27
Architecture Alumni Association Project Life Cycle Concept to Completion Andhra University Architecture Alumni Association Dubai Chapter

Dubai Chapter Venustas 25 Presentation

Embed Size (px)

Citation preview

Architecture

Alumni

Association

Project Life Cycle

Concept to Completion

Andhra University

Architecture Alumni Association

Dubai Chapter

Architecture

Alumni

Association

Alumni Presence in UAE

Bhanu Sri Prakash Gejjala, RSP

Kavitha Saripella, SMDKrishna Kasi, SMD

Kalyan C Gudla, JACOBS, AD

Kumar Yettirajam, CPG

Raju Pusapati, RAK Properties

Brahmaji Rao, Design Integrated

Kiran Kumar Vatada, Loreal

Vinaykumar Tadi, AECOM, AD

Shyam, Shobha Saphire

Ramu Rongali, Woodsbagot

Kishore Pudi, Dar-al-Handasah, AD

Viswanadah Kella, Landmark Group Ramya Pudi, BMA Intl.

Sagar Varma, Dais ContractDileep Mummidi, SMD

Sai Sreedhar, Altorath, AD

Architecture

Alumni

Association

Illustrators

•Bhanu Sri Prakash Gejjalla – 1989-94Vice President, RSP Architects

•Kalyan C Gudla – 1994-99Assistant Program Director, JACOBS

Architecture

Alumni

Association

RSP started out as a small partnership, Raglan Squire & Partners in

1956 in Singapore. It has since then grown in scope and scale, to

become one of the largest architectural practices in the world.

RSP’s reach has steadily grown over the years. Proudly supporting

several leading & progressive governments as well as private sector

Clients, including several who proudly feature amongst the world’s top

1,000 companies, the RSP Group today, in spite of its large

geographical footprint, continues to provide its hallmark ‘on-the-ground’

customized service to Clients within Asia, Middle East, Australasia,

Africa and Europe. With a team of 1,300 professionals worldwide, the

RSP model is based on optimally utilizing the expertise of its global

talent pool

Architecture

Alumni

Association

Jacobs is one of the world’s largest and most diverse

providers of the technical professional and construction

services with offices all around the world. Jacobs ranks #1

in the engineering/architecture, and BIM-Engineering

categories; and #2 engineering firm in the healthcare and

institutional sectors. As a publicly traded company with

70,000 employees, the 2013 revenues of more than

$13 billion, Jacobs offers support to industrial, commercial,

and government clients across multiple markets. In 2010,

Jacobs was named by Forbes as one of America's 100

Most Trustworthy Companies.

Architecture

Alumni

Association

Our Ventures

• A young Dubai and India based firm

• Team of architects and engineers with international experience

• Aimed to provide the services of the professional and design

experience of different worlds to challenging possibilities of the

prospering Middle East and Indian Economy.

• Owned SIS BIM which is located in Hyderabad to facilitate large

production possibilities. Team of 25 members with high caliber and

international experience from Gulf region.

• Caters to the needs of architects, engineers and consultants in the

construction & manufacturing industries.

• Aimed to provide Cost-effective BIM Modeling Services, Shop

drawings through BIM & CAD, High quality architectural

renderings and 3D Animations to our Clients.

• Autodesk – BIM Authorized Training Center

Architecture

Alumni

Association

Our Alumni

Ar. Brahmaji Rao

Ar. Dileep M Ar. Chittoji Raju Ar. Sai Teja

Architecture

Alumni

Association

Project Definition

An individual or collaborative enterprise that is carefully planned

and designed to achieve a particular aim – Oxford/Google definition

Planned set of interrelated tasks to be executed over a fixed period

and within certain cost and other limitations – Business Dictionary

In project management a project consists of a temporary endeavor

undertaken to create a unique product, service or result – PMBOK,

PMI

Architecture

Alumni

Association

Project Management

Project management is the process and activity of planning, organizing,

motivating, and controlling resources, procedures and protocols to

achieve specific goal in scientific or daily problems.

The primary challenge of project management is to achieve all of the

project goals and objectives while honoring the preconceived

constraints. The primary constraints are scope, time, quality and

budget. The secondary challenge is to optimize the allocation of

necessary inputs and integrate them to meet pre-defined objectives.

Architecture

Alumni

Association

Project Life Cycle

Project life Cycle

Initiation –Starting the

project

Planning –organizing &

preparing

Execution –Carry out the

work

Closure –closing the

project

The Project Life Cycle refers to

a series of activities which are

necessary to fulfill project goals

or objectives. Projects vary in

size and complexity, but, no

matter how large or small, all

projects can be mapped to the

following life cycle structure

The project life cycle is divided

into 4 phases

• Initiation

• Planning/Design

• Execution

• Closure

Architecture

Alumni

Association

Project Life Cycle

•Monitoring & Control

•Post Implementation

•Detailed Planning

•Project definition

•Project scope

•Timeframe

Project Initiation

Project Design

Project Execution

Project Closure

Architecture

Alumni

Association

Project Initiation Phase

This is the beginning...the phase where a business

problem or opportunity has been identified, impact

evaluated, alternatives reviewed, and a solution

defined.

Key Outputs

• Client Requirements

• Project Need

• Feasibility

Architecture

Alumni

Association

Project Design Phase

• Concept Design

• Schematic Design

• Detailed Design

• Authority Approvals

• Tender Documents

• Contract Documents

– Issue For Construction

Architecture

Alumni

Association

Concept Design

• Client Brief

• Scope of the Project

• Authority Requirements

• Sustainability Goals

• Examples….

Architecture

Alumni

Association

Concept Design

• Nakheel Mall Concept Presentation….

Architecture

Alumni

Association

Schematic Design

• Understanding Authority requirements

• Fire & Life Safety Strategies

• Sustainability Guidelines

• Structural & MEP Coordination

• Architectural Constructability Issues

• Realistic feasibility Issues

• Outline Specifications

• QS – Ball Park & Typologies

Architecture

Alumni

Association

Detailed Design

• Detailing Façade & All Special Areas

• Detailed Specifications

• Detailing Freezing Sustainable Principles

• Architectural Materials & Detailing

• Intensive Coordination – FLS, Structure & MEP,

and Specialist Sub-consultants, etc.

• Value Engineering – Detailed Quantity Surveying

• Authorities

Architecture

Alumni

Association

Schematic & Detailed Design

• Nakheel Mall BIM way……

Architecture

Alumni

Association

Schematic & Detailed Design

• More Examples…

• Wind Study stunts with The Palm Tower

Architecture

Alumni

Association

Authority Approvals

• Jurisdictions in Dubai• Dubai Municipality

• Trakhees

• EHS

• DCD

• DEWA

• DM-Infra

• RTA

• Telecom – DU / Etisalat

• Dubai Aviation Authority …..

Architecture

Alumni

Association

Tender Documents

• Tender Documents

• Construction Drawings

• Specifications – CSI format & British Spec

• Material & Product Sheets

• Bill Of Quantities (BOQ)

• Conditions of Contract – FIDIC & AIA

• Contract Submittal Requirements

• Tender Review

• Contractor Selection

Architecture

Alumni

Association

Project Execution Phase

The longest phase where the designed work is constructed

on the field to accomplish the intent of the end user. The

key elements of project execution is the ability of working

effectively in the team and the ability of remaining faithful to

project scope while facing unpredicted events and

difficulties.

• Pre-Construction

• Construction

• Post Construction

Architecture

Alumni

Association

Project Execution Phase

Architecture

Alumni

Association

Project Execution Phase

Architecture

Alumni

Association

Project Execution Phase

The Monitoring and Controlling process oversees all the

tasks and metrics necessary to ensure that the approved

and authorized project is within scope, on time, and on

budget so that the project proceeds with minimal risk. This

process involves comparing actual performance with

planned performance and taking corrective action to yield

the desired outcome when significant differences exist.

Monitoring and Controlling process is continuously

performed throughout the life of the project.

Architecture

Alumni

Association

Project Execution Phase

Key Tasks

• Scope Verification

• Schedule Control

• Cost Control

• Quality Control

• Performance Reporting

• Risk Control

• Contract Administration

• Change Management

Architecture

Alumni

Association

Project Closure Phase

Post Construction

• Testing and Commissioning

• Authority Approvals

• Building Occupation Certificates

Facility Management

• Training

• Life Safety Compliance

• Building Maintenance Systems