2016 Capital Facilities Project

Community ForumTuesday, April 12, 2016

East Aurora Union Free School DistrictMiddle School Cafeteria

Page 2: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Agenda

• Proposal One Capital Improvements• Proposal Two Capital Improvements• Tax Impact• Q & A

Page 3: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Capital Project - Proposal One

• HVAC Improvements• Fiber Optic Upgrades• Stage Lighting Controls

Parkdale

Page 4: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

HVAC, era 1955, Update equipment to add AC, improve energy efficiencies, and address the

limited availability of parts.

Page 5: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Capital Project – Proposal One

• Music Wing Renovations & Reconfiguration• Building Entrance Reconfiguration• Masonry Work• West Gym Improvements• 1995 Roof Replacement• Fiber Optic Upgrades• 2nd Floor Classroom Renovations• Nurse’s Office Upgrade• Middle School Office Renovations

Middle School

Page 6: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Music AreaReconfigure existing spaces to accommodate students and activities more efficiently.

Page 7: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Main EntranceBuilding entrance reconfigurations will improve

Safety, Security, Accessibility & Pedestrian access to the facility.

Page 8: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Second Floor Classrooms Renovations & reconfigurations to improve

the learning environment.

Page 9: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Capital Project – Proposal One

High School• Music Wing Renovation & Reconfiguration• 1990 Roof Replacement• Paving and Sidewalk Replacement• 1995 Carpet Replacement• Technology Lab Improvements• 1970’s Locker Room & Shower Renovations• 1970’s Gym Bleacher Replacement• Kitchen Renovation & Reconfiguration

Page 10: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Music Wing Reconfiguration

Page 11: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Boys’ & Girls’ Locker Rooms

Page 12: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Kitchen & Cafeteria Renovations

Page 13: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Capital Project – Proposal One

Athletic Complex• 8‐Lane Track Installation• 1970’s Stadium Bleacher Replacement • Athletic Field Grass Turf Replacement• Tennis Court Repairs

Page 14: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Eight Lane Track and Stadium

Page 15: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Capital Project – Proposal Two

Athletic Complex• Upgrade Athletic Field to Artificial Turf• Public Restroom Facilities Installation

Page 16: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Public RestroomsIntegrated with existing concessions.

Page 17: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

The passage of Proposal Two

is contingent upon:

1. Proposal One must pass by a majority vote.

2. Proposal Two must pass separately by a majority vote.

Page 18: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Tax Impact on Capital Facilities Project

Proposal One Proposal Two Combined Proposals One and Two

Total Project Cost $21,825,000 $1,710,000 $23,535,000

Average Annual Local Share

$646,000 $125,000 $771,000

Percent of Proposed 16‐17 Tax Levy

3.38% 0.65% 4.03%

Less $200,000 Currently included in the 16‐17 Tax Levy

(1.05%) 0% (1.05%)

Net Annual Tax Levy Increase

2.33% 0.65% 2.98%

Page 19: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

Tax Impact on a House Assessed at $100,000

Net Annual Tax Levy Increase

Tax Impact w/out STAR

Basic STAR Exemption

Enhanced STAR Exemption

Proposal One 2.33% $88.00 $61.60 $30.54

Proposal Two 0.65% $24.00 $16.80 $8.33

Combined Proposals

One and Two2.98% $112.00 $78.40 $38.87

Does not impact the tax levy until 2018 - 2019

Page 20: 2016 Capital Facilities Project - East Aurora · 2016 Capital Facilities Project Community Forum Tuesday, April 12, 2016 East Aurora Union Free School District ... Capital Project

May 17 Budget Vote

Ballots will appear as follows:Proposition 1

Budget

Proposition 2Proposal One of Capital Facilities Project

Proposition 3Proposal Two of Capital Facilities Project