REKAPITULASI RENCANA ANGGARAN BIAYA
SATUAN KERJA : PENGEMBANGAN KAWASAN PERMUKIMAN DAN PENATAAN BANGUNAN PROVINSI BALI
PEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
LOKASI : KECAMATAN KARANGASEM KABUPATEN KARANGASEM
TH. ANGGARAN : 2014
NO U R A I A N P E K E R J A A N
I PEKERJAAN PERSIAPAN 300,000.00
II LINGKUNGAN DANGIN SEMA 1,453,160,128.96
III LINGKUNGAN BANGRAS 292,301,265.25
IV LINGKUNGAN KARANGLANGKO 101,297,571.78
V LINGKUNGAN NYULING 13,768,536.41
VI LINGKUNGAN PERUMNAS PADANGKERTA 4,586,041,445.11
VII LINGKUNGAN SUBAGAN DESA 1,649,852,884.40
VIII LINGKUNGAN TELAGA MAS 1,630,109,849.77
IX LINGKUNGAN KECICANG ISLAM 1,566,955,115.72
X LINGKUNGAN UJUNGHYANG 654,038,446.75
XI LINGKUNGAN DAUSA 37,794,195.85
REAL COST = 11,985,619,440.00
PPN 10 % = 1,198,561,944.00
JUMLAH = 13,184,181,384.00
DIBULATKAN = 13,184,181,000.00
TERBILANG : Sebelas Milyar Delapan ratus Sembilan Juta Lima Ratus Tiga Puluh Delapan Ribu Rupiah
BIAYA ( Rp )
Denpasar, 2015
Disiapkan oleh:
Ahli Arsitektur : I Gusti Ngurah Agung Surya Darma, ST .........................................
Ahli Teknik Sipil : I Wayan Mudita, ST .........................................
Drafter : Ida Ayu Werdidwipayanti, ST ..........................................
Mengetahui :Kepala Satuan KerjaPengembangan Kawasan Permukiman Bali
I NYOMAN SUTRESNA, ST NIP. 19641103 199703 1 001
Mengetahui :Kepala Satuan KerjaPengembangan Kawasan Permukiman Bali
I NYOMAN SUTRESNA, ST NIP. 19641103 199703 1 001
DAFTAR KUANTITAS HARGA
SATUAN KERJA : PENGEMBANGAN KAWASAN PERMUKIMAN DAN PENATAAN BANGUNAN PROVINSI BALI
PEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
LOKASI : KECAMATAN KARANGASEM KABUPATEN KARANGASEM
TH. ANGGARAN : 2014
NO U R A I A N VOLUME
HARGA
SATUAN
Rp
I PEKERJAAN PERSIAPAN
- Pembuatan Papan Nama Kegiatan 1.00 BH 300,000.00 300,000.00
SUB TOTAL 300,000.00
II LINGKUNGAN DANGIN SEMA
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 1,305.00
- Pekerjaan Membuang Tanah 221.18 M3 22,820.00 5,047,327.60
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 1,305.00 M' 542,199.63 707,570,517.15
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 1,305.00 M' 283,820.99 370,386,391.95
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 1,305.00 M' 172,764.76 225,458,011.80
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 531.53 M2 118,679.02 63,081,456.84
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 559.67 M2 143,679.02 80,412,834.33
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 5.85 M' 205,741.76 1,203,589.30
SUB TOTAL 1,453,160,128.96
JUMLAH HARGA ( Rp )
NO U R A I A N VOLUME
HARGA
SATUAN
Rp
JUMLAH HARGA ( Rp )
III LINGKUNGAN BANGRAS
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 279.00
- Pekerjaan Membuang Tanah 47.28 M3 22,820.00 1,078,929.60
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 232.49 M' 542,199.63 126,055,991.98
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 232.49 M' 283,820.99 65,985,541.97
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 279.00 M' 172,764.76 48,201,368.04
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 120.08 M2 118,679.02 14,250,976.12
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 118.12 M2 143,679.02 16,971,365.25
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 4.60 M' 205,741.76 946,412.10
- Pekerjaan Pasangan Batu Kali 18.00 M3 828,282.00 14,909,076.00
- Pekerjaan Siaran 60.00 M2 46,276.40 2,776,584.00
- Pekerjaan Plesteran 23.50 M2 47,873.20 1,125,020.20
SUB TOTAL 292,301,265.25
IV LINGKUNGAN KARANGLANGKO
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 94.00
- Pekerjaan Membuang Tanah 15.93 M3 22,820.00 363,522.60
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 94.00 M' 542,199.63 50,966,765.22
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 94.00 M' 283,820.99 26,679,173.06
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 94.00 M' 172,764.76 16,239,887.44
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 8.84 M2 118,679.02 1,049,122.49
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 38.46 M2 143,679.02 5,525,894.92
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 2.30 M' 205,741.76 473,206.05
SUB TOTAL 101,297,571.78
V LINGKUNGAN NYULING
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 29.00
- Pekerjaan Membuang Tanah 1.47 M3 22,820.00 33,545.40
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 58.00 M' 172,764.76 10,020,356.08
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 13.76 M2 118,679.02 1,633,023.25
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 12.34 M2 143,679.02 1,772,999.05
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 1.50 M' 205,741.76 308,612.64
SUB TOTAL 13,768,536.41
NO U R A I A N VOLUME
HARGA
SATUAN
Rp
JUMLAH HARGA ( Rp )
VI LINGKUNGAN PERUMNAS PADANGKERTA
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 2,570.00
- Pekerjaan Membuang Tanah 692.72 M3 22,820.00 15,807,870.40
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 4,440.00 M' 542,199.63 2,407,366,357.20
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 4,440.00 M' 283,820.99 1,260,165,195.60
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 700.00 M' 172,764.76 120,935,332.00
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 300 4,513.14 M2 138,679.02 625,877,809.76
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 300 864.92 M2 163,679.02 141,569,253.65
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 69.60 M' 205,741.76 14,319,626.50
SUB TOTAL 4,586,041,445.11
VII LINGKUNGAN PERUMNAS SUBAGAN
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 192.00
- Pekerjaan Membuang Tanah 9.79 M3 22,820.00 223,407.80
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 384.00 M' 172,764.76 66,341,667.84
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 234.30 M' 118,679.02 27,806,493.21
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 92.10 M' 143,679.02 13,232,837.28
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 2.40 M' 205,741.76 493,780.22
SUB TOTAL 108,098,186.36
VIII LINGKUNGAN SUBAGAN DESA
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 1,083.00
- Pekerjaan Membuang Tanah 244.78 M3 22,820.00 5,585,879.60
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 1,491.00 M' 542,199.63 808,419,648.33
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 1,491.00 M' 283,820.99 423,177,096.09
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 783.40 M' 172,764.76 135,343,912.98
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 1,612.88 M2 118,679.02 191,415,009.71
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 321.90 M2 143,679.02 46,250,274.93
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 300 192.09 M2 138,679.02 26,638,851.99
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 300 63.91 M2 163,679.02 10,460,725.85
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 12.45 M' 205,741.76 2,561,484.91
SUB TOTAL 1,649,852,884.40
IX LINGKUNGAN TELAGA MAS
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 1,103.00
- Pekerjaan Membuang Tanah 238.46 M3 22,820.00 5,441,657.20
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 1,538.95 M' 542,199.63 834,419,204.99
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 1,538.95 M' 283,820.99 436,786,880.20
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 667.00 M' 172,764.76 115,234,094.92
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 194.75 M2 118,679.02 23,112,738.17
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 178.35 M2 143,679.02 25,625,152.33
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 300 1,084.70 M2 138,679.02 150,425,127.57
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 300 220.90 M2 163,679.02 36,156,694.41
- Pekerjaan Memasang Beton Pracetak Type Box Culvert 50 x 50 x 120 Cm, K 350 4.00 M' 354,168.06 1,416,672.22
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 7.25 M' 205,741.76 1,491,627.76
SUB TOTAL 1,630,109,849.77
X LINGKUNGAN KECICANG ISLAM
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 1,443.00
- Pekerjaan Membuang Tanah 223.25 M3 22,820.00 5,094,565.00
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 1,443.00 M' 542,199.63 782,394,066.09
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 1,443.00 M' 283,820.99 409,553,688.57
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 1,443.00 M' 172,764.76 249,299,548.68
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 589.44 M2 118,679.02 69,954,158.60
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 338.91 M2 143,679.02 48,694,254.97
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 9.55 M' 205,741.76 1,964,833.81
SUB TOTAL 1,566,955,115.72
XI LINGKUNGAN UJUNGHYANG
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 685.00
- Pekerjaan Membuang Tanah 91.79 M3 22,820.00 2,094,647.80
- Pekerjaan Memasang Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 Cm 479.99 M' 542,199.63 260,249,316.00
- Pekerjaan Memasang Beton Pracetak Penutup Saluran Type Coper U Heavy 30 x 120 Cm 479.99 M' 283,820.99 136,230,669.35
- Pekerjaan Memasang Beton Pracetak Kansten 50 x 20 x 15 Cm, K - 225 890.00 M' 172,764.76 153,760,636.40
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 475.00 M2 118,679.02 56,372,532.13
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 309.70 M2 143,679.02 44,497,390.95
- Pekerjaan Memasang Kansteen Kursi 18 x 40 x 50 Cm 4.05 M' 205,741.76 833,254.13
SUB TOTAL 654,038,446.75
XII LINGKUNGAN DAUSA
PENATAAN JALAN LINGKUNGAN DAN SALURAN P = 231.00
- Pasangan Paving Block Warna Natural 20 x 20 Tebal 8 Cm, K - 225 192.84 M2 118,679.02 22,886,061.25
- Pasangan Paving Block Warna Merah 20 x 20 Tebal 8 Cm, K - 225 103.76 M2 143,679.02 14,908,134.60
SUB TOTAL 37,794,195.85
R E K A P I T U L A S IDAFTAR VOLUME PEKERJAAN
SATKER : PENGEMBANGAN KAWASAN PERMUKIMAN BALIPPK : PENGEMBANGAN KAWASAN PERMUKIMAN PERKOTAANPEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015LOKASI : KECAMATAN KARANGASEM KABUPATEN KARANGASEMDESA : KECAMATAN KARANGASEM
NO. LOKASI PEKERJAAN
URAIAN PEKERJAAN
Panjang
PENGADAAN
M M3 M3 M3 M3 Unit Unit Unit Unit M2 M' M2 M2 M2 M2 M3 M2 M2 Buah Buah Buah
1 LINGKUNGAN DANGIN SEMA 1,305.00 221.18 221.18 - 90.44 1,087.48 - 1,087.48 - 195.75 1,305.00 531.53 - 559.67 - - - - 2,610.00 1,087.48 -
2 LINGKUNGAN BANGRAS 279.00 47.28 47.28 - 19.58 232.49 - 232.49 - 41.85 279.00 120.08 - 118.12 - 18.00 60.00 23.50 558.00 232.49 -
3 LINGKUNGAN KARANGLANGKO 94.00 15.93 15.93 - 4.95 78.33 - 78.33 - 14.10 94.00 8.84 - 38.46 - - - - 188.00 78.33 -
4 LINGKUNGAN NYULING 29.00 1.47 1.47 - 1.74 - - - - 4.35 58.00 13.76 - 12.34 - 11.60 52.20 15.66 116.00 - -
5 LINGKUNGAN PERUMNAS 3,112.00 633.75 633.75 - 444.88 4,491.64 - 4,491.60 - 51.30 684.00 3,462.76 899.62 1,186.24 196.38 - - - 1,368.00 4,491.64 -
6 LINGKUNGAN SUBAGAN DESA 926.70 150.01 150.01 - 68.67 756.64 - 756.64 - 146.79 1,228.40 277.40 275.10 280.60 16.62 - - - 2,456.80 756.64 -
7 LINGKUNGAN TELAGA MAS 1,103.00 238.46 238.46 - 113.69 1,282.46 - 1,282.46 - 100.05 667.00 194.75 1,084.70 178.35 220.90 - - - 1,334.00 1,282.46 -
8 LINGKUNGAN KECICANG ISLAM 1,443.00 223.25 223.25 - 89.03 1,202.48 - 1,202.48 - 216.45 1,443.00 589.44 - 338.91 - - - - 2,886.00 1,202.48 -
9 LINGKUNGAN UJUNGHYANG 685.00 91.79 91.79 - 32.88 399.99 - 399.99 - 102.75 890.00 475.00 - 309.70 - - - - 1,780.00 399.99 -
10 LINGKUNGAN DAUSA 231.00 - - - - - - - - 39.83 - 192.84 - 103.76 - - - - - - -
TOTAL VOLUME PEKERJAAN 9,207.70 1,623.12 1,623.12 - 865.86 9,531.51 - 9,531.47 - 913.22 6,648.40 5,866.40 2,259.42 3,126.15 433.90 29.60 112.20 39.16 13,296.80 9,531.51 -
Pekerjaan Galian
Tanah Biasa
Pekerjaan Membuang
Tanah
Pekerjaan Urugan Tanah
Kembali
Pekerjaan Urugan Pasir
Pekerjaan Memasang
Beton Pracetak
Saluran Type U-Ditch
30x30x60 cm
Pekerjaan Memasang
Beton Pracetak
Saluran Type U-Ditch
40x40x60 cm
Pekerjaan Memasang
Beton Pracetak Penutup
Saluran Type Cover U Heavy
30x60 cm
Pekerjaan Memasang
Beton Pracetak Penutup
Saluran Type Cover U Heavy
40x60 cm
Pekerjaan Spesi Beton
Pracetak Kanstin
Pekerjaan Memasang
Beton Pracetak Kanstin
Pekerjaan Memasang
Paving Blok Warna Natural 20x20 tebal 8
cm K 225
Pekerjaan Memasang
Paving Blok Warna
Natural 20x20 tebal 8 cm K
300
Pekerjaan Memasang
Paving Blok Warna Merah 20x20 tebal 8
cm K 225
Pekerjaan Memasang
Paving Blok Warna Merah
20x20 tebal 8 cm K 300
Pekerjaan Pasangan Batu Kali
Pekerjaan Siaran
Pekerjaan Plesteran
Beton Pracetak Kanstein
50x20x15 cm, K.225
Beton Pracetak
Saluran Type U-Ditch
30x30x120 cm K.300
Beton Pracetak Saluran Type U-
Ditch 40x40x60 cm K.300
R E K A P I T U L A S IDAFTAR VOLUME PEKERJAAN
Ket
PENGADAAN
Buah Buah Buah
1,087.48 - 5.85
232.49 - 4.60
78.33 - 2.30
- - 1.50
4,491.60 - -
756.64 - -
1,282.46 - 7.25
1,202.48 - 9.55
399.99 - 4.05
- - -
9,531.47 - 35.10
Beton Pracetak Penutup
Saluran Type Cover U
Heavy 30x60 cm Polos
K.300
Beton Pracetak Penutup
Saluran Type Cover U
Heavy 40x60 cm Polos
K.300
Kanstein Kursi
15x40x60 Cm, K.225
DAFTAR ANALISA PEKERJAAN
SATUAN KERJA : PENGEMBANGAN KAWASAN PERMUKIMAN DAN PENATAAN BANGUNAN PROVINSI BALI
PEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
LOKASI : DESA DAUH PEKEN
TH. ANGGARAN : 2014
NO U R A I A N
1 2
1 1 M3 GALIAN TANAH BIASA SEDALAM 1 M
0.750 OH Pekerja
0.025 OH Mandor
2 1 M3 PEMBUANGAN TANAH
0.330 OH Pekerja
0.010 OH Mandor
3 1 M3 URUGAN TANAH KEMBALI
0.250 OH Pekerja
0.008 OH Mandor
4 1 M3 URUGAN PASIR
1.200 M3 Pasir Urug
0.300 OH Pekerja
0.010 OH Mandor
5 1 M3 URUGAN SIRTU
1.200 M3 Sirtu
0.250 OH Pekerja
0.025 OH Mandor
6 1 M3 PASANGAN BATU KOSONG
1.200 M3 Batu Kali
0.432 M3 Pasir Urug
0.780 OH Pekerja
0.390 OH Tukang Batu
0.039 OH Kepala Tukang
0.039 OH Mandor
7 1 M3 PAS BATU KALI CAMP. ( 1PC - 5 PS )
1.200 M3 Batu kali
0.560 M3 Pasir Pasangan
135.350 KG Semen 50 kg
3.600 OH Pekerja
1.200 OH Tukang Batu
0.120 OH Kepala Tukang
0.160 OH Mandor
8 1 M2 PEK. SIARAN 1Pc : 2Ps
6.340 Kg Semen Portland
0.012 M3 Pasir Pasang
0.300 OH Pekerja
0.150 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor
9 1 M2 PLESTERAN 1Pc : 3Ps (TEBAL 1 CM )
5.840 Kg Semen Portland
0.016 M3 Pasir Pasang
0.300 OH Pekerja
0.150 OH Tukang Batu
0.015 OH Kepala Tukang
0.030 OH Mandor
10 1 M3 MEMBUAT BETON 1PC : 3PS : 5Krl
218.000 Kg Semen Portland
0.520 M3 Pasir Beton
0.870 M3 Koral Beton
1.650 OH Pekerja
0.250 OH Tukang Batu
0.025 OH Kepala Tukang
0.080 OH Mandor
11 1 M3 MEMBUAT BETON 1PC : 2PS : 3Krl
232.000 Kg Semen Portland
0.520 M3 Pasir Beton
0.780 M3 Koral Beton
1.650 OH Pekerja
0.250 OH Tukang Batu
0.025 OH Kepala Tukang
0.080 OH Mandor
12 10 KG PEMBESIAN DENGAN BESI POLOS / ULIR
10.500 Kg Besi Beton ( Polos / Ulir )
0.150 M3 Kawat Beton
0.070 OH Pekerja
0.070 OH Tukang Besi
0.007 OH Kepala Tukang
0.004 OH Mandor
13 1M2 PASANG PAVING T = 6 CM (K.225) Warna Natural
1.000 M2 Paving Blok
0.055 M3 Pasir Urug
0.014 M3 Pasir Pasang
0.120 OH Tukang Batu
0.012 OH Kepala Tukang
0.240 OH Pekerja
0.060 OH Mandor
14 1M2 PASANG PAVING T = 6 CM (K.225) Warna Merah
1.000 M2 Paving Blok
0.055 M3 Pasir Urug
0.014 M3 Pasir Pasang
0.120 OH Tukang Batu
0.012 OH Kepala Tukang
0.240 OH Pekerja
0.060 OH Mandor
15 1M2 PASANG PAVING T = 8 CM (K.225) Warna Natural
1.000 M2 Paving Blok
0.055 M3 Pasir Urug
0.014 M3 Pasir Pasang
0.120 OH Tukang Batu
0.012 OH Kepala Tukang
0.240 OH Pekerja
0.060 OH Mandor
16 1M2 PASANG PAVING T = 8 CM (K.225) Warna Merah
1.000 M2 Paving Blok
0.055 M3 Pasir Urug
0.014 M3 Pasir Pasang
0.120 OH Tukang Batu
0.012 OH Kepala Tukang
0.240 OH Pekerja
0.060 OH Mandor
17 1M2 PASANG PAVING T = 8 CM (K.300) Warna Natural
1.000 M2 Paving Blok
0.055 M3 Pasir Urug
0.014 M3 Pasir Pasang
0.120 OH Tukang Batu
0.012 OH Kepala Tukang
0.240 OH Pekerja
0.060 OH Mandor
18 1M2 PASANG PAVING T = 8 CM (K.300) Warna Merah
1.000 M2 Paving Blok
0.055 M3 Pasir Urug
0.014 M3 Pasir Pasang
0.120 OH Tukang Batu
0.012 OH Kepala Tukang
0.240 OH Pekerja
0.060 OH Mandor
19 1 UNIT PEMASANGAN BOX CULVERT 50 x 50 x 120 Cm, K 350
1.000 M2 Box Culvert 50 x 50 x 120
0.100 M3 Galian Tanah
0.100 M3 Pasir Urug
0.100 M3 Buangan Tanah
0.120 OH Kepala Tukang
1.200 OH Pekerja
0.060 OH Mandor
20 1 UNIT PEKERJAAN MEMASANG BETON PRACETAK TYPE BOX CULVERT 50 X 50 X 120 Cm, K 350
0.032 OH Tukang Batu
0.064 OH Pekerja
0.016 OH Mandor
0.123 Jam Sewa Excavaor
0.230 Jam Sewa Dump Truck
0.111 Jam Sewa Crane
1.000 Ls Alat Bantu
21 1 M' PEKERJAAN MEMASANG BETON PRACETAK TYPE BOX CULVERT 50 X 50 X 120 Cm, K 350
0.830 Unit Pemasangan Box Culvert 50 x 50 x 120 Cm, K 350
0.830 Unit Pekerjaan Memasang Box Culvert 50 x 50 x 120 Cm, K 350
22 1 UNIT PEKERJAAN MEMASANG BETON PRACETAK SALURAN TYPE U - DITCH 30 X 30 X 120 Cm, K 300
0.200 OH Tukang Batu
0.800 OH Pekerja
0.100 OH Mandor
0.300 Jam Sewa Dump Truck
1.000 Ls Alat Bantu
23 1 UNIT PEKERJAAN MEMASANG BETON PRACETAK PENUTUP SALURAN TYPE COPER U - 30 X 120 Cm, K. 300
0.133 OH Tukang Batu
0.533 OH Pekerja
0.067 OH Mandor
0.200 Jam Sewa Dump Truck
1.000 Ls Alat Bantu
24 1 UNIT PEKERJAAN MEMASANG BETON PRACETAK SALURAN TYPE U - DITCH 40 X 40 X 120 Cm, K 300
0.267 OH Tukang Batu
1.067 OH Pekerja
0.133 OH Mandor
0.400 Jam Sewa Dump Truck
1.000 Ls Alat Bantu
25 1 UNIT PEKERJAAN MEMASANG BETON PRACETAK PENUTUP SALURAN TYPE COPER U - 40 X 120 Cm, K. 300
0.178 OH Tukang Batu
0.711 OH Pekerja
0.089 OH Mandor
0.267 Jam Sewa Dump Truck
1.000 Ls Alat Bantu
26 1 M' PEKERJAAN MEMASANG BETON PRACETAK SALURAN TYPE U - DITCH 40 X 40 X 120 Cm, K 300
0.125 M3 Galian Tanah Biasa Sedalam 1 m
0.020 M3 Urugan Pasir
0.830 Unit U-Ditch 40 x 40 x 120 cm, K 300
0.830 Unit Memasang U-Ditch 40 x 40 x 120 cm, K 300
27 1 M' PEKERJAAN MEMASANG BETON PRACETAK PENUTUP SALURAN TYPE COPER U - 40 X 120 Cm, K. 300
0.830 Unit Penutup Saluran U-Ditch 40 x 40 x 120 cm, K 300
0.830 Unit Memasang Penutup Saluran U-Ditch 40 x 40 x 120 cm, K 300
28 1 M' PEKERJAAN MEMASANG BETON PRACETAK SALURAN TYPE U - DITCH 30 X 30 X 120 Cm, K 300
1.200 M3 Galian Tanah Biasa Sedalam 1 m
0.300 M3 Urugan Pasir
0.830 Unit U-Ditch 30 x 30 x 120 cm, K 300
0.830 Unit Memasang U-Ditch
29 1 M' PEKERJAAN MEMASANG BETON PRACETAK PENUTUP SALURAN TYPE COPER U - 30 X 120 Cm, K. 300
0.830 Unit Penutup Saluran U-Ditch 30 x 30 x 120 cm, K 300
0.830 Unit Memasang Penutup Saluran U-Ditch 30 x 30 x 120 cm, K 300
30 1M' PEKERJAAN KANSTEN KURSI
2.000 M2 Kansten Kursi 18 x 40 x 50 cm
0.400 M2 Spesi Beton Pracetak Kansten
0.072 M3 Galian Tanah
0.120 OH Kepala Tukang
1.200 OH Pekerja
0.060 OH Mandor
31 1M' PEKERJAAN KANSTEN 15 x 30 x 50 CM (K.225)
2.000 M2 Kansten
0.150 M2 Spesi Beton Pracetak Kansten
0.100 M3 Galian Tanah
0.100 M3 Pasir Urug
0.120 OH Kepala Tukang
1.200 OH Pekerja
0.060 OH Mandor
32 1M' PEKERJAAN KANSTEN 50 x 20 x 15 CM (K.225)
2.000 M2 Kansten
0.150 M2 Spesi Beton Pracetak Kansten
0.100 M3 Galian Tanah
0.100 M3 Pasir Urug
0.120 OH Kepala Tukang
1.200 OH Pekerja
0.060 OH Mandor
DAFTAR ANALISA PEKERJAAN
BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
HARGA HARGA ( RUPIAH )
JUMLAH HARGASATUANUPAH BAHAN
Rp
3 4 5 6
66,000.00 49,500.000
104,000.00 2,600.000
52,100.00 - 52,100.00
66,000.00 21,780.000
104,000.00 1,040.000
22,820.00 - 22,820.00
66,000.00 16,500.000
104,000.00 832.000
17,332.00 - 17,332.00
146,333.00 175,599.60
66,000.00 19,800.00
104,000.00 1,040.00
20,840.00 175,599.60 196,439.60
UNTUK 1 M2 1,964.40
231,100.00 277,320.00
66,000.00 16,500.00
104,000.00 2,600.00
19,100.00 277,320.00 296,420.00
142,300.00 170,760.00
146,333.00 63,215.86
66,000.00 51,480.000
83,000.00 32,370.000
92,000.00 3,588.000
104,000.00 4,056.000
91,494.000 233,975.86 325,469.856
142,300.00 170,760.00
184,200.00 103,152.00
1,400.00 189,490.00
66,000.00 237,600.00
83,000.00 99,600.00
92,000.00 11,040.00
104,000.00 16,640.00
364,880.00 463,402.00 828,282.00
1,400.00 8,876.00
184,200.00 2,210.40
66,000.00 19,800.00
83,000.00 12,450.00
92,000.00 1,380.00
104,000.00 1,560.00
35,190.00 11,086.40 46,276.40
1,400.00 8,176.00
184,200.00 2,947.20
66,000.00 19,800.00
83,000.00 12,450.00
92,000.00 1,380.00
104,000.00 3,120.00
36,750.00 11,123.20 47,873.20
1,400.00 305,200.00
186,000.00 96,720.00
160,000.00 139,200.00
66,000.00 108,900.00
83,000.00 20,750.00
92,000.00 2,300.00
104,000.00 8,320.00
140,270.00 541,120.00 681,390.00
1,400.00 324,800.00
186,000.00 96,720.00
160,000.00 124,800.00
66,000.00 108,900.00
83,000.00 20,750.00
92,000.00 2,300.00
104,000.00 8,320.00
140,270.00 546,320.00 686,590.00
13,500.00 141,750.00
17,000.00 2,550.00
66,000.00 4,620.00
83,000.00 5,810.00
92,000.00 644.00
104,000.00 416.00
11,490.00 144,300.00 155,790.00
61,000.00 61,000.00
146,333.00 8,048.32
184,200.00 2,486.70
83,000.00 9,960.00
92,000.00 1,104.00
66,000.00 15,840.00
104,000.00 6,240.00
33,144.00 71,535.02 104,679.02
91,500.00 91,500.00
146,333.00 8,048.32
184,200.00 2,486.70
83,000.00 9,960.00
92,000.00 1,104.00
66,000.00 15,840.00
104,000.00 6,240.00
33,144.00 102,035.02 135,179.02
75,000.00 75,000.00
146,333.00 8,048.32
184,200.00 2,486.70
83,000.00 9,960.00
92,000.00 1,104.00
66,000.00 15,840.00
104,000.00 6,240.00
33,144.00 85,535.02 118,679.02
100,000.00 100,000.00
146,333.00 8,048.32
184,200.00 2,486.70
83,000.00 9,960.00
92,000.00 1,104.00
66,000.00 15,840.00
104,000.00 6,240.00
33,144.00 110,535.02 143,679.02
95,000.00 95,000.00
146,333.00 8,048.32
184,200.00 2,486.70
83,000.00 9,960.00
92,000.00 1,104.00
66,000.00 15,840.00
104,000.00 6,240.00
33,144.00 105,535.02 138,679.02
120,000.00 120,000.00
146,333.00 8,048.32
184,200.00 2,486.70
83,000.00 9,960.00
92,000.00 1,104.00
66,000.00 15,840.00
104,000.00 6,240.00
33,144.00 130,535.02 163,679.02
275,000.00 275,000.00
52,100.00 5,210.00
146,333.00 14,633.30
22,820.00 2,282.00
92,000.00 11,040.00
66,000.00 79,200.00
104,000.00 6,240.00
118,605.30 275,000.00 393,605.30
83,000.00 2,631.10
66,000.00 4,191.00
104,000.00 1,653.60
43,750.00 5,394.38
43,750.00 10,066.88
37,500.00 4,166.25
5,000.00 5,000.00
33,103.20 - 33,103.20
393,605.30 326,692.40
33,103.20 27,475.66
27,475.66 326,692.40 354,168.06
83,000.00 16,600.00
66,000.00 52,800.00
104,000.00 10,400.00
43,750.00 13,125.00
5,000.00 5,000.00
97,925.00 - 97,925.00
83,000.00 11,072.20
66,000.00 35,204.40
104,000.00 6,926.40
43,750.00 8,750.00
5,000.00 5,000.00
66,953.00 - 66,953.00
83,000.00 22,133.33
66,000.00 70,400.00
104,000.00 13,866.67
43,750.00 17,500.00
5,000.00 5,000.00
128,900.00 - 128,900.00
83,000.00 14,762.93
66,000.00 46,939.20
104,000.00 9,235.20
43,750.00 11,666.67
5,000.00 5,000.00
87,604.00 - 87,604.00
52,100.00 6,512.50
196,439.60 3,928.79
623,000.00 517,090.00
128,900.00 106,987.00
117,428.29 517090 634,518.29
372,000.00 308,760.00
87,604.00 72,711.32
72,711.32 308,760.00 381,471.32
52,100.00 62,520.00
196,439.60 58,931.88
409,000.00 339,470.00
97,925.00 81,277.75
202,729.63 339,470.00 542,199.63
275,000.00 228,250.00
66,953.00 55,570.99
55,570.99 228,250.00 283,820.99
43,500.00 87,000.00
46,276.40 18,510.56
52,100.00 3,751.20
92,000.00 11,040.00
66,000.00 79,200.00
104,000.00 6,240.00
100,231.20 105,510.56 205,741.76
16,500.00 33,000.00
46,276.40 6,941.46
52,100.00 5,210.00
146,333.00 14,633.30
92,000.00 11,040.00
66,000.00 79,200.00
104,000.00 6,240.00
116,323.30 39,941.46 156,264.76
24,750.00 49,500.00
46,276.40 6,941.46
52,100.00 5,210.00
146,333.00 14,633.30
92,000.00 11,040.00
66,000.00 79,200.00
104,000.00 6,240.00
116,323.30 56,441.46 172,764.76
DAFTAR HARGA SATUAN BAHAN
SATUAN KERJA : PENGEMBANGAN KAWASAN PERMUKIMAN DAN PENATAAN BANGUNAN PROVINSI BALI
PEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
LOKASI : DESA DAUH PEKEN
TH. ANGGARAN : 2014
NO URAIAN SATUAN
1 Batu Gunung / Lokal M3
2 Batu Gunung / Lokal Pecah M3
3 Batu Gunung / Lokal 5 - 7 CM M3
4 Batu Gunung / Lokal 3 - 4 CM M3
5 Batu Gunung / Lokal 2 - 3 CM M3
6 Split Jagung M3
7 Split Halus M3
8 Kerikil Beton M3
9 Kerikil Urug M3
10 Sirtu M3
11 Pasir Beton M3
12 Pasir Urug M3
13 Pasir Pasang M3
14 Tanah Urug M3
15 Limestone M3
16 Meratakan / Normalisasi Tanah M'
17 Portland Cement KG
18 Besi Beton Polos KG
19 Kawat Beton KG
20 Paku Usuk KG
21 Aspal KG
22 Kayu Begesting Meranti M3
23 Kayu Bakar/Api M3
24 Sikat Ijuk BUAH
25 Sikat Baja BUAH
26 Solar LITER
27 Olie LITER
28 Minyak Begesting LITER
29 Portland Cement ZAK
30 Kerosine / Minyak Tanah Liter
31 Paving Block T = 6 cm ( K 225 ) Warna Natural M2
32 Paving Block T = 6 cm ( K 225 ) Warna Merah M2
33 Paving Block T = 8 cm ( K 225 ) Warna Natural M2
34 Paving Block T = 8 cm ( K 300 ) Warna Natural M2
35 Paving Block T = 8 cm ( K 225 ) Warna Merah M2
36 Paving Block T = 8 cm ( K 300 ) Warna Merah M2
37 Beton Kansteen 50 x 20 x 15 Cm, K 225 Buah
38 Beton Kansteen 50 x 20 x 15 Cm, K 300 Buah
39 Beton Kansteen 40 x 20 x 10 Cm, K 225 Buah
40 Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 cm K 300 Buah
41 Beton Pracetak Saluran Type U - Ditch 40 x 40 x 120 cm K 300 Buah
42 Beton Pracetak Penutup Saluran Type Cooper U Heavy 30 x 12 x 120 cm Polos K 300 Buah
43 Beton Pracetak Penutup Saluran Type Cooper U Heavy 40 x 12 x 120 cm Polos K 300 Buah
44 Kansten Kursi 18 x 40 x 50 cm Buah
45 Alat Bantu Ls
46 Air Lt
DAFTAR HARGA SATUAN UPAH
SATUAN KERJA : PENGEMBANGAN KAWASAN PERMUKIMAN DAN PENATAAN BANGUNAN PROVINSI BALI
PEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
LOKASI : DESA DAUH PEKEN
TH. ANGGARAN : 2014
NO URAIAN SATUAN
1 MANDOR HARI
2 KEPALA TUKANG HARI
3 KEPALA TUKANG BATU HARI
4 KEPALA TUKANG KAYU HARI
5 KEPALA TUKANG BESI HARI
6 KEPALA TUKANG CAT HARI
7 TUKANG BATU HARI
8 TUKANG KAYU HARI
9 TUKANG BESI HARI
10 TUKANG CAT HARI
11 TUKANG MASAK ASPAL HARI
12 PEKERJA HARI
13 MASINIS / OPERATOR HARI
14 KERNET / PEMBANTU OPERATOR HARI
DAFTAR HARGA SATUAN ALAT
SATUAN KERJA : PENGEMBANGAN KAWASAN PERMUKIMAN DAN PENATAAN BANGUNAN PROVINSI BALI
PEKERJAAN : BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
LOKASI : DESA DAUH PEKEN
TH. ANGGARAN : 2014
NO URAIAN SATUAN
1 WALLES HARI
2 STAMPER HARI
3 MOLLEN HARI
4 VIBRATOR HARI
5 POMPA AIR HARI
6 GENZET HARI
7 DUMP TRUCK HARI
8 TRUCK KAYU HARI
9 PICK UP HARI
10 EXCAVATOR HARI
11 CRANE HARI
DAFTAR HARGA SATUAN BAHAN
BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
HARGA
142,300.00
167,000.00
167,055.00
167,055.00
167,055.00
157,200.00
172,725.00
160,000.00
196,666.00
231,100.00
186,000.00
146,333.00
184,200.00
117,333.00
158,000.00
5,500.00
1,400.00
13,500.00
17,000.00
15,000.00
8,850.00
2,200,000.00
212,500.00
20,000.00
35,000.00
5,500.00
35,000.00
18,000.00
70,000.00
13,275.00
61,000.00
91,500.00
75,000.00
95,000.00
100,000.00
120,000.00
24,750.00
33,000.00
16,500.00
409,000.00
623,000.00
275,000.00
372,000.00
43,500.00
5,000.00
20.00
DAFTAR HARGA SATUAN UPAH
BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
HARGA
104,000.00
92,000.00
92,000.00
93,000.00
90,000.00
80,000.00
83,000.00
88,000.00
83,000.00
78,000.00
66,000.00
66,000.00
148,000.00
117,000.00
DAFTAR HARGA SATUAN ALAT
BANTUAN TEKNIS REVIEW DED PADA KSN PERKOTAAN TA. 2015
HARGA
450,000.00
350,000.00
350,000.00
250,000.00
250,000.00
350,000.00
350,000.00
300,000.00
250,000.00
350,000.00
300,000.00
4,680,000,000.00 100.00
4,680,000,000.00 -
85.00 Batu Gunung / Lokal M3 Batu Gunung / Lokal Pecah M3 Batu Gunung / Lokal 5 - 7 CM M3 Batu Gunung / Lokal 3 - 4 CM M3 Batu Gunung / Lokal 2 - 3 CM M3 Split Jagung M3 Split Halus M3 Kerikil Beton M3 Kerikil Urug M3 Sirtu M3 Pasir Beton M3 Pasir Urug M3 Pasir Pasang M3 Tanah Urug M3 Limestone M3 Meratakan / Normalisasi Tanah M' Portland Cement KG Besi Beton Polos KG Kawat Beton KG Paku Usuk KG Aspal KG Kayu Begesting Meranti M3 Kayu Bakar/Api M3 Sikat Ijuk BUAH Sikat Baja BUAH Solar LITER Olie LITER Minyak Begesting LITER Portland Cement ZAK Kerosine / Minyak Tanah Liter Paving Block T = 6 cm ( K 300) warna natural M2 Paving Block T = 6 cm ( K 300) warna merah M2 Paving Block T = 8 cm ( K 225) warna natural M2 Paving Block T = 8 cm ( K 225) warna merah M2 Paving Block T = 8 cm ( K 300) warna natural M2 Paving Block T = 8 cm ( K 300) warna merah M2 Beton Kansteen 50 x 20 x 15 Cm, K 225 Buah Beton Kansteen 50 x 20 x 15 Cm, K 300 Buah Beton Kansteen 40 x 20 x 10 Cm, K 225 Buah Beton Pracetak Saluran Type U - Ditch 30 x 30 x 120 cm K 300 Buah Beton Pracetak Saluran Type U - Ditch 40 x 40 x 120 cm K 300 Buah Beton Pracetak Penutup Saluran Type Cooper U Heavy 30 x 12 x 120 Buah Beton Pracetak Penutup Saluran Type Cooper U Heavy 40 x 12 x 120 Buah Kansten Kursi 15 x 25 x 40 cm K 300 BuahAlat Bantu Ls
-
4,680,000,000.00 98.00 147.00
60,000.00 50,000.00 50,000.00 50,000.00 50,000.00 45,000.00 45,000.00 45,000.00 45,000.00 45,000.00 40,000.00 46,000.00 50,000.00 2,025,000.00 40,000.00 81,000.00
142,300.00 167,000.00 167,055.00 167,055.00 167,055.00 157,200.00 172,725.00 160,000.00 196,666.00 231,100.00 186,000.00 146,333.00 184,200.00 117,333.00 158,000.00 5,500.00 1,400.00 13,500.00 17,000.00 15,000.00 8,850.00 2,200,000.00 212,500.00 20,000.00 35,000.00 5,500.00 35,000.00 18,000.00 70,000.00 13,275.00 85,000.00 57,000.00 110,000.00 75,000.00 67,000.00 100,000.00 95,000.00 99,000.00 120,000.00 24,750.00 33,000.00 16,500.00 457,500.00 691,500.00 275,000.00 372,000.00
870005000
MANDOR HK
KEPALA TUKANG KAYU HK
KEPALA TUKANG BESI HK
KEPALA TUKANG CAT HK
TUKANG BATU HK
TUKANG KAYU HK
TUKANG BESI HK
TUKANG CAT HK
MASINIS / OPERATOR HK
PEKERJA HK
KERNET / PEMBANTU OPERATOR HK
PEMASAK ASPAL HK
SOPIR TRUK / MATERIAL HK
- 50,000.00
- 45,000.00 - 45,000.00 - 45,000.00 - 40,000.00 - 40,000.00 - 40,000.00 - 40,000.00
- 45,000.00 - 30,000.00 - 40,000.00 - 35,000.00
- 50,000.00
Penggunaan Type Paving Block sesuai kondisi Lebar Jalan terbangun
lebar jalan Dimensi penggunaan pavingKurang dari 1,5 M' 20x20x6, K. 225Lebih Besar 1,5 M' s/d 2,5 M' 20x20x8, K. 225Lebih Besar 2,5 M' 20x20x8, K. 300