Analisa Harga Satuan Pekerjaan Pengecatan Diposkan : 05 Juni 2014 Oleh : Endang Kusman No. URAIAN SAT VOLUME HARGA SAT HARGA N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama - Soda api Kg 0.0500 35,600.00 1,780.00 - Pekerja Oh 0.1500 42,000.00 6,300.00 - Mandor Oh 0.0025 80,000.00 200.00 Jumlah 8,280.00 Dibulatkan 8,280.00 N-02 1 M2 Mendempul Dan Menggosok Kayu - Dempul Kg 0.0800 35,800.00 2,864.00 - Minyak cat Kg 0.0200 38,400.00 768.00 - Batu apung Kg 0.0100 29,600.00 296.00 - Pekerja Oh 0.0400 42,000.00 1,680.00 - Tukang cat Oh 0.0400 65,000.00 2,600.00 - Kepala tukang Oh 0.0040 75,000.00 300.00 - Mandor Oh 0.0025 80,000.00 200.00 Jumlah 8,708.00 Dibulatkan 8,708.00 N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve - Plamir Kg 0.1500 25,000.00 3,750.00 - Cat dasar Kg 0.1700 30,000.00 5,100.00 - Cat penutup setara sieve 2x Kg 0.1700 41,700.00 7,089.00 - Pekerja Oh 0.0700 42,000.00 2,940.00 - Tukang cat Oh 0.0750 65,000.00 4,875.00 - Kepala tukang Oh 0.0075 75,000.00 562.50 - Mandor Oh 0.0025 80,000.00 200.00 Jumlah 24,516.50 Dibulatkan 24,517.00 N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve - Cat meni Kg 0.2000 30,400.00 6,080.00 - Plamir Kg 0.1500 25,000.00 3,750.00 - Cat dasar Kg 0.1700 30,000.00 5,100.00 - Cat penutup 3x setara sieve Kg 0.3500 41,700.00 14,595.00 - Pekerja Oh 0.0700 42,000.00 2,940.00 - Tukang cat Oh 0.1050 65,000.00 6,825.00 - Kepala tukang Oh 0.0040 75,000.00 300.00 - Mandor Oh 0.0025 80,000.00 200.00 Jumlah 39,790.00 Dibulatkan 39,790.00 Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-pengecata... 1 of 4 10/10/2014 18:49

Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB

Embed Size (px)

DESCRIPTION

111

Citation preview

Page 1: Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB

Analisa Harga Satuan Pekerjaan PengecatanDiposkan : 05 Juni 2014Oleh : Endang Kusman

No. URAIAN SAT VOLUME HARGA SAT HARGA

N-01 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama- Soda api Kg 0.0500 35,600.00 1,780.00- Pekerja Oh 0.1500 42,000.00 6,300.00- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 8,280.00Dibulatkan 8,280.00

N-02 1 M2 Mendempul Dan Menggosok Kayu- Dempul Kg 0.0800 35,800.00 2,864.00- Minyak cat Kg 0.0200 38,400.00 768.00- Batu apung Kg 0.0100 29,600.00 296.00- Pekerja Oh 0.0400 42,000.00 1,680.00- Tukang cat Oh 0.0400 65,000.00 2,600.00- Kepala tukang Oh 0.0040 75,000.00 300.00- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 8,708.00Dibulatkan 8,708.00

N-03 1 M2 Pengecatan Bidang Kayu Lama Setara Sieve- Plamir Kg 0.1500 25,000.00 3,750.00- Cat dasar Kg 0.1700 30,000.00 5,100.00

- Cat penutup setarasieve 2x Kg 0.1700 41,700.00 7,089.00

- Pekerja Oh 0.0700 42,000.00 2,940.00- Tukang cat Oh 0.0750 65,000.00 4,875.00- Kepala tukang Oh 0.0075 75,000.00 562.50- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 24,516.50Dibulatkan 24,517.00

N-04 1 M2 Pengecatan Bidang Kayu Baru Setara Sieve- Cat meni Kg 0.2000 30,400.00 6,080.00- Plamir Kg 0.1500 25,000.00 3,750.00- Cat dasar Kg 0.1700 30,000.00 5,100.00

- Cat penutup 3x setarasieve Kg 0.3500 41,700.00 14,595.00

- Pekerja Oh 0.0700 42,000.00 2,940.00- Tukang cat Oh 0.1050 65,000.00 6,825.00- Kepala tukang Oh 0.0040 75,000.00 300.00- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 39,790.00Dibulatkan 39,790.00

Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-pengecata...

1 of 4 10/10/2014 18:49

Page 2: Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB

N-05 1 M2 Pelaburan Bidang Kayu dengan Politur- Politur Ltr 0.1500 48,000.00 7,200.00- Politur jadi Ltr 0.3720 112,700.00 41,924.40- Ampelas Lbr 2.0000 5,000.00 10,000.00- Tukang cat Oh 0.0600 65,000.00 3,900.00- Kepala tukang Oh 0.0160 75,000.00 1,200.00- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 64,424.40Dibulatkan 64,424.00

N-06 1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter- Residu atau ter Ltr 0.3500 8,100.00 2,835.00- Pekerja Oh 0.1000 42,000.00 4,200.00- Mandor Oh 0.0060 80,000.00 480.00

Jumlah 7,515.00Dibulatkan 7,515.00

N-07 1 M2 Pengecatan Tembok BaruSetara ICI- Plamir tembok Kg 0.1000 25,000.00 2,500.00- Cat dasar Kg 0.1000 30,000.00 3,000.00

- Cat penutup 2x setaraICI Kg 0.2600 75,000.00 19,500.00

- Pekerja Oh 0.0200 42,000.00 840.00- Tukang cat Oh 0.0630 65,000.00 4,095.00- Kepala tukang Oh 0.0063 75,000.00 472.50- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 30,607.50Dibulatkan 30,608.00

N-08 1 M2 Pengecatan Tembok Lama Setara ICI- Cat dasar Kg 0.1200 30,000.00 3,600.00- Cat penutup 2 x Kg 0.1800 75,000.00 13,500.00- Pekerja Oh 0.0280 42,000.00 1,176.00- Tukang cat Oh 0.0420 65,000.00 2,730.00- Kepala tukang Oh 0.0042 75,000.00 315.00- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 21,521.00Dibulatkan 21,521.00

N-09 1 M2 Pengecatan Plafond ( 3x ) Setara ICI- Cat tembok setara ICI Kg 0.2000 75,000.00 15,000.00- Plamir tembok Kg 0.1600 25,000.00 4,000.00- Rol cat Bh 0.0100 32,500.00 325.00- Steger werk Ls 1.0000 1,000.00 1,000.00- Ampelas Lbr 0.5000 5,000.00 2,500.00- Pekerja Oh 0.2000 42,000.00 8,400.00- Tukang cat Oh 0.3000 65,000.00 19,500.00- Kepala tukang Oh 0.0300 75,000.00 2,250.00- Mandor Oh 0.0100 80,000.00 800.00

Jumlah 53,775.00Dibulatkan 53,775.00

N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex

- Cat tembok setaraVinilex Kg 0.2000 25,000.00 5,000.00

- Plamir tembok Kg 0.1600 25,000.00 4,000.00- Rol cat Bh 0.0100 32,500.00 325.00- Steger werk Ls 1.0000 1,000.00 1,000.00- Ampelas Lbr 0.5000 5,000.00 2,500.00- Pekerja Oh 0.2000 42,000.00 8,400.00- Tukang cat Oh 0.3000 65,000.00 19,500.00

Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-pengecata...

2 of 4 10/10/2014 18:49

Page 3: Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB

- Kepala tukang Oh 0.0300 75,000.00 2,250.00- Mandor Oh 0.0100 80,000.00 800.00

Jumlah 43,775.00Dibulatkan 43,775.00

N-10-r'1 M2 Pengecatan Plafond ( 2x ) Setara Vinilex

- Cat tembok setaraVinilex Kg 0.1300 25,000.00 3,250.00

- Plamir tembok Kg 0.1100 25,000.00 2,750.00- Rol cat Bh 0.1000 32,500.00 3,250.00- Steger werk Ls 0.6700 1,000.00 670.00- Ampelas Lbr 0.3300 5,000.00 1,650.00- Pekerja Oh 0.1300 42,000.00 5,460.00- Tukang cat Oh 0.2000 65,000.00 13,000.00- Kepala tukang Oh 0.0200 75,000.00 1,500.00- Mandor Oh 0.0100 80,000.00 800.00

Jumlah 32,330.00Dibulatkan 32,330.00

N-11 1 M2 Memasang Wallpaper- Wallpaper m2 1.2000 55,700.00 66,840.00- Lem Perekat Kg 0.2500 35,700.00 8,925.00- Pekerja Oh 0.3500 42,000.00 14,700.00- Tukang cat Oh 0.1750 65,000.00 11,375.00- Kepala tukang Oh 0.0170 75,000.00 1,275.00- Mandor Oh 0.0017 80,000.00 136.00

Jumlah 103,251.00Dibulatkan 103,251.00

N-12 1 M2 Pengecatan Permukaan Baja dengan Meni Besi- Meni besi Kg 0.1000 30,400.00 3,040.00- Kuas 3" Bh 0.0100 16,000.00 160.00- Pekerja Oh 0.0200 42,000.00 840.00- Tukang cat Oh 0.2000 65,000.00 13,000.00- Kepala tukang Oh 0.0200 75,000.00 1,500.00- Mandor Oh 0.0100 80,000.00 800.00

Jumlah 19,340.00Dibulatkan 19,340.00

N-13 1 M2 Pengecatan Permukaan Baja dengan Meni Besi dan Perancah- Meni besi Kg 0.1000 30,400.00 3,040.00- Kuas 3" Bh 0.0100 16,000.00 160.00- Kayu perancah m3 0.0020 2,069,800.00 4,139.60- Pekerja Oh 0.2500 42,000.00 10,500.00- Tukang cat Oh 0.2250 65,000.00 14,625.00- Kepala tukang Oh 0.0225 75,000.00 1,687.50- Mandor Oh 0.0075 80,000.00 600.00

Jumlah 34,752.10Dibulatkan 34,752.00

N-14 1 M2 Pengecatan Permukaan Baja Lapis seng (galbani) secara manual 1lps cat 2 um- Cat besi setara ICI Kg 0.3000 67,700.00 20,310.00- Pekerja Oh 0.0060 42,000.00 252.00- Tukang cat Oh 0.0600 65,000.00 3,900.00- Kepala tukang Oh 0.0120 75,000.00 900.00- Mandor Oh 0.0060 80,000.00 480.00

Jumlah 25,842.00Dibulatkan 25,842.00

N-15 1 M2 Pengecatan Tembok Baru Setara Vinilex (2 x laburan)- Plamir tembok Kg 0.1000 25,000.00 2,500.00- Cat dasar Kg 0.1000 30,000.00 3,000.00

Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-pengecata...

3 of 4 10/10/2014 18:49

Page 4: Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB

- Cat penutup 2x setaravinilex Kg 0.2600 25,000.00 6,500.00

- Pekerja Oh 0.0200 42,000.00 840.00- Tukang cat Oh 0.0630 65,000.00 4,095.00- Kepala tukang Oh 0.0063 75,000.00 472.50- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 17,607.50Dibulatkan 17,608.00

N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)- Plamir tembok Kg 0.1000 25,000.00 2,500.00- Cat dasar Kg 0.1000 30,000.00 3,000.00

- Cat penutup 3x setaravinilex Kg 0.3900 25,000.00 9,750.00

- Pekerja Oh 0.0300 42,000.00 1,260.00- Tukang cat Oh 0.0945 65,000.00 6,142.50- Kepala tukang Oh 0.0095 75,000.00 712.50- Mandor Oh 0.0038 80,000.00 304.00

Jumlah 23,669.00Dibulatkan 23,669.00

N-16 1 M2 Pengecatan Tembok Lama Setara Vinilex- Cat dasar Kg 0.1200 30,000.00 3,600.00- Cat penutup 2 x Kg 0.1800 25,000.00 4,500.00- Pekerja Oh 0.0280 42,000.00 1,176.00- Tukang cat Oh 0.0420 65,000.00 2,730.00- Kepala tukang Oh 0.0042 75,000.00 315.00- Mandor Oh 0.0025 80,000.00 200.00

Jumlah 12,521.00Dibulatkan 12,521.00

Kembali ke AHS-SNI

Copyright @ 2014 softwarerab.com. All rights reserved

Contact | About | Sitemap | Privacy | XHTML- Feed | G+ | G++ | Valid RSS

Analisa Harga Satuan Pekerjaan Pengecatan - Software RAB http://www.softwarerab.com/analisa-harga-satuan-pekerjaan-pengecata...

4 of 4 10/10/2014 18:49