SLIDE SHOW 1 of 3:Pictorial chronology documenting the permeable paver parking lot at Odell Brewing Company. Part 1 of 3 covers site prep., geotextile fabric, sub-base, base course, and bedding.

Citation preview

Page 1: Odell permeable pavers-1of3
Page 2: Odell permeable pavers-1of3

BIO-AQUIFER STORM SYSTEM (BASS™)WITH AQUA-BRIC® PERMEABLE PAVERS

ODELL BREWING COMPANY

Fort Collins, Colorado

Page 3: Odell permeable pavers-1of3

SITE PREPARATION

perimeter edge restraints (concrete curbs and grade beams)

Page 4: Odell permeable pavers-1of3

SITE PREPARATION

interior parking islands with dry wells

Page 5: Odell permeable pavers-1of3

SITE PREPARATION

pumping subgrade, therefore…

Page 6: Odell permeable pavers-1of3

SITE PREPARATION

…subgrade stabilization required

Page 7: Odell permeable pavers-1of3

SITE PREPARATION

6-inch minus pit run material worked into subgrade

Page 8: Odell permeable pavers-1of3

GEOTEXTILE FABRIC

geotextile is adhered to sides of perimeter edge restraints

Page 9: Odell permeable pavers-1of3

GEOTEXTILE FABRIC

option to line bottom in fabric as well

Page 10: Odell permeable pavers-1of3

GEOTEXTILE FABRIC

both exterior and interior edge restraints are wrapped

Page 11: Odell permeable pavers-1of3

GEOTEXTILE FABRIC

begin spreading sub-base material on fabric

Page 12: Odell permeable pavers-1of3

SUB-BASE COURSE

AASHTO No. 2 material, VTC, or approved equal

Page 13: Odell permeable pavers-1of3

SUB-BASE COURSE

1½” – 3” cleaned, fractured, open-graded stone

Page 14: Odell permeable pavers-1of3

taking delivery of a truckload of sub-base material

SUB-BASE COURSE

Page 15: Odell permeable pavers-1of3

12” minimum depth of sub-base course

SUB-BASE COURSE

Page 16: Odell permeable pavers-1of3

no other construction vehicles allowed on sub-base during installation

SUB-BASE COURSE

Page 17: Odell permeable pavers-1of3

sub-base material delivered until design depth achieved

SUB-BASE COURSE

Page 18: Odell permeable pavers-1of3

standard skid-steer loader used to move and place material

SUB-BASE COURSE

Page 19: Odell permeable pavers-1of3

important to keep geotextile secure during placement

SUB-BASE COURSE

Page 20: Odell permeable pavers-1of3

open-graded aggregates are critical to the BASS™ success

SUB-BASE COURSE

Page 21: Odell permeable pavers-1of3

sub-base course is compacted with vibratory drum roller

SUB-BASE COURSE

Page 22: Odell permeable pavers-1of3

panoramic view of permeable sub-base course

SUB-BASE COURSE

Page 23: Odell permeable pavers-1of3

BASE COURSE

4” depth of AASHTO No. 57 material, or approved equal

Page 24: Odell permeable pavers-1of3

BASE COURSE

continue to use vibratory drum roller

Page 25: Odell permeable pavers-1of3

notice ¾” base course against larger sub-base course

BASE COURSE

Page 26: Odell permeable pavers-1of3

BEDDING COURSE

base course

Compare the size of the bedding material

bedding course paver joint

Page 27: Odell permeable pavers-1of3

2” depth of ¼” - ⅜” washed, fractured, open-graded stone

BEDDING COURSE

Page 28: Odell permeable pavers-1of3

BEDDING COURSE

pavers rest directly on setting bed (AASHTO No. 8, or approved equal)