upon it by PEPA, categorizes 

projects  for  IEE  and  EIA,  respectively9.  As  per  Schedule‐II  of  PEPA  Regulations (Review of IEE and EIA), the project lies under Category A “Transmission Lines (11kV and above) and Grid Stations” requiring an EIA. 

 According  to  the  details  provided  in  the  regulations  regarding  preparation, submission,  and  review  of  IEE’s  and  EIA’s,  following  is  a  brief  description  of  the approval process. 

 a.   A  project  is  categorized  as  requiring  an  IEE  or  EIA  using  the  two  schedules 

attached to the regulations i.e. Schedule I and II attached as Annexure – 3 at the end of this report. 

b.   An EIA or IEE is conducted as required and following the Pak‐EPA guidelines. c.    The EIA or IEE is submitted to the concerned EPA: provincial EPAs if the project is 

located  in  the provinces or Pak‐EPA  if  it  is  located  in  the  Federal administered area. 

d.   A non refundable review fee, depending on the cost of the project and the type of  the  report,  is  submitted along with  the document as per  the  rates  shown  in Schedule III (attached as Annexure – 3). 

e.   The submittal  is also accompanied by an application  in the format prescribed  in Schedule IV of the regulations. 

f.  The  EPA  conducts  a  preliminary  scrutiny  and  replies  within  10  days  of  the submittal  of  a  report,  (i)  confirming  completeness,  or  (ii)  asking  for  additional information, if needed, or (iii) returning the report requiring additional studies, if necessary. 

g.   The  EPA  is  required  to make  every  effort  to  complete  the  IEE  and  EIA  review process within  45  and  90  days,  respectively,  for  the  issue  of  confirmation  of completeness. 

h.   When the EPA accord their approval subject to certain conditions: i.   Before commencing construction of the project, the proponent is required to 

submit an undertaking accepting the conditions. ii.     Before  commencing operation of  the project,  the proponent  is  required  to 

obtain from the EPA a written confirmation of compliance with the approval conditions and requirements of the IEE or EIA. 

i.  An environmental management plan (EMP) is to be submitted with a request for obtaining   confirmation of compliance. 

    

9 PEPA Review of IEE and EIA Regulations, 2000, pg‐2 

Page 77: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  23

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

j.  The  EPA  is  required  to  issue  confirmation of  compliance within 15 days of  the receipt of request and complete documentation. 

k.     The  EIA  /  IEE  approval  is  valid  for  three  years  from  the  date  of  accord.  The proponents are required to complete the construction and installation within this time  period  and  start  operations.  In  case  of  any  delays,  the  proponents  are required to obtain extension from EPA. 

 This EIA report has been prepared  in compliance of the Pak‐EPA guidelines and  it  is being submitted to SEPA for their approval by KESC, as the project proponent. 

 3.3.4  National Environmental Quality Standards (NEQS) 

 

With  the  PEPA  1997,  the  Pak‐EPA  revised  the  NEQS with  full  consultation  of  the private   sector:    industrialists,    trade   and   business   associations   and   NGOs.   The municipal  and  liquid  industrial  effluent  standards  cover  32  parameters  and  the standards  for  industrial gaseous emissions  specify  limits  for 16 parameters10  which are given in Annexure – 4. 

 Regulatory provisions of PEPA‐97 under section 11 prohibit discharge or emission of effluent, waste, air pollutant or noise in excess of the NEQS11. 

 3.3.5  Pakistan Penal Code 1860 

 The Pakistan Penal Code deals with the offences where public or private properties and/or human  lives are affected due  to  intentional or accidental misconduct of an individual  or  body  of  people.  In  the  context  of  environment,  the  most  relevant clauses of this law have been summarized in the following: 

 Section  277.  Fouling  water  of  public  spring  or  reservoir:  Whoever  voluntarily corrupts or fouls the water of any public spring or reservoir, so as to render it less fit for the purpose for which  it  is ordinarily used, shall be punished with  imprisonment of  either  description  for  a  term which may  extend  to  three months,  or with  fine which may extend to [one thousand five hundred rupees], or with both. 

 Section  278. Making  atmosphere  noxious  to  health: Whoever  voluntarily  vitiates the  atmosphere  in  any place  so as  to make  it noxious  to  the health of persons  in general  dwelling  or  carrying  on  business  in  the  neighborhood  or  passing  along  a public  way  shall  be  punished with  fine  which may  extend  to  [one  thousand  five hundred rupees]. 

 Section   285.   Negligent   Conduct   with   respect   to   fire   or   combustible   matter: Whoever  does, with fire or any combustible matter, any act so harshly or negligently so  as  to  endanger human  life, or  to be  likely  to  cause hurt or  injury  to  any other person, or knowingly or negligently omits  to  take  such order with any  fire, or any 

 

 10 “Industrial policy and the Environment in Pakistan”: United Nations industrial development  organization; 

11 December, 2000; pg.39. 11 “Pakistan’s waters at risk”, Water and health related issues in Pakistan and key recommendations; 

Feb 2007, WWF‐Pakistan; pg‐15. 

Page 78: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  24

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

combustible matter  in his possession as  is  sufficient  to guard against any probable danger  to human  life  from such  fire or combustible matter, shall be punished with imprisonment of either description  for a  term which may extend  to six months, or with fine which may extend to [three thousand rupees] or both. 

 3.3.6  The Forestry Act, 1927 

 As there is no reserved forest that exists in the vicinity of the project, the provisions of this law are not applicable to the project. 

 3.3.7  The Antiquities Act, 1975 

 By this Act Government of Pakistan has been given the power to prohibit excavation in any area  that may contain articles of archeological significance12. Under  the Act, the project proponents are obligated to ensure that no activity is undertaken within 200  ft  of  a  protected  antiquity13,  and  to  report  to  the  department  of Archeology, Govt. of Pakistan, any archeological discovery made during the course of the project. 

 3.3.8  Factories Act 1934 

 These are not entirely environment  related  laws, but do  incorporate many  clauses pertaining  to general environmental conditions and occupational health and  safety issues. The clauses relevant to the project are those that concern the health, safety and welfare of workers, disposal of solid waste and effluent, and damage to private and public properties. The act also provides regulations for handling and disposing of toxic and hazardous materials. 

 A summary of the relevant applicable laws is provided in Annexure – 5 of this report. 

 3.3.9  Electricity Act, 1910 

 

 

This Act provides a  legal base  for power distribution. A “licensee” under  this Act  is enabled  to operate  for  the  supply of  electricity.  This Act obligates  licensee  to pay compensation for any damages caused during the constructions and maintenance of any power distribution facilities. 

 3.4  NEPRA Licensing (Application & Modification Procedure) Regulations ‐ 

1999  

The  National  Electric  Power  Regulatory  Authority  (NEPRA)  was  established  in December 1997. NEPRA  is  responsible  for  regulating  the power  sector, developing and implementing the regulatory system according to requirements. 

     

12   “The Antiquities Act, 1975”; Section 29 (1) 13   “The Antiquities Act, 1975”; Section 22 

Page 79: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  25

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Clause 3(6) of the NEPRA Licensing Regulations and accompanying Schedule III enlists the  documents  to  be  submitted  along  with  the  application  for  license.  These documents  include  an  Environmental  &  Social  Soundness  Assessment  Report  for new  thermal  power  generation  facilities,  and  emission  values  and  environmental monitoring  data  for  the  last  five  years  for  existing  thermal  power  generation facilities. NEPRA Licensing Regulations are attached as Annexure – 6. 

 3.5  Guidelines 

 The  Federal  EPA  has  published  a  set  of  environmental  guidelines  for  carrying  out environmental assessments and  the environmental management of different  types of development projects. 

 3.5.1  General Guidelines 

 Key  environmental  guidelines  present  in  Pakistan  Environmental  Assessment Procedures  were  taken  into  consideration  while  conducting  this  environmental study. These include: a.   Policy   and   procedures   for   filing,   review   and   approval   of   environmental 

assessments. b.   Guidelines for the preparation and review of Environmental reports. c.   Guidelines for Public Consultation. d.   Guidelines for Sensitive and critical areas. 

 

3.6  Institutional Setup for Environmental Management  

The  structural  setup  of  agencies/departments  in  the  environmental  sector  is  such that the Federal Ministry of Environment governs and regulates environment‐related work at the government level. The PEPA works directly under the control of ministry at  the  federal  level.  The  provincial  environmental  protection  agencies  regulate environmental  related work  at  the  provincial  level.  The  institutional  framework  is such  that  the Ministry  of  Environment  (MoE)  deals with  environment  and wildlife issues at the Federal  level. Within the ministry, the NCS unit, established  in 1992,  is responsible for overseeing the implementation of the NCS. 

 3.6.1  Pakistan Environmental Protection Council (PEPC) and the Pakistan Environmental 

Protection Agency (Pak‐EPA)  

These  two  organizations,  PEPC  and  Pak‐EPA  are  primarily  responsible  for administering the provisions of the PEPA 1997. The PEPC oversees the functioning of the Pak‐EPA.  Its members  include  the  representatives of  the government,  industry, non governmental organizations and  the private sector. The Pak‐EPA  is  required  to ensure compliance with the NEQS, establish monitoring and evaluation systems, and both identify the need to, as well as initiate legislation whenever necessary. It is thus the  primary  implementing  agency  in  the  hierarchy.  The  provincial  EPAs  are  the provincial  arms  of  the  federal  EPA, which  is  authorized  to  delegate  powers  to  its provincial  counterparts.  One  of  the  functions  delegated  by  the  Pak‐EPA  to  the provincial EPA is the review and approval of environmental assessment reports. 

Page 80: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  26

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

3.6.2  Sindh Environmental Protection Agency (SEPA) 

 Each  provincial  government  has  its  own  environmental  protection  institution responsible  for  environmental  pollution  control.  The  SEPA  is  responsible  for  the approval of the EIA and IEE of new developments undertaken in Sindh. 

 3.7  Other Relevant Laws 

 3.7.1  IFC Environmental, Health, and Safety Guidelines  for Electric Power Transmission 

and Distribution 

 The  EHS  Guidelines  for  Electric  Power  Transmission  and  Distribution  include information  relevant  to  power  transmission  between  a  generation  facility  and  a substation located within an electricity grid, in addition to power distribution from a substation to consumers located in residential, commercial, and industrial areas. 

 These   EHS   Guidelines   contain   the   performance    levels   and   measures   that   are generally  considered  to  be  achievable  in  new  facilities  by  existing  technology  at reasonable costs. Application of the EHS Guidelines to existing facilities may  involve the   establishment   of    site‐specific    targets,   with   an   appropriate    timetable    for achieving them. 

 The applicability of  the EHS Guidelines  should be  tailored  to  the hazards and  risks established  for  each  project  on  the  basis  of  the  results  of  an  environmental assessment in which site specific variables, such as host country context, assimilative capacity of the environment, and other project  factors, are taken  into account. The applicability  of  specific  technical  recommendations  should  be  based  on  the professional opinion of qualified and experienced persons. 

Page 81: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  27

    

ENVIRONMENTAL DESCRIPTION OF  PROJECT AREA 

CHAPTER 

4  

  

Spatial project boundary is defined as the specific site area that includes the areas of construction  and  the  zones  of  influence  around  the  construction  site  i.e. physical, biological and  socioeconomic.  It  specifically  includes  the  construction area and  the land adjacent to  it. The adjacent  land  includes any area that  is directly disturbed by the construction and operational activities of the project. The project boundary may vary for different major areas covered under physical, biological and socioeconomic environment depending upon the areas of influence. 

 4.1  Physical Environment 

 Details of  the physical environment of  the area of  the project site are described  in this  section.  The  emphasis  is  given  on  physical  environment  such  as;  geology, topography,  soil  conditions,  climate,  surface  &  ground  water  resources  and seismology of the project site. Most of the data presented  in the following sections has been collected from the secondary sources.  Project team contacted the relevant departments  and  gathered  the  required  information. Available  data has  also been reviewed  for  the  verification.  In most  cases,  the  secondary  data was  also  verified through site visits. 

 4.1.1  Location and Surrounding 

 Gulistan‐e‐Jauhar  is  one  of  the  busiest  and  densely  populated  residential  areas of Karachi.  It  is  surrounded by Gulshan‐e‐Iqbal on  the North  and on  the West,  Faisal Cantonment on  the South, Malir Cantonment on  the East and  Jinnah  International Airport on the South‐East directions. The project site is located in the VIP Block 16‐A of  Gulistan‐e‐Jauhar,  within  the  geographical  coordinates  of  24°54’53.66”N  and 67o07’17.14”E. Location and surroundings of the project are shown in Figure 4.1. The project site is owned by KESC, it is located on the New Service Line Road adjacent to the vacant land owned by PIA. The total constructed area of Grid Station is 200 x 200 square feet. 

 The project  is being constructed on a commercial  land, close to the residential area of  Gulistan‐e‐Jauhar  Block‐16.  Haroon  Royal  City  Apartments,  Naveed  Bungalows and  Cottages  are  in  close  vicinity  of  the  said  project  towards  the  South.  KESC’s Customer Service, Beacon House School, Karachi Gymnasium and a  few  residential blocks  are  located  behind  the  project  site  in  north‐western  direction.  Other neighboring  entities  include  PIA  Cricket  Training  Academy  and  Imam  Khomaini University on the western side while VIBC  (Virtual  Integrated Business Center)  is on the East. Overhead transmission  line route  is along the New Service Line Road from the grid station boundary wall up to Samama Junction, close to University Road. 

Page 82: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  28

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Fig 4.1: Location & Surrounding of Project Site  4.1.2  Soil and Geology 

 Karachi has plains, hills, rivers, valleys and coasts as physical features. Rocks ranging image from Eocene to Recent, deposited under shallow marine to deltaic conditions are exposed. The city  is a part of a major Synclinorium stretching  from Ranpathani River  in the east to Cape Monze  in the west and Mehar and Mol Jabals (mountains) in the north. 

 Within the synclinorium, a number of structures such as Pipri, Gulistan‐e‐Jauhar, Pir Mangho and Cape Monze are exposed. The presence of concealed structures under the  Malir  River  Valley,  Gadap  and  Maripur  plains  can  fairly  be  deduced.  Rock aggregates,  sand,  glass  sand,  limestone  and  clay  are  some  of  the  potentials  for gainful  utilization.  Gulistan‐e‐Jauhar member  of  Gaj  Formation  offer  groundwater 

potential for limited use14.        

14 Geological Map of Karachi Pakistan 2001 

Page 83: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  29

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Soil  in  Karachi  is  not  uniform  everywhere  and  varies  from  place  to  place.  For instance,  the soil  in  the old  flood plain of  two  rivers namely Lyari and Malir and  in their  tributaries  comprised of  admixture of  generally  coarse  to medium  sand with gravels  and  silt  and  clay  layers. While  in  the  coastal  areas  it  is  generally  fine  to medium  sand with  clay  and  silt. As  such  the  soils  in Karachi Division  are  varied  in 

nature and admixture of sand, silt, gravel and layers of clay.15 

 a.   Stratification 

 

The stratification sequence of formations in Karachi is as under;16 

 Formation Age Lithology

Mancher

Pliocene Mainly comprises of sandstone and shales with subordinate conglomerate in gritty, friable and bedded

Gaj

Miocene It comprises of calcareous sandstone and limestone and has a gradation contact

Nari

Early Miocene to Pliocene

It consists of mainly sandstone and shale with subordinating limestone and conglomerate. Limestone exists at base but is not present everywhere

b.   Lithology 

 A member of Gaj formation of Miocene age namely Gulistan‐e‐Jauhar is found at the project area and  its  surroundings.   The Gulistan‐e‐Jauhar member  is newly proposed  for an assemblage of  rocks  that are exposed  in Gulistan‐e‐Jauhar and continues   obliquely   south‐eastwards    to    the   Defence   Housing   Society.   The member has yellow to light brown siltstone and sandstone, grey clays and yellow 

limestone.17 

 The geological map depicting  the stratification and  lithology of  the project area and its surroundings is shown in Annexure – 7. 

 c.   Topography 

 

 

Karachi may be broadly divided  into  two parts;  the hilly areas  in  the north and west  and  an  undulating  plain  and  coastal  area  in  the  south‐east.  The  hills  in Karachi are the off‐shoots of the Kirthar Range. The highest point of these hills in Karachi  is  about  528m  in  the  extreme  north.  All  these  hills  are  devoid  of vegetation and have wide  intervening plains, dry river beds and water channels. Karachi  has  a  long  coastline  in  the  south.  Away  from  the  shoreline  are  small 

islands.18 The project area has a maximum elevation of 139 ft (42m) above mean 

sea level19.  

15 Greater Karachi Sewerage Plan S III 2007 16 Geological Map of Karachi Pakistan 2001 

17 Geological Map of Karachi, Sindh Pakistan 2001 

18 The case of Karachi by Arif Habib 19 Google Earth Map 

Page 84: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  30

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

d.   Soil Conditions of the Project Area  

Soil testing of the project site was done on 14th  January 2010. According to soil 

investigation  report20   of  project  area,  the  top  layer  of  0.4m  consists  of  fill material and brown, loose, silty fine sand. Subsurface information of project area reveals that up to 7m depth the stratification is of grey, medium dense, silty fine sand. Furthermore there  is grayish brown, very dense, silty fine sand with traces of fine gravel from 7m to 12m. Beneath  it are 4m deep  layers, each of grey and brown,  very weak  to weak  rudaceous,  conglomerate material.  The  test  results are  attached  as Annexure  –  8  of  this  report. Due  to  these  soil  characteristics, deep pile foundations are constructed which transfer load to greater depths that have stronger strata. 

 e.   Seismology and Tectonic Activity 

 The prediction of  the potential earthquake  is mainly attributed  to  the presence of  active  faults  in  the  area.  There  are  four  active  faults  near  Karachi  and  its vicinity: Karachi Jati Allah Bund Fault (also known as Runn of Kutch Fault), Surjan Fault,  Jhimpir Fault and Pab Fault. Surjan Fault,  Jhimpir Fault and Pab Fault are 

the  segments  of  Runn  of  Kutch  Fault21.  These  faults  are  shown  in  Figure  4.2. Tectonic Map of Pakistan is attached as Annexure – 9. 

 Hence,  seismo‐tectonic  settings  surrounding  Karachi  can  be  divided  into  three regions; 

 

 

• On the southeast of Karachi, Rann of kutch has exhibited a recurring history of earthquake for the last two decades. 

 

 

• On the North of Karachi exists the Kirthar Fault zone.  

 

• On  the western  Balochistan  province,  it  is  endangered  by  complex  faults, including subduction boundary of Indian and Eurasian plates. 

 The project site falls in the eastern side of Karachi. Following are the Active and Probable Active Faults on the south‐east of Karachi; 

 

 

• Allah  Bund  Fault:  East‐west  trending  fault  with  a  length  of  90  km  runs parallel to the Nagar Parker Fault. 

 

 

• Nagar Parker fault: Fault trending East‐west and 200 km long exists in kutch seismic zone. 

 • Kutch  main  land  fault:  Fault  of  an  approximate   length  of  120  km  that 

produced Bhuj earthquake in 2001.  

  

20 Subsoil investigation report by Soil Testing services 21 Geological Survey of Pakistan, 1984 

Page 85: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  31

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Although  residents of Karachi  felt  shaking  from  the 1945 Makran and 2001 Bhuj earthquakes, and occasional shaking  from M 4‐5 earthquakes on  faults north  and  northwest  of  the  city,  no  earthquake  has  ever  produced documented damage in Karachi. 

                                      

Figure 4.2: Active Faults on Eastern Side of Karachi  4.1.3  Water 

 Karachi Water and Sewage Board  is  the  regulatory authority  for Karachi; KW&SB  is responsible for supplying potable water with an estimated average of 1.47m ³/d (323 

mgd). Two main sources used in this system include Indus River and Hub dam.22 The water distribution  system  in Karachi  covers 18  towns, 6  cantonments and Defence Housing Authority (DHA) area. These 18 towns are included in 3 administrative water supply zones by KW&SB. Water supplied to Karachi via Bulk water supply system  is through water trunk mains from water treatment plants, reservoirs pumping stations or Dumlottee Wells  in Karachi. These trunk mains  in turn supply the secondary and tertiary distribution  systems which distribute water within  the demand  areas.  The trunks main  transmission  system  in  Karachi  is  very  extensive with  over  500km  of large diameter pipelines. 

 

 22 Water & Sanitation, Situation Analysis Report, 2007 

Page 86: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  32

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

a.  Water Resources  

The sources of water supply at the project will be as follows;  

• KWSB line water 

• Bottled mineral water for drinking 

• Water Tankers are being used during construction phase  

At operational stage, water will be obtained from KWSB line. Underground water tank will be  constructed  for  storage purpose and will be maintained by GSO & GSM  departments  of  KESC.  Drinking  water  will  be  purchased  and  provided through dispensers. 

 b.   Ground Water 

 

The ground water  is  found at 2.4m23  depth  in  the project area; however  it will not be used during entire construction and operation phases. 

 4.1.4  Drainage System and Wastewater 

 Wastewater  is discharged  into  the main municipal drain. The  drainage  flow  in  the project area  is by natural gravity;  it  flows  through Mehmoodabad Treatment Plant into Malir River24. Karachi drainage pattern showing documented natural nalas and drains is shown as Annexure – 10. 

 Malir River  is  joined by Thadoo Nallah north of Super Highway and Sukkhan Nallah near National Highway from east. Flowing through Malir town, Shah Faisal town, and near Korangi town,  it discharges to Arabian Sea in Defence Housing Society areas.25 Malir River  is basically a  seasonal  river but becomes perennial within  the  limits of Karachi  due  to  the  continuous  flow  of  untreated  sewage  and  industrial  effluents through its basin into the Arabian Sea. The earlier studies have shown that the most downstream parts of  the  river are grossly polluted due  to  the  inclusion of  sewage and industrial wastes. The pollution has not only deteriorated the pristine conditions 

of this river but it is also causing pollution in Arabian Sea where river finally falls.26 

 4.1.5  Noise 

 Noise monitoring was carried out during the day time at the project site  in order to collect  the  baseline  information.  The  monitoring  was  done  at  all  corners  of  the project site along with the centre. The values are found to be  in the range of 55‐60 dB. 

 

     

23 Soil Investigation Report 24 Drainage Map of Karachi, Orangi Pilot Project 25 Greater Karachi Sewerage Plan S III 2007 26 International  Journal of  Biology & Biotechnology  (Jan‐Apr 2009) 

Page 87: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  33

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.1.6  Ambient Air Quality  

Primary air quality data was gathered on 3rd  February 2011 as part of the EIA study near  PLDP  point  during  day  time.  The  overall  levels  of  Ambient  Air Quality were found  within  prescribed  limits  of  reference  standards  except  for  particulate  level that was quite higher  at  the  site  due  to  construction being  carried out within  the project  premises.  The  results  are  summarized  in  Table  4.127.  Test  Reports  are attached as Annexure – 11 of this report. 

 Table 4.1 

Ambient Air Quality at Site  

Parameters Values NAAQS

PM10 (ug/m3) 78 150

PM2.5(ug/m3) 104 35

SO2    (ppb)28 16 75

NOx   (ppb) 18.1 100 CO    (mg/m3) Nil 40

Currently, Pakistan does not have ambient air quality standards. The air monitoring values when  compared with National Ambient Air Quality Standards29  (NAAQS)  set by USEPA are found to be within safe limits. 

 4.1.7  Temperature and Humidity 

 The city of Karachi  is  located on semi arid zone at 64o  longitude and 27o  latitude on the shores of the Arabian Sea. The climate of Karachi is moderate and sunny with up to 76 % mean  relative humidity during summer months. May and  June are hottest 

months of  the  year with  temperature  as high as 43oC while  January  is  the  coldest 

month with temperature as low as 5oC. In summer the mean air temperature is up to 33°C, while  the mean winter  air  temperature  is  18°C.  The mean  relative  humidity decreases during winter to 30%.  Rain  in Karachi  is seasonal, averaging  less than 22 cm  per  year  between  June  and  September  and  rare  for  the  rest  of  the  year. Occasionally,  there  are  dry  years  too  while  strong  coastal winds  and  better  dew 

formation are the characteristics feature of Karachi.30  

The Meteorological Observatory  at Karachi Airport  is  the nearest  station  from  the project  site and  therefore data  recorded  at  this observatory was  considered more appropriate  and  was  obtained.  Table  4.2  below  present  monthly  amount  of precipitation, mean monthly  relative humidity and mean monthly  temperatures of last three years (2007‐09)31. 

 

   

27 Soil Testing Report 28 ppb = (ug/m

3) x 24.46/(molecular weight of compound) 

29 http://www.epa.gov/air/criteria.html 30 Iqbal & Shafiq 1996 31 Pakistan Meteorological Department 

Page 88: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  34

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Table 4.2 Monthly Amount of Precipitation, Mean Relative Humidity 

& Temperature in Karachi 

  Precipitation (mm) Relative Humidity at 

1200 UTC (%) Temperature (oC)

Year 2007 2008 2009 2007 2008 2009 2007 2008 2009 Jan 0 8.0 3.0 31 28 37 19.9 17.2 20.5

Feb 13.2 0.1 0 44 30 40 23.4 19.0 23.2

Mar 33.4 1.1 0 43 36 46 25.5 27.0 26.9

Apr 0 0 0 47 48 35 30.3 29.2 29.9

May 0 0 0 57 66 55 31.8 30.6 32.2

Jun 110.2 0 2.6 64 62 63 32.5 32.1 32.2

Jul 41 54 159.9 66 63 69 31.3 30.7 31.3

Aug 250.4 37.5 44 72 68 71 30.1 29.4 30.2

Sep 0 0.1 68.9 59 58 67 30.6 30.7 29.6

Oct 0 0 0 35 48 46 28.6 29.7 29.2

Nov 0 0 0 41 31 31 26.2 25.0 25

Dec 17.4 21 1.5 31 47 32 20.0 21.0 21.2

Annual 465.6 121.6 279.9 49.2 48.8 49.3 27.5 26.8 27.6

4.1.8  Climate Wind Condition 

 Wind  blows  throughout  the  year with  highest  velocities  occurring  during  summer months, when the direction  is primarily from southwest to west. During winter, the wind blows  from north to northeast, shifting southwest to west during the evening hours.  The  wind  usually  carries  sand  and  salts  resulting  in  severe  erosion  and corrosion.  Though  occasionally wind  speeds  have  been observed  to  go  as  high  as 12.6 m/s to fall as low as 3.3 m/s, the predominant wind speeds have been observed to  range between 5  ‐ 10 m/s. Table 4.3 below presents mean monthly wind speed 

and wind direction of  the  last  three years32  while Figure 4.3  shows  the  same data graphically. 

 

                   

32  ibid 

Page 89: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  35

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Table 4.3 Mean Monthly Wind Speed (knots) & Wind Direction (at 1200 UTC) 

 Year 2007 2008 2009

Month Wind Speed

Wind Direction

Wind Speed

Wind Direction

Wind Speed

Wind Direction

Jan 4.1 S30W 4.3 N45E 7.0 N45E Feb 7.5 S62W 7.6 S47W 7.2 S45W Mar 6.8 S47W 8.2 S54W 7.9 S41W Apr 7.8 S55W 10.5 S51W 9.3 S58W May 10.2 S58W 12.6 S52W 9.8 S46W Jun 10.5 S47W 7.6 S39W 9.7 S42W Jul 8.6 S41W 11.0 S50W 9.5 S56W Aug 9.4 S55W 9.3 S52W 9.3 S49W Sep 8.0 S60W 8.7 S46W 9.1 S56W Oct 5.8 S48W 6.6 S39W 6.1 S42W Nov 6.2 S48W 5.1 S38W 5.0 S39W Dec 3.3 N45E 3.9 ‐‐ 3.9 S45E Annual 7.4 7.9 7.8 Source: Pakistan Meteorological Department (2007‐2009) 

 

                                   

Figure 4.3: Karachi Wind Rose 

Page 90: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  36

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.2  Biotic and Natural Environment  4.2.1  Flora 

 The  flora  of  Karachi  contains  element  from different  geographical  regions.  Different elements of flora found in the Karachi region are Irano‐Turanian  Flora  and  Saharo  Sindian  Flora. Flora of Karachi  is dominated by  Saharo  Sindian Flora, commonly known as Xerophytics. 

 The  study  area  where  the  project  site  lies  is  a residential land. No rare, endangered or endemic terrestrial  plant  species  were  observed  during the  site  visit,  neither  has  it  ever  been  reported from   the  site  or   its  surroundings.  There  was nothing untowardly particular about  the vegetation on  the project site  from either an ecological or commercial point of view. The plant specimens collected  from  the project  site  are  Azadirachta  indica  (Meliaceae  or  commonly  known  as  Neem), Jasaminum  grandiflorum,  Salvia  santolinifolia,  Datura  metal,  Araucaria,  Aclyfoka, Bougainvillea  glabra  (Nyctagynaceae),  Gnacum  officinale,  Paspalidium  punctatum (Poaceae),  Saocharum  munja,  Cassia  fistula,  Calotropis  procera  (Asclepiadaceae), Achyranthes wofera, and Phoenix dactylifera (Palmae). 

 4.2.2  Fauna 

 As  for  fauna,  there  are  no  endangered/rare  faunal  species  near  the  project  area. Terrestrial  fauna  of  the  area  includes  cats,  dogs,  goats,  chickens  etc.  The  bird community  found  in  the  area  includes  a  variety of  residential birds  such as House sparrows, House crows, Blue rock pigeons etc. Small House rats, House shrew, mice, some  insects, stripped palm  squirrel and a number of chameleons are also  seen  in the area. A mongoose was also sighted, indicating the possible presence of snakes in the area. 

 4.2.3  Ecosystem Sensitivities 

 The study area  is under extensive  institutional, residential and commercial use, and it  does  not  contain  any  sensitive  area  such  as  national  parks, wildlife  sanctuaries, biosphere  reserves,  historical  and  cultural  sites,  defense  installations  or  places  of historical, religious and cultural importance. 

 4.2.4  Aesthetics 

 The  project  is  located within  the  boundary walls  of  a  commercial  land,  close  to  a residential  area;  hence  it does  have  the potential  as  a  separate  recreational  spot. The  project  does  not  alter  the  view  of  any  residence,  roadway,  business,  etc. Therefore, there is no negative visual impact of the project on its surroundings. 

Page 91: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  37

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.3  Status of Socio‐Economic Environment  

For  establishing  the  baseline  of  socio‐economic  environment  in  the  area,  and  to assess the possibility of positive or negative impacts of the project, a socio‐economic profile of  the  surrounding  area  has been  developed.  The data  for  this  profile was obtained  during  a  number  of  field  surveys,  primarily  using  different  structured questionnaires. Sample of  the questionnaires used during  the  field surveys  is given as Annexure – 12. 

 4.3.1  Study Area 

 Gulistan‐e‐Jauhar, where the project is located, is one of the major neighborhoods of Gulshan‐e‐Iqbal Town of Karachi, Pakistan.  It  is named after a popular and dynamic Muslim political leader Maulana Mohammed Ali Jauhar. The project site neighbors a fully populated residential area of Block 16, and 17 of Gulistan‐e‐Jauhar that comes under  the  jurisdiction  of  Faisal  Cantonment.  The  Socio‐economic  study  has  been conducted    in   the   nearest   residential   areas   surrounding   the   project   site.   The important  landmarks of  study area are  clearly marked  in Figure 4.4. The  following sections describe the socio‐economic conditions prevailing in the area. 

                                       

Figure 4.4: Important Landmarks of Study Area 

Page 92: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  38

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.3.2  Administrative & Political Units  

Gulistan‐e‐Jauhar  is one of the major neighborhoods of Gulshan Town  in Karachi;  it comes   under  the   jurisdiction   of   UC‐10  Pehlwan   Goth   and   Faisal   Cantonment. 

Different blocks of Gulistan‐e‐Jauhar are marked  in Figure 4.533. The study area  lies in  the  Cantonment  Board  of  Faisal,  one  of  Karachi’s  six  (6) military  cantonments 

administered  by  the  Pakistan Army34.  The  study  area  is  a  recent  construct  having been altered  in 1995 by  the Government of Pakistan, Ministry of Defense, with  its municipal   extension    towards   Civil   Aviation,   KDA   Officer   Co‐operative   Housing 

Society, Town ship and Malir Halt areas35. 

 The  cantonments  do  not  fall  under  the  jurisdiction  of  the  Karachi  City  District 

Government. According  to  the  official CBF website,36   the  current  President  of  the Cantonment Board Faisal  is Mr. Akmal Hussain, who  is the Base Commander of PAF Faisal Base and Mrs. Zeenat Ahmed is the current Secretary, who is the Cantonment Executive  Officer.  The  study  area  falls  in  Gulistan‐e‐Jauhar,  Block  16,  under  the former  administrative  control  of  the Government of  Pakistan, Military of Defense. CBF  shares  its  boundaries with  Shah  Faisal  Town,  Jamshed  Town, Gulshan‐e‐Iqbal Town  and Malir  Cantonment. Map  of  Gulistan‐e‐Jauhar  showing  different  blocks surrounding  the  project  area  is  shown  in  Figure  4.5,  while  the  land  and  area distribution  of   Cantonment   Board   Faisal   and   the   adjoining   areas   is   shown    in 

Figure 4.6.37 

 In terms of parliamentary representation, the study area falls within the  jurisdiction of National Assembly constituency NA‐256 and Provincial Assembly constituency PS‐ 119.  The Member  National  Assembly  from  the  area  is Mr.  Iqbal Mohammed  Ali Khan;   he   belongs   to   the   Muttahida   Qaumi   Movement    (MQM).   The   Member Provincial  Assembly  is Mr.  Dr.  Nadeem  Maqbool  who  also  belongs  to  the  same political party. 

 As  for  the  law enforcement  function,  the area  falls under  the  jurisdiction of Drigh Road, Shahrah‐e‐Faisal Police Station. 

                 

33 http://221.132.118.186/CDGK/Portals/0/TownMaps/Gulshan_Map_Large.jpg 34 http://www.globalsecurity.org/military/world/pakistan/cantt‐karachi.htm 35 http://cbf.com.pk/ 36  ibid 37 http://cbf.com.pk/cbf_jurisdiction.html 

Page 93: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  39

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

                                          

Figure 4.5: Map Showing Different Blocks of Gulistan‐e Jauhar 

Page 94: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  40

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

                                                      

 Fig 4.6:  Map Showing Major Localities of Faisal Cantonment 

 4.3.3  Population of the Study Area 

 The  last  census  conducted  by Government  of  Pakistan  in  1998  recorded  the  total population  of  Faisal Cantonment  to be  around 130,074 people38. According  to  the secondary sources, the current total population of the study area is estimated to be around 16,000 to 18,000. 

 

 38 http://www.cbf.com.pk/ 

Page 95: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  41

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.4  General Profile of the Area  

Established  in  1995,  Gulistan‐e‐Jauhar  is  a relatively  recent  construct  and  is  still  in  the process of development. The area has around 2,500  residential  flats  divided  into  four main categories;  A,  B,  C  and D.  It  is  also  home  to one   of   the   largest   apartment   projects   in 

Asia,39  including Haroon Royal City, Rabia City, Rufi Lake Drive, Rufi Green City, Noman Grand City,  and  Gulshan‐e‐Amin  Towers.  The  most expensive and  lavish flats are those of Ahmed Residency, Decent Towers and Javed Hill View and  on  average,  comprising  of  over  500  apartments  each.  Economically,  it  is considered one of  the best  residential places  in Karachi  for  the middle  and  lower‐ middle classes. 

 The shops are located in Commercial Area of Rabia City, and are equally divided into 

three  phases,  i.e.,  Commercial  I,  II  and  III40  with  an  object  to  establish  planned commercial activities where respective stakeholders and ordinary people could have all the facilities. Having been developed relatively recent, the status of amenities and public services  is generally better  in this area compared to many other parts of the city. 

 4.4.1  Human Settlements 

 

                 

The  settlements  in  the  close  proximity  of  the  project  are mostly  large  apartment complexes including Haroon Royal City, Farhan Heaven Apartments and also Naveed Bungalows & Cottages. Haroon Royal City  is  situated  right  in  front of  the project’s main gate. The  land behind  the project site  is a vacant plot owned by PIA, beyond which are a few residential blocks. Other neighboring residential areas  include Long Life Bungalows, KDA Overseas Bungalows, Afnan Arcade and Gulshan‐e‐Amin. There are  two  illegal  settlements  along  the  project  site’s  boundary  near  PLDP.  All  the 

 

 39 http://www.bookrags.com/wiki/Gulistan‐e‐Jauhar 40 http://ckarachi.blogspot.com/2010/09/top‐14‐residential‐areas‐of‐karachi.html 

Page 96: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  42

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

apartment buildings are purely residential, housing middle class families of different ethnic  and  religious  backgrounds.  The  buildings  are  quite  well‐maintained  and general amenities of livelihood are present in the area. 

 4.4.2  Type of Houses 

 

                 

Haroon  Royal  City,  Farhan  Heaven  Apartments,  Naveed  Bungalows  and  Cottages, Long Life Bungalows, KDA Overseas Bungalows, Afnan Arcade and Gulshan‐e‐Amin, all are developed human settlements. 

 Haroon  Royal  City   is  the  closest  human  settlement  to  the  project  site  which comprises of two phases. Phase  I  is at the  front, which  further comprises of  fifteen (15)  apartment blocks  and  each  apartment  block  has  seven  (7)  storey,  each block consisting of twenty‐four (24) flats with two (2) or three (3) BDD (Bedrooms, Dining and  Drawing  Room).  The  front  facing  portion  of  Ground  Floor  is  reserved  for commercial use  and  the  inner portion  for  residents’  car parking. Rent of  three  (3) BDD varies from Rs. 8,000 to 12,000 depending upon the covered area and the rent of two (2) BDD is fixed at Rs. 6,000. Whereas Phase II comprises of one‐hundred and twenty  (120) Apartment blocks  and  each  block has  four  (4)  storey  or  sixteen  (16) flats with two (2) and three (3) BDD. The average market price of 2 BDD flat in these apartments is Rs. ± 2 million, for smaller 3 BDD flat is Rs. ± 3 million and for relatively larger 3 BDD flat is Rs. ± 3.5 million. 

 Naveed  Bungalows  and  Cottages  is  the  second  nearest  human  settlement  to  the project   site.  Rent  of   these  Bungalows   is  Rs. 15,000  and  above,  depending  upon  the  size  of the   bungalow.   The   average   market   price   of these bungalows and cottages is Rs. ± 2.2 million to Rs. ± 3.6 million depending upon the size and location  of  the  bungalow.   A  few  of  the residential blocks are also present at the back of the   project   site.   These   houses   are   relatively more  expensive  than  the  other  settlements  of the    study   area.    In   other   nearby   apartment blocks, the cost ranges between Rs. 3 million to 6 million. 

Page 97: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  43

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.4.3  Castes, Ethnicity and Social Groups 

 The neighborhood  in  the  study  area  is  characterized by people of different  ethnic and  religious  backgrounds  living  together  in  buildings with  a  lot  of  common  and shared  facilities  and  space.  Elsewhere  in  Gulistan‐e‐Jauhar  localized  ethnic fragmentation and polarization  is visible whereby various ethnic  communities  tend to  cluster  together  in  their  own  separate  colonies  and  maintain  their  separate identities and ways of  living. Each ethnic group  that  settled  in  the entire  area has progressively  marked  out  its  own  distinctive,  quite  easily  identifiable  territory. Besides  ethnic  diversity,  there  is  substantial  diversity  in  terms  of  religion  as well. Though most  of  the  population  living  in  the  study  area  is Muslim,  they  belong  to various sects of  Islam. The major communal groups  found  in and around  the study area are the following: 

 Mohajirs: The  term  is used  to describe Urdu speaking people who migrated  to  the country at the time of partition, from those parts of the subcontinent that are now in India. 

 Sindhis: Sindhis are a Sindhi speaking socio‐ethnic group of people originating  from interior of Sindh province. Sindhi culture belongs  to a unique group of people with the  sense  of  common  history  and  common  traditions,  as well  as multiplication  of common interests. 

 Punjabis: The Punjabi people originate from the Punjab region. Most of the Punjabis settled  around  the  project  area,  treat  it  as  their  temporary  abode,  and maintain ancestral farmlands in their native towns in Punjab. 

 Pakhtoons: Pakhtoons or Pashtuns are an Eastern Iranian ethno‐linguistic group with populations   primarily    in   Afghanistan   and   western   Pakistan.   The   Pashtuns   are typically  characterized  by  their  usage  of  the  Pashto  language  and  practice  of Pashtunwali.41 

 Balochis: Very  few numbers of Balochis  live  in  the study area. As such, Sindhis and Balochis  have  quite  common  cultural  and  traditional  base  and  therefore  live  as almost a single community. 

 Hazaraywals: The Hazara people  settled around  the project  site basically originate from the Hazara Division of the province Khyber Pakhtoon Khwa. They are typically characterized  by  their  usage  of  Hindko  language.  They  are  also  settled  here temporarily and maintain  their ancestral  farmlands  in  their native  towns  in Hazara Division. 

       

 41 http://en.wikipedia.org/wiki/Pakhtoon 

Page 98: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  44

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.4.4  Family & Household Sizes 

 The average family size, as per the socio‐economic survey, is about 4‐6 persons. Due to mix ethnic  groups  living  in  the  area, people have different  living  styles and  the number of people living in the same house varies significantly. 

 Nuclear family system characterizes the social fabric of the area. Most families living in  these  apartments  are  nuclear  type,  and  the  trend  of  joint  families  is  not  very common. About 90 per cent of the households in the study area are patriarchal. 

 4.4.5  Professions & Occupations 

 A  large  number  of  people  are  either  running  their  own  private  business  or  are working  in private or government  sectors. Quite a  few people  run  their own  small shops in the same area and a few of them are involved in property dealing business. The  livelihood  is  generally  the  responsibility  of  the  elder male  family members. A businessman  is able to generate a monthly  income between Rs. 50,000 to Rs. 1 Lac depending upon  the nature of his business. Those who work  in private  sectors are able to generate a monthly income of Rs. 35,000 and above. 

 4.4.6  Religious Sites 

a)   Mosques 

Every  apartment  project  has  its  own mosque  within  its  premises  and  the residents do not have to go far for offering prayers. Madrassa  Ibn‐e‐Abbas  is  another place  of  worship  in  the  area  that  is  also serving as an educational institute. 

 b)   Churches/Temples 

 No  Church  or  Temple  is  built  in  close proximity of the study area. 

 c)   Graveyards 

 Nearest  graveyard  to  the  study  area  is Cantonment  Graveyard  that  is  located  in the Block‐19 of Gulistan‐e‐Jauhar. 

 4.4.7  Sites of Archaeological and Cultural Significance 

 There  is no specific notified site of archaeological or cultural  importance present  in the project area. 

Page 99: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  45

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.4.8  Recreational Sites                 

Residents of  the study area are  lucky  to have so many well developed  recreational sites  like Euphorbia Family Park, Cantonment Family Park and Maulana Mohammad Ali  Jauhar  Ladies  Park, within  their  colonies  and  surrounding  areas.  Safari Wildlife Park  is one of the  largest parks close to the project site and to the residents of the area.  Moreover  every  apartment  project  has  its  own  park  within  its  premises providing recreational activities to the residents of the flats. 

 4.4.9  Health Status and Facilities 

 According  to data collected by  the Health Ministry,  most  of  the  NIBD  (National Institute  of  Blood  Diseases)  patients  are from  Gulistan‐e‐Jauhar  and  Shah  Faisal Colony.  There  have  been  a  total  of  21 cases  of  dengue‐positive  patients 

reported  in the month of August, 2010.42 The population  in  the study area has also been  affected  by  Dengue  Fever  that  has been prevailing throughout the country  in the  past  few  months.  Total  of  four  (04) cases  of  Dengue  Fever  have  been reported so far from the study area with no expiry. 

 Besides  this,  the  general  health  condition  in  the  surrounding  area  was  found satisfactory. No epidemic or frequent occurrence of serious diseases  in the area has been  reported  in  any  secondary  data  source.  The most  common  complaints  as  is common with  seasonal  change were  cough,  flu,  fever,  headache,  stomach  aches, blood pressure and  seasonal eye  infection. On  an  average, a  typical  family  spends about  Rs.  1,500  to  Rs.  2,000  per  month  on  health  related  expenses.  The  local doctor's  fee  in  the  area  is  between  Rs.  50  to  Rs.  100  per  visit  with  the  cost  of medicine varying according to nature and  intensity of disease. There has not been a single registered case of HIV/AIDS in this particular study area. 

    

42 http://tribune.com.pk/story/44204/uptick‐in‐dengue‐cases/ 

Page 100: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  46

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

The area  is not very well served  in terms of general health facilities. Dar‐ul‐Sehat  is the only closest Hospital to the study area running  in Block 15 of Gulistan‐e‐Jauhar. However,  Ibn‐e‐Sina  Hospital  at  NIPA  Chowrangi,  Shan  Hospital  at  Bismillah  Taqi Road and Ashfaq Memorial Hospital are all at 15 to 20 minutes drive from the study area.  Since  public  transport  and  proper  road  infrastructure  are  available,  patients with  serious  conditions  can  be  taken  to  any  of  these  hospitals  fairly  easily. Furthermore,  in  terms  of  general  physicians,  the  study  area  lacks  the  required number of clinics in comparison to the number of population. Around 04 to 05 clinics at present are providing first aid facilities to the local residents of surrounding areas of the project site. 

 4.4.10  Education 

                   

Compared  with  the  average  overall  literacy  rate  of  about  77%  in  Karachi43,  the literacy  level  is quite good  in the study area. An analysis of the survey revealed that people of the study area generally belong to middle or upper middle class and they not only send their children to school at the primary and secondary level but also for further higher studies. 

 There are a number of government and private schools running  in the area namely; Beacon House Schooling System, The Educators, Ghazi Foundation, Imperial College, Citizen, Metropolitan  Academy  and  Imam  Khomaini  University.  Imam  Khomaini  is basically a university  for Shia Sect of Muslims, where higher education  is given free of cost.  It has separate hostels for girls and boys with  in‐built  libraries. Classes start right after Fajar Prayers and end by 1 pm. Total number of students in this university is 150, out of which 100 are male. All students are taught by only four teachers, the classes are conducted in shifts. 

 About 99% parents send  their children  to schools, out of which 70% parents prefer nearest  schools.  There  are  a  number  of  Seminaries  too  in  the  study  area,  like Madrassa  Ibn‐e‐Abbas, where children are given the basic religious education. Very few are deprived of the blessing of education in the study area. 

 

  

43 Literacy‐Population 10 Years and Older (2006) http://www.statpak.gov.pk/depts/fbs/statistics/pslm_prov2006‐07/2.14a.pdf 

Page 101: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  47

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

4.4.11  Social Status of Women  

                 

Most  of  the  women  in  the  study  area  are  well  educated.  Despite  being  highly qualified, most of  them prefer  to  stay  at home,  look  after  their  children  and  take care of daily household chores. They generally go out in the evening with their young ones to the nearest family parks for recreation. 

 An average of 30% of the total adult female population of the study area is working women. Most of them are beauticians, running their own beauty salons  in the area. Some are  teachers, primarily  teaching at nearby  schools and a  few are engaged  in social activities. 

 4.4.12  Children’s Mobility 

 The  study  area  lies within  the  VIP  Zone  of Gulistan‐e‐Jauhar  Block  16‐A  and  Block  17 where  overall  hygienic  condition  is  good enough  for    children  to  engage  in recreational  activities.   Children  were observed  playing  traditional  and  outdoor games  in  the  nearest  available  parks  and playgrounds. 

 4.4.13  Transportation and Roads Infrastructure 

 Gulistan‐e‐Jauhar,  despite  being  a  newly constructed  area  has  a  high  traffic  load  in comparison  to  other  recent  constructs  of the  city.  As  a  result,  traffic  congestion problems  occur  which  in  turn  create problem  for  the  local  residents.  People  of the  study  area  also  complained  that  they have to change two or three different buses while  going  towards  a  specific  place.  The available  public  transport  in  the  area  has bus  stops  for  routes, G‐25, G‐11, G‐27, G‐ 

Page 102: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  48

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

19,  11‐A,  Gulistan  Coach  and  Safari  Coach.  Taxis  and  rickshaws  are  also  easily available. Most of the residents have their own private vehicles, both two and  four wheelers. Road infrastructure is also properly maintained throughout the study area. 

 4.4.14  Utilities Management 

 As  per  the  primary  data  collected  during  interviews  and  validation  surveys,  utility services are generally available in the study area. 

 Water  is  supplied by Karachi Water and Sewerage Board  (KWSB). According  to  the residents, water  supply  is  sufficient and  fulfills  their daily  requirement; hence  they never  felt the need  for any additional source  like boring or tanker water. However, according to few of the residents, the need for tankers does arise infrequently during summers. 

 Karachi Electric Supply Corporation  (KESC) supplies electricity to the area. No  illegal connections (Kunda System) of electricity were observed during the visit. Natural gas is supplied by SSGC. The area is served by a network of underground gas pipelines. 

 Pakistan  Telecommunication  Limited  (PTCL)  has  installed  a  network  of  telephone lines  in  the  area.  The  nearest  PTCL  Exchange  is  in  Block  13  of  Gulistan‐e‐Jauhar. Various  cell  phone  operators  are  also  providing  telecommunication  services. Moreover, postal  service  is  available  and  the  nearest  Post Office  is  in Block  14  of Gulistan‐e‐Jauhar. 

 4.5  Stakeholder Consultation 

 The  basic  purpose  of  conducting  the  stakeholder  consultation was  to  involve  the local  people  into  the  process  of  project  implementation  and  to  incorporate  the appropriate environmental and social concerns into the process. Moreover, PEPA 97 specifies  that  the  stakeholder  consultation process  shall be  an  integral part of  the EIA and thus makes it mandatory. 

 The consultations were conducted during the reconnaissance visits  in January 2011. Individual and  group  interviews were  conducted  in areas  close  to  the project. The objective  of  the  consultation  was  to  disseminate  the  project  information  and ascertain  stake  holders’  views  on  probable  environmental  and  social  impacts  that may arise due to the implementation of the project. 

 Outcome: 

 Most of the stakeholders were of the opinion that since the project  is envisaged to improve  the electric supply, there would be a rather positive  impact and were also aware of the increased economic benefits due to escalation in property prices. Some expressed  their  concerns  regarding  health  and  safety  issues  related  to  overhead transmission lines. 

Page 103: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  49

    

IDENTIFICATION AND ASSESSMENT OF 

ENVIRONMENTAL IMPACTS 

CHAPTER 

5  

  

This   chapter    identifies   the   significant   potential   environmental,   socio‐economic, health and safety  impacts which may occur during the project  life. The appropriate mitigation measures are also discussed  in  this and  the  subsequent chapters of  this report. 

 A  brief  qualitative  description  of  each  aspect  and  the  affected  environment  is presented in the following sections. 

 The  term “Environmental  Impact” or simply “Impact” covers  the negative, adverse or  harmful  as  well  as  positive,  desirable  or  beneficial  impacts  of  the  project  on environmental  settings.  Prediction  of  impacts  of  the  project  activity  is  based  on factual data; however,  the  significance of  these  impacts  involves a value  judgment technique. The nature of the impacts may be categorised in terms of: 

 

Direction ‐ Positive or NegativeDuration ‐ Long or Short TermEffect ‐ Direct or Indirect Extent ‐ Wide or Local

Impact significance depends on both the nature of the impact and on the sensitivity of the receptor. The more sensitive the receptor the greater will be the significance of impact of that change.  For this EIA Report, nature of change is combined with the sensitivity of the receptor to evaluate the significance of the impact. The significance of  impact  is  characterized  as  very  low,  low,  moderate,  high  and  very  high. Environmental  issues of  “moderate”,  “high” and  “very high”  significance would be provided with mitigation measures. 

 For  identification of potential  impacts of  the project, screening of activities causing impacts had been  carried out  in different phases of  the project  life.  In  the  impact assessment  exercise, major  project  activities  with  their  associated  environmental issues were identified and then their impacts on the relevant physical, biological, and socio‐economic elements of the area were evaluated. All the activities of the project are divided into following broad categories: 

 1.   Design Phase 2.   Construction Phase 3.   Installation & Commissioning Phase 4.   Operation Phase 

Page 104: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  50

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Environmental  issues  and  the  assessment  of  their  impacts  are  presented  in  the following sections. 

 5.1  Environmental Impacts Due to Project Design 

 The  design phase  of  the  project  comprises mainly  of  feasibility  study,  appropriate design selection and studies for the project. Most part of this phase does not require an  extensive  physical  interference  in  the  project  area.  Therefore  no  significant environmental,  socio‐economic  and  health  impacts  have  been  identified  from  the activities of this phase. 

 5.2  Environmental impacts Due to Project Location 

 The project site is located on a commercial land, close to a residential area. However the site does not affect monuments of cultural or historical  importance nor does  it affect any public utility services  like playgrounds or schools and does not affect any sanctuaries, national park or reserve forest areas. The main gate of project site leads to  a  broad  street  and  hence  construction  of  approach  road  is  avoided.  A  132  kV transmission  line  is  constructed  underground  from  the  grid  station  site  up  to  the PLDP  point  at  New  Service  Road,  so  that  the  land  remains  available  for  future construction of KESC Hospital. Overhead  transmission  route stretches 1.2 km up  to Samama Junction near University Road. Due to alignment of this route, at  least two families from the nearby illegal settlements are expected to be displaced. Moreover, it  is observed  that eleven  trees have been removed  from  the  footpaths  in order  to erect tubular poles for these transmission lines. 

 5.3  Environmental Impacts during Construction 

 

 

The construction phase of the project results  in a number of environmental aspects which  create  temporary  hazards  of  moderate  significance  to  the  environmental resources  of  the  project  area  during  the  project  construction  phase.  However,  if managed properly, these activities do not pose any threat to the environment. 

 5.3.1  Air Quality 

 The major sources of air pollution during construction are emissions  from vehicles, generator  sets,  and  heavy  construction  equipment;  and  fugitive  dust  from  vehicle movement   and   soil   excavation.   Impacts   are   minimized   through   established mitigation measures which  include  suppression of  fugitive dust by water  spraying, use of low emission vehicles and construction equipment, and good maintenance of engines. 

 5.3.2  Water Quality 

 Surface Water: The construction of grid station does not have any major  impact on the  surface or  ground water quality of  the area. The  small  amount of wastewater generated during concreting is discharged into municipal sewer line. 

Page 105: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  51

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Adequate drinking water  facilities,  sanitary  facilities and drainage  in  the  temporary camp  of  construction workers  are  provided  to  avoid  the  surface water  pollution. Provision of adequate washing and toilet facilities with septic tanks and soaking pits and appropriate refuse collection and disposal system are also in place. 

 Ground Water: Ground water is found at 2.4m depth in the project area44. Although ground water will not be used  for any activity related to the project, ground water pollution  could  take  place,  if  chemical  substances  and  oily  waste  get  leached  by precipitation of water and percolate to the ground water table. Avoiding spillage at the construction site will minimize the chances of leaching construction chemicals to the ground water. 

 5.3.3  Soil Characteristics 

 Soil Contamination: Soil may be contaminated as a result of fuel/oils/chemicals spillage and  leakage, and  inappropriate disposal. The waste  is generated  from  site  clearance, excavation, concrete batching, concrete conveyance and construction of substructures and superstructures. The generated solid waste is in the form of; 

 

 

• Excavated soil 

• Residual from construction material and equipment cleaning 

• Domestic solid waste from labor camp 

 The  solid  waste  is  recycled  through  the  contractor;  inert  waste  is  buried  in appropriate  locations while  hazardous waste  is  sent  to  GSM, where  it  is  handled according to its nature. Metal wastes are sold as scrap. 

 The responsibility of the contractor  is to ensure that all other waste  is cleared from the  construction  site  and  is  transported off  to  the designated disposal  site  as  and when generated. After completion of  the  transmission  line construction works,  the routes will be completely  restored. No debris,  surplus construction material or any garbage will be left behind. 

 Appropriate  construction  practices  and  management  actions  as  listed  above  will greatly minimize  the  soil  contamination. The  significance of  the  residual  impacts  is therefore expected to be ‘low’. 

 5.3.4  Ambient Noise 

 Construction noise  is created by vehicles, heavy equipment and  some construction activities. The vibrators used for concreting also produce noise. These are temporary in nature and are mitigated by careful planning of machinery operations, use of low noise   equipments   and   scheduling   of   operations   only   during   the   daytime. Construction workers in areas with excessive noise wear ear protection. 

 

   

44 Soil Investigation Report 

Page 106: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  52

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

5.3.5  Flora 

 No rare, endangered or endemic  terrestrial plant species were observed within  the project area during  the site visit. The project area host  large patches of vegetation which  mainly  consists  of  wild  shrubs.  The  project  site  had  to  be  cleared  for construction  of  grid  station  and  underground  cables. Due  to  erection  of  poles  for overhead  transmission  lines along 1.2 km  length, eleven  trees have been  removed from  the  footpaths.  Compensatory  plantation  in  and  around  the  grid  station  area after  construction  phase  is  over  will  improve  the  ecology  and  aesthetics  of  the surroundings.   Hence,   the   significance   of   the   impact   on   flora   from   project construction activity is considered moderate. 

 5.3.6  Fauna 

 No  endangered,  threatened,  or  otherwise  sensitive  faunal  species were  found  to occur near  the project site. The  faunal  species  in  the  study area  is mainly of  those associated with manmade habitat. There is no noticeable wild life occurrence around the  grid  station  areas.  Similarly,  no  special  status  of  wildlife  and  aquatic  faunal species are reported from the project site. Therefore the project will not result in any significant loss of habitat or species of special status. 

 5.3.7  Socio‐Economic Conditions 

 The project is  located close to the residential area of Block‐16 Gulistan‐e‐Jauhar, no site  of  cultural  or  historical  importance  is  present  in  the  close  vicinity.  The  Grid Station  is  being  constructed  within  the  premises  of  a  plot,  owned  by  KESC.  The project  does  not  involve  any  loss of  land  or  property  and  therefore  no  significant negative  impact on  socio‐economic  setting  in  this  respect  is expected. KESC  should make sure that the local population is abreast of the project development. Wherever possible and necessary,  the  local population  should also be  involved  in  the project activities. 

 5.3.8  Health & Safety 

 Various activities during  the construction phase of  the project could have health & safety impacts on workers and the people living in the nearby vicinity. The impact on worker safety is direct and of moderate significance. 

 The  use  of  heavy machinery  and  vehicle  is  carried  out  during  the  excavation  and transportation  activities.  The  safety  of workers  is  of  prime  concern while  dealing with such machineries and vehicles. The probability of such accident at project site is low but the significance might be of moderate nature. 

 Issues  of  safety  are  also  important  due  to  the  location  of  residential  apartments across the project site. Safety measures such as cautionary signboards, speed limits, speed breakers, and indicators shall be provided at all the critical places. 

Page 107: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  53

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

5.4  Installation & Commissioning Phase  

Grid  station  equipment  is  transported  in  containers while  power  transformers  on low  bed  trailers.  During  erection  of  equipment,  cranes  will  be  used  for  placing transformers on  foundations since  it  is a heavy  item. Entry of heavy vehicles  in the area   will   be   allowed   only   after   midnight.   The   installation   process   will   be 

accomplished within three to four months45. This phase will require about 20 to 25 persons. The project’s Mile Stone Schedule is attached as Annexure – 13. 

 5.4.1  Environmental & Safety Issues 

 Grid Station commissioning  is a critical part of  the overall process of  taking  it  from construction  and  installation  through  to  the  full  operation  phase.  Proper  strategic planning is a key to avoid delays, cost overruns and potential safety hazards. 

 The project team should get  involved  in assisting  the construction contractors with the  turn  over  effort.  It  should  also  consult  closely  with  the  grid  operating  team, coaching new employees with on the  job training, working as part of the  initial grid station  operations  team,  ensuring  that  final  operation  meets  the  proponent’s requirements and ensuring that the  integrated systems perform to the proponent’s satisfaction. 

 The activities related to the commissioning phase of the project are not perceived to bring  about  any  changes  in  the  existing  environmental  conditions.  However,  the handling of heavy equipment is always fraught with danger. The safety of workers is of  prime  concern  while  dealing  with  such  equipment.  This  danger  could  be considerably  reduced  if  one  sticks  to  the  safety  regulations,  not  all  of which  are written  in the user’s book or manual. Since the heavy equipment  installation period would be  restricted  to a  relatively  confined area, adequate measures  taken during the  said  period  would  ensure  safe  installation  without  any  significant  impact  on workers’  safety.  Furthermore,  project  proponent  would  ensure  that  the  persons handling heavy machinery and equipment, be they from KESC or the contractor, are adequately trained and skilled. The probability of any accident at the grid station  is low but the significance might be that of moderate nature. 

 5.5  Potential Environmental Impacts during Operation 

 During operational phase, most of the construction phase  impacts will get stabilized and the impacts will be restricted only to the Operation and Maintenance of the grid station.   Minimal   environmental‐disturbing   activities   are   anticipated   during   this phase.   Any environmental, social, health and safety  issues which may occur during the operation phase are discussed in the following sections. The matrix for operation phase general impacts is shown in Table 5.1. 

     

45 Source;  KESC Management 

Page 108: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Table 5.1 Potential Environmental Impacts During Operation Phase

S #

Aspect (Operation Phase) Potentially Significant

Impact

Potentially Significant

Unless Mitigation

Incorporated

Less than

Significant Impact

No Impact

Need to beExplored

1.0 AESTHETICS: Would the Project: 1.1 Have a substantial adverse effect on a scenic vista? 91.2 Substantially damage scenic resources? 9

1.3 Substantially degrade the existing visual character or quality of the site and its surroundings? 9

1.4 Create a source of substantial light or glare, which would adversely

affect day or nighttime views in the area? 9 2.0 AIR QUALITY: Would the Project: 2.1 Conflict with or obstruct implementation of the applicable air quality plan? 9

2.2 Violate any air quality standard or contribute substantially to an existing or projected air quality violation? 9

2.3

Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or state ambient air quality standard ?

9

2.4 Expose sensitive receptors to substantial pollutant concentrations? 92.5 Create objectionable odors affecting a substantial number of people? 93.0 BIOLOGICAL RESOURCES : Would the Project

3.1

Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations?

9

3.2 Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations 9

3.3 Have a substantial adverse effect on federally protected wetlands? 9

3.4 Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites?

9

3.5 Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance? 9

3.6

Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or state habitat conservation plan?

9

4.0 CULTURAL RESOURCES: Would the Project

4.1 Cause a substantial adverse change in the significance of a historical resource? 9

4.2 Cause a substantial adverse change in the significance of an archaeological resource? 9

4.3 Directly or indirectly destroy a unique paleontological resource or site or unique geological feature? 9

5.0 GEOLOGY AND SOILS: Would the Project

5.1 Expose people or structures to potential substantial adverse effects, including the risk of loss, injury, or death involving

a Rupture of a known earthquake fault? 9b Strong seismic ground shaking? 9c Seismic-related ground failure, including liquefaction? 9d Landslides? 9

5.2 Result in substantial soil erosion, or the loss of topsoil? 9

5.3 Be located on a geologic unit or soil that is unstable, or that would become unstable as a result of the project, and potentially result in on- or off-site landslide, lateral spreading, subsidence, liquefaction or collapse

9

5.4

Have soils incapable of adequately supporting the use of septic tanks or alternative waste water disposal system where sewers are not available for the disposal of waste water?

9

Page 109: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

S #

Aspect (Operation Phase) Potentially Significant

Impact

Potentially Significant

Unless Mitigation

Incorporated

Less than

Significant Impact

No Impact

Need to beExplored

6.0 HAZARDS AND HAZARDOUS MATERIALS: Would the Project

6.1 Create a significant hazard to the public or the environment through the routine transport, use or disposal of hazardous materials? 9

6.2

Create a significant hazard to the public or the environment through reasonably foreseeable up-set and accident conditions involving the release of hazardous materials into the environment? (SF6 gas byproducts & Transformer Oil)

9

6.3 Emit hazardous emissions or handle hazardous or acutely hazardous materials,

substances, or waste within one-quarter mile of an existing or proposed school?

9

6.4

For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard for people residing or working in the project area?

9

6.5 Impair implementation of or physically interfere with an adopted emergency

response plan or emergency evacuation plan? 9

6.6 Expose people or structures to a significant risk of loss, injury or death involving wildland fires, including where wildlands are adjacent to urbanized areas or where residences are intermixed with wildlands?

9

7.0 HYDROLOGY AND WATER QUALITY: Would the project :7.1 Violate any water quality standards or waste discharge requirements? 9

7.2

Substantially deplete groundwater supplies or interfere substantially with groundwater recharge such that there would be a net deficit in aquifer volume or a lowering of the local groundwater table level

9

7.3

Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river, or substantially increase the rate or amount of surface runoff in a manner which would result in substantial erosion or siltation on- or off-site?

9

7.4

Create or contribute runoff water, which would exceed the capacity of existing or planned storm water drainage systems or provide substantial additional sources of polluted runoff?

9

7.5 Otherwise substantially degrade water quality? 9

7.6 Expose people or structures to a significant risk of loss, injury or death involving flooding, including flooding as a result of the failure of a levee or dam?

9

7.7 Inundation by tsunami or mudflow? 9

8.0 LANDUSE & PLANNING: would the Project 8.1 Physically divide an established community? 9

8.2

Conflict with any applicable land use plan, policy, or regulation of an agency with jurisdiction over the project adopted for the purpose of avoiding or mitigating an environmental effect?

9

8.3 Conflict with any applicable habitat conservation plan or natural community conservation plan? 9

9.0 NOISE: Would the Project result in

9.1 Exposure of persons to or generation of noise levels in excess of standards established in the local general plan or noise ordinance, or applicable standards of other agencies?

9

9.2 Exposure of persons to or generation of excessive ground-borne vibration or ground-borne noise levels? 9

9.3 A substantial permanent increase in ambient noise levels in the project vicinity

above levels existing without the project? (Transformer Operation)

9

9.4 A substantial temporary or periodic increase in ambient noise levels in the project vicinity above levels without the project? 9

9.5

For a project located within an airport land use plan within two miles of a public airport or public use airport, would the project expose people residing or working in the project area to excessive noise levels?

9

10.0 POPULATION & HOUSING: Would the Project result in

10.1 Induce substantial population growth in an area, either directly or indirectly? 9

10.2 Displace substantial numbers of existing housing, necessitating the construction of replacement housing elsewhere? 9

10.3 Displace substantial numbers of people, necessitating the construction of replacement housing elsewhere? 9

Page 110: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

S #

Aspect (Operation Phase) Potentially Significant

Impact

Potentially Significant

Unless Mitigation

Incorporated

Less than

Significant Impact

No Impact

Need to beExplored

11.0 PUBLIC SERVICES: Would the project result in substantial adverse physical impacts to the following: 11.1 Fire protection? 911.2 Police protection? 911.3 Schools? 911.4 Parks? 911.5 Other public facilities? 912.0 RECREATION:

12.1

Would the project increase the use of existing neighborhood and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated?

9

12.2

Does the project include recreational facilities or require the construction or expansion of recreational facilities, which migh have an adverse physical effect on the environment?

9

13.0 TRANSPORTATION& TRAFFIC: Would the project

13.1 Cause an increase in traffic, which is substantial in relation to the existing traffic load and capacity of the street system 9

13.2 Result in a change in traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks? 9

13.3 Substantially increase hazards due to a design feature (e.g., sharp curves or dangerous intersections)? 9

13.4 Result in inadequate emergency access? 913.5 Result in inadequate parking capacity? 914.0 UTILITIES & SERVICE SYSTEMS: Would the Project

14.1 Exceed wastewater treatment requirements of the applicable Regional Water Quality Standard? 9

14.2 Require or result in the construction of new water or wastewater treatment

facilities, the construction of which could cause significant environmental effects?

9

14.3 Require or result in the construction of new storm water drainage facilities, the construction of which could cause significant environmental effects? 9

Have sufficient water supplies available to serve the project from existing entitlements and resources, or are new or expanded entitlements needed?

9

Be served by a landfill with sufficient permitted capacity to accommodate the project’s solid waste disposal needs? 9

14.4 Comply with federal, state, and local statutes and regulations related to solid waste? 9

15.0 MANDATORY FINDINGS OF SIGNIFICANCE:

15.1

Does the project have the potential to degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, reduce the number or restrict the range of rare or endangered plant or animal or eliminate important examples of the major periods of Karachi ?

9

15.2 Does the project have impacts that are individually limited, but cumulatively considerable (“Cumulatively considerable” means that the incremental effects of a project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects)?

9

15.3

Does the project have environmental effects, which will cause substantial adverse effects on human beings, either directly or indirectly? (EMF Health Risks)

9

Page 111: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  57

Environmental Impact Assessment 

 

5.5.1  Air Emissions  

• SF6 Gas Emission  

Sulfur Hexafluoride  (SF6) will be used  as a  gas  insulator  for  electrical  switching equipment and  transmission  lines. Commercially available SF6  is not dangerous, and  is not  specifically  subjected  to  the  local environmental  regulations. SF6  is a stable gas, heavier than air, not harmful to humans, non combustible, non‐toxic and non‐corrosive. SF6  is used in enclosed systems which are extremely safe and unlikely  to  leak  under  normal  circumstances.  SF6    is  collected  and  recycled  if  a piece of equipment or a substation needs to be opened. 

 SF6  released  into  the  atmosphere  is  considered  a  greenhouse  gas  with  a significantly higher global warming potential  (GWP)  than CO2

46. Despite  the  fact that  SF6   gas  is  very  stable,  it will partly decompose  in association with electric discharges  and  arcs,  for  example,  in  a  breaker.  Then  gaseous  and  solid decomposition  products  are  produced.  Normally  the  level  of  gaseous decomposition products  is kept  low  through  the use of absorbers built  into  the switchgear.  In  large  concentrations,  the  decomposition  products  are  corrosive and poisonous.  Therefore,  there  are  established  routines  for  service  personnel when opening SF6 filled equipment for maintenance or scrapping. 

 The solid decomposition products are mainly metal fluorides in the form of a fine grey powder. The powder only appears where arcing has occurred,  for  instance in  used  circuit  breakers.  The  powder  can  be  easily  taken  care  of  as  separate waste.  The  decomposition  products  are  reactive,  which means  that  they  will decompose  quickly  and  disappear  without  any  long‐term  effect  on  the environment. 

 5.5.2  Liquid Discharges 

 

 

• Transformer Oil Leakage & Seepage 

 Today,  most  transformers  use  insulating  and  cooling  fluids  derived  from petroleum  crude  oil.  Utilities  have  little  choice  but  to  develop  extensive contingency plans  and detailed procedures  that  require  training personnel  and purchasing special equipment to handle accidental spills and leaks of transformer fluid, particularly when contaminated by polychlorinated biphenyl materials. 

 The main causes of transformer oil leakage and seepage are: 

• Continuous  running  of  transformers  over  long  period  of  time  renders  the seals weak. 

• Lack of operation and maintenance (O&M) 

• Poor quality sealing 

• High temperature due to power overloading    

46 EHS Guidelines by IFC 

Page 112: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  58

 Environmental Impact Assessment 

 

Highly refined, mineral base oil will be used in the transformers and transmission lines for cooling transformers and providing insulation between live components, thereby reducing or eliminating the above mentioned elaborate procedures. This oil is a byproduct of petroleum extracted from the earth and is known to have no adverse impact on humans or environment. 

 At the hybrid grid station, transformers are built on a gravel base. The leaked oil is not allowed to permeate  through the base and reach the earth surface.    It  is accumulated  in  the  foundation soakage pit and a  few  liters of additional oil are replenished each time. In case of seepage or leakage, the transformer is repaired in‐situ at the Grid Station or sent to the GSM department for repair respectively. 

 The  transformer  oil  is  regularly monitored  to  ensure  that  the  constituents  are within  permissible  limits  as  recommended  by  the manufactures.  If  the  oil  has degenerated  both  chemically  and  physically,  it  is  upgraded  /  recycled  through dehydration and regeneration process. 

 Waste  oils  and  chemicals will  be  disposed  in  accordance with  their  respective Material Safety Data Sheet (MSDS). Typical MSDS for transformer oil  is attached as  Annexure  –  14.  These  will  be  made  available  at  the  grid  station  and maintenance workshops. 

 • Wastewater Produced due to O&M Activities 

 Since water will not be used  in  the O&M activities,  there  is no discharge of effluent. No water accumulation would be permitted around the constructed grid station, the open area will be gravel based. Mopping will be carried out for cleaning purpose. 

 The possible threat to the water quality from the facility can be the release of contaminated  water.  Since  no  raw material will  be  used  during  operation phase,  chances  of water  contamination  are  not  there.  Storm water will  be directed to the municipal sewer drain. 

 • Domestic Wastewater 

 

Septic  tank  and  soak  pit  would  be  constructed  according  to  design  that already exists. These tanks will be regularly cleaned and disinfected to avoid clogging. Wastewater will be disposed off after  treatment  into KWSB  sewer line.47 

 As the number of permanent employees during operation phase  is about 4‐5 persons,  the quantity of domestic wastewater generated  is also estimated  to be very low. The treated wastewater is expected to remain below NEQS limits for  discharge  into  sewage  plant  as  indicated  in  Annexure  –  4.  So  the significance of this impact is categorized as very low. 

 

 47   KESC Management 

Page 113: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  59

 Environmental Impact Assessment 

 

5.5.3  Solid Waste Generation  

 

• Storage of Waste Materials 

 The  grid  station  premises  will  not  be  used  as  permanent  storage  area.  The essential  spares  will  be  stored  at  Grid  Station’s  designated  area.  All  packing boxes,  shipping  containers which are not  the property of  contractors, planking covers  etc  becomes  the  property  of  proponents  and  will  be  shifted  to  the respective store yards for utilization or disposal. 

 

 

• Domestic Waste: 

 Considering the small number of persons employed during this phase, operation of  the  grid  station will  generate  a  relatively minor  volume  of  solid waste  for disposal. 

 

 

• Maintenance Waste 

 Metal fluoride in form of grey powder would be generated in very small quantity as a result of SF6  decomposition. Other wastes generated would  include wastes from  the  repair  and maintenance  activities  such  as  discarded  equipment  and parts, packing materials, used oils and chemicals, cotton rags and the likes. These wastes  typically would be put  in containers, characterized and  labeled, possibly stored briefly, and transported by a  licensed hauler to an appropriate permitted off‐site disposal facility as a standard practice. 

 

 

• Contaminated Soil 

 Any  soil  contaminated  by  the  oil  spillage  will  be  removed  and  disposed  off appropriately in accordance with the MSDS of the spilled oil. 

 5.5.4  Ambient Noise 

 

 

As discussed earlier,  the ambient noise  level at  the site was measured  to be  in  the range of 55‐60 dB. During the operation phase of the project there will be humming noise generated  from  the grid  station due  to  transformers operation which will be 

felt only up  to 50 m. Transformer noise  level  is designed  to remain below 65 dB.48 Since  the  grid  station  area would be  surrounded by  a wall, which will have  sound attenuation  effect  and  proper maintenance  of  the  equipments/machineries  inside the station, the ambient noise level will remain low at the boundaries of grid‐station. This impact has been characterized as ‘low’. 

        

48 KESC Management 

Page 114: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  60

 Environmental Impact Assessment 

 

5.5.5  Flora  

The  operation phase  of  the  project would  not  bring  about  further  damage  to  the existing  flora  other  than  the  impacts  anticipated  during  the  construction  phase. Therefore the significance of this impact is considered as negligible. 

 5.5.6  Fauna 

 The  faunal  species  in  the  study  area  is mainly of  those  associated with manmade habitat. No wild  life  occurrence  is  there  around  the  grid  station  areas.  Impact  on aquatic ecology is also not anticipated. 

 5.5.7  Socio‐economic Conditions 

 The socioeconomic  impacts of the project on the surrounding area are expected to be on the higher side in terms of their significance. The socioeconomic status of the area would improve to a considerable extent as the price of property would shoot up due  to  firm  and  assured  uninterrupted  power  supply  from  KESC.  The  localized economic impact of the project would be of high magnitude. 

 During  the  process  of  public  consultations,  the  main  concern  raised  by  the stakeholders was the shortage of electricity supply with frequent load shedding and low voltage problems. The construction of grid station and associated  transmission lines  will  play  an  important  role  not  only  to  strengthen  and  stabilize  electricity distribution  system  in  existing  areas  but  will  also  improve  electricity  supply  to adjoining areas. Main beneficiaries will be  the general public  including  students of the nearby area. 

 It should be noted that two families from the  illegal settlements near PLDP point at the beginning of overhead  transmission  line  route will have  to be displaced before the  commissioning  of  grid  station.  The  proponents  plan  to  build  a  security  check point at this place. 

 The  number  of  project  personnel  required  during  the  operation  and maintenance phase would be few (4‐5). Therefore, socioeconomic impacts related directly to jobs would be quite lower. The impact is assessed as negligible. 

 5.5.8  Health & Safety 

 Health  and  safety  impacts  will  be  in  terms  of  risk  of  accidents  and  exposure  to electromagnetic  fields at the grid station. These topics are discussed  in more detail as under; 

 • EMF Risks 

 Electric  and magnetic  fields  (EMF)  are  invisible  lines  of  force  emitted  by  and surrounding any electrical device. Electric fields are produced by voltage and the two are directly proportional.  Its strength  is measured  in volts per meter (V/m). Electric fields are shielded or weakened by materials. 

Page 115: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  61

 Environmental Impact Assessment 

 

Magnetic fields can pass through most materials and are difficult to shield. These are measured  in units of gauss  (G) or  tesla  (T), where 1T equals 10,000G. Both electric and magnetic fields decrease rapidly with distance. Since magnetic fields are most  likely  to penetrate  the body,  they  are  the  component of EMF  that  is usually studied in relation to human health. Power frequency EMF typically has a frequency  in  the  range of  50 – 60 Hertz  (Hz)  and  is  considered Extremely  Low 

Frequency (ELF).49  

 

Although there is a public and scientific concern over the potential health effects such as cancer, changes in behavior, memory loss and other diseases associated with exposure to EMF,   there is no empirical data demonstrating adverse health effects from exposure to typical EMF  levels  from power transmissions  lines and 

equipment.50 Overall, ground‐level magnetic fields from underground cables fall much more rapidly with distance than those from a corresponding overhead line, but  can  actually  be  higher  at  small  distances  from  the  cable.  The  graph  in Figure 5.1  shows  this  illustration  for one particular underground cable and  the 

equivalent overhead line.51                              

Figure 5.1: Typical Magnetic Field Produced by Underground & Overhead Cables 

     

49 National Institute of Environmental Health Sciences (2002) 50      (2001);  International  Agency  for  Research  on  Cancer  (2002);  U.S.  National  Institute  of  Health  (2002); 

Advisory  Group  to  the  Radiation  Protection  Board  of  the  UK  (2001),  and  U.S.  National  Institute  of Environmental Health Sciences  (1999). 

51http://www.emfs.info/Sources+of+EMFs/Overhead+power+lines/specific/132+kV+underground+magnetic.ht m   International Commission on Non‐Ionizing Radiation Protection (ICNIRP) 

Page 116: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  62

 Environmental Impact Assessment 

 

International Commission on Non‐Ionizing Radiation Protection (ICNIRP) is a non‐ governmental  organization  formally  recognized  by  the  World  Health Organization  (WHO),  which  has  set  guidelines  exposure  limits  for  public  and occupational  exposure  to  EMF  as  indicated  in  the  Table  5.2 while  the  typical measured values for magnetic field taken near KESC’s different transformers and power lines are summarized in Tables 5.3 & 5.4. 

 Table 5.2 

ICNIRP Guidelines for EMF Public and Occupational Exposure 

 

Frequency

Public Exposure Occupational Exposure Electric Field 

(V/m) Magnetic Field 

(mG) Electric Field 

(V/m) Magnetic Field 

(mG) 50 Hz 5000 1000 10000 5000

60  Hz 4150 830 8300 4150

Table 5.3 

Typical Measured Values for Magnetic Field Next to KESC Transformers (All values are recorded in mG) 

 

Types of Transformers Right beside transformer

Few meters away from transformers

Switchgears at grids

Offices and 

Control Room

132/11 

Transformer

Max recorded 950 230 155 50 Average during 

all measurements

124 21 25

10

Table 5.4 

Typical Measured Magnetic Field Next to KESC Power Lines (All values are recorded in mG) 

 

Overhead Line Under 132 kV

Overhead line 

Under 11 kV

Under PMT

Right over exposed 

underground lines

Right over underground lines buried 

1.4m in concrete

Max Recorded

30 20 590 1500

9

Average 12 15 30 52 5

The above  tables are evident of  the  fact  that measured EMF  values  for KESC’s existing  132/11  kV  transformers  and  transmission  lines  are  well  within  the exposure  limits as established by  ICNIRP Guidelines for general public as well as the maintenance staff. 

Page 117: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  63

 Environmental Impact Assessment 

 

• Implantable Medical Devices 

 Implantable  medical  devices  such  as  pacemakers  are  becoming  increasingly common.  They  have  been  associated with  problems  arising  from  interference caused by EMF. This  is called electromagnetic  interference or EMI.  It can cause inappropriate  triggering  of  a  device  or  inhibit  the  device  from  responding appropriately. Sources of EMI documented by medical personnel  include  radio‐ controlled model  cars,  slot machines,  car  engines, digital  cellular  phones,  anti‐ theft security systems, radiation therapy, and high voltage electrical systems and devices. 

 Manufacturers’  recommended  threshold  for  modulated  magnetic  fields  is  1 gauss which is 5 to 10 times greater than the magnetic field likely to be produced 

by a high‐voltage transmission  line.52 Research shows a wide range of responses for the threshold at which pacemakers responded to an external EMI source. The results for each unit depended on the make and model of the device, the patient height, build, and physical orientation with respect to the electric field. 

 

 

• Risks related to Transmission Lines 

 Most accidents involving underground transmission lines occur while digging and excavating in areas near underground cables. On the other hand, most accidents with overhead  lines  involve  ladders,  cranes,  truck mounted  lifting devices,  and other machinery  that come  to close  to overhead  lines. As a general precaution, no  one  should  be  on  an  object  taller  than  15‐17  ft  under  an  overhead  high voltage electric line as electric contact can occur even if direct physical contact is not made because electricity can arc across an air gap. Downed overhead power lines can pose a potential public hazard, though transmission  lines are designed to shut off if they fall. 

 In  the  current  project,  overhead  transmission  lines  are  designed  to meet  the European  Electric  Safety  Code.  The  code  establishes  design  and  operating standards and sets minimum distances between wires, poles, the ground and the buildings.  Transmission lines are designed to trip out of service (turn off) if they fall or contact with any object, although they are not likely to fall unless hit by a tornado  or  high  roof  truck.  Typical  protection  system  for  132kV  overhead transmission lines as employed by KESC is attached as Annexure – 1552. 

 

 

• Lightning Strikes: 

 Since  power  poles  and  other  tall  objects  are more  likely  to  intercept  lightning strikes, transmission lines are built with a grounded shield wire at the top of the poles as a protection. 

     

52 Public Service Commission of Wisconsin 

Page 118: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  64

 Environmental Impact Assessment 

 

• Fire Incidents: 

 The fire fighting system at the Grid Station is equipped enough to handle fires on small scale. The main causes of  fires  in Grid Stations are overloading and  short circuiting  of  the  systems.  The  fire  can  break  out  in  any  unit  of  the  integrated complex  of  the  grid  station  and  spread  instantaneously  engulfing  the  whole complex  including  the switchyard and  transformers. The  fire  fighting system  for the   transformers   consists   of   DCP   (dry   chemical   powder),   CO2    and   foam (Table 5.5)53. This will enable quick internal repair of the transformer and reduce plant outages. 

 o In  order  to  contain  a  fault  or  resulting  fire,  switches  are  provided  in  the 

control room to isolate the whole grid station from its feeding sources.  

o Similar   switches   are   also   provided   in   the   switchyard   for   isolation   of equipments from the power circuit. 

 o The grid station will be separated from the nearby built up areas by providing 

a buffer zone and high walls around the Grid Station. 

 Table 5.5 

Fire Extinguishing Arrangement  

S.N

Locations Fire Extinguishers Type

DCP Trolley 50 (kg)

CO2 (5 kg) DCP (6 Kg)

Foam(10 liter)

1 General Area 01 02

2 Building Ground Floor

02 03 02

3 Building First Floor

03 04

Total 03 06 06 02

53 Data provided by KESC Management 

Page 119: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  65

     

 

MITIGATION MEASURES 

CHAPTER 

6  

  

6.1  Introduction  

The main purpose of mitigation measures is to carry out various phases of a project in such a way that the negative impacts of the proposal are eliminated or minimized, and the benefits are enhanced59. 

 The  problems  occurring  during  the  project  are  identified  and  rectified  to  prevent damage  to  the  environment.  The  mitigation  measures  address  specific  impacts identified in the EIA. 

 

The mitigation measures aim to ensure that:  

• They are implemented at each stage of the project 

• The  project  activities  are  managed  so  as   to  avoid  or   reduce   the  negative environmental and social impacts and enhance positive impacts 

• The surrounding communities are better off after the project is implemented, on social and environmental indicators 

• Affected structures, roads and natural features are protected during construction and then rehabilitated 

• Accurate   records  of   the  progress  of   the  project   (including  objections)  are maintained  so  that  the  concerned  can  be  traced  out  in  the  event  of  claims against the client; and 

• The  mechanisms  are   in  place   for   reviewing   the  efficacy  of   the  mitigation measures and any improvements made in the course of the project, so that other similar  projects  may  benefit  from  the  experience  gained  on  the  grid  station project. 

 6.2  Key Environmental Issues 

 

The environmental  issues associated with  the project are discussed  in Chapter 5  in detail. However, the key issues are: 

 

• Contamination of air, water and soil 

• Impacts of noise 

• Emission of SF6 gas 

• Leakage of Transformer Oil 

• Electromagnetic field and 

• Occupational health and safety issues   

59 Guidelines for Preparation and Review of Environmental Reports, 1997 

Page 120: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  66

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

6.3  Mitigation Measures at Different Phases of the Project  6.3.1  Mitigation Measures at Design Phase 

 Most of the significant environmental impacts of the project can be addressed at the design phase, which is mainly the responsibility of the Design Engineers. As discussed in  Chapter  2,  Hybrid  Technology  allows  the  entire  grid  system  to  be  placed  in relatively smaller space as compared to the conventional design. Appropriate cabling with protective shields  is used to suppress electron  flux  in the underground cables. In case of over head transmission lines, minimum clearance between live conductors and other objects is provided as discussed earlier. 

 6.3.2  Mitigation Measures at Construction Phase 

 The main responsibilities for mitigation during the construction phase of the project rest with  contractors appointed  to  construct  the  grid  station. The Contractors  Site Manager  has  the  responsibility  for  monitoring  the  implementation  of  mitigation plans by the contractors and needs to  implement his own system of  internal checks to ensure them. The mitigatory actions recommended during this phase are; 

 Air Quality: 

 

 

• Provisions will be made for sprinkling of water in the area where earth filling and excavation is being carried out. 

• Loose earth will not be allowed to pile up along the approach roads. 

• PPEs such as dust masks will be made available  to  the construction workers at the site to avoid potential health hazards. 

 Water Quality: 

 Spillage  of  fuel/oils  and  other  construction materials will  be  contained with  best handling/construction practices and skilled supervision. 

 Land Environment: 

 

 

• No accumulation of solid waste at the site will be allowed. 

• It will be ensured that no soil is left unconsolidated after completion of work. 

 Noise Levels: 

 

 

• Regular inspection and maintenance of the construction vehicles and equipment will be carried out at the project site. 

• High noise emitting equipments if any will be fitted with noise reduction devices such as mufflers and silencers wherever possible. 

Page 121: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  67

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

Ecological Resources: 

 It was observed from the field survey that no special floral and faunal species exists near  the  project  site.  Since  the  excavation  work  is  done  along  the  footpaths  of service  road,  natural  vegetation  is  not  disturbed;  however  eleven  (11)  trees  have been   removed   for   erection   of   overhead  transmission   line   over   one   kilometer distance.  Compensatory  plantation  is  recommended  in  this  regard  after  the construction phase is over. 

 Safety and Health: 

 The construction work requires careful planning and precautionary measures, which includes the following. 

 

 

• Carefully planned usage of heavy machinery 

• Proper use of personal protection equipments 

• Adequate provision of water supply and sanitation facilities in the labor camps 

• Provision of proper signboards for the local residents  

 

6.3.3  Mitigation Measures at Operation Phase 

 During   the   operation   phase,   all   mitigatory   activities   will   primarily   be   the responsibility of the Director HSEQ, KESC and it will mainly be a matter of exercising proper management of  the grid station. Most of  this activity  should be covered by the management manuals planned for operation of the grid. 

 As described  in  the previous  chapter, no major negative  socio‐cultural  impacts are likely to result from the project. There are no sites of religious, cultural or historical importance near the site. KESC should make sure that the local population is abreast of the project development. 

 The  significant  environmental  issues  and  socioeconomic  concerns  associated with the O&M  activities, which  are expected during  the operation phase of  the project are listed below. The mitigation measures recommended during the operation phase are discussed in the subsequent sections and also shown in Table 6.1. 

 

 

• SF6 Gas Emission 

• Transformer Noise 

• Transformer Oil Leakage 

• EMF Generation 

Page 122: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar

NEC Consultants (Pvt.) Ltd.  68

 Environmental Impact Assessment 

 

Table 6.1 Major Potential Impacts & Mitigations Measures at Operation Phase 

 

S. No

Aspect

Possible Environmental Impact Mitigation Measures

1

SF6 Gas Emission

• Greenhouse Effect 

• Reactive Decomposition 

Products

• SF6 Containment Plan to be followed. 

• Regular & Detailed Inspection is suggested. 

• Metal fluorides to be disposed through authorized contractor.

2

Transformer Oil

• Degeneration of Oil 

• Leakage & Seepage 

• Soil Contamination 

• Ground water contamination

• Dielectric strength of transformer oil will be monitored periodically as is the current practice at other KESC grid stations 

• More comprehensive tests will be carried out after every 5 years. 

• Transformers will have impervious gravel based channels and drainage 

pits to collect any leaked oil which will be recycled & reused. 

• Waste oils will be disposed in accordance with their respective MSDS.

3

Transformer Operation

Increased Noise Level in close vicinity

• Periodic noise measurements will be carried out at the outer fence of the grid stations. 

• Surrounding wall with sound attenuation effect will be built. 

• Proper maintenance of the equipments & machineries inside grid. 

• Liaison with the nearby communities will be maintained.

Page 123: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar

NEC Consultants (Pvt.) Ltd.  69

Environmental Impact Assessment 

 

S. No

Aspect

Possible Environmental Impact Mitigation Measures

4

Domestic wastewater generation

Impact on Water Quality • Regularly maintained septic tank & soak pit with overflow provision.

5

EMF Generation

Health Risks • Regular EMF monitoring to be carried out

6

Fire Incidents

Safety Risks

• CO2gas extinguishers will be kept at appropriate places 

• Isolation switches to be provided 

• Buffer zone/ High wall to be built around grid station

7

O& M Activities

Possible Environmental losses due to incompetent staff

• Preparation & Training in use of O&M Manuals and Standard Operating Practices 

• Adequate Training to all relevant staff

Page 124: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  70

Environmental Impact Assessment 

 

SF6 Gas Emission: 

 To  prevent  any  increase  of  SF6    in  the  atmosphere,  its  use  is  confined  to  closed systems. The gas pressure  is monitored  in the  individually sealed gas compartments and in the circuit‐breaker housing. The low gas losses (below 1 % per year) are taken into account with the first gas filling. Automatic make‐up facilities are not necessary. 

 Table 6.2 

Suggested Routine Inspection & Maintenance Schedule 

  Frequency Details

Ordinary

2 months

Pressure check Recording number of operations of circuit breakers and light arrester

Regular 3 years Gas Leakage Test

Detailed

6 years Detailed inspection of operating device Internal check of Circuit Breaker

Annexure  –  16  shows  the  SF6    Gas  containment  plan  as  per  manufacturer’s recommendation. 

 Transformer Noise: 

 The power transformers at the grid station produce noise  if they are overloaded or the power factor is poor. This can be mitigated by bringing capacitors into the circuit to improve the power factor and consequently lowering the noise produced by them at  the  time of overloading.  Installation of capacitors at  the grid station will help  to control the noise up to much extent. 

 

 

• Periodic noise measurements will be  carried out at  the outer  fence of  the grid stations,  in order  to ensure  that  the noise  levels are within acceptable  limits.  If found beyond these limits at any stage, appropriate measures will be taken, such as replacing the noisy equipment. 

• The grievance redressed mechanism will be maintained on continuous basis.  

Transformer Oil Leakage:  

As   already   mentioned,   pure   hydrocarbon   mineral   oil   will   be   used   for   all transformers, current transformers, potential transformers and capacitors under the project which will not have any adverse environmental impacts. In a grid station the transformers are regularly monitored to ensure that there  is no seepage or  leakage of oil from the transformers. 

 

 

• The dielectric strength of  the  transformer oil  filled  in  the power  transformers  is monitored  every  year  at  the  gird  stations.  It  is  recommended  to  continue  this practice.  If the dielectric strength of the transformer oil  is found to be  less than the allowable limits, then the oil will be replaced. 

Page 125: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  71

 Environmental Impact Assessment 

 

• A more comprehensive test will be carried out for the transformer oil after every five  years.  Oil  samples  will  be  tested  for  Flash  point,  Viscosity,  Moisture, Dissolved Gas Analysis (DGA), Dielectric strength and PCBs. 

 

 

• Oil  filtration/ dehydration will be  carried out  for  removal of moisture or other impurities. 

 Probable end uses of waste oil  leaving workshops  include burning  in brick kilns, oil recycling facilities, miscellaneous works in small workshops and even as a massaging oil (thought to be useful for joint pains). However, KESC ensures that the transformer oil  is recycled and reused. The filtrate  is absorbed  in the fuel filters, which are  later discarded through authorized contractors. 

 Soil Contamination: 

 The following mitigation measures will greatly minimize if not prevent the impacts of the project’s O&M activities on the soil of the area: 

 • Solid waste will not be stored at the grid station 

• The grid stations will have their own septic tanks and soak pits. 

• MSDS of Transformer oil will be made available at the grid station 

• Non‐toxic recyclable waste will be given away for recycling. 

• Toxic  waste  will  be  temporarily  stored  separately,  sent  to  GSM  and  given  to authorized contractors for final disposal. 

• Grid stations will have channels and drainage pits  to collect any  leaked oil  from the  transformers  in  the  grid  stations.  This  oil  will  be  sent  back  to  GSM  for recycling. 

• Any  soil  contaminated  by  the  oil  spillage  will  be  removed  and  disposed  off appropriately in accordance with the MSDS of the spilled oil. 

 Reducing EMF Levels: 

 As discussed  in the previous chapter, magnetic fields quickly dissipate with distance from  the  transmission  line.  In  the current project, double circuit  transmission  lines with three conductors will be provided. The lines should be brought closer together, this will cause  the  fields created by each of  the  three conductors  to  interfere with each other and produce a reduced total magnetic field. 

 Reducing EMI Risks: 

 Transmission lines are only one of a number of external EMI sources. All pacemaker patients  are  informed  of potential  problems  associated with  exposure  to  EMI  and must  adjust  their  behavior  accordingly. Moving  away  from  a  source  is  a  standard response to the effects of exposure to EMI. Patients can shield themselves from EMI with a car, a building, or the enclosed cab of a truck. 

Page 126: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  72

 Environmental Impact Assessment 

 

6.4  Occupational Health & Safety  

The mitigation  measures  for  occupational  health  &  safety  risks  identified  in  this report are presented below: 

 a.   Personal Protective Equipment (PPE) 

 It  is  recommended  that  management  should  ensure  the  proper  use  of  PPEs during all phases of the project. Adequate numbers and appropriate sizes of PPEs should  be made  available  to  the  workers.  PPEs  should  not  be  shared  among workers as it may transmit diseases at the project site. 

 b.   Competence & Trainings 

 It  is  recommended  that  every  worker  whose  work may  have  significant  risks should be adequately skilled in term of relevant experience or adequately trained for  performing his  job. Management  and  Contractor  should be  responsible  for providing  adequate  trainings  to  their  employees  prior  to  their  engagement  at site. 

 c.  Standard Operating Procedures 

 It is recommended that contractor should prepare individual Standard Operating Procedures  (SOPs)  for  all  heavy machineries  present  at  site. Contractor  should also be  responsible  for  providing  training of workers on  these  SOPs.  The  SOPs should be accessible  to operator and  should be used as a  reference when and where required. 

 d.   Periodic Maintenance 

 It  is  recommended  that  all  the  heavy machineries  present  at  the  project  site should be  tuned  frequently by  the contractor.  It  is also  recommended  that  the contractor  should  ensure  the  periodic  maintenance  and  lubrication  of  the machineries in order to minimize the air pollution and noise at the project site. 

 e.   Fire Management 

 Fire   prevention   measures   can   minimize    the    risk   of   outbreak   of    fire   by appropriate  choice,  location  and  installation  of  various  materials  and equipments. The potential sources of fire can be reduced by: 

 

 

• Early warning system. 

• Fire drills on regular basis 

• Effective and efficient first aid fire fighting arrangement. 

Page 127: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

NEC Consultants (Pvt.) Ltd.  73

 Environmental Impact Assessment 

 

f.  Safety Instructions and Practices 

 Signboards  are  an  effective  way  of  communicating  safety  messages  and instructions.  It  is  recommended  to  put  in  place  relevant  safety  instructions  as signboards,  preferably  having  graphical  messages,  so  that  it  could  be  easily understood by even the illiterate workers. 

Page 128: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  74

     

 

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CHAPTER 

7  

  

7.1  General  

The  Environmental Management  Plan  (EMP)  is  a  strategic  approach  towards  the effective  implementation of  the mitigation measures and environmental protection of  the  project  area  and  its  surrounding.  This  EMP  ensures  that  the  undue  or reasonably  adverse  impact  of  the  construction  and  operation  of  a  project  are prevented and  the positive benefits of  the project are enhanced. According  to  this plan, all the activities related to various phases of the project such as construction, commissioning and operation are controlled and monitored. 

 This  EMP  encompasses  all  the  facets  of  the  project  and may  be  used  as  a  quick reference by  the  contractor(s)  as well  as by  the personnel(s) of KESC  for  effective implementation of  the mitigation measures and  tracking  the overall environmental performance of the project. 

 This EMP addresses all the significant  impacts that are  identified during the  impacts identification  process  of  the  EIA.  It  should  be  amended  in  consultation  with  the concerned regulatory authority, in this case SEPA if any issue has been overlooked or if any need would arise as the project continues. 

 7.2  Purpose & Need of the EMP 

 Primarily,   the   purpose   of   this   EMP    is   to   serve   as  a   quick   reference   for   the consultants,  contractor  as  well  as  the  personnel(s)  of  KESC  to  implement  the proposed mitigation measures effectively and to monitor the overall environmental performance  of  the  project.  Further  more  to  house  the  procedure,  which  the proponent  follows  to  implement  and  maintain  this  Environmental  Management Plan,   the need of the EMP is mentioned as follows: 

 

 

• Ensure  that  attention  is  paid  to  the  actual  effects  arising  from  construction & operation; 

• Ensure that anticipated impacts are maintained within the levels predicted; 

• Ensure   that   unanticipated   impacts   are  managed   or  mitigated   before   they become a problem; and 

• Ensure   that   environmental   management   brings   about   real   environmental benefits  and  achieves  environmental  sustainability,  rather  than  the Environmental  Approval  Process  being  a  mere  paper  chase  to  secure  a 

development approval60.   

60 Guidelines for Preparation and Review of Environmental Reports, 1997 

Page 129: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  75

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

7.3  Objectives of the EMP  

The main objectives of the EMP during the construction phase will be to:  

• Monitor   actual   project   impacts   on   the   physical,   ecological,   cultural   and socioeconomic receptors. This will indicate adequacy of EIA. 

• Recommend  mitigation  measure  for  any  unexpected   impacts  of  the  project during  construction  period,  not mentioned  in  the  EIA  study  or  if  the  level  of impact exceeds the anticipated limit of the EIA study. 

• Ensure  compliance of  the  legal  and  community  obligations,  including  safety  on the site; and 

• Ensure  safe  disposal  of  the  construction  debris,   including  excavated  soil  or vegetation. 

 Whereas, the objectives of the EMP during the operation phase of the project are as below: 

 • Evaluate adequacy of   the EIA with respect to the project’s predicted  long term 

impacts on the environment; and 

• Evaluate  effectiveness  of  the  mitigation  measures  proposed   in  the  EIA  and recommend improvement if any need would arise. 

 7.4  Scope of the EMP 

 

 

The scope of the EMP includes the following phases of the project.  

• Construction / Installation Phase 

• Commissioning/ Operation Phase  

All  the  activities  performed  during  these  phases will  be  controlled  and monitored according to this EMP. 

 7.5  Responsibilities 

 The  Director  of  HSEQ  Department  KESC  is  overall  responsible  for  the  effective implementation  of  the  EMP  during  the  construction  &  operation  phase  of  the project.  However,  Contractor(s)  and  Manager  EHS  BU  G&T  are  responsible  for implementing  the  EMP  during  construction  and  operation  phases  of  the  project respectively and report the overall environmental performance to the Director. The details of  roles &  responsibilities are discussed  in  the Section 7.10.1 Organizational Structure; Roles and Responsibilities of the EMP. 

 7.6  Commitment to Environmental, Health and Safety (EHS) 

 KESC,  a  well  known  private  entity  in  Pakistan  is  committed  to  perform  all  of  its activities in a way which is safe for the environment as well as the health & safety of its  employees  and  the  person(s) working  on  behalf  of  them  i.e.  contractors.  The 

Page 130: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  76

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

 Environmental Impact Assessment 

 

management of KESC owns  this EMP  and will use  it  as a  reference  to  control  and monitor  all   the   activities  that  will   be   performed  during   the   construction  and operation phases of the project. 

 7.7  Structure of the EMP 

 The structure of the KESC 132 kV HIS Grid Station EMP comprises of the following; 

 

 

• Key Environmental Issues 

• Impact Mitigation Plan. 

• Organizational Structure; Roles & Responsibilities. 

• Training Program 

• Environmental Monitoring Plan 

• Reporting 

• Risk & Disaster Management Plan 

 7.8  Key Environmental Issues 

 The key environmental issues associated with the project are thoroughly discussed in Chapter 5. However, the key environmental issues of the project are specified briefly as follows: 

 

 

• Contamination  of  air,  water  and  soil  during  the  construction  and  operation phases; 

• Noise Generation by vehicles, construction machinery and transformers installed at the grid station. 

• Occupational  Health &  Safety  Issues  of  the  employees  of  KESC  as well  as  of contractor and  its  staff during  construction and operation phase of  the project and also people living in the close vicinity. 

 7.9  Impact Mitigation Plan 

 Impact mitigation plan is one of the main components of the EMP. It will ensure the effective  implementation of suggested mitigation measures during construction and operation phase of  the project as described  in  the EIA. The  impact mitigation plan based on the EIA is presented in Annexure – 17 of this report. 

Page 131: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  77

Environmental Agency

─ EPA Sindh, SEPA

Government Department

─ Local Government

NGO & Pressure Groups

Erection & Commissioning of 132 kV Hybrid Grid Station at Gulistan‐e‐Jauhar 

Environmental Impact Assessment 

 

7.10  Organizational Structure; Roles & Responsibilities  

The proposed Organizational Structure for the effective implementation of EMP at KESC is depicted in Figure 7.1 below:  

 

CEO

Contractor(s) Director (HSEQ)

Manager EHS BU G&T

LEGEND

Chain of Command

Information Flow BU G & T

LDC GSM GSO Transmission Construction Phase Operation Phase External Communication

Figure 7.1: Organizational Structure 

Page 132: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  78

 Environmental Impact Assessment 

 

7.10.1  Roles & Responsibilities 

 Director HSEQ: 

 The Director HSEQ will have the overall responsibility for ensuring compliance of the EMP  during  all  phases  of  the  project.  Accoring  to  the  EMP  the  responsibilities  of director will include; 

 

 

• Setting  up  system  for  environmental  management  and  supervising environmental and social impact assessment. 

• Providing  or  arranging  extensive  training  program  on  the  EMP  and  other  HSE issues identified in section 7.11 for the members of operation team as well as for contractors. 

• Providing  technical assistance  to  the  contractor(s)  for effective  implementation of EMP during the construction phase and provide support where required. 

• Ensuring compliance of EMP during operation phase of the project. 

• Coordinating   with    the    regulatory   agencies    including   EPA,   District    Local Government,  Local  NGOs,  CBOs  that  could  assist  the  project  in  independent review of environmental compliance. 

• Reporting  environmental monitoring  and  evaluation  of  compliance  to  the  EPA and incorpoating EPA’s comments in the EMP on need arise basis. 

• Reporting perodic EMP compliance status to the CEO. 

• Amending EMP in consultation with the concerened EPA in this case, SEPA if any new environmental legislation will be promulgated or any other requirement will arive in this regard. 

 Manager EHS BU G&T: 

 The following responsibilities are identified for the Manager EHS BU G&T. 

 

 

• Ensuring the compliance of the EMP during the operation phase of the project. 

• Reporting periodic compliance status of  the EMP during operation phase of  the project to the Director. 

 Contractor(s): 

 The responsibilities of contractors will include. 

 

 

• The contractor’s site manager is responsible for effective  implementation of the EIA and EMP during the construction phase of the project. 

• Ensure compliance of the EMP during construction phase. 

• Adhere to the requirement of EMP. 

• Report periodic compliance  status of  the EMP during constuction phase  to  the Director. 

Page 133: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  79

 Environmental Impact Assessment 

 

Environmental Agency: 

 The responisbility of the environmental agency, SEPA will include; 

 

 

• Monitor   compliance   of   the   EMP  of   project   and   any   additional  mitigation measures required by the NOC of the project. 

• Provide  technical  assistance  to  the  project  proponent  for  effective implementation of the EMP. 

 

 

7.11  Training Program  

 

The corporate HSEQ or BU G&T is responsible for identifying, conducting / arranging and evaluating trainings  for the effective  implementation of the EMP. The trainings included in the training program are briefly discussed below; 

 7.11.1  Awareness Training 

 The members of  the operation  team and  the staff deployed on  the construction of the project on behalf of the contractor are needed to be aware of the basic concept, principles and requirements of  the EMP. The  training also  instructs personnel(s) on how to use the EMP and how they can contribute to maintain and improve the EMP. Participation in the awareness training should be recorded. These records should be generated and maintained by the corporate HSEQ and / or BU G&T. 

 7.11.2  EMP Orientation Training 

 The orientation  training of  the  EMP  should be provided  to new  inductee(s)  in  the operation   or   contractor’s   team   by   the   corporate   HSEQ.    It    is   responsible    for conducting / arranging such training and maintain records accordingly. 

 7.11.3  Job Specific Training 

 The  personnel(s)  whose  work  can  cause  a  significant  environmental  impacts  are sufficiently competent and skilled  in performing  their task. However, some workers may  require  increased  level of competence and  speciallized  skills  to be adequately trained  to  upgrade,  reinforce  or  support  their  competence  and  skills.  These personnel(s) may be trained in addition and/or provided with written  instruction on how to perform the specific job. Trainings may be in the form of on‐the‐job training, classroom  instruction  and  demonstration  etc.  All  competence  and  skill  training should be recorded by the corporate HSEQ. 

 Personnel(s) who have proven experiences in their field do not need to demonstrate their competence by education or  training. Competence acquired  through  relevant experience may be indentified and recorded by the corporate HSEQ. 

Page 134: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  80

 Environmental Impact Assessment 

 

7.11.4  Disaster Management Training 

 Personnel(s)  assigned  with  the  specific  responsibilities  in  implementing  disaster management  procedures  are  trained  in  how  to  carry  out  their  task  and  activities assigned  to  them.  Corporate  HSEQ  ensures  that  all  personnel(s)  designated  for specific  disaster  response  activities  are  adequtely  trained.  Training  can  be  in  the form   of   demonstration,   drills   and   classroom   instructions   etc.   All   disaster management  trainings  should  be   recorded.  Corporate  HSEQ   is   responsible  for keeping such training records. 

 7.11.5  Identification of the Need for New or Additional Training 

 To  identify  the  need  for  new  or  additional  training,  the  corporate  HSEQ  and  EHS Manager  BU G&T  should  review  the  records  and  consider  relevant  event,  reports and data such as; 

 

 

• Changes in the EMP, such as revised or any amendment; 

• Changes in applicable law requirement or any other requirement; 

• Non‐attainment  of  specified  environmental  performance,  or  decreasing performance; inadequate performance of an individual or groups of personnel(s). 

 7.12  Environmental Monitoring Plan 

 

 

An Environmental Monitoring Plan has been developed by KESC keeping in view the following objectives: 

 

 

• Systematically   track   the   environmental   performance   of   the   project   during construction and operation phases of the project. 

• Verify  that  the  activities  undertaken  during  the  construction  and  operation phases are  in compliance with  the  requirement of  the EIA and other applicable laws. 

• Reporting  the  observation  related  to  the  environmental  performance  of  the project to the corporate HSEQ/BU G&T, so that any remedial measure if required can be made ahead of time. 

• Preparing environmental performance report of KESC Grid Station. 

• Reporting the overall performance to the regulatory authority, SEPA. 

 The Environmental Monitoring Plan provided  in Annexure – 18 will be used by  the KESC  and  its  Contractor(s)  as  a  reference  tool  for  systematic  environmental monitoring of the significant impacts identified in the EIA. 

 The  following  individuals  will  be  responsible  for  carrying  out  the  Environmental Monitoring during construction and operation phases of the project: 

 

 

• Contractor’s Site Manager will be responsible for carrying out the Environmental Monitoring during construction phase. 

Page 135: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  81

 Environmental Impact Assessment 

 

• Manager  EHS  BU G&T will  be  responsible  for  carrying  out  the  Environmental Monitoring during the operation phase. 

 However,  all  the  observation  of  the  environmental  monitoring  will  be communicated  to  the corporate HSEQ.  It will  then be  responsible  to  report  the overall  environmental performance  of  the  project  to  the  CEO.  This will  enable effective decision making by  the management. Corporate HSEQ will also  inform and update SEPA with the environmental performance of the project. 

 In addition to the above, the management should be responsible for provision of safe drinking water, enforcement of occupational health and  safety equipment, implementation of  sanitation  condition  along with  supply of hygienic  food  and sewerage system for the construction team at the project site. 

 Environmental Monitoring during Operation: 

 According  to  NEQS  (self monitoring &  reporting  by  industries)  Rule  2001,  the project neither  falls under Category A nor under Category B of Schedule‐I. The grid  station  is not expected  to emit  any priority pollutant  as mentioned  in  the above rules during the operational phase. 

 Increase in transportation is not expected during the operation and maintenance activity,  therefore  monitoring  for  vehicular  emissions  is  not  recommended. Similarly, monitoring of effluent discharge is also not recommended as only four to  five persons will be  residing within  the grid building and  the domestic waste generated  in  comparison  to pollution  load  of main  KWSB  sewer  line would be negligible. 

 The solid wastes generation  from the grid station should be monitored so as to ensure that no immediate and long‐term environmental and health problems are caused.  EMF monitoring  is  also  recommended  for  the  grid  station,  biannually. The  management  would  ensure  compliance  of  monitoring  results  with  the Pakistan‐EPA  standards  and  ICNIRP  limits,  respectively.  Regular monitoring  of transformer oil is also recommended. 

 7.13  Reporting 

 The  corporate HSEQ will be  responsible  for presenting  its data  and  findings  in  the form   of   a    formal   report   to   the   CEO,   at   a    frequency   as   deemed   fit   by   the management. It is recommended that this frequency of reporting should not be less than  once  every  six  months.  The  purpose  of  reporting  would  be  essentially  to provide  necessary  information  to  enable  effective  decision  making  by  the management. The monitoring  report  to be presented  to  the management may be of any  format. However, in terms of content, it must include; 

 

 

• Summary of the environmental and social performance. 

Page 136: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  82

 Environmental Impact Assessment 

 

• Record   of   all   incidents   and   their   remedial  measures   to   ensure   that   the emergency   situations   are   responded   in   accordance   with   the   Emergency Response Plan. 

 Based on  this  information,  the management would  take decisions  for performance improvement. In every subsequent monitoring report, the performance and efficacy of measures undertaken by  the management  in the previous review process would also be evaluated. 

 The  proposed  combination  of  environmental  monitoring,  reporting  and management  review  would  complete  the  cycle  for  continual  improvement  and would  ensure  better  environmental  and  social  performance  of  the  project  after every cycle. 

 7.14  Disaster Management Plan 

 Disaster  is  an  unexpected  event  due  to  sudden  failure  of  the  system,  external threats,  internal disturbances, earthquakes,  fire and accidents. Due to the existence of hazards associated with electrical T&D facilities, risk assessment needs to be made in order to evolve a sound Disaster Management Plan to cover the aspects of: 

 

 

• Conditions potentially  leading  to major  release accidents  including  releases  from cables, electric panels, pipes, flexible connections, valves etc 

• Occupational health and well‐being conditions; and 

• Occupational safety conditions. 

 Hazards assessment  for  the grid  station needs  to  take  into account all  the potential 

hazards  that may  occur  during  the  construction  as well  as  operation  phase  of  the 

project as discussed in Chapter 5. Following subsections describe the measures to be 

undertaken  by  the  project  proponent  to  prevent  or minimize  risk  of  unexpected 

event. 

 7.14.1  Preventive Action 

 Once the likelihood of a disaster is suspected, action has to be initiated to prevent a failure. Engineers responsible for preventive action should  identify sources of repair equipments, materials, labor and expertise for use during emergency. 

 The level at which a situation will be termed a disaster, shall be specified. Preventive action plan should cover the following matters: 

 

 

• Exit points 

• Safety areas 

• Nearest medical facilities. 

Page 137: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

NEC Consultants (Pvt.) Ltd.  83

 Environmental Impact Assessment 

 

7.14.2  Communication System 

 An  efficient  communication  system  is  absolutely  essential  for  the  success  of  any disaster management  plan.  This  has  to  be  worked  out  in  consultation  with  local authorities. More  often,  the  entire  communication  system  gets  disrupted when  a disaster occurs. The damage areas need  to be  clearly  identified and provided with temporary and  foolproof communication  system.  It  is essential  to communicate by whom and how a declared emergency will be terminated. 

 7.14.3  Emergency Action Committee 

 To  ensure  coordinated  action,  an  Emergency  Action  Committee  should  be constituted.  Emergency  Action  Committee  will  prepare  the  evacuation  plan  and procedures for implementation based on local needs and facilities available. The plan should include: 

 

 

• Demarcation of the areas to be evacuated with priorities, 

• Safe area and shelters, 

• Functions and responsibilities of various members, and 

• Setting up of joint control action. 

 All personnel  involved  in  the Emergency Action Plan  should be  thoroughly  familiar with all the elements of the plant area and their responsibilities. The staff at the site should  be  trained  for  problem  detection,  evaluation  and  emergency  remedial measures.  Individual responsibility to handle  the segments  in emergency plan must be allotted. 

 7.14.4   Implementation of DMP 

 

 

• The Disaster Management Plan (DMP) will be made available at the grid station. Its salient points will be displayed at all prominent places. 

• The  O&M  staff  will  be  given   training  on   the  DMP.  The  DMP  will   include procedures to inform the nearby communities in case of fire in the grid station. 

• Appropriate signage on safety precautions will be installed at the key locations. 

 A  summary  guide  for  disaster  /  emergency  management  for  the  grid  station  is attached as Annexure – 19 of this report. 

Page 138: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 1

Proposed Grid Station Layout Plan

Page 139: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 140: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 2

Pakistan Environmental Protection Act (PEPA) 1997

Page 141: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Pakistan Environmental Protection Act

(PEPA), 1997 The Pakistan Environmental Protection Act 1997 was passed by the National Assembly of

Pakistan on September 3, 1997, and by the Senate of Pakistan on November 7, 1997. The Act

received the assent of the President of Pakistan on December 3, 1997.

The text of the Environmental Protection Act 1997 is as follows:

Act No. XXXIV of 1997 An Act to provide for the protection, conservation, rehabilitation and improvement of the

environment, for the prevention and control of pollution, and promotion of sustainable

development.

Whereas it is expedient to provide for the protection, conservation, rehabilitation and

improvement of the environment, prevention and control of pollution, promotion of sustainable

development and for matters connected therewith and incidental thereto;

It is hereby enacted as follows:

1) Short Title, Extent and Commencement

(1) This Act may be called the Environmental Protection Act 1997.

(2) It extends to the whole of Pakistan.

(3) It shall come into force at once.

2) Definitions

In this Act, unless there is anything repugnant in the subject or context:

(i) "adverse environmental effect" means impairment of, or damage to, the environment

and includes:

(a) impairment of, or damage to, human health and safety or to biodiversity or

property;

Page 142: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(b) pollution; and

(c) any adverse environmental effect as may be specified in the regulation.

(ii) "agricultural waste" means waste from farm and agricultural activities including

poultry, cattle farming, animal husbandry, residues from the use of fertilizers, pesticides

and other farm chemicals;

(iii) "air pollutant" means any substance that causes pollution of air and includes soot,

smoke, dust particles, odor, light, electro-magnetic, radiation, heat, fumes, combustion

exhaust, exhaust gases, noxious gases, hazardous substances and radioactive substances;

(iv) "biodiversity" or "biological diversity" means the variability among living

organizations from all sources, including inter alia terrestrial, marine and other aquatic

ecosystems and ecological complexes of which they are part; this includes diversity

within species, between species and of ecosystems;

(v) "council" means the Pakistan Environmental Protection Council established under

section 3;

(vi) "discharge" means spilling, leaking, pumping, depositing, seeping, releasing,

flowing out, pouring, emitting, emptying or dumping;

(vii) "ecosystem" means a dynamic complex of plant, animal and micro-organism

communities and their non-living environment interacting as a functional unit;

(viii) "effluent" means any material in solid, liquid or gaseous form or combination

thereof being discharged from industrial activity or any other source and includes a

slurry, suspension or vapour;

Page 143: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(ix) "emission standards" means the permissible standards established by the Federal

Agency or a Provincial Agency for emission of air pollutants and noise and for discharge

of effluent and waste;

(x) "environment" means-

(a) air, water and land;

(b) all layers of the atmosphere;

(c) all organic and inorganic matter and living organisms;

(d) the ecosystem and ecological relationships;

(e) buildings, structures, roads, facilities and works;

(f) all social and economic conditions affecting community life; and

(g) the inter-relationships between any of the factors in sub-clauses (a) to (f)

(xi) "environmental impact assessment" means an environmental study comprising

collection of data, prediction of qualitative and quantitative impacts, comparison of

alternatives, evaluation of preventive, mitigatory and compensatory measures,

formulation of environmental management and training plans and monitoring

arrangements, and framing of recommendations and such other components as may be

prescribed;

(xii) " Environmental Magistrate" means the Magistrate of the First Class appointed

under section 24;

(xiii) "Environmental Tribunal" means the Environmental Tribunal constituted under

section 20;

(xiv) Exclusive Economic Zone" shall have the same meaning as defined in the

Territorial Waters and Maritime Zones Act, 1976 (LXXXII of 1976);

(xv) "factory" means any premises in which industrial activity is being undertaken;

Page 144: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(xvi) "Federal Agency" means the Pakistan Environmental Protection Agency

established under section 5, or any Government Agency, local council or local authority

exercising the powers and functions of the Federal Agency;

(xvii) "Government Agency" includes-

(a) a division, department, attached department, bureau, section, commission, board,

office or unit of the Federal Government or a Provincial Government;

(b) a development or a local authority, company or corporation established or

controlled by the Federal Government or Provincial Government;

(c) a Provincial Environmental Protection Agency; and

(d) any other body defined and listed in the Rules of Business of the Federal

Government or a Provincial Government;

(xviii) "hazardous substance" means-

(a) a substance or mixture of substance, other than a pesticide as defined in the

Agricultural Pesticide Ordinance, 1971 (II of 1971), which, by reason of its chemical

activity is toxic, explosive, flammable, corrosive, radioactive or other characteristics

causes, or is likely to cause, directly or in combination with other matters, an adverse

environmental effect; and

(b) any substance which may be prescribed as a hazardous substance;

(xix) "hazardous waste" means waste which is or which contains a hazardous substance or

which may be prescribed as hazardous waste, and includes hospital waste and nuclear waste;

(xx) "historic waters" means such limits of the waters adjacent to the land territory of

Pakistan as may be specified by notification under section 7 of the Territorial Waters and

Maritime Zones Act, 1976 (LXXXII of 1976);

(xxi) "hospital waste" includes waste medical supplies and materials of all kinds, and waste

blood, tissue, organs and other parts of the human and animal bodies, from hospitals, clinics

and laboratories;

Page 145: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(xxii) "industrial activity" means any operation or process for manufacturing, making,

formulating, synthesizing, altering, repairing, ornamenting, finishing, packing or otherwise

treating any article or substance with a view to its use, sale, transport, delivery or disposal, or

for mining, for oil and gas exploration and development, or for pumping water or sewage, or

for generating, transforming or transmitting power or for any other industrial or commercial

purpose;

(xxiii) "industrial waste" means waste resulting from an industrial activity;

(xxiv) "initial environmental examination" means a preliminary environmental review of

the reasonably foreseeable qualitative and quantitative impacts on the environment of a

proposed project to determine whether it is likely to cause an environmental effect for

requiring preparation of an environmental impact assessment;

(xxv) "local authority" means any agency set-up or designated by the Federal Government

or a Provincial Government by notification in the official Gazette to be a local authority for

the purposes of this Act;

(xxvi) "local council" means a local council constituted or established under a law relating

to local government;

(xxvii) "motor vehicle" means any mechanically propelled vehicle adapted for use upon

land whether its power of propulsion is transmitted thereto from an external or internal

source, and includes a chassis to which a body has not been attached, and a trailer, but does

not include a vehicle running upon fixed rails;

(xxviii) "municipal waste" includes sewage, refuse, garbage, waste from abattoirs, sludge

and human excreta and the like;

Page 146: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(xxix) "National Environmental Quality Standards" means standards established by the

Federal Agency under clause (e) of sub-section (1) of section 6 and approved by the Council

under clause (c) of sub-section (1) of section 4;

(xxx) "noise" means the intensity, duration and character from all sources, and includes

vibrations;

(xxxi) "nuclear waste" means waste from any nuclear reactor or nuclear or other nuclear

energy system, whether or not such waste is radioactive;

(xxxii) "person" means any natural person or legal entity and includes an individual, firm,

association, partnership, society, group, company, corporation, co-operative society,

Government Agency, non-governmental organization, community-based organization,

village organization, local council or local authority and, in the case of a vessel, the master or

other person having for the time being the charge or control of the vessel;

(xxxiii) "pollution" means the contamination of air, land or water by the discharge or

emission or effluents or wastes or air pollutants or noise or other matter which either directly

or indirectly or in combination with other discharges or substances alters unfavourably the

chemical, physical, biological, radiational, thermal or radiological or aesthetic properties of

the air, land or water or which may, or is likely to make the air, land or water unclean,

noxious or impure or injurious, disagreeable or detrimental to the health, safety, welfare or

property of persons or harmful to biodiversity;

(xxxiv) "prescribed" means prescribed by rules made under this Act;

(xxxv) "project" means any activity, plan, scheme, proposal or undertaking involving any

change in the environment and includes;

(a) construction or use of buildings or other works;

(b) construction or use of roads or other transport systems;

(c) construction or operation of factories or other installations;

Page 147: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(d) mineral prospecting, mining, quarrying, stone-crushing, drilling and the like;

(e) any change of land use or water use; and

(f) alteration, expansion, repair, decommissioning or abandonment of existing

buildings or other works, roads or other transport systems; factories or other

installations;

(xxxvi) "proponent" means the person who proposes or intends to undertake a project;

(xxxvii) "Provincial Agency" means a Provincial Environmental Protection Agency

established under section 8;

(xxxviii) "regulations" means regulations made under this Act;

(xxxix) "rules" means rules made under this Act;

(xl) "sewage" means liquid or semi-solid wastes and sludge from sanitary conveniences,

kitchens, laundries, washing and similar activities and from any sewerage system or sewage

disposal works;

(xli) "standards" means qualitative and quantitative standards for discharge of effluents and

wastes and for emission of air pollutants and noise either for general applicability or for a

particular area, or from a particular production process, or for a particular product, and

includes the National Environmental Quality Standards, emission standards and other

standards established under this Act and the rules and regulations made thereunder;

(xlii) "sustainable development" means development that meets the needs of the present

generation without compromising the ability of future generations to meet their needs;

(xliii) "territorial waters" shall have the same meaning as defined in the Territorial Waters

and Maritime Zones Act, 1976 (LXXXII of 1976);

Page 148: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(xliv) "vessel" includes anything made for the conveyance by water of human beings or of

goods; and

(xlv) "waste" means any substance or object which has been, is being or is intended to be,

discarded or disposed of, and includes liquid waste, solid waste, waste gases, suspended

waste, industrial waste, agricultural waste, nuclear waste, municipal waste, hospital waste,

used polyethylene bags and residues from the incineration of all types of waste.

3) Establishment of the Pakistan Environmental Protection Council-

(1) The Federal Government shall, by notification in the official Gazette, establish a Council to

be known as the Pakistan Environmental Protection Council consisting of;

(i)Prime Minister or such other person as the Prime Chairperson

Minister may nominate in this behalf.

(ii)Minister Incharge of the Ministry or Division Vice Chairperson

dealing with the subject of environment.

(iii) Chief Ministers of the Provinces. Members

(iv) Ministers Incharge of the subject of environment in the provinces. Members

(v) Such other persons not exceeding thirty-five as the Federal Members

Government may appoint, of which at least twenty shall be non

-official including five representatives of the Chambers of

Commerce and Industry and Industrial Associations and one

or more representatives of the Chambers of Agriculture, the

medical and legal professions, trade unions, and non-governmental

organizations concerned with the environment and development,

and scientists, technical experts and educationists.

vi) Secretary to the Government of Pakistan, in-charge of Member/Secretary

the Ministry or Division dealing with the subject of environment

(2) The Members of the Council, other than ex–officio members, shall be appointed in

accordance with the prescribed procedure and shall hold office for a term of three years.

Page 149: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(3) The Council shall frame its own rules of procedure.

(4) The Council shall hold meetings as and when necessary, but not less than two meetings shall

be held in a year.

(5) The Council may constitute committees of its members and entrust them with such functions

as it may deem fit, and the

recommendations of the committees shall be submitted to the Council for approval.

(6) The Council or any of its committees may invite any technical expert or representative of any

Government Agency or non-governmental organization or other person possessing specialized

knowledge of any subject for assistance in performance of its functions.

4) Function and Powers of the Council

(1) The Council shall-

(a) co-ordinate and supervise enforcement of the provisions of this Act;

(b) approve comprehensive national environmental policies and ensure their implementation

within the framework of a national conservation strategy as may be approved by the Federal

Government from time to time;

(c) approve the National Environmental Quality Standards;

(d) provide guidelines for the protection and conservation of species, habitats, and

biodiversity in general, and for the conservation of renewable and non-renewable resources;

(e) coordinate integration of the principles and concerns of sustainable development into

national development plans and policies; and

(f) consider the National Environment Report and give appropriate directions thereon.

(2) The Council may, either itself or on the request of any person or organization, direct the

Federal Agency or any Government Agency to prepare, submit, promote or implement projects

for the protection, conservation, rehabilitation and improvement of the environment, the

prevention and control of pollution, and the sustainable development of resources, or to

undertake research in any specified aspect of environment.

5) Establishment of the Pakistan Environmental Protection Agency

Page 150: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(1) The Federal Government shall, by notification in the official Gazette, establish the Pakistan

Environmental Protection Agency, to exercise the powers and perform the functions assigned to

it under the provisions of this Act and

the rules and regulations made thereunder.

(2) The Federal Agency shall be headed by a Director General, who shall be appointed by the

Federal Government on such

terms and conditions as it may determine.

(3) The Federal Agency shall have such administrative, technical and legal staff as the Federal

Government may specify, to be appointed in accordance with such procedure as may be

prescribed.

(4) The powers and function of the Federal Agency shall be exercised and performed by the

Director General.

(5) The Director General may, be general or special order, delegate any of these powers and

functions to staff appointed under

sub-section (3)

(6) For assisting the Federal Agency in the discharge of its functions, the Federal Government

shall establish Advisory Committees for various sectors, and appoint as members thereof

eminent representatives of the relevant sector, educational institutions, research institutes and

non-governmental organizations.

6) Functions of the Federal Agency

(1) The Federal Agency shall-

(a) administer and implement the provisions of this Act and the rules and regulations made

thereunder;

(b) prepare, in coordination with the appropriate Government Agency and in consultation

with the concerned sectoral Advisory Committees, national environmental policies for

approval by the Council;

(c) take all necessary measures for the implementation of the national environmental policies

approved by the Council;

(d) prepare and publish an annual National Environment Report on the state of the

environment;

Page 151: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(e) prepare or revise, and establish the National Environment Quality Standards with

approval of the Council; Provided that

before seeking approval of the Council, the Federal Agency shall publish the proposed

National Environmental Quality

Standards for public opinion in accordance with the prescribed procedure;

(f) ensure enforcement of the National Environmental Quality Standards;

(g) establish standards for the quality of the ambient air, water and land, by notification in the

official Gazette, in consultation with the Provincial Agency concerned;

Provided that

(i) different standards for discharge or emission from different sources and for

different areas and conditions may

be specified;

(ii) where standards are less stringent than the National Environmental Quality

Standards, prior approval of the Council shall be obtained;

(iii) certain areas, with the approval of the Council, may exclude from carrying out

specific activities, projects from the application of such standards;

(h) co-ordinate environmental policies and programmes nationally and internationally;

(i) establish systems and procedures for surveys, surveillance, monitoring, measurement,

examination, investigation, research, inspection and audit to prevent and control pollution,

and to estimate the costs of cleaning up pollution and rehabilitating the environment in

various sectors;

(j) take measures to promote research and the development of science and technology which

may contribute to the prevention of pollution, protection of the environment, and sustainable

development;

(k) certify one or more laboratories as approved laboratories for conducing tests and analysis

and one or more research institutes as environmental research institutes for conducting

research and investigation, for the purposes of this Act;

(l) identify the needs for, and initiate legislation in various sectors of the environment;

(m) render advice and assistance in environmental matters, including such information and

data available with it as may be required for carrying out the purposes of this Act;

Page 152: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Provided that the disclosure of such information shall be subject to the restrictions contained

in the proviso to sub-section (3) of section 12;

(n) assist the local councils, local authorities, Government Agencies and other persons to

implement schemes for the proper disposal of wastes so as to ensure compliance with the

standards established by it;

(o) provide information and guidance to the public on environmental matters;

(p) recommend environmental courses, topics, literature and books for incorporation in the

curricula and syllabi of educational institutions;

(q) promote public education and awareness of environmental issues through mass media and

other means, including seminars and workshops;

(r) specify safeguards for the prevention of accidents and disasters which may cause

pollution, collaborate with the concerned person in the preparation of contingency plans for

control of such accidents and disasters, and co-ordinate implementation of such plans;

(s) encourage the formation and working of non-governmental organizations, community

organizations and village organizations to prevent and control pollution and promote

sustainable development;

(t) take or cause to be taken all necessary measures for the protection, conservation,

rehabilitation and improvement of the environment, prevention and control of pollution and

promotion of sustainable development; and

(u) perform any function which the Council may assign to it.

(2) The Federal Agency may-

(a) undertake inquiries or investigation into environmental issues, either of its own accord or

upon complaint from any person or organization;

(b) request any person to furnish any information or data relevant to its functions;

(c) initiate with the approval of the Federal Government, requests for foreign assistance in

support of the purposes of this Act and enter into arrangements with foreign agencies or

organizations for the exchange of material or information and participate in international

seminars or meetings;

(d) recommend to the Federal Government the adoption of financial and fiscal programmes,

Page 153: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

schemes or measures for achieving environmental objectives and goals and the purposes of

this Act, including:

(i) incentives, prizes, awards, subsidies, tax exemptions, rebates and depreciation

allowances; and

(ii) taxes, duties, cesses and other levies;

(e) establish and maintain laboratories to help in the performance of its functions under this

Act and to conduct research in various aspects of the environment and provide or arrange

necessary assistance for establishment of similar laboratories in the private sector; and

(f) provide or arrange, in accordance with such procedures as may be prescribed, financial

assistance for projects designed to facilitate the discharge of its functions.

7) Powers of the Federal Agency

Subject to the provisions of this Act, the Federal Agency may-

(a) lease, purchase, acquire, own, hold, improve, use or otherwise deal in and with any

property both movable and immovable;

(b) sell, convey, mortgage, pledge, exchange or otherwise dispose of its property and assets;

(c) fix and realize fees, rates and charges for rendering any service or providing any facility,

information or data under this Act or the rules and regulations made thereunder;

(d) enter into contracts, execute instruments, incur liabilities and do all acts or things

necessary for proper management and conduct of its business;

(e) appoint with the approval of the Federal Government and in accordance with such

procedures as may be prescribed, such advisers, experts and consultants as it considers

necessary for the efficient performance of its functions on such terms and conditions as it

may deem fit;

(f) summon and enforce the attendance of any person and require him to supply any

information or document needed for the conduct of any enquiry or investigation into any

environmental issue;

(g) enter and inspect and under the authority of a search warrant issued by the Environmental

Tribunal or Environmental Magistrate, search at any reasonable time, any land, building,

premises, vehicle or vessel or other place where or in which, there are reasonable grounds to

believe that an offence under this Act has been or is being committed;

Page 154: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(h) take samples of any materials, products, articles or substances or of the effluents, wastes

or air pollutants being discharged or emitted or of air, water or land in the vicinity of the

discharge or emission;

(i) arrange for test and analysis of the samples at a certified laboratory;

(j) confiscate any article used in the commission of the offence where the offender is not

known or cannot be found within a reasonable time:

Provided that the power under clauses (f), (h), (i) and (j) shall be exercised in accordance

with the provisions of the Code of Criminal Procedure, 1898 (Act V of 1898), or the rules

made under this Act and under the direction of the Environmental Tribunal or

Environmental Magistrate; and

(k) establish a National Environmental Coordination Committee comprising the Director-

General as its chairman and the Director-Generals of the Provincial Environmental

Protection Agencies and such other persons as the Federal Government may appoint as its

members to exercise such powers and perform such functions as may be delegated or

assigned to it by the Federal Government for carrying out the purposes of this Act and for

ensuring inter–provincial co-ordination in environmental policies;

8) Establishment, Powers and Functions of the Provincial Environmental

Protection Agencies

(1) Every Provincial Government shall, by notification in the official Gazette, establish an

Environmental Protection Agency, to exercise such powers and perform such functions as may

be delegated to it by the Provincial Government under sub-section (2) of section 26.

(2) The Provincial Agency shall be headed by a Director-General who shall be appointed by the

Provincial Government on such terms and conditions as it may determine.

(3) The Provincial Agency shall have such administrative, technical and legal staff as the

Provincial Government may specify, to be appointed in accordance with such procedure as may

be prescribed.

(4) The powers and functions of the Provincial Agency shall be exercised and performed by the

Director-General.

(5) The Director-General may, by general or special order, delegate any of these powers and

functions to staff appointed under sub-section (3).

Page 155: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(6) For assistance of the Provincial Agency in the discharge of its functions, the Provincial

Government shall establish sectoral Advisory Committees for various sectors and appoint

members from amongst eminent representatives of the relevant sector, educational institutions,

research institutes and non-governmental organizations.

9) Establishment of the Provincial Sustainable Development Funds

(1) There shall be established in each Province a Sustainable Development Fund.

(2) The Provincial Sustainable Development Fund shall be derived from the following sources,

namely;

(a) grants made or loans advanced by the Federal Government or the Provincial

Governments;

(b) aid and assistance, grants, advances, donations and other non-obligatory funds received

from foreign governments, national or international agencies, and non-governmental

organizations; and

(c) contributions from private organizations, and other persons.

(3) The Provincial Sustainable Development Fund shall be utilized in accordance with such

procedure as may be prescribed for:

(a) providing financial assistance to the projects designed for the protection, conservation,

rehabilitation and improvement of the environment, the prevention and control of pollution,

the sustainable development of resources and for research in any specified aspect of

environment; and

(b) any other purpose which in the opinion of the Board will help achieve environmental

objectives and the purpose of this Act.

10) Management of the Provincial Sustainable Development Fund

(1) The Provincial Sustainable Development Fund shall be managed by a Board known as the

Provincial Sustainable Development Fund Board consisting of:

i) Chairman, Planning and Development Board/Additional Chairperson

Chief Secretary Planning and Development Department.

Page 156: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(ii) such officers of the Provincial Governments not exceeding Members

six as the Provincial Government may appoint, including

Secretaries in charge of the Finance, Industries and

Environment Departments.

(iii) such non-official persons not exceeding ten as the Provincial Members

Government may appoint including representatives of the Provincial

Chamber of Commerce and Industry, non-governmental organizations,

and major donors.

(iv) Director-General of the Provincial Agency. Member/Secretary

(2) In accordance with such procedure and such criteria as may be prescribed, the Board shall

have the power to:

(a) sanction financial assistance for eligible projects;

(b) invest moneys held in the Provincial Sustainable Development Fund in such profit-

bearing Government bonds, savings schemes and securities as it may deem suitable; and

(c) take such measures and exercise such powers as may be necessary for utilization of the

Provincial Sustainable Development Fund for the purposes specified in sub-section (3) of

section 9.

(3) The Board shall constitute committees of its members to undertake regular monitoring of

project financed from the Provincial Sustainable Development Fund and to submit progress

reports to the Board which shall publish an Annual Report incorporating its annual audited

accounts, and performance evaluation based on the progress reports.

11) Prohibition of Certain Discharges or Emissions

(1) Subject to the provisions of this Act and the rules and regulations made thereunder no person

shall discharge or emit or allow the discharge or emission of any effluent or waste or air

pollutant or noise in an amount, concentration or level which is in excess of the National

Environmental Quality Standards or, where applicable, the standards established under sub-

clause (i) of clause (g) of sub-section (1) of section 6.

(2) The Federal Government levy a pollution charge on any person who contravenes or fails to

comply with the provisions

Page 157: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

of sub-section (1), to be calculated at such rate, and collected in accordance with such procedure

as may be prescribed.

(3) Any person who pays the pollution charge levied under sub-section (2) shall not be charged

with an offence with respect to that contravention or failure.

(4) The provisions of sub-section (3) shall not apply to projects which commenced industrial

activity on or after the thirtieth day of June, 1994.

12) Initial Environmental Examination and Environmental Impact

Assessment

(1) No proponent of a project shall commence construction or operation unless he has filed with

the Federal Agency an initial environmental examination or, where the project is likely to cause

an adverse environmental effect, an environmental impact assessment, and has obtained from the

Federal Agency approval in respect thereof.

(2) The Federal Agency shall;

(a) review the initial environmental examination and accord its approval, or require

submission of an environmental impact assessment by the proponent; or

(b) review the environmental impact assessment and accord its approval subject to such

conditions as it may deem fit to impose, or require that the environmental impact assessment

be re-submitted after such modifications as may be stipulated, or reject the project as being

contrary to environmental objectives.

(3) Every review of an environmental impact assessment shall be carried out with public

participation and no information will be disclosed during the course of such public participation

which relates to:

(i) trade, manufacturing or business activities, processes or techniques of a proprietary

nature, or financial, commercial, scientific or technical matters which the proponent has

requested should remain confidential, unless for reasons to be recorded in writing, the

Director-General of the Federal Agency is of the opinion that the request for confidentiality

is not well-founded or the public interest in the disclosure outweighs the possible prejudice to

the competitive position of the project or it's proponent; or

(ii) international relations, national security or maintenance of law and order, except with the

Page 158: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

consent of the Federal Government; or

(iii) matters covered by legal professional privilege.

(4) The Federal Agency shall communicate is approval or otherwise within a period of four

months from the date the initial environmental examination or environmental impact assessment

is filed complete in all respects in accordance with the prescribed procedure, failing which the

initial environmental examination or, as the case may be, the environmental impact

assessment shall be deemed to have been approved, to the extent to which it does not contravene

the provisions of this Act and the rules and regulations made thereunder.

(5) Subject to sub-section (4) the Federal Government may in a particular case extend the

aforementioned period of four months if the nature of the project so warrants.

(6) The provisions of sub-section (1), (2), (3), (4) and (5) shall apply to such categories of

projects and in such manner as may be prescribed.

(7) The Federal Agency shall maintain separate Registers for initial environmental examination

and environmental impact assessment projects, which shall contain brief particulars of each

project and a summary of decisions taken thereon, and which shall contain brief particulars of

each project and a summary of decisions taken thereon, and which shall be open to inspection by

the public at all reasonable hours and the disclosure of information in such Registers shall be

subject to the restrictions specified in sub-section (3).

13) Prohibition of Import of Hazardous Waste

No person shall import hazardous waste into Pakistan and its territorial waters, Exclusive

Economic Zone and historic waters.

14) Handling of Hazardous Substances

Subject to the provisions of this Act, no person shall generate, collect, consign, transport, treat,

dispose of, store, handle or import any hazardous substance except;

(a) under a licence issued by the Federal Agency and in such manner as may be prescribed;

or

(b) in accordance with the provisions of any other law for the time being in force, or of any

Page 159: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

international treaty, convention, protocol, code, standard, agreement or other instrument to

which Pakistan is a party.

15) Regulation of Motor Vehicles

(1) Subject to the provisions of this Act and the rules and regulations made thereunder, no person

shall operate a motor vehicle from which air pollutants or noise are being emitted in an amount,

concentration or level which is in excess of the National Environmental Quality Standards, or

where applicable the standards established under clause (g) of sub-section (1) of section 6.

(2) For ensuring compliance with the standards mentioned in sub-section (1), the Federal Agency

may direct that any motor vehicle or class of vehicles shall install such pollution control devices

or other equipment or use such fuels or undergo such maintenance or testing as may be

prescribed.

(3) Where a direction has been issued by the Federal Agency under sub-section (2) in respect of

any motor vehicles or class of motor vehicles, no person shall operate any such vehicle till such

direction has been complied with.

16) Environmental Protection Order

(1) Where the Federal Agency or a Provincial Agency is satisfied that the discharge or emission

of any effluent, waste, air pollutant or noise, or the disposal of waste, or the handling of

hazardous substances, or any other act or omission is likely to occur, or is occurring or has

occurred in violation of the provisions of this Act, rules or regulations or of the conditions of a

licence, and is likely to cause, or is causing or has caused an adverse environmental effect, the

Federal Agency or, as the case may be, the Provincial Agency may, after giving the person

responsible for such discharge, emission, disposal, handling, act or omission an opportunity of

being heard, by order direct such person to take such measures that the Federal Agency or

Provincial Agency may consider necessary within such period as may be specified in the order.

(2) In particular and without prejudice to the generality of the foregoing power, such measures

may include:

(a) immediate to stoppage, preventing, lessening or controlling the discharge, emission,

disposal, handling, act or omission, or to minimize or remedy the adverse environmental

Page 160: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

effect;

(b) installation, replacement or alteration of any equipment or thing to eliminate or control or

abate on a permanent or temporary basis, such discharge, emission, disposal, handling, act or

omission;

(c) action to remove or otherwise dispose of the effluent, waste, air pollutant, noise, or

hazardous substances; and

(d) action to restore the environment to the condition existing prior to such discharge,

disposal, handling, act or omission, or as close to such condition as may be reasonable in the

circumstances, to the satisfaction of the Federal Agency or Provincial Agency.

(3) Where the person, to whom directions under sub-section (1) are given, does not comply

therewith, the Federal Agency or Provincial Agency may, in addition to the proceeding initiated

against him under this Act or the rules and regulations, itself take or cause to be taken such

measures specified in the order as it may deems necessary, and may recover the costs of taking

such measures from such person as arrears of land revenue.

17) Penalties

(1) Whoever contravenes or fails to comply with the provisions of section 11, 12, 13, or section

16 or any order issued thereunder shall be punishable with fine which may extend to one million

rupees, and in the case of a continuing contravention or failure, with an additional fine which

may extend to one hundred thousand rupees for every day during which such contravention or

failure continues and where such contravention or failure continues: Provided that if

contravention of the provisions of section 11 also constitutes contravention of the provisions of

section 15, such contravention shall be punishable under sub-section (2) only.

(2) Whoever contravenes or fails to comply with the provisions of section 14 or 15 or any rule or

regulation or conditions of any licence, any order or direction issued by the Council or by the

Federal Agency or Provincial Agency shall be punishable with fine which may extend to one

hundred thousand rupees, and in case of continuing contravention, or failure with an additional

fine which extend to one thousand rupees for every day during which such contravention

continues.

(3) Where an accused has been convicted of an offence under sub-section (1) and (2), the

Environmental Tribunal and Environmental Magistrate shall, in passing sentence, take into

Page 161: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

account the extent and duration of the contravention or failure constituting the offence, and the

attendant circumstances.

(4) Where an accused has been convicted of an offence under sub-section (1) and the

Environmental Tribunal is satisfied that as a result of the commission of the offence monetary

benefits have accrued to the offender, the Environmental Tribunal may order the offender to pay,

in addition to the fines under sub-section (1), further additional fine commensurate with the

amount of the monetary benefits.

(5) Where a person convicted under sub-section (1) or sub-section (2), and had been previously

convicted for any contravention under this act, the Environmental Tribunal or, as the case may

be, Environmental Magistrate may, in addition to the punishment awarded thereunder:

(a) endorse a copy of the order of conviction to the concerned trade or industrial association,

if any, or the concerned Provincial Chamber of Commerce and Industry or the Federation of

Pakistan Chambers of Commerce and Industry;

(b) sentence him to imprisonment for a term which may extend upto two years;

(c) order the closure of the factory;

(d) order confiscation of the factory, machinery, and equipment, vehicle, material or

substance, record or document or other object used or involved in contravention of the

provisions of the Act; Provided that for a period of three years from the date of

commencement of this Act the sentence of imprisonment shall be passed only in respect of

persons who have been previously convicted for more than once for any contravention of

sections 11, 13, 14 or 16 involving hazardous waste.

(e) order, such person to restore the environment at his own cost, to the conditions existing

prior to such contravention or as close to such conditions as may be reasonable in the

circumstances to the satisfaction of the Federal Agency or, as the case may be, Provincial

Agency; and

(f) order that such sum be paid to any person as compensation for any loss, bodily injury,

damage to his health or property suffered by such contravention.

(6) The Director-General of the Federal Agency or of a Provincial Agency or an officer generally

or specially authorized by him in this behalf may, on the application of the accused compound an

offence under this Act with the permission of the Environmental Tribunal or Environmental

Magistrate in accordance with such procedure as may be prescribed.

Page 162: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(7) Where the Director-General of the Federal Agency or of a Provincial Agency is of the

opinion that a person has contravened any provision of this Act, he may, subject to the rules, by

notice in writing to that person require him to pay to the Federal Agency or, as the case may be,

Provincial Agency an administrative penalty in the amount set out in the notice for each day the

contravention continues; and a person who pays an administrative penalty for a contravention

shall not be charged under this Act with an offence in respect of such contravention.

(8) The provisions of sub-sections (6) and (7) shall not apply to a person who has been

previously convicted of offence or who has compounded an offence under this Act or who has

paid an administrative penalty for a contravention of any provision of the is Act.

18) Offences by Bodies Corporate

Where any contravention of this Act has been committed by a body corporate, and it is proved

that such offence has been committed with the consent or connivance or, is attributed to any

negligence on the part of, any director, partner, manager, secretary or other officer of the body

corporate, such director, partner, manager, secretary or other officer of the body corporate, shall

be deemed guilty of such contravention along with the body corporate and shall be punished

accordingly:

Provided that in the case of a company as defined under the Companies Ordinance, 1984 (XLVII

of 1984), only the Chief Executive as defined in the said Ordinance shall be liable under this

section.

Explanation:

For the purpose of this section, "body corporate" includes a firm, association of persons and a

society registered under the Societies Registration Act, 1860 (XXI of 1860), or under the Co-

operative Societies Act, 1925 (VII of 1925).

19) Offences by Government Agencies, Local Authorities or Local Councils

Where any contravention of this Act has been committed by any Government Agency, local

authority or local council, and it is proved that such contravention has been committed with the

consent or connivance of, or is attributable to any negligence on the part of the Head or any other

Page 163: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

officer of the Government Agency, local authority or local council, such Head or other officer

shall also be deemed guilty of such contravention alongwith the Government Agency, local

authority or local council and shall be liable to be proceeded against and punished accordingly.

20) Environmental Tribunals

(1) The Federal Government may, by notification in the official Gazette, establish as many

Environmental Tribunals as it considers necessary and, where it establishes more than one

Environmental Tribunal, it shall specify territorial limits within which, or the class of cases in

respect of which, each one of them shall exercise jurisdiction under this Act.

(2) An Environmental Tribunal shall consist of a Chairperson who is, or has been, or is qualified

for appointment as, a Judge of the High Court to be appointed after consultation with the Chief

Justice of the High Court and two members to be appointed by the Federal Government of which

at least one shall be a technical member with suitable professional qualifications and experience

in the environmental field as may be prescribed.

(3) For every sitting of the Environmental Tribunal, the presence of the Chairperson and not less

than one Member shall be necessary.

(4) A decision of an Environmental Tribunal shall be expressed in terms of the opinion of the

majority of its members, including the Chairperson, or if the case has been decided by the

Chairperson and only one of the members and there is a difference of opinion between them, the

decision of the Environmental Tribunal shall be expressed in terms of the opinion of the

chairperson.

(5) An Environmental Tribunal shall not, merely by reason of a change in its composition, or the

absence of any member from any sitting, be bound to recall and rehearany witness who has given

evidence, and may act on the evidence already recorded by, or produced, before it.

(6) An Environmental Tribunal may hold its sittings at such places within its territorial

jurisdiction as the Chairperson may decide.

(7) No act or proceeding of an Environmental Tribunal shall be invalid by reason only of the

existence of a vacancy in, or defect in the constitution of, the Environmental Tribunal.

(8) The terms and conditions of service of the Chairperson and members of the Environmental

Tribunal shall be such as may be prescribed.

Page 164: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

21) Jurisdiction and Powers of Environmental Tribunals

(1) An Environmental Tribunal shall exercise such powers and perform such functions as are, or

may be, conferred upon or assigned to it by or under this Act, or the rules and regulations made

thereunder.

(2) All contravention punishable under sub-section (1) of section 17 shall exclusively be triable

by an Environmental Tribunal.

(3) An Environmental Tribunal shall not take cognizance of any offence triable under sub-

section (2) except on a complaint in writing by:

(a) the Federal Agency or any Government Agency or local council; and

(b) any aggrieved person, who has given notice of not less than thirty days to the Federal

Agency or the Provincial Agency concerned of the alleged contravention and of his intention

to make a complaint to the Environmental Tribunal.

(4) In exercise of its criminal jurisdiction, the Environmental Tribunal shall have the same

powers as are vested in the Court of Session under the Code of Criminal Procedure, 1898 (Act V

of 1898).

(5) In exercise of the appellate jurisdiction under section 22 the Environmental Tribunal shall

have the same powers and shall follow the same procedure as an appellate court in the Code of

Civil Procedure, 1908 (Act V of 1908).

(6) In all matters with respect to which no procedure has been provided for in this Act, the

Environmental Tribunal shall follow the procedure laid down in the Code of Civil Procedure,

1908 (Act V of 1908).

(7) An Environmental Tribunal may, on application filed by any officer duly authorized in this

behalf by the Director-General of the Federal Agency or Provincial Agency, issue bailable

warrant for the arrest of any person against whom reasonable suspicion exists of his having been

involved in contravention punishable under sub-section (1) of section 17:

Provided that such warrant shall be applied for, issued, and executed in accordance with the

provisions of the Code of Criminal

Procedure, 1898 (Act V of 1898):

Provided further that if the person arrested executes a bond with sufficient sureties in accordance

with the endorsement on the warrant, he shall be released from custody, failing which he shall be

taken or sent without delay to the officer-in-charge of the nearest police station.

Page 165: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(8) All proceedings before the Environmental Tribunal shall be deemed to be judicial

proceedings within the meaning of sections 193 and 228 of the Pakistan Penal Code (Act XLV of

1860), and the Environmental Tribunal shall be deemed to be a court for the purposes of sections

480 and 482 of the Code of Criminal Procedure, 1898 (Act V of 1898).

(9) No court other than an Environmental Tribunal shall have or exercise any jurisdiction with

respect to any matter to which the jurisdiction of an Environmental Tribunal extends under this

Act or the rules and regulations made thereunder.

(10) Where the Environmental Tribunal is satisfied that a complaint made to it under sub-section

(3) is false and vexatious to the knowledge of the complainant, it may, by an order, direct the

complainant to pay to the person complained against such compensatory costs which may extend

to one hundred thousand rupees.

22) Appeals to the Environmental Tribunal

(1) Any person aggrieved by any order or direction of the Federal Agency or any Provincial

Agency under any provision of this Act and rules or regulations made thereunder may prefer an

appeal with the Environmental Tribunal within thirty days of the date of communication of the

impugned order or direction to such person.

(2) An appeal to the Environmental Tribunal shall be in such form, contain such particulars and

be accompanied by such fees as may be prescribed.

23) Appeals from Orders of the Environmental Tribunal

(1) Any person aggrieved by any final order or by any sentence of the Environmental Tribunal

passed under this Act may, within thirty days of communication of such order or sentence, prefer

an appeal to the High Court.

(2) An appeal under sub-section (1) shall be heard by a Bench of not less than two Judges.

24) Jurisdiction of Environmental Magistrates

(1) Notwithstanding anything contained in the Code of Criminal Procedure, 1898 (Act V of

1898), or any other law for the time being in force, but subject to the provisions of this Act, all

Page 166: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

contraventions punishable under sub-section (2) of section 17 shall exclusively be triable by a

judicial Magistrate of the first class as Environmental Magistrate especially empowered in this

behalf by the High Court.

(2) An environmental Magistrate shall be competent to impose any punishment specified in sub-

section (2) and (4) of section 17.

(3) An Environmental Magistrate shall not take cognizance of an offence triable under sub-

section (1) except on a complaint in writing by:

(a) the Federal Agency, Provincial Agency, or Government Agency or local council; and

(b) any aggrieved person.

25) Appeals from Orders of Environmental Magistrates

Any person convicted of any contravention of this Act or the rules or regulations by an

Environmental Magistrate may, within thirty days from the date of his conviction, appeal to the

Court of Sessions, whose decision thereon shall be final.

26) Power to Delegate

(1) The Federal Government may, by notification in the official Gazette, delegate any of its or of

the Federal Agency's powers and functions under this Act and the rules and regulations made

thereunder to any Provincial Government, any Government Agency, local council or local

authority.

(2) The Provincial Government may, by notification in the official Gazette, delegate any of its or

of the Provincial Agency's powers or functions under this Act and the rules and regulations made

thereunder to any Government Agency of such Provincial Government or any local council or

local authority in the Province.

27) Power to give Directions

In the performance of their function under this Act:

(a) the Federal Agency and Provincial Agencies shall be bound by the directions give to them

in writing by the Federal Government; and

Page 167: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(b) a Provincial Agency shall be bound by the directions give to it in writing by the

Provincial Government.

28) Indemnity

No suit, prosecution or other legal proceedings shall lie against the Federal or Provincial

Governments, the Councils, the Federal Agency or Provincial Agencies, the Director-Generals of

the Federal Agency and the Provincial Agency, members, officers, employees, experts, advisors,

committees or consultants of the Federal or Provincial Agencies or the Environmental

Tribunal or Environmental Magistrates or any other person for anything which is in good faith

done or intended to be done under this Act or the rules or regulations made thereunder.

29) Dues Recoverable as Arrears of Land Revenues

Any dues recoverable by the Federal Agency or Provincial Agency under this Act, or the rules or

regulations made thereunder shall be recoverable as arrears of land revenue.

30) Act to Override Other Laws

The provisions of the Act shall have effect notwithstanding anything inconsistent therewith

contained in any other law for the time being in force.

31) Power to Make Rules

The Federal Government may, by notification in the official Gazette, make rules for carrying out

the purposes of this Act including rules for implementing the provisions of the international

environmental agreements, specified in the Schedule to this Act.

32) Power to Amend the Schedule

The Federal Government may, by notification in the official Gazette, amend the Schedule so as

to add any entry thereto or modify or omit any entry therein.

33) Power to Make Regulations

Page 168: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(1) For carrying out the purposes of this Act, the Federal Agency may, by notification in the

official Gazette and with the approval of the Federal Government, make regulations not

inconsistent with the provisions of this Act or the rules made thereunder.

(2) In particular and without prejudice to the generality of the foregoing power, such regulations

may provide for:

(a) submission of periodical reports, data or information by any Government agency, local

authority or local council in respect of environmental matters;

(b) preparation of emergency contingency plans for coping with environmental hazards and

pollution caused by accidents, natural disasters and calamities;

(c) appointment of officers, advisors, experts, consultants and employees;

(d) levy of fees, rates and charged in respect of services rendered, actions taken and schemes

implemented;

(e) monitoring and measurement of discharges and emissions;

(f) categorization of projects to which, and the manner in which, section 12 applies;

(g) laying down of guidelines for preparation of initial environmental examination and

environmental impact assessment and Development of procedures for their filing, review and

approval;

(h) providing procedures for handling hazardous substances; and

(i) installation of devices in, use of fuels by, and maintenance and testing of motor vehicles

for control of air and noise pollution.

34) Repeal, Savings and Succession

(1) The Pakistan Environmental Protection Ordinance, 1983 (XXXVII of 1983) is hereby

repealed.

(2) Notwithstanding the repeal of the Pakistan Environmental Protection Ordinance, 1983

(XXVII of 1983), any rules or regulations or appointments made, order passed, notifications

issued, powers delegated, contracts entered into, proceedings commenced, rights acquired,

liabilities incurred, penalties, rates, fees or charges levied, things done or action taken under any

provisions of that Ordinance shall, so far as they are not inconsistent with the provisions of this

Act, be deemed to have been made, passed, issued, delegated, entered into, commenced,

acquired, incurred, levied, done or taken under this Act.

Page 169: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

(2) On the establishment of the Federal Agency and Provincial Agencies under this Act, all

properties, assets and liabilities pertaining to the Federal Agency and Provincial Agencies

established under that Ordinance shall vest in and be the properties,

assets and liabilities, as the case may be, of the Federal Agency and Provincial Agency

established under this Act.

SCHEDULE

(See Section 31)

1. International Plant Protection Convention, Rome, 1951.

2. Plant Protection Agreement for the South-East Asia and Pacific Region (as amended), Rome

1956.

3. Agreement for the Establishment of a Commission for Controlling the Desert Locust in the

Eastern Region of its Distribution Area in South-West Asia (as amended), Rome, 1963.

4. Convention on Wetlands of International Importance Especially as Waterfowl Habitat,

Ramsar, 1971 and its amending Protocol, Paris, 1982.

5. Convention Concerning the Protection of World Cultural and Natural Heritage (World

Heritage Convention), Paris, 1972.

6. Convention on International Trade in Endangered Species of Wild Fauna and Flora (CITES),

Washington, 1973.

7. Convention on the Conservation of Migratory Species of Wild Animals, Bonn, 1979.

8. Convention on the Law of the Sea, Montego Bay, 1982.

9. Vienna Convention for the Protection of the Ozone Layer, Vienna, 1985.

10. Montreal Protocol on Substances that Deplete the Ozone Layer, Montreal, 1987 and

amendments thereto.

11. Agreement on the Network of Aquaculture Centres in Asia and the Pacific, Bangkok, 1988.

12. Convention on the Control of Transboundary Movements of Hazardous Waste and Their

Disposal, Basel, 1989.

13. Convention on Biological Diversity, Rio De Janiero, 1992.

14. United Nations Framework Convention on Climate Change, Rio De Janiero, 1992

Page 170: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 3

Schedule I, II & III of PEPA Regulations, 2000

Page 171: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

“Major Pakistan Environmental Legislation”

Environmental protection

• The Pakistan Penal Code (1860) • Pakistan Environmental Protection Ordinance, No. XXVII

of 1997

Water quality and resources

• The Pakistan Penal Code (1860) • The Factories Act (1934)

Air quality • The Pakistan Penal Code (1860) • The Factories Act (1934)

Toxic or Hazardous Substances

• The Pakistan Penal Code (1860) • The Factories Act (1934)

Solid wastes and effluents

• The Factories Act (1934) • Pakistan Environmental Protection Ordinance, No. XXVII

of 1997

Forest conservation • The Forests Act (1927)

Cultural environment

• The Antiquities Act (1975)

Public health and safety

• The Pakistan Penal Code (1860)

NEQS

Page 172: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

SCHEDULE I

List of projects requiring an IEE A. Agriculture, Livestock and Fisheries 1. Poultry, livestock, stud and fish farms with total cost more than Rs.10 million 2. Projects involving repacking, formulation or warehousing of agricultural Products

B. Energy 1. Hydroelectric power generation less than 50 MW 2. Thermal power generation less than 200 KW 3. Transmission lines less than 11 KV, and large distribution projects 4. Oil and gas transmission systems 5. Oil and gas extraction projects including exploration, production, gathering systems, separation and storage. 6. Waste-to-energy generation projects

C. Manufacturing and processing 1. Ceramics and glass units with total cost more than Rs.50 million 2. Food processing industries including sugar mills, beverages, milk and dairy products, with total cost less than Rs.100 million 3. Man- made fibers and resin projects with total cost less than Rs.100 million 4. Manufacturing of apparel, including dyeing and printing, with total cost more than Rs.25 million 5. Wood products with total cost more than Rs.25 million

D. Mining and mineral processing 1. Commercial extraction of sand, gravel, limestone, clay, sulphur and other minerals not included in Schedule II with total cost less than Rs.100 million 2. Crushing, grinding and separation processes 3. Smelting plants with total cost less than Rs.50 million

E. Transport 1. Federal or Provincial highways (except maintenance, rebuilding or reconstruction of existing metalled roads) with total cost less than Rs.50 million 2. Ports and harbor development for ships less than 500 gross tons

F. Water management, dams, irrigation and flood protection 1. Dams and reservoirs with storage volume less than 50 million cubic meters of surface area less than 8 square kilometers 2. Irrigation and drainage projects serving less than 15,000 hectares 3. Small-scale irrigation systems with total cost less than Rs.50 million

G. Water supply and treatment Water supply schemes and treatment plants with total cost less than Rs.25 million

Page 173: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

H. Waste disposal Waste disposal facility for domestic or industrial wastes, with annual capacity less than 10,000 cubic meters

I. Urban development and tourism 1. Housing schemes 2. Public facilities with significant off-site impacts (e.g. hospital wastes) 3. Urban development projects

J. Other projects Any other project for which filing of an IEE is required by the Federal Agency under sub- regulation (2) of Regulation 5

Page 174: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

4

SCHEDULE II

List of projects requiring an EIA A. Energy 1. Hydroelectric power generation over 50 MW 2. Thermal power generation over 200 MW 3. Transmission lines (11 KV and above) and grid stations 4. Nuclear power plans 5. Petroleum refineries

B. Manufacturing and processing 1. Cement plants 2. Chemicals projects 3. Fertilizer plants 4. Food processing industries including sugar mills, beverages, milk and dairy products, with total cost of Rs.100 million and above 5. Industrial estates (including export processing zones) 6. Man-made fibers and resin projects with total cost of Rs.100 M and above 7. Pesticides (manufacture or formulation) 8. Petrochemicals complex 9. Synthetic resins, plastics and man-made fibers, paper and paperboard, paper pulping, plastic products, textiles (except apparel),printing and publishing, paints and dyes, oils and fats and vegetable ghee projects, with total cost more than Rs.10 million 10. Tanning and leather finishing projects

C. Mining and mineral processing 1. Mining and processing of coal, gold, copper, sulphur and precious stones 2. Mining and processing of major non- ferrous metals, iron and steel rolling 3. Smelting plants with total cost of Rs.50 million and above

D. Transport 1. Airports 2. Federal or Provincial highways or major roads (except maintenance, rebuilding or reconstruction of existing roads) with total cost of Rs.50 million and above 3. Ports and harbor development for ships of 500 gross tons and above 4. Railway works

E. Water management, dams, irrigation and flood protection 1. Dams and reservoirs with storage volume of 50 million cubic meters and above or surface area of 8 square kilometers and above 2. Irrigation and drainage projects serving 15,000 hectares and above

F. Water supply and treatment Water supply schemes and treatment plants with total cost of Rs.25 million and above

Page 175: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

5

G. Waste Disposal 1. Waste disposal and/or storage of hazardous or toxic wastes (including landfill sites, incineration of hospital toxic waste) 2. Waste disposal facilities for domestic or industrial wastes, with annual capacity more than 10,000 cubic meters

H. Urban development and tourism 1. Land use studies and urban plans (large cities) 2. Large-scale tourism development projects with total cost more than Rs.50 million

I. Environmentally Sensitive Areas All projects situated in environmentally sensitive areas

J. Other projects 1. Any other project for which filing of an EIA is required by the Federal Agency under sub-regulation (2) of Regulation 5. 2. Any other project likely to cause an adverse environmental effect

Page 176: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

6

SCHEDULE III

Total Project Cost IEE EIA

Up to Rs.5,000,000 NIL NIL

Rs.5,000,001 to 10,000,000 Rs.10,000Rs.15,000

Greater than Rs.10,000,000 Rs.15,000 Rs.30,000

Page 177: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 4

Revised NEQS, 2000

Page 178: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

REGISTERED No. M-302 L. 7646

The Gazette of Pakistan

EXTRAORDINARY PUBLISHED BY AUTHORITY

===============================================================

ISLAMABD, THURSDAY, AUGUST 10, 2000 ===============================================================

PART-II

Statutory Notification (S.R.O)

GOVERNMENT OF PAKISTAN

MINISTRY OF ENVIRONMENT, LOCAL GOVERNMENT AND RURAL DEVELOPMENT

NOTIFICATION Islamabad,

the 8th August 2000

S.R.O. 549 (I)/2000. In exercise of the powers conferred under clause (c) of sub-section (1) of section of 6 of the Pakistan environmental Protection Act. 1997 (XXXIV of 1997), the Pakistan Environmental Protection Agency, with the prior approval of the Pakistan Environmental Protection Council, is pleased to direct that the following further amendments shall be made in its Notification No. S.R.O. 742(I)/93, dated the 24th August, 1993, namely:

In the aforesaid Notification, in paragraph 2._

(1289)

[4138(2000)/Ex.GAZ]

Price : Rs. 5.00

Page 179: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1290 THE GAZETTE OF PAKISTAN, EXTRA, AUGUST 10, 2000 [PART-II] =============================================================== (1) for Annex, I the following shall be substituted, namely:

Annex-I

“NATIONAL ENVIRONMENTAL QUALITY STANDARDS FOR MUNICIPAL AND

LIQUID INDUSTRIAL EFFLUENTS (mg/I, UNLESS OTHERWISE DEFINED)

S. No.

Parameter

Existing

Revised Standards

Into

Into

Into Standards Inland

Waters Sewage

Treatment (5) Sea ( )

1

2 3 4 5

6

1.

Temperature or 400C ≤3oC ≤3oC

≤3oC

2. Temperature Increase * pH value (H+) . 6-10 6-9 6-9

6-9

3. Biochemical Oxygen Demand (BOD)5 at 200C (1) 80 80 250

80**

4. Chemical Oxygen Demand(COD) (1) .. .. .. 150 150 400

400

5. Total Suspended Solids (TSS) .. .. .. 150 200 400 200

6. Total Dissolved Solids 3500 3500 3500 3500 (TDS)

7. Oil and Grease 10 10 10 108. Phenolic compounds (as

phenol) 0.1 0.1 0.3 0.39. Chloride (as C1– ) 1000 1000 1000 SC***

10.

Fluoride (as F– ) 20 10 10

1011. Cyanide (as CN–) total .. 2 1.0 1.0 1.012.

13.

An-ionic detergents (as MBAS) (2)

Sulphate (SO42–)

20

600

20

600

20

1000

20

SC***14. Sulphide (S2–) 1.0 1.0 1.0 1.015. Ammonia (NH3) 40 40 40 4016. Pesticides (3) 0.15 0.15 0.15 0.15

Page 180: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

PART-II] THE GAZETTE OF PAKISTAN, EXTRA, AUGUST 10, 2000 1291 ===============================================================

1 2 3 4 5 6

17. Cadmium (4) .. .. 0.1 0.1 0.1

0.118. 19.

Chromium (trivalent and hexavalent (4).. .. Cooper (4) .. ..

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.020. Lead (4) .. .. 0.5 0.5 0.5 0.521. Mercury (4) .. .. 0.01 0.01 0.01 0.0122. Selenium (4) 0.5 0.5 0.5 0.523. Nickel (4) .. .. 1.0 1.0 1.0 1.024. Silver (4) 1.0 1.0 1.0 1.025. Total toxic metals .. .. 2.0 2.0 2.0 2.026. Zinc .. .. .. 5.0 5.0 5.0 5.027. Arsenic (4) .. .. 1.0 1.0 1.0 1.028. Barium (4) .. .. 1.5 1.5 1.5 1.529. Iron .. .. .. 2.0 8.0 8.0 8.030. Manganese .. .. 1.5 1.5 1.5 1.531. Boron (4) .. .. 6.0 6.0 6.0 6.032. Chlorine .. .. .. 1.0 1.0 1.0 1.0

Explanations:

1. Assuming minimum dilution 1:10 on discharge, lower ratio would attract

progressively stringent standards to be determined by the Federal Environmental Protection Agency. By 1:10 dilution means, for example that for each one cubic meter of treated effluent, the recipient water body should have 10 cubic meter of water for dilution of this effluent.

2. Methylene Blue Active Substances; assuming surfactant as biodegradable.

3. Pesticides include herbicides, fungicides, and insecticides.

4. Subject to total toxic metals discharge should not exceed level given at S. N. 25.

5. Applicable only when and where sewage treatment is operational and BOD5=80mg/I

is achieved by the sewage treatment system.

Page 181: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

PART-II] THE GAZETTE OF PAKISTAN, EXTRA, AUGUST 10, 2000 1292 ===============================================================

6. Provided discharge is not at shore and not within 10 miles of mangrove or other

important estuaries.

* The effluent should not result in temperature increase of more than 30C at the edge of the zone where initial mixing and dilution take place in the receiving body. In case zone is not defined, use 100 meters from the point of discharge.

** The value for industry is 200 mg/I

*** Discharge concentration at or below sea concentration (SC).

Note: 1. Dilution of liquid effluents to bring them to the NEQS limiting values is

not permissible through fresh water mixing with the effluent before discharging into the environment.

2. The concentration of pollutants in water being used will be substracted

from the effluent for calculating the NEQS limits” and

(2) for Annex-II the following shall be substituted, namely:

Annex-II

“NATIONAL ENVIRONMENTAL QUALITY STANDARDS FOR INDUSTRIAL GASEOUS EMISSION (mg/Nm3, UNLESS

OTHERWISE DEFINED).”

S. No. Parameter Source of Emission Existing Standards

Revised Standards

1 2 3 4 5 1. Smoke Smoke opacity not to

exceed 40% or 2 Ringlemann Scale

40% or 2 Ringlemann Scale or equivalent smoke number

2. Particulate malter (a) Boilers and Furnaces

(1) (i) Oil fired 300 300 (ii) Coal fired 500 500 (iii) Cement Kilns 200 300

(b) Grinding, crushing, Clinker coolers and Related processes, Metallurgical Processes, converter, blast furnaces and cupolas.

500

500

3. Hydrogen

Chloride Any 400 400

Page 182: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

PART-II] THE GAZETTE OF PAKISTAN, EXTRA, AUGUST 10, 2000 1293 ===============================================================

1 2 3 4 5

4. Chlorine Any 150 150 5. Hydrogen Fluoride Any 150 150 6. Hydrogen Sulphide Any 10 10 7. Sulphur Oxides (2) (3) Sulfuric

acid/Sulphonic acid plants

Other Plants except power Plants operating on oil and coal

400 1700

8. Carbon Monoxide Any 800 800 9. Lead Any 50 50

10. Mercury Any 10 10 11. Cadmium Any 20 20 12. Arsenic Any 20 20 13. Copper Any 50 50 14. Antimony Any 20 20 15. Zinc Any 200 200 16. Oxides of Nitrogen

(3)

Nitric acid manufacturing

unit.

Other plants except power

plants operating on oil or coal:

Gas fired Oil fired

Coal fired

400 400

- -

3000 400 600

1200 Explanations:-

1. Based on the assumption that the size of the particulate is 10 micron

or more.

2. Based on 1 percent Sulphur content in fuel oil. Higher content of Sulphur will case standards to be pro-rated.

3. In respect of emissions of Sulphur dioxide and Nitrogen oxides, the

power plants operating on oil and coal as fuel shall in addition to National Environmental Quality Standards (NEQS) specified above, comply with the following standards:-

Page 183: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1294 THE GAZETTE OF PAKISTAN, EXTRA, AUGUST 10, 2000 PART-II] =============================================================== A. Sulphur Dioxide

Sulphur Dioxide Background levels Micro-gram per cubic meter (ug/m3) Standards.

Background Air Quality (SO2

Basis)

Annual Average

Max. 24-hours Interval

Criterion I Max. SO2

Emission (Tons per Day Per Plant)

Criterion II Max. Allowable ground level increment to ambient (ug/m3)

(One year Average)

Unpolluted Moderately Polluted*

<50 <200 500 50

Low 50 200 500 50 High 100 400 100 10 Very Polluted** >100 >400 100 10

* For intermediate values between 50 and 100 ug/m3 linear interpolations should be used.

** No projects with Sulphur dioxide emissions will be recommended.

B. Nitrogen Oxide

Ambient air concentrations of Nitrogen oxides, expressed as NOx should not be exceed

the following:-

Annual Arithmetic Mean 100ug/m3

(0.05 ppm)

Emission level for stationary source discharge before missing with the atmosphere, should be maintained as follows:-

For fuel fired steam generators as Nanogram (100-gram) per joule of heat input:

Liquid fossil fuel .. .. .. 130Solid fossil fuel .. .. .. 300Lignite fossil fuel .. .. .. 260

Note:- Dilution of gaseous emissions to bring them to the NEQS limiting value is not permissible through excess air mixing blowing before emitting into the environment.

[File No. 14(3)/98-TO-PEPC.]

HAFIZ ABDULAH AWAN

DEPUTY SECRETARY (ADMN)

PRINTED BY THE MANAGER, PRINTING CORPORATION OF PAKISTAN, PRESS

ISLAMABAD. PUBLISHED BY THE MANAGER OF PUBLICATIONS, KARACHI.

Page 184: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 5

Factories Act, 1934 Relevant Applicable Laws

Page 185: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

CHAPTER III “HEALTH AND SAFETY”

# SECTION FACTORIES ACT 1934 REQUIREMENT

1 13. Cleanliness Every factory shall be kept clean and free from effluvia arising from drain, privy or other nuisance, and

in particular: (See details in Factories Act 1934)

2

14. Disposal of Wastes and Effluents

Effective arrangements shall be made in every factory for the disposal of wastes and effluents due to the manufacturing process carried on therein. (See details in Factories Act 1934)

3

15. Ventilation and Temperature Effective and suitable provisions shall be made in every factory for securing and maintaining in every work room. (See details in Factories Act 1934)

4

16. Dust and Fume (1) In every factory in which, by reason of the manufacturing process carried on, there is given off any dust or fume or other impurity of such a nature and to such an extent as is likely to be injurious or offensive to the workers employed therein, effective measures shall be taken to prevent its accumulation in any work-room and its inhalation by workers and if any exhaust appliance is necessary for this purpose, it shall be applied as near as possible to the point of origin of the dust, fume or other impurity, and such point shall be enclosed so far as possible.

(2) In any factory no stationary internal combustion engine shall be operated unless the exhaust is

conducted into open air and exhaust pipes are insulated to prevent scalding and radiation heat, and no internal combustion engine shall be operated in any room unless effective measures have been taken to prevent such accumulation of fumes there from as are likely to be injurious to the workers employed in the work-room.

5

19. Lighting In every part of a factory where workers are working or passing, there shall be provided and maintained: a) sufficient and suitable lighting, natural or artificial, or both and b) emergency lighting of special points in work room and passages to function automatically in case of

failure of ordinary electric supply system (See details in Factories Act 1934)

6

20. Drinking Water (1) In every factory effective arrangements shall be made to provide and maintain at suitable points conveniently situated for all workers employed therein a sufficient supply of wholesome drinking water.

Page 186: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

(2) All such points shall be legibly marked “Drinking Water” in a language understood by majority of workers and no such points shall be situated within twenty feet of any washing place, urinals or latrine.

(3) In every factory wherein more than 250 workers are ordinarily employed, provision shall be made for cooling the drinking water during the hot weather by effective means and for distribution thereof and arrangements shall also be made for: (a) the daily renewal of water if not laid on; and (b) a sufficient number of cups or other drinking vessels, unless the water is being delivered in an upward jet.

(4) The Provincial Government may, in respect of all factories or any class or description of factories, make riles for securing compliance with provisions of this section.

7

21. Latrines and Urinals (1) In every factory:

a) sufficient latrines and urinals of prescribed types shall be provided conveniently situated and accessible to workers at all times while they are in factory;

b) enclosed latrines and urinals shall be provided for male and female workers;

c) such latrines and urinals shall be adequately lighted and ventilated and no latrine and urinal shall, unless specially exempted in writing by the Chief Inspector, communicate with any work-room except through and intervening open space or ventilated passage;

d) all such latrines and urinals shall be maintained in a clean and sanitary condition at all times

with suitable detergents or disinfectants or with both;

e) the floors and internal walls of the latrines and urinals and the sanitary block shall, upto a height of 3 feet, be finished to provide a smooth polished impervious surface;

f) washing facilities shall be provided near every sanitary convenience.

(2) The Provincial Government may prescribe the number of latrines and urinals to be provided in any

factory in proportion to the number of male and female workers ordinarily employed therein and such further matters in respect of sanitation in the factories as it may deem fit.

Page 187: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

8

22. Spittoons (1) In every factory there shall be provided at convenient places, a sufficient number of spittoons which shall be maintained in a clean and hygienic condition.

(2) The provincial government may make the rules prescribing the type and the number of spittoons to be

provided and their location in any factory and such further matters as may be deemed necessary relating to their maintenance in a clean and hygienic condition.

(3) No person shall spit within the premises of a factory except in the spittoon provided for the purpose.

A notice containing this provision and the penalty for its violation shall be prominently displayed at suitable places in the premises.

(4) Whosoever spits in contravention of sub-section (3) shall be punishable with a fine not exceeding

two rupees.

9

23. Precaution against contagious disease

(1) Each worker in a factory be provided with a ‘Hygiene Card’ in which (during the month of January and July every year entries) shall be recorded after examination by appointed factory doctor to the effect that the worker is not suffering from any contagious or infectious disease. The fee of such an examination shall be fixed by the Provincial Government and will be borne by the occupier or manager of the factory.

(2) If a worker Is found to be suffering from any contagious or infectious disease on an examination

under sub section (1), he shall not be appointed on work till he is declared free of such a disease.

10 23(A) Compulsory vaccination and inoculation

Each worker in a factory shall be vaccinated and inoculated against such disease and at such intervals as may be prescribed. The expenses, if any, of such vaccination and inoculation shall be borne by the occupier or manager of the factory.

11

24 Power to make rules for the provision of canteen

(1) The provincial government may rules requiring that in any specified factory wherein more than hundred and fifty workers are ordinarily employed, an adequate canteen shall be provided for the use of the workers.

(2) Without prejudice to the generality of the following power, such rules may provide for:

(a) the date by which such canteen shall be provided; (b) the standards in respect of construction, accommodation, furniture and other equipment of the

canteen; (c) the foodstuff to be served therein and the charges which may be made thereof; (d) representative of the workmen in the management of the canteen; (e) enabling, subject to such conditions, if any, as may be specified, the power to make rules under

clause (c) to be exercised also by the Chief Inspector.

Page 188: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

4

12

25 Precautions in case of fire (1) Every factory shall be provided with such means of escape in case of fire as may be prescribed. (2) If it appear to the Inspector that any factory is not provided with the means prescribed under sub-

section (1), he may serve on the manager of the factory an order in writing specifying the measure which, in his opinion, should be adopted before a date specified in the order.

(3) In every factory the doors affording exist from any room shall not be locked or fastened so that they

can be easily and immediately opened from inside type while any person is within the room, and all such doors, unless they are of the sliding type, shall be constructed to open outwards or where the doors is between two rooms, in the direction of the nearest exit from the building and such door shall not be locked or obstructed while work is being carried out in the room and shall at all times be kept free from any obstruction.

(4) In every factory every window, door, or other exit affording means of escape in case of fire, other

than means of exit in ordinary use, shall be distinctively marked in a language understood by the majority of the workers and in red letters of adequate size or by some other effective and clearly understood sign.

(5) In every factory there shall be provided effective and clearly audible means of giving warning in case

of fire to every person employed therein. (6) A free passage-way giving access to each means of escape in case of fire shall be maintained for the

use of all workers in every room of the factory. (7) In every factory wherein more than ten workers are ordinarily employed in any place above the

ground floor, or explosive or highly inflammable materials are used or stored, effective measures shall be taken to ensure that all the workers are familiar with the means of escape in case of fire and have been adequately trained in the routine to be followed in such case.

(8) The Provincial Government may make rules prescribing in respect of any factor, or class or

describing of factories, the means of escape to be provided in case of fire and the nature and amount of fire-fighting apparatus to be provided and maintained.

13

26 Fencing of machinery (1) In every factory the following shall be securely fenced by the safeguards of substantial construction which shall be kept in position while the parts of machinery required to be fenced are in motion or in use, namely-

Page 189: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

5

(a) every motor part of a prime mover, and every fly wheel connected to a prime mover; (b) The handrace and tailrace of every water wheel and water turbine; (c) any part of a stock-bar which projects beyond the head stock of a lathe; and (d) unless they are in such position or of such construction as to be safe to every person employed

in the factory as they would be if they were securely fenced: (i) every part of an electric generator, a motor or rotary converter; (ii) every part of transmission machinery; and (iii) every dangerous part of any machinery:

Provided that, in the case of dangerous parts of machinery that cannot be securely fenced by reason of the nature of operation, such fencing ay be substituted by other adequate measures, such as:

(i) device automatically preventing the operation from coming into contact with the dangerous

parts; and (ii) automatic stopping devices;

(See details in Factories Act-1934)

14

27 Work on or near machinery in motion

(1) Where in any factory necessary to examine any part of machinery referred to in section 26 while the machinery is in motion, or as a result of such examination, to carry out any mounting or shipping of belts, lubrication or other adjusting operation while the machinery is in motion, such examination or operation shall be made or carried out only by a specially trained adult male worker wearing right fitting clothing whose name has been recoded in the register prescribed in this behalf and while he is so engaged, such workers shall not handle a belt at a moving pulley unless the belt is less than six inches in width and unless the belt joint is either laced or flush with the belt.

(2) No women or child shall be allowed in any factory to clean, lubricate or adjust ant part of machinery

while that part is in motion, or to work between moving parts or between fixed and moving parts of any machinery which is in motion.

(3) The Provincial Government may, by notification in the official Gazette prohibit, in any specified

factory or class or description of factories, the cleaning, lubricating or adjusting by any person, of specified parts of machinery when those parts are in motion.

15

29. Striking gear and devices for cutting off power

(1) In every factory:

(a) suitable striking gear or other efficient mechanical appliance shall be provided and maintained and used to move driving parts of the transmissions machinery, and such gear or appliance shall

Page 190: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

6

be so constructed, placed and maintained as to prevent the belt from creping back on the fast pulleys;

(b) driving belts when not in use shall be allowed to rest or ride upon shafting in motion.

(1) In every factory suitable devices for cutting off power in emergency from running machinery shall be

provided and maintained in every work-room.

(Please see details in Factories Act- 1934)

16

31. Casing of new machinery (1) In all machinery driven by power and installed in any factory after the commencement! of the Labour Laws (Amendment) Ordinance, 1972-

(a) every set screw, belt or key on any revolving shaft, spindle, wheel or pinion shall be so sunk,

encased or otherwise effectively guarded as to prevent danger; and

(b) all spur, worm and other toothed or friction gearing which does not require frequent adjustment while in motion shall be completely encased unless it is so situated as to be as safe as it would be if it were completely encased.

(2) Whoever sell, or lets on hire or, as agent of a seller or hirer, causes or procures to be sold or let on

hire, for use in a factory any machinery driven by power which does not comply with the provisions of sub-section (1), shall be punishable with imprisonment, for a term which may extend to three months, or with fine which may extend to five hundred rupees, or with both.

(3) The Provincial Government may make rules specifying further safeguards to be provided in respect

of any other dangerous part of any particular machine or class or description of machines.

17

33. Cranes and other lifting machinery

(1) The following provisions shall apply in respect of cranes and all other lifting machinery, other than hoists and lifts in any factory :-

(a) every part thereof, including the working gear, whether fixed or moveable ropes and chains and

anchoring and fixing appliances shall be -

(i) of good construction, sound material and adequate strength; (ii) properly maintained; (iii) thoroughly examined by a competent person at least once in every period of twelve months,

and a register shall be kept containing the prescribed particulars of every such examination;

Page 191: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

7

(b) no such machinery shall be loaded beyond the safe working load which shall be plainly marked

thereon;

(c) while any person is employed or working on or near the wheel tract of a travelling crane in any place where he would be liable to be struck by the crane, effective measures shall be taken to ensure that the crane does not approach within twenty feet of that place or come into accidental contact with live electrical lines;

(d) limit switches shall be provided to prevent over-running; and

(e) jib cranes, permitting the raising or lowering of the jib shall be provided with an automatic safe

load indicator or have attached to them a table indicating the safe working load at corresponding inclinations of the jib.

(2) The Provincial Government may make rules in respect of any lifting machinery or class or

description of lifting machinery in factories:

(a) prescribing requirements to be complied with in addition to those set out in this section; or

(b) exempting from compliance with all or any of the requirements of this section, where in its opinion such compliance is unnecessary or impracticable.

18

33-A. Hoist and lifts (1) In every factory -

(a) every hoist and lift shall be -

(i) of good mechanical construction, sound material and adequate strength;

(ii) properly maintained, and shall be thoroughly examined by a competent person authorised by the Chief Inspector in this behalf at least once in every period of six months, and a register shall be kept containing the prescribed particulars of every such examination of which a copy shall be forwarded to the Chief Inspector;

(b) every hoistway and liftway shall be sufficiently protected by an enclosure fitted with gates, and

the hoist or lift and every such enclosure Shall be so constructed as to prevent any person or thing from being trapped between any part of the hoist or lift and any fixed structure or moving part;

Page 192: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

8

(c) the maximum safe working load shall be plainly marked on every hoist or lift, and no loadgreater than such load shall be carried thereon;

(d) the cage of every hoist or lift used for carrying persons shall be fitted with a gate on each side

from which access is afforded to a landing;

(e) every gate referred to in clause (b) or clause (d) shall be fitted with interlocking or other efficient device to secure that the gate cannot be opened except when the cage is at the landing and that the cage cannot be moved unless the gate is closed.

(2) The following additional requirements shall apply to hoist and lift used for carrying persons and

installed or reconstructed in a factory after the commencement of the Labour Laws (Amendment) Ordinance, 1972 namely :-

(a) where the cage is supported by rope or chain there shall be at least two ropes or chains

separately connected with the cage and balance weight, and each rope or chain with its attachments shall be capable of carrying the whole weight of the cage together with its maximum load;

(b) efficient devices shall be provided and maintained capable of supporting the cage together with

its maximum load in the event of breakage of the ropes, chains or attachments;

(c) an efficient automatic device shall be provided and maintained to prevent the cage from over- running.

(3) The Chief Inspector may permit the continued use of a hoist or lift installed in a factory before the

commencement of this Ordinance which does not fully comply with the provisions of sub-section (1) upon such conditions for ensuring safety as he may think fit to impose.

(4) The Provincial Government may, if, in respect of class or description of hoist or lift, it is of opinion

that j requirement of sub-sections (1) and (2) by order direct that such requirements shall not apply to such class or description of hoist or lift.

19

33-C Pressure plant (1) If in any factory any part of the plant or machinery used in a manufacturing process is operated above atmospheric pressure, effective measures pressure of such part is not exceeded.

(Please see details in Factories Act-1934)

Page 193: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

9

20

33-D Floors, stairs and means of access

In every factory- (a) all floors, stairs, passages and gangways shall be of sound construction and properly maintained and

where it is necessary to ensure safety, steps, stairs, ladders, passages and gangways shall be provided with substantial handrails;

(b) there shall, so far as is reasonably practicable be provided and maintained safe means of access to

every place at which any person is at any time required to work; (c) all places of work from which a worker may be liable to fall a distance exceeding three feet and six

inches shall be pro- vided with fencing or other suitable safeguards; and (d) adequate provision shall be made for the drainage of floors in wet processes and for the use of

slatted stands and platforms.

21

33-E. Pits, sumps, opening in floors, etc.

(1) In every factory, every fixed vessel, sump, tank pit or opening in the ground or in floor which by reason of its depth, situation, construction or contents, is o may be a source of danger, shall be either securely covered or securely fenced.

(2) The provincial Government may, by order in writing, exempt, subject to such conditions as may be

imposed, any factory or class or description of factories in respect of any vessel, sump, tank pit or opening from compliance with the provisions of this section.

22

33-F. Excessive weights (1) No person shall be employed in any factory to lift carry or move any load so heavy as to be likely to cause him injury.

(2) The Provincial Government may make rules prescribing the maximum weights which ma be lifted,

carried or moved by adult men, adult women, adolescents and children employed in factories or in any class or description of factories or in carrying on any specified process.

23

33-G. Protection of eyes The Provincial Government may, in respect of any manufacturing process carried on in any factory, by rules require that effective screens or suitable goggles shall be provided for the protection of persons employed on, or in the immediate vicinity of, a process which involves

(a) risks of injury to the eyes from particles or fragments thrown off in the course of the process, or

(b) risk to the eyes by reason of exposure to excessive light or heat.

24 33-H. Power to require If it appears to the Inspector that any building or part of a building, or any part of the ways, machinery or

Page 194: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

10

specifications of defective parts or tests of stability

plant in a factory, is in such a condition that it may be dangerous to human life or safety, he may serve onthe Manager of the factory an order in writing, requiring him before a specified date -

(a) to furnish such drawings, specifications and other particulars as may be necessary to determine

whether such building ways, machinery or plant can be used with safety, or (b) to carry out such tests as may be necessary to determine the srel1gth or quality of any specified parts

and to inform the Inspector of the results thereof.

25

33-1. Safety of building, machinery and manufacturing process.

(1) If it appears to the Inspector that any building or part of a building or any part of the way, machinery or plant or manufacturing process in a factory is in such a condition that it is dangerous to human health or safety, he may serve on the Manager of the factory an order in writing specifying the measures which, in his opinion

(2) If it appears to the Chief Inspector that the requisitions made under sub-section (1) are not

satisfactorily fulfilled thereby involving exposure of workers to serious hazards, he may serve on the Manager of the factory an order in writing, containing a statement of the grounds of his opinion, prohibiting until the dangers is removed, the employment, in or about the factory or part thereof, of any person whose employment is not in his opinion reasonably necessary for the purpose of removing the danger.

(3) It is appears to the Inspector that the use of building or part of a building or of any part of the ways,

machinery or plant or manufacturing process in a factory involves imminent danger to human health or safety he may serve on the Manager of factory an order in writing prohibiting, until the danger is removed, the employment =, in or about the factory or part thereof, of any person whose employment is not in his opinion reasonably necessary for the purpose of removing the danger.

(4) Nothing in sub-section (2) or (3) shall be deemed to affect the continuance in the employment of the

factory of person whose employment in or about the factory or part thereof is prohibited under that sub-section.

26

33-K. Precautions against dangerous fumes

(1) In any factory no person shall enter or be permitted to any chamber, tan, pit, pipe, flue or other confined space in which dangerous fumes are likely to be present to such an extent as to involve risk of persons being overcome thereby, unless it is provided with a manhole of adequate size or other effective means of ingress.

(2) No portable electric light of voltage exceeding twenty-four volts to be inflammable, a lamp or light

other than of flame proof construction shall not be permitted to be used in such confined space as is

Page 195: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

11

referred to in sub-section (1) and where the fumes present are likely to be inflammable a lamp or light other than of flame proof construction shall not be permitted to be used in such confined space.

(3) No person in any factory shall enter or be permitted to enter any confined space such as is referred to

in sub-section (1) until all practicable measures have been taken to remove any fumes which may be present and to pre- vent ingress of fumes and unless either –

(a) a certificate in writing has been given by a competent per- son, based on a test carried out by

himself, that the space is free from dangerous fumes and fit for persons to enter, or

(b) the worker is wearing suitable breathing apparatus and a belt securely attached to a rope, the free end of which is held by a person standing outside the confined space.

(4) Suitable breathing apparatus, reviving apparatus and belts and ropes shall in every factory be kept

ready for instant use beside any such confined space as aforesaid which any person has entered, and all such apparatus shall be periodically examined and certified by a competent person to be fit for use; and a sufficient number of persons employed in every factory shall be trained and practiced in the use of all such apparatus and in the method of restoring respiration.

(5) No person shall be permitted to enter in any factory, any boiler furnace, boiler flue, chamber, tank,

vat, pipe or other confined space for the purpose of working or making any examination therein until it has been sufficient cooled by ventilation or otherwise to be safe for persons to enter.

(6) The Provincial Government may make rules prescribing the maximum dimensions of the manholes

referred to in sub-section (1) and may, by order in writing, exempt, subject to such conditions as it may think fit to impose, any factory or class or description of factories from compliance with any of the provisions of this section.

27

33-L. Explosive or inflammable dust, gas, etc.

(1) Where in any factory any manufacturing process produces dust, gas, fume or vapour of such character and to such extent as to be likely to explode an ignition, all practicable measures shall be taken to prevent. any such explosion by -

(a) effective enclosure of the plant or machinery used in the process;

(b) removal or prevention of the accumulation ofsucl1 dust, gas, fume or vapour;

Page 196: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

12

(c) exclusion or effective enclosure of all possible sources of ignition

(2) Where in any factory the plant or machinery used in a process such. (1) is not so constructed as to

withstand the an explosion as aforesaid would produce, all practicable measures shall be taken to restrict the spread and effects of the explosion by the provision in the plant or machinery of chokes, baffles, vents or other effective appliances.

(3) Where any part of the plant or machinery in a factory contains any explosive or inflammable gas or

vapour pressure greater than atmospheric pressure, that part shall be opened except in accordance with the following provisions, namely:

(a) before the fastening of any joint of any pipe connected with the part of the fastening of the

cover of any opening into the part is loosened, any flow of the gas or vapour into the part or any such pipe shall be effectively stopped by a stop-valve or other means;

(b) before any such fastening as aforesaid is removed all practicable measures shall be taken to

reduce the pressure of the gas or vapour in the part or pipe to atmospheric pressure;

(c) where any such fastening as aforesaid has been loosened or removed, effective measures shall be taken to prevent any explosive or inflammable gas or vapour from entering the part or pipe until the fastening has been secured, or, as the case may be, securely replaced:

28

33-N Notice of certain accidents Where in any factory an accident occurs which causes death, or which causes any bodily injury whereby any person injured is prevented from resuming his work in the factory during the forty-eight hours after the accident occurred, or which is of any nature which may be prescribed in this behalf, the manager of the factory shall send notice thereof to such authorities, and in such form and within such time, as may b prescribed.

29

33-Q Additional power to make health and safety rules relating to shelters during rest

The Provincial Government may make rules requiring that in any specified factory wherein more than one hundred and fifty workers are ordinarily employed, an adequate shelter shall be provided for the use of workers during period o rest, and such rules may prescribe the standards of such shelters.

(Please see details in Factories Act-1934)

Page 197: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 6

NEPRA Licensing Regulations

Page 198: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

EXTRAORDINARY PUBLISHED BY AUTHORITY ISLAMABAD, WEDNESDAY,

JULY 9,2008 PART II

Statutory Notifications (S. R. 0.) GOVERNMENT OF PAKISTAN

NATIONAL ELECTRIC POWER REGULATORY AUTHORITY NOTIFICATION

Islamabad, the 2nd July, 2008

S. R. O. 737(1)/2008:-ln exercise of power conferred by Section 47 of the Regulations of Generation, Transmission and Distribution of Electric Power Act, 1997 (XL of 1997), the National Electric Power Regulatory Authority is please to approve the following additions in NEPRA Licensing (Application & Modification Procedure) Regulations, 1999, notified vide S .R .0. 142(1)/99 dated 1st March, 1999. Other contents of the S. R. O. 142 (1)/99 will remain un-changed.

1. Regulation 2 (1) (k) be added as under:

"Captive Power Plant" means Industrial undertakings or other businesses carrying out the activity of power production for self consumption, who intend to sell the power, surplus to their requirement, to a Distribution Company or bulk power consumer."

2. Regulation 3 (5)-A be added before Regulation 3 (6) as under:

(5)-A the- following documents-in-support shall be filed alongwith an application for a licence by a Captive Power Plant:

(i) Certificate of Incorporation of applicant; (ii) Memorandum of Articles of Association of applicant; (iii) Latest financial statement of the applicant; (iv) Location (Location map, site map); (v) Type of Technogy (vi) Number of units (No.)/Size (MW); ( vii) Year Make/Model. Operation date and expected remaining life;

Installed capacity, de-rated capacity, Auxiliary Consumption, Net Capacity;

(ix) Fuel (Oil/Gas): type, imported/indigenous, supplier, logistics, pipeline etc. In case of Gas fuel, a Gas Sale Agreement (GSA) signed between the applicant and Gas Supplier;

(x) Supply voltage (11 KV/132 KV), in case of 132 KV voltage distance and name of nearest grid (Single line diagram);

(xi) Plant characteristics: generation voltage, frequency, power factor, automatic generation control, ramping rate, alternative fuel, time(s) required to synchronize to grid;

(xii) Provision of Metering, Instrumentation, Protection and Control arrangement.

MAHJOOB AHMAD MIRZA,

.' Registrar.

Page 199: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

NATIONAL ELECTRIC POWER REGULATORY AUTHORITY

Licensing (Application & Modification Procedure) Regulations

EXTRAORDINARY

PUBLISHED BY AUTHORITY

ISLAMABAD, FRIDAY, MARCH 5, 1999

PART II

Statutory Notifications (S.R.O.)

GOVERNMENT OF PAKISTAN

NOTIFICATION

Islamabad, the 1st March, 1999

S.R.O. 142 (I)/99.— ln exercise of the powers conferred by section 47 of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 (XL of 1997), the National Electric Power Regulatory Authority hereby notifies the following regulations, namely:—

1. Title and commencement.—

PART I

(1) These regulations may be called the National Electric Power Regulatory Authority Licensing (Application & Modification Procedure) Regulations, 1999.

(2) They shall come into force at once.

Page 200: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

2. Definitions.—

(1) In these rules, unless there is anything repugnant in the subject or context, —

(a) "Act" means the Regulation of Generation, Transmission and

Distribution of Electric Power Act, 1997 (XL of 1997);

(b) "application" means an application made by a person in accordance with the provisions of these regulations and shall, where the context so admits, include the documents-in-support, and "applicant" shall be construed accordingly;

(c) "Authority proposed modification" means a modification to a licence

proposed by the Authority;

(d) "documents-in-support" means the documents to be provided with the application for the licence or subsequently, in accordance with regulation 3;

(e) "information" includes documents, accounts, reports, records, data,

returns or estimates of any description;

(f) "licensee proposed modifications" means a modification to the licence proposed by the licensee;

(g) "NEPRA (Fees and Penalties) Rules" means the rules developed

by the Authority in respect of the payment of fees by the licensees and the procedure for imposition and payment of fines and penalties levied by the Authority;

(h) "Ordinance" means the Companies Ordinance, 1984;

(i) "prospectus" means a report prepared by the applicant setting out:

(i) a brief introduction of the applicant;

(ii) the salient features of the facility or the system in respect of which the licence is sought;

(iii) the proposed investment; and

(iv) the social and environmental impact of the proposed facility

or system in a non-technical and commonly understood language; and

(j) "Registrar" means the officer of the Authority appointed to perform

the functions of the Registrar laid down in these regulations.

(2) Words and expressions used but not defined in these regulations shall have the same meaning as in the Act.

Page 201: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

3. Application for licence.—

PART II

(1) An application for a licence shall be made in the form specified in Schedule I to these regulations.

(2) The applicant shall pay a non-refundable application fee to the

Authority for the consideration and processing of the application, calculated in accordance with Schedule II to these regulations.

(3) The registrar shall not receive the application unless it is accompanied

with the correct amount of application fee.

(4) The application for a licence shall be submitted in triplicate.

(5) The following documents-in-support shall be filed along with the application for a license:

(a) certified copies of:

i) certificate of incorporation;

ii) memorandum and articles of association;

iii) in case of an applicant who has submitted the annual return

required to be submitted to the registrar of companies pursuant to section 156 of the Ordinance, the last filed annual return;

iv) in case of an applicant to whom sub-clause (a)(iii) of

sub-regulation (5) is not applicable, a return comprising all such information, in as close a form and content as possible, laid down in the third schedule to the Ordinance;

(b) a reasonably detailed profile of the experience of the applicant, its

management staff and its members in the electricity industry;

(c) the curriculum vitae of the applicant's senior management, technical and professional staff;

(d) evidence, satisfactory to the Authority, of the availability of

adequate financial and technical resources to the applicant for the purposes of the generation, transmission or distribution business, as the case may be, and such evidence may consist of:

i) cash balances held in reserve along with the

bank certificates;

ii) expressions of interest to provide credit or financing along with sources and details

Page 202: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

4

thereof;

iii) latest financial statements of the applicant;

iv) employment records of engineering and technical staff of the applicant proposed to be employed;

v) profile of sub-contractors, if any, along with

expressions of interest of such sub-contractors; and

vi) verifiable references in respect of the

experience of the applicant and its proposed sub-contractors;

(e) in respect of a going concern, details of any charges or

encumbrances attached to the company's assets;

(f) in case of a first application for a licence by a going concern, technical and financial proposals in reasonable detail for the operation, maintenance, planning and development of the generation, transmission or distribution facility or system in respect of which the licence is sought;

(g) in case of:

a) generation licence applications, the type, technology, model,

technical details and design of the facilities proposed to be acquired, constructed, developed or installed;

b) distribution and transmission licence applications,

(i) the type, technology, model, technical details and

design of the facilities proposed to be acquired, constructed, developed or installed;

(ii) a territorial map of the service area proposed to be

covered;

(iii) particulars in respect of the availability, sources, rates and evidence of commitments from the sources of electric power.

(h) in case of a licence for a new facility or system, a feasibility report

in respect of the project, specifying in detail:

(i) the type, technology, model, technical details and design of the facilities proposed to be constructed, developed or installed;

Page 203: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

5

(ii) the expected life of the facility or the system;

(iii) the location of the facility or the system, or the territory with outer boundaries within which the facilities or the system is proposed to be installed and operated by the licensee, along with maps and plans; and

(iv) the type and details of the services proposed to be provided;

and

(i) a prospectus.

(6) Schedule III to these regulations sets out, by way of illustration, the technical, financial and other information the documents-in-support may contain, provided that the contents of Schedule III shall not constitute an exhaustive list of the information which may be provided by the applicant either of his own volition or on the direction of the Authority.

(7) Notwithstanding the provisions of sub-regulation (5) and (6), the Authority

may require the applicant to provide further information or furnish any other document-in-support at the time of the submission of the application or at any stage thereafter.

4. Unincorporated applicants.—

An applicant, not being a company registered under the Ordinance, seeking exemption from the Authority pursuant to and for the purposes of section 24 of the Act, shall add a document-in-support setting out the grounds on which the exemption is sought.

5. Eligibility criteria.—

(1) The Authority may, in considering an application for the grant of a licence,

take into account such factors as may be deemed relevant by the Authority, including the following:

(a) business experience of the applicant, its management staff, sub-

contractors, engineering and technical staff in the electric power industry, if any;

(b) financial status of the applicant;

(c) the ability of the applicant to comply with the conditions of the

licence;

(d) technology, technical specifications, model, design, operational characteristics and economic life of the facility or the system;

(e) the ability of the applicant, the facility or the system in respect of

synchronous operation in co-ordination with other licensees;

Page 204: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

6

(f) the ability of the applicant to comply with prudent utility practices, the grid code, the distribution code or the uniform industry standards and codes of conduct; and

(g) project milestones and evidence of capability to achieve such

milestones and expressions of interest of contractors, financial institutions or the suppliers, as the case may be.

(2) Notwithstanding the applicant meeting the eligibility criteria, the Authority

may decline to issue a licence if the Authority determines in writing that:

a) the investments associated with the facility or system are not justifiable in view of the needs of the electric power industry or where the applicant has failed to demonstrate, in the opinion of the Authority, the existence of the demand for the proposed facility or system;

b) the plant and capacity requirements of the electric power

industry do not warrant the installation of additional plant or capacity or warrant the installation of plant or capacity with technical, financial or other characteristics different from the ones specified in the licence application;

c) among competing applicants, another applicant qualifies

better in terms of quality of equipment, plant, service and the corresponding economy of costs; or

d) the site proposed by the applicant is not suitable on

environmental, social or other grounds. 6. Application procedure.—

(1) An application shall be submitted to the Registrar, who shall ensure that

the application is submitted in accordance with regulation 3, that all the relevant information in the application form is provided, that all the documents-in-support and the application fee are duly attached and, upon being satisfied of the matters aforesaid, the registrar shall forthwith:

(a) allot a registration number to the application; and

(b) forward the application to the Authority for a decision on

admission of the application.

(2) In case of the application being incomplete in any respect, the registrar shall notify the applicant with directions to furnish the required information or documents-in-support within seven days of the receipt of such notice by the applicant.

7. Admission of application.—

Page 205: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

7

(1) Subject to the provisions of sub-regulation (2), within three days of the receipt of the application by the Authority from the Registrar pursuant to sub-regulation (1)(b) of regulation 6, the Authority shall review the application and shall make a decision as to whether the application should be admitted for consideration by the Authority.

(2) The Authority may require further information or documents-in-support

from the applicant for the purpose of a decision on admission of the application and:

(a) a request for further information or documents-in-support

shall be dispatched no later than the third day of the receipt of the application by the Authority from the Registrar; and

(b) the applicant shall provide the requested information or

documents-in-support within seven days of the receipt of the request in this regard from the Authority,

provided that, the Authority may extend the time for submission of the information or the documents-in-support for a further period not exceeding fourteen days.

(3) The Authority may:

(a) if the form and content of the application are in substantial

compliance with regulation 3, admit the application; and

(b) if the form and content of the application do not substantially comply with regulation 3, and the applicant fails to comply with the request for further information and documents-in-support in the manner and within the time limit provided in sub-regulation (2), reject the application.

8. Advertisement.—

Within three days of the admission of the application by the Authority, the Registrar shall cause to be published, in one English and one Urdu daily newspapers with circulation in the entire country:

(a) the prospectus;

(b) a notice to the general public of the admission of the application;

(c) an invitation to the general public to submit their comments to the Registrar within a period of fourteen days from the date of the publication; and

(d) such other information as the Authority may from time to time direct.

Page 206: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

8

9. Consideration of application.—

(1) The Registrar shall place the application, along with comments, if any, received from the public pursuant to regulation 8, before the Authority no later than three days after the last date for receipt of the comments from the public.

(2) Notwithstanding the provisions of regulation 8, the Authority may invite

any person to provide comments or otherwise assist the Authority in the consideration of the application.

(3) In the event the Authority intends to reject an application, it may allow an

opportunity to the applicant to make a representation before it as to why the application should not be rejected and, upon being notified of such opportunity, the applicant may make a representation within a period not exceeding fourteen days following the receipt of the afore-said notice from the Authority.

(4) Subject to the provisions of sub-regulation (5), the Authority shall decide

the application within twenty eight days after the date the application, along with the comments received from the public, is placed before the Authority pursuant to sub-regulation (1), provided that the time taken, if any, by the applicant in making a representation before the Authority in terms of sub-regulation (3) shall be excluded from the afore-said period of twenty eight days.

(5) The decision by the Authority to grant a licence shall be without prejudice

to the power of the Authority to defer the issuance of the licence until such time the provisions of the licence are settled by the Authority, and the Authority may refuse to issue the licence in the event the licensee fails, within the time stated in this respect by the Authority, to agree to the terms and conditions of the proposed licence.

(6) Subject to the applicable provisions of the Act and the rules and

regulations made pursuant thereto in this regard, the grant of a licence for any purpose shall not in any way hinder or restrict the grant of a licence to another person within the same territory for a like purpose.

PART III

10. Modification to the licence.—

(1) Subject to the provisions of sub-regulation (15), the Authority may, at any time during the term of a licence, communicate to the licensee an Authority proposed modification setting out:

(a) the text of the proposed modification; and

(b) a statement of the reasons in support of the modification.

Page 207: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

9

(2) Subject to the provisions of sub-regulation (15), a licensee may, at any time during the term of his licence, communicate to the Authority a licensee proposed modification setting out:

(a) the text of the proposed modification;

(b) a statement of the reasons in support of the modification; and

(c) a statement of the impact on the tariff, quality of service and the

performance by the licensee of its obligations under the licence.

(3) In case of a licensee proposed modification, the licensee shall pay to the Authority at the time of submission of the licensee proposed modification to the Registrar, a non-refundable fee calculated in accordance with the provisions of Schedule II for the modification of the license.

(4) Within seven days of:

(a) the receipt of a licensee proposed modification by the Registrar; or

(b) the date the Authority proposed modification is forwarded

to the licensee,

the Registrar shall publish the Authority proposed modification or the licensee proposed modification, as the case may be, in one English and one Urdu daily newspaper, inviting comments from the public within a period of fourteen days of the date of publication.

(5) The Authority may modify a licence in accordance with an Authority

proposed modification or a licensee proposed modification, subject to and in accordance with such further changes as the Authority may deem fit if, in the opinion of the Authority, such modification:

(a) does not adversely affect the performance by the licensee of its

obligations;

(b) does not cause the Authority to act or acquiesce in any act or omission of the licensee in a manner contrary to the provisions of the Act or the rules or regulations made pursuant to the Act;

(c) is or is likely to be beneficial to the consumers;

(d) is reasonably necessary for the licensee to effectively and

efficiently perform its obligations under the licence; and

(e) is reasonably necessary to ensure the continuous, safe and reliable supply of electric power to the consumers keeping in view the financial and technical viability of the licensee.

(6) If a licensee does not agree to an Authority proposed modification, the

Authority shall fix a time, date and place for a public hearing to be held

Page 208: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

10

with the licensee no later than fourteen (14) days following the communication of the final refusal of the licensee to agree to the Authority proposed modification or such date as the Authority may determine, not being a date falling prior to the expiry of twenty eight days after the date the Authority proposed modification is forwarded to the licensee.

(7) At the public hearing to be held pursuant to sub-regulation (6), the

Authority shall allow the licensee to make out a case against the Authority proposed modification within a period of seven days.

(8) The Authority shall address the licensee's case made out against the

Authority proposed modification within a period of seven days after the close of the case made out by the licensee pursuant to sub-regulation (7).

(9) The registrar shall, upon the conclusion of the public hearing in

accordance with sub-regulations (6), (7) and (8), cause to be published in one English and one Urdu daily newspaper, a notice inviting comments from the public in respect of the public hearing within fourteen days of the date of conclusion of the public hearing.

(10) The Authority may extend the time limits provided in this regulation 10,

provided that the Authority shall conclude the proceedings and render its decision no later than one hundred twenty days following the earlier of the date of communication of the final refusal of the licensee to agree to the Authority proposed modification or the date determined, if any, by the Authority for the commencement of public hearing under sub-regulation (6).

(11) The Authority may:

(a) approve, with or without changes, a proposed modification; or

(b) reject a proposed modification,

in each case for reasons to be recorded in writing taking into account the comments received, if any, from the public pursuant to sub-regulations (4) and (9).

(12) Subject to the provisions of regulation 11, the Authority may call for any

information in the possession or control of the licensee or any other person, or may allow the licensee to call for any information available with the Authority or in the possession or control of any other person, which in the opinion of the Authority is material and relevant to the proceedings.

(13) The Authority may declare that the procedure set out in rules 3 through 16

of the National Electric Power Regulatory Authority (Tariff Standards and Procedure) Rules, 1998, shall apply to a public hearing ordered to be held pursuant to sub-regulation (6), subject to such modifications, if any, as the Authority may determine in advance of the proceedings, taking into

Page 209: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

11

account the complexity of the issues involved, the requirements of the licensee in respect of the details of the procedure and with a preference for an expedited hearing over matters of procedure.

(14) The Authority may determine that an Authority Proposed modification or a

licensee proposed modification, the principal object of which relates to the tariff, shall be initiated and determined pursuant to and in accordance with the National Electric Power Regulatory Authority (Tariff Standards and Procedure) Rules, 1998, whereupon such Authority proposed modification or the licensee proposed modification shall be initiated as a petition pursuant to the afore-mentioned rules.

(15) Neither the Authority nor a licensee shall propose an Authority proposed

modification or a licensee proposed modification and no licence shall be modified before the expiry of three hundred sixty five days following the date of issue of the licence.

(16) Notwithstanding any thing to the contrary stated in this regulation 10, an

Authority proposed modification or a licensee proposed modification may be withdrawn by the Authority or the licensee, as the case may be, at any time prior to the commencement of a public hearing pursuant to sub- regulation (6).

(17) Where a licence is modified, the Authority shall cause to be published, in

one English and one Urdu newspaper, the substance of the modification in such form and content as may be determined by the Authority.

PART IV

11. Confidentiality.—

In any application, document-in-support or information required to be furnished under these regulations, the applicant or the licensee may, as the case may be, request the Authority to permit the applicant or the licensee to withhold information the disclosure of which may materially and adversely affect the commercial interests of the applicant or the licensee, or in respect of which the applicant or the licensee is under a contractual or other valid and enforceable obligation of non-disclosure, provided that, the Authority shall have the power to call for review such information in order to determine whether or not to allow the request for confidentiality by the applicant or the licensee.

12. Amendments.—

The Authority may amend or supplement these regulations from time to time, provided that, such amendments or supplements shall be prospective only and shall not apply in respect of:

(a) an application already admitted by the Authority; and

Page 210: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

12

(b) a licensee proposed modification or an Authority proposed modification, which has been communicated to the Authority or the licensee, respectively.

SCHEDULE I

(regulation 3(1))

FORM OF APPLICATION The Registrar National Electric Power Regulatory Authority

Subject: Application for a [GENERATION/TRANSMISSION/SPECIAL

PURPOSE TRANSMISSION/DISTRIBUTION] License

I, [NAME, DESIGNATION], being the duly authorized representative of [NAME OF APPLICANT COMPANY] by virtue of [BOARD RESOLUI'ION/POWER OF ATTORNEY] dated [DATE], hereby apply to the National Electric Power Regulatory Authority for the grant of a [GENERATION/TRANSMISION/ SPECIAL PURPOSE TRANSMISSION/DISTRIBUTION LICENCE] to the [NAME OF APPLICANT COMPANY] pursuant to section [ ] of the Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997.

1 certify that the documents-in-support attached with this application are prepared and submitted in conformity with the provisions of the National Electric Power Regulatory Authority Licensing (Application and Modification Procedure) Regulations, 1999, and undertake to abide by the terms and provisions of the above-said regulations. 1 further undertake and confirm that the information provided in the attached documents-in- support is true and correct to the best of my knowledge and belief.

A [BANK DRAFT/ PAY ORDER] in the sum of Rupees [ ], being the non-

refundable licence application fee calculated in accordance with Schedule II to the National Electric Power Regulatory Authority Licensing (Application and Modification Procedure) Regulations, 1999, is also attached herewith.

Date: ---------------------------------

Company Seal

Signature [Name, designation]

Page 211: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

13

SCHEDULE II (regulations

3(2) and 10(3)) TABLE OF

FEES

PART I

LICENCE APPLICATION AND MODIFICATION FEES

Category of licence Fees (Million Rs)

GENERATION

Upto 100 MW 0.75

101 to 500 MW 1.50

Above 500 MW 3.00 TRANSMISSION

National Grid Company 1.50

Special purpose 1.50

DISTRIBUTION 3.00

The fee specified in this Part I may be changed by the Authority after every five years.

Page 212: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

14

PART II INDEXATION OF FEES

1. The licence application and modification fee payable by an applicant or the licensee, as the case may be, shall be indexed to the Consumer Price Index ("CPI") published from time to time by the Federal Bureau of Statistics.

2. The indexation shall be done on the basis of the most recent CPI prevailing on the date of payment of the licence application fee or the modification fee, as the case may be, and the fee payable on the date of payment shall be increased or decreased, as the case may be, in accordance with the following formula:

Fpd = Ft [ CPI pd/CPI rd]

Where

Fpd = The actual fee payable on the date of payment.

Ft = The respective fee set out in Part I of this Schedule II.

CPI pd = The most recent CPI prevalent on the last day of the month immediately preceding the month in which the application or the

modification proposal is made.

CP1rd = The reference or base CPI, prevalent on the last day of the month in which the National Electric Power Regulatory Authority Licensing (Application and Modification Procedure) Regulations, 1999, are notified in the official gazette.

1. GENERATION

SCHEDULE III

(regulation 3(6))

(a) NEW GENERATION FACILITIES (Thermal) 1. Location (location maps, site map), land

2. Technology, size of the plant, number of units

3. Fuel: type, imported/indigenous, supplier, logistics, pipeline etc.

4. Emission values

5. Cooling water source: tube wells, sea/river/canal, distance from source, etc.

6. Interconnection with national grid company, distance and name of nearest grid,

Page 213: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

15

voltage level (single line diagram) 7. Infrastructure: roads, rail, staff colony, amenities

8. Project cost, information regarding sources and amounts of equity and debt

9. Project commencement and completion schedule with milestones

10. ESSA (Environmental and Social Soundness Assessment)

11. Safety plans, emergency plans

12. System studies: load flow, short circuit, stability, reliability

13. Plant characteristics: generation voltage, frequency, power factor, automatic generation control, ramping rate, alternative fuel, auxiliary consumption, time(s) required to synchronize to grid

14. Control, metering, instrumentation and protection 15. Training and development

16. Feasibility report

(b) EXISTING GENERATION FACILITIES (Thermal)

1. Location (location maps, site map)

2. Technology, number of units

3. Fuel: type, imported/indigenous, supplier, logistics, pipeline etc.

4. Emission values

5. Cooling water source: tube wells, sea/river/canal

6. Interconnection with national grid company: distance and name of nearest grid,

voltage level (single line diagram) 7. Installed capacity, derated capacity, expected remaining life

8. Due diligence report

9. Rehabilitation plans, previous rehabilitation programme

10. Operational record including environmental monitoring data for the last five

years, constraints in despatching 11. Project cost, information regarding sources and amounts of equity and debt

12. Plant characteristics: generation voltage, frequency, power factor, automatic

generation control, ramping rate, alternative fuel, auxiliary consumption, time(s) required to synchronize to grid

Page 214: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

16

13. Training and development

(c) NEW GENERATION FACILITIES (Hydel) 1. Location (location maps, site map), land

2. Plant: run of the river, storage, veir

3. Head: minimun, maximum

4. Technology: Francis, Pelton, etc. size, number of units

5. Tunnel (if proposed): length, diameter

6. ESSA

7. Detailed feasibility report

8. Resettlement issues

9. Consents

10. Infrastructure development

11. Interconnection with national grid company, length of transmission line(s)

12. Project cost, information regarding sources and amounts of equity and debt

13. Project schedule, expected life

14. Peaking/base load operation

15. Plant characteristics: generation voltage, power factor, frequency, automatic

generation control, ramping rate, control metering and instrumentation 16. System studies load flow, short circuit, stability

17. Training and development

(d) EXISTING GENERATION FACILITIES (Hydel)

1. Location (location maps, site map)

2. Plant: run of the river, storage, veir

3. Head: minimum, maximum

4. Technology: Francis, Pelton, etc. size, number of units

5. Tunnel(s) if existing: length, diameter

6. Due diligence report, expected life

7. Rehabilitation plan, previous rehabilitation programmes

Page 215: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

17

8. Operations record for the last five years, operation constraints 9. Consents

10. Interconnection with national grid company, length of transmission line(s)

11. Peaking/base load operation

12. Plant characteristics: generation voltage, power factor, frequency, automatic

generation control, ramping rate, control metering and instrumentation 13. Training and development

B. TRANSMISSION

(a) EXISTING TRANSMISSION FACILITIES

1. Network configuration

2. Territory maps

3. Voltage levels

4. System statistics, system development, line lengths, technical parameters for

transmission lines and grid stations, etc. 5. Central and regional dispatch facilities, connection facilities

6. Interface nodes with generation entities

7. Interface nodes with distribution entities.

8. Dispatch procedures, software, hardware information

9. Emergency provisions, blackout restoration procedures

10. Safety provisions

11. Operations record, operational constraints

12. Due diligence report

13. Training and development

(b) SPECIAL PURPOSE TRANSMISSION FACILITIES.

1. Purpose

2. Line route and territory maps

3. Line lengths, starting point, termination point, year of completion

Page 216: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

18

4. System studies 5. ESSA

6. Structures: type, number/km

7. Line characteristics

8. Conductor, type, current carrying capacity, circuit power transfer

9. Insulators

10. Shield-wire: number, size

11. Compensation employed: series, Shunt, SVC

12. Communication system: PLC, fibre optics, microwave

13. Grid station(s) involved: number, existing/new and details of the following:

- Scope, size, number of transmission circuits, in and out

- Type: indoor/outdoor, transformation/switching

- Arrangement scheme: breaker and a half, double bus

- Basic insulation level: kV

- Control and protection system

- Specification of equipment : breakers-type, re-closing mechanism,

duty cycle etc. isolators, transformers-type, size, cooling system, tap-changer, and protection

- Lightening arresters, shunt reactors, metering and instrumentation

- SCADA and communication

C. DISTRIBUTION

1. Distribution system configuration, service territory, right of way, feeder maps

2. Voltage levels, regulation

3. Type of distribution system

4. Line equipment characteristics

5. Power quality control

6. Back-up/express feeder provision

Page 217: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

19

7. Accident protection/ prevention procedures 8. Maintenance plans and procedures

9. Fault location/trouble-shooting procedures

10. Emergency provisions

11. Patrolling and inspection procedures

12. Customer service data/manuals

13. Billing and collection procedures

14. Protection, control and measuring instruments

15. Metering and testing facilities

16. Communication systems

17. Training and development

MAJ. GEN. (R) MUHAMMAD HASAN AQEEL, Secretary,

National Electric Power Regulatory Authority

Page 218: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 7

Geological Map of Project Area

Page 219: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Project Area

Page 220: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 8

Soil Test Report

Page 221: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 222: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 223: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 224: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 225: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 9

Tectonic Map of Pakistan

Page 226: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Study Area

Project Area

Page 227: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 10

Drainage Map of Karachi

Page 228: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Project Area

Page 229: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 11

Ambient Air Quality Test Report

Page 230: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 231: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 12

Socio – Economic Questionnaire

Page 232: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

Socioeconomic Survey for the Environmental  Impact Assessment  (EIA) of proposed 132 kV 

Hybrid Grid Station  

A)   Survey from Local Residents  

   

01. Name of the Settlement:   02. Type of Area (Mark √ against the Type) 

 Serial 

No. Type

1. Commercial 2. Residential

03. Distance of the residential area from the proposed project: 

04. Respondents Bio data 

 Name Age Gender Marital Status Qualification Occupation Contact # (optional)

05. FAMILY PROFILE (mention total #) 

 Serial 

No. Category Males Females

1. Adults 2. Married 3. Unmarried 4. Children

5.1. Age pattern 

 Age Total #

0‐10 11‐20 21‐30 31‐40 40 & Above

Page 233: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

5.2. Family Type  

Serial 

No. Family Type Response

1. Joint Family 2. Nuclear Family

5.3. Ethnic Group (Mark √ against the response) 

 Serial 

No. Group Response

1. Sindhi 2. Punjabi 3. Baloch 4. Pathan 5. Mahajir 6. Hazaraywaal 7. Memon 8. Siraiki 9. Aga Khani 10. Other

6. EDUCATIONAL PROFILE (mention total #) 

 Serial No.

Educational Levels Males Females Children

1. Primary 2. Middle 3. Matriculate 4. Graduate 5. Masters 6. Illiterate 7. Other Skills

7. Land Ownership  (Mark √ against the response) 

 Serial 

No. Ownership Response

1. Owner 2. Tenant

Page 234: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

08. If owner, what is the worth of the Apartment/House?  09. If on rent, what is the monthly rent? 

10. Length of stay in area (Mark √ against the response) 

 Serial 

No. Length (in years) Response

1. < 5 2. 5‐10 3. 10 and above

11. Occupational profile (Mark √ against the response) 

 Serial 

No. Occupation Response

1. Land lord

2. Govt. Service 3. Private Service 4. Own Business 5. Teaching 6. Doctor 7. Engineer 8. Driving 9. Labor 10. Other

12. ECONOMIC PROFILE 

 

12.1. Monthly Income of Household:  13. Type of house (Mark √ against the response) 

 Type Area\Number of rooms

House Apartment 14.   Health Profile 

 

14.1. Did any of the family members ever get victimized with any epidemic disease (like 

most common these days is Dengue Fever)?  14.2. Or with any Common Diseases  like: (Mark √ against the response) 

 Serial 

No. Diseases Males Females Children

1. Respiratory 2. Skin

Page 235: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

4

3. Eye Infection 4. Digestive 5. Infections 6. Other

14.3. What is your average monthly expenditure on medicines? 

15.   Source of Water (mention currently available sources or mark √ against the 

response)   

Water Supply Line Water Boring Tankers Other

15.1. If boring, what is its approximate depth? 

15.2. Water Quality (Mark √ against the response) 

 Clear Turbid Salty Other

16.   Public perception of this project? 

 16.1 Do you have any knowledge of installation of the grid station? 

 16.2 Do you think it will reduce load shedding  in the area? 

 16.3 Will it increase the value of land in the area? 

 16.4 Will it bring economic uplift of the area? 

 16.5 Will it have any negative effects? 

Page 236: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

5

Socioeconomic Survey for the Environmental  Impact Assessment  (EIA) of proposed 132 kV 

Hybrid Grid Station  

B)   Survey from the Commercial Establishments  Respondents Bio data 

 Name Age Gender Marital Status Qualification Occupation Contact # (optional)

01. Name of the Settlement:  

02. Average total population of the surrounding residential area? 

03. When this community came into existence? 

04. Are most of the houses on rent or self owned? 

05. What is the minimum to maximum rent of the surrounding  flats/houses? 

 06. What is the minimum to maximum worth of the surrounding  flats/houses? 

 07. Ethnic Groups predominantly  living in the Area: 

 Serial 

No. Group Response

1. Sindhi 2. Punjabi 3. Baloch 4. Pathan 5. Mahajir 6. Hazaraywaal 7. Memon 8. Siraiki 9. Aga Khani 10. Other

08. What is the average family size of the surrounding population? 

09. Is the medical facility nearby? 

10. Per visit medical charges of the clinic? 

Page 237: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

6

11. What might be the average number of people earning  in each of the surrounding 

households?  12. Dominating Political Party in the area? 

13. Water Supply 

 

Line Water

Boring Tankers

14. If boring, what could be its approximate depth? 

 15. Are there any Non‐Muslims  residing  in the area? 

 

Hindu

Christian Other

16.   Public perception of this project: 

 16.1 Do you have any knowledge of installation of the grid station? 

 

   16.2 Do you think it will reduce load shedding  in the area? 

 

   16.3 Will it increase the value of land in the area? 

 

   16.4 Will it bring economic uplift of the area? 

 

   16.5 Will it have any negative effects? 

Page 238: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

7

Socioeconomic Survey for the Environmental  Impact Assessment  (EIA) of proposed 132 kV 

Hybrid Grid Station  

C)  General Observations of the Study Area  

   

01. Average total population of the surrounding residential area?  02. General Cleanliness  level of the area: 

 No litter or refuse 3

Predominantly  free of litter or refuse, apart from small items 2

Widespread distribution of litter and refuse, with minor accumulations 1

Heavily  littered with significant accumulations 0

03. Type of Transport  in the area: 

 Public Private

04. Type of Roads: 

 Narrow Wide One Way Two Way

05. Source of Electricity and Natural Gas 

 • KESC/WAPDA 

• SSGC 

• Kunda connections  if found any 

 06. Are the educational institutes nearby? 

07. Number of Educational Institutes: 

Schools Colleges Universities Seminaries

08. Is schooling common among the young ones? 

Page 239: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

8

09. Average number of children going to schools:  

Nearest Schools Distance Schools

11. Is there any record of epidemic disease (e.g. most common these days is Dengue Fever) 

in the area?  12. Are there any other Common Diseases prevailing  in the area?  Like: 

 Serial No.

Diseases Response

1. Respiratory 2. Skin 3. Eye Infection 4. Digestive 5. Other

13. Is the medical facility nearby? 

14. Per visit medical charges of the clinic? 

15. Landline facility of Telephone 

16. Sewerage and drainage system 

17. Nearest Police station 

18. Nearest Post office 

19. Recreational sites 

20. Archaeological or Historical Sites 

21. Number of Mosques 

22. Nearest Grave yard 

23. What is the social status of women in this particular area? 

24. Negative and Positive aspects of the area? 

25. Are political/ethnic/religious  strife’s common? Dominant strife? 

 26. Presence of Drug peddlers or frequency of drug peddling in the area? 

• Like Gutka, Tobbacco, etc. 

Page 240: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

 

                           

Annexure - 13

Mile Stone Schedule

Page 241: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ID Task Name 2010 2011 1 Civil Works

2 MV Switchgear & Control Building

3 Foundation upto Plinth

11 Ground Floor

19 First Floor

27 Plumbing & sanitry works

30 Internal electrification

34 Airconditioning & False Ceiling

37 Outdoor Equipment Foundation

148 Cable Trenches

154 Station Grounding

158 Construction of Moving Area & Fire Wall

173 Surface & Trench Drainage System

177 Construction of Approach Roads

181 Outdoor Electrification, Fitting & Auxiliary Works 0%

Project: Hospital Grid Station Date: 30-04-2010

Task Milestone External Tasks

Split Summary External MileTask

Progress Project Summary Split

Page 1

Page 242: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ABB CONSORTIUM - KESC/2480-04/04A TESTING & COMMISSIONING SCHEDULE - HOSPITAL GRID S/S Page : 1 of 1 ID WBS Task Name 10 11 12 1 1 HG-T-1 Supervision of Testing & Commissioning (KESC-2480-04) / Erection & Testing (KESC-2480-04A)

2 HG-T-1.1 Inspection of Steel Structures in 132 kV Switchyard

3 HG-T-1.2 Inspection of Buswork of 132 kV Switchyard

5 HG-T-1.3 Inspection of Earthing Grid Installation

9 HG-T-1.4 Batteries and Chargers

12 HG-T-1.5 Test on 400/230 V AC-Distribution

16 HG-T-1.6 Test on 220 V DC-Distribution

20 HG-T-1.7 11 kV MV-Switchgear

31 HG-T-1.8 11/0.4 kV Aux. Transformers

36 HG-T-1.9 11 kV Capacitor Bank

38 HG-T-1.10 11 kV Cables

40 HG-T-1.11 132 kV Hybrid Switchyard

46 HG-T-1.12 132 / 11 kV Transformers

52 HG-T-1.13 132 / 11 kV Protection System

58 HG-T-1.14 Substation Automation System (SAS)

66 HG-T-1.15 OHL-Teleprotection, End to End Test

69 HG-T-1.16 Readiness for Energization of 132 / 11 kV Substation (TOC) 1/11

Month : June, 2009 Project: 9x132KV Substations

Karachi.

Task Rolled Up Task External Tasks

Progress Rolled Up Milestone Project Summary

Milestone Rolled Up Progress Group By Summary

Summary Split Deadline

Dated : 09.06.2009

Page 243: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 14

Typical Material Safety Data Sheets (MSDS) of Transformer Oil

Page 244: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 245: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1. PRODUCT AND COMPANY IDENTIFICATION

Product Name: Transformer Oil

MSDS Code: 390730

Synonyms: Phillips Transformer Oil

Intended Use: Insulating Oil

Responsible Party: ConocoPhillips Lubricants 600 N. Dairy Ashford Houston, Texas 77079-1175

Customer Service: 888-766-7676

Technical Information: 800-255-9556

Transformer Oil M a t e r i a l S a f e t y D a t a S h e e t

MSDS Information: Internet: http://w3.conocophillips.com/NetMSDS/

Emergency Telephone Numbers: Chemtrec: 800-424-9300 (24 Hours) California Poison Control System: 800-356-3219

2. HAZARDS IDENTIFICATION

Emergency Overview

This material is not considered hazardous according to OSHA criteria.

NFPA

Appearance: Clear and bright Physical Form: Liquid Odor: Petroleum

Potential Health Effects Eye: Contact may cause mild eye irritation including stinging, watering, and redness.

Skin: Contact may cause mild skin irritation including redness and a burning sensation. Prolonged or repeated contact can defat the skin, causing drying and cracking of the skin, and possibly dermatitis (inflammation). No harmful effects from skin absorption are expected.

Inhalation (Breathing): Expected to have a low degree of toxicity by inhalation.

Ingestion (Swallowing): No harmful effects expected from ingestion.

Signs and Symptoms: Effects of overexposure may include Effects of overexposure may include irritation of the digestive tract, nausea and diarrhea. Inhalation of oil mist or vapors at elevated temperatures may cause respiratory irritation.

Pre-Existing Medical Conditions: Conditions aggravated by exposure may include skin disorders.

See Section 11 for additional Toxicity Information.

390730 - Transformer Oil Page 1/7 Date of Issue: 04-Oct-2007 Status: Final

Page 246: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

390730 - Transformer Oil Date of Issue: 04-Oct-2007

Page 2 /7 Status: Final

3. COMPOSITION / INFORMATION ON INGREDIENTS

Component CAS Concentration (wt %)Lubricant Base Oil (Petroleum) VARIOUS >99Additives PROPRIETARY <1

4. FIRST AID MEASURES

Eye: If irritation or redness develops from exposure, flush eyes with clean water. If symptoms persist, seek medical attention.

Skin: Remove contaminated shoes and clothing and cleanse affected area(s) thoroughly by washing with mild soap and water or a waterless hand cleaner. If irritation or redness develops and persists, seek medical attention.

Inhalation (Breathing): First aid is not normally required. If breathing difficulties develop, move victim away from source of exposure and into fresh air. Seek immediate medical attention.

Ingestion (Swallowing): First aid is not normally required; however, if swallowed and symptoms develop, seek medical attention.

Notes to Physician: Acute aspirations of large amounts of oil-laden material may produce a serious aspiration pneumonia. Patients who aspirate these oils should be followed for the development of long-term sequelae. Inhalation exposure to oil mists below current workplace exposure limits is unlikely to cause pulmonary abnormalities.

5. FIRE-FIGHTING MEASURES

NFPA 704 Hazard Class

Health: 0 Flammability: 1 Instability: 0 (0-Minimal, 1-Slight, 2-Moderate, 3-Serious, 4-Severe)

Unusual Fire & Explosion Hazards: This material may burn, but will not ignite readily. If container is not properly cooled, it can rupture in the heat of a fire.

Extinguishing Media: Dry chemical, carbon dioxide, foam, or water spray is recommended. Water or foam may cause frothing of materials heated above 212°F. Carbon dioxide can displace oxygen. Use caution when applying carbon dioxide in confined spaces.

Fire Fighting Instructions: For fires beyond the incipient stage, emergency responders in the immediate hazard area should wear bunker gear. When the potential chemical hazard is unknown, in enclosed or confined spaces, or when explicitly required by DOT, a self contained breathing apparatus should be worn. In addition, wear other appropriate protective equipment as conditions warrant (see Section 8).

Isolate immediate hazard area and keep unauthorized personnel out. Stop spill/release if it can be done with minimal risk. Move undamaged containers from immediate hazard area if it can be done with minimal risk. Water spray may be useful in minimizing or dispersing vapors and to protect personnel. Cool equipment exposed to fire with water, if it can be done with minimal risk. Avoid spreading burning liquid with water used for cooling purposes.

See Section 9 for Flammable Properties including Flash Point and Flammable (Explosive) Limits

Page 247: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

390730 - Transformer Oil Date of Issue: 04-Oct-2007

Page 3 /7 Status: Final

6. ACCIDENTAL RELEASE MEASURES

Personal Precautions: This material may burn, but will not ignite readily. Keep all sources of ignition away from spill/release. The use of explosion-proof electrical equipment is recommended. Stay upwind and away from spill/release. Notify persons down wind of the spill/release, isolate immediate hazard area and keep unauthorized personnel out. Wear appropriate protective equipment, including respiratory protection, as conditions warrant (see Section 8). See Sections 2 and 7 for additional information on hazards and precautionary measures.

Environmental Precautions: Stop spill/release if it can be done with minimal risk. Prevent spilled material from entering sewers, storm drains, other unauthorized drainage systems, and natural waterways. Use water sparingly to minimize environmental contamination and reduce disposal requirements. Spills into or upon navigable waters, the contiguous zone, or adjoining shorelines that cause a sheen or discoloration on the surface of

the water, may require notification of the National Response Center (phone number 800-424-8802).

Methods for Containment and Clean-Up: Notify fire authorities and appropriate federal, state, and local agencies. Immediate cleanup of any spill is recommended. Dike far ahead of spill for later recovery or disposal. Absorb spill with inert material such as sand or vermiculite, and place in suitable container for disposal.

7. HANDLING AND STORAGE

Precautions for safe handling: Wash thoroughly after handling. Use good personal hygiene practices and wear appropriate personal protective equipment.

Do not enter confined spaces such as tanks or pits without following proper entry procedures such as ASTM D-4276 and 29CFR 1910.146. Do not wear contaminated clothing or shoes.

"Empty" containers retain residue and may be dangerous. Do not pressurize, cut, weld, braze, solder, drill, grind, or expose such containers to heat, flame, sparks, or other sources of ignition. They may explode and cause injury or death. "Empty" drums should be completely drained, properly bunged, and promptly shipped to the supplier or a drum reconditioner. All containers should be disposed of in an environmentally safe manner and in accordance with governmental regulations. Before working on or in tanks which contain or have contained this material, refer to OSHA regulations, ANSI Z49.1, and other references pertaining to cleaning, repairing, welding, or other contemplated operations.

Conditions for safe storage: Keep container(s) tightly closed. Use and store this material in cool, dry, well-ventilated areas away from heat and all sources of ignition. Store only in approved containers. Keep away from any incompatible material (see Section 10). Protect container(s) against physical damage.

8. EXPOSURE CONTROLS / PERSONAL PROTECTION

Component ACGIH OSHA Other:Lubricant Base Oil (Petroleum) TWA: 5mg/m3

STEL: 10 mg/m3

as Oil Mist, if generated

TWA: 5 mg/m3

as Oil Mist, if generated ---

Note: State, local or other agencies or advisory groups may have established more stringent limits. Consult an industrial hygienist or similar professional, or your local agencies, for further information.

Engineering controls: If current ventilation practices are not adequate to maintain airborne concentrations below the established exposure limits, additional engineering controls may be required.

Personal Protective Equipment (PPE):

Eye/Face: The use of eye protection that meets or exceeds ANSI Z.87.1 is recommended to protect against potential eye contact, irritation, or injury. Depending on conditions of use, a face shield may be necessary.

Skin: The use of gloves impervious to the specific material handled is advised to prevent skin contact. Users should check with manufacturers to confirm the performance of their products. Suggested protective materials: Nitrile

Page 248: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

390730 - Transformer Oil Date of Issue: 04-Oct-2007

Page 4 /7 Status: Final

Respiratory: Where there is potential for airborne exposure above the exposure limit a NIOSH certified air purifying respirator equipped with R or P95 filters may be used. A respiratory protection program that meets or is equivalent to OSHA 29 CFR 1910.134 and ANSI Z88.2 should be followed whenever workplace conditions warrant a respirator's use. Air purifying respirators provide limited protection and cannot be used in atmospheres that exceed the maximum use concentration (MUC) as directed by regulation or the manufacturer's instructions, in oxygen deficient (less than 19.5 percent oxygen) situations, or other conditions that are immediately dangerous to life and health (IDLH).

Suggestions provided in this section for exposure control and specific types of protective equipment are based on readily available information. Users should consult with the specific manufacturer to confirm the performance of their protective equipment. Specific situations may require consultation with industrial hygiene, safety, or engineering professionals.

9. PHYSICAL AND CHEMICAL PROPERTIES

Note: Unless otherwise stated, values are determined at 20°C (68°F) and 760 mm Hg (1 atm). Data represent typical values and are not intended to be specifications.

Appearance: Clear and bright Physical Form: Liquid Odor: Petroleum Odor Threshold: No data pH: Not applicable Vapor Pressure: <1 Vapor Density (air=1): >1 Boiling Point/Range: No data Melting/Freezing Point: <-40°F / <-40°C Pour Point: <-40°F / <-40°C Solubility in Water: Soluble Partition Coefficient (n-octanol/water) (Kow): No data Specific Gravity: 0.88 @ 60ºF (15.6ºC) Bulk Density: 7.4 lbs/gal Viscosity: 2.3 cSt @ 100°C; 9.6 cSt @ 40°C Evaporation Rate (nBuAc=1): No data Flash Point: >248°F / >120°C Test Method: Pensky-Martens Closed Cup (PMCC), ASTM D93, EPA 1010 LEL (vol % in air): No data UEL (vol % in air): No data Autoignition Temperature: No data

10. STABILITY AND REACTIVITY

Stability: Stable under normal ambient and anticipated conditions of storage and handling.

Conditions to Avoid: Extended exposure to high temperatures can cause decomposition.

Materials to Avoid (Incompatible Materials): Avoid contact with strong oxidizing agents.

Hazardous Decomposition Products: Combustion can yield carbon dioxide and carbon monoxide.

Hazardous Polymerization: Not known to occur.

Page 249: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

390730 - Transformer Oil Date of Issue: 04-Oct-2007

Page 5 /7 Status: Final

11. TOXICOLOGICAL INFORMATION

Chronic Data:

The petroleum base oils contained in this product have been highly refined by a variety of processes including severe hydrocracking/hydroprocessing to reduce aromatics and improve performance characteristics. All of the oils meet the IP-346 criteria of less than 3 percent PAH's and are not considered carcinogens by NTP, IARC, or OSHA.

Acute Data:

Component Oral LD50 Dermal LD50 Inhalation LC50Lubricant Base Oil (Petroleum) >5 g/kg >2 g/kg No data

12. ECOLOGICAL INFORMATION

Lubricant oil basestocks are complex mixtures of hydrocarbons (primarily branched chain alkanes and cycloalkanes) ranging in carbon number from C15 to C50. The aromatic hydrocarbon content of these mixtures varies with the severity of the refining process. White oils have negligible levels of aromatic hydrocarbons, whereas significant proportions are found in unrefined basestocks. Olefins are found only at very low concentrations. Volatilization is not significant after release of lubricating oil basestocks to the environment due to the very low vapor pressure of the hydrocarbon constituents. In water, lubricating oil basestocks will float and will spread at a rate that is viscosity dependent. Water solubilities are very low and dispersion occurs mainly from water movement with adsorption by sediment being the major fate process. In soil, lubricating oil basestocks show little mobility and adsorption is the predominant physical process.

Both acute and chronic ecotoxicity studies have been conducted on lubricant base oils. Results indicate that the acute aquatic toxicities to fish, Daphnia, Ceriodaphnia and algal species are above 1000 mg/l using either water accommodated fractions or oil in water dispersions. Since lubricant base oils mainly contain hydrocarbons having carbon numbers in the range C15 to C50, it is predicted that acute toxicity would not be observed with these substances due to low water solubility. Results from chronic toxicity tests show that the no observed effect level (NOEL) usually exceeds 1000 mg/l for lubricant base oils with the overall weight of experimental evidence leading to the conclusion that lubricant base oils do not cause chronic toxicity to fish and invertebrates.

Large volumes spills of lubricant base oils into water will produce a layer of undissolved oil on the water surface that will cause direct physical fouling of organisms and may interfere with surface air exchange resulting in lower levels of dissolved oxygen. Petroleum products have also been associated with causing taint in fish even when the latter are caught in lightly contaminated environments. Highly refined base oils sprayed onto the surface of eggs will result in a failure to hatch.

Extensive experience from laboratory and field trials in a wide range of crops has confirmed that little or no damage is produced as a result of either aerosol exposure or direct application of oil emulsion to the leaves of crop plants. Base oils incorporated into soil have resulted in little or no adverse effects on seed germination and plant growth at contamination rates up to 4%.

13. DISPOSAL CONSIDERATIONS

The generator of a waste is always responsible for making proper hazardous waste determinations and needs to consider state and local requirements in addition to federal regulations.

This material, if discarded as produced, would not be a federally regulated RCRA "listed" hazardous waste and is not believed to exhibit characteristics of hazardous waste. See Sections 7 and 8 for information on handling, storage and personal protection and Section 9 for physical/chemical properties. It is possible that the material as produced contains constituents which are not required to be listed in the MSDS but could affect the hazardous waste determination. Additionally, use which results in chemical or physical change of this material could subject it to regulation as a hazardous waste.

This material under most intended uses would become "Used Oil" due to contamination by physical or chemical impurities. Whenever possible, Recycle Used Oil in accordance with applicable federal and state or local regulations. Container contents should be completely used and containers should be emptied prior to discard.

14. TRANSPORTATION INFORMATION

U.S. Department of Transportation (DOT) Shipping Description: Not regulated Note: If shipped by land in a packaging having a capacity of 3,500 gallons or more, the provisions of

49 CFR, Part 130 apply. (Contains oil)

Page 250: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

390730 - Transformer Oil Date of Issue: 04-Oct-2007

Page 6 /7 Status: Final

14. TRANSPORTATION INFORMATION

International Maritime Dangerous Goods (IMDG) Shipping Description: Not regulated Note: Federal compliance requirements may apply. See 49 CFR 171.12.

International Civil Aviation Org. / International Air Transport Assoc. (ICAO/IATA) UN/ID #: Not regulated

LTD. QTY Passenger Aircraft Cargo Aircraft Only

Packaging Instruction #: --- --- ---Max. Net Qty. Per Package: --- --- ---

15. REGULATORY INFORMATION CERCLA/SARA - Section 302 Extremely Hazardous Substances and TPQs (in pounds): This material does not contain any chemicals subject to the reporting requirements of SARA 302 and 40 CFR 372.

CERCLA/SARA - Section 311/312 (Title III Hazard Categories)

Acute Health: No Chronic Health: No Fire Hazard: No Pressure Hazard: No Reactive Hazard: No

CERCLA/SARA - Section 313 and 40 CFR 372: This material does not contain any chemicals subject to the reporting requirements of SARA 313 and 40 CFR 372.

EPA (CERCLA) Reportable Quantity (in pounds): This material does not contain any chemicals with CERCLA Reportable Quantities.

California Proposition 65: This material does not contain any chemicals which are known to the State of California to cause cancer, birth defects or other reproductive harm at concentrations that trigger the warning requirements of California Proposition 65.

Canadian Regulations: This product has been classified in accordance with the hazard criteria of the Controlled Products Regulations (CPR) and the MSDS contains all the information required by the CPR.

WHMIS Hazard Class None

National Chemical Inventories: All components are either listed on the US TSCA Inventory, or are not regulated under TSCA. All components are either on the DSL, or are exempt from DSL listing requirements.

U.S. Export Control Classification Number: EAR99

16. OTHER INFORMATION

Issue Date: 04-Oct-2007 Status: Final Revised Sections or Basis for Revision: New MSDS MSDS Code: 390730

Page 251: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

390730 - Transformer Oil Date of Issue: 04-Oct-2007

Page 7 /7 Status: Final

MSDS Legend: ACGIH = American Conference of Governmental Industrial Hygienists; CAS = Chemical Abstracts Service Registry; CEILING = Ceiling Limit (15 minutes); CERCLA = The Comprehensive Environmental Response, Compensation, and Liability Act; EPA = Environmental Protection Agency; IARC = International Agency for Research on Cancer; LEL = Lower Explosive Limit; NE = Not Established; NFPA = National Fire Protection Association; NTP = National Toxicology Program; OSHA = Occupational Safety and Health Administration; PEL = Permissible Exposure Limit (OSHA); SARA = Superfund Amendments and Reauthorization Act; STEL = Short Term Exposure Limit (15 minutes); TLV = Threshold Limit Value (ACGIH); TWA = Time Weighted Average (8 hours); UEL = Upper Explosive Limit; WHMIS = Worker Hazardous Materials Information System (Canada)

Disclaimer of Expressed and implied Warranties: The information presented in this Material Safety Data Sheet is based on data believed to be accurate as of the date this Material Safety Data Sheet was prepared. HOWEVER, NO WARRANTY OF MERCHANTABILITY, FITNESS FOR ANY PARTICULAR PURPOSE, OR ANY OTHER WARRANTY IS EXPRESSED OR IS TO BE IMPLIED REGARDING THE ACCURACY OR COMPLETENESS OF THE INFORMATION PROVIDED ABOVE, THE RESULTS TO BE OBTAINED FROM THE USE OF THIS INFORMATION OR THE PRODUCT, THE SAFETY OF THIS PRODUCT, OR THE HAZARDS RELATED TO ITS USE. No responsibility is assumed for any damage or injury resulting from abnormal use or from any failure to adhere to recommended practices. The information provided above, and the product, are furnished on the condition that the person receiving them shall make their own determination as to the suitability of the product for their particular purpose and on the condition that they assume the risk of their use. In addition, no authorization is given nor implied to practice any patented invention without a license.

Page 252: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

PRODUCT: TRANSVOLT TRANSFORMER OIL NFPA Rating: Flammability: 1, Reactivity: 0, Health:0

SECTION 1: MANUFACTURER AND LOCATION Manufacturers Name: Royal Mfg Co LP Address: P.O. Box 693, Tulsa, OK 74101- 0693 Telephone Number: (918) 587-5711 Emergency: 1-800-299-2671

SECTION 2: MATERIAL IDENTIFICATION AND INFORMATION COMPONENT CAS NUMBER TLV/PEL (mg/M3) WEIGHT % PETROLEUM OIL 64741-88-4 5 (AS OIL MIST) > 85 PROPRIETARY ADDITIVES MIXTURE NE < 15

The specific chemical names and composition of the components not disclosed is confidential business information and is withheld as permitted by 29CFR 1910.1200 and various state Right-to-Know laws.

This material is not known to contain any chemical listed as a carcinogen or suspected carcinogen by OSHA Hazard Communication Standard 29CFR 1910.1200, IARC, or the National Toxicology Program (NTP) at a concentration greater than 0.1%.

SECTION 3: PHYSICAL AND CHEMICAL PROPERTIES Chemical Name: TRANSVOLT TRANSFORMER OIL Form: Liquid Odor: Slight petroleum odor Specific Gravity (water = 1): 0.87 Melting Point: NE Boiling Point: NE Volatility, weight % at 25C: Negligible Evaporation Rate: Negligible Vapor Pressure, mmHg at 25C: < 1 mm Solubility in Water: Insoluble Stability: Stable under normal conditions

SECTION 4: FIRE AND EXPLOSION DATA Flashpoint (Cleveland Open Cup): 300F Autoignition Temperature: NE Flammable Limits: NE Fire Extinguishing Agents: Water Spray (fog), dry chemical, foam, halon, or carbon dioxide. Water stream may splash burning liquid and spread fire. Special Fire Fighting Procedures: As for petroleum products. Do not use direct or heavy water stream to fight fire. Use self-contained breathing apparatus to fight fires.

SECTION 5: FIRST AID Contact with EYES: Immediately flush with large quantities of cool water for at least 15 minutes. Get medical attention. Contact with SKIN: Wash off with soap and water. Inhalation: Remove to fresh air. If not breathing, give artificial respiration. Get medical attention. Ingestion: Do NOT induce vomiting. Get medical attention.

Page 253: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SECTION 6: REACTIVITY Reactivity: Stable under normal temperatures and pressures. Incompatibilities: Strong oxidizing agents, heat, open flame. Hazardous Polymerization: Does not occur. Hazardous Decomposition Products: CO2, CO

SECTION 7: SPECIAL PROTECTION INFORMATION Ventilation (Local, Mechanical, Special): Use in a well ventilated area with local exhaust ventilation. Respiratory Protection: None required in normal use. Use only NIOSH/MSHA Organic vapor approved equipment if necessary. Gloves: Not required in normal use. Eye Protection: Goggles or safety glasses are recommended. Other Protective Equipment: Practice good personal hygiene. Wash hands after use and handling.

SECTION 8: ENVIRONMENTAL PROCEDURES Spills or Leaks: Contain any spills with absorbents to prevent migrations and entry into sewers or streams. Take up small spills with dry chemical absorbent. Large spills may be taken up with pump or vacuum and finished off with dry chemical absorbent. May require excavation of contaminated soil. Waste Disposal: To the best of Royal Manufacturing Company, LP knowledge, this product is not regulated by CERCLA/RCRA as a hazardous waste or material. However, this product has not been tested for the toxicity characteristic via the Toxicity Characteristic Leaching Procedure. Therefore, it may be disposed of as an industrial waste in a manner acceptable to good waste management practice and in compliance with applicable local, state, and federal regulations. Right-to-Know: None

TSCA: This material is in compliance with the Toxic Substances Control Act (15USC2601-2629)

SECTION 9: STORAGE AND HANDLING Keep containers sealed until ready for use. Avoid excessive long-term storage temperatures to prolong shelf life. Maximum storage temperature: 120F. Store in well ventilated areas.

SECTION 10: TRANSPORT D.O.T. Shipping Name: Not Regulated D.O.T. I.D. Number: NA Reportable Quantity: NA Freight Classification: NA UN Hazard Class: NA Special Transportation Notes: None Notes: NA = Not Applicable NE = Not Established

Royal Manufacturing Company, LP believes that the information and recommendations contained herein (including data and statements) are accurate as of the date hereof. No warranty of fitness, warranty of merchantability or any other warranty, expressed or implied, is made concerning the information provided herein. The information provided herein relates only to the specific product designated and may not be valid where such product is used in combination with any other materials or process. Further, since the conditions and methods of use of this product and of the information referred to herein are beyond the control of Royal Manufacturing Company, LP, Royal Manufacturing Company, LP expressly disclaims any and all liability as to any results obtained or arising from any use of the product or reliance on such information.

Revision Date: October 22, 2003 Supercedes: Any previous versions Prepared by: Riverside Laboratories

Page 254: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 15

Typical Protection System for 132kV Overhead Transmission Lines

Page 255: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 256: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 16

SF6 Containment Plan

Page 257: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

SF6 GAS RECOVERY PLAN

Summary “Indefinite re-use of recovered SF6generally possible

• Immediate re-use (using CIGRE( SF6-Recycling Guide)/ IEC standards) of recovered SF6 even in new GIE (Gas Infrastructure Europe) generally possible

• Properly trained personnel will be able to minimize/eliminate handling losses and exposure to harmful by-products

• Provide specialized training for personnel involved in SF6 handling” The standard manufacturer recommendations used for recovering of SF6 Gas are as follows.

SF6 Handling –Safety Harmless in the presence of air

• Will displace air / asphyxiation

Will decompose at temperatures > 350 F • Breaker operations • Welding • Running engines / heaters / open flames • Smoking • Temperature during drawing up to 700 C (1292 F) • Faulted / Arced SF6 • Corrosive, highly acidic (SOF/SOF2, HF) • Present as solid (powder) as well as vapor • Consequences of exposure • Respiratory irritant • Acid burn / Skin rash • Eye irritation • Serious health risk • Handling heavily arced SF6 • Heavily arced SF6generally a result of catastrophic equipment failure • GIE will need extensive repairs or need to be replaced • No urgency to clean / repair GIE • Use specialized Hazmat contractor

SF6 Handling- Recovery Preparation Provide adequate storage

• Enough in-date cylinders on hand Use Pre-Filter as needed

• Normally or heavily arced SF6 • High moisture levels

Leak check hoses / fittings (vacuum raise test)

SF6 Handling-Gas Recovery SF6 recovery comparison GIE containing 2,200 lbs @ 87 PSIG operating pressure

Page 258: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

• Recovery to 0 PSIG = 85.71% SF6removal 315 lbs of SF6 lost

• Recovery to 200 mmHg = 96.21% SF6removal 86 lbs of SF6 lost

Breakers with known leakage • Initially stop recovery process at 2 PSIG • Recover and store residual SF6into separate cylinders

SF6Handling –Gas Recovery Suggestions / Avoiding mistakes

• Always analyze/test gas before recovery • Standardize GIE fittings • Use properly sized recovery system/compressor

No replacement for displacement • Complete SF6recovery from GIE

Do not purposely release SF6to avoid air intrusion during recovery process (GIE leakage) In the equipment manufacturing and equipment maintenance during the use of advanced SF6 gas recovery unit, the recovery through a variety of filters used to remove the SF6 gas in the water, oils, dust, and other elements resultant decomposition

SF6Handling –Vacuuming

• Before closing breaker add new desiccant • Immediate air and moisture removal once GIE has been sealed • Vacuum reading only accurate at static pressure • Proper vacuuming instructions must include level (example: 1 Torr) and hold time

(example: 1 hour) This requires that after having the pump stopped for 1 hour, vacuum level is = < 1 Torr

• Gas-scavenging will speed up the process

Suggestions / avoiding mistakes • Use gas-scavenging whenever possible • Use properly sized vacuum pump

No replacement for displacement • Use least restrictive hose/fitting/connection • Properly perform vacuum raise test

SF6Handling –Filling

• Fill GIE using regulators only • Fill from upright cylinders only

Exception: Using filling equipment with integrated evaporator and filter • Apply heat to cylinders before filling

Use only thermostatically controlled heating blankets Limit heat to < 120 F

• Test SF6 again before energizing equipment.

SF6 Cylinder Handling • Only use weight to determine SF6content in cylinders

Page 259: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3

• As SF6is liquefied in cylinder, static vapor pressure cannot be used to determine SF6content

• Cylinders in storage should be separated Full Partial Empty

Environmental Considerations

• SF6is not an ozone depleting • One of (6) gases listed under Kyoto Protocol Because of its environmental unfriendly attributes SF6 was included in the Kyoto Protocol with the aim of emission reduction. Due to its excellent insulating and arc quenching properties it is globally used as insulating gas in high and medium voltage equipment like substations, switchgears, circuit breakers, transformers etc. • GWP 24,000 times higher than CO2 • Estimated atmospheric lifespan 3,200 years • EPA SF6 Emission Reduction Partnership

Page 260: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 17

Impact Mitigation Plan

Page 261: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

DE C EHS

Design Engineer Contractor/ Contractor’s Site ManagerManager EHS

DP CP OP

Design Phase of the Project Construction Phase of the Project Operation Phase of the Project

CM KESC

Compliance ManagerKESC Management

1

DE Compliance DP

2. Dust Suppression

C

C

Impact Mitigation Plan

No. Project Component or Impact Mitigation Measure Responsibility Parameters for

Monitoring

Project Phase

1. Project Design Consideration • Ensure that all aspects for health & safety of workers are considered at design phase.

• Ensure that regular water sprinkling will be done at all the unpaved surfaces during the construction activities.

C Physical Verification CP

• Ensure that the waste generated during construction activities and

3. Dumping of Construction Waste

4. Noise Pollution

5. Gaseous Emissions

6. Use of Personal Protective Equipment (PPEs)

7. Worker Trainings

equipment cleaning should be properly managed and disposed in an environmental friendly way.

• Equipment with high levels will be fitted with noise reduction devices & will only be used during regular working hours.

• Regular inspection and maintenance of the construction vehicle and equipment.

• Ensure use of PPEs such as ear plugs and ear muffs by the workers working in noisy areas and dealing with noisy machineries.

• Ensure that all construction vehicles and other equipment used during construction will be properly and regularly tuned and maintained.

• Ensuring the use of PPEs during the construction phase of the project. Appropriate PPEs should be provided to the workers as well as for site visitors.

• Ensuring that all workers whose work may have significant risk should be adequately skilled in term of experience or adequately

Compliance/ Physical Verification

CP C Compliance CP

C Compliance CP

Compliance/ Physical Verification

CP

C Compliance/ Training

CP

trained for performing their jobs. Records

8. Development & Use of Standard Operating Procedures

• Ensuring that “Standard Operating Procedures (SOP)” for all heavy machineries would be in place and use adequately.

C Compliance CP

9 Environmental Monitoring Plan

• Ensuring that “Environmental Monitoring Plan” should be strictly implemented and followed during the construction phase

C

Compliance/ Monitoring Records

CP Compliance/

10. SF6 containment • Ensuring that SF6 Containment plan will be followed EHS

11. Transformer Oil • Ensuring that waste oil will be collected, recycled and reused or Monitoring Records

OP Compliance/

disposed in accordance with MSDS EHS

Monitoring Records OP

• Ensure that the waste water generated during operation &

12. Waste water Management maintenance should be properly managed and disposed in an EHS Compliance/ Physical

OP

environmental friendly way. Verification

Page 262: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

DE C EHS

Design Engineer Contractor/ Contractor’s Site ManagerManager EHS

DP CP OP

Design Phase of the Project Construction Phase of the Project Operation Phase of the Project

CM KESC

Compliance ManagerKESC Management

2

15. Health & Safety

No. Project Component or Impact Mitigation Measure Responsibility Parameters for

Monitoring

Project Phase

13. Use of Personal Protective Equipment (PPEs)

• .Ensuring the use of PPEs during the operation phase of the project.

EHS

• Ensuring that all workers whose work may have significant risk

Compliance/ Physical Verification

OP

14. Competence & Training should be adequately skilled in term of experience or adequately CM Compliance/ Training

OP

trained for performing their jobs. Records

• Ensure provision of safe drinking water, PPEs, Hygienic eating places etc.

KESC Physical Verification CP & OP

16. EMF Monitoring • Ensuring that EMF Monitoring will be carried out at set Compliance/

frequency EHS

Monitoring Records OP

17 Environmental Monitoring Plan

• Ensuring that “Environmental Monitoring Plan” should be strictly implemented and followed during the operation phase.

EHS

Compliance/ Monitoring Records

OP

Page 263: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 18

Environmental Monitoring Plan

Page 264: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Environmental Monitoring Plan for KESC-132kV HIS Grid Station at Jauhar

Phase Parameters Locations Frequency Duration Standards

Noise

Operation

Decibels (dB) At the grid station and surrounding areas Biannually 24 hours WHO Guidelines

Solid waste

Operation O&M/Domestic waste At the grid station site Daily -- --

EMF Monitoring

Operation

EMF At the grid station site Biannually --- ICNIRP Guidelines

SF6 Monitoring

Operation Gas Pressure Monitoring At sealed gas compartment 2 Months -- --

Gas Leakage Test At sealed gas compartment 3 years -- --

Detailed Inspection At sealed gas compartment 6 years -- --

Transformer Oil

Operation

Dissolved Gas Analysis Transformer Oil -- -- As prescribed by Manufacturer

PCB Analysis Transformer Oil -- -- US-EPA

Page 265: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Annexure - 19

Disaster Management Plan

Page 266: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1

Disaster Management Plan at Proposed 132 kV HIS Grid Station

Potential Risk  Areas

Nature of Accident

I M P A C T S Management / Mitigation Measures

Human Health Grid Station Downstream Environment

A.  Transportation of Heavy Equipment

Roads 1. Heavy Vehicle Accident with other vehicles, Humans, Animals.

Injury to manpower

Damage to equipment – delay

‐‐ • Traffic management measures, signboard.

Project Site

2. Unloading Heavy 

Equipment

Injury to manpower

Damage to equipment – delay

‐‐

• Careful handling, experienced labor with proper tools. 

• Fencing the area. • Immediate Medical Attention

B.   Construction Phase Project Site

1. Mishap during construction activities

Injury, Fatal Injury Sickness

Damage to equipment‐delay

‐‐

• Provide First Aid Medical • Proper safeguard & supports for 

construction activities • Adequate OHS measures, rest 

hours • Fencing the area.

C.   Installation & Commissioning Phase Project Site 1.    General Injury 

2.    Fall from height Injury to man power Delay ‐‐ • Use of proper PPEs 

• Use of simple scaffoldings

3. Failure of any equipment Injury to 

manpower Equipment damage and delay ‐‐ • Mobile equipment / cranes to be 

well maintained

Work stoppage

• Fencing the area • Immediate Medical Attention

Page 267: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2

Potential Risk  Areas

Nature of Accident

I M P A C T S Management / Mitigation Measures

Human Health Grid Station Downstream Environment

D.   Operation Grid Station  & Allied Facilities 

Control Room

SF6 Leakage 

Electrical explosion /Sparking 

Short Circuiting 

Fire outbreak

Greenhouse Gas 

Splash on face of workers/Burn Injury 

Burn Injury

Affected Delayed 

Affected Delayed 

Affected Delayed

‐‐

• Acknowledge alarm and take 

action accordingly.  • Fire Extinguishers will be kept 

nearby.  • Immediate Medical Attention • Regular fire drills. • Grid Insurance.

 

Page 268: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “F”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “F”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “F”

Page 269: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

GSO- 1801/13/ 58/662Dated: 31st December, 2010

CIRCULAR NO. 58/ 2010

VOLUNTARY SEPARATION SCHEME (VSS)(For Non-Management Employees/ Workmen)

In line with the market trends, the Karachi Electric Supply Company has decided to offer aVoluntary Separation Scheme (VSS) to its non-management employee/ workmen (“employee”)in “non-core functions”.

Despite the fact that KESC has accumulated heavy losses over the past decade, the companyhas offered through this scheme sufficiently attractive and handsome benefits which ifprudently invested will not only enable the employee to plan for another career, but will alsoenable him to maintain a decent standard of living.

In some respects, the benefits being offered are unprecedented in the market. As a matter ofspecial consideration, a large number of employees with one year service are being offered alump sum gross payment of Rs. 700,000/-.

Needless to add that any loan or other forms of liability outstanding, against the non-management employee/workmen, shall be adjusted as a part of final settlement.

The scheme is purely voluntary. Each employee is requested to seriously consider the offerbeing made by the Management. Every non-management employee/ workman who are in“non-core functions” as indicated through personal communication to the concerned shouldevaluate the advantages of the scheme, and therefore make his choice in total freedom andunencumbered by any fear or hindrance.

Every non-management employee/ workman covered under the scheme shall receive aprovisional statement showing his estimated benefits. These calculations are subject to furtherverification and audit.

The workmen who elect to opt for the scheme may submit duly signed Option Form throughone of their respective Manager/ DGM/ GM/ Director (any one) for onward submission toHuman Resource Management Department on or before January 15th, 2011.

The details of the scheme are given below:

1. Eligibility Criteria

All non-management regular workmen of less than 59 years age in non-core roles. (listattached)

Page 270: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

This Scheme will not be applicable to the employees;

on probation on contract who have resigned

Employees under Disciplinary Action: Employees under disciplinary action or against whom anaction is likely to be taken may apply for the scheme, but decision on their VSS option will betaken at the sole discretion of the Company after the finalization of disciplinary action.

Please note that: VSS is a discretionary Scheme. The Company having the sole discretion to decide

whether to accept the option of resignation under VSS. The Company reserves the rightto refuse the VSS Option without assigning any reason.

This Scheme is a one-time offer for a limited period which will expire at the close ofbusiness on January 15th, 2011.

This Scheme will not in any way create a precedent for the future, and is being made asa very special case and in exceptional circumstances.

2. Time Period

This Scheme is valid up to January 15th, 2011. Those who elect to opt for VSS must submit their‘VSS Option Forms’ within this date.

3. VSS Incentive Payment (Scheme details)

The following benefits will be admissible to those who elect to opt for this scheme and theiroption is accepted:

I. Employees under 58 years of age as on January 31, 2011:Ex-Gratia Payment - Four month basic salary for each remaining year of servicewith a minimum of 25 and a maximum of 85 basics

II. Employees between 58 – 59 years age bracket as on January 31, 2011:Ex-Gratia Payment - One basic salary for each remaining month of service

III. Employees of 59 years of age or more as on January 31, 2011 shall NOT be eligible forVSS.

Entitlement:

1. Provident Fund – as per the existing rules.2. Gratuity – as per the existing rules/ entitlement

Page 271: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3. Leave Encashment – Encashment of un-availed privilege leave balance on the date ofrelease.

4. Upfront Payment of Post-Retirement Benefits shall be paid as:i. Medical – 7.5 basic salary

ii. Electricity – for five (5) years

Minimum Guaranteed Payment:

As a matter of special consideration it has been decided that minimum gross payout will beRs. 700,000/-.

4. Mode of Payment

The net payout amount will be split in to two tranches: 75% of the amount will be paid in cashupfront at the time of separation and the remaining 25% will be paid in the form of3-year Term Finance Certificates to be issued by KESC. The Term Finance Certificates (TFCs) willpay an expected profit rate of 16%-17% per annum, through a monthly coupon. Repayments ofthe TFC’s will be two equal principal installments, paid at the end of years 2 and 3 of the term.The TFCs will be listed on the Karachi Stock Exchange, and will be traded on the exchange. TheCompany will also endeavor to secure liquidity or discounting facility from one or morecommercial banks to allow employees to encash the TFCs upfront. Employees should be awarethat encashment may result in the realized amount being lower than the face value of the TFCs,depending on the discount rate, fees and charges applied by the bank (s).

The objective of converting 25% of payout in the form of TFCs is to ensure that a reasonableportion of the VSS payout is invested in savings instruments that generate an attractivemonthly income. The expected profit rate on KESC’s TFCs will be at or above the rates offeredby similar instruments available through National Savings Scheme.

5. Final Settlement

The final settlement will be made within one month of the last working day of the employee, subject toclearance from all concerned/adjustment of any loan/finance payable to the Company.

6. Procedure

Those who select to opt for the scheme should fill in the prescribed ‘VSS Option Form’ andsubmit it to their respective Manager/ DGM/ GM/ Director (any one), who will duly approve itand shall forward it Human Resource Management Department.

7. Other Terms & Conditions

7.1 This Scheme is independent and without prejudice to the rights of the Company todispense with the services of a non-management employee/ workman.

Page 272: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

7.2. This Scheme is discretionary and the Company reserves the right, in its sole andabsolute discretion, to accept or reject any VSS Option Form submitted to it by an eligibleemployee, without

assigning any reason whatsoever.

7.3. This Scheme is a one-time offer and the option once exercised by the employee withinthe prescribed time frame shall be final and cannot be withdrawn.

7.4. Income tax will be deducted in accordance with the tax laws.

7.5. The Company reserves the right at any time to alter, amend, add or dispense with anyor all of the rules, terms and/ or conditions defined in this Scheme.

On behalf of Karachi Electric Supply Company Management

Page 273: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 274: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 275: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 276: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 277: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 278: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “G”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “G”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “G”

Page 279: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 280: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 281: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 282: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 283: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “H”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “H”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “H”

Page 284: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 285: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 286: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “I”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “I”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “I”

Page 287: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 288: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 289: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 290: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “J”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “J”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “J”

Page 291: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

LIST OF INDUSTRIAL ACCIDENT CASES OF WORKMEN DURING THE PERIOD

FROM July 2011 TO June 2012

SNoName of

EmployeeEmp.

NoDepartment

Date ofAccident

Category Cause ofAccident

Lost Time

Major Minor Fatal Day Hours

1 M. Ishaque 8799 Opn. Abuzar(N.Naz)

09.07.2011 Fatal ElectricShock

0 0

2 M. Arif 9239 NWDKorangi

03.08.2011 Fatal ElectricShock

0 0

3 Niaz Ahmed 15677 VIBC Tipu(OC-IV)

10.08.2011 Major ElectricShock (Flash)Fell down

37 296

4 Arif Tanoli 14269 Transm.(O/H)

11.08.2011 Major Fell downfrom CraneBucket

207 1656

5 M. Shafiq 1150 Opn.Korangi

15.08.2011 Fatal Fell Downfrom PMTStructure

0 0

6 S. DanishNafees Zaidi

14109 NW Malir 17.09.2011 Minor Fell downfrom MTLLadder

5 40

7 Rashid Khan 14906 SSM (R-I)DFS

11.10.2011 Minor Barri (IronRod) Slippedand hit him

0 0

8 MukhtarAhmed

3555 Opn. (R-IV) 18.10.2011 Minor ElectricShock

0 0

Page 292: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

9 M. Yaseen 13531 NW Landhi(Sherpao)

18.11.2011 Minor ElectricShock

61 488

10 MalikMuhammad

9370 UGM (R-II)Defence

19.11.2011 Major Fell downalogn withdamagedpole

11 MuhammadNazeer

5625 IBC Uthal 04.01.2012 Fatal Electricshock & FellDown

0 0

12 GhulamAbbas

6221 UGM(Society) R-II

15.01.2012 Major MTL Hit byMazda Coach

81 648

13 Saleem Khan 6364 UGM(Society) R-II

15.01.2012 Major MTL Hit byMazda Coach

0 0

14 KhalidMehmood

3848 Operation(R-I) DFS

24.02.2012 Major DuringCrossingRoad hit byTwo vehicles

127 1016

15 Afzal 13619 VIBC Lyari 01.03.2012 Major SustainedElectricCurrent &Fell Downfrom MTL

121 968

16 GhulamMurtaza

3896 Operation(R-I)

04.04.2012 Fatal Electricshock & FellDown

0 0

Page 293: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

17 MuhammadSafdar

5256 Operation(R-I)

04.04.2012 Minor MinorElectricShock

0 0

18 MuhammadAslam

8786 UGM 'A'Div. (R-III)

12.04.2012 Major UndergroundCableFlashed

29 232

19 M. Tariq Aziz 8816 GSM(South)

31.05.2012 Minor Minor flashon face andhands

1 8

20 ShabbirAhmed

6991 BQPS 05.06.2012 Major Due to shiftvan accident

25 200

21 Babar Khan 14030 IBC KIMZ 17.06.2012 Minor Slipped fromMTL

13 104

Total Working Hours Lost 707 5,656

Page 294: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “K”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “K”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “K”

Page 295: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Summary of Air Emissions Performance of KESC during the reporting period 2011-12:

InstalledCapacity(MW)

GrossGeneratrion(GWh): A

GasConsumed(MMBtu)

Fuel OilConsumed(MMBtu)

SulfurContentofFuelOil(%)Max: Ave

SOxEmissions(tonSO2 /MMBtu):B

SOxEmissionsRate(gSO2

/kWh):C=B/A

NOxEmissions(tonNOxasNO2):D

NOxEmissionRate(gNOx/kWh):E=D/A

BinQasimThermalPS

1,260 4704 26,710,845 22,598,330 3% 33611 7.1 *

KorangiThermalPS

125 163 2,131,677 0 NA NA NA

KorangiTownGT

20 0 0 0 NA NA NA

SITE GasTurbines 20 0 0 0 NA NA NA

BQExpansion Units

560 1140 10,216,949 0 NA NA NA

KorangiCCPP 220 1011 8,481,676 0 NA NA NA

GEjanbacherSGTPS II

88 416 3,975,712 0 NA NA NA

GEJanbacherKTGTPSII

88 595 5,868,252 0 NA NA NA

KESCTotal 2381 8029 57,385,109 23,158,464 0 33611 7

NA: Not Applicable

* NOx performance is measure by third party for compliance monitoring to NEQS and is provided inQuarterly Reports as APPENDIX – “L”

Page 296: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

History of Air Emissions Performance of KESC

Emission Indicator 2006(E)

2007 2008 2009 2010 2011 2012

SO2 (gSO2 / kWh) 7

NOx (gNOx / kWh)

Performance Evaluation of the SOx has commenced from 2011 and is hence stated above. SOx and NOxparameters are regularly monitored for their compliance to NEQS.

Page 297: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “L”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “L”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “L”

Page 298: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

3rd QTR MonitoringReport of Gaseous

Emissions & Effluent(July-Sept 2011)

Page 299: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

BIN QASIM POWER STATION (BQPS) – 3rd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Bin Qasim Thermal Power Plant

(Reporting Period: Jul-Sep 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 32 372 pH value 6-9 6-9 6-9 7.61 7.693 BOD5 mg/l 80 250 80 50 534 COD mg/l 150 400 400 200 1705 Oil & Grease mg/l 10 10 10 1 16 Total Dissolved Solids mg/l 3500 3500 3500 39990 39120 *Higher7 Total Suspended Solids mg/l 200 400 200 43 42

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 300: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 301: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 302: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 303: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

BIN QASIM POWER STATION (BQPS) – 3rd QTR

Gaseous Emission Monitoring ReportFuel Used: F Oil /Natural gas

# Parameters NEQS(mg/Nm3)

Turbine1 2 3 4 5 6

1 CO 1700 16.0 37.33 20.67 21 189.00 760.72 NOx 400 114.67 297.67 249.67 163 107.33 183.73 SO2 - 81.00 502.67 809.67 701 42.33 196.74 Particulate Matter (PM) 300 90.00 253.33 273.33 60 193.3 146.7

Page 304: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 305: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 306: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

COMBINE CYCLE POWER PLANT (CCPP) - 3rd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Combined Cycle Power Plant

(Reporting Period: Jul-Sep 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 33 392 pH value 6-9 6-9 6-9 7.79 7.853 BOD5 mg/l 80 250 80 72 784 COD mg/l 150 400 400 200 2705 Oil & Grease mg/l 10 10 10 BDL BDL6 Total Dissolved Solids mg/l 3500 3500 3500 38540 38060 *Higher7 Total Suspended Solids mg/l 200 400 200 29 29

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 307: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 308: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 309: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 310: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

COMBINE CYCLE POWER PLANT (CCPP) - 3rd QTR

Gaseous Emission Monitoring ReportFuel Used: Natural Gas

# Parameters NEQS (mg/Nm3)Turbine

1 2 3 41 CO 1700 267.0 450.00 34.00 29.52 NOx 400 68.00 242.00 86.00 62.53 SO2 - 10.00 23.00 12.00 11.54 Particulate Matter (PM) 300 100.00 140.00 193.00 140

Page 311: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 312: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 313: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) – 3rd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: KTGTPS

(Reporting Period: Jul-Sep 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 312 pH value 6-9 6-9 6-9 8.433 BOD5 mg/l 80 250 80 644 COD mg/l 150 400 400 1205 Oil & Grease mg/l 10 10 10 16 Total Dissolved Solids mg/l 3500 3500 3500 6907 Total Suspended Solids mg/l 200 400 200 5

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 314: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) – 3rd QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 1 South Section 1 North Section 2 South Section 2 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 599.3 529.7 558.3 542.7 609.7 683 665.7 551.3 576 523.7 516.7 522.3 286.7 425.0 416.3 491.0

2 NOx 400 308.3 341.3 278.7 226.3 265.3 212.5 201.7 362.0 302 330.7 271.0 277.3 166 201.7 256.0 199.5

3 SO2 - 311 294.0 273.0 212.3 260.0 241.5 213.7 357.0 246.5 242.0 279.7 225.3 126 195.3 275.3 224.5

4 Particulate Matter(PM) 300 43.3 84.4 35.5 77.8 115.5 115 45.5 54.4 165.0 122.2 106.7 151.1 133 147.8 176.7 63.3

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 3 South Section 3 North Section 4 South Section 4 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 609.0 636.3 638.0 543.7 522 559.3 486.5 557.3 428.7 483.7 540.0 490.0 499.3 512.33 582.3 537.0

2 NOx 400 423.3 393.7 353.3 406.7 511 417.0 273.0 436.7 242.0 278.3 358.0 374.7 286.7 243.7 286.7 314.3

3 SO2 - 255.0 298.7 240.7 358.7 431.7 407.3 298 449.0 260.5 280.0 387.7 351.7 395.7 344.7 333.0 346.7

4 Particulate Matter(PM) 300 124.4 151.1 102.2 90 137.8 110.0 155 126.7 186.7 143.3 65.5 134.4 132.2 91.1 85.5 136.7

Page 315: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 316: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 317: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 318: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 319: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 320: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) – 3rd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: SGTPS

(Reporting Period: Jul-Sep 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 352 pH value 6-9 6-9 6-9 7.673 BOD5 mg/l 80 250 80 724 COD mg/l 150 400 400 2005 Oil & Grease mg/l 10 10 10 BDL6 Total Dissolved Solids mg/l 3500 3500 3500 11007 Total Suspended Solids mg/l 200 400 200 8

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 321: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) – 3rd QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 1 South Section 1 North Section 2 South Section 2 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 507.7 530 478.3 485.3 523.0 498 534 490.3 538.3 598 516.7 553.3 505.7 607.3 474.7 522.33

2 NOx 400 373.0 363.0 310.0 348.7 277.7 333.3 353.5 376.0 330.3 260.7 335.7 353.7 346.3 289.0 320.3 422.33

3 SO2 - 332.7 258.5 315.7 320.7 280.7 306 295.5 393.0 323.0 261.0 300.7 325.3 303 254.7 294.3 364.67

4 Particulate Matter(PM) 300 146.7 110 100 168.7 139.33 91 103 136.7 212.3 168.33 126.7 172.0 258.7 174.3 154.7 206.67

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 3 South Section 3 North Section 4 South Section 4 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 553.3 493.0 543 477.3 494 563.0 520.33 521.7 429.7 518 576.67 507.7 479.5 509 561.7 486.3

2 NOx 400 367.3 361.7 383 289.3 305 275.0 333.33 321.3 270.0 320 333.67 320.3 342.5 378.7 414.0 390.7

3 SO2 - 487 339.7 339 395.0 306 332.0 380.00 383.3 251.3 335 356.7 330.0 302.5 448.3 404.0 326.7

4 Particulate Matter(PM) 300 236.7 165.3 191 213.3 199 110.0 175.33 108.7 96.3 240 141.0 53.3 60 110 163.3 150

Page 322: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 323: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 324: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 325: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 326: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 327: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

4th QTR MonitoringReport of Gaseous

Emissions & Effluent(Oct-Dec 2011)

Page 328: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

BIN QASIM POWER STATION (BQPS) – 4th QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Bin Qasim Thermal Power Plant

(Reporting Period: Oct-Dec 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 32 342 pH value 6-9 6-9 6-9 7.67 7.73 BOD5 mg/l 80 250 80 60 564 COD mg/l 150 400 400 150 1405 Oil & Grease mg/l 10 10 10 1 16 Total Dissolved Solids mg/l 3500 3500 3500 36850 36930 *Higher7 Total Suspended Solids mg/l 200 400 200 6 5

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Gaseous Emission Monitoring ReportFuel Used: F Oil /Natural gas

# Parameters NEQS(mg/Nm3)

Turbine1 2 3 4 5 6

1 CO 1700 33.0 62.00 57.00 26 105.00 14.02 NOx 400 112.00 248.00 283.00 127 141.00 177.03 SO2 - 50.00 39.00 210.00 310 96.00 97.04 Particulate Matter (PM) 300 140.00 160.00 273.33 40 120.0 190.0

Page 329: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

COMBINE CYCLE POWER PLANT (CCPP) - 4th QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Combined Cycle Power Plant

(Reporting Period: October-Dec 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 32 342 pH value 6-9 6-9 6-9 7.45 7.483 BOD5 mg/l 80 250 80 84 704 COD mg/l 150 400 400 220 1905 Oil & Grease mg/l 10 10 10 BDL BDL6 Total Dissolved Solids mg/l 3500 3500 3500 38700 38610 *Higher7 Total Suspended Solids mg/l 200 400 200 5 5

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Gaseous Emission Monitoring ReportFuel Used: Natural Gas

# Parameters NEQS (mg/Nm3)Turbine

1 2 3* 41 CO 1700 567.0 49.00 162 NOx 400 184.00 69.00 283 SO2 - 200.00 21.00 84 Particulate Matter (PM) 300 80.00 20.00 40

*Note: due to low pressure Unit # 3 was shut down

Page 330: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) – 4th QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: KTGTPS

(Reporting Period: October-Dec 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 312 pH value 6-9 6-9 6-9 8.433 BOD5 mg/l 80 250 80 644 COD mg/l 150 400 400 1205 Oil & Grease mg/l 10 10 10 16 Total Dissolved Solids mg/l 3500 3500 3500 6907 Total Suspended Solids mg/l 200 400 200 5

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 331: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) – 4th QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 1 South Section 1 North Section 2 South Section 2 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 301.0 340.0 386.0 516.0 612.0 603 642.0 626.0 564 631.0 541.0 574.0 684.0 446.0 611.0 593.0

2 NOx 400 0.0 0.0 0.0 594.0 376.0 234 283.0 221.0 267 214.0 379.0 324.0 425 364.0 469.0 333.0

3 SO2 - 0 0.0 0.0 464.0 293.0 305 294.0 312.0 245 307.0 452.0 269.0 326 311.0 289.0 215.0

4 Particulate Matter(PM) 300 60.0 55.0 50.0 340.0 240.0 420 280.0 140.0 60.0 140.0 180.0 100.0 240 160.0 40.0 180

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 3 South Section 3 North Section 4 South Section 4 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 624.0 511.0 428.0 315.0 490 514.0 544.0 410.0 386.0 457.0 511.0 407.0 476.0 521.00 493.0 583.0

2 NOx 400 384.0 284.0 290.0 300.0 350 310.0 390.0 286.0 296.0 386.0 331.0 252.0 272.0 334.0 306.0 369.0

3 SO2 - 291.0 205.0 358.0 250.0 310.0 340.0 415 310.0 350.0 325.0 296.0 274.0 321.0 264.0 287.0 323.0

4 Particulate Matter(PM) 300 20.0 120 100.0 120 20.0 200.0 260 200.0 20.0 240.0 140.0 60.0 100.0 120.0 80.0 60.0

Page 332: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) - 4th QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: SGTPS

(Reporting Period: Oct-Dec 11)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 332 pH value 6-9 6-9 6-9 7.693 BOD5 mg/l 80 250 80 1384 COD mg/l 150 400 400 3515 Oil & Grease mg/l 10 10 10 16 Total Dissolved Solids mg/l 3500 3500 3500 11107 Total Suspended Solids mg/l 200 400 200 14

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Note: No monitoring of gaseous emissions was carried out in thequarter as all engines were shut down due to low gas pressure.

Page 333: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

EFFLUENT

Page 334: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 335: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 336: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report
Page 337: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

1st QTR MonitoringReport of Gaseous

Emissions & Effluent(Jan-Mar 2012)

Page 338: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

BIN QASIM POWER STATION (BQPS) - 1st QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Bin Qasim Thermal Power Plant

(Reporting Period: Jan-Mar 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 25 20.62 pH value 6-9 6-9 6-9 7.83 7.963 BOD5 mg/l 80 250 80 39 384 COD mg/l 150 400 400 90 905 Oil & Grease mg/l 10 10 10 BDL BDL6 Total Dissolved Solids mg/l 3500 3500 3500 20000 182407 Total Suspended Solids mg/l 200 400 200 20 54.4

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Gaseous Emission Monitoring ReportFuel Used: F Oil

# Parameters NEQS(mg/Nm3)

Turbine1 2 3 4 5 6

1 CO 1700 639.7 237.33 206.67 32 413.67 410.52 NOx 400 163.33 278.67 229.33 393 125.33 585.53 SO2 - 1999.00 2099.67 2254.33 2004 809.33 29814 Particulate Matter (PM) 300 329.67 208.67 293.00 178 211 453

Page 339: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

COMBINE CYCLE POWER PLANT (CCPP) - 1st QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Combined Cycle Power Plant

(Reporting Period: Jan-Mar 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 18.5 212 pH value 6-9 6-9 6-9 7.8 83 BOD5 mg/l 80 250 80 11 144 COD mg/l 150 400 400 590 6205 Oil & Grease mg/l 10 10 10 BDL BDL6 Total Dissolved Solids mg/l 3500 3500 3500 37015 38060 *Higher7 Total Suspended Solids mg/l 200 400 200 10 40

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Gaseous Emission Monitoring ReportFuel Used: Natural Gas

# Parameters NEQS (mg/Nm3)Turbine

1 2 3 41 CO 1700 23.3 37.00 23.00 22.52 NOx 400 61.00 83.00 80.00 493 SO2 - 42.67 74.00 35.00 21.54 Particulate Matter (PM) 300 120.33 211.50 186.00 153

Page 340: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) - 1st QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: KTGTPS

(Reporting Period: Jan-Mar 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 212 pH value 6-9 6-9 6-9 8.273 BOD5 mg/l 80 250 80 284 COD mg/l 150 400 400 935 Oil & Grease mg/l 10 10 10 36 Total Dissolved Solids mg/l 3500 3500 3500 6207 Total Suspended Solids mg/l 200 400 200 20

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 341: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) - 1st QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 1 South Section 1 North Section 2 South Section 2 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 189.3 336 338.7 509.7 327.3 281 338 323.5 211 363 336 401 321 225 308 223

2 NOx 400 62.3 77.3 51.3 121.7 31.0 67 53.7 45.5 54 94 130 224 84 115 80 58

3 SO2 - 48.5 60.7 65.7 61.3 55.3 39 62 61.5 34 63 60 77 54 43 60 43

4 Particulate Matter(PM) 300 18 18 15 16 16 18 19 21 22 24 19 20 19 23 24 18

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 3 South Section 3 North Section 4 South Section 4 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 379 277 285 274 296 320.5 336 358.5 341 469.5 346.5 283.5 324 289.5 422.5 404.5

2 NOx 400 42.5 45 88.5 13 110.5 86.5 48 71 68 77 65.5 112.5 101 89.5 68.5 68.5

3 SO2 - 59.5 29.5 38.5 49 49.5 43 44.5 53 63 75.5 40 25.5 17 15.5 57 67

4 Particulate Matter(PM) 300 16 17 19 19 19 24 21 20 17 19 15 18 20 20 24 22

Page 342: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) - 1st QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: SGTPS

(Reporting Period: Jan-Mar 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 252 pH value 6-9 6-9 6-9 7.383 BOD5 mg/l 80 250 80 294 COD mg/l 150 400 400 825 Oil & Grease mg/l 10 10 10 16 Total Dissolved Solids mg/l 3500 3500 3500 8807 Total Suspended Solids mg/l 200 400 200 4

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 343: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) - 1st QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# ParametersNEQS

(mg/Nm3

)Section 1 South

Section 1North

Section 2South

Section 2 North

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 41 CO 1700 351

.0293

316.5

332.5

361.5

360

340

318.5

445

502

374.5

340.5

340.5

397.5

419

345.5

2 NOx 400 159.0

73.5

86.5

69.0

53.0 73 52.

084.5 65 52 44 31 55.

5 69 66.5

48.5

3 SO2 - 31 37.0

51.5

30.0

47.5

38.5 43 46 71.

5 89 51.5 53 64 61.

5 47 36

4 ParticulateMatter (PM) 300 15 16 17 18 22 21 19 17 25 21 21 19 25 19 19 19

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# ParametersNEQS

(mg/Nm3

)Section 3 South

Section 3North

Section 4 South Section 4 North

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 41 CO 1700 419 46

9 384 255 247.5

289

375.5 328 362

.5353.5 344 351 315

.5 456 397

335.5

2 NOx 400 133 58 96 77 40 62.5 55 70 89.

5 56 74 63 73 88 58.5

77.5

3 SO2 - 60 63 60 31 40 28.5 56 46 46 35.

5 66 177 46 74 68.5 77

4 ParticulateMatter (PM) 300 23 21 21 17 17 17 21 17 21 21 19 17 22 19 23 17

Page 344: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

2nd QTR MonitoringReport of Gaseous

Emissions & Effluent(Apr-June 2012)

Page 345: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

BIN QASIM POWER STATION (BQPS) – 2nd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Bin Qasim Thermal Power Plant

(Reporting Period: April-June 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 32 32.672 pH value 6-9 6-9 6-9 7.61 83 BOD5 mg/l 80 250 80 50 534 COD mg/l 150 400 400 200 1705 Oil & Grease mg/l 10 10 10 0 06 Total Dissolved Solids mg/l 3500 3500 3500 39990 57800 *Higher7 Total Suspended Solids mg/l 200 400 200 43 56.33

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Gaseous Emission Monitoring ReportFuel Used: F Oil /Natural gas

# Parameters NEQS(mg/Nm3)

Turbine1 2 3 4 5 6

1 CO 1700 161.0 191.00 0.00 0 14.00 5.02 NOx 400 166.00 157.00 0.00 0 127.00 153.03 SO2 - 77.00 318.00 0.00 0 12.00 41.04 Particulate Matter (PM) 300 190.00 100.00 0.00 0 80.0 60.0

Page 346: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

COMBINE CYCLE POWER PLANT (CCPP) - 2nd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: Combined Cycle Power Plant

(Reporting Period: April-June 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS Sea

WaterWastewater

Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 29.6 342 pH value 6-9 6-9 6-9 7.8 83 BOD5 mg/l 80 250 80 25 274 COD mg/l 150 400 400 570 6005 Oil & Grease mg/l 10 10 10 0 06 Total Dissolved Solids mg/l 3500 3500 3500 45866 45924 *Higher7 Total Suspended Solids mg/l 200 400 200 29 29

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Gaseous Emission Monitoring ReportFuel Used: Natural Gas

# Parameters NEQS (mg/Nm3)Turbine

1 2 3 41 CO 1700 25.0 17.00 1.00 02 NOx 400 51.00 64.00 3.00 03 SO2 - BDL BDL BDL 04 Particulate Matter (PM) 300 50.00 90.00 75.00 0

Page 347: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) – 2nd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: KTGTPS

(Reporting Period: April-June 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 312 pH value 6-9 6-9 6-9 8.433 BOD5 mg/l 80 250 80 644 COD mg/l 150 400 400 1205 Oil & Grease mg/l 10 10 10 16 Total Dissolved Solids mg/l 3500 3500 3500 6907 Total Suspended Solids mg/l 200 400 200 5

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 348: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

KORANGI TOWN GAS TURBINE POWER STATION (KTGTPS) – 2nd QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 1 South Section 1 North Section 2 South Section 2 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 173.0 130.0 112.0 104.0 129.0 84 201.0 148.0 190 175.0 223.0 136.0 160.0 221.0 391.0 402.0

2 NOx 400 23.0 33.0 20.0 18.0 27.0 18 33.0 48.0 93 45.0 75.0 52.0 54 47.0 72.0 100.0

3 SO2 - 10 26.0 24.0 12.0 19.0 20 44.0 48.0 36 24.0 29.0 48.0 30 43.0 71.0 29.0

4 Particulate Matter(PM) 300 20.0 50.0 60.0 20.0 40.0 25 60.0 20.0 80.0 100.0 50.0 40.0 20 110.0 90.0 40

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 3 South Section 3 North Section 4 South Section 4 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 0.0 79.0 221.0 41.0 404 410.0 203.0 245.0 290.0 0.0 190.0 207.0 198.0 209.00 171.0 142.0

2 NOx 400 0.0 37.0 86.0 10.0 80 86.0 42.0 90.0 89.0 0.0 91.0 77.0 85.0 90.0 69.0 56.0

3 SO2 - 0.0 10.0 40.0 72.0 77.0 49.0 37 86.0 28.0 0.0 42.0 51.0 63.0 42.0 79.0 28.0

4 Particulate Matter(PM) 300 0.0 60 90.0 40 20.0 40.0 80 100.0 80.0 0.0 100.0 110.0 40.0 20.0 60.0 90.0

Page 349: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) – 2nd QTR

KARACHI ELECTRIC SUPPLY COMPANYName of Unit/Site: SGTPS

(Reporting Period: April-June 12)Liquid Effluent Monitoring Report

# Parameters UnitNEQS

Waste water Remarks1 2 3

1 Temperature 0C 40=<3 40=<4 40=<5 352 pH value 6-9 6-9 6-9 7.673 BOD5 mg/l 80 250 80 724 COD mg/l 150 400 400 2005 Oil & Grease mg/l 10 10 10 BDL6 Total Dissolved Solids mg/l 3500 3500 3500 11007 Total Suspended Solids mg/l 200 400 200 8

NEQS: National Environmental Quality Standard1: NEQS for Municipal & Industrial effluent into Inland water2: NEQS for Municipal & Industrial effluent into Sewage Treatment3: NEQS for Municipal & Industrial effluent into SeaBDL: Below Detectable LimitAcc to NEQS 2000; “The conc. of pollutant in water being used will be subtracted from the effluent for calculating the NEQSlimits”.

Page 350: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

SITE GAS TURBINE POWER STATION (SGTPS) – 2nd QTR

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 1 South Section 1 North Section 2 South Section 2 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 305.0 410 349.0 293.0 0.0 369 0 258.0 365.0 349 320.0 389.0 383.0 405.0 344.0 386.00

2 NOx 400 75.0 59.0 62.0 71.0 0.0 58.0 0.0 88.0 64.0 32.0 52.0 39.0 60.0 48.0 76.0 129.00

3 SO2 - 54.0 83.0 66.0 57.0 0.0 80 0 57.0 83.0 80.0 80.0 97.0 94 103.0 100.0 106.00

4 Particulate Matter(PM) 300 60.0 40 100 75.0 0.00 90 0 100.0 120.0 90.0

0 80.0 120.0 80.0 90.0 60.0 75.00

Gaseous Emission Monitoring ReportGE Janbacher Gas Engine 90 MW

# Parameters NEQS(mg/Nm3)

Section 3 South Section 3 North Section 4 South Section 4 North1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 CO 1700 0.0 0.0 0 351.0 399 179.0 386.00 363.0 0.0 0 0.00 0.0 0 0 0.0 0.0

2 NOx 400 0.0 0.0 0 70.0 40 43.0 40.00 82.0 0.0 0 0.00 0.0 0 0.0 0.0 0.0

3 SO2 - 0 0.0 0 94.0 109 89.0 102.00 109.0 0.0 0 0.0 0.0 0 0.0 0.0 0.0

4 Particulate Matter(PM) 300 0.0 0.0 0 90.0 95 100.0 120.00 110.0 0.0 0 0.0 0.0 0 0 0.0 150

Page 351: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “M”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “M”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “M”

Page 352: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

EHS AUDIT OF T & D ASSETS

(FINDINGS AND RECOMMENDED ACTIONS)

Page 353: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

As per point ‘3’ of IFC action plan, dated October 23, 2009, external audit was required to be undertaken. External auditors wereselected, who conducted an EHS audit of our T&D assets. All stakeholders are being provided relevant audits findings forimplementation of recommendations. The same shall be followed up by corporate HSE dept. and final report be forwarded to IFCrepresentative as part of our quarterly progress report due in June 2010.

Major findings, action required and responsibilities along with implementation schedule are enumerated below:

S. No. Findings Required Actions Status Responsibility

1. Identification andManagement of PCBContaminatedSubstance

Identify PCB substances in your area /equipment

Label PCB Substance Provide/arrange suitable PCB

management training for staff Adopt sound handling, maintenance

and transportation of PCB equipment(Like Transformers, capacitors etc)

Provide adequate storage of PCBwaste

Investigate the availability of PCBdisposal techniques suitable to thePCB waste characteristics.

Transformer oil containing PCBswere added in the system inearly 1960s in US AID, in 1970owing to effects of oil we startedreplacing the equipment and oil.Now there is no PCB in our oil.(Closed)

GM (GSM- Ejaz Rashid)

GM (Transformer W/S – AbuQasim Nayeem)

2. Handling & Storage ofhazardous substanceother than PCB (Acid,Chemicals, cleaners,thinners, surfactantsetc):

Keep & Maintain records of handledhazardous substances (Like Acids,caustics, chemicals, batteries, paints,thinners, surfactant, cleaners etc)

Ask MSDS (Material Safety DataSheet) to be supplied with everyhazardous material by the supplier

IM maintained MSDS has beentranslated & displayed.Awareness training withtranslation in Urdu is alsoarranged & displayed inconcerned areas

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (IM- Sikandar AliChandio)GM (Transmission – Bilal

Page 354: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Provide MSDS awareness to relevantstaff

Provide secondary containment forstorage areas

Investigate the possibility of replacingsome mineral oils with biodegradableoils.

(Closed) Ahmed Mirza)GM (S/S – Ilyas Mansoor)

3. Soil Contamination: Keep records of existingcontaminated spots in your area

Minimizing spills risks Clean-up and remediate

contaminated soil in different assets.

Maintaining the record ofcontaminated spots.At workstation max efforts arebeing made to avoid oil spillage.Trays and stands are been usedat centrifuging to avoid oilspillage.

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim)GM’s (S/S- Ilyas Mansoor)

4. Hazardous WasteManagement:

Keep inventory records for hazardouswaste

Transfer scattered items in gridstations to Baldia scrap yard

Apply availabledecontamination/disposal procedures

Establish hazardous waste collectionareas in grid stations and in Baladeyascrap yard

Investigate access to licensedhazardous waste disposal facilities /vendors

As an alternative, investigate thepossibility of establishing hazardouswaste cell in Baladeya scrap yard

Procedure has been formed

Scrap record maintained andmax waste has been transferred.The practice is on going.(Closed)

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (IM- Sikandar AliChandio)GM (Transmission – BilalAhmed Mirza)GM (S/S – Ilyas Mansoor)

Page 355: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

5. Non- HazardousWaste Management:

Keep records of scrap items Transfer accumulated items to Baldia

scrap yard. Investigate waste minimization

procedures Keep records of ration of recycled

waste.

Record maintained.Process of transferringaccumulated items to Baldiascrap yard is in practice(Closed)

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (Transmission – BilalAhmed Mirza)GM (S/S – Ilyas Mansoor)

6. Health Risks ofAsbestos:

Keep inventory records for allAsbestos Contained Materials used inT&D assets

Undertake air sampling to identifyareas of un-safe exposure

Adopt safe containment and disposaltechnique for existing asbestos scrap

Provide asbestos managementtraining to your staff

Apply safe operation andmaintenance procedures to assetscontaining ACMs

Apply safe encapsulation and/or safereplacement of disturbed ACMsurfaces

Investigate the possibility of safereplacement all ACM surfaces, toeliminate the risk

Asbestos management workingbeing done with collaboration ofcivil & safety deptt. They havebeen involved to either removeor manage theasbestos/operation control asper safety regulatorycompliance.

Damaged patches have beenrecorded and requisiteoperational control has beenadopted. Continuous Periodicmonitoring of asbestos is beingdone through timely applicationof operational control.Management has decided toreplace the sound asbestossheets in second phase(Closed)

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (IM- Sikandar AliChandio)GM (Transmission – BilalAhmed Mirza)GM (S/S – Ilyas Mansoor)

7. Waste water Characterize quantity and quality of Adhoc operational control of Oil GM (Transformer W/S – Abu

Page 356: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

discharge fromTransformerworkshop:

the wastewater Prepare tender document for a

suitable treatment unit Erect a suitable treatment unit using

gravity oil separation or dissolved airfloatation along with monitoringeffluent quality and adequatehandling of sludge

separation has been adopted.Structured waste watertreatment has been formulatedand will be taken up on shiftingof washing work station to newsite at DFS Yard.(On going)

Qasim Nayeem)

9. Birds & PlantsBiodiversity:

Keep records of plantation (Tree)cutting and birds' fatality due tocollision with or electrocution bypower lines

Undertaking ornithological analysis inEIAs of future extension of the T&Dgrid

Whenever bushes/herbs cuttingis done a record is maintained(Closed)

GM (Transmission – BilalAhmed Mirza)

GM (Corporate Compliance –Chander Perkash)

11. SF6 Management tominimize fugitiveemissions:

Keep inventory records of used SF6 Monitor equipment with fugitive

(Leak, break etc) emissions andrepair/replace such equipment

Keep integrity of used cylinders forpossibly reuse

Investigate the possibility of SF6recovery during maintenance.

We have attended the 53.19% ofSF6 leakages.We are planning to attendbalance leakages by changingthe gaskets and busting disks.Maintaining the record.

GM (GSM – Ejaz Rashid)GM (IM – Sikandar AliChandio)

12. CFCs(Chlorofluorocarbon)Management tominimize fugitiveemissions:

Keep inventory records of used R-22and other ODS (Ozone DepletionSubstance)

Monitor equipment with fugitive(Leak, Break etc) emissions andrepair/replace such equipment

N.A GM (Special Projects / FAD –Maj. Tariq Ali)

Page 357: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Gradually phase out R-22 and applyprocurement policy for using non-ODS units in the future

13. EMF Management: Keep records of EMF emissions(Corporate HSE will provide)

Assess occupational exposures foremployees (How much time they areexposing while carrying routinemaintenance in S/S and grid withhigher EMF values)

EMF of almost 364 equipments& lines have been measured,which include 11kv switches,132 kv lines , Power / AutoTransformer s, 132 kv breaker,220 kv lines, 220 kv circuitbreaker.It is ongoing process.Record is maintained.(Closed)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)

14. HSE Representativesof BU’s:

Ensure your knowledge, roles andresponsibilities according to thelegislative framework (HSEProcedures, work method, techniquesetc).

HSEQ Coordinators from eachdepartment have beennominatedKnowledge, roles andresponsibilities have beenwritten in Manual of Grid &Transmission Systems.Job has been assigned andgetting improvement.Improving the knowledge day byday.Trainings are conducted on theregular basis.And record of TBT, Safety walk

Grid representative – (ZaheerAhmed Shaikh)H/T representative – (IlyasMansoor)Transformer w/Srepresentative- Mr. Sohail

Page 358: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

and other activities is beingmaintained(Closed)

15. LeadershipCommitment &Accountability:

Establish the scope, priority and pacefor implementation of the EHS system

Establish EHS system that ensuresthat expectations are translated intoprocedures and practices

Establish clear goals and objectivesfor the system

Evaluate performance against thesegoals and objectives

Considering the complexity and risksinvolved with your operations

Know and exercise roles,responsibilities, authorities andaccountabilities for the system

Ensure active participation andinvolvement of employees and sharelessons learned through practiceConsult, support and work with theJEHS (Joint Occupational Health andsafety committees)

Accident prevention planprepared, duly approved by HSEDeptt for implementation.System has established fortransferring the planning inprocedures and practices. Andare maintaining the record.Have planned clear goal andobjects for the system.Have fixed the roles,responsibilities, authorities andaccountabilities for the system.

(Closed)

Director (GSM- Syed AbrarAli)Director (Transmission –Shahid HussainDirector (HT – Zaheer HussainRizvi)

16. Communications: Established means of inter- Sector(departmental) communications tospread information on EHS relatedmatters (i.e. inspection checklists,hazardous occurrences) Share best

Ample Safety signs have beendisplayed and added oncontinuous basis as per workingconditions.Adequate reporting mechanism

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (Transmission – BilalAhmed Mirza)

Page 359: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

practices methods Establish formal means for

communicating with designateddepartmental experts (Herecorporate HSE) in certain EHS relatedtopics for legal or safety relatedinformation

Develop process in place to generateand compile S&H information(including accidents, spills, illnessesand other occurrences) for internaland Central Agency use (HereCorporate HSE)

Develop mechanism for timely,accurate and complete reporting ofinformation to the appropriateauthorities (either internal orexternal) relating to S&H (Safety &Health)

Establish mechanisms in place toconduct follow-up investigations,issue reports and revise policies ifrequired.

Introduce employee AssistanceProgram in matters relating to S&H

Establish approval, record and reviewsystem for Safety documentation

of reporting /documenting/recurringprevention actions taken andfollowed in line with HSEQdirectivesWe have fixed the minimummonthly meeting on the safetyaffairs. We are communicatingwith HSE.We are compiling theinformation regarding policies.We are maintaining record.Compiling the incident andaccident reports.Maintaining the record ofminutes of meeting and allrelevant documents.Procedure of investigation iscarried out by HSEQ(Closed / Ongoing)

GM (S/S – Ilyas Mansoor)

17. EHS Trainings: Start EHS orientation program formanagers focusing on, regulatory

On- Going, Trainings plan is inplace and trainings are being

Corporate HSEQ

Page 360: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

requirement, safety concepts, properhandling of hazardous material andreporting occurrences

Start process for Identifying EHStraining needs for staff; this willinclude training for both regulatoryrequirements and workplace SOPs

Make EHS training needs as part ofthe annual performance appraisalprocess

Prepare annual EHS plan whichreflects employee training needs soas to link the identification process,training scheduled and performanceappraisals

Start training for emergency responseand preparedness.

Provide published, accessible, ERPprocedures available to staff

conducted round the year dulyapproved by HSEQ Deptt andrecorded in line with procedurespelled out by HSEQ.

18. Work Procedures /SOP’s

Develop / Write work procedures(SOP’s) and state a step-by- stepmethod to perform a proceduresafely and properly

Maintain a permanent file to keep allSOP’s on critical tasks

Review file periodically and updatedby a front line supervisor / Manager.

State / Describe / prepare apreventative maintenance program

SOPs/ Work Instruction alreadyexist and new SOPs are beingdeveloped as and when needed.(Closed/ Ongoing)

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (Transmission – BilalAhmed Mirza)GM (S/S – Ilyas Mansoor)

Page 361: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

Establish monitoring systems toensure hazardous substances areproperly labeled Keep MSDS(Material Substance Data Sheets)with material so that they areavailable for staff reference

19. Ergonomics: Consider ergonomics part of S&H On-Going. Corporate HSEQ

20. Format Preparation /(Paper tools)

Prepare logs, forms, check sheets,model reports, and registers fordocumentation of various proceduresand events related to EHS.

Logs and sheets are beingimplemented and updatedaccordingly.SOPs are regularly developed &updated(Closed / Ongoing)

GM (GSM-Ejaz Rashid)GM (Transformer W/S – AbuQasim Nayeem)GM (Transmission – BilalAhmed Mirza)GM (S/S – Ilyas Mansoor)

21. Hazard Analysis: Carry out planned, periodic andsystematic analysis of potentialhazards at the work site throughactual observations of taskperformance and a discussion ofpotential situations.

Develop a set of in-place proceduresto ensure that new or revisedpreventative measures includingIndustrial hygiene factors arrived atthrough hazard analysis or workplacemeasurement are incorporated intostandard operating procedures and

Hazard Analysis has been doneperiodically incrementalimprovement is in process.(Closed / On going)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim)

Page 362: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

EHS training. Develop a process whereby

consideration is given to S&H issueswhile planning for changes tooperations, reduction in staff.

22. Safety InstructionsPreparation &Implementation:

Document Safety instructions onimportant work procedures orequipment operations in asafety/operating manual

Make manual accessible and availableall the times for staff reference

Safety instructions should havefactored in the requirements ofcentral agency guidelines/directivesand appropriate Acts and theirassociated Regulations.

Work Instructions are in placeand reviewed periodically.Manual has already beenprepared which fulfill theserequirementsTrainings are conducted for allthe staff & officersSite visit being done for verifyingthe implementation(Closed / Ongoing)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

23. Provision of PPE’s: Determined the need for protectiveequipment for those exposed tohazardous materials or proceduresthrough a periodic review ofoperations

PPE must be provided to thoseemployees identified as beingexposed to a stressor

Take steps to ensure that equipmentmeets the safety requirements of theSafety Code / standards.

The PPEs are procured &supplied on regular intervals asper KESC policy.Live line Tester etc have beenprovided for safe operation andworking by staffNo officer & staff are allowed toattend the site without properPPEs.(Closed/Ongoing)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

Page 363: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

24. EmergencyPreparedness andResponse Plan:

Prepare an emergency plan for yourfacility which: assigns responsibilityfor the plan; contains acommunication plan element;provides for emergency responseteams which has received trainingand have designated backups;ensures emergency evacuation, fireor other emergency.

Accident prevention plandeveloped and duly approved byHSEQ deptt for Implementation.ERP plan has been prepared andgot approved.

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

25. Formation of safetyCommittees:

Identify employees who have clearroles and responsibilities as memberof safety committee

Senior management to be active andvisible in Safety committee meetingsand deliberations

Establish written guidelines for safetycommittee members on their rolesand responsibilities regarding EHSissues, their access to records andinformation and their authority inregards to the correction of EHSissues deemed by them to beunsatisfactory.

Formal Structure duly approvedby HSEQ in place and effectivelyoperated.(Closed)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

26. Self Inspection andAuditing:

Carry out periodic Inspections using apre-established check list of reviewelements or modules

Safety Walks by line Managerand Check Sheet is in use. NextInternal Audit to be carried outon Wednesday.We have developed new Auditforms /check list and visitactivity form for self audit of grid

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

Page 364: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

stationsCompliance is being checkedand recorded(Closed)

27. Incident ReportingSystem:

Report and investigate hazardoussituations or incidents promptly

Assign a risk factor or priority forcorrecting the identified deficiency

Establish time frame to correct thedeficiency

Assign responsibility clearly to correctthe deficiency

Review status of corrective actionregularly by the respective Safetycommittee

Correct and rectify hazardoussituations promptly

Establish process to ensure thatpersonnel have been identified to beresponsible for input of accurateinformation in reporting systems

Devise a reporting system to provideemployees the opportunity to reportdeficiencies without fear ofretaliation or retribution

Formal occurrence reportingsystem is in practice anddocumented and trend reviewedon Monthly basis by centralManagement Review meetingon trend analysis.(Closed On going)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

28. ApproachingPhysician:

Encourage employees to seek medicalattention and medical testingImplement medical surveillance

Vaccination by IHU is donePeriodically and as and whenneeded.

IHU- Dr. Badar- ul- HudaGM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)

Page 365: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

examinationsEstablish periodic medical checkupsfor staff.

Preparation of schedule formedical testing of staff is inpipeline with HSEQ(Closed/ Pending)

GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

29. Chemical Inventories: Prepare a list of chemical used /stored in your dept.

Establish Permissible Exposure Limits Up keep proper house-keeping Establish chemical waste

management system

Preventive/precautionarymeasures needed vide MSDShave been pasted on workstations for easyimplementation reference.Effective awareness andmotivations tools are used forcontinuous improvementresulting in WINNING ofOrganizational Annual SafetyAward.(Closed / On going)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)GM (IM – Sikandar AliChandio)

30. MachineSafeguarding:

Prepare list of all machines Replace old machine by new one Adopt / apply machine safeguarding

for all moving parts Isolate all dangerous operations

List of Machineries maintained.Requisite addition/ Up gradationcontinuous featureAdequate SafeguardingAdopted.(Closed / Ongoing)

GM (GSM- Ejaz Rashid)GM (S/S – Ilyas Mansoor)GM (Transmission – BilalAhmed Mirza)GM (Transformer W/S – AbuQasim Nayeem)

CHANDER PERKASHG M (Corporate Compliance)

Page 366: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “N”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “N”

ASIAN DEVELOPMENT BANK QUERIES KESC

APPENDIX “N”

Page 367: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

ELECTROCUTION CASES FROM JULY 2011 TO JUNE 2012

SNO AGE REASON AREA DATE

1 6 Year OldGirl Touched live broken wire lying on road Kamran Chowrngi 22-Jul-11

2 Boy Electrocution due to H.T O/H was nearly crossing Basera Tower 4-Aug-11

3 Girl Electrocuted from a stay wire Ravian Society Gulistan-E-Johar 6-Aug-11

4 Man Electrocuted by falling in to digged area with HT cable Khayaban-E-Mujahid 9-Aug-11

5 13/14 YearBoy OH LT wire broke and fell directly on the boy Sector-II, Surjani 13-Aug-11

6 08 Years OldChild

Electrocuted by return current of existing hook connection"kunda" at pole

B-203,Block-4A,SahafiColony Park, 17-Aug-11

7 Man Attemping conductor theft KDA Chorangi NorthNazimabad 6-Sep-11

8Girl In

Between 10-15 Years Old

Electricution during current heavy rain in korangi. Baraf Wali PMT, Sector34/1, Korangi 6-Sep-11

9 A Person Electrocuted Ghonghat ShahdiHall,Lakhnow Society 6-Sep-11

10 Girl 4 Years Touching wall where kunda wire tied House # L-433 Sector 34/3Korangi 7-Sep-11

11 Man Iron rod touched HT line while construction work Near Gul Mohd Pmt OldMuzafarabad 9-Sep-11

12 Boy Pole current Babar Mkt. Stop NearLucky Sweets 10-Sep-11

1302 Women &02 Children Touching telephone wire used for Kunda Near Choona Bhatti Misri

Maojee Street 10-Sep-11

14 Man Changing kunda Pole 44 Gulbahar 10-Sep-1115 Boy 12 Years Touching Steel pipe of Shop Iqbal Market Dolly Khata 10-Sep-11

Page 368: Annual Environment & Social Monitoring Report …Annual Environment & Social Monitoring Report (July 2011 to June 2012) – Part 2 of 2 The Environmental and Social Performance Report

16 Man Wire broken Shop#17 Mateen ArcadeBlock 7 Gulshan 10-Sep-11

17 Man Pole current Model A Pmt ModelColony 10-Sep-11

18 Man Wire broken Badar ManzilI.I.Chandregar Road 10-Sep-11

19 Women Confirmation by Concerned VIBC awaited Kharader 10-Sep-11

20Person

Electrocuted Electrocuted due to wire broken/wires fallen in rain water Market (Mobilink Pmt) 13-Sep-11

21 PersonElectrocuted Electrocuted, as he came in contact with electric pole. D Area Qayoomadab 13-Sep-11

22 ChildElectrocuted Electrocution due to leakage of current Gulshan-E-Hadeed, Phase

–II. 14-Sep-11

23 Thief Shock while attempting theft of HT Conductor 12-Oct-11

24 Thief Victim was cutting HT conductor with a cutter when the feederwas normalized and he was electrocuted 16-Nov-11

25 Unknown Coming in contact with internal wiring of consumers duringcleaning shelter of shop Karim Centre Saddar 26-Feb-12

26 Private MTLDriver HT broken wire on Pole 58 feeder( tripped at 1800 hrs) in Samo Goth 29-Apr-12

27 Small GirlAged 3 Years

Came in contact with L.T pole through which current waspassing due to kunda and Korangi 12-Jun-12