13
Acton Campus Building # 32 Hazardous Materials Register This document is uncontrolled once printed. Register Version Date: 17/2/2016 To update this register please contact [email protected]

Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

 

 

 

Acton Campus 

Building # 32 

Hazardous Materials Register 

 This document is uncontrolled once printed. 

 

Register Version Date: 17/2/2016 

To update this register please contact 

[email protected]  

Page 2: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Site Location: Building 48, ANUAssessor: Tim Smith

48/B-01A/A03 CH, AM 2 Asbestos Ceiling Sheeting

Internal; Basement Room B-01A, ceiling lining. 1 1 1 2 2 4 L 12m2

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

48/L1.R12/A07 CH 3 Green Speckled Vinyl Floor Tiles Internal; Level 1 Room 12, floor covering. 1 1 2 2 2 8 L 25m2

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

Same as 48/L1.R12/A07 CH 4 Green Speckled Vinyl

Floor TilesInternal; Level 2 Rooms 1.04, 1.04A & 1.04B,

floor covering. 1 1 2 2 2 8 L 45m2

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

Same as 48/L1.R12/A07 CH 5 Green Speckled Vinyl

Floor TilesInternal; Level 2 Photocopying Room 1.13,

floor covering. 1 1 2 2 2 8 L 6m2

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

Visual Observation

Presumed Asbestos 6 Bituminous Hard Board

Internal; Level 2 Service Riser Cupboard (2.10H) between Rooms 1.04 & 1.06, board in

bottom of cupboard.1 1 2 2 2 8 L 0.5m2

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

Description Location

Inspection Date: 19 May 2015, Updated December 2015.Reinspection Date: May 2020 or as specified within comments

Qua

ntity

(m, m

2, m

3)

Actions/Comments

Expo

sure

Pot

entia

l

Ris

k Sc

ore

Act

ion

Prio

rity

Asbestos Containing Materials

Con

ditio

n

Acc

essi

bilit

y

Airb

orne

Pot

entia

l

Asb

esto

s Ty

pe

Sample No.

Res

ults

Phot

o ID

Page 3: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Same as 48/L1.R12/A07 CH - Green Speckled Vinyl

Floor TilesInternal; level 1, room 27, tiles beneath

carpet. 1 1 2 2 1 4 L 70m²

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition. Tiles removed on 31/10/15. See

Clearance Report H1601 by Robson Environmental.

Visual Observation PCBs 7 Florescent Light

CapacitorInternal; Basement Plant Room, Twin (9) &

Single (10) Florescent Light Fittings. - G - - - - L 19

Maintain in current condition. Review condition of PCB's by May

2020. Remove prior to refurbishment or demolition.

Visual Observation PCBs 8 Florescent Light

Capacitor

Internal; Level 1 & 2 Corridors, Entrances and Throughout Offices (offices that have not had

recent renovations).- G - - - - L >70

Maintain in current condition. Review condition of PCB's by May

2020. Remove prior to refurbishment or demolition.

ODS Containing Materials

Visual Observation ODS 9 ODS (Refrigerant 22) External; Rooftop, Air Conditioning Units. - G - - - - L 14

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

Visual Observation ODS 10 ODS (Refrigerant 22) External; Level 1 North, South & East Sides,

air conditioning units. - G - - - - L 7

Maintain in current condition. Review condition of asbestos

material by May 2020. Remove prior to refurbishment or

demolition.

Visual Observation SMF 11 Pipework Insulation Internal; Basement Plant Room, insulation to

pipework. - G - - - - L >100m Good condition. Remove prior to refurbishment or demolition.

Visual Observation SMF 12 Ceiling Insulation Internal; Level 1 & 2 Corridors, Insulation

above Decorative Timber Ceilings. - G - - - - L 200m²Good condition. Remove prior to

refurbishment or demolition.

Visual Observation SMF 13 Roof Insulation Internal; Insulation under Roof Sheeting. - G - - - - L 2,000m²

Good condition. Remove prior to refurbishment or demolition.

48/B/A01 NAD - Fire Door Core Insulation

Internal; Basement Plant Room Eastern End (2 Single Doors, 2 Double Doors). - - - - - - - 6 No action required.

PCBs Containing Materials

SMF Containing Materials

No Asbestos Detected

Page 4: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

48/B/A02 NAD - Electrical Cable Bandage Internal; Basement Tunnel - - - - - - - >80m No action required.

48/L1&L2/A04 NAD - Light Green Speckled Vinyl Floor Tile Internal; Level 1 & 2 Corridors. - - - - - - - 200m² No action required.

Same as 48/L1&L2/A04 NAD - Light Green Speckled

Vinyl Floor Tile Internal; Level 2 Western Foyer. - - - - - - - 70m² No action required.

48/L1&L2/A05 NAD - Black Vinyl Floor Tile Glue

Internal; Glue under Light Green Speckled Vinyl Floor Tile in Level 1 & 2 Corridors. - - - - - - - 200m² No action required.

48/L1&L2/A05 NAD - Black Vinyl Floor Tile Glue

Internal; Glue under Light Green Speckled Vinyl Floor Tile in Level 2 Western Foyer. - - - - - - - 70m² No action required.

48/L1/A06 NAD - Flange Joint Mastic Internal; Air Conditioning Duct Flange Joint Level 1 Corridor Ceiling near Room 13. - - - - - - - 3m No action required.

Same as 48/L1/A06 NAD - Flange Joint Mastic

Internal; Air Conditioning Duct Flange Joint Level 1 Electrical Switchboard Room 5 (3

small air con ducts).- - - - - - - 10m No action required.

48/L1.R34/L01 <0.05% w/w - White Paint Internal; Level 1 Cool Room 34 Wall Paint (+

7 other Cool Rooms). - - - - - - - 20m² No action required.

No Lead Detected

Page 5: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Robson Environmental Pty Ltd ~ ABN: 55 008 660 900 ~ www.robsonenviro.com.au p: 02 6239 5656 ~ f: 02 6239 5669 ~ [email protected] PO Box 112 Fyshwick ACT 2609 ~ 140 Gladstone Street Fyshwick ACT 2609

Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

ASBESTOS CLEARANCE INSPECTION PASS Project/Location: ANU Building 48, Forrestry Building, Linnaeus Way, Acton,

ACT, 2601 Job Number: H15601

Date of Inspection: Saturday, 31 October 2015

Description of Work: Removal of asbestos vinyl floor tiles to room 27.

Asbestos Removalist: International Asbestos Removals

Certification:

A visual inspection was carried out on Saturday, 31 October 2015, by Morgan Leech following the completion of the asbestos works listed above in accordance with Robson Environmental’s NATA, ISO9001, ISO14001 and AS4801 accreditations. It should be noted that this clearance certificate relates only to the exact area(s) specified above.

The inspection found no visible asbestos residue from the asbestos work in the area or in the vicinity of the area where the work was carried out.

Air monitoring during the works returned results below the minimum practical detection limit of <0.01 F/mL.

The work area has been given the “all clear” and restrictions associated with the asbestos works can now be lifted and the area safely reoccupied.

Note: Presumed asbestos vinyl floor tiles may still remain behind enclosed riser. Refer to appendix B.

Authorised by:

Morgan Leech - Licensed Asbestos Assessor

#2013834

Hazardous Materials Consultant

No. 3181

Accredited for compliance with ISO/IEC 17020

Page 6: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031 Page 2 of 3

Appendix A – Air Monitoring Results

Page 7: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031 Page 3 of 3

Appendix B – Photo(s)

Presumed asbestos vinyl floor tiles still remain behind enclosed riser

Page 8: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Robson Environmental Pty Ltd ~ ABN: 55 008 660 900 ~ www.robsonenviro.com.au p: 02 6239 5656 ~ f: 02 6239 5669 ~ [email protected] PO Box 112 Fyshwick ACT 2609 ~ 140 Gladstone Street Fyshwick ACT 2609

H1560_ANU Building 48_ACT_MA_20151028

Binutti Constructions P.O. Box 5042 ACT Garran 2605 28/10/2015

Dear Jeremy,

Re: Asbestos analysis and Risk Assessment of green with fleck vinyl floor tile (VFT) on the floor of Room 27, Building 48 of the Australian National University (ANU) on 27/10/2015.

Site Work

Andrew Dibb and Morgan Leech, ACT Asbestos Assessor of Robson Environmental sampled suspected asbestos containing material (ACM) from the above location. The analytical result is presented in Table 2 and a photograph in Appendix A.

Risk Assessment

A Risk Assessment was undertaken to enable informed decisions to be made concerning the management of ACM as per current legislation. This Risk Assessment takes into account:

the type of ACM (non friable or friable) the condition and location of the ACM whether the ACM is likely to be disturbed due to its condition and location and the likelihood of exposure to asbestos fibre

Material Assessment Restrictions and Caveats Robson Environmental has taken care to ensure that this report includes the most accurate information available. This report does not constitute a full register of asbestos containing materials at the above premises as required by current legislation. The material assessments, recommendations and/or conclusions contained in this report must not be used to absolve a person of their responsibility to work in accordance with relevant Statutory Requirements, Codes of Practice, Guidelines, Safety Data Sheets, Work Instructions or reasonable work practices.

Table 1 details the ratings for the condition and associated risk of each positively identified asbestos material at the time of the assessment. The ratings for each item are presented in Table 2.

No. 3181

Accredited for compliance with ISO/IEC 17020

Page 9: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: Binutti Constructions H1560_ANU Building 48_ACT_MA_20151028 Page 2 of 6

Table 1: ACM Condition & Risk Ratings

ACM CONDITION RATING

1 Severe Material in very poor condition

2 Poor Deteriorated material and considerable damage

3 Fair Minor damage or signs of weathering

4 Good Well sealed stable material

ACM RISK RATING

A Very High Exposure to airborne asbestos likely as a consequence of minor disturbance

B High Exposure to airborne asbestos possible as a consequence of minor disturbance

C Medium Exposure to airborne asbestos unlikely during normal building use

D Low Negligible exposure to airborne asbestos during normal building use

LABORATORY METHODOLOGY

The sampled material was double bagged and transported to Robson Environmental’s National Association of Testing Authorities (NATA) accredited laboratory with a Chain of Custody (COC) form written by the assessor which was signed off on receipt by the laboratory. The received material was analysed for asbestos fibre content which is determined by Polarised Light Microscopy with dispersion staining techniques. Refer to Appendix B for the Certificate of Analysis.

The sample taken from suspected ACM is representative of the material sampled, individually identified, transported, analysed and reported in accordance with current legislation and Robson Environmental In-house Procedures 2 & 3.

All inspections, sampling, identification and reporting was undertaken in accordance with Robson Environmental’s NATA, ISO9001, ISO14001 and AS4801 accreditations.

Non friable ACM

Non friable asbestos is any material that contains asbestos firmly bound into a matrix. It may consist of cement or various resins/binders and cannot be reduced to a dust by hand pressure. As such it does not present an exposure hazard unless cut, abraded, sanded or otherwise disturbed. Therefore, the exposure risk from non friable ACM is negligible during normal building occupation.

Page 10: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: Binutti Constructions H1560_ANU Building 48_ACT_MA_20151028 Page 3 of 6

Note: If non friable ACM is damaged or otherwise deteriorated, the Risk Assessment must be reviewed to reflect a higher potential for exposure to asbestos fibres. When severely damaged, non friable ACM may be assessed as being friable. A licensed Asbestos Assessor must perform the Risk Assessment.

Friable ACM

Friable asbestos material can be crumbled or reduced to a dust by hand pressure when dry. It can represent a significant exposure hazard as a consequence of minor disturbance. Examples of friable asbestos are hot water pipe lagging, severely damaged asbestos cement sheet, limpet spray and electrical duct heater millboard.

Table 2: Sample Analysis Results

Sample Number Location description Material Type Risk

Rating Fibrous Content

U0272 Floor of room 27 Green with fleck vinyl floor tile

Non-friable 3D Chrysotile Asbestos

Asbestos containing material

Presumed asbestos containing material

Non- asbestos containing material

Conclusions & Recommendations

The green with fleck VFT sampled from the floor of room 27 was found to contain chrysotile asbestos. It is recommended that any loose tiles or debris be removed. If the material is to be disturbed by works or removed in the course of refurbishments it should be removed by a licensed asbestos removalist. If it is to remain in situ it should be maintained, entered into the asbestos register for the building and controls put in place to brief persons who may disturb the material.

Page 11: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: Binutti Constructions H1560_ANU Building 48_ACT_MA_20151028 Page 4 of 6

Asbestos Removal

Removal of ACM must be undertaken by a licensed Asbestos Removalist as per current legislation. The removal/remediation of friable ACM must be undertaken by a licensed Class A Asbestos Removalist. Removal or remediation of non friable asbestos may be undertaken by either an A or B Class Asbestos Removalist.

Prior to the commencement of any removal or remediation works associated with any amount or type of asbestos, a Building Certifier must be engaged and Building Approval sought from WorkSafe ACT a minimum of 5 working days prior to the commencement of the works. An asbestos removal contractor must supply an Asbestos Removal Control Plan (ARCP) and a Safe Work Method Statement (SWMS). An independent licensed Asbestos Assessor should be engaged to ensure that the ARCP addresses all safety issues relating to the planned asbestos works.

Air monitoring is mandatory during the removal or remediation of friable asbestos and should be considered during the removal or remediation of non friable asbestos. Air sampling is to be undertaken in accordance with the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres, 2nd Edition [NOHSC: 3003(2005)] and test certificates must be National Association of Testing Authorities (NATA) endorsed.

An independent licensed Asbestos Assessor must also be employed to undertake a Clearance Inspection of both friable and non friable asbestos removal or remediation works. A satisfactory clearance certificate for the remediated areas must ensure that no visible asbestos or presumed asbestos remains, or that the ACM has been satisfactorily sealed or remediated. Additionally no asbestos fibres should be detected by laboratory analysis in any validation samples. All surfaces within the remediated area must be free of general dust and debris.

Yours sincerely,

Morgan Leech - Licensed Asbestos Assessor #2013834 Hazardous Materials Consultant

Mobile: 0478 672 004

Page 12: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: Binutti Constructions H1560_ANU Building 48_ACT_MA_20151028 Page 5 of 6

APPENDIX A - PHOTOGRAPH OF ACM

SAMPLE NO

LOCATION DESCRIPTION MATERIAL PHOTOGRAPH

U0272 Floor of room 27 Green with fleck VFT

Page 13: Acton Campus Building 32 Hazardous Materials Register · Acton Campus Building # 32 Hazardous Materials Register ... Client: IAR H15601_ANU Bldg 48_Pass_Clearance_Certificate_20151031

Client: Binutti Constructions H1560_ANU Building 48_ACT_MA_20151028 Page 6 of 6

APPENDIX B - FIBRE IDENTIFICATION CERTIFICATE OF ANALYSIS