127th HSJV Weekly Meeting

Embed Size (px)

Citation preview

  • 7/29/2019 127th HSJV Weekly Meeting

    1/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    P ease Turn o your

    mobile! Or Switch to

    vibration mode!

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Check! Right Now!

  • 7/29/2019 127th HSJV Weekly Meeting

    2/27

    7/14/20

    SCREEN

    Dont Panic11

    Switch Off All Electrical Equipment22

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Dont Run, Walk Fast!33

    Go to the Assembly Point44

    Wait for the Final Instruction55

    1. Safety Moment

    2. Previous Meeting

    1. Safety Moment

    2. Previous Meeting

    7. Weekly Inspection

    Committee Inspection

    Weekly Inspection

    7. Weekly Inspection

    Committee Inspection

    Weekly Inspection

    . rograms

    4. HSE Statistics

    Performance per Area and Total

    5. HSE Findings Summary

    HSE Findings by Company

    . rograms

    4. HSE Statistics

    Performance per Area and Total

    5. HSE Findings Summary

    HSE Findings by Company

    8. Incident Reports

    9. Medical Cases

    10.Environmental Issues

    11.Action Plans

    Ujin

    8. Incident Reports

    9. Medical Cases

    10.Environmental Issues

    11.Action Plans

    Ujin

    BARAKAH NUCLEAR POWER PLANT PROJECT

    va ua on y n ngs core6. Findings Analysis per Discipline

    va ua on y n ngs core6. Findings Analysis per Discipline

    Seoyong (Infra)

    Hilalco

    Seoyong (Infra)

    Hilalco

  • 7/29/2019 127th HSJV Weekly Meeting

    3/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    4/27

    7/14/20

    NO.NO. ITEMSITEMS ACTIONACTION PLANSPLANS ACTION BYACTION BYDUEDUE

    DATEDATESTATUSSTATUS

    A comparison was made on number of findings

    reported by every Subcontractor and findings raised by

    HS V KEPCO. Both Seo on and Hilalco failed to Hilalco Next

    Findings

    .

    exceed number of HSE findings. Both companies are

    requested to prepare action plans and report on next

    meeting.

    Seoyong

    MeetingDone

    2InjuryCases

    Preventive

    Actions

    Medical cases reported by subcontractors should

    include preventive actions to be taken by immediate

    supervisor.

    HSJVNext

    MeetingDone

    A letter should be issued to UJ IN requesting

    BARAKAH NUCLEAR POWER PLANT PROJECT

    3Attendance

    explanation on their absent from HSE meeting. Medical

    case from UJ IN will be reported again on next meeting.

    UJIN

    MeetingDone

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    5/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Descript ionDescript ion

    Al l vehic les leavi ng Gate 3 should tak e roundab out at wes t par t of BNPPAl l vehic les leavi ng Gate 3 should tak e roundab out at wes t par t of BNPP

    before proceeding to Gate 1. Speed l imit at service r oad is set at maximumbefore proceeding to Gate 1. Speed l imit at service r oad is set at maximum

    of 60of 60 kphkph, and overtaking is prohib ited on this road., and overtaking is proh ibited on this ro ad.

    ConstructionTeam

    prepareswork

    plan,includes

    PlanforTomorroworHolidaywork

    TodaysNightwork

    Managersignsthe

    WorkPlan

    before4:30PMdailyat

    HSJVHSE

    HSJVHSEManagerConstructionTeamHSJVHSETeam

    BARAKAH NUCLEAR POWER PLANT PROJECT

    s gns

    t e

    or

    an

    Planto

    Site.

    WorkPlan

    Descript ionDescript ion

    As par t of work prep ar at ion ev er y Su bcontrac tor must prep ar e an d submitAs par t of work prep ar at ion ev er y Su bcontrac tor must prep ar e an d submit

    dai ly wor k plan to HSE Department. Night w ork and hol i day shal l bedai ly wor k plan to HSE Department. Night w ork and hol i day shal l be

    includ ed on this form. This wi l l ease monitoring act iv i t ies at s i te.includ ed on this form. This wi l l ease monitoring act iv i t ies at s i te.

  • 7/29/2019 127th HSJV Weekly Meeting

    6/27

    7/14/20

    Descript ionDescript ion

    n c u s ve a es : ~ u g.n c u s ve a es : ~ u g.

    Training Provider : TAPROOT, U.S.ATraining Provider : TAPROOT, U.S.A

    Training Part ic ipants :Training Part ic ipants :

    HSJVHSJV, KEPCO,, KEPCO, SubcontractorsSubcontractors

    Benefi ts :Benef i ts :

    BARAKAH NUCLEAR POWER PLANT PROJECT

    incident and prevent ingincident and prevent ing

    recurrence of such case.recurrence of such case.

    Incident from safety or q ual i ty.Incident from safety or q ual i ty.

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    7/27

    7/14/20

    ItemAncil lary Ar ea Camp Area Offic e Area Power Bloc k Village 1 Village 2 HSJV Total

    For theWeek

    CumFor theWeek

    CumFor theWeek

    CumFor theWeek

    CumFor theWeek

    CumFor theWeek

    CumFor theWeek

    Cum

    Near Misses 0 0 0 0 0 2 0 18 0 0 0 0 0 20

    Over speeding 0 0 0 0 0 0 0 0 0 1 0 0 0 1

    (This Week From July 6 July 12, 2013)

    First Aid Cases (FA) 0 4 0 0 3 10 0 45 0 7 0 3 3 68

    Medical TreatmentCases (MTC) 0 3 0 1 0 5 0 12 0 0 0 1 0 22

    Restricted Work

    Cases (RWC) 0 3 0 1 0 0 0 4 0 0 0 0 0 8

    LTIs 0 0 0 0 0 0 0 3 0 0 0 0 0 3

    Property/Vehicle

    Accid ents 0 4 0 1 0 4 0 7 0 2 0 1 0 19

    Environmental

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Legend : Ancill ary Rebar Shop, Batch Plant, Paint Shop, Heavy Equipm ent Shop

    Power Block Cut Off Wall, Wharf Area, Concrete Block Area

    * : 41 cases (Oc t- Dec. 2011), 64 cases (2012), 27 (2013)

    Release

    Forthisweek Cumulative

    OneStrike Policy 2 133*

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    8/27

    7/14/20

    (This Week From July 6 July 12, 2013)

    Issued

    NearMissNearMiss

    CARCAR

    0 0 1 1

    12 15 164 191

    Findings TotalKE

    P

    C

    O

    H

    S

    J

    V

    S

    U

    B

    C

    O

    N

    Open Closed

    KEPCO HSJV Subcon KEPCO SubconHSJV

    0 0 0 0 0 1

    12 5 0 0 10 164

    BARAKAH NUCLEAR POWER PLANT PROJECT

    TOTALTOTAL

    OC&WFOC&WF 0 56 266 322

    12 71 431 514

    0 0 0 0 56 266

    12 5 0 0 66 431

    3131

    3334

    35

    Access&Egress

    ElectricalSafety

    Health&Welfare

    Plant&Equipment

    Scaffolding

    (This Week From July 6 July 12, 2013)

    1112

    1313

    151919

    2122

    2626

    2730

    Environmental

    WorkingatHeight

    PoorIllumination

    HotWorks

    Signs,Barriers&barricades

    MaterialManagement

    Lifting

    WasteManagement

    Hand&PowerTools

    FirePrevention

    PPE

    FallProtection

    ColorCoding

    BARAKAH NUCLEAR POWER PLANT PROJECT

    00

    12

    67

    88

    0 5 10 15 20 25 30 35 40

    SteelErection

    LOTO

    RoadSafety

    ConfinedSpace

    Documents

    PTW

    Training

    Supervision

    Source: CAR, Near Miss, Walkthrough and Observation Card

  • 7/29/2019 127th HSJV Weekly Meeting

    9/27

    7/14/20

    Ensure continuous supply of

    water in the workplace.

    Ensure scaffold have guard

    rail, supervisor to check

    com leteness

    Banks men should control

    ground personnel movement

    1 32

    (RCB,(RCB, SamjinSamjin))

    Sufficient amount of ORSshould be on hand for heat

    stress prevention (Power(Power

    Block,Block, AdvanAdvan))

    Maintain minimum stock of

    medical items in the first aid

    ki t (TGB1, D&I)(TGB1, D&I)

    (CWDC,(CWDC, GusanGusan))

    Clear scaffold pl atform of

    unnecessary materials

    (ADB,(ADB, SeobonSeobon))

    Scaffold inspectors to

    thoroughly check for

    damaged section(STC, Hanlim E&C)(STC, Hanlim E&C)

    (Office Area,(Office Area, JonghapJonghap))

    Install operational reverse

    alarm for tanker

    (CWDC, WBG)(CWDC, WBG)

    Ensure motor chain are

    installed with safety guards

    (Batch Plant, Eugene)(Batch Plant, Eugene)

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Ensure condition of water is

    cold and drinkable

    (STC, Hyundai C&I)(STC, Hyundai C&I)

    Use of standard scaffold

    materials in railings and

    platform (CWIS,(CWIS, Hilalc oHilalco))

    ns a w p c ec arres o r

    and fire extinguisher

    available in air compressor.

    (CWIC, Hilalco )

    Scaffolding Health and WelfarePlant and Equipment

    BARAKAHNUCLEARPOWERPLANTPROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    10/27

    7/14/20

    AncillaryAreaVillage1

    48

    FindingsperArea

    (This Week From July 6 July 12, 2013)

    Arch(I)Mech

    Piping

    21

    FindingsperDiscipline

    65

    13%CampArea

    2

    0%

    OfficeArea

    93

    19%

    10%96

    19%

    Elec

    61

    12%

    42

    9%

    4

    BARAKAH NUCLEAR POWER PLANT PROJECT

    PowerBlock

    288

    58%

    Arch(PB)

    132

    27%

    Civil

    14429%

    (This Week From July 6 July 12, 2013)

    4046

    149

    2120

    30

    40

    50

    FindingsperCompany(ArchPB)

    41

    55

    Signs,Barriers&Barricades

    Training

    WasteManagement

    WorkingatHeight

    FindingsperCause(ArchPB)

    1 2

    0

    10

    Advan D&I DOW Isam

    Kabbani

    Seobon Seoyong

    (PB)

    Ujin

    2

    22

    52

    15

    1 16

    1

    139

    3 4

    34

    71 1

    6

    05

    10152025303540

    FindingsperArea(ArchPB)

    29

    111

    45

    166

    144

    57

    17

    38

    Documents

    ElectricalSafety

    Environmental

    FallProtection

    FirePrevention

    Hand&PowerTools

    Health&Welfare

    HotWorks

    Housekeeping

    Lifting

    MaterialManagement

    Plant&Equipment

    PoorIllumination

    PPE

    PTW

    Scaffolding

    BARAKAH NUCLEAR POWER PLANT PROJECT

    78

    0 5 10 15 20

    Access&

    Egress

    ColorCoding

    Corrective Action

    Ensure that toilets have continuous supply of water. Completion of basic supplies inside the first aid kit. Proper arrangement of cables be maintained at all times.

  • 7/29/2019 127th HSJV Weekly Meeting

    11/27

    7/14/20

    (This Week From July 6 July 12, 2013)

    38

    2017 1820

    30

    40

    FindingsperCompany(ArchInfra)

    6

    2

    7

    2

    Signs,Barriers&Barricades

    Supervision

    WasteManagement

    WorkingatHeight

    FindingsperCause(ArchInfra)

    2

    0

    10

    Hanlim Seobon Towerstech Uwell YooA

    18

    45

    31

    20

    30

    40

    50

    FindingsperArea(ArchInfra)

    7

    3

    5

    10

    5

    4

    6

    4

    10

    4

    3

    1

    8

    ElectricalSafety

    Environmental

    FallProtection

    FirePrevention

    Hand&PowerTools

    Health&Welfare

    Housekeeping

    MaterialManagement

    Plant&Equipment

    PoorIllumination

    PPE

    PTW

    Scaffolding

    BARAKAH NUCLEAR POWER PLANT PROJECT

    1

    0

    AncillaryArea CampArea OfficeArea Village1

    5

    3

    0 2 4 6 8 10 12

    Access&Egress

    ColorCoding

    Corrective Action

    Repair air compressor and prevent equipment from oil leakage. Use of gas cylinders will be supported by fire extinguishers.Air compressor must be kept in drip tray to contain possible leaks.

    (This Week From July 6 July 12, 2013)

    104

    80

    100

    120

    FindingsperCompany(Civil)

    43

    42

    Supervision

    Training

    WasteManagement

    WorkingatHeight

    FindingsperCause(Civil)

    7 1 315 14

    0

    20

    40

    AlRaeel Athena Eugene Gusan Hilalco WBG

    4

    90

    6 5 417

    7 1 3 3 4

    0

    20

    40

    60

    80

    100

    FindingsperArea(Civil)

    244

    26

    42

    43

    1410

    611

    54

    113

    4

    Documents

    ElectricalSafety

    Environmental

    Excavation

    FallProtection

    FirePrevention

    Hand&PowerTools

    Health&Welfare

    HotWorks

    Housekeeping

    Lifting

    MaterialManagement

    Plant&Equipment

    PoorIllumination

    PPE

    RoadSafety

    Scaffolding

    Signs,Barriers&Barricades

    BARAKAH NUCLEAR POWER PLANT PROJECT

    16142

    0 5 10 15 20

    Access&Egress

    ColorCoding

    ConfinedSpace

    Corrective Action

    Removal of unnecessary materials at the scaffold platform.

    Install safe access for rebar works. Conduct inspection on grinder and sling belt and have items properly attached with color code.

  • 7/29/2019 127th HSJV Weekly Meeting

    12/27

    7/14/20

    (This Week From July 6 July 12, 2013)

    10

    16

    9710

    15

    20

    FindingsperCompany(Mech)

    1

    1

    2

    PPE

    Scaffolding

    Training

    WasteManagement

    FindingsperCause(Mech)

    0

    5

    Hwachon Samjin Seil YounChang

    19

    7

    35

    7

    5

    10

    15

    20

    FindingsperArea(Mech)

    4

    2

    5

    2

    2

    1

    2

    3

    1

    3

    2

    Color Codin

    ElectricalSafety

    FallProtection

    FirePrevention

    Hand&PowerTools

    Health&Welfare

    HotWorks

    Housekeeping

    Lifting

    MaterialManagement

    Plant&Equipment

    PoorIllumination

    BARAKAH NUCLEAR POWER PLANT PROJECT

    1

    0

    Ancillary

    Area

    OfficeArea PBCLP PBLaydown PBRCBUnit

    1

    PBWorkshop

    1

    0 2 4 6 8 1 0

    Access&Egress

    l

    Corrective Action

    Use of suitable hand protection during hot works activities. Replace damage fitting of oxy-acetylene tanks.

    Arrangement of argon hose line to avoid possible hazards.

    (This Week From July 6 July 12, 2013)

    8

    11

    6

    8

    10

    12

    FindingsperCompany(Piping)

    4

    3

    Scaffolding

    WasteManagement

    FindingsperCause(Piping)

    2

    0

    2

    4

    Hwachon SungChang YounChang

    13

    46

    8

    10

    12

    14

    FindingsperArea(Piping)

    2

    1

    2

    1

    1

    2

    2

    1

    2

    Color Codin

    Excavation

    FirePrevention

    Hand&PowerTools

    Health&Welfare

    HotWorks

    Housekeeping

    Lifting

    PPE

    BARAKAH NUCLEAR POWER PLANT PROJECT

    2 1 1

    0

    2

    AncillaryArea Offic eArea PBABUnit1 PBLay down Village1

    0 1 2 3 4 5

    l

    Corrective Action

    Ensure toe board and guard rails are complete while scaffold is put into use.

    Observe proper segregation of waste- paper, and plastic segregated.

  • 7/29/2019 127th HSJV Weekly Meeting

    13/27

    7/14/20

    (This Week From July 6 July 12, 2013)

    15

    37

    20

    30

    40

    FindingsperCompany(Elec)

    1

    2

    3

    3

    l

    Signs,Barriers&Barricades

    Supervision

    Training

    WorkingatHeight

    FindingsperCause(Elec)

    36

    0

    10

    D ae my un g H yu nd aiC&I Jonghap JongHap(PB)

    39

    20

    25

    30

    35

    40

    45

    FindingsperArea(Elec)

    3

    6

    3

    1

    7

    6

    1

    3

    2

    3

    3

    1

    2

    2

    Environmental

    Excavation

    FallProtection

    FirePrevention

    Hand&PowerTools

    Health&Welfare

    HotWorks

    Housekeeping

    Lifting

    MaterialManagement

    Plant&Equipment

    PoorIllumination

    PPE

    PTW

    ca old ng

    BARAKAH NUCLEAR POWER PLANT PROJECT

    9

    1

    0

    5

    10

    15

    AncillaryArea Camp

    Area Office

    Area Village

    1

    2

    1

    1

    4

    0 1 2 3 4 5 6 7 8

    Access&Egress

    ColorCoding

    Documents

    ElectricalSafety

    Corrective Action

    Replace appropriate machine guards of power tools. Maintain quality of drinking water ensuring cold water are distributed on site.

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    14/27

    7/14/20

    91

    80

    90100

    26

    37

    15 1819

    20

    30

    40

    50

    60

    70

    BARAKAH NUCLEAR POWER PLANT PROJECT

    15 4 1

    5 6 6 4 6 7 7

    0

    10

    80

    90

    100 RoadSafetyExcavation

    ConfinedSpace

    PTW

    Environmental

    Documents

    13,Housekeeping

    20

    30

    40

    50

    60

    70Supervision

    PoorIllumination

    WorkingatHeight

    Hand&PowerTools

    HotWorks

    Signs,Barriers&Barricades

    WasteManagement

    MaterialManagement

    FirePrevention

    ElectricalSafety

    PPE

    8,Housekeeping

    2,Plant&Equipment

    2,ElectricalSafety

    6,Health&Welfare

    6,Health&

    Welfare

    3,Housekeeping

    BARAKAH NUCLEAR POWER PLANT PROJECT

    0

    10

    Lifting

    Plant&Equipment

    FallProtection

    ColorCoding

    Health&Welfare

    Access&Egress

    Scaffolding

    Housekeeping

    3,Scaffolding

  • 7/29/2019 127th HSJV Weekly Meeting

    15/27

    7/14/20

    700

    80090

    100KEPCO/HSJV

    SUBCON

    (This Week From July 6 July 12, 2013)

    100

    200

    300

    400

    500

    600

    203040506070 Manpower

    BARAKAH NUCLEAR POWER PLANT PROJECT

    00

    Seoyo

    ng

    Seoyong(PB)

    TowersTech

    Gusan

    Jongh

    ap

    Jonghap(PB)

    YounChang

    YounChang(PB)

    Hwach

    on

    W

    BG

    Hila

    lco

    Advan

    Hanlim

    Uw

    ell

    YooA

    HyundaiC

    &I

    Sam

    jin

    Euge

    ne

    Daemyu

    ng

    Seob

    on

    D

    &I

    AlRa

    eel

    DO

    W

    Sam

    ho

    Geumh

    wa

    Sungcha

    ng

    Seil

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    16/27

    7/14/20

    25.023.2

    FindingsScore=NumberofCausalxRisk(FactorScore)FindingsScore=NumberofCausalxRisk(FactorScore)

    Source: CAR, Near Miss, Walkthrough and

    Observation Card reported by KEPCO & HSJV

    0.0

    5.0

    10.0

    15.0

    20.0

    0.2 0.2

    3.4 3.0 3.01.7

    4.2

    0.51.7 1.9 1.0 1.0

    BARAKAH NUCLEAR POWER PLANT PROJECT

    ActionPlanActionPlan forCompanyrequiringassistanceandsupportfromthesystemforCompanyrequiringassistanceandsupportfromthesystem

    1.JointInspection willbecarriedoutbyAreaManagementTeam.

    2.SpotTrainingwillbegiven toworkersaboutmajorfindings

    3.Actionplanwillbe submittedtoHSJVHSETeamdevelopby GUSAN

    Legend : (I) Infra, (PB) Power Block

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    17/27

    7/14/20

    Top Hazards

    Cause Nos

    Color Coding 12

    Total No. of Findings : 104ColorCoding,12

    PPE,3HotWorks,2

    Training,2Supervision,2

    Housekeeping 12

    Control Measure Due Date

    Observeregular

    housekeepingatsite,

    organizeteamstocarryout

    thetask

    Continuous

    Housekeeping,12Material

    Management,6

    FallProtection,4

    BARAKAH NUCLEAR POWER PLANT PROJECT

    ,

    andliftingapparatuswith

    colorcodemarking.

    Done

    Access&Egress,11

    Scaffolding,10Lifting,8

    Source: CAR, Near Miss, Walkthrough and Observation Card

    Top Hazards

    Total No. of Findings: 38

    Hand&PowerTools,5

    FallProtection,4Waste

    Signs,Barriers&Barricades,2

    HandandPowerTools 5

    Fall Protection 4

    Control Measure Due Date

    Prohibituseofimprovised

    tools,andrepairof

    damagedtools

    Done

    FirePrevention,2

    Housekeeping,2Management,2

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Useof

    safe working

    platformandprovisionof

    guardrailsystematedgesof

    building

    DonePoor

    Illumination,3Scaffolding,3

    Health&Welfare,2

    ElectricalSafety,2

    Source: CAR, Near Miss, Walkthrough and Observation Card

  • 7/29/2019 127th HSJV Weekly Meeting

    18/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    BARAKAH NUCLEAR POWER PLANT PROJECT

    InspectionInspection DateDate AttendeesAtt endees RemarkRemark

    Commi tt ee Ins pect ion 2013-07-09 HSJV, KEPCO, HSE Manag ement Team 4 Fi ndi ngs

    Weekly Inspection 2013-07-10 HSJV HSE Team 10 Findings

  • 7/29/2019 127th HSJV Weekly Meeting

    19/27

    7/14/20

    3

    4

    5

    FindingsperCompany

    2

    I

    Plankswithgap

    FindingsperCausal

    2

    4

    1

    2

    1

    0

    1

    2

    D&I Gusan Hanlim Seobon Seoyong

    BARAKAH NUCLEAR POWER PLANT PROJECT

    1

    1

    1

    1

    2

    0 0.5 1 1.5 2 2.5

    UnsafeAccess

    SubstandardScaffold

    IncompleteBracing

    Housekeeping

    NotInspected

    I

    Key item : Scaffolding

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    20/27

    7/14/20

    No.Source of

    InjuryArea Descr ip tion

    ImmediateAct ion

    PlannedSupervisor

    Preventive Act ion

    1

    littlefingerof

    lefthandafter

    contactwith

    hotobject

    Geumhwa

    TIGWelder

    WeldingSchool

    (Welding

    TrainingCenter)

    Accidentallytouchhottube

    whilecheckingit.

    AssessedbyDr.

    Anand

    Antibiotic

    ointment

    applied

    Wound

    Providewarning

    signsonhot

    surfaces

    Awarenesstoall

    workers

    BARAKAH NUCLEAR POWER PLANT PROJECT

    s er

    09072013

    10:30am

    dressing

    applied

    seo appropr ate

    PPE

    No.Source of

    InjuryArea Descr ip tion

    Immediate

    Act ion

    Planned

    Supervisor

    Preventive Act ion

    2

    Leftchestwall

    pain

    secondaryto

    theinjury

    Geumhwa

    Rigger

    Powerblock

    TGBarea

    Hewasaccidentallyhitbya

    scaffoldingmaterialonhischest

    whileworking

    AssessedbyDR

    :Kim

    Painonthe4th

    ribcage

    Salonpaspatch

    applied

    Advisedfor

    Use oftagline

    whileonlifting

    process.

    Riggertoattend

    refreshertraining

    BARAKAH NUCLEAR POWER PLANT PROJECT

    1007

    2013

    10:00

    chestxray

    Referredto

    Hospital

    RiggingTechniques.

  • 7/29/2019 127th HSJV Weekly Meeting

    21/27

    7/14/20

    No.Source of

    InjuryArea Descr iption

    Immediate

    Acti on

    Planned

    Supervisor

    Preventive

    Act ion

    2 Syncope

    Samjin

    Construction

    Engineer

    PowerBlock

    nearTower1

    Hyungi Minaconstruction

    engineermakeaninspectionat

    RCBouterareaaround4:50PM,

    when suddenl felt dizz

    AssessedbyDr.

    KIM

    Vitalsignstaken

    andmonitored

    Restprovided

    Awarenesstoall

    personnelon

    signsofheat

    stress

    Coordinate with

    HSEonsite

    conditionand

    BARAKAH NUCLEAR POWER PLANT PROJECT

    11072013

    16:50

    . Oralrehydration

    solutiongiven

    heatstressindex.

    Newworkerto

    undergo

    acclimatization.

    No.Source of

    InjuryArea Descr iption

    Immediate

    Act ion

    Planned

    Supervisor

    Preventive

    Act ion

    5Injuryright

    ankle sprain

    Ujin

    CommonLabour

    PowerBlock

    (RCB)

    Whilecleaningtheareahe

    slippedonthefloorthat

    causesprain.

    AssessedbyDr.

    Kim

    Analgesicspray

    applied

    Elasticbandage

    Implement

    regular

    housekeeping

    onsite

    Define

    BARAKAH NUCLEAR POWER PLANT PROJECT

    0207

    2013

    17:38

    applied wa ways or

    workers

  • 7/29/2019 127th HSJV Weekly Meeting

    22/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Schedule & Planning

    Control Manager

    Housekeeping & Site Workplace Cleanness Organization

    D. Manager

    Subcon Site

    Manager

    D. Manager

    Subcon Site

    Manager

    D. Manager

    Subcon Site

    Manager

    D. Manager

    Subcon Site

    Manager

    D. Manager

    Subcon Site

    Manager

    D. Manager

    Subcon Site

    Manager

    D. Manager

    O&M Team

    Housekeeping CoordinatorHousekeeping

    team

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Housekeeping

    Manpower

    Housekeeping

    Team

    Housekeeping

    Manpower

    Housekeeping

    Manpower

    Housekeeping

    Manpower

    Housekeeping

    Manpower

    Housekeeping

    Manpower

    Descript ionDescript ion

    Site Housekeeping team has been organized to keepSite Housekeeping team has been organized to keep w orkplace clean.workp lace clean.

    KEPCO and HSJV is maintaining andKEPCO and HSJV is maintaining and managingmanaging the t eam.the team.

  • 7/29/2019 127th HSJV Weekly Meeting

    23/27

    7/14/20

    Responsible disciplines and subcontractors by area

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Descript ionDescript ion

    As s igned res ponsible per son for each locat ion each levelAs s igned res ponsible per son for each locat ion each lev el of bui ld ing.of bui ld ing.

    PPE Standard for housekeeping team

    Blue color safety helmet

    Purple color safety vest

    Yellow color coverall

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    24/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Location Marine Works Wharf Phase 2

    Description Crawler Crane on barge observed disch arging heavy black smoke whil e dredging works.

    Act ion taken Ensure to conduct preventive maintenance according to manufacturers specification

    Status OPEN

    No.0 DateActio n by

    CompanyS ta tu s C lo s in g D ate

    Expiration

    Date

    Ref. No.

    CARM ai n Area Sub -A re a Issu ed By

    Issuer

    Company

    1

    11 July

    2013 Athena

    Crawler Crane on barge with body

    number LIMA 2400-B observed

    discharging heavy black smoke from

    the exhaust system while dredging

    works in progress which contributes

    to degradation of ambient air quality.

    OPEN

    16 July

    2013

    16 June

    2013 1621 Wharf Phase 2

    Renato

    Ponce HSJV

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    25/27

    7/14/20

    WASTEMANAGEMENT

    UPDATE

    Week=04/07/2013 10/07/2013

    WASTETYPEThisweek Lastweek

    Collected(m3) Disposal(m3) Recycled(m3) Recycle(%) Collected(m3) Disposal(m3) Recycled(m3) Recycle(%)

    Paper 56 0 45 80 0 0

    Metal 32 0 45 64 0 45

    Construction 112 495 0 128 675 0

    Concrete 0 0 0 0 0 0

    Wood(Good) 0 0 0 0 0 45

    Wood(Bad) 240 45 0 216 270 0

    Plastic 144 0 45 144 0 0

    Municipal 0 296 0 0 328 0

    BARAKAH NUCLEAR POWER PLANT PROJECT

    Legend:Collected WastefromSitetoTemporaryStorageAreaDisposal WastefromTemporaryStorageAreatoLandfillArea

    Recycle Treatedwaste(GMET)toRecyclingPlants

    Hazardous 32 32 0 24 24 0

    TotalSolidWaste 616 868 135 21.96% 656 1297 90 13.72%

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    26/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    BARAKAH NUCLEAR POWER PLANT PROJECT

  • 7/29/2019 127th HSJV Weekly Meeting

    27/27

    7/14/20

    BARAKAH NUCLEAR POWER PLANT PROJECT

    BARAKAH NUCLEAR POWER PLANT PROJECT