VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION Project Unit Doc. type Mat.Code S/No. Rev. Page 8455003 600 SOW 2500 002 A 1 of 28 SCOPE OF WORKS TANKS ERECTION DOCUMENT CLASS : X A Issue For Review NG.TAN LUAT TR.DAT NGUYEN PH.VAN HUNG Rev Date DD/MM/YY STATUS WRITTEN BY (name & visa) CHECKED BY (name & visa) APPROVED BY (name & visa) DOCUMENT REVISIONS

8455003-600-SOW-2500-002-REV

Embed Size (px)

Citation preview

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           1 of 28 

 

   

 

 

 

 

 

SCOPE OF WORKS TANKS ERECTION

 

 

 

 

DOCUMENT CLASS : X

A Issue For Review NG.TAN LUAT TR.DAT NGUYEN PH.VAN HUNG

Rev Date DD/MM/YY STATUS WRITTEN BY

(name & visa) CHECKED BY (name & visa)

APPROVED BY

(name & visa)

DOCUMENT REVISIONS

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           2 of 28 

CONTENTS

1.0 PREAMBLE

2.0 INTRODUCTION 2.1 Project General Description 2.2 Description of the works covered by these Scope of Work document 2.3 Exclusion from the SUBCONTRACT 2.4 Documentation

3.0 GENERAL DOCUMENTATION 3.1 Technical documentation 3.2 Specific documentation to be issued before the beginning of the construction works 3.3 Specific documentation to be issued during the construction works 3.4 Specific documentation to be issued at the end of the construction works

4.0 RESOURCES

5.0 SUPPLIES

6.0 WORKS DESCRIPTION 6.1 Site facilities 6.2 Protection 6.3 Maintenance of works area 6.4 Construction 6.5 Miscellaneous

7.0 QUALITY CONTROL/TESTS/INSPECTION 7.1 Conformity of EQUIPMENT and MATERIAL used 7.2 Welding 7.3 Control 7.4 Completion of Works

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           3 of 28 

1. PREAMBLES

 

The purpose of the present document is to specify, in Article 1 to 7, the limits of scope of WORK between CONTRACTOR (PTSC) and Erection SUBCONTRACTOR relevant to the Erection of Tankage WORKS.

 

The scope of the CONTRACTOR is strictly limited to that defined herein; on the other hand, the scope of the Erection SUBCONTRACTOR shall be construed as being inclusive of all that is not included in CONTRACTOR'S scope. All activities / duties not included in the CONTRACTOR'S scope of WORK, as herein defined, are deemed to be included in the Erection SUBCONTRACTOR'S scope of WORK and paid by the SUBCONTRACT PRICE All activities /duties listed in the following paragraphs are complementary of the ones specified by the correspondent paragraph of Scope of Work document of each discipline.

 

The WORKS shall be performed in conformity with the SUBCONTRACT and, in particular, with the specification, the supplier recommendations, the "rules of art" and in conformity with the Project Documentation.

2. INTRODUTIONS

2.1 PROJECT GENERAL DESCRIPTION

 The CLIENT is Vietnam Oil and Gas Corporation (PETROVIETNAM), at Dung Quat, in Quang Ngai Province of central Vietnam.

2.2 DESCRIPTION OF THE WORKS COVERED BY THESE SCOPE OF WORK DOCUMENT

 The scope of WORK for this Tankage Works Package consists of the Erection of the Tanks, as de-tailed in this Document. This WORK shall include but not limited to:

 ‐  Mobilisation and demobilisation of Erection SUBCONTRACTOR plant, tools and equipment.  ‐  Site transport, site erection, site test of the tanks  ‐  Internal and external painting in accordance to specification.

 ‐  Tank plates shall be delivered to site with only primer, the plasting/painting material will be supplied by Contractor.

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           4 of 28 

 ‐  Fabrication and erection of small bore piping (if necessary)

 ‐  Piping, accessories and supports installation.

‐  NDE (non destructive examination) such as radiographic and ultrasonic magnetic particle examina-tion

 ‐  Tank calibration, Tank testing (hydraulic test & etc.) per relevant design codes  ‐ 

Erection of stairways, cages, ladders, handrail, access platform walkway and interconnec-tion walkway and platforms

 ‐  Breather valves, emergency vent covers, standard gauge hatches, slot dipping devices and accesso-ries installation.

 ‐  Approved scaffolding system, temporary working platform and temporary support

 ‐  Post weld heat treatment (PWHT) if required by design codes as per paragraphs 4 and 6 here after

 ‐  Jet Mixer installation

 ‐  Water spray system & foam system for tankages installation  ‐  Temporary facilities supply and installation

 ‐  Name plates and tags installation

 ‐  Support, grating for access platform / walkways installation

 ‐  Manholes & nozzles installation

 ‐  Grounding Clips, earth boss installation

 ‐  Anchorage / anchor chair to resist wind /seismic over-tuning installation

 ‐  Compression rings/Annular rings installation

 ‐  Nozzles, flanges, reducers and connections installation

 ‐  Installation of spiral stairway, 2m from bottom personnel protection

 ‐  Installation of what ever material supplied by Contractor

It also includes in particular all activities / duties common to all discipline such as:

 ‐  Project construction management including in particular the preparation and issuance of documenta-

tion related to SITE organization, WORKS scheduling, reporting, compliance to Vietnamese codes and regulations.

 ‐  Administrative activities and duties

 ‐  Complimentary construction engineering to main design

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           5 of 28 

 ‐  Documentation

 ‐  Material control and management,

 ‐  Health and safety

 ‐  Resources

 ‐  Material supply

 ‐  Quality assurance and quality control

Note: Foundation design and construction will be done by CONTRACTOR.

2.2.1 Design.

It includes all necessary detailed studies in complement to Engineering performed by Contractor

2.2.2 Supply of MATERIAL, Equipment, Manpower, Consumables

 It includes the supply of all Material, Equipment, Manpower, Consumable for the execution of the WORKS (as for Article 5)

2.2.3 Transport

  It includes transportation from DungQuat port to and within DungQuat Refinery, Quang Ngai, Viet Nam

2.2.4 Construction and Test

  The work of erection SUBCONTRACT.

 It includes the Execution of all Erection and Test activities in conformity with the specification, the applicable code and standard, the construction rules and the Contract, such as but not limited to:

- Preparation and erection of the storage facilities (including all the relevant accessories) as per the Tanks lists, tank data sheets and associated miscellaneous mechanical, electrical and / or instrument erection works (access stairs, ladders, accessories, etc.)

- Welding activities, including heat treatment as required by the specifications and/or bolting activities (fitting-up activities as required).

- Any tests required by the contractual documents and specifications related (such as NDE non-destructive test, heat treatment, all services related to the quality control as specified by the specifica-tions).

- Hydraulic/Vacuum tests, Calibration.

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           6 of 28 

- Pre-commissioning works, such as cleaning and closing-up of the storage facilities.

- Local authorities approval and acceptance

2.3 EXCLUSION FROM THE SCOPE

  The following is excluded from Erection SUBCONTRACTOR'S scope:

- Land for the WORK to be performed

- Laydown area for the WORK to be performed at the job site

 NOTES: In Article 3 to 7 the CON column corresponds to CONTRACTOR (PTSC) and the SUB column corresponds SUBCONTRACTOR

- In Article 3 the DOC column indicates the number of copies and the updating frequency of the doc-ument to be transmitted. The figure indicated is the number of copies to be handed over to the other party (from CONTRACTOR to Erection SUBCONTRACTOR or from Erection SUBCONTRAC-TOR to CONTRACTOR). The code following this number is:

  • N if the document does not have to be re-issued periodically

  • M if the document has to be issued on a Monthly basis

  • W if the document has to be issued on a Weekly basis

  • D if the document has to be issued on a Daily basis for every working day

  • A : to be approved by CONTRACTOR and/or OWNER

  • R : to be reviewed by CONTRACTOR and/or OWNER

  • Others : only for information

  For instance:

  • 1N = one set without requirement of being periodically re-issued

  • 3M = three sets to be issued every month

  • 2D = two sets to be issued every working day

- Definitions and abbreviations:

  Small Bore Piping: piping whose nominal diameter is strictly below 2" (DN 50)

  Large bore Piping: piping whose nominal diameter is 2" (DN 50) or above

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           7 of 28 

  FQCP: Field Quality Control Plan

  MS: Method Statement.

  ITP: Inspection and Test Plan

3. DOCUMENTATION CON SUB DOC

3.1 GENERAL DOCUMENTATION

- General specification (basic design data) X 1N

- General plot plans of the installation X 1N

- Contractual schedule of works and contractual X 1N

- General schedule of works X 1N

3.2 TECHNICAL DOCUMENTATION

  (Format of the documentation should be specified in case electronic files are provided to be customized for each project)

 The technical documentation is listed per discipline in the related scope of works documents.

3.2.1 Equipment ( Tanks)

‐  Storage Equipment dimensional drawings X 1N

‐  Equipment data sheet X 1N

‐  Piping Flow Diagram, PIDs (foam and deluge systems) X 1N

‐  Small bore Piping Flow Diagram, PIDs (foam and deluge systems) X 1N

‐  Job Specification for Supply. X 1N

‐  Specification for heat tracing X 1N

‐  Piping Specifications / Piping Classes X 1N

3.2.2 Painting/ Insulation

‐  Painting Specification X 1N

‐  Specifications for Hot and Cold Insulation X 1N

3.2.3 Instrumentation/ Electrical

‐  Erection Instruction and specification. X 1N

‐  Job Specifications for Design. X 1N

‐  Job Specifications for Supply. X 1N

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           8 of 28 

‐  Standards for grounding / cathodic Protection/Lighting. X 1N

3.3 SPECIFIC DOCUMENTATION TO BE ISSUED BEFORE THE BEGINNING OF THE ERECTION WORKS

 The following documents will be issued and transmitted before the beginning of the Erection works

3.3.1 Organisation

‐  Detailed construction execution plan, taking in account the SITE constraints X 2NA

‐  Mobilisation plan X 2NA

‐  Scaffolding plan, including resources, technical solution proposed material speci-fication and scaffolding management (HSE) procedure.

X 2NA

 ‐  The nominative organisation charts down to but excluding Foremen level and

corresponding CV’s X 2NA

‐  The list of resources assigned to the WORK: X 2NA

 • Personnel per category and nationality and split between the different

disciplines and significant activities within each discipline

• Construction equipment (type and quantity)

‐  Allocation of SITE temporary facilities and storage areas to the SUBCON-TRACTOR

X 1N

‐  The SITE temporary facilities detailed layout drawing and description X 2NA

‐  The SITE storage areas (raw material, finished materials) detailed layout X 2NA

‐  The project execution plan. X

3.3.2 Logistics

 ‐  The documentation and certification of construction equipment and relevant op-

erators (according to PTSC and/or OWNER procedures). X 2NA

‐  List of software used for the WORK, subject to CONTRACTOR approval. X 2NA

‐  List of special tools for Erection and Assembly X

3.3.3 Works scheduling

 The documents related to works scheduling shall be issued and transmitted in particular:

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           9 of 28 

‐  Contractual milestones for the storage facilities supply, fabrication, transport and erection activities X

‐  General schedule of WORKS X

‐  Forecast SITE delivery dates, Pre-Fabricated material delivery dates X  ‐  The level II time schedule of WORKS consistent with the contractual sche-

dule/milestone and the general schedule issued by CONTRACTOR and showing the associated resources required (direct productive workforces)

X 2NA

‐  Two weeks look ahead planning to be updated and submitted, and the associated resources (direct productive man-hours, construction equipment, etc.)

X 4WR

‐  A productive personnel histogram based on the weekly progress schedule X

3 3.4 Design

‐  Detailed design of the storage equipment including In particular:   • General hoisting study for each rigging operation taking in account the

site constraint (access, road, soil, others works on going...) in accordance with Contractor's requirement.

X

 • Preparation of fabrication & construction drawing, primary reaction

loads. X

• Welding rod specification for Site erection X

• List of verifications and tests to be performed on site X

• Procedure for erection and installation X

• Details of site assembly and field welds. X

3.3.5 Welding

‐  Site quality control plan (QCP) X 1N

‐  Procedure for Welding map and NDE register. X 2NA

‐ All specific procedures required for using of special material of welding tech-niques.

X 2NA

‐  Procedure for management and control of welding materials. X 2NA

‐  List of consumable for Erection X 1N

‐  Welding procedure specification (certified by a qualified Third Party) for Erec-tion

X 2NR

‐  Welder's qualification for Erection. X 2NA

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           10 of 28 

‐  PQR (certified by a qualified Third Party) for Construction. X 2NR

‐  Detail of Field Weld X 2NR

‐  The procedure for Non Destructive Examination (NDE) X 2NA

‐  The procedure for handing radioactive sources X X

3.3.6 QA/QC (*)

Independently from the limits defined in FQCP and in Article 7

‐  The SUBCONTRACT Quality Assurance Plan and Inspection and Test Plan, in conformance with the requirements included

X 2NA

‐  The procedure for maintenance and calibration of testing equipment X 2NA

‐  The procedure for MATERIAL management at SITE X 2NA

‐  The purchasing procedure for EQUIPMENT and MATERIAL supplied by SUBCONTRACT if required by OWNER

X 2NB

‐  The construction completion procedure, conformity checks and punch-lists man-agement

X 1NA

‐  Testing procedures X 2NA

‐  The procedure for the preventive maintenance of all equipment and material. X 2NA

‐  Document control procedure X 2NA

‐  The procedure for cleaning / closing-up the equipment X 2NA

‐  Procedures from Erection and Installation, leveling and welding X 2NA

‐  The welders qualification certificates X 1NA

3.3.7 HSE

‐  HSE general organization plan X

‐  Health, Safety and Environment Plan in conformance with the requirements for SITE.

X 2NA

3.3.8 Administrative documents

‐  Insurance certificates X 1N

‐  Bonds and Bank certificates X 1N

‐  Financial status report for progress payment purpose X 2NA

‐  All necessary permits, licence, registration, from local Authorities permitting Erection SUBCONTRACTOR to carry out the work.

X 2NA

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           11 of 28 

 

(*).SUBCONTRACTOR must keep at SITE an updated copy of all codes, stan-dards and regulations applicable to the present SUBCONTRACT and must also keep at SITE an updated file of the execution documents and drawings. CON-TRACTOR will be allowed permanent and free access to such documentation

3.4 SPECIFIC DOCUMENTATION TO BE ISSUED DURING THE CONSTRUC-

TION WORKS

3.4.1 Detailed time schedules

 

The documents related to detailed time schedules shall be construed, issued and transmitted in particular:

‐  The detailed time schedules (level III, 90 Days Schedule, Weekly work Plan - overall) according to CONTRACTOR instructions

X 2NA

 ‐  The detailed programs of the erection and of the various activities (including pre-assembly at ground, erection, inspections, testing, boxing-up, calibration, etc.) to be erected during the week and month, according to CONTRACTOR instruc-tions.

X 2R

‐  The programs' of the items to be Erected during the week and month, according to the priorities defined by CONTRACTOR

X 2R

‐  The programs of cleaning and boxing-up of equipment. X 2R

 

NOTE : It is understood that the scheduling of the WORK, and in particular, when construction and tests are near completion, shall be coordinated with the start-up schedule specified by CONTRACTOR.

3.4.2 Management follow-up documents

 

Management follow-up shall be issued and transmitted in accordance with the SUBCONTRACT and most especially those as follows:

‐  Progress reports (daily, weekly, monthly, flash) X 2A

‐  HSE report X 2R

‐  Work schedules X 2A

‐  Physical progress reports X 2A

‐  CONSTRUCTON equipment status reports X 2

‐  Supplies status report, certificate of origin of all equipment and materials to be provided by the SUBCONTRACTOR

X 2R

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           12 of 28 

‐  CO/CQ for all consumables to be provided by the SUBCONTRACTOR X 2

‐  Monthly status of material taken over by SUBCONTRACTOR X 2

‐  Updating of the list of work items drawings X 2

3.4.3 Progress Measurement (*)

 

Progress measurement shall be performed in accordance with the requirements as follows:

‐  General

 

• Weekly and monthly documents justifying the corresponding progress and schedule reports

X 2A

 

• Weekly and monthly progress against the schedules of the main types of work as per the programs defined in chapter 3.4.1

X 2A

‐  Physical progress measurement

 

• Progress calculation rules -The weighting of works will be unless oth-erwise instructed by CONTRACTOR SITE MANAGEMENT:

X

* By work item according to the unit of the price schedule

 

* By type of work item, trade, area, unit and above, according to the productive man-hours estimated by CONTRACTOR.

• Calculation of progress X 2A

• Checking of progress X

‐  Setting up and updating of all take-offs according to SUBCONTRACT measurement conventions and breakdown

X

  (*) It is reminded that progress is calculated according to the SUBCONTRACT term and conditions. It is expressly understood that the sole documents to be con-sidered in this respect are take-offs provided by CONTRACTOR

3.4.4 Engineering and design

‐  Recording of any modifications on drawings and other technical documentation such as bill of material, list... (see paragraph 3.5)

X

3.4.5 EQUIPMENT and MATERIAL control

3.4.5.1 Equipment and material supplied by subcontractor

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           13 of 28 

‐  MATERIAL certificates and technical sheets for all MATERIAL (including welding material) and / or EQUIPMENT. X 1NA

‐  Conformity certificates of MATERIAL and EQUIMENT supplied by SUBCON-TRACTOR such as supports components, etc X 1NA

‐  Status and progress of SUBCONTRACTOR procurement activities X 1N

‐  Copy of all un-priced purchase orders, indicating the origin of all supply X 1N

3.4.5.2 Free Issued CONTRATOR SUPPLY

 

Material inspection and control (quantitative and qualitative) of Free Issued CONTRACTOR'S SUPPLY. Such inspection shall be done by qualified person-nel.

X

NOTE : SUBCONTRACTOR shall notify any non-conformance to specification, shortage or damage

3.4.6 Welding

Refer also to FQCP ‐  Welding map and NDE register. X

‐  Chemical analysis of welding materials. X

‐  Material certificates of welding materials (electrodes, wire weld, etc.). X 1NR

‐  Certificates of non-destructive testing and PWHT equipment. X 1NR

3.4.7 Test and Inspection  

‐  Execution and record of all controls and tests as defined in the SUBCONTRACT X

‐  Material Identification X

‐  Welder’s and welding operator’s performance qualification test per Spec& Code X

‐  Welding procedure qualification test per Spec& Code X

‐  Edge preparation per Spec& Code X

‐  NDE per Spec& Code X

‐  Visual, Dimension, Orientation inspection X

3.4.8 Permit To Works

 The preparation of all Permit To Work requests in strict compliance with CON-TRACTOR and/or CLIENT rules and regulations X  

3.4.9 Punch lists

‐  Issue preliminary Punch list X 1NA

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           14 of 28 

‐  Issue final Punch list X 1NA

‐  Punch lists clearing X 1NA

3.4.10 Request of Inspection and Testing

‐  Issuance and management of all Requests for Inspection and Test (RIT). X

3.4.11 Miscellaneous

‐  Permanent updating of a "MASTER" file of execution drawings and documents (documents shall be at CONTRACTOR and/or CLIENT disposal, if requested) X

3.5 SPECIFIC DOCUMENTATION TO BE ISSUED AT THE END OF THE CONSTRUCTION WORKS

 After completion of the construction works or part of the construction works, the following documents will be issued and transmitted:

‐  Checking and acceptance of final take-off performed by SUBCONTRACTOR X

‐  Marking on the drawings to prepare as built. X

 ‐  Final take-off (supported with related drawings) listing, for each contractual Price

Schedule by Items, the reference of the related drawings and the qualities taken off from each of the said drawings

X 2NA

 ‐  Construction dossier including all technical (drawings, lists,...), material confor-

mity certificates, quality assurance and control documents. This dossier shall be presented as per format agreed by CONTRACTOR

X 2NA

‐  Proposed Final Financial Statement (for the Project). X 2NA

‐  "As-built" drawings for all works performed X 2NA

4.RESOURCES

  ‐  In order to ensure the proper performance of the WORK in accordance with the

SUBCONTRACT SCHEDULE, from the commencement of the WORK to its completion, Erection SUBCONTRACTOR shall fully adapt his organization for each specific phase of the WORK to fulfill all SUBCONTRACT requirements and accordingly shall mobilize, develop and maintain the overall functional or-ganization and corresponding resources, including when, where and as necessary by providing additional means.

X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           15 of 28 

 ‐  All Erection equipment, scaffolding, tools, protection, testing and control equip-

ment, auxiliaries, consumables, etc., and personnel (including management and supervision), necessary for the performance of the WORK, in particular for han-dling, transportation, warehousing, prefabrication, erection, testing. These in-clude, but are not limited to:

• Provision of all welding equipment X

• Provision of erection gear and tackle X

• Provision of maintenance and running of construction equipment X

• Provision of safety equipment and tools for personnel and works X

• Provision of personnel small tools X

 • Provision of mechanical equipment and material necessary for working

in water free conditions, whatever the volume or flow X

 • Provision, storage, distribution and disposal of consumables (oil, lubri-

cants, gas, etc.) and auxiliary materials (planks, timbers,tarpaulins, etc.) X

  • Provision of scaffolding and protection material X

 

• Provision of materials and apparatus -for the technological laboratory to test materials, welders and provision of materials and apparatus to test all completed works

X

• Safety equipment, cranes, trucks, trailer…, electric power X

• Pumps, calibrated manometers, connecting hoses for hydrostatic test. X

 • Pumps/compressors, manometers and connections for hydrau-

lic/pneumatic tests. X

  • Compressors and equipment for air test. X

 

• Cranes, equipment, lifting devices and accessories (such as spreader bar, gantries, pulley block, jack, winches..,), transportation and handling equipment for the safe and necessary lifting operation and Site handling operation (loading / unloading, Site transportation, unpacking and check-ing operation, handling of parts within / to storage yard, warehouse) ac-tivities, as specified by contractual documents and by the approved lifting studies.

X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           16 of 28 

 

• Any equipment and material required for the execution of any temporary foundation, soil improvement, earthworks, and reinforcement of existing facilities.

X

• Auto welding sets and special tools X

• Provision and equipment for execution of the tests. X

 

• For some particular activities the WORK will be subject to the Tanks Vendors Specialists supervision, according to CONTRACTOR state-ments. CONTRACTOR will inform Erection SUBCONTRACTOR of the activities to be supervised by the Vendor Specialist and their presence at Site, prior to start of the activities themselves.

X

 

• Refunding to CONTRACTOR any charges for keeping at Site the Ven-dor Specialist, when extended time of permanence at Site is due to SUB-CONTRACTOR fault or non-fulfillment

X

 

NOTE: SUBCONTRACTOR shall allow the use by others of any of his scaffold-ing as required by CONTRACTOR as far as such use does not interfere, such in-terference been measurable and demonstrable, with SUBCONTRACTOR'S activi-ties.

5.SUPPLIES

 

SUBCONTRACTORS shall provide all SUPPLY such as EQUIPMENT, MA-TERIAL, consumables, tools, facilities, items necessary for the execution of the WORKS with the exception of the SUPPLY provided by CONTRACTOR as sti-pulated in SUBCONTRACT.

 ‐  Protection and preventive maintenance of the MATERIAL handed over to SUB-

CONTRACTOR as per the state of art and the supplier's recommendations X

 ‐  Upon instruction of CONTRACTOR, SUBCONTRACTOR shall proceed with-

out delay to:

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           17 of 28 

 

• Substitute all SUPPLY to be supplied by SUBCONTRACTOR, which were not purchased in time and are no longer available on the market, with any equivalent or higher quality item, subject to CONTRACTOR'S SITE MANAGEMENT prior authorization.

X

 

• Replace (including any remaking of involved WORKS) all EQUIP-MENT and MATERIALS supplied by SUBCONTRACTOR and incor-porated In the completed WORKS, which are found to be faulty, of poor quality, or different type from the requirements of project documents and/or specified standards and/or prescribed quantities.

X

   ‐ 

All other MATERIAL and EQUIPMENT including consumables necessary for the works such as, but not limited to:

 • Consumables such as fuel and lubricants for SUBCONTRACTOR'S con-

struction equipment, graphite oil and Moiykote grease for greasing of threaded rods, other greases, tools, consumables, miscellaneous gases, compressed air, rugs, Teflon tapes etc.

X

• All steel materials, plates ...for the Tanks X

• Steel Structures X

• Plates material, nameplates, earth lugs, internal piping. X

• Water spray system, support cleat, ladder & support platform material X

 

• Painting/ coating/ zinc galvanized material including for surface not ac-cessible after erection such as in particular the paint for external surface of the bottom of the tanks and for equipment touch-up for site all coats

X

• CS heating coil X

• Lugs for insulation and cathodic protection X

• Protection and identification coatings X

• Cathodic Protection X

• Tank accessories (seals, breather valve, gaskets, bolts, nuts...) X

• Fireproofing supports. X

• Materials for walkways, platform, handrails, escape ladder X

• Nozzles, manholes, flanges for normal operation and hydrostatic test X

• Gauging instruments (level, meters) X

• Shimming for equipment leveling X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           18 of 28 

 • Anchoring bolts or plate for mechanical elements to be fixed/ welded to

concrete works. X

• Grouting. X

• Fire proofing materials. X

 • Graphite grease for greasing anchor bolts, or any others part required to

be greased. X

 

• Temporary materials and works to prepare the field for the cranes access and stability (plates, soil improvement, aggregates, con-crete, etc) as per the approved lifting study.

X

 

• Supply and application of grease and/or similar products to protect the machined parts of machineries, bolts threads, etc. during the construction phase.

X

• Temporary blinds and spacers necessary for tests, X

• Welding rods, filling materials for tanks X

• Protection gases, welding gases for tanks X

 

• Supplies and equipment necessary for heat treatments and surface treat-ments as applicable (thermal insulation, thermal sources, measurement devices, etc.).

X

 • Radiographic laboratory and equipment with its radioactive source for

gamma rays and X rays for shots taking. X

• Test steel plate and all provisions needed for welder WQPT X

 • Test steel plate and all provisions needed for PQR (Same material as

tank) X

• Spare parts as described in the Specification X

 • Laboratory services and materials for any test or analysis as required by

the specifications. X

• Films for radiographs. X

• Consumables for development of shots X

• Soap materials for joints inspections X

 • Consumables, tools and equipment for non-destructive testing (dye pene-

trate tests, hardness test, ultrasonic test, RT test, magnetic test etc.) X

  • Consumables, tools and equipments and manpower for hydraulic test X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           19 of 28 

6. WORKS DESCRIPTION

6.1 SITE FACILITIES

‐ Erection, maintenance, dismantling and removal of all temporary SITE facilities, including all complementary works, civil, electrical, etc. inside the allocated areas. It includes, but is not limited to:

 • For prefabricate SUBCONTRACTOR supervision on site (same office

than CO) X

• For erection SUBCONTRACTOR X

 

• SUBCONTRACTOR'S site facilities such as office, workshop, ware-house, shelter, sanitary building, and storage area, concrete or bituminous mix production plant, etc. including all complementary works, civil, raw and potable water and sewer networks, power supply, etc. inside the allo-cated areas

X

• Lighting of the works areas X

 • Temporary works to prevent personnel from injuries and/or properties

from damage X

 

• Scaffolding and safety equipment necessary for the WORKS. Such scaf-folding and safety equipment must left in place as long as necessary to al-low inspection, tests and control

X

• Disposal of all sewer and wastewater, rubbish and trash... X

6.2 PROTECTION

‐ Respect of SITE constraints (safety, units in operation, layout, location and set-up of temporary SITE facilities, etc.) X

‐ Protection of all tracks and roads used by SUBCONTRACTOR and located in the vicinity of the SITE X

‐ 

Make good to the original condition at SUBCONTRACTOR cost by the other Subcontractors in charge of the relevant works on SITE or by other Subcontrac-tors agreed by CONTRACTOR of the parts damaged by SUBCONTRACTOR or his representatives (Concrete, steel structures, piping, instruments, painting, etc.)

X

‐ Installation, dismantling and removal of all temporary protection devices used by SUBCONTRACTOR to protect personnel, structures, piping, facilities and equipment on the SITE

X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           20 of 28 

‐ Any precaution and measure to avoid damage caused by traffic, dust, noise and any other cause that may affect the personnel, buildings, equipment or goods lo-cated nearby

X

‐  Protection of existing reference points (benchmarks, beacons, etc) X

6.3 MAINTENANCE OF WORKS AREAS

‐ Daily collecting and removal of any materials used within the works areas such as iron scrap, debris, etc. to a tip defined by CONTRACTOR X

‐  Disposal of refuse and debris in the relevant authorised dumps X

‐  Housekeeping of the areas allocated to SUBCONTRACTOR X

‐ Daily cleaning of SITE and of all tracks and roads used by SUBCONTRACTOR and located in the vicinity of the SITE. This also includes spraying of water, if required, for stabilising the dust.

X

‐ Destruction of temporary paving and concrete works, including removal, trans-portation to an authorised dump and leveling of the concerned areas X

‐  Returning the SITE to a suitable condition at Complete of the Works X

6.4 CONSTRUCTION

‐ 

Care and custody of WORKS and SUPPLY handed over by CONTRACTOR to SUBCONTRACTOR. This taking in care and custody constitutes a qualitative and quantitative take-over of the WORKS and SUPPLY handed over and has to he performed by qualified personnel.

X

 

NOTE: The unloading operation shall be done promptly In order to avoid any stand by of third party truck / ship / ... Any consequences related to abnormal stand by (above two hours for normal cargo) due to the lack of resources will be charged to SUBCONTRACTOR.

‐  Preventive maintenance of all equipment and material according to the state of art and / or supplier / CONTRACTOR Instruction. X

‐  Benchmarks allowing proper positioning of work items. X

‐  Surveying, marking and positioning of work items in relation to existing bench-marks X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           21 of 28 

‐  Respecting site constraints (safety, units in operation, site layout, location and set-up of temporary site facilities, etc.). X

‐  Maintaining Works Water free (draining, pumping, water table lowering, water lifting etc.) X

6.4.1 Warehousing

‐  Warehousing of SUBCONTRACTOR'S SUPPLY. X

‐  Taking delivery of free issued CONTRACTOR'S SUPPLY in the SITE ware-house and SITE storage areas including loading, unloading, handling, transporta-tion, warehousing...

X

‐  Warehousing of material issued by CONTRACTOR after handing over to SUBCONTRACTOR and/ or sent to SUBCONTRACTOR workshops / storage facilitates

X

‐  Return, within the time allocated by CONTRACTOR to the warehouse designat-ed by the CONTRACTOR of all surplus material, including handing, transporta-tion, loading and unloading.

X

‐  Unloading, handing, transportation, stacking, of all/ any Material and Equipment involved in the construction of the plan including spare parts at location and as per construction given by Contractor

X

‐  Removal from crates, checking of the content as per packing lists, reporting any shortage or damages and storage on areas.:'. indicated by CONTRACTOR out-side, or in the site warehouse or on shelves, etc,

X

‐  Supply and install all material required to store the material such as warehouse wooden block, shelves, etc." X

‐  Protection of threaded rods by greasing. X

‐  Protection of flange faces, chamfered ends, beveled surfaces' against corrosion and mechanical damages (wooden or had PVC pads, etc.). X

6.4.2. PRE-FABRICATION

‐  Shell plates

• Cutting and edge preparation X

• End pressing and rolling X

• Assembly of nozzles and manholes to shell plate (including PWHT) X

• Assembly of flush type cleanout to shell plate (including PWTH) X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           22 of 28 

‐  Cutting of sketch plate for bottom plate X

‐  Cutting and edge preparation of bottom annular plate X

‐  Floating roof

• Cutting and edge preparation X

• Cutting of compartment plates X

• Cutting of outer rim and centre rim plate X

• Cutting of pontoon rafter. X

• Bending of outer rim and centre ring plates X

• Drilling of bolt holes X

• Cutting of supporting legs and leg guides X

• Cutting of gusset plates X

‐  Top and secondary wind griders (plate type)

• Cutting and welding of flange channel X

• Cutting of fan shaped (not rectangular) X

• Assembly of stair opening. X

‐  Roof plates (fixed roof)

• Cutting of sketch plate ing of flange channel X

• Cutting of fan shaped (not rectangular) X

• Pressing of fan shape (not rectangular if required) X

‐  Roof supporting frame (for fixed roof)

• Cutting of Rafter and girder X

• Bending of rafters X

• Drilling of bolt holes X

‐  Top angle/top girders/stiffeners (shaped steel)

• Cutting, Bending and edge preparation X

‐  Appurtenances (Stairway and hand rail etc.)

• Cutting and bending of frames (knocked down) X

‐  Nozzles and manholes

• Cutting and edge preparation X

• Welding of flange to nozzle/manhole neck X

• Cutting and bending of shell reinforcing plates X

• NDT implementation X

‐  Heating coil

• Cutting edge preparation X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           23 of 28 

• Bending 180 degree elbow X

• NDT implementation X

6.4.3 Fabrication

‐  Identification of prefabricated elements by cold marking

6.4.4 Transport

‐  Custom clearance X

‐  Transportation to site X

6.4.5 Erection

‐  Execution of foundations (by CIVIL SUBCONTRACTOR) X

‐  Installation of anchor bolts (by CIVIL SUBCONTRACTOR) X

‐  Grouting of equipment basement and foundation (by CIVIL SUBCONTRAC-TOR).

X

 ‐ 

Execution of the WORKS in accordance with the terms and conditions of the SUBCONTRACT, the specifications, the suppliers recommendations, and in con-formity with the requirements of the above listed documents and including par-ticularly

 

• Taking delivery of Free Issued MATERIALS and EQUIPMENT at the CONTRACTOR warehouse or at SITE storage areas, including loading, handling, and transportation and unloading, whatever the distance be-tween CONTRACTOR warehouse/SITE storage areas to Erection Site

X

• Cleaning of materials, accessories, etc. X

 • Transportation from site storage to the erection location, including inter-

mediate storage if applicable. X

• Installation of supports for insulation and / or fireproofing. X

 • Provision, erection, maintenance and dismantling of scaffolding neces-

sary for the performance of the works. X

 • Checking of location and levels of storage tanks foundations and sup-

ports. X

 

• Execution of any earthworks, soil improvement... required for the prepa-ration of the accesses to lifting area and of the lifting area itself. X

 • Cleaning material / equipment before erection to remove any foreign ma-

terial which could adhere such as dust, tags, welding slag. X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           24 of 28 

 • Cleaning concrete foundation (blowing / washing) including anchors

bolts (including greasing) and / or anchor pockets. X

 

• Installation of insulation wood or resins supporting blocks, to be inserted between cold equipment base plates and the foundation, in order to ther-mally/electrically insulate the foundations or support

X

 • Erection of all equipment, material (loose or pre-assembled) and asso-

ciated supports according to drawing, procedure and specification X

• Grounding installation. X

• Any temporary supporting works, as necessary. X

• Installation of all accessories including steel structures, piping X

 

• PWHT performance with any related preparation activity, such as. but not limited to erection of thermal insulation and thermocouples and thermal sources as necessary, according to the approved procedure/ specifications/codes

X

• PWHT Supervision X

‐  Surface preparation and painting or coating

• Blasting to SA 2 1/4 of external surfaces at shop X

• Blasting to SA 2 1/4 of external surfaces at shop X

• External surface painting

* Primer at shop for shipment X

* Blast and primer X

* Intermediate coat X

* Final coat X

‐  Internal surface painting

* Primer at shop for shipment X

* Blast and primer X

* Intermediate coat X

* Final coat X

‐  Final bolts tightening after grouting has cured. X

‐  Internal cleaning of all equipment to remove any object, debris. X

‐  Touch ups X

‐  Changing of all manhole gaskets. X

‐  Removal of temporary supports and wedging. X

‐  Wastes disposal to authorized tip. Daily cleaning of work locations. X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           25 of 28 

‐  Cleaning of the storage equipment after test. X

6.4.6 Welding

Refer to FQCP ‐  Joints preparation and welding. Check of proper preservation of beveled faces,

Restoration of surfaces not properly prepared or damaged for welding activities start.

X

‐  Welding X

‐  Updating of Welding books/registers. X

‐  Checking of extremities and their reshaping, if necessary, before welding. X

‐  Marking of welds, with:

• Weld number X

 • Welder identification stamp and marking of welds, in accordance

with MS X

6.5 MISCELLANEOUS

‐ Checking and management of Free issued CONTRACTOR'S SUPPLY surpluses or wastes belonging to CONTRACTOR'S

X

‐ Protection and preventive maintenance of the material handed over to SUBCON-TRACTOR as per the state of art and the supplier recommendations when store or installed

X

7. QUALITY CONTROL / TESTS / INSPECTION

‐  Preparation of the Inspection and-Test Plan (ITP) in compliance : with the above and the SUBCONTRACT conditions, to be submitted for approval to CON-TRACTOR.

X

‐  Issuance and logging of RIT (Request for Inspection & Testing) X

‐  Execution and recording of all test and inspection for equipment /materials and WORK X

‐  Verification / checking the conformity of the WORK and provide records X

‐  Issuance of construction method statement as per CONTRACTOR re-quest (for critical works) X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           26 of 28 

7.1 CONFORMITY OF EQUIPMENT AND MATERIAL USED

‐  Traceability requirements X

‐  Traceability procedure X

‐  SUBCONTRACTOR'S must be able to prove at all times that the quality of the SUPPLY incorporated in the WORK complies with the quality specified in the CONTRACT.

X

7.2 WELDING CONTROL

‐  Inspection of welding operations to guarantee the quality X

‐  Supervision of welding operations X

‐  Surveillance of welding operation X

‐  Designation of welds to be controlled: X

 

CONTRACTOR and/or the Owner reserve the right to designate the location of welds to be controlled, SUBCONTRACTOR shall make no claim whatsoever or requests for VARIATION with respect to price adjustment and/or time extension in respect of such designation.

‐  Costs of the Third Party entructed by CONTRACTOR of the counter interpreta-tion of radiographs.

X

‐  NDE including supply of necessary consumables and inspection and testing equipment X

‐  Soap application for inspection joints X

‐  Interpretation of NDE results X

 NOTE: the CONTRACTOR reserves the right to check and approve / reject the SUBCONTRACTOR interpretation

‐  Control by a duly certified agent of all welds subject to national welding regula-tions. X

‐  Correction of defective welds and associated re-inspection and re-testing until the defects has been put right. X

 ‐ 

Implementation of a register that allows the monitoring of the performance of each welder; such file will contain activity reports, refusal notes, repetitive faults and defects, etc

X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           27 of 28 

7.3 CONTROL

‐  Execution of all controls as defined in the ITP

7.4 TEST

7.4 .1 Preparation of Testing

‐  Execution and installation of purges, vents, temporary spools, temporary blinds necessary for hydrostatic /pneumatic tests of equipment. X

‐  Filling X

‐  Transfer of water X

7.4 .2 Hydrostatic testing as required

 ‐ 

Performance of the hydrostatic test including the removing and re-installation after test of all instruments and other sensitive material, installation of final joint, supply and installation of all material required for the performance of the test such as temporary blinds

X

‐  Draining and disposal of testing water X

‐  Cleaning of storage equipment after draining X

7.4.3 Other tests as required

 ‐  Performance of the other tests as required by the specifications/codes/ regulations

(such as but not limited to tightness test on piping, coils, heaters; water &hydraulic pressure tests; performance tests of foam and water spray and halon systems, etc.), including any supply/resources/third parties' involvement neces-sary for the tests execution.

X

7.4.4 Calibration

‐  Identification of the equipment to be calibrated X

‐  Supply of means, equipment and resources for calibration purposes X

‐ Execution of all WORKS required for the calibration of the tanks including oper-ations such as:

• Preparation of the lines/circuits/equipment as required X

                                    VIETNAM OIL AND GAS CORPORATION (PETROVIETNAM) PETROVIETNAM TECHNICAL SERVICES CORPORATION TWO ADDITIONAL CRUDE TANKS PROJECT SCOPE OF WORKS FOR TANK ERECTION

  

 Project        Unit    Doc. type   Mat.Code    S/No.    Rev.        Page 8455003       600       SOW            2500           002       A           28 of 28 

 • Supply of the tools, temporary material (flexible, pipe material...),

equipment (tanks, pumps, filters...), etc X

• Re-instatement of the outer piping lines X

 ‐  Supply of the Calibration reports issued by the approved certifying entity),

including data for Tank Gauging system electronic acknowledgement. X

‐  Performance of the tank strapping and gage tables. X

‐ Disposal of waste product further to chemical cleaning operations com-pletion. X

7.5 COMPLETIONS OF THE WORKS

‐  Checking after completion of erection works, and test. X

‐ Execution of any activities, preparation up to the box-up of the equipment, to be ready for process fluids fill-in. X

 ‐  SUBCONTRACTOR shall mobilize finishing teams independent from erections teams. Prior to testing, finishing teams will perform any flushing and modifica-tion necessary for the performance of the tests. After tests, finishing teams will perform any necessary reinstatement. Independent teams will perform tests.

X

‐ Commissioning (OT's SUBCONTRACTOR to ASSIST CONTRACTOR by pro-viding instruction).

X

‐  Checking after completion of hydrostatic tests. X

‐  Release completion certification to Subcontractor X

  GENERAL NOTES:

 * SUBCONTRACTOR scaffoldings and equipment must be left in place as long as necessary to allow inspection and control of works.

* A phase can be started only after acceptance of the preceding one.   * Final Acceptance can be pronounced only after all items of the "punch list'

have been cleared