Upload
aashuranjan
View
220
Download
0
Embed Size (px)
Citation preview
7/31/2019 9 Section 5B - TECH Requirements
1/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
TECHNICAL REQUIREMENTS
IA. DRY FLY ASH HANDLING EQUIPMENT MECHANICAL
1.0 FLY ASH HOPPER ISOLATIONVALVES
1.1 Manufacturer : Self manufactured
1.2 Numbers provided & location : As Pre flow Scheme
1.3 Type of Valve & Its operation : Isolation Valve and ChainOperated
1.4 Size : To Suit System Requirement
1.5 Material of Construction andHardness of Components
1.5.1 Body : As per Spec. & EEPL Standard
1.5.2 Gate/Plate/Disc (Indicate thicknessalso)
: As per Spec. & EEPL Standard
1.5.3 Seat : As per Spec. & EEPL Standard
1.5.4 Operating Gear : As per Spec. & EEPL Standard
1.5.5 Chain : As per Spec. & EEPL Standard
1.6 Drawing of the isolation Valveenclosed
: DDE
2.0 ADAPTOR PIECE
2.1 No. of Adaptor Pieces provided : As per Flow Scheme
2.2 Material and Thickness of Adaptor Pieces
: MS & 10mm Thick
2.3 Weight of Adaptor Piece : DDE
3.0 FLY ASH EXTRACTION VALVE
3.1 Manufacturer : Self Manufactured
3.2 Type of Valve :
3.3 Location & No. of Valves : As per Flow Scheme
3.4 Size : 200 NB
3.5 Fly Ash Extraction Rate (Tonnes/Hr) : 45 T/hr
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 1 of 64
7/31/2019 9 Section 5B - TECH Requirements
2/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
3.06 Material of Construction andHardness of Components:
:
3.6.1 Body : As per Spec. & EEPL Standard
3.6.2 Plate/Disc/Gate/Dome/Cone(Indicate thickness also)
: As per Spec. & EEPL Standard
3.6.3 Seat (Specify Details in case of Inflatable Seat offered)
: As per Spec. & EEPL Standard
3.07 Type of Operating Device : As per Spec. & EEPL Standard
3.8 Other specific Features of Valves, if
any
:
3.9 Access Platforms with necessaryStaircase provided below ESPHoppers for the Operation &Maintenance of Fly Ash ExtractionValves and other equipment/instruments, etc.?
: Yes
4.0 EXPANSION JOINTS : As applicable
4.1 Manufacturer : Self Manufactured
4.2 Type : Bellow Type
4.3 Standard to which the ExpansionJoints conform
: As per Spec. & EEPL Standard
4.4 Material of Construction :
4.4.1 Bellow/Convolutes : SS
4.4.2 Inner Liner :
4.5 Expansion
4.5.1 In Axial Direction : To Suit System Requirement
4.5.2 In Lateral Direction : To Suit System Requirement
4.6 Angular Deflection : To Suit System Requirement
4.7 Type of End Connection : To Suit System Requirement
4.8 Location & Number of ExpansionJoints provided
: As per flow scheme
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 2 of 64
7/31/2019 9 Section 5B - TECH Requirements
3/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
5.0 FLY ASH BRANCH ISOLATIONVALVES (FOR VACUUM &
PRESSURE SYSTEMS)
:
5.1 Manufacturer : Self Manufactured
5.2 No. of Valves & Location : As per flow scheme
5.3 Type of Valves : Pneumatic Operated Isolationvalves
5.4 Size : 200 NB
5.5 Material of Construction andHardness of Components
:
5.5.1 Body : As per Spec. & EEPL Standard
5.5.2 Gate/Disc/Plate/Dome (IndicateThickness also)
: As per Spec. & EEPL Standard
5.5.3 Seat (specify details in caseinflatable seat offered)
: As per Spec. & EEPL Standard
5.6 Type of Operating Device :
5.7 Other specific features of the Valve,if any
:
6.0 PNEUMATIC ASH TRANSPORTPIPE LINES & FITTINGS
:
6.1 Piping : Vacuum PressureConveying from ConveyingESP Hoppers from Surgeto Surge Tank/ Tank toWetting Head Storage
Silo6.1.1 Manufacturer : Approved Vendor
6.1.2 Material and Hardness : CI Class D MS ERW
6.1.3 Standard : IS 1536/ IS1239/3589BS 1211
6.1.4 Size (OD x Thk.) : 200 NB 200 NB
6.1.5 Velocity of Air Ash Mixture (M/Sec.) : DDE
6.1.6 Pick Up Velocity : DDE
6.1.7 Exit Velocity : DDE
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 3 of 64
7/31/2019 9 Section 5B - TECH Requirements
4/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
6.1.8 Friction Coefficient : DDE
6.1.9 Air Pressure Drop (Kg/Cm2(g) : DDE
6.1.10 Ash Air Mixture Pressure Drop(Kg/Cm2(g)
: DDE
6.1.11 Maximum Length of Pipingconsidered for Pressure drop (M)
:
6.1.12 No. of Length of Pipes :
6.1.13 Quantity of each Pipe Length (M) :
6.1.14 Total Pipe Quantity (M) :
6.1.15 Type of Joints :
6.1.16 Pipe to Pipe :
6.1.17 Pipe to Fitting/Valve :
6.1.18 Fitting to Fitting/Valve :
6.2 Fittings (Elbows, Bends Etc.) AndSpool Piece
:
6.2.1 Manufacturer : Self Manufactured
6.2.2 Type of Fittings & Spool Piece : ACI Fittings
6.2.3 Estimated No. of various Fittings &Spool Pieces
: DDE
6.2.4 Radius of Fittings : 5D
6.2.5 Length of Straight Spool Piece : DDE
6.2.6 Material of Construction, Thickness
and Hardness of Fittings, SpoolPiece and Lining, if applicable
: As per Specification
7.0 SURGE TANK
7.1 Manufacturer : Self Manufactured
7.2 Total No. of Surge Tanks Provided : One(1) Nos
7.3 Holding Capacity of each SurgeTank (Tonnes)
To Suit
7.3.1 Effective Holding Capacity : DDE
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 4 of 64
7/31/2019 9 Section 5B - TECH Requirements
5/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
7.3.2 Total Capacity : DDE
7.4 Type of Surge Tank :
7.5 Pressure/Vacuum Relief Systemprovided for:-
- Surge Tank- Existing Silo
::
YesYes
7.6 Type of Venting arrangement for contaminated air from Surge Tank
:
7.7 Whether bag/ vent filters & fans as
specified have been provided on :-
- Surge Tank- Existing Silo
:
YesYes
7.8 Material of Construction andThickness
7.8.1 Body : MS as per IS 2062
7.8.2 Liners (indicate hardness also) :
7.9 All accessories, supporting StructureSteel, platforms, Staircases, etc.,included as per Specificationsrequirement?
: Yes
7.10 No. of Outlet connection provided :
8.0 FLUIDISING SYSTEM ESP Hoppers/ StorageSurge Tank Silo
(Existing)
8.1 Manufacturer : Self Manufactured
8. Type of Aeration System (whether Aeration Pads or Air Slides)
: Aeration Pad Aeration Slide
8.3 No. of Air Slides Provided:
DDE
8.4 No. of Fluidising Pads provided : 2 Nos./ESP Hopper
8.5 Quantity of Fluidising air required for each Surge Tank silo (NM3/Min)
: DDE
8.6 Pressure of fluidizing air required,Kg/cm2(g)
: As per Load List
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 5 of 64
7/31/2019 9 Section 5B - TECH Requirements
6/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
8.7 Temperature of Fluidising Air oC : DDE
8.8 Material of construction of FluidisingPads
: DDE
8.9 Material of Construction of Air Slides : As per Spec. & EEPl Standard
8.10 Slope provided : DDE
8.11 Air quantity required NM3/Min. : DDE
8.12 No. of Blowers/Fan provided : As per Flow Scheme
8.13 Material of porous media : DDE
8.14 Source of Fluidising Air to besupplied to Surge Tank/Silo
: DDE
9.0 ASH TRANSFER VESSELS (forPneumatic Ash Extraction &Transportation System)
9.1 No. of Ash Transfer Vesselemployed per Unit
: As per Flow Scheme
9.2 Sequence of operation of AshTransfer Vessel
: DDE
9.3 Size of Ash Transfer Vessel inlet andoutlet (mm)
: DDE
9.4 Capacity of each Ash Transfer Vessel (CuM.)
: DDE
9.5 No. of As Feed Valves provided atthe inlet of each Ash Transfer Vessel
:
9.6 Type of discharge system (whether
bottom discharge or top discharge)
:
9.7 No. of Isolation Valves (if any)provided at the outlet of each AshTransfer Vessel
:
9.8 Type of Ash Feed/Outlet Valves(indicate method of OperatingDevice of Valve)
:
9.9 Ash Extraction Rate per AshTransfer Vessel
:
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 6 of 64
7/31/2019 9 Section 5B - TECH Requirements
7/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
9.10 Fly Ash/Air ratio by weight at AshTransfer Vessel outlet
:
9.11 Design velocity of ash air mixture atAsh Transfer Vessel outlet
:
9.12 Ash Transfer Vessel material of Construction
:
9.13 Ash Transfer Vessel Design Code :
9.14 Ash Transfer Vessel DesignPressure
:
9.15 Ash Transfer Vessel over Pressuresafety equipment
:
9.16 No. of Conveying Lines from AshTransfer Vessel
:
9.17 Compressed Air Pressure andQuantity requirement at each AshTransfer Vessel
:
10.0 BAG FILTERS/VENT FILTERS On Surge Tank On ExistingSilo
10.1 Make : Self Manufactured
10.2 Type and Size : Reverse Pulse Jet
10.3 Material of Filtering Media : Ash
10.4 Maximum/Continuous PermissibleTemperature for Filtering Media :
10.5 Air Dust Flow rate for which bagfilters have been sized (M3/Hr)
: DDE
10.6 Guaranteed Outlet Dust Emission(mg/Nm3)
: DDE
10.7 Material of Construction of Body &Thickness
: DDE
10.8 Type of Bag Filter cleaningarrangement offered?
:
11.0 AIR INTAKE VALVE
11.1 Manufacturer : Self Manufactured
11.2 Location and No. of Valve : As per Flow Scheme
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 7 of 64
7/31/2019 9 Section 5B - TECH Requirements
8/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
11.3 Type of Valves : As per Spec. and EEPL standard
11.4 Size :
11.5 Material of Construction andHardness of Components
:
11.5.1 Body : As per Spec & EEPL Std.
11.5.2 Seat : As per Spec & EEPL Std.
11.5.3 Spring : As per Spec & EEPL Std.
11.5.4 Disc : As per Spec & EEPL Std.
11.6 Type of Operating device :
12.0 VACUUM BREAKER
12.1 Manufacturer : Self Manufactured
12.2 Type of Valve :
12.3 Quantity : As per Flow Scheme
12.4 Size : To Suit
12.5 Location :
12.6 Material of Construction andHardness of Components
:
12.6.1 Body : As per Spec & EEPL Std.
12.6.2 Gate/Plate/Disc (indicate thicknessalso)
: As per Spec & EEPL Std.
12.7 Type of Operating device : Pneumatic Operation
12.8 Other specific features of the Valve :
13.0 MECHANICAL EXHASTERS/VACUUM PUMPS
13.1 Manufacturer : Approved Vendor
13.2 Type & Model No. : Liquid Ring Type
13.3 Design Standard : As per Spec & OEM Std
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 8 of 64
7/31/2019 9 Section 5B - TECH Requirements
9/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
13.4 Guaranteed Vacuum Pumpscapacity (CFM) at Pump Inlet
conditions of 60oF Gas Temp. 60oFSeal water temp. & 50% RH
: Refer Load List
13.5 Volumetric efficiency % : DDE
13.6 Isothermal efficiency % : DDE
13.7 Mechanical efficiency % : DDE
13.8 Vacuum Pumps working pressure(inch of mercury column vacuum)
: Refer Load list
13.9 No. of Vacuum Pumps working andstandby for the unit
: As per Flow Scheme
13.10 Type of Transmission between pump& motor
: Belt Driven
13.11 Maximum Pump input power in theentire operating Range (KW)
: Refer Load List
13.12 Transmission Efficiency : DDE
13.13 Max. Permissible inlet gas temp. atsuction of vacuum pump (oC)
: As per Spec
13.14 Material of Construction andHardness of various components
:
13.14.1 Body : As per Specification
13.14.2 Rotor : As per Specification
13.14.3 Shaft : As per Specification
13.14.4 Shaft Sleeve : As per Specification
13.14.5 Port Plates/Cone : As per Specification
13.15 Quantity (m3/Hr) and quality of working/seal water required
: DDE
13.16 Condensing factor at seal water temperature
: DDE
13.16.1 At 15oC : DDE
13.16.2 At 36oC : DDE
13.17 Motor rating at 50oC Ambient (KW) Refer Load List
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 9 of 64
7/31/2019 9 Section 5B - TECH Requirements
10/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
14.0 AIR COMPRESSORS/ BLOWERSFOR DRY FLY ASH
TRANSPORTATION (To be filledseparately for each type and size)
14.1 Type and make : Oil Free Reciprocating Type
14.2 Operating/rated speed of compressor/blower shaft
: As per OEM Standard
14.3 Discharge Pressure (Kg/cm2(g) : Refer Load List
14.4 Discharge Capacity (Nm3/Min) : Refer Load List
14.5 Design Standard :
14.6 No. offered (indicate Nos. workingand Nos. standby)
:
14.7 Design Conditions:
14.7.1 Ambient Temper (oC) : 50 Deg C
14.7.2 Ambient Pressure (Kg/cm2) :
14.7.3 Ambient Relative Humidity (%) : 100 %
14.7.4 Mean Sea Level (m) :
14.8 FAD at design conditions(Cu. M/hr)
:
14.9 Maximum shaft input power over operating range (KW)
: Refer Load List
14.10 Motor Rating at 50oC Ambient (KW)and motor speed
:
14.11 Type of Transmission between
motor and compressor/blower
: Direct drive
14.12 Inlet air Filter details:
14.12.1 Inlet Filter Area (Sq. m) : DDE
14.12.2 Filter efficiency (% Microns) : DDE
14.13 Air Drying Plant (forCompressors)
14.13.1 Manufacturer : Approved Vendor
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 10 of 64
7/31/2019 9 Section 5B - TECH Requirements
11/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
14.13.2 Model No. : DDE
14.13.3 Type of Air drying plant provided : Refrigerated Type
14.13.4 Numbers offered :
14.13.5 Design, air flow (Nm3/Min) andTemp. (oC) at Plant Inlet
:
14.13.6 Air Pressure drop in air drying plantKg/cm2(g)
: DDE
14.13.7 Dew Point of air after Air DryingPlant (oC)
: DDE
14.13.8 Refrigeration tonnage (TR) of air drying plant, corresponding tocooling water temp. of 38oC
: DDE
14.13.9 Motor rating of air drying plant at50oC (KW)
: DDE
14.14 Compressed Air Heatingarrangement details (applicable forBlowers only)
:
14.14.1 Air temperature at inlet to air heater (oC)
:
14.14.2 Air temperature at heater outlet (oC) :
14.14.3 Type of air heating/rating of air heater (KW)
:
14.14.4 Dew Point of compressed air (oC) :
14.15 Offered compressor/blower is oil-freedesign or oil injector design with oilseparator?
:
14.16 Material of construction of variouscomponents
:
14.16.1 Body :
14.16.2 Rotor/Screw :
14.16.3 Shaft :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 11 of 64
7/31/2019 9 Section 5B - TECH Requirements
12/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
14.17 Oil Carry over in compressed air atthe down stream of oil filter in case
of oil injected compressor/blowerwith oil separator (ppm)
:
14.18 Air receiver details
14.18.1 No. and Location :
14.18.2 Design standard :
14.18.3 Size (Length x Dia mm) :
14.18.4 Material of construction :
14.18.4.1 Shell :
14.18.4.2 Dished Ends :
14.18.4.3 Design Pressure :
14.19 Cooler (if provided) :
14.19.1 Water cooled or air cooled :
14.19.2 If water cooled, State water pressurein Kg/cm2 and quantity in Cu. M./hr
:
14.20 Bearing details
14.20.1 Make & Type :
14.20.2 Bearing No. & Qty. :
14.20.3 Lubricant used :
15.0 INSTRUMENT AIR COMPRESSORAND DRYING PLANT
15.1 Instrument Air Compressor
15.1.1 Manufacturer : Approved Vendor
15.1.2 Model Number : DDE
15.1.3 Type of Compressor : As Per Spec.
15.1.4 Qty. offered (indicate nos. workingand no. standby)
:
15.1.5 FAD of each compressor at design
ambient (Cu. M/hr)
:
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 12 of 64
7/31/2019 9 Section 5B - TECH Requirements
13/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
15.1.6 Discharge Pressure (kg/cm2(g) :
15.1.7 Discharge capacity (Nm3/Min) :
15.1.8 Design condition:
15.1.8.1 Design Ambient Temp. (oC) :
15.1.8.2 Design Ambient Pressure (Kg/cm2) :
15.1.8.3 Design Ambient Relative Humidity(%)
:
15.1.8.4 Mean Seal Level (m)
15.1.9 Design Standard :
15.1.10 Air Temperature after first stage of Compressor
:
15.1.11 Air temperature after last stagecompression
:
15.1.12 Outlet air temperature (after cooler)oC
:
15.1.13 Maximum Shaft input power requiredin the entire operating rage (KW)
:
15.1.14 Type of Transmission betweenMotor and Compressor
:
15.1.15 Motor rating at 50oC Ambient :
15.1.16 Crank shaft speed (rpm) :
15.1.17 No. of Stages :
15.1.18 Single acting or double acting :
15.1.19 Cylinder/compression chamber borein mm
:
15.1.20 Stroke/Length mm :
15.1.21 Clearance in % in volume :
15.1.22 Method of cylinder/compressionchamber lubrication
:
15.1.23 Cooling by air or water :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 13 of 64
7/31/2019 9 Section 5B - TECH Requirements
14/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
15.1.24 If water cooled, state pressure inKg/cm2, and m3/hr
:
15.1.25 Type of valves (Suction andDischarge)
:
15.1.26 Inter Cooler (if provided) :
15.1.26.1 Water cooler or air cooled :
15.1.26.2 If water cooled state pressure inkg/cm2 and quantity m3/hr
:
15.1.27 Bearing Details
15.1.27.1 Type & Make :
15.1.27.2 Bearing No. and quantity :
15.1.27.3 Lubricant used :
15.1.28 Intake air filter
15.1.28.1 Inlet Filter area (m2) :
15.1.28.2 Filter efficiency (% microns) :
15.2 Air Receiver Details
15.2.1 Design standard :
15.2.2 Nos. offered and Location :
15.2.3 Size (Length x Dia mm) and capacity(CuM.)
:
15.2.4 Material of Construction :
15.2.4.1 Shell :
15.2.4.2 Dished Ends :
15.2.5 Design Pressure :
15.3 Air Drying Plant :
15.3.1 Manufacturer :
15.3.2 Model No. :
15.3.3 Type of Air Drying Plant :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 14 of 64
7/31/2019 9 Section 5B - TECH Requirements
15/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
15.3.4 Nos. offered :
15.3.5 Design Air Flow at Plant Inlet(NM3/Min)
:
15.3.6 Air temperature at inlet of air dryingplant (oC)
:
15.3.7 Dew Point of air after Air DryingPlant (oC)
:
16.0 WATER AND AIR PIPING VALVES & FITTINGS
16.1 Water And Air Piping
Give details of water piping for ash water system, seal water system,compressed air piping, and any other piping (in the same serial order in theform below) (Use extra sheets if necessary
Service&Location
DesignPressure
Kg/cm2(g)
Materialand
Standardof
Manufacturer
Lengthconsidered
TypeofPipeJoint
Remarks
16.1.1
16.1.2
16.1.3
16.1.4
16.1.5
16.1.6
16.2 Water And Air Line Valves
Give details of Valves for Ash Water System, Seal Water System compressedair piping, any other piping (in the same order in the form below) (Use extrasheets if necessary
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 15 of 64
7/31/2019 9 Section 5B - TECH Requirements
16/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
ServiceandLo
cation
Type(Gate,G
lobe,
Plug,etc
.)
MaterialofConstr
uction
(IS,BSorequiva
lent)
Make
DesignPressure
(Kg/cm2(g)
EndDetails(scr
ewed,
flangedetc.)
Remarks
16.2.1
16.2.2
16.2.3
16.2.4
16.2.5
16.2.6
16.3 Furnish all necessary piping includingvalves, fittings, strainers, flanges,indicators, hangers supports, auxiliarysteel etc. as required
: Yes/No
17.0 WATER CONSUMPTION DATA
17.1 Seal Water/Raw Water required for Quantity PressureM3/Hr Kg/cm2
17.1.1 TAC/ TAB Cooling :
17.1.2 IA Comp. Cooling :
17.1.3 Vacuum Pump Sealing :
17.1.4 Others (specify & indicate) :
18.0 AIR REQUIREMENT DATA
18.1 Approx. free air requirement (Nm3/Min) :
18.1.1 Valve Operation :
18.1.2 Storage and Surge Tank FluidisingSystem
:
18.1.3 Bag /Vent filters
18.1.4 Other requirements as per equipment /
System Design
:
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 16 of 64
7/31/2019 9 Section 5B - TECH Requirements
17/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
18.2 Technical details of Air Pressurereducing stations, air heaters and filters
submitted?
: Yes/No
19.0 PUMPS
19.1 WATER PUMPS LP Ash Water Booster Pump
Cooling WaterPump
SealingWaterPump
19.1.1 Manufacturer
19.1.2 Model and Type
19.1.3 Qty. furnished(Working + Standby)
19.1.4 Rated Capacity, M3/hr
19.1.5 Total Dynamic Head atspecified ratedcapacity, MWC
19.1.6 Shut-off head, MWC
19.1.7 Pump efficiency at ratedcapacity point
19.1.8 Pump input power atspecified ratedcapacity, KW
19.1.9 Power required at Pumpshut-off, KW
19.1.10 Rated output of the drivemotor, KW
19.1.11 Design temperature of
water, oC
19.1.12 Pump Speed, rpm
19.1.12.1 Operating
19.1.12.2 Maximum
19.1.12.3 Specific speed (indicatealso the formulaand units used)
19.1.13.1 Flange Size, Suction(mm)
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 17 of 64
7/31/2019 9 Section 5B - TECH Requirements
18/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
19.1.13.2 Flange Size, Discharge
(mm)
19.1.14 No. of Stages
19.1.15 Impeller Size and Type
19.1.16 No. of Vanes
19.1.17 Material of Construction(mention IS orequivalent)
19.1.17.1 Casing (specify BHN)
19.1.17.2 Impeller (specify BHN)
19.1.17.3 Impeller Wear Ring(specify BHN)
19.1.17.4 Casing Wear Ring(specify BHN)
19.1.17.5 Shaft Sleeve (specifyBHN)
19.1.17.6 Shaft
19.1.17.7 Stuffing Box
19.1.17.8 Bolts, Nuts, Fasteners
19.1.17.9 Base Plate
19.1.17.10 Pump Shaft Bearing
19.1.17.10.1 Quantity
19.1.17.10.2 Type of Lubrication
19.1.17.10.3 Arrangement of Cooling
19.1.17.11 Pump Thrust Bearing
19.1.17.11.1 Location
19.1.17.11.2 Type
19.1.17.11.3 Lubrication
19.1.18 Design of Pumpconforms to
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 18 of 64
7/31/2019 9 Section 5B - TECH Requirements
19/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
Code/Standard No.
19.1.19 Characteristic curves for the pumps andother data asrequired by thespcn. enclosed withthe Proposal
Yes/No Yes/No Yes/No
19.1.20 Coupling between Motor Shaft and PumpShaft
19.1.21.1 Manufacturer
19.1.21.2 Type
19.1.21.3 Coupling Guardfurnished
19.1.21.4 Furnished air releasevalves, drain plugs,etc.
19.1.22 Total Weight of PumpMotor Assembly(Kg)
19.1.23 Various shop testconform to therequirement of thespecification
Yes/No Yes/No Yes/No
19.1.24 Performance testing of pumps possible inManufacturersshop
Yes/No Yes/No Yes/No
19.1.25 If the above answer in
No, explain clearlywhether testing atcondition other thanrated condition canbe undertaken bymanufacturer andcode followed
20.0 MANUALLY OPERATEDPENDANTCONTROLLED EOTCRANE
Transport Air Compressor/Blower/ Vacuum Pump/ WaterPump House (Existing RCWBuilding)
20.1 Name of the Manufacturer
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 19 of 64
7/31/2019 9 Section 5B - TECH Requirements
20/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
20.2 No. of Cranes
20.3 Max. Weight to be handledduring erection andmaintenance
20.4 Performance Data
20.4.1 Class of crane & IS Code
20.4.2 Hoist Capacity, Tonnes
20.4.3 Maximum Lift of Hoist, Metre
20.4.4 Bridge Travel, Metre (Existing)
20.4.5 Trolley Travel, Metre (Existing)
20.4.6 Span, Metre (Existing)
20.4.7 Hoisting speed
20.4.8 Cross Travel Speed
20.4.9 Type of Control
20.4.10 Creep Speed
20.5 Crane Design Data
20.5.1 Crane Bridge
20.5.1.1 Girder Particulars
20.5.1.2 Type of Grinder Construction
20.5.1.3 Material
20.5.1.4 Numbers Provided
20.5.2 Runway Rails
20.5.2.1 Type or Size
20.5.2.2 Length
20.5.2.3 Material
20.5.3 Bridge travel Buffers
20.5.3.1 Numbers
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 20 of 64
7/31/2019 9 Section 5B - TECH Requirements
21/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
20.5.3.2 Type of Stops to engageBuffers
20.5.4 Rail Clamp
20.5.4.1 Type
20.5.4.2 Material
20.5.5 Manual Traversing Device
20.5.5.1 Type of Operation
20.5.5.2 Length of Operating Chain
provided
20.5.5.3 Material of Chain
20.5.5.4 Material of driving Gear
20.6 Trolley Assembly
20.6.1 Trolley Frame particulars
20.6.1.1 Type of Construction
20.6.1.2 Material
20.6.2 Trolley Drive Motor
20.6.2.1 Manufacturer
20.6.2.2 Type
20.6.2.3 Voltage, Phase, Frequency
20.6.2.4 KW Rating
20.6.2.5 Rated Speed, RPM
20.6.3 Hoisting Mechanism
20.6.3.1 Winding Drum
20.6.3.1.1 Type and Size
20.6.3.1.2 Material
20.6.3.1.3 Ratio of winding drum diameter to diameter of wire rope
20.6.3.2 Hoist Drive Motor
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 21 of 64
7/31/2019 9 Section 5B - TECH Requirements
22/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
20.6.3.2.1 Manufacturer
20.6.3.2.2 Type
20.6.3.2.3 KW Rating at 50oC
20.6.3.2.4 Voltage, Phase, Frequency
20.6.3.2.5 Rated Speed, rpm
20.6.3.3 Service Brake
20.6.3.3.1 Type
20.6.3.3.2 Type of Control
20.6.3.3.3 Location
20.6.3.3.4 Breaking Capacity, % of fullload Torque
20.6.3.3.5 Braking Time
20.6.3.3.6 Brake Drum material to IS
20.6.3.3.7 Brake Shoe Material
20.7 Electrical
20.7.1 Limit Switches (furnish detailsfor all)
20.7.1.1 Manufacturer
20.7.1.2 Type
20.7.1.3 Material of Contact
20.7.2 Controllers for Motors (furnish
details of all motors)
20.7.2.1 Type
20.7.2.2 Manufacturer
20.7.3 Main/Runway Conductors
20.7.3.1 Type
20.7.3.2 Manufacturer
20.7.3.3 Size
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 22 of 64
7/31/2019 9 Section 5B - TECH Requirements
23/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
20.7.3.4 Material
20.7.3.5 Length provided
20.7.4 Flexible Cables
20.7.4.1 Manufacturer
20.7.4.2 No. of Cores/Size
20.7.4.3 Material
20.7.4.4 Length provided
20.7.5 Switch Board and WiringDetails
20.7.6 Pendant details as per specification requirements
20.7.7 Safety arrangement
21.0 PAINTS (List out for allequipment/structure)
:
21.1 Type of Primer and Number of Coats :
21.2 Make of Primer :
21.3 Type of final Paints and No. of Coats :
21.4 Make of Final Paints :
21.5 Dry Film thickness of System :
22.0 MEASURING INSTRUMENTS (Primary & Secondary)
22.1 Performance data detailed technicalliterature/design specification
sheet and technical datacovering the guaranteedperformance of each of theproposed equipment for thedesign and operating conditionsspecified at
:
22.2 Experience(Refer lists to satisfy the employerregarding compliance with qualifyingrequirements for samemake/model/product range as those
proposed y the bidder for this project
:
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 23 of 64
7/31/2019 9 Section 5B - TECH Requirements
24/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
22.3 Bill of Material
Complete Bill of Material for allmeasuring instruments coveredunder this section, coveringmake, model No., range,technical features, accessoriesfurnished, quantity offered andall other relevant data for eachitem
:
22.4 Electronic Transmitters :
22.4.1 Make & Model No. :
22.4.2 Output Signal (Analog) :
22.4.3 Whether provision of digitalcommunication on hart protocol
: Yes/No
22.4.4.1 Accuracy :
22.4.4.2 Stability :
22.4.5 Electrical connection through plug &sockets
: Yes/No
22.4.6 Response time (time betweenchange in process variable &signal available at transmitteroutput terminal) for 4-20ma/superimposed hart signal
:
22.4.6.1 For 4-20 ma analog :
22.4.6.2 For superimposed hart signal :
22.4.7 Technical literature furnished at :
22.5 Temperature Sensing Elements/Wells
:
22.5.1 Temperature Elements : Thermo ThermoCouple CoupleK Type R Type
22.5.1.1 Make & Model No. :
22.5.1.2 Dual Elements grounded/ under grounded
:
22.5.1.3 Response Time :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 24 of 64
7/31/2019 9 Section 5B - TECH Requirements
25/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
22.5.1.4 Protective Sheath with MgOinsulation provided as per
specification
:
22.5.1.5 Limits of Error/Accuracy :
22.5.1.6 Time constant (indicate for variousapplications)
:
22.5.1.7 Applicable Standard :
22.5.2 Thermowells :
22.5.2.1 Make & Model No. :
22.5.2.2 Construction Material offered for following services:
22.5.2.2.1 Furnace :
22.5.2.2.2 Flue Gas Services :
22.5.2.2.3 Mill Classifier Outlet :
22.5.2.2.4 Others :
22.5.2.3 Applicable Design Standard :
22.6 Flow Gauges/Indicators : Rotameter Flow Gauge
22.6.1 Make & Model No. :
22.6.2 Body/Material :
22.6.3 Accuracy :
22.6.4 Accessories :
22.7 Process Actuated Switches : Press/DP Temp. Level
Switch Switch Switch
22.7.1 Make & Model No. (Application wise) :
22.7.2 Sensing Element :
22.7.3 Material :
22.7.4 Repeatability :
22.7.5 Contact Rating & No. of Contacts :
22.7.6 Accessories :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 25 of 64
7/31/2019 9 Section 5B - TECH Requirements
26/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
22.8 Indicator/Recorders : Digital / IntegralIndicator / Recorder
22.8.1 Make & Model No. :
22.8.2 Type :
22.8.3 Input Signal :
22.8.4 Accuracy :
22.8.5 Size :
22.8.6 Response Time :
22.8.7 Mosaic Compatible : Yes/No Yes/No
22.9 Electrical Meters :
22.9.1 Motor Current Ammeters :
22.9.1.1 Manufacturers Name :
22.9.1.2 Model No. :
22.9.1.3 Overall Dimensions : W . mm x H .mm x D mm
22.9.1.4 Accuracy : . % of full scale
22.9.1.5 Technical literature furnished at :
22.9.2 Voltmeters
22.9.2.1 Manufacturers Name :
22.9.2.2 Model No. :
22.9.2.3 Input :22.9.2.4 Overall Dimensions : W . mm x H .mm x D mm
22.9.2.5 Accuracy : . % of full scale
22.9.2.6 Technical literature furnished at :
22.10 Level Transmitters (UltrasonicType)
:
22.10.1 Make & Model No. :
22.10.2 Accuracy :
22.10.3 Type :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 26 of 64
7/31/2019 9 Section 5B - TECH Requirements
27/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
22.10.4 Compatible to HART communication : Yes/No
22.11 Level Transmitters (RF Type)
22.11.1 Make & Model No. :
22.10.2 Accuracy :
22.10.3 Type :
22.10.4 Compatible to HART Communication : Yes/No
22.11 Level Transmitters (RADAR Type)
22.11.1 Make & Model No. :
22.11.2 Accuracy :
22.11.3 Type :
22.11.4 Compatible to HART communication : Yes/No
22.12 Dew Point Monitor
22.12.1 Make & Model No. :
22.12.2 Accuracy :
22.12.3 Type :
22.12.4 Compatible to HART communication : Yes/No
23.0 INSTRUMENTATION CABLE,INTERNAL WIRING ANDELECTRICAL FIELDCONSTRUCTION MATERIAL
23.1 Technical Information23.1.1 Detailed technical literature and data
conveying specification of eachtype of instrumentation cable,internal wiring, electrical fieldconstruction material and allother accessories
:
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 27 of 64
7/31/2019 9 Section 5B - TECH Requirements
28/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
23.1.2 Typical interconnection philosophydiagram (refer sub-section-INST
CABLE Part-B of Section-VI)indicating signal routing fromfield to the control systemcabinets along with the type ofcables employed for eachinterconnection furnished at(This should cover both mainplant and auxiliary plant)
:
23.2 Bill of MaterialComplete bill of material for all
instrumentation cables including
prefabricated cables, co-axialcables, electrical fieldconstruction materials andaccessories furnished as perspecification
:
23.3 Proposal Data Sheets
Bidder shall furnish the followingdata separately for each type &size of instrumentation cableincluding special cables
23.3.1 Manufacturers Name :
23.3.2 Reference design standards :23.3.3 Conductor Size :23.3.4 Conductor Material :23.3.5 No. of Pairs/Cores :
23.3.6 Conductor 23.3.6.1 Material :23.3.6.2 Reference Standard :23.3.6.3 Grade :23.3.6.4 No. of Strands :
23.3.6.5 Diameter of Strands (mm) :
23.3.6.6 Approx. dia of conductor (mm) /cross section area (Sq.mm)
:
23.3.6.7 Maximum conductor resistance per KM (in Ohm)
:
23.3.7 Insulation
23.3.7.1 Reference Standard :
23.3.7.2 Material Composition :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 28 of 64
7/31/2019 9 Section 5B - TECH Requirements
29/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
23.3.7.3 Nominal Thickness (mm) :23.3.7.4 Thickness (mm) : Min. . Max.
23.3.7.5 Minimum Volume Resistivity as per VDE-0207 Part-IV
: .. ohm cm at 20oC
23.3.7.6 Dielectric Constant : ohm cm at 70oC23.3.7.7 The insulation will withstand
conductor operating temp. of 70Deg. C/ 205 Deg. C (if applicable) specificconfirmation required)
: Yes/No
23.3.7.8 Core diameter (mm) includinginsulation
:
23.3.8.1 Whether Pairs are twisted : Yes/No23.3.8.2 Maximum lay of twist (mm) :
23.3.9 Shield23.3.9.1 Material :23.3.9.2 Thickness over individual pair in mm
(if applicable):
23.3.9.3 Thickness of overall shield (in mm) :
23.3.9.4 Noise interference better than : db23.3.10 Drain Wire23.3.10.1 Reference standard :
23.3.10.2 Size & No. of Strands :
23.3.10.3 Material :23.3.10.4 Resistance of drain wire per Km
(ohm):
23.3.10.5 Separate Drain wires for i ndividualas well as overall shieldprovided
: Yes/No
23.3.11 Fillers (if applicable) are flameretardant and moisture resistant
:
23.3.12 Outer Sheath :
23.3.12.1 Reference standard :23.3.12.2 Material :23.3.12.3 Nominal thickness of outer sheath
(mm):
23.3.12.4 Thickness of outer sheath (mm) : Min.. Max.
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 29 of 64
7/31/2019 9 Section 5B - TECH Requirements
30/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
23.3.12.5 Calculated Dia. Under outer sheath(mm)
:
23.3.12.6 Oxygen index (as per ASTMD-2863)in %
:
23.3.12.7 Temperature index (in deg.C as per ASTMD-2863)
:
23.3.12.8 Maximum acid gas Generation (byWeight) as per IEC-754-1 (in %)
:
23.3.12.9 Colour of outer sheath sky blue asper specification
: Yes/No
23.3.13.1 Overall diameter of cable (mm) :
23.3.13.2 Tolerance on overall diameter (mm) :
23.3.13.3 Weight per KM of cable :
23.3.14 Cable Parameters at 20oC (+ 3oC) :
23.3.14.1 Conductor resistance (max.) :23.3.14.2 Insulation resistance (min.) :23.3.14.3 Mutual capacitance at 0.8 kHz (Max) :
23.3.14.4 Cross Talk at 0.8 kHz (Min.) :23.3.14.5 Attenuation at 1 kHz (Max.) :23.3.14.6 Characteristic Impedance (Max.) :23.3.15 Continuous operating temp. (oC) :23.3.16 Whether Complete Cable Assembly
flame retardant as per IEEE-383
: Yes/No
23.3.17 Whether complete cable assemblypasses Swedish Chimney testas per SEN 4241475 (f3)
: Yes/No
23.3.18 Identification
23.3.18.1 Length of the Cable marked at everymeter
: Yes/No
23.3.18.2 FRLS marked at every 5 meter : Yes/No
23.3.18.3 Each core of the pair numbered : Yes/No
23.3.18.4 Conductor identification details for pairs
: Colour
Band ..
Numbering
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 30 of 64
7/31/2019 9 Section 5B - TECH Requirements
31/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
23.3.18.5 Details of cable markings :
23.3.19 Test Voltage : Core to Core Core to Shield
23.3.19.1 High voltage test (dielectric strength)
i) Voltage (kV) :
ii) Duration (min) :
23.3.19.2 Resistance to direct current test :i) Voltage (kV) :ii) Duration (min) :
23.3.20 Cable Cross-Sectional Drawings for each type of cable furnished at
:
23.3.21 Confirm that cables are includedunder bidders scope on asrequired basis
: Yes/No
23.3.22 Confirm that prefabricated cablesshall have 10% spare cores notconnected to connector
: Yes/No
23.3.23 Technical Literature furnished at :
23.3.24 i) Length of single coil in adrum
:
ii) Termite proof seasonedwood drum provided
: Yes/No
iii) Gross Weight :
iv) Net Weight :
v) Identification marksprovided
: Yes/No
23.4 Cable termination provided : Yes/No
23.5 Internal wiring for controldesk/electronic system cabinets
23.5.1 Conductor size and number of strands
:
23.5.2 Conductor Material :23.5.3 Insulation
23.5.3.1 Conductor insulation material FRLS : Yes/No
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 31 of 64
7/31/2019 9 Section 5B - TECH Requirements
32/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
23.5.3.2 Conductor Insulation Thickness :
23.5.3.3 Applicable design Standard for conductor insulation
:
23.5.4 Voltage Grade :
23.5.5 Reference Standard :
23.5.6 Technical Literature furnished at :
24.0 CABLING ACCESSORIES &ELECTRICAL FIELDCONSTRUCTION MATERIAL
24.1 Confirm that all conduits, conduitsupports, junctionboxes/terminals blocks (withspare terminals as specified)and all electrical fieldconstruction material for theworks included under technicalspecification, shall be furnishedby the Bidder on as requiredbasis
: Yes/No
24.2 Confirm that fire proof sealing toprevent entry/propagation offire/dust through floor slots havebeen provided for all application
: Yes/No
24.3 Confirm that two (2) new sets of
cable termination accessoriesrequired for cablingmaintenance work shall besupplied
: Yes/No
24.4 List of items covered in 7.03.4.3above with technicalspecification furnished at
:
24.5 Type Test Procedures as per VDE0472, IS 10810, VDE 0815 andother relevant standards
enclosed
: Yes/No
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 32 of 64
7/31/2019 9 Section 5B - TECH Requirements
33/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
24.6 Cable support system :
24.6.1 Conduit Pipes & Accessories :
24.6.1.1 Makers Name and Country of Manufacturer
:
24.6.1.2 Material :24.6.1.3 Catalogue attached as Annexure no. :
24.6.1.4 Applicable Standard :
24.6.2 Junction Boxes
24.6.2.1 Makers Name and Country of Manufacturer
:
24.6.2.2 Material :24.6.2.3 Applicable Standard :24.6.3 Cable Glands
24.6.3.1 Makers Name and Country of Manufacturer
:
24.6.3.2 Type of Cable Gland :
24.6.3.3 Applicable standard :
24.6.4 Cable Jointing/Termination Kits
24.6.4.1 Makers Name and Country of Manufacturer
:
24.6.4.2 Type of System
a) Termination :b) Joints :
24.6.4.3 Catalogue attached as Annexure No. :
24.6.4.4 Type Test Reports enclosed asAnnexure No.
:
24.6.4.5 Applicable Standard :24.6.5 Cable Lugs & Terminals :24.6.5.1 Makers Name and Country of
Manufacturer:
24.6.5.2 Applicable Standard :24.6.6 Type Test procedure as per VDE
0472 IS:10810, VDE 0815 andother relevant standards
enclosed
: Yes/No
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 33 of 64
7/31/2019 9 Section 5B - TECH Requirements
34/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
25.0 PROCESS CONNECTION PIPING
25.1 ScopeConfirm that impulse pipes/tubes,
sample pipes, pneumatic pipes,required fittings, valves, valvemanifolds, condensing pots,balancing reservoirs, air filterregulators, etc. and otheraccessories for impulse pipingand sample piping system shallbe furnished by the Bidder onas required basis
: Yes/No
25.2 Detailed technical literature and dataand bill of materials coveringspecification of each type ofimpulse piping & tubing, samplepiping, pneumatic tubing fittings,instrument valves, valvemanifolds and all other installation hardware &accessories
25.3 Proposal Data Sheets25.3.1 Impulse Piping/Tubing System
The following data shall be suppliedindividually for each piping classas applicable
25.3.1.1 Impulse Pipea) Manufacturers Name :b) Material Specification :c) Size & Schedule No. :
25.3.1.2 Impulse Tubea) Manufacturers Name :b) Material Specification :c) Wall Thickness :
25.3.1.3 Fittings
a) Manufacturers Name :b) Type :c) Material Specification :d) Size :e) Design Rating :
25.3.1.4 Valvesa) Manufacturers Name :b) Type :c) Material Specification :d) Size :e) Pressure Class :f) Temp. Rating :
25.3.1.5 Valves Manifoldsa) Manufacturers Name :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 34 of 64
7/31/2019 9 Section 5B - TECH Requirements
35/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
b) Type :c) Material Specification :
d) Design Rating :25.3.2 Sample Piping System (indicate for
each sample)
25.3.2.1 Sample Pipea) Manufacturers Name :b) Material Specification :c) Size & Schedule No. :
25.3.2.2 Fittingsa) Manufacturers Name :b) Type :c) Material Specification :
d) Design Rating :e) Size :
25.3.2.3 Air Filter Regulator a) Make & Model No. :
25.3.2.4 Valvesa) Manufacturers Name :b) Type :
c) Material Specification :d) Size :e) Pressure Class :f) Temp. Rating :
25.3.2.5 Purge Rotameter The following data shall be supplied
individually for:
a) Make and Model No. :25.3.3 Pneumatic Tube
a) Manufacturers Name :b) Material Specification :c) Design Rating :d) Size (OD x thickness) :
25.3.4 Fittingsa) Manufacturers Name :b) Type :
c) Material Specification :d) Design Rating :e) Size :
25.3.5 Air Filter Regulator a) Make & Model No. :
IB. WET FLY ASH HANDLING EQUIPMENT MECHANICAL
1.0 WETTING HEAD
1.1 Manufacturer :
1.2 Quantity :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 35 of 64
7/31/2019 9 Section 5B - TECH Requirements
36/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
1.3 Size, Inlet/ Outlet :
1.4 Material of Construction andHardness of Components
:
1.4.1 Body :
1.4.2 Nozzle Tips :
1.5 Weight of Assembly :
1.6 Drawing enclosed : Yes/No
2.0 COLLECTOR TANK
2.1 Quantity :
2.2 Material and Thickness :
2.2.1 Body
2.2.2 Liners
2.2.3 Impact Plate
2.3 Size
2.4 Weight of Assembly (Kg.) :
2.5 Supporting Structure complete withAccess Platforms, Staircase up tothe top level provided?
: Yes/ No
3.0 AIR WASHER
3.1 Manufacturer :
3.2 Quantity :
3.3 Size :
3.4 Material of Construction andHardness of Components:
:
3.4.1 Body :
3.4.2 Nozzle Holder :
3.4.3 Nozzle Tips :
3.5 Weight of Assembly :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 36 of 64
7/31/2019 9 Section 5B - TECH Requirements
37/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
4.0 VACUUM BREAKER
4.1 Manufacturer :
4.2 Type of Valve :
4.3 Quantity :
4.4 Size :
4.5 Location :
4.6 Material of Construction andHardness of Components
:
4.6.1 Body :
4.6.2 Gate/Plate/Disc (indicate thicknessalso)
:
4.7 Type of Operating device :
4.8 Other specific features of the Valve :
II. DRY FLY ASH EVACUATION SYSTEM FOR NEW ESP HOPPERS
ELECTRICAL EQUIPMENTS
1.0 Information and drawings to be submitted along with the following:
The following information and drawings of the proposed equipment shall besubmitted in required number of copies by the Bidder along with his proposal.
1.1 Complete technical literature supported by catalogues for all the equipmentsand accessories covered in his scope of supply.
1.2 Instruction Manuals for all the equipments covered in the Bidders scope of supply.
1.3 Technical Data Sheets (guaranteed technical particulars) of the equipmentoffered.
2.0 Information and drawings to be submitted after the award of the contract.
2.1 Contractor shall submit all the drawings, data sheets, manuals, catalogues etc.as per the requirements given under applicable sections of the specifications.
2.2 Drawings showing adequate details o f equipment/panels and accessoriesoffered and typical drawings of major schemes offered.
2.3 Contractor shall also submit the technical data sheets (Guaranteed TechnicalParticulars) of all the equipments being supplied.
2.4 Type test and routing test reports for all the equipments and accessories
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 37 of 64
7/31/2019 9 Section 5B - TECH Requirements
38/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
covered under Bidder scope of supply.
3.0 Check List for Information and Drawings to be submitted with the Bid(This check list must be attached to the data sheet)
3.1 Complete technical literaturesupported by catalogue for all theequipments and accessoriesenclosed
Yes/No
3.2 Instruction Manuals for all theequipments enclosed
Yes/No
4.0 MOTORS (to be filled in for each Type & Rating)
4.1 Manufacture & Country of Origin :
4.2 Equipment
4.3 a) Motor Type (SquirrelCage/Slip ring/DC etc.)
:
b) Type of Duty :
4.4 Frame Size & Type Destination :
4.5 Application standard to which motor conforms
:
4.6 Standard rating at 50oC ambienttemperature
:
4.7 Maximum Power input to the drivenequipment over entire operatingrange (KW) (for HT motors only)
a) At rated Speed :
b) At 103% Speed :
4.8 Stator Winding Insulation
a) Class & Type :
b) Tropicalized :
c) Temperature rise over specified ambient of50oC
:
4.9 Direction of Rotation as viewed
from non-driving end
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 38 of 64
7/31/2019 9 Section 5B - TECH Requirements
39/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
4.10 Full load current at rated voltage &frequency
:
4.11 Power Factor at rated load :
4.12 Starting Current at
a) 100 Voltage :
b) 85% Voltage
4.13 Torques (Kg-Meter) at
a) Starting :
Pull-up :
c) Pull-out :
4.14 Type of Construction of Rotor :
4.15 Rotor Insulation :
4.16 Type of Enclosure and Method of Cooling
:
4.17 Degree of Protection :
4.18 Rated Voltage and Frequency :
4.19 Rated Speed :
4.20 Efficiency at design duty point(without ve tolerance) and 100%full load
:
4.21 Power factory at design duty point :
4.22 Type of Mounting :
4.23 Type of Terminal Box for Stator Leads
:
4.24 Bearing Type
a) DE :
b) NDE :
5.0 LT SWITCHGEAR
Bidder to furnish following data foreach type and class of
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 39 of 64
7/31/2019 9 Section 5B - TECH Requirements
40/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
switchgear separately.
5.1 Switchgear & MCC
5.1.1 General
5.1.1.1 Manufacturers Name :
5.1.1.2 Type Designation :
5.1.1.3 Country of origin :
5.1.2 Rated Voltage :
5.1.3 Symmetrical short circuit withstandcurrent at rated voltage ofswitchgear/MCC cubicle
:
5.1.4 Peak Short circuit withstand current :
5.1.5 Rated current at ambient :
5.1.6 Degree of protection as per IS:13947
:
5.1.6.1 Breaker/MCC Cubicles :
5.1.6.2 Bus bar Chamber :5.1.7 Cubicle sheet metal details
5.1.7.1 Cold rolled/hot rolled :
5.1.7.2 Thickness, structural & loadbearing members
:
5.1.7.3 Thickness, front & rear :
5.1.7.4 Thickness, Sides & Top :
5.1.7.5 Thickness of gland Plates :
5.1.8 Painting shade & thickness as per IS:5
5.1.8.1 Extern Surfaces
a) Front & Rear :
b) Side End Covers :
5.1.8.2 Internal Surfaces :
5.1.9 Minimum Clearance in Air for Bus
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 40 of 64
7/31/2019 9 Section 5B - TECH Requirements
41/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
bars
5.1.9.1 Between Phases :
5.1.9.2 Between phase & Earth :
5.1.10 Standard height, Width & Depth of typical panel
:
5.1.10.1 Circuit Breaker panel :
5.1.10.2 MCC Panels (S.F./D.F.0 :
5.1.10.3 Circuit Breaker panel with Bus
trucking/Bus Duct Termination
:
5.1.10.4 ACDB/DCDB :
5.1.10.5 AC/DC Fuse boards :
5.1.11 Width of cable alley :
5.1.12 Shrouding arrangement in cablealley provided or not
: Yes/No
5.1.13 Earth Bus bar size & material :
5.1.14 Approx. weight of one panel withcircuit breaker
:
5.1.15 Recommended dynamic loading for foundation design
:
5.1.16 Approx. Weight of one MCC Panel :
5.2 Power Bus Bars and Insulators
5.2.1 Material & applicable standards :
5.2.3 Bare/Painted/EpoxyInsulated/Sleeved
:
5.2.4 Continuous Current Rating :Over an Ambient Temperature
(Amps)
5.2.5 Temperature rise over designambient temperature forcontinuous current ratingDeg.C
:
5.2.6 Material of the support insulators :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 41 of 64
7/31/2019 9 Section 5B - TECH Requirements
42/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
5.2.7 One Second Current Rating (KA) :
5.3 Control Supply Transformers
5.3.1 Make :
5.3.2 Type :
5.3.3 Material & Class of Insulation :
5.3.4 Voltage Rating & Taps :
5.3.5 Continuous Rating (VA) :
5.4 Circuit Breaker
5.4.1 Manufacturers name and countryof manufacturer
:
5.4.2 Manufacturers type anddesignation
:
5.4.3 Rated Voltage :
5.4.4 Rated Operating Duty :
5.4.5 Design ambient temperature :5.4.6 Rated current at design ambient
temperature:
5.4.7 Derating factor for site operatingconditions inside panel
:
5.4.8 Continuous current at ambienttemp.
:
5.4.9 Rated symmetrical breaking current :
5.4.10 Rated peak making current :
5.4.11 Rated short time rating (for 1Second)
:
5.4.12 Rated Peak momentary Rating :
5.4.13 Number of openings, the circuitbreaker is capable of performing without inspection,replacement of contracts orother parts at 100% ratedbreaking current
:
5.4.14 No. of Breaker auxiliary contacts :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 42 of 64
7/31/2019 9 Section 5B - TECH Requirements
43/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
provided on fixed portion ofbreaker and their rating
5.4.15 Trip free and anti-pumping featureshave been provided (Furnishdescription)
: Yes/No
5.4.16 Power operating mechanism :
5.4.17 Spring Charging Motor details :
5.4.17.1 Type :
5.4.17.2 Rating Watts :
5.4.17.3 Rated Voltage :
5.4.17.4 Class of Insulation :
5.4.17.5 Time for fully charging the closingspring
:
5.4.18 Emergency manual Chargingfacility provided
:
5.4.19 Limits of voltage for satisfactoryoperation of the followingdevices as percentage ofnormal voltage
:
5.4.19.1 Motor :
5.4.19.2 Closing Coil :
5.4.19.3 Tripping Coil :
5.4.20 Manual Operating Mechanism :
5.4.21.1 Type of Releases provided :
5.4.21.2 Available range of followingparameters for each type ofrelease offered
:
5.4.22.1 Maximum Tripping Time :
5.4.22.2 Maximum Closing Time :
5.4.23.1 Closing Coil VA :
5.4.23.2 Tripping Coil VA :
5.4.23 Telescopic trolley
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 43 of 64
7/31/2019 9 Section 5B - TECH Requirements
44/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
5.4.23.1 Make :
5.4.23.2 Type Designation :
5.4.23.3 Dimensions :
5.5 Air Break Switches
The following details shall befurnished for each type &Rating
5.5.1 Make :
5.5.2 Type :
5.5.3 Applicable Standards :
5.5.4 Rated current at design ambienttemperature (Amps)
:
5.5.5 Design ambient temperatureDeg. C
:
5.5.6 Rated Breaking Current (kA) :5.5.7 Maximum through fault current
withstand kA:
5.5.8 Door interlock as specified hasbeen provided?
: Yes/No
5.5.9 No. of auxiliary contacts and itsrating
:
5.6 Control/Selector Switch
5.6.1 Make :
5.6.2 Type Designation :
5.6.3 Voltage Grade :
5.7 Contactor
The following details shall be furnished for each type & rating)
5.7.1 Make :
5.7.2 Type & applicable standards :
5.7.3 Rated voltage of main and auxiliary :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 44 of 64
7/31/2019 9 Section 5B - TECH Requirements
45/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
contacts
5.7.4 Rated Voltage of Coils :
5.7.5 Limits of Operation :
5.7.5.1 Supply Voltage Variation +/-% :
5.7.5.2 Supply frequency variation for closing (+/-)
:
5.7.5.3 Drop out voltage % :
5.7.5.4 Rated (Thermal) current A :
5.7.5.5 Rated Duty :
5.7.5.6 Rated utilization category as per IS:13947
:
5.7.5.7 Rated breaking capacity kA :
5.7.5.8 Rated making capacity kA :
5.7.5.9 Coil VA burden :
5.8 Auxiliary Contactor
5.8.1 Make :
5.8.2 Type :
5.9 MCCB
5.9.1 Make :
5.9.2 Type, rating :
5.9.3 Category :
5.10 Current Transformer
The following details shall be provided for each Type & Rating
5.10.1 Make :
5.10.2 Applicable Standards :
5.10.3 Ratio :
5.10.4 VA Rating :
5.10.5 Accuracy Class :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 45 of 64
7/31/2019 9 Section 5B - TECH Requirements
46/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
5.10.6 Class & Type of Insulation :
5.11 Voltage Transformers
5.11.1 Make :
5.11.2 Ratio :
5.11.3 VA Rating :
5.11.4 Accuracy Class :
5.11.5 Over Voltage Factor :
5.11.6 Class & Type of Insulation :
5.12 Relays
The following details shall be furnished for each type & applications includingcoupling relay.
5.12.1 Make :
5.12.2 Type :5.12.3 Application :
5.12.4 Catalogue :
5.13 Thermal Overload Relay & SinglePhasing Preventer
The following details shall be furnished for each type & rating.
5.13.1 Make & Type designation :
5.13.2 Catalogue :
5.14 Voltmeter
5.14.1 Make :
5.14.2 Type :
5.14.3 Catalogue :
5.15 Ammeter
5.15.1 Make :
5.15.2 Type :
5.153 Catalogue :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 46 of 64
7/31/2019 9 Section 5B - TECH Requirements
47/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
5.16 Push Buttons
5.16.1 Make :
5.16.2 Type Designation :
5.16.3 Catalogue :
5.17 Indicating Lamps
5.17.1 Make :
5.17.2 Type :
5.17.3 Catalogue :
5.18 Local Starters
5.18.1 Make & Type :
5.18.2 Catalogue :
5.19 415V BUS BARS with Linkageprovision
5.19.1 Manufacturers name & Address :
5.19.2 Type of Bus Bars :
5.19.3 Material and cross section of busbars
:
5.19.4 Rated Voltage (Volts) :
5.19.5 Maximum voltage at which bus bar can operate continuously(volts)
:
5.19.6 Continuous current rating of Busbars (Amps)
:
5.19.7 Short circuit current ratings &duration (kA/Sec.)
:
5.19.8 Momentary current rating kA pack :
5.19.9 Temperature rise over the ambienttemperature
:
5.19.9.1 Bus bars :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 47 of 64
7/31/2019 9 Section 5B - TECH Requirements
48/64
7/31/2019 9 Section 5B - TECH Requirements
49/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
and size of cables
6.1 Make & Type :
6.2 Country of manufacturer :
6.3 Type & Designation :
6.4 Applicable Standard :
6.5 Cable Size & No. of Cores :
6.6 Rated Voltage :
6.7 Catalogue attached : Yes/No
6.8 Continuous current rating for max.conductor temperature
:
6.8.1 When laid in air at an ambienttemperature of 50 Deg.C
:
6.8.2 When buried in soil having thermalResistivity of 150 Deg.C cm/nat a depth of 1000 mm atground ambient temperature of40 Deg.C
:
6.9 Short circuit withstand capacity andduration for
6.9.1 Conductor :
6.9.2 Screen :
6.9.3 Armour :
6.10 Conductor
6.10.1 Material :
6.10.2 Nominal cross section area in sq.mm
:
6.10.3 Shape of conductor :
6.10.4 DC resistance at 20oC :
6.11 Insulation
6.11.1 Material :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 49 of 64
7/31/2019 9 Section 5B - TECH Requirements
50/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
6.11.2 Nominal Thickness (in mm) :
6.11.3 Type of Curing (for XLPE) :
6.12 Metallic screen (wherever applicable)
:
6.12.1 Material :
6.12.2 Type :
6.12.3 Rating (KA Sec.) :
6.13 Type of Inner Sheath :
6.14 Armour Material :
6.15 Outer Sheath Material :
6.16 Over all Dia Cable (in mm) :
6.17 Guarantee Value of Minimumoxygen index of outer sheath
:
6.18 Maximum acid gas generation byweight (%) of outer sheath
:
6.19 Average light transmission :
7.0 ILLUMINATION SYSTEM
7.1 Lighting Distribution Board
7.1.1 Make :
7.1.2 Applicable Standard :
7.1.3 Type of Construction :
7.1.4 Degree of Protection :
7.1.5 Catalogue attached : Yes/No
7.2 Lighting Panel
7.2.1 Make :
7.2.2 Applicable Standard :
7.2.3 Enclosure :
7.3 Miniature Circuit Breaker
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 50 of 64
7/31/2019 9 Section 5B - TECH Requirements
51/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
7.3.1 Make :
7.3.2 Type designation :
7.3.3 Applicable Standard :
7.3.4 Rated Current Voltage :
7.3.5 Breaking Capacity of 0.6 p.f. :
7.3.6 Catalogue attached : Yes/No
7.4 Insulator
7.4.1 Make :
7.4.2 Type designation :
7.5 MCCB
7.5.1 Make :
7.5.2 Type, Rating :
7.6 Contactor
7.6.1 Make :
7.6.2 Type & Duty :
7.7 Synchronous Timer
7.7.1 Make :
7.7.2 Type :
7.7.3 Applicable Standard :
7.8 Lighting Fixtures & Accessories
7.8.1 Make of lighting fixture andaccessories
:
7.8.2 Catalogue for each type of fixtureattached as annexure no.
:
7.8.3 Applicable standard :
7.9 Switches
7.9.1 Make :
7.9.2 Type :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 51 of 64
7/31/2019 9 Section 5B - TECH Requirements
52/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
7.9.3 Catalogue attached as annexure
No.
:
7.9.4 Applicable Standard :
7.10 Receptacles/Sockets
7.10.1 Make :
7.10.2 Type :
7.10.3 Applicable Standard :
7.11 Junction Boxes
7.11.1 Make :
7.11.2 Type :
7.11.3 Material :7.11.4 Applicable Standard :
7.12 Terminal Blocks
7.12.1 Make :
7.12.2 Type :
7.12.3 Rating :
7.13 Rigid Steel Conduits/Fittings &Accessories
7.13.1 Make :
7.13.2 Material :
7.13.3 Applicable Standard :
7.14 Hume Pipes
7.14.1 Make :
7.14.2 Applicable Standard :
7.15 Flexible Steel Conduit
7.15.1 Make :
7.15.2 Applicable Standard :
7.16 Lighting Wires
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 52 of 64
7/31/2019 9 Section 5B - TECH Requirements
53/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
7.16.1 Make :
7.16.2 Applicable Standard :
7.16.3 Voltage Grade :
7.16.4 Size :
7.16.5 Conductor material :
7.16.6 Insulation :
7.17 Lighting Poles
7.17.1 Make :
7.17.2 Applicable Standard :
7.17.3 Type :7.17.4 Pole Height :
7.18 Lighting Masts
7.18.1 Make :
7.18.2 Type :
7.18.3 Overall Height :
7.18.4 Applicable Standard :
7.18.5 Catalogue attached as AnnexureNo.
:
8.0 CABLING, EARTHING ANDLIGHTNING PROTECTIONCABLE SUPPORT SYSTEM
8.1 Cable, Trays, Tray Covers andAccessories
8.1.1 Make :
8.1.2 Type of cable Tray :
8.1.3 Type of Cable support system :
8.1.4 Applicable Standard :
8.1.5 Catalogue and indicative sketch
attached as Annexure no.
:
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 53 of 64
7/31/2019 9 Section 5B - TECH Requirements
54/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
8.2 Conduit Pipes & Accessories
8.2.1 Make :
8.2.2 Material :
8.2.3 Catalogue attached as Annexureno.
:
8.2.4 Applicable Standard :
8.3 Junction Boxes
8.3.1 Make :
8.3.2 Material :
8.3.3 Applicable Standard :
8.4 Cable Glands
8.4.1 Make :
8.4.2 Material :
8.4.3 Applicable Standard :
8.5 Cable Jointing/ Termination Kits
8.5.1 Make :
8.5.2 Type of System
8.5.2.1 Termination :
8.5.2.2 Joints :
8.5.3 Catalogue attached as AnnexureNo.
:
8.5.4 Applicable Standard :
8.6 Cable Lugs & Terminals
8.6.1 Make :
8.6.2 Applicable Standard :
8.7 Earthing System
8.7.1 Buried Earth Mat
8.7.1.1 Material & Size :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 54 of 64
7/31/2019 9 Section 5B - TECH Requirements
55/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
8.7.1.2 Applicable Standard for the System :
8.7.2 Equipment Earthing
8.7.2.1 Material :
8.7.2.2 Size :
8.7.2.3 Applicable Standard :
8.8 Lightning Protection System
8.8.1 Applicable Standard :
8.8.2 Size & Material for Air terminationand down conductor
:
9.0 ELECTRICAL CONTROL DESK /CONTROL PANELS / PLC
9.1 Different Control Panels
9.1.1 Application :
9.1.2 Overall Dimensions :
9.2 Control Switch :
9.2.1 Manufacturer :
9.2.2 Type and Designation :
9.2.3 Catalogue attached : Yes/No
9.3 Annunciators
9.3.1 Manufacturer :
9.3.2 Type and Designation :
9.3.3 Solid State or Electromechanical :
9.3.4 Catalogue attached : Yes/No
9.4 Meter & Instruments
9.4.1 Manufacturer :
9.4.2 Type & Designation :
9.4.3 Catalogue attached : Yes/No
9.5 Energy Meters
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 55 of 64
7/31/2019 9 Section 5B - TECH Requirements
56/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
9.5.1 Manufacturer :
9.5.2 Type & Designation :
9.5.3 Catalogue attached : Yes/No
9.6 Indicating Lamps
9.6.1 Manufacturer :
9.6.2 Type and Designation :
9.6.3 Catalogue attached : Yes/No
9.7 Push Buttons
9.7.1 Manufacturer :
9.7.2 Type Designation :
9.7.3 Catalogue attached : Yes/No
9.8 Auxiliary Instrument Transformer
9.8.1 Manufacturer :
9.8.2 Type & Designation :
9.8.3 Catalogue attached : Yes/No
9.9 Panels
9.9.1 Manufacturer :
9.9.2 Type & Designation :
9.9.3 Catalogue attached : Yes/No
9.10 Control Panel Details
9.10.1 Make of control panel :
9.10.2 Manufacturers type & designation :
9.10.3 Overall dimension of panel (W x Dx H) mm
:
9.10.4 Anti-vibration pad provided : Yes/No
9.10.5 Transportation size of panel :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 56 of 64
7/31/2019 9 Section 5B - TECH Requirements
57/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
9.10.6 Total weight of panel :
9.10.7 Operating device height (Minimum) :
9.10.8 Operating device height (Maximum) :
9.10.9 Panel IP Protection :
.10.10 Make, technical details andcatalogue of air breakswitches, fuses, contactors,annunciators, MCBs, pushbuttons indicating lamps, etc.provided in the panel
:
9.11 PLC SYSTEM
9.11.1 Make of the PLC System :
9.11.2 Write up of PLC System :
9.11.3 Details of protection and interlockscheme
:
9.11.4 Description of list and diagnosticfeatures of PLC System
:
9.11.5 Field interrogation voltage level :
9.11.5.1 For Input :
9.11.5.2 For output :
9.11.6 No. of control/monitoring stationsprovided
:
9.11.7 Whether operation through controlpanel is possible
:
9.11.8 Hot standby provided : Yes/No
9.12 FIBRE OPTIC CABLE
9.12.1 Make :
9.12.2 Type :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 57 of 64
7/31/2019 9 Section 5B - TECH Requirements
58/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
SCHEDULE A
SCHEDULE OF GENERAL PARTICULARS OF BIDDER
1.0 GENERAL
1.1 Name :
1.2 Postal Address :
1.3 E-Mail and Fax Numbers :
1.4 Place of Manufacturer :
1.5 Service Facilities :
1.6 Availability of Spare Parts :
1.7 Name and designation of anauthorized Officer at SuppliersWorks to whom reference shallbe made for expeditious technicalco-ordination
:
1.8 Proposal No. and Date :
1.9 Proposal Validity Period :
1.10 Completion t ime in months fromthe date of issue of Letter ofIntent/Order
: ______________
1.11 Completion period in clause 1.10above guaranteed with specifiedpenalties
: Yes/No
1.12 Estimated man-hours or personnel required for erection,testing and commissioning of Dry
Fly Ash Extraction & DisposalSystem along with all accessories
: Unloading Installation& Storage
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 58 of 64
7/31/2019 9 Section 5B - TECH Requirements
59/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
1.12.1 Erection Engineers :
1.12.2 Testing & CommissioningEngineers
:
1.12.3 Erection Supervisors :
1.12.4 Testing & CommissioningSupervisors
:
1.12.5 Skilled Labour :
1.12.6 Semi-Skilled Labour :
1.12.7 Unskilled Labour :
1.13 Whether the Terms of Paymentlaid down in the GeneralConditions of Contractagreeable?
: Yes/No
1.14 Whether Earnest Money of thedesired value and in the formmentioned in Instructions toBidder submitted?
: Yes/No
1.15 Current Registration No. withDGS&D, if any
:
Name of the Firm : ____________________
Signature : ____________________
Name : ____________________
Designation : ____________________
Date : ____________________
Seal of the Company
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 59 of 64
7/31/2019 9 Section 5B - TECH Requirements
60/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
SCHEDULE B
GUARANTEED PERFORMANCE
1.0 Water Pumps
1.1 LP Ash Water Booster Pumps
1.1.1 Rated Capacity (M3/Hr) :
1.1.2 Total Dynamic Head (MWC) :
1.1.3 BHP at rated flow and head(KW)
:
1.1.4 Pump efficiency (percent) :
1.1.5 Motor rating at 50o C (KW) :
1.2 Cooling Water Pumps
1.2.1 Rated Capacity (M3/Hr) :
1.2.2 Total Dynamic Head (MWC) :
1.2.3 BHP at rated flow and head(KW)
:
1.2.4 Pump efficiency (percent) :
1.2.5 Motor rating at 50o C (KW) :
1.3 Seal Water Pumps
1.3.1 Rated Capacity (M3/Hr) :
1.3.2 Total Dynamic Head (MWC) :
1.3.3 BHP at rated flow and head(KW)
:
1.3.4 Pump efficiency (percent) :
1.3.5 Motor rating at 50o C (KW) :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 60 of 64
7/31/2019 9 Section 5B - TECH Requirements
61/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
2.0 Mechanical Exhauster
2.1 Rated Capacity (M3/Hr) :
2.2 Vacuum (mm of Hg.) :
2.3 BHP at rated flow and Vacuum(KW)
:
2.4 Pump efficiency (percent) :
2.5 Motor rating at 50o C (KW) :
3.0 Fluidizing Air Blower
3.1 Rated Capacity (M3/Hr) :
3.2 Discharge Pressure (Kg./ sq. cm.g)
:
3.3 BHP at rated flow and head(KW)
:
3.4 Blower efficiency (percent) :
3.5 Motor rating at 50o C (KW) :
4.0 Transport Air Compressor/ AirBlower
4.1 Rated Capacity (M3/Hr) :
4.2 Discharge Pressure (Kg./ sq. cm.g)
:
4.3 BHP at rated Capacity & Head(KW)
:
4.4 Compressor efficiency (percent) :
4.5 Motor rating at 50o C (KW) :
5.0 Instrument Air Compressorincluding Dryer
5.1 Rated Capacity (M3/Hr) :
5.2 Discharge Pressure (Kg./ sq. cm.g)
:
5.3 BHP at rated Capacity & :
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 61 of 64
7/31/2019 9 Section 5B - TECH Requirements
62/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
Pressure (KW)
5.4 Compressor efficiency (percent) :
5.5 Motor rating at 50o C (KW) :
5.6 Air Dryer Plant for above, KW :6.0 Vent Fan
6.1 Rated Capacity (M3/Hr) :
6.2 Discharge Pressure (mm WC) :
6.3 BHP at rated Capacity &
Pressure (KW)
:
6.4 Fan efficiency (percent) :
6.5 Motor rating at 50o C (KW) :
7.0 Air Heaters
8.0 Fluidizing Air Blower (KW)
8.1 Rated Capacity (M3/Hr) :
8.2 Discharge Pressure (Kg./ sq. cm.g)
:
8.3 BHP at rated Capacity &Pressure (KW)
:
8.4 Blower efficiency (percent) :
8.5 Motor rating at 50o C (KW) :
9.0 Any Other Requirement (KW))Bidder to add other sheets ifrequired.
10.0 Optional Items
Name of Firm: _________________________
Signature : _________________________Name : _________________________ Designation : _________________________Date : _________________________
Seal of Company
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 62 of 64
7/31/2019 9 Section 5B - TECH Requirements
63/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
SCHEDULE D
SCHEDULE OF DEVIATIONS
All commercial and technical deviations from the specification shall be set out by the Bidder clauseto clause in this schedule, other the bid shall be deemed to conform to the PurchasersSpecifications.
S. No. Clause No. Deviations Justification
A. Commercial
B. Technical
Name of Firm: _________________________
Signature : _________________________
Name : _________________________
Designation : _________________________
Date : _________________________
Seal of Company
RTS B, (1x62.5 MW UNIT)SPECN. NO. CEG-1/E4A3/DFAHS/2012
Page 63 of 64
7/31/2019 9 Section 5B - TECH Requirements
64/64
VOLUME - II
SECTION - 5 B - TECHNICAL REQUIREMENTS
SCHEDULE E
SCHEDULE OF DRAWINGS ENCLOSED WITH THE BID
S.No. Drawing No. Title
Name of Firm: _________________________
Signature : _________________________
Name : _________________________
Designation : _________________________
Date : _________________________
Seal of Company