9 Section 5B - TECH Requirements

Embed Size (px)

Citation preview

  • 7/31/2019 9 Section 5B - TECH Requirements

    1/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    TECHNICAL REQUIREMENTS

    IA. DRY FLY ASH HANDLING EQUIPMENT MECHANICAL

    1.0 FLY ASH HOPPER ISOLATIONVALVES

    1.1 Manufacturer : Self manufactured

    1.2 Numbers provided & location : As Pre flow Scheme

    1.3 Type of Valve & Its operation : Isolation Valve and ChainOperated

    1.4 Size : To Suit System Requirement

    1.5 Material of Construction andHardness of Components

    1.5.1 Body : As per Spec. & EEPL Standard

    1.5.2 Gate/Plate/Disc (Indicate thicknessalso)

    : As per Spec. & EEPL Standard

    1.5.3 Seat : As per Spec. & EEPL Standard

    1.5.4 Operating Gear : As per Spec. & EEPL Standard

    1.5.5 Chain : As per Spec. & EEPL Standard

    1.6 Drawing of the isolation Valveenclosed

    : DDE

    2.0 ADAPTOR PIECE

    2.1 No. of Adaptor Pieces provided : As per Flow Scheme

    2.2 Material and Thickness of Adaptor Pieces

    : MS & 10mm Thick

    2.3 Weight of Adaptor Piece : DDE

    3.0 FLY ASH EXTRACTION VALVE

    3.1 Manufacturer : Self Manufactured

    3.2 Type of Valve :

    3.3 Location & No. of Valves : As per Flow Scheme

    3.4 Size : 200 NB

    3.5 Fly Ash Extraction Rate (Tonnes/Hr) : 45 T/hr

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 1 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    2/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    3.06 Material of Construction andHardness of Components:

    :

    3.6.1 Body : As per Spec. & EEPL Standard

    3.6.2 Plate/Disc/Gate/Dome/Cone(Indicate thickness also)

    : As per Spec. & EEPL Standard

    3.6.3 Seat (Specify Details in case of Inflatable Seat offered)

    : As per Spec. & EEPL Standard

    3.07 Type of Operating Device : As per Spec. & EEPL Standard

    3.8 Other specific Features of Valves, if

    any

    :

    3.9 Access Platforms with necessaryStaircase provided below ESPHoppers for the Operation &Maintenance of Fly Ash ExtractionValves and other equipment/instruments, etc.?

    : Yes

    4.0 EXPANSION JOINTS : As applicable

    4.1 Manufacturer : Self Manufactured

    4.2 Type : Bellow Type

    4.3 Standard to which the ExpansionJoints conform

    : As per Spec. & EEPL Standard

    4.4 Material of Construction :

    4.4.1 Bellow/Convolutes : SS

    4.4.2 Inner Liner :

    4.5 Expansion

    4.5.1 In Axial Direction : To Suit System Requirement

    4.5.2 In Lateral Direction : To Suit System Requirement

    4.6 Angular Deflection : To Suit System Requirement

    4.7 Type of End Connection : To Suit System Requirement

    4.8 Location & Number of ExpansionJoints provided

    : As per flow scheme

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 2 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    3/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    5.0 FLY ASH BRANCH ISOLATIONVALVES (FOR VACUUM &

    PRESSURE SYSTEMS)

    :

    5.1 Manufacturer : Self Manufactured

    5.2 No. of Valves & Location : As per flow scheme

    5.3 Type of Valves : Pneumatic Operated Isolationvalves

    5.4 Size : 200 NB

    5.5 Material of Construction andHardness of Components

    :

    5.5.1 Body : As per Spec. & EEPL Standard

    5.5.2 Gate/Disc/Plate/Dome (IndicateThickness also)

    : As per Spec. & EEPL Standard

    5.5.3 Seat (specify details in caseinflatable seat offered)

    : As per Spec. & EEPL Standard

    5.6 Type of Operating Device :

    5.7 Other specific features of the Valve,if any

    :

    6.0 PNEUMATIC ASH TRANSPORTPIPE LINES & FITTINGS

    :

    6.1 Piping : Vacuum PressureConveying from ConveyingESP Hoppers from Surgeto Surge Tank/ Tank toWetting Head Storage

    Silo6.1.1 Manufacturer : Approved Vendor

    6.1.2 Material and Hardness : CI Class D MS ERW

    6.1.3 Standard : IS 1536/ IS1239/3589BS 1211

    6.1.4 Size (OD x Thk.) : 200 NB 200 NB

    6.1.5 Velocity of Air Ash Mixture (M/Sec.) : DDE

    6.1.6 Pick Up Velocity : DDE

    6.1.7 Exit Velocity : DDE

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 3 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    4/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    6.1.8 Friction Coefficient : DDE

    6.1.9 Air Pressure Drop (Kg/Cm2(g) : DDE

    6.1.10 Ash Air Mixture Pressure Drop(Kg/Cm2(g)

    : DDE

    6.1.11 Maximum Length of Pipingconsidered for Pressure drop (M)

    :

    6.1.12 No. of Length of Pipes :

    6.1.13 Quantity of each Pipe Length (M) :

    6.1.14 Total Pipe Quantity (M) :

    6.1.15 Type of Joints :

    6.1.16 Pipe to Pipe :

    6.1.17 Pipe to Fitting/Valve :

    6.1.18 Fitting to Fitting/Valve :

    6.2 Fittings (Elbows, Bends Etc.) AndSpool Piece

    :

    6.2.1 Manufacturer : Self Manufactured

    6.2.2 Type of Fittings & Spool Piece : ACI Fittings

    6.2.3 Estimated No. of various Fittings &Spool Pieces

    : DDE

    6.2.4 Radius of Fittings : 5D

    6.2.5 Length of Straight Spool Piece : DDE

    6.2.6 Material of Construction, Thickness

    and Hardness of Fittings, SpoolPiece and Lining, if applicable

    : As per Specification

    7.0 SURGE TANK

    7.1 Manufacturer : Self Manufactured

    7.2 Total No. of Surge Tanks Provided : One(1) Nos

    7.3 Holding Capacity of each SurgeTank (Tonnes)

    To Suit

    7.3.1 Effective Holding Capacity : DDE

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 4 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    5/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    7.3.2 Total Capacity : DDE

    7.4 Type of Surge Tank :

    7.5 Pressure/Vacuum Relief Systemprovided for:-

    - Surge Tank- Existing Silo

    ::

    YesYes

    7.6 Type of Venting arrangement for contaminated air from Surge Tank

    :

    7.7 Whether bag/ vent filters & fans as

    specified have been provided on :-

    - Surge Tank- Existing Silo

    :

    YesYes

    7.8 Material of Construction andThickness

    7.8.1 Body : MS as per IS 2062

    7.8.2 Liners (indicate hardness also) :

    7.9 All accessories, supporting StructureSteel, platforms, Staircases, etc.,included as per Specificationsrequirement?

    : Yes

    7.10 No. of Outlet connection provided :

    8.0 FLUIDISING SYSTEM ESP Hoppers/ StorageSurge Tank Silo

    (Existing)

    8.1 Manufacturer : Self Manufactured

    8. Type of Aeration System (whether Aeration Pads or Air Slides)

    : Aeration Pad Aeration Slide

    8.3 No. of Air Slides Provided:

    DDE

    8.4 No. of Fluidising Pads provided : 2 Nos./ESP Hopper

    8.5 Quantity of Fluidising air required for each Surge Tank silo (NM3/Min)

    : DDE

    8.6 Pressure of fluidizing air required,Kg/cm2(g)

    : As per Load List

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 5 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    6/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    8.7 Temperature of Fluidising Air oC : DDE

    8.8 Material of construction of FluidisingPads

    : DDE

    8.9 Material of Construction of Air Slides : As per Spec. & EEPl Standard

    8.10 Slope provided : DDE

    8.11 Air quantity required NM3/Min. : DDE

    8.12 No. of Blowers/Fan provided : As per Flow Scheme

    8.13 Material of porous media : DDE

    8.14 Source of Fluidising Air to besupplied to Surge Tank/Silo

    : DDE

    9.0 ASH TRANSFER VESSELS (forPneumatic Ash Extraction &Transportation System)

    9.1 No. of Ash Transfer Vesselemployed per Unit

    : As per Flow Scheme

    9.2 Sequence of operation of AshTransfer Vessel

    : DDE

    9.3 Size of Ash Transfer Vessel inlet andoutlet (mm)

    : DDE

    9.4 Capacity of each Ash Transfer Vessel (CuM.)

    : DDE

    9.5 No. of As Feed Valves provided atthe inlet of each Ash Transfer Vessel

    :

    9.6 Type of discharge system (whether

    bottom discharge or top discharge)

    :

    9.7 No. of Isolation Valves (if any)provided at the outlet of each AshTransfer Vessel

    :

    9.8 Type of Ash Feed/Outlet Valves(indicate method of OperatingDevice of Valve)

    :

    9.9 Ash Extraction Rate per AshTransfer Vessel

    :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 6 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    7/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    9.10 Fly Ash/Air ratio by weight at AshTransfer Vessel outlet

    :

    9.11 Design velocity of ash air mixture atAsh Transfer Vessel outlet

    :

    9.12 Ash Transfer Vessel material of Construction

    :

    9.13 Ash Transfer Vessel Design Code :

    9.14 Ash Transfer Vessel DesignPressure

    :

    9.15 Ash Transfer Vessel over Pressuresafety equipment

    :

    9.16 No. of Conveying Lines from AshTransfer Vessel

    :

    9.17 Compressed Air Pressure andQuantity requirement at each AshTransfer Vessel

    :

    10.0 BAG FILTERS/VENT FILTERS On Surge Tank On ExistingSilo

    10.1 Make : Self Manufactured

    10.2 Type and Size : Reverse Pulse Jet

    10.3 Material of Filtering Media : Ash

    10.4 Maximum/Continuous PermissibleTemperature for Filtering Media :

    10.5 Air Dust Flow rate for which bagfilters have been sized (M3/Hr)

    : DDE

    10.6 Guaranteed Outlet Dust Emission(mg/Nm3)

    : DDE

    10.7 Material of Construction of Body &Thickness

    : DDE

    10.8 Type of Bag Filter cleaningarrangement offered?

    :

    11.0 AIR INTAKE VALVE

    11.1 Manufacturer : Self Manufactured

    11.2 Location and No. of Valve : As per Flow Scheme

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 7 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    8/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    11.3 Type of Valves : As per Spec. and EEPL standard

    11.4 Size :

    11.5 Material of Construction andHardness of Components

    :

    11.5.1 Body : As per Spec & EEPL Std.

    11.5.2 Seat : As per Spec & EEPL Std.

    11.5.3 Spring : As per Spec & EEPL Std.

    11.5.4 Disc : As per Spec & EEPL Std.

    11.6 Type of Operating device :

    12.0 VACUUM BREAKER

    12.1 Manufacturer : Self Manufactured

    12.2 Type of Valve :

    12.3 Quantity : As per Flow Scheme

    12.4 Size : To Suit

    12.5 Location :

    12.6 Material of Construction andHardness of Components

    :

    12.6.1 Body : As per Spec & EEPL Std.

    12.6.2 Gate/Plate/Disc (indicate thicknessalso)

    : As per Spec & EEPL Std.

    12.7 Type of Operating device : Pneumatic Operation

    12.8 Other specific features of the Valve :

    13.0 MECHANICAL EXHASTERS/VACUUM PUMPS

    13.1 Manufacturer : Approved Vendor

    13.2 Type & Model No. : Liquid Ring Type

    13.3 Design Standard : As per Spec & OEM Std

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 8 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    9/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    13.4 Guaranteed Vacuum Pumpscapacity (CFM) at Pump Inlet

    conditions of 60oF Gas Temp. 60oFSeal water temp. & 50% RH

    : Refer Load List

    13.5 Volumetric efficiency % : DDE

    13.6 Isothermal efficiency % : DDE

    13.7 Mechanical efficiency % : DDE

    13.8 Vacuum Pumps working pressure(inch of mercury column vacuum)

    : Refer Load list

    13.9 No. of Vacuum Pumps working andstandby for the unit

    : As per Flow Scheme

    13.10 Type of Transmission between pump& motor

    : Belt Driven

    13.11 Maximum Pump input power in theentire operating Range (KW)

    : Refer Load List

    13.12 Transmission Efficiency : DDE

    13.13 Max. Permissible inlet gas temp. atsuction of vacuum pump (oC)

    : As per Spec

    13.14 Material of Construction andHardness of various components

    :

    13.14.1 Body : As per Specification

    13.14.2 Rotor : As per Specification

    13.14.3 Shaft : As per Specification

    13.14.4 Shaft Sleeve : As per Specification

    13.14.5 Port Plates/Cone : As per Specification

    13.15 Quantity (m3/Hr) and quality of working/seal water required

    : DDE

    13.16 Condensing factor at seal water temperature

    : DDE

    13.16.1 At 15oC : DDE

    13.16.2 At 36oC : DDE

    13.17 Motor rating at 50oC Ambient (KW) Refer Load List

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 9 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    10/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    14.0 AIR COMPRESSORS/ BLOWERSFOR DRY FLY ASH

    TRANSPORTATION (To be filledseparately for each type and size)

    14.1 Type and make : Oil Free Reciprocating Type

    14.2 Operating/rated speed of compressor/blower shaft

    : As per OEM Standard

    14.3 Discharge Pressure (Kg/cm2(g) : Refer Load List

    14.4 Discharge Capacity (Nm3/Min) : Refer Load List

    14.5 Design Standard :

    14.6 No. offered (indicate Nos. workingand Nos. standby)

    :

    14.7 Design Conditions:

    14.7.1 Ambient Temper (oC) : 50 Deg C

    14.7.2 Ambient Pressure (Kg/cm2) :

    14.7.3 Ambient Relative Humidity (%) : 100 %

    14.7.4 Mean Sea Level (m) :

    14.8 FAD at design conditions(Cu. M/hr)

    :

    14.9 Maximum shaft input power over operating range (KW)

    : Refer Load List

    14.10 Motor Rating at 50oC Ambient (KW)and motor speed

    :

    14.11 Type of Transmission between

    motor and compressor/blower

    : Direct drive

    14.12 Inlet air Filter details:

    14.12.1 Inlet Filter Area (Sq. m) : DDE

    14.12.2 Filter efficiency (% Microns) : DDE

    14.13 Air Drying Plant (forCompressors)

    14.13.1 Manufacturer : Approved Vendor

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 10 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    11/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    14.13.2 Model No. : DDE

    14.13.3 Type of Air drying plant provided : Refrigerated Type

    14.13.4 Numbers offered :

    14.13.5 Design, air flow (Nm3/Min) andTemp. (oC) at Plant Inlet

    :

    14.13.6 Air Pressure drop in air drying plantKg/cm2(g)

    : DDE

    14.13.7 Dew Point of air after Air DryingPlant (oC)

    : DDE

    14.13.8 Refrigeration tonnage (TR) of air drying plant, corresponding tocooling water temp. of 38oC

    : DDE

    14.13.9 Motor rating of air drying plant at50oC (KW)

    : DDE

    14.14 Compressed Air Heatingarrangement details (applicable forBlowers only)

    :

    14.14.1 Air temperature at inlet to air heater (oC)

    :

    14.14.2 Air temperature at heater outlet (oC) :

    14.14.3 Type of air heating/rating of air heater (KW)

    :

    14.14.4 Dew Point of compressed air (oC) :

    14.15 Offered compressor/blower is oil-freedesign or oil injector design with oilseparator?

    :

    14.16 Material of construction of variouscomponents

    :

    14.16.1 Body :

    14.16.2 Rotor/Screw :

    14.16.3 Shaft :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 11 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    12/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    14.17 Oil Carry over in compressed air atthe down stream of oil filter in case

    of oil injected compressor/blowerwith oil separator (ppm)

    :

    14.18 Air receiver details

    14.18.1 No. and Location :

    14.18.2 Design standard :

    14.18.3 Size (Length x Dia mm) :

    14.18.4 Material of construction :

    14.18.4.1 Shell :

    14.18.4.2 Dished Ends :

    14.18.4.3 Design Pressure :

    14.19 Cooler (if provided) :

    14.19.1 Water cooled or air cooled :

    14.19.2 If water cooled, State water pressurein Kg/cm2 and quantity in Cu. M./hr

    :

    14.20 Bearing details

    14.20.1 Make & Type :

    14.20.2 Bearing No. & Qty. :

    14.20.3 Lubricant used :

    15.0 INSTRUMENT AIR COMPRESSORAND DRYING PLANT

    15.1 Instrument Air Compressor

    15.1.1 Manufacturer : Approved Vendor

    15.1.2 Model Number : DDE

    15.1.3 Type of Compressor : As Per Spec.

    15.1.4 Qty. offered (indicate nos. workingand no. standby)

    :

    15.1.5 FAD of each compressor at design

    ambient (Cu. M/hr)

    :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 12 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    13/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    15.1.6 Discharge Pressure (kg/cm2(g) :

    15.1.7 Discharge capacity (Nm3/Min) :

    15.1.8 Design condition:

    15.1.8.1 Design Ambient Temp. (oC) :

    15.1.8.2 Design Ambient Pressure (Kg/cm2) :

    15.1.8.3 Design Ambient Relative Humidity(%)

    :

    15.1.8.4 Mean Seal Level (m)

    15.1.9 Design Standard :

    15.1.10 Air Temperature after first stage of Compressor

    :

    15.1.11 Air temperature after last stagecompression

    :

    15.1.12 Outlet air temperature (after cooler)oC

    :

    15.1.13 Maximum Shaft input power requiredin the entire operating rage (KW)

    :

    15.1.14 Type of Transmission betweenMotor and Compressor

    :

    15.1.15 Motor rating at 50oC Ambient :

    15.1.16 Crank shaft speed (rpm) :

    15.1.17 No. of Stages :

    15.1.18 Single acting or double acting :

    15.1.19 Cylinder/compression chamber borein mm

    :

    15.1.20 Stroke/Length mm :

    15.1.21 Clearance in % in volume :

    15.1.22 Method of cylinder/compressionchamber lubrication

    :

    15.1.23 Cooling by air or water :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 13 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    14/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    15.1.24 If water cooled, state pressure inKg/cm2, and m3/hr

    :

    15.1.25 Type of valves (Suction andDischarge)

    :

    15.1.26 Inter Cooler (if provided) :

    15.1.26.1 Water cooler or air cooled :

    15.1.26.2 If water cooled state pressure inkg/cm2 and quantity m3/hr

    :

    15.1.27 Bearing Details

    15.1.27.1 Type & Make :

    15.1.27.2 Bearing No. and quantity :

    15.1.27.3 Lubricant used :

    15.1.28 Intake air filter

    15.1.28.1 Inlet Filter area (m2) :

    15.1.28.2 Filter efficiency (% microns) :

    15.2 Air Receiver Details

    15.2.1 Design standard :

    15.2.2 Nos. offered and Location :

    15.2.3 Size (Length x Dia mm) and capacity(CuM.)

    :

    15.2.4 Material of Construction :

    15.2.4.1 Shell :

    15.2.4.2 Dished Ends :

    15.2.5 Design Pressure :

    15.3 Air Drying Plant :

    15.3.1 Manufacturer :

    15.3.2 Model No. :

    15.3.3 Type of Air Drying Plant :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 14 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    15/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    15.3.4 Nos. offered :

    15.3.5 Design Air Flow at Plant Inlet(NM3/Min)

    :

    15.3.6 Air temperature at inlet of air dryingplant (oC)

    :

    15.3.7 Dew Point of air after Air DryingPlant (oC)

    :

    16.0 WATER AND AIR PIPING VALVES & FITTINGS

    16.1 Water And Air Piping

    Give details of water piping for ash water system, seal water system,compressed air piping, and any other piping (in the same serial order in theform below) (Use extra sheets if necessary

    Service&Location

    DesignPressure

    Kg/cm2(g)

    Materialand

    Standardof

    Manufacturer

    Lengthconsidered

    TypeofPipeJoint

    Remarks

    16.1.1

    16.1.2

    16.1.3

    16.1.4

    16.1.5

    16.1.6

    16.2 Water And Air Line Valves

    Give details of Valves for Ash Water System, Seal Water System compressedair piping, any other piping (in the same order in the form below) (Use extrasheets if necessary

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 15 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    16/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    ServiceandLo

    cation

    Type(Gate,G

    lobe,

    Plug,etc

    .)

    MaterialofConstr

    uction

    (IS,BSorequiva

    lent)

    Make

    DesignPressure

    (Kg/cm2(g)

    EndDetails(scr

    ewed,

    flangedetc.)

    Remarks

    16.2.1

    16.2.2

    16.2.3

    16.2.4

    16.2.5

    16.2.6

    16.3 Furnish all necessary piping includingvalves, fittings, strainers, flanges,indicators, hangers supports, auxiliarysteel etc. as required

    : Yes/No

    17.0 WATER CONSUMPTION DATA

    17.1 Seal Water/Raw Water required for Quantity PressureM3/Hr Kg/cm2

    17.1.1 TAC/ TAB Cooling :

    17.1.2 IA Comp. Cooling :

    17.1.3 Vacuum Pump Sealing :

    17.1.4 Others (specify & indicate) :

    18.0 AIR REQUIREMENT DATA

    18.1 Approx. free air requirement (Nm3/Min) :

    18.1.1 Valve Operation :

    18.1.2 Storage and Surge Tank FluidisingSystem

    :

    18.1.3 Bag /Vent filters

    18.1.4 Other requirements as per equipment /

    System Design

    :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 16 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    17/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    18.2 Technical details of Air Pressurereducing stations, air heaters and filters

    submitted?

    : Yes/No

    19.0 PUMPS

    19.1 WATER PUMPS LP Ash Water Booster Pump

    Cooling WaterPump

    SealingWaterPump

    19.1.1 Manufacturer

    19.1.2 Model and Type

    19.1.3 Qty. furnished(Working + Standby)

    19.1.4 Rated Capacity, M3/hr

    19.1.5 Total Dynamic Head atspecified ratedcapacity, MWC

    19.1.6 Shut-off head, MWC

    19.1.7 Pump efficiency at ratedcapacity point

    19.1.8 Pump input power atspecified ratedcapacity, KW

    19.1.9 Power required at Pumpshut-off, KW

    19.1.10 Rated output of the drivemotor, KW

    19.1.11 Design temperature of

    water, oC

    19.1.12 Pump Speed, rpm

    19.1.12.1 Operating

    19.1.12.2 Maximum

    19.1.12.3 Specific speed (indicatealso the formulaand units used)

    19.1.13.1 Flange Size, Suction(mm)

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 17 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    18/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    19.1.13.2 Flange Size, Discharge

    (mm)

    19.1.14 No. of Stages

    19.1.15 Impeller Size and Type

    19.1.16 No. of Vanes

    19.1.17 Material of Construction(mention IS orequivalent)

    19.1.17.1 Casing (specify BHN)

    19.1.17.2 Impeller (specify BHN)

    19.1.17.3 Impeller Wear Ring(specify BHN)

    19.1.17.4 Casing Wear Ring(specify BHN)

    19.1.17.5 Shaft Sleeve (specifyBHN)

    19.1.17.6 Shaft

    19.1.17.7 Stuffing Box

    19.1.17.8 Bolts, Nuts, Fasteners

    19.1.17.9 Base Plate

    19.1.17.10 Pump Shaft Bearing

    19.1.17.10.1 Quantity

    19.1.17.10.2 Type of Lubrication

    19.1.17.10.3 Arrangement of Cooling

    19.1.17.11 Pump Thrust Bearing

    19.1.17.11.1 Location

    19.1.17.11.2 Type

    19.1.17.11.3 Lubrication

    19.1.18 Design of Pumpconforms to

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 18 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    19/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    Code/Standard No.

    19.1.19 Characteristic curves for the pumps andother data asrequired by thespcn. enclosed withthe Proposal

    Yes/No Yes/No Yes/No

    19.1.20 Coupling between Motor Shaft and PumpShaft

    19.1.21.1 Manufacturer

    19.1.21.2 Type

    19.1.21.3 Coupling Guardfurnished

    19.1.21.4 Furnished air releasevalves, drain plugs,etc.

    19.1.22 Total Weight of PumpMotor Assembly(Kg)

    19.1.23 Various shop testconform to therequirement of thespecification

    Yes/No Yes/No Yes/No

    19.1.24 Performance testing of pumps possible inManufacturersshop

    Yes/No Yes/No Yes/No

    19.1.25 If the above answer in

    No, explain clearlywhether testing atcondition other thanrated condition canbe undertaken bymanufacturer andcode followed

    20.0 MANUALLY OPERATEDPENDANTCONTROLLED EOTCRANE

    Transport Air Compressor/Blower/ Vacuum Pump/ WaterPump House (Existing RCWBuilding)

    20.1 Name of the Manufacturer

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 19 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    20/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    20.2 No. of Cranes

    20.3 Max. Weight to be handledduring erection andmaintenance

    20.4 Performance Data

    20.4.1 Class of crane & IS Code

    20.4.2 Hoist Capacity, Tonnes

    20.4.3 Maximum Lift of Hoist, Metre

    20.4.4 Bridge Travel, Metre (Existing)

    20.4.5 Trolley Travel, Metre (Existing)

    20.4.6 Span, Metre (Existing)

    20.4.7 Hoisting speed

    20.4.8 Cross Travel Speed

    20.4.9 Type of Control

    20.4.10 Creep Speed

    20.5 Crane Design Data

    20.5.1 Crane Bridge

    20.5.1.1 Girder Particulars

    20.5.1.2 Type of Grinder Construction

    20.5.1.3 Material

    20.5.1.4 Numbers Provided

    20.5.2 Runway Rails

    20.5.2.1 Type or Size

    20.5.2.2 Length

    20.5.2.3 Material

    20.5.3 Bridge travel Buffers

    20.5.3.1 Numbers

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 20 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    21/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    20.5.3.2 Type of Stops to engageBuffers

    20.5.4 Rail Clamp

    20.5.4.1 Type

    20.5.4.2 Material

    20.5.5 Manual Traversing Device

    20.5.5.1 Type of Operation

    20.5.5.2 Length of Operating Chain

    provided

    20.5.5.3 Material of Chain

    20.5.5.4 Material of driving Gear

    20.6 Trolley Assembly

    20.6.1 Trolley Frame particulars

    20.6.1.1 Type of Construction

    20.6.1.2 Material

    20.6.2 Trolley Drive Motor

    20.6.2.1 Manufacturer

    20.6.2.2 Type

    20.6.2.3 Voltage, Phase, Frequency

    20.6.2.4 KW Rating

    20.6.2.5 Rated Speed, RPM

    20.6.3 Hoisting Mechanism

    20.6.3.1 Winding Drum

    20.6.3.1.1 Type and Size

    20.6.3.1.2 Material

    20.6.3.1.3 Ratio of winding drum diameter to diameter of wire rope

    20.6.3.2 Hoist Drive Motor

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 21 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    22/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    20.6.3.2.1 Manufacturer

    20.6.3.2.2 Type

    20.6.3.2.3 KW Rating at 50oC

    20.6.3.2.4 Voltage, Phase, Frequency

    20.6.3.2.5 Rated Speed, rpm

    20.6.3.3 Service Brake

    20.6.3.3.1 Type

    20.6.3.3.2 Type of Control

    20.6.3.3.3 Location

    20.6.3.3.4 Breaking Capacity, % of fullload Torque

    20.6.3.3.5 Braking Time

    20.6.3.3.6 Brake Drum material to IS

    20.6.3.3.7 Brake Shoe Material

    20.7 Electrical

    20.7.1 Limit Switches (furnish detailsfor all)

    20.7.1.1 Manufacturer

    20.7.1.2 Type

    20.7.1.3 Material of Contact

    20.7.2 Controllers for Motors (furnish

    details of all motors)

    20.7.2.1 Type

    20.7.2.2 Manufacturer

    20.7.3 Main/Runway Conductors

    20.7.3.1 Type

    20.7.3.2 Manufacturer

    20.7.3.3 Size

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 22 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    23/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    20.7.3.4 Material

    20.7.3.5 Length provided

    20.7.4 Flexible Cables

    20.7.4.1 Manufacturer

    20.7.4.2 No. of Cores/Size

    20.7.4.3 Material

    20.7.4.4 Length provided

    20.7.5 Switch Board and WiringDetails

    20.7.6 Pendant details as per specification requirements

    20.7.7 Safety arrangement

    21.0 PAINTS (List out for allequipment/structure)

    :

    21.1 Type of Primer and Number of Coats :

    21.2 Make of Primer :

    21.3 Type of final Paints and No. of Coats :

    21.4 Make of Final Paints :

    21.5 Dry Film thickness of System :

    22.0 MEASURING INSTRUMENTS (Primary & Secondary)

    22.1 Performance data detailed technicalliterature/design specification

    sheet and technical datacovering the guaranteedperformance of each of theproposed equipment for thedesign and operating conditionsspecified at

    :

    22.2 Experience(Refer lists to satisfy the employerregarding compliance with qualifyingrequirements for samemake/model/product range as those

    proposed y the bidder for this project

    :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 23 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    24/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    22.3 Bill of Material

    Complete Bill of Material for allmeasuring instruments coveredunder this section, coveringmake, model No., range,technical features, accessoriesfurnished, quantity offered andall other relevant data for eachitem

    :

    22.4 Electronic Transmitters :

    22.4.1 Make & Model No. :

    22.4.2 Output Signal (Analog) :

    22.4.3 Whether provision of digitalcommunication on hart protocol

    : Yes/No

    22.4.4.1 Accuracy :

    22.4.4.2 Stability :

    22.4.5 Electrical connection through plug &sockets

    : Yes/No

    22.4.6 Response time (time betweenchange in process variable &signal available at transmitteroutput terminal) for 4-20ma/superimposed hart signal

    :

    22.4.6.1 For 4-20 ma analog :

    22.4.6.2 For superimposed hart signal :

    22.4.7 Technical literature furnished at :

    22.5 Temperature Sensing Elements/Wells

    :

    22.5.1 Temperature Elements : Thermo ThermoCouple CoupleK Type R Type

    22.5.1.1 Make & Model No. :

    22.5.1.2 Dual Elements grounded/ under grounded

    :

    22.5.1.3 Response Time :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 24 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    25/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    22.5.1.4 Protective Sheath with MgOinsulation provided as per

    specification

    :

    22.5.1.5 Limits of Error/Accuracy :

    22.5.1.6 Time constant (indicate for variousapplications)

    :

    22.5.1.7 Applicable Standard :

    22.5.2 Thermowells :

    22.5.2.1 Make & Model No. :

    22.5.2.2 Construction Material offered for following services:

    22.5.2.2.1 Furnace :

    22.5.2.2.2 Flue Gas Services :

    22.5.2.2.3 Mill Classifier Outlet :

    22.5.2.2.4 Others :

    22.5.2.3 Applicable Design Standard :

    22.6 Flow Gauges/Indicators : Rotameter Flow Gauge

    22.6.1 Make & Model No. :

    22.6.2 Body/Material :

    22.6.3 Accuracy :

    22.6.4 Accessories :

    22.7 Process Actuated Switches : Press/DP Temp. Level

    Switch Switch Switch

    22.7.1 Make & Model No. (Application wise) :

    22.7.2 Sensing Element :

    22.7.3 Material :

    22.7.4 Repeatability :

    22.7.5 Contact Rating & No. of Contacts :

    22.7.6 Accessories :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 25 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    26/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    22.8 Indicator/Recorders : Digital / IntegralIndicator / Recorder

    22.8.1 Make & Model No. :

    22.8.2 Type :

    22.8.3 Input Signal :

    22.8.4 Accuracy :

    22.8.5 Size :

    22.8.6 Response Time :

    22.8.7 Mosaic Compatible : Yes/No Yes/No

    22.9 Electrical Meters :

    22.9.1 Motor Current Ammeters :

    22.9.1.1 Manufacturers Name :

    22.9.1.2 Model No. :

    22.9.1.3 Overall Dimensions : W . mm x H .mm x D mm

    22.9.1.4 Accuracy : . % of full scale

    22.9.1.5 Technical literature furnished at :

    22.9.2 Voltmeters

    22.9.2.1 Manufacturers Name :

    22.9.2.2 Model No. :

    22.9.2.3 Input :22.9.2.4 Overall Dimensions : W . mm x H .mm x D mm

    22.9.2.5 Accuracy : . % of full scale

    22.9.2.6 Technical literature furnished at :

    22.10 Level Transmitters (UltrasonicType)

    :

    22.10.1 Make & Model No. :

    22.10.2 Accuracy :

    22.10.3 Type :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 26 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    27/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    22.10.4 Compatible to HART communication : Yes/No

    22.11 Level Transmitters (RF Type)

    22.11.1 Make & Model No. :

    22.10.2 Accuracy :

    22.10.3 Type :

    22.10.4 Compatible to HART Communication : Yes/No

    22.11 Level Transmitters (RADAR Type)

    22.11.1 Make & Model No. :

    22.11.2 Accuracy :

    22.11.3 Type :

    22.11.4 Compatible to HART communication : Yes/No

    22.12 Dew Point Monitor

    22.12.1 Make & Model No. :

    22.12.2 Accuracy :

    22.12.3 Type :

    22.12.4 Compatible to HART communication : Yes/No

    23.0 INSTRUMENTATION CABLE,INTERNAL WIRING ANDELECTRICAL FIELDCONSTRUCTION MATERIAL

    23.1 Technical Information23.1.1 Detailed technical literature and data

    conveying specification of eachtype of instrumentation cable,internal wiring, electrical fieldconstruction material and allother accessories

    :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 27 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    28/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    23.1.2 Typical interconnection philosophydiagram (refer sub-section-INST

    CABLE Part-B of Section-VI)indicating signal routing fromfield to the control systemcabinets along with the type ofcables employed for eachinterconnection furnished at(This should cover both mainplant and auxiliary plant)

    :

    23.2 Bill of MaterialComplete bill of material for all

    instrumentation cables including

    prefabricated cables, co-axialcables, electrical fieldconstruction materials andaccessories furnished as perspecification

    :

    23.3 Proposal Data Sheets

    Bidder shall furnish the followingdata separately for each type &size of instrumentation cableincluding special cables

    23.3.1 Manufacturers Name :

    23.3.2 Reference design standards :23.3.3 Conductor Size :23.3.4 Conductor Material :23.3.5 No. of Pairs/Cores :

    23.3.6 Conductor 23.3.6.1 Material :23.3.6.2 Reference Standard :23.3.6.3 Grade :23.3.6.4 No. of Strands :

    23.3.6.5 Diameter of Strands (mm) :

    23.3.6.6 Approx. dia of conductor (mm) /cross section area (Sq.mm)

    :

    23.3.6.7 Maximum conductor resistance per KM (in Ohm)

    :

    23.3.7 Insulation

    23.3.7.1 Reference Standard :

    23.3.7.2 Material Composition :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 28 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    29/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    23.3.7.3 Nominal Thickness (mm) :23.3.7.4 Thickness (mm) : Min. . Max.

    23.3.7.5 Minimum Volume Resistivity as per VDE-0207 Part-IV

    : .. ohm cm at 20oC

    23.3.7.6 Dielectric Constant : ohm cm at 70oC23.3.7.7 The insulation will withstand

    conductor operating temp. of 70Deg. C/ 205 Deg. C (if applicable) specificconfirmation required)

    : Yes/No

    23.3.7.8 Core diameter (mm) includinginsulation

    :

    23.3.8.1 Whether Pairs are twisted : Yes/No23.3.8.2 Maximum lay of twist (mm) :

    23.3.9 Shield23.3.9.1 Material :23.3.9.2 Thickness over individual pair in mm

    (if applicable):

    23.3.9.3 Thickness of overall shield (in mm) :

    23.3.9.4 Noise interference better than : db23.3.10 Drain Wire23.3.10.1 Reference standard :

    23.3.10.2 Size & No. of Strands :

    23.3.10.3 Material :23.3.10.4 Resistance of drain wire per Km

    (ohm):

    23.3.10.5 Separate Drain wires for i ndividualas well as overall shieldprovided

    : Yes/No

    23.3.11 Fillers (if applicable) are flameretardant and moisture resistant

    :

    23.3.12 Outer Sheath :

    23.3.12.1 Reference standard :23.3.12.2 Material :23.3.12.3 Nominal thickness of outer sheath

    (mm):

    23.3.12.4 Thickness of outer sheath (mm) : Min.. Max.

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 29 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    30/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    23.3.12.5 Calculated Dia. Under outer sheath(mm)

    :

    23.3.12.6 Oxygen index (as per ASTMD-2863)in %

    :

    23.3.12.7 Temperature index (in deg.C as per ASTMD-2863)

    :

    23.3.12.8 Maximum acid gas Generation (byWeight) as per IEC-754-1 (in %)

    :

    23.3.12.9 Colour of outer sheath sky blue asper specification

    : Yes/No

    23.3.13.1 Overall diameter of cable (mm) :

    23.3.13.2 Tolerance on overall diameter (mm) :

    23.3.13.3 Weight per KM of cable :

    23.3.14 Cable Parameters at 20oC (+ 3oC) :

    23.3.14.1 Conductor resistance (max.) :23.3.14.2 Insulation resistance (min.) :23.3.14.3 Mutual capacitance at 0.8 kHz (Max) :

    23.3.14.4 Cross Talk at 0.8 kHz (Min.) :23.3.14.5 Attenuation at 1 kHz (Max.) :23.3.14.6 Characteristic Impedance (Max.) :23.3.15 Continuous operating temp. (oC) :23.3.16 Whether Complete Cable Assembly

    flame retardant as per IEEE-383

    : Yes/No

    23.3.17 Whether complete cable assemblypasses Swedish Chimney testas per SEN 4241475 (f3)

    : Yes/No

    23.3.18 Identification

    23.3.18.1 Length of the Cable marked at everymeter

    : Yes/No

    23.3.18.2 FRLS marked at every 5 meter : Yes/No

    23.3.18.3 Each core of the pair numbered : Yes/No

    23.3.18.4 Conductor identification details for pairs

    : Colour

    Band ..

    Numbering

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 30 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    31/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    23.3.18.5 Details of cable markings :

    23.3.19 Test Voltage : Core to Core Core to Shield

    23.3.19.1 High voltage test (dielectric strength)

    i) Voltage (kV) :

    ii) Duration (min) :

    23.3.19.2 Resistance to direct current test :i) Voltage (kV) :ii) Duration (min) :

    23.3.20 Cable Cross-Sectional Drawings for each type of cable furnished at

    :

    23.3.21 Confirm that cables are includedunder bidders scope on asrequired basis

    : Yes/No

    23.3.22 Confirm that prefabricated cablesshall have 10% spare cores notconnected to connector

    : Yes/No

    23.3.23 Technical Literature furnished at :

    23.3.24 i) Length of single coil in adrum

    :

    ii) Termite proof seasonedwood drum provided

    : Yes/No

    iii) Gross Weight :

    iv) Net Weight :

    v) Identification marksprovided

    : Yes/No

    23.4 Cable termination provided : Yes/No

    23.5 Internal wiring for controldesk/electronic system cabinets

    23.5.1 Conductor size and number of strands

    :

    23.5.2 Conductor Material :23.5.3 Insulation

    23.5.3.1 Conductor insulation material FRLS : Yes/No

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 31 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    32/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    23.5.3.2 Conductor Insulation Thickness :

    23.5.3.3 Applicable design Standard for conductor insulation

    :

    23.5.4 Voltage Grade :

    23.5.5 Reference Standard :

    23.5.6 Technical Literature furnished at :

    24.0 CABLING ACCESSORIES &ELECTRICAL FIELDCONSTRUCTION MATERIAL

    24.1 Confirm that all conduits, conduitsupports, junctionboxes/terminals blocks (withspare terminals as specified)and all electrical fieldconstruction material for theworks included under technicalspecification, shall be furnishedby the Bidder on as requiredbasis

    : Yes/No

    24.2 Confirm that fire proof sealing toprevent entry/propagation offire/dust through floor slots havebeen provided for all application

    : Yes/No

    24.3 Confirm that two (2) new sets of

    cable termination accessoriesrequired for cablingmaintenance work shall besupplied

    : Yes/No

    24.4 List of items covered in 7.03.4.3above with technicalspecification furnished at

    :

    24.5 Type Test Procedures as per VDE0472, IS 10810, VDE 0815 andother relevant standards

    enclosed

    : Yes/No

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 32 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    33/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    24.6 Cable support system :

    24.6.1 Conduit Pipes & Accessories :

    24.6.1.1 Makers Name and Country of Manufacturer

    :

    24.6.1.2 Material :24.6.1.3 Catalogue attached as Annexure no. :

    24.6.1.4 Applicable Standard :

    24.6.2 Junction Boxes

    24.6.2.1 Makers Name and Country of Manufacturer

    :

    24.6.2.2 Material :24.6.2.3 Applicable Standard :24.6.3 Cable Glands

    24.6.3.1 Makers Name and Country of Manufacturer

    :

    24.6.3.2 Type of Cable Gland :

    24.6.3.3 Applicable standard :

    24.6.4 Cable Jointing/Termination Kits

    24.6.4.1 Makers Name and Country of Manufacturer

    :

    24.6.4.2 Type of System

    a) Termination :b) Joints :

    24.6.4.3 Catalogue attached as Annexure No. :

    24.6.4.4 Type Test Reports enclosed asAnnexure No.

    :

    24.6.4.5 Applicable Standard :24.6.5 Cable Lugs & Terminals :24.6.5.1 Makers Name and Country of

    Manufacturer:

    24.6.5.2 Applicable Standard :24.6.6 Type Test procedure as per VDE

    0472 IS:10810, VDE 0815 andother relevant standards

    enclosed

    : Yes/No

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 33 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    34/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    25.0 PROCESS CONNECTION PIPING

    25.1 ScopeConfirm that impulse pipes/tubes,

    sample pipes, pneumatic pipes,required fittings, valves, valvemanifolds, condensing pots,balancing reservoirs, air filterregulators, etc. and otheraccessories for impulse pipingand sample piping system shallbe furnished by the Bidder onas required basis

    : Yes/No

    25.2 Detailed technical literature and dataand bill of materials coveringspecification of each type ofimpulse piping & tubing, samplepiping, pneumatic tubing fittings,instrument valves, valvemanifolds and all other installation hardware &accessories

    25.3 Proposal Data Sheets25.3.1 Impulse Piping/Tubing System

    The following data shall be suppliedindividually for each piping classas applicable

    25.3.1.1 Impulse Pipea) Manufacturers Name :b) Material Specification :c) Size & Schedule No. :

    25.3.1.2 Impulse Tubea) Manufacturers Name :b) Material Specification :c) Wall Thickness :

    25.3.1.3 Fittings

    a) Manufacturers Name :b) Type :c) Material Specification :d) Size :e) Design Rating :

    25.3.1.4 Valvesa) Manufacturers Name :b) Type :c) Material Specification :d) Size :e) Pressure Class :f) Temp. Rating :

    25.3.1.5 Valves Manifoldsa) Manufacturers Name :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 34 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    35/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    b) Type :c) Material Specification :

    d) Design Rating :25.3.2 Sample Piping System (indicate for

    each sample)

    25.3.2.1 Sample Pipea) Manufacturers Name :b) Material Specification :c) Size & Schedule No. :

    25.3.2.2 Fittingsa) Manufacturers Name :b) Type :c) Material Specification :

    d) Design Rating :e) Size :

    25.3.2.3 Air Filter Regulator a) Make & Model No. :

    25.3.2.4 Valvesa) Manufacturers Name :b) Type :

    c) Material Specification :d) Size :e) Pressure Class :f) Temp. Rating :

    25.3.2.5 Purge Rotameter The following data shall be supplied

    individually for:

    a) Make and Model No. :25.3.3 Pneumatic Tube

    a) Manufacturers Name :b) Material Specification :c) Design Rating :d) Size (OD x thickness) :

    25.3.4 Fittingsa) Manufacturers Name :b) Type :

    c) Material Specification :d) Design Rating :e) Size :

    25.3.5 Air Filter Regulator a) Make & Model No. :

    IB. WET FLY ASH HANDLING EQUIPMENT MECHANICAL

    1.0 WETTING HEAD

    1.1 Manufacturer :

    1.2 Quantity :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 35 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    36/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    1.3 Size, Inlet/ Outlet :

    1.4 Material of Construction andHardness of Components

    :

    1.4.1 Body :

    1.4.2 Nozzle Tips :

    1.5 Weight of Assembly :

    1.6 Drawing enclosed : Yes/No

    2.0 COLLECTOR TANK

    2.1 Quantity :

    2.2 Material and Thickness :

    2.2.1 Body

    2.2.2 Liners

    2.2.3 Impact Plate

    2.3 Size

    2.4 Weight of Assembly (Kg.) :

    2.5 Supporting Structure complete withAccess Platforms, Staircase up tothe top level provided?

    : Yes/ No

    3.0 AIR WASHER

    3.1 Manufacturer :

    3.2 Quantity :

    3.3 Size :

    3.4 Material of Construction andHardness of Components:

    :

    3.4.1 Body :

    3.4.2 Nozzle Holder :

    3.4.3 Nozzle Tips :

    3.5 Weight of Assembly :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 36 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    37/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    4.0 VACUUM BREAKER

    4.1 Manufacturer :

    4.2 Type of Valve :

    4.3 Quantity :

    4.4 Size :

    4.5 Location :

    4.6 Material of Construction andHardness of Components

    :

    4.6.1 Body :

    4.6.2 Gate/Plate/Disc (indicate thicknessalso)

    :

    4.7 Type of Operating device :

    4.8 Other specific features of the Valve :

    II. DRY FLY ASH EVACUATION SYSTEM FOR NEW ESP HOPPERS

    ELECTRICAL EQUIPMENTS

    1.0 Information and drawings to be submitted along with the following:

    The following information and drawings of the proposed equipment shall besubmitted in required number of copies by the Bidder along with his proposal.

    1.1 Complete technical literature supported by catalogues for all the equipmentsand accessories covered in his scope of supply.

    1.2 Instruction Manuals for all the equipments covered in the Bidders scope of supply.

    1.3 Technical Data Sheets (guaranteed technical particulars) of the equipmentoffered.

    2.0 Information and drawings to be submitted after the award of the contract.

    2.1 Contractor shall submit all the drawings, data sheets, manuals, catalogues etc.as per the requirements given under applicable sections of the specifications.

    2.2 Drawings showing adequate details o f equipment/panels and accessoriesoffered and typical drawings of major schemes offered.

    2.3 Contractor shall also submit the technical data sheets (Guaranteed TechnicalParticulars) of all the equipments being supplied.

    2.4 Type test and routing test reports for all the equipments and accessories

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 37 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    38/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    covered under Bidder scope of supply.

    3.0 Check List for Information and Drawings to be submitted with the Bid(This check list must be attached to the data sheet)

    3.1 Complete technical literaturesupported by catalogue for all theequipments and accessoriesenclosed

    Yes/No

    3.2 Instruction Manuals for all theequipments enclosed

    Yes/No

    4.0 MOTORS (to be filled in for each Type & Rating)

    4.1 Manufacture & Country of Origin :

    4.2 Equipment

    4.3 a) Motor Type (SquirrelCage/Slip ring/DC etc.)

    :

    b) Type of Duty :

    4.4 Frame Size & Type Destination :

    4.5 Application standard to which motor conforms

    :

    4.6 Standard rating at 50oC ambienttemperature

    :

    4.7 Maximum Power input to the drivenequipment over entire operatingrange (KW) (for HT motors only)

    a) At rated Speed :

    b) At 103% Speed :

    4.8 Stator Winding Insulation

    a) Class & Type :

    b) Tropicalized :

    c) Temperature rise over specified ambient of50oC

    :

    4.9 Direction of Rotation as viewed

    from non-driving end

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 38 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    39/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    4.10 Full load current at rated voltage &frequency

    :

    4.11 Power Factor at rated load :

    4.12 Starting Current at

    a) 100 Voltage :

    b) 85% Voltage

    4.13 Torques (Kg-Meter) at

    a) Starting :

    Pull-up :

    c) Pull-out :

    4.14 Type of Construction of Rotor :

    4.15 Rotor Insulation :

    4.16 Type of Enclosure and Method of Cooling

    :

    4.17 Degree of Protection :

    4.18 Rated Voltage and Frequency :

    4.19 Rated Speed :

    4.20 Efficiency at design duty point(without ve tolerance) and 100%full load

    :

    4.21 Power factory at design duty point :

    4.22 Type of Mounting :

    4.23 Type of Terminal Box for Stator Leads

    :

    4.24 Bearing Type

    a) DE :

    b) NDE :

    5.0 LT SWITCHGEAR

    Bidder to furnish following data foreach type and class of

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 39 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    40/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    switchgear separately.

    5.1 Switchgear & MCC

    5.1.1 General

    5.1.1.1 Manufacturers Name :

    5.1.1.2 Type Designation :

    5.1.1.3 Country of origin :

    5.1.2 Rated Voltage :

    5.1.3 Symmetrical short circuit withstandcurrent at rated voltage ofswitchgear/MCC cubicle

    :

    5.1.4 Peak Short circuit withstand current :

    5.1.5 Rated current at ambient :

    5.1.6 Degree of protection as per IS:13947

    :

    5.1.6.1 Breaker/MCC Cubicles :

    5.1.6.2 Bus bar Chamber :5.1.7 Cubicle sheet metal details

    5.1.7.1 Cold rolled/hot rolled :

    5.1.7.2 Thickness, structural & loadbearing members

    :

    5.1.7.3 Thickness, front & rear :

    5.1.7.4 Thickness, Sides & Top :

    5.1.7.5 Thickness of gland Plates :

    5.1.8 Painting shade & thickness as per IS:5

    5.1.8.1 Extern Surfaces

    a) Front & Rear :

    b) Side End Covers :

    5.1.8.2 Internal Surfaces :

    5.1.9 Minimum Clearance in Air for Bus

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 40 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    41/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    bars

    5.1.9.1 Between Phases :

    5.1.9.2 Between phase & Earth :

    5.1.10 Standard height, Width & Depth of typical panel

    :

    5.1.10.1 Circuit Breaker panel :

    5.1.10.2 MCC Panels (S.F./D.F.0 :

    5.1.10.3 Circuit Breaker panel with Bus

    trucking/Bus Duct Termination

    :

    5.1.10.4 ACDB/DCDB :

    5.1.10.5 AC/DC Fuse boards :

    5.1.11 Width of cable alley :

    5.1.12 Shrouding arrangement in cablealley provided or not

    : Yes/No

    5.1.13 Earth Bus bar size & material :

    5.1.14 Approx. weight of one panel withcircuit breaker

    :

    5.1.15 Recommended dynamic loading for foundation design

    :

    5.1.16 Approx. Weight of one MCC Panel :

    5.2 Power Bus Bars and Insulators

    5.2.1 Material & applicable standards :

    5.2.3 Bare/Painted/EpoxyInsulated/Sleeved

    :

    5.2.4 Continuous Current Rating :Over an Ambient Temperature

    (Amps)

    5.2.5 Temperature rise over designambient temperature forcontinuous current ratingDeg.C

    :

    5.2.6 Material of the support insulators :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 41 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    42/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    5.2.7 One Second Current Rating (KA) :

    5.3 Control Supply Transformers

    5.3.1 Make :

    5.3.2 Type :

    5.3.3 Material & Class of Insulation :

    5.3.4 Voltage Rating & Taps :

    5.3.5 Continuous Rating (VA) :

    5.4 Circuit Breaker

    5.4.1 Manufacturers name and countryof manufacturer

    :

    5.4.2 Manufacturers type anddesignation

    :

    5.4.3 Rated Voltage :

    5.4.4 Rated Operating Duty :

    5.4.5 Design ambient temperature :5.4.6 Rated current at design ambient

    temperature:

    5.4.7 Derating factor for site operatingconditions inside panel

    :

    5.4.8 Continuous current at ambienttemp.

    :

    5.4.9 Rated symmetrical breaking current :

    5.4.10 Rated peak making current :

    5.4.11 Rated short time rating (for 1Second)

    :

    5.4.12 Rated Peak momentary Rating :

    5.4.13 Number of openings, the circuitbreaker is capable of performing without inspection,replacement of contracts orother parts at 100% ratedbreaking current

    :

    5.4.14 No. of Breaker auxiliary contacts :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 42 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    43/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    provided on fixed portion ofbreaker and their rating

    5.4.15 Trip free and anti-pumping featureshave been provided (Furnishdescription)

    : Yes/No

    5.4.16 Power operating mechanism :

    5.4.17 Spring Charging Motor details :

    5.4.17.1 Type :

    5.4.17.2 Rating Watts :

    5.4.17.3 Rated Voltage :

    5.4.17.4 Class of Insulation :

    5.4.17.5 Time for fully charging the closingspring

    :

    5.4.18 Emergency manual Chargingfacility provided

    :

    5.4.19 Limits of voltage for satisfactoryoperation of the followingdevices as percentage ofnormal voltage

    :

    5.4.19.1 Motor :

    5.4.19.2 Closing Coil :

    5.4.19.3 Tripping Coil :

    5.4.20 Manual Operating Mechanism :

    5.4.21.1 Type of Releases provided :

    5.4.21.2 Available range of followingparameters for each type ofrelease offered

    :

    5.4.22.1 Maximum Tripping Time :

    5.4.22.2 Maximum Closing Time :

    5.4.23.1 Closing Coil VA :

    5.4.23.2 Tripping Coil VA :

    5.4.23 Telescopic trolley

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 43 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    44/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    5.4.23.1 Make :

    5.4.23.2 Type Designation :

    5.4.23.3 Dimensions :

    5.5 Air Break Switches

    The following details shall befurnished for each type &Rating

    5.5.1 Make :

    5.5.2 Type :

    5.5.3 Applicable Standards :

    5.5.4 Rated current at design ambienttemperature (Amps)

    :

    5.5.5 Design ambient temperatureDeg. C

    :

    5.5.6 Rated Breaking Current (kA) :5.5.7 Maximum through fault current

    withstand kA:

    5.5.8 Door interlock as specified hasbeen provided?

    : Yes/No

    5.5.9 No. of auxiliary contacts and itsrating

    :

    5.6 Control/Selector Switch

    5.6.1 Make :

    5.6.2 Type Designation :

    5.6.3 Voltage Grade :

    5.7 Contactor

    The following details shall be furnished for each type & rating)

    5.7.1 Make :

    5.7.2 Type & applicable standards :

    5.7.3 Rated voltage of main and auxiliary :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 44 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    45/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    contacts

    5.7.4 Rated Voltage of Coils :

    5.7.5 Limits of Operation :

    5.7.5.1 Supply Voltage Variation +/-% :

    5.7.5.2 Supply frequency variation for closing (+/-)

    :

    5.7.5.3 Drop out voltage % :

    5.7.5.4 Rated (Thermal) current A :

    5.7.5.5 Rated Duty :

    5.7.5.6 Rated utilization category as per IS:13947

    :

    5.7.5.7 Rated breaking capacity kA :

    5.7.5.8 Rated making capacity kA :

    5.7.5.9 Coil VA burden :

    5.8 Auxiliary Contactor

    5.8.1 Make :

    5.8.2 Type :

    5.9 MCCB

    5.9.1 Make :

    5.9.2 Type, rating :

    5.9.3 Category :

    5.10 Current Transformer

    The following details shall be provided for each Type & Rating

    5.10.1 Make :

    5.10.2 Applicable Standards :

    5.10.3 Ratio :

    5.10.4 VA Rating :

    5.10.5 Accuracy Class :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 45 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    46/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    5.10.6 Class & Type of Insulation :

    5.11 Voltage Transformers

    5.11.1 Make :

    5.11.2 Ratio :

    5.11.3 VA Rating :

    5.11.4 Accuracy Class :

    5.11.5 Over Voltage Factor :

    5.11.6 Class & Type of Insulation :

    5.12 Relays

    The following details shall be furnished for each type & applications includingcoupling relay.

    5.12.1 Make :

    5.12.2 Type :5.12.3 Application :

    5.12.4 Catalogue :

    5.13 Thermal Overload Relay & SinglePhasing Preventer

    The following details shall be furnished for each type & rating.

    5.13.1 Make & Type designation :

    5.13.2 Catalogue :

    5.14 Voltmeter

    5.14.1 Make :

    5.14.2 Type :

    5.14.3 Catalogue :

    5.15 Ammeter

    5.15.1 Make :

    5.15.2 Type :

    5.153 Catalogue :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 46 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    47/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    5.16 Push Buttons

    5.16.1 Make :

    5.16.2 Type Designation :

    5.16.3 Catalogue :

    5.17 Indicating Lamps

    5.17.1 Make :

    5.17.2 Type :

    5.17.3 Catalogue :

    5.18 Local Starters

    5.18.1 Make & Type :

    5.18.2 Catalogue :

    5.19 415V BUS BARS with Linkageprovision

    5.19.1 Manufacturers name & Address :

    5.19.2 Type of Bus Bars :

    5.19.3 Material and cross section of busbars

    :

    5.19.4 Rated Voltage (Volts) :

    5.19.5 Maximum voltage at which bus bar can operate continuously(volts)

    :

    5.19.6 Continuous current rating of Busbars (Amps)

    :

    5.19.7 Short circuit current ratings &duration (kA/Sec.)

    :

    5.19.8 Momentary current rating kA pack :

    5.19.9 Temperature rise over the ambienttemperature

    :

    5.19.9.1 Bus bars :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 47 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    48/64

  • 7/31/2019 9 Section 5B - TECH Requirements

    49/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    and size of cables

    6.1 Make & Type :

    6.2 Country of manufacturer :

    6.3 Type & Designation :

    6.4 Applicable Standard :

    6.5 Cable Size & No. of Cores :

    6.6 Rated Voltage :

    6.7 Catalogue attached : Yes/No

    6.8 Continuous current rating for max.conductor temperature

    :

    6.8.1 When laid in air at an ambienttemperature of 50 Deg.C

    :

    6.8.2 When buried in soil having thermalResistivity of 150 Deg.C cm/nat a depth of 1000 mm atground ambient temperature of40 Deg.C

    :

    6.9 Short circuit withstand capacity andduration for

    6.9.1 Conductor :

    6.9.2 Screen :

    6.9.3 Armour :

    6.10 Conductor

    6.10.1 Material :

    6.10.2 Nominal cross section area in sq.mm

    :

    6.10.3 Shape of conductor :

    6.10.4 DC resistance at 20oC :

    6.11 Insulation

    6.11.1 Material :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 49 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    50/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    6.11.2 Nominal Thickness (in mm) :

    6.11.3 Type of Curing (for XLPE) :

    6.12 Metallic screen (wherever applicable)

    :

    6.12.1 Material :

    6.12.2 Type :

    6.12.3 Rating (KA Sec.) :

    6.13 Type of Inner Sheath :

    6.14 Armour Material :

    6.15 Outer Sheath Material :

    6.16 Over all Dia Cable (in mm) :

    6.17 Guarantee Value of Minimumoxygen index of outer sheath

    :

    6.18 Maximum acid gas generation byweight (%) of outer sheath

    :

    6.19 Average light transmission :

    7.0 ILLUMINATION SYSTEM

    7.1 Lighting Distribution Board

    7.1.1 Make :

    7.1.2 Applicable Standard :

    7.1.3 Type of Construction :

    7.1.4 Degree of Protection :

    7.1.5 Catalogue attached : Yes/No

    7.2 Lighting Panel

    7.2.1 Make :

    7.2.2 Applicable Standard :

    7.2.3 Enclosure :

    7.3 Miniature Circuit Breaker

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 50 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    51/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    7.3.1 Make :

    7.3.2 Type designation :

    7.3.3 Applicable Standard :

    7.3.4 Rated Current Voltage :

    7.3.5 Breaking Capacity of 0.6 p.f. :

    7.3.6 Catalogue attached : Yes/No

    7.4 Insulator

    7.4.1 Make :

    7.4.2 Type designation :

    7.5 MCCB

    7.5.1 Make :

    7.5.2 Type, Rating :

    7.6 Contactor

    7.6.1 Make :

    7.6.2 Type & Duty :

    7.7 Synchronous Timer

    7.7.1 Make :

    7.7.2 Type :

    7.7.3 Applicable Standard :

    7.8 Lighting Fixtures & Accessories

    7.8.1 Make of lighting fixture andaccessories

    :

    7.8.2 Catalogue for each type of fixtureattached as annexure no.

    :

    7.8.3 Applicable standard :

    7.9 Switches

    7.9.1 Make :

    7.9.2 Type :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 51 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    52/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    7.9.3 Catalogue attached as annexure

    No.

    :

    7.9.4 Applicable Standard :

    7.10 Receptacles/Sockets

    7.10.1 Make :

    7.10.2 Type :

    7.10.3 Applicable Standard :

    7.11 Junction Boxes

    7.11.1 Make :

    7.11.2 Type :

    7.11.3 Material :7.11.4 Applicable Standard :

    7.12 Terminal Blocks

    7.12.1 Make :

    7.12.2 Type :

    7.12.3 Rating :

    7.13 Rigid Steel Conduits/Fittings &Accessories

    7.13.1 Make :

    7.13.2 Material :

    7.13.3 Applicable Standard :

    7.14 Hume Pipes

    7.14.1 Make :

    7.14.2 Applicable Standard :

    7.15 Flexible Steel Conduit

    7.15.1 Make :

    7.15.2 Applicable Standard :

    7.16 Lighting Wires

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 52 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    53/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    7.16.1 Make :

    7.16.2 Applicable Standard :

    7.16.3 Voltage Grade :

    7.16.4 Size :

    7.16.5 Conductor material :

    7.16.6 Insulation :

    7.17 Lighting Poles

    7.17.1 Make :

    7.17.2 Applicable Standard :

    7.17.3 Type :7.17.4 Pole Height :

    7.18 Lighting Masts

    7.18.1 Make :

    7.18.2 Type :

    7.18.3 Overall Height :

    7.18.4 Applicable Standard :

    7.18.5 Catalogue attached as AnnexureNo.

    :

    8.0 CABLING, EARTHING ANDLIGHTNING PROTECTIONCABLE SUPPORT SYSTEM

    8.1 Cable, Trays, Tray Covers andAccessories

    8.1.1 Make :

    8.1.2 Type of cable Tray :

    8.1.3 Type of Cable support system :

    8.1.4 Applicable Standard :

    8.1.5 Catalogue and indicative sketch

    attached as Annexure no.

    :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 53 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    54/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    8.2 Conduit Pipes & Accessories

    8.2.1 Make :

    8.2.2 Material :

    8.2.3 Catalogue attached as Annexureno.

    :

    8.2.4 Applicable Standard :

    8.3 Junction Boxes

    8.3.1 Make :

    8.3.2 Material :

    8.3.3 Applicable Standard :

    8.4 Cable Glands

    8.4.1 Make :

    8.4.2 Material :

    8.4.3 Applicable Standard :

    8.5 Cable Jointing/ Termination Kits

    8.5.1 Make :

    8.5.2 Type of System

    8.5.2.1 Termination :

    8.5.2.2 Joints :

    8.5.3 Catalogue attached as AnnexureNo.

    :

    8.5.4 Applicable Standard :

    8.6 Cable Lugs & Terminals

    8.6.1 Make :

    8.6.2 Applicable Standard :

    8.7 Earthing System

    8.7.1 Buried Earth Mat

    8.7.1.1 Material & Size :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 54 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    55/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    8.7.1.2 Applicable Standard for the System :

    8.7.2 Equipment Earthing

    8.7.2.1 Material :

    8.7.2.2 Size :

    8.7.2.3 Applicable Standard :

    8.8 Lightning Protection System

    8.8.1 Applicable Standard :

    8.8.2 Size & Material for Air terminationand down conductor

    :

    9.0 ELECTRICAL CONTROL DESK /CONTROL PANELS / PLC

    9.1 Different Control Panels

    9.1.1 Application :

    9.1.2 Overall Dimensions :

    9.2 Control Switch :

    9.2.1 Manufacturer :

    9.2.2 Type and Designation :

    9.2.3 Catalogue attached : Yes/No

    9.3 Annunciators

    9.3.1 Manufacturer :

    9.3.2 Type and Designation :

    9.3.3 Solid State or Electromechanical :

    9.3.4 Catalogue attached : Yes/No

    9.4 Meter & Instruments

    9.4.1 Manufacturer :

    9.4.2 Type & Designation :

    9.4.3 Catalogue attached : Yes/No

    9.5 Energy Meters

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 55 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    56/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    9.5.1 Manufacturer :

    9.5.2 Type & Designation :

    9.5.3 Catalogue attached : Yes/No

    9.6 Indicating Lamps

    9.6.1 Manufacturer :

    9.6.2 Type and Designation :

    9.6.3 Catalogue attached : Yes/No

    9.7 Push Buttons

    9.7.1 Manufacturer :

    9.7.2 Type Designation :

    9.7.3 Catalogue attached : Yes/No

    9.8 Auxiliary Instrument Transformer

    9.8.1 Manufacturer :

    9.8.2 Type & Designation :

    9.8.3 Catalogue attached : Yes/No

    9.9 Panels

    9.9.1 Manufacturer :

    9.9.2 Type & Designation :

    9.9.3 Catalogue attached : Yes/No

    9.10 Control Panel Details

    9.10.1 Make of control panel :

    9.10.2 Manufacturers type & designation :

    9.10.3 Overall dimension of panel (W x Dx H) mm

    :

    9.10.4 Anti-vibration pad provided : Yes/No

    9.10.5 Transportation size of panel :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 56 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    57/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    9.10.6 Total weight of panel :

    9.10.7 Operating device height (Minimum) :

    9.10.8 Operating device height (Maximum) :

    9.10.9 Panel IP Protection :

    .10.10 Make, technical details andcatalogue of air breakswitches, fuses, contactors,annunciators, MCBs, pushbuttons indicating lamps, etc.provided in the panel

    :

    9.11 PLC SYSTEM

    9.11.1 Make of the PLC System :

    9.11.2 Write up of PLC System :

    9.11.3 Details of protection and interlockscheme

    :

    9.11.4 Description of list and diagnosticfeatures of PLC System

    :

    9.11.5 Field interrogation voltage level :

    9.11.5.1 For Input :

    9.11.5.2 For output :

    9.11.6 No. of control/monitoring stationsprovided

    :

    9.11.7 Whether operation through controlpanel is possible

    :

    9.11.8 Hot standby provided : Yes/No

    9.12 FIBRE OPTIC CABLE

    9.12.1 Make :

    9.12.2 Type :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 57 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    58/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    SCHEDULE A

    SCHEDULE OF GENERAL PARTICULARS OF BIDDER

    1.0 GENERAL

    1.1 Name :

    1.2 Postal Address :

    1.3 E-Mail and Fax Numbers :

    1.4 Place of Manufacturer :

    1.5 Service Facilities :

    1.6 Availability of Spare Parts :

    1.7 Name and designation of anauthorized Officer at SuppliersWorks to whom reference shallbe made for expeditious technicalco-ordination

    :

    1.8 Proposal No. and Date :

    1.9 Proposal Validity Period :

    1.10 Completion t ime in months fromthe date of issue of Letter ofIntent/Order

    : ______________

    1.11 Completion period in clause 1.10above guaranteed with specifiedpenalties

    : Yes/No

    1.12 Estimated man-hours or personnel required for erection,testing and commissioning of Dry

    Fly Ash Extraction & DisposalSystem along with all accessories

    : Unloading Installation& Storage

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 58 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    59/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    1.12.1 Erection Engineers :

    1.12.2 Testing & CommissioningEngineers

    :

    1.12.3 Erection Supervisors :

    1.12.4 Testing & CommissioningSupervisors

    :

    1.12.5 Skilled Labour :

    1.12.6 Semi-Skilled Labour :

    1.12.7 Unskilled Labour :

    1.13 Whether the Terms of Paymentlaid down in the GeneralConditions of Contractagreeable?

    : Yes/No

    1.14 Whether Earnest Money of thedesired value and in the formmentioned in Instructions toBidder submitted?

    : Yes/No

    1.15 Current Registration No. withDGS&D, if any

    :

    Name of the Firm : ____________________

    Signature : ____________________

    Name : ____________________

    Designation : ____________________

    Date : ____________________

    Seal of the Company

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 59 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    60/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    SCHEDULE B

    GUARANTEED PERFORMANCE

    1.0 Water Pumps

    1.1 LP Ash Water Booster Pumps

    1.1.1 Rated Capacity (M3/Hr) :

    1.1.2 Total Dynamic Head (MWC) :

    1.1.3 BHP at rated flow and head(KW)

    :

    1.1.4 Pump efficiency (percent) :

    1.1.5 Motor rating at 50o C (KW) :

    1.2 Cooling Water Pumps

    1.2.1 Rated Capacity (M3/Hr) :

    1.2.2 Total Dynamic Head (MWC) :

    1.2.3 BHP at rated flow and head(KW)

    :

    1.2.4 Pump efficiency (percent) :

    1.2.5 Motor rating at 50o C (KW) :

    1.3 Seal Water Pumps

    1.3.1 Rated Capacity (M3/Hr) :

    1.3.2 Total Dynamic Head (MWC) :

    1.3.3 BHP at rated flow and head(KW)

    :

    1.3.4 Pump efficiency (percent) :

    1.3.5 Motor rating at 50o C (KW) :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 60 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    61/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    2.0 Mechanical Exhauster

    2.1 Rated Capacity (M3/Hr) :

    2.2 Vacuum (mm of Hg.) :

    2.3 BHP at rated flow and Vacuum(KW)

    :

    2.4 Pump efficiency (percent) :

    2.5 Motor rating at 50o C (KW) :

    3.0 Fluidizing Air Blower

    3.1 Rated Capacity (M3/Hr) :

    3.2 Discharge Pressure (Kg./ sq. cm.g)

    :

    3.3 BHP at rated flow and head(KW)

    :

    3.4 Blower efficiency (percent) :

    3.5 Motor rating at 50o C (KW) :

    4.0 Transport Air Compressor/ AirBlower

    4.1 Rated Capacity (M3/Hr) :

    4.2 Discharge Pressure (Kg./ sq. cm.g)

    :

    4.3 BHP at rated Capacity & Head(KW)

    :

    4.4 Compressor efficiency (percent) :

    4.5 Motor rating at 50o C (KW) :

    5.0 Instrument Air Compressorincluding Dryer

    5.1 Rated Capacity (M3/Hr) :

    5.2 Discharge Pressure (Kg./ sq. cm.g)

    :

    5.3 BHP at rated Capacity & :

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 61 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    62/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    Pressure (KW)

    5.4 Compressor efficiency (percent) :

    5.5 Motor rating at 50o C (KW) :

    5.6 Air Dryer Plant for above, KW :6.0 Vent Fan

    6.1 Rated Capacity (M3/Hr) :

    6.2 Discharge Pressure (mm WC) :

    6.3 BHP at rated Capacity &

    Pressure (KW)

    :

    6.4 Fan efficiency (percent) :

    6.5 Motor rating at 50o C (KW) :

    7.0 Air Heaters

    8.0 Fluidizing Air Blower (KW)

    8.1 Rated Capacity (M3/Hr) :

    8.2 Discharge Pressure (Kg./ sq. cm.g)

    :

    8.3 BHP at rated Capacity &Pressure (KW)

    :

    8.4 Blower efficiency (percent) :

    8.5 Motor rating at 50o C (KW) :

    9.0 Any Other Requirement (KW))Bidder to add other sheets ifrequired.

    10.0 Optional Items

    Name of Firm: _________________________

    Signature : _________________________Name : _________________________ Designation : _________________________Date : _________________________

    Seal of Company

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 62 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    63/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    SCHEDULE D

    SCHEDULE OF DEVIATIONS

    All commercial and technical deviations from the specification shall be set out by the Bidder clauseto clause in this schedule, other the bid shall be deemed to conform to the PurchasersSpecifications.

    S. No. Clause No. Deviations Justification

    A. Commercial

    B. Technical

    Name of Firm: _________________________

    Signature : _________________________

    Name : _________________________

    Designation : _________________________

    Date : _________________________

    Seal of Company

    RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012

    Page 63 of 64

  • 7/31/2019 9 Section 5B - TECH Requirements

    64/64

    VOLUME - II

    SECTION - 5 B - TECHNICAL REQUIREMENTS

    SCHEDULE E

    SCHEDULE OF DRAWINGS ENCLOSED WITH THE BID

    S.No. Drawing No. Title

    Name of Firm: _________________________

    Signature : _________________________

    Name : _________________________

    Designation : _________________________

    Date : _________________________

    Seal of Company