Upload
mohamed
View
224
Download
0
Embed Size (px)
Citation preview
7/27/2019 6. Unit 5 Handouts - Appraisal of Projects
1/3
6/13/2012
1
Project Appraisal
Unit 4
Sunjay Lutchman
June2012
Resource /ProjectOptions
Assessment
Project
FeasibilityAnalysis
ProjectDevelopment
ProjectProjectFinancingFinancing
ProjectPlanning
Pre-Development Development Construction/Operations
ProjectOperations
2
2- to 5- year period
ProjectConstruction
Project Development Process
The purpose of Project Appraisal is to ascertain whetherthe project will be sound technically, economically,financially and managerially and ultimately viable as acommercial proposition.
The appraisal of a project will involve the examination of:
a) Technical Feasibility - To determine the suitabilityof the technology selected and the adequacy of the
technical investigation, and design.
Project Appraisal
b) Economic Feasibility - To determine theconduciveness of economic parameters to setting upthe project and their impact on the scale ofoperations.
c) Financial Feasibility - To determine the accuracy ofcost estimates, suitability of the envisaged patternof financing and general soundness of the capitalstructure.
d) Commercial Viability - To ascertain the extent ofprofitability of the project and its sufficiency inrelation to the repayment obligations pertaining toterm finance.
Project Appraisal
e) Managerial Competency - To ascertain that
competent men are behind the project to ensure itssuccessful implementation and efficient managementafter commencement of commercial production.
A project should also be examined, whereverappropriate, from the point of view of its value to thenational economy in terms of socio-economic benefitslike generation of employment opportunities, foreignexchange earnings, the quantum of import substitution,etc.
Project Appraisal
The first step in Project Appraisal is to find out
whether the project is prima facie acceptable byexamining salient features such as:
The background and experience of the applicants,particularly in the proposed line of activity
The potential demand for the product
The availability of the required inputs, utilities andother infrastructural facilities
Whether the project is in keeping with the priorities,if any, laid down by the Government.
Project Appraisal
7/27/2019 6. Unit 5 Handouts - Appraisal of Projects
2/3
6/13/2012
2
The original application may not contain all the basicdata / information. In such cases, it may benecessary to interview the applicants and elicit all thenecessary data / information with a view to formingan overall idea about the general feasibility of theproject.
After satisfying itself about the prima facieacceptability of the project, the Branch should callfor from the promoters, an Application, containingthe following essential data / information, such as:
a) Particulars of the project - Report furnishingdetails of the technology, manufacturing process,availability of construction / production facilities,etc.
Project Appraisalb) Estimates of cost of the project detailing the
itemised assets acquired / to be acquired, and WCmargin requirements.
c) Details of financing promoters contribution,Share Capital to be raised by public issue, thecomposition of the capital, Term Loans, DPGs,Foreign, etc.
d) Working Capital requirements at the peak level.
e) Project Implementation Schedule.
f) Organisation - Board of Directors and the keypersonnel to be used.
Project Appraisal
g) Demand Projections - based on the market surveyreport.
h) Estimates of Sales, CoP and profitability.
i) Projected Annual Financial Statements (I/S andB/S).
j) Projected Cash Flow Statement.
k) Proposed Amortisation schedule - repaymentprogramme.
l) Other material documentations e.g. consents fromthe Government, etc.
Project Appraisal
An inspection of the project site (or factory in thecase of existing units) is a must.
Each project has to be examined in properperspective having due regard to its nature, size andscope.
Although the basic techniques employed forappraising the viability of various projects are moreor less the same, there could be no standard or
uniform approach for appraising all projects.
Project Appraisal
The ultimate objective of the appraisal exercise is to
ascertain the viability of a project with a view toensuring the repayment of the borrowers obligationsunder the Banks term assistance.
Therefore, it is not so much the quantum of theproposed term assistance as the prospects of itsrepayment that should weigh with the Branch whileappraising a project.
Project Appraisal
In project appraisal, nothing should be assumed or
taken for granted. All the data / information should be checked and,
wherever possible, counter-checked through inter-firm and inter-industry comparisons.
It should be borne in mind that Healthy scepticismis a cardinal virtue in project appraisal.
Project Appraisal
7/27/2019 6. Unit 5 Handouts - Appraisal of Projects
3/3
6/13/2012
3