02.02.GCB.inspection.V2 Portuguese

Embed Size (px)

Citation preview

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    1/18

    ABB Group

    August 30, 2013 | Slide 1

    ABB Switzerland Ltd, High Voltage Products, October 2011

    Generator Circuit Breaker Service

    Maintenance InspectionAnalysis Inspection

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    2/18

    ABB Group

    August 30, 2013 | Slide 2

    Maintenance Inspection / Analysis InspectionService Products - Inspection

    Applies for all SF6 Type breakers and all power plants

    Scope

    Full visual and functional check of the breaker system

    Benefit

    Non-destructive testing of the breaker system in order to evaluate of thecurrent condition

    Goal Early warning indication in order to prevent unexpected downtime of the

    production

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    3/18

    ABB Group

    August 30, 2013 | Slide 3

    Introduction InspectionService Products - Inspection

    Inspection is an integrated part of the maintenance concept for

    generator circuit breakers

    Interval (depended on power plant usage)

    Base load power plants

    aging service interval

    Peak load and pump storage power plants

    ~ 2 years or 75% electrical / mechanical lifetime criteria

    Preventive

    Maintenance

    CorrectiveMaintenance

    Maintenance

    Schedule

    CommissioningReplacement

    Upgrade /Modification

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    4/18

    ABB Group

    August 30, 2013 | Slide 4

    Introduction InspectionService Products - Inspection

    ABB highly recommends executing an dynamic resistance

    measurement in order to retrieve valuable service data of

    your breaker system such as

    Foot print

    Maintenance

    Inspection

    Analysis

    Inspection

    DRM

    *SF6 analysis

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    5/18

    ABB Group

    August 30, 2013 | Slide 5

    From main functionalities of GCB

    Main functionalities of the breaking chamber must beguaranteed at all time

    Carry rated nominal current

    Low ohmic resistance of the nominal current path

    No overheating at nominal current

    Interrupt current (nominal / short circuit)

    Sufficient overlap between nominal and arcingcontact system

    Short circuit current will have enough time tocommutate from the nominal to the arcing contactsystem

    Short circuit current will be interrupted

    Exceeding the electrical endurance will end up in a majorfailure of the breaking chamber

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    6/18

    ABB Group

    August 30, 2013 | Slide 6

    How does ablation and contamination occur

    MC

    AC

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    7/18

    ABB Group

    August 30, 2013 | Slide 7

    Reduction of electrical lifetime

    Ablation (erosion) of the

    arcing contact material

    caused by the arc

    Contamination of the

    nominal contact system due

    to the burn-off material from

    the arc

    Wear and tear due tomechanical operation

    Electromagnetic forces

    arise caused by high

    current which reduces thelifetime of mechanical parts

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    8/18

    ABB Group

    August 30, 2013 | Slide 8

    How can the electrical rest life time be defined?

    By calculation

    Electrical endurance curve in all O&M manuals

    All records of switched currents need to be available

    PSC can provide XLS template spread sheet

    By testing

    DRM (Dynamic resistance measurement)

    Also need to define current rest life time in case records

    should ne be availed

    By continuous measurement

    Retrofit of monitoring system

    Records or DRM testing required for presetting

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    9/18

    ABB Group

    August 30, 2013 | Slide 9

    DRM Testing

    The corresponding time

    difference determines the

    status of the arcing contact

    system

    MC

    AC

    Overlap time between MC and AC

    during an opening operation

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    10/18

    ABB Group

    August 30, 2013 | Slide 10

    Interpretation of DRM test results

    The first peak shows the separation ofthe nominal contact system

    The separation of the arcing contact

    system is when the voltage increases to

    infinite and the current starts to drop to

    zero

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    11/18

    ABB Group

    August 30, 2013 | Slide 11

    Calculation of the remaining electrical lifetime

    Any current above 150% of the nominalcurrent will count as a short circuit

    current

    Ablation increases disproportionately

    High electrodynamics forces arise

    Example

    93 mechanical operations k = 1

    523 opening operations at 0.3 kA k = 1

    7 opening operations at 2.0 kA k = 2.204

    12 opening operations at 8.0 kA k = 10.795

    2 opening operation at 10.0 kA k = 14.4241 opening operation at 57.3 kA k = 2500

    k = 93 x 1 + 523 x 1 + 7 x 2.204 + 12 x 10.795 +

    2 x 14.424 + 1 x 2500 = 3290

    The circuit-breaker has reached 33 % of its electrical lifetime.

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    12/18

    ABB Group

    August 30, 2013 | Slide 12

    Scope: Maintenance Inspection SF6 BreakersService Products - Inspection

    Visual check Visual check of the different operating linkages

    Visual check for function control: damages, corrosion, & tightness of screw connections.

    Visual check of the condition of all wirings and cable connections

    Check

    SF6-Gas pressure

    Fixation of breaker system to foundation

    Checking of torque of all flexible connections to active parts

    Centering check and function control of isolator and earthing switch Checking of reciprocal interlocking between breaker, isolator & earthing device

    Functions control of mech. key interlocking of isolator - & earthing device with motordrive

    Testing of all signals & indications

    Tightness of all fixations of: PT/CT/Capacitors & surge arresters

    Hydr. stored energy spring drive:

    Spring discharge mm / 24h (12b) Air supply unit)

    Oil level / signs of oil leaks

    Taking readings of: - Nr. of C-O operations:

    - Nr. of pumping hours:

    Evaluation of remaining life time of the breaker by means of load switchings

    Measurements:

    Times for operating mechanism reload

    Timing measurement of the breaker incl. travel curve over time

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    13/18

    ABB Group

    August 30, 2013 | Slide 13

    Scope: Analysis InspectionService Products - Inspection

    Same as Maintenance Inspection

    In addition

    DRM (dynamic resistance measurements)

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    14/18

    ABB Group

    August 30, 2013 | Slide 14

    Inspection by Customer

    Visual inspection Check for Alarms

    Check SF6 gas density

    Check pump counters on hydraulic spring operating mechanism

    Check oil level on hydraulic spring operating mechanism

    Visual check of Generator Circuit Breaker and control cubicle

    Visual inspection of components regarding corrosion or damages

    Check for unexplainable noise and smell

    Record findings in logbook or report form

    Compare results with service criteria

    Functional Checks of earthling switches and disconnector

    Calculation

    List down all switched current and calculate the remaining lifetime

    Use an excel template (available from the training centre)

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    15/18

    ABB Group

    August 30, 2013 | Slide 15

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    16/18

    ABB Group

    August 30, 2013 | Slide 16

    Comparison of old and new electrical lifetime graph for HEC 3 (2/2)

    Sequence of make-break operat ions :

    Example 1

    4 times 100 kA

    4 2500 k = 10000 k

    The breaker reached 100 % of the electr ical l i fet ime accordin gto the n ew def in i t ion ( technical ly one addi t ional shor t ci rcui t

    current is st i l l possible)

    The breaker reached 80 % of the electr ical l i fet ime according tothe old def ini t ion

    Example 2

    300 times 2 k, 50 t imes 6 kA, 100 times 12 kA, 3 t imes 100 kA

    300 2.5 k + 50 9 k + 100 20 k + 3 2500 k = 10700 k

    The breaker reached 107% of the electr ical l i fet ime accordin g tothe new defini t ion

    The breaker reached 86 % of the electr ical l i fet ime according tothe old def ini t ion

    New curve

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    17/18

    ABB Group

    August 30, 2013 | Slide 17

    Remaining overlap time/ end of electrical lifetime

    berlappungszeit

    0.00

    1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    0 200 400 600 800 1000 1200 1400 1600 1800

    Schussnummer

    berlappungszeit(ms)

    Pol A Pol B Pol C

    minimum overlap time

    end of electrical lifetime

    Test: 1800 current switching operation with a breaking current of 8 kA

    Overlap time

    Remaining overlap time of electrilce endureance

  • 7/30/2019 02.02.GCB.inspection.V2 Portuguese

    18/18

    ABB Group

    August 30, 2013 | Slide 18

    Comparison of old and new electrical lifetime graph for HEC 3 (1/2)

    This maintenance graph can be interpreted in a way that thelifetime is the sum of the switched number of currents:

    ai: coefficient (look for the coefficient in the current class table)

    ni: number of CO-Operations at one current

    Ii: current

    Sequence of make-break operat ion s:

    Example 1

    4 times 100 kA

    4 18 x 100 kA = 7200 kA

    The breaker reached 80 % of the electr ical l i fet ime

    Example 2

    300 times 2 kA, 50 t imes 6 kA , 100 times 12 kA, 3 t im es 100 kA

    300 1 2 kA + 50 1.15 6 kA + 100 1.3 12 kA + 3 18 100 kA =7905 kA

    The breaker reached 88 % of his electr ical l i fet ime

    Old curve