55
1 Navi Mumbai Municipal Corporation Town Planning Department GENERAL GUIDELINES FOR HIGH RISE BUILDING PROPOSALS

Hrc nmmc guidelines

Embed Size (px)

Citation preview

Page 1: Hrc nmmc guidelines

1

Navi Mumbai Municipal Corporation

Town Planning Department

GENERAL GUIDELINES FOR HIGH RISE BUILDING PROPOSALS

Page 2: Hrc nmmc guidelines

2

GUIDELINES FOR HIGH RISE BUILDING (HRB) PROPOSALS

INDEX

Sr. No.

Description Page Nos.

from to 1. Submission of High Rise Building (HRB) Proposal 02-04

2. Checklist for submission of proposal 04

3. Processing Fees (Non-Refundable) 05

4. General Instructions 06

5. Guidelines for High Rise Development 07-22

6. APPENIDX – A 23

7. APPENDIX- B 24

8. DESIGN BASIS REPORT 25-26

9. Check List for the Main Structural Consultant 27-31

10. APPENDIX - C 32-33

11. Environmental and Contextual Guidelines for

High Rise Buildings.

34-41

12. Report for ECG V1 42-43

13. Report EPPP-V1 44

14. Requirements for Fire Prevention and Life Safety

in High Rise Buildings (Modifications)

45-54

Page 3: Hrc nmmc guidelines

3

1. Submission of High Rise Building (HRB) Proposal

Requirements Of Fresh Submission To High-Rise Committee NMMC/HRC/REQ -SUB/V1

a. Proposed Development/ Building must comply with prevailing NMMC

DCR amended up to date stating that the plans for full height within

the purview of the DCR & these guidelines along with all Performa /

attachment , all Architectural/Structural plans etc, shall be submitted

in 8 sets ( hard + soft copies CD) along with Processing Fees as

prescribed in the Clause No. 3 herein below.

b. If applicable Environment Clearance should be appended with the High

Rise Submission.

c. All architectural features like detailed dimensioned elevations and

façade sections, façade support system details and parameters and

description of elevation finishes must be frozen.

d. The application made to HRC (High Rise Committee) should be

based strictly on the currently available FSI to the project proponent.

In the absence of any of the above mentioned requirements, fresh

submission of High Rise Bldg. will not be allowed.

e. The Structural Consultant and the Geotechnical Consultant along with

Architect, Project Proponent, Environment Consultant, MEP /Fire &

Safety Consultant, Landscape Designer, & any other Consultant

concerned with the proposed development shall jointly present the

concept with power point presentation and structural scheme of the

building in each HRC Meeting otherwise HRC hearing will not be held in

the absence of any of the above Consultants.

f. Materials used, the design parameters, loading standards, references

used, software used, the load flow pattern, foundation system,

superstructure framing, construction methodology to be adopted in

support of the structural design assumptions and any innovative

techniques used in the design of the high rise building to convince the

HRC that the design will make the building safe, stable and that the

performance of the building is suitable for comfortable occupancy.

Page 4: Hrc nmmc guidelines

4

g. The following documents shall be submitted in 8 sets to HRC.

i. Appendix A- Project Personnel on Record Information Sheet given

in Appendix A must be filled by the Architect, Structural Engineer,

Geotechnical Consultant and the Client and signed along with their

License No. as applicable. .

ii. Appendix B – Plot and Geotechnical Information shall be filled in

and signed by the Geotechnical Consultant.

iii. Design Basis Report which includes minimum information shown in

document NMMC/ HRC/DBR/V1 shall be submitted.

iv. The CD containing the presentation made by the consultant’s team

as described above.

v. A checklist shown in document NMMC/HRC/CHK-LST-STR-

ENG/V1 along with Appendix - C (I & II) shall be filled and

submitted by Structural Engineer.

vi. All details mentioned in document NMMC/HRC/CHK-LST-STR-

ENG/V1 along with Appendix C (I & II) must be submitted by

the Structural Engineer on Record.

vii ECG-V1 & EEPP-V1( For Development Proposals having Gross BUA

less than 20000 Sq M )

h. HRC will, after scrutinizing the above documents, if required, convey

its comments, suggestions, recommendations and instructions to alter

any design aspects of the building in the Scheduled HRC Meeting only.

Further, the Project Proponent is required to resubmit

corrected/modified proposal in all Performa/Attachment in 8 sets

(hard+ soft CD copies) within 30 days from the date of hearing &

present the same in power point presentation in the next scheduled

HRC Meeting, failing which the Development Proposal will stand

rejected with records in the HRC Meeting. If and when all parameters

appear to be satisfactory, no more discussions will be held and the

HRB /Development proposal will be cleared.

Page 5: Hrc nmmc guidelines

5

i. The First hearing of the HRC will be scheduled within 45 days of the

submission of Development proposal along with all required documents

& prescribed formats of Guidelines.

j. After the clearance given by HRC for a proposed bldg, no further

changes of any kind shall be effected without approval of the HRC.

k. Any changes made in the proposal without obtaining clearance from

HRC, earlier clearance given by the HRC shall be treated as revoked /

invalid.

l. As per the notification of Ministry of Environment & Forest

(Government of India) dated 7th July, 2004, amended from time to

time, the Proponent of Development proposal having Gross Built up

Area 20000 Sq mt & above is required to obtain Environmental

Clearance by the MoEF before commencing the construction

activities. However, development proposals submitted to the HRC

having Gross Built up Area less than 20000 Sq mt are required to be

submitted along with in the ECG V1 & EEPP V1 formats while

submission along with other documents as prescribed below.

2. Checklist for submission of proposal

a) Information as per NMMC/CHK-LST- STR-ENG-V1,

b) NMMC/DBR/V1,

c) Information as per Appendix A, B &C (I&II), ,

d) All Information as per NMMC/HRC/REQ-SUB/V1,

e) ECG V1 and EPPP V1 ( if applicable)

f) Submit 8 sets of Complete Architectural Drawings & Environment

Management Plan Structural Plans etc. duly signed & stamped by

Project Proponent, Architect & respective Consultant.

Page 6: Hrc nmmc guidelines

6

3. Processing Fees (Non-Refundable)

The project proponent shall pay processing fees by Demand Draft in

favour of Navi Mumbai Municipal Corporation on any working days

while submitting the development proposal as under.

Plots above 1000 Sq mt & up to 4000 Sq mt– Rs.50,000/-

Plots above 4000 Sq mt – Rs. 1,00,000/- The fees once paid shall not be refundable under any circumstances.

Further, for any deviation/revision/amendment in the development

proposal already approved by the HRC, the project proponent shall be

liable to pay the NMMC three times the processing fees as stipulated

above for each such revision/ submission thereafter.

4. General Instructions

a) The Guidelines published on the website of the NMMC

(nmmconline.com)are the minimum requirements and can be

further enhanced or modified/amended/cancelled without any

notice. The Commissioner reserves the rights for the same & no

further communication or claim whatsoever will be entertained in

this regard.

b) These guidelines are in addition to the rules made in

D.C.Regulations,1994 (amended up to date) and NBC-2005.

c) The Guidelines are mandatory for all Development Proposals

having Height 70.0 Mt & above up to 120.0 Mt only w.e.f.

16-11-2013. However, the Development Proposals having Height

70.0 Mt & above that approved by the HRC(High Rise

Committee) earlier & the Commencement Certificate has been

issued for the same, provided the construction activities not

started may submit a fresh proposal in required prescribed

formats etc. to the HRC prior to Amended Development

Permission.

d) No High Rise Building (HRB) Proposal shall be considered on the

net plot area less than 1000 Sq. mt.

Page 7: Hrc nmmc guidelines

7

e) High Rise Building Proposal shall be submitted for total High Rise

Building / Development as planned. The clearance will be

restricted only in respect of FSI admissible on the date of

submission of the Proposal. Additional FSI, if availed, developer

will submit appropriate proposal for clearance of additional FSI.

f) The submission of the proposal shall be received in the prescribed

formats only. (enclosed within) along with required processing

fees.

Page 8: Hrc nmmc guidelines

8

Guidelines for High Rise Development 1) Min Plot Area = 1000 m²

2) Abutting Road and Access Road

The width of abutting road shall be 12 mt. minimum.

In case of plots which do not abut to Municipal/ Public Road, Then

other requirements like strength of road, etc. shall be as per

relevant I.R.C. and B.I.S. Codes.

3) Open Spaces Inside Plot Area

a) Residential, Commercial & all other High Rise Buildings:- The side, front and rear open spaces of the building shall not be

less than 8.00 mt .for buildings above 70.00 mt. height. However,

due to any hardship/planning constraints or irregular shape & size

of the plot, the HRC on scrutiny & satisfaction may permit 6.00 mt.

front open marginal space, if Refuge area/ Fire escape route is not

provided in the side of proposed front open marginal space & the

same is not abutting Fire Refuge Area / Floor.

Further, for the buildings above 45.00 mt height and upto 70.00

mt. height one of the open marginal space abutting Fire Refuge

gallery/ approachable area of refuge floor as directed by the Fire

Officer shall have minimum 7.50 mt. clear open marginal space &

all other remaining side open marginal spaces shall be 6.00mt

minimum.

4) Parking Spaces

The parking spaces shall be provided as per the provisions of

NMMC D.C.R. 1994. (amended up to date).

The location of parking spaces shall be well ventilated. Sufficient

provision for visitors parking shall be proposed at suitable location

with toilet for drivers. Parking floor height shall not be more than

4.27 mt. Mechanical ventilation, in addition, may be insisted

depending upon the proximity of the surrounding buildings and

Page 9: Hrc nmmc guidelines

9

condition of the ventilation. Parking floors shall not have any

features except parapet wall of 1.5 mt. height.

In addition to car parks, additional space should be earmarked for

two wheelers and cycles within the parking area, preferably on

ground levels. The requirement shall be on the basis of analysis of

occupancy and use.

The sprinklers shall be provided to car parking area (refer Clause

No.5.1.7 i.e. Automatic Sprinklers of Part 4 of N.B.C.2005).

Entry to the car parking area shall be accessed/ gained through air

lock room with 3 hours fire resistant & smoke check door (please

refer Clause No.4.10, i.e., Pressurization of Staircases (Protected

Escape Routes) of Part 4 of N.B.C.2005).

If required parking cannot be accommodated with multilevel

basement as per requirements specified herein below and parking

floor level up to 21 mt. then a separate car park tower with

automatic car parking shall be provided (please refer Sub Clause

10.9 of Clause no 10 of Part-3, NBC 2005 & Clause No.5.1.7 of Part

4 of N.B.C.2005 for Automatic Sprinklers for fire protection of

basement & upper level parking). All car park floors should be open

from all sides. No windows are to be provided. One meter high

parapet wall is permitted all around.

Natural ventilation in the form of individual/ separate cutouts at

the rate of 2.5% of the floor area of the basements (from the

individual basements to ground level open to sky) shall be

provided. In addition mechanical ventilation shall also be provided

(please refer Clause No.12.9 i.e. Basement of Part-3 of N.B.C.2005

& Clause No.C-1.6 of Annexure-C of Part-4 of N.B.C.2005).

Stack Parking shall be provided only on ground floor, 1st

parking floor level and in 1st basement, with 3.60 mt. minimum

height with sunken pit

If the basement area exceeds 750 Sq. mt. shall be

compartmented with brick walled and fire resistance door, both

having three hours fire resistance. These fire doors can be held

Page 10: Hrc nmmc guidelines

10

open with fusible link/ detector activated link (please refer to

Clause No.C-1.8 of Annexure-C of Part-4 of N.B.C.2005).

5) Staircases

a) As per the provisions of NBC minimum 2 Nos. of staircases

shall be proposed for High Rise Buildings. One of them shall

be having exit on the external side of building directly and

should have adequate natural light. Natural ventilation for

both staircases and passages connecting both the staircases

must be naturally lit and ventilated.

In case of parking floors, sufficient Nos. of additional

staircases shall be provided from parking floors to Ground for

easy evacuation point of view in case of any disaster.

Considering the provisions of D.C.R., N.B.C., etc. along with

the exit multiplying factors maintained therein; the clear

width of main staircase and fire escape staircase shall be

1.50 mt. minimum for Residential, Commercial & mixed

occupancies.

The position of both the staircase shall be preferably

staggered.

The maximum height of riser shall be 190 mm for residential

and 150 mm for other buildings and should be restricted to

12 per flight. The minimum clear headroom under landing in

a staircase shall be 2.2 mt.. The minimum clear headroom

under any staircase shall be 2.2 mt.

b) Basement and parking floors (additional staircases):

For every 750 sq. mt. of basement area provided without

sprinklers one fire escape staircase shall be provided of 1.5

mt. flight width. Where sprinklers are provided for an area of

1150 sq. mt. one staircase of 1.5 mt. flight width needs to

be provided.

Horizontal/ Vertical cutouts shall be provided in basements

to the extent as directed by the Fire Officer

Page 11: Hrc nmmc guidelines

11

C) The staircase shall be free from winders.

One of the staircases which is externally located should be

provided with smoke-check (air-lock) lobby with two fire

resisting doors (self-closing) of three hour fire resistance to

have an access to lobby on the floor (please refer Clause

No.4.10 & Clause No.4.11 of Part-4 of N.B.C.2005).

It should have louvers in top half portion of the door (please

refer Clause No.3.4.11 i.e. Air-Conditioning & Ventilation and

Clause No.3.4.12 i.e. Smoke Venting of Part-4 of

N.B.C.2005).

It is proposed to provide latch-lock to door for access to

terrace from staircase (normal door) with breakable glass

window just above latch-lock so as to open the door in case

of an emergency by breaking the glass window and opening

the latch-lock. The main key for the latch should be kept

with BMS/Security/ Shift Fire Officer of the building. The

latch-lock can be synchronized with manual fire alarm

system so as to have notification of opening on control panel

on ground floor.

6) Refuge Area

The Refuge Area shall be provided as per the provisions of N.B.C

/D.C.R., preferably entire first refuge floor/area to be at 24 mt. and

thereafter the refuge floor/area shall be provided at interval of 15

mt. The refuge area shall be approachable easily by all the

occupants and all Fire Appliances in case of any disaster. All the

refuge areas shall also be easily approachable from common lobby/

fire lift/ staircases & also it shall satisfy the travel distance criteria

as mentioned in D.C.R/NBC. No furniture shall be permitted in the

refuge area. One toilet and drinking water facility shall be provided

in every refuge floor.

Page 12: Hrc nmmc guidelines

12

The Fire Resistance Door (F.R.D.) of 3 hours fire resistance shall be

provided to segregate the refuge area from other area in case of

Fire/explosion.

Fire Fighting/ evacuation of occupants should be from open space

on ground level only.

Automatic Sprinkler Arrangement shall be provided in entire

building area and horizontal parking area as per provisions of

National Building Code,2005 with proper Building Management

System (BMS) accessible and having connectivity from nearest Fire

Station.

The refuge area proposed shall be preferably planned on the area

facing the main road side of the proposal. Parking floor and building

face shall flush on the main road side and any other habitable side

to allow access for Fire Engine.

The refuge area should be made accessible from staircase/

common protected lobby (please refer Clause No.4.12.3 and Clause

No.C-1.11 of Annexure-C of Part-4 of N.B.C.2005).

Manner of providing refuge area :

a) The refuge area shall be so located that it shall preferably face

the access road/s or otherwise face the wider open space on the

side of the building perpendicular to the main access road.

b) The cantilevered refuge area shall necessarily be of RCC Type.

c) The cantilevered refuge area up to 54.0M height shall be

provided with railing / parapet of 1.10 m height and 1.50 m above

height of 54.0 M.

d) R.C.C. covering shall be provided above the topmost refuge

area.

e) The cantilever refuge area shall have access through a door

which shall be painted with a sign in luminous paint mentioning ―

REFUGE AREA.

f) The lift/s shall not be permitted to be open into the refuge areas.

Page 13: Hrc nmmc guidelines

13

g) Drenchers shall be provided in refuge areas above 70.0 M

height

h) Use of Refuge area :

i) The refuge area shall be earmarked exclusively for the use

of occupants as temporary shelter and for the use of Fire

Department or any other organization dealing with fire or

other emergencies when occur in the building and also for

exercises/drills if conducted by the Fire Department.

ii) The refuge areas shall not be allowed to be used for any

other purpose and it shall be the responsibility of the

owner/occupier to maintain the same clean and free of

encumbrances and encroachments at all times.

iii) Facilities to be provided at refuge area:

Adequate emergency lighting facility shall be provided.

iv)The maximum permissible Refuge Area shall be 4% of Built

up area of serving floors. The area beyond the stipulated above

shall be computed in the FSI.

As far as possible, refuge floor shall be within the building line

itself.

7) Disaster Management Plan

The Disaster Management Plan shall be prepared as per the norms.

Central Control Room/ Building Management System (B.M.S.)

Room, in view of disaster management, shall be proposed abutting

the common passage near the exit/ reception at Ground floor.

Detailed disaster management plan for the onsite and offsite use

shall be prepared keeping in view all the possible disaster

situations. These DMPs shall be operational system which can be

made working immediately after the completion. It is also expected

that proper plan also is in place for the building construction period.

8) Environment Protection and Preservation Plan

The process of building must start with green thoughts at the start

of the conceptual plan itself. A building can be said to be green‘ or

Page 14: Hrc nmmc guidelines

14

eco-friendly‘ when conscious steps are taken during the entire

process of planning and construction of the building starting from

excavation, selection of materials as well as through the operation

and maintenance phase of the building to keep natural resource

depletion and pollution as low as possible. Thus, the aim of the

creating an environmentally conscious building is to minimize

demand on non-renewable resources, maximize resource utilization

efficiency, and maximize reusing and recycling of renewable

resources. The eco-housing movement graduates through a design

process that requires thoughtful inputs from all the concerned

professionals – the architect; the landscape designer and the air

conditioning, electrical, plumbing, and energy consultants to work

as a team and carefully consider all aspects of construction of

building and associated services starting from the design stage

itself. As per the notification of Ministry of Environment & Forest

(Government of India) dated 7th July, 2004, amended from time to

time, the proponent of development proposal having Gross Built up

Area 20000 Sq mt. & above is required to obtain Environmental

Clearance by the MoEF before commencing the construction

activities. Hence, it is not necessary to submit ECG V1 & EEPP V1

formats to HRC for such proposals. However, development

proposals submitted to the HRC having Gross Built up Area less

than 20000 Sq mt are required to be submitted along with ECG V1

& EEPP V1 formats while submission along with other documents

as prescribed in these Guidelines.

The Environmental and Contextual Guidelines (Annexure

ECG V1) provides the overall guidelines as well needs for the

environmental and contextual need for the high rise building

development. It is expected that a report is prepared based on ECG

VI and submit along with the mitigation plan. After careful analysis

of all the aspects of environmental context, design, environment

protection, safety etc, proponent is expected to prepare a

Environmental Protection and Preservation Plan (EPPP V1)

Page 15: Hrc nmmc guidelines

15

for all the aspects and commit to its implementation which should

be based on ECG V1.

9) Fire Fighting System

• The Fire Fighting System shall be designed and confirming at least with the indicative guidelines as listed below:-

• The all fire and sprinkler pumps shall preferably have positive

Suction.

• Separate access shall be provided to fire pump room from

ground level to fire pump room. Submersible pump shall not be

allowed for the fire fighting system (please refer IS 3844 (Year

1989) (Reaffirmed in 2000)).

• Over head tank shall be not less than 30,000 Liters (Thirty

Thousand Liters) per wing of the building & capacity of over

head / underground fire tank shall be increased as per

requirements of Fire Officer. Please refer Table 23 of Part-4 of

N.B.C.2005) for other aspects.

• Motorized valve shall be provided to down comer feeder line of

over head tank connected to wet riser through pump and shall

open automatically if there is sudden loss of pressure in wet

rise.

• In addition to electrical operated fire pump Automatic Diesel

operated standby pump of same capacity shall be provided (it is

mandatory as per Table 23 of N.B.C.2005. Refer IS 3844 (Year

1989) (Reaffirmed in 2000).

• All the occupancies shall be provided with sprinklers (please

refer Clause No.5.1.7 i.e. Automatic Sprinklers of Part-4 of

N.B.C.2005). Entire building shall be complied with Automatic

Sprinkler System as per IS 15105 & separate pumping

arrangement along with pump room at the uppermost basement

or ground level shall be provided.

Page 16: Hrc nmmc guidelines

16

• Addressable fire detection shall be provide in the entire building

including enclosed lobbies and basement (please refer I.S.2189

(Year 1999) (Reaffirmed in 2004)).

• Natural ventilation in form of openable windows shall be

provided to corridors & lift lobby. (please refer Clause Nos.3.4.8

i.e. openings in separate walls and floors and Clause No.3.4.8.4

i.e. Vertical Opening and Clause No.3.4.9 Fire Stop or enclosure

of Openings of Part 4 of N.B.C.2005. And for lifts please refer

Clause No.4.15 and Clause No.C-1.5 of Annexure-C of

N.B.C.2005).

• The Corridors/ passages and lobbies shall be painted with non

toxic fire retardant paint. (please refer Clause No.C-11 of

Annexure-C of Part-4 of N.B.C.2005).

• All the upholstery curtains shall be treated fire retardant

coating. (please refer Point No.C-11 of Annexure-C of Part-4 of

N.B.C.2005) for all referred occupancies above 70.00 mt.

height.

• All self closing smoke check doors shall not be less than 3 hours

rating. (please refer Clause No.C-09 of Annexure-C of Part-4

N.B.C.2005).

• Flow switch shall be provided to sprinkler main branch pipe on

every floor and the same shall be connected to fire detection

panel.

• The low/ high tension electrical cable shall be laid in dedicated

shaft with 3 hours fire rating and if opening is provided for

maintenance/ repairs purpose, metal door having rating of the

shaft shall be provided to the openings (please refer Point No.C-

1.9 i.e. Service Ducts/ Shafts and Clause No.C-1.12 for

Electrical Services of Annexure-C of Part-4 of N.B.C.2005).

• The all vertical shaft provided in staircase or lobby shall be

closed at every floor level with concrete/ vermiculite/ in-

Page 17: Hrc nmmc guidelines

17

tumescent material/ feelers, etc. (please refer Clause C-1.9 of

Annexure-C of Part-4 of N.B.C.2005).

• The automatic change over switch shall be provided to the lift

from normal to alternate power supply i.e. Diesel Generator

(please refer Clause No.C- 1.5 of Annexure-C of Part-4 of

N.B.C.2005).

• Separate power connectivity with isolation switch to override the

normal and alternate power shall be provided.

• If the lift opens in common lift lobby, the lift be suitable

compartmented and entry to refuge shall be gained through 3

hours fire resistant door with class vision panel of same

resistance.

• Fall safe rugged intercom facility between refuge floor to main

lobby on ground floor and fire control room shall be provided.

• The possibility of provision of chutes or other means shall be

proposed to have early & fast evacuation of population in case

of disaster.

• On the contrary it should be mandatory for all the buildings

above 70 mt. to have a separate duct for vertical fire chute

accessible from staircase landing of alternate floor with smoke

stop door. This duct should be externally located and well

segregated from rest of the building with having three hours fire

resistant wall.

• The refuge chute shall be accessible directly through the area

between two consecutive refuge area/ refuge floor at not more

than 15.0 mt. intervals.

• Fire Escape Chutes :- High rise building having height more

than 70 m, shall necessarily be provided with fire escape chute

shafts/s for every wing adjacent to staircase. Wall of the shaft

shall have 3 hr fire resistance.

Page 18: Hrc nmmc guidelines

18

One side of the shaft shall be at external face of the building

with proper ventilation.

The dimension of the shaft shall not be less than 2.5m X 1.5m.

The access to the fire escape chute’s shaft shall be made at

alternate floor level from staircase mid-landing with self closing

fire resistant door of at least one hour.

The fire chute shall be of staggered type with landing of each

section at the vertical height of not more than 15mtrs.

• Only LPG or CNG through approved pipeline network for cooking

fuel shall be permitted in entire building. (please refer Clause

No.C-1.13 of Annexure-C of Part 4 of N.B.C.2005).

• Use of L.P.G. cylinders and Kerosene/ Kerosene pressurized

stove shall strictly be prohibited in entire building.

• Two dedicated fire lifts with air-lock lobby shall provide to the

building. Out of which one Lift shall be having Stretcher Lift Car

of minimum size 1.70 mt. x2.10 mt.

• The lift well shall be independent well located externally with

three hour fire resistance structure . A Shift Fire Officer shall be

appointed by the Project Proponent / Registered Society as part

of the BMS ( Building Management Services).

10) Fire Check Floor/ Fire Cut off Floor

• A high rise building having ht more than 70 m, hall be provided

with fire check floor (entire floor) above 70 mt at immediate

habitable floor level. Height of the fire check floor shall not be

more than 2.60 mt.

• The fire check floor shall not be used for any purpose and it

shall be the responsibility of the owner/occupier/ registered

society to maintain the same clean and free of encumbrances

and encroachments at all times. Drinking water facility and toilet

facility shall be provided.

• Periphery of the Fire Check floor shall not be enclosed.

Page 19: Hrc nmmc guidelines

19

• Fire Drenchers shall be provided at the periphery of the each

fire check floor externally.

• Fire Check Floor/ Fire Cut off Floor shall be free of FSI.

11. Fire Safety Requirements For Glass Wall In Building

Glass Wall (Walls Functioning As Fire Compartment Wall And Wall

Adjoining Escape Routes)

1) Architect should earmark conspicuously the glass wall either by

sign or in words, on the plans submitted at the time of submission

of proposal.

2) The said wall including doors frame work if any should be one

hour fire resistances and shall satisfy stability, integrity and

insulation characteristics for the fire resistance period given.

3) Plastic or any combustible film shall not be coated on external or

internal face of the wall.

12. Fire Safety Requirements For Glass Facade In Building

Use of glass façade for high rises should be minimized if adequate

gaps are not provided. Safety issue with regard to glass façade

breaking or any other can be fatal.

1) An Opening to the glass façade of min. width 1.5 m and height

1.5m shall be provided at every floor at a level of 1.2 m from the

flooring facing compulsory open space as well as on road side.

Minimum one such opening shall be provided at the interval of

every 15m- Mechanism of Opening: The openable glass panel shall

be either left or right shall have manual opening mechanism from

inside as well as outside. Such oepnable panels shall be marked

conspicuously so as to easily identify the openable panel from

outside.

2) Distance between the external wall (glass/brick) and glass

façade shall not be more than 300 mm.

Page 20: Hrc nmmc guidelines

20

3) The smoke seals/barriers between building wall and façade shall

be provided at every floor level in the form of non-combustible

material/ vermiculate cement.

4) Glass facade blocking the area of staircase, lift lobby and

corridor shall be kept openable. Pressurized system of the

staircase/lobby shall be synchronized with opening mechanism.

5) The glazing used for the façade shall be of toughened

(tempered) safety glass as per I.S.2553, Part I or laminated safety

glass as per I.S.2553-Part I satisfying stability criteria.

6) Automatic Dry type water curtain system shall be provided at

every floor level from inside of the façade.

7) Openable vent of 600 mm height to be installed below ceiling

level or false ceiling level (if provided)- The openable vent of

minimum 2.5% of the floor area shall be provided. It shall be of

min 600 mm depth below ceiling/false ceiling or full length on the

periphery of the façade whichever is less- Openable mechanical

devices for the said vent shall be located at 1.2 m height from the

flooring level. The Openable vent can be pop out type or bottom

hinged provided with fusible link opening mechanism and shall also

be integrated with automatic Smoke Detection System.

OR

Alternate vertical glass panels of the façade shall be oepnable type

with the mechanism mentioned above in order to ventilate the

smoke.

8) Refuge areas covered with the glass façade shall have all the

panels openable (either left or right hinged) both from inside as

well as outside.

13) Basement (Open Space)

• If the basement is exclusively planned for required parking only

due to planning constraints or any hardship with written

permission of the Commissioner the basement beyond

prescribed building line exclusively for required parking may be

allowed for maximum depth of 8.0 mt.. Then, if, basement

Page 21: Hrc nmmc guidelines

21

excluding excavation is up to 4.0 mt., the minimum open space

for basement for side & rear margins shall be 2.0 mt. Further, if,

the depth of basement excluding excavation is from 4.0 mt. to

8.0 mt., the minimum open space for basement for side & rear

margins shall be 2.5 mt. No basement shall be allowed in front

open margin. All structural design/safety aspects as per NBC &

latest BIS Codes shall be complied along with consideration of

weight of Fire Engine & its maneuverings. Further, while

planning & designing basement in these aforesaid margins,

utmost care shall be taken so as not to foul with any building

services such as water supply tank/ lines, sewerage network,

town gas lines, rain water harvesting system, gray water reuse

& recycle system with STP, Communication/MTNL cable lines,

MSED power cables, foundations of abutting structures/

compound walls, fencing etc. A detailed Architectural plan

depicting basement with all above aspects shall be submitted

along with the checklist.

• The depth of the excavation should not exceed 10 mt from the

existing ground level.

• In case, the proponent wants to increase the depth of

excavation, a proper justification may be recorded & presented

to HRC.

14) Ramp

• The ramp to basement and parking floors shall be between 6

mt. to 7 mt. wide for two way traffic and 3.0 mt. to 4.0 mt.

width for one way traffic shall be provided with Gradient of 1:10

for cars and 1:15 for heavy vehicles.

• If it is proposed to ply the fire engine on the ramp the width

shall be minimum 9.00 mt. with turning radius of 12.00 mt.

minimum shall be provided. As far as possible, this should be

avoided. Also, taking of fire engine on car park floor shall be

avoided. Fire fighting should be done from open spaces only, to

the extent possible.

Page 22: Hrc nmmc guidelines

22

• All structural design/safety aspects as per latest BIS Codes &

NBC shall be complied along with consideration of weight of Fire

Engine & its maneuverings.

• The clear head room of 5.50 mt. shall be proposed in case of

fire engine movement underneath the parking floor is required &

the same shall not be counted towards FSI.

15) Structural Design

The structural design in standard commercial software package and

AutoCAD format duly certified by Licensed Structural Consultant

shall be submitted. The submission shall be as per the documents

NMMC/HRC/CHK-LST-STR- ENG/V1 along with Appendix C (I

& II), NMMC/ HRC/DBR/V1, NMMC/HRC/REQ-SUB/V1.

The following additional details shall be considered over and above

those stipulated in relevant codes of practice.

1) Possibility of pounding with adjacent HRB in a cluster or at expansion joint shall be cross checked.

2) All structural as well as not structural elements shall have

minimum fire rating as prescribed in NBC-2005, with minimum protection of 3 hours.

3) No anchors shall be allowed to extend beyond the line drawn

1.5 mt. inside the plot boundary.

4) External walls shall be either 230 mm thick brick wall or concrete block wall. Such walls shall be properly anchored to the RC / steel structural elements.

5) Minimum three bore holes shall be provided in the main tower

area. The depth of the bore holes shall be up to about 15 mt.

below the Rock strata / Founding strata.

6) RCC Design of proposed development that cleared by the HRC

shall be proof checked by the IIT Bombay / VJTI, Mumbai or any

equivalent Institution as directed by the NMMC. Report

compliance shall be submitted to the NMMC before securing

Plinth Completion Certificate.

Page 23: Hrc nmmc guidelines

23

16) General

The signs for showing staircase, exit, lift, refuge and fire fighting

driveway to be pointed on the ground, fire shafts to be identified

with red colour and basement ventilation shafts to be indicated

shall be displayed distinctly at all common places where possible.

Further, following points shall be observed.

1) Projections beyond the building line in the form of niche, deck

etc including the balcony, terrace shall not exceed 1.50 mt.

2) All terraces shall be open to sky. No multiple terraces should be

allowed.

3) Swimming pools shall be preferably planned at podium levels or

lower floors to minimize wastage of energy in pumping,

cleaning, leakage, maintenance etc.

4) As far as possible, the recreation areas shall be on ground level

rather than podiums.

Page 24: Hrc nmmc guidelines

24

APPENIDX – A PROJECT PERSONNEL ON RECORD AND CONTACT INFORMATION

1

Project Reference No. with HRC Meeting schedule.

2

Municipal Reference No.(Building Proposal Ref. /File No.)

3 Project Name As advertised by Developer to the public

4

Project Address As mentioned in Building Development Proposal File

5

Project Proponent /Developer‘s Name & Signature

6

Project Proponent /Developer‘s Address

7

Project Proponent /Developer‘s Telephone /Mobile / email address

8

Architect‘s Name, qualifications & License No.

9 Architect‘s Address & Signature 10

Architect‘s Telephone / Mobile / email address

11

Structural Engineer‘s Name, qualifications & License No.

12

Structural Engineer‘s Address & Signature

13

Structural Engineer‘s Telephone / Mobile / Email address

14

Geotechnical Consultant‘s Name and qualifications.

15

Geotechnical Consultant‘s Address & Signature

16 Geotechnical Consultant‘s Telephone / Mobile / Email address

17

M.E.P. Consultant‘s Name, Address, License No & Signature

18

M.E.P. Consultant‘s Telephone / Mobile / Email address

19

Project Management Consultant‘s Address & Signature (If required)

Page 25: Hrc nmmc guidelines

25

APPENDIX- B

PLOT AND GEOTECHNICAL INFORMATION Area of Plot in sq.mt.

At which depth suitable Founding strata is available in meter

Nature of foundation recommended for high-rise building

Ground Water table level with respect to existing ground level

No of basements Proposed with justifications.

Total depth of excavation in meter.

Arrangement for shoring.

Details of the structures along with height abutting the boundaries of the plot.

North Side

West Side

South Side

East Side

Page 26: Hrc nmmc guidelines

26

NMMC/HRC/DBR-V1

DESIGN BASIS REPORT

Following data should be part of Design Basis Report.

• Brief Description of the Project – Number of basements,

commercial floors, residential floors, Service floor, refuge floors,

projection above terrace level and number of additional /

provisional floors considered in design.

• List of Codes – Codes which are considered in design. If any

specific reference is taken from foreign codes, same should be

clearly mentioned. Any specific assumption in the design should be

supported by reference papers.

• Loading Parameters – All the loading assumptions shall be

clearly mentioned in A3 size GA drawings with sunken loading, live

load. Typical sections indicating the elevational / façade features

shall be shown.

Assumptions and the basis of the same for the elevational features

above terrace slab shall be mentioned. Calculation of Time Period

for the structure, Importance factor, performance factor shall be

specified. Wind terrain category, Gust wind calculations shall be

mentioned.

• Clear cover to Reinforcement – These shall be mentioned for all

structural members with minimum fire rating of 2 hours for

columns, shear walls and beams and 1.5 hours for slabs.

• Grade of concrete – Minimum Grade of Concrete Mix for various

RCC elements viz. beams, slabs, columns, shear walls etc shall be

M 250 & Minimum size/ thickness of RCC Column / Shear Wall / Lift

Wall shall be 230mm.

• Exposure condition – Exposure condition assigned to site should

be specified.

Page 27: Hrc nmmc guidelines

27

• Construction Sequence and loading parameters for the same

– If due to any site constraints the loading on the floor slabs is to

be enhanced, the mention of the same and calculations for the

same shall be provided.

• Proposed Approach to Structural Analysis – Various flooring

systems considered in the structure, the software used for analysis

and design approach adopted. Release in moments of link beams,

cracked moment of Inertias for structural members along with the

assumptions for the same shall be specified.

• Load Combinations – Various load combinations used in the

design of individual members. Additional combinations from the

Wind tunnel tests considered, if any.

• Soil Profile in Brief – In brief the soil profile of the project along

with the Safe bearing capacity and the type of foundations adopted.

• Soil Retention system – A brief description of the soil retention

system adopted for the project along with the construction

sequence.

• Key Plan - showing Expansion / Separation joints (if any).

• Added Features – If any additional features are considered in

design such as dampers, out rigger beams, etc shall be specified

clearly stating the purpose of the same.

Page 28: Hrc nmmc guidelines

28

NMMC/HRC/CHK-LST-STR-ENG/V1 Check List for the Main Structural Consultant The main structural consultant is required to submit following information.

(Note : Provide appropriate unit against each quantity)

1) Provide Design Basis Report as per the document

NMMC/HRC/DBR/V1

2) Provide description of Sub-structure and Super-structure as

per the format given in the Appendix C(I&II) enclosed.

3) Provide brief Description of Structural System with sketches,

images of drawing. etc. with specific focus on Lateral load

resisting system‘.

4) Provide brief note on modeling, software used etc. Clearly

mention whether infill / partition wall is idealized as part of

lateral load system?

5) Provide the height of building in meters.

5A) Provide plan dimensions of the building (mt x mt)

6) Provide following EQ loading details.

a) Zone Factor

b) Importance factor

c) Response Reduction factor

d) Soil Type

e) % LL considered in seismic

f) Time Period in the horizontal X-direction (sec)

(from formula in code)

g) Time Period in the horizontal Z-direction (sec)

(from formula in code)

h) Total Seismic weight (Sw) of building (kN)

i) Static Base-shear in X-direction (as % of Sw)

j) Static Base-shear in Z-direction (as % of Sw)

k) Table of distribution for static base shear

l) Max. deflection at roof level. (mm)

m) Max. inter storey drift./ Height

Page 29: Hrc nmmc guidelines

29

7) Provide following Wind loading details.

a) Category of building

b) Class of building c) Basic wind speed in m/sec.

d) Maximum wind pressure (kN/m2)

e) Force coefficient

f) Wind Base-shear in the horizontal X-direction(Kn)

g) Wind Base-shear in the horizontal Z-direction(kN)

h) Gust factor calculations (if Gust-wind applied)

i) Details of wind-tunnel force data (if applicable)

j) Estimated magnitude of wind induced vibrations

k) Max. deflection at roof level (mm)

l) Max. inter storey drift.

8) Provide following data from Dynamic Analysis

Modes Frequency in Hz

Time Period in sec

X-participation

Z-participation

Mode 1 Mode 2 Mode 3 Mode 4 Mode 5 Mode 6 Mode 7 Mode 8 Mode 9 Mode 10 Summation

(Note : Fundamental mode should not be a torsional mode)

9) Provide Table for lateral deflections (mm) at Terrace Level in the following format.

Load Case Dx-max

H/Dx Drift-x Dz-max

H/Dz Drift-z

DL DL + LL EQx EQz Wx Wz

Page 30: Hrc nmmc guidelines

30

10) Provide Corner displacements (mm) for Torsional Irregularity (along x-direction) in the following format.

Load Case

Corner-1

Cornor-2

Cornor-3

Cornor-4

Avg-x

% Max./Avg.

Eq-x Wl-x

11) Provide Corner displacements (mm) for Torsional Irregularity

(along z-direction) in the following format.

Load Case

Corner-1

Cornor-2

Cornor-3

Cornor-4

Avg-x

% Max./Avg.

Eq-z Wl-z

12) Provide acceleration (mg) values in the following format.

Eq-x Eq-z WL-x WL-z

13) Provide following data regarding Vertical Elements.

a) Size of maximum loaded column

b) Gravity load on max. loaded column

c) Axial stress in max. loaded column (Gravity loads)

d) Grade of max. loaded column

e) Axial settlement in max. loaded column

f) Axial settlement in min. loaded column

g) % Base-shear resisted by all columns along X (static)

h) % Base-shear resisted by all columns along Z (static)

14) Provide, if applicable, following data regarding Floating

Columns.

a) Total gravity load on floating column (provide table if

there are multiple floating columns)

b) Size and span of girders supporting floating columns

c) Number of floors supported by floating columns

d) Deflection of girder under column (from model)

e) Deflection of girder under column (from s/s action)

f) Specific details about floating columns on cantilever

girders (Refer Table below)

Page 31: Hrc nmmc guidelines

31

Supporting Girder

Deflection Values Column

Size Span Model

S/S Action

Floors Above

Total Load in Column

-S/S denotes the simply supported.

15) Provide, if applicable, following data regarding soft story

effect.

a) Stiffness of lower floor (in deflection/KN)

b) Stiffness of upper floor (in deflection/KN)

c) Relative stiffness ratio (upper/ lower)

d) Level of story

e) Number of floors above soft story

16) Provide, if applicable, following data for each cantilever.

a) Cantilever span

b) Structural system

c) Nature of usage

d) Maximum elastic deflection under gravity loads

17) Provide stability calculations for uplift and overturning

(model extract in case of model)

18) Typical design calculations for footings

19) Typical design calculations for RCC columns Composite

Columns

20) Typical design calculations for RCC walls

21) Typical design calculations for RC beams (Or Steel Beams)

22) Typical design calculations for RCC Girders (Or Steel Girders/

Truss)

23) Typical design calculations for Steel Bracings

Page 32: Hrc nmmc guidelines

32

24) It is desirable to conduct Wind tunnel studies for any HRB

with total height beyond normal ground level exceeding 250

mt. However, such buildings above 250 mt. height can also

be designed as per the BIS.Code as well.

25) Provide a note on special provisions suggested for the

building (like dampers etc.)

26) Soft copy of model including input and output.

27) Soft copy of Power point presentation including all above

points.

28) Items 1 through 27 on CD.

Page 33: Hrc nmmc guidelines

33

APPENDIX - C

(I) DESCRIPTION OF SUB-STRUCTURE No. of basement Minimum clearance between outermost basement retaining wall and compound wall

Has a Shoring system been installed ? Submit sectional detail of the shoring system

Give details of methodology used to resist uplift pressure due to ground water for tower portion as well as the portion outside the tower.

Description of the foundation for the tower block

Nature of Foundation SBC assumed T/sq.mt. Sub-grade Elastic Modulus Intended Use of basements

If rock anchors are used, are they grouted after installation and stressing?

Is structural steel used in the construction of the sub-structure?

If yes, what are the measures taken for its fire proofing and corrosion resistance?

Whether Expansion/ Separation joints provided? Whether expansion joint/ separation joint continues through basement? If yes, detail at Basement level & retaining wall junction

Page 34: Hrc nmmc guidelines

34

(II) DESCRIPTION OF SUPER STRUCTURE No. of Floors & height of building in m

Shape of Building, Plan, Elevation, Whether Symmetric in Elevation

Maximum plan dimension in either direction in m.

Ratio of plan dimension

Typical Floor to floor height in m Maximum floor to floor height in entire height of building in m.

Aspect ratio ( Height of Building till Terrace / Minimum Dimension of Building)

Type of floor slab Average thickness of floor slab in mm.

Whether column are RCC, Composite or In structural steel

Page 35: Hrc nmmc guidelines

35

ECG-V1 (For Development Proposals having Gross BUA Less than 20000 m²)

Environmental and Contextual Guidelines for High Rise Buildings. Use of Guidelines The guidelines are aimed at addressing high rises in mixed types of

development and surroundings. The purpose is to integrate the

development with the vision of the city which looks at more and more

vertical development. Many of the guidelines can vary from place to place

and in the context in which the development is proposed, however, in

large number of cases, these can be easily applied.

Guidelines for High Rise Development The Guidelines presented below are the minimal requirement and can be

further Enhanced which can add to the quality of life of people and

rejuvenated environmental conditions.

Contextual, Location, Typology and Environmental Architecture 1- Detailed layout with Location Plan: A detailed layout of the

proposed building and location showing surrounding areas (1-3km)

around the site. This preferably includes the details about major

roads, road width, access roads to the site, number of high rise

building in the vicinity, number of high rise buildings proposed in

the locality etc. Apart from this a note of prominent features such

as Archaeologically important place, Heritage sites, schools, places

of worships, forest/national park etc. be provided. Layout plan

should clearly show the distances of other buildings/roads

surrounding all 4 sides of the plot.

2- The building should be oriented and thought of from the point of

view unifying in such a way that it matches.

a. with the overall goal and look of the region, lane and locality

b. with other buildings (current or future), looks, shape, colour etc

c. Links with public access roads, connectivity etc

Page 36: Hrc nmmc guidelines

36

3- The building creates a view which aims at unifying the features and

space

4- Distinctly identify and announce the type of building proposed: an

iconic building (head office, tower of excellence etc) or other high

rises. The latter type should mix with the other buildings, features,

space and needs. The former could be unique in its shape, look,

features however meets the needs of the place and justifies the

reason for it to be called iconic building.

5- The base of the building and its height (base or podium) should

have a proper relationship with the street or roads facing the

property. The building should be able to provide appropriate

space for the pedestrian besides other spaces for utilities for fire,

earthquake, ambulances, riot vehicles/police etc.

6- Design should be able to provide the open spaces close to its own

location as also provide public access and movement.

7- Building should not obstruct the views of important landmark,

historic buildings parks etc as far as possible. The purpose is to

maintain the aesthetics of the place and region.

8- The key parameter for tall buildings with regards to shadow of it is

to minimize the extent and duration of the shadow. The shadow

on parks, streets and other buildings must be minimized after

carrying out a proper analysis and mitigation plan, if applicable.

9- Micro-climate of the place needs to be analyzed with regard to

other usages and buildings which may impact others with regard to

wind, temperature, sunlight and activities.

10- The buildings base is the main part which should be analyzed with

regard to its functionality and its relationship with local streets,

roads, shadow, functionalities etc.

11- High rises are meant to provide spaces for more people by going

higher and therefore there is likelihood that there would be need of

Page 37: Hrc nmmc guidelines

37

more open space on ground, for pedestrian and road spaces.

Proper setback and space for pedestrian should be created.

12- The road facing façade of the building should not be featureless

and bland as it brings out ugly development. The podium or base

facing the street should be designed to make the place easily mixes

with the nature and locations with proper landscaping and street-

scaping. As far as possible high podium should be avoided besides

use of mix use system should be created.

13- Minimum distance from one property to another (especially high

rise) or buildings within the plots should be based on the shadow

analysis and wind analysis. The shape and location should be such

that it can provide sense of space creation.

14- Provision of sidewalks for high current and projected pedestrian

traffic as high-rises would make more people to use the space.

Commercial high-rises should create more pedestrian space and

open spaces. Building residents spill out area outside the building

and design should also be given importance.

15- Pedestrian walkways development across the area would be the

priority which indicates that the creation of newer buildings creates

more accessibility and connectivity to open spaces and

communities.

16- Walkways design must keep in mind unobstructed and smooth

yielding with the movement of able and disable citizens.

17- The setback for the area can consider providing places for buses

and public utilities movement and related infrastructure.

18- Location of open spaces should preferably be at the lower level as it

provides sense of space as also the buildings related sun, wind,

shadow and views. The open space could also be for gatherings,

emergency situation, benches, chairs, etc.

Page 38: Hrc nmmc guidelines

38

19- Day lighting description, passive solar gain, energy generation

through photovoltaic, solar panels etc should be discussed and

described for the building.

20- Climatic conditions based use of material: Use of glass for daylight

justification and later using high cooling needs to be avoided. If

used, its justification should be amply given for a climate conditions

of region.

21- Use of glass façade for high rises should be minimized if adequate

gaps are not provided. Safety issue with regard to glass façade

breaking or any other can be fatal.

22- Wind breaking and wind movement analysis from micro-climate

point of view needs to be analyzed for a high rise keeping in view

the existing building. Wind harnessing for natural ventilation is a

key factor for better air quality indoors, which gets affected due to

glass façade.

23- Water budgeting for use within the building for various purposes

describing sources, distribution, current supply of the region,

exceedance if any and to what extent, impact on neighborhood

water availability, sewage generation, its treatment with

technology, CAPEX-OPEX analysis, sustainability, impact of existing

sewer infrastructure, reuse type and categories etc.

24- Solid waste handling and its management explaining the methods

of collection, generation types, handling, management for its use or

sale. Description of trained manpower and working structure.

25- Position, orientation, height, discharge of AC heat, vehicle heat etc

needs to be analyzed and its dissipation mechanism should be

addressed. Energy use analysis, smart energy management

system, manpower to manage, per capita energy load, comparison

with existing loads and additional loads should be provided.

26- Access Roads and Traffic details: A complete scenario of existing

access roads with its width, capacity in terms of PCU‘s prior and

Page 39: Hrc nmmc guidelines

39

post project of such magnitude be carried out in detail. A detailed

traffic survey covering entire types of vehicles on hourly basis for

week days and week ends be carried out. Emissions from traffic

may be established using appropriate models studies for existing

and proposed scenarios keeping in view the growth being

witnessed in the region. An action plan should be prepared for

mitigating the congestion and related air pollution problem that

would get created. if required.

27- Parking for cars, cycles, scooters for residents, visitors,

neighborhood, integration of these with the area‘s need. Study of

needs base site and development analysis should be included in the

environment plan.

28- Bird hits due to glass façade, façade justification, additional cooling

needs, wind related microclimate analysis, heat island effect due to

release of heat from air conditioning should be studied and a

mitigation plan should be prepared.

29- Capacity building of workers, amenities manager and people should

be carried out. A detailed plan for the same should be drawn which

shall be part of the implementation plan and which could be

checked after the completion.

30- Wooded space and its design within the building area as well as in

the overall context of the 1-3 km radius of the location.

31- Noise barriers within as well as outside after noise generation and

its effect analysis should be carried out. A Mitigation plan should

also be included if it is likely to exceed the MPCB/MoEF norms, if

required.

32- Utilities needs and its availability (sewer, water and electrical

loads). This analysis should start with the regions current status,

forecasted numbers and its impact on the existing systems. The

utilities availability for high density population use must be

assessed from existing records of the NMMC/CIDCO and the same

should be used for prediction and its use.

Page 40: Hrc nmmc guidelines

40

33- Roads infrastructure, vehicular loads and its impact, public utility

and its use, emissions and its control with recourse to adequate

air quality modeling study. Management plan for air emission

reduction using multiple feasible techniques.

Safety and Disaster Management Plan

34- Identify all the risk areas and develop a disaster management plan

keeping in view any accidents which may occur within the building

or outside.

35- Some of the scenario for disaster would be fire, earthquake, flood,

terror strike, power failure, water unavailability, blasts, road

congestions, communication, others.

36- The DMP should not be limited to the high rise building but also if

disaster strikes neighborhood buildings and activities.

37- Indoor air quality maintenance plan in case of closed design with

closed façade, especially glass façade with limited opening.

38- Description of any buildings important from architectural, historical,

hospitals and other important installations, such as defense, police,

jail, railways, airport etc

Building Material and Micro-climate and Micro-Environment

39- Use of granite and other building material in the should be

understood carefully from environment impact angle. An analysis of

their sourcing and their environmental issues (such as Radon

emission from granite) should be listed and a plan of its mitigation

should be included.

40- Paints related VOCs, formaldehyde etc emissions and its built up

within the building should be analyzed. Action plan for mitigating

the same in the building design should be included and presented.

41- Natural ventilation for all areas should be preferred. Use of

balconies and other designs to improve these aspects should be

highlighted and explained for benefits with regard to indoor air

Page 41: Hrc nmmc guidelines

41

pollution mitigation. Appropriate model should be used to analyse

the indoor air and ventilation design for avoiding any built up of

pollutants indoors, especially in commercial building.

42- Use of glass should be minimized as a complete external façade

due to its environmental and energy use issues. Detailed safety

aspects pertaining to use of Glass for Façade be provided. It should

cover accidental breaking, damage due to blast explosion and its

effect of nearby buildings/populations etc. The detailed thermal

characteristics of the glass to be provided (single glazed/double

glazed). Details of the energy consumption due to use of glass may

be specified with calculations in comparison with the standard non-

glass use benchmark.

Alternatives to the glass materials should be thought of to minimize

energy consumption in light of city climate. Glass use should also

reduce as the height increases.

Places where glass façade is insisted upon for any reasons, the

possible use of PV panels should be explored which will also provide

additional energy source.

43- Paving material, construction material, sources of supply and

embodied energy analysis for the whole building should be

presented in the report.

44- Air ventilation impacts of the wall effect‘‘ resulting from the

alignment of high-rise buildings, which can happen if there are

multiple high rises (more than 35 mt.) are on the same lane/road.

This situation can adversely affect the outdoor air and can create a

gas chamber effect.

45- Centralized or decentralized heating cooling must be analyzed for

different use pattern of the building. The site location, wind speed

and direction can play a major role in heat dissipation.

46- Micro-environment Design Consideration is key to understanding of

environment surrounding. The heat island phenomenon in urban

Page 42: Hrc nmmc guidelines

42

center is well known, the wind is the major driving force to alleviate

the problem.

Therefore, the density of building blocks, or interconnectedness of

the porosity between building blocks, and their effects on the local

micro-wind environment and eventually, the thermal and air quality

environments need to be incorporated in urban planning and estate

development.

47- All the issues listed above can be considered as problems and

opportunities associated with high-rise and high-density residential

building design. High density provides opportunities for the

application of more efficient centralized systems which can bring in

efficiency.

However, high density high rise also modifies the local

microenvironment, depending on outdoor weather conditions. The

purpose of the better micro-climate and micro-environment based

design would be to assess these impacts, and make an attempt

achieve healthy and comfortable design of the living environment

using minimal use of energy for all functionality of the building.

48- Separate budget should be allocated for the implementation of the

EMP and the same should be operational before the Occupancy

Certificate. It should also be ensured that O&M contract of all the

STP, SWM facility and RWH system and Solar system is in place

with competent agency for a minimum duration of 5 years.

49- The report shall be assessed with comments and the final copy will

be attached with a summary of analysis and action plan in terms of

EPPP in given format.

This part shall be used for compliance monitoring in future by

The report shall also contain the credentials of the consultants and

their personnel. Any false and misleading information by the

consultant should be avoided to avoid delays and consequences.

Page 43: Hrc nmmc guidelines

43

Minimal Requirement for submission of information in the

Report for ECG V1 ( For Development Proposals having Gross BUA Less than 20000 Sq mt )

Summary of Information required for Environment Issues

Keeping in view the overall guidelines described above, a report should be

prepared which shall include all the above information, analysis and action

plan. The report at the end must have a plan which is meant for

implementation with a written consent that the same will be implemented.

This document can be used by the NMMC later for assessing the

compliance.

Environment Issues

Remarks

Location details

Description with Google map with details of the locality in terms of neighborhood building, historic and or important or sensitive facilities etc (about 1-3 km radius)

Plot area & neighborhood details

Microclimate & heat island study (If required)

Based on the heat generated due to air conditioning and heat reflected due to glass/other material, an analysis should be presented for the micro-cosmic of the place (not limited to the building). Action plan for its mitigation is expected.

Disaster Management Plan- DMP (all situations) for onsite and offsite

All buildings must have its own onsite and offsite DMP which should not only include fire but also many disastrous situation such as but not limited to (earthquake, power failure, explosion, communication failure etc). It must include the response system and its responsibility with detailed action plan, budget etc

Water and waste water management plan study

Water use and water budget for the building. However, it should also include a scenario analysis for current demand future projection ( at least 10 years) for the area. Its impact on the water resources and sewerage/treatment system. Action plan is expected. STP if proposed, its size, location, technology, technology provider and its performance reference etc should be included for intention of recycle and reuse. Rain water harvesting along with a total water harvesting plan.

Page 44: Hrc nmmc guidelines

44

Ecological aspects and vegetation

Plan for ecosystem preservation and enhancement through integrated plan, especially green cover, land surfaces open to sky, types of trees and vegetation, pathways greening and maintenance plan.

Indoor air prediction and mitigation plan

Building design should be able to demonstrate design aspects which will avoid indoor air pollutants built up. Appropriate model should be used for this purpose with ventilation assessment with respect to outdoor conditions. Action plan for better design and also mitigation plan for remaining problem is expected, more specifically in closed building or commercial buildings.

Open space manage- ment and its design

Environmental architectural feature should be amply demonstrated through open space management and its design which integrates inside from outside.

Materials types, its use, sources, energy etc

Types of materials, their environment ratings, benefits compared to conventional material should be brought out especially keeping in mind the climate, energy use, material life cycle and others

Energy use plan for residents, commercial, DG sets etc

Energy use plan should be detailed and included which must address the energy use pattern for housing, amenities, others (essential and non-essential)

Amenities creation for others and nearby areas

Amenities which will get created by the proponent in and around its area, which could be useful for the society in general.

Other Environment improvement measures

Any other environment improvement measures (such as EMP during construction, carbon footprint and offset, awareness camp, others)

Environment Protection Preservation Plan (submit as per format EPPP-V1)

A final summary of the EMP which shall be in form of all the above issues, analysis and action plan. This may also include the budget and management system for its implementation.

Page 45: Hrc nmmc guidelines

45

EPPP-V1

Environment Protection Preservation Plan (For Development Proposals having Gross BUA Less than 20000 Sq mt)

Sr.No. Environment issues Impacts Mitigation

Plan Remarks

1 Legal aspects of the project (EC, CTE etc)

2 Microclimate impacts and heat island effects

3 Water Use 4 Wastewater

generation

5 Disaster situation (onsite, offsite)

6 Indoor air impacts with Ventilation

7 Ecological status 8 Solid waste generation 9 Open space use 10 Construction material 11 Energy use 12 Construction impacts 13 Other environment

impacts (specify)

14 Other environment enhancement initiative (pl specify)

More items can be added above as per the site location, building types,

construction types, user base, etc. More space should be used to describe

the mitigation action plan.

This set will be signed by the project proponent along with ECG-V1 which

shall once approved will be binding unless until it has been revised

through HRC.

We undertake to fulfill the above Environmental Commitments & provide

adequate budget therefore.

Project Proponent Architect Environment Consultant (Stamp & Signature) (Stamp & Signature) (Stamp & Signature)

Page 46: Hrc nmmc guidelines

46

Requirements for Fire Prevention and Life Safety in High Rise Buildings

[Source: Part 4: Fire and Life Safety, NBC (2005) as recommended by

Maharashtra Fire Prevention and Life Safety Measures Act (2006)]

Suggestions & corrections to be incorporated

Note: 1) Following amendments and corrections are applicable for

building having height more than 70 m of height irrespective

of its occupancy,

2) The clauses which need to be amended are only mentioned

below. All other clauses in N.B.C. 2005 are as it is.

Sr. No.

Clauses & Clauses No. from NBC (2005) Part 4

Prescription and Recommendations

1 2.39 Wet Riser

An arrangement for the fire fighting within

the building by means of vertical rising

mains not less than 150 mm nominal

diameter with landing valves on each floor

/ landing in the independent duct in the

lobby near every staircase entrance, for

fire fighting purposes and permanently

charged with water from a pressurized

supply. NOTE – For definitions of other

terms, reference shall be made to good

practice.

2 3.4.4 Maximum Height

Every building shall be restricted in its

height above the ground level and the

number of storey, depending upon its

occupancy and the type of construction.

The height shall be measured as specified

in Part 3 NBC Requirements.

High Rise Buildings -Residential/

Commercial/ Mixed Occupancies - up to

Page 47: Hrc nmmc guidelines

47

120.00 M height (Height Limit) shall be

permitted.

Note: In specific cases where a clearly demonstrable hardship is caused, the Commissioner may for reasons to be recorded in writing, may restrict the height of any building, and may also permit the prescribed heights to be exceeded.

3 3.4.6 Open Spaces

The side, front and rear open spaces of

the building shall not be less than 8.00

mt.for buildings above 70.00 mt. height.

However, due to any hardship/planning

constraints or irregular shape & size of

the plot, the HRC on scrutiny &

satisfaction may permit 6.00 mt. front

open marginal space, if Refuge area/ Fire

escape route is not provided in the side of

proposed front open marginal space & the

same is not abutting Fire Refuge Area /

Floor. Further, for the buildings above

45.00 mt height and up to 70.00 mt.

height one of the open marginal space

abutting Fire Refuge gallery/ approachable

area of refuge floor as directed by the Fire

Officer shall have minimum 7.50 mt. clear

open marginal space & all other remaining

side open marginal spaces shall be 6.00mt

minimum.

Page 48: Hrc nmmc guidelines

48

4 3.4.19 Glass of facade

Fire Safety Requirements For Glass

Wall In Building

Glass Wall (Walls Functioning As Fire

Compartment Wall And Wall Adjoining

Escape Routes)

1)Architect should earmark conspicuously

the glass wall either by sign or in words,

on the plans submitted at the time of

submission of proposal.

2) The said wall including doors frame

work if any should be one hour fire

resistances and shall satisfy stability,

integrity and insulation characteristics for

the fire resistance period given.

3) Plastic or any combustible film shall

not be coated on external or internal face

of the wall.

Fire Safety Requirements For Glass

Facade In Building

Glass Facade 1) An Opening to the glass façade of min.

width 1.5 m and height 1.5m shall be

provided at every floor at a level of 1.2 m

from the flooring facing compulsory open

space as well as on road side. Minimum

one such opening shall be provided at the

interval of every 15mt.

Mechanism of Opening: The openable

glass panel shall be either left or right

shall have manual opening mechanism

from inside as well as outside. Such

oepnable panels shall be marked

conspicuously so as to easily identify the

openable panel from outside.

Page 49: Hrc nmmc guidelines

49

2) Distance between the external wall

(glass/brick) and glass façade shall not be

more than 300 mm.

3) The smoke seals/barriers between

building wall and façade shall be provided

at every floor level in the form of non-

combustible material/ vermiculate

cement.

4) Glass facade blocking the area of

staircase, lift lobby and corridor shall be

kept openable. Pressurized system of the

staircase/lobby shall be synchronized with

opening mechanism.

5) The glazing used for the façade shall

be of toughened (tempered) safety glass

as per I.S.2553, Part I or laminated safety

glass as per I.S.2553-Part I satisfying

stability criteria.

6) Automatic Dry type water curtain

system shall be provided at every floor

level from inside of the façade.

7) Openable vent of 600 mm height to be

installed below ceiling level or false ceiling

level (if provided)- The openable vent of

minimum 2.5% of the floor area shall be

provided. It shall be of min 600 mm depth

below ceiling/false ceiling or full length on

the periphery of the façade whichever is

less- Openable mechanical devices for the

said vent shall be located at 1.2 m height

from the flooring level. The Openable vent

can be pop out type or bottom hinged

provided with fusible link opening

Page 50: Hrc nmmc guidelines

50

mechanism and shall also be integrated

with automatic Smoke Detection System.

OR

Alternate vertical glass panels of the

façade shall be oepnable type with the

mechanism mentioned above in order to

ventilate the smoke.

8) Refuge areas covered with the glass

façade shall have all the panels openable

(either left or right hinged) both from

inside as well as outside.

5 4.12.3 Refuge Areas:

Manner of providing refuge area :

a) The refuge area shall be so located

that it shall preferably face the access

road/s or otherwise face the wider open

space on the side of the building

perpendicular to the main access road.

b) The cantilevered refuge area shall

necessarily be of RCC Type.

c) The cantilevered refuge area up to

54.0M height shall be provided with railing

/ parapet of 1.10 m height and 1.50 m

above height of 54.0 M.

d) R.C.C. covering shall be provided

above the topmost refuge area.

e) The cantilever refuge area shall have

access through a door which shall be

painted with a sign in luminous paint

mentioning ― REFUGE AREA.

f) The lift/s shall not be permitted to be

open into the refuge areas.

g) Drenchers shall be provided in refuge

areas above 70.0 M height.

Page 51: Hrc nmmc guidelines

51

h) Use of Refuge area :

i) The refuge area shall be earmarked

exclusively for the use of occupants as

temporary shelter and for the use of Fire

Department or any other organization

dealing with fire or other emergencies

when occur in the building and also for

exercises/drills if conducted by the Fire

Department.

ii) The refuge areas shall not be allowed

to be used for any other purpose and it

shall be the responsibility of the

owner/occupier to maintain the same

clean and free of encumbrances and

encroachments at all times.

iii) Facilities to be provided at refuge

area:

Adequate emergency lighting facility shall

be provided.

iv)The maximum permissible Refuge Area

shall be 4% of Built up area of serving

floors. The area beyond the stipulated

above shall be computed in the FSI.

As far as possible, refuge floor shall be

within the building line itself.

6 Fire Escape Chutes ( New Clause)

Fire Escape Chutes :- High rise building

having height more than 70 m, shall

necessarily be provided with fire escape

chute shafts/s for every wing adjacent to

staircase. Wall of the shaft shall have 3 hr

fire resistance.

One side of the shaft shall be at external

face of the building with proper

Page 52: Hrc nmmc guidelines

52

ventilation.

The dimension of the shaft shall not be

less than 2.5m X 1.5m.

The access to the fire escape chute’s shaft

shall be made at alternate floor level from

staircase mid-landing with self closing fire

resistant door of at least one hour.

The fire chute shall be of staggered type

with landing of each section at the vertical

height of not more than 15mtrs.

7 Fire Check Floor ( New Clause)

Fire Check Floor/ Fire Cut off Floor

A high rise building having ht more than

70 m, hall be provided with fire check

floor (entire floor) above 70 mt at

immediate habitable floor level. Height of

the fire check floor shall not be more than

2.60 mt.

The fire check floor shall not be used for

any purpose and it shall be the

responsibility of the owner/occupier to

maintain the same clean and free of

encumbrances and encroachments at all

times. Drinking water facility and toilet

facility shall be provided.

Periphery of the Fire Check floor shall not

be enclosed.

Fire Drenchers shall be provided at the

periphery of the each fire check floor

externally.

Page 53: Hrc nmmc guidelines

53

8 Basement (Open

Spaces) ( New Clause)

Basement Depth:

It may be one level or more, total depth

not exceeding 8.0 m below the ground

level.

If the basement is exclusively planned for

required parking only due to planning

constraints or any hardship with written

permission of the Commissioner the

basement beyond prescribed building line

exclusively required for parking may be

allowed for maximum depth of 8.0m.

Then, if, basement excluding excavation is

up to 4.0 m, the minimum open space for

basement for side & rear margins shall be

2.0 m Further, if, the depth of basement

excluding excavation is from 4.0 m to 8.0

m, the minimum open space for basement

for side & rear margins shall be 2.5 m, No

basement shall be allowed in front open

margin. All structural design/safety

aspects as per latest BIS Codes shall be

complied along with consideration of

weight of Fire Engine & its maneuverings.

Further, while planning & designing

basement in these aforesaid margins,

utmost care shall be taken so as to avoid

foul with utility/building services such as

water supply tank/ lines, sewerage

network, town gas lines, rain water

harvesting system, gray water reuse &

Page 54: Hrc nmmc guidelines

54

Recycle system with STP,

Communication/MTNL cable lines, MSED

power cables, foundations of abutting

structures/ compound walls, fencing etc. A

detailed Architectural plan depicting

basement along with all above aspects

shall be submitted along with the

checklist.

9 4.14 Ramp The ramp to basement and parking floors

shall be between 6 mt. to 7 mt. wide for

two way traffic and 3.0 mt. to 4.0 mt.

width for one way traffic shall be provided

with Gradient of 1:10 for cars and 1:15

for heavy vehicles.

If it is proposed to ply the fire engine on

the ramp the width shall be minimum 9.00

mt. with turning radius of 12.00 mt.

minimum shall be provided. As far as

possible, this should be avoided. Also,

taking of fire engine on car park floor shall

be avoided. Fire fighting should be done

from open spaces only, to the extent

possible.

All structural design/safety aspects as per

latest BIS Codes & NBC shall be complied

along with consideration of weight of Fire

Engine & its maneuverings.

Page 55: Hrc nmmc guidelines

55

The clear head room of 5.50 mt. shall be

proposed in case of fire engine movement

underneath the parking floor is required &

the same shall not be counted towards

FSI.

(V. S. Rane) Member, HRC

& Fire Officer ,

Navi Mumbai Municipal Corporation

(P. R. Thakur) Member, HRC

& Assistant Director of Town Planning Navi Mumbai Municipal Corporation

(S. W. Patil) Member, HRC

& Additional City Engineer

Navi Mumbai Municipal Corporation

(M. B, Dagaonkar) Member, HRC

& City Engineer,

Navi Mumbai Municipal Corporation

(Shantilal Jain) Member, HRC

(Dr. Mahua Chakrabarti) Member, HRC

(A. L. Jarhad ) Chairman, HRC

& Commissioner

Navi Mumbai Municipal Corporation