6
Analisa Harga Satuan Pekerjaan Penutup Besi dan Aluminium Analisa Harga Satuan Pekerjaan Penutup Besi dan Aluminium Diposkan : 01 Juni 2014 Oleh : Endang Kusman No. URAIAN SAT VOLUME HARGA SAT HARGA (Rp) (Rp) K-01 1 Kg Besi profil - Besi profil WF Kg 1.1000 24,000.00 26,400.00 - Meni besi Kg 0.0800 30,400.00 2,432.00 - Pekerja Oh 0.0600 42,000.00 2,520.00 - Tukang besi Oh 0.0060 65,000.00 390.00 - Kepala tukang Oh 0.0060 75,000.00 450.00 - Mandor Oh 0.0003 80,000.00 24.00 Jumlah 32,216.00 Dibulatkan 32,216.00 K-02 1 Kg Perakitan baja - Solar m' 0.0100 7,150.0000 71.50 - Minyak pelumas m' 0.0010 55,000.0000 55.00 - Sewa alat jam 0.0080 100,000.0000 800.00 - Pekerja Oh 0.0010 42,000.0000 42.00 - Tukang besi Oh 0.00001 65,000.0000 0.65 - Kepala tukang Oh 0.00001 75,000.0000 0.75 - Mandor Oh 0.00005 80,000.0000 4.00 Jumlah 973.90 Dibulatkan 974.00 K-03 1 Cm Pengelasan dengan las listrik - kawat las kg 0.0400 23,600.00 944.00 - Solar ltr 0.0300 7,150.00 214.50 - Minyak pelumas ltr 0.0040 55,000.00 220.00 - Sewa alat jam 0.0170 100,000.00 1,700.00 - Pekerja org 0.0040 42,000.00 168.00 - Tukang org 0.0020 65,000.00 130.00 - Kepala Tukang org 0.0002 75,000.00 15.00 - Mandor org 0.0002 80,000.00 16.00 Jumlah 2,463.50

Analisa Harga Satuan Besi Dan Aluminium Bayu

Embed Size (px)

DESCRIPTION

deskripsi

Citation preview

Page 1: Analisa Harga Satuan Besi Dan Aluminium Bayu

Analisa Harga Satuan Pekerjaan Penutup

Besi dan Aluminium

Analisa Harga Satuan Pekerjaan Penutup

Besi dan Aluminium

Diposkan : 01 Juni 2014

Oleh : Endang Kusman

No. URAIAN SAT VOLUME HARGA SAT HARGA

(Rp) (Rp)

K-01 1 Kg Besi profil

- Besi profil WF Kg 1.1000 24,000.00 26,400.00

- Meni besi Kg 0.0800 30,400.00 2,432.00

- Pekerja Oh 0.0600 42,000.00 2,520.00

- Tukang besi Oh 0.0060 65,000.00 390.00

- Kepala tukang Oh 0.0060 75,000.00 450.00

- Mandor Oh 0.0003 80,000.00 24.00

Jumlah

32,216.00

Dibulatkan

32,216.00

K-02 1 Kg Perakitan baja

- Solar m' 0.0100 7,150.0000 71.50

- Minyak pelumas m' 0.0010 55,000.0000 55.00

- Sewa alat jam 0.0080 100,000.0000 800.00

- Pekerja Oh 0.0010 42,000.0000 42.00

- Tukang besi Oh 0.00001 65,000.0000 0.65

- Kepala tukang Oh 0.00001 75,000.0000 0.75

- Mandor Oh 0.00005 80,000.0000 4.00

Jumlah

973.90

Dibulatkan

974.00

K-03 1 Cm Pengelasan dengan las listrik

- kawat las kg 0.0400 23,600.00 944.00

- Solar ltr 0.0300 7,150.00 214.50

- Minyak pelumas ltr 0.0040 55,000.00 220.00

- Sewa alat jam 0.0170 100,000.00 1,700.00

- Pekerja org 0.0040 42,000.00 168.00

- Tukang org 0.0020 65,000.00 130.00

- Kepala Tukang org 0.0002 75,000.00 15.00

- Mandor org 0.0002 80,000.00 16.00

Jumlah

2,463.50

Page 2: Analisa Harga Satuan Besi Dan Aluminium Bayu

Dibulatkan

2,464.00

K-04 1 m2 Pintu Rolling Door

- Rolling door M2 1.0000 306,600.00 306,600.00

- Pekerja Oh 1.0500 42,000.00 44,100.00

- Tukang besi Oh 1.5000 65,000.00 97,500.00

- Kepala tukang Oh 0.1050 75,000.00 7,875.00

- Mandor Oh 0.0052 80,000.00 416.00

Jumlah

456,491.00

Dibulatkan

456,491.00

K-05 1 m2 Pintu Alluminium Natural

- Pintu alluminium natural m2 1.0000 211,800.00 211,800.00

- Pekerja Oh 1.0500 42,000.00 44,100.00

- Tukang besi Oh 1.0500 65,000.00 68,250.00

- Kepala tukang Oh 0.1050 75,000.00 7,875.00

- Mandor Oh 0.0052 80,000.00 416.00

Jumlah

332,441.00

Dibulatkan

332,441.00

K-06 1 m2 Terali Besi

- Besi strip 2 x 3 m' 11.5000 5,500.00 63,250.00

- Pekerja Oh 1.2000 42,000.00 50,400.00

- Tukang las Oh 1.2000 65,000.00 78,000.00

- Kepala tukang Oh 0.0120 75,000.00 900.00

- Mandor Oh 0.0006 80,000.00 48.00

Jumlah

192,598.00

Dibulatkan

192,598.00

K-07 1 m2 Kawat Harmonika 4 cm

- Kawat harmonika M2 1.1000 35,900.00 39,490.00

- Paku biasa ½" - 1" kg 0.0200 23,800.00 476.00

- Papan kayu kamper M2 0.0018 5,692,600.00 10,246.68

- Pekerja Oh 0.1000 42,000.00 4,200.00

- Tukang kayu Oh 0.1000 65,000.00 6,500.00

- Kepala tukang Oh 0.0100 75,000.00 750.00

- Mandor Oh 0.0050 80,000.00 400.00

Jumlah

62,062.68

Dibulatkan

62,063.00

K-08 1 m' Talang Datar, Seng BJLS 28 lebar

90 cm

- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05

- Paku biasa ½" - 1" Kg 0.0150 23,800.00 357.00

- Kayu papan borneo super M3 0.0096 5,595,800.00 53,719.68

- Flincote / meni besi Kg 0.2500 30,400.00 7,600.00

- Pekerja Oh 0.1500 42,000.00 6,300.00

- Tukang kayu Oh 0.4000 65,000.00 26,000.00

- Kepala tukang Oh 0.0250 75,000.00 1,875.00

- Mandor Oh 0.0013 80,000.00 104.00

Page 3: Analisa Harga Satuan Besi Dan Aluminium Bayu

Jumlah

117,796.73

Dibulatkan

117,797.00

K-09 1 m' Talang Miring, Seng BJLS 28 lebar

90 cm

- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05

- Paku biasa ½" - 1" Kg 0.0150 23,800.00 357.00

- Kayu papan borneo super M3 0.0190 5,595,800.00 106,320.20

- Flincote / meni besi Kg 0.3000 30,400.00 9,120.00

- Pekerja Oh 0.2000 42,000.00 8,400.00

- Tukang kayu Oh 0.4000 65,000.00 26,000.00

- Kepala tukang Oh 0.0250 75,000.00 1,875.00

- Mandor Oh 0.0013 80,000.00 100.00

Jumlah

174,013.25

Dibulatkan

174,013.00

K-10 1 m' Talang 1/2 lingkaran D-15 cm, seng

pelat BJLS 28 lebar 90 cm

- Seng plat 3' x 6' BJLS 30 m' 1.0500 20,801.00 21,841.05

- Paku biasa ½" - 1" Kg 0.1000 23,800.00 2,380.00

- Kayu papan borneo super kg 0.0190 5,595,800.00 106,320.20

- Besi strip Kg 0.5000 26,800.00 13,400.00

- Pekerja Oh 0.1500 42,000.00 6,300.00

- Tukang kayu Oh 0.3000 65,000.00 19,500.00

- Kepala tukang Oh 0.0300 75,000.00 2,250.00

- Mandor Oh 0.0080 80,000.00 640.00

Jumlah

172,631.25

Dibulatkan

172,631.00

K-11 1 m' Pasang kusen pintu/jendela

alluminium natural 4"

- Alumunium profil natural 4" m' 1.1000 151,100.00 166,210.00

- Skrup fixer bh 2.0000 250.00 500.00

- Sealant m' 1.0000 7,500.00 7,500.00

- Pekerja Oh 0.0430 42,000.00 1,806.00

- Tukang kayu Oh 0.0430 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.50

- Mandor Oh 0.0021 80,000.00 168.00

Jumlah

179,301.50

Dibulatkan

179,302.00

K-12 1 m' Pasang kusen pintu/jendela

alluminium warna 4"

- Alumunium profil warna 4" m' 1.1000 163,000.00 179,300.00

- Skrup fixer bh 2.0000 250.00 500.00

- Sealant m' 1.0000 7,500.00 7,500.00

- Pekerja Oh 0.0430 42,000.00 1,806.00

- Tukang kayu Oh 0.0430 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.50

Page 4: Analisa Harga Satuan Besi Dan Aluminium Bayu

- Mandor Oh 0.0021 80,000.00 168.00

Jumlah

192,391.50

Dibulatkan

192,392.00

K-13 1 m' Pasang kusen pintu/jendela

alluminium natural 3"

- Alumunium profil natural 3" m' 1.1000 81,000.00 89,100.00

- Skrup fixer bh 2.0000 250.00 500.00

- Sealant m' 1.0000 7,500.00 7,500.00

- Pekerja Oh 0.0430 42,000.00 1,806.00

- Tukang kayu Oh 0.0430 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.50

- Mandor Oh 0.0021 80,000.00 168.00

Jumlah

102,191.50

Dibulatkan

102,192.00

K-14 1 m' Pasang kusen pintu/jendela

alluminium warna 3"

- Alumunium profil warna 3" m' 1.1000 102,000.00 112,200.00

- Skrup fixer bh 2.0000 250.00 500.00

- Sealant m' 1.0000 7,500.00 7,500.00

- Pekerja Oh 0.0430 42,000.00 1,806.00

- Tukang kayu Oh 0.0430 65,000.00 2,795.00

- Kepala tukang Oh 0.0043 75,000.00 322.50

- Mandor Oh 0.0021 80,000.00 168.00

Jumlah

125,291.50

Dibulatkan

125,292.00

K-15 1 m2 Pintu alluminium strip lebar 8 cm

- Alumunium profil 4" natural m' 4.4000 151,100.00 664,840.00

- Alumunium strip 6mm m2 1.0500 171,800.00 180,390.00

- Pekerja Oh 0.0850 42,000.00 3,570.00

- Tukang kayu Oh 0.0850 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.50

- Mandor Oh 0.0042 80,000.00 336.00

Jumlah

855,298.50

Dibulatkan

855,299.00

K-16 1 m2 Pintu/jendela kaca rangka

alluminium natural 4"

- Alumunium profil natural 4" m' 4.4000 151,100.00 664,840.00

- Profil alluminium T m' 4.5000 12,200.00 54,900.00

- Sealant tube 0.2700 7,500.00 2,025.00

- Pekerja Oh 0.0850 42,000.00 3,570.00

- Tukang kayu Oh 0.0850 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.50

- Mandor Oh 0.0050 80,000.00 400.00

Jumlah

731,897.50

Dibulatkan

731,898.00

Page 5: Analisa Harga Satuan Besi Dan Aluminium Bayu

K-17 1 m2 Pintu/jendela kaca rangka

alluminium warna 4"

- Alumunium profil warna 4" m' 4.4000 163,000.00 717,200.00

- Profil alluminium T m' 4.5000 12,200.00 54,900.00

- Sealant tube 0.2700 7,500.00 2,025.00

- Pekerja Oh 0.0850 42,000.00 3,570.00

- Tukang kayu Oh 0.0850 65,000.00 5,525.00

- Kepala tukang Oh 0.0085 75,000.00 637.50

- Mandor Oh 0.0050 80,000.00 400.00

Jumlah

784,257.50

Dibulatkan

784,258.00

K-18 1 m2 Jendela nako & teralis (10 klips)

- Jendela nako (rangka + kaca 5 mm) m2 1.1000 300,000.00 330,000.00

- Paku skrup 1cm - 2,5cm bh 10.0000 250.00 2,500.00

- Besi strip m' 7.0000 5,500.00 38,500.00

- Pekerja Oh 0.2000 42,000.00 8,400.00

- Tukang kayu Oh 0.2000 65,000.00 13,000.00

- Kepala tukang Oh 0.0200 75,000.00 1,500.00

- Mandor Oh 0.0010 80,000.00 80.00

Jumlah

393,980.00

Dibulatkan

393,980.00

K-19 1 m2 Pintu pelat baja tebal 2mm rangkap, rangka baja

siku

- Besi siku L 30.30.3 Kg 15.0000 24,000.00 360,000.00

- Baja pelat Kg 32.8000 24,000.00 787,200.00

- kawat las Kg 0.0500 23,600.00 1,180.00

- Pekerja Oh 0.2000 42,000.00 8,400.00

- Tukang kayu Oh 0.2000 65,000.00 13,000.00

- Kepala tukang Oh 0.0200 75,000.00 1,500.00

- Mandor Oh 0.0010 80,000.00 80.00

Jumlah

1,171,360.00

Dibulatkan

1,171,360.00

K-20 1 m2 Rangka jendela besi square tube (5

x 5) cm

- Besi square tube M 4.7600 7,300.00 34,748.00

- Besi lis kaca (1 x 1) cm Kg 4.5220 24,000.00 108,528.00

- Pengelasan Cm 20.0000 2,464.00 49,280.00

- Pekerja Oh 0.6500 42,000.00 27,300.00

- Tukang kayu Oh 0.6500 65,000.00 42,250.00

- Kepala tukang Oh 0.0650 75,000.00 4,875.00

- Mandor Oh 0.0320 80,000.00 2,560.00

Jumlah

269,541.00

Dibulatkan

269,541.00

K-21 1 m2 Pintu lipat (folding door) bahan

besi

Page 6: Analisa Harga Satuan Besi Dan Aluminium Bayu

- Pintu lipat M2 1.0000 501,700.00 501,700.00

- Pekerja Oh 1.0500 42,000.00 44,100.00

- Tukang kayu Oh 1.0500 65,000.00 68,250.00

- Kepala tukang Oh 0.1050 75,000.00 7,875.00

- Mandor Oh 0.0052 80,000.00 416.00

Jumlah

622,341.00

Dibulatkan

622,341.00

K-22 1 m2 Tirai (venetions blinds and vertical

blinds)

- Tirai M2 1.0000 537,300.00 537,300.00

- Pekerja Oh 0.3500 42,000.00 14,700.00

- Tukang kayu Oh 0.3500 65,000.00 22,750.00

- Kepala tukang Oh 0.0350 75,000.00 2,625.00

- Mandor Oh 0.0018 80,000.00 144.00

Jumlah

577,519.00

Dibulatkan

577,519.00

Kembali Ke Analisa AHS SNI