Service Training SERV1770Meeting Guide 770 May 2003
TECHNICAL PRESENTATION
992G WHEEL LOADER
BEST MAINTENANCE PRACTICES
8/10/2019 1.-Prcticas de Mantenimeinto
2/34
992G WHEEL LOADERBEST MAINTENANCE PRACTICES
MEETING GUIDE 770 VISUALS AND SCRIPT
AUDIENCE
Dealer and customer personnel who are responsible for the daily maintenance and service of the 992G
Wheel Loader.
CONTENT
This presentation provides basic information for the 992G Wheel Loader front linkage. It is intended to
be used in conjunction with existing training material and service manuals.
OBJECTIVES
After learning the information in this meeting guide, personnel will be able to:
1. perform a Daily Walk-Around Inspection with emphasis on the front linkage;
2. identify problems before the problems become failures; and
3. inspect and maintain the pin flag retention systems.
REFERENCES
992G (7HR, ADZ) Wheel Loader Service Manual SENR1344992G (7HR, ADZ) Wheel Loader Operation and Maintenance Manual SEBU7009
992G (7HR, ADZ) Wheel Loader Operation and Maintenance Manual SEBP2989
992G (7HR, ADZ) Wheel Loader Boom Stop Maintenance Special Instruction REHS0250
992G (7HR, ADZ) Wheel Loader Autolube Field Installation Special Instruction REHS1349
992G (7HR, ADZ) Wheel Loader Autolube System Instruction REHS1395
992G (7HR, ADZ) Wheel Loader Installation and Replacement Procedure for
Greased Link Pin Joints Special Instruction REHS1501
Dimensions for Articulated Hitches Special Instruction SEHS8642
992G (7HR, ADZ) Wheel Loader Daily Walk-Around Inspection
Technical Information Bulletin TIBU3641
Estimated Time: 4 Hours
Visuals: 21 Visuals
Student Handouts: 4
Form: SERV1770
Date: 5/03
2003 Caterpillar Inc.
8/10/2019 1.-Prcticas de Mantenimeinto
3/34
STMG 770 - 3 -
5/03
TABLE OF CONTENTS
INTRODUCTION ..................................................................................................................4
REWORK PROGRAMS .......................................................................................................5
BEST MAINTENANCE PRACTICES SERVICE LITERATURE ......................................6
DAILY WALK AROUND INSPECTION ............................................................................7
PIN FLAG RETENTION MAINTENANCE.......................................................................17
MEASURE JOINT STACK UP ...........................................................................................19
COMPONENT REPLACEMENT ......................................................................................20
BEARING REMOVAL ........................................................................................................21
PIN JOINT ASSEMBLY......................................................................................................22
BREAK IN PROCEDURE...................................................................................................23
PRE-DELIVERY PROCEDURE .........................................................................................24
CONCLUSION.....................................................................................................................25
VISUAL LIST .....................................................................................................................26
DAILY WALK AROUND INSPECTION CHECKLIST ...................................................27
STUDENT HANDOUTS .....................................................................................................30
8/10/2019 1.-Prcticas de Mantenimeinto
4/34
STMG 770 - 4 -
5/03
1
INTRODUCTION
This presentation identifies the best maintenance and service practices for
the 992G Wheel Loader structures.
The presentation will cover a service literature list, a daily machineinspection, and a pin flag retention maintenance. Component
replacement, installation procedure, and break-in procedure for pins and
bearings will also be covered.
Several handouts containing key information regarding 992G Wheel
Loader best maintenance practices are located at the end of this Service
Training Meeting Guide. The handouts are intended for copying and use
in class. The handouts can also be copied, laminated, and used by service
personnel on a daily basis.
999922GGWWHHEEEELLLLOOAADDEERR
BBEESSTTMMAAIINNTTEENNAANNCCEEPPRRAACCTTIICCEESS
2003 Caterpillar Inc.
8/10/2019 1.-Prcticas de Mantenimeinto
5/34
2
992G WHEEL LOADERLINKAGE REWORK PROGRAMS
PI30110/PI30368 Linkage Pin Conversion to Daily Grease
PS40808 Discounted Purchase Price for Autolube
REWORK PROGRAMS
The rework programs listed above should be completed on a 992G Wheel
Loader in order to realize the expected life of the linkage. All pins should
be converted to daily grease and Autolube should be installed on the
machine.
STMG 770 - 5 -
5/03
8/10/2019 1.-Prcticas de Mantenimeinto
6/34
STMG 770 - 6 -
5/03
3
992G WHEEL LOADER
BEST MAINTENANCE PRACTICESSERVICE LITERATURE LIST
REHS0250 Boom Stop MaintenanceREHS1349 Autolube Field Installation
REHS1395 Autolube System Instruction
- Available in Paper Only by Ordering REHS1396
REHS1501 Installation and Replacement of Grease Pins
SEHS8642 Dimensions for Articulated Hitches
TIBU3641 Daily Walk Around Inspection
BEST MAINTENANCE PRACTICES SERVICE LITERATURE
This graphic lists the service literature containing information regarding
maintenance of the 992G Wheel Loader linkage. Personnel responsible
for maintaining and servicing the 992G Wheel Loader should be supplied
with the literature listed above.
NOTE: The instructor should provide the students with the above
literature and go over the literature in class.
8/10/2019 1.-Prcticas de Mantenimeinto
7/34
STMG 770 - 7 -
5/03
4
DAILY WALK-AROUND INSPECTION
A walk-around inspection should be performed daily on the 992G Wheel
Loader. All pin joints should be checked for loose or damaged
components, proper lubrication, and operation. It is important to identify
a potential problem before the problem becomes a failure.
NOTE: Refer to SEBU7009, 992G Wheel Loader Operation and
Maintenance Manual, for additional information regarding the daily
walk-around inspection for the 992G Wheel Loader.
8/10/2019 1.-Prcticas de Mantenimeinto
8/34
STMG 770 - 8 -
5/03
5
The condition of the lubrication delivery system should be checked daily.
The lines, the hoses, and the injectors should all be inspected. When
damaged components are found, those components should be repaired or
replaced immediately.
Starting at the articulation joint on the left side of the machine, the
inspector should check the condition of the hoses (1) and the injectors (2).
1
2
8/10/2019 1.-Prcticas de Mantenimeinto
9/34
STMG 770 - 9 -
5/03
6
Standing in the same location and looking up, the inspector can check the
lubrication lines (1) and (2) and the hoses for the A pin and G pin. The
inspector should also check the end plates (3) and (4) and the bolts (5).
This is a visual inspection, checking for loose or damaged parts.
The inspector should also check the left end of the Y pin (not pictured)
from this location.
1
2
3
4
5
8/10/2019 1.-Prcticas de Mantenimeinto
10/34
STMG 770 - 10 -
5/03
7
Moving forward around the front left tire, the inspector should check the
lines and the hoses (1), (2), and (3) and the injectors (4). The end plate
(5) and bolt (6) for the K pin should be checked also.
1
3
2
4
5
6
8/10/2019 1.-Prcticas de Mantenimeinto
11/34
STMG 770 - 11 -
5/03
8
The E and F pin areas can be checked from the same location. The
inspector should check the flag, retaining plate, retaining bolts, and the
lubrication lines at the E pin (1). The lubrication line (2) should be in
good condition with no leaks. At the F pin (3), check the flag, the
retaining plates, the retaining bolts, and verify there is grease exiting the
relief valve.
1
3
2
8/10/2019 1.-Prcticas de Mantenimeinto
12/34
STMG 770 - 12 -
5/03
9
Check the hoses (1), the lines (2), and the injectors (3) on the bottom of
the bucket link (4).
12
34
8/10/2019 1.-Prcticas de Mantenimeinto
13/34
STMG 770 - 13 -
5/03
10
From the right side of the machine, check the hoses (1) and the lines (2)
on the bottom of the bucket link (3). Any leaks or damaged components
should be repaired immediately.
1
2
3
8/10/2019 1.-Prcticas de Mantenimeinto
14/34
STMG 770 - 14 -
5/03
11
On the right side of the K pin, check the flag (1), the retaining plate (2),
and the fasteners (3). Grease should be exiting relief valve (4).
1